foundation tratment

download foundation tratment

of 9

Transcript of foundation tratment

  • 7/29/2019 foundation tratment

    1/9www.powergenu.com

    Foundation TreatmentMeasures for Dams

    Located onKarst Foundations

  • 7/29/2019 foundation tratment

    2/92 www.powergenu.com

    Educational ObjectivesOn completion of this course, students will:

    This course will provide the student with an overview of

    foundation treatments for dams constructed on karst foun-

    dations. For this course the Kavar Dam in Iran was the

    example where an unusual combination of a surface mem-

    brane, coupled with a gypsum surcharge and other seepage

    control measures, were planned to seal a highly karstic

    foundation.

    IntroductionKarsticity occurs as a result of a progressive disolutioning

    of carbonate rocks exposed to water and carbon dioxide. In

    pure water, at 25oC, the maximum possible concentration

    of dissolved calcium carbonate is in the range of 14 mg/L

    (Fookes and Hawkins, 1988). However, in the presence of

    dissolved carbon dioxide, maximum concentrations increase

    dramatically, accounting for the fact that seepage owing

    from karst formations often contains up to 400 mg/L of

    calcium carbonate ( James and Fitzpatrick, 1988). Therefore,

    a karstic formation implies the presence of a network of

    solutioned, often highly permeable, discontinuities which

    are, by denition, connected to the surface so that the free

    carbon dioxide necessary to allow the solutioning process to

    continue is available. This fact means that Karst founda-

    tions are usually associated with highly deformed, complex,

    rock masses that have pervious windows extending directly

    to the foundation surface.

    The diculties involved in constructing a dam on a

    karstic foundation were rst documented at Hales Bar damthat was built by private interests on the Tennessee River

    between 1905 and 1913. Although the existence of cavernous

    rock in the limestone foundation was postulated, geological

    theory at the time suggested that cave formation occurred

    only above the water table. (T.V.A. Technical Report No.

    22, 1949). Therefore, very little foundation treatment was

    performed and, following construction, leakage under the

    dam of up to 48 m3/s was measured. Various remedial works

    projects were carried out at the site over the 60 years that

    it was in operation until, in 1968, the dam was demolished.

    In the years following the construction of the Hales bar

    dam the eects of solutioning have had adverse impacts on

    both reservoir water tightness and the structural integrity

    of many dams. Although there are few documented struc-

    tural failures attributed to sinkhole collapse in karst ter-

    rain, there are numerous examples of problems associated

    with reservoir lling. For example, at the Lar dam in Iran

    (Uromeihy, 2000) it was not possible to impound to full sup-

    ply level due to foundation leakage that reached two-thirds

    of the total river ow. A remedial grouting program, per-

    formed between 1985 and 1990, was only partially success-

    ful in reducing seepage and, to date, the reservoir remains

    partially lled. In the case of the Anchor Dam constructed

    in 1960, (Fig. 1), an extensive system of sinkholes and faults

    have prevented any permanent storage of water, despite

    numerous remedial sealing attempts. (ww w.usbr.gov/cdams/

    dams)

    As a result of experience gained from such dams,

    techniques have been developed to successfully treat even

    seriously karstic foundations. This course describes current

    practice for the design of dams on karst terrain as well assome unique seepage control measures that are planned to

    mitigate risks associated with a highly karstic limestone

    foundation in Iran. These measures include the use of an

    Foundation Treatment Measures for

    Dams Located on Karst Foundations

    1. Understand the diculties of constructing

    a dam on a karstic foundation.

    2. Identify methods to treat karstic foundationsfor the construction of a dam.

    3. Understand grouting techniques and other seepage

    control measures for karstic foundations.

    4. Understand the eects of solutioning on reservoirwater tightness and the structural integrity of dams.

  • 7/29/2019 foundation tratment

    3/9

    Figure 1 The Anchor Dam Wyoming USA

    Figure 2 Effect of Multiple Line Grouting on the Median Post Impoundment

    Seepage Reported for Some Selected Precedent Dams (ref. Table 1)

    600

    300

    200

    MedianPos

    tImpoundmentSeepage(l/sec)

    100

    0

    0

    Number of Grout Lines

    1 2 3 4

    400

    400

    www.powergenu.com 3

    engineered soluble ll and a surcial shot-

    crete membrane to seal the foundation

    surface.

    CurrentPractice

    The key to any successful construction

    on a karst foundation is a thorough un-

    derstanding of the nature of the problemsthat must be treated. In the rst half of

    the 20th century, dams such as the Hales

    Bar, Wolf Creek, Mosul, and Great Falls

    were constructed on karstic foundations without adequate

    foundation explorations. All experienced either foundation

    leakage or piping problems. More recently, the problems

    at the Lar dam are likely related, at least in part, to an in-

    adequate understanding of the depth of karst prior to the

    commencement of construction.

    On the other hand, if exploration and foundation treat-

    ment measures are carried out thoroughly, even a highlykarstic foundation can be successfully treated. For example,

    advanced karst foundations beneath the 90 to 100 m high

    Pueblo Viejo and Punt Dal Gall dams were successfully

    treated such that post-impoundment seepage has only been

    25 and 50 l/sec respectively.

    In broad terms, modern practice for the successful treat-

    ment of karstic foundations requires a means of reducing

    the amount of seepage, techniques to prevent dissolution

    of soluble minerals that may be present in the foundation,

    and methods to ensure that the foundation has adequate

    capacity to resist the post impoundment loadings without

    excessive settlement.

    Improving Deformability

    Commonly applied techniques for improving the deform-

    ability and stability of karst foundation rocks include exca-

    vation/mucking of solution cavities followed by lling with

    a sand and gravel slurry, concrete and/or compaction grout-

    ing. For example, at the 21 dams that the Tennessee Valley

    Authority (TVA) has constructed on carbonate foundations,

    Soderberg (1988) notes that foundation treatment typically

    includes consolidation grouting to ensure adequate bearing

    strength and to minimize settlements. Solutioned areas, in

    otherwise sound rock, are then mucked or excavated and

    lled with concrete.

    More recently, compaction grouting has been used to

    treat karst features. This technique involves the injection

    of low-slump soil/cement grout to displace and/or compress

    the surrounding soils for greater strength (Fischer and

    Fischer, 1995). This typically results in hydraulic fractur-

    ing, extrusion and consolidation of clayey llings within

    the sinkholes increasing strength, and resistance to seep-age stresses. Welsh (1988) and Zuomei and Pinshou (1988)

    describe the use of compaction grouting to rectify sinkholes

    and caves lled with clay llings and to build a seepage

    resistant barrier in Karst terrain for the

    Wujiangdu Hydroelectric Project in China.

    Reducing the Potential for Dissolution of Soluble

    Minerals

    The most commonly occurring soluble rock

    minerals are calcium carbonate (limestone)

    gypsum, anhydrite and halite. In general,mitigation of the risk of solutioning in a

    foundation containing such minerals re-

    quires reducing the volume of seepage and

    seepage gradients. This, traditionally, had been accom-

    plished on the basis of precedent practice. An analytical

    framework for assessing the solutioning potential of various

    forms of soluble rock minerals was rst presented by James

    and Lupton (1978). James and Kilpatrick (1980) used these

    solutions to study seepage control measures for dam con-

    structed on foundations containing the soluble rocks. They

    concluded that grouting, or the provision of an upstreamimpervious blanket, can control the solutioning of calcium

    carbonate rock. For foundations containing gypsum, con-

    ventional (sulphate resistant) cement curtain grouting was

    recommended. Mineral deposits such as anhydrite were

    found to require a more ecient cuto, such as plastic con-

    crete wall in combination with measures such as upstream

    blankets or other techniques designed to reduce seepage

    velocities. They recommended that halite, in its massive

    form, be avoided. However, it is of note that an active brine

    injection system has been used to treat foundations contain-

    ing hal ite mineral deposits (Pokrovskii, 1994).

    Grouting

    For well developed karst foundations, a sulphate resistant

    multiple line grout curtain, with provisions to allow future

    grouting, is typically used to reduce seepage losses. For

    lower head dams, or for dams on less well developed karst,

    single or double line curtains are often used. However,

    all karstic foundations should be treated with caution. As

    shown on Table 1, very high seepages can be experienced

    for even low head dams if karstic conditions are advanced.

    On the basis of median grout takes reported at a number of

  • 7/29/2019 foundation tratment

    4/94 www.powergenu.com

    Table 1: Precedent Examples of Some Dams Built on Karstic Foundations

    Project DamTypeandDate Head(m) GeologyNo.of

    GroutLinesSeepage

    Remedial

    Work

    J. Percy

    Priest Dam

    Earthfll/Concrete

    1963-6835.4

    Thin-bedded limestone, solu-

    tioned jts, sinkholes2 - 4 N. R. N. R.

    Sainte Croix

    Dam FranceArch 1971-74 72 Cavernous limestone 1 Negligible N. R.

    Quinson Dam

    FranceArch 1971-74 45 Cavernous limestone 1 Negligible N. R.

    Grand Rapids

    G. S. Canada

    Earthfll/Concrete

    1962-6436.5

    Dolomite limestone, sinkholes,

    solution channels1 Minimal None

    Arnprior G. S.

    Canada

    Earth/Rockfll/

    Concrete gravity

    1972-76

    21Limestone, Solutioned jts, voids

    1 cm - 1 m wide3 - 4 l/s N. R.

    Lar Dam IranEarthfll

    1972-8198

    Limestone, advanced karst,

    caverns, voids1

    Extreme

    9 m3/s

    Yes

    (see text)

    Stewartville

    Dam Canada

    Concrete

    gravity/EarthfllCompleted 1948

    41

    Crystalline limestone open

    seams at depth 1 370 l/s Yes.3

    Francisco Zarco

    Dam Mexico

    Earthfll/Concrete

    Completed 196823

    Limestone, solution channels,

    mode karst3 1000 l/s None

    La Amistad

    Mexico/U.S.A.

    Rockfll/Concrete

    Completed 196830 Limestone, caverns, sinkholes 1 Minimal None

    Sklope Dam

    YugoslaviaRockfll 80

    Limestone, advanced karst,

    caverns1 - 2 500 l/s None

    Globocica Dam

    Yugoslavia

    Rockfll

    Completed 196580

    Limestone, med. to adv. karst,

    solution channels3 4 l/s Yes.4

    Hales Bar Dam

    U.S.A.

    Earthfll/Concrete

    1905-19135 11.5

    Limestone, solution jts., cavi-

    ties, caverns 1

    Max. 48

    m3/s Yes.

    6

    Great Falls

    U.S.A.

    Concrete gravity

    Completed 191645.7

    Limestone, solution channels,

    cavities1 12 m3/s Yes.7

    Normandy Dam

    U.S.A.

    Concrete gravity/

    Earthfll 1972-7617

    Limestone with shale, clay solu-

    tion cavities1 - 2 Negligible None

    Pueblo Viejo

    Dam GuatemalaRockfll 1977-83 92

    Limeston & dolomite, advanced

    artesian karst1 - 2 25 l/s None

    Punt Dal Gall

    Switzerland

    Arch

    Completed 1969100

    Dolomite limestone, calcareous

    sandstone, deep karst, solu-

    tioned jts

    1 50 l/s None

    La Bolera Dam

    Spain Arch 1961-68 45 Limestone, advanced caverns 1 600 l/s None

    Sprinagarind

    Dam Thailand

    Rockfll/Concrete

    1974-80113

    Calcareous sandstone, lime-

    stone, solution cavities3 25 l/s N. R.

    King Talal Dam

    Jordan

    Rockfll/Concrete

    gravity Completed

    1971-75

    100Karstic limestone to 30 m below

    calcareous sandstone1 63 l/s None

    La Angostura

    Dam Mexico

    Rockfll/Concrete

    1971-7589

    Limestone, clay seams and

    solutioned jts2 100 l/s None

    3 Asphalt grouting in 1985 reduced leakage by up to 33 l/s

    4 Grout curtain extended in left abutment in 19745 Demolished 1960

    6 Extensive in 1944

    7 Cement and asphalt grouting performed

  • 7/29/2019 foundation tratment

    5/9

    Figure 3 Precedent Examples of Grout Curtain Extension into Abutments16

    RatioofGroutCurtainExtentioninto

    Abutmen

    tstoHydraulicHead

    00

    Maximum Normal Hydraulic Head (m)

    Open symbol indicates that remedial work

    or excessive seepage (>300 l/s) was reported.

    2

    4

    6

    8

    10

    12

    14

    20 40 60 80 100 120 140 160 180

    Slightly Karstic

    (grout take 0 to 50 kh/m)

    Highly Karstic

    (grout take > 400 kg/m)

    Karstic

    (grout take 50 to 400 kg/m)

    Grout take not reported

    Figure 4 Kavar Reservoir and Dam Site

    Razak Formation

    Asmari Formation

    Fault Line

    Full Service Level (FSL)Reservoir Rim

    Existing River

    DamLocation

    Lower Reservoir

    Upper Reservoir

    www.powergenu.com 5

    precedent dams reported in the literature, triple line grout-

    ing can be seen to reduce post impoundment risks (Figure 2)

    It is also clear from Table 1 that a signicant factor

    governing the performance of grout curtains in karst foun-

    dations is whether or not the curtain is anchored into an

    impervious base. For example, at the 11.5m high Hales Bar

    dam, post construction seepage reached 48 m3 per second

    through the hanging curtain. Similarly, at the FranciscoZaro Dam, seepage ows in the order of 1000 L/sec through

    the hanging curtain were measured, despite the fact that a

    triple line grout curtain had been used.

    It is usually necessary to extend the grout curtain some

    distance along the dam axis into the abutments to reduce

    risks associated with end run seepage. The amount of exten-

    sion required can be somewhat subjective, and is dependent

    on geological conditions such as the existence of an impervi-

    ous boundary. However, for dams founded on a moderately

    permeable karstic foundation, a review of precedent would

    suggest that the amount of extension required to minimizerisk varies logarithmically as a function of the hydraulic

    head (Figure 3).

    Asphalt Grouting

    When remedial grouting is required after impounding, the

    TVA and others have reported good results using hot asphalt

    grouting. In this technique, asphalt is melted and pumped

    through heated pipes into open cavities. On contact with

    the water, the asphalt cools and assumes a globular form

    that progressively blocks the solution channels. On various

    projects, the TVA has adopted a wait and see approach to

    the issue of reservoir watertightness using asphalt grouting

    for spot treatment after impoundment often followed by a

    program of cement grouting to ensure the long term stabil-

    ity of the seal.

    TheKavarReservoirThe Kavar site is situated in a mountainous region about 70

    km south of Shiraz, Iran, in the Kavar valley. To provideirrigation water, a 60m high concrete faced rockll dam is

    planned to impound the Qareh Aghaj River.

    Site Conditions

    As indicated on Figure 4, the project site can be character-

    ized by two distinct regions, a broad upper reservoir and

    a lower reservoir. The lower reservoir is contained within

    a relatively steep sided canyon where the dam is located.

    The elevated margins in the upper reservoir and the steeply

    dipping right abutment of the lower reservoir at the dam

    site are composed of a strong, moderately to highly karsticlimestone known as the Asmari formation. Weaker Razak

    marls are present, locally, within the base of both the upper

    and lower reservoirs and form the relatively shal low dipping

    left bank of the lower reservoir.

    Bedrock Geology

    The Asmari Limestone is highly permeable to great depths

    throughout the site area due to the existence of solutioned

    channels that formed along and across bedding planes.

    This has created an unpredictable system of interconnected

    ow channels and a rock mass permeability in the order of100 Lugeons and higher. The characteristics of the Razak

    formation vary across the site. At the dam site, the Razak

    formation is highly deformed as a result of the intense fold-

    ing that was responsible for the creation of the canyon itself.

    The geologic environment has produced gypsum formations

    along bedding planes as well increased hydraulic conductivi-

    ties in the range of 10 to 50 Lugeons. In the upper reservoir,

    the Razak is generally undeformed and was found to be es-

    sentially impervious.

    Overburden Conditions

    In the upper reservoir, overburden consists of a broad, deep

    deposit of lacustrine materials anked on the margins by

    slopewash. Both the slopewash and lacustrine materials

    were found to be of relatively low permeabi lity. In the

    immediate area of the river channel, coarse grained, per-

    vious, river alluvium is present. However, it is completely

    surrounded by the relatively impervious slopewash or lacus-

    trine materials. This distribution of overburden materials

    forms a natural impervious blanket, eectively isolating the

    pervious Asmari limestone formation from the future res-

    ervoir. At the dam site, there are no lacustrine deposits and

  • 7/29/2019 foundation tratment

    6/9

    Figure 6 Seepage Control Measures at the Kavar Dam

    Concrete Facing

    EL. 1665 m (Reservoir Level)

    EL. 1626 m

    GypsumSurcharge Plastic Concrete Cutoff Wall

    Conceptual Location of Gypsum BedGrout Curtain

    EL. 1605 m

    EL. 1535 m

    11

    EL. 1640 m

    Rock Fill

    EL. 1671 m

    EL. 1595 m(Assumed Downstream Groundwater Level)

    4A5

    Impervious Fill

    Semi-Pervious Fi llUpstreamCofferdam

    DownstreamCofferdam

    Figure 5 Conceptual Sketch of Selected

    Lower Reservoir Water Tightness Scheme

    Reinforced ShotcreteMembrane 10-8

    Impervious Blanket toMaximum Reservoir Level 10-5

    1660 m(Maximum Reservoir El.)

    Slope Wash 10-3

    AS 10-2

    30-80 m

    Undeformed Razak 10-5

    Deformed Razak10-3 to 10-4

    6 www.powergenu.com

    the river alluvium can come in contact with, or be very close

    to, highly pervious bedrock. In addition, slopewash materi-

    als were found to be signicantly more permeable than in

    the upper reservoir area due to the fact that these materials

    originated as a result of the mass movement of considerably

    steeper rock slopes, thereby producing a coarser material.

    Groundwater ConditionsIn the lower reservoir val ley, groundwater levels were found

    to be about 10m below the river level, conrming the pervi-

    ous nature of the bedrock and the need to seal the reservoir.

    ReservoirTreatment

    On the basis of the explorations undertaken at the site, a

    clear picture of the nature of the foundation conditions, and

    the problems that they presented, was developed. In the

    upper reservoir area most of the leakage would be forced,

    under a moderate head, through the impervious lacustrine

    materials and/or the low permeability slopewash that blan-ket the bedrock side slopes before reaching the pervious

    Asmari bedrock. Therefore, provided that local treatment

    of exposed Asmari outcrops in the upper reservoir was un-

    dertaken, losses would generally be minimal. On the other

    hand, in the lower reservoir area, leakage will occur under

    relatively high head through relatively pervious slopewash

    into the immediately adjacent pervious Razak bedrock and/

    or directly into the right abutment highly pervious Asmari

    formation. Limiting seepage losses to manageable levels in

    this area, therefore, required a comprehensive treatment

    plan to seal the entire ooded canyon.

    Originally, it had been planned to use of a complex

    grouting scheme to tie the highly pervious Asmari into,

    what was assumed to be, impervious Razak bedrock us-

    ing a technique similar to one that had been successfully

    employed at the El Cajun project. However, as the explo-

    ration program evolved, it became apparent that both the

    upper portion of the Razak, and the overlying slopewash

    materials, were signicantly more permeable than had

    been previously assumed. To reduce concerns regardingsubsurface unknowns, and the reliance on grouting to great

    depths to adequately seal the foundation, an alternative wa-

    tertightness treatment using a surcial impervious surface

    membrane was developed as shown conceptually in Figure

    5. On the relatively steep right bank where the Asmari out-

    crops, the membrane consists of a 120 mm thick, silica fume

    reinforced shotcrete membrane anchored into the slope. In

    the valley bottom, and over the left bank where relatively

    at slopes exist due to the presence of the Razak formation,

    an overburden blanket, consisting of compacted impervi-

    ous and erosion protection lls is planned. This treatment

    wil l cover the entire lower reservoir area, extending ap-

    proximately 700-800 m upstream of the dam site to the

    upper reservoir where it will be connected into the natural

    impervious materials that exist there. Although unusual, as

    shown on Table 2, the use of shotcrete for sealing a dam or

    reservoir is not unprecedented.

  • 7/29/2019 foundation tratment

    7/9

    Figure 7 The Effect of Gypsum Particle Size

    on the Contact Time Required for Saturation1.0

    0.4

    0.2

    Concentration

    Ratio

    0

    0

    Contact Time (Days)

    0.5mm Particle Size

    0.1mm Particle Size Saturation

    50 150 250100 200 300

    0.6

    0.8

    Figure 8 Estimated Mass Removal Rates

    for the Gypsum Surcharge at the Kavar Dam

    800

    320

    80Masso

    fGypsum

    Remove

    dper

    Un

    it

    Surc

    harge

    Area

    (kg

    /sq.

    m)

    0

    0

    Time After Reservoir Impoundment (Years)

    Upper Bound

    70 kg/sq.m/year

    Lower Bound2 kg/sq.m/year

    1 2 3 4 5 6 7 8 9 10

    160

    480

    640

    400

    240

    560

    720

    www.powergenu.com 7

    To further reduce the likelihood of any future problemsassociated with progressive dissolution of the gypsum

    beds known to exist above a depth of 50 m in the Razak

    formation at the dam site, a plastic concrete cut-o wall is

    planned. This will be supplemented by a double line grout

    curtain to reduce seepage gradients across the cuto, and

    to further reduce the bedrock permeability. Details of the

    treatment measures planned at the dam site are shown on

    Figure 6.

    TheGypsumSurcharge

    Another unique feature of the treatment measures used at

    the Kavar site is a gypsum surcharge that is to be installed

    immediately upstream of the dam. The purpose of the

    surcharge ll is to cause water seeping through the ll to

    become saturated with dissolved gypsum at a concentration

    as close as possible to the solubility limit, similar to a con-

    cept reported by Pokrovskii, 1994 in which salt solutions are

    injected into the foundation of dams constructed on rocks

    containing water-soluble salts (ha lite).

    To assess the gypsum requirements for the dam, the

    approach of James and Lupton for particulate forms of gyp-

    sum and anhydrite was used. Key parameters in the analysis

    included the density, D, of gypsum 2300 kg/m3, the initiallinear particle size lo, the particle volume coecient b (vol.

    =bl3), the particle area coecient a (area= al2), the solubil-

    ity rate constant K, and the solubility limit cs of gypsum.

    As a rst step, ow nets were constructed to estimate the

    hydraulic ux through the gypsum surcharge. The thick-

    ness of the gypsum bed could then be designed by assuming

    advective transport only (i.e., neglecting diusion). In this

    way, the dissolved mass of gypsum leaving the surcharge

    per unit area could be approximated by the product of the

    gypsum concentration and seepage ux per unit area of

    surcharge. The calculated ow rate through the gypsum

    surcharge was found to vary from 2.0x10-6 to 9.5x10-5cm/

    sec. Based on an assumed porosity of 0.3, seepage velocities

    through the gypsum bed were estimated to vary between

    6.7x106cm/sec and 3x10-4 cm/sec.

    The size of surcharge required is based on the design

    life of the project and the amount of time required to en-

    sure that the seepage water owing through the gypsum

    surcharge area is fully saturated with gypsum. To achieve

    the required contact time with a reasonable sized surcharge

    ll, a number of alternatives were considered, including:

    increasing the surcharge thickness, reducing the hydraulic

    Table 2: Summary of Examples of Shotcrete used as for Water Tightness Treatment

    Project Country Date Structure DescriptionLength

    (m)

    Height

    (m)

    La Joie Canada 1955Timer aced

    rockfll damGunite used to seal deteriorated timber aced dam 400 60.0

    Leichhardt

    RiverAustralia 1957 Rockfll dam

    Reinorced gunite used as sole impervious ele-

    ment or rockfll dam260 26.5

    Corella Australia 1957 Rockfll damReinorced gunite used as the sole impervious

    element146 23

    Hammam

    GrouzAustria 1987

    Concrete

    gravity dam

    Shotcrete and clay blanket used to seal karstic

    limestone reservoir slopes50 36.0

    Tranavka Czech 1988 Earth dam Shotcrete and plastic membrame used or sealing 20.0

    Jordan

    RiverCanada 1989

    Amberson

    buttres damShotcrete used or sealing 29.0

    Eastside

    ReservoirUSA 1998

    Blasted rock

    SlopesShotcrete used or sealing the reservoir 250 50.0

  • 7/29/2019 foundation tratment

    8/98 www.powergenu.com

    conductivity of the impervious blanket within 100 meters

    of the upstream plinth and reducing the particle size of

    the gypsum. The most eective means of enhancing con-

    tact time was found to be reducing the particle size. For

    example, as shown on Figure 7, as gypsum particle size is

    reduced from 0.5 mm to 0.1 mm, minimum contact times

    reduced from 200 to 40 days.

    On this basis, the Kavar surcharge was designed as a 5m thick mixture of 40% (by weight) ground gypsum, with

    a maximum particle size in the range of 0.1 to 0.5 mm,

    thoroughly mixed with ne a grained soil. This produces

    an engineered ll with a dry unit mass of 1900 kg/m3 and

    a permeability in the desired range of 10-4 to 10-5 cm/sec.

    As indicated in Figure 8, for this design, the annual mass

    removal rate is expected to vary between 2 kg to 70 kg per

    square meter of surcharge. For the 3,800 kg Kavar sur-

    charge, this will result in a service life of at least 50 years.

    ConclusionsTechniques exist to treat even highly karstic foundations.

    However, for treatment measures to be eective, a thorough

    understanding of the site conditions is essential. At the Ka-

    var Dam, an unusual combination of a surface membrane,

    in combination with a gypsum surcharge and other seepage

    control measures, is planned to deal with the complex foun-

    dation problems that had been identied.

    References

    Fischer, J.A. and Fischer, J.J., 1995. Karst site remediation grouting.

    Karst GeoHazards: Proc. 5th Multidisciplinary Conference onSinkholes and the Engineering and Environmental Impacts ofKarst.Balkema, Roterdam, pp. 363-369.

    Freeze, R.A. and Cherry, J.A. , 1979. Groundwater, Prentice HallInc., Upper Saddle River, New Jersey., pp. 383-462.

    James, A.N. and Kirkpatrick, I.M., 1988. Design of foundations ofdams containing soluble rocks and soils. Quarterly Journal ofEngineering Geology, Vol. 13, pp. 189-198.

    James A.N., and Lupton, A.R. 1978, Gypsum and anhydrite infoundations of hydraulic structures. Geotechnique, Vol. 28,No. 3, pp. 249-272.

    Pokrovski i, G.I., 1994. Combined methods of protecting saliferousfoundation soils of hydraulic structures from dissolution.Hydrotechnical Construction Vol. 28, No. 10, pp 10-14.

    Soderberg, A.D., 1988. Foundation treatment of karstic featuresunder TVA dams. Geotechnical Aspects of Karst Terrain,

    ASTM Geotechnical Special Publication No. 14, pp. 149-165.

    Uromeihy, A. 2000. The Lar Dam; an example of infrastructuredevelopment in a geologically active karstic region. Journalof Asian Earth Sciences, Elsevier Science , vol. 18, no. 1, pp.25-31(7).

    Welsh, J.P., 1988. Sinkhole rectication by compaction grouting.Geotechnical Aspects of Karst Terrain, ASTM GeotechnicalSpecial Publication No. 14, pp. 115-132.

    Zuomei, Z. and Pinshou, H., 1988. Grouting of the karstic caves

    with clay llings. Geotechnical Aspects of Karst Terrain,ASTM Geotechnical Special Publication No. 14, pp. 92-104.

    Fookes, P. G., and Hawkings, A. B., 1988. Limestone weathering:its engineering signicance and a proposed classicationsystem. Quarterly Journal of Engineering Geology, London,Vol. 21, pp. 7-31.

    ACKNOWLEDGEMENTS:This course is based on the presentation entitled The Design

    of Foundation Treatment Measures for Dams on KarstFoundations as presented at Waterpower 2001. The authorsfor this paper are acknowledged as C. R. Donnelly and S.Hinchberger of Acres International, and E. Mohammadian ofDezab Consulting Engineers. Portions of the original paperhave been modied for this course.

  • 7/29/2019 foundation tratment

    9/9www powergenu com 9

    Questions

    OnlineCompletionUse this page to review the questions and choose your answers. Return to www.powergenu.com and sign in. I you have not previously purchased the program

    select it rom the Online Courses listing and complete the online purchase. Once purchased the exam will be added to your User History page where a Take

    Exam link will be provided. Click on the Take Exam link, complete all the program questions and submit your answers. An immediate grade report will be

    provided and upon receiving a passing grade (70%) your Certifcate o Completion will be provided immediately or viewing and/or printing. Certifcates o

    Completion can be viewed and/or printed anytime in the uture by returning to www.powergenu.com, sign in and return to your User History Page.

    1. Karsticity occurs as a resultof a progressive disolutioningof carbonate rocks exposed to

    water and carbon dioxide.

    a. Trueb . Falsec. I dont know what Karsticity is

    2. In the presence of dissolved carbondioxide, maximum concentrationsincrease dramatically, account-ing for the fact that seepageowing from karst formations

    often contains up to _____mg/L of calcium carbonate.

    a. 200b. 300c. 400d. 600e. 800

    3. A karstic formation impliesthe presence of a network ofsolutioned, often highly permeable,discontinuities which are, bydenition, connected to the surfaceso that the free carbon dioxidenecessary to allow the solutioningprocess to continue is available.

    a. Trueb. False

    4. The diculties involved inconstructing a dam on a karsticfoundation were rst documentedat ____ ____ dam that was built byprivate interests on the Tennessee

    River between 1905 and 1913.a. Hails Boxb. Hills Barnc. Hales Bard. Hanes Bar & Grill

    5. The problems at dams that havesevere seepage or leakage arelikely related, at least in part, toan inadequate understanding ofthe _____ of karst prior to thecommencement of construction.

    a. depthb. typec. colord. strength

    e. All of the above

    6. Successful treatment of karstic

    foundations requiresa. a means of reducing the

    amount of seepage

    b. techniques to prevent dissolution

    of soluble minerals that may be

    present in the foundation

    c. methods to ensure that the

    foundation has adequate capacity

    to resist the post impoundment

    loadings without excessive settlement

    d. All of the above

    7. Foundation treatment for karstic

    formations typically includes

    consolidation grouting to

    a. increase adequate bearing strength

    b. minimize settlements

    c. reduce subsurface water ows

    d. seal void areas

    8. Compaction grouting typically

    results in hydraulic fracturing,

    extrusion and consolidation

    of clayey llings within the

    sinkholes increasing strength, and

    resistance to seepage stresses.

    a. True

    b. False

    9. The most commonly occurring

    soluble rock mineral(s) are

    a. calcium carbonate (limestone)b. gypsum

    c. anhydrite

    d. halite

    e. All of the above

    10. Mitigation of the risk of solutioning

    in a foundation containing such

    minerals as calcium carbonate,

    gypsum, anhydrite, and halite

    requires reducing the volume of

    a. karstic voids

    b. subsurface groundwater

    c. seepage and seepage gradients

    d. hydraulic gradient

    11. An active brine injection system

    has been used to treat foundationscontaining halite mineral deposits.

    a. True

    b. False

    12. The Median Post Impound-

    ment Seepage of approximately

    50 l/sec would require

    a. 1 line of grout

    b. 2 lines of grout

    c. 3 lines of grout

    d. 4 lines of grout

    13. It is usually necessary to extend

    the grout curtain along the dam

    axis into the abutments to

    reduce risks associated with

    end run seepage. The amount

    of extension is dependent

    a. on geological conditions

    b. on economic impacts

    c. on diculty of install ing

    the grout curtain

    d. on the schedule of remediation

    14. Hot asphalt grouting is a technique

    where asphalt is melted and

    pumped through heated pipes into

    open cavities. On contact with the

    water, the asphalt cools and as-

    sumes a globular form that progres-

    sively blocks the solution channels.

    a. True

    b. False

    15. At the Kavar Project, the proposed

    reservoir treatment included an

    impervious surface membrane; an

    overburden blanket, consisting

    of compacted impervious and

    erosion protection ll; a reinforced

    concrete shotcrete membrane;and a gypsum surcharge.

    a. True

    b. False