Former Brukunga Mine Site (SA) Lessons of a long-term ... · • Acid and metalliferous drainage...
Embed Size (px)
Transcript of Former Brukunga Mine Site (SA) Lessons of a long-term ... · • Acid and metalliferous drainage...

Former Brukunga Mine Site (SA)Lessons of a long-term remediation strategy
Dealing with Derelict Mines 2016
Raul MollehuaraProject Director / Operations Brukunga Mine Site

Overview
- Background- Brukunga Mine site: Location, history and site features- The issue and the impact
- The remediation strategy- The Strategy & Objectives- The remediation framework
- The long term program - Mine Remediation- Remediation model- Design Features
- The short / medium term program - Water Quality- Dawesley Creek diversion- Water treatment- Water quality
- Where are we at- Lessons learned

LocationHistory - The Mine
Site featuresThe issue
The Impact
Background

Brukunga Mine Site – Location

Brukunga Mine Site – history
• Mining 1950’s through to 1970’s. Mine sponsored by the State Govt. Production subsidy by the Federal Government
• Produced 5.5 Mt ore (11% Sulphur: Pyrite & Pyrrhotite) and concentrated in a flotation process.• The concentrate railed to Pt Adelaide for further processing into sulphuric acid to produce fertiliser.

Brukunga Mine Site – Features
• 165 Ha• Open pits• 8 Million tonnes waste
rock• 3.5Million tonnes of
tailings• Water Treatment Plant• Township• Other users of the site:
CFS, DET CRC, Boart Longyear, TAFE SA, RTOs, Research groups.

Brukunga Mine Site – The issue
cross section looking North
• Geological setting • Hydrogeological and geochemical processes• Acid and metalliferous drainage (AMD) release

Brukunga Mine Site – The impact
Not just about the site, water is the main transport mechanism. These waters from the Brukunga site nearly 70kms as the creek flows and 43 in a straight line affecting along the way, farm land, agriculture and ecosystems
Heavy metal pollution.- The Brukunga mine impacted on a socio-ecological system. The
system consists of the Dawesley creek, the Bremer river and Lake Alexandrina, and importantly – all the associated terrestrial adjacent ecosystems, and the local families and businesses using these ecosystems.
Dawesley Creek downstream properties cannot currently use the water from the creek.- Downstream landholders rely on subsidised water supply.
Financial and environmental liability to Government. - Without remediation the AMD is likely to continue for 750 to
1,000 years.
In 2001, Government commited $26m to conduct remediation works and improve water quality in Dawesley Creek.
Brukunga
Freeway
Langhorne Creek
Lake Alexandrina
Extent of historic AMD contamination

Remediation strategyRemediation framework
Brukunga Remediation Strategy

Brukunga Remediation Strategy
The objectives of the remediation are to:
• Improve water quality in Dawesley Creek to a standard as good as possible.
• Substantially limit or avoid the need to intercept and treat acid waters indefinitely.
• Return all or part of the site back to productive uses or for environmental/ ecosystem values.
• Apply leading practice to site management and mine completion.
The strategies at the site:
1. Short / medium term program: Ensure water in Dawesley Creek meet quality standards.
2. Long term program: Mine completion through to full remediation.
Since 2007 an expert Technical Advisory Group (TAG) has overseen extensive testing to develop a technically feasible remediation strategy. Comprised of internationally respected experts in the field of AMD management and mine remediation, the TAG has provided guidance and assessed a program of technical studies to identify a suitable whole-of-site strategy to remediate the site.
10

Brukunga Remediation Framework
Dawesley Creek Diversion Extension
Acid Water Retention Pond
Water in Dawesley Creek - Fit for use
Phase 1& 2Assessment & Definition &
Feasibility
Phase 3 Design & Costing
Phase 4 Days CkImplementation
Pre-mine Surface Water Quality
Environmental Audit (Phase1)
Brukunga Water Monitoring Program
Program Structure
Consultative gateways
Asset management- WTP upgrade & Automation
2nd Stage
Process Improvement- WTP Automation 1st
Stage
Toxicological Risk Assessment
Toxicity Assessment of Pulsed Discharges
Real time Monitoring – 3G or telemetry
Risk Management Plan
Defining WQ
Criteria
Water Management
AMD Interception & Treatment
In situ monitoring –Loggers
EPA Process –Water Quality criteria /
Fit for use
Sustained Water Quality – Irrigation & livestock
Monitoring & Control
Program Goal / Outcomes
Land rehabilitated to productive use
Phase 5&6 Days CkMonitoring & Validation
Phase 7 Whole of Mine Remediation
Stop ongoing AMD treatment
Remediation
Program
Relinquish EPA licence and discontinue:
t = 1
-2 y
ears
t = long term
Program Assessment (Options Paper) & Forward Program
Ongoing Water Treatment Plant Operation and Property Maintenance
‘Remediation of the site that requires no further intervention by, ongoing responsibility for or cost to governmentand / or community’
REM
EDIA
TIO
N P
RO
GR
AM
(long
term
)W
ATER
QU
ALIT
Y PR
OG
RAM
(s
hort
/ med
ium
term
)
2017+
Third Party users and opportunities: Mine Skill Centre Framework (Organic growth), commercial activities (filming, technology testing, etc)
Opportunities for Research & Collaboration (geosciences, mine exploration, mine remediation & rehabilitation, …)
Stop supply of water to six properties
downstream
t = long term
2007-2011 20012-2015
11
2016
Environmental Audit (Phases 2&3)

Remediation modelDesign features
Long term: Mine remediation

The remediation model
13
• A solution concept that is technically feasible for a long term remediation of the site was developed by the TAG – The Saturated co-disposed waste model that involves the compaction and saturation of co-disposed (mixed) waste rock, tailings and limestone, contained by mine voids and an embankment, under an engineered cover system.
• Given the nature and cost of the remediation works the site has been divided into domains: Days Creek, Dawesley Creek and Taylors Creek (with Days Creek as the section of the mine to be remediated first)
• The long term remediation program is a phased program: - Phase 1 – Development and assessment of remediation options (2007-09)- Phase 2 – Option definition & Feasibility (2009-11)- Phase 3 – Days Creek detailed investigation & design (2012-15)- Phase 4 – Implementation (subject to funding)

Design features – Days Creek domain• Section of mine to be remediated first –
contains approximately 800,000 m3 of waste rock and tailings.
• Co-disposing waste rock and tailings with limestone. High infiltration cover to maximise rainfall into the co-disposed material.
• Seepage control to limit the loss of water.
Co-disposed waste60.5% Waste Rock35.5% Tailings4.0% CaCO3

Dawesley Creek DiversionWater Treatment
Water Quality
Short / medium term: Water Quality

Dawesley Creek Diversion
1.7 km (2004)
260m extension(2014)

Water Treatment – Lime based neutralisation plant
Lime slurry tank Lime/sludgetank Reactor 1
tank
Reactor 2 tank
Thickener12m¢
OUT:
Sludge
(gypsum+metal hydroxides)
OUT: Treated water
Air
Sludge recycling
IN: 75 – 100 kL/h
Acid water (Sulfuric acid + dissolved metals)
Lime AMDpH=2.5
pH=9.5
pH= 9.0 – 9.5
TSS < 10 NTU
High Density Sludge (HDS) Process

Water Treatment & Water Quality - pH

Water Treatment & Water Quality - Cadmium

Water Quality improvements
20
Brukunga
Bre
mer
Riv
er
43 km
20 km
<1 km
Dawesley Creek
Mine Site
Langhorne Creek Wine Region
Nairne
Lower lakes
Extent of Historic Contamination1950’s ‐1980’s
Extent of Contamination2004 ‐2014
Extent of Contamination2014+
(outside flood events)
With reference to agriculture irrigation & livestock quality standards (ANZECC)

Where are we at – timeline
$26.1m

Where are we at – key points
• Brukunga former mine site is a 165 Ha property that requires ongoing management.
• Water quality has improved significantly and contamination has been reduced in the zone of influence from 40km in 1980 to less than 1km in 2014+ (Agriculture irrigitation / livestock – ANZECC 2000).
• While the concentration of contaminants in the water are managed by interception and treatment (120-150 ML of acid water per year), this is not a permanent solution due to volatility from rainfall events.. Treatment would be required for 700-1000 years.
• More than $35 million has already been spent on operational and capital costs over last 30 years. Approximately $700k annual cost to Government (incl. treatment of acid water plus maintenance of the site)
• A technical rehabilitation solution has been developed and can be implemented quickly or can be staged over a longer timeframe subject to funding.
• Detailed design, engineering and costing (Phase 3) have been conducted for the first domain – Days Creek ($35 million). The cost of remediating one domain gives an insight into the scale and long-term cost of remediation.

Lessons learned
Technical• A better understanding of the remediation concept and its interactions with the site
characteristics (e.g. hydrology, hydrogeology, geochemistry, geology, erosion and landform evolution, soil hydrology, cover systems, revegetation, climate change).
• A better understanding of the saturated co-disposed waste model. Proof of concept through laboratory testings and field trials. Strategies to overcome constructuability issues and challenges (e.g. compaction rates due to heterogenetity of waste rock particle sizes).
Regulatory• Knowledge areas to support regulatory function of the Mining Regulation Branch in South
Australia regarding PEPRs and closure plans.

Other beneficial uses: Third Parties
24
Drilling Technologies for Exploration: (Deep Exploration Technologies CRC / Boart Longyear)
Training (SACOME, TAFE SSA, RTOs) County Fire Services (CFS)
Films & Commercials

Former Brukunga Mine Site (SA)Lessons of a long-term remediation strategy
THANK YOU
Raul MollehuaraProject Director / Operations Brukunga Mine Site