Flowchart 8-NY-g:NYISO Large Facility Interconnection Request
Developed by the National Renewable Energy Laboratory for the DOE
Color Key
Developer
Agency
Other
Public
Page 1 of 6
To Page 2
NYISO
8-NY-g.5
Review LFIR for completeness
8-NY-g.6
Is the LFIR valid?
Developer
8-NY-g.1
Large Facility Interconnection Request (LFIR)
NYISOProvide copy of LFIR to
Connecting Transmission Owner (CTO)
8-NY-g.3
NYISO
8-NY-g.2
Send acknowledgement notice to developer
NYISO
8-NY-g.7 5 days
LFIR Deficiency Notice
Developer
8-NY-g.8 10 days
Submit requested information to NYISO (If Applicable)
NYISO
8-NY-g.10
Forward additional information to CTO
8-NY-g.9
Is the deficiency cured within 15 days?
Yes
No
Yes
No
Version: 7 December 2016
From Flowchart: 8-NY-b - NYISO Interconnection Process
NYISO
8-NY-g.4
Assign LFIR a queue position
5 days
Flowchart 8-NY-g: (continued)NYISO Large Facility Interconnection Request
Developed by the National Renewable Energy Laboratory for the DOE
Color Key
Developer
Agency
Other
Public
Page 2 of 6
To Page 4
From Page 1
NYISO
8-NY-g.11
Send acknowledgement notice to developer and CTO
NYISO
8-NY-g.12
Interconnection Feasibility Study Agreement (FESA)
NYISO
8-NY-g.13
Schedule scoping meeting
10 days
NYISO
8-NY-g.14
Hold scoping meeting
30 days
8-NY-g.15
Is a Feasibility Study (FES) required?
Developer
8-NY-g.16 5 days
Designate point(s) of interconnection
NYISO
8-NY-g.17
Tender FESA to developer
5 days
NYISO
8-NY-g.19
Conduct FES
45 days
NYISO
8-NY-g.23
Provide Final FES report to developer
Responsible Parties
8-NY-g.20
Draft FES Report
NYISO
8-NY-g.22
Final FES Report
NYISO
8-NY-g.24
Hold FES study report results meeting
10 days
NYISO/Developer/CTO
8-NY-g.21Review draft FES Report
NYISO
8-NY-g.25
Provide cost and time estimates for completion of the
SRIS3 days
Yes
Developer
8-NY-g.18 30 days
Return FESA to NYISO with deposit
No
Flowchart 8-NY-g: (continued)NYISO Large Facility Interconnection Request
Developed by the National Renewable Energy Laboratory for the DOE
Color Key
Developer
Agency
Other
Public
Page 3 of 6
To Page 4
From Page 2
NYISO
8-NY-g.26
Interconnection System Reliability Impact Study Agreement (SRISA)
Developer
8-NY-g.30 30 days
Execute and return SRISA to NYISO and submit study fee
Developer
8-NY-g.31
Demonstrate site control
8-NY-g.27
Does the developer request an Optional
Interconnection Study (OIS)?
NYISO
8-NY-g.28
Optional Interconnection Study Agreement (OISA)Yes
No
5 days
Developer
8-NY-g.29 10 days
Execute and return OISA to NYISO and submit study fee
8-NY-g.32
Is the SRISA and/or OIS complete?
NYISO
8-NY-g.33
Notify developer of SRISA and/or OIS deficiency
5 days
Developer
8-NY-g.34 10 days
Cure SRISA and/or OIS deficiency
No
NYISO/CTO
8-NY-g.35 30 days
Execute SRISA and/or OIS
Yes
Flowchart 8-NY-g: (continued)NYISO Large Facility Interconnection Request
Developed by the National Renewable Energy Laboratory for the DOE
Color Key
Developer
Agency
Other
Public
Page 4 of 6
To Page 5
From Page 3
NYISO
8-NY-g.36
Prepare scope of SRIS and/or OIS
90 days
8-NY-g.38
Does the NYISO Operating Committee approve the scope of the SRIS and/or OIS?
NYISO/CTO/Developer/Others
8-NY-g.37
Review the scope of the SRIS and/or OIS
NYISO/CTO/Developer/Others
8-NY-g.39
Renegotiate the scope of the SRIS and/or OIS
No
Developer
8-NY-g.45 30 days
Designate SRIS or OIS to submit to NYSIO Operating Committee
(If Applicable)
Responsible Parties
8-NY-g.41
Draft SRIS and/or OIS Report
NYISO
8-NY-g.44
Hold SRIS and/or OIS study report meeting
10 days
NYISO/Developer/CTO
8-NY-g.42
Review draft SRIS and/or OIS Report
NYISO
8-NY-g.40
Conduct SRIS and/or OIS
90 days
Yes
NYISO
8-NY-g.43
Provide Final SRIS and/or OIS report to developer and CTO
NYISO
8-NY-g.46
NYISO Review Report (If Applicable)
Flowchart 8-NY-g: (continued)NYISO Large Facility Interconnection Request
Developed by the National Renewable Energy Laboratory for the DOE
Color Key
Developer
Agency
Other
Public
Page 5 of 6
To Page 6
From Page 4
TPAs
8-NY-g.47
Review SRIS or OIS
NYISO
8-NY-g.50
Class Year Interconnection Facilities Study Agreement
(CYFSA)
Developer
8-NY-g.51 30 days
Execute and return CYFSA to NYISO and CTO, and submit
study fee
NYISO/CTO
8-NY-g.52 10 daysExecute CYFSA
NYISO
8-NY-g.53
Conduct CYFS
90 days
NYISO
8-NY-g.54
Draft CYFS Report
NYISO
8-NY-g.55
Submit draft CYFS Report to developer
NYISO/CTO/Developer/Others
8-NY-g.56Hold CYFS Report meeting
10 days
NYISO/CTO/Developer/Others
8-NY-g.48Negotiate SRIS or OIS
NYISO or Consultant
8-NY-g.49
Conduct Class Year Interconnection Study (CYFS)
Flowchart 8-NY-g: (continued)NYISO Large Facility Interconnection Request
Developed by the National Renewable Energy Laboratory for the DOE
Color Key
Developer
Agency
Other
Public
Page 6 of 6
From Page 5
TPAs
8-NY-g.57
Review CYFS Report and cost allocations
END8-NY-g.58
Does the NYISO Operating Committee
approve the CYFS and cost allocations?
NYISO
8-NY-g.60
Draft Large Generator Interconnection Agreement (LGIA)
No
Developer
8-NY-g.59 30 days
Submit notice to NYISO
Yes
Developer
8-NY-g.61 30 days
Execute and return draft LGIA to NYISO and CTO
Developer
8-NY-g.63
Demonstrate site control or post additional security fee
15 days
Developer
8-NY-g.64
Provide evidence of completed milestones
Developer
8-NY-g.65
Execute and return Final LGIA to NYISO and CTO
60 days
NYISO
8-NY-g.62
Final Large Generator Interconnection Agreement (LGIA)
NYISO/CTOs
8-NY-g.66
File Final LGIA with FERC
15 days