For - Jharkhandjuidco.jharkhand.gov.in/MIS/home/newsfiles/38_Ramgarh M Building.… · G-1/4,...
Transcript of For - Jharkhandjuidco.jharkhand.gov.in/MIS/home/newsfiles/38_Ramgarh M Building.… · G-1/4,...
JHARKHAND URBAN INFRASTRUCTURE
DEVELOPMENT COMPANY LIMITED.
MONTHLY PROGRESS REPORT
For
“Construction of Municipal Office Building
atRamgarh”
Prepared By: JUIDCO
PROGRESS UPTO 3rd NOVEMBER2017
Project Background
General Information Name of Project Construction of Municipal Office Building At
Ramgarh-Jharkhand
Client Name JUIDCO.
Consultant’s Name Mass N Void Design Consultants (A Pranav Group) G-1/4, Basement, Malviya Nagar, New Delhi - 110017
Contractor’s Name Ma Vindhayawashini Enterprises
Date of Commencement
10 June 2017
Date of Completion
09 September 2018
Contract Period 15 Months
Contract Amount
8,02,67,875.00
Activity in Progress
Following activities are in progress on site
Activity Status Scope Quantity % Remaining
QTY Executed Completed
Basement & Foundation Progress
Excavation of basement Completed 01 Nos 01 Nos 100% Nil
Excavation of Foundation Completed 30 Nos 30 Nos 100% Nil
PCC of Foundation Completed 30 Nos 30 Nos 100% Nil
Steel Fixing & Formwork of Completed 30 Nos 30 Nos 100% Nil
Foundation
Concrete Pouring of Completed 30 Nos 30 Nos 100% Nil
Foundation
Boundary Wall Progress
Excavation of Foundation In Progress 87 Nos 49 Nos 77% 38 Nos
PCC of Foundation In Progress 87 Nos 49 Nos 77% 38 Nos
Steel Fixing & Formwork of In Progress 87 Nos 49 Nos 77% 38 Nos
Foundation
Concrete Pouring of In Progress 87 Nos 49 Nos 77% 38 Nos
Foundation
Excavation of Plinth Beam In Progress 257 RM 163RM 63.4% 94 RM
Steel Fixing & Formwork of In Progress 257 RM 163RM 63.4% 94 RM
Plinth Beam
Concrete Pouring of Plinth In Progress 257 RM 163 RM 63.4% 94 RM
Beam
Brick Work In Progress 257 RM 150 RM 58% 107 RM
Retaining Wall Progress Upto 2.4m
Excavation of Retaining wall Completed 85 RM 85 RM 100% Nil
PCC of Retaining wall Completed 85 RM 85 RM 100% NIl
Steel Fixing & Formwork ofRetaining wall Completed 85 RM 85 RM 100% Nil
Concrete Pouring ofRetaining wall Completed 85 RM 85 RM 100% Nil
Grade Slab
PCC of Grade Slab Completed 817 SQM 817 SQM 100% Nil
RCC of Grade Slab Completed 817 SQM 817 SQM 100% Nil
Project Mile Stones:
S.N.
Milestone
Duration
Finish Date
1.
Upto Concrete Work Completion
7 Months
09January 2018
2.
Upto finishing upto Roof Level Completed
5 Months
09 June 2018
3.
Rest Work Completed
3 Months
09 September 2018
List of Manpower on Site:
S.N. Name of the Employee
Designation Company Contact No
Consultant’s Staff
1. Mohammad Yasir Project Manager MNVDC 9871780249
2. Waseem Ahmad Dy. Project Manager MNVDC 8084121800
3. Abhishek Kr. Gittu Ast. Project Manager MNVDC 9470178531
Contractor’s Staff
1. Mohd Alam Project Manager-cum-site Engineer
Ma Vindhayawashini 9664529069
2. Sameer Store Keeper Ma Vindhayawashini ---------------
3. Umesh Site engineer Ma Vindhayawashini nil
4. Rakesh singh Forman Ma Vindhayawashini
List of Equipment on Site:
S.N. Description Units Available
1. J.C.B.
Nos 1
2. Concrete Mixer Nos 1
3. Vibrator Nos 3
4. Needle Nos 3
5. Bar Cutting Machine Nos 1
6. Generator Nos 1
7. Plate 600*1200 Nos 150
8. Plate600*900 Nos 50
9. Jack Nos 150
10. Pump Nos 1
Site Photographs
Photo 1 – Concrete Pouring
Photo 2 – Steel Checking
Photo 3 - Shuttering of Columns
Photo 4 – Boundary Wall Progress
Photo 5 - Dewatering of trenches through pumps
Photo6 – Construction of Retaining wall
Photo 7 – Shuttering of retaining wall
Photo 8: Casted retaining wall
Photo 9: Curing of casted columns
Photo 10: Formwork of retaining wall
Photo 11:Boundary wall construction.
Photo 12: Shuttering of Column