FORM I · Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal...
Transcript of FORM I · Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal...
FORM I
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
1
APPENDIX I
(See paragraph – 6)
Form – 1
(a) For item (I) relating to the basic information, the following shall be substituted, namely:-
Sr. No. Items Details
1. Name of the project/s Proposed Commercial Construction
project 'Runwal REGALIA' by M/s
Runwal Erectors Pvt Ltd At Survey
no.153A/1 to 4/1/1 & Survey No.153A/1
to 4/1, Hadapsar, Pune.
2. Sr. No. in the schedule 8(a)
3. Proposed capacity/area/length/tonnage
to be handled/ command area/lease
area/ number of wells to be drilled
Total Plot Area = 8340.00 SQ.M
Total Built up area = 36925.20Sq.M.
(12340.57Sq.M. FSI 24584.63Non-FSI
Sq.M.)
4. New / Expansion / Modernization New
5. Existing Capacity/ Area etc. Construction done till date is FSI area 4678
Sq.m. Non FSI area 14977.99 Total Builtup
19655.99 Sq.m. (Including Parking).
Construction done is in accordance with
first sanction CC/1610/05 DT: 27.07.2005
with builtup 9010.12 Sq.m. & Second
sanction CC/1132/07 DT: 09.07.2007 with
builtup 11621.47 Sq.m. As the Total Built
up area was less than 20,000.00 Sq.M.
hence Environment Clearance not required.
As per the Ministry of Environment and
Forest notification dt: 4th April 2011, the
basement & parking area has to be included
into the Built UP Area. Hence our project
came into purview of Environmental
Clearance.
6. Category of Project i.e. ‘A’ or ‘B’ Category ‘B’
7. Does it attract the general condition?
If Yes, please specify.
N.A.
8. Does it attract the specific condition?
If Yes, please specify
N.A.
9. Location
Plot/Survey/Khasra No. Survey no.153A/1 to 4/1/1 & Survey
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
2
Sr. No. Items Details
No.153A/1 to 4/1
Village Mauje Hadapsar
Tehsil Haveli
District Pune
State Maharashtra
10. Nearest railway station/airport along
with distance in kms.
Hadapsar railway station – 3 km
11. Nearest town, city, district
headquarters along with distance in
Km.
Town- Hadapsar – 0.5 km,
District Headquarter - Pune – 8 km.
12. Village panchayats, Zilla Parishad,
Municipal Corporation, Local body
(complete postal addresses with
telephone nos. to be given)
Municipal Corporation – Pune Municipal
Corporation
13. Name of the applicant M/s Runwal Erectors Pvt Ltd
Mr. Pradeep Amrutlal Runwal
14. Registered address 41/12, Karve Road, Runwal Plaza, First
Floor,Pune-411004
15. Address for correspondence: 41/12, Karve Road,Runwal Plaza,First
Floor,Pune-411004
Name Mr. Ankush Jasraj Parakh
Designation (Owner/Partner/CEO) Vice President
Address 41/12, Karve Road,Runwal Plaza,First
Floor,Pune
Pin Code 411004
E-mail [email protected]
Telephone No. 02066020390,9923102117
Fax No. 02025412471
16. Details of Alternatives Sites
examined, if any. Location of these
sites should be shown on a Topo sheet
No
17. Interlinked Project No
18. Whether separate application of
interlinked project has been
submitted?
No
19. If Yes, date of Submission Not applicable.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
3
Sr. No. Items Details
20. If no, reason Not applicable.
21. Whether the proposal involves
approval/clearances under: if yes,
details of the same and their status to
be given.
The Forest (Conservation) Act, 1980?
The Wildlife (Protection) Act, 1972?
The C.R.Z Notification, 1991?
No
22. Whether there is any Government Order
/Policy relevant/ relating to the site?
No
23. Forest land involved (hectares) No
24. Whether there is any litigation pending
against the project and/or land in which
the project is propose to be set up?
Name of the court
Case No.
Orders/directions of the Court, if any
and its relevance with the proposed
project.
No
(II)Activity
1. Construction, operation or decommissioning of the Project involving actions, which will
cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
Sr.
No
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
1.1 Permanent or temporary change in
land use, land cover or topography
including increase in intensity of
land use (with respect to local land
use plan)
Yes The proposed project site is designated
for the intended purpose & proposed
estimated built-up area is 36925.20
Sq.M.
1.2 Clearance of existing land, vegetation
and buildings?
No No tree cutting or falling is proposed.
1.3 Creation of new land uses? Yes The proposed project site is designated
for the intended purpose & proposed
estimated built-up area is 36925.20
Sq.M.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
4
Sr.
No
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
1.4 Pre-construction investigations e.g.
bore houses, soil testing?
Yes Please refer Ground water quality
Analysis Report. Annexure: 4
Soil Testing Report.
Annexure: 3
1.5 Construction works?
Yes Built up area estimated = 36925.20
Sq.M. will be the construction work.
1.6 Demolition works? No Not applicable.
1.7 Temporary sites used for construction
works or housing of construction
workers?
Yes Temporary housing will be provided
for about average 50 laborers at site.
They will be provided with water &
sanitation facility. Water is pumped
and stored in Storage Tank.
Modular toilets will be provided
during construction phase.
1.8 Above ground buildings, structures
or earthworks including linear
structures, cut and fill or excavations
Yes Excavated top soil will be used for
landscaping and excavated material
will be used for backfilling.
1.9 Underground works including mining
or tunneling?
No Not Applicable as the proposal pertains
to construction of Building only.
1.10 Reclamation works?
No Not applicable.
1.11 Dredging?
No Not applicable.
1.12 Offshore structures? No Not applicable.
1.13 Production and manufacturing
processes?
No Not Applicable as the proposal pertains
to construction of Building only.
1.14 Facilities for storage of goods or
materials?
Yes Storage Facility will be provided on
site for the storage of goods or
material like cement, steel, building
material etc with proper shed.
1.15 Facilities for treatment or disposal of
solid waste or liquid effluents?
Yes Modular toilets will be provided for
construction labors. For solid waste
will be treated in OWC.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
5
Sr.
No
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
Solid Waste Management
a) During Construction phase:
Construction debris will be used for
construction site itself and therefore
there will not be any solid waste
problem from generation of
construction-excavated earth.
Solid waste, which will be generated
from construction workers working
within site, will be disposed through
composting.
b) During Operation Phase:-
Total population of the Commercial
scheme is projected to be 2409 nos.
Quantity of solid waste – 602 kg/day
Quantity of wet waste – 279 kg/day
Quantity of dry waste – 323 kg/day
Organic waste will be converted in to
manure by composting in OWC
machine.
The dry waste collection, segregation,
recycling & disposal by SWaCH.
Liquid waste management
During construction: 50
M3/DAY
Source: Tanker Water
During operation:
Source: Pune Municipal Corporation
Fresh water : 89 m3/day
Recycled water (Flushing): 68 m3/day
Recycled water (Gardening): 9 m3/day
Total Water Requirement :166 m3/day
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
6
Sr.
No
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
Sewage generation: 152 m3/day
STP capacity: 160 m3/day
Treated water: 144 m3/day
Total recycled water: 77 m3/day
Excess water to drain: 67 m3/day
Swimming pool: 12.0 m3/day
1.16 Facilities for long term housing of
operational workers?
No Workers will be residing outside the
project area hence, no housing of
construction workers proposed.
1.17 New road, rail or sea traffic during
construction or operation?
Yes The development will not have major
impact on traffic pattern. Internal roads
will be well constructed to manage
traffic.
1.18 New road, rail, air waterborne or
other transport infrastructure
including new or altered routes and
stations, ports, airports etc?
Yes Construction Phase:
There will be some increase in road
traffic. In construction phase 3-5trucks
per day. JCB may ply once or twice a
day.
Operation Phase:
The development will not have major
impact on traffic pattern; internal roads
will be well constructed to manage
traffic.
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No No change in existing road network.
1.20 New or diverted transmission lines or
pipelines?
No Not Applicable.
1.21 Impoundment, damming, culverting,
realignment or other changes to the
hydrology of watercourses or
aquifers?
No Not Applicable.
1.22 Stream crossings? No No stream crossings in the project site.
1.23 Abstraction or transfers of water
form ground or surface waters?
No During Construction phase Tanker
water will be used for the construction
purpose.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
7
Sr.
No
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
1.24 Changes in water bodies or the land
surface affecting drainage or run-off?
No Not Applicable.
1.25 Transport of personnel or materials
for construction, operation or
decommissioning?
Yes Only material transport approx. 5 or so
trucks per day.
1.26 Long-term dismantling or
decommissioning or restoration
works?
No Not Applicable since there is no
dismantling involved in the project.
1.27 Ongoing activity during
decommissioning which could have
an impact on the environment?
No Not Applicable.
1.28 Influx of people to an area in either
temporarily or permanently?
Yes Influx during construction: As it will
be built in phases during Construction
average 50 numbers of workers will be
working on site.
Influx during operation: During
operation Influx of approximately
projected to be 2409 persons including
Commercial and floating population.
1.29 Introduction of alien species?
No Not Applicable.
1.30 Loss of native species or genetic
diversity?
No Not Applicable.
1.31 Any other actions? No Not Applicable.
2. Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-renewable or in short
supply):
Sr
No.
Information/checklist confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
2.1 Land especially undeveloped or
agricultural land (ha)
The proposed development has been
planned in such a way that it does not
damage the existing contours.
2.2 Water (expected source & competing
users) unit: KLD
Yes Liquid waste management
During construction: 50
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
8
Sr
No.
Information/checklist confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
M3/DAY
Source: Tanker Water
During operation:
Source: Pune Municipal Corporation
Fresh water : 89 m3/day
Recycled water (Flushing): 68 m3/day
Recycled water (Gardening): 9 m3/day
Total Water Requirement :166 m3/day
Sewage generation: 152 m3/day
STP capacity: 160 m3/day
Treated water: 144 m3/day
Total recycled water: 77 m3/day
Excess water to drain: 67 m3/day
Swimming pool: 12.0 m3/day
2.3 Minerals (MT) No Since this is a construction project
there will be no use of major minerals
for construction.
2.4 Construction material – stone,
aggregates, sand / soil (expected
source – MT)
Yes Cement: 4230 MT
Crush Sand: 10290 MT
Sand : 12300 MT
Metal: 9000 MT
2.5 Forests and timber (source – MT) No Timber used for Doors & Windows
are purchased from local market
(Pune).
2.6 Energy including electricity and fuels
(source, competing users) Unit: fuel
(MT), energy (MW)
Yes During Construction Phase –
Demand load = 25 kVA
Source: D.G.
DG Set Required = 25 kVA X 1 No.
During Operation Phase –
Source: MSEDCL
Demanded load = 2043 kVA
Connected load = 3204 kVA
Proposed Transformer Configuration:
630KVA X 4 Nos.
Source: D.G. sets
Required Capacity Of D. G. Set With
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
9
Sr
No.
Information/checklist confirmation
Yes/No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
Sound Proof Enclosure: 630KVA X 4
No
2.7 Any other natural resources (use
appropriate standard units)
No No use of other natural resource.
3. Use, storage, transport, handling or production of substances or materials, which could
be harmful to human health or the environment or raise concerns about actual or
perceived risks to human health.
Sr
No.
Information/Checklist
confirmation
Yes/No
Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
3.1 Use of substances or materials,
which are hazardous (as per
MSIHC rules) to human health or
the environment (flora, fauna, and
water supplies)
No Not Applicable
3.2 Changes in occurrence of disease or
affect disease vectors (e.g. insect or
water borne diseases)
No No such activity will be carried out
which will change or affect vectors to
born.
3.3 Affect the welfare of people e.g. by
changing living conditions?
Yes It can help in improving living
standards of the area.
3.4 Vulnerable groups of people who
could be affected by the project e.g.
hospital patients, children, the
elderly etc.,
No Project will not negatively affect
welfare of people. It will help in
improving living standards in the area.
3.5 Any other causes
No Not Applicable.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
10
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)
Sr
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
4.1 Spoil, overburden or mine wastes Yes Excavated material will be used for
backfilling at the site.
4.2 Municipal waste (domestic and or
commercial wastes)
Yes Solid Waste Management
a) During Construction phase:
Construction debris will be used for
construction site itself and therefore
there will not be any solid waste
problem from generation of
construction-excavated earth.
Solid waste, which will be generated
from construction workers working
within site, will be disposed through
composting.
b) During Operation Phase:-
Total population of the Commercial
scheme is projected to be 2409 nos.
Quantity of solid waste – 602 kg/day
Quantity of wet waste – 279 kg/day
Quantity of dry waste – 323 kg/day
Organic waste will be converted in to
manure by composting in OWC
machine.
The dry waste collection, segregation,
recycling & disposal by SWaCH.
4.3 Hazardous wastes (as per Hazardous
Waste Management Rules)
No Not Applicable.
4.4 Other industrial process wastes
No Not Applicable.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
11
Sr
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
4.5 Surplus product No Not Applicable.
4.6 Sewage sludge or other sludge from
effluent treatment
The Sludge will be used as manure
after treatment.
4.7 Construction or demolition wastes No Construction waste will be used for
road making & hardening the base of
working area.
4.8 Redundant machinery or equipment No No redundant machinery or equipment
at project site.
4.9 Contaminated soils or other
materials
No No contamination of soil because land is kept unutilized before this development. Soil Testing will be done prior to project.
4.10 Agricultural wastes No Not Applicable.
4.11 Other solid wastes
No Not Applicable.
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
Sr
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
5.1 Emissions from combustion of fossil
fuels from stationary or mobile
sources.
No Not Applicable.
5.2 Emissions from production processes No Not Applicable.
5.3 Emissions from materials handling
including storage or transport
No Not Applicable.
5.4 Emissions from construction
activities including plant and
equipment
No Not Applicable.
5.5 Dust or odours from handling of
materials including construction
materials, sewage and waste
Yes Problem of odour will be avoided by
using modular toilets during
construction phase.
5.6 Emissions from incineration of waste No Not Applicable.
5.7 Emissions from burning of waste in No Not Applicable.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
12
Sr
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
open air (e.g. slash materials,
construction debris)
5.8 Emissions from any other sources No Not Applicable.
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
Sr
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data with
source of information data
6.1 From operation of equipment e.g.
engines, ventilation plant, crushers
Yes Sources of noise Pollution during
construction phase are machinery like
compressor, Compactors, Concrete
machinery, Cranes and transportation
materials. These equipment/s will be
used in day time only & proper care
will be taken for the minimization of
noise during operation.
6.2 From industrial or similar processes No Not Applicable.
6.3 From construction or demolition Yes Construction equipments will cause
some noise. Ear plugs will be provided
to construction workers, working near
noise generating equipments (about 65
to 70 dB(A)
6.4 From blasting or piling
No Not Applicable.
6.5 From construction or operational
traffic
Yes As per EMP
6.6 From lighting or cooling systems
No Not Applicable.
6.7 From any other sources
No Not Applicable.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
13
7. Risks of contamination of land or water from releases of pollutants into the ground or
into sewers, surface waters, groundwater, coastal waters or the sea:
Sr
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
7.1 From handling, storage, use or
spillage of hazardous materials
No Not Applicable.
7.2 From discharge of sewage or other
effluents to water or the land
(expected mode and place of
discharge)
Yes Proper sewage treatment scheme will
be provided & treated sewage will be
reused for flushing & gardening. 77
m3/day treated water will be reused.
7.3 By deposition of pollutants emitted
to air into the land or into water
No No risk of contamination due to
pollutants in air or water Annexure 10-
EMP for further details.
7.4 From any other sources No Not Applicable.
7.5 Is there a risk of long term build up
of pollutants in the environment
from these sources?
No Proposed proper environment
management will be done as per
various guidelines by MoEF & CC and
CPCB.
8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment
Sr.
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
8.1 From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous substances
No Not Applicable.
8.2 From any other causes
Yes There is a risk of accident during
construction however proper safety
measures shall be taken.
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g. floods,
earthquakes, landslides, cloudburst
etc)?
Yes Floods and landslides are not expected
in the area.
Earthquake proneness: The area falls
under Zone III as per IS- 1893-2002.
Hence relevant design parameters as
per zone III have been considered for
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
14
Sr.
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
RCC design of the buildings.
Dynamic analysis will be done by
Response spectrum method.
Importance factor 1 special moment
resisting frame R-5, Zone factor Z-
0.16.
Annexure 7 (Seismic Zoning Map of
India.)
9. Factors which should be considered (such as consequential development) which could
lead to environmental effects or the potential for cumulative impacts with other
existing or planned activities in the locality
Sr.
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
9.1 Lead to development of supporting,
lities, ancillary development or
development stimulated by the
project which could have impact on
the environment e.g.:
• Supporting infrastructure (roads,
power supply, waste or waste
water treatment, etc.)
• housing development
• extractive industries
• supply industries
• other
Yes Proposed project is construction of
commercial infrastructure building.
The site and nearby areas are developed
with good supportive infrastructure
Like roads, transport facility,
entertainment and hospitals.
9.2 Lead to after-use of the site, which
could have an impact on the
environment
No The proposed project will prove to be
boon for the site development.
9.3 Set a precedent for later
developments
No The proposed project will help to
redefine surrounding areas with
enrichment of hassle free life & eco-
friendly project.
9.4 Have cumulative effects due to No Not applicable, because Minor impacts
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
15
Sr.
No.
Information/Checklist
confirmation
Yes/No Details thereof (with approximate
quantities/rates, wherever possible)
with source of information data
proximity to other existing or
planned projects with similar
effects
on water availability, sewage disposal,
storm water discharge, availability of
electricity etc. There will be minor
impact on vehicular traffic in nearby
areas of the site.
(I) Environmental Sensitivity
Sr.
No.
Areas Name/
Identity
Aerial distance (within 15 km.)
Proposed project location boundary
1 Areas protected under international
conventions, national or local
legislation for their ecological,
landscape, cultural or other related
value
No No, not any areas protected under
international conventions, national or
local legislation for their ecological,
landscape, cultural or other related
value within 15 km of aerial distance.
2 Areas which are important or
sensitive for ecological reasons -
Wetlands, watercourses or other
water bodies, coastal zone,
biospheres, mountains, forests
No No, not any Areas which are important
or sensitive for ecological reasons -
Wetlands, watercourses or other water
bodies, coastal zone, biospheres,
mountains, forests. Mula Mutha river is
located at 3.6 km of aerial distance.
3 Areas used by protected, important
or sensitive species of flora or fauna
for breeding, nesting, foraging,
resting, over wintering, migration
No No, not any areas used by protected,
important or sensitive species of flora
or fauna for breeding, nesting, foraging,
resting, over wintering, migration
within 15 km of aerial distance.
4 Inland, coastal, marine or
underground waters
NO Mula Mutha river is located at 3.6 km
of aerial distance.
5 State, National boundaries No No, not any State /National boundaries
within 15 km of aerial distance.
6 Routes or facilities used by the
public for access to recreation or
other tourist, pilgrim areas
No Project site is not located in the route of
any recreation or other tourist, pilgrim
areas.
7 Defence installations No Defence installations are located at 4.2
km from project site. However defence
area is surrounded by residential and
commercial zone. The nature of our
construction project is such that it will
not have any adverse impact on defence
installations.
8 Densely populated or built-up area No Census Data 2011- Annexure: 8
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
16
Sr.
No.
Areas Name/
Identity
Aerial distance (within 15 km.)
Proposed project location boundary
9 Areas occupied by sensitive man-
made land uses (hospitals, schools,
places of worship, community
facilities)
No Community health centers and
primary schools exist in 15 km radius.
School – 1.7 km, Hospital – 1.5 km
10 Areas containing important, high
quality or scarce resources
(ground water resources, surface
resources, forestry, agriculture,
fisheries, tourism, minerals)
No Mula Mutha river is located at 3.6 km
of aerial distance.
11 Areas already subjected to pollution
or environmental damage. (those
where existing legal environmental
standards are exceeded)
No Not Applicable. Nil in 15 km radius
area.
12 Areas susceptible to natural hazard
which could cause the project to
present environmental problems
(earthquakes, subsidence,
landslides, erosion, flooding or
extreme or adverse climatic
conditions)
No Not Applicable. Nil in 15 km radius
area. Floods and landslides are not
expected in the area.
Earthquake proneness: The area falls
under Zone III as per IS- 1893-2002.
Hence relevant design parameters as
per zone III have been considered for
RCC design of the buildings.
(IV). Proposed Terms of Reference for EIA studies (IV):- EIA not required as project is
under 8(a) Category.
FORM IA
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
1
APPENDIX – II
(See paragraph 6)
FORM - 1 A
(Only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIRONMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary
attach explanatory notes with the Form and submit along with proposed environmental
management plan & monitoring programme)
1. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1.Will the existing land-use get significantly altered from the project that is not consistent
with the surroundings? (Proposed land-use must conform to the approved Master Plan /
Development Plan of the area. Change of land-use if any and the statutory approval from
the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding
features of the proposed site (within 500 meters) and (iii) The site (indicating levels &
contours) to appropriate scales. If not available attach only conceptual plans.
The proposed land use is in conformity with the DP of the area.
Annexure – 1 : Master Plan
Annexure – 2 : Site Location Map
1.2.List out all the major project requirements in terms of the land area, built up area, water
consumption, power requirement, connectivity, community facilities, parking needs etc.
Total Area of the Plot 8340.00 Sq.M
Total Built-up Area 36925.20Sq.M.
Landscape area 785.41Sq.M.
The overall area of the plot is 8340.00 Sq. M and proposed builtup area is 36925.20 Sq.
M. Landscape area will be 785.41 Sq. M. Total Population for Commercial scheme will
be 2409.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
2
Area Statement
Non FSI Statement
F.S.I NON F.S.I AREA F.S.I NON F.S.I AREA F.S.I NON F.S.I AREA
EXISTING PROPOSED TOTAL
FSI AREA 4678.00 BUILT UP AREA 7662.57 BUILT UP AREA 12340.57
BALCONY 431.76 BALCONY 1434.83 BALCONY 1866.59
STAIRCASE 522.38 STAIRCASE 614.41 STAIRCASE 1136.79
PASSAGE/LOBBY/ATRIUM 3250.69 PASSAGE/LOBBY/ATRIUM 440.31 PASSAGE/LOBBY/ATRIUM 3691.00
TERRACE 1233.44 TERRACE 1689.64 TERRACE 2923.08
L.M.R 0.00 L.M.R 105.41 L.M.R 105.41
LIFT SHAFT 16.33 LIFT SHAFT 22.79 LIFT SHAFT 39.12
SERVICE AREA 0 SERVICE AREA 957.29 SERVICE AREA 504.41
PARKING 9059.60 PARKING 3859.04 PARKING 12918.64
ARCH. PROJECTION 463.79 ARCH. PROJECTION 528.80 ARCH. PROJECTION 992.59
SWIMMING POOL 0.00 SWIMMING POOL 407.00 SWIMMING POOL 407.00
TOTAL NON F.S.I 14977.99 TOTAL NON F.S.I 10059.52 TOTAL NON F.S.I 24584.63
TOTAL CONSTRUCTION 19655.99 TOTAL CONSTRUCTION 17722.09 TOTAL CONSTRUCTION 36925.20
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
3
Tenement Statement
Parking statement:
(REFER ANNEXURE 9 – Parking Plan)
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
4
vi) LANDSCAPING AND TREE PLANTATION
The green belt area will be 785.41Sq.M. to keep the campus green and environment friendly. We
will give the preference to the local & indigenous species. The list of trees to be planted is as
follows -
In this Plot area total 100 numbers of trees will be planted in the project area.
List of Trees
Sr.
No. Name
Quanti
ty
Characteristics & Ecological
Importance
1 Nyctanthes Arbortritis 10 Tree reches upto height of 10m. flowering tree.
2 Taebubea rosea 20
Is also called trumpet tree, neotropical tree.
deciduous tree
3 Anthocephalous
kadamb 9
Evergreen tree fast growing tree with broad crown
4 Bauhinia variegata 10
It is medium sized tree growing upto 10m. is known
for its dry sson flowering pattern.
5 Areca catchew 17
It is a tropical tree of palm species growing straight
and tall.
6 Plumeria alba. 34
Plumerias grow well in absolutely all kinds of soils.
Plumerias can go without water for long periods of
time.
Total No. of Trees 100
The Project proponents have proposed a landscape development plan, which includes planting of
flowering and shady trees, shrubs and lawn within the plot.
The open spaces inside the plot will be suitably landscaped and covered with vegetation of
indigenous variety.
1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the
proposed site? (Such as open spaces, community facilities, details of the existing land use
and disturbance to the local ecology).
Although it is a construction activity, its impact on air quality, water quality, noise and soil will
not be notable. As a matter of fact this activity will have positive impact on socio-economic
culture of people residing in the vicinity of the proposed area. There will not be any disturbance
to the local ecology as the selected site for the construction is a open land and meant for
development.
The project site and the surrounding area have Residential, Commercial, Educational & Heath
buildings. The open area will be occupied by vegetation, which will be helpful in increasing
green cover of the area. Proposed project will require manpower during construction phase and
operational phase thereby creating job opportunities. Local skilled and unskilled laborers will
have an opportunity for employment directly or indirectly.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
5
There will be additional employment for the poor strata of society by way of domestic helpers,
drivers, cleaners etc.
Due to the proposed project, facilities are likely to grow in line with the development. As during
the construction and operational phases of the project a skilled and unskilled workforce will be
needed. The introduction of workers from areas outside the region, could introduce a potential
effect on the local culture, habits and economics.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence &
instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity, etc
may be given).
A. Details of Soil quality and slope
Generally, soil types found in Pune district are black, copper, red and paddy soil. Soil blends of
variable proportions are modified by sand, gravel, lime salts and other ingredients. Soil erosion is
acute in these soils because of the sloppy nature of lands mostly unprotected by natural
vegetation due to over grazing.
Samples were collected within a radius of 10 Km in the study area. Soil samples collected and
were analyzed for pH, moisture content, water holding capacity, organic matter, ammonia
nitrogen, potassium, phosphorous, Magnesium as Mg, Chlorides as Cl-, Sulphates as SO4--
using standard methods of Association of Official Agricultural Chemist.
(REFER ANNEXURE 3 – Soil Analysis Report)
The geology of the Pune consists of Deccan traps with inter-trapped beds. The volcanic lava
flows are spread out in the forms Horizontal sheets or beds. Pune is a plateau city situated near
the western margin of the Deccan plateau. The main system of hills is Sahyadri, which run south
in the western portion of the district. Pune is situated at latitude of 18o31’ N and longitude 73
o51’
E. Mean elevation of the site is 560 meters.
B. Vulnerability to Seismicity and precautions:
As per the Seismic Zoning Map of India (given in Enclosures) Pune region falls under Zone- 3.
Stability Certificate, as per prevalent IS Code will be obtained for these buildings from registered
Consulting Structural Engineer considering the seismic forces and wind forces etc.
(REFER ANNEXURE 7 – Seismic Zoning Map)
C. Vulnerability to Subsidence
Ground level of the plot is plain land. Backfilling in the vicinity of site is not included in the
project plan. Hence, subsidence is not expected.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
6
1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour
map showing the natural drainage near the proposed project site)
Not Applicable.
1.6. What are the quantities of work involved in the construction activity-cutting, filling,
reclamation etc. (Give details of the quantities of earthwork involved, transport of fill
materials from outside the site etc.)
During construction total earthwork involved approximately Excavation in murum/soft rock -
2952.29 Cu.m. Excavation in hard rock- 2882.906 Cu.m. This will be used for Filling with
murum/soft rock&Rubble filling in floor bedding.
1.7. Give details regarding water supply, waste handling etc during the construction period.
CONSTRUCTION PHASE:
Total water requirement during construction phase shall be 50 cum/day approximately for
construction as well as domestic use for the workers working on the site and also for the
construction purpose. This water will be made available from Tanker Water. Portable Toilet
block will be provided.
The Biodegradable waste will be composted at site and non-biodegradable solid waste will be
sent recycling. The construction debris will be used for development of Landscape.
All required sanitary and hygienic measures should be in place before starting construction
activities and to be maintained throughout the construction phase.
1.8. Will the low lying areas & wetlands get altered? (Provide details of how low lying and
wetlands are getting modified from the proposed activity)
Not Applicable
1.9. Whether construction debris & waste during construction cause health hazard? (Give
quantities of various types of wastes generated during construction including the
construction labour and the means of disposal)
Construction debris and waste during construction will not cause health hazard. Temporary
housing will be provided at the site for 50 workers in the form of Labour camp within the site.
Construction debris generated will be used for development of landscape. All the waste generates
will be properly treated and taken care of, therefore will not create any health hazard.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
7
2. WATER ENVIRONMENT
2.1. Give the total quantity of water requirement for the proposed project with the breakup of
requirements for various uses. How will the water requirement met? State the sources &
quantities and furnish a water balance statement.
The proposed source of water will be PMC.
It is proposed that water will be available from PMC. The underground tank (UGT) be provided
for the filtered water storage tank. Water may be pumped from proposed UGT to the overhead
tanks on all buildings through a hydro pneumatic tank filling system. It will be then distributed to
Overhead tank on terrace building.
During construction: 50 M3/DAY
Source: Tanker Water
During operation:
Source: Pune Municipal Corporation
Fresh water : 89 m3/day
Recycled water (Flushing): 68 m3/day
Recycled water (Gardening): 9 m3/day
Total Water Requirement :166 m3/day
Sewage generation: 152 m3/day
STP capacity: 160 m3/day
Treated water: 144 m3/day
Total recycled water: 77 m3/day
Excess water to drain: 67 m3/day
Swimming pool: 12.0 m3/day
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
8
2.2 What is the capacity (dependable flow or yield) of the proposed source of water?
WATER BALANCE STATEMENT
Sl
No
Description Area
In
Sqm.
Popula
tion
Water
Req.(Lit)
Per Person
Total
Water
Req.(Lit)
Domestic
Capacity
(Lit)
Flushing
Capacity
(Lit)
Sewage
Generation
(Lit)
1 Hotel
Rooms(121
Nos)
--- 363 135 49005 32670 16335 47372
2 Banquet 419.83 280 45 12594.9 5598 6997 12315
3 Restaurant 871.34 484 75 36306 24204 12102 35096
4 Shopping 4567.1
3
761 45 34253 15224 19030 33492
5 Office 581.41 58 45 2616 1163 1454 2558
6 Sports 2378.6
5
463 45 20835 9260 11575 20372
Total Water Requirement(Lit) 155611 88118 67492 151205
Stp Capacity (Lit Per Day) 160000
Ugr Capacity (Lit)1.5 Days Storage ( Only For
Domestic)
132177
Fire Capacity (Lit)( To Be Confirmed As Per Fire
Noc)
200000
Raw Water Tank(Lit) 44059
Total Ugr ( Dom+Fire+Raw)(Lit) 376236
2.3. What is the quality of water required, in case, the supply is not from a municipal
source? (Provide physical, chemical, biological characteristics with class of water
quality)
The 89 m3/day water will be available from Pune Municipal Corporation.
(REFER ANNEXURE: 4- BASELINE STATUS OF WATER QUALITY)
2.4. How much of the water requirement can be met from the recycling of treated
wastewater? (Give the details of quantities, sources and usage)
77 m3/day Water used for Landscape and Flushing will be recycled water.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
9
2.5. Will there be diversion of water from other users? (Please assess the impacts of the
project on other existing uses and quantities of consumption)
Not Applicable.
2.6. What is the incremental pollution load from wastewater generated from the
proposed activity? (Give details of the quantities and composition of wastewater
generated from the proposed activity)
The quantity of sewage is about 90% of domestic water consumption. The wastewater-
generated from the proposed activity shall be domestic. The sewage will be collected
from 1934 population.
2.7. Give details of the water requirements met from water harvesting? Furnish details
of the facilities created.
(A) Total availability of water at the site
= Geographical area x Rainfall x Runoff Coefficient
= 8340 Sq.Mt. x 0.70 Mt. (700 mm) x 0.6
= 3,502.8 M3
We have considered runoff coefficient for calculating flow for rainwater design based on
Central Pollution Control Board Ministry of Environment & Forests data.
By studying feasibility of ground water recharge we have proposed rain water harvesting
by constructing 160 cum. Rain water harvesting tank to minimized fresh water
requirement.
Rain Water Harvesting Tank Calculations
Sn Descreption Area In
Sq.M
Rain
Intensity
Cm/Hr
Runoff
Coefficient
Storm Water
Runoff
(Cubicm/Sec)
Storm Water
Runoff
(Lit/Sec)
Storm Water
Runoff
(Lit/Min)
1
Area
Considered
For Design
7858 7.5 0.9 0.1473375 147.3375 8840.25
Rain Water Harvesting Tank For 16.40 Minues Holding Capacity 144980.1
Say 1,60,000 Lit
CONCLUSION:
Based on the resistivity modeled values it can be seen that the area shows the presence of shallow
aquifer restricted to 15-20 meters depth at 2 & 3 VES locations. The all VES shows continuous
increase in the resistivity values beyond ~ 10 meters indicating presence of massive hard rock. It
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
10
is to be noted that from the groundwater potential point of view the overall area can be
categorized as with very low potential.
2.8. What would be the impact of the land use changes occurring due to the proposed project on
the runoff characteristics (quantitative as well as qualitative) of the area in the post
construction phase on a long term basis? Would it aggravate the problems of flooding or
water logging in any way?
The proposed land use is in conformity with the DP so there will not be any land use change. The
runoff from the project site will be used for recharging the aquifers.
The Storm water drains of the area are proposed to be connected to the drain line which will be
developed as a part for project and subsequently connected to public drainage/storm water
system.
2.9. What are the impacts of the proposal on the ground water? (Will there be tapping of
ground water; give the details of ground water table, recharging capacity, and approvals
obtained from competent authority, if any)
Source of water supply will be from PMC during operation phase. However during construction
phase ground water will be utilized for which necessary permission wil be taken from competent
authority.
Rain water entering into the stilt & lower ground floor through ramps etc shall be collected by
Provision of channel drain with pre cast RCC / CI gratings discharging by gravity in to the
nearest external storm drain
2.10. What precautions/measures are taken to prevent the run-off from construction activities
polluting land & aquifers? (Give details of quantities and the measures taken to avoid the
adverse impacts)
The general ground level of the project site will not be elevated. The run off from the site will be
filtered mechanically through recharge pits and then will reach aquifers thereby preventing direct
pollution of land or aquifers.
2.11. How is the storm water from within the site managed?(State the provisions made to avoid
flooding of the area, details of the drainage facilities provided along with a site layout
indication contour levels)
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
11
The storm water from the site will be used for recharging the aquifers. Recharge pits will be
created on site.
2.12. Will the deployment of construction laborers particularly in the peak period lead to
unsanitary conditions around the project site (Justify with proper explanation)
During construction phase number of workers will be 50. Municipal solid waste generated during
construction will be composted at site. Modular toilets will be provided for the construction
labours. So activity will not lead to unsanitary conditions at the site.
2.13. What on-site facilities are provided for the collection, treatment & safe disposal of sewage?
(Give details of the quantities of wastewater generation, treatment capacities with
technology & facilities for recycling and disposal)
The sewage will be collected from 2409 Population. The quantity of sewage is about 90% of
domestic water consumption. The wastewater-generated from the proposed activity shall be
domestic. Sewage will treated in the Sewage Treatment Plant having capacity – 160 m3/day.
The treated sewage will be partly recycled for flushing & partly connected to Municipal sewer
line.
DETAILED DESCRIPTION OF PROCESS UNITS
Bar Screen:
Bar Screen shall be provided at the entrance point of the holding tank to separate floating
material form the raw effluent. Screened effluent shall be collected in the Equalization tank.
Aeration Tank:
ASEA system is a specially designed aerobic treatment system. The extended aeration process
operates in the endogenous respiration phase of bacterial growth curve, which necessitates a
relatively low organic loading and long aeration time. Thus it is generally applicable to low
strength wastewater only. In order to ensure required population of bacteria in the unit, mixed
liquor suspended solids (MLSS) concentration and food to microorganism ratio (F/M) is
maintained by controlled drainage of excess sludge to drying beds.
Clarifier + Intermediate Tank :
The function of the activated sludge-settling tank is to separate the activated sludge solids from
the mixed liquor. This is the final step in the production of a well-clarified, stable effluent low in
BOD and suspended solids, and as such, represents a critical link in the operation of an activated
sludge treatment process. The presence of the large volume of flocculent of solids in the mixed
liquor requires special consideration during design of activated sludge settling tanks. Mixed
liquor suspended solids are separated from the treated effluent and are recirculated back in the
aeration tank to maintain desired quantity of active biological culture in the tank. The effluent
will overflow to intermediate tank before passing through sand filters.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
12
Filter Press:
Sludge generated during the treatment process will be pases through filter press to squeeze out
the water from suldge and compact the solids. Dried sludge shall be disposed in farms /
gardening area. Because of the ASEA process the sludge generated is biologically stable and
does not require separate digestion.
Tertiary Treatment and Filtration
Tertiary Treatment is must if water is to be re-used for Gardening / Flushing
Pressure Sand Filter:
The device is provided to filter the neutralized effluent to remove the suspended solids impurity
in the effluent. Clarified water from the settling tank passed through the system to remove traces
of suspended particles.
Activated Carbon filter:
Activated carbon filter shall be provided to remove the traces of organic material present in the
effluent. It adsorbs the traces of oils, detergents and solvents.
Ozonation :
The outlet water from ACF is dosed with ozone via ozone generator for disinfection. The water
coming out will be free from fecal coliforms and other harmful bacteria.
QUALITY OF THE SEWAGE AFTER TERTIARY TREATMENT
SR.
NO
.
DETAILS Units As per EPA
act
Proposed Conc.
1 pH --- 5.5-9.0 6.5-8.5
2 Total Suspended solids Mg/lit <100 <10
4 Chemical Oxygen Demand Mg/lit <250 <50
5 Total Dissolved Solids Mg/lit 200-300 <10
6 Biochemical Oxygen Demand, 3 day, 27
°C
Mg/lit <30 <10
7 Oil & Grease Mg/lit <10 Nil
8 Phosphorus as P Mg/lit < 5 < 2
9 Fecal Coliforms MPN/ 100
ml
< 100 < 100
10 Residual Chlorine Mg/lit < 1 Ozonation
11 Color and Odor --- Unobjectiona
ble
Unobjectionable
12 Ammonical nitrogen as N Mg/lit < 50 20 max
13 Total kjeldahl nitrogen Mg/lit < 100 20 max
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
13
2.14. Give details of dual plumbing system if treated waste used is used for flushing of
toilets or any other use.
The quantity of sewage is about 90% of domestic water consumption. The wastewater-
generated from the proposed activity shall be domestic. Sewage will be treated in the
Sewage Treatment Plant having capacity - 160 m3/day. The treated sewage will be
recycled for flushing.
3. VEGETATION
3.1. Is there any threat of the project to the biodiversity? (Give a description of the local
ecosystem with it’s unique features, if any)
There will not be any threat of the project to the biodiversity. The selected site for project
is barren land. The Project proponents have proposed a landscape development plan,
which includes planting of flowering and shady trees, shrubs and lawn within the plot.
Flowering plants, shrubbery and lawns shall be planted. So, Biodiversity will in turn
increase.
3.2. Will the construction involve extensive clearing or modification of vegetation?
(Provide a detailed account of the trees & vegetation affected by the project)
Selected site is barren land. However, the project site will cover the flowering plants,
shrubs and lawns. The open spaces inside the plot will be suitably landscaped and covered
with vegetation of indigenous variety.
3.3. What are the measures proposed to be taken to minimize the likely impacts on
important site features (Give details of proposal for tree plantation, landscaping,
creation of water bodies etc along with a layout plan to an appropriate scale)
The site presently is Barren land. There is no important site feature so as to cause any
impact on important site features.
Landscaping and Tree Plantation
The area 785.41 Sq. M will be covered by tree plantation & landscaping so as to give rest
of the area massive to keep the campus green and environment friendly. The Project
proponents have proposed a landscape development plan, which includes planting of
flowering and shady trees, shrubs and lawn within the plot. In this Plot area total 85
number of trees will be planted. The open spaces inside the plot will be suitably
landscaped and covered with vegetation of indigenous variety.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
14
4. FAUNA
4.1. There likely to be any displacement of fauna- both terrestrial and aquatic or
creation of barriers for their movement? Provide the details.
The floristic component of the area does not include any rare or endangered species.
Thus, impact on rare and endangered species of flora is nil. There are no potential sources
of impacts on terrestrial biological environment during operation phase of Commercial
scheme.
4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.
Biological Environment:
The project site and the surrounding area have plain land. The whole area will be
occupied by vegetation. The plantations, which would be grown in the Commercial area,
will be helpful in increasing green cover in the area. This would also increase avifauna in
the area.
4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on
fauna.
The proposed project will not have any adverse impact on the flora or fauna.
5. AIR ENVIRONMENT
5.1. Will the project increase atmospheric concentration of gases & result in heat
islands? (Give details of background air quality levels with predicted values based
on dispersion models taking into account the increased traffic generation as a result
of the proposed constructions)
As this will be a Commercial scheme, air pollution is not expected to be a major concern.
There will not be notable increase in pollution therefore dispersion model calculations are
not done. But the data on Ambient Air Quality have been collected during the study
period.
In view of the revision of national Ambient Air Quality Standards by Central Pollution
Control Board ambient air quality stations were identified and monitored. The sampling
locations are Project site and buffer zone.
(REFER ANNEXURE 5: BASELINE STATUS OF AIR QUALITY)
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
15
5.2. What are the impacts on generation of dust, smoke, odorous fumes or other
hazardous gases? Give details in relation to all the meteorological parameters.
During construction phase, PM - 2.5, PM-10 will be the main pollutant, which could be
generated from site development activities. Concentration of SO2, NO2 and CO may rise
a little due to traffic. Proper upkeep and maintenance of vehicles, sprinkling of water on
roads and construction site and providing sufficient vegetation all around the plant site
are some of the measures that would reduce the impact during construction phase.
It is generally observed that PM-2.5, PM-10 levels are higher in dry weather i.e. during
summer and winter seasons. Pollutant load of the atmosphere is generally low during
monsoon as the gaseous pollutants tend to dissolve and particulate pollutants get
adsorbed forming aerosols.
Fog formation aggravates the problem as rate of dispersion of pollutants reduces. High
wind velocity is helpful for dispersion of pollutants. Higher temperature and pressure in
the troposphere is helpful for better dispersion of pollutants. In general, effective
dispersion of pollutants in the atmosphere depends primarily on the degree of stability of
the atmosphere and on its turbulent structure.
5.3. Will the proposal create shortage of parking space for vehicles? Furnish details of
the present level of transport infrastructure and measures proposed for
improvement including the traffic management at the entry & exit to the project
site.
As this is an commercial scheme, there will be no reserved car parking. Scooters & cycle
parking will be provided as per norms.
Measures proposed for improvement including traffic management at the entry and exit to
the project site are:
Maintaining flow of traffic for approach roads
Entry and Exit points carefully placed so as not to disturb this flow
One way traffic inside the complex for comfortable movement of vehicles and
reduction in possibility of congestion.
There will be one entry and exit gate provided to enter within campus and
vehicles will be park accordingly with the building.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
16
5.4. Provide details of the movement patterns with internal roads, bicycle tracks,
pedestrian pathways, footpaths etc., with areas under each category.
We will provide pathways etc as per DC rules and sometimes beyond that to make the
project environment friendly.
5.5. Will there be significant increase in traffic noise & vibrations? Give details of the
sources and the measures proposed for mitigation of the above.
The proposed activity being of Commercial scheme will not cause a notable increase in
the noise and vibration during operation. However, use of heavy machinery is inevitable
during construction phase of the project. Sources of noise Pollution during construction
phase are machinery like Earthmoving Machinery Mini Hoist Crane, Hoist Crane,
Concrete mini mixer, Weigh batcher, Compressors and transportation materials.
Incremental increase in baseline noise levels due to this Commercial scheme will not
exceed 55 dB(A). The post project noise levels at the nearest habitation will be less than
the stipulated standards of CPCB.
Noise has various adverse effects on workers and their activities. The first and foremost
effect of noise on workers exposed to high noise level over a long period of severe
impulsive noise of short duration is ‘Loss of Hearing’. This effect is either temporary or
permanent in nature depending upon the length and severity of noise exposure.
Other effects of noise are such as blood pressure, cardiovascular problems and ulcers.
Some studies also point to noise related learning difficulties, reduced work efficiency,
irritation, fatigue, increased accidents and errors and socially undesirable behavior.
MITIGATIVE MEASURES:
The project proponents have agreed to take precautions to control noise pollution as
mentioned under:
Use of equipment generating noise of not greater than 90 dB (A).
High noise generating construction activities would be carried out only during
daytime. Also, adequate parking space will be provided to avoid crowding and
noise pollution
Installation, use and maintenance of mufflers on equipment.
Workers working near high noise construction machinery would be supplied
with ear muffs/ear plugs.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
17
5.6. What will be the impact of DG sets & other equipment on noise levels & vibration in
& ambient air quality around the project site? Provide details.
DURING CONSTRUCTION PHASE:
Sources of noise Pollution during construction phase are machinery like Earthmoving
Machinery, Mini Hoist Crane, Concrete Mixer, Lift lade, JCB, Dumpers, Compressors
and transportation materials.
DURING OPERATION
These Machineries will be used only during daytime
Canopies will be provided to these mechanical devices to reduce noise and vibration.
There will not be any considerable impact on the ambient air quality around the project
site as CPCB approved DG sets along with acoustic room will be developed and
plantations will be provided.
6. AESTHETICS
6.1. Will the proposed constructions in any way result in the obstruction of a view, scenic
amenity or landscapes? Are these considerations taken into account by the
proponents?
Proposed construction will not result in obstruction of a view, scenic amenity or
landscapes. The open spaces have been picturesquely landscaped to capture the variety of
flowers and plants.
6.2. Will there be any adverse impacts from new constructions on the existing
structures? What are the considerations taken into account?
Not Applicable
6.3. Whether there are any local considerations of urban form & urban design
influencing the design criteria? They may be explicitly spelt out.
No
6.4. Are there any anthropological or archaeological sites or artefacts nearby? State if
any other significant features in the vicinity of the proposed site have been
considered.
No
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
18
7. SOCIO-ECONOMIC ASPECTS
7.1. Will the proposal result in any changes to the demographic structure of local
population? Provide the details.
It could be seen that the overall impact on Socio-Economic Environment is positive and
permanent in nature. The impacts on socio-economic environment due to the proposed
project are listed below:
Proposed project will require manpower during construction phase and operational
phase thereby creating job opportunities. Local skilled and unskilled laborers will have
an opportunity for employment directly or indirectly.
There will be additional employment for the poor strata of society by way of helpers,
drivers, cleaners etc.
Due to the proposed project, facilities are likely to grow in line with the development.
As during the construction and operational phases of the project a workforce will be
needed this will be including both skilled and unskilled people. The introduction of
workers from areas outside the region, could introduce a potential effect on the local
culture, habits and economics. Those effects have both positive and negative elements and
will be managed by the project proponents and developers. The construction phase
induces employment opportunities for the local people. About 150 persons will be
employed during peak period.
(REFER ANNEXURE 8 : CENSUS DATA & SOCIOECONOMIC ASPECTS OF
PROJECT AREA)
7.2. Give details of the existing social infrastructure around the proposed project.
Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors
Pvt Ltd., At Survey no.153A/1 to 4/1/1 Hadapsar, Pune. This area is rapidly developing
area. Development of this commercial project will cater to the needs of residents in this
area.
7.3. Will the project cause adverse effects on local communities, disturbance to sacred sites
or other cultural values? What are the safeguards proposed?
It could be seen that the overall impact on Socio-Economic Environment is positive and
permanent in nature. The impacts on socio-economic environment due to the proposed
project are listed below:
Positive Aspects of the Projects are as follows
Improvement in transport, communication facilities.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
19
Improvement in lifestyle and social status, etc.
Increase in revenue generation.
Due to the proposed project, facilities are likely to grow in line with the development.
Possible sources of income for this community are direct like Construction and
various job works in Commercial scheme.
As during the construction phases of the project a workforce will be needed which
will be including both skilled and unskilled people. The introduction of workers from
areas outside the region, could introduce a potential effect on the local culture, habits
and economics. Those effects have both positive and negative elements and will be
managed by the project proponents and developers. The construction phase induces
employment opportunities for the local people. About 400 persons will be employed
during peak period.
The open spaces have been picturesquely landscaped to capture the true lavish ambience
of a vacation resort replete with palms, water bodies, fountains and a variety of flowers
and plants.
8. BUILDING MATERIALS
8.1. May involve the use of building materials with high-embodied energy. Are the
construction materials produced with energy efficient processes? (Give details of
energy conservation measures in the selection of building materials and their energy
efficiency)
ECBC (Energy Conservation Building Code`) norms will become applicable for all
buildings as per Energy Conservation Act 2001. These norms will be recommended and
included in design.
8.2. Transport and handling of materials during construction may result in pollution,
noise & public nuisance. What measures are taken to minimize the impacts?
During construction phase, sources of noise pollution will be due to operation of
machinery like Earthmoving Machinery, Mini Hoist Crane, Hoist Crane, Concrete mini
mixer, Weigh batcher, Compressors and transportation materials as well as transportation
vehicles. This will cause nuisance to the occupants of the nearby area. The project
proponents have agreed to take precautions to control noise pollution as mentioned under:
Use of equipment generating noise of not greater than 90 dB (A).
High noise generating construction activities would be carried out only during
daytime.
Installation, use and maintenance of mufflers on equipment.
Workers working near high noise construction machinery would be supplied with ear
muffs/ear plugs.
(REFER ANNEXURE 6 - BASELINE STATUS OF NOISE QUALITY)
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
20
8.3. Are recycled materials used in roads and structures? State the extent of savings achieved?
Solid waste that would be generated due to excavation will be in the form of rubble and soil. This
soil and rubble would be used for development of Landscape. Construction debris will be reused
for backfilling of roads and other construction.
8.4. Give details of the methods of collection, segregation & disposal of the garbage generated
during the operation phases of the project.
Solid Waste Management
a) During Construction phase:
Construction debris will be used for construction site itself and therefore there will not be any
solid waste problem from generation of construction-excavated earth.
Solid waste, which will be generated from construction workers working within site, will be
disposed through composting.
Modular toilets will be provided for proper disposal of liquid effluent.
b) During Operation Phase:-
Total population of the Commercial scheme is projected to be 2409 nos.
Quantity of solid waste – 602 kg/day
Quantity of wet waste – 279 kg/day
Quantity of dry waste – 323 kg/day
Organic waste will be converted in to manure by composting in OWC machine.
The dry waste collection, segregation, recycling & disposal by SWaCH.
9. ENERGY CONSERVATION
9.1. Give details of the power requirements, source of supply, backup source etc. What is
the energy consumption assumed per square foot of built-up area? How have you
tried to minimize energy consumption?
During Construction Phase –
Source: D.G.
DG Set Required = 40 KVA.
During Operation Phase –
Source: MSEDCL
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
21
Demanded load = 2043 kVA
Connected load = 3204 kVA
Proposed Transformer Configuration: 630KVA X 4 Nos.
Source: D.G. sets
Required Capacity Of D. G. Set With Sound Proof Enclosure: 630KVA X 4 No2
9.2. What type of, and capacity of, power back-up to you plan to provide?
Alternative Back Up: -
During Construction Phase –
DG Set Required During Construction = 25 KVA.
During Operation Phase –
Required Capacity Of D.G.Set: 630KVA X 4 No2
9.3. What are the characteristics of the glass you plan to use? Provide specifications of its
characteristics related to both short wave and long wave radiation?
Normal 6 mm clear float glass is used. The glass will allow short as well as long wave
radiations to pass through. However, use of sunscreens on window panes will reduce
heating inside the buildings.
9.4. What passive solar architectural features are being used in the building? Illustrate
the applications made in the proposed project.
The external walls exposed to high solar exposure are double walls/cavity walls. Most of
the openings are with appropriate sunshades to cast shadow inside the room. Most of the
external facades are double height terraces, which help in reducing direct exposure to
solar heat.
ARCHITECTURAL DESIGN
Maximum ground is covered by green patches to reduce reflection of heat from
ground surface.
Shade giving trees are proposed around the condominium especially on South and
west side to cast shadow on the ground and building.
By accommodating maximum parking areas are covered parking, heat generation
due to vehicle is compressed below the building.
Thermal Paint application is proposed for external walls which reduce and reflect
heat. Adequate sunshades are proposed.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
22
9.5. Does the layout of streets & buildings maximize the potential for solar energy devices?
Have you considered the use of street lighting, emergency lighting and solar hot
water systems for use in the building complex? Substantiate with details.
Street lighting will be considered within the complex. For the emergency lighting proper
provision will make by considering available stocks. Solar hot water system will be not
used within complex.
The appurtenant spaces where common lighting is required are proposed to use
unconventional energy.
9.6. Is shading effectively used to reduce cooling/heating loads? What principles have
been used to maximize the shading of Walls on the East and the West and the Roof?
How much energy saving has been effected?
The construction is designed in order to assure maximum of the natural light and
ventilation in the structure.
Thermal Paint application is proposed for external walls which reduce and reflect heat.
Adequate sunshades are proposed.
9.7. Do the structures use energy-efficient space conditioning, lighting and mechanical
systems? Provide technical details. Provide details of the transformers and motor
efficiencies, lighting intensity and air-conditioning load assumptions? Are you using
CFC and HCFC free chillers? Provide specifications.
As it is a Commercial scheme within built provision for space cooling. Energy efficiency
in lighting and mechanical systems will be achieved by:
Purchase of energy efficient appliances
Adjusting the settings and illumination levels to ensure minimum energy used
for desired comfort levels
Installing programmable on/off timers and sensors for low occupancy areas
Use of solar energy for street lights
Use of compact fluorescent lamps and low voltage lighting.
9.8. What are the likely effects of the building activity in altering the micro-climates?
Provide a self assessment on the likely impacts of the proposed construction on
creation of heat island & inversion effects?
The proposed project is of Commercial scheme and will have provision for space
conditioners. Alteration of microclimate is not notable in this case. The glass will be used
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
23
in a way just to provide optimal lights inside. Also the glass used will be energy efficient
to reduce the heat gain inside the building.
Systematic design of buildings in order to assure maximum natural ventilation and light
will be considered to reduce the effect of creation of heat island.
9.9. What are the thermal characteristics of the building envelope? (a) roof (b) external
walls; and (c) fenestration? Give details of the material used and the U-values or the
R values of the individual components.
Wall: 1] 20 mm Cement Plaster + 150 mm BBM + 12 mm Cement
Plaster: U Value – 0.309 BT/Hr. / SqFt °F
Thermal Characteristics of the building envelope:
Terraces will be treated with a layer of brick bat coba for reduction in heat gain
through roof.
Overhang projections and horizontal and vertical elevation band of 0.45m will be
provided around the windows which will be reducing solar heat gain but will assure
maximum natural light and ventilation in the buildings.
External shading is prominently used in the complex it intercepts solar heat before it
reaches the glass/ wall.
External walls are 150 mm with 20 mm plaster on both the sides [cavity wall]. The
external walls of the buildings will be coloured with light slightly tinted colours to
reduce solar heat gain and will reflect heat.
1.10. What precautions & safety measures are proposed against fire hazards? Furnish
details of emergency plans.
The building plan approvals are subject to clearance by the Fire Advisor of the state. He pre
sanction the fire safety measures which will be complied.
1.11. If you are using glass as wall material provides details and specifications including
emissivity and thermal characteristics.
The entire building is designed with appropriate openings to reduce heat energy inside the
building.
1.12. What is the rate of air infiltration into the building? Provide details of how you are
mitigating the effects of infiltration.
The ground surfaces are covered with green patches to have dust control. These Openings
too habitable spaces are adequate just to be functional. The openings are covered with
dust proof, air and water light aluminum glazing.
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
24
1.13. To what extent the non-conventional energy technologies are utilized in the overall
energy consumption? Provide details of the renewable energy technologies used.
Energy Saving Measures
Use energy efficient lamps like T5, CFL, LED.
Use of solar energy to meet hot water demand.
Use of Higher Efficiency transformer.
Use of efficient motors.
Electrical metering and monitoring.
Use of Solar lighting in street lighting.
Timer based switching for common area Lighting
Use of Energy Efficient Transformers, Energy efficient Motors, power factor correction
Panel, metering and monitoring, power distribution systems shall be as specified in
ECBC.
Lighting scheme shall be designed as per the reference illumination levels as mentioned
in ECBC.
Solar Conventional
Description Units
Saved/
year
Energy cost
savings/
Year
Units
Saved/
Day
Units / year Energy cost
/ Year
%
energy
saving/
yr Kw-hr/
year
Rs/year Kw-hr/
Day
Kw-hr/ year Rs/year
Street
Lights/Landscapin
g/Parking/Passage/
Lobby
16,521.36
67,241.94
45.26
165,213.60
672,419.35
10
Street/Parking +
Passage + Lobby +
Staircase area
44,607.67
181,553.23
122.21
148,692.24
605,177.42
30
VFD’s on Lifts
183,960.00
748,717.20
504.00
919,800.00
3,743,586.00
20
Total
Savings/year
(KWH)
245,089.03
997,512.36
1,233,705.84
5,021,182.77
20
Total Savings/
day (Kwh)
671.48
2,732.91
3,380.02
13,756.67
Form 1 & 1A for Proposed Commercial Construction project 'Runwal REGALIA' by M/s Runwal Erectors Pvt Ltd,
At Survey no.153A/1 to 4/1/1 & Survey No.153A/1 to 4/1,Hadapsar, Pune
25
10. Environment Management Plan
The Environment Management Plan (EMP) would consist of all mitigation measures for
each item wise activity to be undertaken during the construction, operation and the entire
life cycle to minimize adverse environmental impacts as a result of the activities of the
project. It would also delineate the environmental monitoring plan for compliance of
various environmental regulations. It will state the steps to be taken in case of emergency
such as accidents at the site including fire.
LIST OF ANNEXURES
I hereby given undertaking that the data and information given in the application and enclosures
are true to the best of my knowledge and belief and I am aware that if any part of the data and
information submitted is found to be false or misleading at any stage, the project will be rejected
and clearance give, if any to the project will be revoked at our risk and cost.
Date: 25/01/2017
Place: Pune
Mr. Pradeep Amrutlal Runwal
M/s Runwal Erectors Pvt Ltd.
41/12, Karve Road, Runwal Plaza, First
Floor,Pune-411004
SR. NO. DESCRIPTION
1. Master Plan
2. Site Location
3. Soil testing Report
4. Baseline Status of Water Quality
5. Baseline Status of Air Quality
6. Baseline Status of Noise Quality
7. Seismic Zoning Map
8. Census Data and Socioeconomic Aspects of Project area
9. Parking Plan
10. Service Layout
ANNEXURES
+98.50 M
OFFICE DROP
OFF POINT BELOW
T
O
E
X
I
T
T
O
M
A
I
N
R
O
A
D
PROJECT
B B'
1
3
.4
0
5.60
26.96
6.17
29.04
7.07
3
4
.
6
6
4.32
22.92
9
.
4
7
2
1
.
6
5
5
.4
5
2
1
.4
2
1
0
.2
3
11.24
4.38
1
.50
7.5
0
2.50
7
.5
0
2
.5
0
1
.50
1
.5
0
1
.2
0
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
+110.4M SECOND FLOOR LVL
+114.6M SERVICE FLOOR LVL
+122.7M FOURTH FLOOR LVL
+128.8M SIXTH FLOOR LVL
+134.9M EIGHTH FLOOR LVL
+137.95M NINTH FLOOR LVL
+141.95M TERRACE LVL
95.6M BASEMENT
FLOOR LVL
+125.75M FIFTH FLOOR LVL
UP DNUPDN
DNUPDN
BANQUET LVL
TERRACE
(TRUSS ROOF)
(2100 x 3080)
DU
CT
SERVICE
LIFT
LIFT
LIFT
LIFT
(2750 x 2050)
(2750 x 2050)
(2750 x 2050)
+117.1M THIRD FLOOR LVL
+131.85M SEVENTH FLOOR LVL
98.8M UPPER GROUND
FLOOR LVL
+106.2 MFIRST FLOOR LVL
+102.0M GROUND FLOOR LVL
(2500 x 2350)
SERVICE
LIFT
(2500 x 2350)
SERVICE
LIFT
(2100 x 3080)
DU
CT
SERVICE
LIFT
LIFT
LIFT
LIFT
(2750 x 2050)
(2750 x 2050)
(2750 x 2050)
BANQUET HALL
SPORTS/ GAMES FLOOR
SHOPS
SHOPS
RESTAURANT /
COFFEE SHOP
HOTEL ENTRANCE LOBBY / PARKING
PARKING
ENTRY LVL
FOR HOTEL
98.8 M
ROOMS
SERVICE FLOOR
BAR/
BUSINESS
CENTRE
ROOMS
ROOMS
ROOMS
ROOMS
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
Annexure 8
CENSUS DATA- 2001
DEMOGRAPHIC STRUCTURE
Sr.
No.
Name
No. of
househo
lds
Total population
Schedu
led
Castes
Schedu
led
Tribes
Literat
es
Main
Worke
rs
Margi
nal
Worke
rs
Non
Work
ers
TP M F
Rural
01 Hinjewadi 1128 5407 3047 2360 548 84 3344 2197 149 3061
02 Sus 450 2138 1120 1018 258 21 1197 1125 148 580
03 Bavdhan
Bu.
425 3125 1668 1477 196 60 1687 1250 120 382
04 Bavdhan
kh.
460 2876 1554 1322 230 20 1524 1450 153 422
05 Chinchwad 76 331 165 166 38 - 191 141 58 132
06 Pimpri 145 722 359 363 31 106 249 357 14 351
07 Pimple
Saudagar
2307 9263 4831 4432 1334 77 7064 3270 57 5936
08 Kalewadi 1050 4851 2495 2356 939 26 3622 1658 39 3154
09 Pimple
Nilakh
1844 8500 4316 4184 732 507 6544 2342 209 5949
10 Morwadi 1623 7342 3914 3428 546 108 504 2256 125 4961
11 Wakad 503 3050 1586 1464 1420 122 1769 1528 125 358
12 Chinchwad
Gaothan
1712 7605 3930 3675 433 53 6462 2383 73 5149
13 Bhatnagar 3099 1330
7
7269 6038 1520 111 9930 4354 211 8742
14 Nigdi
Gaothan
2148 9036 5077 3959 931 124 6192 3145 166 5725
15 Akurdi
Gaothan
1806 8315 4348 3967 2692 122 5337 2686 249 5380
Total 18,776 85,868 45,679 40,209 11,848 1,541 60,916 30,142 1,896 50,282
(2100 x 3080)
DU
CT
SERVICE
LIFT
LIFT
LIFT
LIFT
(2750 x 2050)
(2750 x 2050)
(2750 x 2050)
DUCT
LIFT
LIFT
(2000 x 2000)
(2000 x 2000)
RAMP UP TO UPPER GROUND
PROJECT
61057435
1725
5715
6.00
7.44
7.39
6.00
6.00
6.00
6.00
6.00
6.00
6.00
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
(2100 x 3080)
DU
CT
SERVICE
LIFT
LIFT
LIFT
LIFT
(2750 x 2050)
(2750 x 2050)
DUCT
LIFT
LIFT
(2000 x 2000)
(2000 x 2000)
ENTRY TO B1 LVL
RAMP DOWN TO BASEMENT
PROJECT
+98.50 M
1
3
.4
0
5.60
7
.50
2.50
7
.5
0
2.50
1.5
0
4.38
1
.5
0
2
1
.4
2
5.45
1
0
.2
3
11.24
4.49
18.89
1
9
.1
0
1.80
(2750 x 2050)
6.00
6.98
7.26
6.00
6.00
6.00
6.00
6.00
6.69
6.00
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PROJECT
ENTRY TO B1 LVL
6820
STP LOCATION TRANSFORMER
YARD LOCATION
D.G SET LOCATION
150MMØ FIRE
BRIGADE INLET
CONNECTION
CONNECT TO EXISTING
MUNICIPAL SEWER
CHAMBER BY PUMPING
12110 6685 14425 14410 14420 11390
8515
12970 17455 15440 14360 17985
FIRE BOX-01
0.9 X 0.6 1.2M
FIRE BOX-02
0.9 X 0.6 1.2M
FIRE BOX-03
0.9 X 0.6 1.2M
FIRE BOX-04
0.9 X 0.6 1.2M
FIRE BOX-05
0.9 X 0.6 1.2M
FIRE BOX-06
0.9 X 0.6 1.2M
FIRE BOX-07
0.9 X 0.6 1.2M
FIRE BOX-08
0.9 X 0.6 1.2M
FIRE BOX-09
0.9 X 0.6 1.2M
FIRE BOX-10
0.9 X 0.6 1.2M
FIRE BOX-11
0.9 X 0.6 1.2M
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
SEWER LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
FIRE-FIGHTING
HYDRENT LINE
STORM WATER
LINE
300MM WIDE
STORM CHANEL
300MM WIDE
STORM CHANEL
TO
RAINWATER
HARWESTING
OWC LOCATION
59 SQR AREA
500 KG/DAY CAPACITY
FIRE-FIGHTING HYDRENT
PIPE OUTLET FROM PUMP
ROOM
1200
1390
Ø100mm EXCESS TREATED
WATER LINE CONNECTED TO
EXTERNAL MUNICIPAL STORM
WATER LINE (BY PUMPING)
13220
61057435
1725
5715
DROP
CHAMBER
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
PR
OD
UC
ED
B
Y A
N A
UT
OD
ES
K E
DU
CA
TIO
NA
L P
RO
DU
CT