VIETNAM - Central Intelligence Agency · Title: VIETNAM Subject: VIETNAM Keywords
Fixed Platforms - EPCI Platform for Vietnam
Click here to load reader
-
Upload
muhammad-wildan -
Category
Documents
-
view
215 -
download
0
Transcript of Fixed Platforms - EPCI Platform for Vietnam
![Page 1: Fixed Platforms - EPCI Platform for Vietnam](https://reader038.fdocuments.in/reader038/viewer/2022100505/577cb5771a28aba7118d26db/html5/thumbnails/1.jpg)
8/9/2019 Fixed Platforms - EPCI Platform for Vietnam
http://slidepdf.com/reader/full/fixed-platforms-epci-platform-for-vietnam 1/5
22 • J. Ray NEWS jraymcdermo
Major achievementsWithin just 22.5 months, the deck fabrication was completed, ready
to sail, 100 percent mechanically complete, commissioned onshore
and with no carry-over work. In addition, the Su Tu Vang project dis-
tinguished itself for a number of other achievements reflective of its
lion-like qualities.
It took courage, for instance, to agree to the customer’s request to
assemble a detailed engineering team in Singapore in just one month
expanding a core team from J. Ray’s Jakarta office. And with more
than 80 percent of the engineering, procurement, project control and
ocated in Mekong Basin, in 170 feet of water, the massive
Su Tu Vang Central Processing Platform (CPP) is slated to
become Vietnam’s largest source of crude oil over the next
three years with the capacity to process 100,000 barrels of
oil and 160 million cubic feet of gas per day.
It is also an excellent example of J. Ray’s strong project manage-
ment and execution expertise. As a fully integrated EPCI project
– from FEED and preliminary engineering to installation, hook-up
and commissioning – it is comprised of a 4,400-ton, eight-leg jacket;
17,000-ton float-over topsides; 66-person, 1,323-ton living quarters
module; pipelines; umbilicals and PLEMs.
The project clearly demonstrates in-house capabilities to take on
large, challenging projects, and established a benchmark in the
industry for a project of this size and complexity.
Awarded to J. Ray in March 2006, the Su Tu Vang first steel-cut-
ting ceremony took place at the Batam Island, Indonesia, facility on
September 28. Twenty-four months later, the project enabled First
Oil – producing at an initial rate of 10,000 barrels per day – ahead of
schedule. Another benefit to the customer related to the project’s
EPCI status and single contractor was elimination of interface issuesand a smaller customer team required to oversee all aspects of work
at a central location.
“Most importantly, the Su Tu Vang project is viewed as a major suc-
cess by the customer,” said Scott Cummins, J. Ray Vice President and
General Manager of Asia Pacific operations. “We are proud of this
achievement and recognition of the value added through our EPCI
capabilities and project execution focus. We are also honored and
delighted that this is our second and most challenging project for
CuuLong Joint Operating Company (CLJOC) since the start of our
relationship in 2001.”
True to its name − “gold lion” in Vietnamese − the Su Tu Vang project
epitomizes courage, strength, resilience and unwavering focus.
L
Lion
ROARS
T h e
proudly
![Page 2: Fixed Platforms - EPCI Platform for Vietnam](https://reader038.fdocuments.in/reader038/viewer/2022100505/577cb5771a28aba7118d26db/html5/thumbnails/2.jpg)
8/9/2019 Fixed Platforms - EPCI Platform for Vietnam
http://slidepdf.com/reader/full/fixed-platforms-epci-platform-for-vietnam 2/5
J. Ray NEWS •aymcdermott.com
project management personnel being new hires, building teamwork
was a courageous endeavor.
“Each new hire received an orientation package with details about
the project, schedule, targets and other information,” explained
Anwar Ali, Su Tu Vang Senior Project Director. “A break-down of the
project scope was provided to each discipline level and then to the
individual level. Team members were virtually integrated with the
customer at all levels and a seamless open-door policy was estab-
lished to facilitate the ability to make decisions in the best interest of
the project and to guide, encourage and motivate team members.”
Another bold move was adding construction of a 66-person, four-
storey, living quarters module to the work scope half-way through
the project.
“We had to take this on, or jeopardize the whole project, as the
original subcontractor was falling behind schedule,” Anwar added.
The strength of J. Ray’s projec t management and execution abilities
made other achievements possible. A project-centric focus allowed
the team to establish priorities and resource allocation, facilitating
construction and achieving 100 percent onshore commissioning.
Involvement of fabrication and operations personnel in construc-tability reviews during FEED, preliminary engineering and detailed
design resulted in a platform design that is optimum, well laid out,
and construction- and maintenance-friendly.
A post-award vendor management task force comprised of pack-
age engineers, quality engineers and expediting commissioning
personnel, ensured timely delivery of a majority of the packages
with minimum punch-list items. During the procurement stage, a
structured scope definition led to simplified site assembly of large
packages and minimized interface issues.
Key personnel from in-house marine and hook-up groups
were involved throughout the various phases of the project to
Su Tu VangProject Experience
Jacket load-out and installation
4,000 tons, 8 legs•
4 conventional jacket roll ups•
Unique design for vertical launch•
Deck jack-up and load-out
17,000 tons•
Jack-up to insert load-out support frame•
4 strand jacks, 992-ton capacity each•
Deck height gain: 26 feet•
Distance pulled to quayside: 98 feet•
Break-out friction: 4.5%•
Pull distance to nal position: 656 feet•
42 portable submerged ballast pumps (capacity•
of each: 35,315 ft3 /hr) continually pumped
water to maintain constant level for 20 hours
Level within 1 inch despite a tidal•
range of 10 feet
Float-over installation
I-650 vessel used; second largest•
launch barge in the world
Rapid ballasting system triggered: 20•
minutes for 100 percent topsides load
transfer; 30 minutes to clear barge
10-point mooring system supplemented•
with soft mating lines
![Page 3: Fixed Platforms - EPCI Platform for Vietnam](https://reader038.fdocuments.in/reader038/viewer/2022100505/577cb5771a28aba7118d26db/html5/thumbnails/3.jpg)
8/9/2019 Fixed Platforms - EPCI Platform for Vietnam
http://slidepdf.com/reader/full/fixed-platforms-epci-platform-for-vietnam 3/5
24 • J. Ray NEWS jraymcdermo
expeditiously address interface issues. Similarly,
commissioning and customer operations person-
nel were integrated into the project team. Their
continuous involvement in vendor data review and
participation in factory acceptance testing (FAT)
eliminated bottlenecks during system hand-over,
onshore commissioning and testing prior to load
out of the deck.
As a result, the project experience strengthened
J. Ray’s relationship with the customer and its repu-
tation in the wider market.
Resilience also came into play on a number of
occasions. The unique geometry of the Su Tu Vang
jacket – large, almost cuboid – combined with a
water depth of 170 feet at the proposed installation
site posed a host of design, fabrication and installa-
tion challenges.
First, the planned dimensions of the jacket, dic-
tated by the float-over methodology, topsides
layout requirements and water depth at installation
site, precluded the traditional horizontal load out
and launch.
Secondly, as the jacket was to be installed over
an existing 12-slot conductor template, it was
preferable that it self-upend and float with suffi-
cient clearance from the seabed. A vertical launch
was developed, but with constraints on the jacket
weight and launch barge geometry.
While many smaller jackets have been built ver-
tically at Batam Island in previous years, the sheersize and complexity of the Su Tu Vang CPP was
uniquely challenging.
Build height of the topsides took into account
the height and space requirement for the installa-
tion of the jacking assembly, eliminating the need
for any late modification to the framing facilities
prior to jack up. The sub-cellar deck framing was
designed in a way that allowed jacking columns
to be inserted without any interference. This mini-
mized installation work subsequent to the jacking
operation and enabled the complete sub-cellar
deck assembly to be inserted prior to jacking.
Lessons learnedAs prescribed in the project life cycle, Su Tu Vang
included a comprehensive review and implemen-
tation of “lessons learned” from the 2007 Arthit
project, which was the first use of Intermac 650
(I-650) for float-over installation, to carry out the
operation smoothly and efficiently.
From these lessons learned, I-650 was further
modified to adapt the barge for float-over opera-
tions. The layout was improved to optimize the use
of space on the barge’s deck, coiled polyrope mats
were added to prevent paint damage to the jacket
legs, and a new tank-gauging system and display
were installed at control rooms. Another major
change was a more robust mooring system that
allowed crews to essentially “walk” I-650 to the Su
Tu Vang jacket for float over.
As a result of incorporating Arthit’s lessonslearned, the Su Tu Vang float over was “picture per-
fect,” according to Anwar.
Thus taming the golden lion, these achievements
highlight the team work, dedication and ingenu-
ity required to ensure a successful, safe and speedy
completion of a major project. They also illustrate
and validate the significant synergies that are pos-
sible with early planning, design inputs and proper
coordination among all parties.
Following local tradition, the
Batam Island, Indonesia facility
uses the services of a rain stop-
per on important occasions.
Efforts to stop, delay or divert
unwelcome rainfall represent
one of the oldest traditions in
Indonesian cultural practices. It
is the only natural occurrence
that such intervention is applied.
Earthquakes, tsunamis, floods,
strong winds and thunder are
considered predestined through
Mother Nature and unable to be
predicted, stopped or diverted.
The rain can be controlled,
however, by a unique rit-
ual called “Pawang Hujan.”
Performed at a rain-free spot
where a function or activity
is being held, the ceremony
involves burning incense and a
plate of fire to produce smoke
that on rising is believed to push
clouds away and make the rain
fall elsewhere or to actually stop
until after the rain-stopping rit-
ual ends.
A recent example at Batam
Island was on the 2 p.m. sched-
uled celebration of the Su Tu
Vang sail away. Torrential rain at
10 a.m. that day prompted the
services of a rain stopper, who
announced at noon that the rain
would stop at 1:30 p.m. It did,
and then started again at 4 p.m.
“I’ve seen it happen like thatmany times,” said Anwar Ali, Su
Tu Vang Senior Project Director.
![Page 4: Fixed Platforms - EPCI Platform for Vietnam](https://reader038.fdocuments.in/reader038/viewer/2022100505/577cb5771a28aba7118d26db/html5/thumbnails/4.jpg)
8/9/2019 Fixed Platforms - EPCI Platform for Vietnam
http://slidepdf.com/reader/full/fixed-platforms-epci-platform-for-vietnam 4/5
jraymcdermo
Arthit/Gulf of Thailand This major project included the largest topsides – 18,700 tons – ever built in Asia Pacific; 5,400-ton,
90-inch diameter, eight-leg jacket and associated infrastructure; and innovative engineering of trans-
port and rapid-ballast float-over installation hardware. Despite a demanding schedule and conditions,
seamless integration of J. Ray’s worldwide capabilities ensured schedule certainty.
Engineering: Houston/New Orleans/Singapore – Float-over engineering design, testing and
conversion of Intermac 650 transport and oat-over installation barge • Batam Island Indonesia –
Construction engineering for topsides • Dubai, UAE – Installation engineering support
Procurement: Asia Pacific region
Construction: Batam Island, Indonesia – Topsides and jacket
Installation: Asia Pacic eet – Jacket • Intermac 650 – Topsides oat over
As an EPCI company, we not only providecomprehensive services – from concept
to commissioning – but offer the resource
commitment, contracting strategy and mature
project management systems to execute on
the most complex, fastest track projects.
Integrated services, worldw
Poinsettia/Northwest Coast of TrinidadJ. Ray undertook this fast-track EPCI field development project from FEED to installation under a con-
sortium with Fluor. Facilities include a 9,100-ton jacket, 4,658 tons of piles and a 4,267-ton topsides.
Engineering: Houston, Texas – FEED and detailed design of jacket
Procurement: Houston, Texas – Jacket and piles
Construction: Morgan City, Louisiana – Jacket and piles
Installation: Gulf of Mexico fleet – jacket and topsides
Houston, TexasNew Orleans, Louisiana
26 • J. Ray NEWS
Map Key
Engineering
Procurement
Construction
Installation
Morgan City, Louisiana
![Page 5: Fixed Platforms - EPCI Platform for Vietnam](https://reader038.fdocuments.in/reader038/viewer/2022100505/577cb5771a28aba7118d26db/html5/thumbnails/5.jpg)
8/9/2019 Fixed Platforms - EPCI Platform for Vietnam
http://slidepdf.com/reader/full/fixed-platforms-epci-platform-for-vietnam 5/5
J. Ray NEWS •aymcdermott.com
resources
Su Tu Vang/Mekong Basin, VietnamJ. Ray’s regional Asia Pacific resources completed this challenging EPCI project, setting an industry
benchmark for the 17,000-ton float-over deck from FEED to First Oil.
Engineering: Jakarta, Indonesia – FEED and preliminary engineering • Singapore – Design and
detailed engineering for topsides and jacket • Dubai, UAE – Installation engineering support •
Houston, Texas – Float-over engineering and model testing
Procurement: Asia Pacific region
Construction: Batam Island, Indonesia – Topsides and jacket
Installation: Asia Pacic eet – Pipelines, cables, PLEMs and jacket • Intermac 650 – Topsides oat over
Reliance/Offshore IndiaJ. Ray completed this fast-track EPCI project in 18 months, mobilizing worldwide resources to meet
the challenging deadline on a 19,842-ton control and riser platform.
Engineering: Houston, Texas – Major engineering services • Dubai, UAE – Construction and installa -
tion engineering support
Procurement: Houston, Texas • Dubai, UAE • Morgan City, Louisiana
Construction: Morgan City, Louisiana – Jacket • Dubai, UAE – Topsides, living quarters modules,
piles and boat landing
Installation: Asia Pacific fleet’s DB101 construction vessel
Singapore
Jakarta, IndonesiaBatam, Indonesia
Dubai, UAE