foundation tratment
Transcript of foundation tratment
-
7/29/2019 foundation tratment
1/9www.powergenu.com
Foundation TreatmentMeasures for Dams
Located onKarst Foundations
-
7/29/2019 foundation tratment
2/92 www.powergenu.com
Educational ObjectivesOn completion of this course, students will:
This course will provide the student with an overview of
foundation treatments for dams constructed on karst foun-
dations. For this course the Kavar Dam in Iran was the
example where an unusual combination of a surface mem-
brane, coupled with a gypsum surcharge and other seepage
control measures, were planned to seal a highly karstic
foundation.
IntroductionKarsticity occurs as a result of a progressive disolutioning
of carbonate rocks exposed to water and carbon dioxide. In
pure water, at 25oC, the maximum possible concentration
of dissolved calcium carbonate is in the range of 14 mg/L
(Fookes and Hawkins, 1988). However, in the presence of
dissolved carbon dioxide, maximum concentrations increase
dramatically, accounting for the fact that seepage owing
from karst formations often contains up to 400 mg/L of
calcium carbonate ( James and Fitzpatrick, 1988). Therefore,
a karstic formation implies the presence of a network of
solutioned, often highly permeable, discontinuities which
are, by denition, connected to the surface so that the free
carbon dioxide necessary to allow the solutioning process to
continue is available. This fact means that Karst founda-
tions are usually associated with highly deformed, complex,
rock masses that have pervious windows extending directly
to the foundation surface.
The diculties involved in constructing a dam on a
karstic foundation were rst documented at Hales Bar damthat was built by private interests on the Tennessee River
between 1905 and 1913. Although the existence of cavernous
rock in the limestone foundation was postulated, geological
theory at the time suggested that cave formation occurred
only above the water table. (T.V.A. Technical Report No.
22, 1949). Therefore, very little foundation treatment was
performed and, following construction, leakage under the
dam of up to 48 m3/s was measured. Various remedial works
projects were carried out at the site over the 60 years that
it was in operation until, in 1968, the dam was demolished.
In the years following the construction of the Hales bar
dam the eects of solutioning have had adverse impacts on
both reservoir water tightness and the structural integrity
of many dams. Although there are few documented struc-
tural failures attributed to sinkhole collapse in karst ter-
rain, there are numerous examples of problems associated
with reservoir lling. For example, at the Lar dam in Iran
(Uromeihy, 2000) it was not possible to impound to full sup-
ply level due to foundation leakage that reached two-thirds
of the total river ow. A remedial grouting program, per-
formed between 1985 and 1990, was only partially success-
ful in reducing seepage and, to date, the reservoir remains
partially lled. In the case of the Anchor Dam constructed
in 1960, (Fig. 1), an extensive system of sinkholes and faults
have prevented any permanent storage of water, despite
numerous remedial sealing attempts. (ww w.usbr.gov/cdams/
dams)
As a result of experience gained from such dams,
techniques have been developed to successfully treat even
seriously karstic foundations. This course describes current
practice for the design of dams on karst terrain as well assome unique seepage control measures that are planned to
mitigate risks associated with a highly karstic limestone
foundation in Iran. These measures include the use of an
Foundation Treatment Measures for
Dams Located on Karst Foundations
1. Understand the diculties of constructing
a dam on a karstic foundation.
2. Identify methods to treat karstic foundationsfor the construction of a dam.
3. Understand grouting techniques and other seepage
control measures for karstic foundations.
4. Understand the eects of solutioning on reservoirwater tightness and the structural integrity of dams.
-
7/29/2019 foundation tratment
3/9
Figure 1 The Anchor Dam Wyoming USA
Figure 2 Effect of Multiple Line Grouting on the Median Post Impoundment
Seepage Reported for Some Selected Precedent Dams (ref. Table 1)
600
300
200
MedianPos
tImpoundmentSeepage(l/sec)
100
0
0
Number of Grout Lines
1 2 3 4
400
400
www.powergenu.com 3
engineered soluble ll and a surcial shot-
crete membrane to seal the foundation
surface.
CurrentPractice
The key to any successful construction
on a karst foundation is a thorough un-
derstanding of the nature of the problemsthat must be treated. In the rst half of
the 20th century, dams such as the Hales
Bar, Wolf Creek, Mosul, and Great Falls
were constructed on karstic foundations without adequate
foundation explorations. All experienced either foundation
leakage or piping problems. More recently, the problems
at the Lar dam are likely related, at least in part, to an in-
adequate understanding of the depth of karst prior to the
commencement of construction.
On the other hand, if exploration and foundation treat-
ment measures are carried out thoroughly, even a highlykarstic foundation can be successfully treated. For example,
advanced karst foundations beneath the 90 to 100 m high
Pueblo Viejo and Punt Dal Gall dams were successfully
treated such that post-impoundment seepage has only been
25 and 50 l/sec respectively.
In broad terms, modern practice for the successful treat-
ment of karstic foundations requires a means of reducing
the amount of seepage, techniques to prevent dissolution
of soluble minerals that may be present in the foundation,
and methods to ensure that the foundation has adequate
capacity to resist the post impoundment loadings without
excessive settlement.
Improving Deformability
Commonly applied techniques for improving the deform-
ability and stability of karst foundation rocks include exca-
vation/mucking of solution cavities followed by lling with
a sand and gravel slurry, concrete and/or compaction grout-
ing. For example, at the 21 dams that the Tennessee Valley
Authority (TVA) has constructed on carbonate foundations,
Soderberg (1988) notes that foundation treatment typically
includes consolidation grouting to ensure adequate bearing
strength and to minimize settlements. Solutioned areas, in
otherwise sound rock, are then mucked or excavated and
lled with concrete.
More recently, compaction grouting has been used to
treat karst features. This technique involves the injection
of low-slump soil/cement grout to displace and/or compress
the surrounding soils for greater strength (Fischer and
Fischer, 1995). This typically results in hydraulic fractur-
ing, extrusion and consolidation of clayey llings within
the sinkholes increasing strength, and resistance to seep-age stresses. Welsh (1988) and Zuomei and Pinshou (1988)
describe the use of compaction grouting to rectify sinkholes
and caves lled with clay llings and to build a seepage
resistant barrier in Karst terrain for the
Wujiangdu Hydroelectric Project in China.
Reducing the Potential for Dissolution of Soluble
Minerals
The most commonly occurring soluble rock
minerals are calcium carbonate (limestone)
gypsum, anhydrite and halite. In general,mitigation of the risk of solutioning in a
foundation containing such minerals re-
quires reducing the volume of seepage and
seepage gradients. This, traditionally, had been accom-
plished on the basis of precedent practice. An analytical
framework for assessing the solutioning potential of various
forms of soluble rock minerals was rst presented by James
and Lupton (1978). James and Kilpatrick (1980) used these
solutions to study seepage control measures for dam con-
structed on foundations containing the soluble rocks. They
concluded that grouting, or the provision of an upstreamimpervious blanket, can control the solutioning of calcium
carbonate rock. For foundations containing gypsum, con-
ventional (sulphate resistant) cement curtain grouting was
recommended. Mineral deposits such as anhydrite were
found to require a more ecient cuto, such as plastic con-
crete wall in combination with measures such as upstream
blankets or other techniques designed to reduce seepage
velocities. They recommended that halite, in its massive
form, be avoided. However, it is of note that an active brine
injection system has been used to treat foundations contain-
ing hal ite mineral deposits (Pokrovskii, 1994).
Grouting
For well developed karst foundations, a sulphate resistant
multiple line grout curtain, with provisions to allow future
grouting, is typically used to reduce seepage losses. For
lower head dams, or for dams on less well developed karst,
single or double line curtains are often used. However,
all karstic foundations should be treated with caution. As
shown on Table 1, very high seepages can be experienced
for even low head dams if karstic conditions are advanced.
On the basis of median grout takes reported at a number of
-
7/29/2019 foundation tratment
4/94 www.powergenu.com
Table 1: Precedent Examples of Some Dams Built on Karstic Foundations
Project DamTypeandDate Head(m) GeologyNo.of
GroutLinesSeepage
Remedial
Work
J. Percy
Priest Dam
Earthfll/Concrete
1963-6835.4
Thin-bedded limestone, solu-
tioned jts, sinkholes2 - 4 N. R. N. R.
Sainte Croix
Dam FranceArch 1971-74 72 Cavernous limestone 1 Negligible N. R.
Quinson Dam
FranceArch 1971-74 45 Cavernous limestone 1 Negligible N. R.
Grand Rapids
G. S. Canada
Earthfll/Concrete
1962-6436.5
Dolomite limestone, sinkholes,
solution channels1 Minimal None
Arnprior G. S.
Canada
Earth/Rockfll/
Concrete gravity
1972-76
21Limestone, Solutioned jts, voids
1 cm - 1 m wide3 - 4 l/s N. R.
Lar Dam IranEarthfll
1972-8198
Limestone, advanced karst,
caverns, voids1
Extreme
9 m3/s
Yes
(see text)
Stewartville
Dam Canada
Concrete
gravity/EarthfllCompleted 1948
41
Crystalline limestone open
seams at depth 1 370 l/s Yes.3
Francisco Zarco
Dam Mexico
Earthfll/Concrete
Completed 196823
Limestone, solution channels,
mode karst3 1000 l/s None
La Amistad
Mexico/U.S.A.
Rockfll/Concrete
Completed 196830 Limestone, caverns, sinkholes 1 Minimal None
Sklope Dam
YugoslaviaRockfll 80
Limestone, advanced karst,
caverns1 - 2 500 l/s None
Globocica Dam
Yugoslavia
Rockfll
Completed 196580
Limestone, med. to adv. karst,
solution channels3 4 l/s Yes.4
Hales Bar Dam
U.S.A.
Earthfll/Concrete
1905-19135 11.5
Limestone, solution jts., cavi-
ties, caverns 1
Max. 48
m3/s Yes.
6
Great Falls
U.S.A.
Concrete gravity
Completed 191645.7
Limestone, solution channels,
cavities1 12 m3/s Yes.7
Normandy Dam
U.S.A.
Concrete gravity/
Earthfll 1972-7617
Limestone with shale, clay solu-
tion cavities1 - 2 Negligible None
Pueblo Viejo
Dam GuatemalaRockfll 1977-83 92
Limeston & dolomite, advanced
artesian karst1 - 2 25 l/s None
Punt Dal Gall
Switzerland
Arch
Completed 1969100
Dolomite limestone, calcareous
sandstone, deep karst, solu-
tioned jts
1 50 l/s None
La Bolera Dam
Spain Arch 1961-68 45 Limestone, advanced caverns 1 600 l/s None
Sprinagarind
Dam Thailand
Rockfll/Concrete
1974-80113
Calcareous sandstone, lime-
stone, solution cavities3 25 l/s N. R.
King Talal Dam
Jordan
Rockfll/Concrete
gravity Completed
1971-75
100Karstic limestone to 30 m below
calcareous sandstone1 63 l/s None
La Angostura
Dam Mexico
Rockfll/Concrete
1971-7589
Limestone, clay seams and
solutioned jts2 100 l/s None
3 Asphalt grouting in 1985 reduced leakage by up to 33 l/s
4 Grout curtain extended in left abutment in 19745 Demolished 1960
6 Extensive in 1944
7 Cement and asphalt grouting performed
-
7/29/2019 foundation tratment
5/9
Figure 3 Precedent Examples of Grout Curtain Extension into Abutments16
RatioofGroutCurtainExtentioninto
Abutmen
tstoHydraulicHead
00
Maximum Normal Hydraulic Head (m)
Open symbol indicates that remedial work
or excessive seepage (>300 l/s) was reported.
2
4
6
8
10
12
14
20 40 60 80 100 120 140 160 180
Slightly Karstic
(grout take 0 to 50 kh/m)
Highly Karstic
(grout take > 400 kg/m)
Karstic
(grout take 50 to 400 kg/m)
Grout take not reported
Figure 4 Kavar Reservoir and Dam Site
Razak Formation
Asmari Formation
Fault Line
Full Service Level (FSL)Reservoir Rim
Existing River
DamLocation
Lower Reservoir
Upper Reservoir
www.powergenu.com 5
precedent dams reported in the literature, triple line grout-
ing can be seen to reduce post impoundment risks (Figure 2)
It is also clear from Table 1 that a signicant factor
governing the performance of grout curtains in karst foun-
dations is whether or not the curtain is anchored into an
impervious base. For example, at the 11.5m high Hales Bar
dam, post construction seepage reached 48 m3 per second
through the hanging curtain. Similarly, at the FranciscoZaro Dam, seepage ows in the order of 1000 L/sec through
the hanging curtain were measured, despite the fact that a
triple line grout curtain had been used.
It is usually necessary to extend the grout curtain some
distance along the dam axis into the abutments to reduce
risks associated with end run seepage. The amount of exten-
sion required can be somewhat subjective, and is dependent
on geological conditions such as the existence of an impervi-
ous boundary. However, for dams founded on a moderately
permeable karstic foundation, a review of precedent would
suggest that the amount of extension required to minimizerisk varies logarithmically as a function of the hydraulic
head (Figure 3).
Asphalt Grouting
When remedial grouting is required after impounding, the
TVA and others have reported good results using hot asphalt
grouting. In this technique, asphalt is melted and pumped
through heated pipes into open cavities. On contact with
the water, the asphalt cools and assumes a globular form
that progressively blocks the solution channels. On various
projects, the TVA has adopted a wait and see approach to
the issue of reservoir watertightness using asphalt grouting
for spot treatment after impoundment often followed by a
program of cement grouting to ensure the long term stabil-
ity of the seal.
TheKavarReservoirThe Kavar site is situated in a mountainous region about 70
km south of Shiraz, Iran, in the Kavar valley. To provideirrigation water, a 60m high concrete faced rockll dam is
planned to impound the Qareh Aghaj River.
Site Conditions
As indicated on Figure 4, the project site can be character-
ized by two distinct regions, a broad upper reservoir and
a lower reservoir. The lower reservoir is contained within
a relatively steep sided canyon where the dam is located.
The elevated margins in the upper reservoir and the steeply
dipping right abutment of the lower reservoir at the dam
site are composed of a strong, moderately to highly karsticlimestone known as the Asmari formation. Weaker Razak
marls are present, locally, within the base of both the upper
and lower reservoirs and form the relatively shal low dipping
left bank of the lower reservoir.
Bedrock Geology
The Asmari Limestone is highly permeable to great depths
throughout the site area due to the existence of solutioned
channels that formed along and across bedding planes.
This has created an unpredictable system of interconnected
ow channels and a rock mass permeability in the order of100 Lugeons and higher. The characteristics of the Razak
formation vary across the site. At the dam site, the Razak
formation is highly deformed as a result of the intense fold-
ing that was responsible for the creation of the canyon itself.
The geologic environment has produced gypsum formations
along bedding planes as well increased hydraulic conductivi-
ties in the range of 10 to 50 Lugeons. In the upper reservoir,
the Razak is generally undeformed and was found to be es-
sentially impervious.
Overburden Conditions
In the upper reservoir, overburden consists of a broad, deep
deposit of lacustrine materials anked on the margins by
slopewash. Both the slopewash and lacustrine materials
were found to be of relatively low permeabi lity. In the
immediate area of the river channel, coarse grained, per-
vious, river alluvium is present. However, it is completely
surrounded by the relatively impervious slopewash or lacus-
trine materials. This distribution of overburden materials
forms a natural impervious blanket, eectively isolating the
pervious Asmari limestone formation from the future res-
ervoir. At the dam site, there are no lacustrine deposits and
-
7/29/2019 foundation tratment
6/9
Figure 6 Seepage Control Measures at the Kavar Dam
Concrete Facing
EL. 1665 m (Reservoir Level)
EL. 1626 m
GypsumSurcharge Plastic Concrete Cutoff Wall
Conceptual Location of Gypsum BedGrout Curtain
EL. 1605 m
EL. 1535 m
11
EL. 1640 m
Rock Fill
EL. 1671 m
EL. 1595 m(Assumed Downstream Groundwater Level)
4A5
Impervious Fill
Semi-Pervious Fi llUpstreamCofferdam
DownstreamCofferdam
Figure 5 Conceptual Sketch of Selected
Lower Reservoir Water Tightness Scheme
Reinforced ShotcreteMembrane 10-8
Impervious Blanket toMaximum Reservoir Level 10-5
1660 m(Maximum Reservoir El.)
Slope Wash 10-3
AS 10-2
30-80 m
Undeformed Razak 10-5
Deformed Razak10-3 to 10-4
6 www.powergenu.com
the river alluvium can come in contact with, or be very close
to, highly pervious bedrock. In addition, slopewash materi-
als were found to be signicantly more permeable than in
the upper reservoir area due to the fact that these materials
originated as a result of the mass movement of considerably
steeper rock slopes, thereby producing a coarser material.
Groundwater ConditionsIn the lower reservoir val ley, groundwater levels were found
to be about 10m below the river level, conrming the pervi-
ous nature of the bedrock and the need to seal the reservoir.
ReservoirTreatment
On the basis of the explorations undertaken at the site, a
clear picture of the nature of the foundation conditions, and
the problems that they presented, was developed. In the
upper reservoir area most of the leakage would be forced,
under a moderate head, through the impervious lacustrine
materials and/or the low permeability slopewash that blan-ket the bedrock side slopes before reaching the pervious
Asmari bedrock. Therefore, provided that local treatment
of exposed Asmari outcrops in the upper reservoir was un-
dertaken, losses would generally be minimal. On the other
hand, in the lower reservoir area, leakage will occur under
relatively high head through relatively pervious slopewash
into the immediately adjacent pervious Razak bedrock and/
or directly into the right abutment highly pervious Asmari
formation. Limiting seepage losses to manageable levels in
this area, therefore, required a comprehensive treatment
plan to seal the entire ooded canyon.
Originally, it had been planned to use of a complex
grouting scheme to tie the highly pervious Asmari into,
what was assumed to be, impervious Razak bedrock us-
ing a technique similar to one that had been successfully
employed at the El Cajun project. However, as the explo-
ration program evolved, it became apparent that both the
upper portion of the Razak, and the overlying slopewash
materials, were signicantly more permeable than had
been previously assumed. To reduce concerns regardingsubsurface unknowns, and the reliance on grouting to great
depths to adequately seal the foundation, an alternative wa-
tertightness treatment using a surcial impervious surface
membrane was developed as shown conceptually in Figure
5. On the relatively steep right bank where the Asmari out-
crops, the membrane consists of a 120 mm thick, silica fume
reinforced shotcrete membrane anchored into the slope. In
the valley bottom, and over the left bank where relatively
at slopes exist due to the presence of the Razak formation,
an overburden blanket, consisting of compacted impervi-
ous and erosion protection lls is planned. This treatment
wil l cover the entire lower reservoir area, extending ap-
proximately 700-800 m upstream of the dam site to the
upper reservoir where it will be connected into the natural
impervious materials that exist there. Although unusual, as
shown on Table 2, the use of shotcrete for sealing a dam or
reservoir is not unprecedented.
-
7/29/2019 foundation tratment
7/9
Figure 7 The Effect of Gypsum Particle Size
on the Contact Time Required for Saturation1.0
0.4
0.2
Concentration
Ratio
0
0
Contact Time (Days)
0.5mm Particle Size
0.1mm Particle Size Saturation
50 150 250100 200 300
0.6
0.8
Figure 8 Estimated Mass Removal Rates
for the Gypsum Surcharge at the Kavar Dam
800
320
80Masso
fGypsum
Remove
dper
Un
it
Surc
harge
Area
(kg
/sq.
m)
0
0
Time After Reservoir Impoundment (Years)
Upper Bound
70 kg/sq.m/year
Lower Bound2 kg/sq.m/year
1 2 3 4 5 6 7 8 9 10
160
480
640
400
240
560
720
www.powergenu.com 7
To further reduce the likelihood of any future problemsassociated with progressive dissolution of the gypsum
beds known to exist above a depth of 50 m in the Razak
formation at the dam site, a plastic concrete cut-o wall is
planned. This will be supplemented by a double line grout
curtain to reduce seepage gradients across the cuto, and
to further reduce the bedrock permeability. Details of the
treatment measures planned at the dam site are shown on
Figure 6.
TheGypsumSurcharge
Another unique feature of the treatment measures used at
the Kavar site is a gypsum surcharge that is to be installed
immediately upstream of the dam. The purpose of the
surcharge ll is to cause water seeping through the ll to
become saturated with dissolved gypsum at a concentration
as close as possible to the solubility limit, similar to a con-
cept reported by Pokrovskii, 1994 in which salt solutions are
injected into the foundation of dams constructed on rocks
containing water-soluble salts (ha lite).
To assess the gypsum requirements for the dam, the
approach of James and Lupton for particulate forms of gyp-
sum and anhydrite was used. Key parameters in the analysis
included the density, D, of gypsum 2300 kg/m3, the initiallinear particle size lo, the particle volume coecient b (vol.
=bl3), the particle area coecient a (area= al2), the solubil-
ity rate constant K, and the solubility limit cs of gypsum.
As a rst step, ow nets were constructed to estimate the
hydraulic ux through the gypsum surcharge. The thick-
ness of the gypsum bed could then be designed by assuming
advective transport only (i.e., neglecting diusion). In this
way, the dissolved mass of gypsum leaving the surcharge
per unit area could be approximated by the product of the
gypsum concentration and seepage ux per unit area of
surcharge. The calculated ow rate through the gypsum
surcharge was found to vary from 2.0x10-6 to 9.5x10-5cm/
sec. Based on an assumed porosity of 0.3, seepage velocities
through the gypsum bed were estimated to vary between
6.7x106cm/sec and 3x10-4 cm/sec.
The size of surcharge required is based on the design
life of the project and the amount of time required to en-
sure that the seepage water owing through the gypsum
surcharge area is fully saturated with gypsum. To achieve
the required contact time with a reasonable sized surcharge
ll, a number of alternatives were considered, including:
increasing the surcharge thickness, reducing the hydraulic
Table 2: Summary of Examples of Shotcrete used as for Water Tightness Treatment
Project Country Date Structure DescriptionLength
(m)
Height
(m)
La Joie Canada 1955Timer aced
rockfll damGunite used to seal deteriorated timber aced dam 400 60.0
Leichhardt
RiverAustralia 1957 Rockfll dam
Reinorced gunite used as sole impervious ele-
ment or rockfll dam260 26.5
Corella Australia 1957 Rockfll damReinorced gunite used as the sole impervious
element146 23
Hammam
GrouzAustria 1987
Concrete
gravity dam
Shotcrete and clay blanket used to seal karstic
limestone reservoir slopes50 36.0
Tranavka Czech 1988 Earth dam Shotcrete and plastic membrame used or sealing 20.0
Jordan
RiverCanada 1989
Amberson
buttres damShotcrete used or sealing 29.0
Eastside
ReservoirUSA 1998
Blasted rock
SlopesShotcrete used or sealing the reservoir 250 50.0
-
7/29/2019 foundation tratment
8/98 www.powergenu.com
conductivity of the impervious blanket within 100 meters
of the upstream plinth and reducing the particle size of
the gypsum. The most eective means of enhancing con-
tact time was found to be reducing the particle size. For
example, as shown on Figure 7, as gypsum particle size is
reduced from 0.5 mm to 0.1 mm, minimum contact times
reduced from 200 to 40 days.
On this basis, the Kavar surcharge was designed as a 5m thick mixture of 40% (by weight) ground gypsum, with
a maximum particle size in the range of 0.1 to 0.5 mm,
thoroughly mixed with ne a grained soil. This produces
an engineered ll with a dry unit mass of 1900 kg/m3 and
a permeability in the desired range of 10-4 to 10-5 cm/sec.
As indicated in Figure 8, for this design, the annual mass
removal rate is expected to vary between 2 kg to 70 kg per
square meter of surcharge. For the 3,800 kg Kavar sur-
charge, this will result in a service life of at least 50 years.
ConclusionsTechniques exist to treat even highly karstic foundations.
However, for treatment measures to be eective, a thorough
understanding of the site conditions is essential. At the Ka-
var Dam, an unusual combination of a surface membrane,
in combination with a gypsum surcharge and other seepage
control measures, is planned to deal with the complex foun-
dation problems that had been identied.
References
Fischer, J.A. and Fischer, J.J., 1995. Karst site remediation grouting.
Karst GeoHazards: Proc. 5th Multidisciplinary Conference onSinkholes and the Engineering and Environmental Impacts ofKarst.Balkema, Roterdam, pp. 363-369.
Freeze, R.A. and Cherry, J.A. , 1979. Groundwater, Prentice HallInc., Upper Saddle River, New Jersey., pp. 383-462.
James, A.N. and Kirkpatrick, I.M., 1988. Design of foundations ofdams containing soluble rocks and soils. Quarterly Journal ofEngineering Geology, Vol. 13, pp. 189-198.
James A.N., and Lupton, A.R. 1978, Gypsum and anhydrite infoundations of hydraulic structures. Geotechnique, Vol. 28,No. 3, pp. 249-272.
Pokrovski i, G.I., 1994. Combined methods of protecting saliferousfoundation soils of hydraulic structures from dissolution.Hydrotechnical Construction Vol. 28, No. 10, pp 10-14.
Soderberg, A.D., 1988. Foundation treatment of karstic featuresunder TVA dams. Geotechnical Aspects of Karst Terrain,
ASTM Geotechnical Special Publication No. 14, pp. 149-165.
Uromeihy, A. 2000. The Lar Dam; an example of infrastructuredevelopment in a geologically active karstic region. Journalof Asian Earth Sciences, Elsevier Science , vol. 18, no. 1, pp.25-31(7).
Welsh, J.P., 1988. Sinkhole rectication by compaction grouting.Geotechnical Aspects of Karst Terrain, ASTM GeotechnicalSpecial Publication No. 14, pp. 115-132.
Zuomei, Z. and Pinshou, H., 1988. Grouting of the karstic caves
with clay llings. Geotechnical Aspects of Karst Terrain,ASTM Geotechnical Special Publication No. 14, pp. 92-104.
Fookes, P. G., and Hawkings, A. B., 1988. Limestone weathering:its engineering signicance and a proposed classicationsystem. Quarterly Journal of Engineering Geology, London,Vol. 21, pp. 7-31.
ACKNOWLEDGEMENTS:This course is based on the presentation entitled The Design
of Foundation Treatment Measures for Dams on KarstFoundations as presented at Waterpower 2001. The authorsfor this paper are acknowledged as C. R. Donnelly and S.Hinchberger of Acres International, and E. Mohammadian ofDezab Consulting Engineers. Portions of the original paperhave been modied for this course.
-
7/29/2019 foundation tratment
9/9www powergenu com 9
Questions
OnlineCompletionUse this page to review the questions and choose your answers. Return to www.powergenu.com and sign in. I you have not previously purchased the program
select it rom the Online Courses listing and complete the online purchase. Once purchased the exam will be added to your User History page where a Take
Exam link will be provided. Click on the Take Exam link, complete all the program questions and submit your answers. An immediate grade report will be
provided and upon receiving a passing grade (70%) your Certifcate o Completion will be provided immediately or viewing and/or printing. Certifcates o
Completion can be viewed and/or printed anytime in the uture by returning to www.powergenu.com, sign in and return to your User History Page.
1. Karsticity occurs as a resultof a progressive disolutioningof carbonate rocks exposed to
water and carbon dioxide.
a. Trueb . Falsec. I dont know what Karsticity is
2. In the presence of dissolved carbondioxide, maximum concentrationsincrease dramatically, account-ing for the fact that seepageowing from karst formations
often contains up to _____mg/L of calcium carbonate.
a. 200b. 300c. 400d. 600e. 800
3. A karstic formation impliesthe presence of a network ofsolutioned, often highly permeable,discontinuities which are, bydenition, connected to the surfaceso that the free carbon dioxidenecessary to allow the solutioningprocess to continue is available.
a. Trueb. False
4. The diculties involved inconstructing a dam on a karsticfoundation were rst documentedat ____ ____ dam that was built byprivate interests on the Tennessee
River between 1905 and 1913.a. Hails Boxb. Hills Barnc. Hales Bard. Hanes Bar & Grill
5. The problems at dams that havesevere seepage or leakage arelikely related, at least in part, toan inadequate understanding ofthe _____ of karst prior to thecommencement of construction.
a. depthb. typec. colord. strength
e. All of the above
6. Successful treatment of karstic
foundations requiresa. a means of reducing the
amount of seepage
b. techniques to prevent dissolution
of soluble minerals that may be
present in the foundation
c. methods to ensure that the
foundation has adequate capacity
to resist the post impoundment
loadings without excessive settlement
d. All of the above
7. Foundation treatment for karstic
formations typically includes
consolidation grouting to
a. increase adequate bearing strength
b. minimize settlements
c. reduce subsurface water ows
d. seal void areas
8. Compaction grouting typically
results in hydraulic fracturing,
extrusion and consolidation
of clayey llings within the
sinkholes increasing strength, and
resistance to seepage stresses.
a. True
b. False
9. The most commonly occurring
soluble rock mineral(s) are
a. calcium carbonate (limestone)b. gypsum
c. anhydrite
d. halite
e. All of the above
10. Mitigation of the risk of solutioning
in a foundation containing such
minerals as calcium carbonate,
gypsum, anhydrite, and halite
requires reducing the volume of
a. karstic voids
b. subsurface groundwater
c. seepage and seepage gradients
d. hydraulic gradient
11. An active brine injection system
has been used to treat foundationscontaining halite mineral deposits.
a. True
b. False
12. The Median Post Impound-
ment Seepage of approximately
50 l/sec would require
a. 1 line of grout
b. 2 lines of grout
c. 3 lines of grout
d. 4 lines of grout
13. It is usually necessary to extend
the grout curtain along the dam
axis into the abutments to
reduce risks associated with
end run seepage. The amount
of extension is dependent
a. on geological conditions
b. on economic impacts
c. on diculty of install ing
the grout curtain
d. on the schedule of remediation
14. Hot asphalt grouting is a technique
where asphalt is melted and
pumped through heated pipes into
open cavities. On contact with the
water, the asphalt cools and as-
sumes a globular form that progres-
sively blocks the solution channels.
a. True
b. False
15. At the Kavar Project, the proposed
reservoir treatment included an
impervious surface membrane; an
overburden blanket, consisting
of compacted impervious and
erosion protection ll; a reinforced
concrete shotcrete membrane;and a gypsum surcharge.
a. True
b. False