Formats of Cost and Financial Control Reports
Click here to load reader
-
Upload
kashif-khawja -
Category
Documents
-
view
252 -
download
1
Transcript of Formats of Cost and Financial Control Reports
Balance Cost To Complete Report
Quantity ValueActual
QuantityActual Cost Quantity
forecast Cost
A B C D E F G=D+F H=B - G
Remarks:This report shows an expected outcome of a project in terms of meeting cost targets set at the bid level.Any negative variations will be further analysed.
BOQActual Progress upto
Sept-2010 Balance to CompleteBOQ Item/WP/Cost Center
Total Projected
Cost
Diff in Bid Cost and Actual
expected cost
Cash Operating Cycle of a Project Jan-10
No of Days required to receive Progress Invoices 80No of days Material is in Stock 15No of days to pay labour 35*14% -4.9No of days to pay Subcontractors 50*60% -30No of days to pay other expenses and purchases 35*26% -9.1Cash Operating Cycle of a project 51 days
Remarks:
Developed by:Abdul Kashif
This report shows that it takes 51 days to convert our periodic investments into the projects to be returned back into our bank accounts with profit. Therefore, we must be able to finance 51 days through our own capital or through external financing. An increase in Cash Operating Cycle due to any reason e.g. Client is delaying payment, will require us to make arrangements of additional financing.
Project wise return on Investments
Project-1 Project-2 Project-3 Project-4 Project-5 Project-6(Millions)
Material on Site 80Accounts Receivables 400Advances to suppliers 150Other current assets 300Fixed Assets 600Total Assets 1530
Accounts Payables 150
Net Investments 1380
Gross Profit 90
Return on Investments 6.52%
Remarks:
The solution can be:Either increase profit margin by decreasing costDecrease investments such as reduction in receivables, obsolete materialsIncrease Payables as an alternative of decrease in investments.Through above three choices Return on Investment on a Project can be increased.
Any project which is earning less than the desired Return on Investment will be analysed further for causes of lower profitability
Proportion of Cost Elements in Total Cost
Amount %age Amount %age Amount %age Gen. Req. 13 15 11 Labor 4 15 16 Subcon (Apply Only) 5 5 5 Material 14 20 25
Others 1 2 1
Equipment 2 2 2 Subcon (S&A) 61 41 40
Total Cost 100% 100% 100%
Remarks:
Actual amounts deleted from the original report
Developed by:Abdul Kashif
Original Budget Jan-10 Sep-10
Cost Items
This table and accompanied graph shows how cost structure is deviating from the budget. In the above case Subcontractor (S&A) is decreasing while Material cost is increasing-this means we are taking jobs from Subcontractors and doing them ourselves.
0
10
20
30
40
50
60
70
1 2 3
General Requirements
Labor
Subcon (Apply Only)
Material
Others
Equipment
Subcon (S&A)
Historial analysis of Revenue and CostPeriods Revenue Total Cost Gross Profit
Jan-10 700 735 -35
Feb-10 800 856 -56Mar-10 850 807.5 42.5May-10 900 819 81Jun-10 950 883.5 66.5Jul-10 1010 858.5 151.5
Aug-10 970 776 194Sep-10 950 760 190
(Figures are hypothetical)
Remarks: This table highlights historical performance of a particular project and describe different phasis of its profitability cycle. Management may be interested to explore more any sharp deviations in a particular period.
-200
0
200
400
600
800
1000
1200
Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10
Revenue
Total Cost
Gross Profit
Historial analysis of Revenue and Cost
Periods Revenue Material Labour SubcontracTotal Cost Gross ProfitJan-10 700 257.25 36.75 441 735 -35Feb-10 800 299.6 128.4 428 856 -56Mar-10 850 282.625 201.875 323 807.5 42.5Apr-10 825 262.7625 225.225 262.7625 750.75 74.25
May-10 900 286.65 245.7 286.65 819 81Jun-10 950 309.225 247.38 326.895 883.5 66.5Jul-10 1010 300.475 214.625 343.4 858.5 151.5
Aug-10 970 271.6 186.24 318.16 776 194Sep-10 950 266 197.6 296.4 760 190
Remarks:This table and accompanied graph shows how components of Total Costs are moving during the period.Subcontract cost decreased while labour cost increased.
Perhaps now project is coming down from its peak activity. Is there any chance to further reducethe labour and over head expenses?
This and similar analysis will provide an opportunity to look into the future requirements of the project
-200
0
200
400
600
800
1000
1200
Revenue
Material
Labour
Subcontract
Gross Profit
Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10Cash InflowCash Outflow
Excess (Shortfall)Opening BalanceClosing Balance
Remarks:
This is a very simplified version of actual Rolling Cash Flow of a project. Based on future Revenue and expenses, a projected Cash Statement is prepared to enable Management to arrange necessary finances at appropriate time; or withdraw excess funds.
Planning QuantitiesAssumptionsWorking Hours/Day 16
Data
Crusher (O&M) 100 Rs/cum
Generator POL Consumption
Diesel Consumption 78.1 ltr/hr RsDeisel Rate 38.1 Rs/hrOil change 1 change per 550 hr 11,000 Oil filter change 1 change per 550 hr 2,100 Air filter change 1 change per 1000 hr 20,000 Fuel filter change 1 change per 1100 hr 1,835
Lease Cost 1,200,000 Rs/monthManpower Crew Cost 1,010 Rs/hr
Other Equipment
DumpersQty 20 UnitsRent 95,000 Rs/monthDiesel Consumption 10 ltr/hr
ExcavatorQty 2 UnitsRent 150,000 Rs/monthDiesel Consumption 10 ltr/hr
LoaderQty 2 UnitsRent 160,000 Diesel Consumption 10 ltr/hr
Raw Material 275 Rs/dumper
Description Qty Units RemarksTotal Qty Required (Planning) 125,534 cumProduction 95 cum/hrHours Required 1,321 hrMonths 4 months 16 hrs/day
250 TPH Crusher PlantCost & Benefit Analysis
This Capex analysis were made to establish Crush Plant for a road project. In organizations where Capex decisions are regularly made, this template can expedite and improve decision-making process
COSTS RsPOL (500 KVA) 3,992,109 Other Equipment
Dumpers 7,600,381 Excavator 1,200,381 Loader 1,280,381
Lease 4,800,000 #REF!Raw Material 3,797,404 Crusher (O&M) 12,553,400 6Manpower 1,334,625 #REF!Total 36,558,680
Decision:291.23 Rs./cum We should
8.25 Rs./cft establish our514.00 Rs./cum own plant
14.55 Rs./cft
Savings 27,965,796 Rs
DEL Rate
Market Rate