Foundation Design for the Beatrice Offshore Wind Farm - Beatrice.pdf · Foundation Design for the...
Transcript of Foundation Design for the Beatrice Offshore Wind Farm - Beatrice.pdf · Foundation Design for the...
-
Foundation Design for the Beatrice Offshore Wind Farm
R. McLean – SUPERGEN Wind Hub General Assembly, 08th November 2018
Image: BOWL Image: BOWL
-
Contents
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Introduction to Beatrice
Foundation Design Challenges
• Site characterisation
• Pile design
• Jacket design
• Fabrication approach
• Installation considerations
• Other challenges
Conclusions
-
Introduction
-
Overview
588MW offshore wind farm in the Moray Firth
Clean electricity for 450,000 homes
Overall project £2.6bn
Site:
Circa 13km offshore
132km2
Water depths 35-55m LAT
Scotland’s largest offshore wind farm!
Image: BOWL
Image: BOWL
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Overview
Offshore structures
84no. 7MW wind turbine generators (WTGs)
2no. offshore transformer modules (OTMs)
Foundations = jackets on driven piles
86 jackets; 85,000 tonnes
344 piles; >14km total length; 44,000 tonnes
Deepest offshore wind fixed structures in the world
Image: BOWL
Image: Siemens UK
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
~55
~45
~11
0
154
Jacket
Piles
WTG
Gherkin, 180
Heron Tower, 230
Image: Wikimedia
Image: Hufton + Crow
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
2011 2012 2013 2014 2015 2016
CONCEPT FEED DETAILED DESIGN
2019
INSTALLATION OPERATION
2017 2018Consent
Appli-cation
Qualified CfD Consent
CfDLease agree-ment
Financial CloseSG2 FID
Piling Start
Piling Com-plete
Jackets Start
Cables Start Turbines
Start
First gene-ration
Full Gene-ration
Feb 2009 -STW
Grant
SSE Offshore Wind Alliance
Framework of key suppliers designed to
address the key challenges of Round 3
offshore wind and drive efficiencies in SSE's
offshore wind programme.
Collaborative work through Concept and
FEED between Developer, WTG and OSP
Supplier, Installation contractor, Fabricator
and Designer.
BOWL
SHL
EPCI 91 inter-array cables
SIEM
EPCI 84 WTG foundations
Fabrication:
Jackets: Bladt, Smulders,
BiFab
Piles: EEW, SIF
Installation: SHL
Design: AtkinsT&I 2 OTM and foundations
STDL
EPC 2 OTM and foundations
Design: Atkins
EPCI export cables
SWP EPCI 84 WTG
AtkinsGI, soil
parameters for design
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Foundation Design Challenges
-
Site Characterisation
-
Vast site
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Image: Google
-
Available data - onshore
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Image: BGS
-
Available data - offshore
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Image: BGS
-
Phased investigation
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
CONCEPT FEED DETAILED DESIGN
20162014 2015201320122011
Desk study
Review GM
Geophys, 5 BH
Prelim GM Interim GI Update GM
CP
TS
am
plin
gLab tests
Routine Advanced
Completion GI Final GM
(BE-B5, -39.7)
(BE-C4, -38.1)
(BE-C5, -40.4)
(BE-C6, -41.4)
(BE-D3, -38.2)
(BE-D4, -39.4)
(BE-D5, -41.9)
(BE-E1, -38.9)
(BE-E2, -38.2)
(BE-E3, -38.6)
(BE-E4, -40.7)
(BE-E5, -40.4)
(BE-E6, -40.7)
(BE-F2, -40.2)
(BE-F3, -38.7)
(BE-F4, -40.4)
(BE-F5, -39.7)
(BE-F6, -41.6)
(BE-G3, -40.5)
(BE-G4, -38.6)
(BE-G5, -39.7)
(BE-G6, -40.2)
(BE-G7, -41.2)
(BE-H4, -41.1)
(BE-H5, -41.9)
(BE-H6, -40.0)
(BE-J5, -41.4)
(BE-J6, -41.5)
(BE-B6, -44.0)
(BE-B7, -46.4)
(BE-C7, -42.3)
(BE-C8, -43.3)
(BE-C9, -45.5)
(BE-D10, -45.3)
(BE-D6, -42.2)
(BE-D7, -44.0)
(BE-D8, -43.8)
(BE-D9, -44.4)
(BE-E7, -43.7)
(BE-E8, -46.0)
(BE-E9, -46.0)
(BE-F8, -45.7)
(BE-G8, -45.2)
(BE-H7, -42.5)
(BE-H8, -44.2)
(BE-J7, -42.7)
(BE-J8, -45.5)
(BE-K6, -44.6)
(BE-K7, -44.3)
(BE-L7, -44.5)
(BE-A5, -47.7)
(BE-E10, -46.6)
(BE-E11, -46.6)
(BE-F10, -48.2)
(BE-F11, -48.8)
(BE-F12, -48.6)
(BE-F9, -49.0)
(BE-G10, -49.4)
(BE-G9, -49.9)
(BE-H10, -49.6)
(BE-H9, -47.8)
(BE-J10, -49.5)
(BE-J9, -47.8)
(BE-K8, -47.6)
(BE-K9, -48.6)
(BE-L10, -49.6)
(BE-L8, -47.8)
(BE-L9, -49.4)
(BE-M9, -49.0)
(BE-M10, -49.9)
(BE-D11, -50.1)
(BE-E12, -52.9)
(BE-G11, -51.1)
(BE-G12, -50.5)
(BE-H11, -50.2)
(BE-H12, -51.8)
(BE-J11, -50.8)
(BE-J12, -52.2)
(BE-K10, -51.5)
(BE-K11, -52.0)
(BE-F13, -54.2)
(BE-G13, -53.4)
(BE-G14, -54.9)
(BE-H13, -53.4)
(BE-J13, -54.2)
(BE-K12, -53.1)
(BE-L11, -52.4)
(BE-F7, -42.5)
6448000
6449000
6450000
6451000
6452000
6453000
6454000
6455000
6456000
6457000
6458000
6459000
6460000
6461000
6462000
6463000
6464000
6465000
6466000
499000 500000 501000 502000 503000 504000 505000 506000 507000 508000 509000 510000 511000 512000 513000 514000
NO
RT
HIN
G
EASTING
Beatrice Farm Layout with Clusters & Water Depth
Cluster1
Cluster2
Cluster3
Cluster4
Cluster5
Spare
OTM Location
NOTES:
1. All Water depths are relative to (mLAT)2. Names and locations taken from LF000005-MAP-091
Locations in each Cluster:
Cluster 1 = 27 WTGs + 1 OTMCluster 2 = 21 WTGs + 1 OTMCluster 3 = 20 WTGsCluster 4 = 10 WTGsCluster 5 = 6 WTGs
Total = 84 WTGs + 2 OTMs
Spares = 2 locations not used
Date: 19/04/2016
Images: BOWL/ Fugro/ Atkins
-
Pile Design Process
-
Loading
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Relatively small vertical load
Large horizontal loads from wind, waves and currents
High overturning moment at mudline
Resisted by piles in ‘push / pull’
Piles work in compression & tension
Cyclic
Wind
Wave & current
Largemoment
Small self weight
Push-pull(compression-tension in piles)
WTG
Jacket
Piles
-
Pile axial capacity
Need efficiency & reliability Which method?
Efficient & reliable pile
design
Optimised pile length
Reliable level of safety
Reliable axial
response
Reduced fatigue
damage
Reduced install. time
Reduced install. risk
Optimised CAPEX
Optimised safety
Reduced noise
0
5
10
15
20
25
30
35
40
0 2 4 6 8 10 12 14 16 18 20 22 24
Pil
e p
enet
raio
n (
m b
ml)
Pile Tensile Capacity (MN)
ICP-05
UWA-05
NGI-05
DNV / API
Load
6m difference between
ICP-05 and DNV / API
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Jacket Design Process- Clustering approach
- Structural analyses
-
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Design Process
AFC DesignUncoupled Analysis
Coupled Analysis
Bookending Site
Variances in-Cluster
Inclusive of all contributors
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Design Process: Coupled Analysis
Pre-processing:
› ~1,000 wave loading simulations
SWP Analysis:
› Up to 20,000 combined wave + turbine simulations
Post-processing (Retrieval):
› ~300 critical ULS simulations
› 232 FLS simulations
› Code checking
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Design Process: Uncoupled Analysis
ULS:
En
ve
lop
ing
Fa
cto
rs
Baseline:
As per CA
Deep Water:
5% WTG contingency
Water depth uncertainty
Shallow Water:
Short stickup
Stiff soil
5% WTG contingency
Water depth uncertainty
En
ve
lop
ing
Fa
cto
rs
Baseline:
As per CA
Deep Water:
5% WTG contingency
± Water depth uncertainty
Shallow Water:
Short stickup
Stiff soil
5% WTG contingency
± Water depth uncertainty
FLS:
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Design Process: AFC Design
Primary Steel AFC
Weld Root Assessment
Uncoupled Analysis Factors
T&I & VIV Damage
TP & Joint FEM
Attachments [sympathetic
loading]
Joint Axial Stress
Factor for all FLS cases
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Fabrication
-
Beatrice Foundation Fabricators
Image: Google
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Design for Serial FabricationCommon TP & Upper Jacket
Cluster Specific Lower JacketImage: Smulders
Image: Smulders
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Installation
-
Pile Installation risks
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Boulders
Bedrock horizons
Strong and laterally traceable seismic
reflectors
Identified in intact Lower Cretaceous
Variable in lateral extent
Some have corresponding evidence in the
borehole data
Some relate to sandstone beds
Stratum II
Stratum IV
Stratum IV
Stratum IV
Stratum III
Stratum I Seabed
Major geological fault
Horizons within Stratum IV
Horizons within Stratum IV
~1km
-
Mitigation
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Remediation = drive-drill-drive
Derive method to assess
Reduction of capacity from drilling
Shaft friction increase from ageing that can be relied upon
Capacity gain from concrete plug
Analyse impact of drilling at varying depths with and without concrete plug
Installation contractor has clear pre-defined scenarios to know instantly whether:
Pile must be abandoned,
Pile can be saved with a concrete plug
Pile does not require a concrete plug
-
Jacket Installation
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
• Transportation fatigue
• Upending vs vertical towing
• Installation vessel limits
• Early age cycling
• Safe access
• Walk to work systems
• Evacuation procedures
Image: Ian GreenwoodImage: SHL
-
Conclusions
-
Conclusions
› Multi-disciplinary approach required to manage risk and optimise
standardisation
› Good design should consider:
› Variable site conditions
› Fabrication approach
› Installation approach
› Project programme
› Through life user safety
› Innovation, collaboration and adaptability are key to future success of
industry.
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Successes to date
› Design AFC and certification to
programme
› Pile installation completed
December 2017
› Jacket installation completed July
2018
› First power generation July 2018
› Fully operational in 2019
Image: BOWL
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
-
Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General
Assembly, 08th November 2018
Thank you
All images © Atkins unless otherwise stated.