Forcados Wdl Technical Presentation Rev 1
-
Upload
mitchellgrany -
Category
Documents
-
view
238 -
download
3
Transcript of Forcados Wdl Technical Presentation Rev 1
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
1/45
TECHNICAL PRESENTATION
REHABILITATION OF FORCADOS
PIPELINE
PRESENTED BY
OIS/GREDOR CONSORTIUM
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
2/45
CONTRACTNO:NG01002625INTEGRATEDPIPELINESMAINTENANCEANDREPAIRS NG01002625Page : 8
EXECUTIONPLANFORREHABILITATIONOFFORCADSTERMINAL36WATERDISPOSALLINE Rev :0PROJECTEXECUTIONPLAN Date :15Apr,2012
1.0 General Introduction
The 36 x 11.1km Forcados Terminal Water Disposal Pipeline (WDL) was
commissioned in 1997 to evacuate produced water from the Forcados
Terminal oil processing facilities for disposal offshore. The WDL is made up of
two sections viz: 36 x 6km onshore section of Glass Re-enforced Epoxy
(GRE) material and 36x5.1km offshore Carbon Steel section. An underwater
inspection to assess the condition of the diffusers showed that the 500m
diffusers at the offshore section had about 30m severed and completely
detached. This requires repair to restore the diffuser as described below.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
3/45
Pipelay
/DerrickBarge
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
4/45
HOOK RADIUS vs. LIFTING CAPACITY & HOOK HEIGHT
VESSEL DATA SHEET
CHEROKEE
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
5/45
HOOK RADIUS vs. LIFTING CAPACITY & HOOK HEIGHT
Akpevweoghene
Pi p e la y
D e r r i c k
B a r g e
MOORING EQUIPMENT
No. of Anchors; Weight (8); 30,000 lb (13,608 kg)
Make, type Navy, Stockless
No. of Winches (4) Double DrumMake, type Manitowoc 560Wire (length/diameter) 5,000 ft (1,524 m) / 1.75 in
GENERAL MAIN CRANE
Length (overall) 387 ft (117.96 m) Derrick
Width 100 ft (30.48 m) Make, Model Manitowoc Seacrane 600Depth 25 ft (7.62 m) Type Revolving
Classification USCG, ABS A-1
Year Built 1 9 6 9A u x i l i a r y 260 ft (79.25 m)
Registry (Flag) USA Whip 275 ft (83.82 m)Operating Draft (min/max) 12 ft (3.66 m) / 17 ft (5.19 m) Capacity
Tonnage (gross / net) 7655 / 2296 Main Revolving 600 s. tons @ 70 ft (544 MT @ 21.34 m)Max Deck Load Project Specific Main Fixed 925 s. tons @ 80 ft (839 MT @ 24.38 m)Free Deck Area ( length x w idth) 100 ft (30 .48 m) x 60 ft (18.3 m) Auxiliary 150 s. tons @ 100 ft (136 MT @ 30.48 m)Moon Pool (yes / no) no Whip 50 s. tons @ 250 ft (45.36 MT @ 76.2 m)
Accommodations 174 people
Hospital Beds 6 AUXILIARY CRANE(s)
Transit Speed (econ / max) Towed Make, Model Manitowoc 3900 WHelicopter Max Rating 6,200 lbs Type Crawler
Helicopter Refueling capacity N/A Boom Length 120 ft (36.59 m)
Helideck Dimensions 40 ft (18.16 m) x 40 ft (18.6 m) Capacity 86 s. tons (78 MT)
Boom LengthMain 200 ft (60.96 m)
MACHINERY MISSION EQUIPMENT
Main Engines N/A Pipelay Method(s) Conventional S-Lay
No. of Generators 4N o . o f W o r k S t a t i o n s ( @ 4 0 f t ) 7
Main Power (3) 500 kW Pipe Diameter (min/max) 2 in / 48 in
Auxiliary Power (1) 100 kW emergency Tensioners (make, type) (2) Western Gear
No. of Compressors (3) 125 psi Total Capacity (ea/ttl) 160 kips (72,576 kg) / 320 kips (145,152 kg)
Total Output 1,759 cfm (2,988.54 m /h) Reel Capacity (tonnage) N/A3
Water Makers Sea Recovery Abandon/Rec. Winch
Total Capacity 780 USG/h (2,952.3 L/h) Type (make/model) RentalAR Wire (length/diameter) 4 ,000 ft (1 ,219 m) / 2.5 in
BUNKER CAPACITY Capacity 300,000 lb (12,000 kg)Fuel 350,000 USG (1,324,750 L) Davits N/AFresh Water 1,000,000 USG (3,785,000 L)
Potable Water 138,000 USG (522,330 L) STINGER
Type Truss (Ballast) Stinger 16;
DYNAMIC POSITIONING 2 section Articulated (Ballast) Stinger 14N/A Length (min/max) 160 ft truss; 120 ft articulated
COMMUNICATION SYSTEMS PIPE BURY EQUIPMENT
(1) 125 watt SS Band N/A(1) Inmarsat B Celluar Phone
(4) Modular VHF DIVING SYSTEM
NAVIGATION 650 SAT System with HRC
N/A
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
6/45
Akpevweoghene
CHEROKEE
CHEROKEE
Profile
37
Plan
Operations Office Head Office
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
7/45
2. ANCHOR HANDLING AND SUPPLY VESSELPICTURES AND DETAILS OF FENOGS ANCHOR HANDLING AND SUPPLY VESSEL FORMALLY
CALLED: OROGHENE
View of Oroghene Anchor Handling /Supply Vessel in Fenogs Jetty, Warri.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
8/45
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
9/45
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
10/45
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
11/45
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
12/45
Engineering
Bathymetric Survey Diffuser inspection
ng neer ng a cu at ons an es gn na ys s
Deliverablesurvey p an
Diffuser inspection report detailing condition of coating, anodes,diffuser burial and type of material
Calculation report for allowable free spamLifting plan and Drawings
HSE reports
Risk management report
Work method statement Approved for construction Drawings
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
13/45
Mobilization and Marine Operations
General Site Layout
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
14/45
Mobilization and Marine Operations (continued)
1. Mobilization
Gredor yard, Warri will be used to support the marine logistics ofthis project.
All Equipment to assemble at FENOG marine base where theAKPEVWOGHENE La Bar e is located.
Materials shall be transported to FENOG marine base wherethey shall be loaded onto the lay barge
to Forcados slot by the OROGHENE tugboat
The spread shall stop for 1day at the Forcados slot for SPDCu as may e ecessary.
There after spread shall leave the Forcados slot through the
Forcados River following the route indicated to the work site. Surveyors shall have marked out the allowable at which the 48
export pipeline can be crossed by the OROGHENE Tugboat andthe AKPEVWOGHENE Barge.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
15/45
Mobilization and Marine Operations (cont)
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
16/45
2 Anchoring
Mobilization and Marine Operations (cont)
2.1 Anchor Mooring System
The APKEVWOGHENE Bar e anchor moorin s stem is shown in the table below
Name of Vessel Akpevwoghene
Length of Overall 117.96 m
Breadth Moulded 30.48 m
Depth Moulded 7.62 m
Max. Draft 5.19 m
Bollard PullMain Engine
Positionin
(anchor) Winch
- Quantity
4 Double Drum
-Manitowoc- Type
- Capacity
- 560 ton
Anchor T e 8 each Nav Stockless
Wire Size x Length 44 mm x1524 m
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
17/45
.
1. Barge on the same side of the pipeline as anchor
Anchor
Vessel >=100m
ipe ine
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
18/45
ANCHORAGE CRITERIA (continued)
1. The pipeline lies between the Barge and the anchor
Anchor
>=200m
esse
Pipeline
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
19/45
ANCHORIAGE PLAN
ay arge w e suppor e y anc or an ng ugs
Lay barge will be moored by 8(eight) Navy, Stockless anchors with44mm (1.75) O.D. cable in 1524 meter len ths.
The length of the mooring lines is based on catenary theory to have
sufficient length of mooring line lying on seabed under expected
While moving barge, the tugs will be responsible for the placementand relocation of the barge anchors
The anchor handling tugs will use their winch to set and retrieve thebarge anchors
Every Anchor position shall be established by the On-Board Surveyteam
lines damage prevention (D.P) buoys will be installed to preventcontact between anchor wire and the pipeline
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
20/45
ANCHORAGE CRITERIA (continued)
Damage Prevention
D. P. Buoy
Pendant Wire
AnchorPosition of D. P. Buoy to be checked by
Diver every 12 hours of operation
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
21/45
ANCHORAGE CRITERIA (continued)
CatenaryTables
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
22/45
ANCHORAGE CRITERIA (continued)
Typycal Anchor Layout
Existing
Existing
Pi elineD. P. Buoy
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
23/45
LIFTING
1. Items to be Lifted
Above figure is a typical representation of the WDLshowing the damaged Diffuser.
While the severed section is to be salvaged the main
section is to be repaired
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
24/45
LIFTING (continued)
2. Lifting Methods
or e an ec on e an onmen ecovery .Winch on the Lay barge shall be used
For the Salva in of the Severed Section Davits on theBarge shall be utilized
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
25/45
LIFTING (continued)
3. Preparation for Lifting
e o owng as een accomp s e
Pre Repair Survey
n a nspec on as een carre ou an repa rscope fully established
Extent of de osition and t e of debris is known
And the following are available on Site
Design Reports and AFC Drawings
Complete Diving and Survey Spreads
Air bags, Lifting and Rigging Tools
Spreader Bars of up to 15m Span
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
26/45
LIFTING (continued)
4. Step I : Diving Activities
e rs emova
Debris deposited on and around the Diffuser shall be
removed b Water J ettin
Divers will use Air at high Pressure to Air-Lift andhence fluidize debris around and beneath the diffuser .
.
Water currents at the Sea Bed will carry the fluidizeddebris away thereby freeing the Diffuser.
The Boat MV DELTA SKY will support this activity
Installation of Lifting Apparatus
Lifting Slings and Shackles
Air Bags (Main Diffuser Section only)
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
27/45
LIFTING (continued)
15m
.
30m
Severed Section ofDiffuser
amage n o
Diffuser
20m 20m 20m
on r
BagLifting Sling
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
28/45
LIFTING (continued)
5. Step II : Lifting
e erm ne a owa e ree span o e ame er p pe yengineering calculation. Previous computation for similar size of
pipe at 50barg established the allowable free span at between.
Controlling Factor is the minimum allowable radius ofConcrete coating determined for previous test as equal to800m
To work within this range previous practice shows that for
down is about 110m from the barge stern and a bendingradius more than 800m
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
29/45
LIFTING (continued)
5. Step II : Lifting
A b di di f 1000 h ll b li d i thi lifti Abending radius of 1000m or more shall be applied in this lifting
Based on Engineering computations to be done before the actual
lifting the horizontal distance to achieve this will be determined.g
10ton Air Bags shall be installed at 20m intervals over theentire length of the diffuser in order to achieve this.
Determine the minimum distance between the end of the thediffuser and the barge stern (Minimum X). From previous
analysis the minimum X for 36 diameter pipe was found to be
58m.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
30/45
LIFTING (continued)
5. Step II : Lifting
Pipeline
towards the end of the diffuser. Pre-ballast the stinger.
Pass lifting cable around the end of the diffuser and attach to amarker buoy.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
31/45
LIFTING (continued)
5. Step II : Lifting
Lifting Head
Determine the minimum distance between the end of the
.analysis the minimum X for 36 diameter pipe was found to be
58m.
Position lay barge so that the A/R head is no closer than a
minimum X meters from stern of the barge.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
32/45
LIFTING (continued)
5. Step II : Lifting
Lifting Head
Using tug thread cable tied to the pipe through the stinger andpipe ramp, attach end to the A/R winch drum.
Inflate airbags beginning with the one farthest from and end withthe one nearest to the lay barge.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
33/45
LIFTING (continued)
5. Step II : Lifting
Liftin Head
Maintain barge position and reel in wire until the Lay Tension isreached.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
34/45
LIFTING (continued)
5. Step II : Lifting
Direction of Movement of Barge
Lifting Head
Slowly move barge towards the diffuser end position andmaintainin the tension. As this is done the diffuser end rises
gradually.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
35/45
LIFTING (continued)
5. Step II : Lifting
Direction of Movement of Barge
LiftingHead
moves up the stinger, past the ramp and through the tensioners.
Transfer tension from the A/R winch to the tensioners. Detachthe pull cable from the end of lifted diffuser. Prepare for cutting
and welding.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
36/45
WELDING
of work
Welders to be qualified based on the Qualified WPS
to e eve ope an ua e at t e t me o or xecut on
Shielded Metal Arc Welding (SMAW) Process shall used for all Welding
Works Hot Cutting shall be adopted for Pipe cutting and bevelling
Joint Alignment shall be with both Internal and External Line-Up Clamps
-during a typical pipe laying activity
Details of Welding and NDE can be found in Appendix A to Section 6.5 ofthe Work Execution Plan
Quality of Welds
Welds shall undergo 100% Radiographic Inspection
Other Tests to be at the request of SPDC
JOINT COATING
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
37/45
JOINT COATING
External Coating shall consist of the appropriate Anti-Corrosionfollowed by Concrete Coating
Internally Surface of the Pipe shall be lined with 10mm thickconcrete coating
Internal coating shall require the worker going into the pipe with ona trolley and lighting. Ventilation of the inside of the pipe shall also
be necessary.
Generally procedures for working in confined spaces shall beadopted in order to safely execute the internal coating work
LAUNCHING (LOWERING)
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
38/45
LAUNCHING (LOWERING)
.
involved
Sling the flanged end with the A/R cable
Gradually transfer Tension from the Tensioners to the A/RWinch
Gradually Move the Lay barge away from the diffuser until it isinside water
-
the line is not unduly stressed Remove the A/R cable
LAUNCHING (LOWERING)
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
39/45
LAUNCHING (LOWERING)
.
involved
Sling the flanged end with the A/R cable
Gradually transfer Tension from the Tensioners to the A/RWinch
Gradually Move the Lay barge away from the diffuser until it isinside water
-
the line is not unduly stressed Remove the A/R cable
Special Note
A piece shall be welded to the flanged exit of the diffuser toprovide a bevel for relatively smooth passage across the rollers
LAUNCHING (LOWERING)
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
40/45
LAUNCHING (LOWERING)
Typical Diffuser Launch
LAUNCHING (LOWERING)
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
41/45
LAUNCHING (LOWERING)
Transition PieceDiffuser Pipe
for Launching
DIFFUSER PORT OPENING
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
42/45
DIFFUSER PORT OPENING
WDL Port Plug Non Metallic.
Requires a Key to open
Diffuser Port Plug Key to be
fabricated
SCOOPING OF TOPSOIL)
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
43/45
SCOOPING OF TOPSOIL)
This will be done by scooping the specially marked area with agrab bucket dredge using the deck crane of the lay barge.
disposed onshore at an SPDC designated location
CATHODIC PROTECTION SYSTEM REPAIR
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
44/45
CATHODIC PROTECTION SYSTEM REPAIR
When required sacrificial Anodes shall be installed by Divers.
REINSTATEMENT
Sand for deposition shall be imported from other areas onbarges and shall be placed using the deck crane and a grab
Concrete Mats shall be placed using the deck crane andspreader bars.
-
7/30/2019 Forcados Wdl Technical Presentation Rev 1
45/45