Floodline Determination for the Resource and Reserve ...
Transcript of Floodline Determination for the Resource and Reserve ...
Floodline Determination for the Resource
and Reserve Drilling Project at the
Dwarsrivier Chrome Mine
Project Number:
ENG004
Prepared for:
EnviroGistics (Pty) Ltd
P.O. Box 22014, Helderkruin, 1733
Email: [email protected]
Tel: 082 412 1799
Fax: 086 551 5233
Compiled by:
Hydrospatial (Pty) Ltd
17 Sonop Place, Randpark, 2194
Email: [email protected]
Tel: 084 441 9539
July 2018
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
i July 2018
DOCUMENT CONTROL
Project Name Floodline Determination for the Resource and Reserve Drilling Project at the
Dwarsrivier Chrome Mine
Report Type Floodline Determination
Client EnviroGistics (Pty) Ltd
Project Number ENG004
Report Number 02
Report Status Final draft
Submission Date 26 July 2018
Author Andy Pirie (Pr.Sci.Nat.)
Author Signature
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
ii July 2018
TABLE OF CONTENTS
EXECUTIVE SUMMARY ..................................................................................................... IV
1 INTRODUCTION AND BACKGROUND ........................................................................ 1
1.1 Project Location ...................................................................................................... 1
1.2 Legal Requirements ................................................................................................ 3
1.2.1 National Water Act (Act No. 36 of 1998) .......................................................... 3
1.2.2 Government Notice 704 ................................................................................... 3
2 SCOPE OF WORK ........................................................................................................ 3
3 METHODOLOGY AND DATA SOURCES ..................................................................... 3
3.1 Site Visits ................................................................................................................ 3
3.2 Elevation Data ........................................................................................................ 4
3.3 Land Cover and Soils .............................................................................................. 4
3.4 Mannings n Roughness Coefficients ....................................................................... 4
3.5 Peak Flow Calculations ........................................................................................... 4
3.6 Software Choice ..................................................................................................... 5
3.7 Hydraulic Model Setup ............................................................................................ 6
4 ASSUMPTIONS AND LIMITATIONS ............................................................................ 6
5 CATCHMENT CHARACTERISTICS AND PEAK FLOWS ............................................ 6
6 RESULTS AND DISCUSSION ...................................................................................... 9
6.1 Assessment of the Possible Drainage Line near the Proposed Truck Parking
Facility (Option 1) .............................................................................................................. 9
6.2 Drilling Project ....................................................................................................... 16
7 CONCLUSIONS AND RECOMMENDATIONS ............................................................ 24
8 REFERENCES ............................................................................................................ 25
LIST OF TABLES
Table 4-1: Catchment characteristics, Rational Method parameters and calculated peak
flows ..................................................................................................................................... 8
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
iii July 2018
LIST OF FIGURES
Figure 1-1: Location of the Mine ............................................................................................ 2
Figure 5-1: Catchments and general topography .................................................................. 7
Figure 6-1: Cross-section A................................................................................................... 9
Figure 6-2: Cross-section B................................................................................................. 10
Figure 6-3: Cross-section C ................................................................................................ 10
Figure 6-4: Cross-section D ................................................................................................ 10
Figure 6-5: Drainage line cross-sections near the proposed truck parking option 1 facility .. 11
Figure 6-6: Road blocking the clean cut-off trench .............................................................. 12
Figure 6-7: Blocked culvert near the fence below the Sekhukhune road ............................. 12
Figure 6-8: Catchments 1 and 2 .......................................................................................... 13
Figure 6-9: Catchment 1 floodlines and 100 m drainage line buffer ..................................... 14
Figure 6-10: Catchment 2 floodlines and 100 m drainage line buffer ................................... 15
Figure 6-11: Catchment 3 floodlines and 100 m buffer ........................................................ 17
Figure 6-12: Catchment 4, 5, 6 and 7 floodlines and 100 m buffer ...................................... 18
Figure 6-13: Catchment 8, 9, 10 and 11 floodlines and 100 m buffer .................................. 19
Figure 6-14: Catchment 12, 13 and 14 floodlines and 100 m buffer .................................... 20
Figure 6-15: Catchment 15 floodlines and 100 m buffer ...................................................... 21
Figure 6-16: Catchment 16 and 17 floodlines and 100 m buffer .......................................... 22
Figure 6-17: Catchment 18 floodlines and 100 m buffer ...................................................... 23
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
iv July 2018
EXECUTIVE SUMMARY
Hydrospatial (Pty) Ltd (hereafter Hydrospatial) was appointed by EnviroGistics (Pty) Ltd
(hereafter EnviroGistics) to undertake a floodline determination for the Dwarsrivier Chrome
Mine (hereafter the Mine) Resource and Reserve Drilling Project (hereafter the Drilling
Project). In addition to the above, Hydrospatial was further requested to assess the area
between the discard dump and old Tailings Storage Facility (TSF), as the Mine is
considering a truck parking facility near to a drainage line that was previously diverted for
open pit operations, and which is currently still in place.
The area between the old TSF and discard dump, where the truck parking option 1 is
proposed, was thoroughly assessed during a site visit. A remnant drainage line was noted in
the area, that consisted of a shallow channel directly south-east of the discard dump, but
was noted to be more defined further downstream. In order to determine whether water
would flow down the drainage line, the topography of the area was assessed, to determine if
there would be any contributing catchment area. Two contributing catchments were
delineated; catchment 1 took the clean cut-off trench that diverts water around the discard
dump into consideration, while catchment 2 ignored the trench. The 1:50 and 1:100 year
floodlines indicated that the truck parking option 1 falls outside of the floodlines in both
instances (catchment 1 and 2), but within the 100 m buffer of the drainage line.
The 1:50 and 1:100 year floodlines were determined for the drainage lines that intersect the
proposed Drilling Plan. A number of drilling targets and access roads are located within the
floodlines and 100 m buffer.
The following is recommended:
■ The clean cut-off trench upslope of truck parking option 1 is upgraded. This includes
unlocking the culvert near the Sekhukhune road, which may require the installation of
a new culvert, due to its poor condition. It is recommended that should a new culvert
be considered, that it is sized correctly to convey the 1:50 year runoff, as required by
the GN704 Regulations. It is further recommended that a culvert is considered where
the road has blocked the trench. Lastly, the sizing of the clean cut-off trench should
be checked, to ensure that it complies with GN704;
■ Truck parking option 1 falls outside of the 1:100 year floodlines, but within a 100 m
horizontal distance of the drainage line. It is recommended that a GN704 exemption
from Regulation 4 (a) and (b) is obtained;
■ The proposed drilling holes and access roads that fall within the 1:50 year floodlines,
and within a 100 m horizontal distance of the drainage lines, are exempted from
GN704 regulations 4 (a) and 4 (b);
■ In order to minimise the impacts of the drilling sites located within the floodlines, it is
proposed that they are only accessed during the dry season; and
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
v July 2018
■ A 100 m buffer has been placed around the Richmond dam, however, this should be
confirmed with the Department of Water and Sanitation.
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
1 July 2018
1 INTRODUCTION AND BACKGROUND
Hydrospatial (Pty) Ltd (hereafter Hydrospatial) was appointed by EnviroGistics (Pty) Ltd
(hereafter EnviroGistics) to undertake a floodline determination for the Dwarsrivier Chrome
Mine (hereafter the Mine) Resource and Reserve Drilling Project (hereafter the Drilling
Project). In addition to the above, Hydrospatial was further requested to assess the area
between the discard dump and old Tailings Storage Facility (TSF), as the Mine is
considering a truck parking facility near to a drainage line that was previously diverted for
open pit operations, and which is currently still in place.
The Drilling Project involves the construction of access roads, drilling pads and the removal
of vegetation. The drill pads are proposed to be 20 metres (m) by 20 m (400 m²), and will
comprise of the drill site and a portable sump for the storage of dirty water from drilling
activities. Dirty water collected by the portal sump, will be disposed of in a licenced facility.
Access roads to drill sites will be 6 m wide, and will be temporary in nature. Temporary
offices may be erected if and when required. Small scale diesel/lubrication/oil storage may
be required for the drill rigs. The exploration activities are planned over the Dwarsrivier Mine
Mining Rights area, however, this will extend onto the Two Rivers Platinum Mines Surface
Rights area, which includes the Two Rivers Platinum Mine Plant, as well as the TSF. For the
TSF, the exploration programme will allow for a 100 m buffer. Where mine infrastructure is
present, consultation with the landowner will be undertaken and drilling will only be
conducted in approved areas and in line with the landowners’ rules and requirements. Since
the mine is located within a mountainous area, various drainage lines are present.
The 1:50 and 1:100 year floodlines for the Dwars Rivier, Klein Dwars Rivier and
Springkaanspruit, were previously determined for the Mine (Krige, 2009). However, a
number of ephemeral (only flowing in response to high rainfall) drainage lines indicated on
the 1:50 000 topographical maps, were not determined, which are located in close proximity
to the proposed exploration drilling holes and access roads.
The purpose of this report is to summarise the floodline determinations undertaken for the
Drilling Project, as well as the assessment of the potential drainage line near the proposed
truck parking option 1.
1.1 Project Location
The Mine is situated approximately 60 km northwest of Lydenburg, 25 km south of
Steelpoort and 63 km northeast of Roossenekal in the Limpopo Province (Error! Reference
source not found.).
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
2 July 2018
Figure 1-1: Location of the Mine
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
3 July 2018
1.2 Legal Requirements
The following legal requirements are applicable to this study:
1.2.1 National Water Act (Act No. 36 of 1998)
According to section 21 of the National Water Act (Act No. 36 of 1998) (hereafter NWA), the
following sections are relevant in terms of water uses –
(c) Impeding or diverting the flow of water in a watercourse; and
(i) Altering the bed, banks, course or characteristics of a watercourse.
1.2.2 Government Notice 704
According to Regulation 4 of Government Notice 704 (hereafter GN704), promulgated in
terms the NWA, no person in control of a mine or activity may –
(a) Locate or place any residue deposit, dam, reservoir, together with any associated
structure or any other facility within the 1:100 year floodline or within a horizontal distance of
100 metres from any watercourse or estuary, borehole or well, excluding boreholes or wells
drilled specifically to monitor the pollution of groundwater, or on water-logged ground, or on
ground likely to become water-logged, undermined, unstable or cracked; and
(b) Carry on any underground or opencast mining, prospecting or any other operation or
activity under or within the 1:50 year floodline or within a horizontal distance of 100 m from
any watercourse or estuary, whichever is the greatest.
Exemption from the above requirements may be applied for, in terms of Regulation 3 of
GN704.
2 SCOPE OF WORK
The scope of work for the study included the following:
■ Determine the 1:50 and 1:100 year floodlines for drainage lines indicated on the 1:50
000 topographical maps, that intersect the proposed resource drilling plan; and
■ Assess the area between the discard dump and old TSF near the proposed truck
parking option 1, to determine if a drainage line exists in the vicinity.
3 METHODOLOGY AND DATA SOURCES
3.1 Site Visits
Two site visits were undertaken on 11 May and 22 June 2018. The purpose of the site visits
was to assess the catchment characteristics, channels and floodplains of the drainage lines
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
4 July 2018
under consideration. A thorough walkthrough of the area between the old TSF and discard
dump was conducted.
3.2 Elevation Data
Accurate, detailed and up-to-date elevation data is a critical component for accurate floodline
modelling. Elevation data from the following sources was used for modelling purposes:
■ 5 m contour interval elevation data obtained from the Mine from the file: Master Plan
2018 - Existing Infrastructure.dgn. Although not ideal in terms of the course scale
contour interval resolution, as well as being outdated, this was the best available
elevation data covering the Drilling Project; and
■ 1 m contour elevation data obtained from the Mine for the area between the old TSF
and discard dump. This area was surveyed between 21 to 23 February 2018 by Trail
Surveys, and was used to model the floodlines for this area.
3.3 Land Cover and Soils
Land cover and soil data is used in the calculation of the peak flows. Land cover data was
assessed using Google Earth imagery, as well as the 2013 – 2014 South African National
Land-Cover Dataset (Geoterraimage, 2015).
An understanding of the soil types of the area was obtained from the 2010 Environmental
Management Programme Report (EMP) for the Mine. Soil data was further obtained from the
land type and capability dataset from the Agricultural Resource Council – Institute for Soil,
Climate and Water (ARC-ISCW).
3.4 Mannings n Roughness Coefficients
The Manning’s n roughness coefficients are values that are used to model the channel and
adjacent floodplains resistance to flow. The Mannings roughness was assessed during the
site visits. The channels of the drainage lines in the area were noted to be generally shallow
and not well defined, and consisted of fairly dense vegetation. Similarly, the adjacent
floodplains also consisted of dense vegetation. Based on these observations, a Mannings n
roughness coefficient of 0.1 was assigned to the channels and adjacent floodplain areas.
3.5 Peak Flow Calculations
The Rational Method is a hydrological method that was used to estimate the 1:50 and 1:100
year peak flows. It is based on the following equation:
𝑄𝑇 =𝐶 𝐼 𝐴
3.6
where:
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
5 July 2018
QT = Peak flow for a recurrence interval e.g. a 1:100 year flood (m³/s)
C = Runoff coefficient (dimensionless)
I = Average rainfall intensity over the catchment (mm/hour)
A = Catchment area contributing to the peak flow (km²)
3.6 = Conversion factor
The runoff coefficient “C” is calculated from the physical characteristics of the contributing
catchment. These include the vegetation type, slope, soil permeability, and land use
characteristics.
The average rainfall intensity “I” was calculated from the gridded storm rainfall depths
obtained from Smithers and Schulze (2002), and is equal to the time of concentration (Tc).
The Tc is the amount of time it takes for water to travel from the hydraulically most remote
point of the catchment, to the catchment outlet. It is essentially the amount of time for runoff
in the catchment to contribute to the peak flow.
The contributing catchment area “A” was calculated by delineating a catchment for the peak
flow points. The 5 m contours obtained from the Mine as well as the 1:50 000 topographical
contours were used to delineate the contributing catchments.
A Microsoft Excel spreadsheet (Gericke and du Plessis, 2013) was used to calculate the
peak flows based on the South African National Roads Agency Limited (SANRAL)
procedure.
The Rational Method is based on the following key assumptions:
■ Rainfall has a uniform area distribution across the total contributing catchment;
■ Rainfall has a uniform time distribution for at least a duration equal to the Tc;
■ The peak discharge occurs when the total catchment contributes to the flow
occurring at the end of the critical storm duration, or Tc;
■ The runoff coefficient “C” remains constant for the storm duration, or Tc; and
■ The return period of the peak flow is the same as that of the rainfall intensity.
3.6 Software Choice
The following software’s were used:
■ ArcMap 10.2 is a Geographical Information System (GIS) software programme used
to view, edit, create and analyse geospatial data. ArcMap was used to view spatial
data and to create maps. Its extension 3D Analyst was used for terrain modelling
purposes, for converting the elevation data into a DEM grid format;
■ HEC-GeoRAS utilises the ArcMap environment and is used for the preparation of
geometric data (cross-sections, river profile, banks and flow paths) for input into the
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
6 July 2018
HEC-RAS hydraulic model. It is further used in post processing to import HEC-RAS
results back into ArcMap, to perform flood inundation mapping; and
■ HEC-RAS 4.1 (Brunner, 2010) was used to perform hydraulic modelling. HEC-RAS is
a hydraulic programme used to perform one-dimensional hydraulic calculations for a
range of applications, from a single watercourse to a full network of natural or
constructed channels.
3.7 Hydraulic Model Setup
Development of the hydraulic model included the following steps:
■ Preparation of geometric data (cross-sections, stream centre lines, bank lines and
flow paths) in HEC-GeoRAS;
■ Importing of geometric data into HEC-RAS;
■ HEC-RAS setup for the Manning’s n roughness coefficient values at cross-sections,
entering peak flows, and entering upstream and downstream slope boundary
conditions for normal depth calculations;
■ Performing steady, mixed flow (combination of subcritical, supercritical, hydraulic
jumps and drawdowns) hydraulic modelling within HEC-RAS to generate flood water
levels at cross-sections; and
■ Importing flood level elevations at cross-sections into HEC-GeoRAS to perform
floodplain delineations.
4 ASSUMPTIONS AND LIMITATIONS
The following are key assumptions and limitations:
■ Due to the use of coarse resolution 5 m contour data for modelling, the determined
floodlines must only to be used for environmental and indicative purposes, to provide
a broad estimate of the 1:50 and 1:100 year flood levels. They cannot be used for
engineering design purposes; and
■ Calibration of the hydrological and hydraulic models was not possible. Conservative
guideline values for parameters have been used based on site observations. This is
a standard approach for determining indicative floodlines.
5 CATCHMENT CHARACTERISTICS AND PEAK FLOWS
An overview of the catchments delineated to calculate the flood peaks is indicated on Figure
5-1. The catchment characteristic, Rational Method parameters, and calculated peak flows
are summarised in Table 5-1.
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
7 July 2018
Figure 5-1: Catchments and general topography
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
8 July 2018
Table 5-1: Catchment characteristics, Rational Method parameters and calculated peak flows
Catchment MAP (mm)
Catchment Area (km²)
Longest Water- course
(km)
Average Slope of Longest Water- course (m/m)
1:50 Year Runoff
Coefficient
1:100 Year Runoff
Coefficient
Tc (hrs)
1:50 Year
Rainfall Intensity (mm/h)
1:100 Year
Rainfall Intensity (mm/h)
Peak Flow
Method
1:50 Year Peak Flow (m³/s)
1:100 Year Peak Flow (m³/s)
Catchment 1 571 0.06 0.4 0.046 0.309 0.373 0.29 143.4 162.4 Rational 0.7 1.0
Catchment 2 571 0.44 1.5 0.039 0.265 0.319 0.61 92.3 104.7 Rational 3.0 4.1
Catchment 3 571 2.16 2.1 0.158 0.310 0.370 0.48 105.9 120.1 Rational 19.7 26.6
Catchment 4 571 0.17 0.5 0.065 0.327 0.344 0.35 128.4 145.5 Rational 2.0 2.3
Catchment 5 571 0.80 1.6 0.219 0.349 0.367 0.39 119.6 135.6 Rational 9.3 11.0
Catchment 6 571 0.30 0.9 0.077 0.302 0.318 0.40 116.9 132.5 Rational 3.0 3.6
Catchment 7 571 0.60 1.7 0.144 0.323 0.340 0.39 119.4 135.3 Rational 6.4 7.6
Catchment 8 571 0.10 0.7 0.060 0.266 0.278 0.44 110.9 125.8 Rational 0.8 1.0
Catchment 9 571 1.03 1.7 0.135 0.341 0.358 0.46 109.0 123.6 Rational 10.6 12.7
Catchment 10 571 1.46 2.8 0.208 0.342 0.359 0.54 98.7 111.9 Rational 13.6 16.3
Catchment 11 571 0.72 0.9 0.032 0.322 0.339 0.68 86.2 97.7 Rational 5.6 6.7
Catchment 12 571 0.65 0.8 0.020 0.282 0.336 0.50 104.3 118.3 Rational 5.3 7.2
Catchment 13 571 1.67 0.8 0.019 0.312 0.372 0.56 96.8 109.7 Rational 14.0 19.0
Catchment 14 571 0.17 0.4 0.030 0.273 0.288 0.51 103.3 117.2 Rational 1.3 1.6
Catchment 15 571 0.36 1.1 0.228 0.419 0.442 0.39 119.2 135.1 Rational 5.0 6.0
Catchment 16 571 6.08 5.0 0.035 0.319 0.334 1.21 61.4 69.6 Rational 33.1 39.3
Catchment 17 571 0.68 1.0 0.059 0.334 0.352 0.48 106.5 120.8 Rational 6.8 8.1
Catchment 18 571 0.36 1.0 0.139 0.294 0.309 0.48 106.3 120.6 Rational 3.1 3.7
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
9 July 2018
6 RESULTS AND DISCUSSION
6.1 Assessment of the Possible Drainage Line near the Proposed Truck
Parking Facility (Option 1)
During the site visit, a remnant drainage line/ditch was noted between the old TSF and
discard dump. This drainage line was previously diverted to prevent flooding of open pit
operations, which have since been rehabilitated. The diversion is still currently in place
(Figure 6-8), and diverts runoff away from the North Return Water Dam, and into the
Springkaanspruit.
The drainage line near to the proposed truck parking option 1 was confirmed by assessing
the 1 m contour survey data. A number of cross-sections were drawn through the drainage
line as indicated on Figure 6-5. The upper section of the drainage channel, directly to the
south-east and south of the discard dump, is shallow and not well defined (Figure 6-1 and
Figure 6-2), but becomes more defined and prominent towards the lower sections (Figure
6-3 and Figure 6-4).
Figure 6-1: Cross-section A
Cross-Section A
Horizontal Distance (m)
50454035302520151050
ma
msl
932.3
932.2
932.1
932
931.9
931.8
931.7
931.6
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
10 July 2018
Figure 6-2: Cross-section B
Figure 6-3: Cross-section C
Figure 6-4: Cross-section D
Cross-Section B
Horizontal Distance (m)
26252423222120191817161514131211109876543210
mam
sl
928.8
928.6
928.4
928.2
928
927.8
927.6
Cross-Section C
Horizontal Distance (m)
35302520151050
mam
sl
926
925.8
925.6
925.4
925.2
925
924.8
924.6
924.4
924.2
Cross-Section D
Horizontal Distance (m)
56545250484644424038363432302826242220181614121086420
ma
msl
920.6
920.4
920.2
920
919.8
919.6
919.4
919.2
919
918.8
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
11 July 2018
Figure 6-5: Drainage line cross-sections near the proposed truck parking option 1
facility
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
12 July 2018
In order to determine whether water would flow down the drainage line, the topography of
the area was assessed, to determine if there would be any contributing catchment area.
Catchments 1 and 2 were delineated as indicated on Figure 6-8. This was done as a clean
cut-off trench was noted upstream of the drainage line, which diverts runoff around the
discard dump (Figure 6-6). However, the cut-off trench was noted to be degraded, as it was
blocked by a road (Figure 6-6), and was further noted to be blocked at a culvert near the
fence below the Sekhukhune road (Figure 6-7). Catchment 1 considers the upslope clean
water cut-off trench to be fully operational, diverting upslope runoff around the discard dump.
Catchment 2 considers the cut-off trench to be degraded (as noted on the site visit), allowing
upslope runoff to pass into the drainage ditch between the old TSF and discard dump. The
1:50 and 1:100 year floodlines for catchment 1 and 2 are indicated on Figure 6-9 and Figure
6-10.
Figure 6-6: Road blocking the clean cut-off trench
Figure 6-7: Blocked culvert near the fence below the Sekhukhune road
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
13 July 2018
Figure 6-8: Catchments 1 and 2
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
14 July 2018
Figure 6-9: Catchment 1 floodlines and 100 m drainage line buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
15 July 2018
Figure 6-10: Catchment 2 floodlines and 100 m drainage line buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
16 July 2018
As observed from Figure 6-9 and Figure 6-10, the truck parking option 1 falls outside of the
floodlines, but within the 100 m buffer of the drainage line. It is therefore unlikely that the
proposed truck parking will disturb the drainage line or be at risk of flooding. However, the
elevated area (approximately 1.5 m to 3 m elevation difference) on which the truck parking is
proposed, should be kept in place, as it provides important elevation for the left bank of the
drainage line. Due to the truck parking facility being located within the 100 m buffer of the
drainage line, it is likely that a GN704 exemption from Regulation 4 (a) and (b) will be
required.
6.2 Drilling Project
The 1:50 and 1:100 year floodlines and 100 m buffer of drainage lines intersecting the
Drilling Project are indicated on Figure 6-11, Figure 6-12, Figure 6-13, Figure 6-14, Figure
6-15, Figure 6-16 and Figure 6-17 below. A number of drilling targets and access roads are
located within the floodlines and 100 m buffer. As mentioned under section 1.2, no mining
activities may take place within the floodlines or 100 m buffer of watercourses, without
obtaining exemption from GN704. Furthermore, the drill sites and access roads may
potentially disturb drainage lines, triggering a water use in terms of section 21 (c) and (i) of
the NWA. In order to minimise any impact on the drainage lines, it is recommended that they
are only accessed during the dry season.
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
17 July 2018
Figure 6-11: Catchment 3 floodlines and 100 m buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
18 July 2018
Figure 6-12: Catchment 4, 5, 6 and 7 floodlines and 100 m buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
19 July 2018
Figure 6-13: Catchment 8, 9, 10 and 11 floodlines and 100 m buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
20 July 2018
Figure 6-14: Catchment 12, 13 and 14 floodlines and 100 m buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
21 July 2018
Figure 6-15: Catchment 15 floodlines and 100 m buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
22 July 2018
Figure 6-16: Catchment 16 and 17 floodlines and 100 m buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
23 July 2018
Figure 6-17: Catchment 18 floodlines and 100 m buffer
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
24 July 2018
7 CONCLUSIONS AND RECOMMENDATIONS
Hydrospatial was appointed to determine the 1:50 and 1:100 year floodlines for drainage
lines intersecting the Mines proposed Drilling Project. In addition to the above, Hydrospatial
was further requested to assess the area where the truck parking option 1 facility is
proposed, to determine whether a drainage line is present.
The area between the old TSF and discard dump, where the truck parking option 1 is
proposed, was thoroughly assessed during a site visit. A remnant drainage line was noted in
the area, that consisted of a shallow channel directly south-east of the discard dump, but
was noted to be more defined further downstream. Two contributing catchments were
delineated; catchment 1 took the clean cut-off trench into consideration, while catchment 2
ignored the trench. The 1:50 and 1:100 year floodlines indicated that the truck parking option
1 falls outside of the floodlines in both instances (catchment 1 and 2), but within the 100 m
buffer of the drainage line.
The 1:50 and 1:100 year floodlines were determined for the drainage lines that intersect the
proposed Drilling Plan. A number of drilling targets and access roads are located within the
floodlines and 100 m buffer.
The following is recommended:
■ The clean cut-off trench upslope of truck parking option 1 is upgraded. This includes
unlocking the culvert near the Sekhukhune road, which may require the installation of
a new culvert, due to its poor condition. It is recommended that should a new culvert
be considered, that it is sized correctly to convey the 1:50 year runoff, as required by
the GN704 Regulations. It is further recommended that a culvert is considered where
the road has blocked the trench. Lastly, the sizing of the clean cut-off trench should
be checked, to ensure that it complies with GN704;
■ Truck parking option 1 falls outside of the 1:100 year floodlines, but within a 100 m
horizontal distance of the drainage line. It is recommended that a GN704 exemption
from Regulation 4 (a) and (b) is obtained;
■ The proposed drilling holes and access roads that fall within the 1:50 year floodlines,
and within a 100 m horizontal distance of the drainage lines, are exempted from
GN704 regulations 4 (a) and 4 (b);
■ In order to minimise the impacts of the drilling sites located within the floodlines, it is
proposed that they are only accessed during the dry season; and
■ A 100 m buffer has been placed around the Richmond dam, however, this should be
confirmed with the Department of Water and Sanitation.
Floodline Determination for the Resource and Reserve Drilling Project at the Dwarsrivier Chrome Mine
ENG004
25 July 2018
8 REFERENCES
Brunner G.W. 2010. HEC-RAS – River Analysis System Hydraulic Reference Manual, US
Army Corps of Engineers Hydrologic Engineering Center (HEC).
Geoterraimage. 2015. The 2013 – 2014 South African National Land-Cover Dataset. Data
User Report and MetaData.
Gericke O.J. and du Plessis J.A. 2013. Development of a Customised Design Flood
Estimation Tool to Estimate Floods in Gauged and Ungauged Catchments. Water SA Vol.
39 No. 1 January 2013.
Land Type Survey Staff. 1972 - 2006. Land types of South Africa; Digital Map (1:250 000
scale) and Soil Inventory Database. Pretoria: ARC-Instatute for Soil, Climate, and Water.
Smithers J.C. and Schulze R.E. 2002. Design Rainfall and Flood Estimation in South Africa.
WRC Project No. K5/1060.