  • 8/12/2019 Footings Foundations

    1/89

    BUILDING TECHNOLOGY II

    FOOTINGS AND FOUNDATIONS

  • 8/12/2019 Footings Foundations

    2/89

    FOOTINGS

    Footings are the first part of a house that is built,

    and they stop your house shifting from its

    intended position.

    Every new house and extension will need new

    footings, the footings will need to be specified by

    an engineer ( or possibly architect if they are very

    straight forward). There are a number of factors which will

    determine the type of foundations you will need.

  • 8/12/2019 Footings Foundations

    3/89

    SITE CONSTRAINTS

    Each site is unique, the slope, soil type and

    rock position will all affect the design of your

    footings. If there is any slope to your site you

    may need to do some cut and fill excavation or

    you may have a site with uneven rock under

    the soil. Footings need to have even bearing

    on solid ground, this means that the concreteneeds to sit on rock or very hard compacted

    earth.

  • 8/12/2019 Footings Foundations

    4/89

    EXCAVATION

    The excavation of footings will be done with a

    bobcat or excavator. If you need to drill piers

    then the excavator that you hire will need to

    have a orger bit attachment. You may need to

    consider how the excavator will access your

    site and where the excavated earth will go, are

    there some garden beds planned for near thehouse.

  • 8/12/2019 Footings Foundations

    5/89

  • 8/12/2019 Footings Foundations

    6/89

    HOW TO DECIDE WHICH FOOTING

    SYSTEM TO USE:1. The type of house you are building:

    If you are building a house which includes many of thefollowing, then your house will be heavy. This means that yourfooting system will need to be substantial to handle the higher

    loads, and will typically come at an increased cost.

    Concrete slabs

    Double brick walls (known as "full-brick")

    Multi-storey (particularly if concrete slabs are used forfloors at all levels)

    Tile roofing

    Large load-bearing concrete columns and walls ("framing").

  • 8/12/2019 Footings Foundations

    7/89

    If you are building a house which includes many of thefollowing, then your house will be lighter and you will beable to use a foundation system which typically would notcost as much.

    Steel frame (advantage is they are truly straight, andunaffected by vermin)

    Timber frame

    Virtually any floor system which is not concrete Cladded walls (metal or timber)

    Metal roofing

  • 8/12/2019 Footings Foundations

    8/89

    2. The type of ground you are building on

  • 8/12/2019 Footings Foundations

    9/89

  • 8/12/2019 Footings Foundations

    10/89

    DETAILS OF WOODEN FOOTING

  • 8/12/2019 Footings Foundations

    11/89

  • 8/12/2019 Footings Foundations

    12/89

    FOUNDATION

    Foundations for wood-frame structures are built

    to take advantage of the structures ability to

    spread the load out over a wider area rather than

    concentrating it on columns. Because of this, it isimportant for the footings to be placed deep

    enough in the ground to avoid freeze/thaw cycles

    There are two primary options for foundationsfor wood-frame structures: concrete and pressure

    treated wood.

  • 8/12/2019 Footings Foundations

    13/89

    PRESSURE TREATED WOOD

    FOUNDATION

  • 8/12/2019 Footings Foundations

    14/89

    By eliminating the concrete floor slab, wooden

    foundations are best used in areas with heavy

    precipitation, which can cause problems with

    the concrete. It is important that the wood bepressure treated to ensure that the structural

    stability of the wood is not compromised due

    to insects and moisture.

  • 8/12/2019 Footings Foundations

    15/89

    CONCRETE SLAB FOUNDATION

  • 8/12/2019 Footings Foundations

    16/89

    DETAILS OF WOODEN FOUNDATION

    A. Anchor boltsB. Ledger board

    C. Joists (typical)

    D. Band board

    E. Vertical post

    F. Concrete footing (shown with form)

  • 8/12/2019 Footings Foundations

    17/89

  • 8/12/2019 Footings Foundations

    18/89

  • 8/12/2019 Footings Foundations

    19/89

  • 8/12/2019 Footings Foundations

    20/89

  • 8/12/2019 Footings Foundations

    21/89

    LESSON 1:FOUNDATION

    UNIT1: FOUNDATION

    Brief History

    Therefore, whosoever heareth these saying of mine,

    doeth them, I will liken him onto a wise man, whichbuilt his house upon a rock, And the rain descends,

    and the floods came, and the winds blew, and beat

    upon the house, and it fell not for it was founded

    upon a rock.

  • 8/12/2019 Footings Foundations

    22/89

    Matthew 7:24-25

    The advanced knowledge brought about by the science of Geology andSoil mechanics have confirmed the rock foundation bed to be the most

    stable medium where to lay the footing of the structure . The early buildings of the babylonian Empire constructed Raft or Mat

    foundation from out of the sundried and burned bricks on top of flatmoulded earth which was filled up from 1.50m. to 4.50meters high Themany foundation was constructed to a thickness of 1.00. to 1.50meters ofbrick platform bound together by a natural asphaltic material forming a

    solid foundation where the city walls, temples and public buildings, wereconstructed.

    The Greeks extensively used marble blocks as foundation oftenly tiedtogether with metal band likewise, the Chinese buildings also used largestones carefully cut and accurately fitted to each other without the use ofmortar as evidently seen in the construction of the Great Wall of China.

  • 8/12/2019 Footings Foundations

    23/89

    The Roman builders introduced various foundation types tosuit the soil condition Woodpiles were used on very soft

    ground and ground and wooden mats were laid undergroundwhere masonry structure were built upon them. The Romanbuilders further developed, this early use of concrete, wasforgotten consisting of flat stone bonded with cement which,unfortunately, this erly use of concrete, was forgotten duringthe middle ages.

    The introduction the grillage footing resolved the problem offoundation weight in the year 1880 when it was firstintroduced. The improved grillage footing made of steel railembedded in concrete was introduced in Chicago by JohnRoot in the year 1891. The advent of reinforced concrete in

    the early part of 1890. superceded all these kind of footingdue to the advantage it offered in all aspect of buildingconstruction.

  • 8/12/2019 Footings Foundations

    24/89

    UNIT2: SOIL AS A FOUNDATION

    The earth underlying the building of man provides theultimate support of the structure against all elements ofnature. Thus, the soil where the building stand automaticallybecomes a material of construction Physically, soil is amaterial to carry load satisfactorily, a greater area of volume

    of soil is necessarily required. Loads that are carried by thesteel, concrete, and wood has to be transmitted to the groundbut in needs a transfer device called foundation.

    Foundation has its purpose, to transmit the collective buildingload to the in such a way that the supporting soil will not be

    overstressed (load) and will not undergo deformation thatmay cause serious building settlement.

  • 8/12/2019 Footings Foundations

    25/89

    A structural foundation performs properly only if thesupporting soil behaves properly. Building support is providedby a soil foundation system, which is an in separable

    combination. Considering that soil foundation systemresponsible for proving support for the lifetime of thebuilding, all forces that may not over that time period must beconsidered. For the building to last, its foundation must bedesigned for the worst conditions that may develop.

  • 8/12/2019 Footings Foundations

    26/89

    Typically, foundation design always include the

    following1. the effect of the natures dead load plus

    the live load

    2. Load effects caused by wind, heat, water,earthquake

    3. Explosive blasts

  • 8/12/2019 Footings Foundations

    27/89

    Foundation are grouped into two boad

    categories:

    1. Spread footing

    2. Mat or Raft foundations

  • 8/12/2019 Footings Foundations

    28/89

    Shallow foundations includes:

    a. Spread footing

    b. Mat or Raft foundations

  • 8/12/2019 Footings Foundations

    29/89

    Deep foundations also includes:

    a. Piles

    b. Pilesc. Caissons

  • 8/12/2019 Footings Foundations

    30/89

    The Floating Foundations is a special category

    of foundation and is not a different type but it

    represents a special application of soil

    mechanics principles to combination mat-caisson foundation

  • 8/12/2019 Footings Foundations

    31/89

    The General types of foundations are:

    1. Spread Footing

    2. Mat or Raft Foundation3. Piles and Pier Foundation

    4. Floating Foundation

  • 8/12/2019 Footings Foundations

    32/89

    Spread footing

    Spread Footing is typically of plan concrete or reinforced

    concrete. Basically, it is used to spread put building column

    and wall loads over a sufficiently large soil area.

    Spread footing are constructed as close to the ground surface

    as the building design permits and as controlled by local

    conditions and building regulations. To be classified as spread

    footing, the foundation does not have to be on shallow depth.

    However, spread footing will be located deep enough into

    ground if soil conditions or building design requires.

  • 8/12/2019 Footings Foundations

    33/89

    The spread footing foundations for building columns and wall

    have a common shape of:

    1. Square

    2. Rectangular

    3. Trapezoidal

    4. Long Strips

  • 8/12/2019 Footings Foundations

    34/89

    Mat or Raft Foundations

    The mat or raft foundation is considered a largefooting extending over a wide area. Frequently, theentire area is occupied by mat or raft foundation.

    The mat foundation is adopted in a condition where

    individual column footings (if used) would tend to becloser with each other or tend to overlap. The typeof foundation is utilized as a means to reducedifferential settlement between adjacent areas. Themat structure should be rigid and thicker than spread

    footing to function effectively.

  • 8/12/2019 Footings Foundations

    35/89

    Pile and Pier Foundations

    Pile and pier foundation is intended to transmit structuralload through the upper zone of poor soil to a depth where theearth is capable of providing the desired support. The type offoundation is utilized where it is necessary to provideresistance to uplift or where is a possible loss of ground orerosion due to flowing water. Piles are slender foundationunits driven into place. Pier units are formed in place byexcavating an opening to the desired depth where concrete ispoured. Naturally, such foundations are large enough to allow

    an individual to enter and inspect the exposed earth layer.

  • 8/12/2019 Footings Foundations

    36/89

    A clear distinction between pile and pier type type foundationis not definite because of the changes and innovations inconstruction or installation methods. The developing practiceclassify all deep slender foundation units simply as pile typefoundation with terms such as driven, bored, or drilled alldeep slender foundation units simply as pile type foundationwith terms such as driven, bored or drilled and precast or castin place to indicate the method of installation and

    construction . A caisson is a structural box or chamber that is sunk in place

    or built in place by excavating systematically below thebottom of the unit which descends to the final depth.

  • 8/12/2019 Footings Foundations

    37/89

    Open caisson maybe: box type or pile type. The top and

    bottom are opening during installation. When in place, the

    bottom maybe sealed with concrete if needed to keep out ofwater. Sometimes the bottoms are socketed into rock to

    obtain a high bearing capacity.

    Pneumatic caissons have the top and side sealed and use

    compressed air to prevent water and soil from entering thelower chamber where excavations to advance the caissons

    occur.

  • 8/12/2019 Footings Foundations

    38/89

    Floating Foundation

    The floating foundation is a special type of foundation appliedin location where deep deposits of compressible cohesivesoils exist and the use of piles is impractical. The floatingfoundation concept requires that a building substructure(below the ground structure) be assembled as a combinationmat and caisson to create a rigid box. This foundation isinstalled to a selected depth that the total weight of the soilexcavated for the rigid box is equal to the total weight of theplanned building. In theory, the soil below the structure occur

    when the bottom of the excavation expands after excavationand recompresses during and after the construction

  • 8/12/2019 Footings Foundations

    39/89

    Piles

    By definition, piles is a structural member of

    small cross-sectional area with reasonable

    length driven down the ground by means of

    hammer or vibratory generators.

  • 8/12/2019 Footings Foundations

    40/89

    Piles are classified according to:

    a. Type and size

    b. Shape as to the cross-sectionc. Material

  • 8/12/2019 Footings Foundations

    41/89

    As to the kind of material

    a. Timber pile

    b. Concrete pile

    c. Metal pile

  • 8/12/2019 Footings Foundations

    42/89

    The important functions and uses of Piles:

    The decision to use pile foundation is the result of scientific

    method of exploration and tests of the underlying soilconducted by designing engineers which were brought about

    by any one of the following purpose:

  • 8/12/2019 Footings Foundations

    43/89

    a. As friction pile at their bottom portion transmitting the load

    through soft strata into stiffer lower strata.

    b. As friction pile utilizing its full length.

    c. As soil compactor

    d. As end bearing column

    e. As stabilizer of banks

    f. As batter pile

    g. As a dolphin

    h. As sheeting

  • 8/12/2019 Footings Foundations

    44/89

    Unless batter piles are intended to be effective in serving any

    one of these functions, they should not be utilized, otherwise,

    driving piles without any purpose will be expensive exercise in

    futility.

  • 8/12/2019 Footings Foundations

    45/89

    UNIT 3: POST AND COLUMUS

    Wooden post

    The traditional methods of construction utilizing wood as post

    have been outmoded by reinforced concrete column and the

    use of load bearing masonry blocks. The use of lumber in

    most construction is now limited to floor and roof framing,

    studs and joists, ceiling and paneling. Lumber material is fast

    becoming are and costly despite of its being inferior in quality.

    Lumber, which is most abundant and a cheap construction

    material something ago has turned out to become hot itemtoday.

  • 8/12/2019 Footings Foundations

    46/89

    For brief historical background, the construction of

    building with wooden post is briefly discussed as

    follows:

    1. wooden post to rest on a concrete footing is dressed with

    its bottom end squared and trimmed perpendicular at its side.

    2. A charcoal or chalk mark is established along the face

    length of the post connecting both ends. This marking willserve as the reference line for checking its vertical position

    with the aid of plumb bob.

  • 8/12/2019 Footings Foundations

    47/89

    3. From the bottom of the post, measure and indicate theheight of the girder and girts, make the necessary dap beforeits erection to assure that the girder and girts are in the

    horizontal level. However, it is assumed that the concretefooting is horizontally leveled with the floor line.

    4. The post could be erected manually using 2*3 lumberbraces and man power or by the use of rope and pulleymounted on a jump-pole.

    5. Check the vertical position of the post on two sides with theaid of plumb bob, then have it permanent position. The size ofthe drill must be the same as that of the machine bolts.

    6. With boring tools, drill a hole across the opposite strap andhave it bolted to its permanent position. The size of the drillmust be the same as that of the machine bolts.

  • 8/12/2019 Footings Foundations

    48/89

    In most cases, not all wooden post selected for post

    structures are straight. Some are bowed slightly curved but

    thry could be corrected in the process of construction.

    Bent posts are erected in a counter-bend position with other

    post facing toward the outside of the building perimeter. After

    mounting the girder and floor joist-straightening operation

    could follow.

    However, no attempt should be done through the use of a barclamp or a rope as shown in Figure 4-2. The common failure

    of this process is the crushing of footing pedestal caused by

    twisting of the wrought iron post strap. However, it could be

    prevented with a proper diagonal and horizontal bracing atthe lower potion of the wooden post along the post strap.

  • 8/12/2019 Footings Foundations

    49/89

    Column

    Reinforced Concrete

    The term column is loosely used in a general sense for anysupport such as a post or pier. The chief purpose of a columnis to support a floor and roof beam or arch. Most columns arefree standing; some however, are integrated, that is , part of

    the circumference is embedded in a wall.

  • 8/12/2019 Footings Foundations

    50/89

    Reinforced concrete columns are classified

    into two:

    1. Short column-when the unsupported height is not greaterthan times shortest lateral dimension of the cross section.

    2. Long column-when the unsupported height is more than

    ten times the shortest dimensions of the cross section.

  • 8/12/2019 Footings Foundations

    51/89

    Columns are classified according to the types

    of reinforcement used:

    1. Tied column

    2. Spiral column

    3. Composite column

    4. Combined column

    5. Lally column

  • 8/12/2019 Footings Foundations

    52/89

    The cross section of a column is either

    1. Square2. Rectangular

    3. Circular

    4. Elliptical

    5. Octagonal or any other geometrical forms depending upon

    the needs and tastes of the designer.

  • 8/12/2019 Footings Foundations

    53/89

    Tied Column

    Tied column has reinforcement consisting of vertical or

    longitudinal bars held in position by lateral reinforcementcalled lateral ties. The vertical reinforcement shall consist of at

    least 4 bars with a minimum diameter of 16mm or number 5

    steel bars.

  • 8/12/2019 Footings Foundations

    54/89

    Lateral Ties-the ACI code on lateral ties

    provides:

    All non-prestressed bars for tied column shall be enclosed by

    lateral ties of at least NO. 3 bar size for longitudinal bars NO.

    10 or smaller and at least NO. 4 size for NO. 11, 14 and 18 and

    bundled longitudinal bars. The spacing of the ties shall not

    exceed 16 longitudinal bar diameter or the least dimension of

    the column.

  • 8/12/2019 Footings Foundations

    55/89

    The Code is specific as to the size of the lateral ties

    required with respect to the size of the longitudinal

    bars, which is the main reinforcement of the column,thus:

    1. A No. 3 or 10mm lateral tie is required if the main

    reinforcement of the column size is No. 10(32mm) or smaller.

    2. No. 4(12mm) lateral ties shall be used if the main

    reinforcement size of the column is either Nos. 11, 14 or

    18(36mm, 45mm or 57mm) steel bars.

  • 8/12/2019 Footings Foundations

    56/89

    The spacing of the lateral ties of a tied column is governed by

    conditions:

    1. That the distance should not be more than 16 times thediameter of the main reinforcing bar.

    2. That the spacing should not be more than 48 times the

    diameter of the lateral ties.

    3. Spacing should not be more than the shortest dimension ofthe cross section of the column.

  • 8/12/2019 Footings Foundations

    57/89

    To find the spacing of a lateral tie required for

    a tie column the following illustration is

    presented:

    Determine the spacing of the lateral ties for

    a tied column as shown in figure 8-3.

  • 8/12/2019 Footings Foundations

    58/89

    Solution:

    1. The diameter of the longitudinal bar is 20mm.

    2. Multiply 16*20mm=320mm or 32cm

    3. Multiply 48*10mm=480mm or 48cm.

    4. The shortest dimension of the column is 35cm.

    F th lt f th b t ti it ld b

  • 8/12/2019 Footings Foundations

    59/89

    From the result of the above computation, it could be seenthat the least value found is 32cm. Therefore, the spacing ofthe lateral ties will be 32cm. On center.

    When there are more than 4 vertical bars in a tied column,

    additional ties shall be provided to hold the longitudinal barsfirmly to its designed position. The Code further states:

    The tie shall be so arranged that every corner and thealternate longitudinal bar shall have lateral support providedby the corner of the tie having an inclined angle of not more

    than 135 degrees and no bar shall be farther apart than 15cm.Clear on either side from such a laterally supported bar.

  • 8/12/2019 Footings Foundations

    60/89

    Reinforcement Ratio and Limitation

    The size and number of steel bars to be places in a tiedcolumn is governed by the proportion of its cross sectionalarea to the gross area of the column. The Code so providesthat:

    The cross sectional area of the vertical reinforcement shallnot be less than 0.01 nor more than 0.08 times the gross areaof the column section.

    Find the minimum and maximum steel bars that could beplaced in a tied column having a cross sectional dimension of

    25*30cm. In figure 8-5.

  • 8/12/2019 Footings Foundations

    61/89

    Solution:

    A. Determine the Minimum Reinforcement Area:

    1. The cross sectional area of the column is:25*30=750sq.cm

    2. Find the minimum area of the vertical reinforcement area

    0.01*750=7.5sq.cm

    3. Convert this area to the size and number of steel barswith the aid of Table 10-1 and 10-4 Area of 4pcs. No. 5

    (16mm) bar=8.04sq.cm

  • 8/12/2019 Footings Foundations

    62/89

    B. Determine the Maximum Reinforcement Area

    1. 0.08*750=60sq.cm Maximum area of steel bars.

    2. Referring to Table 10-2

    10pcs. Of No. 9(28mm) bars=61.6sq.cm

    8pcs. Of No. 10(32mm) bars=64.3sq.cm

  • 8/12/2019 Footings Foundations

    63/89

    From the result of the illustration (Figure 8-5), the minimum

    steel bars that could be placed in a 25*30cm, column are 4pcs.

    16mm. And the maximum are either 10pcs. 28mm. Or 8pcs.32mm.

    dl d i l

  • 8/12/2019 Footings Foundations

    64/89

    Bundled Bars in a Column

    Difficulties have been experienced in placing concrete mixture

    inside forms congested with steel bars. A column that is

    heavily loaded with reinforcement has this serious problem

    when large number of steel bars are positioned and held

    individually by lateral ties. Bundled bars consisting of 2 to 4

    bars tied in direct contact with each other is somethings

    employed to using bundled bars is to accommodate therequired steel bars for the column and at the same time

    provide enough space for the concrete thereby observing the

    rules and specifications as to the spacing of bar limitation and

    the required concrete protective covering.

  • 8/12/2019 Footings Foundations

    65/89

    Failure of Tied Column

    The failure of a tied column is by crushing and shearing

    outward along an inclined plane where vertical bars fail by

    bucking outward between lateral ties. The failure of a tied

    column is said to be abrupt and complete and is considered to

    be more disastrous than the failure of a single beam girder in

    the same floor.

  • 8/12/2019 Footings Foundations

    66/89

    Methods of Constructing Tied Column

    There are three methods presented in constructing a tiedcolumn for a small and medium reinforced concrete structure:

    1. Block laying after the concreting of tied column.

    2. Concreting of the tied column after block laying.

    3. Simultaneous concreting of columns and wall.

  • 8/12/2019 Footings Foundations

    67/89

    Stock laying after the concreting of tied column.

    This type of construction is actually erecting an isolated or

    independent column providing steel dowels in anticipation ofthe installation of walls and partitions. There are two methods

    adopted in setting tied column reinforcement of the column

    on the footing by means of steel dowel embedded during the

    concreting of the footing slab. The other is directly attaching

    the main reinforcement itself to the footing slab

    reinforcement, followed by concreting of the footing slab

    ahead or monolithically with the column.

    The constr ction proced res nder this method of block la ing after the

  • 8/12/2019 Footings Foundations

    68/89

    The construction procedures under this method of block laying after theconcreting of the concreting of the tied column are as follows:

    1. Install the scaffolding that will support the column reinforcement andits form. Usually, there are 4 pieces of lumber installed vertically around

    the 4 corners of the column provided with horizontal members anddiagonal braces. The horizontal member of the scaffolding is verticallyspaced at about 1.00 meter between each layer.

    2. Transfer the marking and reference point of the building from the batterboard to the upper and lower member of the scaffolding. By the use ofplumb bob, check the vertical projections of this marking.

    3. Install the assembled tied column reinforcement directly to the footingslab reinforcement if concreting of the column and foundation aresimultaneous, or to the footing dowels if concreting of the foundation slabis ahead of the column.

    4. Provide a temporary wood brace on top and lower members of thescaffolding across the column reinforcement. Insert these braces acrossthe tied column reinforcement to hold the bars to its vertical position. The

    idea of inserting this brace across the tied reinforcement is to give way tothe mounting or installation of the column forms.

    5. Verify the vertical position of the reinforcement in the row

  • 8/12/2019 Footings Foundations

    69/89

    5. Verify the vertical position of the reinforcement in the rowof several columns in series both in either direction.

    6. Install first the narrower side forms in opposite direction onits vertical position.

    7. Do not cover the form until after the following accessorieshave been verified from the plan and installed, if there is:

    a. Downspout

    b. Electrical conduits and utility boxes

    c. Stand pipe or fire hydrant d.Plumbing soil and water supply line e.Telephone line f.Burglar alarm line g.Intercom door bell line

    h. Steel dowels for walls and partitions, etc.

    8. Have the work inspected by authorized inspectors or

  • 8/12/2019 Footings Foundations

    70/89

    8. Have the work inspected by authorized inspectors orsupervisions. This is done as a matter of procedures to giveaccess to the inspector to see everything inside the formbefore it is closed.

    9. Before covering the form, see to it that the wide cover isprovided with charcoal line mark and nail as a guide to assurethe column size and in fixing the form to its vertical position.All dirt and debris inside the form shall be removed before

    covering. 10. Do not leave the forms if it is not firmly set and completely

    supported. Most of the bulging failures of forms are due tonegligence and the inherited manana habit attitude.

    11. Verify if the form is provided with window opening for

    pouring of concrete at lower elevation pouring of concrete athigh elevation is one cause of segregation of particles

    Concreting of column after block laying of walls

  • 8/12/2019 Footings Foundations

    71/89

    Concreting of column after block laying of walls

    Under this type of construction, which is very common, the

    wall footing and the column footing are worked and

    concreted ahead. The column and the wall reinforcement areset into its final position followed by installing masonry blocks

    then concreting of the column.

  • 8/12/2019 Footings Foundations

    72/89

    The methods of construction are as follows:

    1. After the excavation of the soil, guide post for block laying

    is prepared and installed about the corner of the wall line.This guide post is usually lumber of the size from2*2 or 2*3

    erected vertically in plumb line to serve as guide of the mason

    for his block laying work.

    2. Concretion of the wall footing is followed immediately byconcrete block laying. The idea is to have a strong bond

    between the footing and the masonry block aside from the

    saving in the use of mortar.

    3 The tied column footing is concreted much ahead than the

  • 8/12/2019 Footings Foundations

    73/89

    3. The tied column footing is concreted much ahead than thewall footing with the column reinforcement embedded on it.Masonry block laying stops where it meets the columnreinforcement.

    4.after the block laying, the forms for the column are installedand properly braced, but see to it that accessories such asdownspouts, electrical conduits, etc. are also installed if calledfor the plans.

    5.prior to the pouring of concrete mix to the column, theinside space of the forms are cleared with dirt, sawdust,debris and washed thoroughly then grouted before pouring ofconcrete.

    The popularity of this method of construction is

  • 8/12/2019 Footings Foundations

    74/89

    The popularity of this method of construction is

    attributed to the following advantages:

    1. This method of construction requires less material

    for forms scaffolding and bracing.

    2. Once the column form is mounted, G.I. tie wire

    could be sufficient to hold the form in rigid position

    3. The bond between the wall and the column isstronger than when they are connected by mortar as

    in the other method of construction.

    4. Cracks between the wall and the column are

    unlikely or seldom appear on the surface.

    h h l b d bl k l l d

  • 8/12/2019 Footings Foundations

    75/89

    5. The horizontal bars used in block laying are laidcontinuously across the column reinforcement. This processminimize the horizontal overlapping of splices and

    consequently eliminate the use of horizontal dowelssupposed to be inserted across the column in preparation forthe wall construction if column concreting is ahead of theblock laying.

    6. The column will not be affected much by shocks or

    vibrations caused by the removal of forms because thecolumn is laterally supported by the hollow block walls andonly two forms are to be removed.

    7. The work is fast, easy, and economical with less destruction

    of forms, lumber braces and supports, waste of nails andlabor aside from the handy handing in transferring andreinstalling of the forms.

  • 8/12/2019 Footings Foundations

    76/89

    The methods of construction under the third category of

    simultaneous pouring for column and walls in one setting of

    mixing could only be made possible if the concrete mixture

    for both the wall and columns are of the same proportions.

    Otherwise, if the concrete proportion of column differs from

    that of the wall, one structure must be poured ahead using

    each specified mixture proportions. In such a case, the

    column has the priority, which in effect, the methods ofconstruction fall under the first category.

  • 8/12/2019 Footings Foundations

    77/89

    Spiral Column

    Spiral column is the term given where a circular concrete coreis enclosed by spirals with vertical or longitudinal bars. The

    vertical reinforcement is provided with evenly spaced

    continuous spiral held firmly in position by at least three

    vertical bar spacers. The column reinforcement is also protected by a concrete

    covering cast monolithically with the core. Comparatively, this

    type of column is stronger than the tied column and is

    preferred for a slender (long) column in carrying heavy load.

    Wh l d i i d li d i l l l t l

  • 8/12/2019 Footings Foundations

    78/89

    When a load is imposed on a cylindrical column, a lateralpressure is exerted at the confining materials, whicheventually causes hoop tension in the spiral. A closely spaced

    spiral, confining the concrete and vertical bar, counteracts thelateral expansion, while the concrete in the core increases itscarrying capacity. The sign of failure of spiral column isadvanced by the shell (protective covering) spall due toexcessive load, but failure of the column occurs only when the

    spirals yield or burst. Unlike the tied column that fails abruptly, the spiral column

    with heavy spirals shows a gradual and ductile failure.

    Spiral reinforcement limitation and Spacing

  • 8/12/2019 Footings Foundations

    79/89

    Spiral reinforcement limitation and Spacing

    or cast in place of construction, the following should be observed:

    1. The spiral column shall have a minimum diameter of 10 mm,

    or 1cm.

    2. The clear spacing between the spirals shall not be more

    than 7.5cm. Or less than 2.5cm.

    3. The longitudinal reinforcement area to the gross column

    area shall not be less than 0.01 nor more than 0.08.

    4. The minimum number of vertical bars shall not be less than

    6 pieces of 16mm. Bar diameter.

    Section 7-12 2 of the ACI Building Code provides that: Spiral

  • 8/12/2019 Footings Foundations

    80/89

    Section 7 12 2 of the ACI Building Code provides that: Spiralreinforcement for compression members shall consists ofevenly spaced continuous spiral held firmly in place and trueto the line by vertical spacers. At least two spacers shall be

    used for spirals less than 50cm. diameter, three for spirals50cm. to 75cm. In diameter and four spaces for more than75cm. Diameter.

    When bigger size of steel bar is used for spiral such as 16mm.Or larger, three spaces shall be used for a spiral having 60cm.

    diameterThe spiral shall be protected from distortion due tohanding and placing from the designed dimensions.

  • 8/12/2019 Footings Foundations

    81/89

    Spiral Anchorage and Spacing

    The anchorage of spiral reinforcement shall be provided byone and a half-extra turn of spiral bar or wire at each end of

    the spiral unit. When splices are necessary for special bars itshall be tension lap splices with 48 bar diameters as minimumbut in no cases shall be less than 30cm. or welded.

    The reinforcing spiral shall extend from the floor level in anystorey or from the top of the footing to the level of the lowest

    horizontal reinforcement in the slab, drop panel or beamabove. Where beams or brackets are not present on all sidesof the column, ties shall extend above the terminal of thespiral to the bottom of the slab or drop panel. In a columnwith a capital, the spiral shall extend to a plane at which thediameter or width of the capital is twice that of the column.

  • 8/12/2019 Footings Foundations

    82/89

    Composite, Combined and Lally Column

    Composite column is another type of column where structuralsteel column is embedded into the concrete core of a spiralcolumn. The work involved under this type of column issimilar to that of a spiral column after the structural steelhave been set to its position.

    The combined column is a column with a structural steelencased in concrete of at least 7cm. Thick reinforced withwire mess surrounding the column at a distance of 3cm.Inside the outer surface of the concrete covering.

    The construction process of a combined column calls for the

  • 8/12/2019 Footings Foundations

    83/89

    The construction process of a combined column calls for the

    installation of the structural steel as the main reinforcement

    followed by the attachment of the wire mesh covering. The

    wire mesh serves as the holding rids of the encased concrete.Usually the wire mess is attached to the structural steel by

    weld. The forms are similar to that of the tied column

    construction as previously discussed.

    Lally column is a fabricated post made of steel pipe providedwith a plain flat steel bar or plate which hold a girder, bear or

    girts. The steel pipe is something filled with a grout or

    concrete for additional strength and protection from rust and

    corrosion.

  • 8/12/2019 Footings Foundations

    84/89

    The Relationship Between the Material and the Structure

    Building structure has to be distinguished from buildingmaterials. Although, the quality and durability of the materialis a prime consideration, material in its original form as a unithas nothing to do with the strength of participation insupporting load nor resisting forces unless utilized as part of

    the structural. The combination of different building materialsthat make it into a building part is called building structure.The utilization of the different materials in the structure hastheir own purpose of service in counteracting the differentforces affecting the structure. This is where design comes in to

    determine the sizes, quantity, quality, spacing, proportions,etc.

    Although this subject matter is beyond the scope of this book

  • 8/12/2019 Footings Foundations

    85/89

    Although this subject matter is beyond the scope of this book

    to discuss stresses, moments, compression, torsion and the

    like is considered as important matter since to discuss those

    terms briefly will orient the beginner and future builders ofthe rudimentary knowledge on how these terms influences

    the principle on designing structure. Likewise, the reacting

    behaviors of the structure when different forces are applied

    on it are also relevant in the knowledge of buildingconstruction.

    Th diff t ki d f t th t t

  • 8/12/2019 Footings Foundations

    86/89

    The different kinds of stresses that may act on

    structures are:

    1. Compressive Stresses2. Tensile (Tension) Stresses

    3. Shear and Strain Stresses

    4. Torsion Stress and Strain

    Stresses on structures are usually brought

  • 8/12/2019 Footings Foundations

    87/89

    Stresses on structures are usually brought

    about by load, which are classified into three

    categories:a. Live load

    b. Dead load

    c. Environmental load

    Live Load refers to the occupancy load which is either

  • 8/12/2019 Footings Foundations

    88/89

    Live Load-refers to the occupancy load, which is eitherpartially or fully in place or may not be present at all.

    Dead load-are those loads that are distributed or

    concentrated, which are fixed in position throughout thelifetime of the structure such as the weight of the structureitself.

    Environment load-consist of wind pressure and suctions,earthquake, rainwater on flat roof, snow and forces caused bytemperature differentials.

    Strength-is the cohesive power of the materials that resist anattempt to pull it apart in the direction of its fiber.

    Ultimate Strength-is the maximum unit of stress developed at

    anytime before rupture.

    Moment is a kind of alteration or deformation produced by

  • 8/12/2019 Footings Foundations

    89/89

    Moment-is a kind of alteration or deformation produced by

    the stresses.

    Strain-is a kind of alteration or deformation produced by the

    stresses.

    Stress-is an internal action set up between the adjacent

    molecule of the body when acted upon by forces, or

    combination of forces, which produces strain. Stress refers too

    the pressure of load, weight and some other adverse forces orinfluences.