Framework and Toolkit for UN Coherence, Effectiveness and Relevance at Country Level:
Step 9 – Coordinate change and ongoing implementation
![Page 2: FRAMEWORK FOR UN COHERENCE, EFFECTIVENESS AND RELEVANCE AT COUNTRY LEVEL](https://reader036.fdocuments.in/reader036/viewer/2022082611/56812cfb550346895d91cdfe/html5/thumbnails/2.jpg)
2
FRAMEWORK FOR UN COHERENCE, EFFECTIVENESS AND RELEVANCE AT COUNTRY LEVEL
Increasedcoherence,
effectiveness and
relevance
Initiate & mobilize
Prioritize and set
outcomes
Determine strategy
Plan organis-
ation changes
Plan implement-
ationImplement
1 2 3 4 5 6
7
8
9
Communicate about change
Monitor and evaluate
Coordinate change & ongoing implementation
Manage change programme, put in place the required processes, resources and governance structure to manage the
change
![Page 3: FRAMEWORK FOR UN COHERENCE, EFFECTIVENESS AND RELEVANCE AT COUNTRY LEVEL](https://reader036.fdocuments.in/reader036/viewer/2022082611/56812cfb550346895d91cdfe/html5/thumbnails/3.jpg)
STEP 9: COORDINATE CHANGE & ONGOING IMPLEMENTATION : OBJECTIVES
3
Ensure overall coordination and successful implementation of the change process
Coordinate and oversee the implementation of the integrated
programme and operations strategy
![Page 4: FRAMEWORK FOR UN COHERENCE, EFFECTIVENESS AND RELEVANCE AT COUNTRY LEVEL](https://reader036.fdocuments.in/reader036/viewer/2022082611/56812cfb550346895d91cdfe/html5/thumbnails/4.jpg)
STEP 9: COORDINATE CHANGE & ONGOING IMPLEMENTATION : MAIN ACTIONS
Main actionsStep
4
• Assign roles & responsibilities and governance structure for the change process [starting at Step 1, updating as needed during subsequent steps]
• Develop budget tracking approach [at each step of the process]
• Produce periodic progress reports on implementation of the integrated programme and operations strategy [at each step of the process]
Coordinate change and
ongoing implementati
on
9
![Page 5: FRAMEWORK FOR UN COHERENCE, EFFECTIVENESS AND RELEVANCE AT COUNTRY LEVEL](https://reader036.fdocuments.in/reader036/viewer/2022082611/56812cfb550346895d91cdfe/html5/thumbnails/5.jpg)
STEP 9: COORDINATE CHANGE & ONGOING IMPLEMENTATION: ACTIVITIES & TOOLS
Guidance and Templates
Main action Sub activities / analyses
Examples (Pilot & Non pilot)
Assign roles & responsibilities and
governance structure for change process
(starting at Step 1, updated as needed during later steps)
• Set up governance for change process coordination
• Define and agree on roles & responsibilities in the change process
• Illustrative governance for the effort to improve coherence, effectiveness and relevance
• Role descriptions of change team
• Examples of governance structures successfully adopted in pilot countries
Produce periodic reports on implementation(at each step of the
process)
• Track progress against plan
• Identify risks
• Work charter and progress report
• Issue log
• Sample of pilot country status report, issue log
Develop budget tracking approach
(at each step of the process)
• Track budget throughout the change process
• Template: Budget tracking sheet
5
![Page 6: FRAMEWORK FOR UN COHERENCE, EFFECTIVENESS AND RELEVANCE AT COUNTRY LEVEL](https://reader036.fdocuments.in/reader036/viewer/2022082611/56812cfb550346895d91cdfe/html5/thumbnails/6.jpg)
Main action Checklist
2
STEP 9: COORDINATE CHANGE & ONGOING IMPLEMENTATION: ACTIVITY CHECKLIST
Assign of roles & responsibilities and
governance structure for the change process
• Dedicated change team in place (whether part the RCO or from one of the agencies)
• Dedicated change management resources – both people and funds – are in place (likely to increase as the steps proceed before decreasing again as the changes take root)
• Governance structure for the change management process is defined
Produce periodic progress reports on
implementation of the integrated programme
and operations strategy
• Periodic progress reports to the UNCT, according to the monitoring plan, on execution of the implementation plan
• Issues consistently identified through progress review discussions or otherwise, and successfully and promptly addressed
Develop budget tracking approach
• Budget tracking approach developed
6