Five Year Financial Plan April 14 !"#$ The City of Williams Lake Five Year Financial Plan including supplementary information is provided in this overview. Key areas of note are long term debt, level of taxation, capital projects and City Council Committee recommendations. 2015 Budget

description

2015 Budget Presentation by the City of Williams Lake

Transcript of Five Year Financial Plan Presentation

  • Five Year Financial Plan

    April 14

    !"#$The City of Williams Lake Five Year Financial Plan including supplementary information is provided in this overview. Key areas of note are long term debt, level of taxation, capital projects and City Council Committee recommendations.

    2015 Budget

  • 2015 Budget

    1 | P a g e

    Table of Contents FIVE YEAR FINANCIAL PLAN BYLAW #2232 ................................................................................... 2

    RESERVES ................................................................................................................................................. 14

    SUMMARY OF 2015 CAPITAL PROJECTS ......................................................................................... 15

    General Fund Capital Includes Airport ......................................................................................... 15

    Water and Sewer Capital .................................................................................................................... 16

    Pavement Rehabilitation ..................................................................................................................... 17

    DEBT FINANCING ................................................................................................................................. 19

    TAXATION ............................................................................................................................................... 20

    COMMITTEE COMPOSITION AND RESOLUTIONS ...................................................................... 21

    Other Committee Recommendations and Changes to the Initial Budget ................................... 24

    ORGANIZATIONAL STRUCTURE ...................................................................................................... 25

    SUMMARY ............................................................................................................................................... 27

  • 2015 Budget

    2 | P a g e

    FIVE YEAR FINANCIAL PLAN BYLAW #2232

    The City of Williams Lake Council Committees met over the course of several months to each review the budgets associated with their individual portfolios. The Finance Committee also met in Public Forum over January and February to discuss the budget and allow input from the public on the budget content or the changes being proposed.

    Long term goals to be incorporated into the budget process include:

    A goal of establishing new growth and a 0% increase in taxation to cover operating and capital costs; A goal to eliminate reliance on reserves for operations; Strive to be the most open and transparent budget process in the Province of BC;

    The City will begin budget discussions for the 2016-2020 budgets in September of 2015 and hope to have a finalized budget to present to the public by December. This will allow staff to begin the tendering process earlier in the year to prepare and complete approved capital projects. The City of Williams Lake has also publicly published on the City Website the incremental steps of the budget as well as the last 5 years of expenditures and revenues for the public to view and comment. The site is interactive and presents the figures in several different table views, allows for custom reports to compare years and exports to excel for public analysis. The site has an option to comment, ask questions, and enables the City to be fully transparent with revenue and expenditures to the public.

    We are striving to be the most transparent community in B.C. The newest report on OpenGov visualizing our budget process is the latest example of our commitment to an open, public budget in which we invite the communitys participation, said Finance Committee Chair Councilor Scott Nelson.

    The culmination of all the suggestions and meetings has resulted in the completion of the presented 5 Year Financial Plan.

  • 2015 Budget

    3 | P a g e

  • 2015 Budget

    4 | P a g e

  • 2015 Budget

    5 | P a g e

  • 2015 Budget

    6 | P a g e

  • 2015 Budget

    7 | P a g e

  • 2015 Budget

    8 | P a g e

  • 2015 Budget

    9 | P a g e

  • 2015 Budget

    10 | P a g e

  • 2015 Budget

    11 | P a g e

  • 2015 Budget

    12 | P a g e

  • 2015 Budget

    13 | P a g e

  • 2015 Budget

    14 | P a g e

    RESERVES

    The presented 5 Year Financial Plan includes transfers to reserves increasing each year. The plan is heavily reliant on the use of these transfers within the individual budget years. Council has made a resolution to decrease dependency on reserves and look for efficiencies within operations to achieve this goal.

    New reserves established within the Financial Plan include a transfer to a Water Reserve at a level of $125,000 and a transfer to a Sewer Reserve in the amount of $125,000. The recommendation of the Finance Committee is that these reserves are used towards extending future water and sewer infrastructure in areas that currently do not have access to these services. Past applications for this type of infrastructure extension have not been successful.

  • 2015 Budget

    15 | P a g e

    SUMMARY OF 2015 CAPITAL PROJECTS

    General Fund Capital Includes Airport

    Airport Capital projects have been mainly dependent on receiving funding from ACAP (Airport Capital Assistance Program). ACAP dependent projects are noted in yellow.

  • 2015 Budget

    16 | P a g e

    Water and Sewer Capital

  • 2015 Budget

    17 | P a g e

    Pavement Rehabilitation

    The City of Williams Lake is committed to continuing with the road rehabilitation and reconstruction projects proposed in the 2014 Budget process at an annual cost of approximately $1.2 million dollars. The 2015 road rehabilitations and costs are outlined below.

  • 2015 Budget

    18 | P a g e

  • 2015 Budget

    19 | P a g e

    DEBT FINANCING

    The City of Williams Lake will not be acquiring any new debt for 2015, but of note in the 5 Year Financial Plan is debt acquisition in 2016 and in 2018 for purchases of Fire Department trucks. Short Term Borrowing for Cameron Street Reconstruction will be fully paid in 2015. Long Term Debt will be maturing 2018-2031.

  • 2015 Budget

    20 | P a g e

    TAXATION

    The 5 Year Financial Plan includes a 0% increase for 2015, with a 3% increase built in over the next 4 years. Taxation in subsequent years will be determined by Council based on tax base growth, economy, capital requests and inflationary considerations. Increases are for presentation of the Financial Plan only. Taxation in 2014 showed an $114,000 decrease in taxation due to supplementary re-assessments and decreased growth. 2015 preliminary growth calculations show an $114,000 growth in taxation, essentially gaining back what was lost in the prior year.

    Anticipated growth in taxation over the next 5 Years is estimated at approximately $110,000 annually which equates to a 1% taxation increase.

    With the re-establishment of the Economic Development Corporation and dedicated funding from the City of Williams Lake, the Corporation hopes to attract new business, development and promote growth within the City. This will result in an increased assessment base which will minimize dependency on reserves and taxation increases.

    The residents of the City of Williams Lake will see an increase in taxation of approximately $40 per $100,000 of assessed value due to the passing of the pool referendum. This taxation will take effect beginning in 2015.

  • 2015 Budget

    21 | P a g e

    COMMITTEE COMPOSITION AND RESOLUTIONS

  • 2015 Budget

    22 | P a g e

  • 2015 Budget

    23 | P a g e

  • 2015 Budget

    24 | P a g e

    Other Committee Recommendations and Changes to the Initial Budget

  • 2015 Budget

    25 | P a g e

    ORGANIZATIONAL STRUCTURE

    During the 2015 Budget Year, the City has made some significant changes to staffing. The new management structure for the organization is depicted below.

    City departments with some functions Include:

    Protective Services Fire Protection, Bylaw Municipal Services Public Works, Roads, Water, Sewer, Fleet, Solid Waste, Cemetery, Buildings,

    Purchasing, Parks and Transportation. Corporate Administration Policies, Agendas, FOI, Legal, Bylaws Development Services Planning, Engineering and Building Inspection Financial Services Budget, Financial Statements, Investment, Debt Administration, Taxation, Utilities,

    Accounts Payable, Payroll and Accounts Receivable Recreation Services Complex Administration (Pool and Arena), Trails Human Resources Hiring, Employee Wellness, Safety, Benefits RCMP Policing, Community Safety, Victim Services Airport

  • 2015 Budget

    26 | P a g e

    Payroll The Payroll Section administers the pay function for City employees in accordance with the collective agreement and policies which are in effect. As of March 1, 2015 there are currently 169 employees excluding Management and Council on the payroll system, divided into the groups below. The City is not anticipating any major changes to this number over the course of the Financial Plan. IUOE Local 882B (City employees) ... 122 Exempt Employees (Volunteer Fire Fighters) ... 47

  • 2015 Budget

    27 | P a g e

    SUMMARY

    The City of Williams Lake has changed the budget deliberation and public presentation process considerably in the last year from what has been presented in the past. This is mainly due to public Finance Committee meetings and our new transparency website hosted by OpenGov. Our goal to be the most transparent financial and budget process in BC is attainable and will be built upon each year.

    Although this report outlines mostly financial implications and goals for the community, Council has made a commitment through its Official Community Plan to long term non-financial goals such as community safety, social development, environmental sustainability, convenient transportation, distinctive arts, culture and heritage, world class recreation, affordable housing, partnering with First Nations and a lively downtown.

    The individual departments of the City of Williams Lake are consistently striving to improve services to the community, and have been successful in achieving goals set by Council. This continues to be a work in progress over the 5 Year Financial Plan to work within the constraints of the current economy and revenue generation levels. Staff will continue to bring forward ideas for alternative revenue streams and maximize granting opportunities as they become available.