Clarksville Street Department Fiscal Year 2017 Budget Presentation

Transcript of Fiscal Year 2017 Budget Presentation

Clarksville Street Department

Fiscal Year 2017

Budget Presentation

Clarksville Street Department FY 2017 Proposed Budget

39.9%

54.3%

5.8%

Salaries/Benefits

OperatingExpenses

Capital Outlay

Clarksville Street Department

Services Provided: 6 basic areas

• Pavement Managemento 640 miles of road maintained

o $4.2 million annually on street maintenance

o Resurfacing done both in-house and by bid/contract

o Pavement management system—streets rated 1 to 100

• Drainageo 3 crews

o Maintain culverts, ditches, sinkholes and other drainage structures

• Traffico 21,800 +/- street signs

o 10,800 street lights

o 93 traffic signals—traffic operations center at office complex

o pavement markings and guardrail

Clarksville Street Department

• R-O-W Maintenanceo Street sweeping

o Mowing

o Trash pickup

o Snow and ice removal

o Beautification

o Cemetery

o Flower Beds

• Concreteo 5 person crew—maintains sidewalks, curb & gutter, other concrete structures

• Mosquito Controlo done all by bid/contract with McGee pest control of Hopkinsville: $95,000.00

o Phone Number: 1-800-420-2847

Clarksville Street Department

Engineering Division:• Engineering Staff - Manager, Traffic Engineer, Storm Water Drainage Engineer

• 5 Inspectors — monitor construction of new subdivisions and capitol projects

• GIS Administrator — maintains computerized mapping system of City of Clarksville, pavement management system

• NPDES Coordinator

Recently Completed Capital Projects:• Salt Shed (Needmore Road)

• Dunbar Cave Road improvements

• ADA and new sidewalk compliance

• TDOT has determined the bridge to be structurally deficient

• TDOT estimate with bridge in kind $1,432,000• Replacement with culvert and fill $150,000

Recently Completed Capital ProjectNeedmore Salt Complex

Recently Completed Capital ProjectDunbar Cave Road Improvements

Recently Completed Capital ProjectNew Sidewalk

• 28.12 Miles paved

Paving 2015-16

Clarksville Street Department FY 2017 Proposed Budget

Actual 2015Original Budget

2016

Projected2016

Proposed2017

Salaries/Benefits $5,082,122.10 $5,318,213.00 $5,232,627.00 $5,341,349.00

Operating Expenses $6,467,701.90 $6,953,815.00 $7,074,066.00 $7,257,372.00

Capital Outlay $338,764.60 $489,650.00 $454,980.00 $775,036.00

TOTAL $11,888,588.60 $12,761,678.00 $12,761,673.00 $13,373,757.00

FTE/New Employee RequestsFull-time

EquivalentFY 2013 FY 2014 FY 2015 FY 2016

ProposedFY 2017

# of Full-time 86 86 88 88 88

# of Part-time 5 5 4 6 6

Full-time Equivalent

88.5 88.5 91.5 90.8 90.8

New Employee Requests Expected Cost Reason for Position

None

Increases

• Software – Traffic signal coordination $60,000– Replacing out of date software

• Contract Paving – Increased $300,000– Inflation

– More miles of road to maintain

• Building Repair – Roof at Street Department Complex $30,000

• Vehicle Repair - $25,000 – Due to aging fleet

Capital Vehicle Outlay RequestsOperating Expenses

RequestCost Justification

(2) Single-Axle DumpTrucks

$173,968.00 Replaces (2) 2004 Freightliner FL70

Tandem Dump Truck $106,778.00 Replaces 2005 Sterling Acterra

Extended Cab FWD Pick-up Truck

$26,080.00 Replaces 2006 Dodge Ram

One-Ton Dump Truck $47,230.00 Replaces 2001 GMC 3500

Capital Equipment Outlay Requests

Operating ExpensesRequest

Cost Justification

Caterpillar 297D Compact Tracked Loader

$81,215.00 Need for milling and drainage work.

Sweeper – Leaf Vacuum $163,850.00 Replaces 1998 model

Caterpillar 305 Mini Excavator

$82,980.00 Used to access ditcheswhere backhoes are unable to.

Capital Equipment Outlay Requests

Operating ExpensesRequest

Cost Justification

(1) 8’ Snow Plow $7,350.00 To enable new 1-ton dump truck to clear snow.

(3) 10’ Snow Plows $25,800.00 To enable new single axle and tandem dump trucks to clear snow.

(3) 10’ Salt Boxes $44,445.00 To enable new single axle and tandem dump trucks to distribute salt.

Capital Equipment Outlay Requests

Operating ExpensesRequest

Cost Justification

(1) 8’ Salt Box $8,390.00 To enable new 1-ton dump truck to distribute salt.

Bush Hog $6,950.00 To maintain City mowing right-of-ways.

• TDOT has determined the bridge to be structurally deficient

• TDOT estimate with bridge in kind $1,432,000• Replacement with culvert and fill $150,000

Capital ProjectRinggold Bridge

Capital ProjectTraffic Signal Installation: Ringgold Rd and 101st Airborne Pkwy

• Estimated Construction Cost - $250,000

• High Crash Rate - over 13 per year

• High Crash Severity - 46% Injury or Fatal

Capital ProjectAdaptive Signal Control Wilma Rudolph

Blvd• Estimated Construction Cost - $800,000

• City will seek Federal and State Funding

• 10 intersections

• Adjusts Timing based on current conditions

• Responds to Seasonal Demands, I-24 Incident Traffic Diversions and Military Deployments

Capital ProjectNew Sidewalk

• Continue with new sidewalk according to the Sidewalk Priority Indicator

• Design and Construction $700,000

Capital ProjectTylertown Road and Oakland Road Design

• Road Improvements due to extreme growth and Oakland Elementary

• 3 to 5 lane road with sidewalks with curb and gutter• Potential for Bike Lanes• Design and Environmental $1,500,000

Capital ProjectDunlop Lane – International Blvd. Intersection Design

• In anticipation of Hankook opening

• Design only $20,000

Capital ProjectTrenton Road Storm Water Overflow Pipe

• Continuation of aerial drainage improvements

• Design and Construction $920,000