FISCAL YEAR2016-2017
OVERALL WORK PROGRAM
Quarter 4 April – June 2017 (Final Expenditures)
Work Element
Project Number Project Name Page
010 SYSTEM PLANNING
SCG00170 Regional Transportation Plan (RTP)
170.01 RTP Support, Development, and Implementation 1
170.07 Implementation Strategy For 2012 RTP 4
170.08 Transportation Safety and Security 6
SCG01631 TDM Strategies
1631.02 Transportation Demand Management (TDM) Planning 8
1631.04 Congestion Management Process (CMP) 10
1631.05 TDM Strategic Plan 12
SCG02106 System Preservation
2106.02 System Preservation 14
015 TRANSPORTATION FINANCE
SCG00159 Transportation Finance
159.01 RTP Financial Planning 16
159.02Transportation User Fee - Planning Groundwork Project Phase II 18
159.04 Value Pricing Project Management Assistance 20
020 ENVIRONMENTAL PLANNING
SCG00161 Environmental Compliance
161.04 Regulatory Compliance 23
161.05 Intergovernmental Review (IGR) 25
Overall Work Program
Table of Contents
FY 16/17 OWP Table of Contents 1 of 10
Work Element
Project Number Project Name Page
025 AIR QUALITY CONFORMITY
SCG00164 Air Quality Planning and Conformity
164.01 Air Quality Planning and Conformity 27
030 FEDERAL TRANSPORTATION IMPROVEMENT PROGRAM
SCG00146 Federal Transportation Improvement Program
146.02 Federal Transportation Improvement Program 30
045 GEOGRAPHIC INFORMATION SYSTEM (GIS)
SCG00142 Application Development
142.05 Advanced Technical Support 34
142.07 FTIP System Enhancement, Maintenance, and Support 36
142.12 Enterprise GIS (EGIS) Implementation 38
142.17 Quality Assurance Requirements and Documentation 41
142.22 Planning System Development 43
SCG00694 GIS Development and Applications
694.01 GIS Development and Applications 45
694.02 Enterprise GIS Implementation 47
694.03 Professional GIS Services Program Support 49
694.04 GIS Programming and Geospatial Analysis 51
50 ACTIVE TRANSPORTATION PLANNING
SCG00169 Active Transportation Planning
169.01 Regional Active Transportation Strategy 54
169.02 Active Transportation Safety 56
169.06 Active Transportation Program 58
FY 16/17 OWP Table of Contents 2 of 10
Work Element
Project Number Project Name Page
055 REGIONAL FORECASTING AND POLICY ANALYSIS
SCG00133 Integrated Growth Forecasts
133.06 University Partnership & Collabortation 61
SCG00704 Region Wide Data Collection & Analysis
704.02 Region-Wide Data Coordination 63
SCG01531 Southern California Economic Growth Strategy
1531.01 Southern California Economic Growth Strategy 66
1531.02 Economic Analysis of Adopted 2012-2035 RTP/SCS 70
060 CORRIDOR PLANNING
SCG00124 Corridor Planning
124.01 Corridor Planning 75
065 SUSTAINABILITY PROGRAM
SCG00137 Sustainability Program
137.01 Sustainability Program Call for Projects 77
137.07 Local Technical Assistance 83
137.08 Sustainability Recognition Awards 85
137.09 CEO Sustainability Working Group 87
137.10 Civic Sparks Program 89
137.11 Sustainability Interns 91
SCG02663 Transportation Land Use Planning
2663.03 2050 GHG Pathways Regional Study 93
SCG04092 GHG Adaptation Framework
4092.01 Adaptation Analysis 96
FY 16/17 OWP Table of Contents 3 of 10
Work Element
Project Number Project Name Page
070 MODELING
SCG00130 Regional Transp. Model Development and Maintenance
130.10 Model Enhancement and Maintenance 98
130.12 Heavy Duty Truck (HDT) Model Update 101
130.13 Activity-Based Model (ABM) Development and Support 103
SCG00132 Regional & Subregional Model Coordination/Outreach
132.01 Subregional Model Development 106
132.04 Regional Modeling Coordination and Modeling Task Force 108
132.08 Model Data Distribution and Support 110
SCG00147 Model Application & Analysis
147.01 RTP Modeling, Coordination and Analysis 112
147.02 FTIP Modeling, Coordination and Analysis 114
147.03 Speical Planning Studies Modeling and Analysis 116
SCG02665 Scenario Planning and Growth Forecasting
2665.01 Scenario Planning and Modeling 118
080 PERFORMANCE ASSESSMENT & MONITORING
SCG00153 Performance Assessment & Monitoring
153.04 Regional Assessment 120
153.05 Data Compilation and Circulation 122
090 PUBLIC INFORMATION & COMMUNICATION
SCG00148 Public Information and Communication
148.01 Public Information and Communication 124
FY 16/17 OWP Table of Contents 4 of 10
Work Element
Project Number Project Name Page
095 REGIONAL OUTREACH AND PUBLIC PARTICIPATION
SCG01533 Regional Transportation Plan Development Outreach
1533.01 Regional Transportation Plan Outreach 127
1533.02 Regional Planning & Policy Intern Program 129
1533.03 Media Support for Planning Activities 131
SCG01633 Regional Outreach and Public Participation
1633.01 Public Involvement 133
SCG04097System-wide Emergency/Earthquake Preparedness Planning
4097.01System-wide Emergency/Earthquake Preparedness Planning 135
100 INTELLIGENT TRANSPORTATION SYSTEM (ITS)
SCG01630 Intelligent Transportation Systems Planning
1630.02 Intelligent Transportation Systems (ITS) Planning 137
1630.03Regional ITS Strategic Plan and Regional ITS Architecture Update 139
120 OWP DEVELOPMENT & ADMINISTRATION
SCG00175 OWP Development & Administration
175.01 OWP Development & Administration 141
175.02 Grant Administration 144
130 GOODS MOVEMENT PLANNING
SCG00162 Goods Movement
162.02 Southern California National Freight Gateway Collaboration 146
162.09Urban Goods Movement (Warehousing/Transloading in the SCAG Region) 148
162.10 East-West Freight Corridor/I-15 Phase II 150
162.13Southern California P3 Financial Capacity Analysis and Business Case Development 152
162.18 Goods Movement Planning 154
FY 16/17 OWP Table of Contents 5 of 10
Work Element
Project Number Project Name Page
140 TRANSIT AND RAIL
SCG00121 Transit and Rail Planning
121.01 Transit and Planning 156
121.02 Regional High Speed Transport Program 159
121.06 LA-San Bernardino Inter-County Connectivity Study 162
121.07LA-Orange Inter-County Connectivity Study (Green Line Extension) 164
150 COLLABORATIVE PROJECTS
SCG004093 Partnership for Sustainability
4093.01 Integrated Co-Benefits/Special Programs 207
4093.02 HQTA/Sustainable Communities Initiative 210
SCG004094 Cap and Trade
4094.01 Integrated Sustainability Program 213
4094.02Greenhouse Gas Reduction Fund (GGRF) Technical Assistance 216
SCG004095 Comprehensive Monitoring
4095.01 RTP/SCS Performance Monitoring 218
4095.02 Mobility Innovations/Technology Study 221
4095.03 SCAG Regional Active Transportation Partnership Platform 223
SCG004096Scenario Planning & Local Input: Pathways to the 2020 RTP/SCS
4096.01 RTP/SCS Land Use Policy and Program Development 226
4096.02 Regional Growth and Policy Analysis 229
4096.03Growth Forecasting - Development, Outreach, and Collaboration 232
4096.04 Outreach and Technical Collaboration 235
4096.05 Affordable Housing and Displacement Analysis 237
FY 16/17 OWP Table of Contents 6 of 10
Work Element
Project Number Project Name Page
230 AIRPORT GROUND ACCESS
SCG00174 Aviation System Planning
174.05Regional Aviation Demand Forecasts and Airport Ground Access Element for 2016 RTP/SCS 198
SPECIAL GRANT PROJECTS
145 TRANSIT PLANNING GRANT STUDIES & PROGRAMS
SCG02567 Calexico Transit Needs Assessment Study
2567.01 Calexico Transit Needs Assessment Study 166
SCG02570Imperial Valley-SDSU-Imperial Valley Transit Shuttle Anlaysis
2570.01Imperial Valley-SDSU-Imperial Valley Transit Shuttle Anlaysis 168
SCG03170 City of Thousand Oaks Transit Student Internship
3170.01 City of Thousand Oaks Transit Student Internship 170
SCG03172 Gold Coast Transit Internship
3172.02 Gold Coast Transit Internship 172
SCG03173 Thousand Oaks Transit Master Plan
3173.01 Thousand Oaks Transit Master Plan 174
SCG03174 Pasadena Transit Division Student Internship II
3174.01 Pasadena Transit Division Student Internship 176
SCG03253 State Routes 57 & 60 Confluence, Feasibility Study
3253.01 State Routes 57 & 60 Confluence, Feasibility Study 178
SCG03475 Transit Climate Adaptation and Resiliency Plan
3475.01Transit Climate Adaptation and Resiliency Plan for Southern California 180
SCG03477 RTA First and Last Mile Strategic Mobility Assessment
3477.01 RTA First and Last Mile Strategic Mobility Assessment 182
SCG03480 Aviation Boulevard Multimodal Corridor Plan
3480.01 Aviation Boulevard Multimodal Corridor Plan 184
FY 16/17 OWP Table of Contents 7 of 10
Work Element
Project Number Project Name Page
SCG03481 Pacific Coast Highway Parking Master Plan
3481.01 Pacific Coast Highway Parking Master Plan 186
SCG03482City of Fontana - Malaga Bridge Community-based Opportunities Analysis
3482.01City of Fontana - Malaga Bridge Community-based Opportunities Analysis 188
SCG03483 Transit Planning for Sustainable Communities
3483.01Anaheim Integrated Transportation & Capacity Building Plan 190
SCG03824San Gabriel Valley Active Transportation Data Planning Project
3824.01 Activetrans Data Planning Project 192
SCG03829Active Streets LA - Pedestrian and Bicycle-Friendly Streets for South Los Angeles
3829.01Active Streets LA - Pedestrian and Bicycle-Friendly Streets for South Los Angeles 195
SCG03830Customer Based Ridesharing and Interconnectivity Study
3830.01 Customer Based Ridesharing and Interconnectivity Study 197
SCG03831Huntington Drive Safe Streets Corridor Improvement Plan
3831.01 Huntington Drive Safe Streets Corridor Improvement Plan 199
SCG03832 Los Angeles River Bikeway Feasibility Study
3832.01 Los Angeles River Bikeway Feasibility Study 201
SCG04424 I 105 Corribor Study
4424.01 I 105 Corridor Study 203
SCG04425 City of Santa Ana Active Transportation Plan
4425.01 City of Santa Ana Active Transportation Plan 205
225
SCG01641Electric Vehicle (EV) Program (Multi-Unit Dwelling (MUD) Plug-in PEV Readiness Strategies)
1641.04Electric Vehicle (EV) Program (Multi-Unit Dwelling (MUD) Plug-in PEV Readiness Strategies) 239
SCG02659 Open Space Strategic Plan
2659.01 Comprehensive Planning for Open Space Strategic Plan 241
SPECIALIZED GRANT PROJECTS
FY 16/17 OWP Table of Contents 8 of 10
Work Element
Project Number Project Name Page
2659.02SANBAG/County of San Bernardino Habitat Conservation Framework 243
2659.03 Scenario Planning Module - Land Conservation 245
2659.04 County Transportation Commission Open Space Initiative 247
SCG02661 Public Health
2661.01 Public Health 249
SCG03564 So. California Active Transportation Safety & Encourag
3564.01So. California Active Transportation Safety & Encouragement Campaign 252
3564.02 County of Riverside Tactical Urbanism Events 255
3564.04 OC Parks Tactical Urbanism Event 257
3564.05 SANBAG Tactical Urbanism Event 259
3564.07 City of Cudahy Tactical Urbanism Event 261
3564.09 Go Human - Office of Traffic Safety 263
3565.10 MSRC Go Human - Sustainability Planning Grants 265
SCG03565 FHWA First Mile/Last Mile Greenhouse Gas Demo
3565.01 First Mile/Last Mile Greenhouse Demonstration Analysis 267
SCG04345San Gabriel Valley Active Transportation Planning Initiative
4345.01 San Gabriel Valley Active Transportation Planning Initiative 269
260 JARC/NEW FREEDOM PROGRAM ADMINISTRATION
SCG00469 JARC & New Freedom Program Administration
469.01 Administration of JARC & New Freedom Program 273
265 SO. CALIF. VALUE PRICING PILOT PROGRAM
SCG02125 Express Travel Choices Phase II
2125.01 Express Travel Choices Phase II 275
2125.02 Express Travel Choices Phase III 277
FY 16/17 OWP Table of Contents 9 of 10
Work Element
Project Number Project Name Page
266 REGIONAL SIGNIFICANT TDA-FUNDED PROJECTS
SCG00715 Locally-Funded Projects
715.01 Locally-Funded Projects 279
715.04 SGC - AHSC Pilot Program 281
715.05 Riverside Reconnects Phase 2 283
SCG03920 SCAG/Caltrans East-West Freight Corridor
3920.01 SCAG/Caltrans East-West Freight Corridor 285
267 CLEAN CITIES PROGRAM
SCG01241 Clean Cities Coalition
1241.04 SCAG and DOE/NETL Clean Cities Coalition Coordination 287
270 FTA SECTION 5310, 5337 & 5339 GRANT ADMINISTRATION
SCG03833 FTA 5339 Program and Support Administration
3833.01 FTA 5339 Program and Support Administration 289
3833.02 Orange County Transp. Commission 291
3833.03 OMNITRANS Bus Replacements 297
3833.04 Riverside Transit Agency Section 5339 Bus & Bus Facilities 295
3833.05Sunline Transit Agency S. 5339 Bus & Bus Facilities and S. 5312 LONO 297
SCG03834 FTA 5310 Program and Support Administration
3834.01 Administration of Section 5310 299
SCG03835 FTA 5337 Program and Support Administration
3835.01 Administration of Section 5337 301
FY 16/17 OWP Table of Contents 10 of 10
OWP Progress ReportFOURTH QUARTER FY 16-17
010.00170.01 RTP SUPPORT, DEVELOPMENT, AND IMPLEMENTATION
OBJECTIVE: PROJECT MANAGER:
Ensure that the RTP is consistent with state and federal requirements while addressing the region's transportation
needs.
NARESH AMATYA
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Process amendments to the 2016
RTP/SCS as needed.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Support outreach activities
associated with the implementation
of the 2016 RTP/SCS and the
development of the 2020 RTP/SCS
as needed.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Continue to provide staff support for
the Transportation Committee by
preparing agendas, technical reports,
memos, and presentations, and
coordinate action items arising from
the Committee.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Continue to provide staff support for
technical advisory committees and
subcommittees as needed and
appropriate.
5
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor, manage, and maintain
capital list of projects associated
with the 2016 RTP/SCS on an
ongoing basis.
6
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate/manage the development
of the 2020 RTP/SCS.
7
100Staff06/30/201707/01/201606/30/201707/01/2016Review, comment, and coordinate
transportation studies conducted by
partner agencies to ensure
consistency with the adopted 2016
RTP/SCS.
8
Page 1 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.00170.01 RTP SUPPORT, DEVELOPMENT, AND IMPLEMENTATION
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 2016 RTP/SCS Amendments (as needed). 06/30/2017 06/30/2017
3 Meeting agendas and minutes from the Transportation
Committee and other technical committees and from
public outreach.
06/30/2017 06/30/2017
3 Technical issue papers, memorandums, presentations,
and/or reports.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
The 2016 RTP/SCS Amendment #1 FHWA/FTA conformity approval was received on May 12, 2017. The public
hearing for Amendment #2 was held on April 25, 2017. The 2016 RTP/SCS Amendment #2 is being finalized and
SCAG's Regional Council is scheduled to consider it for final approval at its July 6, 2017 meeting. In addition, staff
meets on a monthly basis to plan for and coordinate the development of the 2020 RTP/SCS. Staff also continues
working to support the Transportation Committee.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
567,291
153,592 114,998 0 213,632 5,000 15,000 0 0 0 0 65,069 0
502,222 0 0 0 0 0 0 0 65,069 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
Page 2 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.00170.01 RTP SUPPORT, DEVELOPMENT, AND IMPLEMENTATION
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 399,648 88,719 127,394 123,487 60,048
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 3 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.00170.07 IMPLEMENTATION STRATEGY FOR THE 2016 RTP/SCS
OBJECTIVE: PROJECT MANAGER:
Develop an implementation framework for the 2016 RTP/SCS for the next four years that will provide a road-map to
implement key transportation initiatives included in the 2016 RTP/SCS. The framework will aim to consider laying out
the coordination framework and process, progress monitoring mechanism, including identification and development
of appropriate data, review, assessment and adjustment methodology, and ultimately identify action steps to
reconcile the 2016 RTP/SCS with the realities on the ground.
COURTNEY AGUIRRE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage and coordinate consultant
work, including preparation of scope
of work, monitoring budget and
schedule.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop a framework for
implementation and monitoring of the
2016 RTP/SCS progress.
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Identify implementation actions
associated with the transportation
strategies for the 2016 RTP/SCS.
3
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Identify parameters, metrics and data
sources for monitoring progress of
the 2016 RTP/SCS.
4
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop methodologies, tools and
analytics to assess progress of the
2016 RTP/SCS.
6
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Framework for Implementation Strategy Plan 06/30/2017 06/30/2017
2 Progress reports for major initiatives 06/30/2017 06/30/2017
3 Technical issue papers, memorandums, presentations,
and/or reports
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Staff continued to coordinate implementation of the adopted 2016 RTP/SCS and monitor that progress, as well as
reviewing transportation studies conducted by partner agencies to ensure consistency with the RTP/SCS. The 2016
RTP/SCS Amendment #1 FHWA/FTA conformity approval was received on May 12, 2017. The public hearing for
PROGRESS
COMPLETED
Page 4 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.00170.07 IMPLEMENTATION STRATEGY FOR THE 2016 RTP/SCS
Amendment #2 was held on April 25, 2017. The 2016 RTP/SCS Amendment #2 is being finalized and SCAG's
Regional Council is scheduled to consider it for approval at its July 6, 2017 meeting.
Issues:
Resolution:
Comment:
Consultant contract was funded through multiple tasks. In the FY18 Adopted OWP, task 010-0170.07 was merged
with task 010-0170.01 and renamed RTP Support, Development and Policy Implementation. A consultant budget of
$150k is included in task 0170.01.
BUDGET / EXPENDITURE
226,989
35,808 26,810 0 49,805 0 0 100,000 0 0 0 14,566 0
112,423 88,530 0 0 0 11,470 0 0 14,566 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 56,669 9,476 20,367 14,398 12,428
CONTRACT STATUS (IF APPLICABLE)
SYSTEMS METRICS GROUPCONTRACT EXECUTED VENDOR:STATUS:
04/23/2013 12/31/2016 13-023-C1
2,112,321 69,213 533,698
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 5 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.00170.08 TRANSPORTATION SAFETY AND SECURITY
OBJECTIVE: PROJECT MANAGER:
Integrate safety and security into transportation planning projects to improve the safety and security of the
transportation system for motorized and non-motorized users by evaluating existing safety and security policies.
Evaluate transportation safety and security and assist in the development of regional safety and security policies for
the 2020 RTP/SCS.
COURTNEY AGUIRRE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Integrate safety and security into
transportation planning by
coordinating with other agencies and
jurisdictions to evaluate and develop
regional transportation safety and
security policies.
1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Transportation Safety and Security potential policies and
strategies for the 2020 RTP/SCS
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Staff continued to regularly participate in the SHSP Steering Committee meetings. In addition, staff attended
Caltrans' June 22 workshop regarding the statewide safety targets. Staff is evaluating existing safety conditions
within the region and is developing a report to share with stakeholders in the summer/fall. Staff is also evaluating
safety trends/forecasts and potential regional safety targets. This information will eventually be reflected in the 2020
RTP/SCS. Potential policies and strategies are also being evaluated.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 6 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.00170.08 TRANSPORTATION SAFETY AND SECURITY
BUDGET / EXPENDITURE
155,343
43,803 32,796 0 60,926 0 0 0 0 0 0 17,818 0
137,525 0 0 0 0 0 0 0 17,818 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 99,598 18,570 16,182 20,991 43,855
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 7 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.01631.02 TDM PLANNING
OBJECTIVE: PROJECT MANAGER:
TDM is a key strategy for helping the region achieve its mobility, air quality, and sustainability goals. The objective of
this task is to develop transportation options to improve mobility in the region by identifying and evaluating strategies
that promote alternatives to the single-occupant vehicle.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Continue updating and refining the
TDM toolbox for inclusion in
RTP/SCS.
1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Updated TDM strategies for inclusion in RTP/SCS update 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Staff worked on various TDM elements in the 4th Qtr., including researching innovative first/last mile strategies in the
SCAG region.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
This project continues in FY 18.
Page 8 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.01631.02 TDM PLANNING
BUDGET / EXPENDITURE
36,436
10,274 7,692 0 14,290 0 0 0 0 0 0 4,180 0
32,256 0 0 0 0 0 0 0 4,180 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 30,562 2,067 7,115 9,750 11,630
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 9 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.01631.04 CONGESTION MANAGEMENT PROCESS (CMP)
OBJECTIVE: PROJECT MANAGER:
The objective of this task is to ensure congestion management is part of the continuing transportation planning
process in accordance with California Government Code 65089 and the US Code of Federal Regulations,
23CFR450.320. Measures to monitor current congestion, evaluate projected congestion, and identify strategies to
manage congestion will be incorporated into the RTP/SCS update.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor and review county
Congestion Management Programs
for consistency with state and federal
requirements.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor and review county
submissions to Federal
Transportation Improvement Program
(FTIP) for consistency with USDOT
requirements for Congestion
Management Process (23 CFR
450.320).
2
100Staff06/30/201707/01/201606/30/201707/01/2016Review and refine measures to
monitor and evaluate current and
projected congestion, and identify
strategies to manage congestion for
inclusion in RTP/SCS.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 County Congestion Management Program comment
letters
06/30/2017 06/30/2017
2 Congestion management element of RTP/SCS update 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
1. During the 4th Quarter, staff continued to monitor county Congestion Management Programs for consistency with
state and federal requirements.
2. Staff also monitored and reviewed county submissions to Federal Transportation Improvement Program (FTIP)
for consistency with USDOT requirements.
PROGRESS
COMPLETED
Page 10 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.01631.04 CONGESTION MANAGEMENT PROCESS (CMP)
Issues:
Resolution:
Comment:
This project continues in FY 18.
BUDGET / EXPENDITURE
36,436
10,274 7,692 0 14,290 0 0 0 0 0 0 4,180 0
32,256 0 0 0 0 0 0 0 4,180 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 28,177 2,367 4,620 8,311 12,879
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 11 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.01631.05 TDM STRATEGIC PLAN
OBJECTIVE: PROJECT MANAGER:
The objective of this task is to develop a long-range TDM Strategic Plan to provide a framework for an
objectives-driven, performance-based planning process that identifies and promotes strategies to increase the
efficiency of the transportation system through alternative modes of travel. The Strategic Plan will help guide
long-range TDM initiatives, define specific management strategies for the region's most congested corridors, and
develop TDM-specific performance measures to assist with evaluating system-wide and project-level performance.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
0Staff06/30/201907/01/201806/30/201712/01/2016Provide project management,
support, and administration.
1
0Consultant06/30/201907/01/201806/30/201712/01/2016Solicit and incorporate stakeholder
input and participation.
2
0Consultant06/30/201907/01/201806/30/201712/01/2016Establish vision, goals, and
objectives for TDM.
3
100Consultant06/30/201704/24/201706/30/201712/01/2016Assess and strengthen TDM
performance evaluation and
monitoring methods and tools.
4
0Consultant06/30/201907/01/201806/30/201712/01/2016Develop regional TDM strategies and
Final Report.
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Long-Range TDM Strategic Plan 06/30/2017 06/30/2019
PERCENTAGE COMPLETED: 20 STATUS:
Accomplishments:
Purchased an upfront payment in full for data and online analysis tool which is available to SCAG beyond June 30,
2017
PROGRESS
DELAYED
This multi-year project was not funded in FY17-18 due to budget constraints.
Issues:
Given time constraints on the remainder of the fiscal year, available budget will be used to support Step 4
performance evaluation and monitoring through existing consultant support contracts. The consultant support
Resolution:
Page 12 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.01631.05 TDM STRATEGIC PLAN
consists of performance data and online analysis tool. The project will be temporarily suspended pending future
budget availability.
Comment:
This project is not in the FY 18 budget.
BUDGET / EXPENDITURE
176,000
0 0 0 0 0 0 176,000 0 0 0 0 0
0 155,813 0 0 0 20,187 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 160,000 0 0 0 160,000
CONTRACT STATUS (IF APPLICABLE)
INRIX, INC.CONTRACT EXECUTED VENDOR:STATUS:
04/24/2017 04/24/2018 17-022-C1 Amend1
359,000 359,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 13 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.02106.02 SYSTEM PRESERVATION
OBJECTIVE: PROJECT MANAGER:
The objective of this project is to continue ongoing efforts to develop a performance-based regional transportation
system management and monitoring program to help address the region’s preservation needs. This project also
aims to incorporate policies as part of the system preservation needs of the region in the upcoming 2016 RTP/SCS.
DANIEL TRAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage the project including
monitoring schedule,
budget, and objectives.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Continue ongoing efforts to develop a
performance-based regional
transportation system management
and monitoring program to help
address the region’s preservation
needs.
2
100Staff06/30/201701/02/201706/30/201707/01/2016Develop Draft and Final System
Preservation Memorandum.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Final Report on System Preservation to be incorporated
into the 2016 RTP/SCS.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
During the 4th quarter, staff continued to monitor the progress of system preservation efforts and is continuing
on-going coordination with partner agencies. Staff has also worked closely with Caltrans providing input regarding
their development of the Transportation Asset Management Plan - Phase II which will be submitted to FHWA next
fiscal year.
PROGRESS
COMPLETED
Issues:
Resolution:
Page 14 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
010.02106.02 SYSTEM PRESERVATION
Comment:
BUDGET / EXPENDITURE
120,220
33,899 25,381 0 47,150 0 0 0 0 0 0 13,790 0
106,430 0 0 0 0 0 0 0 13,790 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 19,885 7,776 2,647 4,805 4,657
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 15 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
015.00159.01 RTP FINANCIAL PLANNING
OBJECTIVE: PROJECT MANAGER:
Updates to 2016 RTP financial plan as required and initial development of 2020 RTP financial plan and supporting
elements. Facilitate work on efforts to evaluate alternative funding mechanisms for transportation. Work with
stakeholders on federal surface transportation re-authorization efforts related to technical input and analyses
associated with transportation finance component.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Prepare, manage, and coordinate
with stakeholders, the financial
component of the RTP.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor state and federal budgets as
well as reauthorization efforts to
assess implications on the RTP
financial plan.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate with Federal
Transportation Improvement Program
(FTIP) staff as needed to address
financial plan component.
3
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop/produce technical work and
analysis of transportation
funding/financing mechanisms.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Technical issue papers, memorandums, and/or reports
highlighting regional transportation finance concerns,
including assessment of current financial system needs.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Performed analysis for Amendments 1 and 2 to 2016 RTP/SCS. Started initial development of 2020 RTP/SCS
financial plan and supporting elements. Staff continues to monitor state and federal legislation and budgets to
assess implications on transportation finance.
PROGRESS
COMPLETED
Issues:
Page 16 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
015.00159.01 RTP FINANCIAL PLANNING
Resolution:
Comment:
This ongoing task is included in the FY 17/18 OWP.
BUDGET / EXPENDITURE
532,160
142,093 106,389 0 197,639 5,000 10,000 0 0 0 10,000 61,039 0
471,121 0 0 0 0 0 0 0 61,039 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 456,421 68,285 101,103 115,908 171,125
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 17 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
015.00159.02 TRANSPORTATION USER FEE - PLANNING GROUNDWORK PROJECT PHASE II
OBJECTIVE: PROJECT MANAGER:
Research, development, and demonstration specific to Southern California context. Explore partnerships with
automobile manufacturers and technology developers, and local/regional business leaders, including targeted
marketing and research specific to the SCAG region. Continue development of strategic action plan and initial
demonstration framework. Consider efforts outside the region for their application in the Southern California context.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide project management,
support, and administration.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Development of strategic action plan
and demonstration framework for a
transportation user fee.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Technical issue papers, memorandums and/or reports on
transportation user fees.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Outreach work is continuing, including planning for and initial deployment of expanded scope of outreach.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Work is a multi-year effort and is included in FY 17/18 OWP.
Page 18 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
015.00159.02 TRANSPORTATION USER FEE - PLANNING GROUNDWORK PROJECT PHASE II
BUDGET / EXPENDITURE
575,310
16,224 12,147 0 22,566 0 0 450,000 0 0 60,000 14,374 0
110,937 0 0 0 0 450,000 0 0 14,373 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 37,404 6,221 38 9,159 21,986
Consultant 450,000 0 54,737 66,539 328,724
CONTRACT STATUS (IF APPLICABLE)
INRIXCONTRACT EXECUTED VENDOR:STATUS:
06/25/2015 06/30/2017 15-035-C1
125,000 450,000 34,682
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 19 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
015.00159.04 VALUE PRICING PROJECT MANAGEMENT ASSISTANCE
OBJECTIVE: PROJECT MANAGER:
Development of critical milestones and documentation of the region’s progress in implementing the 2016 RTP.
Identification of potential challenges with implementing key value pricing initiatives, new opportunity areas,
recommended action steps, and implications for the 2020 RTP. Development of technical groundwork for 2020
RTP. Assistance to facilitate project management and technical coordination of multiple activities underway for the
region’s value pricing projects, as identified in the 2016 RTP.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Provide documentation of critical
milestones and progress in
implementing 2016 RTP, including
steps taken to demonstrate
applicability of value pricing
strategies, establish a regional
concept of operations for value
pricing, and integration of value
pricing with other transportation
components (e.g., transit) and land
use strategies.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop technical groundwork for
2020 RTP, including the development
of value pricing performance
measures, technology and
performance measure provisions, and
integration with statewide managed
lane policies.
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Provide technical assistance with
region's value pricing projects as
identified in the 2016 RTP.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Technical issue papers, memorandums, and/or reports
on 2016 RTP implementation, groundwork for the
development of the 2020 RTP, and value pricing projects
as identified in 2016 RTP.
06/30/2017 06/30/2017
Page 20 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
015.00159.04 VALUE PRICING PROJECT MANAGEMENT ASSISTANCE
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Consultant continued to provide technical support for SCAG's Value Pricing initiatives and coordinating efforts with
Caltrans and the county transportation commissions.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
This is a multi-year project; work will continue in FY 17/18.
BUDGET / EXPENDITURE
382,894
23,374 17,501 0 32,511 0 0 300,000 0 0 0 9,508 0
73,386 265,590 0 0 0 34,410 0 0 9,508 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 90,798 19,142 23,905 19,642 28,109
Consultant 235,355 0 54,737 15,291 165,327
Page 21 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
015.00159.04 VALUE PRICING PROJECT MANAGEMENT ASSISTANCE
CONTRACT STATUS (IF APPLICABLE)
SYSTEMS METRICS GROUPCONTRACT EXECUTED VENDOR:STATUS:
04/23/2013 12/31/2017 13-023-C1
2,462,322 596,298 533,698
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
SYSTEMS METRICS GROUPCONTRACT EXECUTED VENDOR:STATUS:
08/21/2014 06/30/2017 14-024-C1
485,585 65,801 207,395
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 22 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
020.00161.04 REGULATORY COMPLIANCE
OBJECTIVE: PROJECT MANAGER:
Preparation of RTP/SCS environmental documentation (note, first year of multi-year). Preparation of environmental
compliance documentation for other planning efforts as required.
PING CHANG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Prepare studies and documentation
to facilitate regulatory compliance by
SCAG and member jurisdictions as
necessary.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor for potential changes to
environmental justice requirements.
Work with stakeholders on
environmental justice concerns as
they relate to transportation planning,
as needed.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Environmental documentation and studies related to
regulatory compliance as necessary
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Developed a draft PEIR Addendum for Amendment 1 and 2 to the 2016 RTP/SCS
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 23 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
020.00161.04 REGULATORY COMPLIANCE
BUDGET / EXPENDITURE
423,622
117,540 88,005 0 163,487 0 6,000 0 0 0 0 48,590 0
375,032 0 0 0 0 0 0 0 48,590 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 336,150 91,209 132,574 95,806 16,561
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 24 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
020.00161.05 INTERGOVERNMENTAL REVIEW (IGR)
OBJECTIVE: PROJECT MANAGER:
To provide grant acknowledgements and review environmental documents for regionally significant projects, plans,
and programs for consistency with the goals and policies of the RTP/SCS. To include internal coordination to
integrate performance monitoring in the review of environmental documents.
PING CHANG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Review grants, plans, programs, and
projects subject to Intergovernmental
Review for consistency with
RTP/SCS goals and policies.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare federal grant
acknowledgement letters and
RTP/SCS consistency letters for
projects of regional significance.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare bi-monthly IGR
Clearinghouse reports to facilitate
interagency consultation and public
participation regarding federal grants
and regionally significant projects
that may impact the RTP/SCS.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare annual IGR Clearinghouse
report that summarizes yearly
Clearinghouse activities.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Bi-monthly IGR clearinghouse reports. 06/30/2017 06/30/2017
2 Annual clearinghouse report. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Completed the review and comment of environmental documents (Initial Studies, Mitigated Negative Declarations,
Negative Declarations, and Environmental Impact Reports) submitted to SCAG; Produced weekly, Bi-monthly, and
annual reports for agency and public review
PROGRESS
COMPLETED
Page 25 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
020.00161.05 INTERGOVERNMENTAL REVIEW (IGR)
Issues:
Resolution:
Comment:
Task is ongoing and is included in FY 18 OWP.
BUDGET / EXPENDITURE
194,686
49,755 37,253 8,991 76,356 0 0 0 0 0 0 22,331 0
172,355 0 0 0 0 0 0 0 22,331 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 207,518 68,625 74,816 47,221 16,856
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 26 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
025.00164.01 AIR QUALITY PLANNING AND CONFORMITY
OBJECTIVE: PROJECT MANAGER:
Conduct all SCAG transportation conformity air quality planning, analysis, documentation and policy implementation
to help improve air quality throughout the region and ensure the RTP/SCS, FTIP and any amendments comply with
the Transportation Conformity Rule and conform to applicable federal and state requirements.
Staff will facilitate inter-agency consultation and staff the TCWG including the processing and acting as
clearinghouse for particulate matter (PM) hot spot analyses for transportation projects within the SCAG region. Staff
will update and continue the process to ensure timely implementation of Transportation Control Measures (TCMs),
as needed. Staff will continue to track and report on air quality rule making, policies and issues.
RONGSHENG LUO
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Comply with transportation
conformity regulations. Periodic
conformity findings for RTP / FTIP
updates or amendments. Oversee
Clean Air Act TCM requirements
including ensuring timely
implementation and preparing
conformity updates for periodic TCM
substitutions.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Provide support to the Transportation
Conformity Working Group .
2
100Staff05/31/201710/01/201604/30/201709/01/2016Review and approve the reporting of
CMAQ Improvement Program funded
projects .
3
100Staff06/30/201707/01/201606/30/201707/01/2016Present air quality issues to policy
committees and task forces .
4
100Staff06/30/201707/01/201606/30/201707/01/2016Participate in technical and policy
committees / working groups and
discussions on air quality,
AQMP / SIP development, and
conformity .
5
100Staff06/30/201707/01/201606/30/201707/01/2016Perform air quality analyses as
needed.
6
Page 27 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
025.00164.01 AIR QUALITY PLANNING AND CONFORMITY
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Conformity analyses, reports, and determinations as
necessary for RTP/FTIP and amendments
06/30/2017 06/30/2017
2 TCWG meeting documentation, including maintaining
PM Hot Spot review/determination clearinghouse
06/30/2017 06/30/2017
3 Air quality planning analyses, revisions, and reports as
necessary for AQMP/SIP
06/30/2017 06/30/2017
4 CMAQ reporting documentation 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
1. Held 11 TCWG meetings & processed 34 PM hot spot forms/analyses
2. RC adoption & federal approval of conformity determinations for 2017 FTIP & 2016 RTP/SCS A#1
3. Federal approval of conformity analysis for two 2015 FTIP Amends and five 2017 FTIP Amends
4. Prepared draft conformity analysis for 2016 RTP/SCS A#2
5. SCAQMD adoption of Final 2016 AQMP Appendix IV-C
6. Collaborated with ARB & air districts for new conformity budgets
7. RC adoption and EPA & ARB concurrence of an OCTA TCM substitution; processed on-going TCM delay
requests
8. Provided update to RC/committees on important air quality & conformity issues/topics
9. Prepared input to monthly ED Reports & ARB Update talking points
10. Attended monthly meetings of HRAG, MSRC, MSRC-TAC, & SCAQMD MSC
11. Attended two 2016 AQMP Advisory Group meetings, six 2016 AQMP public workshops, & 6 Facility-based
Measures Working Groups meetings
12. Compiled, analyzed, & uploaded annual CMAQ reports from six CTCs
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 28 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
025.00164.01 AIR QUALITY PLANNING AND CONFORMITY
BUDGET / EXPENDITURE
471,161
121,617 91,058 17,982 183,461 0 3,000 0 0 0 0 54,043 0
417,118 0 0 0 0 0 0 0 54,043 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 409,514 83,884 120,756 90,500 114,374
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 29 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
030.00146.02 FEDERAL TRANSPORTATION IMPROVEMENT PROGRAM
OBJECTIVE: PROJECT MANAGER:
To keep funds flowing in the SCAG Region so that projects may be implemented consistent with SCAG's approved
2016-2040 Regional Transportation Plan/Sustainable Communities Strategy (2016-2040 RTP/SCS).
MARIA LOPEZ
Page 30 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
030.00146.02 FEDERAL TRANSPORTATION IMPROVEMENT PROGRAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff11/01/201607/01/201611/01/201607/01/2016Analyze and approve 2015 FTIP
Amendments and Administrative
Modifications and transmit them to
the state and federal agencies for
approval.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Provide grant administration of the
Federal Transit Administration
Section 5307 Program for the 6
Urbanized Areas where SCAG is the
designated recipient, including MPO
Concurrence of all FTA grants in the
SCAG Region.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct interagency consultation
process as required by State statue
AB1246 and the Federal Metropolitan
Planning Regulations (23 U.S.C (h)
and Federal Transportation
conformity rule (Section 93105 of 40
C.F.R. Part 51 and 93).
3
100Staff09/01/201607/01/201610/02/201607/01/2016Initiate release of Draft 2017 Federal
Transportation Improvement Program
for 30 day public review and obtain
SCAG Board approval.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Assist in the continued coordination
and implementation of the FTIP
Database with the information
technologies staff to improve its
efficiency.
5
100Staff06/30/201707/01/201606/30/201707/01/2016Represent SCAG at monthly
statewide meetings such as
Regional Transportation Planning
Agencies; California Transportation
Commission; and California Federal
Programming Group meetings which
deal with transportation programming
and planning.
6
100Staff06/30/201707/19/201606/30/201710/01/2016Analyze and approve 2017 FTIP
Amendments and Administrative
Modifications and transmit them to
the state and federal agencies for
approval.
7
100Staff06/30/201703/01/201706/30/201703/01/2017Initiate development of the 2019 FTIP
Guidelines.
8
Page 31 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
030.00146.02 FEDERAL TRANSPORTATION IMPROVEMENT PROGRAM
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Final 2017 FTIP comprised of 3 volumes (Executive
Summary, Project Listing and Technical Appendix)
12/30/2016 09/22/2016
2 2015 FTIP Amendments and Administrative Modifications 11/01/2016 11/10/2016
3 2017 FTIP Amendments and Administrative Modifications 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
During the 4th Quarter, SCAG analyzed and approved two Administrative Modifications of the 2017 FTIP.
Additionally, SCAG analyzed, approved, and received Federal approval of 1 Amendment of the 2017 FTIP. SCAG
also received Federal approval of the Consistency Amendment (#17-03) to the 2016 RTP/SCS Amendment #1.
SCAG staff continued analysis of the Consistency Amendment (#17-07) to the 2016 RTP/SCS Amendment #2.
SCAG FTIP staff completed the Draft 2019 FTIP Guidelines. The draft guidelines are currently being reviewed by
stakeholders (county commission staff and state and federal partners) and will be presented to the SCAG Regional
Council for adoption in September (or October) of FY17/18. FTIP staff participated in FTA’s Grant Workshop held on
April 24th and presented to all grantees in attendance on the FTIP process. Additionally, staff issued 10 grant
concurrences for FTA related grants and issued 5307 Quarterly Balance reports for Federal Fiscal Year 17, 2nd
Quarter ending.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
This continuing task is included in the FY17/18 OWP.
Page 32 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
030.00146.02 FEDERAL TRANSPORTATION IMPROVEMENT PROGRAM
BUDGET / EXPENDITURE
2,210,831
618,622 463,179 0 860,447 0 15,000 0 0 0 0 253,583 0
1,957,248 0 0 0 0 0 0 0 253,583 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 1,952,361 518,915 549,142 517,023 367,281
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 33 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.05 ADVANCED TECHNICAL SUPPORT
OBJECTIVE: PROJECT MANAGER:
Provide and obtain advanced technical support to assist staff with application development issues by researching
and purchasing development and Planning software tools, software/hardware upgrades and professional technical
support.
CATHERINE KIRSCHBAUM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Submit the technical support case
and work with the support
representative to resolve the issues
1
100Staff06/30/201707/01/201606/30/201707/01/2016Purchase and subscribe annual
support for the software upgrade and
technical support
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Documentation for the resolutions and logs. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Purchased all products to support Planning technology for this year, including GIS, statistical software, and
transportation modeling software.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 34 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.05 ADVANCED TECHNICAL SUPPORT
BUDGET / EXPENDITURE
290,423
3,147 2,356 0 4,377 0 0 0 0 0 247,231 33,312 0
257,111 0 0 0 0 0 0 0 33,312 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 207,377 187,442 15,097 2,249 2,589
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 35 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.07 FTIP SYSTEM ENHANCEMENT, MAINTENANCE, AND SUPPORT
OBJECTIVE: PROJECT MANAGER:
To maintain and support the FTIP database for the County Transportation Commission (CTC) users and SCAG staff
with a more user-friendly interface and a more efficient environment to manage the FTIP projects. In addition,
continue to provide analyses, troubleshooting, and problem resolution to the users. The target for this new fiscal
year is to add Lumpsum Project module, Maintenance module, and Web Services for data transfer between Metro,
OCTA and SCAG.
CATHERINE KIRSCHBAUM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Collect business requirements from
users.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Prepare the scope of work, detailed
user requirements, and function
specifications.
2
100Consultant06/30/201707/01/201606/30/201707/01/2016Design and develop the applications.3
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct comprehensive testing and
update the user manual and online
help.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Deploy new versions throughout the
year.
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Several new versions of FTIP database program to fulfill
prioritized tasks from users requests.
06/30/2017 06/30/2017
2 Updated user manual and online help files. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Completed the TIP version 7.3 and put into production after user training and acceptance.
Gathered requirements for version 7.4. Features include:
1. Total project cost field status update.
2. Change to fund grid to be locked in all status, as is.
3. Subproject summary table to include short project description/hovering and running sub total
4. Programming (funds) cannot be done/ entered for future years.
5. Add Post Model Field for Signage
6. Only Modeled projects are allowed to have CMP
PROGRESS
COMPLETED
Page 36 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.07 FTIP SYSTEM ENHANCEMENT, MAINTENANCE, AND SUPPORT
7. Limit Map Data to 2015 data in production, pending 2017 update by separate consultant
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
255,933
25,568 19,143 0 35,562 0 2,000 163,000 0 0 0 10,660 0
82,273 144,304 0 0 0 18,696 0 0 10,660 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 94,320 38,296 25,798 14,835 15,391
Consultant 160,218 20,674 44,096 31,324 64,124
CONTRACT STATUS (IF APPLICABLE)
RADGOV, INC.CONTRACT EXECUTED VENDOR:STATUS:
07/27/2016 06/30/2019 16-040B-C8
310,622 310,622
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 37 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.12 ENTERPRISE GIS (EGIS) IMPLEMENTATION
OBJECTIVE: PROJECT MANAGER:
To ensure the implementation of the data warehouse initiated last year is working as expected, and can be easily
accessed by the read-only GIS applications with optimal performance.
CATHERINE KIRSCHBAUM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff04/30/201707/01/201606/30/201707/01/2016Prepare scope of work and initiate
consultant procurement process.
1
100Staff09/30/201607/01/201606/30/201707/01/2016Issue an RFP and interview the
Consultants for the Geodatabase
maintenance and support.
2
100Staff/Consultant10/15/201610/01/201606/30/201707/01/2016Kick-off meeting with the Consultant.3
100Consultant06/30/201710/01/201606/30/201707/01/2016Perform the databases maintenance,
enhancement, and support.
4
100Staff/Consultant04/30/201707/01/201606/30/201707/01/2016Collect business requirements from
users and write up the SOW for the
requests.
5
100Consultant06/30/201710/01/201606/30/201707/01/2016Design and develop the GIS
application(s).
6
100Staff06/30/201710/01/201606/30/201707/01/2016Conduct QA processes for the
developed application(s).
7
100Staff06/30/201710/01/201606/30/201707/01/2016Deploy the developed application(s).8
100Staff06/30/201710/01/201606/30/201707/01/2016Train users and write up user
manuals and online help files.
9
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Applications, components, and tools specified in the
project workscope.
06/30/2017 06/30/2017
2 Test cases, user manual, and training materials. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
App dev: ATDB design to create a view for geodatabase to show required maps of bicycle counts; pending final
database and SQL scripts. Worked with users to create new Enterprise login accounts for ArcGIS Online (AGOL).
PROGRESS
COMPLETED
Page 38 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.12 ENTERPRISE GIS (EGIS) IMPLEMENTATION
Staff training (basic) for AGOL completed. Researched open source SW comparison report for CIO. Coordinated
server setup for v 10.5.1 upgrade. Finalized requirements for next version Green Region Sustainability Indicators
(GRI) map. On the EGIS Implementation side, continued to update 2016 Parcel Data, including comparison to 2012
boundaries, added new fields, developed metadata and replicated data. Coordinated server configuration repair.
Completed server upgrade plan and regular database maintenance, update, repair, and support.
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
433,625
17,088 12,794 0 23,768 0 2,500 370,200 0 0 0 7,275 0
56,150 327,738 0 0 0 42,462 0 0 7,275 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 40,830 13,167 15,144 2,926 9,593
Consultant 303,941 39,646 51,088 30,705 182,502
Page 39 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.12 ENTERPRISE GIS (EGIS) IMPLEMENTATION
CONTRACT STATUS (IF APPLICABLE)
22ND CENTURY TECHNOLOGIES, INC.CONTRACT EXECUTED VENDOR:STATUS:
02/05/2015 08/31/2016 15-018-C1
292,110 215,480 181,215
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ALLIED NETWORK SOLUTIONS, INC.CONTRACT EXECUTED VENDOR:STATUS:
08/06/2013 08/31/2016 14-004-C1
503,000 28,800 171,090
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
IBUSINESS SOLUTIONCONTRACT EXECUTED VENDOR:STATUS:
08/03/2016 06/30/2019 16-040B-C4
133,784 133,784
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
VTECH SOLUTION, INC.CONTRACT EXECUTED VENDOR:STATUS:
08/01/2016 06/30/2019 16-040B-C9
157,680 157,680
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 40 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.17 QA REQUIREMENTS AND DOCUMENTATION
OBJECTIVE: PROJECT MANAGER:
Continue to provide application assurance and quality control for all products developed, maintained, and supported
by the IT Application Development Team. The QA process will ensure to provide quality applications for SCAG users
or regional stakeholders, and help document the test cases, user manuals of software applications that support
Transportation Improvement Programs, GIS Applications, and all applications under Planning System Development
project.
CATHERINE KIRSCHBAUM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Update Business Requirements,
User Manual, and On-line help for
each product release.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Document the testing bugs in the
bug tracker or using Microsoft Team
System.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Create and update testing cases for
all applications required QA process.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Perform QA on each production
release.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Updated technical documents such as business
requirements, user manual, and online help for the
Regional Transportation Improvement Plan (RTIP),
CBDS, OMS, the Customer Relation Management
system (CRM), and other applications managed by
Application Development Team throughout the year for
each product release.
06/30/2017 06/30/2017
2 Testing cases built via Excel or Doc formats or Microsoft
Team System
06/30/2017 06/30/2017
3 Reported testing bugs to the bug tracker or Microsoft
Team System 2008
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Performed comprehensive testing in the last quarter for:Federal Transportation Improvement Program (FTIP): v7.3
and completed bug fixes and documented the UAT cases. Assisted with creating requirements document for FTIP
version 7.4 after gathering details.
PROGRESS
COMPLETED
Page 41 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.17 QA REQUIREMENTS AND DOCUMENTATION
EGIS: Participated in discussion of design of ATDB application, have involved in ERD design meetings.
Planning Systems: Performed QA for various Planning projects.
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
188,868
46,394 34,736 12,000 74,074 0 0 0 0 0 0 21,664 0
167,204 0 0 0 0 0 0 0 21,664 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 170,875 37,695 53,665 33,201 46,314
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 42 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.22 PLANNING SYSTEM DEVELOPMENT
OBJECTIVE: PROJECT MANAGER:
The main objective for this project is to maintain and support planning applications for SCAG staff. This includes but
not limited to Inter-governmental Review (IGR), Regional Outreach (RAO), Compass Blue Print (CBP), and Regional
Transportation Plan (RTP), and Local Profiles (LP).
CATHERINE KIRSCHBAUM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Gather business requirements from
users.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Prepare the scope of work, detailed
business requirements, and
functional specifications.
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Design and develop the applications3
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct comprehensive testing,
update user manuals and online help
files.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct specific user acceptance
test
5
100Staff06/30/201707/01/201606/30/201707/01/2016Deploy new applications on
production servers.
6
100Consultant06/30/201707/01/201606/30/201707/01/2016Conduct user training.7
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Developed web applications on production servers. 06/30/2017 06/30/2017
2 Scope of Work for each release, updated user manuals,
test cases, and training materials.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
1, Prepared research for the CIO for various Business Intelligence options.
2. Updated the Local Profiles system with additional changes and requirements requested by Compliance and
Performance Monitoring; included chart updates for Public Health; deployed the reports for jurisdictional review.
3. Received knowledge transfer for the highly-complex FTIP system and provided small system changes and
prepared to support the system for business contingency purposes.
4. Reviewed IGR requests from users.
PROGRESS
COMPLETED
Page 43 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00142.22 PLANNING SYSTEM DEVELOPMENT
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
286,977
32,240 24,139 0 44,843 0 0 172,640 0 0 0 13,115 0
101,222 152,838 0 0 0 19,802 0 0 13,115 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 45,972 13,153 18,362 6,256 8,201
Consultant 133,138 0 30,936 32,831 69,371
CONTRACT STATUS (IF APPLICABLE)
RADGOV, INC.CONTRACT EXECUTED VENDOR:STATUS:
07/27/2016 06/30/2019 16-040B-C8
310,622 310,622 75,033
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 44 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.01 GIS DEVELOPMENT AND APPLICATIONS
OBJECTIVE: PROJECT MANAGER:
Create mapping and data oriented web applications that allow stakeholders and local jurisdictions to view and update
SCAG's technical databases in accordance with the agency's long term policy priorities. Specific web tools include
those that allow local jurisdictions to view their local data, including socioeconomic data, land use information,
building permits, demolition permits, business establishments and jobs, etc.
KIMBERLY CLARK
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Develop maps for SCAG Projects1
100Staff06/30/201707/01/201606/30/201707/01/2016Maintain and update GIS database2
100Staff06/30/201707/01/201606/30/201707/01/2016Develop and update web-based GIS
applications
3
100Staff06/30/201707/01/201606/30/201707/01/2016Provide GIS training to SCAG staff,
member jurisdictions
4
100Staff06/30/201707/01/201606/30/201707/01/2016Attend GIS seminars and
conferences to learn new GIS
technology
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Maps for SCAG planning projects 06/30/2017 06/30/2017
2 GIS training material, web-based GIS applications with
supporting documents
06/30/2017 06/30/2017
3 Edits to SCAG's region-wide database made by local
jurisdictions through automated web-based applications
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
SCAG's GIS database is undergoing update and staff has created several web maps to encourage economic
development at the local level. SCAG staff hosted four trainings on these apps in partnership with Metro for
jurisdictions in LA County and the greater SCAG region. Staff have also been able to attend GIS seminars and
conferences to learn new GIS technology.
PROGRESS
COMPLETED
Issues:
Page 45 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.01 GIS DEVELOPMENT AND APPLICATIONS
Resolution:
Comment:
BUDGET / EXPENDITURE
357,694
99,268 74,325 0 138,073 0 5,000 0 0 0 0 41,028 0
316,666 0 0 0 0 0 0 0 41,028 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 318,806 113,925 62,205 79,146 63,530
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 46 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.02 ENTERPRISE GIS IMPLEMENTATION
OBJECTIVE: PROJECT MANAGER:
Study MAP_21 performance based planning for GIS database development, build multiple data-sharing platforms of
seamless access and maximum usage of centralized GIS datasets for both SCAG staff and local jurisdictions;
integrated GIS applications with new geodatabase; improve GIS database management, maintenance and
performance; enhance GIS datasets system security.
PING WANG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Identify enhancement areas of SCAG
geodatabase
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Provide geodatabase configuration,
management, and enhancement
supports
2
100Staff06/30/201707/01/201606/30/201707/01/2016Perform GIS geoprocessing spatial
analysis
3
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Provide GIS trainings to internal staff
and local jurisdictions
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Report of Geodatabase improvement recommendation 06/30/2017 06/30/2017
2 Spatial analysis result and report 06/30/2017 06/30/2017
3 Document of geodatabase support 06/30/2017 06/30/2017
4 GIS training material and related documents 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
- completed 2016 Assessor parcel boundary cleanup including eliminating stacked parcel, sliver or overlay parcels
- created SCAG 2016 parcel unique IDs and assigned 2012 LU and city information to 2016 parcel attributes
- completed version 1 of local population projection tool development
- continue the update of SCAG Open Data portal by adding more datasets and fixing bugs
PROGRESS
COMPLETED
Issues:
Page 47 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.02 ENTERPRISE GIS IMPLEMENTATION
Resolution:
Comment:
BUDGET / EXPENDITURE
316,077
66,554 49,831 0 92,571 0 5,000 74,400 0 0 0 27,721 0
213,956 65,866 0 0 0 8,534 0 0 27,721 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 252,187 49,963 91,146 64,671 46,407
Consultant 77,180 0 20,460 54,400 2,320
CONTRACT STATUS (IF APPLICABLE)
IBUSINESS SOLUTIONCONTRACT EXECUTED VENDOR:STATUS:
08/03/2016 06/30/2019 16-040B-C4
133,784 133,784
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 48 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.03 PROFESSIONAL GIS SERVICES PROGRAM SUPPORT
OBJECTIVE: PROJECT MANAGER:
Provide professional GIS support to SCAG member jurisdictions. Specific assistance will be provided to jurisdictions
with few or no GIS resources.
JAVIER AGUILAR
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Evaluate and assess local
jurisdictions' existing GIS system
and requirements
1
100Staff06/30/201707/01/201606/30/201707/01/2016Develop local GIS work plan
including GIS data generation,
update, and integration
2
100Staff06/30/201707/01/201606/30/201707/01/2016Enhance or integrate GIS system
with local jurisdictions' data systems
3
100Staff06/30/201707/01/201606/30/201707/01/2016Provide GIS trainings and GIS spatial
analysis
4
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct one-on-one meetings with
local jurisdictions
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 GIS work plans for local jurisdictions 06/30/2017 06/30/2017
2 GIS data product for cities 06/30/2017 06/30/2017
3 GIS analytical reports 06/30/2017 06/30/2017
4 GIS training and related materials 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
We have GIS rollout out to Irwindale and Hawaiian Gardens. We had trainings in: Imperial, Glendora, Irwindale, La
Quinta, and Downey. In addition, GIS Services have placed GIS interns in Baldwin Park, Colton, Irwindale, La
Puente, Jurupa Valley, Pico Rivera, Santa Paula, and Los Alamitos.
PROGRESS
COMPLETED
Issues:
Page 49 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.03 PROFESSIONAL GIS SERVICES PROGRAM SUPPORT
Resolution:
Comment:
BUDGET / EXPENDITURE
747,087
95,639 71,608 190,000 284,149 0 20,000 0 0 0 0 85,691 0
661,396 0 0 0 0 0 0 0 85,691 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 670,202 180,098 224,428 198,257 67,419
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 50 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.04 GIS PROGRAMMING AND GEOSPATIAL ANALYSIS
OBJECTIVE: PROJECT MANAGER:
Develop and enhance efficient and effective GIS workflow through GIS programming and automation to streamline
regional geospatial data development and update process. Establish innovative analytical methodology to develop
geospatial information and facilitate policy discussion on complex planning issues using spatial and statistical
applications.
JUNG SEO
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Develop and enhance Automated
GIS (AGIS) to automate workflows of
spatial, socioeconomic,
environmental data processing and
mapping, using GIS programming
and statistical analysis applications.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Collect detailed zoning code
information and develop
comprehensive regional zoning
database.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Maintain, update and monitor
regional general plan land use,
specific plan land use and existing
land use datasets.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Update and monitor geospatial
database of SB 375 resource areas
and farmland in the region.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct geospatial analysis of
transit stops and corridors for SB
375 Transit Project Priority (TPP)
analysis, SB743 Transit Priority Area
(TPA) analysis, and other
TOD-related analysis.
5
100Staff06/30/201707/01/201606/30/201707/01/2016Perform geoprocessing, mapping and
geospatial analysis to facilitate
policy discussion, using spatial and
statistical analysis applications.
6
100Staff06/30/201707/01/201606/30/201707/01/2016Attend conferences and trainings to
learn advanced GIS programming
and geospatial technology.
7
Page 51 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.04 GIS PROGRAMMING AND GEOSPATIAL ANALYSIS
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Regional zoning code information database 06/30/2017 06/30/2017
2 Updated regional general plan land use, specific plan
land use, and existing land use datasets
06/30/2017 06/30/2017
3 Updated SB 375 resource areas and farmland datasets 06/30/2017 06/30/2017
4 Documentation, reports, GIS data and maps of GIS
programming, spatial and statistical analysis for various
programs/projects
06/30/2017 06/30/2017
5 Conference presentation materials 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
1. Continued to enhance the automated GIS/Data workflow using GIS programming and Statistical Analysis
Software.
2. Continued to maintain regional land use datasets in preparation for the 2020 RTP/SCS development.
3. Collected the detailed information on zoning codes for local jurisdictions in the SCAG Region.
4. Continued to update and monitor geospatial datasets of SB 375 resource areas and farmland.
5. Conducted geospatial analysis and mapping tasks for High-Quality Transit Areas and SB 743-related studies.
6. Conducted geoprocessing and geospatial analysis and developed maps and web applications for various SCAG’s
policy analysis and projects.
7. Attended conference, workshops and training to present SCAG's achievements in geospatial analysis and to learn
advanced skills and knowledge in geospatial technology.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 52 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
045.00694.04 GIS PROGRAMMING AND GEOSPATIAL ANALYSIS
BUDGET / EXPENDITURE
203,776
25,907 19,397 51,000 76,599 0 7,500 0 0 0 0 23,373 0
180,403 0 0 0 0 0 0 0 23,373 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 120,407 0 0 63,459 56,948
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 53 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
050.00169.01 RTP/SCS ACTIVE TRANSPORTATION DEVELOPMENT & IMPLEMENTATION
OBJECTIVE: PROJECT MANAGER:
Continue collaboration with counties (through sustainability joint work programs) to implement active transportation
initiatives including planning, analysis and pilot projects. The pilot projects support counties in better understanding
and communicating benefits of active transportation projects in order to more strategically invest resources and
attract greater investment, including from statewide sources (ATP/Cap & Trade) and existing discretionary and new
local sources (LA City Street Bond, Metro Measure X). Increased investment in active transportation is critical to
implementing RTP/SCS and demonstrating progress.
ALAN THOMPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Continue to develop Safe Routes to
School Strategies and Data
Development to facilitate
implementation of joint work
programs
1
100Staff06/30/201702/01/201706/30/201701/04/2017Begin development of 2020
RTP/Active Transportation Plan,
including developing 2020 Outlook.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Support Joint Work Program
Development, Coordination and
Collaboration with Counties
3
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct research and analysis and
convene stakeholders to further
explore and advance concepts put
forth in 2016 RTP/SCS, including
short trip strategies, complete
streets as funding strategy, etc...
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 2020 Plan Outlook 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Draft 2020 RTP/Active Transportation Plan outline and schedule completed and in internal review.
PROGRESS
COMPLETED
Page 54 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
050.00169.01 RTP/SCS ACTIVE TRANSPORTATION DEVELOPMENT & IMPLEMENTATION
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
591,700
161,430 120,867 0 224,535 0 17,000 0 0 0 0 67,868 0
523,832 0 0 0 0 0 0 0 67,868 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 526,040 146,681 186,692 122,776 69,891
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 55 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
050.00169.02 ACTIVE TRANSPORTATION SAFETY
OBJECTIVE: PROJECT MANAGER:
Incorporate safety into the Active transportation planning process. Improve integration of SHSP Action Steps into
local safety strategies.
ALAN THOMPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Continue participation on SHSP
Steering Committee
1
100Staff06/30/201707/01/201606/30/201707/01/2016Incorporate Safety into a State of the
Region report
2
100Staff06/30/201707/01/201606/30/201707/01/2016Establish an ad hoc Transportation
Safety Working Group to help
complement State SHSP
activities/actions and to guide the
Safety Report development
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Minutes, meetings and agendas for SHSP Steering
Committee and challenge area meetings
06/30/2017 06/30/2017
2 SCAG Transportation Safety Report 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Developed list of active transportation safety stakeholders for working group.
PROGRESS
COMPLETED
Task 2 will not be in State of Region Report
Issues:
Task 2 will be part of a Transportation Safety Report,
Resolution:
Comment:
Ad Hoc Safety Working Group meetings will be held in conjunction with Technical Working Group meetings and will
be in workshop format beginning in Jul 2017
Page 56 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
050.00169.02 ACTIVE TRANSPORTATION SAFETY
BUDGET / EXPENDITURE
85,069
23,987 17,960 0 33,364 0 0 0 0 0 0 9,758 0
75,311 0 0 0 0 0 0 0 9,758 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 65,474 10,550 21,976 22,397 10,551
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 57 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
050.00169.06 ACTIVE TRANSPORTATION PROGRAM
OBJECTIVE: PROJECT MANAGER:
Facilitate the selection and programming of Active Transportation projects that improve safety, encourage physical
activity, and support and grow the economy.
STEPHEN PATCHAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Facilitate program administration.
Program administration includes
convening of the ATP Subcommittee,
scheduling and facilitating ATP
Subcommittee meetings, producing
meeting minutes, developing meeting
agendas, and managing the
programming of the MPO
component.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Contribute to the review and revision
of the overall program guidelines,
which includes attendance and
hosting of several workshops,
dissemination of information/updates
to stakeholders and review/revision to
the regional programming framework.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Oversee project development
assistance. This includes
administration, technical and design
support for projects that have been
selected for funding as well as
preparation and enhancements for
ATP applications.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Programmed Project List 06/30/2017 06/30/2017
2 Workshops 06/30/2017 06/30/2017
Page 58 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
050.00169.06 ACTIVE TRANSPORTATION PROGRAM
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Approved the 2017 ATP Regional Program.
Assisted California Transportation Commission on implementing the 2017 ATP Augmentation Program.
PROGRESS
COMPLETED
The CTC announced an interim call for projects (2017 ATP Augmentation) due to the addition of SB1 funding to the
program.
Issues:
SCAG will facilitate the 2017 ATP Augmentation Regional Program program and call for projects.
Resolution:
Comment:
SCAG staff will partner with each county staff to monitor implementation of the first three ATP cycles.
SCAG will collaborate with local stakeholders and facilitate discussion and coordinate regional feedback on the
development of Cycle 4 guidelines.
BUDGET / EXPENDITURE
260,451
66,130 49,513 10,000 99,934 0 5,000 0 0 0 0 29,874 0
230,577 0 0 0 0 0 0 0 29,874 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 238,162 61,040 75,630 70,706 30,786
Page 59 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
050.00169.06 ACTIVE TRANSPORTATION PROGRAM
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 60 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.00133.06 UNIVERSITY PARTNERSHIP & COLLABORATION
OBJECTIVE: PROJECT MANAGER:
Conduct advanced research and analyses of the selected priority topic areas with participation of university
researchers and students. Discussions of demographic changes and planning implications, policy responses and
options. Host workshops or seminars to discuss the priority topic areas and policy implications and options as it
relates to the 2020 RTP/SCS.
JOHN CHO
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Host workshops or seminars to
discuss the priority topic areas and
policy implications and options
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Conduct advanced research and
analyses of the selected priority
topic areas with participation of
university researchers and students.
Discussions of planning implications,
policy responses and options.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Workshops or seminar proceedings or reports. 06/30/2017 06/30/2017
2 Research reports on the research on the selected topic
areas
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
A research on measuring longitudinal changes of socio-economic and land use around transit station was
completed.
Released an RFP for Advanced Research on the Built Environment and Collisions
Hosted a workshop for Built Environmental Contributing Factors to the Spatiotemporal Patterns of Pedestrian
Collisions
PROGRESS
COMPLETED
Advanced Research on the Built Environment and Collisions has been delayed and started on July 3. $25K which
was supposed to spend will be used in FY 17-18.
Issues:
$25K which was supposed to be spent for Advanced Research on the Built Environment and Collisions will be used
in FY 17-18.
Resolution:
Page 61 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.00133.06 UNIVERSITY PARTNERSHIP & COLLABORATION
Comment:
BUDGET / EXPENDITURE
182,501
24,685 18,482 0 34,334 5,000 5,000 90,000 0 0 5,000 0 0
0 26,559 0 0 0 155,942 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 70,788 7,809 11,132 11,332 40,515
Consultant 62,884 0 68,091 -5,207 0
CONTRACT STATUS (IF APPLICABLE)
ADVANCED RESEARCH ON THE BUILT ENCONTRACT EXECUTED VENDOR:STATUS:
05/01/2017 09/30/2017 17-037
50,000 25,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
USCCONTRACT COMPLETE VENDOR:STATUS:
05/11/2016 10/31/2016 15-026-C1
49,800 39,800 108,894
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 62 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.00704.02 REGION-WIDE DATA COORDINATION.
OBJECTIVE: PROJECT MANAGER:
Develop, maintain and enhance data and information to support planning and decision making in a timely and
effective manner. To provide quality data analysis, reports, and information to support decision makers and promote
economic development.
JOHN CHO
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Collect data and information to
support SCAG planning activities.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Perform data analyses to support the
planning mandates and activities of
the agency.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Maintain SCAG's Census Data
Center. Coordinate activities
including training with staff from the
Census Regional Office.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Provide SCAG data and information
to both internal and external users.
Keep a log of all requests.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Serve on the Enterprise GIS Steering
Committee to integrate data with
GIS.
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Copy of building permit database 06/30/2017 06/30/2017
2 Copy of street centerline file 06/30/2017 06/30/2017
3 Report of data/information/GIS requests handled by staff 06/30/2017 06/30/2017
4 Copy of InfoUSA 2014 data 06/30/2017 06/30/2017
5 Copy of Goods movement related data 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Purchased Local Profile Data: Home Sales, Foreclosure
Purchased Plugshare data license
Subscribed Rand data
PROGRESS
COMPLETED
Page 63 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.00704.02 REGION-WIDE DATA COORDINATION.
Subscribed Social Explorer
Supported for Household travel survey
purchased 2017 CIRB Subscription
Purchased Real Estate Software License
Renewed RERC Southern California Subscription
Renewed Urban Transportation Monitor subscription
Paid for CDR Subscription
Responded to data requests
Coordinated to host LUCA workshop
Produced 2017 SCAG Regional Pocket Guide
Purchased 2016 vehicle sales data
Issues:
Resolution:
Comment:
Task will continue into next year and included in FY 18 OWP.
BUDGET / EXPENDITURE
1,189,317
97,941 73,331 42,000 169,633 0 10,000 0 0 0 660,000 136,412 0
0 1,052,905 0 0 0 0 0 0 136,412 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 760,502 231,447 212,315 177,866 138,874
Page 64 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.00704.02 REGION-WIDE DATA COORDINATION.
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 65 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.01 SOUTHERN CALIFORNIA ECONOMIC GROWTH STRATEGY
OBJECTIVE: PROJECT MANAGER:
Through the agency’s analyses, SCAG has produced information quantifying the economic benefits of reducing
congestion. The objective of the Southern California Economic Growth Strategy is to continue this analysis to
provide information to support regional decision making and long-range transportation and land use planning, as well
as a common set of short and long-term priorities and recommendations for the region to help businesses, public
agencies, and communities improve their economic viability.
HOUSTON LANEY
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
75Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop a short-term (less than 5
years) and long-term (more than 5
years) action plan for successful
RTP strategies to reduce congestion
and ensure livability and economic
viability.
1
75Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Conduct outreach to affected
stakeholders in support of step 1.
2
75Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Identify opportunities for and build
partnerships to expedite delivery and
implementation of adopted
RTP/SCS.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Economic analysis of identified opportunities expedited
delivery and implementation of adopted RTP/SCS, as
well as short- and long-term priorities and
recommendations for the region to help businesses,
public agencies, and communities improve their
economic viability.
06/30/2017
PERCENTAGE COMPLETED: 75 STATUS:
Accomplishments:
Economic consultants completed the first county-specific economic reports after the adoption of the 2016-2040
RTP/SCS, which were featured at the Seventh Annual Southern California Economic Summit held in December
2016. In addition, one of the consultants completed four pilot studies evaluating the financial viability of establishing
an EIFD or CRIA in areas served by regionally significant transportation projects. Consultant developed outreach and
presentation materials for engaging with stakeholders to present results of this effort. Consultant provided technical
assistance at four workshops – three in L.A. County to support Metro’s pilot Tax Increment Financing grant program
PROGRESS
IN PROGRESS
Page 66 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.01 SOUTHERN CALIFORNIA ECONOMIC GROWTH STRATEGY
for local jurisdictions, and one for the greater SCAG region on the basics of tax increment financing.
Delay in progress due to economic analysis work that is needed for upcoming Southern California Economic
Summit in November 2017.
Issues:
Provide economic analysis work for the upcoming Southern California Economic Summit in November 2017. Task
has been carried over into FY 18.
Resolution:
Comment:
Task included in FY 17-18 OWP.
BUDGET / EXPENDITURE
179,178
23,609 17,677 0 32,838 0 0 105,054 0 0 0 0 0
0 0 0 0 0 179,178 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 15,647 13,033 2,648 -23 -11
Consultant 75,539 0 39,112 28,137 8,290
Page 67 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.01 SOUTHERN CALIFORNIA ECONOMIC GROWTH STRATEGY
CONTRACT STATUS (IF APPLICABLE)
CALIFORNIA LUTHERAN UNIVERSITYCONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C7
62,863 7,500 14,150
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
CALIFORNIA LUTHERAN UNIVERSITYCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C2
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
CENTER FOR CONTINUING STUDY OF THE CONTRACT COMPLETE VENDOR:STATUS:
10/03/2012 12/30/2016 12-043-C6
149,734 7,000 100,873
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
DEVELOPMENT MANAGEMENT GROUP, INCONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C9
66,547 7,500 8,948
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
DEVELOPMENT MANAGEMENT GROUP, INCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C3
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ECONOMICS & POLITICS, INC.CONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C1
128,995 10,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ESTOLANO LESAR PEREZ AADVISORSCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C5
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
GREEN TECH COASTCONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C4
294,492 2,500
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 68 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.01 SOUTHERN CALIFORNIA ECONOMIC GROWTH STRATEGY
GREEN TECH COASTCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C6
10,000 10,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
IMPRENTA COMMUNICATIONS GROUPCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C7
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
KOSMONT & ASSOCIATES, INC.CONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C11
72,449 11,250 29,946
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
LOS ANGELES COUNTY ECONOMIC DEVECONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C3
176,550 10,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ORANGE COUNTY BUSINESS COUNCILCONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C2
348,600 17,500 42,775
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
RAND CORPORATIONCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C11
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 69 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.02 ECONOMIC ANALYSIS OF TRANSPORTATION PLANNING ACTIVITIES &
INVESTMENTS
OBJECTIVE: PROJECT MANAGER:
Through various analyses, SCAG has produced information quantifying the economic benefits of the agency’s
transportation planning efforts and investments into the region’s transportation infrastructure. The objective will be to
continue this economic analysis in a number of areas including, but not limited to, regional transportation plans,
regional economic outlooks, county economic reports, and SCAG’s various planning program areas.
HOUSTON LANEY
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
75Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Continue to assess and articulate
economic and job creation benefits
associated with the adopted
RTP/SCS.
1
75Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Quantify economic benefits of
transportation investments through
case studies, reports and/or fact
sheets
2
75Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop and refine framework for the
RTP/SCS Economic and Job
Creation Analysis.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Case studies, reports and fact sheets quantifying
economic benefits of transportation investments through
case studies, reports, and/or fact sheets.
06/30/2017
2 Framework for development of RTP/SCS Economic and
Job Creation Analysis.
06/30/2017
PERCENTAGE COMPLETED: 75 STATUS:
Accomplishments:
To support SCAG’s planning activities, an economic analysis of the 2017 FTIP was conducted. This product built off
of work conducted for the economic analysis of the 2016-2040 RTP/SCS. In addition, economic consultants
completed the first county-specific economic reports after the adoption of the 2016-2040 RTP/SCS, which were
featured at the Seventh Annual Southern California Economic Summit held in December 2016.
PROGRESS
IN PROGRESS
With the adoption of the 2016-2040 Regional Transportation Plan/Sustainable Communities Strategy (RTP/SCS),
extra work is needed to develop fact sheets and other communicative pieces to support the RTP/SCS. In addition,
Issues:
Page 70 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.02 ECONOMIC ANALYSIS OF TRANSPORTATION PLANNING ACTIVITIES &
INVESTMENTS
work will be required to support the development of the 2020 RTP/SCS Economic and Job Creation Analysis.
Develop fact sheets and other communicative pieces to support the 2016-2040 Regional Transportation
Plan/Sustainable Communities Strategy (RTP/SCS). Start process to develop framework for the 2020 RTP/SCS
Economic and Job Creation Analysis.
Resolution:
Comment:
Carryover to FY 17-18. Included in FY 17-18 OWP.
BUDGET / EXPENDITURE
333,728
23,609 17,677 0 32,838 0 0 250,000 0 0 0 9,604 0
74,124 221,325 0 0 0 28,675 0 0 9,604 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 18,372 15,748 2,664 -27 -13
Consultant 75,638 0 35,098 23,475 17,065
Page 71 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.02 ECONOMIC ANALYSIS OF TRANSPORTATION PLANNING ACTIVITIES &
INVESTMENTS
CONTRACT STATUS (IF APPLICABLE)
AECOMCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C1
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
CALIFORNIA LUTHERAN UNIVERSITYCONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C7
62,863 7,500 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
CALIFORNIA LUTHERAN UNIVERSITYCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C2
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
CENTER FOR CONTINUING STUDY OF THE CONTRACT COMPLETE VENDOR:STATUS:
10/03/2012 12/30/2016 12-043-C6
149,734 7,000 142,139
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
DEVELOPMENT MANAGEMENT GROUP, INCONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C9
66,547 7,500 8,948
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
DEVELOPMENT MANAGEMENT GROUP, INCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C3
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ECONOMICS & POLITICS, INC.CONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C1
128,995 10,000 20,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ECONOMICS & POLITICS, INC.CONTRACT EXECUTED VENDOR:STATUS:
Page 72 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.02 ECONOMIC ANALYSIS OF TRANSPORTATION PLANNING ACTIVITIES &
INVESTMENTS
01/02/2017 06/30/2017 17-002-C4
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ESTOLANO LESAR PEREZ ADVISORSCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C5
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
GREEN TECH COASTCONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C4
294,492 2,500
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
GREEN TECH COASTCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C6
10,000 10,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
IMPRENTA COMMUNICATIONS GROUPCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C7
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
KOSMONT & ASSOCIATES, INC.CONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C11
72,449 11,250 24,946
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
KOSMONT COMPANIESCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C8
7,500 7,500 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
LOS ANGELES COUNTY ECONOMIC DEVECONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C3
176,550 10,000 5,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
LOS ANGELES COUNTY ECONOMIC DEVECONTRACT EXECUTED VENDOR:STATUS:
Page 73 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
055.01531.02 ECONOMIC ANALYSIS OF TRANSPORTATION PLANNING ACTIVITIES &
INVESTMENTS
01/02/2017 06/30/2017 17-002-C9
7,500 7,500 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ORANGE COUNTY BUSINESS COUNCILCONTRACT COMPLETE VENDOR:STATUS:
09/20/2012 12/31/2016 12-043-C2
348,600 17,500 53,075
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ORANGE COUNTY BUSINESS COUNCILCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C10
20,000 20,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
RAND CORPORATIONCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C11
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
THE SIERRA GROUPCONTRACT EXECUTED VENDOR:STATUS:
01/02/2017 06/30/2017 17-002-C12
5,000 5,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 74 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
060.00124.01 CORRIDOR PLANNING
OBJECTIVE: PROJECT MANAGER:
Work completed via this task will provide input to the RTP/SCS on the locally-preferred strategies of major
transportation investments, as identified upon the completion of multimodal corridor planning studies conducted
under this work element and in partnership with other agencies.
DANIEL TRAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Participate in corridor study efforts
led by other regional planning partner
agencies including Caltrans, county
transportation commissions, and
subregions.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Provide input into the next RTP/SCS
update regarding changes to
regionally significant transportation
investments, based upon completion
and approval of corridor planning
studies.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Quarterly progress reports, summary reports, etc. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
During the 4th quarter, Staff continued to attend on-going meetings with its regional partner planning agencies
providing input regarding various corridor projects. More specifically, staff attended monthly meetings involving the
SR-710 North Study and the I-210 Connected Corridors Pilot project providing input and support as needed.
PROGRESS
COMPLETED
Issues:
Resolution:
Page 75 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
060.00124.01 CORRIDOR PLANNING
Comment:
BUDGET / EXPENDITURE
120,220
33,899 25,381 0 47,150 0 0 0 0 0 0 13,790 0
106,430 0 0 0 0 0 0 0 13,790 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 76,262 25,881 18,663 19,093 12,625
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 76 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.01 SUSTAINABILITY PROGRAM CALL FOR PROJECTS
OBJECTIVE: PROJECT MANAGER:
Primary objective is collaborative assistance to member local governments and communities for coordinating
sustainable transportation, land use and regional policies and issues in local planning. The task will implement the
SCAG Sustainability Planning Grant program to support and implement the policies of the 2016 RTP/SCS. Built on
the Compass Blueprint program's past success of providing an array of tools and resources to local governments to
develop policies, plans, and development projects that implement the 2012 Regional Transportation Plan and
Sustainable Communities Strategy (RTP/SCS). Work will also be consistent with Caltrans' Smart Mobility
Framework and Complete Streets program (Deputy Directive 64-R1) and FHWA Planning Emphasis Areas (PEAs.)
Emphases will include local and regional planning for greenhouse gas reductions, locally-applied "Green Region
Initiative" strategies, public health impacts related to transportation activities and assistance in General Plan updates.
Local-regional partnerships that integrate land use planning and transportation investment decision-making are
critical to improving mobility, accessibility and air-quality in Southern California. Sustainability Planning Grant projects
focused on key opportunity sites as identified in the RTP/SCS, will provide assistance to local jurisdictions for
comprehensive planning solutions such as context-sensitive design, multi-modal transportation planning, infill and
transit-oriented development projects community outreach and consensus building, fiscal and economic impact
analysis, green house gas (GHG) reduction standards, innovative financing and public private partnerships.
MARCO ANDERSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct outreach and develop
partnerships for Sustainability
Planning Grant projects and other
technical assistance.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Complete local Sustainability
Planning Grant projects that
showcase the local and regional
benefits of sustainable planning and
support the 2012 RTP/SCS and other
regional policies.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Manage and coordinate consultant
work including preparation of scope
of work, monitoring project budget
and schedule.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Updated program website(s), presentations and other
documentation of outreach activities
06/30/2017 06/30/2017
2 Project materials for Sustainability Planning Grant
projects.
06/30/2017 06/30/2017
Page 77 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.01 SUSTAINABILITY PROGRAM CALL FOR PROJECTS
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
On September 12, 2013, the Regional Council approved seventy-five (75) Sustainability Planning Grant projects and
directed staff to proceed with funding projects. October 2, 2014 the Regional Council approved funding for the
remaining projects on the list. Subsequently, six (6) projects removed themselves from the program.
As of 3/27/17 sixty-five (65) grant projects have been completed, three (3) grant projects are scheduled to be
completed by the end of FY 2016-2017, and one project, funded by SGC grant is scheduled to be completed by Dec.
31, 2017.
As of 6/30/17 sixty-eight (68) grant projects have been completed, and one project, funded by an SGC grant, is
scheduled to be completed by March 31, 2018. This task has been carried over and included in FY 18 OWP
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
1,633,810
3,998 2,993 0 5,561 0 0 1,619,631 0 0 0 1,627 0
12,552 0 0 0 0 1,018,030 601,601 0 1,627 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
Page 78 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.01 SUSTAINABILITY PROGRAM CALL FOR PROJECTS
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 78,947 34,603 19,392 17,087 7,865
Consultant 1,031,756 45,624 443,534 171,557 371,041
Page 79 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.01 SUSTAINABILITY PROGRAM CALL FOR PROJECTS
CONTRACT STATUS (IF APPLICABLE)
AECOM TECHNICAL SERVICES, INC.CONTRACT COMPLETE VENDOR:STATUS:
09/21/2015 10/31/2016 15-001-B56A
199,964 103,036
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ALTA PLANNING + DESIGNCONTRACT COMPLETE VENDOR:STATUS:
07/08/2015 12/30/2016 15-001-B72
198,355 33,701 164,654
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
DYETT & BHATIACONTRACT COMPLETE VENDOR:STATUS:
07/01/2014 09/30/2016 14-001-B39
97,606 5,087 25,365
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
DYETT & BHATIACONTRACT COMPLETE VENDOR:STATUS:
07/01/2014 12/30/2016 14-001-B35
198,956 73,734 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ELP ADVISORS, LLCCONTRACT COMPLETE VENDOR:STATUS:
08/31/2015 09/30/2016 15-001-B63A
199,500 61,267 138,233
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ELP ADVISORS, LLCCONTRACT COMPLETE VENDOR:STATUS:
08/31/2015 12/31/2016 15-001-B45
198,992 66,519
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ENVIRONMENTAL SCIENCE ASSOCIATES CONTRACT COMPLETE VENDOR:STATUS:
01/21/2015 12/30/2016 15-001-B49
149,999 69,964
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
FREEDMAN, TUNG AND SASAKICONTRACT COMPLETE VENDOR:STATUS:
01/22/2015 06/30/2017 15-001-B75
200,000 68,575
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 80 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.01 SUSTAINABILITY PROGRAM CALL FOR PROJECTS
GENSLERCONTRACT COMPLETE VENDOR:STATUS:
10/12/2015 12/31/2016 15-001-B68
82,887 29,284
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
IBI GROUPCONTRACT COMPLETE VENDOR:STATUS:
07/15/2014 10/31/2016 14-001-B18
122,784 14,608 2,850,703
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ICF JONES & STOKESCONTRACT COMPLETE VENDOR:STATUS:
07/09/2015 12/31/2016 15-001-B48
148,952 14,457
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ITERIS, INC.CONTRACT COMPLETE VENDOR:STATUS:
04/15/2014 12/31/2016 14-001-B23
199,001 53,926
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
KTU&A, INC.CONTRACT COMPLETE VENDOR:STATUS:
11/14/2014 12/30/2016 14-001-B36
81,542 25,467
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
MOORE IACOFANO GOLTSMAN (MIG)CONTRACT COMPLETE VENDOR:STATUS:
07/01/2015 10/31/2016 15-001-B73
173,500 23,500
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
RAIMI ASSOCIATESCONTRACT COMPLETE VENDOR:STATUS:
06/17/2015 12/31/2016 15-001-B65
49,482 22,712
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
RAIMI ASSOCIATESCONTRACT COMPLETE VENDOR:STATUS:
07/16/2015 03/31/2017 15-001-B54
149,315 83,776 65,540
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
RANGWALA ASSOCIATESCONTRACT COMPLETE VENDOR:STATUS:
Page 81 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.01 SUSTAINABILITY PROGRAM CALL FOR PROJECTS
09/08/2015 11/30/2016 15-001-B47a
155,677 74,333
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
SARGENT TOWN PLANNINGCONTRACT EXECUTED VENDOR:STATUS:
09/30/2015 12/31/2017 15-001-B52
199,148 128,047 71,101
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 82 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.07 LOCAL TECHNICAL ASSISTANCE AND TOOLBOX TUESDAYS
OBJECTIVE: PROJECT MANAGER:
Provide Local Technical Assistance and the Toolbox Tuesdays Training Series to build local capacity in innovative
and integrated transportation and planning tools. The Toolbox Tuesdays serve as important opportunities for
inter-governmental communication. By bringing together planners from diverse areas of the region the sessions
provide opportunities for jurisdictions to learn from each other about successes and failures in new approaches to
transportation and planning. In a region as vast as SCAG, forums where staff from dense urban communities can
share their concerns and successes with planners from less populated areas are highly valued. Toolbox Tuesdays
sessions equip local government planners to think beyond their traditional roles, and respond to new mandates (e.g.
2012 RTP/SCS, Caltrans' Smart Mobility Framework and Complete Streets program) that require collaboration and
public participation.
INDIA BROOKOVER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant09/30/201607/01/201606/30/201707/01/2016Develop Toolbox Tuesdays program
and session topics, and recruit
speakers.
1
100Staff08/30/201607/01/201606/30/201707/01/2016Prepare Toolbox Tuesdays sessions,
promote attendance, and manage
session logistics.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Toolbox Tuesdays training agendas, and presentation
materials.
06/30/2017 06/30/2017
2 Toolbox Tuesdays registration rosters, and
announcements
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Toolbox Tuesday events held on April 18th, May 16th, and June 27th. Topics were Health Data for Planners,
GreenTrip Certification, and EIFD/CRIA training. Began plan for FY 17-18 schedule of events
PROGRESS
COMPLETED
Issues:
Resolution:
Page 83 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.07 LOCAL TECHNICAL ASSISTANCE AND TOOLBOX TUESDAYS
Comment:
BUDGET / EXPENDITURE
80,098
20,993 15,718 0 29,199 0 0 0 0 0 5,000 9,188 0
70,910 0 0 0 0 0 0 0 9,188 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 65,451 14,517 12,277 17,747 20,910
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 84 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.08 SUSTAINABILITY RECOGNITION AWARDS
OBJECTIVE: PROJECT MANAGER:
Plan and complete an Awards Program for outstanding examples of integrated transportation and land use planning,
implementing the 2012 RTP/SCS at the local level. The Awards Program is meant to inspire the rest of the region to
pursue innovative mobility, sustainability, livability and prosperity solutions locally. In addition they allow diverse types
of communities to learn from each other, and to realize that there is a variety of transportation and land use planning
approaches to fit agencies of all sizes and level of complexity. Recognized projects also serve as local
embodiments of Caltrans' Smart Mobility Framework and Complete Streets Program (Deputy Directive 64-R1) and
FHWA Planning Emphasis Areas (PEAs.)
INDIA BROOKOVER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201712/01/201606/30/201707/01/2016Prepare Sustainability Recognition
Awards nomination packet
1
100Staff06/30/201712/01/201606/30/201707/01/2016Hold Jury Day that gathers planning
professionals to assist in determining
winners of the Sustainability
Recognition Awards.
2
100Staff06/30/201712/01/201606/30/201707/01/2016Prepare videos and program
materials for Recognition Awards
Reception
3
100Staff06/30/201712/01/201606/30/201707/01/2016Hold Recognition Awards Reception4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Program materials; summaries of winning projects 06/30/2017 06/30/2017
2 Videos for high-level winners 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Filmed and edited award videos
wrote and edited material for program book
managed registration and hotel for awardees and guests
designed and ordered trophies
wrote script for award show
managed student poster exhibition
arranged blocking/rehearsal for awards show
PROGRESS
COMPLETED
Page 85 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.08 SUSTAINABILITY RECOGNITION AWARDS
Awards ceremony took place on May 4th
Issues:
Awards ceremony took place on May 4th
Resolution:
Comment:
BUDGET / EXPENDITURE
142,456
36,984 27,691 0 51,441 0 0 0 0 0 10,000 16,340 0
126,116 0 0 0 0 0 0 0 16,340 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 80,367 0 6,601 36,770 36,996
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 86 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.09 CEO SUSTAINABILITY WORKING GROUP
OBJECTIVE: PROJECT MANAGER:
Policy coordination among SCAG and CTCs for various sustainability issues related to implementation of the
RTP/SCS and CTC Joint Work Programs, such as First mile/Last mile, complete streets, climate action plans,
adaptation, and active transportation.
GRIEG ASHER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate meetings, conference
calls, and/or workshops, including
meeting preparation, meeting
reporting, and staff/outside
presentations
1
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct project management and
management of studies, work
products, other assistance/support,
and progress reporting to
management and SCAG Regional
Council.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Meeting/workshop records; periodic reports to
management or Regional Council; year-end reporting;
joint work programs with CTCs
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
The group has completed 4 scheduled meetings and discussed planning issues of high importance to SCAG and
the 6 County Transportation Commissions (CTCs). No joint studies were conducted this FY.
PROGRESS
COMPLETED
July, October, December & April mtgs held.
Issues:
July, October, December & April mtgs held.
Resolution:
Page 87 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.09 CEO SUSTAINABILITY WORKING GROUP
Comment:
BUDGET / EXPENDITURE
108,942
30,719 23,000 0 42,727 0 0 0 0 0 0 12,496 0
96,446 0 0 0 0 0 0 0 12,496 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 121,006 0 42,524 34,363 44,119
CONTRACT STATUS (IF APPLICABLE)
GRUEN ASSOCIATESCONTRACT EXECUTED VENDOR:STATUS:
06/14/2017 06/30/2018 17-024-C1
261,898 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 88 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.10 CIVIC SPARKS PROGRAM
OBJECTIVE: PROJECT MANAGER:
The Civic Sparks program was established and is overseen by the California Office of Planning and Research
(OPR), and is administered by the Local Government Commission. SCAG will serve as the Regional Coordinator for
this statewide planning program to identify plan policies and strategies to support the region’s transportation priorities
and infrastructure.
GRIEG ASHER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Provide technical support to further
the 2016 RTP/SCS policies in the
region
1
100Staff06/30/201707/01/201606/30/201707/01/2016Develop foundation for growth
scenarios for the 2020 RTP/SCS
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Facilitate integration of land use,
transportation, community goals and
housing by assisting jurisdictions
and providing technical support for
programs such as Affordable
Housing and Sustainable
Communities (AHSC) administered
by the California Strategic Growth
Council.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Analyze and assess transportation
impacts and sustainability efforts on
regional community livability
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Final report from program fellows 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Completed webmap to reflect Sustainability Indicators project updates. Reports for individual indicators complete,
draft factsheets complete to support 2016 RTP/SCS. Participated in Climate Adaptation Forum and presented
findings to EEC and at All Staff meeting.
PROGRESS
COMPLETED
Issues:
Page 89 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.10 CIVIC SPARKS PROGRAM
Resolution:
Comment:
Sponsorship agreement with local government commission to implement the Civic Sparks program in the LA region,
effective 10-10-16 to 9-30-17. Sponsoring three staff.
BUDGET / EXPENDITURE
210,610
37,442 28,034 0 52,079 0 2,500 75,000 0 0 0 15,555 0
120,055 0 0 0 0 75,000 0 0 15,555 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 72,889 0 0 17,184 55,705
Consultant 15,000 0 0 15,000 0
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 90 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.11 SUSTAINABILITY INTERNS
OBJECTIVE: PROJECT MANAGER:
Support Sustainability Department personnel and work program.
Interns will be paid and are procured through a competitive process from local universities.
JASON GREENSPAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201709/01/201606/30/201707/01/2016Assist staff to identify and analyze
issues relating to integrating regional
transportation and community goals
and objectives as they relate to the
2016 RTP/SCS, particularly in land
use, housing, and environmental
preservation.
1
100Staff06/30/201709/01/201606/30/201707/01/2016Develop reports and techniques that
allow for better assessment of
regional transportation impacts on
community livability, with a potential
focus on High Quality Transit Areas.
2
100Staff06/30/201709/01/201606/30/201707/01/2016Identify and document transportation
facilities, projects and services
particularly related to clean
transportation technology, new
mobility innovations, and to support
regional accessibility.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Report from intern on work completed 06/30/2015 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Interns recruited and commenced work to support Sustainability Department staff and associated workplan.
PROGRESS
COMPLETED
Issues:
Page 91 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.00137.11 SUSTAINABILITY INTERNS
Resolution:
Comment:
BUDGET / EXPENDITURE
121,362
11,347 8,496 40,000 47,598 0 0 0 0 0 0 13,921 0
107,441 0 0 0 0 0 0 0 13,921 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 15,117 0 0 10,785 4,332
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 92 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.02663.03 2050 GHG PATHWAYS REGIONAL STUDY
OBJECTIVE: PROJECT MANAGER:
The California Air Resources Board (CARB) has developed a new statewide analysis model (Pathways) for
evaluating various greenhouse gas (GHG) reduction strategies for achieving the Governor’s Executive Orders to
reduce 80% of statewide GHG by 2050. SCAG will refine the Pathway model analysis to develop specific and
regional based solutions, strategies and potential paths to State's 2050 GHG goals and other critical interim targets
prior to preparation of the 2020 RTP/SCS. Based on the methodology and framework of CARB’s 2050 Pathways
statewide model, SCAG will develop regional inputs that will lead to regional outputs for use in the 2020 RTP/SCS,
specifically to help ensure transportation investments and land use strategies help the SCAG region achieve a
shared vision to reach 2050 GHG goals and other critical interim targets. In addition to developing consensus for
SCAG’s 2020 plan, this effort will help support ARB’s Scoping Plan and Caltrans 2040 Plan and associated GHG
reduction goals.
GRIEG ASHER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Establish working group1
15Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Identify applicable goals and targets
to clarify pathway (e.g. 80% GHG
reduction by 2050; 1.5 million ZEVs
deployed by 2025; 50% petroleum
reduction/50% of electricity from
renewable sources/double energy
efficiency savings in existing
buildings by 2030)
2
15Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Manage consultant3
15Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop 2050 GHG Pathways
Regional Study
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Outreach records including meeting agendas and
materials
06/30/2017 06/30/2017
2 Progress Report 02/28/2017 06/30/2017
3 Final 2050 GHG Pathways Regional Study and
implementation recommendations
06/30/2017 06/30/2017
Page 93 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.02663.03 2050 GHG PATHWAYS REGIONAL STUDY
PERCENTAGE COMPLETED: 32 STATUS:
Accomplishments:
PROGRESS
IN PROGRESS
Had to wait for Amendment 2 approval late 2016. RFP processed for release in late Jan 2017. RFP pulled and Sole
Source Contract negotiated. Work began in May 2017. Already included in FY 18 and will be completed in FY 18.
Issues:
RFP prepared for release.
Sole Source contract under negotiated.
Work underway starting May 2017.
Already included in FY 18 and will be completed in FY 18.
Resolution:
Comment:
BUDGET / EXPENDITURE
451,142
45,438 34,021 0 63,200 0 0 290,000 0 0 0 18,483 0
142,659 221,326 0 0 0 68,674 0 0 18,483 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 29,730 0 0 0 29,730
Staff 142,338 72,819 69,830 -207 -104
Page 94 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.02663.03 2050 GHG PATHWAYS REGIONAL STUDY
CONTRACT STATUS (IF APPLICABLE)
ENERGY AND ENVIRONMENTAL ECONOMCONTRACT EXECUTED VENDOR:STATUS:
05/05/2017 06/30/2018 17-028-SS1
198,034 150,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 95 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.04092.01 ADAPTATION ANALYSIS
OBJECTIVE: PROJECT MANAGER:
Develop climate adaptation framework for SCAG region stakeholders, in coordination with state legislation and state
guidelines; and ongoing regional studies including potential partners including NOAA
GRIEG ASHER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
25Staff/Consultant01/01/201707/01/201606/30/201707/01/2016Work with agencies and member
cities
1
25Staff/Consultant01/01/201707/01/201606/30/201707/01/2016Coordination with stakeholders and
consultant
2
25Staff/Consultant01/01/201707/01/201606/30/201707/01/2016Establish climate adaptation working
group
3
25Staff/Consultant01/01/201707/01/201606/30/201707/01/2016Identify opportunities per 2016
RTP/SCS
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Conference materials 06/30/2017 01/01/2017
2 Outreach records (agendas and materials) 06/30/2017 01/01/2017
3 Status report on implementation of adaptation framework 06/30/2017 01/01/2017
PERCENTAGE COMPLETED: 25 STATUS:
Accomplishments:
PROGRESS
DELAYED
Had to wait for Amendment 2 approval late 2016. RFP being processed for release in late Jan 2017.
This project has been put on Hold until Dec.2017.
Already included in FY 18 and will be completed in FY 18.
Issues:
RFP is being prepared for release.
The only work done was to prepare the SOW and RFP for release. Release was postponed until Dec.2017
Already included in FY 18 and will be completed in FY 18.
Resolution:
Page 96 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
065.04092.01 ADAPTATION ANALYSIS
Comment:
BUDGET / EXPENDITURE
308,464
43,090 32,263 0 59,935 0 5,000 150,000 0 0 0 18,176 0
140,288 132,795 0 0 0 17,205 0 0 18,176 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 123,448 37,249 14,677 16,686 54,836
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 97 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00130.10 MODEL ENHANCEMENT AND MAINTENANCE
OBJECTIVE: PROJECT MANAGER:
To ensure SCAG’s models are up-to-date by continuously updating model inputs and parameters. To improve model
procedures and incorporate new modeling methodologies to further enhance SCAG's modeling capabilities. These
activities may include enhancements and updates to the following SCAG models: Trip-Based Model; Activity-Based
Model; sub-regional models; goods movement and warehousing models; pricing models; seaports and airports
related trips; visitors and inter-regional travel models; air quality models; Scenario Planning Model; and growth
forecasting models.
HSI-HWA HU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct project management
including: manage consultant
contracts; review consultant
products; monitor progress; and
conduct progress meetings.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Perform model maintenance by
updating model parameters and
model inputs to reflect current and
future conditions. Perform model
applications, conduct model
sensitivity testing, and incorporate
new modeling methodologies to
further enhance SCAG's Models.
2
85Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Provide transportation, air quality,
growth forecasting, and scenario plan
modeling and technical support.
Tasks may include providing the
following services: 1) Transportation
model support and development; 2)
Land use and socio-economic
data/model support and
development; 3) Air quality model
support and development, 4)
Scenario Planning Model support
and enhancement, and 5) Research,
data gathering/analysis, and
advanced statistical services.
3
80Consultant06/30/201711/01/201606/30/201707/01/2016Provide computer
software/programming services,
model documentation, and training
for SCAG's models.
4
Page 98 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00130.10 MODEL ENHANCEMENT AND MAINTENANCE
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Updated transportation, air quality, growth forecasting,
and scenario planning models and inputs.
06/30/2017 06/30/2017
2 Model documentation, conduct workshops, and provide
training.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 90 STATUS:
Accomplishments:
1) 2016 Regional Screenline Count
- Conducted traffic counts on 400 local streets (80%)
- Completed 5 freeway traffic counts (16%)
2) 2016 Model Update and Validation
- Completed the long-term choice, mobility choice, and CDAP models: Consultant completed model development
and test;SCAG staff completed 1) model validation targets, 2) household expansion, 3) model output analysis.
3) Imperial County Model:
- Completed and delivered a work plan.
- Collected traffic count data.
- Delivered model prototype
- Update TAZ and network
4) Scenario Planning Model
- Provided routine maintenance and monitoring
- Performed trouble shooting
- Provided workshop and training
PROGRESS
IN PROGRESS
The project is 90% completed
Issues:
All consultant projects are moving good progress, will be completed on schedule at FY18 (all are multi-year
projects).
Resolution:
Comment:
Task included in FY 18 OWP.
Page 99 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00130.10 MODEL ENHANCEMENT AND MAINTENANCE
BUDGET / EXPENDITURE
1,233,007
228,400 171,009 36,000 346,317 0 0 350,000 0 0 0 101,281 0
781,726 309,855 0 0 0 40,145 0 0 101,281 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 641,401 257,567 194,638 78,610 110,586
Consultant 252,723 0 0 2,095 250,628
CONTRACT STATUS (IF APPLICABLE)
CALTHORPE ANALYTICSCONTRACT EXECUTED VENDOR:STATUS:
12/09/2016 11/30/2017 17-009-SS
27,780 27,780
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
CAMBRIDGE SYSTEMATICSCONTRACT EXECUTED VENDOR:STATUS:
01/19/2017 02/28/2018 17-016
129,476 80,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
CAMBRIDGE SYSTEMATICSCONTRACT NEGOTIATI VENDOR:STATUS:
04/01/2017 12/31/2018 17-018
78,112 50,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
WSP / PARSONS BRINKERHOFFCONSULTANT EVALUA VENDOR:STATUS:
03/22/2017 06/30/2018 17-010
150,000 150,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 100 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00130.12 HEAVY DUTY TRUCK (HDT) MODEL UPDATE
OBJECTIVE: PROJECT MANAGER:
SCAG developed the Heavy Duty Truck (HDT) Model to evaluate important policy choices and investment decisions.
The HDT model is a primary analysis tool to support the goods movement policy decisions made by SCAG and
regional stakeholders. The objective of this project is to update the inter-regional component of the existing HDT
model and to perform a preliminary 2016 HDT model validation.
HSI-HWA HU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Project management, support, and
weekly discussion
1
75Staff/Consultant06/30/201806/12/201706/30/201707/01/2016Data analysis - analyze updated
commodity flow or HDT data
2
40Staff/Consultant06/30/201806/12/201706/30/201707/01/2016Model estimation - estimate HDT
model, and conduct model
calibration and validation
3
20Consultant06/30/201806/12/201706/30/201707/01/2016Model implementation - software
coding, testing, and fine tuning
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 SCAG heavy-duty truck model update plan. 06/30/2017
2 Data analysis on truck traffic. 06/30/2017
PERCENTAGE COMPLETED: 50 STATUS:
Accomplishments:
- SCAG issued the Notice to Proceed and fully executed of contract to Resource Systems Group(RSG).
- SCAG held a kickoff meeting.
- RSG is working on Model Development Plan (MDP) and draft model framework, expected delivery date: early July.
PROGRESS
IN PROGRESS
- Step No 2, 3 and 4 are delayed
Issues:
- The project is multi-year project. The tasks have been carried over already into the FY 18 budget.
- The project and final products will be completed.
- Task has been carried over and included in FY 18 OWP.
Resolution:
Page 101 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00130.12 HEAVY DUTY TRUCK (HDT) MODEL UPDATE
Comment:
- The NTP was issued on June 12, 2017 which was delay due to contract negotiation process.
- Data analysis on truck traffic is delay, pending "TRANSEARCH" data purchase from Goods Movement department.
Task included in FY 18 OWP.
BUDGET / EXPENDITURE
299,089
56,138 42,032 0 78,083 0 0 100,000 0 0 0 22,836 0
176,253 88,530 0 0 0 11,470 0 0 22,836 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 2,562 0 0 0 2,562
Staff 175,661 39,350 19,977 49,467 66,867
CONTRACT STATUS (IF APPLICABLE)
RESOURCE SYSTEMS GROUP (RSG)CONTRACT EXECUTED VENDOR:STATUS:
07/01/2017 06/30/2018 17-032-C1
150,000 150,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 102 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00130.13 ACTIVITY-BASED MODEL (ABM) DEVELOPMENT AND SUPPORT
OBJECTIVE: PROJECT MANAGER:
The Activity-Based Model is a new generation of travel demand model. According to the RTP Guideline by California
Transportation Commission, the largest four MPOs in California are encouraged to transition to activity-based travel
demand models. The objective of this project is to develop SCAG activity-based model. The model will be validated
and calibrated. A peer review meeting will be conducted.
HSI-HWA HU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Support of project management -
weekly progress meeting with
consultant
1
100Staff06/30/201707/01/201606/30/201707/01/2016Analyze data - household travel
survey data analysis for each
sub-model, model estimation dataset
preparation
2
85Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Estimating modeling - estimate and
analyze each sub-model, conduct
model calibration, validation, and
sensitivity test.
3
70Consultant06/30/201702/15/201606/30/201707/01/2016Implement modeling - model software
coding, testing, and fine tuning.
4
70Consultant06/30/201702/15/201706/30/201701/01/2017Prepare draft model development
summary report and conduct peer
review meeting.
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 SCAG ABM model framework and design. 06/30/2017 06/30/2017
2 Model validation target and data analysis. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 85 STATUS:
Accomplishments:
- Consultant completed 1) model estimation review, 2) software development, and 3) validation test for 1% and 10%
samples for following models:
1) Input data review
2) PopSyn module
3) Long-term choice models
4) Mobility choice models
PROGRESS
IN PROGRESS
Page 103 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00130.13 ACTIVITY-BASED MODEL (ABM) DEVELOPMENT AND SUPPORT
5) CDAP (Daily Activity Pattern)
- On-going mode development (will be continued to next FY)
1) Household survey expansion to year 2016
2) Joint travel
- SCAG staff completed 1) household survey analysis for model validation targets, 2) model output analysis for
household expansion, 3) model output analysis, 4) school enrollment and person type analysis, and 5) model server
coordination.
The project is 85% completed due to late start of consultant project.
Issues:
NTP issued at end of March. The consultant has been making great progress. This is a multi-year project. The
product will be completed on schedule at FY18.
Resolution:
Comment:
Task included in FY 18 OWP.
BUDGET / EXPENDITURE
1,050,848
195,795 146,597 0 272,333 0 0 300,000 0 0 50,000 86,123 0
664,725 265,590 0 0 0 34,410 0 0 86,123 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 36,506 0 0 0 36,506
Staff 593,742 0 97,254 252,197 244,291
Page 104 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00130.13 ACTIVITY-BASED MODEL (ABM) DEVELOPMENT AND SUPPORT
CONTRACT STATUS (IF APPLICABLE)
PARONS BRINCKERHOFFCONTRACT EXECUTED VENDOR:STATUS:
03/22/2017 04/01/2018 17-010-C1
784,999 168,206
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
WSP / PARSONS BRINKERHOFFCONSULTANT EVALUA VENDOR:STATUS:
03/22/2017 06/30/2018 07-010
18,206 18,206
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 105 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00132.01 SUBREGIONAL MODEL DEVELOPMENT, COORDINATION AND OUTREACH
OBJECTIVE: PROJECT MANAGER:
SCAG strives to continually improve the level of modeling within the SCAG region and ensure local agencies are
using consistent model input data and modeling tools. To achieve these objectives, SCAG provides modeling
assistance and modeling data to sub-regional modeling agencies. Also, SCAG works closely with the sub regions to
ensure their model changes and data enhancements are incorporated into the Regional Model.
HAO CHENG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide technical support; model
input data, model setups, and model
documentation to subregional
modeling agencies and other
stakeholders.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Support member agencies
developing and improving their
models by assisting in the
implementation of SCAG's new
Subregional Modeling Tool and by
participating on modeling advisory
committees.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Perform outreach to regional and
subregional modeling agencies to
coordinate and promote SCAG's
major modeling initiatives.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Subregional model coordination and technical support 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
- Continued the coordination with Caltrans staff on Imperial County transportation model development project.
- Processed survey data to support sub regional model calibration.
- Continued processing and providing input data for SBCTA to support SBTAM model improvement. Met with
SBCTA's consultant to discuss sub regional model improvement work.
- Continued supporting VCTC's consultant on VCTM development by providing data and technical advice.
PROGRESS
COMPLETED
Page 106 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00132.01 SUBREGIONAL MODEL DEVELOPMENT, COORDINATION AND OUTREACH
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
341,505
96,296 72,099 0 133,939 0 0 0 0 0 0 39,171 0
302,334 0 0 0 0 0 0 0 39,171 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 309,337 80,763 130,592 50,439 47,543
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 107 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00132.04 REGIONAL MODELING COORDINATION AND MODELING TASK FORCE
OBJECTIVE: PROJECT MANAGER:
To elevate the level of transportation modeling within the SCAG Region. SCAG provides leadership to the Southern
California modeling community by coordinating national, state, regional and local modeling programs.
MANA SANGKAPICHAI
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct outreach to SCAG
members to educate and promote
SCAG's state of the art modeling
program. Conduct inter-agency
coordination through bi-monthly
Modeling Task Force Meetings and
other forums.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate modeling activities with
transportation commissions, MPOs,
Caltrans, ARB, air districts, and
State/Federal agencies.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Participate in technical committees,
conferences, and other technical
forums.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Bi-monthly Modeling Task Force Meeting Agendas &
Meeting Minutes
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
- Participate in ARB's SB 375 Regional GHG Target Update Workshop and discussed on proposed GHG Targes.
- Participate in ARB’s EMFAC2017 Workshop and provided technical comments.
- Conducted Modeling Task Force Meetings at SCAG (05/2017)
- Coordinated with SACOG, SANDAG and MTC in Future Mobility Research Program, reviewed RFP and provided
comments.
- Coordinated with other three large MPOs (SACOG, MTC, SANDAG) on joint household survey development.
PROGRESS
COMPLETED
Issues:
Page 108 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00132.04 REGIONAL MODELING COORDINATION AND MODELING TASK FORCE
Resolution:
Comment:
BUDGET / EXPENDITURE
229,575
59,957 44,891 0 83,394 0 15,000 0 0 0 0 26,333 0
203,242 0 0 0 0 0 0 0 26,333 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 180,744 49,943 21,743 73,616 35,442
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 109 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00132.08 MODEL DATA DISTRIBUTION AND SUPPORT
OBJECTIVE: PROJECT MANAGER:
SCAG provides modeling data to support stakeholders' planning programs, to assist in the development and
maintenance of city and subregional models, and to help in project analyses. SCAG provides modeling data services
to member agencies, universities, and other public agencies by providing model setups, model input data, and
model results.
HAO CHENG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide technical assistance; model
setups; model input data; model
results; and model documentation to
member agencies and external
stakeholders.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Track and monitor model and data
requests.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Various modeling data to stakeholders. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
- Provided SCAG data, technical support, and SCAG models for more than 40 data/model requests
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 110 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00132.08 MODEL DATA DISTRIBUTION AND SUPPORT
BUDGET / EXPENDITURE
570,703
160,924 120,488 0 223,831 0 0 0 0 0 0 65,460 0
505,243 0 0 0 0 0 0 0 65,460 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 412,113 107,947 95,713 94,770 113,683
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 111 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00147.01 RTP MODELING, COORDINATION AND ANALYSIS
OBJECTIVE: PROJECT MANAGER:
To provide modeling analysis for developing SCAG's RTP/SCS and RTP amendments. Major tasks include:
coordinating with planning staff, preparing model inputs, conducting model runs, analyzing model results, performing
conformity analysis, producing summary reports, and writing model documentation.
HSI-HWA HU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate RTP/SCS modeling
activities with other SCAG
departments, outside stakeholders,
and State and Federal agencies.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare model inputs including
highway and transit networks. Also,
review and update model
assumptions, parameters, and
socio-economic data.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Perform transportation model runs,
evaluate model results, and produce
summary reports.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Apply air quality emission models
and preform conformity analysis.
Also, coordinate modeling activities
and provide technical assistance to
SCAG's Air Quality Staff.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Model results and summary reports. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
- Delivered transit output data (boarding) of SCAG's 2016 RTP/SCS amendment 2.
- Archived all model input/output data for the 2016 RTP amendment 2 (16 sets).
PROGRESS
COMPLETED
Issues:
Page 112 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00147.01 RTP MODELING, COORDINATION AND ANALYSIS
Resolution:
Comment:
BUDGET / EXPENDITURE
218,360
61,572 46,101 0 85,641 0 0 0 0 0 0 25,046 0
0 193,314 0 0 0 0 0 0 25,046 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 158,422 48,039 42,788 19,229 48,366
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 113 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00147.02 FTIP MODELING, COORDINATION AND ANALYSIS
OBJECTIVE: PROJECT MANAGER:
To provide modeling analysis for the FTIP. Major tasks include coordinating with planning staff, preparing model
inputs, conducting model runs, analyzing model results, performing emissions analysis, and producing summary
reports.
HSI-HWA HU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate FTIP modeling activities
with other SCAG departments,
outside stakeholders, and State and
Federal agencies.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare model inputs including
highway and transit networks. Also,
review and update model
assumptions and socio-economic
data.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Perform transportation model runs,
evaluate model results, and produce
summary reports.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Apply air quality emission models
and preform conformity analysis.
Also, coordinate modeling activities
and provide technical assistance to
SCAG's Air Quality Staff.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Model results and summary reports. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
- Reviewed and commented on 2019 FTIP Guidelines.
- Continued the development of base year network.
- Coordinated with planning staff in the preparation of 2018 STIP.
- Coordinated with planning staff in the preparation of 2019 FTIP.
- Discussed model data need for transit project (DASH).
- Reviewed potential conformity impact on 2019 FTIP due to a new air quality model
PROGRESS
COMPLETED
Page 114 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00147.02 FTIP MODELING, COORDINATION AND ANALYSIS
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
418,999
118,147 88,460 0 164,332 0 0 0 0 0 0 48,060 0
370,939 0 0 0 0 0 0 0 48,060 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 309,487 36,498 125,197 80,778 67,014
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 115 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00147.03 SPECIAL PLANNING STUDIES MODELING AND ANALYSIS
OBJECTIVE: PROJECT MANAGER:
To participate in policy development and provide modeling and other technical analysis for regional planning
initiatives, corridor studies, and scenario testing.
HSI-HWA HU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate with project sponsors to
obtain background information
regarding the strategic initiative,
planning scenario, or other planning
study. Provide technical
recommendations regarding the
study approach and/or findings.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare model inputs including
highway and transit networks. Also,
review and update model
assumptions and socio-economic
data.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Perform transportation model runs,
evaluate model results, and produce
summary reports.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Modeling and other planning analyses for internal and
external applications.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
- Continued the development and data collection for 2016 base year network for both highway and transit
- Collected parking cost data
- Traffic data analysis for I-5 Corridor
- Support model analysis for SB743
- Participated in the joint 4 MPOs household travel survey project
PROGRESS
COMPLETED
Issues:
Page 116 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.00147.03 SPECIAL PLANNING STUDIES MODELING AND ANALYSIS
Resolution:
Comment:
BUDGET / EXPENDITURE
202,299
57,043 42,710 0 79,342 0 0 0 0 0 0 23,204 0
179,095 0 0 0 0 0 0 0 23,204 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 103,541 32,847 25,424 8,936 36,334
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 117 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.02665.01 SCENARIO PLANNING AND MODELING
OBJECTIVE: PROJECT MANAGER:
Prepare roll out of the model to all SCAG local jurisdictions in the preparation for the next round of Regional
Transportation Plan (RTP)/ Sustainable Communities Strategy that will provide local planners with enhanced
capacity for local data management and scenario planning. Also continued maintenance of the SPM with the
provision of training and technical assistance, outreach and educational programs to assist local planners.
JUNGA UHM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
50Staff06/30/201707/01/201606/30/201707/01/2016Prepare and provide training to
SCAG staff and member jurisdictions
1
50Staff06/30/201707/01/201606/30/201707/01/2016Provide outreach and support
services to jurisdictions in the
application of the Scenario Planning
Model
2
75Staff06/30/201707/01/201606/30/201707/01/2016Maintain and enhance the
capabilities of the SCAG Scenario
Planning Model
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Model training and dissemination 06/30/2017
2 Enhanced SCAG Scenario Planning Modeling system 06/30/2017
PERCENTAGE COMPLETED: 55 STATUS:
Accomplishments:
-Staff continued to provide support services to local users, including access and account set up
-Staff managed SPM Data Management system operation and maintenance support project
-Staff continued the discussion with staff from other departments at SCAG, focusing on each of the SPM’s six
analysis modules
-Staff continued to review the current scenario development system to build internal capacities for future
maintenance and enhancement
PROGRESS
IN PROGRESS
SPM Data Management system release scheduled has been delayed to be in synch with a local review and input
process for the 2020 RTP/SCS. Until then, the application is available per request basis.
Issues:
Page 118 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
070.02665.01 SCENARIO PLANNING AND MODELING
Extensive outreach and support services including training will be provided to jurisdictions as part of a local review
and input process for the 2020 RTP/SCS in the Fall 2017.
Resolution:
Comment:
Task included in FY 18 OWP.
BUDGET / EXPENDITURE
863,245
229,935 172,159 18,000 334,136 0 10,000 0 0 0 0 99,015 0
764,230 0 0 0 0 0 0 0 99,015 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 724,118 246,031 244,453 159,961 73,673
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 119 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
080.00153.04 REGIONAL ASSESSMENT
OBJECTIVE: PROJECT MANAGER:
Assess the region's progress toward the achievement of goals of the 2016 RTP/SCS in collaboration with local
jurisdictions. Assess the region's progress in comparison with other large metropolitan regions.
PING CHANG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Collect data and information for
regional assessment studies,
including, for example, data related
to transportation, housing,
environment and economy, and
share with local stakeholders.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct analysis of the data and
information
collected to assess the progress of
the region toward the goals of the
2016 RTP/SCS and in comparison
with other large metropolitan regions
2
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor and assess environmental
justice issues based on the analysis
of the 2016 RTP/SCS in collaboration
with other planning partners and
stakeholders.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Summary of Regional Assessment 06/30/2017 06/30/2017
2 Materials for public distribution on regional assessment
topics
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Data was continually collected in support of regional performance monitoring. Substantial SCAG staff effort &
resources were put forth in preparation, logistics, & outreach in support of the SCAG Regional Housing Summit that
was held in October, 2016. Over 400 persons attended this event that brought into focus the critical need for
affordable housing in the Southern California region. SCAG staff participated in the annual Demographic Workshop
held on the campus of the University of Southern California on June 26th.
PROGRESS
COMPLETED
Page 120 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
080.00153.04 REGIONAL ASSESSMENT
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
543,003
132,365 99,105 8,991 191,259 0 9,000 0 0 0 40,000 62,283 0
480,720 0 0 0 0 0 0 0 62,283 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 505,520 165,626 168,263 89,492 82,139
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 121 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
080.00153.05 DATA COMPILATION AND CIRCULATION
OBJECTIVE: PROJECT MANAGER:
Develop and publish the 2017 Local Profiles to support local and regional planning efforts.
PING CHANG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Enhance the process of data
acquisition and management.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Collect new data since the
publication of the 2015 Local
Profiles.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare and publish the 2017 Local
Profiles.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 2017 Local Profiles 06/30/2017 05/04/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
The 2017 Local Profiles reports were officially released at the SCAG General Assembly in Palm Desert on May 4th.
A total of 201 reports were developed, one for each member jurisdiction in the SCAG region, including 189 cities, 6
counties, and 6 unincorporated county areas. Throughout the year, SCAG staff worked to acquire the necessary
data, prepare the master data worksheet, format & design the reports, and update the various report templates. The
draft 2017 Local Profiles reports were released for local jurisdictional review during the month of March. Local
comments were then incorporated, as appropriate, into the final reports. SCAG continues to receive many requests
for copies of the reports from local elected officials who use them as resources in support of local planning,
economic development, and community outreach efforts. The 2017 Local Profiles reports are now available for
download on the SCAG website.
PROGRESS
COMPLETED
Issues:
Resolution:
Page 122 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
080.00153.05 DATA COMPILATION AND CIRCULATION
Comment:
BUDGET / EXPENDITURE
344,134
97,037 72,654 0 134,970 0 0 0 0 0 0 39,473 0
304,661 0 0 0 0 0 0 0 39,473 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 266,616 32,274 26,537 64,440 143,365
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 123 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
090.00148.01 PUBLIC INFORMATION AND COMMUNICATION
OBJECTIVE: PROJECT MANAGER:
Develop external communications and media strategy to promote partnerships, build consensus, and foster
inclusiveness in the decision-making process. SCAG's media and communications strategy facilitates the agency's
transportation planning activities by helping to inform the general public, media, agency stakeholders and partners
about the existence, purpose and potential impact of these activities and to convey this information in ways that are
engaging, interesting and easy for general audiences to understand. Materials developed for this purpose include
website content, videos, news releases, fact sheets, signage, posters, and other publications. Related activities
include public outreach meetings and workshops, special events, editorial board meetings, and other similar
activities. The major objective in FY 2015/16 is to engage regional stakeholders in the discussion of issues related to
the implementation of the 2016 RTP/SCS.
JEFF LIU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Write, edit and disseminate news
releases and media advisories
1
100Staff/Consultant06/30/201712/01/201606/30/201707/01/2016Produce videos promoting agency
programs, plans, policies and
services.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Video record and web stream
monthly regional council meetings
3
100Staff06/30/201707/01/201606/30/201707/01/2016Write, edit, design and disseminate
monthly Regional Council Spotlight
eNewsletter
4
100Staff06/30/201707/01/201606/30/201707/01/2016Write, edit, design and disseminate
monthly SCAG Update eNewsletter
5
100Staff06/30/201707/01/201606/30/201707/01/2016Write, edit, design and disseminate
factsheets and other outreach
material.
6
100Staff06/30/201707/01/201606/30/201707/01/2016Write, edit, design and produce new
member orientation materials and
other promotional materials.
7
100Staff06/30/201707/01/201606/30/201707/01/2016Write, edit, design and produce
annual Regional Conference and
General Assembly material.
8
100Staff06/30/201707/01/201606/30/201707/01/2016Write, edit, design and produce Your
Guide To SCAG booklet.
9
100Staff06/30/201707/01/201606/30/201707/01/2016Enhance and maintain website
content.
10
Page 124 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
090.00148.01 PUBLIC INFORMATION AND COMMUNICATION
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Videos promoting agency programs, plans, policies and
services,
06/30/2017 06/30/2017
2 Website promoting and describing all SCAG programs,
plans, services and initiatives.
06/30/2017 06/30/2017
3 News releases and media advisories to general media,
specialized media and agency stakeholders, publicizing
and promoting agency programs, plans, services and
initiatives.
06/30/2017 06/30/2017
4 Regional Council's monthly 'Spotlight' eNewsletter 06/30/2017 06/30/2017
5 Agency's periodic 'Update e-Newsletter' 06/30/2017 06/30/2017
6 Web-stream and video record of Regional Council
meetings
06/30/2017 06/30/2017
7 Factsheets describing programs, plans, services and
initiative of agency
06/30/2017 06/30/2017
9 Materials for annual Regional Conference and General
Assembly
06/30/2017 06/30/2017
10 Materials for recurring New Member Orientations 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Developed and distributed press releases on the Regional Conference and General Assembly, Demographic
Workshop; Completed Year in Review and Sustainability Awards videos; SCAG has recorded, streamed and
provided archive videos of its monthly Regional Council meetings; Produced and distributed the monthly Spotlight
e-newsletter, plus SCAG Update newsletters; Produced flyers for SCAG's earthquake initiative; Developed program
and event materials for Regional Conference; and developed new Annual Accomplishments report in lieu of Your
Guide to SCAG.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 125 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
090.00148.01 PUBLIC INFORMATION AND COMMUNICATION
BUDGET / EXPENDITURE
1,417,395
365,542 273,691 0 508,436 35,000 5,000 125,000 0 0 70,000 34,726 0
268,024 0 0 0 0 1,114,645 0 0 34,726 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 1,168,955 334,140 344,048 249,770 240,997
Consultant 80,472 0 0 1,990 78,482
CONTRACT STATUS (IF APPLICABLE)
MELTWATER NEWS US INC.CONTRACT EXECUTED VENDOR:STATUS:
09/21/2016 06/30/2019 17-004-C1
61,783 17,950
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ONE EIGHTEEN ADVERTISINGCONTRACT EXECUTED VENDOR:STATUS:
01/22/2016 10/31/2016 16-015
63,875 0 61,982
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ROBERT WALL CONSULTING, LLCCONTRACT EXECUTED VENDOR:STATUS:
11/03/2016 06/30/2020 17-012
563,925 123,775 173,055
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 126 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.01533.01 REGIONAL TRANSPORTATION PLAN OUTREACH
OBJECTIVE: PROJECT MANAGER:
Conduct a public outreach strategy to engage regional stakeholders in a collaborative effort to continue consensus
building on SCAG plans and programs and initiate the implementation of the 2016 RTP/SCS.
JEFF LIU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide project management and
administration.
1
100Consultant06/30/201707/01/201606/30/201707/01/2016Assist with public outreach to
engage stakeholders in dialogue on
SCAG's regional priorities identified
in the 2016 RTP/SCS to help
facilitate the implementation.
2
100Consultant06/30/201707/01/201606/30/201707/01/2016Assist with meeting and workshop
coordination and other activities
intended to provide outreach support
for SCAG's planning activities.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Meeting agendas and supporting documentation for
SCAG facilitated activities
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Prepared materials and promoted electronically the public hearing for RTP Amendment #2.
PROGRESS
COMPLETED
Issues:
Resolution:
Page 127 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.01533.01 REGIONAL TRANSPORTATION PLAN OUTREACH
Comment:
BUDGET / EXPENDITURE
127,322
21,803 16,324 0 30,326 0 0 50,000 0 0 0 8,869 0
68,453 44,265 0 0 0 5,735 0 0 8,869 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 8,405 4,025 1,309 -8 3,079
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 128 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.01533.02 REGIONAL PLANNING & POLICY INTERN PROGRAM
OBJECTIVE: PROJECT MANAGER:
To establish a SCAG Internship Program providing students in planning, policy and related fields the opportunity to
gain real-world experience while providing policy research, data analyses, and other services to
divisions/departments throughout the agency.
CARMEN FLORES
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Develop a framework for
administering the program that
includes program goals and
objectives, administrative details
(e.g. hiring procedures, term and
compensation, supervision
responsibility, budget), work detail,
evaluation procedures, etc.
1
100Consultant06/30/201707/01/201606/30/201707/01/2016Initiate year one of the program for
interns.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Program Framework Guidelines and Implementation 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
New Summer Intern Orientation fully implemented. SCAG hired 15 interns for the summer with possible extensions
and additional hires planned on a quarterly basis.
PROGRESS
COMPLETED
Summer Internship hiring has been completed. Onboarding and orientation will take place July 17, 2018.
Issues:
Staff has hired and processed summer interns. Start date is July 17, 2018.
Revamping intern hiring policies and procedures.
Resolution:
Page 129 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.01533.02 REGIONAL PLANNING & POLICY INTERN PROGRAM
Comment:
Task is ongoing and has been carried into FY 18.
BUDGET / EXPENDITURE
323,169
0 0 180,000 143,169 0 0 0 0 0 0 0 0
0 0 0 0 0 323,169 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 153,203 0 82,523 45,050 25,630
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 130 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.01533.03 MEDIA SUPPORT FOR PLANNING ACTIVITIES
OBJECTIVE: PROJECT MANAGER:
Provide media support to build awareness of SCAG's role and planning activities to a broad constituency
representative of the region's diversity.
JEFF LIU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Assist with media needs associated
with SCAG planning activities,
notably the RTP/SCS, including
translation services, as needed
1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Media log, op-ed pieces and other original content
intended for print and electronic media.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Developed and distributed targeted press releases for the Regional Conference & General Assembly, Demographic
Workshop, Go Human events and 100 Hours campaign. Also developed press release calling for greater federal
freight funding.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 131 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.01533.03 MEDIA SUPPORT FOR PLANNING ACTIVITIES
BUDGET / EXPENDITURE
250,038
14,109 10,564 0 19,625 0 0 200,000 0 0 0 5,740 0
44,298 177,060 0 0 0 22,940 0 0 5,740 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 30,324 11,988 6,897 6,380 5,059
Consultant 118,933 9,096 16,216 23,837 69,784
CONTRACT STATUS (IF APPLICABLE)
THE 20/20 NETWORKCONTRACT EXECUTED VENDOR:STATUS:
07/01/2016 10/31/2017 14-009-C1
300,000 75,964 58,295
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
THE SIERRA GROUPCONTRACT EXECUTED VENDOR:STATUS:
07/01/2016 06/30/2017 14-009-C2
500,000 102,801 75,614
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 132 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.01633.01 PUBLIC INVOLVEMENT
OBJECTIVE: PROJECT MANAGER:
Engage regional stakeholders in the SCAG planning and programming process through the support and
enhancement of outreach efforts to local governments, Tribal Governments, and members of various stakeholder
entities, including community, environmental, business, and academic groups, as well as other interested parties.
The public outreach efforts include presentations, workshops, public meetings, and public hearings on major SCAG
initiatives.
JEFF LIU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage the Regional Offices,
including coordinating special events
throughout the year
1
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct on-going coordinating
meetings with staff & consultants
associated with major SCAG
initiatives and other outreach efforts,
such as the RTP/SCS, active
transportation, economic strategy
and sustainability programs.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor budget, prepare regular
progress reports, & provide timely
coordinated and accurate support to
the Regional Council and Policy
Committees
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Tracking log of meetings attended and outreach
presentations by Regional Affairs Officers and at
Regional Offices, including supporting documentation,
such as agendas, meeting summaries, sign-in sheets,
etc...
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Staff attended local city council, COG meetings and special events throughout the region. Compiled weekly reports
on what's happening in the region. Conducted outreach for earthquake workshops. Monitored elections for incoming
and outgoing city council members.
PROGRESS
COMPLETED
Page 133 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.01633.01 PUBLIC INVOLVEMENT
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
2,082,181
562,280 420,994 0 782,080 0 53,000 0 0 0 25,000 238,827 0
243,354 1,600,000 0 0 0 0 0 0 238,827 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 1,719,557 493,935 522,774 503,267 199,581
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 134 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.04097.01 SYSTEM-WIDE EMERGENCY/EARTHQUAKE PREPAREDNESS PLANNING
OBJECTIVE: PROJECT MANAGER:
Develop a comprehensive framework to prepare for and mitigate the transportation impacts of region-wide
emergencies, including earthquakes and other natural disasters.
JEFF LIU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Develop a comprehensive framework
to prepare for and mitigate the
transportation impacts of region-wide
emergencies, including earthquakes
and other natural disasters.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Project and contract management2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Written report, presentations and other materials as
directed.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Held one Phase II workshops for local jurisdictions in Ventura County with close to 50 participants and follow-up
Phase III meeting with utilities.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 135 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
095.04097.01 SYSTEM-WIDE EMERGENCY/EARTHQUAKE PREPAREDNESS PLANNING
BUDGET / EXPENDITURE
230,949
8,727 6,534 0 12,138 0 0 200,000 0 0 0 3,550 0
27,399 177,060 0 0 0 22,940 0 0 3,550 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 4,366 3,322 1,304 -257 -3
Consultant 191,671 0 50,382 62,875 78,414
CONTRACT STATUS (IF APPLICABLE)
STRATISCOPECONTRACT EXECUTED VENDOR:STATUS:
08/04/2016 06/30/2018 17-003-SS1
199,500 199,500 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 136 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
100.01630.02 INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PLANNING
OBJECTIVE: PROJECT MANAGER:
The objective of this task is to plan for transportation technology advancements and assess potential impacts to the
transportation system, and to support the effective implementation of technology through the integration of ITS into
common architecture, via participation with regional partners in the implementation and maintenance of the Regional
ITS architecture.
PHILIP LAW
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Continue participation with Regional
Integration of Intelligent
Transportation Systems (RIITS)
development and Information
Exchange Network (IEN) integration,
and examine areas of RIITS/IEN that
can/should be integrated into
Regional Architecture.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Identify ITS strategies for inclusion in
RTP/SCS update.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 ITS element of RTP/SCS update. 06/30/2017 06/30/2019
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
During the 4th Quarter, staff continued to participate in regional coordination activities associated with ITS planning
and ITS architecture development. The ITS Architecture update study also began.
PROGRESS
IN PROGRESS
Issues:
Resolution:
Page 137 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
100.01630.02 INTELLIGENT TRANSPORTATION SYSTEMS (ITS) PLANNING
Comment:
BUDGET / EXPENDITURE
44,907
10,274 7,692 0 14,290 0 7,500 0 0 0 0 5,151 0
39,756 0 0 0 0 0 0 0 5,151 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 38,170 3,122 13,505 9,195 12,348
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 138 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
100.01630.03 REGIONAL ITS STRATEGIC PLAN AND REGIONAL ITS ARCHITECTURE UPDATE
OBJECTIVE: PROJECT MANAGER:
The objective of this multi-year task is first, to develop a regional ITS Strategic Plan in coordination with Caltrans,
county transportation commissions, and other agency stakeholders, and second, to update of the Regional ITS
Architecture. The Strategic Plan will identify and assess emerging ITS and technologies and potential impacts to the
regional transportation system, identify institutional and technological systems and processes needed to address the
issues and support successful implementation, and provide a framework for updating the Regional ITS Architecture.
The second phase of the project will be to update the Regional ITS Architecture.
PHILIP LAW
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
10Consultant06/30/201812/01/201606/30/201712/01/2016Provide project management,
support, and administration.
1
5Consultant06/30/201806/01/201706/30/201712/01/2016Solicit and incorporate stakeholder
input and participation.
2
0Consultant06/30/201808/01/201706/30/201712/01/2016Identify and assess emerging ITS
and technology issues and develop
Regional ITS Strategic Plan (will
continue through FY17-18).
3
0Consultant06/30/201809/15/201706/30/201712/01/2016Identify elements and parameters for
Regional ITS Architecture Update
(will continue through FY17-18).
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Assessment of emerging technology issues 06/30/2017 06/30/2018
2 Regional ITS Strategic Plan 06/30/2017 06/30/2018
3 Updated Regional ITS Architecture 06/30/2017 06/30/2018
PERCENTAGE COMPLETED: 3 STATUS:
Accomplishments:
A contract has been awarded to a consultant and work has begun.
PROGRESS
IN PROGRESS
Issues:
Page 139 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
100.01630.03 REGIONAL ITS STRATEGIC PLAN AND REGIONAL ITS ARCHITECTURE UPDATE
Resolution:
Comment:
Task is carried over and included in FY 18 OWP.
BUDGET / EXPENDITURE
250,000
0 0 0 0 0 0 250,000 0 0 0 0 0
0 221,325 0 0 0 28,675 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 11,335 0 0 0 11,335
CONTRACT STATUS (IF APPLICABLE)
KIMLEY HORN AND ASSOCIATESCONTRACT EXECUTED VENDOR:STATUS:
06/12/2017 06/30/2018 17-036c1
344,161 39,754 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 140 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
120.00175.01 OWP DEVELOPMENT & ADMINISTRATION
OBJECTIVE: PROJECT MANAGER:
Manage the Overall Work Program (OWP) and budget including project performance monitoring and reporting
activities. Prepare and submit amendments to the OWP as required. Produce required quarterly progress reports
and manage the development of next fiscal year's OWP.
ANDREW MORA
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff08/30/201607/01/201606/30/201707/01/2016Prepare FY 2015/16 OWP 4th
Quarter Progress Reports with
preliminary and final expenditures
and submit to Caltrans
1
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor OWP project performance
and produce required progress
reporting to funding agencies
including Caltrans Quarterly
Progress Reports.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Evaluate departmental budget
requests, balancing revenues and
expenditures and prepare
amendments to the OWP as
required.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Provide support for the OWP
Management System (OMS) and
assist in the preparation of project
progress and expenditure variance
reports for management.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Provide Transportation Planning
Grant management and
administration; coordinate call for
projects with Caltrans; coordinate the
preparation of Memorandums of
Understanding with subrecipients,
assist with grant application
preparation; and monitor and prepare
quarterly progress reports.
5
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare SCAG's annual budget and
OWP and submit draft and final
documents to Caltrans, FTA and
FHWA.
6
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate and participate in the
Annual MPO Meeting.
7
Page 141 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
120.00175.01 OWP DEVELOPMENT & ADMINISTRATION
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 FY 2016/17 Preliminary and Final 4th Quarter Progress
Report
06/30/2017 08/30/2017
2 Quarterly Progress Reports 06/30/2017 06/30/2017
3 OWP Amendments 06/30/2017 06/30/2017
4 Draft FY18 OWP and Budget 06/30/2017 03/01/2017
5 Final FY18 OWP and Budget 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Prepared and submitted the FY16 4th quarter progress report and FY17 OWP 1st, 2nd, 3rd quarter progress report.
Prepared and submitted Amendments 1, 2, and 3 to the FY17 OWP. Hosted the annual MPO meeting between
SCAG and its funding partners. Prepared and submitted Draft + Final FY18 OWP to Caltrans, FHWA and FTA.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
3,324,571
934,461 699,656 18,000 1,314,066 0 0 0 0 0 0 358,387 0
322,732 2,443,451 0 0 0 200,000 0 0 358,388 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
Page 142 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
120.00175.01 OWP DEVELOPMENT & ADMINISTRATION
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 2,665,865 584,309 746,485 728,487 606,584
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 143 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
120.00175.02 GRANT ADMINISTRATION
OBJECTIVE: PROJECT MANAGER:
To identify funding sources and prepare grant applications. Coordinate the implementation of grant awards and
ensure post-award compliance. Compiles financial data for the preparation of internal reports, progress reports and
grant billings.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Research and prepare grant
applications
1
100Staff06/30/201707/01/201606/30/201707/01/2016Perform general grant administration
functions such as billings, budget
amendments, workscope changes,
monitoring grant budgets and
expenditures
2
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare, review and maintain
Memorandum of Understandings
and/or Agreements with Grantors
and subrecipients. Includes monitor
and oversight of grant funded
projects, including subrecipients and
beneficiaries.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Attend and participate in any
required grant related meetings,
workshops, program updates and
seminars.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Grant Applications, Sub-Agreements/MOUs 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Coordination of SCAG's 2016 Sustainable Transportation Planning Grant Program and the FY 2017-18 Caltrans
Sustainable Transportation Planning Grant Program.
PROGRESS
IN PROGRESS
Issues:
Page 144 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
120.00175.02 GRANT ADMINISTRATION
Resolution:
Comment:
BUDGET / EXPENDITURE
632,677
201,513 150,878 0 280,286 0 0 0 0 0 0 0 0
0 0 0 0 0 632,677 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 147,388 22,422 29,482 44,499 50,985
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 145 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.02 SOUTHERN CALIFORNIA NATIONAL FREIGHT GATEWAY COLLABORATION
OBJECTIVE: PROJECT MANAGER:
To fulfill the obligations of MOU signed by regional, state, and federal agencies to advance Southern California’s role
as a national leader and support the identified regional goods movement system.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide project management, support
and administration.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Identify, support, and execute
opportunities for interagency
stakeholders to advance the delivery
of projects identified as part of the
regional goods movement system in
the Southern California region.
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Provide assistance in developing
appropriate strategies that support
the regional goods movement
system with discrete near-term
projects under a unified brand of
FreightWorks.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Materials from meetings and initiatives developed in
partnership with interagency stakeholders on strategies
to advance projects identified as part of the regional
goods movement system.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
SCAG staff continued to work with regional, state, and federal stakeholders on FAST Act grant opportunities.
PROGRESS
COMPLETED
Issues:
Page 146 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.02 SOUTHERN CALIFORNIA NATIONAL FREIGHT GATEWAY COLLABORATION
Resolution:
Comment:
BUDGET / EXPENDITURE
114,411
32,261 24,155 0 44,872 0 0 0 0 0 0 13,123 0
101,288 0 0 0 0 0 0 0 13,123 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 59,558 25,810 18,356 5,904 9,488
CONTRACT STATUS (IF APPLICABLE)
ZEPOL CORPORATIONCONTRACT EXECUTED VENDOR:STATUS:
06/28/2012 06/30/2017 12-040-C1
29,916 0 5,983
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 147 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.09 URBAN GOODS MOVEMENT (WAREHOUSING/TRANSLOADING IN THE SCAG REGION)
OBJECTIVE: PROJECT MANAGER:
To identify and analyze regional trade impacts including a more detailed analysis of manufacturing, local distribution,
and import/export trends and the implications for freight transportation in the SCAG region.
WARREN WHITEAKER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct additional stakeholder
outreach.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct additional analysis to further
understanding of logistics facilities at
a county level or refine freight
sustainability.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Study fact sheets, PowerPoint presentations, and/or
other communication material.
06/30/2017 06/30/2017
2 Brief task reports summarizing the analysis findings. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Staff finalized stakeholder outreach, collaboration, and study products.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 148 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.09 URBAN GOODS MOVEMENT (WAREHOUSING/TRANSLOADING IN THE SCAG REGION)
BUDGET / EXPENDITURE
259,040
73,043 54,689 0 101,596 0 0 0 0 0 0 29,712 0
229,328 0 0 0 0 0 0 0 29,712 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 187,493 41,525 71,894 39,116 34,958
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 149 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.10 EAST-WEST FREIGHT CORRIDOR/I-15 PHASE II
OBJECTIVE: PROJECT MANAGER:
To perform continued analysis for the regional dedicated freight corridor system including analysis of truck traffic and
potential institutional frameworks.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide project management, support
and administration.
1
100Consultant06/30/201707/01/201606/30/201707/01/2016Continue analysis of truck traffic on
the eastern segment of the
East-West Freight Corridor and initial
segment of the I-15.
2
100Consultant06/30/201707/01/201606/30/201707/01/2016Analyze potential institutional
frameworks.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Technical memorandum of truck traffic on the eastern
segment of the East-West Freight Corridor and initial
segment of the I-15.
06/30/2017 06/30/2017
2 Ad-hoc analyses completed in consideration of potential
institutional frameworks.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
PSR work by Caltrans continues; continued analysis in support of the technical alternatives identified in prior fiscal
year.
PROGRESS
IN PROGRESS
Issues:
Resolution:
Page 150 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.10 EAST-WEST FREIGHT CORRIDOR/I-15 PHASE II
Comment:
This is a multi-year project. Work will continue in FY 17/18.
BUDGET / EXPENDITURE
796,542
126,478 94,697 0 175,919 0 0 348,000 0 0 0 51,448 0
397,094 0 0 0 0 348,000 0 0 51,448 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 259,270 67,940 59,074 60,916 71,340
Consultant 241,387 0 54,737 0 186,650
CONTRACT STATUS (IF APPLICABLE)
ERNST AND YOUNGCONTRACT EXECUTED VENDOR:STATUS:
08/08/2014 06/30/2017 14-019-C1
349,776 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
SYSTEMS METRICS GROUPCONTRACT EXECUTED VENDOR:STATUS:
04/23/2013 12/31/2017 13-023-C1
2,462,322 596,298 533,698
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 151 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.13 SOUTHERN CALIFORNIA P3 FINANCIAL CAPACITY ANALYSIS AND BUSINESS CASE
DEVELOPMENT
OBJECTIVE: PROJECT MANAGER:
To assess the financial capacity for public-private partnerships, and their potential application to transportation
projects, specifically those related to goods movement activities in the Southern California region, through research
and the development of innovative financial instruments.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide project management, support
and administration.
1
100Consultant06/30/201707/01/201606/30/201707/01/2016Research the development of
innovative financial instruments and
their potential application for
public-private partnerships (P3) to
transportation projects.
2
100Consultant06/30/201707/01/201606/30/201707/01/2016Develop business case scenarios to
assess the financial capacity for
public-private partnerships.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Technical memorandum identifying innovative financial
instruments and their potential application for
public-private partnerships (P3) to transportation projects.
06/30/2017 06/30/2017
2 Final report assessing the financial capacity for
public-private partnerships.
06/30/2017 06/30/2018
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Initial financial assessment of funding opportunities conducted; several alternative financial scenario model runs
conducted. PSR scenario analysis continues.
PROGRESS
COMPLETED
Issues:
Page 152 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.13 SOUTHERN CALIFORNIA P3 FINANCIAL CAPACITY ANALYSIS AND BUSINESS CASE
DEVELOPMENT
Resolution:
Comment:
This is a multi-year project and will continue in FY 2017/18. Will be inserted in amendment 2 FY 18 OWP.
BUDGET / EXPENDITURE
208,255
30,525 22,855 0 42,458 0 0 100,000 0 0 0 12,417 0
95,838 88,530 0 0 0 11,470 0 0 12,417 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 42,637 4,635 13,203 24,830 -31
CONTRACT STATUS (IF APPLICABLE)
ERNST AND YOUNGCONTRACT EXECUTED VENDOR:STATUS:
08/08/2014 12/30/2016 14-019-C1
349,776 95,562 40,436
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 153 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.18 GOODS MOVEMENT PLANNING
OBJECTIVE: PROJECT MANAGER:
Facilitate implementation of goods movement recommendations in 2016 RTP and Comprehensive Regional Goods
Movement Plan and Implementation Strategy. Begin development of 2020 RTP goods movement elements. Work
with stakeholders on federal surface transportation re-authorization effort related to technical input and analyses
associated with goods movement.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare, manage, and coordinate
with stakeholders, the goods
movement component of the RTP.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Monitor state and federal legislation,
regulations, and guidance to assess
implications on RTP goods
movement planning.
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop/produce technical work and
analysis of goods movement needs
and strategies.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Technical issue papers, memorandums, and/or reports
highlighting regional goods movement needs and
strategies.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Staff continued background research and selected consultant to engage consultant assistance. Data purchase
under separate consultant contract completed.
PROGRESS
COMPLETED
Issues:
Resolution:
Page 154 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
130.00162.18 GOODS MOVEMENT PLANNING
Comment:
This is a multi-year project and has been included in FY18 OWP.
BUDGET / EXPENDITURE
816,762
107,493 80,483 0 149,513 5,000 15,000 300,000 0 0 100,000 59,273 0
457,489 265,590 0 0 0 34,410 0 0 59,273 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 39,160 0 0 0 39,160
Staff 675,210 172,876 166,875 178,150 157,309
CONTRACT STATUS (IF APPLICABLE)
INRIX, INC.CONTRACT EXECUTED VENDOR:STATUS:
12/30/2016 03/31/2020 17-022-C1
79,000 79,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ITERIS, INC.CONTRACT EXECUTED VENDOR:STATUS:
04/04/2017 06/30/2018 17-014-C1
306,067 150,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 155 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.01 TRANSIT PLANNING
OBJECTIVE: PROJECT MANAGER:
Support regional transit operators in the planning process pursuant to the FTA's Metropolitan Transportation
Planning requirements and the SCAG MOU with transit operators. Monitor FTA rule-making related to new provisions
in the Moving Ahead for Progress in the 21st Century Act (MAP-21) and coordinate with transit operators to address
new requirements regarding transit asset management and transit safety as they relate to metropolitan
transportation planning. Provide technical memoranda and support to the Regional Transit Technical Advisory
Committee. Assess and evaluate alternative transit service delivery methods to enhance transit system availability
and connectivity. Provide support and analysis for regional High-Speed Rail (HSR) planning efforts and for the
LOSSAN corridor planning efforts. Provide environmental document review and analysis. Participate in regional,
state and federal transit studies and forums. Incorporate new performance measures into existing conditions
analyses as mandated in MAP-21.
MATTHEW GLEASON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Convene Regional Transit TAC
meetings.
1
100Staff12/01/201607/01/201606/30/201707/01/2016Produce Regional Transit System
Performance Report.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Address new federal requirements for
transit planning under MAP-21,
including transit asset management
and transit safety, as they relate to
metropolitan transportation planning.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Provide technical analysis and
support for regional transit planning
studies and in preparation for the
RTP update.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Regular Transit TAC meetings, with agendas, minutes,
technical reports and memoranda
06/30/2017 06/30/2017
2 Regional Transit System Performance Report 06/30/2017 06/30/2018
3 RTP/SCS transit element and transit technical appendix 06/30/2017 06/30/2017
Page 156 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.01 TRANSIT PLANNING
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
In the fourth quarter of Fiscal Year 2016-17, staff continued work with local transit agencies and county
transportation commissions to comply with new federal requirements for transit planning under MAP-21 and the
FAST Act, specifically relating to the final rule for Transit Asset Management (TAM). Staff have developed draft TAM
targets to be submitted to the Regional Council for approval in July.
In addition, staff convened the Regional Transit Technical Advisory Committee in May. Staff also continued to
provide analysis and support for regional transit planning studies.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
658,247
173,665 130,028 0 241,553 0 16,500 0 0 0 21,000 75,501 0
0 582,746 0 0 0 0 0 0 75,501 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 601,489 172,819 159,257 147,791 121,622
Page 157 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.01 TRANSIT PLANNING
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 158 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.02 REGIONAL HIGH SPEED TRANSPORT PROGRAM
OBJECTIVE: PROJECT MANAGER:
Guide implementation of the Southern California High-Speed Rail MOU between the California High-Speed Rail
Authority and SCAG, CTCs, and Metrolink for the programming of $1 billion in High-Speed Rail (HSR) funds to the
region's existing passenger rail services.
Provide support and analysis for the region's HSR planning efforts, including participation in the LOSSAN Board and
TAC, the Metrolink Board and TAC, the Southern California Rail Partners Group, the Southern California Inland
Corridor Group and various stakeholder and community meetings.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Guide implementation of HSR MOU
between the California High Speed
Rail Authority and SCAG, local
transportation commissions,
Metrolink and MPOs for the
programming of $1 billion in
high-speed rail (HSR) funds to the
region's existing passenger rail
services.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Provide support and analysis for the
region's HSR planning efforts,
including participation in the
LOSSAN JPA, Metrolink Board and
TAC, the Southern California Rail
Partners Working Group, the
Southern California Inland Corridor
Group and other stakeholder and
community meetings.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Produce passenger rail element of
the RTP/SCS update.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Written reports and memoranda, and participation in the
LOSSAN JPA, Metrolink Board and TAC, the Southern
California Rail Partners Working Group, the Southern
California Inland Corridor Group and other stakeholder
and community meetings.
06/30/2017 06/30/2017
2 Passenger rail element of the RTP/SCS update,
including technical appendix
06/30/2017 06/30/2017
Page 159 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.02 REGIONAL HIGH SPEED TRANSPORT PROGRAM
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
1. During the 4th Quarter, SCAG staff worked on furthering CA HSR MOU projects with CHSRA, CalSTA, Metrolink,
and local CTCs.
2. Staff also provided continued support and analysis for the region's rail planning efforts, including participation in
the LOSSAN JPA, Metrolink Board and TAC, and Coachella Valley Rail effort.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
This project continues in FY 18 and included in OWP.
BUDGET / EXPENDITURE
406,200
114,538 85,758 0 159,312 0 0 0 0 0 0 46,592 0
0 359,608 0 0 0 0 0 0 46,592 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 339,370 85,315 88,506 85,487 80,062
Page 160 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.02 REGIONAL HIGH SPEED TRANSPORT PROGRAM
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 161 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.06 LA-SAN BERNARDINO INTER-COUNTY CONNECTIVITY STUDY
OBJECTIVE: PROJECT MANAGER:
This multi-year study will assess east-west travel needs between LA and San Bernardino Counties, and identify a
preferred, coordinated transit and rail strategy that considers the Metro Gold Line, the Metrolink San Bernardino Line,
express bus services on the I-10 carpool/express lanes, and bus rapid transit on local streets.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
65Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Provide project management,
support, and administration.
1
100Consultant12/31/201607/01/201606/30/201707/01/2016Develop Stakeholder and Public
Participation Plan.
2
100Consultant07/31/201607/01/201606/30/201707/01/2016Develop Existing Conditions Report
and Travel Market Analysis.
3
50Consultant06/30/201707/01/201601/31/201707/01/2016Develop Alternatives Analysis.4
0Consultant06/30/201701/31/201706/30/201701/31/2017Develop Technical
Recommendations.
5
0Consultant06/30/201704/01/201706/30/201704/01/2017Develop Draft and Final Report.6
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Stakeholder and Public Participation Plan 07/31/2016 12/31/2016
2 Existing Conditions Report and Travel Market Analysis 07/31/2016 07/31/2016
3 Alternatives Analysis Report 01/31/2017 06/30/2017
4 Draft and Final Report 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 50 STATUS:
Accomplishments:
1. Public open houses were held June 7th and 8th.
2. The consultant team began the second stage of alternatives analysis in the 4th quarter of FY17.
PROGRESS
IN PROGRESS
The initial screening process took longer than originally anticipated, as there was much discussion and input from
the stakeholder committees.
Issues:
Page 162 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.06 LA-SAN BERNARDINO INTER-COUNTY CONNECTIVITY STUDY
The project is on schedule and is expected to be completed in the fall of 2017.
Resolution:
Comment:
This task is also continuing in to FY 18 and is in the FY 18 budget.
BUDGET / EXPENDITURE
660,352
3,998 2,993 0 5,561 0 0 647,800 0 0 0 0 0
0 0 0 0 0 660,352 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 13,205 898 5 6,077 6,225
Consultant 238,626 44,693 50,513 61,736 81,684
CONTRACT STATUS (IF APPLICABLE)
AECOM TECHNICAL SERVICES, INC.CONTRACT EXECUTED VENDOR:STATUS:
09/22/2015 12/31/2017 16-003-C1
782,800 532,800 130,610
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 163 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.07 LA-ORANGE INTER-COUNTY CONNECTIVITY STUDY (GREEN LINE EXTENSION)
OBJECTIVE: PROJECT MANAGER:
This multi-year study will evaluate an extension of the Metro Green Line to connect to the Norwalk/Santa Fe Springs
Metrolink station and improve connectivity between Metro Rail and the Los Angeles-San Diego-San Luis Obispo
(LOSSAN) rail corridor. The study will evaluate horizontal and vertical alignment issues, ridership, costs, impacts,
station area development opportunities, and TOD opportunities along the corridor.
PHILIP LAW
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide project management,
support, and administration
1
100Consultant06/30/201708/11/201606/30/201707/01/2016Conduct stakeholder outreach2
50Consultant06/30/201708/11/201606/30/201707/01/2016Develop and analyze alternatives
(alignments, stations, ridership,
community and environmental
impacts)
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Alternatives Assessment and Ridership Forecasts 06/30/2017 03/31/2018
2 Final Report and Recommendations 06/30/2017 03/31/2018
PERCENTAGE COMPLETED: 83 STATUS:
Accomplishments:
Developed and refined draft alternatives based on input from project development team.
PROGRESS
IN PROGRESS
Minor delay in finalizing alternatives due to request by City of Norwalk staff for more time to brief their City Council
due to other City staff issues not related to this project.
Issues:
Working with City of Norwalk staff to adjust project schedule. Task is already included in FY18 OWP.
Resolution:
Page 164 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
140.00121.07 LA-ORANGE INTER-COUNTY CONNECTIVITY STUDY (GREEN LINE EXTENSION)
Comment:
Task is carried over and included in FY 18 OWP.
BUDGET / EXPENDITURE
762,552
3,998 2,993 0 5,561 0 0 750,000 0 0 0 0 0
0 0 0 0 0 762,552 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 374,714 0 0 0 374,714
Staff 681 0 0 682 -1
CONTRACT STATUS (IF APPLICABLE)
IBI GROUPCONTRACT EXECUTED VENDOR:STATUS:
08/11/2016 03/30/2018 16-039-C1
817,613 600,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 165 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.02567.01 CALEXICO TRANSIT NEEDS ASSESSMENT STUDY
OBJECTIVE: PROJECT MANAGER:
To review and evaluate existing transit services within Calexico; identify existing mobility needs and develop mobility
strategies to meet those needs.
MATTHEW GLEASON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant12/31/201607/01/201606/30/201707/01/2016Project initiation and management1
100Consultant12/31/201607/01/201606/30/201707/01/2016Conduct existing conditions analysis
and due diligence
2
100Consultant12/31/201607/01/201606/30/201707/01/2016Conduct community outreach3
100Consultant12/31/201610/31/201606/30/201707/01/2016Develop final analysis of proposed
facilities and implementation report
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Existing conditions memorandum 06/30/2017 12/31/2016
2 Outreach plan and materials 06/30/2017 12/31/2016
3 Final implementation report 06/30/2017 04/07/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Work has been completed, and the City Council has adopted the sudy.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 166 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.02567.01 CALEXICO TRANSIT NEEDS ASSESSMENT STUDY
BUDGET / EXPENDITURE
85,684
0 0 0 0 0 0 75,855 0 0 0 0 9,828
0 0 0 75,856 0 0 0 0 0 9,828
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 71,369 19,917 0 34,295 17,157
CONTRACT STATUS (IF APPLICABLE)
NELSON/NYGAARDCONTRACT EXECUTED VENDOR:STATUS:
05/12/2016 12/31/2016 16-009A-C1
81,851 71,851 10,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 167 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.02570.01 IMPERIAL VALLEY-SDSU-IMPERIAL VALLEY TRANSIT SHUTTLE ANALYSIS
OBJECTIVE: PROJECT MANAGER:
Develop recommendations for transit service to connect college campuses in the Imperial Valley.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant08/31/201607/01/201606/30/201712/01/2016Project management.1
100Consultant08/31/201607/01/201606/30/201712/01/2016Develop and analyze alternatives.2
100Consultant08/31/201607/01/201606/30/201712/01/2016Develop transit service
implementation plan.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Alternatives analysis report 06/30/2017 08/31/2016
2 Transit service implementation plan. 06/30/2017 08/31/2016
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
This project was successfully completed in August, 2016. The consultant contract expired August 31, 2016.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
This project ended in FY 17.
Page 168 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.02570.01 IMPERIAL VALLEY-SDSU-IMPERIAL VALLEY TRANSIT SHUTTLE ANALYSIS
BUDGET / EXPENDITURE
152,256
0 0 0 0 0 0 134,792 0 0 0 0 17,464
0 0 0 134,792 0 0 0 0 0 17,464
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 41,836 0 0 41,836 0
CONTRACT STATUS (IF APPLICABLE)
AECOMCONTRACT COMPLETE VENDOR:STATUS:
08/17/2015 08/31/2016 15-032-C1
259,615 41,836
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 169 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03170.01 CITY OF THOUSAND OAKS TRANSIT STUDENT INTERNSHIP
OBJECTIVE: PROJECT MANAGER:
To recruit, hire, train and employ qualified student interns.
MATTHEW GLEASON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Recruit and Hire Qualified Interns1
100Consultant06/30/201707/01/201606/30/201707/01/2016Train and Employ Qualified Interns2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Letter of Program Completion 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
This project has been completed, and the subrecipient is preparing close out materials.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 170 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03170.01 CITY OF THOUSAND OAKS TRANSIT STUDENT INTERNSHIP
BUDGET / EXPENDITURE
9,998
0 0 0 0 0 0 8,569 0 0 0 0 1,429
0 0 0 8,569 0 0 0 0 0 1,429
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 8,569 0 0 8,569 0
CONTRACT STATUS (IF APPLICABLE)
CITY OF THOUSAND OAKSCONTRACT EXECUTED VENDOR:STATUS:
05/05/2014 06/30/2017 M-003.14
30,000 12,857 9,875
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 171 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03172.02 GOLD COAST TRANSIT INTERNSHIP
OBJECTIVE: PROJECT MANAGER:
To recruit, hire, train and employ qualified student interns.
MATTHEW GLEASON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Recruit and Hire Qualified Interns1
100Consultant06/30/201707/01/201606/30/201707/01/2016Train and Employ Qualified Interns2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Letter of Program Completion 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
This project has been completed, and the subrecipient is preparing close out materials.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 172 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03172.02 GOLD COAST TRANSIT INTERNSHIP
BUDGET / EXPENDITURE
3,548
0 0 0 0 0 0 3,141 0 0 0 0 407
0 0 0 3,141 0 0 0 0 0 407
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 3,140 0 2,417 0 723
CONTRACT STATUS (IF APPLICABLE)
GOLD COAST TRANSITCONTRACT EXECUTED VENDOR:STATUS:
04/17/2014 06/30/2017 M-004-14
36,000 12,000 10,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 173 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03173.01 THOUSAND OAKS TRANSIT MASTER PLAN
OBJECTIVE: PROJECT MANAGER:
To produce a Master Plan for Thousand Oaks Transit.
MATTHEW GLEASON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201607/01/201506/30/201707/01/2016Initiate and Manage Project1
100Consultant06/30/201607/01/201506/30/201707/01/2016Engage Public and Stakeholders2
100Consultant06/30/201607/01/201506/30/201707/01/2016Prepare Final Plan3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Existing Conditions Technical Memorandum 06/30/2017 06/30/2016
2 Public Participation Plan 06/30/2017 06/30/2016
3 Draft and Final Report 06/30/2017 06/30/2016
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
This project was completed in FY 2015-16.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Task was included in the FY16/17 OWP during OWP development but work was accelerated and completed in
FY15/16 and the products already submitted.
Page 174 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03173.01 THOUSAND OAKS TRANSIT MASTER PLAN
BUDGET / EXPENDITURE
54,419
0 0 0 0 0 0 54,419 0 0 0 0 0
0 0 0 47,334 0 0 0 7,085 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 175 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03174.01 PASADENA TRANSIT DIVISION STUDENT INTERNSHIP
OBJECTIVE: PROJECT MANAGER:
To recruit, hire, train and employ qualified student interns.
MATTHEW GLEASON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201711/01/201606/30/201707/01/2016Recruit and Hire Qualified Interns1
100Consultant06/30/201711/01/201606/30/201707/01/2016Train and Employ Qualified Interns2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Letter of program completion 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Interns were hired, and multi-year internship program has ended.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 176 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03174.01 PASADENA TRANSIT DIVISION STUDENT INTERNSHIP
BUDGET / EXPENDITURE
15,186
0 0 0 0 0 0 13,444 0 0 0 0 1,742
0 0 0 13,444 0 0 0 0 0 1,742
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 9,545 0 0 4,680 4,865
CONTRACT STATUS (IF APPLICABLE)
CITY OF PASADENACONTRACT EXECUTED VENDOR:STATUS:
05/13/2014 06/30/2017 M-006-14
44,265 20,986 10,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 177 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03253.01 STATE ROUTES 57 & 60 CONFLUENCE, FEASIBILITY STUDY
OBJECTIVE: PROJECT MANAGER:
SR 57/60 improvements project was identified in Los Angeles County Metro's multi-county goods movement action
plan, and included and programmed in the Metro long range transportation plan and SCAG RTP. The purpose of the
requested funding is to secure professional and technical consultant services to prepare a feasibility study related to
improvements within the SR -60 and SR -57 confluence in the cities of Diamond Bar and Industry. The feasibility
study will evaluate alternative improvements within the confluence area to address congestion, safety, weaving,
traffic diversion, goods movement, and other related issues.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Develop and execute project
management and coordination plan.
1
100Consultant06/30/201707/01/201606/30/201707/01/2016Conduct public involvement and
outreach efforts.
2
100Consultant06/30/201707/01/201606/30/201707/01/2016Develop and evaluate technical
screening criteria/alternatives for the
project.
3
100Consultant06/30/201707/01/201606/30/201707/01/2016Evaluation of truck facilities.4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Project management plan, project schedule, and monthly
progress reports.
06/30/2017 06/30/2017
2 Project website, presentations, and summaries of
comments from public meetings.
06/30/2017 06/30/2017
3 Draft and final screening criteria technical memoranda. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Feasibility study completed.
PROGRESS
COMPLETED
Issues:
Page 178 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03253.01 STATE ROUTES 57 & 60 CONFLUENCE, FEASIBILITY STUDY
Resolution:
Comment:
BUDGET / EXPENDITURE
61,738
0 0 0 0 0 0 61,738 0 0 0 0 0
0 0 49,390 0 0 0 0 12,348 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 61,625 1,321 23,822 31,252 5,230
CONTRACT STATUS (IF APPLICABLE)
PARSONS BRINCKERHOFFCONTRACT EXECUTED VENDOR:STATUS:
01/12/2016 12/31/2016 16-012-C1
124,888 61,626 63,262
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 179 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03475.01 TRANSIT CLIMATE ADAPTATION AND RESILIENCY ASSESSMENT FOR SOUTHERN
CALIFORNIA
OBJECTIVE: PROJECT MANAGER:
This project will provide a Climate Change Adaptation and Resiliency Assessment for use by providers of public
transportation in the SCAG Region, particularly for small and mid-sized agencies with constrained financial
resources. It will do so by identifying critical assets and resources that are likely to be affected by climatic stressors
as a result of climate change and integrating climate change forecast data into local and regional transit planning
process, particularly with regard to asset management and system preservation.
MATTHEW GLEASON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
15Consultant06/30/201801/15/201706/30/201707/01/2016Initiation of project, management and
oversight
1
5Consultant06/30/201801/15/201706/30/201707/01/2016Stakeholder participation2
10Consultant06/30/201801/15/201706/30/201707/01/2016Conduct Asset inventory3
0Consultant06/30/201801/15/201706/30/201707/01/2016Application of climate data4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Interim technical memoranda discussing asset inventory
and climate data.
06/30/2017 06/30/2018
2 Draft and Final Report 06/30/2017 06/30/2018
PERCENTAGE COMPLETED: 7 STATUS:
Accomplishments:
Work on this multiyear project began during the 4th quarter.
PROGRESS
IN PROGRESS
Issues:
Resolution:
Page 180 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03475.01 TRANSIT CLIMATE ADAPTATION AND RESILIENCY ASSESSMENT FOR SOUTHERN
CALIFORNIA
Comment:
This is a multiyear project that is included in FY18 OWP.
BUDGET / EXPENDITURE
199,001
0 0 0 0 0 0 199,001 0 0 0 0 0
0 21,247 0 154,928 0 22,826 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 23,873 0 0 0 23,873
CONTRACT STATUS (IF APPLICABLE)
ICF CONSULTING, LLCCONTRACT EXECUTED VENDOR:STATUS:
05/22/2017 06/30/2018 17-017
198,919 24,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 181 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03477.01 RTA FIRST AND LAST MILE STRATEGIC MOBILITY ASSESSMENT
OBJECTIVE: PROJECT MANAGER:
The objective of this project is to establish a First and Last Mile Mobility Plan that identifies cost-effective
improvements to solve first and last mile barriers for transit riders.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant04/30/201707/01/201606/30/201707/01/2016Provide Project Management1
100Consultant04/30/201707/01/201606/30/201707/01/2016Develop Transit Facilities
Assessment and Evaluation
2
100Consultant04/30/201707/01/201606/30/201707/01/2016Develop Preliminary Strategies3
100Consultant04/30/201707/01/201606/30/201707/01/2016Provide Public Outreach and
Stakeholder Input
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Preliminary Strategies Report 05/31/2017 02/28/2017
2 Public Participation and Stakeholder Outreach Plan 06/30/2017 02/28/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Consultant completed the final report in the 4th quarter.
The project was completed in April, 2017.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 182 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03477.01 RTA FIRST AND LAST MILE STRATEGIC MOBILITY ASSESSMENT
BUDGET / EXPENDITURE
164,942
0 0 0 0 0 0 145,149 0 0 0 0 19,793
0 0 0 145,149 0 0 0 0 0 19,793
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 145,039 0 74,275 40,356 30,408
CONTRACT STATUS (IF APPLICABLE)
KTU+ACONTRACT COMPLETE VENDOR:STATUS:
12/18/2015 11/17/2017 15-041
194,875 145,039 74,096
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 183 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03480.01 AVIATION BOULEVARD MULTIMODAL CORRIDOR PLAN
OBJECTIVE: PROJECT MANAGER:
Help make the heavily traveled roadway segment a safe corridor for bicyclists and pedestrians as well as cars,
trucks, and transit vehicles. The project also includes a living streets manual for context planning purposes. The
objective is to promote active transportation plans as well as improve the regional transportation system, reduce
GHG, comply with SB 375, and implement SCAGs 2016 RTP/SCS.
STEPHEN PATCHAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
30Consultant05/31/201804/03/201706/30/201707/01/2016Public outreach1
25Consultant05/31/201804/03/201706/30/201707/01/2016Customization of living streets design
manual
2
0Consultant05/31/201804/03/201706/30/201707/01/2016Development of living streets concept
design for aviation corridor
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Customize Living Streets Design manual 06/30/2017 02/28/2018
PERCENTAGE COMPLETED: 13 STATUS:
Accomplishments:
Completed Task 1: kick off meeting and meeting notes (along with bi-weekly meeting notes/emails)
Task 2: first draft of PowerPoint presentation and posters for first outreach meeting to be held on 7/17
PROGRESS
IN PROGRESS
The Consultant and partnering cities have commenced project development by hosting a kick off meeting, collecting
data and developing a public engagement strategy.
Issues:
Work will carryover into FY 18 and is included in the OWP. Project will be completed with all deliverables provided
by the end of the contract 6/18).
Resolution:
Comment:
Page 184 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03480.01 AVIATION BOULEVARD MULTIMODAL CORRIDOR PLAN
BUDGET / EXPENDITURE
277,000
0 0 0 0 0 0 221,600 0 0 0 0 55,400
0 0 221,600 0 0 0 0 0 0 55,400
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 12,150 0 0 0 12,150
CONTRACT STATUS (IF APPLICABLE)
STANTECCONTRACT EXECUTED VENDOR:STATUS:
02/01/2017 03/31/2018 17-005-C1
221,600 221,600 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
STANTEC CONSULTINGCONTRACT EXECUTED VENDOR:STATUS:
03/14/2017 04/30/2018 17-005
218,224 200,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 185 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03481.01 PACIFIC COAST HIGHWAY PARKING MASTER PLAN
OBJECTIVE: PROJECT MANAGER:
The objective of this project is to develop the Pacific Coast Highway Parking Master Plan.
DANIEL TRAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Assess existing conditions and
prepare Draft and Final Existing
Conditions Report.
1
100Consultant06/30/201707/01/201606/30/201707/01/2016Conduct safety and mobility
assessment of shoulder & on-street
parking and prepare Draft and Final
Safety and Mobility Assessment
Report.
2
100Consultant06/30/201707/01/201606/30/201707/01/2016Develop and evaluate site specific
strategies and prepare Draft Malibu
PCH Parking Master Plan.
3
100Consultant06/30/201707/01/201606/30/201707/01/2016Circulate Draft Malibu PCH Parking
Master Plan, conduct public
workshops, incorporate public input
and prepare Final Malibu PCH
Parking Master Plan.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Monthly Meeting Notes. 06/30/2017 06/30/2017
2 Final Report on Existing Conditions. 06/30/2017 06/30/2017
3 Final Safety and Mobility Assessment Report. 06/30/2017 06/30/2017
4 Alternative Analysis Report. 06/30/2017 06/30/2017
5 Draft Malibu Pacific Coast Highway Parking Master Plan. 06/30/2017 06/30/2017
6 Final Malibu Pacific Coast Highway Parking Master Plan. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Public feedback on the draft study was sought at a Planning/Public Works Commission meeting on March 29 and at
a City Council meeting on June 12. The City Council received and filed the proposed final draft report at the June 12
PROGRESS
COMPLETED
Page 186 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03481.01 PACIFIC COAST HIGHWAY PARKING MASTER PLAN
meeting.
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
99,096
0 0 0 0 0 0 99,096 0 0 0 0 0
0 0 79,277 0 0 0 0 19,819 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 98,172 0 0 52,074 46,098
CONTRACT STATUS (IF APPLICABLE)
STANTEC CONSULTING SERVICES, INC.CONTRACT EXECUTED VENDOR:STATUS:
10/12/2015 06/30/2017 15-033-C1
283,830 98,927 184,903
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 187 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03482.01 CITY OF FONTANA - MALAGA BRIDGE COMMUNITY-BASED OPPORTUNITIES
ANALYSIS
OBJECTIVE: PROJECT MANAGER:
Develop opportunities Analysis for Historic Malaga Bridge. Evaluate preferred method for preservation, collect public
comments, and develop plan.
ALAN THOMPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant01/12/201712/01/201606/30/201712/01/2016Review literature1
100Consultant06/30/201712/01/201606/30/201712/01/2016Public Outreach2
100Consultant02/23/201712/01/201606/30/201712/01/2016Develop Opportunities Analysis3
100Consultant02/23/201712/01/201606/30/201712/01/2016Develop Funding Plan4
100Consultant06/30/201703/01/201706/30/201712/01/2016Final Report5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Draft Opportunities Analysis 06/30/2017 02/23/2017
2 Funding Plan 06/30/2017 01/12/2017
3 Final Report 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Project Completed. All products received.
PROGRESS
COMPLETED
Issues:
Resolution:
Page 188 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03482.01 CITY OF FONTANA - MALAGA BRIDGE COMMUNITY-BASED OPPORTUNITIES
ANALYSIS
Comment:
BUDGET / EXPENDITURE
221,325
0 0 0 0 0 0 210,259 0 0 0 11,066 0
0 0 177,060 0 0 0 0 0 11,066 33,199
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 134,422 0 0 39,820 94,602
CONTRACT STATUS (IF APPLICABLE)
STANTEC CONSULTING SERVICES, INC.CONTRACT COMPLETE VENDOR:STATUS:
07/05/2016 06/30/2017 16-007-Ca
154,800 154,800
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 189 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03483.01 ANAHEIM INTEGRATED TRANSPORTATION & CAPACITY BUILDING PLAN
OBJECTIVE: PROJECT MANAGER:
The Anaheim Transportation Network will conduct three stakeholder-driven planning meetings to focus on three
transportation hot-spots:
1) Anaheim Resort;
2) Platinum Triangle and ARTIC: and
3) Downtown
Participants will formulate their vision for ideal transportation operations and methodologies, identify steps needed to
realize the vision, and brainstorm solutions to the obstacles that stand in the way. The project will culminate in the
development of the 'Anaheim: Integrated Transportation and capacity Building Plan and the identification of potential
sources of funding for implementation of the Plan.
MATTHEW GLEASON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Kick-off meeting with stakeholders1
100Consultant06/30/201707/01/201606/30/201707/01/2016Outreach to public: plan and
implementation
2
100Consultant06/30/201707/01/201606/30/201707/01/2016Prepare Anaheim integrated
transportation and capacity building
plan.
3
100Consultant06/30/201711/15/201606/30/201707/01/2016Identify potential funding sources4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Public outreach plan 06/30/2017 06/30/2017
2 Final Anaheim: Integrated transportation capacity
building plan
06/30/2017 06/30/2017
3 Funding source report 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Work has concluded on this multiyear project. Service improvements have been identified, as well as governance
reforms. A financial plan has been developed as well.
PROGRESS
COMPLETED
Page 190 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03483.01 ANAHEIM INTEGRATED TRANSPORTATION & CAPACITY BUILDING PLAN
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
118,059
0 0 0 0 0 0 58,336 0 0 0 0 59,723
0 0 0 58,336 0 0 0 0 0 59,723
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 58,337 0 0 0 58,337
CONTRACT STATUS (IF APPLICABLE)
ANAHEIM TRANSPORTATION NETWORKCONTRACT EXECUTED VENDOR:STATUS:
05/05/2015 06/30/2017 M-018-015
160,000 60,000 100,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 191 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03824.01 ACTIVETRANS DATA PLANNING PROJECT
OBJECTIVE: PROJECT MANAGER:
The San Gabriel Valley Active Transportation Data Planning Project will address a major gap in the realm of active
transportation planning in the San Gabriel Valley, the lack of localized bicycle and pedestrian planning data to inform
effective project development, design and construction. The project will utilize manual bicycle and pedestrian counts,
resident surveys, community street audits (walking and biking), and bicycle parking audits to gather data for streets
with planned/proposed bike infrastructure and/or recently installed infrastructure (e.g., Rosemead Blvd. cycletrack,
City of Temple City), needed to facilitate and measure the efficacy of future active transit investments.
ALAN THOMPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Initiate Project1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Collection of Data, Tool and Plan2
75Staff/Consultant01/02/201807/01/201606/30/201707/01/2016Collect Data3
25Staff/Consultant06/30/201803/01/201706/30/201707/01/2016Analyze Data, and Evaluation4
25Staff/Consultant06/30/201803/01/201706/30/201707/01/2016Work on Active Transportation
Planning Data Report and Outreach
5
25Staff/Consultant06/30/201803/01/201706/30/201707/01/2016Work on Fiscal Management6
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Active Transportation Surveys 06/30/2017 06/30/2017
2 Safety summary by city. 06/30/2017 03/30/2018
3 Training materials. 06/30/2017 06/30/2017
4 Bicycle parking audit map. 06/30/2017 03/30/2018
5 Count data. 06/30/2017 06/30/2017
6 Preliminary/final report 06/30/2017 06/30/2018
Page 192 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03824.01 ACTIVETRANS DATA PLANNING PROJECT
PERCENTAGE COMPLETED: 37 STATUS:
Accomplishments:
Completed 100th bicycle count
PROGRESS
IN PROGRESS
Parking audits and data evaluation could not be complete until after bicycle counts are complete
Issues:
BikeSGV completed their 100th bicycle count, allowing preliminary analysis to be started. Project will continue into
FY 17-18 and is in FY17-18 OWP.
Resolution:
Comment:
San Gabriel Valley Bicycle Coalition (BikeSGV) is performing data collection under MOU M-003-16.
BUDGET / EXPENDITURE
164,621
1,555 1,164 0 2,163 0 0 136,943 0 0 5,054 0 17,742
0 0 0 145,739 0 1,140 0 0 0 17,742
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 4,401 4,383 27 -6 -3
Consultant 70,496 0 20,213 5,291 44,992
Page 193 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03824.01 ACTIVETRANS DATA PLANNING PROJECT
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 194 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03829.01 ACTIVE STREETS LA - PEDESTRIAN AND BICYCLE-FRIENDLY STREETS FOR SOUTH
LOS ANGELES
OBJECTIVE: PROJECT MANAGER:
In partnership with LADOT, LACBC and TRUST South LA will utilize the proven Active Streets LA process to solicit
community input and develop concept plans for bicycle and pedestrian safety improvements consistent with the
City’s 2010 Bicycle Plan and draft Mobility Plan 2035’s neighborhood network.
STEPHEN PATCHAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
85Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Project Management1
85Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop Toolkit and Outreach Guide2
85Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Engage Public3
90Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Evaluation and Data4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Concept plans for bicycle and pedestrian safety
improvements.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 85 STATUS:
Accomplishments:
TRUST and LACBC met with LADOT at the end of April to debrief Cycle 4 event 1 (on 4/15) and prepare for event 2
(which occurred 5/20).
Roles & Script: Partners reviewed maps and audit routes, as well as messaging around the enlarged ASLA toolkit.
Partners agreed to create an enlarged ASLA poster that included a subset of ASLA toolkit treatments, which could
be hung up at events in order to expose participants to the treatments.
LACBC worked closely with LADOT and TRUST to coordinate maps, surveys, and other audit materials in
preparation for the 5/20 event. A walk and bike audit checklist in both English and Spanish was developed to help
residents participating think about some elements they may encounter while on the street. Additionally, a map with
pictures of key neighborhood landmarks was developed.
PROGRESS
IN PROGRESS
Page 195 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03829.01 ACTIVE STREETS LA - PEDESTRIAN AND BICYCLE-FRIENDLY STREETS FOR SOUTH
LOS ANGELES
LACBC and South LA Trust are implementing the final outreach and events of the contract. The final products
including the Toolkit and Outreach guide are being developed.
Issues:
Budget will carryover into FY 18 to fund completion of project including Toolkit and Outreach Guide by the end of the
contract (9/17). Budget is included in FY18 OWP.
Resolution:
Comment:
BUDGET / EXPENDITURE
423,669
4,666 3,494 0 6,490 0 0 353,842 0 0 9,335 0 45,842
0 0 0 375,074 0 2,753 0 0 0 45,842
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 4,401 4,383 27 -6 -3
Consultant 204,302 0 0 5,779 198,523
CONTRACT STATUS (IF APPLICABLE)
LOS ANGELES COUNTY BICYCLE COALITIOCONTRACT EXECUTED VENDOR:STATUS:
01/01/2016 06/30/2018 M-002-16
455,665
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 196 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03830.01 CUSTOMER BASED RIDESHARING AND INTERCONNECTIVITY STUDY
OBJECTIVE: PROJECT MANAGER:
To develop a customer-focused, multi-modal effort to see San Bernardino County’s mobility components as a more
integrated, interconnected system and to improve the information disseminated about the system. The study will
include an analysis of options for improved fare media compatibility across modes.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
40Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Conduct Project Initiation.1
100Staff/Consultant06/30/201707/01/201612/31/201607/01/2016Conduct Outreach.2
60Staff/Consultant06/30/201701/01/201705/31/201701/01/2017Identify Strategies to Promote
Alternative Modes of Transportation.
3
0Staff/Consultant06/30/201706/01/201706/30/201706/01/2017Development of an Action Plan for
Improvements to Ridesharing and
Transit Interconnectivity.
4
50Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Conduct Fiscal Management.5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Outreach Finding and Conclusions Technical
Memorandum
09/30/2016 06/30/2017
2 Alternative Mode Strategies Technical Memorandum 12/31/2016 06/30/2017
3 Final Report and Action Plan 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 50 STATUS:
Accomplishments:
Focus groups of commuters were held in June, 2017. In addition, the consultant team continued to research and
refine ridesharing and inter-connectivity strategies; and a technology workshop was held in the 4th Qtr.
PROGRESS
IN PROGRESS
This project was delayed a bit by difficulty in getting large employers to commit to surveying their employees as they
had just gone through the AQMD employee survey.
Issues:
Page 197 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03830.01 CUSTOMER BASED RIDESHARING AND INTERCONNECTIVITY STUDY
Progress was made and a good survey size resulted. Also, AQMD furnished the consultant team with data from
their survey.
Resolution:
Comment:
This task is also continuing in to FY 18 and is in the FY 18 budget.
BUDGET / EXPENDITURE
433,440
4,148 3,106 0 5,770 0 0 383,730 0 0 7,784 0 28,902
0 0 0 354,185 0 2,387 0 47,966 0 28,902
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 226,711 9,810 72,269 58,571 86,061
CONTRACT STATUS (IF APPLICABLE)
HEATHER MENNIGER DBA AMMA TRANSIT CONTRACT EXECUTED VENDOR:STATUS:
05/24/2016 06/30/2018 16-013
357,995 227,996 16,270
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 198 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03831.01 HUNTINGTON DRIVE SAFE STREETS CORRIDOR PLAN
OBJECTIVE: PROJECT MANAGER:
The objective of this project is to develop the Huntington Drive Safe Streets Corridor Plan.
COURTNEY AGUIRRE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Coordinate Project1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Involve Public Participation and
Stakeholder Outreach
2
40Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Conduct Draft and Final Plan3
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Reporting and Invoicing
Administration
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Public Outreach Report. Documents all public outreach
related to the development of the plan.
06/30/2017 06/30/2017
2 Administrative Draft Plan. Draft plan that includes
recommendations on policies/programs/projects to
implement to improve the safety and efficiency of the
corridor.
06/30/2017 09/30/2017
PERCENTAGE COMPLETED: 88 STATUS:
Accomplishments:
SCAG participates in recurring monthly meetings with the consultant, Caltrans, and the City of San Marino. We have
finalized the existing conditions report. We also conducted community tours of the corridor to assess issues in April
and the consultant produced a summary outreach report. The consultant has conducted outreach at multiple
schools (assemblies and bike/ped rodeos).
PROGRESS
IN PROGRESS
The consultant has completed the existing conditions component of the draft plan. The corridor's concepts are still
being developed. A full draft plan will be completed by the fall.
Issues:
The consultant requires additional time to prepare the draft report. The project is still anticipated to be completed well
before the grant funds expire.
Resolution:
Page 199 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03831.01 HUNTINGTON DRIVE SAFE STREETS CORRIDOR PLAN
Comment:
Projected included in FY 18 OWP.
BUDGET / EXPENDITURE
151,020
1,555 1,164 0 2,163 0 0 126,155 0 0 3,639 0 16,344
0 0 0 133,699 0 977 0 0 0 16,344
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 89,660 0 27,142 4,277 58,241
CONTRACT STATUS (IF APPLICABLE)
KOA CORP.CONTRACT EXECUTED VENDOR:STATUS:
03/23/2016 03/23/2017 16-014
142,919 100,571 17,205
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 200 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03832.01 LOS ANGELES RIVER BIKEWAY FEASIBILITY STUDY
OBJECTIVE: PROJECT MANAGER:
To assess current conditions, conduct engineering studies, and present the best options for extending the Bikeway.
ALAN THOMPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
65Staff/Consultant09/30/201709/01/201606/30/201707/01/2016Conduct Project Planning and
Coordination
1
75Staff/Consultant09/30/201710/03/201606/30/201707/01/2016Involve Public Outreach and
Participation
2
90Staff/Consultant09/30/201709/01/201606/30/201707/01/2016Preparation of Feasibility Study3
0Staff/Consultant09/30/201706/30/201706/30/201707/01/2016Adoption of Feasibility Study4
70Staff/Consultant09/30/201707/01/201606/30/201707/01/2016Conduct Project Management and
Administration
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Opportunities and Constraints Analysis 06/30/2017 10/31/2017
2 Alternatives Analysis 06/30/2017 10/31/2017
3 Cost Estimate/Comparisons Analysis 06/30/2017 10/31/2017
4 Funding Plan 06/30/2017 10/31/2017
5 Recommendations and Implementation 06/30/2017 10/31/2017
6 Final Report 06/30/2017 10/31/2017
PERCENTAGE COMPLETED: 73 STATUS:
Accomplishments:
Received Draft Feasibility study and Evaluation Method.
Received Final Outreach Plan.
PROGRESS
IN PROGRESS
City requesting new city manager review draft reports prior to finalizing. Will not come on board until August.
Issues:
Page 201 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.03832.01 LOS ANGELES RIVER BIKEWAY FEASIBILITY STUDY
City staff and SCAG will review draft documents and make recommendations prior to City Manager assuming
duties.
Resolution:
Comment:
Project on schedule to be completed November 2017. Project is included in the FY17-18 OWP.
BUDGET / EXPENDITURE
268,698
2,636 1,974 0 3,667 0 0 256,804 0 0 3,617 0 0
0 0 0 237,878 0 1,365 0 29,455 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 89,318 0 6,120 27,827 55,371
CONTRACT STATUS (IF APPLICABLE)
ALTA PLANNINGCONTRACT EXECUTED VENDOR:STATUS:
08/10/2016 01/31/2018 16-008
253,207 222,208
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 202 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.04424.01 I 105 CORRIDOR STUDY
OBJECTIVE: PROJECT MANAGER:
This multi-year study will assess current and future performance along the I-105 corridor from a multi-modal
perspective and will develop and integrate a series of sustainable strategies that will encompass Complete Streets
concepts, Smart Mobility Framework (SMF), managed lanes, and operational strategies.
DANIEL TRAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
0Staff/Consultant06/30/201706/01/201706/30/201706/01/2017Provide project management,
support, and administration
1
0Staff/Consultant06/30/201706/01/201706/30/201706/01/2017Develop Stakeholder and Public
Engagement Strategy.
2
0Staff/Consultant06/30/201706/01/201706/30/201706/01/2017Develop Evaluation Framework3
0Staff/Consultant06/30/201706/01/201706/30/201706/01/2017Develop Current Conditions
Assessment
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Stakeholder and Public Engagement Strategy Tech
Memo
03/01/2017
PERCENTAGE COMPLETED: 0 STATUS:
Accomplishments:
During this quarter, staff have completed the RFP process and have selected a consultant to conduct the I-105
CSS. The project kick-off meeting is scheduled to take place next quarter.
PROGRESS
IN PROGRESS
During the 4th Quarter, SCAG initiated the RFP and selected a consultant; however, work has not officially started
as of June 28, 2017. We anticipate to have our kickoff meeting in July 2017.
Issues:
We anticipate to have a consultant to begin work by the beginning of FY17/18.
Resolution:
Comment:
The consultant will begin work in July 2017, FY17/18. Task included in FY 18 OWP.
Page 203 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.04424.01 I 105 CORRIDOR STUDY
BUDGET / EXPENDITURE
625,000
0 0 0 0 0 0 625,000 0 0 0 0 0
0 0 500,000 0 0 125,000 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 204 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.04425.01 CITY OF SANTA ANA ACTIVE TRANSPORTATION PLAN
OBJECTIVE: PROJECT MANAGER:
The proposed plan will prioritize a bikeway network and pedestrian focus areas based on criteria (for example
connectivity or safety). The plan would then analyze costs and alternatives of the top priority projects.
STEPHEN PATCHAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
0Staff/Consultant05/01/201905/01/201706/30/201710/15/2016Project Management1
0Consultant07/30/201810/01/201706/30/201704/15/2017Data Collection and Analysis2
0Consultant08/30/201802/01/201806/30/201706/15/2017Community Outreach3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Documentation of pertinent information including
photographs, mapping, schematics, field notes, and
other required information
08/15/2018 05/31/2018
2 Memorandum Summarizing community feedback
received and any photographs taken
09/15/2018 08/30/2018
3 Active transportation Feasibility and Implementation
Plan.
09/15/2018 05/30/2019
PERCENTAGE COMPLETED: 0 STATUS:
Accomplishments:
Consultant selected. Contract will go to September Regional Council for approval. Work anticipated to commence
in September.
PROGRESS
IN PROGRESS
Consultant will commence work in September 2017.
Issues:
Task has been carried over and included in FY 18 OWP.
Resolution:
Page 205 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
145.04425.01 CITY OF SANTA ANA ACTIVE TRANSPORTATION PLAN
Comment:
Task included in FY 18 OWP.
BUDGET / EXPENDITURE
507,000
0 0 0 0 0 0 451,028 0 0 0 0 55,973
0 0 0 448,847 0 2,180 0 0 0 55,973
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 206 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04093.01 INTEGRATED CO-BENEFITS/SPECIAL PROGRAMS
OBJECTIVE: PROJECT MANAGER:
Bring new voices to the table and promote cross-sectoral engagement on key planning/policy issues. Advance
planning practices to reflect changing nature of society as a result of demographic and technological changes. Test
new methods of engagement and dialogue to find solutions to challenging policy/planning issues. Attract new
partners and resources to promote RTP/SCS implementation
SARAH JEPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Develop and hold workshops on the
implications and benefits of
coordinated land-use and
transportation planning for a
wide-range of sustainability issues-
-water, energy, public health, waste,
and resiliency—in order to promote
implementation of the RTP/SCS.
Explore new forms of engagement
beyond “traditional” workshops
including mobile
workshops/demonstration projects
and other strategies enabled by
technology including
competitions/challenges,
hackathons, etc…
1
100Staff06/30/201701/01/201706/30/201707/01/2016Leverage workshops to develop
partnerships and coordinated
projects with water, public health,
and other agencies to advance
common objectives. Example:
Green Streets, Active Transportation,
Clean-Energy Vehicles, etc….
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Workshops (2). 06/30/2017 06/30/2017
2 Policy Committee Reports 06/30/2017 06/30/2017
Page 207 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04093.01 INTEGRATED CO-BENEFITS/SPECIAL PROGRAMS
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Provided a series of reports to SCAG’s Energy and Environment Committee on water and energy issues related to
land-use and/or transportation planning to facilitate and promote more integrated planning.
Partnering with other departments to host a Story Maps Challenge for university students as part of the General
Assembly. The challenge opens up a considerable portion of SCAG’s data on ArcGIS Online for students to utilize
and analyze as they see fit, and then create a story using that data and the ESRI Story Map platform. This exercise
facilitates cross-sectoral analysis, engages new partners and fosters discussion of key demographic, land-use and
transportation trends and issues facing the region for consideration in RTP/SCS development.
Hosted Water Roundtable on April 26 for local leaders and land-use, transportation and water to discuss
opportunities for coordination and collaboration .
PROGRESS
COMPLETED
Direction for workshop focus delayed as a result of other agency priorities.
Issues:
For Step 1:Anticipate work will increase in third quarter once clear direction is provided on approach for workshops.
Work on Step 2 is dependent on progress in Step 1 and will begin in March 2017.
Received direction to pursue StoryMap Challenge and a Water Roundtable as the key focus areas for the
workshops. Work to plan and implement these efforts is on track.
Resolution:
Comment:
BUDGET / EXPENDITURE
163,631
46,140 34,546 0 64,176 0 0 0 0 0 0 18,769 0
144,862 0 0 0 0 0 0 0 18,769 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
Page 208 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04093.01 INTEGRATED CO-BENEFITS/SPECIAL PROGRAMS
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 130,250 21,057 28,287 24,929 55,977
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 209 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04093.02 HQTA/SUSTAINABLE COMMUNITIES INITIATIVE
OBJECTIVE: PROJECT MANAGER:
The SCAG region, home to about 18.3 million people in 2012, currently features 5.9 million households and 7.4
million jobs. By 2040, the 2016 RTP/SCS projects that these figures will increase by 3.8 million people, with nearly
1.5 million more homes and 2.4 million more jobs. The 2016 RTP/SCS projects and anticipates an overall land use
pattern that reinforces the trend of focusing new housing and employment in the region’s High Quality Transit Areas
(HQTAs). Consensus will need to be reached to ensure these patterns can be achieved, will reinforce VMT and GHG
reductions, and will support transit oriented development. A pilot project approach will be developed to identify and
analyze issues that relate to integration of regional transportation and community goals and objectives in land use to
better determine context-sensitive approaches for supporting growth in HQTAs in a variety of regional settings.
High-Quality Transit Areas (HQTAs) are generally walkable transit villages or corridors, consistent with the 2016
RTP/SCS and are within one half-mile of a well-serviced transit stop or a transit corridor with 15-minute or less
service frequency during peak commute hours.
An HQTA is based on the language in SB 375 which defines:
• Major Transit Stop - A site containing an existing rail transit station, a ferry terminal served by either a bus or rail
transit service, or the intersection of two or more major bus routes with a frequency of service interval of 15 minutes
or less during the morning and afternoon peak commute periods (CA Public Resource Code Section 21064.3).
• HQTC High-Quality Transit Corridor – A corridor with fixed route bus service with service intervals no longer than
15 minutes during peak commute hours.
GRIEG ASHER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
35Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Establish working group to identify
candidate HQTAs
1
25Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop maps that express key
policies of the 2016 RTP/SCS and
local plans
2
25Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Manage consultant3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Project maps 06/30/2017 06/30/2017
2 Outreach records (agenda and materials) 06/30/2017 06/30/2017
3 Implementation records showing advancement of 2016
RTP/SCS land use strategies and transportation
investments
06/30/2017 06/30/2017
Page 210 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04093.02 HQTA/SUSTAINABLE COMMUNITIES INITIATIVE
PERCENTAGE COMPLETED: 28 STATUS:
Accomplishments:
PROGRESS
IN PROGRESS
Waited for Budget Amendment 2 to be approved.
RFP prepared and released in January 2017.
Start date was June 2017.
Already included in FY 18 and will be completed in FY 18.
Issues:
RFP released in January 2017.
4 firms interviewed.
One firm selected. Contract negotiations completed.
NTP June 2017.
Already included in FY 18 and will be completed in FY 18.
Resolution:
Comment:
BUDGET / EXPENDITURE
398,247
41,802 31,298 0 58,143 0 0 250,000 0 0 0 17,004 0
131,243 199,192 0 0 0 50,808 0 0 17,004 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 5,149 0 0 0 5,149
Staff 135,655 14,552 42,165 79,037 -99
Page 211 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04093.02 HQTA/SUSTAINABLE COMMUNITIES INITIATIVE
CONTRACT STATUS (IF APPLICABLE)
GRUEN ASSOCIATESCONTRACT EXECUTED VENDOR:STATUS:
06/14/2017 06/30/2018 17-024-C1
261,898 10,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 212 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04094.01 INTEGRATED SUSTAINABILITY PROGRAM
OBJECTIVE: PROJECT MANAGER:
Primary objective is collaborative assistance to member local governments and communities for coordinating
sustainable transportation, land use and regional policies and issues in local planning. The task will implement the
SCAG Sustainability Planning Grant program to support and implement the policies of the 2016 RTP/SCS. Built on
the Compass Blueprint program's past success of providing an array of tools and resources to local governments to
develop policies, plans, and development projects that implement the 2012 Regional Transportation Plan and
Sustainable Communities Strategy (RTP/SCS). Work will also be consistent with Caltrans' Smart Mobility
Framework and Complete Streets program (Deputy Directive 64-R1) and FHWA Planning Emphasis Areas (PEAs.)
Emphases will include local and regional planning for greenhouse gas reductions, locally-applied "Green Region
Initiative" strategies, public health impacts related to transportation activities and assistance in General Plan updates.
Local-regional partnerships that integrate land use planning and transportation investment decision-making are
critical to improving mobility, accessibility and air-quality in Southern California. Sustainability Planning Grant projects
focused on key opportunity sites as identified in the RTP/SCS, will provide assistance to local jurisdictions for
comprehensive planning solutions such as context-sensitive design, multi-modal transportation planning, infill and
transit-oriented development projects community outreach and consensus building, fiscal and economic impact
analysis, green house gas (GHG) reduction standards, innovative financing and public private partnerships.
MARCO ANDERSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
90Staff06/30/201707/01/201606/30/201707/01/2016Conduct outreach and develop
partnerships for Sustainability
Planning Grant projects and other
technical assistance.
1
45Staff/Consultant06/30/201701/01/201706/30/201707/01/2016Complete local Sustainability
Planning Grant projects that
showcase the local and regional
benefits of sustainable planning and
support the 2012 RTP/SCS and other
regional policies.
2
50Staff06/30/201701/01/201706/30/201707/01/2016Manage and coordinate consultant
work including preparation of scope
of work monitoring project budget
and schedule
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Updated program website(s), presentations and other
documentation of outreach activities
06/30/2017
2 Project materials for Sustainability Planning Grant
projects.
06/30/2017
Page 213 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04094.01 INTEGRATED SUSTAINABILITY PROGRAM
PERCENTAGE COMPLETED: 61 STATUS:
Accomplishments:
Staff has developed a consolidated Sustainability Planning Grants Program (SPG) Call for Proposals. The 2016
SPG Call for Proposals updates the program application and guidelines to promote implementation of the goals,
objectives and strategies of the recently adopted 2016 RTP/SCS, and incorporates the planning components of
SCAG’s 2017 Regional Active Transportation Program (ATP). The call for projects was released on September 29th.
SCAG received a total of 139 project proposals requesting approximately $35.5 million dollars by the November 18,
2016 deadline. Staff completed a ranking of proposals, and on February 2, 2017 the Regional Council approved
fifty-four (54) top ranked projects for funding totaling approximately $9.6 million dollars.
Already included in FY 18 and will be completed in FY 18.
PROGRESS
IN PROGRESS
Sustainability projects have not been started. Steps nos. 2 & 3 should have had start dates that reflect the issuance
of the call during the first half of the fiscal year.
Issues:
Call for proposals was developed internally. Applications received and going to RC for approval in Feb 2017.
Project RFP releases will be delayed until Spring 2017.
Already included in FY 18 and will be completed in FY 18.
Resolution:
Comment:
BUDGET / EXPENDITURE
2,252,261
67,946 50,873 0 94,507 0 10,000 2,000,000 0 0 0 28,935 0
1,108,626 0 0 0 0 1,114,700 0 0 28,935 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
Page 214 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04094.01 INTEGRATED SUSTAINABILITY PROGRAM
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 197,008 49,612 48,900 32,315 66,181
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 215 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04094.02 GREENHOUSE GAS REDUCTION FUND (GGRF) TECHNICAL ASSISTANCE
OBJECTIVE: PROJECT MANAGER:
Help ensure state greenhouse gas reduction fund monies are available to Southern California region jurisdictions
and stakeholders, and that funded projects support goals of the RTP/SCS as well as state and federal transportation
planning priorities. Support member cities and disadvantaged communities, in their efforts to mitigate climate
change through the use of Greenhouse Gas Reduction Fund Monies for integrated transportation and land use
projects. Participate in proposal review in collaboration with state agencies.
JASON GREENSPAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
85Staff06/30/201807/01/201606/30/201707/01/2016Assist in the consultation phase of
project development
1
75Staff06/30/201807/01/201606/30/201707/01/2016Engage stakeholders to ensure
competiveness of projects
2
75Staff06/30/201807/01/201606/30/201707/01/2016Coordinate GGRF applications of
member cities.
3
75Staff06/30/201807/01/201606/30/201707/01/2016Develop support letter and other
materials where appropriate
4
100Staff06/30/201807/01/201606/30/201707/01/2016Participate in proposal review in
collaboration with state agencies.
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Support letters for member cities submitting GGRF
grant/loan applications
06/30/2017 06/30/2018
2 Records 06/30/2017 06/30/2018
3 Report summarizing applications of all member cities
that applied for GGRF monies and their status.
06/30/2017 06/30/2018
PERCENTAGE COMPLETED: 82 STATUS:
Accomplishments:
Amendment #4 for Contract 16-010A approved.
PROGRESS
IN PROGRESS
Due to a delay with the State releasing Round 3 of AHSC, this work had to be postponed until 2018. This budget
was included in Amend. 4 and will be completed by June 30, 2018.
Issues:
Page 216 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04094.02 GREENHOUSE GAS REDUCTION FUND (GGRF) TECHNICAL ASSISTANCE
Amendment #4 extended contract to 6/30/2018.
Resolution:
Comment:
Amendment #4 extended contract to 6/30/2018. This project has been included in FY 18 OWP.
BUDGET / EXPENDITURE
925,853
215,586 161,415 0 299,861 0 10,000 150,000 0 0 0 88,991 0
686,862 132,795 0 0 0 17,205 0 0 88,991 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 490,929 99,067 134,694 108,459 148,709
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 217 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04095.01 RTP/SCS PERFORMANCE MONITORING
OBJECTIVE: PROJECT MANAGER:
Develop a robust program for ongoing monitoring of the implementation of regional Sustainable Communities
Strategy. Pilot applications of monitoring tools. Support the Highway Performance Monitoring System (HPMS)
Program in coordination with Caltrans.
PING CHANG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop a comprehensive monitoring
framework and systems
1
100Staff06/30/201707/01/201606/30/201707/01/2016Pilot applications of CALOTS for
monitoring
2
100Consultant06/30/201707/01/201606/30/201707/01/2016Continue to enhance the CALOTS
tool for monitoring
3
100Consultant06/30/201707/01/201606/30/201707/01/2016Maintain the CALOTS database4
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor and participate in MAP-21
performance measures rule-making
and implementation
5
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor implementation of the
Sustainable Communities Strategies
6
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate the HPMS data collection
from local
jurisdictions through distributing data
files, providing
guidance and technical assistance
as needed
7
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate with Caltrans in providing
guidance to local jurisdictions in
support of the annual HPMS data
collection effort.
8
100Staff06/30/201707/01/201606/30/201707/01/2016Review and evaluate the
Transportation Corridor Agency
(TCA) and Orange County
Transportation Agency (OCTA)
Average Vehicle Occupancy (AVO)
Program Monitoring Reports
9
Page 218 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04095.01 RTP/SCS PERFORMANCE MONITORING
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 consultant reports related to comprehensive monitoring
framework and systems
06/30/2017 06/30/2017
2 Summary of the jurisdictional HPMS guidance process. 06/30/2017 06/30/2017
3 Summary of the HPMS data collection 06/30/2017 06/30/2017
4 TCA and OCTA AVO Program Monitoring Reports 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Work continued by SCAG staff on the development of a Comprehensive Regional Performance Monitoring Program
for the SCAG region. SCAG staff actively participated in the rule-making process in support of MAP-21 performance
measures, including coordinating with local implementation agencies. HPMS traffic and pavement data collection
was coordinated with local jurisdictions & with Caltrans. Annual Average Vehicle Occupancy (AVO) reports were
completed for the SR-91 Express Lanes and the Eastern and San Joaquin Hills Transportation Corridors in Orange
County.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 219 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04095.01 RTP/SCS PERFORMANCE MONITORING
BUDGET / EXPENDITURE
549,786
118,369 88,626 0 164,641 0 0 130,000 0 0 0 48,150 0
371,636 115,089 0 0 0 14,911 0 0 48,150 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 185,953 30,425 37,732 34,089 83,707
CONTRACT STATUS (IF APPLICABLE)
UCLA LEWIS CENTERCONTRACT EXECUTED VENDOR:STATUS:
07/01/2014 06/30/2019 M-003-13
50,000 10,000 10,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 220 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04095.02 MOBILITY INNOVATIONS/TECHNOLOGY STUDY
OBJECTIVE: PROJECT MANAGER:
Determine transportation technology penetration in the region and/or technology, i.e. ridesharing, carsharing
modeling assumptions and methodology
MARCO ANDERSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage consultant1
100Staff/Consultant06/30/201701/01/201706/30/201707/01/2016Establish staff working group to
identify opportunities and issues
relating to new mobility innovations
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop modeling assumptions and
methodology
3
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Coordinate with other MPOs on
comparable assumptions and
methodologies
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Status report on methodology development and
deployment
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
SCAG has developed a scope of work to address data gathering, modeling, and planning issues surrounding
shared, connected, and automated vehicles entering the transportation system.
SCAG has worked with MTC, SANDAG, and SACOG to refine the RFP, and develop a multi-MPO MOU to facilitate
transfer of funds.
$25,000 needs to be transferred to MTC by June 30, 2017.
The RFP SOW, inter agency MOU, have been finalized, still waiting for MTC to issue, and all MPOS to execute the
MOU and transfer letters. MOU completed and signed. Already included in FY 18 and will be completed in FY 18.
MOU Completed, and Funding transferred to MTC.
PROGRESS
COMPLETED
MOU needs to be executed.
Issues:
Page 221 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04095.02 MOBILITY INNOVATIONS/TECHNOLOGY STUDY
MOU executed. Already included in FY 18 and will be completed in FY 18.
Resolution:
Comment:
BUDGET / EXPENDITURE
117,939
21,639 16,202 0 30,098 0 0 50,000 0 0 0 0 0
0 0 0 0 0 117,939 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 222 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04095.03 SCAG REGIONAL ACTIVE TRANSPORTATION DATA PARTNERSHIP PLATFORM
OBJECTIVE: PROJECT MANAGER:
This task supports expanding performance monitoring and modeling efforts by developing a sidewalk inventory,
Bike/Street geodata integration and Phase 3 of the Bicycle Database Clearinghouse in collaboration with cities,
counties, subregions and state partners.
This task anticipates further steps and products in future years
RYE BAERG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct outreach activities to the
CTCs and local jurisdictions to
collect input into the development of
tools used for bicycle and pedestrian
data collection
1
55Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop Sidewalk Inventory
Methodology to help local
jurisdictions and CTCs to develop
pedestrian networks that can inform
the development of SCAG modeling
processes
3
50Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Integrate bicycle network geodata
with SCAG Street Network geodata
to inform modeling outcomes and
provide data to local jurisdictions
4
100Staff06/30/201707/01/201606/30/201707/01/2016Work with modeling department to
calibrate and validate SCAG AT
models with the latest data, conduct
peer reviews, and implement the
models.
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
2 Sidewalk Inventory Methodology and Feasibility Report 06/30/2017 12/31/2017
3 Updated Street Network Geodata 06/30/2017 06/30/2017
Page 223 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04095.03 SCAG REGIONAL ACTIVE TRANSPORTATION DATA PARTNERSHIP PLATFORM
PERCENTAGE COMPLETED: 85 STATUS:
Accomplishments:
Outreach to local, state and regional partners completed. Review of C-PHAM model completed. ATDB Draft
Strategic Plan completed. ERD completed, database website and mobile app design completed. SCAG has
identified technology platforms suitable to host the sidewalk inventory tool.
PROGRESS
IN PROGRESS
Sidewalk methodology preliminary scope of work is complete but additional research will be needed to determine
variables that have coefficients that can be modeled.
Geodata for LA County was completed but task required more hours than initially estimated.
Issues:
SCAG will continue to research possible variables for use in partnership with UCLA and regional stakeholders.
Modeling tasks are ongoing into FY 17-18 until adoption of 2020 RTP/SCS.
SCAG will allocate additional resources to align remaining 5 counties Geo Data to the street network.
Resolution:
Comment:
Project included in FY18 OWP.
BUDGET / EXPENDITURE
376,895
10,085 7,551 0 14,027 0 1,000 340,000 0 0 0 4,232 0
32,663 212,472 0 0 0 27,528 0 0 4,232 100,000
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 40,349 8,931 10,269 11,226 9,923
Consultant 320,877 19,084 35,655 66,051 200,087
Page 224 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04095.03 SCAG REGIONAL ACTIVE TRANSPORTATION DATA PARTNERSHIP PLATFORM
CONTRACT STATUS (IF APPLICABLE)
CAMBRIDGE SYSTEMATICSCONTRACT EXECUTED VENDOR:STATUS:
05/03/2016 05/03/2019 15-031-C1
410,733 140,000 59,804
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 225 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.01 RTP/SCS LAND USE POLICY AND PROGRAM DEVELOPMENT
OBJECTIVE: PROJECT MANAGER:
This task will facilitate the implementation of the 2016 RTP/SCS land use and transportation policies. Work will focus
on collaboration among staff, consultant teams, other agencies and local governments to:
• Comply with state planning mandates, particularly coordinating regional and local transportation planning with state
housing law;
• Develop coordinated transportation and land use plans, policies and projects for the 2016 RTP/SCS and that are
consistent with, Caltrans' Smart Mobility Framework and Complete Streets program (Deputy Directive 64-R1) and
FHWA Planning Emphasis Areas (PEAs) as well as other federal, state and regional transportation plans and
policies;
• Promote compact, walkable, and transit-oriented development patterns where feasible. This has been shown to be
an effective strategy in reducing vehicle miles traveled and greenhouse gas emissions in the long-tern. This also
focuses on collaboration amongst agencies and plans to a greater degree.
• Complete policy analysis and scenario planning for the 2016 RTP/SCS.
Coordination tasks include:
- Conduct training for SCAG staff on use of Scenario Planning Model (Consultant)
- Deployment of Scenario Planning Model (Consultant)
- Participating in the outreach portion of 2016 RTP/SCS development
INDIA BROOKOVER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
12Staff06/30/201707/01/201606/30/201707/01/2016Coordinate with other departments
within SCAG on the various
components of 2016 RTP/SCS
development
1
12Staff06/30/201707/01/201606/30/201707/01/2016Outreach to potential partners via
Regional Affairs Department to local
jurisdictions to identify jurisdictions
that desire to implement RTP/SCS
9
0Staff06/30/201707/01/201606/30/201707/01/2016Establish work plan with local
jurisdiction for procurement process
10
0Staff06/30/201707/01/201606/30/201707/01/2016Administer contract and project to
ensure needs of both local
jurisdiction and project team are met
11
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Documentation and review of requests from local
jurisdictions' proposal to implement RTP/SCS
06/30/2017
4 Final report 06/30/2017
Page 226 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.01 RTP/SCS LAND USE POLICY AND PROGRAM DEVELOPMENT
PERCENTAGE COMPLETED: 6 STATUS:
Accomplishments:
PROGRESS
IN PROGRESS
Delay due to waiting for Amendment #1 to budget.
MoneReprogrammed $100K in consultant budget from 150-4096.01 RTP/SCS Land Use Policy & Program
Development to 2050 GHG Pathways 065-02663.03 to continue work related to implementation of the 2016
RTP/SCS being reprogrammed to other projects in Amendment #3.
Issues:
Amendment #1 approved.
Reprogrammed $100K in consultant budget from 150-4096.01 RTP/SCS Land Use Policy & Program Development
to 2050 GHG Pathways 065-02663.03 to continue work related to implementation of the 2016 RTP/SCS.
Resolution:
Comment:
Project included in FY18 OWP.
BUDGET / EXPENDITURE
167,842
47,327 35,435 0 65,828 0 0 0 0 0 0 19,252 0
148,590 0 0 0 0 0 0 0 19,252 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 62,042 19,509 16,777 9,467 16,289
Page 227 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.01 RTP/SCS LAND USE POLICY AND PROGRAM DEVELOPMENT
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 228 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.02 REGIONAL GROWTH AND POLICY ANALYSIS
OBJECTIVE: PROJECT MANAGER:
Prepare the preliminary integrated growth forecast with input from local jurisdictions for 2020 RTP/SCS. Conduct
historical and base year socioeconomic data and trend analysis. Conduct advanced study on urban and regional
issues important to growth planning for the 2020 RTP/SCS.
JOHN CHO
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Evaluate, update and improve
regional growth
estimation/forecasting assumptions
and methodologies that will be used
in the RTP/SCS development and
modeling process.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Research, evaluate, update and
improve regional growth forecasting
models.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Collect and analyze new and existing
socio-economic data including vital
statistics, migration, household
formation, housing, employment, etc.
from diverse private and public
sources.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Update estimates and forecasts of
population and
employment by detailed
characteristics at the county level.
4
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Conduct advanced research and
analysis of the current and emerging
urban and transportation issues and
to seek policy options for 2020
RTP/SCS. .
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Preliminary socio-economic and other data sets
necessary for 2020 RTP/SCS Growth Forecast
06/30/2017 06/30/2017
2 Technical reports on various elements of preliminary
growth forecasting assumptions and methodology for
2020 RTP/SCS Growth Forecast
06/30/2017 06/30/2017
3 Research reports on the regional forecasting and
modeling practice, and the current and emerging urban
and transportation issues
06/30/2017 06/30/2017
Page 229 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.02 REGIONAL GROWTH AND POLICY ANALYSIS
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Staff collected historical data to produce 2020 RTP/SCS growth forecast and to improve the regional growth
forecasting methodology.
Staff executed a project for Technical Support to Update Regional Growth Forecast
Completed project for SCAG REGIONAL TAZ-LEVEL EMISSIONS ESTIMATION TOOL DEVELOPMENT
Staff and consultant hosted panel of expert meeting to discuss assumptions for 2020 RTP/SCS growth forecast.
Staff and consultant produced and presented preliminary growth forecast at TWG and CEHD meeting.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
892,813
187,707 140,541 36,000 289,717 5,000 7,500 140,000 0 0 0 86,348 0
666,465 123,942 0 0 0 16,058 0 0 86,348 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
Page 230 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.02 REGIONAL GROWTH AND POLICY ANALYSIS
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 679,652 194,961 331,762 96,851 56,078
Consultant 124,782 0 41,510 8,456 74,816
CONTRACT STATUS (IF APPLICABLE)
CENTER FOR CONTINUING STUDY OF THE CONTRACT COMPLETE VENDOR:STATUS:
07/01/2016 12/31/2016 12-043-C6
7,000 7,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ICF INTERNATIONALCONTRACT COMPLETE VENDOR:STATUS:
01/01/2017 06/30/2017
35,000 35,000 35,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ICF INTERNATIONALCONTRACT COMPLETE VENDOR:STATUS:
07/01/2016 09/30/2016 16-043-C1
25,000 25,000 25,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ICF RESOURCES, LLCCONTRACT EXECUTED VENDOR:STATUS:
03/27/2017 06/30/2017 17-020-C1
34,000 34,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
MANHAN GROUPCONTRACT COMPLETE VENDOR:STATUS:
08/01/2016 01/31/2017 16-038-C1
24,916 25,000 24,916
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
TECHNICAL SUPPORT TO UPDATE REGIOCONTRACT EXECUTED VENDOR:STATUS:
05/01/2017 06/30/2018 17-033
50,037 15,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 231 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.03 GROWTH FORECASTING - DEVELOPMENT, OUTREACH, AND COLLABORATION
OBJECTIVE: PROJECT MANAGER:
To develop base year socioeconomic estimates and growth projections for the 2020 RTP/SCS; coordinate with local
jurisdictions and subregional agencies to build consensus on socioeconomic and land use growth forecasts;
conduct Scenario Planning analysis and develop technical methodologies for SCAG's planning programs; produce
socioeconomic data for SCAG's various transportation model runs; and provide data services to SCAG partners,
stakeholders, and local jurisdictions for various planning activities.
YING ZHOU
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Evaluate and update county,
jurisdictional, and small area growth
allocation assumptions and
methodologies; Analyze base year
socioeconomic data sources and
build a solid base year estimate for
the 2020 RTP/SCS growth forecast.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Develop socioeconomic growth
forecasts for population, household,
and employment with their
characteristics at various geographic
levels including county, subregion,
jurisdiction and TAZ level.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct subregional workshops,
public outreach, and one-on-one
meetings with local jurisdictions to
confirm the accuracy of small area
socioeconomic and land use data;
and Support services to jurisdictions
in the application of the Scenario
Planning Model.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Perform advanced research and
analysis of current and emerging
land use and transportation issues
which influence transportation
planning and policy making.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Draft 2016 RTP/SCS growth forecast including estimates
and projections for population, households and
employment.
06/30/2017 06/30/2017
Page 232 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.03 GROWTH FORECASTING - DEVELOPMENT, OUTREACH, AND COLLABORATION
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
After various data sources evaluations and method updates, the 2016 base year county/TAZ level estimates for the
2020 RTP/SCS growth forecast have been developed.
We also facilitated a forum to collaborate with member agencies to start the growth forecast process.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
893,805
236,960 177,418 18,000 343,907 0 15,000 0 0 0 0 102,520 0
791,285 0 0 0 0 0 0 0 102,520 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 813,358 248,281 261,651 246,409 57,017
Page 233 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.03 GROWTH FORECASTING - DEVELOPMENT, OUTREACH, AND COLLABORATION
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 234 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.04 OUTREACH AND TECHNICAL COLLABORATION
OBJECTIVE: PROJECT MANAGER:
Supporting outreach to local jurisdictions including SPM training, local input process, one-on-one meeting and so on.
KIMBERLY CLARK
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Develop outreach plan including SPM
training, local input process, and
one-on-one meeting.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Communicate with local jurisdictions
and stakeholders to confirm and
rearrange outreach plan.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Implement the developed outreach
plan and develop a log of the
outreach.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
Summary of outreach to local jurisdiction, one-on-one
meeting, and SPM training including date, comments,
and follow up.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Staff completed the draft schedule for the 2020 RTP/SCS (including outreach), and has worked with subregional
partners to develop the 2020 RTP/SCS Subregional SCS Delegation Framework & Guidelines, which was approved
by SCAG's Community, Economic, and Human Development Committee and gained Regional Council Approval in
April. Staff also structured the outreach guidelines for the 2020 RTP/SCS Local Input and Collaborative Envisioning
Process and presented this framework to the Technical Working Group in June. Staff also developed the Local Input
Survey for the 2020 RTP/SCS, and sought input from a selection of jurisdictional planning directors for refinement.
PROGRESS
COMPLETED
Issues:
Resolution:
Page 235 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.04 OUTREACH AND TECHNICAL COLLABORATION
Comment:
BUDGET / EXPENDITURE
586,144
165,278 123,748 0 229,887 0 0 0 0 0 0 67,231 0
518,913 0 0 0 0 0 0 0 67,231 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 573,206 21,112 42,522 66,881 442,691
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 236 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.05 AFFORDABLE HOUSING AND DISPLACEMENT ANALYSIS
OBJECTIVE: PROJECT MANAGER:
Work with local jurisdictions and partner agencies to assess and identify the region's inventory of affordable housing
units. Analyze trends related to the supply of affordable housing, and specifically examine trends in areas that are
vulnerable to displacement resulting from gentrification and/or transportation investments.
MA AYN JOHNSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
35Staff06/30/201707/01/201606/30/201707/01/2016Survey local jurisdictions and partner
agencies (e.g., US Dept of Housing
and Urban Development, Local
Housing Authorities, California
Department of Housing and
Community Development, etc.) to
establish a regional inventory of
affordable housing units.
1
50Staff06/30/201707/01/201606/30/201707/01/2016Analyze regional trends related to
the supply of affordable housing
units.
2
50Staff06/30/201707/01/201606/30/201707/01/2016Examine trends in areas that are
vulnerable to displacement resulting
from gentrification and/or
transportation investments.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Data related to regional housing trends. 06/30/2017
2 Meeting materials that are used to communicate with
local jurisdictions and stakeholders. Meeting notes that
includes dates, agenda, and comments.
06/30/2017
PERCENTAGE COMPLETED: 42 STATUS:
Accomplishments:
Staff has published a report on the challenges of developing affordable housing, including displacement and
gentrification, and strategies to address the challenges.
PROGRESS
IN PROGRESS
Not all jurisdictions have reported their annual production of affordable housing units to HCD.
Issues:
Page 237 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
150.04096.05 AFFORDABLE HOUSING AND DISPLACEMENT ANALYSIS
SCAG staff will be surveying local jurisdictions on affordable housing built as part of the local input survey for the
2020 RTP/SCS, which will begin in Fall 2017.
Resolution:
Comment:
Task has been included in FY 18 OWP.
BUDGET / EXPENDITURE
410,957
115,880 86,762 0 161,178 0 0 0 0 0 0 47,137 0
363,820 0 0 0 0 0 0 0 47,137 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 236,516 57,058 22,890 44,517 112,051
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 238 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.01641.04 ELECTRIC VEHICLE (EV) PROGRAM (MULTI-UNIT DWELLING (MUD) PLUG-IN
ELECTRIC VEHICLE (PEV) READINESS STRATEGIES
OBJECTIVE: PROJECT MANAGER:
Develop a sub-regional E(Multi-Unit Dwelling (MUD) Plug-In Electric Vehicle (PEV) Readiness Strategies for the
SCAG region. This effort is anticipated to be funded through by a CEC grant and local funds.
MARCO ANDERSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop regional EV readiness
program with subregional focus
studies.
1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 EV Readiness Subregional Plans 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
This activity will leverage SCAG’s strength as an MPO with direct land use and transportation system expertise with
CEC’s implementation focus. Task 1 (Task 2.1 in the scope) of this activity will fund a much needed update of the
regional database and atlas of station and PEV vehicle market penetration.
In December SCAG hosted, in partnership with SBCCOG a policy forum attended by cities, stakeholders, staff from
the CEC, and bldg owners and managers. In addition, SCAG completed outreach to bldgs. with existing PEV
installations. SCAG continues to conduct outreach, and acquires data for the grant sub recipients.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 239 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.01641.04 ELECTRIC VEHICLE (EV) PROGRAM (MULTI-UNIT DWELLING (MUD) PLUG-IN
ELECTRIC VEHICLE (PEV) READINESS STRATEGIES
BUDGET / EXPENDITURE
139,667
17,370 13,005 0 24,160 0 0 85,132 0 0 0 0 0
0 0 0 0 0 14,486 125,181 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 47,661 11,215 18,145 10,574 7,727
Consultant 82,416 0 0 59,386 23,030
CONTRACT STATUS (IF APPLICABLE)
UCLA LUSKIN CENTERCONTRACT EXECUTED VENDOR:STATUS:
07/01/2016 06/30/2017 M-004-16
70,132 70,132
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
WEST SIDE CITIES COUNCIL OF GOVTS (WCONTRACT EXECUTED VENDOR:STATUS:
07/01/2016 06/30/2017 M-005-16
15,000 15,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 240 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02659.01 REGIONAL PLANNING FOR OPEN SPACE STRATEGIC PLAN
OBJECTIVE: PROJECT MANAGER:
Support dissemination of data and best practices; document progress for 2016 RTP/SCS open space conservation
policy recommendations.
INDIA BROOKOVER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage consultant.1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Engage working group with partners
and stakeholders.
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Collect comments and suggestions.3
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Begin implementation of 2016
RTP/SCS Natural Lands (open
space) component policy
recommendations
4
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Coordinate with other MPOs and
stakeholders on conservation/open
space module in Scenario Planning
Model/Urban Footprint
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Regional open space maps 06/30/2017 06/30/2017
2 Status report on 2016 RTP/SCS Natural Lands (open
space) component implementation recommendations.
06/30/2017 06/30/2017
3 Working group and stakeholder outreach process
records (agenda and materials)
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
submitted comments on Title 5 School Siting plan in regards to siting schools in locations that do not disturb natural
habitat
Conducted outreach to cities regarding Sustainable Agricultural Lands Conservation Program (SALC) grant
Held webinar workshop for SALC program in conjunction with CA. Department of Conservation
PROGRESS
COMPLETED
Page 241 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02659.01 REGIONAL PLANNING FOR OPEN SPACE STRATEGIC PLAN
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
101,201
28,536 21,366 0 39,691 0 0 0 0 0 0 11,608 0
89,593 0 0 0 0 0 0 0 11,608 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 97,680 7,900 40,881 48,971 -72
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 242 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02659.02 SANBAG/COUNTY OF SAN BERNARDINO HABITAT CONSERVATION FRAMEWORK
OBJECTIVE: PROJECT MANAGER:
Collect data to support regional and county conservation strategy.
INDIA BROOKOVER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Provide resources to
SANBAG/County of San Bernardino
to procure a consultant
1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 SANBAG Habitat Conservation Framework Phase 2 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Ongoing support for SANBAG/County of San Bernardino's Environment Element Phase II project.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Consultant is managed by SANBAG and County of San Bernardino.
Page 243 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02659.02 SANBAG/COUNTY OF SAN BERNARDINO HABITAT CONSERVATION FRAMEWORK
BUDGET / EXPENDITURE
46,108
6,723 5,034 0 9,351 0 0 25,000 0 0 0 0 0
0 0 0 0 0 46,108 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 25,000 0 0 25,000 0
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 244 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02659.03 SCENARIO PLANNING MODULE - LAND CONSERVATION
OBJECTIVE: PROJECT MANAGER:
Develop land conservation module for scenario planning tool.
INDIA BROOKOVER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
75Staff06/30/201707/01/201606/30/201707/01/2016Manage consultant1
75Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Coordinate with statewide working
group
2
75Consultant06/30/201707/01/201606/30/201707/01/2016Build land conservation module3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Land Conservation Module 06/30/2017
PERCENTAGE COMPLETED: 75 STATUS:
Accomplishments:
Ongoing support for development of Scenario Planning Module for measuring greenhouse gas sequestration.
PROGRESS
CANCELED
Budget was not sufficient to support module.
Issues:
An ultimate determination was made that budget was not sufficient to support module and the project is no longer
going forward.
Resolution:
Comment:
Page 245 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02659.03 SCENARIO PLANNING MODULE - LAND CONSERVATION
BUDGET / EXPENDITURE
25,538
6,723 5,034 0 9,351 0 1,500 0 0 0 0 2,930 0
22,608 0 0 0 0 0 0 0 2,930 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 444 0 0 0 444
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 246 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02659.04 COUNTY TRANSPORTATION COMMISSION OPEN SPACE INITIATIVE
OBJECTIVE: PROJECT MANAGER:
Support county transportation commission efforts to implement open space components of joint work programs.
INDIA BROOKOVER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage consultant1
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate with county staff2
100Consultant07/01/201707/01/201606/30/201707/01/2016Gather data and make
recommendations on
regionally-relevant conservation
policies.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Report on approaches to county-level conservation
planning policies
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Ongoing support for development of county-wide open space initiatives.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
SCAG provided SBCTA with financial support to work on phase 2 of their countywide habitat conservation plan. All of
the work is performed by a consultant, consultant then bills SBCTA.
Page 247 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02659.04 COUNTY TRANSPORTATION COMMISSION OPEN SPACE INITIATIVE
BUDGET / EXPENDITURE
21,108
6,723 5,034 0 9,351 0 0 0 0 0 0 0 0
0 0 0 0 0 21,108 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
CONTRACT STATUS (IF APPLICABLE)
GRUEN ASSOCIATESCONTRACT EXECUTED VENDOR:STATUS:
06/14/2017 06/30/2018 17-024-C1
261,898 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 248 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02661.01 PUBLIC HEALTH
OBJECTIVE: PROJECT MANAGER:
Provide leadership and strategic policy formulation for transportation and land use-related public health in the SCAG
region. Through the development of appropriate Regional Transportation Plan performance measures for public
health. And providing a forum for information sharing and identify best practices employed at the local level. Promote
active transportation safety and encouragement among the general population.
RYE BAERG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide technical support to cities
through Fellowship Program.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Provide support for the
implementation of the Active
Transportation & Safety
Encouragement Campaign, through
partnership development and
promotion of educational materials.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate with local jurisdictions,
industry leaders, and stakeholders to
collaborate on available public health
resources and determine additional
data needs.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Develop performance information and
best practices for public health.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Develop outreach framework for
regional public health policies for the
2020 RTP/SCS
5
100Staff06/30/201707/01/201606/30/201707/01/2016Provide policy input and support
statewide coordination on efforts to
enhance analytical capacities
through testing, calibration of public
health module and other modeling
tools.
6
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Technical support to local and regional agencies 06/30/2017 06/30/2017
2 Report on implementation of Public Health Work
Program
06/30/2017 06/30/2017
Page 249 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02661.01 PUBLIC HEALTH
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Fellows have completed assignments. Support to Active Transportation Safety and Encouragement Campaign
around Public Health has been provided and will be ongoing. Outreach Framework has been developed, initial Public
Health Working Group was held to discuss 2020 RTP/SCS. Staff continues to participate in the statewide Office of
Health Equity Advisory Committee. Staff participates in regular meetings with regional public health stakeholders.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
265,670
46,320 34,681 50,000 104,196 0 0 0 0 0 0 30,473 0
235,197 0 0 0 0 0 0 0 30,473 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 230,460 36,192 38,472 105,790 50,006
Page 250 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.02661.01 PUBLIC HEALTH
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 251 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.01 SOUTHERN CALIFORNIA SAFETY AND ENCOURAGEMENT CAMPAIGN
OBJECTIVE: PROJECT MANAGER:
Campaign will educate all roadway users on the rules of the road, encourage more people to bike/walk through
education, increase public awareness and support for active transportation as a mode of transportation, and build a
regional partnerships between transportation agencies, health departments, local agencies, non-profits, and private
sector partners to cost effectively expand the reach of the Campaign.
RYE BAERG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Perform Project Management1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Conduct regional
coordination/stakeholder meetings,
continued outreach and promotion of
advertising campaign through
communications and outreach efforts
2
95Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Complete tactical urban campaign (8
additional events) and complete
targeted trainings
3
75Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Prepare Draft/Final Reports4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Quarterly Progress Reports 06/30/2017
2 Project Components: Advertising Campaign, Community
Outreach, tactical urbanism
06/30/2017
3 Final Report 06/30/2017
PERCENTAGE COMPLETED: 94 STATUS:
Accomplishments:
Nine tactical urbanism events were completed. Additional media push for May 2017 was completed. Steering
committee and stakeholder engagement continues. Passport program was developed.
PROGRESS
IN PROGRESS
This is a multi year project.
Issues:
Page 252 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.01 SOUTHERN CALIFORNIA SAFETY AND ENCOURAGEMENT CAMPAIGN
Project will be completed in FY 17-18. Final deliverables to be completed include one of four final reports and project
wrap up.
Resolution:
Comment:
Project included in FY18 OWP.
BUDGET / EXPENDITURE
754,699
31,439 23,539 0 43,728 0 0 655,993 0 0 0 0 0
0 0 0 0 622,699 132,000 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 55,600 47,759 7,963 -81 -41
Consultant 448,445 0 11,959 72,257 364,229
Page 253 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.01 SOUTHERN CALIFORNIA SAFETY AND ENCOURAGEMENT CAMPAIGN
CONTRACT STATUS (IF APPLICABLE)
ALTA PLANNINGCONTRACT EXECUTED VENDOR:STATUS:
08/03/2016 08/31/2017 16-042
934,911 329,592
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ELP ADVISORS, LLCCONTRACT EXECUTED VENDOR:STATUS:
07/28/2015 09/30/2016 15-034-C1
765,482 148,279 631,203
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
STEER DAVIES GREAVECONTRACT EXECUTED VENDOR:STATUS:
11/02/2015 10/31/2016 16-004-C1
259,432 75,798 183,634
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 254 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.02 COUNTY OF RIVERSIDE TACTICAL URBANISM EVENTS
OBJECTIVE: PROJECT MANAGER:
Project will host a tactical urbanism event to compliment the GoHuman Campaign by providing safety education and
information about potential projects in the City of Riverside and within the County of Riverside.
SARAH JEPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Perform Project Management1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Facilitate Event Planning and
Identifying Event Partners and
Community Input
2
100Staff/Consultant06/30/201701/01/201706/30/201707/01/2016Host Production of Event3
75Staff/Consultant06/30/201705/01/201706/30/201707/01/2016Prepare Final Report4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Progress Reports 06/30/2017
2 Event Marketing, Community Outreach and Event
Production Materials.
06/30/2017
PERCENTAGE COMPLETED: 96 STATUS:
Accomplishments:
City of Palm Desert event was implemented 5/7/16.
City of Riverside event was implemented 6/1/18.
PROGRESS
IN PROGRESS
Event completed. Final report to be included as part of comprehensive report on Phase 2 Go Human. The consultant
is developing the final report. The work has carried over into FY 18.
Issues:
Work will be carried over in to fiscal year 18 as part of a future budget amendment in FY18.
Resolution:
Comment:
All events are completed.
Page 255 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.02 COUNTY OF RIVERSIDE TACTICAL URBANISM EVENTS
BUDGET / EXPENDITURE
108,912
10,419 7,801 0 14,490 0 0 76,202 0 0 0 0 0
0 0 0 0 0 22,898 86,014 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 12,006 3,336 1,747 -7 6,930
Consultant 89,333 0 44,308 0 45,025
CONTRACT STATUS (IF APPLICABLE)
ALTA PLANNINGCONTRACT EXECUTED VENDOR:STATUS:
08/03/2016 08/31/2017 16-042
934,911 90,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 256 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.04 OC PARKS TACTICAL URBANISM EVENT
OBJECTIVE: PROJECT MANAGER:
Project will host a tactical urbanism event to compliment the GoHuman Campaign by providing safety education and
information about potential projects in cities within the respective county.
SARAH JEPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Perform Project Management1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Facilitate event planning by
developing project costs, integrating
community input and identifying
partners
2
100Staff/Consultant06/30/201701/01/201706/30/201707/01/2016Host Production of Events3
75Staff/Consultant06/30/201705/01/201706/30/201707/01/2016Prepare Final Report4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Progress Reports 06/30/2017
2 Event Marketing, Community Outreach and Event
Production Materials.
06/30/2017
PERCENTAGE COMPLETED: 96 STATUS:
Accomplishments:
City of Westminster event was implemented on 5/21/16.
City of Garden Grove Event was implemented on 4/1/17.
City of Brea event was implemented on 5/27/17
OC Parks event was implemented on 6/10/17
PROGRESS
COMPLETED
Event completed. Final report to be included as part of comprehensive report on Phase 2 Go Human. The consultant
is developing the final report. The work has carried over into FY 18.
Issues:
Work will be carried over in to fiscal year 18 as part of a future budget amendment in FY18.
Resolution:
Page 257 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.04 OC PARKS TACTICAL URBANISM EVENT
Comment:
BUDGET / EXPENDITURE
197,030
17,191 12,871 0 23,910 0 0 143,058 0 0 0 0 0
0 0 0 0 0 115,432 81,598 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 97,110 14,013 35,677 42,262 5,158
Consultant 166,353 0 36,648 0 129,705
CONTRACT STATUS (IF APPLICABLE)
ALTA PLANNINGCONTRACT EXECUTED VENDOR:STATUS:
08/03/2016 08/31/2017 16-042
934,911 119,058
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 258 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.05 SANBAG TACTICAL URBANISM
OBJECTIVE: PROJECT MANAGER:
Project will host a tactical urbanism event to compliment the GoHuman Campaign by providing safety education and
information about potential projects in cities within the respective county
SARAH JEPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Perform Project Management1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Facilitate Event Planning and
Identifying Event Partners and
Community Input
2
100Staff/Consultant06/30/201701/01/201706/30/201707/01/2016Host Production of Events3
75Staff/Consultant06/30/201705/01/201706/30/201707/01/2016Prepare Final Report4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Progress Reports 06/30/2017
2 Event Marketing, Community Outreach and Event
Production Materials.
06/30/2017
PERCENTAGE COMPLETED: 96 STATUS:
Accomplishments:
City of Fullerton event implemented 6/30/17.
City of Rialto event was implemented on 4/18/17.
City of Rancho Cucamonga was implemented on 5/13/17.
PROGRESS
IN PROGRESS
Event completed. Final report to be included as part of comprehensive report on Phase 2 Go Human. The consultant
is developing the final report. The work has carried over into FY 18.
Issues:
Work will be carried over in to fiscal year 18 as part of a future budget amendment in FY18.
Resolution:
Page 259 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.05 SANBAG TACTICAL URBANISM
Comment:
BUDGET / EXPENDITURE
183,455
7,293 5,460 0 10,143 0 0 160,559 0 0 0 0 0
0 0 0 0 0 22,896 160,559 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 22,299 17,636 4,711 -32 -16
Consultant 144,201 0 42,111 0 102,090
CONTRACT STATUS (IF APPLICABLE)
ALTA PLANNINGCONTRACT EXECUTED VENDOR:STATUS:
08/03/2016 08/31/2017 16-042
934,911 147,580
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 260 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.07 CITY OF CUDAHY TACTICAL URBANISM EVENT
OBJECTIVE: PROJECT MANAGER:
Project will host a tactical urbanism event to compliment the GoHuman Campaign by providing safety education and
information about potential projects in cities within the respective county.
SARAH JEPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant03/01/201707/01/201606/30/201707/01/2016Perform Project Management1
100Staff/Consultant03/01/201707/01/201606/30/201707/01/2016Facilitate Event Planning and
Identifying Event Partners and
Community Input
2
100Staff/Consultant03/01/201707/01/201606/30/201712/01/2016Host production of event.3
100Staff/Consultant03/01/201707/01/201606/30/201712/01/2016Final report.4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Progress Reports 06/30/2017 01/01/2017
2 Event Marketing, Community Outreach and Event
Production Materials.
06/30/2017 01/01/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Hosted event on December 3.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Consultant procured
Page 261 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.07 CITY OF CUDAHY TACTICAL URBANISM EVENT
BUDGET / EXPENDITURE
95,190
10,419 7,801 0 14,490 0 0 62,480 0 0 0 0 0
0 0 0 0 0 14,721 80,469 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 62,480 0 0 0 62,480
Staff 11,718 9,151 2,453 -17 131
CONTRACT STATUS (IF APPLICABLE)
ALTA PLANNINGCONTRACT EXECUTED VENDOR:STATUS:
08/03/2016 08/31/2017 16-042
934,911 62,480
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 262 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.09 GO HUMAN - OFFICE OF TRAFFIC SAFETY
OBJECTIVE: PROJECT MANAGER:
SCAG will procure a consultant to conduct media buys across multiple media markets within the region, expand
existing creative/advertising images, develop graphics, evaluate campaign success and develop a dynamic event
passport program to be implemented at open streets events/safety demonstration projects across the region.
Pedestrian and bicycle education including safety programming and materials will be conducted at 12 active
transportation events/projects.
RYE BAERG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201711/01/201606/30/201711/01/2016Develop creative content.1
90Consultant06/30/201711/01/201606/30/201711/01/2016Develop advertising campaign.2
85Staff/Consultant10/31/201711/01/201610/31/201711/01/2016Develop pedestrian and bicycle
education.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Passport program 01/31/2017
2 Campaign creative 02/28/2017
3 Completed educational activities 10/31/2017
4 Paid advertisement placements 05/31/2017
PERCENTAGE COMPLETED: 91 STATUS:
Accomplishments:
Campaign ran from May through June. Educational outreach activities including social media adds and bike rodeos
have begun and will be continued into FY 17-18. Evaluation will be completed in FY 17-18.
PROGRESS
IN PROGRESS
Multi Year Project.
Issues:
Educational outreach activities including social media adds and bike rodeos have begun and will be continued into
FY 17-18. Evaluation will be completed in FY 17-18. Final Report will be delivered in FY 17-18. Task is included in FY
18 OWP.
Resolution:
Page 263 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.09 GO HUMAN - OFFICE OF TRAFFIC SAFETY
Comment:
BUDGET / EXPENDITURE
551,596
36,647 27,439 0 50,972 0 3,538 433,000 0 0 0 0 0
0 0 0 0 473,185 78,411 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 127,691 0 41,298 48,960 37,433
Consultant 390,132 0 0 3,923 386,209
CONTRACT STATUS (IF APPLICABLE)
TWO Q, INC. (DBA JP MARKETING)RFP POSTED VENDOR:STATUS:
03/01/2017 09/30/2017 17-011-C1
411,595 400,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 264 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.10 MSRC GO HUMAN - SUSTAINABILITY PLANNING GRANTS
OBJECTIVE: PROJECT MANAGER:
SCAG will manage Active Transportation safety and encouragement projects in partnership with local cities,
including Go Human events a San Bernardino Safe Routes to School program.
RYE BAERG
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201804/01/201706/30/201804/01/2017Project management.1
100Staff/Consultant06/30/201804/01/201706/30/201804/01/2017Initiate and execute Go Human
events and San Bernardino County
Safe Routes to Schools program.
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 SCAG will implement a series of Go Human events in
partnership with local jurisdictions.
06/30/2018
2 San Bernardino County Safe Routes to Schools program. 06/30/2018
3 Final Reports 06/30/2018
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
RFP's were drafted for Go Human Events and the San Bernardino County Safe Routes to Schools program.
PROGRESS
IN PROGRESS
Release of RFPs was delayed until July of FY 17-18.
Issues:
Contract execution and consultant selection will occur in FY 17-18. Project is included in FY 17-18 OWP.
Resolution:
Comment:
Page 265 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03564.10 MSRC GO HUMAN - SUSTAINABILITY PLANNING GRANTS
BUDGET / EXPENDITURE
2,500,000
0 0 0 0 0 0 2,500,000 0 0 0 0 0
0 0 0 0 0 0 2,500,000 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 266 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03565.01 FIRST MILE/LAST MILE GREENHOUSE DEMONSTRATION ANALYSIS
OBJECTIVE: PROJECT MANAGER:
The purpose of the demonstration project is to develop and apply advanced methods of analyzing GHG emissions to
provide a more comprehensive understanding of emissions generated from the multimodal transit trip, including
first-last mile access and egress from stations.
GRIEG ASHER
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant03/01/201712/01/201606/30/201712/01/2016Conduct data collection in
collaboration with SCAG and Metro
related to GHG emissions from first
and last mile trips.
1
100Consultant03/01/201712/01/201606/30/201712/01/2016Conduct analysis of first and last
mile GHG emissions from different
trip types and combinations of trips.
2
100Consultant03/01/201712/01/201606/30/201712/01/2016Prepare draft and final report detailing
the results of the analysis to inform
RTP/SCS development and provide
an understanding of first last mile
improvements on reducing GHG
emissions.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Final Report 06/30/2017 03/01/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Completed Draft and Final Report on the final life cycle results and an assessment of the potential benefits of
strategies that reduce first/last mile automobile use. The findings were presented to both Metro and SCAG's Boards,
as well as at the TRB Conference in 2016.
PROGRESS
COMPLETED
Issues:
Resolution:
Page 267 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.03565.01 FIRST MILE/LAST MILE GREENHOUSE DEMONSTRATION ANALYSIS
Comment:
Contract was with Arizona State University for services performed from 9/16/16 to 12/31/16. Agreement No.
M-001-16 with Arizona State University for analyzing greenhouse gas emissions related to first mile/last mile access.
BUDGET / EXPENDITURE
32,050
0 0 0 0 0 0 32,050 0 0 0 0 0
0 0 0 0 25,640 6,410 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 4,400 0 0 4,400 0
CONTRACT STATUS (IF APPLICABLE)
ARIZONA STATE UNIVERSITYCONTRACT COMPLETE VENDOR:STATUS:
09/16/2016 12/31/2016
75,000 75,000
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 268 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.04345.01 SAN GABRIEL VALLEY ACTIVE TRANSPORTATION PLANNING INITIATIVE
OBJECTIVE: PROJECT MANAGER:
Develop active transportation plans for cities of Glendora, Irwindale, La Puente, Montebello and Monrovia. Develop
Regional Greeway plan for San Gabriel Valley, using over 80 miles of rivers, channels and washes. Develop regional
way finding signage and branding for existing and planned routes. Collect bicycle/pedestrian counts for partner
communities within the active transportation planning cities and along Rio Hondo/San Gabriel River bike paths.
Provide bicycle safety and maintenance education to encourage safe cycling.
ALAN THOMPSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
2Consultant06/30/201806/06/201706/30/201801/01/2017Develop active transportation plans.1
1Consultant06/30/201806/06/201706/30/201801/01/2017Develop regional Greenway feasibility
plans.
2
1Consultant06/30/201806/06/201712/30/201701/01/2017Conduct active transportation counts.3
0Consultant06/30/201808/01/201706/30/201801/01/2017Education/safety campaign.4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Active transportation plans. 06/30/2018
2 Regional Greenway feasibility plans. 06/30/2018
3 Education/safety campaign. 06/30/2018
PERCENTAGE COMPLETED: 1 STATUS:
Accomplishments:
NTP issued. Project kick off meeting held June 2017
PROGRESS
IN PROGRESS
Project had extended consultant selection and a more lengthy pre-award audit/contract negotiation.
Issues:
NTP was issued in June.
Resolution:
Page 269 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
225.04345.01 SAN GABRIEL VALLEY ACTIVE TRANSPORTATION PLANNING INITIATIVE
Comment:
Project is in FY17-18 OWP.
BUDGET / EXPENDITURE
643,000
0 0 0 0 0 0 600,000 0 0 43,000 0 0
0 0 0 0 0 0 643,000 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 2,198 0 0 0 2,198
CONTRACT STATUS (IF APPLICABLE)
ALTA PLANNINGCONTRACT EXECUTED VENDOR:STATUS:
06/06/2017 12/30/2018 17-021
520,969 15,000 0
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 270 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
230.00174.05 REGIONAL AVIATION PROGRAM 2016 RTP/SCS IMPLEMENTATION
OBJECTIVE: PROJECT MANAGER:
Implement the 2016 RTP/SCS Aviation Program including promotion of regionalization at airports within the region.
RYAN HALL
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
75Staff06/30/201707/01/201606/30/201707/01/2016Document recent trends in the US
airline industry and collect
operational statistics from regional
airports.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Staff the Aviation Task Force (ATF)-
obtain policy direction on
implementation of the 2016
RTP/SCS.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Staff the Aviation Technical Advisory
Committee (ATAC)- obtain
professional and technical input on
the Aviation program activities.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Analyze data and input from ATAC
and the ATF to develop focus for the
2020 RTP/SCS.
4
65Staff06/30/201707/01/201606/30/201707/01/2016Document an air cargo needs
analysis for Southern California.
5
100Staff06/30/201707/01/201606/30/201707/01/2016Monitor the progress of airport
ground access improvement projects
from the 2016 RTP/SCS.
6
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Summary of Aviation data and statistics for FY 17. 06/30/2017 06/30/2017
2 Aviation Program Scope of work for the 2020 RTP/SCS. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 88 STATUS:
Accomplishments:
In the third quarter of FY17 staff finalized a memo outlining resources and steps needed to pursue airport ground
access projects called for as a deliverable by the settlement agreement with the City of El Segundo that was
approved during this quarter. Staff also continued to work with the partner agencies and the airports to assist with
their planning work as well as collect most current activity data.
PROGRESS
IN PROGRESS
Page 271 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
230.00174.05 REGIONAL AVIATION PROGRAM 2016 RTP/SCS IMPLEMENTATION
Most of the data collection activities related to aviation and air cargo trends have been completed. Need to complete
data collection and fully analyze the data and identify implications for the next RTP/SCS. Incomplete work due to
unexpected departure of Aviation staff at the beginning of fourth quarter.
Issues:
Hire new staff as quickly as possible and work towards completion of the critical tasks. This should not have effect
on the ultimate delivery of the 2020 RTP/SCS.
Resolution:
Comment:
Task has been included in FY 18 OWP.
BUDGET / EXPENDITURE
512,714
142,980 107,053 0 198,872 0 5,000 0 0 0 0 58,809 0
453,905 0 0 0 0 0 0 0 58,809 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 267,597 87,846 90,103 83,885 5,763
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 272 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
260.00469.01 ADMINISTRATION OF JARC & NEW FREEDOM PROGRAM
OBJECTIVE: PROJECT MANAGER:
Administration of JARC and New Freedom grant programs.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage program funds including
determining the county level
allocation of annual program funds to
Riverside and San Bernardino
Counties.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Ensure subrecipient projects are
submitted by the Riverside County
Transportation Commission and San
Bernardino Associated Governments
and are programmed into the Federal
Transportation Improvement Program
and submitted to the state for
inclusion in the State Transportation
Improvement Plan.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Maintain copies of annual grant
applications.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Quarterly Progress reports 06/30/2017 07/25/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
This task was completed as of 12/31/2016. Submitted final progress reports in TrAMS on 7/25/17.
PROGRESS
IN PROGRESS
Issues:
Page 273 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
260.00469.01 ADMINISTRATION OF JARC & NEW FREEDOM PROGRAM
Resolution:
Comment:
Not included in the FY18 OWP.
BUDGET / EXPENDITURE
16,937
5,286 3,958 0 7,352 0 0 0 0 0 341 0 0
0 0 0 0 16,937 0 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 15,574 3,321 12,287 -23 -11
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 274 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
265.02125.01 EXPRESS TRAVEL CHOICES PHASE II
OBJECTIVE: PROJECT MANAGER:
Initiate development of implementation plan for value pricing, including a build-out of the existing and planned
managed network of Express/HOT lanes across Southern California and integration with one or more pilot projects
for cordon/area pricing within specific major activity centers.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage and coordinate consultant
work, including preparation of scope
of work, monitoring project budget
and schedule.
1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Evaluate value pricing strategies.2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Execute stakeholder engagement
strategy.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Quarterly progress reports. 06/30/2017 06/30/2017
2 Implementation plan. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Completed Concept of Operations for a regional network of express lanes.
PROGRESS
COMPLETED
Task was not included in initial FY 16/17 OWP.
Issues:
Task added.
Resolution:
Comment:
Note that Project Title was revised in FY 17/18 OWP.
Page 275 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
265.02125.01 EXPRESS TRAVEL CHOICES PHASE II
BUDGET / EXPENDITURE
63,074
0 0 0 0 0 0 63,074 0 0 0 0 0
0 0 0 0 0 0 0 0 0 63,074
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 5,332 0 0 0 5,332
CONTRACT STATUS (IF APPLICABLE)
AECOMCONTRACT EXECUTED VENDOR:STATUS:
10/08/2015 06/30/2018 13-008-C1
4,071,936 1,175,285 459,715
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
PBCONTRACT EXECUTED VENDOR:STATUS:
04/25/2013 06/30/2018 13-008-C2
2,058,303
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 276 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
265.02125.02 EXPRESS TRAVEL CHOICES PHASE III
OBJECTIVE: PROJECT MANAGER:
Express Travel Choices Phase III will build on the prior feasibility work. A key part of this process will include
preparation of an initial study and environment assessment.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Provide project management, support
and administration.
1
100Consultant06/30/201707/01/201606/30/201707/01/2016Initial study and environmental
assessment (IS/EA)
2
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Initial study and environmental assessment (IS/EA) 06/30/2017 06/30/2018
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Key stakeholder engagement meetings and workshops completed. Stakeholder engagement strategy developed.
Stakeholder engagement underway. Outreach work is continuing, including planning for and initial deployment of
expanded scope of outreach.
PROGRESS
COMPLETED
Step 2 and Product 1 were revised in the FY 17/18 OWP but not reflected here.
Issues:
The FY 17/18 OWP shows the correct Step 2 and Product 1 information. Stakeholder engagement and feasibility
analysis is underway.
Resolution:
Comment:
Work is a multi-year effort and is included in FY 17/18 OWP.
Page 277 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
265.02125.02 EXPRESS TRAVEL CHOICES PHASE III
BUDGET / EXPENDITURE
892,320
54,577 40,863 0 75,911 0 0 720,969 0 0 0 0 0
0 0 0 0 576,776 315,544 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 167,060 74,196 58,591 34,395 -122
Consultant 720,969 0 0 446,291 274,678
CONTRACT STATUS (IF APPLICABLE)
AECOMCONTRACT EXECUTED VENDOR:STATUS:
10/08/2015 06/30/2018 13-008-C1
4,071,936 1,175,285 459,715
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 278 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
266.00715.01 LOCALLY-FUNDED PROJECTS
OBJECTIVE: PROJECT MANAGER:
To fund projects with local funds.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Review scopes of work and
determine if project is ineligible for
Federal planning funds.
1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Locally funded projects. 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Funded local initiatives not eligible for federal planning funds.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 279 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
266.00715.01 LOCALLY-FUNDED PROJECTS
BUDGET / EXPENDITURE
200,000
0 0 0 0 0 0 200,000 0 0 0 0 0
0 0 0 0 0 200,000 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 338,661 0 0 15,418 323,243
Consultant 195,604 1,276 4,705 16,476 173,147
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 280 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
266.00715.04 SGC - AHSC PILOT PROGRAM
OBJECTIVE: PROJECT MANAGER:
This is an SGC grant to fund an AHSC technical assistance pilot program for disadvantaged communities in the
SCAG region. The program will provide individual assistance for up to 29 applicants as well as build future capacity
through partnership building workshops.
JASON GREENSPAN
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201608/30/201607/01/2016Technical assistance1
100Consultant06/30/201707/01/201609/30/201607/01/2016Workshops2
100Consultant06/30/201707/01/201609/30/201607/01/2016Network meeting3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 TA action plans 09/30/2016 06/30/2017
2 Workshop materials 09/30/2016 06/30/2017
3 Network meeting materials 09/30/2016 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Held 4 workshops in April and June to provide TA to Inland Empire and Imperial County.
Completed toolkit mockup.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Page 281 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
266.00715.04 SGC - AHSC PILOT PROGRAM
BUDGET / EXPENDITURE
151,337
0 0 0 0 0 0 151,337 0 0 0 0 0
0 0 0 0 0 0 151,337 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Consultant 139,193 12,014 33,073 39,807 54,299
CONTRACT STATUS (IF APPLICABLE)
ELP ADVISORS, LLCCONTRACT EXECUTED VENDOR:STATUS:
11/13/2015 06/30/2017 16-010A
378,405 219,046 159,358
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
ESTOLANO LESAR PEREZ ADVISORSCONTRACT EXECUTED VENDOR:STATUS:
07/01/2016 06/30/2017 16-010A-C1
378,405 151,337
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 282 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
266.00715.05 RIVERSIDE RECONNECTS PHASE 2
OBJECTIVE: PROJECT MANAGER:
Develop a funding and implementation for a modern electric trolley in the City of Riverside.
STEPHEN FOX
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
0Consultant06/30/201704/03/201706/30/201701/01/2017Project management1
0Consultant06/30/201704/03/201701/31/201701/01/2017Conduct baseline report2
0Consultant06/30/201704/03/201704/30/201702/01/2017Conduct technical analysis and
ridership forecasting
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Baseline report 01/31/2017 06/30/2018
2 Technical analysis and ridership report 04/30/2017 06/30/2018
3 Final report 06/30/2017 06/30/2018
PERCENTAGE COMPLETED: 0 STATUS:
Accomplishments:
PROGRESS
DELAYED
Project is delayed and has not started yet due to City of Riverside workload and priorities.
Issues:
SCAG staff is waiting on City of Riverside staff to develop a scope-of-work for the project.
Resolution:
Comment:
This task is also continuing in to FY 18 and is in the FY 18 budget.
Page 283 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
266.00715.05 RIVERSIDE RECONNECTS PHASE 2
BUDGET / EXPENDITURE
50,000
0 0 0 0 0 0 50,000 0 0 0 0 0
0 0 0 0 0 50,000 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 284 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
266.03920.01 SCAG/CALTRANS EAST-WEST FREIGHT CORRIDOR
OBJECTIVE: PROJECT MANAGER:
SCAG is working with Caltrans to proceed with the development of the Project Initiation Document (PID) phase for
the proposed East West Freight Corridor. The purpose of the PID is to initiate the necessary project studies to move
into the Project Approval and Environmental Document (PA&ED) phase. This Project is funded by Transportation
Development Act (TDA) funds.
ANNIE NAM
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Define Purpose and Need of the PID.1
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Gather existing information, initial
assumptions, identified risks and
constraints.
2
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop an approach (i.e., scope)
including alternatives that will be
taken to meet or reduce
transportation deficiencies and
address the purpose and need.
3
100Staff/Consultant06/30/201707/01/201606/30/201707/01/2016Develop realistic cost estimates and
schedules to fund the project.
4
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Draft and Final Reports summarizing the purpose and
Need Statements for the Project, existing information,
initial assumptions, identified risks and constraints. The
reports will also include alternatives and the cost
estimates.
06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
PSR work underway by Caltrans; funding already transferred to Caltrans.
PROGRESS
COMPLETED
Issues:
Page 285 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
266.03920.01 SCAG/CALTRANS EAST-WEST FREIGHT CORRIDOR
Resolution:
Comment:
PSR work continues to be supported in FY17/18 under task 130.00162.10 East-West Freight Corridor/I-15 Phase II.
BUDGET / EXPENDITURE
353,813
33,065 24,757 0 45,991 0 0 250,000 0 0 0 0 0
0 0 0 0 0 353,813 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 87,456 34,001 20,387 19,235 13,833
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 286 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
267.01241.04 SCAG AND DOE/NETL CLEAN CITIES COALITION COORDINATION
OBJECTIVE: PROJECT MANAGER:
Coordinate and promote the efforts of the Department of Energy (DOE) Clean Cities Program and fulfill all DOE
Clean Cities Program requirements. Coordinate with regional alternative fuel vehicle promotion stakeholders.
MARCO ANDERSON
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Plan and execute the required
number of stakeholder meetings and
events to further the goals of the
Clean Cities Program.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Complete and update the quarterly
Alternative Fuels report and submit
results to DOE.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Participate in required Clean Cities
conferences, seminars and training
sessions.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct an annual survey of
members and stakeholders on
alternative fuels in the SCAG region.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Conduct outreach and education
activities to keep stakeholders
informed.
5
100Staff06/30/201707/01/201606/30/201707/01/2016Expand the Clean Cities
stakeholders
6
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 SCAG Clean Cities Coalition meeting agendas 01/31/2017 06/30/2017
2 Documentation required by the Clean Cities Program,
including annual survey, annual operating plan, and
biannual Coalition newsletter
01/31/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
The coordinator, has continued to work with partners throughout the region to pursue grant opportunities. This
included working with applicants, and signing four letters of support for organizations applying the California Energy
Commission (CEC) – GFO 15-603DC Fast Chargers for California’s Interregional Corridor.
PROGRESS
COMPLETED
Page 287 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
267.01241.04 SCAG AND DOE/NETL CLEAN CITIES COALITION COORDINATION
SCAG completed the annual survey and report, and executed the grant agreement for Federal FY17-18
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
41,956
11,994 8,980 0 16,682 0 4,300 0 0 0 0 0 0
0 0 0 0 41,956 0 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 40,853 14,374 18,604 6,557 1,318
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 288 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.01 ADMINISTRATION OF SECTION 5339
OBJECTIVE: PROJECT MANAGER:
SCAG is direct recipient of the Section 5339 and must allocate the funds via formula, execute grants and
sub-agreements, monitor sub-recipients, and manage the project and overall program.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage program funds including
determining the annual county level
allocations and balances.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare Call for Applications and
review submitted applications.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Ensure selected and approved
projects are submitted by the County
Transportation Commissions (CTC)
and programmed into the Federal
Transportation Improvement Program
(FTIP) as well as submitted to the
State for inclusion in the State
Transportation Improvement Plan.
3
100Staff06/30/201707/01/201606/30/201707/01/2016Prepare and submit the grant
application(s) directly to the Federal
Transit Administration's (FTA) via
TEAM-web/TRAMS.
4
100Staff06/30/201707/01/201606/30/201707/01/2016Program oversight; such as grant
and financial reporting and program
compliance.
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Annual county level allocations 06/30/2017 06/30/2017
2 Grant Application(s) 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Prepared annual county level allocations and balances.
PROGRESS
IN PROGRESS
Page 289 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.01 ADMINISTRATION OF SECTION 5339
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
186,147
57,697 43,199 0 80,251 0 5,000 0 0 0 0 0 0
0 0 0 0 0 186,147 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 44,639 12,253 7,803 13,696 10,887
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 290 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.02 ORANGE COUNTY TRANSP. COMMISSION
OBJECTIVE: PROJECT MANAGER:
Pass-thru grant to OCTA for Bus and Bus Facility related capital items.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Monitor Project1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Quarterly Reports 06/30/2017 07/25/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
This project has been completed. Final quarterly progress report submitted in TrAMS on 7/25/17.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Not included in the FY18 OWP.
Page 291 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.02 ORANGE COUNTY TRANSP. COMMISSION
BUDGET / EXPENDITURE
4,711,109
0 0 0 0 0 0 0 0 4,711,109 0 0 0
0 0 0 0 4,711,109 0 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 292 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.03 OMNITRANS BUS REPLACEMENTS
OBJECTIVE: PROJECT MANAGER:
Pass-thru grant to Omnitrans for Bus and Bus Facility related capital items.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Monitor Project1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Quarterly Reports 06/30/2017 07/25/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
This project has been completed. Final quarterly progress report submitted in TrAMS on 7/25/17.
PROGRESS
COMPLETED
Issues:
Resolution:
Comment:
Not included in FY18 OWP.
Page 293 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.03 OMNITRANS BUS REPLACEMENTS
BUDGET / EXPENDITURE
2,139,813
0 0 0 0 0 0 0 0 2,139,813 0 0 0
0 0 0 0 2,139,813 0 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 3,611,526 0 3,611,526 0 0
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 294 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.04 RIVERSIDE TRANSIT AGENCY SECTION 5339 BUS & BUS FACILITIES
OBJECTIVE: PROJECT MANAGER:
Pass-thru grant to Riverside Transit Agency for Bus and Bus Facility related capital items.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Monitor Project1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Quarterly Reports 06/30/2017 07/27/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Submitted quarterly progress reports in TrAMS.
PROGRESS
IN PROGRESS
Issues:
Resolution:
Comment:
Page 295 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.04 RIVERSIDE TRANSIT AGENCY SECTION 5339 BUS & BUS FACILITIES
BUDGET / EXPENDITURE
5,926,633
0 0 0 0 0 0 0 0 5,926,633 0 0 0
0 0 0 0 5,926,633 0 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 508,577 0 93,965 322,315 92,297
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 296 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.05 SUNLINE TRANSIT AGENCY SECTION 5339 BUS & BUS FACILITIES AND SECTION
5312 LONO
OBJECTIVE: PROJECT MANAGER:
Pass-thru grant to the SunLine Transit Agency for Bus and Bus Facility related capital items.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Consultant06/30/201707/01/201606/30/201707/01/2016Monitor Project1
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Quarterly Reports 06/30/2017 07/27/2017
PERCENTAGE COMPLETED: 100 STATUS:
Accomplishments:
Submitted quarterly progress reports in TrAMS.
PROGRESS
IN PROGRESS
Issues:
Resolution:
Comment:
Page 297 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03833.05 SUNLINE TRANSIT AGENCY SECTION 5339 BUS & BUS FACILITIES AND SECTION
5312 LONO
BUDGET / EXPENDITURE
10,591,357
0 0 0 0 0 0 0 0 10,591,357 0 0 0
0 0 0 0 10,591,357 0 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 9,971 0 0 0 9,971
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 298 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03834.01 ADMINISTRATION OF SECTION 5310
OBJECTIVE: PROJECT MANAGER:
Improve mobility for seniors and individuals with disabilities by removing barriers to transportation service and
expanding transportation mobility options.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
50Staff06/30/201707/01/201606/30/201707/01/2016Execute Agreements with Caltrans
regarding program responsibilities
and terms.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Manage program funds including
determining the annual county level
allocations and balances.
2
100Staff06/30/201707/01/201606/30/201707/01/2016Coordinate with applicable counties
in regards to project selection
process, including selection criteria
and eligibility.
3
50Staff06/30/201707/01/201606/30/201707/01/2016Prepare and submit Project
Selections along with Resolution to
Caltrans for each applicable large
urbanized area (UZA).
4
100Staff06/30/201707/01/201606/30/201707/01/2016Provide any necessary support and
technical assistance to County
Transportation Commission (CTC),
Sub-recipients and Caltrans for
ongoing activity.
5
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Annual county level allocations 06/30/2017 06/30/2017
2 Program of Projects 06/30/2017
PERCENTAGE COMPLETED: 85 STATUS:
Accomplishments:
Prepared annual county level allocations and balances.
PROGRESS
IN PROGRESS
Page 299 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03834.01 ADMINISTRATION OF SECTION 5310
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
72,117
21,377 16,006 0 29,734 0 5,000 0 0 0 0 0 0
0 0 0 0 0 72,117 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 16,657 8,140 50 5,189 3,278
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 300 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03835.01 ADMINISTRATION OF SECTION 5337
OBJECTIVE: PROJECT MANAGER:
Section 5337 is dedicated to repairing and upgrading the nation’s rail transit systems along with high-intensity motor
bus systems that use high-occupancy vehicle lanes, including bus rapid transit (BRT). These funds reflect a
commitment to ensuring that public transit operates safely, efficiently, reliably, and sustainably so that communities
can offer balanced transportation choices that help to improve mobility, reduce congestion, and encourage
economic development.
ERIKA BUSTAMANTE
STEPS
DescriptionNo. Plan Start
Date
Plan End
Date
Current
Start Date
Current
End DatePercentage
Completed
Work Type
100Staff06/30/201707/01/201606/30/201707/01/2016Manage program funds including
determining the annual county level
allocations, balances and submit
annual split letter to the Federal
Transit Administration.
1
100Staff06/30/201707/01/201606/30/201707/01/2016Ensure projects are submitted by the
County Transportation Commissions
(CTC) and programmed into the
Federal Transportation Improvement
Program (FTIP) as well as submitted
to the State for inclusion in the State
Transportation Improvement Plan.
2
50Staff06/30/201707/01/201606/30/201707/01/2016Prepare and submit Metropolitan
Planning Organization concurrence
letters to the Federal Transit
Administration for approval of the
program funds for each applicable
applicant.
3
PRODUCTS
Product Delivery DatePlan Delivery DateDescriptionNo.
1 Annual county level allocations 06/30/2017 06/30/2017
PERCENTAGE COMPLETED: 87 STATUS:
Accomplishments:
Prepared annual county level allocations and balances.
PROGRESS
IN PROGRESS
Page 301 of 302
OWP Progress ReportFOURTH QUARTER FY 16-17
270.03835.01 ADMINISTRATION OF SECTION 5337
Issues:
Resolution:
Comment:
BUDGET / EXPENDITURE
79,342
25,271 18,921 0 35,150 0 0 0 0 0 0 0 0
0 0 0 0 0 79,342 0 0 0 0
BUDGET:
Salaries Benefits Temps Indirect Print Travel Consult Sub Staff Sub Cons Other 3rd PartyLocal /
Cash
FHWA FTA SPR 5304 Fed Other TDA State Other Cash Match 3rd Party Local Other
EXPENDITURE
Work Type Total Q1 Actuals Q2 Actuals Q3 Actuals Q4 Actuals
Staff 26,498 3,287 20 13,817 9,374
CONTRACT STATUS (IF APPLICABLE)
VENDOR:STATUS:
Start Date: End Date: Number:
Total Award: FY Value: PY Expends:
Page 302 of 302
818 West 7th Street, 12th FloorLos Angeles, CA 90017Phone: (213) 236-1800Fax: (213) 236-1825
The Southern California Association of Governments (SCAG) is the nation’s largest metropolitan planning organization and council of governments. To better serve the 18 million residents and 191 cities it represents, SCAG has an office in each of its six member counties: Imperial, Los Angeles, Orange, Riverside, San Bernardino and Ventura. For more information about SCAG call (213) 236-1800 or visit us at www.scag.ca.gov.
IMPERIAL COUNTY1405 North Imperial Avenue, Suite 1El Centro, CA 92243Phone: (760) 353-7800Fax: (760) 353-1877
ORANGE COUNTYOCTA Building600 South Main Street, Suite 1233Orange, CA 92868Phone: (714) 542-3687Fax: (714) 560-5089
RIVERSIDE COUNTY3403 10th Street, Suite 805Riverside, CA 92501Phone: (951) 784-1513Fax: (951) 784-3925
SAN BERNARDINO COUNTYSanta Fe Depot1170 West 3rd Street, Suite 140San Bernardino, CA 92418Phone: (909) 806-3556Fax: (909) 806-3572
VENTURA COUNTY950 County Square Drive, Suite 101Ventura, CA 93003Phone: (805) 642-2800Fax: (805) 642-2260
please recycle 2730 2016.10.13
REGIONAL OFFICES