D235 Santos Oyong Phase II Project Design Premise
Report No: D235-E001
Revision: 02
Date: 12th April 2008
Submitted by: Luke Wilkinson
Wellstream International Limited
D235 / SANTOS OYONG PHASE II DEVELOPMENT D235-E001 REV 02 PAGE I
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
Table of Contents
1. GENERAL INFORMATION................................................................................. 1
2. DESIGN PARAMETERS..................................................................................... 2 2.1 GENERAL DESIGN PARAMETERS................................................................................. 2 2.2 INTERNAL FLUID PARAMETERS ................................................................................... 2 2.3 TEMPERATURE REQUIREMENTS.................................................................................. 2 2.4 PRESSURE REQUIREMENTS ......................................................................................... 3 2.5 SERVICE DEFINITION...................................................................................................... 3 2.6 INSULATION REQUIREMENTS ....................................................................................... 3 2.7 NYLON SERVICE LIFE..................................................................................................... 3 2.8 GAS VENTING.................................................................................................................. 3 2.9 CORROSION PROTECTION REQUIREMENTS............................................................... 3 2.10 OTHER.............................................................................................................................. 3 2.11 CONNECTOR ................................................................................................................... 4 2.12 JUMPER PARAMETERS.................................................................................................. 4
2.12.1 On-Bottom Stability .............................................................................................. 4 2.12.2 Protection Requirements ..................................................................................... 4 2.12.3 Upheaval Buckling................................................................................................ 4
3. EXTERNAL ENVIRONMENT.............................................................................. 5 3.1 SEAWATER DATA ........................................................................................................... 5 3.2 SOIL DATA ....................................................................................................................... 5 3.3 OTHER.............................................................................................................................. 5
4. ADDITIONAL REQUIREMENTS ........................................................................ 6
5. DELIVERY, INSTALLATION AND MAINTENANCE ......................................... 7 5.1 INSTALLATION REQUIREMENTS................................................................................... 7 5.2 INSTALLATION DESIGN CRITERIA................................................................................ 7
Appendix A Wave and Current Data
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 1
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
Flexible Pipe Design Premise
1. GENERAL INFORMATION Client Bakrie Pipe Industries, Indonesia Project Name Santos - Oyong Phase II Development WIL Project Reference D235 Client Contact: Adi Bagus Tirto Client Contact Phone : TBA Client Contact Fax : TBA Client Contact Email [email protected] Client Contact Address Bakrie Pipe Industries, JJ Raya Pejuang, Medan Satria, Kota Bekasi 17131, Indonesia.
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 2
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
2. DESIGN PARAMETERS
2.1 GENERAL DESIGN PARAMETERS
Service description (static / dynamic) Dynamic Pipe bore definition (smooth / rough) Rough Internal diameter 10.0 inch 254.0 mm Estimated length required 85 m Tolerance required on length 1.0 %+ 0.0 %- Required minimum bend radius NA m Required OD / weight ratio (empty in air) NA mm/kg.m Service life 15 years Maximum permissible axial load NA kN Design water depth 41 m
2.2 INTERNAL FLUID PARAMETERS
Fluid description oil / gas / water[4] maximum 996[4] kg/m3
minimum 650[4] kg/m3 Density operating As above[4] kg/m3 maximum 160[4] BPD
Liquids operating 15[4] BPD maximum 60[4] MMscfd
Flow rates Gases
operating 60[4] MMscfd NaCl content n/s[1] mg/l Chlorides content n/s[5] ppm Gas-oil ratio n/s[1] m3 / m3
Methanol n/s[1] l/min Water cut n/s[1] % Alcohols (yes / no) n/s[1]
Corrosive agents (yes / no) n/s[1]
Inhibitors (scale, paraffin etc) (yes / no) n/s[1]
Injected chemicals (yes / no) n/s[1]
Solids, precipitates etc n/s[1]
2.3 TEMPERATURE REQUIREMENTS
Design minimum temperature -20 oC Design maximum temperature 65[3] oC Operating temperature 37 - 60 oC
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 3
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
2.4 PRESSURE REQUIREMENTS
Design pressure 15.5 MPa Operating pressure 13.8 MPa
2.5 SERVICE DEFINITION
Description (sweet / sour) Sweet
NACE MR01-75 to apply (yes / no) No
H2S content 0.00 ppmv CO2 content 1.07 mol% CH4 content 92.72 mol% Titrated acid number n/s[1] mgKOH/g
2.6 INSULATION REQUIREMENTS
Thermal insulation required (yes / no) No
Required insulation value (based on ID) NA W/m2K
2.7 NYLON SERVICE LIFE
Temperature profile attached (yes / no) No[1]
End of life CIV 1.2 dl/g supplied n/s[1]
pH calculated 5.0
HCO3 n/s[1] ppm Total iron content n/s[1] ppm
2.8 GAS VENTING
Gas venting required (yes / no) Yes
System components (valves, burst disks) Vent valves only
2.9 CORROSION PROTECTION REQUIREMENTS
Corrosion protection required (yes / no) Yes Cathodic protection system required (yes / no) No[2] Electrical continuity required (yes / no) Yes
External coating description (end fitting) Ceramkote (blue) Internal coating description (flange faces and end fitting bore) Inconel 625
2.10 OTHER
Fire resistance required (yes / no) No
Pigging, TFL, work over etc (yes / no) No
Piggyback required (yes / no) No
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 4
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
2.11 CONNECTOR
Barge topside connector type 10-inch ANSI Class 900 RTJ Platform topside connector type 10-inch ANSI Class 900 RTJ Midline connector type NA
2.12 JUMPER PARAMETERS
Flowline routing description attached (yes / no) No
Cross over requirements (yes / no) No
Required ancillaries 2 x Bend stiffeners / 2 x Topside hang offs.
2.12.1 ON-BOTTOM STABILITY
On-bottom stability to be checked (yes / no) No current NA yr
Installation sea state wave NA yr current NA yr
Operational sea state wave NA yr
2.12.2 PROTECTION REQUIREMENTS
Impact resistance to accidental loads (yes / no) No
Trenching (yes / no) No
Rock dumping (yes / no) No
Mattresses (yes / no) No
2.12.3 UPHEAVAL BUCKLING
Upheaval buckling to be checked (yes / no) No
Required minimum soil coverage NA m Allowable bend radius NA m Load cases attached (yes / no) No
Notes
[1] This information has not been supplied specifically for the Santos Oyong Phase II project.
[2] End connections are to be considered as part of the Platform impressed current system.
[3] For intermittent operation only.
[4] In Design Premise Rev 2 Internal Fluid Parameters have been modified to oil, gas and water service,
details as shown.
[5] Chloride content has not been supplied, this is critical to pipe service life.
Max allowable Chloride = 65 000 ppm. During service life there is a limit of 30 days maximum total internal exposure to untreated seawater.
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 5
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
3. EXTERNAL ENVIRONMENT
3.1 SEAWATER DATA
Density 1025 kg/m3
Temperature profile attached (yes / no) No
Minimum surface temperature 27.0 oC Maximum surface temperature 29.7 oC Minimum seabed temperature 26.2 oC Maximum seabed temperature 29.5 oC
3.2 SOIL DATA
Soil description NA
Soil shear strength NA MPa Angle of internal friction NA o
Lateral friction coefficient NA
Longitudinal friction coefficient NA
3.3 OTHER
Marine growth to be considered (yes / no) Yes
Marine growth profile attached (yes / no) No
Ice effects to be considered (yes / no) No
Sunlight exposure (yes / no) Yes
Current data attached (yes / no) Yes (See Appendix A)
Wave data attached (yes / no) Yes (See Appendix A)
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 6
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
4. ADDITIONAL REQUIREMENTS Materials required in addition to API specification 17J (yes / no) No
If yes, specify details:
Manufacturing required in addition to API specification 17J (yes / no) No
If yes, specify details:
FAT required in addition to API specification 17J (yes / no) No
If yes, specify details:
Marking required in addition to API specification 17J (yes / no) No
If yes, specify details:
Prototype tests required (yes / no) No
If yes, specify details:
Additional national authority / government regulations (yes / no) No
If yes, specify details:
Purchaser inspection requirements (yes / no) No
If yes, specify details:
General requirements in addition to API specification 17J (yes / no) No
If yes, specify details:
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 7
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
5. DELIVERY, INSTALLATION AND MAINTENANCE Delivery requirements: Ex. Works FAS delivery 30th September 2008.
Shipping, packing and storage requirements: Detailed packing arrangement and marking drawings to be submitted for Company approval.
Documentation requirements: Documentation will be issued in accordance with Wellstream Master Document List D235-MDL.
5.1 INSTALLATION REQUIREMENTS
Method n/s[1]
Vessel n/s[1]
General: n/s[1]
5.2 INSTALLATION DESIGN CRITERIA
Equipment bend radius NA m Tensioner crush loads NA kN/m-track Installation / lifting device requirements: To be determined during the Project as part of the Seastream joint venture. Transport reel used for installation (yes / no) No
Pipe internal fluid at delivery NA
Pipe internal fluid during installation NA
Seawater flooding requirements (yes / no) No
Notes
[1] This information has not been supplied specifically for the Santos Oyong Phase II project.
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 1
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
APPENDIX A
Wave and Current Data
D235 / SANTOS / OYONG DEVELOPMENT D235-E001 REV 02 PAGE 2
© 2007 Wellstream international limited. This document contains information which is confidential and property to Wellstream International Limited.
The following summary of data has been extracted from Santos Specification 9811-55-SP-001 Rev 0.
Wave Data
Oyong-Grati 2 – Years 100 – Years Description
Oyong Oyong Significant wave height, Hs (m) 1.85 2.37
Zero crossing period, Tz (sec) 4.28 4.73
Spectral peak period, Tp (sec) 5.51 6.11
Maximum wave height, Hmax (m) 3.44 4.41
Period of maximum wave, Tmax (sec) 5.30 5.88
JONSWAP Parameters : - Phillips parameter 0.0142 0.0150 - peakedness
t2.29 2.46
- sigma A 0.078 0.076 - sigma B 0.093 0.092
Current Data
Oyong-Grati 2 – Years 100 – Years Depth
(m) Oyong Oyong 1mAbove Seabed (m/sec)
0.27 0.32
Additional Reference Data and Specifications
100 year RAO’s
9800-GEN-003
9810-40-RPT-001 Rev.0 – Structural Analysis Report
D3574-2-DR-01 FPSO Barge Mooring Analysis Rev C
D3574-2-EC-01 FPSO Barge Motion Rev A
D3574-S1-06 150668-Mooring Hose-Chain DWG 2
DWG-02-P-005-Rev 1 AS BUILT
Existing Oyong Flexible Jumper
ISO-02-P-001 Rev.1 – AS BUILT
Oyong Facilities – Photos
Production Barge COG