First Wall and Shield Activities M. Ulrickson Presented at ... · Coil. Poloidal Field Coil Machine...
Transcript of First Wall and Shield Activities M. Ulrickson Presented at ... · Coil. Poloidal Field Coil Machine...
First Wall and Shield Activities
M. UlricksonPresented at the FNST Meeting
UCLAAugust 18, 2009
Sandia is a multiprogram laboratory operated by Sandia Corporation, a Lockheed Martin Company,for the United States Department of Energy’s National Nuclear Security Administrationunder contract DE-AC04-94AL85000.
1
Outline
• Scope of US contribution• The Blanket Integrated Project Team• Recent Design Progress• Issues• Future Work
2
SCOPE OF THE SANDIACONTRIBUTION
3
International Thermonuclear Experimental Reactor (ITER)
Central Solenoid
Outer Inter-coil Structure
Toroidal Field Coil
Poloidal Field Coil
Machine Gravity Support
Blanket Module 20%
Vacuum Vessel
Cryostat
Port Plug
(IC Heating)
Divertor
Torus Cryopumping
Additional Scope and Options
• There is a possibility that the US will contribute the first wall on the equatorial ports for diagnostics (6 ports) in place of our initial Port Limiter contribution.
• The baseline US contribution is for modules 7 (near the top), 12 and 13 (above the equatorial port)
5
BLANKET INTEGRATED PRODUCT TEAM
6
Blanket Integrated Product Team
• Both the DA’s and the ITER Organization recognized that sharing the blanket/first wall procurement among six parties would be very complex and make quality control more difficult.
• In addition the IO recognized that the design could not be completed solely at the IO.
• A “build to print” procurement arrangement was not going to succeed.
• Guenter Janeschitz proposed forming teams to share the design among the IO and the DA’s and a discussion of redivision of the scope of the parties contributions to reduce the number of DA’s fabricating similar parts.
• The BIPT was formed in the Fall of 2008 with the intent of achieving these objectives.
• Doug Loesser (PPPL) is the BIPT leader.
7
Procurement Sharing Baseline
• First WallEU 40%US 20%RF 20%JA 10%CN 10%Design by IO for all
• Shield ModulesCN 40%US 20%RF 20%EU 10%KO 10%
8
BIPT Scope Revisions (draft)
• First WallEU 50%RF 40%CN 10%US design of all
• Shield ModulesCN 40-50%KO 30-25%RF 30-25%RF design of all
• This agreement was not ratified at the July meeting and further changes are almost certain.
9
RECENT DESIGN PROGRESS
10
Latest Concept for First Wall
11
Latest Concept for Shield Module
12
Design by Analysis ProcessCATIA
Concept
Neutron Transport (MCNP)
Simplify for
Analysis
Electromagnetic Analysis (OPERA)
Fluid Flow & Heat
Transfer Analysis
Primary Stress (ABAQUS)
Secondary Stress
Meet Require-ments
Refine ConceptNo
Yes Done
FW Surface Heat
Design Tools
• ModelingCATIA to match IO; SMARTEAM to interface with ENOVIA
• Neutron TransportMCNP; University of Wisconsin
• Thermal HydraulicsCFDesign; good CATIA interface but no 2 phaseSCTetra; good transient analysis but no 2 phase, UCLAFLUENT; Some 2 phase STAR-CCM; Full capability
• ElectromagneticOPERA; Experience, full 3D, ferromagnetic, full V&V
• Mechanical and stressABAQUS; Sandia site license
CFD Analysis for BM04 (US fixed)
CFD model total nuclear heat to BM04 = 0.40473 MW
Water= 0.0494 MW
Steel = 0.35531MW
CFD water outlettemperature= 112.01C
(Inlet T= 100 C; inlet mass flow rate = 8 kg/s)
Steady State Analysis Water volume = 0.0284942 m3
Steel volume= 0.254979 m3
∆P = 148864 Pa
UCLA
Non-Uniformity of Velocity
FW Panel in the Removal Position
Interference region
Panel Ready for Removal
Installed
Rotation ~10 deg.
Vertical Displacement
Issues
• New concepts from the IO have relatively little analysis and are created mostly by intuition.
• The new concepts tend to appear much more rapidly than the analysis can be done.
• This breaks the design by analysis logic and actually slows the design process. People like what they have “designed” and don’t want problems to be found.
• Technical issuesFW can’t be removed from the shield unless slots are
increased.Flow is not uniform in the shield or first wall. (hot spots)Cooling pattern has low water volume fraction (~13%)Many fewer EM slits because of preferences.
22
Future Work
• Option 1We design modules 7, 12, 13 and fabricate sameMust make another FWQM and test at SNLSmaller design scope and larger manufacturing, prototype,
heat sink R&D, and Be to Cu R&D budget• Option 2
We design all first wall panelsWe perform basic heat sink R&D and Be to 316 SS joining
R&DWe design and fabricate the first wall for the equatorial
diagnostic ports.
23