Flower Mound Riverwalk RFQ

59
Town Council Meeting Town of Flower Mound August 19, 2013 Town of Flower Mound Denton County, Texas PUBLIC IMPROVEMENT DISTRICT

description

 

Transcript of Flower Mound Riverwalk RFQ

Page 1: Flower Mound Riverwalk RFQ

Town Council Meeting Town of Flower Mound

August 19, 2013

Town of Flower Mound Denton County, Texas

PUBLIC IMPROVEMENT DISTRICT

Page 2: Flower Mound Riverwalk RFQ

Centurion American Mehrdad Moayedi

President

Jack Dawson Vice President of Development

T. Kirk Wilson T. Wilson & Associates

Centurion American Development Group

www.centurionamerican.com

Page 3: Flower Mound Riverwalk RFQ

Centurion American • Since 1990 developed well over 10,000 single-family lots

and have acquired over 15,000 acres of land • Award winning communities with impeccable amenities

• Open Space Areas • Community Pools and Splash Areas • Clubhouses

• 2011 Largest Residential Developer • Largest Residential Developments Include:

• Trophy Club (#1) • Woodland Springs VII (#6) • Frisco Ranch (#13) • Rolling Meadows (#19)

• Urban Developments Include: • Downtown Dallas – Including Stoneleigh Tower • University Park

• Developments in the Nearby Area Include: • Terracina • Estancia Estates • Montalcino Estates • Legends

• Projects Starting Include: • Savannah, Southlake • Granada, Westlake • Barcelona, McKinney

Legends

E Estancia Estates

Page 4: Flower Mound Riverwalk RFQ

Team Members

Robert J. Dollak, Jr., PE Senior Project Engineer

Ron A. Stewart, ASLA Landscape Architect

Randi L. Rivera, AICP Senior Planner

Scott Minnis, EIT Project Manager

Integrity-Based Relationships Bringing Together Community and Site

Development

Offices in Roanoke and

Lewisville

www.gacon.com

Page 5: Flower Mound Riverwalk RFQ

Previous Vision

Page 6: Flower Mound Riverwalk RFQ

Property Purchased

Page 7: Flower Mound Riverwalk RFQ

Ground-Breaking

Page 8: Flower Mound Riverwalk RFQ

Public Improvement District

107 Acres

Page 9: Flower Mound Riverwalk RFQ

Enhancement Areas

River Walk Amenity

Amphitheater

Chapel

Entertainment District

Page 10: Flower Mound Riverwalk RFQ

Original Amenities Estimated Costs: Central Park: $1.6M River Walk Amenity: $1.5M

Page 11: Flower Mound Riverwalk RFQ

Enhanced River Walk Amenity Pole Lighting Enhanced Landscaping

Pedestrian Bridge and Specialty Lighting

Benches and Trash Receptacles

Sculpture Platform Enhanced Rock Weir / Water Fall w/ LED Lights

Grade Transition with ADA Ramps and Flagstone Steps

and Boulders

Bollard Lighting

Enhanced Paving

Special Lighting

Naturalistic Rock Channel w/ Rock Edges

Speakers Along Pedestrian Path

Page 12: Flower Mound Riverwalk RFQ

Enhanced River Walk Amenity

Page 13: Flower Mound Riverwalk RFQ

8’ Waterfall

Water Scupper on Arched Flying Buttress

4’ Stepped Water Cascade

River Walk Channel Level

Arched Flying Buttresses w/ Water Scupper

Street Level Pedestrian Plaza Recessed Stone Arched Section

Water Cascade w/ Inset Lighting

Water Wall w/ LED Lighting

Shade Tree Overstory w/ Enhanced Landscape at

Pedestrian Level

Enhanced River Walk Amenity

Page 14: Flower Mound Riverwalk RFQ

Enhanced River Walk Amenity

Enhanced Waterfalls

Page 15: Flower Mound Riverwalk RFQ

Enhanced River Walk Amenity

Features of Water Wall

Page 18: Flower Mound Riverwalk RFQ

Enhanced River Walk Amenity

Outdoor Speakers Integrated into Landscape

Enhanced Pavement

Page 19: Flower Mound Riverwalk RFQ

River Walk Comparison Item Original River Walk

Amenity Proposed River Walk

Amenity

Waterfalls X Enhanced

Rock Edges X

Sidewalks X X

Specialty Lighting X

Bollards X X

Pole Lights X X

Benches & Trash Cans X X

Outdoor Speakers X

Water Wall as Backdrop X

Sculptures X

Landscaping X Enhanced

Enhanced Pavement X

Trees X X

$1.5M $2.2M PLUS

Page 20: Flower Mound Riverwalk RFQ

Enhanced Amphitheater

Stage

Backstage / Greenroom / Dressing Room / Storage

Vendor Area

Pavilion

Interactive Fountain / Splash

Park

Plaza w Enhanced Paving

Kiosk Restrooms

Sloped Retaining Wall for At-Grade Entry

Vendor Area

Entry Plaza with Water Feature and Public Art

Vehicular Access to Stage

Recessed Seating

Raised Seating

Restrooms

Water Wall with River Walk Amenity

8’ Arched Retaining Wall w/ 2’ Parapet and 4’ Wrought Iron Fence

Entry Rooftop w/ Sound Board and Stage Lighting

Page 21: Flower Mound Riverwalk RFQ

Enhanced Amphitheater

Seating

Page 22: Flower Mound Riverwalk RFQ

Enhanced Amphitheater

Stage with Equipment (Sound & Lighting)

Page 23: Flower Mound Riverwalk RFQ

Enhanced Amphitheater

Interactive Fountain/Splash Pad

Page 25: Flower Mound Riverwalk RFQ

Enhanced Amphitheater

Outdoor Speakers Integrated into Landscape

Enhanced Pavement

Page 26: Flower Mound Riverwalk RFQ

Enhanced Amphitheater

Kiosks

Page 27: Flower Mound Riverwalk RFQ

Amphitheater Comparison Item Original Enhancements

Seating Area X Enhanced

Restrooms X Enhanced

Stage X Enhanced

Backstage/Greenroom X

Lighting & Equipment X

Splash Pad X

Benches & Trash Cans X X

Trees X X

Fountains X Enhanced

Sculptures X Enhanced

Landscaping X Enhanced

Enhanced Pavement X Enhanced

Kiosk/Pavilion X X

½ of Parking Structure X

$1.6M $6.1M PLUS

Page 28: Flower Mound Riverwalk RFQ

Chapel

210 Seat Chapel

Page 29: Flower Mound Riverwalk RFQ

Chapel

Chapel

Page 30: Flower Mound Riverwalk RFQ

Chapel

Door

Interior Furnishings

Page 31: Flower Mound Riverwalk RFQ

Chapel

Stained Glass

Page 32: Flower Mound Riverwalk RFQ

Chapel

Statues

Page 33: Flower Mound Riverwalk RFQ

Chapel

Additional Pedestrian Bridge

Page 34: Flower Mound Riverwalk RFQ

Entertainment District

Water Aqua Duct

Restaurants

Water Mill

Statues

River Walk Amenity Farmers Market Buildings / Artisan Huts

Fountains

Enhanced Pavement

Plaza

Farmers Market

Page 35: Flower Mound Riverwalk RFQ

Entertainment District

Statues

Page 36: Flower Mound Riverwalk RFQ

Entertainment District

Water Wheel

Page 37: Flower Mound Riverwalk RFQ

Entertainment District

Enhanced Pavement

Page 38: Flower Mound Riverwalk RFQ

Entertainment District

Farmer’s Market / Artisan Huts

Page 39: Flower Mound Riverwalk RFQ

Entertainment District

Plaza Public Lighting Effects

Page 40: Flower Mound Riverwalk RFQ

Summary of Enhancements Enhancement Amount Start Date End Date

River Walk Amenity $2.2M Feb 2014 Oct 2014

Amphitheater $6.1M July 2014 Oct 2015

Chapel $3M July 2014 Oct 2015

Entertainment District $2.5M Spring 2015 Oct 2016

TOTAL $13.8M

Page 41: Flower Mound Riverwalk RFQ

PID Infrastructure

Infrastructure Item Amount

Parcel 1 $569,999.00

Parcel 2 $741,505.50

Parcel 3 --

Parcel 4 --

Parcel 5 $975,517.00

Parcel 6 $838,423.00

Parcel 7 $59,572.00

Parcel 8 --

Parcel 9 --

Parcel 10 $57,276.00

Medical Off Site $320,453.00

Common To All $9,700,513.75

TOTAL $13,263,259.25

Page 42: Flower Mound Riverwalk RFQ
Page 43: Flower Mound Riverwalk RFQ

Timber Trails

Page 44: Flower Mound Riverwalk RFQ

Central Park

Page 45: Flower Mound Riverwalk RFQ

Rebecca Falls

Page 46: Flower Mound Riverwalk RFQ

Forums Park

Page 47: Flower Mound Riverwalk RFQ

PID Infrastructure Parcel 1 = $569,999.00

Insert parcel photo from pid package here

Infrastructure Item Amount

Water $150,450.00

Sanitary Sewer $61,100.00

Storm Sewer $230,310.00

TOTAL $441,860.00

Engineering/Admin $128,139.00

GRAND TOTAL $569,999.00

Page 48: Flower Mound Riverwalk RFQ

PID Infrastructure Parcel 2 = $741,505.50

Insert parcel photo from pid package here

Infrastructure Item Amount

Water $60,460.00

Sanitary Sewer $53,280.00

Paving $262,809.50

Storm Sewer $198,261.00

TOTAL $574,810.50

Engineering/Admin $166,695.00

GRAND TOTAL $741,505.50

Page 49: Flower Mound Riverwalk RFQ

PID Infrastructure PARCEL 3 Infrastructure Costs are Common To All

Insert parcel photo from pid package here

Page 50: Flower Mound Riverwalk RFQ

PID Infrastructure

Insert parcel photo from pid package here

PARCEL 4 Infrastructure Costs are Common To All

Page 51: Flower Mound Riverwalk RFQ

PID Infrastructure

Insert parcel photo from pid package here

Infrastructure Item Amount

Water $159,230.00

Sanitary Sewer $52,800.00

Paving $249,960.00

Storm Sewer $249,225.00

TOTAL $756,215.00

Engineering/Admin $219,302.00

GRAND TOTAL $975,517.00

Parcel 3 = $975,517.00

Page 52: Flower Mound Riverwalk RFQ

PID Infrastructure Parcel 6 = $838,423.00

Insert parcel photo from pid package here

Infrastructure Item Amount

Water $172,600.00

Sanitary Sewer $72,200.00

Paving $48,200.00

Storm Sewer $356,940.00

TOTAL $649,940.00

Engineering/Admin $188,933.00

GRAND TOTAL $838,423.00

Page 53: Flower Mound Riverwalk RFQ

PID Infrastructure Parcel 7 = $59,572

Insert parcel photo from pid package here

Infrastructure Item Amount

Paving $46,180.00

TOTAL $46,180.00

Engineering/Admin $13,392.00

GRAND TOTAL $59,572.00

Page 54: Flower Mound Riverwalk RFQ

PID Infrastructure

Insert parcel photo from pid package here

PARCEL 8 Infrastructure Costs are Common To All

Page 55: Flower Mound Riverwalk RFQ

PID Infrastructure

Insert parcel photo from pid package here

PARCEL 9 Infrastructure Costs are Common To All

Page 56: Flower Mound Riverwalk RFQ

PID Infrastructure Parcel 10 = $52,276.00

Insert parcel photo from pid package here

Infrastructure Item Amount

Water $25,400.00

Sanitary Sewer $19,000.00

TOTAL $44,400.00

Engineering/Admin $12,876.00

GRAND TOTAL $57,276.00

Page 57: Flower Mound Riverwalk RFQ

PID Infrastructure Medical Off Site = $320,453.00

Insert parcel photo from pid package here

Infrastructure Item Amount

Paving $248,413.00

TOTAL $248,413.00

Engineering/Admin $72,040.00

GRAND TOTAL $320,453.00

Page 58: Flower Mound Riverwalk RFQ

PID Infrastructure Common To All = $9,700,513.75

Infrastructure Item Amount

Paving $4,779,905.75

Water $536,338.00

Sanitary Sewer $376,794.00

Storm Sewer $1,826,740.00

TOTAL $7,519,777.75

Engineering/Admin $2,180,736.00

GRAND TOTAL $9,700,513.75

Page 59: Flower Mound Riverwalk RFQ

PID Infrastructure Summary

Infrastructure Item Amount

Parcel 1 $569,999.00

Parcel 2 $741,505.50

Parcel 3 --

Parcel 4 --

Parcel 5 $975,517.00

Parcel 6 $838,423.00

Parcel 7 $59,572.00

Parcel 8 --

Parcel 9 --

Parcel 10 $57,276.00

Medical Off Site $320,453.00

Common To All $9,700,513.75

TOTAL $13,263,259.25