ADDENDUM NO. 1 Page 1
Florida Governmental Utility Authority (FGUA) Lift Station No. 6 Replacement Project
FGUA Project No. PSP09
Addendum No. 1
The following are revisions and/or clarifications to the Bid Documents (Drawings and
Technical Specifications).
A. QUESTIONS
1. Question: Pages 00700-57 & 01600-6 of the specifications mention a one year
warranty. Pages 01030-9 & 01720-4 mention a two year warranty. Please advise
if the contract is to have a one year or two year warranty.
Response: The warranty period for the work shall be one-year from date of
Substantial Completion. See Section C of this addendum for revisions to Sections
01030 & 01720.
2. Question: For the installation of the new below grade structures, is a caisson method acceptable? Response: Caisson method shall not be an acceptable method of installing below grade structures.
3. Question: Can a line item be added to the bid form for compensation if sheeting
is to be left in place? (Reference page 02221-10)
Response: The base project bid shall be based on the removal of all sheeting used to facilitate construction, therefore the addition of a bid item for sheeting left in place will not be added to the bid form. If the Contractor is directed to leave any sheeting in place, this will be considered a change to the Contract and the Contractor will be compensated in accordance with the Contract Documents.
4. Question: Can the geotechnical report be posted in an addendum? (Reference
Page 00800-1)
Response: The geotechnical report and FDEP permit are being added as attachments to the Specifications. See Section C of this addendum for revision.
ADDENDUM NO. 1 Page 2
B. DRAWINGS
1. Drawing C1.01
Add the following clouded note to Drawing C1.01.
2. Drawing C2.01
Add the following clouded callout to Drawing C2.01.
3. Drawing C2.01
Add the following clouded note to Drawing C2.01.
ADDENDUM NO. 1 Page 3
C. TECHNICAL SPECIFICATIONS
1. CHANGE the paragraph in Specification Section 01030, Part 1.21, A to read as
follows:
“A. It is assumed that portions of the work will be completed prior to completion
of the entire work. Upon completion of construction in each individual
facility, including testing, if the Owner, at his sole discretion, desires to
accept the individual facility, the Contractor will be issued a dated certificate
of completion and acceptance for each individual facility. The Owner will
assume ownership and begin operation of the individual facility on that date
and the one-year guaranty period shall commence on that date. The Owner
has the option of not accepting any individual completed facility, but
accepting the entire work as a whole when it is completed and tested.”
2. CHANGE the paragraph in Specification Section 01720, Part 1.07 A to read as
follows:
“A. This manual shall contain all warranties, guarantees, bonds, certificates,
and similar documents, including those customarily provided by
manufacturers and suppliers which cover a period greater than the one-year
correction period. Show Owner as beneficiary on these documents.”
3. ADD the following paragraphs to Section 02222, Part 3.03, A.
ADDENDUM NO. 1 Page 4
“2. In general, sheeting and bracing shall be removed as the excavation is
backfilled in such a manner as to avoid the caving in of the bank or
disturbance of adjacent areas or structures. The voids left by withdrawal of
the sheeting and bracing shall be carefully filled by jetting, ramming or other
means approved by the Engineer. Permission shall be obtained from the
Engineer prior to removal of any sheeting or bracing. Permission shall not
relieve the Contractor of any responsibility for damage due to failure to leave
such sheeting and bracing in place.”
3. The Engineer may order, in writing, any or all sheeting or bracing to be left
in place for the purpose of preventing injury to adjacent structures, property,
etc. If left in place, such sheeting shall be cut off at the elevation ordered,
but in no case less than thirty-six (36) inches below the existing grade.
Bracing remaining in place shall be driven in tight. The right of the Engineer
to order sheeting and bracing to remain in place shall not be construed as
creating any obligation on his part to issue such orders. Payment for
sheeting and bracing, unless specifically called for on the Drawings shall
not be paid under separate item, but shall be included in the payment for
other items of Work.”
4. DELETE paragraph in Section 02222, Part 3.07, A.
5. ADD the following to the end of the Table of Contents.
“ATTACHMENTS
Attachment 1 - Geotechnical Report
Attachment 2 – FDEP General Permit for Constructing a Domestic Wastewater
Collection/Transmission System”
6. ADD the attached Geotechnical Report and FDEP Permit to the end of the
Technical Specifications.
END OF ADDENDUM NO. 1
Attachment 1 - Geotechnical Report
Attachment 2 – FDEP General Permit for Constructing a Domestic
Wastewater Collection/Transmission System
www.floridadep.gov
FLORIDA DEPARTMENT O F
Environmental Protection
Southwest District Office
13051 North Telecom Parkway #101
Temple Terrace, Florida 33637-0926
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Noah Valenstein
Secretary
February 26, 2020
PERMIT NUMBER: CS51-0081364-107-DWC/CG
ISSUE DATE: February 26, 2020
EXPIRATION DATE: February 25, 2025
COUNTY: Pasco
PROJECT NAME: Lift Station No. 6 Replacement Project
WWTF NAME: Seven Springs WWTF
FACILITY ID: FLA012752
NOTIFICATION OF ACCEPTANCE OF USE OF A GENERAL PERMIT
Dear Mr. Dickson ,
This letter acknowledges receipt of your Notification/Application for Constructing a Domestic
Wastewater Collection/Transmission System for the subject project. Our Office received the
Notice on February 14, 2020.
This is to advise you that the Department does not object to your use of this general permit for the
following: twelve-inch diameter gravity pipe(s), with one manhole, and one lift station with
eight-inch diameter force mains pipe(s).
Please note the attached requirements apply to your use of this general permit for constructing the
proposed domestic wastewater collection/transmission system.
You are further advised that the construction activity must conform to the description contained
in your Notification/Application for Constructing a Domestic Wastewater
Collection/Transmission System and that any deviation may subject the permittee to enforcement
action and possible penalties.
PERMITTEE:
Mr. Robert Dickson, P.E., Capital Program Manager, GSG
Florida Governmental Utility Authority
280 Wekiva Springs Road, Suite 2070
Longwood, Florida 32779
Mr. Robert Dickson, P.E., Capital Program Manager, GSG
Page 2
February 26, 2020
If you have any questions, please contact Alexandria Moorehead at 813-470-5704 or via email at
Sincerely,
_________________________
For Pamala Vazquez
Program Administrator
Permitting & Waste Cleanup Program
Southwest District
Copies furnished to:
Matthew W. Davis, P.E., Ardurra Group, Inc., [email protected]
Sharmeela R. Khemlani, E.I., Ardurra Group, Inc., [email protected]
Alexandria Moorehead, DEP SWD, [email protected]
Mr. Robert Dickson, P.E., Capital Program Manager, GSG
Page 3
February 26, 2020
REQUIREMENTS FOR USE OF THE GENERAL PERMIT FOR DOMESTIC
WASTEWATER COLLECTION/TRANSMISSION SYSTEMS:
1. This general permit is subject to the general permit conditions of Rule 62-4.540, F.A.C., as
applicable. This rule is available at the Department’s Internet site at:
http://www.dep.state.fl.us/water/rulesprog.htm#ww [62-4.540]
2. This general permit does not relieve the permittee of the responsibility for obtaining a dredge
and fill permit where it is required. [62-604.600(6)(b)1]
3. This general permit cannot be revised, except to transfer the permit. [62-604.600(6)(b)2]
4. This general permit will expire five years from the date of issuance. If the project has been
started and not completed by that time, a new permit must be obtained before the expiration
date in order to continue work on the project. [62-4.030]
5. Upon completion of construction of the collection/transmission system project, and before
placing the facilities into operation for any purpose other than testing for leaks or testing
equipment operation, the permittee shall submit to the Department’s Southwest District Office
Form 62-604.300(8)(b), Request for Approval to Place a Domestic Wastewater
Collection/Transmission System into Operation. This form is available at the Department’s
Internet site at: http://www.dep.state.fl.us/water/wastewater/forms.htm [62-604.700(2)]
6. The new or modified collection/transmission facilities shall not be placed into service until the
Department clears the project for use. [62-604.700(3)]
7. Abnormal events shall be reported to the Department’s Southwest District Office in accordance
with Rule 62-604.550, F.A.C. For unauthorized spills of wastewater in excess of 1000 gallons
per incident, or where information indicates that public health or the environment may be
endangered, oral reports shall be provided to the STATE WATCH OFFICE TOLL FREE
NUMBER (800) 320-0519 as soon as practical, but no later than 24 hours from the time the
permittee or other designee becomes aware of the circumstances. Unauthorized releases or
spills less than 1000 gallons per incident are to be reported orally to the Department’s
Southwest District Office within 24 hours from the time the permittee, or other designee
becomes aware of the circumstances. [62-604.550]