Forcados Wdl Technical Presentation Rev 1

download Forcados Wdl Technical Presentation Rev 1

of 45

Transcript of Forcados Wdl Technical Presentation Rev 1

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    1/45

    TECHNICAL PRESENTATION

    REHABILITATION OF FORCADOS

    PIPELINE

    PRESENTED BY

    OIS/GREDOR CONSORTIUM

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    2/45

    CONTRACTNO:NG01002625INTEGRATEDPIPELINESMAINTENANCEANDREPAIRS NG01002625Page : 8

    EXECUTIONPLANFORREHABILITATIONOFFORCADSTERMINAL36WATERDISPOSALLINE Rev :0PROJECTEXECUTIONPLAN Date :15Apr,2012

    1.0 General Introduction

    The 36 x 11.1km Forcados Terminal Water Disposal Pipeline (WDL) was

    commissioned in 1997 to evacuate produced water from the Forcados

    Terminal oil processing facilities for disposal offshore. The WDL is made up of

    two sections viz: 36 x 6km onshore section of Glass Re-enforced Epoxy

    (GRE) material and 36x5.1km offshore Carbon Steel section. An underwater

    inspection to assess the condition of the diffusers showed that the 500m

    diffusers at the offshore section had about 30m severed and completely

    detached. This requires repair to restore the diffuser as described below.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    3/45

    Pipelay

    /DerrickBarge

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    4/45

    HOOK RADIUS vs. LIFTING CAPACITY & HOOK HEIGHT

    VESSEL DATA SHEET

    CHEROKEE

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    5/45

    HOOK RADIUS vs. LIFTING CAPACITY & HOOK HEIGHT

    Akpevweoghene

    Pi p e la y

    D e r r i c k

    B a r g e

    MOORING EQUIPMENT

    No. of Anchors; Weight (8); 30,000 lb (13,608 kg)

    Make, type Navy, Stockless

    No. of Winches (4) Double DrumMake, type Manitowoc 560Wire (length/diameter) 5,000 ft (1,524 m) / 1.75 in

    GENERAL MAIN CRANE

    Length (overall) 387 ft (117.96 m) Derrick

    Width 100 ft (30.48 m) Make, Model Manitowoc Seacrane 600Depth 25 ft (7.62 m) Type Revolving

    Classification USCG, ABS A-1

    Year Built 1 9 6 9A u x i l i a r y 260 ft (79.25 m)

    Registry (Flag) USA Whip 275 ft (83.82 m)Operating Draft (min/max) 12 ft (3.66 m) / 17 ft (5.19 m) Capacity

    Tonnage (gross / net) 7655 / 2296 Main Revolving 600 s. tons @ 70 ft (544 MT @ 21.34 m)Max Deck Load Project Specific Main Fixed 925 s. tons @ 80 ft (839 MT @ 24.38 m)Free Deck Area ( length x w idth) 100 ft (30 .48 m) x 60 ft (18.3 m) Auxiliary 150 s. tons @ 100 ft (136 MT @ 30.48 m)Moon Pool (yes / no) no Whip 50 s. tons @ 250 ft (45.36 MT @ 76.2 m)

    Accommodations 174 people

    Hospital Beds 6 AUXILIARY CRANE(s)

    Transit Speed (econ / max) Towed Make, Model Manitowoc 3900 WHelicopter Max Rating 6,200 lbs Type Crawler

    Helicopter Refueling capacity N/A Boom Length 120 ft (36.59 m)

    Helideck Dimensions 40 ft (18.16 m) x 40 ft (18.6 m) Capacity 86 s. tons (78 MT)

    Boom LengthMain 200 ft (60.96 m)

    MACHINERY MISSION EQUIPMENT

    Main Engines N/A Pipelay Method(s) Conventional S-Lay

    No. of Generators 4N o . o f W o r k S t a t i o n s ( @ 4 0 f t ) 7

    Main Power (3) 500 kW Pipe Diameter (min/max) 2 in / 48 in

    Auxiliary Power (1) 100 kW emergency Tensioners (make, type) (2) Western Gear

    No. of Compressors (3) 125 psi Total Capacity (ea/ttl) 160 kips (72,576 kg) / 320 kips (145,152 kg)

    Total Output 1,759 cfm (2,988.54 m /h) Reel Capacity (tonnage) N/A3

    Water Makers Sea Recovery Abandon/Rec. Winch

    Total Capacity 780 USG/h (2,952.3 L/h) Type (make/model) RentalAR Wire (length/diameter) 4 ,000 ft (1 ,219 m) / 2.5 in

    BUNKER CAPACITY Capacity 300,000 lb (12,000 kg)Fuel 350,000 USG (1,324,750 L) Davits N/AFresh Water 1,000,000 USG (3,785,000 L)

    Potable Water 138,000 USG (522,330 L) STINGER

    Type Truss (Ballast) Stinger 16;

    DYNAMIC POSITIONING 2 section Articulated (Ballast) Stinger 14N/A Length (min/max) 160 ft truss; 120 ft articulated

    COMMUNICATION SYSTEMS PIPE BURY EQUIPMENT

    (1) 125 watt SS Band N/A(1) Inmarsat B Celluar Phone

    (4) Modular VHF DIVING SYSTEM

    NAVIGATION 650 SAT System with HRC

    N/A

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    6/45

    Akpevweoghene

    CHEROKEE

    CHEROKEE

    Profile

    37

    Plan

    [email protected]

    Operations Office Head Office

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    7/45

    2. ANCHOR HANDLING AND SUPPLY VESSELPICTURES AND DETAILS OF FENOGS ANCHOR HANDLING AND SUPPLY VESSEL FORMALLY

    CALLED: OROGHENE

    View of Oroghene Anchor Handling /Supply Vessel in Fenogs Jetty, Warri.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    8/45

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    9/45

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    10/45

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    11/45

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    12/45

    Engineering

    Bathymetric Survey Diffuser inspection

    ng neer ng a cu at ons an es gn na ys s

    Deliverablesurvey p an

    Diffuser inspection report detailing condition of coating, anodes,diffuser burial and type of material

    Calculation report for allowable free spamLifting plan and Drawings

    HSE reports

    Risk management report

    Work method statement Approved for construction Drawings

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    13/45

    Mobilization and Marine Operations

    General Site Layout

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    14/45

    Mobilization and Marine Operations (continued)

    1. Mobilization

    Gredor yard, Warri will be used to support the marine logistics ofthis project.

    All Equipment to assemble at FENOG marine base where theAKPEVWOGHENE La Bar e is located.

    Materials shall be transported to FENOG marine base wherethey shall be loaded onto the lay barge

    to Forcados slot by the OROGHENE tugboat

    The spread shall stop for 1day at the Forcados slot for SPDCu as may e ecessary.

    There after spread shall leave the Forcados slot through the

    Forcados River following the route indicated to the work site. Surveyors shall have marked out the allowable at which the 48

    export pipeline can be crossed by the OROGHENE Tugboat andthe AKPEVWOGHENE Barge.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    15/45

    Mobilization and Marine Operations (cont)

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    16/45

    2 Anchoring

    Mobilization and Marine Operations (cont)

    2.1 Anchor Mooring System

    The APKEVWOGHENE Bar e anchor moorin s stem is shown in the table below

    Name of Vessel Akpevwoghene

    Length of Overall 117.96 m

    Breadth Moulded 30.48 m

    Depth Moulded 7.62 m

    Max. Draft 5.19 m

    Bollard PullMain Engine

    Positionin

    (anchor) Winch

    - Quantity

    4 Double Drum

    -Manitowoc- Type

    - Capacity

    - 560 ton

    Anchor T e 8 each Nav Stockless

    Wire Size x Length 44 mm x1524 m

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    17/45

    .

    1. Barge on the same side of the pipeline as anchor

    Anchor

    Vessel >=100m

    ipe ine

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    18/45

    ANCHORAGE CRITERIA (continued)

    1. The pipeline lies between the Barge and the anchor

    Anchor

    >=200m

    esse

    Pipeline

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    19/45

    ANCHORIAGE PLAN

    ay arge w e suppor e y anc or an ng ugs

    Lay barge will be moored by 8(eight) Navy, Stockless anchors with44mm (1.75) O.D. cable in 1524 meter len ths.

    The length of the mooring lines is based on catenary theory to have

    sufficient length of mooring line lying on seabed under expected

    While moving barge, the tugs will be responsible for the placementand relocation of the barge anchors

    The anchor handling tugs will use their winch to set and retrieve thebarge anchors

    Every Anchor position shall be established by the On-Board Surveyteam

    lines damage prevention (D.P) buoys will be installed to preventcontact between anchor wire and the pipeline

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    20/45

    ANCHORAGE CRITERIA (continued)

    Damage Prevention

    D. P. Buoy

    Pendant Wire

    AnchorPosition of D. P. Buoy to be checked by

    Diver every 12 hours of operation

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    21/45

    ANCHORAGE CRITERIA (continued)

    CatenaryTables

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    22/45

    ANCHORAGE CRITERIA (continued)

    Typycal Anchor Layout

    Existing

    Existing

    Pi elineD. P. Buoy

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    23/45

    LIFTING

    1. Items to be Lifted

    Above figure is a typical representation of the WDLshowing the damaged Diffuser.

    While the severed section is to be salvaged the main

    section is to be repaired

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    24/45

    LIFTING (continued)

    2. Lifting Methods

    or e an ec on e an onmen ecovery .Winch on the Lay barge shall be used

    For the Salva in of the Severed Section Davits on theBarge shall be utilized

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    25/45

    LIFTING (continued)

    3. Preparation for Lifting

    e o owng as een accomp s e

    Pre Repair Survey

    n a nspec on as een carre ou an repa rscope fully established

    Extent of de osition and t e of debris is known

    And the following are available on Site

    Design Reports and AFC Drawings

    Complete Diving and Survey Spreads

    Air bags, Lifting and Rigging Tools

    Spreader Bars of up to 15m Span

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    26/45

    LIFTING (continued)

    4. Step I : Diving Activities

    e rs emova

    Debris deposited on and around the Diffuser shall be

    removed b Water J ettin

    Divers will use Air at high Pressure to Air-Lift andhence fluidize debris around and beneath the diffuser .

    .

    Water currents at the Sea Bed will carry the fluidizeddebris away thereby freeing the Diffuser.

    The Boat MV DELTA SKY will support this activity

    Installation of Lifting Apparatus

    Lifting Slings and Shackles

    Air Bags (Main Diffuser Section only)

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    27/45

    LIFTING (continued)

    15m

    .

    30m

    Severed Section ofDiffuser

    amage n o

    Diffuser

    20m 20m 20m

    on r

    BagLifting Sling

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    28/45

    LIFTING (continued)

    5. Step II : Lifting

    e erm ne a owa e ree span o e ame er p pe yengineering calculation. Previous computation for similar size of

    pipe at 50barg established the allowable free span at between.

    Controlling Factor is the minimum allowable radius ofConcrete coating determined for previous test as equal to800m

    To work within this range previous practice shows that for

    down is about 110m from the barge stern and a bendingradius more than 800m

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    29/45

    LIFTING (continued)

    5. Step II : Lifting

    A b di di f 1000 h ll b li d i thi lifti Abending radius of 1000m or more shall be applied in this lifting

    Based on Engineering computations to be done before the actual

    lifting the horizontal distance to achieve this will be determined.g

    10ton Air Bags shall be installed at 20m intervals over theentire length of the diffuser in order to achieve this.

    Determine the minimum distance between the end of the thediffuser and the barge stern (Minimum X). From previous

    analysis the minimum X for 36 diameter pipe was found to be

    58m.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    30/45

    LIFTING (continued)

    5. Step II : Lifting

    Pipeline

    towards the end of the diffuser. Pre-ballast the stinger.

    Pass lifting cable around the end of the diffuser and attach to amarker buoy.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    31/45

    LIFTING (continued)

    5. Step II : Lifting

    Lifting Head

    Determine the minimum distance between the end of the

    .analysis the minimum X for 36 diameter pipe was found to be

    58m.

    Position lay barge so that the A/R head is no closer than a

    minimum X meters from stern of the barge.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    32/45

    LIFTING (continued)

    5. Step II : Lifting

    Lifting Head

    Using tug thread cable tied to the pipe through the stinger andpipe ramp, attach end to the A/R winch drum.

    Inflate airbags beginning with the one farthest from and end withthe one nearest to the lay barge.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    33/45

    LIFTING (continued)

    5. Step II : Lifting

    Liftin Head

    Maintain barge position and reel in wire until the Lay Tension isreached.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    34/45

    LIFTING (continued)

    5. Step II : Lifting

    Direction of Movement of Barge

    Lifting Head

    Slowly move barge towards the diffuser end position andmaintainin the tension. As this is done the diffuser end rises

    gradually.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    35/45

    LIFTING (continued)

    5. Step II : Lifting

    Direction of Movement of Barge

    LiftingHead

    moves up the stinger, past the ramp and through the tensioners.

    Transfer tension from the A/R winch to the tensioners. Detachthe pull cable from the end of lifted diffuser. Prepare for cutting

    and welding.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    36/45

    WELDING

    of work

    Welders to be qualified based on the Qualified WPS

    to e eve ope an ua e at t e t me o or xecut on

    Shielded Metal Arc Welding (SMAW) Process shall used for all Welding

    Works Hot Cutting shall be adopted for Pipe cutting and bevelling

    Joint Alignment shall be with both Internal and External Line-Up Clamps

    -during a typical pipe laying activity

    Details of Welding and NDE can be found in Appendix A to Section 6.5 ofthe Work Execution Plan

    Quality of Welds

    Welds shall undergo 100% Radiographic Inspection

    Other Tests to be at the request of SPDC

    JOINT COATING

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    37/45

    JOINT COATING

    External Coating shall consist of the appropriate Anti-Corrosionfollowed by Concrete Coating

    Internally Surface of the Pipe shall be lined with 10mm thickconcrete coating

    Internal coating shall require the worker going into the pipe with ona trolley and lighting. Ventilation of the inside of the pipe shall also

    be necessary.

    Generally procedures for working in confined spaces shall beadopted in order to safely execute the internal coating work

    LAUNCHING (LOWERING)

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    38/45

    LAUNCHING (LOWERING)

    .

    involved

    Sling the flanged end with the A/R cable

    Gradually transfer Tension from the Tensioners to the A/RWinch

    Gradually Move the Lay barge away from the diffuser until it isinside water

    -

    the line is not unduly stressed Remove the A/R cable

    LAUNCHING (LOWERING)

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    39/45

    LAUNCHING (LOWERING)

    .

    involved

    Sling the flanged end with the A/R cable

    Gradually transfer Tension from the Tensioners to the A/RWinch

    Gradually Move the Lay barge away from the diffuser until it isinside water

    -

    the line is not unduly stressed Remove the A/R cable

    Special Note

    A piece shall be welded to the flanged exit of the diffuser toprovide a bevel for relatively smooth passage across the rollers

    LAUNCHING (LOWERING)

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    40/45

    LAUNCHING (LOWERING)

    Typical Diffuser Launch

    LAUNCHING (LOWERING)

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    41/45

    LAUNCHING (LOWERING)

    Transition PieceDiffuser Pipe

    for Launching

    DIFFUSER PORT OPENING

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    42/45

    DIFFUSER PORT OPENING

    WDL Port Plug Non Metallic.

    Requires a Key to open

    Diffuser Port Plug Key to be

    fabricated

    SCOOPING OF TOPSOIL)

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    43/45

    SCOOPING OF TOPSOIL)

    This will be done by scooping the specially marked area with agrab bucket dredge using the deck crane of the lay barge.

    disposed onshore at an SPDC designated location

    CATHODIC PROTECTION SYSTEM REPAIR

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    44/45

    CATHODIC PROTECTION SYSTEM REPAIR

    When required sacrificial Anodes shall be installed by Divers.

    REINSTATEMENT

    Sand for deposition shall be imported from other areas onbarges and shall be placed using the deck crane and a grab

    Concrete Mats shall be placed using the deck crane andspreader bars.

  • 7/30/2019 Forcados Wdl Technical Presentation Rev 1

    45/45