(I) Basic Information
S.
No. Item Details
1 Name of the Project “Horizons at Wakad”
2 S. No. in the Schedule 8 (a)
3 Proposed capacity/area/length/tonnage to be handled/ command area/ lease
area/ number of wells to be drilled
Total Plot Area = 12365.0 m2
Total Built up Area (FSI) = 16538.00 m2
Total Built up Area (NON FSI) = 14356.26 m2
Total Construction Area = 30894.26 m2
4 New/Expansion/Modernization New
5 Existing Capacity/Area etc. Total Plot Area = 12365.0 m2
Total Built up Area (FSI) = 16538.00 m2
Total Built up Area(NON FSI) = 14356.26 m2
Total Construction Area = 30894.26 m2
6 Category of Project i.e. ‘A’ or ‘B’ Category ‘B’
7 Does it attract the general condition? If
yes, please specify. No
8 Does it attract the specific condition? If
yes, please specify. No
9 Location of Project Wakad- Hinjewadi Road
Plot/Survey/Khasra No. S. No. 127/2A, 127/2B/2, 176/2/1B(Plot no. 1)
, Wakad –Hinjewadi Road
Village Wakad
Tehsil Mulshi
District Pune
State Maharashtra
10 Nearest railway station/airport along
with distance in Kms. Akurdi Railway Station = 4.9 Kms.
11 Nearest Town, city, District
Headquarters along with distance in
Kms.
Pune – 15 Km
12 Village Panchayats, Zilla Parishad,
Municipal Corporation, Local body
PCMC
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
(Complete postal addresses with
telephone nos. to be given)
13 Name of the applicant M/s .Adi Realties
14 Registered Address Survey No. 127/2A,127/2B/2, 176/2/1B (plot
no 1).off Wakad Hinjewadi Road, Wakad,
Pune.
15
Address for correspondence: Survey No. 127/2A,127/2B/2, 176/2/1B (plot
no 1).off Wakad Hinjewadi Road, Wakad,
Pune
Name Mr. Dilip Bhagwani
Designation (Owner/Partner/CEO) Director
Address Survey No. 127/2A,127/2B/2, 176/2/1B (plot
no 1).off Wakad Hinjewadi Road, Wakad,
Pune
Pin code 411057
E- mail [email protected]
Telephone No. 020 – 30683848
Fax No. 020 – 30683848
16 Details of Alternative Sites examined,
if any. Location of these sites should be
shown on a toposheet.
No
17 Interlinked Projects No
18 Whether separate application of
interlinked project has been submitted?
Not Applicable
19 If yes, date of submission Not Applicable
20 If no, reason Not Applicable
21 Whether the proposal involves
approval/ clearance under: if yes,
details of the same and their status to be
given.
(a) The Forest (Conservation) Act,
1980?
(b) The Wild life (Protection) Act
1972?
The C.R.Z. Notification, 1991?
Not Applicable
22 Whether there is any Government
Order / Policy relevant/ relating to the
site?
Not Applicable
23 Forest Land involves (hectares) Not Applicable
24 Whether there is any litigation pending Not Applicable
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
against the project and/ or land in which
the project is proposal to be set up?
a) Name of the Court
b) Case No.
c) Orders / directions of the Court, if
any and its relevance with the proposed
project.
(II) Activity
1. Construction, operation or decommissioning of the Project involving actions, which
will cause physical changes in the locality (Topography, land use, changes in water
bodies, etc.)
Sr.
No
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
1.1 Permanent or temporary
change in land use, land cover
or topography including
increase in intensity of land
use (with respect to local
land use plan)
No Basically land is barren land. The proposed
project site is designated for the intended
purpose and the necessary change in the land
use of the plot area measuring 12365.0 m2
has already been affected by converting it for
residential use.
SITE LOCATION PLAN IS ATTACHED
AS AN ANNEXURE : III
1.2 Clearance of existing land, vegetation and buildings?
No Not Applicable
1.3 Creation of new land uses? No Not Applicable
1.4 Pre-construction investigations
e.g. bore houses, soil testing? No Not Applicable
1.5 Construction works?
Yes
• FSI area :16538.00 m2
• Non FSI :14356.26 m2
30894.26 m2will be total built up area.
MASTER PLAN IS ATTACHED AS
AN ANNEXURE: V
1.6 Demolition works? No Not Applicable
1.7 Temporary sites used for construction works or housing
of construction workers?
Yes During construction total 50 Nos. of workers.
1.8 Above ground buildings,
structures or Earth works including linear structures, cut
Yes 30745.05m2 (FSI 16531.69 m2 + NON FSI
14213.36m2) will be built up area for residential purpose. Excavated material
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
and fill or excavations during construction will be used for leveling
of land.
1.9 Underground works including
mining or tunneling? No Not Applicable
1.10 Reclamation works? No Not Applicable
1.11 Dredging? No Not Applicable
1.12 Offshore structures? No Not Applicable
1.13 Production and manufacturing
processes? No Not Applicable
1.14 Facilities for storage of goods
or materials? Yes
Temporary shed will be constructed for the
storage of the construction material.
1.15
Facilities for treatment or
disposal of solid waste or
liquid effluents?
Yes
A) SOLID WASTE MANAGEMENT
a) During Construction phase –
Excavated material will be used for
backfilling and landscape.
During Operation Phase –
Total population of the residential scheme is
–1452 Nos.
1) Total Quantity of Solid Waste =
631.90 kg/day
2) Total quantity of Wet Waste = 385.75
kg/day.
3) Total quantity of Dry Waste = 246.15
Kg/day.
Biodegradable and non biodegradable waste will be segregated. Dry waste will be sold
out.
Wet waste will be treated by ‘Organic waste
Convertor’ for composting.
(ANNEXURE NO- XII: OWC- Solid
Waste Management)
B) WATER MANAGEMENT –
I) During Construction Phase:
Water Requirement – 30 m3/day
source - Tankers
II) During Operation Phases: Source –PCMC
WATER DEMAND : Total Water demand is 198.05 m3/day
• Total Water demand is 198.05m3/day.
• Domestic for residence is 119.70m3/day.
• Flushing for residence is - 59.85m3/day.
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
• Domestic for commercial -2.44m3/day.
• Flushing for commercial is 3.04m3/day
• Landscaping is -10.0m3/day.
• Swimming pool -3.0 m3/day
(ANNEXURE VIII – Water Balance
Statement )
1.16 Facilities for long term
housing of operational
workers?
No Not Applicable
1.17 New road, rail or sea traffic
during construction or
operation?
No Not Applicable
1.18 New road, rail, air waterborne
or other transport infrastructure
including new or altered routes
and stations, ports, airports
etc?
No Not Applicable
1.19 Closure or diversion of
existing transport routes or
infrastructure leading to
changes in traffic
movements?
No Not Applicable
1.20 New or diverted transmission
lines or pipelines?
No Not Applicable
1.21 Impoundment, damming,
culverting, realignment or other changes to the hydrology
of watercourses or aquifers?
No Not Applicable
1.22 Stream crossings? No Not Applicable
1.23 Abstraction or transfers of
water from ground or surface waters?
Yes During Construction phase Bore well /
Tanker water will be used for the construction purpose.
1.24 Changes in water bodies or the land surface affecting drainage
or run-off?
No Not Applicable
1.25 Transport of personnel or
materials for construction, operation or
decommissioning?
Yes Approx. 9 trucks per day for Material
transport. Workers through public transport
1.26 Long-term dismantling or
decommissioning or
restoration works?
No Not Applicable
1.27 Ongoing activity during
decommissioning which could
have an impact on the
environment?
No Not Applicable
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
1.28 Influx of people to an area in
either temporarily or permanently?
Yes INFLUX DURING CONSTRUCTION:
During construction approximately 50 nos. workers.
INFLUX DURING OPERATION:
During operation influx of approximately
1452 Nos. of persons are going to reside in
the Residential and commercial complex.
1.29 Introduction of alien species? No Not Applicable
1.30 Loss of native species or
genetic diversity?
No Not Applicable
1.31 Any other actions? No Not Applicable
2. Use of Natural resources for construction or operation of the Project (such as land,
water, materials or energy, especially any resources which are non-renewable or in
short supply):
Sr.
No.
Information/checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
2.1 Land especially undeveloped or
agricultural land (ha)
Yes
Undeveloped land of about 12365.0 m2
The proposed development has been planned
on Non Agriculture land.
2.2 Water (expected source &
competing users) unit: KLD
Yes WATER MANAGEMENT –
I) During Construction Phase:
Water Requirement –30 m3/day
source –Tankers/Bore well
II) During Operation Phases:
Source – PCMC
WATER DEMAND :
Total Water demand is 198.05 m3/day
• Total Water demand is 198.05m3/day.
• Domestic for residence is 119.70m3/day.
• Flushing for residence is - 59.85m3/day.
• Domestic for commercial -2.44m3/day.
• Flushing for commercial is 3.04m3/day
• Landscaping is -10.0m3/day.
• Swimming pool -3.0 m3/day
(ANNEXURE VIII – Water Balance
Statement )
2.3 Minerals (MT) No Not Applicable
2.4 Construction material - Stone, Yes Companies authorized approved local
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
Aggregates, Sand/Soil
(expected source-MT)
vendors.
2.5 Forests and timber (source –
MT)
No Not Applicable
2.6 Energy including electricity and
fuels (source, competing users) Unit: fuel (MT), energy (MW)
Yes SOURCE – Maharashtra State Electricity
Distribution Company Limited (MSEDCL)
During Construction Phase:
Load – 100 KW
D.G. Set - 100 KVA x 1No.
During Operation Phase:
A)Total Connected Load –1850KW
B)Maximum Demand – 1290 KW
c) Transformer –630KVA x2 Nos
d)DG Set-125 KVA x 1No.
e) Fuel Consumption / hr- for 125 KVA 19
lit./hr
2.7 Any other natural resources
(use appropriate standard units)
No Not Applicable
3. Use, storage, transport, handling or production of substances or materials, which could
be harmful to human health or the environment or raise concerns about actual or
perceived risks to human health.
Sr.
No. Information/Checklist
confirmation
Yes /
No
Details thereof (with approx. quantities/
rates, wherever possible) with source of
information data
3.1 Use of substances or materials,
which are hazardous (as per
MSIHC rules) to human health
or the environment (flora,
fauna, and water supplies)
No Not Applicable
3.2 Changes in occurrence of
disease or affect disease vectors
(e.g. insect or water borne
diseases)
No Not Applicable
3.3 Affect the welfare of people
e.g. by changing living
conditions?
No It can help in improving the living standards
of that area.
3.4 Vulnerable groups of people
who could be affected by the
project e.g. hospital patients,
children, the elderly etc.,
No Not Applicable
3.5 Any other causes No Not Applicable
4. Production of solid wastes during construction or operation or decommissioning
(MT/month)
Sr.No. Information/Checklist Yes/ Details thereof (with approx.
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
confirmation No quantities/rates, wherever possible) with
source of information data
4.1
4.2
Soil, overburden or mine
wastes
Municipal waste (domestic
and/or commercial wastes)
Yes
Yes
Excavated material during construction will
be used for leveling of land.
SOLID WASTE MANAGEMENT
During Operation Phase –
Total population of the residential scheme is
–1452 Nos.
1) Total Quantity of Solid Waste =
631.90 kg/day
2) Total quantity of Wet Waste = 385.75
kg/day.
3) Total quantity of Dry Waste = 246.15
Kg/day.
Biodegradable and non biodegradable waste
will be segregated. Dry waste will be sold
out. Wet waste will be treated by ‘Organic
waste Convertor’ for composting.
ANNEXURE – XII -Organic Waste
Convertor- Solid Waste Management
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
No Not Applicable
4.4 Other industrial process wastes No Not Applicable
4.5 Surplus product No Not Applicable
4.6 Sewage sludge or other sludge
from effluent treatment
Yes Sewage Treatment Plant will be provided for
treatment of domestic effluent. STP details
are enclosed.
Refer Annexure – XI Sewage Treatment
Plant – Schematic Plan & Details
4.7 Construction or demolition
wastes
Yes Construction debris will be used for leveling /
backfilling etc. for landscapes, Internal roads
etc.
4.8 Redundant machinery or
equipment
No Not Applicable
4.9 Contaminated soils or other
materials
No Not Applicable
4.10 Agricultural waste No Not Applicable
4.11 Other solid wastes No Not Applicable
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
Sr.No. Information/Checklist
confirmation
Yes/
No
Details thereof (with approx.
quantities/rates, wherever possible) with
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
source of information data
5.1 Emissions from combustion of fossil fuels from stationary or
mobile sources
No Not Applicable
5.2 Emissions from production
processes
No Not Applicable
5.3 Emissions from materials
handling including storage or transport
No Not Applicable
5.4 Emissions from construction activities including plant and
equipment
Yes There will be temporary emission from construction equipments (mobile Source)
5.5 Dust or odors from handling of
materials including construction materials, sewage
and waste
Yes As per Environment Management Plan refer
ANNEXURE XVI
5.6 Emissions from incineration of
waste
No Not Applicable
5.7 Emissions from burning of
waste in open air (e.g. slash
materials, construction debris)
No Not Applicable
5.8 Emissions from any other
sources
No Not Applicable
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
6.1 From operation of equipment
e.g. engines, ventilation plant,
crushers
Yes Sources of noise Pollution during
construction phase are machinery like
compressor, Compactors, Concrete Plant,
Cranes and transportation materials.
During operation phase DG sets will be
provided with Canopy to reduce noise.
6.2 From industrial or similar
processes
No Not Applicable
6.3 From construction or
demolition
Yes As per Environment Management Plan
6.4 From blasting or piling No Not Applicable
6.5 From construction or
operational traffic
Yes As per Environment Management Plan
6.6 From lighting or cooling systems
No Not Applicable
6.7 From any other sources No Not Applicable
7. Risks of contamination of land or water from releases of pollutants into the ground or
into sewers, surface waters, groundwater, coastal waters or the sea:
Sr.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approx.
quantities/rates, wherever possible) with
source of information data
7.1 From handling, storage, use or No Not Applicable
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
spillage of hazardous materials
7.2 From discharge of sewage or other effluents to water or the
land (expected mode and place of discharge)
No Sewage will be treated and reused for flushing & gardening.
Hence there is no risk of contamination due to release of sewage.
7.3 By deposition of pollutants emitted to air into the land or
into water
No Not Applicable
7.4 From any other sources No Not Applicable
7.5 Is there a risk of long term build
up of pollutants in the
environment from these
sources?
No Not Applicable
8. Risk of accidents during construction or operation of the Project, which could affect
human health or the environment
Sr.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approx.
quantities/rates, wherever possible) with
source of information data
8.1 From explosions, spillages, fires
etc from storage, handling, use
or production of hazardous
substances
No Not Applicable
8.2 From any other causes Yes There is a risk of accident during
construction however proper construction
safety measures will be taken
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g.
floods, earthquakes, landslides, cloudburst etc)?
Yes Floods and landslides are not expected in the
area. Earthquake proneness: the area falls
under Zone III as per IS 1893-2002. Hence
relevant design parameters as per zone III have been considered for RCC design of the
building. Adequate earthquake proof RCC design is adapted.
ANNEXURE IX - Seismic Zoning Map Of
India
9. Factors which should be considered (such as consequential development) which could
lead to environmental effects or the potential for cumulative impacts with other
existing or planned activities in the locality.
Sr.
No.
Information/Checklist
confirmation
Yes/
No
Details thereof (with approx.
quantities/rates, wherever possible)
with source of information data
9.1 Lead to development of supporting.
Facilities, ancillary development or
development stimulated by the
project which could have impact on
the environment e.g.:
• Supporting infrastructure (roads,
Yes 1) Power supply is available.
2) Sewage Treatment Plant will be
provided hence there will not additional
load on Municipal Sewage treatment.
3) Solid Waste Management facility
will be provided.
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
power supply, waste or waste water
treatment, etc.) • Housing development
• Extractive industries • Supply industries
• Other
4) Adequate parking facility available
within campus.
Housing development
9.2 Lead to after-use of the site, which
could have an impact on the
environment.
No Not Applicable
9.3 Set a precedent for later
developments
No Not Applicable
9.4 Have cumulative effects due to proximity to other existing or planned
projects with similar effects
No Not Applicable
(III) Environmental Sensitivity
Sr.
No. Areas
Name/
Identity
Aerial distance (within 15 km.)
Proposed project location boundary
1 Areas protected under international
conventions, national or local
legislation for their ecological,
landscape, cultural or other related value
No Not Applicable
2 Areas which are important or
sensitive for ecological reasons -
Wetlands, watercourses or other
water bodies, coastal zone,
biospheres, mountains, forests
No Not Applicable
3 Areas used by protected, important
or sensitive species of flora or
fauna for breeding, nesting,
foraging, resting, over wintering,
migration
No Not Applicable
4 Inland, coastal, marine or
underground waters
No Not Applicable
5 State, National boundaries No Not Applicable
6 Routes or facilities used by the
public for access to recreation or other tourist, pilgrim areas
No
Not Applicable
7 Defense installations No Not Applicable
8 Densely populated or built-up area No Not Applicable
9 Areas occupied by sensitive man-
made land uses (hospitals, schools,
places of worship, community
facilities)
No Not Applicable
10 Areas containing important, high
quality or scarce resources
No Not Applicable
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
(Ground water resources, surface
resources, forestry, agriculture, fisheries, tourism, minerals)
11 Areas already subjected to pollution or environmental damage. (Those
where existing legal environmental standards are exceeded)
No Not Applicable
12 Areas susceptible to natural hazard which could cause the project to
present environmental problems
(Earthquakes, subsidence,
landslides, erosion, flooding or
extreme or adverse climatic
conditions)
No Not Applicable
(IV) Proposed Terms of Reference for EIA studies.
EIA not required as project is under B-2 Category
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
�
�
�
�
I hereby given undertaking that the data and information given in the application and enclosures
are true to the best of my knowledge and belief and I am aware that if any part of the data and
information submitted is found to be false or misleading at any stage, the project will be rejected
and clearance give, if any to the project will be revoked at our risk and cost.
________________________
Signature of the applicant
With Name and Full Address
(Project Proponent/ Authorized Signatory)
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
FORM-1 A
(Only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIRONMENTAL IMPACTS
1. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1 Will the existing land use get significantly altered from the project that is not consistent
with the surroundings? (Proposed land use must conform to the approved Master Plan /
Development Plan of the area. Change of land use if any and the statutory approval from
the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding
features of the proposed site (within 500 meters) and (iii) the site (indicating levels &
contours) to appropriate scales. If not available attach only conceptual.
The proposed land use is in conformity with the DP of the area
ANNEXURE NO. I- AERIAL VIEW ANNEXURE NO. II- D.P. PLAN
ANNEXURE NO. III- SITE LOCATION MAP ANNEXURE NO.IV-CONTOURE MAP
1.2
List out all the major project requirements in terms of the land area, built up area, water
consumption, power requirement, connectivity, community facilities, parking needs etc.
Total Area of the plot 12365.0 m2
Total Built up Area (FSI)
16538.00 m2
Total Built up Area (Non FSI) 14356.26 m2
Total Construction Area 30894.26 m2
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
AREA STATEMENT
Sr.No. Details Area m2
1 Plot area 12365.00
2 Road widening Area 1491.74 + 116.75
3 Reservation --
4 Well 38.48
5 Total 10718.03
6 Open space 10% 1071.95
7 Net plot area 9646.08
8 Addition for
a Road area 1491.74 + 1444.26 + 116.75 3052.75
b T.D.R. 3841.77
9 Total plot area 16540.60
10 F.A.R. Permissible 1
11 Permissible B/up area 16540.60
12 Existing B/up area Residential 13846.13
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
Sr.No. Details Area m2
13 Proposed B/up area residential 1967.41
14 Proposed B/up area Commercial 402.30
15 Excess balcony 315.85
16 Proposed balcony 325.43
17 Existing balcony 2422.79
18 Total B/up area proposed 16531.69
TOTAL CONSTRUCTION AREA
Sr. No Description Area in m2
1. F.S.I. Area 16538.00
2. Non F.S.I
Balcony 2749.91
Passage 2086.9
Staircase 1201.14
Lift & Lift Machine Room 105.48
Terrace 2967.66
Refuge Area 422.53
Connecting Slab 68.77
OHT Area 210
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
UGT Area 300
OWC Area 29.80
STP Area 40.38
Transformer Room 52.65
Security Cabin 20
Clubhouse 301.39
Covered Parking within bldg. 1900.65
Elevated Open space 1072
Covered parking Other than bldg. 670
Treated water tank 7.00
Commercial Top Terrace 150
Total Non F.S.I. 14356.26
Construction Built Up Area
Total F.S.I. Area + Total Non F.S.I.
30894.26
TENEMENT STATEMENT
Sr.
No. Name of BUILDING
No. of
Floor
Type No. of
Tenements Population
2 BHK 3BHK
1. BUILDING- A P+11 21 22 43 215
2. BUILDING – B P+12 47 - 47 235
3. BUILDING – C P+12 47 - 47 235
4. BUILDING – D P+12 47 - 47 235
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
5. BUILDING – E P+12 47 - 47 235
6 BUILDING – F G+9 35 - 35 175
9. Total ( Residential )
266 1330
10.
Commercial
Area (
402.30
m2 )
Building F
(216.05m2)
Ground
floor
No. of shops –
6Nos. 72
Convenient
shopping
(186.25m2)
Ground
& 1st
floor
No. of shops-9Nos.
50
11. Total Population (Residential + Commercial) 1452
1.3 WATER REQUIREMENT
I) During Construction Phase:
Water Requirement –30m3/day
source –Tankers/Borewell
II) During Operation Phases:
Source –PCMC
WATER DEMAND :
• Source - Pimpri-Chinchwad Municipal Corporation
• Total Water demand is - 198.05 m3/day.
• Domestic for residence is - 119.70 m3/day.
• Flushing for residence is - 59.85 m3/day.
• Domestic for commercial -2.44 m3/day.
• Flushing for commercial is - 3.04 m3/day
• Landscaping is -10.0 m3/day.
• Swimming pool -3.0 m3/day
WATER BALANCE STATEMENT
Total No. of Tenements – 266 Nos. Total Populations –1330 Nos.
Total Comm. Area – 402.30 m2 Total Population- 122 Nos.
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
Sr.
No. Description
Water
Requirement Loss
Sewage
Generation
Water Use
Fresh Recycled
1
Domestic for residence
(@ 90 LPCD ) no. of
persons 1330
119.70 11.97 107.73 119.70 -
2
Flushing for residence
(@ 45 LPCD ) no. of
persons 1330
59.85 5.985 53.865 - 59.85
3
Domestic for Commercial
(@ 20 LPCD ) no. of
persons 122
2.44 0.24 2.20 2.44 -
4
Flushing for commercial
( @ 25 LPCD ) no. of
persons 122
3.05 0.31 2.74 - 3.05
6 Landscaping 10.0 0.0 0.0 - 10.0
7. Swimming pool 3.0 0.0 0.0 3.0 -
TOTAL 198.05 185.05 166.54 125.15 72.90
STP CAPACITY – 180 m3/day
(ANNEXURE VIII – WATER BALANCE STATEMENT)
POWER REQUIREMENT :
SOURCE -MSEDCL. (Maharashtra State Of Electricity Distribution Company Ltd.)
During Construction Phase:
Total Load - 100KW
b) D G Set – 100 KVA x 1 No
During Operation Phase:
• A)Total Connected Load –1850KW
• B)Maximum Demand – 1290 KW
• c) Transformer –630KVA x2 Nos
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
• d)DG Set - 125 KVA x 1No.
• Fuel Consumption / hr -for 125 KVA 19 lit./hr
(ANNEXURE XIV ELETRICAL CALCULATION, D.G. CHART & LOCATION & DETAILS)
PARKING STATEMENT:
Approximately 145 Nos. of four wheeler, 566 Nos. of two wheelers & 546 Nos. cycles are proposed
in the residential & commercial complex Internal circulation pattern will be so as to avoid any
congestion within the complex. Parking space will be allotted within the campus.
(REFER ANNEXURE VII– PARKING AND TRAFFIC MANAGEMENT PLAN)
1.1.What are the likely impacts of the proposed activity on the existing facilities adjacent to the
proposed site? (Such as open spaces, community facilities, details of the existing land use and
disturbance to the local ecology).
Although it is a construction activity, its impact on air quality, water quality, noise and soil will not be
notable. As a matter of fact this activity will have positive impact, on socio-economic culture of people
residing in the vicinity of the proposed area. There will not be any disturbance to the local ecology as
the selected site for the construction is a barren land.
The project site and the surrounding area are not developed. The plantations, which would be grown in
the residential area, will be helpful in increasing green cover of the area. This would also increase
avifauna in the area.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence & instability?
(Details of soil type, slope analysis, vulnerability to subsidence, seismicity, etc may be given
Generally, soil types found in Pune district are black, copper, red, & paddy soil. Soil blends
Of variable properties are modified by sand, gravel, lime salts, & other ingredients.
(REFER ANNEXURE IV - CONTOUR PLAN)
1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour map
showing the natural drainage near the proposed project site)
Not Applicable
(REFER ANNEXURE IV- CONTOUR PLAN)
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
1.6 What are the quantities of earthwork involved in the construction activity cutting, filling,
reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials
from outside the site etc.)?
Excavated material during construction will be used for leveling of land at site.
1.7 Give details regarding water supply, waste handling etc during the construction Period.
Total water requirement during construction phase will be approximately 30 m3/day for domestic use
for the workers working/dwelling on the site. The construction water requirement will be in addition to
this. The source will be Bore well. The non biodegradable solid waste will be segregated and will send
to kabadi. The wet waste will be treated by ‘Organic Waste Convertor”.
A septic tank and soak pit will be constructed for temporary shelters of construction workers. The
construction debris and cut and fill waste will be recycled for road construction.
1.8
Will the low-lying areas & wetlands get altered? (Provide details of how low lying and wetlands
are getting modified from the proposed activity). Not Applicable.
1.9 Whether construction debris & waste during construction cause health hazard? (Give quantities
of various types of wastes generated during construction including the construction labor and the
means of disposal)
Construction debris and waste during construction will not cause health hazard. The natural depression
on site will be lined and converted into water bodies which would add to passive cooling and will act as
Rainwater Harvesting devices.
Construction debris generated will be used for development of landscape.
2. WATER ENVIRONMENT
2.1 Give the total quantity of water requirement for the proposed project with the breakup of
requirements for various uses. How will the water requirement be met? State the sources &
quantities and furnish a water balance statement.
The proposed source of water will be PCMC. The underground tank is provided for the filtered water
storage tank. Water may be pumped from proposed underground tank to overhead tanks on all building
through a hydro pneumatic tank filling system. It will be then distributed to overhead tank on terrace
building.
WATER REQUIREMENT
II) During Construction Phase:
Water Requirement –30 m3/day
source –Tankers/Borewell
II) During Operation Phases:
Source – PCMC
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
WATER DEMAND :
• Total Water demand is - 198.05 m3/day.
• Domestic for residence is - 119.70 m3/day.
• Flushing for residence is - 59.85 m3/day.
• Domestic for commercial -2.44 m3/day.
• Flushing for commercial is - 3.04 m3/day
• Landscaping is -10.0 m3/day.
• Swimming pool -3.0 m3/day
WATER BALANCE STATEMENT
Total No. Of Tenements – 266 Nos. Total Populations –1330 Nos.
Total Comm. Area – 402.30 M2 Total Population- 122 Nos.
Sr.
No. Description
Water
Requirement Loss
Sewage
Generation
Water Use
Fresh Recycled
1
Domestic For Residence
(@ 90 Lpcd ) No. Of
Persons 1330
119.70 11.97 107.73 119.70 -
2
Flushing For Residence
(@ 45 Lpcd ) No. Of Persons 1330
59.85 5.985 53.865 - 59.85
3
Domestic For Commercial
(@ 20 Lpcd ) No. Of Persons 122
2.44 0.24 2.20 2.44 -
4
Flushing For Commercial
( @ 25 Lpcd ) No. Of
Persons 122
3.05 0.31 2.74 - 3.05
6 Landscaping 10.0 0.0 0.0 - 10.0
7. Swimming Pool 3.0 0.0 0.0 3.0 -
Total 198.05 185.05 166.54 125.15 72.90
(REFER ANNEXURE VIII – WATER BALANCE CHART)
2.2 What is the capacity (dependable flow or yield) of the proposed source of water?
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
The source of water during operation is PCMC.
2.3 What is the quality of water required, in case, the supply is not from a municipal source?
(Provide physical, chemical, biological characteristics with class of water quality)
The Source of water will be available from tanker which will accomplish the water requirement for this Residential complex.
2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give
the details of quantities, sources and usage)
About 72.90 m3/day of water will be recycled for flushing at Residential building & landscaping.
2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on
other existing uses and quantities of consumption)
Not Applicable
2.6 What is the incremental pollution load from wastewater generated from the proposed activity?
(Give details of the quantities and composition of wastewater generated from the proposed
activity)
There will not be any incremental pollution load from the proposed activity. The Quantity of sewage is
about 88.56% of domestic water consumption. The wastewater-generated from the proposed activity
shall be domestic. Total water will be treated and recycled within the site to the extent possible
2.7 Give details of the water requirements met from water harvesting? Furnish details the facilities
created?
RUN-OFF CALCULATION
RUNOFF CALCULATIONS
Total Plot Area= 10710.8 Sq.m.
Annual Average Rain fall= 500 mm.
Run off
Coefficients
Concrete= 0.9
Roads= 0.7
Landscape= 0.5
Podium/Concrete= 0.9
Other areas&Open Parking= 0.7
Annual Surface
Run off
Annual Runoff in
m3
Roof Top Area
A & F Bldg. 529.36 Sq.m. 238212 238.212
B,C,D&E Bldg. 1071.08 Sq.m. 481986 481.986
Commercial Area 207.9 Sq.m. 93555 93.555
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
Services 712.9 Sq.m. 320805 320.805
Internal Road Area 4112.39 Sq.m. 1439336.5 1439.3365
Landscape Area 2719.65 Sq.m. 679912.5 679.9125
Podium Area 364 Sq.m. 163800 163.8
Rest Area & Open Parking
Area 993.56 Sq.m. 347746 347.746
Roof Top Area
Surface Run
Off Per day
Total Run
Off Per Day
(M3)
A & F Bldg. 529.36 Sq.m.
B,C,D&E Bldg. 1071.08 Sq.m. 5.9553
Commercial Area 207.9 Sq.m. 12.04965
Services 712.9 Sq.m. 2.338875
Internal Road Area 4112.39 Sq.m. 8.020125
Landscape Area 2719.65 Sq.m. 35.9834125
Podium Area 364 Sq.m. 16.9978125
Rest Area & Open Parking
Area 993.56 Sq.m. 4.095
Total = ( m3 ) 8.69365 94.133825
INTENSITY OF PRECIPITATION
• Average Daily Rainfall = 55 mm
• Total no. of pits is 9 Nos.
• Size of pit 1.0 X 1.0 X 1.0 M. Depth and 60 m. deep bore well.
(REFER ANNEXURE X – RAIN WATER HARVESTIG & STORM WATER MANAGEMENT
PLAN )
2.8 What would be the impact of the land use changes occurring due to the proposed project on the
runoff characteristics (quantitative as well as qualitative) of the area in the post construction
phase on a long term basis? Would it aggravate the problems of flooding or water logging in any
way?
The proposed land use is in conformity with the Development Plan so there will not be any land use
change. The runoff from the project site will be used for the aquifers.
The storm water drains of the area are proposed to be connected to the future drain line which is future
development along the project.
2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of ground
water; give the details of ground water table, recharging capacity, and approvals obtained from
competent authority, if any)
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
A comprehensive Rainwater Harvesting System will be implemented in the form of aquifer recharge.
The water table in the area is likely to increase due to the proposed system with no adverse effects
envisage.
2.10 What precautions/measures are taken to prevent the run-off from construction activities
polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse
impacts)
The runoff from the site will be filtered mechanically and present rate of discharge will be retained
without any incremental pollution load from the site.
2.11 How is the storm water from within the site managed?(State the provisions made to avoid
flooding of the area, details of the drainage facilities provided along with a site layout indication
contour levels)
The storm water from the site will be harvested in the form of recharging the aquifers. Recharge pits will be created on site.
2.12 Will the deployment of construction laborers particularly in the peak period lead to unsanitary
conditions around the project site (Justify with proper explanation)
During construction phase numbers of workers will be 40.Municipal solid waste generated during
construction will be composted at site. Temporary Toilets, Septic tank and soak pits are provided during
construction phase. This will not lead unsanitary conditions at the site.
2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give
details of the quantities of wastewater generation, treatment capacities with technology &
facilities for recycling and disposal)
The sewage will be collected from 266 Nos. tenements. The quantity of sewage is about 88.56 % of
domestic water consumption. The waste water generated from the proposed activity shall be domestics. Sewage will be treated in the sewage treatment plant of 180 m3/day. The treated sewage will be
recycled for flushing & gardening.
(REFER ANNEXURE XI – SEWAGE TREATMENT PLANT- SCHEMATIC PLAN &
DETAILS)
Design Basis
Capacity of STP :180 m3 /d Average
Design Parameters with Inlet & Outlet Characteristics:
RAW WATER
CHACTERISTICS
TREATED WATER
CHARACTERISTICS
pH 5.5 - 9 5.5 - 9
Total suspended solids < 300 ppm < 10 ppm
C.O.D < 500 ppm < 50 ppm
B.O.D < 300 ppm < 20 ppm
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
Oil & Grease < 20 ppm < 10 ppm
Copper (as Cu) < 3 ppm < 3 ppm
Fluoride (as F) < 15 ppm < 15 ppm
Iron (as Fe) < 3 ppm < 3 ppm
Zinc (as Zn) < 15 ppm < 15 ppm
PROCESS DESCRIPTION
The Sewage Treatment System being proposed by us is SMBR Based technology. Suspended Media
Bio Reactor (SMBR)(MMBR) is emerging as a clear choice for STP’s all across the sector for various
reasons like:
Less Area Requirement.
No Sludge Recycle, monitoring of F/M ratio etc. hence easy to operate Minimal moving parts thus
lesser maintenance requirements.Flexibility to correct the performance by just adding the media in a
reactor or increasing the Air quantity. No more costly replacements. The STP being proposed by us has
following steps incorporated as a part of our system
Bar Screen: The System is provided with a Bar Screen to remove the objects like plastics, pouches,
metal pieces etc.
Equalization: Equalization of effluents is essential to make a uniform mixture for further treatment. To
achieve this air is bubbled in the first chamber through air grid. In smaller systems this is achieved by
taking help of turbulence of the incoming stream.
SMBR (Suspended Media Bio Reactor) (MMBR) : This is a very important part of treatment process
where Oxygen from the air is transferred to the liquid with the help of Air Grid.
A specially designed plastic media are filled in the tank (to the required level). During the treatment
this media facilitates attached growth. This also ensures that the required MLSS (Mixed Liquor
Suspended Solids) are maintained at the required level (3500 – 5000 p.m.). The residence time of the
reactor tank is considered in such a way that there is enough time for treatment in the reactor. A blower
is provided to supply air to the Grid.
Settling Chamber: After Solid Liquid separation in SMBR reactor, the liquid is taken in the Settling
Chamber. The Settling Chamber is provided with Tube Packs in the top section of the tank. The
Bottom portion is with sufficient Slope to ensure the accumulation of suspended solids. There are no
moving parts in this section.
Sludge Handling: A Sludge pump is provided to periodically remove the Solids accumulated at the
bottom of Settler Chamber. The Sludge is pumped to a Sludge Holding tank which is provided to hold
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
the sludge in rainy season. The Sludge holding tank size is usually designed considering 2-3 months
storage. From sludge holding tank, concentrated sludge will be pumped to proposed Filter Press .
Filtrated from Filter press will be recycled in Equalization tank. The Sludge Holding tank is provided
by Air pipe to facilitate complete removal of sludge and to tackle odour nuisance if it occurs.
Filtration : The water from the settling chamber is taken clear water tank from where it is pumped to
set of 2 filters in series. The first filter has a specific combination of media like Gravels, Pebbles,
Filtration Sand to ensure proper filtration. The next filter has Activated Carbon media of higher (1200)
Iodine Value which absorb colour & odour of filtered water. The Carbon beds also ensures further
polishing of BOD. Backwash water from both filters will be recycled in Equalization Tank.
Disinfection: Ozonization System will be provided after ACF in Treated Water Tank for disinfection
of treated sewage water.
Treated water achieved out of such treatment is suitable for gardening as well as toilet flushing.
2.2.14 What on-site facilities are provided for the collection, treatment & safe disposal of sewage?
(Give details of the quantities of wastewater generation, treatment capacities with technology
& facilities for recycling and disposal)
The sewage will be collected from 266 Nos. tenements. The quantity of sewage is about 88.56 % of
domestic water consumption. The waste water generated from the proposed activity shall be
domestics. Sewage will be treated in the sewage treatment plant of 180 KLD. The treated sewage will
be recycled for flushing & gardening.
3 VEGETATION
3.1 Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem
with its unique features, if any)
There will not be any threat of the project to the biodiversity. The selected site for project is a barren
land. The project proponents have proposed a landscape development plan, which includes planting
of flowering and shady trees, shrubs and lawn within the plot.
3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide a
detailed account of the trees & vegetation affected by the project
No. Selected site is a barren land. However, the project site will cover the flowering plants, lawns.
The open spaces inside the plot will be suitably landscaped and covered with Vegetation.
3.3 What are the measures proposed to be taken to minimize the likely impacts on important site
features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc
along with a layout plan to an appropriate scale)
The site presently is a barren land with no important site features. Addition to this landscape is
proposed.
LANDSCAPING AND TREE PLANTATION
Total Green belt area will be 1072.0 m2
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
Total Nos. of Trees 110 Nos.
Landscape design is in such a way that,
1) Maximum Green Area covers the site.
2) Native Trees species are used which have water retaining capacity
(REFER ANNEXURE VII – LANDSCAPE PLAN & LIST OF TREES)
4. FAUNA
4.1 Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of
barriers for their movement? Provide the details.
No
4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.
No
4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna
The proposed project will not have any adverse impact on the flora or fauna.
5. AIR ENVIRONMENT
5.1 Will the project increase atmospheric concentration of gases & result in heat islands? (Give
details of background air quality levels with predicted values based on dispersion models
taking into account the increased traffic generation as a result of the proposed constructions)
As this will be a Residential complex, air pollution is not expected to be a major concern.
5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases?
Give details in relation to all the meteorological parameters.
During construction phase, suspended particulate matter, dust, will be the main pollutant, which
could be generated from site development activities and movement of vehicles. Odorous fumes or
hazardous gases generation is not expected. Concentration of SO2, NO2 and CO may rise a little due
to traffic. Proper upkeep and maintenance of vehicles, sprinkling of water on roads and construction
site and providing sufficient vegetation all around the plant site are some of the measures that would
reduce the impact during construction phase.
5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present
level of transport infrastructure and measures proposed for improvement including the traffic
management at the entry & exit to the project site.
Residential Parking –
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
Approximately 145 Nos. of four wheeler, 566 Nos. of two wheelers & 546 Nos. of cycle proposed
within the complex will ensure no traffic congestion outside the campus. Measures proposed for
traffic management at the entry and exit to the project site are: Maintaining flow of traffic for
approach roads Entry and Exit points carefully placed so as not to disturb this flow. Easy movement
of fire tender in and around the complex ensuring accessibility to every building.
(REFER ANNEXURE VII - PARKING AND TRAFFIC MANAGEMENT PLAN)
5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian
pathways, footpaths etc., with areas under each category.
Area of Internal road will be 6 m wide also serve as pedestrian pathway and footpath.
5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and
the measures proposed for mitigation of the above.
The proposed activity being of residential type will not cause a notable increase in the noise and vibration during operation.
Sources of noise Pollution during construction phase are machinery like compressor, Compactors,
Concrete Plant, Cranes and transportation materials.
Mitigation measures:
The project proponents have agreed to take precautions to control noise pollution as mentioned
under:
• Use of equipment generating noise of not greater than 90 dB (A).
• High noise generating construction activities would be carried out only during day time. Also,
adequate parking space will be provided to avoid crowding and noise Pollution.
• Installation, use and maintenance of mufflers on equipment.
• Workers working near high noise construction machinery would be supplied with ear
Muffs/ear plugs.
5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in &
ambient air quality around the project site? Provide details.
During Construction Phase:
Sources of noise pollution during construction phase are machinery like Earthmoving Machinery,
Mini Hoist Crane, Mixer, Lift lade, JCB, Dumpers, Compressors and transportation materials.
These machineries will be used only day time. Canopies will be provided to these mechanical devices to reduce noise & vibration. Maximum mitigation measures such as regular maintenance or
overhauling etc.
During Operation Phase:
There will not be any considerable impact on the ambient air quality around the project site as CPCB approved DG sets along with acoustic room will be developed and plantation will be
provided.
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
6. AESTHETICS
6.1 Will the proposed constructions in any way result in the obstruction of a view, scenic amenity
or landscapes? Are these considerations taken into account by the proponents?
No. Proposed construction will not result in obstruction of a view, scenic amenity or landscapes.
6.2 Will there be any adverse impacts from new constructions on the existing structures? What
are the considerations taken into account?
Not Applicable
6.3 Whether there are any local considerations of urban form & urban design influencing the
design criteria? They may be explicitly spelt out.
No
6.4 Are there any anthropological or archaeological sites or artifacts nearby? State if any other
significant features in the vicinity of the proposed site have been considered.
No
7. SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any changes to the demographic structure of local Population?
Provide the details.
Critically analyzing the socio-economic baseline in the context of the proposed project, the impacts
of the project could be variable in nature. The proposed project does not involve any displacement
of inhabitants.
During construction 50 will be provided temporary shelters at the site. After completion of the
project, there will be influx of 1452 people in the area. The population of the area is likely to
increase.
7.2 Give details of the existing social infrastructure around the proposed project.
This project has proposed to establish Residential by Adi Realties is coming up at S. No. Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad, Town/Tehsil –Mulshi,
District-Pune . This area is rapidly developing.
7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other
cultural values? What are the safeguards proposed?
It could be seen that the overall impact on Socio-Economic Environment is positive and permanent
in nature. The impacts on socio-economic environment due to the proposed project are listed below
Positive aspects of the projects are as follows
� Improvement in transport, communication facilities.
� Improvement in lifestyle & social status etc.
� Increase in revenue generation
� Due to the proposed project, facilities are likely to grow in line with the development.
� Possible source of income for this community are direct like Construction and various job
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
works in Residential complex
8. BUILDING MATERIALS
8.1 May involve the use of building materials with high-embodied energy. Are the construction
materials produced with energy efficient processes? (Give details of energy conservation
measures in the selection of building materials and their energy efficiency)
Conventional construction materials used from nearest source to minimize energy consumption for
transportation.
8.2 Transport and handling of materials during construction may result in pollution, noise &
public nuisance. What measures are taken to minimize the impacts?
During construction phase, sources of noise pollution will be due to operation of machinery like
compressors, compactors, concrete plant, cranes etc. as well as transportation vehicles. This will
cause nuisance to the occupants of the nearby area. The project proponents have agreed to take precautions to control noise pollution as mentioned under
i)Use of equipment generating noise of not greater than 90 dB (A).
ii) High noise generating construction activities would be carried out only during day time. Also,
adequate parking space will be provided to avoid crowding and noise Pollution.
iii) Installation, use and maintenance of mufflers on equipment.
iv) Workers working near high noise construction machinery would be supplied with ear
Muffs/ear plugs.
8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?
Solid waste that would be generated due to excavation will be in the form of rubble and soil. This
soil and rubble would be used for development of landscaping. Construction debris will be reused
for backfilling of roads and other construction.
8.4 Give details of the methods of collection, segregation & disposal of the garbage generated
during the operation phases of the project.
Solid waste generated in the campus is domestic type having source separated dry and wet
components. As far as possible the dry waste like paper, cardboard boxes, thermocol packing, plastics etc. shall be sent for recycling purpose.
However, wet waste, which is biodegradable, shall be converted to bio-compost adopting following
aerobic composting method. The quantity of biodegradable waste generated is about 695.5 Kg/Day.
The ‘Organic waste Convertor’ will be used for composting of solid waste.
Solid Waste Management –
4) Total Quantity of Solid Waste = 631.90 kg/day
5) Total quantity of Wet Waste = 385.75 kg/day.
6) Total quantity of Dry Waste = 246.15 Kg/day.
Biodegradable and non biodegradable waste will be generated. Dry waste will be sent for recycling
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
and wet waste will be treated by’ Organic Waste Convertor’’ for composting.
“Organic Waste Convertor” is based on the following principles.
1) Valuable resources must be recovered & reused / recycled.
2) Biodegradable matter must be composted.
3) Minimize the material to be disposed off in a landfill.
B) Organic Waste Convertor
PROCESS DESCRIPTION
Segregation: The waste will be segregated at source by flat owners
Flat owners will segregate garbage in two different color
buckets
Collection: 03 people will manage to collect the waste from each flat and
deliver it to OWC in closed containers
Storage: The B/D waste will be treated on daily basis. In order to store
the manure, a small storage room is proposed on site
Treatment –Biodegradable waste : KWIK Composter (Organic Waste
Converter)
Disposal: Biodegradable waste will used in garden as manure
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
Disposal –Non-biodegradable waste : Through Authorized vendors
Process Flow Chart
(REFER ANNEXURE XII – ORGANIC WASTE CONVERTOR – SOLID WASTE
MANAGEMENT)
9.1 Give details of the power requirements, source of supply, backup source etc. What is the
energy consumption assumed per square foot of built-up area?
Source – Maharashtra State Electricity Distribution Company Limited (MSEDCL)
a. During Construction Phase:
• a) Total Load - 100KW
• b) D G Set – 100 KVA x 1 No
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
b. During Operation Phase:
• A)Total Connected Load –1850KW
• B)Maximum Demand – 1290 KW
• b) Transformer –630KVA x2 Nos
• D.G. Set Suggested – 125 KVA X 1Nos
• Fuel Consumption – 19 Lit/hr. at full load
9.2 What type of, and capacity of, power back-up do you plan to provide?
• A)Total Connected Load –1850KW
• B)Maximum Demand – 1290 KW
• b) Transformer –630KVA x2 Nos
• D.G. Set Suggested – 125 KVA X 1Nos
• Fuel Consumption – 19 Lit/hr. at full load
(REFER ANNEXURE XIV – ELECTRICAL CALCULATIONS, TRANSFORMER,
D.G.SET LOCATION & DETAILS)
9.3 What are the characteristics of the glass you plan to use? Provide specifications of its
characteristics related to both short wave and long wave radiation?
Normal 5 mm clear float glass is used. The glass will allow short as well as long wave radiations to
pass through. However, use of shading devices on window panes will reduce heating inside the
buildings. Sunshades will be provided & sufficient no. of windows will be provided for natural light
& Ventilation.
9.4 What passive solar architectural features are being used in the building? Illustrate the
applications made in the proposed project.
Solar architectural features have been planned in order to reduce cooling loads of the structure. They
are:
1. Longer side facing dominant wind direction
2. Water bodies ample adding to passive cooling
3. Proper shading devices for windows. (Not Applicable)
9.5 Does the layout of streets & buildings maximize the potential for solar energy devices? Have
you considered the use of street lighting, emergency lighting and solar hot water systems for
use in the building complex? Substantiate
Solar System is being used for Hot water & street lighting.
9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used to
maximize the shading of Walls on the East and the West and the Roof? How much energy
saving has been effected?
The construction is designed in order to assure maximum of the natural light and ventilation in the
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
structure. Light shades will be used to color the walls so that heat gain is reduced.
9.7
Do the structures use energy-efficient space conditioning, lighting and mechanical systems?
Provide technical details. Provide details of the transformers and motor efficiencies, lighting
intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers?
Provide specifications.
As it is a residential complex with no built provision for space cooling. Energy efficiency in lighting
and mechanical systems will be achieved by:
• Auto Timer control for external & Common lighting
• Use of CFL / LED lamps in all public/ common areas.
• Solar powered water heating .
• Electronic V3F Drives for Elevators
9.8 What are the likely effects of the building activity in altering the micro-climates? Provide a
self-assessment on the likely impacts of the proposed construction on creation of heat island &
inversion effects?
The proposed project is of residential type and will not have space conditioners or glass wall.
Alteration of microclimate is not notable in this case. Systematic design of buildings in order to
assure maximum natural ventilation and light will be considered to reduce the effect of creation of heat island.
9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external walls;
and (c) fenestration? Give details of the material used and the U-values or the R values of the
individual components.
Fenestration area is most vulnerable to heat gain or loss. Thermal characteristics of the envelope are
as follows:
The U and R values of the construction parameters shall comply with ECBC.
9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of
emergency plans.
The project proponents shall follow all the safety rules and regulations as prescribed by
regulatory authority.
(ANNEXURE XV- FIRE MOVEMENT & SERVICES ATTACHED)
9.11
If you are using glass as wall material provides details and specifications including
emissivity and thermal characteristics.
The entire building is designed with appropriate opening to reduce heat energy inside the building. No use of glass as wall material.
9.12 What is the rate of air infiltration into the building? Provide details of how you are
mitigating the effects of infiltration.
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
I hereby given undertaking that the data and information given in the application and
enclosures are true to the best of my knowledge and belief and I am aware that if any part of
Not applicable. As the ground surfaces are covered with green patches to have dust control.
These openings too habitable spaces are adequate just to be functional. The openings are
covered with dust proof, air and water light aluminum glazing.
9.13 To what extent the non-conventional energy technologies are utilized in the
Overall energy consumption? Provide details of the renewable energy technologies used.
Use of Solar Energy.
10 Environment Management Plan
The Environment Management Plan would consist of all mitigation measures for each item
wise activity to be undertaken during the construction, operation and the entire life cycle to
minimize adverse environmental impacts as a result of the activities of the project. It would
also delineate the environmental monitoring plan for compliance of various environmental
regulations. It will state the steps to be taken in case of emergency such as accidents at the
site including fire.
(REFER ANNEXURE – XVI - ENVIRONMENT MANAGEMENT PLAN)
Form 1 & 1A for proposed Residential and Commercial Project “Horizon at Wakad” by
Survey No-127/2A, 127/2B/2, 176/2/1B(Plot no. 1). of Wakad –Hinjewadi Road Wakad,
Town/Tehsil –Mulshi, District-Pune
�
the data and information submitted is found to be false or misleading at any stage, the project
will be rejected and clearance give, if any to the project will be revoked at our risk and cost.
________________________
Signature of the applicant
With Name and Full Address
(Project Proponent/ Authorized Signatory)