Foundation Design for the Beatrice Offshore Wind Farm - Beatrice.pdf · Foundation Design for the...

33
Foundation Design for the Beatrice Offshore Wind Farm R. McLean SUPERGEN Wind Hub General Assembly, 08 th November 2018 Image: BOWL Image: BOWL

Transcript of Foundation Design for the Beatrice Offshore Wind Farm - Beatrice.pdf · Foundation Design for the...

  • Foundation Design for the Beatrice Offshore Wind Farm

    R. McLean – SUPERGEN Wind Hub General Assembly, 08th November 2018

    Image: BOWL Image: BOWL

  • Contents

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    Introduction to Beatrice

    Foundation Design Challenges

    • Site characterisation

    • Pile design

    • Jacket design

    • Fabrication approach

    • Installation considerations

    • Other challenges

    Conclusions

  • Introduction

  • Overview

    588MW offshore wind farm in the Moray Firth

    Clean electricity for 450,000 homes

    Overall project £2.6bn

    Site:

    Circa 13km offshore

    132km2

    Water depths 35-55m LAT

    Scotland’s largest offshore wind farm!

    Image: BOWL

    Image: BOWL

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Overview

    Offshore structures

    84no. 7MW wind turbine generators (WTGs)

    2no. offshore transformer modules (OTMs)

    Foundations = jackets on driven piles

    86 jackets; 85,000 tonnes

    344 piles; >14km total length; 44,000 tonnes

    Deepest offshore wind fixed structures in the world

    Image: BOWL

    Image: Siemens UK

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • ~55

    ~45

    ~11

    0

    154

    Jacket

    Piles

    WTG

    Gherkin, 180

    Heron Tower, 230

    Image: Wikimedia

    Image: Hufton + Crow

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • 2011 2012 2013 2014 2015 2016

    CONCEPT FEED DETAILED DESIGN

    2019

    INSTALLATION OPERATION

    2017 2018Consent

    Appli-cation

    Qualified CfD Consent

    CfDLease agree-ment

    Financial CloseSG2 FID

    Piling Start

    Piling Com-plete

    Jackets Start

    Cables Start Turbines

    Start

    First gene-ration

    Full Gene-ration

    Feb 2009 -STW

    Grant

    SSE Offshore Wind Alliance

    Framework of key suppliers designed to

    address the key challenges of Round 3

    offshore wind and drive efficiencies in SSE's

    offshore wind programme.

    Collaborative work through Concept and

    FEED between Developer, WTG and OSP

    Supplier, Installation contractor, Fabricator

    and Designer.

    BOWL

    SHL

    EPCI 91 inter-array cables

    SIEM

    EPCI 84 WTG foundations

    Fabrication:

    Jackets: Bladt, Smulders,

    BiFab

    Piles: EEW, SIF

    Installation: SHL

    Design: AtkinsT&I 2 OTM and foundations

    STDL

    EPC 2 OTM and foundations

    Design: Atkins

    EPCI export cables

    SWP EPCI 84 WTG

    AtkinsGI, soil

    parameters for design

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Foundation Design Challenges

  • Site Characterisation

  • Vast site

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    Image: Google

  • Available data - onshore

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    Image: BGS

  • Available data - offshore

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    Image: BGS

  • Phased investigation

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    CONCEPT FEED DETAILED DESIGN

    20162014 2015201320122011

    Desk study

    Review GM

    Geophys, 5 BH

    Prelim GM Interim GI Update GM

    CP

    TS

    am

    plin

    gLab tests

    Routine Advanced

    Completion GI Final GM

    (BE-B5, -39.7)

    (BE-C4, -38.1)

    (BE-C5, -40.4)

    (BE-C6, -41.4)

    (BE-D3, -38.2)

    (BE-D4, -39.4)

    (BE-D5, -41.9)

    (BE-E1, -38.9)

    (BE-E2, -38.2)

    (BE-E3, -38.6)

    (BE-E4, -40.7)

    (BE-E5, -40.4)

    (BE-E6, -40.7)

    (BE-F2, -40.2)

    (BE-F3, -38.7)

    (BE-F4, -40.4)

    (BE-F5, -39.7)

    (BE-F6, -41.6)

    (BE-G3, -40.5)

    (BE-G4, -38.6)

    (BE-G5, -39.7)

    (BE-G6, -40.2)

    (BE-G7, -41.2)

    (BE-H4, -41.1)

    (BE-H5, -41.9)

    (BE-H6, -40.0)

    (BE-J5, -41.4)

    (BE-J6, -41.5)

    (BE-B6, -44.0)

    (BE-B7, -46.4)

    (BE-C7, -42.3)

    (BE-C8, -43.3)

    (BE-C9, -45.5)

    (BE-D10, -45.3)

    (BE-D6, -42.2)

    (BE-D7, -44.0)

    (BE-D8, -43.8)

    (BE-D9, -44.4)

    (BE-E7, -43.7)

    (BE-E8, -46.0)

    (BE-E9, -46.0)

    (BE-F8, -45.7)

    (BE-G8, -45.2)

    (BE-H7, -42.5)

    (BE-H8, -44.2)

    (BE-J7, -42.7)

    (BE-J8, -45.5)

    (BE-K6, -44.6)

    (BE-K7, -44.3)

    (BE-L7, -44.5)

    (BE-A5, -47.7)

    (BE-E10, -46.6)

    (BE-E11, -46.6)

    (BE-F10, -48.2)

    (BE-F11, -48.8)

    (BE-F12, -48.6)

    (BE-F9, -49.0)

    (BE-G10, -49.4)

    (BE-G9, -49.9)

    (BE-H10, -49.6)

    (BE-H9, -47.8)

    (BE-J10, -49.5)

    (BE-J9, -47.8)

    (BE-K8, -47.6)

    (BE-K9, -48.6)

    (BE-L10, -49.6)

    (BE-L8, -47.8)

    (BE-L9, -49.4)

    (BE-M9, -49.0)

    (BE-M10, -49.9)

    (BE-D11, -50.1)

    (BE-E12, -52.9)

    (BE-G11, -51.1)

    (BE-G12, -50.5)

    (BE-H11, -50.2)

    (BE-H12, -51.8)

    (BE-J11, -50.8)

    (BE-J12, -52.2)

    (BE-K10, -51.5)

    (BE-K11, -52.0)

    (BE-F13, -54.2)

    (BE-G13, -53.4)

    (BE-G14, -54.9)

    (BE-H13, -53.4)

    (BE-J13, -54.2)

    (BE-K12, -53.1)

    (BE-L11, -52.4)

    (BE-F7, -42.5)

    6448000

    6449000

    6450000

    6451000

    6452000

    6453000

    6454000

    6455000

    6456000

    6457000

    6458000

    6459000

    6460000

    6461000

    6462000

    6463000

    6464000

    6465000

    6466000

    499000 500000 501000 502000 503000 504000 505000 506000 507000 508000 509000 510000 511000 512000 513000 514000

    NO

    RT

    HIN

    G

    EASTING

    Beatrice Farm Layout with Clusters & Water Depth

    Cluster1

    Cluster2

    Cluster3

    Cluster4

    Cluster5

    Spare

    OTM Location

    NOTES:

    1. All Water depths are relative to (mLAT)2. Names and locations taken from LF000005-MAP-091

    Locations in each Cluster:

    Cluster 1 = 27 WTGs + 1 OTMCluster 2 = 21 WTGs + 1 OTMCluster 3 = 20 WTGsCluster 4 = 10 WTGsCluster 5 = 6 WTGs

    Total = 84 WTGs + 2 OTMs

    Spares = 2 locations not used

    Date: 19/04/2016

    Images: BOWL/ Fugro/ Atkins

  • Pile Design Process

  • Loading

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    Relatively small vertical load

    Large horizontal loads from wind, waves and currents

    High overturning moment at mudline

    Resisted by piles in ‘push / pull’

    Piles work in compression & tension

    Cyclic

    Wind

    Wave & current

    Largemoment

    Small self weight

    Push-pull(compression-tension in piles)

    WTG

    Jacket

    Piles

  • Pile axial capacity

    Need efficiency & reliability Which method?

    Efficient & reliable pile

    design

    Optimised pile length

    Reliable level of safety

    Reliable axial

    response

    Reduced fatigue

    damage

    Reduced install. time

    Reduced install. risk

    Optimised CAPEX

    Optimised safety

    Reduced noise

    0

    5

    10

    15

    20

    25

    30

    35

    40

    0 2 4 6 8 10 12 14 16 18 20 22 24

    Pil

    e p

    enet

    raio

    n (

    m b

    ml)

    Pile Tensile Capacity (MN)

    ICP-05

    UWA-05

    NGI-05

    DNV / API

    Load

    6m difference between

    ICP-05 and DNV / API

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Jacket Design Process- Clustering approach

    - Structural analyses

  • Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Design Process

    AFC DesignUncoupled Analysis

    Coupled Analysis

    Bookending Site

    Variances in-Cluster

    Inclusive of all contributors

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Design Process: Coupled Analysis

    Pre-processing:

    › ~1,000 wave loading simulations

    SWP Analysis:

    › Up to 20,000 combined wave + turbine simulations

    Post-processing (Retrieval):

    › ~300 critical ULS simulations

    › 232 FLS simulations

    › Code checking

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Design Process: Uncoupled Analysis

    ULS:

    En

    ve

    lop

    ing

    Fa

    cto

    rs

    Baseline:

    As per CA

    Deep Water:

    5% WTG contingency

    Water depth uncertainty

    Shallow Water:

    Short stickup

    Stiff soil

    5% WTG contingency

    Water depth uncertainty

    En

    ve

    lop

    ing

    Fa

    cto

    rs

    Baseline:

    As per CA

    Deep Water:

    5% WTG contingency

    ± Water depth uncertainty

    Shallow Water:

    Short stickup

    Stiff soil

    5% WTG contingency

    ± Water depth uncertainty

    FLS:

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Design Process: AFC Design

    Primary Steel AFC

    Weld Root Assessment

    Uncoupled Analysis Factors

    T&I & VIV Damage

    TP & Joint FEM

    Attachments [sympathetic

    loading]

    Joint Axial Stress

    Factor for all FLS cases

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Fabrication

  • Beatrice Foundation Fabricators

    Image: Google

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Design for Serial FabricationCommon TP & Upper Jacket

    Cluster Specific Lower JacketImage: Smulders

    Image: Smulders

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Installation

  • Pile Installation risks

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    Boulders

    Bedrock horizons

    Strong and laterally traceable seismic

    reflectors

    Identified in intact Lower Cretaceous

    Variable in lateral extent

    Some have corresponding evidence in the

    borehole data

    Some relate to sandstone beds

    Stratum II

    Stratum IV

    Stratum IV

    Stratum IV

    Stratum III

    Stratum I Seabed

    Major geological fault

    Horizons within Stratum IV

    Horizons within Stratum IV

    ~1km

  • Mitigation

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    Remediation = drive-drill-drive

    Derive method to assess

    Reduction of capacity from drilling

    Shaft friction increase from ageing that can be relied upon

    Capacity gain from concrete plug

    Analyse impact of drilling at varying depths with and without concrete plug

    Installation contractor has clear pre-defined scenarios to know instantly whether:

    Pile must be abandoned,

    Pile can be saved with a concrete plug

    Pile does not require a concrete plug

  • Jacket Installation

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    • Transportation fatigue

    • Upending vs vertical towing

    • Installation vessel limits

    • Early age cycling

    • Safe access

    • Walk to work systems

    • Evacuation procedures

    Image: Ian GreenwoodImage: SHL

  • Conclusions

  • Conclusions

    › Multi-disciplinary approach required to manage risk and optimise

    standardisation

    › Good design should consider:

    › Variable site conditions

    › Fabrication approach

    › Installation approach

    › Project programme

    › Through life user safety

    › Innovation, collaboration and adaptability are key to future success of

    industry.

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Successes to date

    › Design AFC and certification to

    programme

    › Pile installation completed

    December 2017

    › Jacket installation completed July

    2018

    › First power generation July 2018

    › Fully operational in 2019

    Image: BOWL

    Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

  • Foundation Design for the Beatrice Offshore Wind Farm - R. McLean – SUPERGEN Wind Hub General

    Assembly, 08th November 2018

    Thank you

    All images © Atkins unless otherwise stated.