FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has...

41
i COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED 2007 EFY (07/07/2014-10/10/2014) DECEMBER 2014

Transcript of FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has...

Page 1: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

i

COMMUNITY-LED ACCELERATED WASH (COWASH)

PROJECT

FIRST QUARTER PERFORMANCE REPORT

OUTPUT BASED 2007 EFY (07/07/2014-10/10/2014)

DECEMBER 2014

Page 2: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

ii

Table of Contents

1 EXECUTIVE SUMMARY ........................................................................................................................................ 1

2 OVERALL OBJECTIVE ACHIEVEMENT.................................................................................................................... 5

3 PROJECT PURPOSE ACHIEVEMENT ...................................................................................................................... 5

4 COMPONENT 1: STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS

ALONGSIDE WITH A SUPPORT TO THE ESTABLISHMENT OF THE ONE WASH NATIONAL PROGRAM .................. 6

4.1 RESULT 1 OF COMPONENT 1: COMMUNITY MANAGED PROJECT APPROACH SCALED-UP AT NATIONAL LEVEL ....... 6

4.1.1 Output 1: Manuals and Guidelines Reviewed and Developed for Standardizing the CMP Implementation

within the WaSH Implementation Framework .............................................................................................. 6

4.1.2 Output 2: Tools and Mechanisms Reviewed and Developed for Standardizing the Planning,

Implementation and Monitoring of CMPs ..................................................................................................... 8

4.1.3 Output 3: CMP Approach within the Rural WaSH Scientifically Researched ................................................. 9

4.1.4 Output 4: Information, Education and Communication (IEC) on CMP Implementation Modality Enhanced 9

4.2 RESULT 2 OF COMPONENT 1: CMP IMPLEMENTATION CAPACITY AT THE FEDERAL AND REGIONAL LEVELS

DEVELOPED ....................................................................................................................................................... 10

4.2.1 Output 1: Capacity Building Instruments Reviewed and Developed ........................................................... 10

4.2.2 Output 2: Capable and Adequate Personnel in place for CMP Implementation at National and Regional

Levels ........................................................................................................................................................... 11

4.3 RESULT 3 OF COMPONENT 1: DEVELOPMENT AND IMPLEMENTATION OF ONE WASH NATIONAL PROGRAM

SUPPORTED ...................................................................................................................................................... 12

4.3.1 Output 1: COWASH Support Provided in Preparing One WaSH National Program ..................................... 12

4.3.2 Output 2: COWASH Support Provided in Implementation of One WaSH National Program ....................... 12

5 COMPONENT 2: ESTABLISHING AND STRENGTHENING THE CAPACITY IN REGIONS TO SCALE-UP

IMPLEMENTATION OF CMP ...............................................................................................................................13

5.1 RESULT 1 OF COMPONENT 2: TARGET REGIONS, ZONES AND WOREDAS CAPABLE TO PLAN, MANAGE, MONITOR

AND IMPLEMENT RURAL WASH INTERVENTIONS USING CMP APPROACH ....................................................... 13

5.1.1 Output 1: Regional Support Units (RSU) Established and Functional .......................................................... 13

5.1.2 Output 2: Regions, Zones and Woredas Capacitated to Implement Rural WaSH through CMP ................. 14

5.2 RESULT 2 OF COMPONENT 2: FINANCIAL AND PROCUREMENT SERVICES DELIVERED FOR CMP INTERVENTION AT

ALL LEVELS IN THE SELECTED REGIONS .............................................................................................................. 18

5.2.1 Output 1: Flow of Funds for CMPs Functional ............................................................................................. 18

5.2.2 Output 2: Linkages Created with Private Sector in the Supply of Materials, Equipment, Tools and Services

..................................................................................................................................................................... 19

5.3 RESULT 3 OF COMPONENT 2: SUSTAINABLE COMMUNITY AND INSTITUTIONAL ACCESS TO SAFE WATER,

SANITATION AND HYGIENE IN THE TARGET WOREDAS INCREASED.................................................................. 19

5.3.1 Output 1: Access to Improved Water Sources for Communities and Institutions Increased ....................... 19

5.3.2 Output 2: Access to Sanitation for Household and Institutions Increased and Hygiene Behavior Improved

..................................................................................................................................................................... 21

5.3.3 Output 3: Sustainability of Communal and Institutional Water Schemes in the Targeted Woredas

Strengthened ............................................................................................................................................... 22

5.3.4 Output 4: Potable Water Quality Ensured in Targeted Woredas ................................................................ 24

6 FINANCIAL UTILIZATION PERFORMANCE ...........................................................................................................25

6.1 FINANCIAL PERFORMANCE OF COMPONENT 1 ............................................................................................................. 25

6.1.1 Cumulative expenditures ............................................................................................................................. 25

6.1.2 Comparison of the budget utilization with the 3 - months budget of 2007 EFY .......................................... 27

Page 3: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

iii

6.2 FINANCIAL PERFORMANCE OF COMPONENT 2 ............................................................................................................. 28

6.2.1 Financial Performance of Amhara region.................................................................................................... 28

6.2.2 Financial Performance of Tigray Region ...................................................................................................... 29

6.2.3 Financial Performance of SNNP Region ....................................................................................................... 30

6.2.4 Financial Performance of Oromia region .................................................................................................... 31

6.2.5 Financial Performance of BSG region .......................................................................................................... 32

7 PROJECT COORDINATION WITH KEY STAKEHOLDERS .........................................................................................33

8 CHALLENGES ......................................................................................................................................................35

Page 4: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

iv

Abbreviation Interpretation

ACSI

Amhara Credit and Saving Institution

AfDB African Development Bank

AWP Annual Work Plan

BoE Bureau of Education

BoFED Bureau of Finance and Economic Development

BoH Bureau of Health

CARE Cooperative for Assistance and Relief Everywhere

CBN Community Based Nutrition

CDF Community Development Fund

CFT Community Facilitation Team

CIDA Canadian International Development Agency

CLTSH Community-Led Total Sanitation and Hygiene

CMP Community Managed Project

COWASH Community Led Accelerated WASH in Ethiopia

CRS Catholic Relief Services

CTA Chief Technical Advisor

CWA Consolidated WaSH Account

DCSI Dedebit Credit & Saving Institution

DFID Department for International Development (UK)

EFY Ethiopian Fiscal Year

EIRR Economic Internal Rate of Return

ETB Ethiopian Birr

EU European Union

EUR Euro

EUWI European Union Water Initiative

EWA Ethiopian Water Alliance

FI Financial Intermediary

FinnWASH-BG Rural Water Supply, Sanitation and Hygiene Programme in

Benishangul-Gumuz Region

FTAT Federal Technical Assistance Team

GoE Government of Ethiopia

GoF Government of Finland

GTP Growth and Transformation Plan

HEW Health Extension Worker

HIV/AIDS Human Immunodeficiency Virus/ Acquired Immunodeficiency

Syndrome

HQ Head Quarter

HRD Human Resource Development

HSDP Health Sector Development Plan

IDC Italian Development Cooperation

IEC Information, Education and Communication

JFA Joint Financing Agreement

JICA Japan International Cooperation Agency

JMP Joint Monitoring Program

JTR Joint Monitoring Review

KWT Kebele WaSH Team

Page 5: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

v

Abbreviation Interpretation

LWI

Living Water International

MDG Millennium Development Goal

M&E Monitoring and Evaluation

METB Million Birr

MEUR Million Euros

MFA Ministry for Foreign Affairs (of Finland)

MFI Microfinance Institution

MIS Management Information System

MMS Mass Mobilization Strategy

MoE Ministry of Education

MoFED Ministry of Finance and Economic Development

MoH Ministry of Health

MoU Memorandum of Understanding

MoWE Ministry of Water & Energy

MSF Multi-Stakeholder Forum

MUS Multiple Use of Services (Water)

MUSD Million United States Dollars

MWA Millennium Water Alliance

NGO Non-Governmental Organization

NPV Net Present Value

NUWI Netherlands-UNICEF WaSH Initiative

NWCO National WaSH Coordination Office

NWI National WaSH Inventory

NWMU National WaSH Management Unit

NWSC National WaSH Steering Committee

NWTT National WaSH Technical Team

OCSSCO Oromia Credit and Saving Shareholder Company

ODF Open Defecation Free

O&M Operation and Maintenance

OMA Office Management Assistant

OMFI OMO Micro-Finance Institution

OMSU Operation and Maintenance Support Unit

ORDA Organization for Rehabilitation and Development in Amhara

PASDEP Plan for Accelerated and Sustainable Development to End Poverty

REST Relief Society of Tigray

RiPPLE Research Inspired Policy and Practice Learning in Ethiopia and the

Nile Region

RSU Regional Support Unit

RWCO Regional WaSH Coordination Office

RWSC Regional WaSH Steering Committee

RWSEP Rural Water Supply and Environment Programme

RWTT Regional WaSH Technical Team

SAP National Hygiene and Sanitation Strategic Action Plan

SNNPR Southern Nations & Nationalities Peoples Region

SNV Netherlands Development Organization

SvB Supervisory Board

SWAp Sector Wide Approach

TA Technical Assistance

Page 6: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

vi

Abbreviation Interpretation

TVETC

Technical Vocational & Educational Training College

UAP Universal Access Plan

UK United Kingdom

UNESCO United Nations Educational, Scientific and Cultural Organization

UNICEF United Nations Children’s Fund

WaSH Water Supply, Sanitation and Hygiene

WASHCO Water Supply, Sanitation and Hygiene Committee

WB The World Bank

WEW Water Extension Worker

WIF WaSH Implementation Framework

WMP Woreda Managed Project

WMU WaSH Management Unit

WRDB Water Resources Development Bureau

WSA Woreda Support Agent

WSG Woreda Support Group

WSP Water Safety Plan

WSP-AF Water and Sanitation Program-Africa

WSS Water Supply and Sanitation

WSSD Water Supply and Sanitation Directorate

WSSP Water Supply and Sanitation Program

WWT Woreda WaSH Team

WYCB Women, Youth and Children Bureau

Page 7: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

1

1 EXECUTIVE SUMMARY

The COWASH project has two components. Component 1 strives to strengthen the federal

level capacity for implementation of the CMP approach and to support the overall WaSH sector

development process including the establishment and implementation of One WaSH National

Program (OWNP).

Under Component 1, a number of activities were planned to be conducted by COWASH FTAT at

the federal level and in the regions in the first quarter of 2007 EFY. The main achievements in

the quarter were the following:

Combined Rural Water Supply O&MM Manual for Rural Piped Schemes (RPS) and

Pastoralist areas and Generic O&MM Strategic Framework underdevelopment:

The development of the manual and strategic framework started in 2006 EFY continued in

the reporting period. Thus far, the consultant submitted 7 of the 18 parts (39.0%) of the

manual and the task force members commented on these parts of the manual submitted.

The consultant is working as per a content approved by the task force and the strategic

framework is to be started as per its own content. COWASH is strictly following and

providing technical assistance for the development of the manual and strategic framework.

GLOWS/WSP training manual translated into Amharic: A GLOWS/WSP training

manual was developed by MetaMeta. It was found necessary to translate the manual into

the working languages of the project regions so as to ease GLOWS/WSP trainings at the

grassroots level. Cognizant of the importance of this manual for woreda and kebele staff,

COWASH hired a short term consultant for the translation and the translation of the

manual into Amharic has been done in the reporting period. The translated manual was

reviewed by some Amhara RSU staff and COWASH FTAT so that it can be used for the

upcoming GLOWS/WSP trainings in the regions.

1 PhD level research underway and 1 MSc level CMP Research sponsored: The

project has been carrying out the on-going PhD level research and the newly started

Master’s level research entitled “Assessment of Potable Water Access & Users’ service

satisfaction in Gonji Kolella woreda rural communities during CMP implementation”.

1 Case Study on the Impact of CMP Water Supply in Gonji Kollela Woreda

conducted: A case study was conducted, by a short term consultant, on the impact of CMP

water supplies on the life of Abunebla and Besanit village communities in Gonji Kolela

woreda of West Gojjam Zone of Amhara region. It was found out that the implementation

of rural water supply schemes using CMP funding mechanism created sense of ownership

and motivation to rural communities in these villages. Farmers are looking to improve their

livelihood using the excess water from the improved sources and rope pumps.

5 Regions provided Technical Assistance in the preparation of 2007 EFY Planning:

With the view to prepare the 2007 EFY regional plans timely, the COWASH federal technical

assistant team prepared draft planning formats (both physical and financial) and estimated

unit costs and distributed to Regional Support Units (RSUs). With these templates the

regions have started preparing their annual plans.

Human Capacity Building Assistance to Regions:

1) 41 (14.6% female) Woreda, Zone and Regional staff trained by COWASH FTAT

in GIS/M&E: With the view to mapping of project woredas and equipping GIS skills to

Page 8: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

2

woreda, zonal and regional staff, COWASH GIS expert trained 41 regional, zonal and

woreda staff of Tigray and Oromia regions on Quantum GIS, Data Management and

Basic Computer skills. The training was provided in collaboration with MoWIE GIS

department staff and regional water bureau staff of Tigray and Oromia regions.

2) 29 (2 female) COWASH FTAT, RSU and Water Bureau Staff trained for 5 days in

GLOWS/WSP ToT Training: MetaMeta trained a total of 29 RSU, Water Bureau and

COWASH FTAT staff on GLOWS/WSP. These trainees are expected to train woreda and

zonal staff on GLOWS/WSP so as to sustain the water points constructed at the

grassroots level. The Amharic version of the GLOWS/WSP manual was reviewed by

COWASH staff during the training.

2006 EFY Annual Performance Report Prepared and disseminated to stakeholders

of COWASH: In the reporting period, COWASH FTAT prepared and disseminated the

2006EFY performance of COWASH. The report was consolidated by incorporating the

performances of the project regions and Component 1 achievements. The quarterly reports

can be found at http://www.cmpethiopia.org/page/273.

6,500 Table Calendars printed and disseminated: Like the previous fiscal year, the

project planned to produce CMP table calendars. Accordingly, a total of 6,500 copies of the

2007 CMP calendars were produced and disseminated to all 5 regions, zones, woredas and

also to the stakeholders at federal level. These calendars are believed to promote CMP in

the COWASH woredas and beyond.

3 MoWIE staff Participated in Stockholm Water Week 2014 with the sponsorship

of COWASH: COWASH planned to assist MoWIE to participate in Stockholm Water Week

2014. As part of COWASH’s effort to promote CMP at the international and national levels,

the project sponsored 3 MoWIE staff to participate in Stockholm Water Week. Moreover,

The project has also sponsored the stand of MoWIE exhibition, which was successfully

carried out.

1 Training Impact Research Completed: Impact research on the CMP related trainings

held in 2005 EFY in Tigray and Amhara regions has been conducted in 2006EFY by a

private consultant called Lisan Management. The consultant has completed the research

report by incorporating comments and suggestions forwarded by workshop participants and

COWASH FTAT.

CMP Implementation Manual using Public Finance and Procurement Management

System(PFPMS) prepared: Consultants (IRC ad Eyob Defere) financed by UNICEF and

COWASH jointly developed the CMP Implementation Manual using PFPMS with several

stakeholder consultations. This Manual is the mitigation measure included into the One

WASH Program Operational Manual (POM) also finalized in 2006 EFY. The Manual to be

annexed to POM. The manual is to be presented to MoWIE before it is submitted to MoFED

for approval.

Component 1 Budget Utilization: The total cumulative COWASH Component 1 (C-1) five

year financial plan (2004 – 2008 EFY) is EUR 3,730,410. The actual cumulative expenditure

of COWASH C- 1 at the end of Sept. 2014 was EUR 2,216,845. This accounts 59.0% of the

total allocated for the five years of the project. Delay in the approval of the revised

COWASH Project Document is the main reason for the low budget utilization. In the

reporting period, a total of about EUR 212,189 (104.0% of the total allocated for the

quarter, EUR 204,740) was utilized for the activities planned under Component 1 of the

project.

Page 9: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

3

Component 2 of the project deals with “Establishing and Strengthening the Capacity in

Regions to Scale-up Implementation of CMP”. Regions have been preparing their 2007 EFY

annual plan in the reporting period. Regional plans have not been approved in the reporting

period and hence, there have not been much activities performed in the quarter. Anyhow,

some activities rolled over from 2006 EFY have been accomplished in the reporting period.

Increasing the Number of CMP Woredas: The number of woredas implementing the

CMP approach has been on the rise. In 2003 EFY, only 26 woredas in Amhara (19 by

RWSEP and 7 by UNICEF and 5 woredas in Benishangul-Gumuz) have been implementing

CMP. This accounts for 16% of the 166 woredas in Amhara Region and 24% of the 21

woredas in Benishangul-Gumuz region, respectively. In 2004 EFY, the approach has been

implemented in 44 woredas in Amhara, Tigray, SNNPR and BSGR, which is 7% of the

woredas in the four regions. In 2005 EFY, the share of CMP woredas in the 5 regions,

including Oromia, has increased to 9 %. According to the COWASH revised project

document, 23 new woredas (13 in Amhara, 3 in Tigray, 4 in SNNPR and 3 in Oromia) were

encompassed by the project in 2006 EFY. In 2007 EFY, the number of woredas

implementing CMP approach increased to 76 (13.0% of the rural woredas) in the five

regional states of the country.

Construction of Water Points: As the preparation and approval of the 2007EFY annual

plan of regions was delayed and the rainy season in many of the project woredas, many

regions have not conducted construction of water points and institutional latrines. Anyhow,

SNNPR has completed the construction of 20 On-Spot Springs started in the previous fiscal

year. These community water points are benefiting more than 7,658 rural people.

Reports of the regions reveal that the aggregate number of water points constructed in

COWASH woredas with the CMP approach has been increasing. Thus far, 5,054 water

points (4,150 in Amhara, 224 in Tigray, 199 in SNNPR and 481 in Oromia) were

constructed in the COWASH woredas of four regions. Of these, 4,760 are built by

communities themselves with the support of COWASH and 294 for institutions (235 for

schools and 59 for health institutions) with COWASH’s financial and technical support. The

4,760 water points built by communities are benefiting more than 1.2 million rural people

in the COWASH/CMP kebeles of the four regions. Over 89,887 students and teachers and

12,968 staff of health facilities and clients of the institutions are benefiting from the 294

institutional water points.

Rehabilitation of Water Points: No rehabilitations reported from regions in the reporting

period. To date, a total of 315 water points (288 in Amhara, 12 in Tigray, 8 in SNNPR and

7 in Oromia regions) have been rehabilitated since the launching of the COWASH project.

The rehabilitation of these water points will improve the functionality rate and water supply

coverage of the project woredas. More than 79,263 rural people and 2,314 students and

teachers are benefiting from these rehabilitated water points through the CMP approach

with the support of COWASH.

Institutional Latrine Construction: There was no institutional latrine constructed

completed in the reporting period. Since the introduction of COWASH in the regions, a total

of 99 institutional latrines (61 for schools and 38 for health facilities) were constructed in

the four project regions. More than 65,779 teachers, students, health staff and clients of

the health facilities are using these latrines. These latrines would contribute in improving

the sanitation and hygiene situation of the schools and health institutions in the woredas.

Page 10: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

4

The number of institutional latrines constructed is less than the figure reported in 2006 EFY

as Tigray region wrongly included 8 on-going latrines.

From the total Euro 22 million allocated by the Government of Finland for the project,

about Euro 18,269,590 is allocated for Component 2 of the project. This was apportioned

into the five project regions based on funding agreements signed between the Government

of Finland and Finance Bureaus of the regions. Since then the project regions have been

receiving funds (Euro) from the Ministry for Foreign Affairs of Finland (MFA) as per their

funding agreement. The total amount of Euro received by each region thus far is indicated

in the following table. Of the total amount of Birr 233.1 million transferred from MFA about

72.5% has been utilized by the regions until end of Oct. 10, 2014.

Table 1: Amount of Funds (in EURO and Birr) transferred from MFA to Project Regions until Oct.10, 2014

Project Region

Amount of Euro

Agreed for 5

Years

Amount of Euro

Transferred from MFA

until 10th Oct. 2014

Amount

Transferred from

MFA (in Birr) until

10th Oct.2014*

Amount utilized

(in Birr) until

10th Oct. 2014

%

Utilized

Amhara*10,310,578.00 7,177,051.71 179,238,149.79 130,683,903.24 72.9

Tigray2,184,299.00 609,257.77 14,600,276.83 13,395,341.60 91.7

SNNPR1,746,084.00 649,675.00 16,084,498.38 11,610,201.50 72.2

Oromia1,766,000.00 603,267.00 14,839,248.47 13,279,408.00 89.5

BSGR2,262,629.00 324,796.00 8,332,614.38 0.00 0.0

Total18,269,590.00 9,364,047.48 233,094,787.85 168,968,854.34 72.5

Page 11: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

5

2 OVERALL OBJECTIVE ACHIEVEMENT

The overall objective of COWASH is ‘to achieve universal access to WaSH in the rural

areas of Ethiopia’. The project tries to attain this objective through implementing Component

1 at the federal level and Component 2 in the regions through the adoption and application of

Community Managed Project (CMP) approach. Complete information on the contribution of the

project in improving the water supply, sanitation and hygiene situation of the project woredas

will be presented in the detailed report that will be prepared upon the receipt of regional

reports.

3 PROJECT PURPOSE ACHIEVEMENT

Within the framework of the overall objective described above, the project purpose is to

“Support the acceleration of UAP-rural water and sanitation targets attainment

through the establishment of an enabling environment and the implementation of

CMP interventions in selected rural areas of Ethiopia”. Thus, COWASH strives to provide

support for developing the enabling environment at the federal level and in the project regions

where hydro-geological conditions are suitable for its replication.

The key indicators for the verification of the achievement of the Project purpose are:

i) Percentage of Regions implementing CMP approach; ii) Percentage of Woredas of targeted

regions implementing CMP approach; iii) Percentage of Kebeles of targeted woredas

implementing CMP approach; iv) Percentage of rural people that has access to potable water

through COWASH; and v) Amount of regional budget allocated for COWASH.

The number of regions implementing CMP has increased from two regions (22.2% of the 9

administrative regions of Ethiopia, excluding the city administrations of Addis Ababa and Dire

Dawa) in 2003 EFY to five regions (55.6%) in 2007 EFY. Benishangul Gumuz region is

encompassed by COWASH in 2007 EFY as delay in the preparatory activities delayed the

implementation of activities in 2006 EFY.

The number of woredas implementing CMP approach is increasing. In 2003 EFY, only 26

woredas in Amhara (19 by RWSEP and 7 by UNICEF) and 5 woredas in Benishangul-Gumuz

have been implementing CMP. This accounts for 17 % of the 153 rural woredas in Amhara

Region and 25 % of the 20 rural woredas in Benishangul-Gumuz region, respectively. Including

the FinnWASH-BG woredas, in 2007 EFY, the approach is being implemented in 13.0 % of the

woredas in the project regions (40 in Amhara, 7 in Tigray, 8 in SNNPR, 12 in Oromia and 9 in

BSG). In all, the number of COWASH/CMP woredas has been increasing from 6.4% in 2004

EFY to 12.2 % in 2007 EFY.

The actual number of project kebeles could not be reported as regional plans are still under

preparation and number of kebeles to be encompassed by the project in 2007 EFY are not yet

known. Besides, total beneficiaries and budget allocated awaits the regional plans to be

approved by the respective Regional WASH Steering Committees.

Page 12: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

6

4 COMPONENT 1: STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT

COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT TO THE

ESTABLISHMENT OF THE ONE WASH NATIONAL PROGRAM

Component 1 of the COWASH project strives to strengthen the federal level capacity for

implementation of the CMP approach and to support the overall WaSH sector development

process. It also strives to support the establishment and implementation of One WaSH

National Program. In order to scale-up the CMP approach, tools in planning, implementation

and monitoring mechanisms were developed for a wider application of the CMP approach.

Networking and coordination activities have been performed to promote CMP and generate

more funds for CMP implementations thereby accelerate the WaSH interventions in water

supply access, sanitation and hygiene.

In 2007 EFY, the project planned to widen and deepen its support in achieving the GTP targets

of WaSH by providing technical and financial support to NWCO and other stakeholders of the

project. The Component 1 major activities performed during the reporting period are

presented under the outputs indicated below (Component 1 detailed activities performed in the

quarter are attached in Annex 1). It should be noted that all the activities performed by the

federal COWASH team do not automatically belong to Component 1 but support directly

Component 2 (the project regions).

4.1 RESULT 1 OF COMPONENT 1: COMMUNITY MANAGED PROJECT APPROACH

SCALED-UP AT NATIONAL LEVEL

4.1.1 Output 1: Manuals and Guidelines Reviewed and Developed for Standardizing

the CMP Implementation within the WaSH Implementation Framework

The achievement of the output is measured by the three indicators: i) number of generic CMP

implementation guidelines harmonized with WIF and incorporating crosscutting issues

developed and implemented, ii) number of tested higher technology options reviewed and

incorporated into CMP manuals and guidelines and iii) number of generic O&MM

manuals/guidelines for rural water supply developed.

A number of manuals/guidelines have been prepared in the last fiscal years. Some main

activities were planned to be executed in the reporting period: i) Participate as a member of

the Task Force in the development of Generic RPS and Pastoralist areas Water Supply O&MM

Manual and Strategic Framework; ii) Provision of technical assistance in the development of

GLOWS/Water Safety Planning Guideline for CMP point water schemes; iii) Assist in the

approval of the CMP Implementation Manual by the MoFED; and iv) Develop new CMP financial

management manual training materials using Public Financial Management System (PFMS) in

CMP Implementation.

The analysis of the status of the above and some other documents and manuals is presented

below.

4.1.1.1 Participation in the Task Force in the Development of Generic Rural Water Supply O&MM RPS and Point Water Schemes and Generic O&MM Strategic Framework

The guideline and strategic framework have been under preparation in the last fiscal year

based on the table of content prepared based on comments and suggestions of a half-day

meeting of the taskforce established to lead the assignment. The preparation of the manual

Page 13: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

7

and framework has continued in the reporting period with the overall guidance of the

taskforce. So far, 7 of the 18 parts (5 parts of Volume I and 2 Parts of Volume II) of the report

(39.0%) were submitted to the taskforce and 4 of them already commented by the taskforce

and comments and suggestions given to the consultant. The parts of the report prepared are:

Technical O&M Requirement for RPS (Volume I)– Part B: Water Resources for Water Supply,

Part C: Electro-Mechanical Equipments, Part D: Transmission and Distribution System, Part E:

Spare Part Supply and Management, and Part H: Asset Management for Water Supply;

Management Requirement for O&M for RPS (Volume II)- Part A: Financial Management and

Part B: Community Based Management. The strategic framework is being prepared and the

whole assignment (including the remaining parts of the report and the strategic framework) is

expected to be finalized in the upcoming quarter of the fiscal year.

4.1.1.2 Translation of GLOWS/WSP Guideline into Amharic

COWASH planned to promote and implement GLOWS and Water Safety Planning

(GLOWS/WSP) in its project woredas. For this purpose the English version of the GLOWS/WSP

guideline should be translated into working languages: Amharic, Oromifa and Tigrigna. The

training guideline has been translated into Amharic by a private consultant experienced in

GLOWS and commented by COWASH FTAT and some experienced Amhara RSU. It is planned

to translate the Amharic version into Oromifa and Tigrigna so that it can be used in the

trainings in Tigray and Oromia woredas.

4.1.1.3 Developing GIS based mapping trainers manual

It was planned to prepare a manual for GIS training of regional, zonal and woreda staff of

project regions. Accordingly, the GIS Expert has prepared a training manual and distributed to

trainees in digital and hardcopy during the GIS trainings in the regions.

4.1.1.4 Editing of the Point Source O&M Manual for rural water supply

It was planned to edit the Point Source O&M Manual completed last fiscal year to make it

suitable for training at the grassroots level. The activity has not yet been started as it was

found important to make the editing together with the RPS O&MM manual under preparation.

4.1.1.5 Preparation of CMP Implementation Manual based on the Public Financial Management Sytem

(PFMS)

The preparation of the CMP Implementation Manual based on the Public Financial Management

System by private consultants has been completed and ready to be presented to MoWIE. The

manual was deliberated at a half-day workshop and all the comments have been incorporated

However, the manual could not be presented to MoWIE mainly due to engagement of officials

on priority issues both at home and overseas.

The delay in the submission of the manual for MoFED’s approval has in turn delayed a number

of activities to be implemented to put the manual into effect.

Page 14: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

8

4.1.2 Output 2: Tools and Mechanisms Reviewed and Developed for Standardizing

the Planning, Implementation and Monitoring of CMPs

Four indicators were set to measure the achievement of the output, namely, i) number of

annual plans prepared; ii) number of quarterly reports prepared and disseminated to partners;

iii) M&E framework developed; and iv) number of federal level steering committee meetings

conducted.

As in the previous implementation years, as indicated in Annex 1, a series of activities that are

believed to contribute for the achievement of the output were planned to be carried out in the

reporting period. The status of some of the main activities is presented as follows:

4.1.2.1 Preparation of Annual Plans

COWASH FTAT has been assisting in the preparation of regional plans. Planning templates

(physical and financial) and unit costs were prepared and distributed to RSUs to modify them

to be suitable to their situation and employ them in their planning exercises. All of the regions

have been preparing their 2007 EFY annual plans based on the templates and COWASH FTAT

are assisting the RSUs in the preparation of their plans. All of the regions have been working

to finalize their detailed planning at the beginning of the 2nd quarter of the fiscal year.

4.1.2.2 Participation in Federal and Regional WaSH Steering Committee Meetings

National and Regional WaSH Steering Committee meetings are expected to be made twice a

year. COWASH facilitates the meetings and provides technical assistance for undertaking these

meetings. Usually, quite a lot of issues and challenges hindering the implementation of the

project are raised and deliberated and important decisions made during these meetings. In

the reporting period, only one National Wash Steering Committee (NWSC) meeting was held in

July 2014. Component 1 achievement in 2006 EFY and the 2007 EFY plan were discussed

during the meeting; a Minute of Meeting (MoM) was prepared and signed by the respective

members of the NWSC and the 2007 EFY annual plan started to be implemented.

4.1.2.3 COWASH Quarterly Report Preparation

Every fiscal year, COWASH is expected to prepare four progress reports – one annual report

and three quarterly reports and one annual report. Accordingly, the 2006 EFY annual report

was prepared (100.0%) and distributed to all stakeholders of the project. Moreover, a

summarized version of the Results-Based Report is still being prepared. The annual report was

prepared based on the four regions annual performance reports and Component 1

performance.

4.1.2.4 Indicator Monitoring Plan Preparation

COWASH planned to complete the indicator monitoring plan preparation of four regions.

Accordingly, the indicator monitoring plans of three regions (Amhara, SNNPR and Oromia)

have been completed (75.0%) and the preparation of the Tigray indicator monitoring plan is

underway.

4.1.2.5 Production of WASH facility maps for each COWASH woreda

COWASH planned to produce 67 maps (one for each project woreda) in the fiscal year, of

which 10 were planned for the reporting period. Accordingly, the GIS expert produced 10

Page 15: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

9

woreda maps (100.0%) and the maps for the majority of the project woredas are to be

produced in the upcoming quarters.

4.1.3 Output 3: CMP Approach within the Rural WaSH Scientifically Researched

Three indicators are set for measuring the achievement of this output. These are: i) number of

CMP researches (disaggregated by Doctoral, Masters and Bachelor levels) completed;

ii) number of published articles on CMP research results; and iii) number of CMP research

result presentations given in international conferences.

So far, one PhD level research is underway and 3 MSc level and 1 BSc level researches on CMP

were completed with the financial and technical support of COWASH. All the completed

researches are uploaded in the website www.cmpethiopia.org. Some activities have been

carried out in the reporting quarter. The main ones are indicated below:

4.1.3.1 Continuation of the PhD level research

This fiscal year, the PhD level research has continued. In this reporting period, an article

entitled ‘Evolution of Community Managed Projects (CMP) from 1994 to 2010 in Ethiopia’ to be

published on international journal has been completed by the PhD researcher. The article has

been commented by CTA and Tampere University of Technology. The article is being shaped to

be sent for publication in a reputable journal.

4.1.3.2 New MSC level research

A new MSC level CMP research was started and COWASH has provided financial support to the

MSC level research being conducted in Gonji Kolela woreda of Amhara region. The research is

entitled “Assessment of Potable Water Access & Users’ service satisfaction in Gonji Kolella

woreda rural communities during CMP implementation”.

4.1.3.3 Case study on the Impact of CMP Water Supply in Gonji Kolela Woreda

COWASH has conducted a case study on the impact of CMP water supplies on the life of rural

community in Gonji Kolela woreda of West Gojjam Zone of Amhara region. It was found out

that the implementation of rural water supply schemes using CMP funding mechanism created

sense of ownership and motivation to rural communities in Abunebla and Besanit village. Since

the introduction of this approach in the area, rural communities have understood the value and

ownership of water resources. Farmers are looking to improve their livelihood using the excess

water from the improved sources and rope pumps. All households visited stopped open

defecation and practice hand washing at critical moments.

4.1.4 Output 4: Information, Education and Communication (IEC) on CMP

Implementation Modality Enhanced

The major indicators for measuring the achievement of the output are: i) Communication

strategy developed; ii) Number of major international and national events (workshops,

seminars, conferences, symposiums) where CMP awareness is raised through COWASH

participation; and iii) Number of CMP related information and education materials prepared

and published (disaggregated by types).

As indicated in Annex 1, a number of communication-related activities were planned for the

reporting period. The major ones and their status are indicated hereunder:

Page 16: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

10

4.1.4.1 Production and distribution of table calendars with CMP incorporated

COWASH produced its own table calendars in the first month of the reporting period. A total of

6,500 CMP table calendars (100.0%) were produced and disseminated to all 5 regions, zones,

woredas and also to the stakeholders at federal level. These calendars are believed to promote

CMP in the COWASH woredas and beyond.

4.1.4.2 Participation in selected International conferences, networking and forums

COWASH has been supporting participation in international conferences, networking meetings

and forums so as to promote CMP at the international and national levels. This reporting

quarter, it was planned to participate 3 MoWIE staff in Stockholm Water Week 2014.

Accordingly, Abiy Girma (NWCO), Nuredin Muhammed (WSSD) and Lakech Haile (WCYD)

participated in the conference with the sponsorship of COWASH. The project has also

sponsored the stand of MoWIE exhibition, which was successfully carried out.

4.1.4.3 Water Credit Market Assessment Report Dissemination Workshop

The water credit market assessment was carried out by M2i consultants from India with the

support of Water.Org and co-operation of COWASH. A workshop was organized jointly with

Water.org, WaterAid and COWASH on July 23, 2014. A total of 73 participants (7 female)

participated in the one-day event facilitated by COWASH CTA. In this workshop, findings and

experience of the WASH/MFI workshop held on October 2012 was presented by COWASH CTA

and experiences from Kenya, Uganda and India were also presented at the workshop.

COWASH also assisted in the commenting the data collection instruments and draft report.

4.1.4.4 Updating CMP WEB page

The official CMP website (www.cmpethiopia.org) was developed in collaboration with IRC to

disseminate basic information on CMP and attract more funding for the country. In the

reporting period, it was planned to update the website thrice and accordingly, the website was

updated as planned and a number of documents has been uploaded. This website assists any

person interested of the Ethiopian WaSH sector to access major WaSH related documents.

COWASH has been receiving appreciations from many international and national organizations

for availing important WASH related documents at the CMP web page.

4.2 RESULT 2 OF COMPONENT 1: CMP IMPLEMENTATION CAPACITY AT THE

FEDERAL AND REGIONAL LEVELS DEVELOPED

4.2.1 Output 1: Capacity Building Instruments Reviewed and Developed

The achievement of the output is to be measured by three indicators: i) Generic CMP capacity

building strategy developed; ii) Generic woreda level capacity building package developed;

and iii) number of impact assessments made on CMP related trainings (one in each project

region).

The project has developed generic CMP capacity building strategy and generic woreda level

capacity building package in the previous implementation years. The capacity building

strategy has been revised every year to capture new developments in the WaSH sector.

Moreover, training impact assessment on trainings conducted in 2004 EFY was completed

and an in-depth study was conducted on CMP trainings conducted in 2005 EFY in Amhara and

Page 17: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

11

Tigray regions. One of the main activities planned for the reporting period was the completion

of the training impact research. Accordingly, the research report was completed by the

consultant by including all the comments and suggestions forwarded by stakeholders:

development partners, MoWIE representatives and COWASH federal and regional unit staff.

The report is uploaded to the CMP website http://www.cmpethiopia.org/page/184.

4.2.2 Output 2: Capable and Adequate Personnel in place for CMP Implementation at

National and Regional Levels

Number of people hired at federal and regional level (disaggregated by sex), number of

trainings given by the federal COWASH team and number of people participated in trainings

(disaggregated by sex) are the indicators set to measure the achievement of the output.

COWASH planned to carry out a number of capacity building activities in the first quarter of

2007 EFY. The activities were planned to be conducted at the federal and regional levels. The

major activities and their achievements in the reporting period are the following.

4.2.2.1 Hiring of Staff for Phase II of COWASH

Ramboll hired all staff needed for COWASH Phase II as per the revised project document. All of

the COWASH Phase I national staff continued to Phase II and some additional staff

(Crosscutting and Communication Specialists) were included. The new national and

international staff will assume their posts until November 2014.

Moreover, it was planned to provide technical assistance to Water Bureau of BSG region in the

hiring of 4 RSU staff. In the reporting period, ToRs were sent and technical assistance in

recruitment process was given to the bureau. So far, 4 Specialists posts advertised and about

60 applications received by the Water Bureau. However, screening of the applications was

delayed due to some competing activities in the different offices.

4.2.2.2 GIS/M&E Training

COWASH planned to map out its project woredas with all (community and institutional water

points and institutional latrine) facilities constructed over the years. For this purpose, training

of regional and woreda staff in Quantum GIS, Data Management and Basic Computer skills

were planned and executed. In the period under reporting, two trainings (for 7 woredas and

regional staff of Tigray region and 5 woreda and regional staff of Oromia region) were

conducted by the GIS expert in collaboration with GIS department staff of MoWIE, COWASH

FTAT and regional water bureaus. A total of 41 woreda, zone and regional staff (24 in Tigray

and 17 in Oroima) have received training in the reporting period. Of these trainees, 14.6 %

were female (1 in Oromia and 5 in Tigray). As a result, some woreda and regional staff have

started to collect more data of water points and latrines and produce maps of their woredas

with facilities constructed with the support of COWASH. Training of woreda, zone and regional

staff in Amhara and remaining woredas and zones of SNNPR and Tigray regions is scheduled to

be conducted in the coming quarters of the fiscal year.

4.2.2.3 GLOWS/WSP Training

COWASH is promoting and implementing GLOWS/WSP in view of sustaining facilities it has

been supporting in the project woredas. To attain this objective, the project has started

training staff at the federal and regional levels to cascade the capacity building down the

Page 18: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

12

administrative ladder of the project regions. This quarter, 3 COWASH FTAT were trained by

MetaMeta for 3 days in GLOWS/WSP together with other trainees constituted from different

organizations based in Addis Ababa. Moreover, COWASH in co-operation with MetaMeta

conducted ToT training in GLOWS-Rural Water Safety Planning (GLOWS/WSP) for 5 days. A

total of 29 staff (2 female, one each from MetaMeta and COWASH) of COWASH FTAT, RSU and

Regional Water Bureaux received the training sponsored by COWASH.

Trainees of GLOWS/WSP learnt how to facilitate rural water assessments and action plans

preparation in water safety planning. GLOWS modules 1-10 and Kebele Water Safety Plan

Guideline provided the main resources for the training. The participants learned kebele water

safety plan preparation and its concept from resource protection to the point of use of water.

They also learned to understand the participatory approach, how to facilitate the woreda staff

trainings to become more participative and how to develop support materials to be used in participatory

training. During the training, the Amharic version of the training manual was reviewed and made ready for

training in the woredas and kebeles. The English and Amharic versions of GLOWS manual and Kebele WSP

Guideline were uploaded to the CMP web page http://www.cmpethiopia.org/page/401. The plan is to

publish these Amharic documents in a book so that they can be adequately used at woreda level.

4.2.2.1 CMP Management Training in BSG Region

COWASH FTAT planned to carry out CMP management, appraisal and WASHCO CMP

management ToT trainings in BSG in the reporting period. However, these trainings could not

be provided as the region could not speed up the start up activities to start implementation of

activities were delayed in the region.

4.3 RESULT 3 OF COMPONENT 1: DEVELOPMENT AND IMPLEMENTATION OF

ONE WaSH NATIONAL PROGRAM SUPPORTED

In the One WaSH National Program development, COWASH is accountable for the provision

of technical assistance and financial support as per the mutually agreed terms of references.

COWASH is not, however, responsible in the development and implementation of One WaSH

National Program.

4.3.1 Output 1: COWASH Support Provided in Preparing One WaSH National

Program

Number of short term consultancy days provided by COWASH for the development and

implementation of One WaSH National Program, and amount of finance provided for the

development and implementation of One WaSH National Program are the indicators set to

measure the achievement of this output.

The COWASH support (technical and financial) to NWCO in the preparation of the OWNP Phase

II document and participation in the task force are planned for the upcoming quarters.

4.3.2 Output 2: COWASH Support Provided in Implementation of One WaSH National

Program

Number of people trained in CMP implementation in non-COWASH regions by federal

COWASH and number of federal level advisers assigned in the One WaSH National Program

management are the two indicators set for measuring the achievement of the output.

Page 19: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

13

This quarter, COWASH planned to participate and provide technical and financial support in the

first Joint Technical Review of the fiscal year (JTR 9) and development of the national Water

Safety Plan Guideline. It was also planned to provide technical assistance in the development

of planning and reporting formats of OWNP upon request of the NWCO.

However, much of these activities have not been conducted as planned due to delay in the

preparatory activities. Anyhow, COWASH TA provided technical input to the development of

Climate Resilient Water Safety Guideline preparation. A ToR was prepared by the MoWIE on

Climate Resilient Water Safety Plan implementation and on establishment of Task Force. The

ToR was presented to COWASH TA by a consultant. The document was discussed in detail and

revision was made. COWASH provided its feedback on the questionnaires prepared by WHO on

the experience of COWASH in WSP in Amhara region. The first Task Force meeting was

postponed to 2nd Quarter. COWASH didn’t provide any technical assistance in JTR 9 and

development of OWNP planning and reporting formats as it was informed that JTR 9 has been

postponed to the upcoming quarter and no specific request presented to COWASH.

5 COMPONENT 2: ESTABLISHING AND STRENGTHENING THE CAPACITY IN

REGIONS TO SCALE-UP IMPLEMENTATION OF CMP

The two components in the original project document (Component 2 & 3) are merged into one

Component in the revised project document. This new component aims at building the capacity

of target Regions, Zones and Woredas to plan, manage, monitor and implement WaSH

interventions through the CMP approach; deliver financial and procurement services for CMP

interventions at all levels; and to increase the sustainable community and institutional access

to safe water, sanitation and hygiene in the target areas.

The 2007 EFY annual plans of regions have not yet been finalized and as a result the woredas

have been undertaking only some activities rolled over from 2006 EFY. Many of the activities

rolled from the previous fiscal year have not been accomplished due to the rainy season in

many parts of the project woredas. Anyhow, some activities performed in the reporting period

are presented; however, they cannot be compared with the quarterly targets as annual plans

have not been approved.

5.1 RESULT 1 OF COMPONENT 2: TARGET REGIONS, ZONES AND WOREDAS

CAPABLE TO PLAN, MANAGE, MONITOR AND IMPLEMENT RURAL WaSH

INTERVENTIONS USING CMP APPROACH

The major achievements of the regions in the reporting period in planning, managing,

monitoring and implementing WaSH interventions through CMP approach are presented in the

following output levels.

5.1.1 Output 1: Regional Support Units (RSU) Established and Functional

Number of Regional Support Unit (RSU) staff hired (disaggregated by region and sex), number

of annual COWASH work plans produced and number of COWASH quarterly and annual reports

produced as per the annual plan are set to measure the achievement of this output of

Component 2.

Adequate staff has been hired in the regions in previous years of implementation of the

project. What was remaining was the hiring of Benishangul Gumuz region RSU staff. The hiring

Page 20: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

14

of 4 RSU staff has been underway with the assistance of the COWASH FTAT in the reporting

period.

Like any other region of the country, all project regions are expected to prepare and approve

their annual plans of a fiscal year before the fiscal year starts. However, the annual work plans

of all the project regions have not been completed in the first quarter of the fiscal year. The

delay in the preparation and approval of the plans has been delaying implementation of the

activities rolled over from 2006 EFY. The plans could not be prepared timely due to one or

more of the following reasons: i) delay in the announcement of shares of the annual budget of

the woredas and zones from the regional governments and other competing activities in the

regions.

With regards to performance reports, RSU of the respective region are expected to prepare

four reports per fiscal year- three quarterly and one annual report. In the reporting period,

RSUs of the four COWASH regions (Amhara, Tigray, SNNPR and Oromia) have prepared and

submitted the 2006 EFY annual physical and financial reports.

5.1.2 Output 2: Regions, Zones and Woredas Capacitated to Implement Rural WaSH

through CMP

Number of trainings types held by region, zone and woreda (disaggregated by type of

training), number of people (disaggregated by sex and type of training) participated in

trainings given by regions, zones and woredas and number of water pints and institutional

latrines built as per plan (proxy indicator) are the indicators set to measure the achievement

of the output.

The scaling-up of the CMP approach requires extensive human capacity building activities at

the regional, zonal and woreda levels. A number of trainings rolled over from the previous

fiscal year were expected to be conducted in the reporting period. However, very few human

capacity building activities have been carried out only in SNNPR during the reporting period

mainly due to delay in the preparation of annual plans and presence of competing activities in

the woredas. Many of the regions didn’t conduct trainings or not reported some trainings

conducted in the woredas.

5.1.2.1 Trainings Conducted in the First Half of 2006EFY

SNNPR woredas were actively engaged in training of stakeholders mainly due to their delay in

carrying out these trainings in the previous fiscal year. Ten types of trainings rolled over from

2006 EFY have been conducted in the reporting period with the capacity building funds leftover

from 2006 EFY (Table 2). The trainings were: 1) O&M training for members of WASHCOs; 2)

CLTSH training for kebele level experts; 3) KWT CMP management, promotion and appraisal

training; 4) WASHCO CMP management training; 5) New Artisans Training; 6) ‘Old Artisans’

refreshment training; 7) Pump attendants and caretakers training; 8) KWT gender awareness

and mainstreaming training; 9) WASHCO water quality training; and 10) Kebele strategic plan

preparation.

Artisan training was one of the trainings conducted in 2 woredas- Chencha and Misha.

Eighteen new artisans (50.0% female) were trained in Misha and 15 previously trained

artisans (26.7% female) were refreshed in Chencha for 7 days. With these artisans, the 2

woredas are ready to start construction in the new kebeles.

Page 21: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

15

A total of 1, 026 woreda and zone staff in SNNPR (43.1% female) have attended these

trainings for 3 to 28 days. Capacity building fund, from Government of Finland (GoF)

contribution, amounting to Birr 270,570 was spend for the trainings.

Page 22: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

16

Table 2: Trainings held in SNNPR in First Half of 2007 EFY

M F T

1

O&M training of new WPs WaSHCOs, tariff collection

& caretaking & Scheme managementWWO 185 124 309 3 235,342 Duna, Gorche &

M isha Woreda

2 CLTSH Training for Kebele Level Experts W HO 37 49 86 5 42,140 Chencha Woreda

3KWT CM P Promotion & Appraisal Training WWO 77 33 110 3 74,702 Es ara , Go rche &

Chencha Wo redas

4WASHCO CMP Management & Implementation

TrainingWWO 77 68 145 4 146,679 Es ara , Go rche &

Mis ha Wo redas

5 New artisans Training WWO 9 9 18 28 49,815 M isha Woreda

6 Refreshment training for old artisans WWO 11 4 15 7 12936 Chencha Woreda

7Pump Attendants & Caretakers Training WWO 80 50 130 5 44,740 Chencha Wo reda

8 Kebele strategic plan in 5 kebeles per Woreda WWO 15 10 25 4 15,000 Chencha Woreda

9 KWT gender awareness & mainstreaming Training WWAO 40 45 85 4 45,406 Chencha & Gorche

10 Training of WASHCOs in Water Quality WWO 53 50 103 4 34,962Chencha Woreda

Total 584 442 1 ,026 270,570

S/

NType of Training

Responsible

body/Trainer

Number Trained

Remark

Estimated cost of

training (in

Birr)1st Quarter

No. of

Days

Trained

5.1.2.2 Workshops and Meetings held in the Regions

All regions were expected to conduct 2006 EFY annual performance review and 2007 EFY

Planning workshop in the reporting period. However, none of the regions organized these

workshops. Anyhow, 2 workshops were reported from Esara and Duna woredas of SNNP

region. Esara woreda conducted review of 2006 EFY performance and 2007 EFY planning

workshop with the attendance of 54 (30 females) woreda staff for 2 days at an estimated cost

of Birr 27,000 from leftover capacity building funds of 2006 EFY. Besides, Duna woreda has

conducted Whole System in the Room (WSR) workshop in the presence of 50 participants (10

females) for 2 days at a cost of about Birr 24,785.

Table 3: Workshops & Review meetings held in the first quarter of 2007 EFY

M F T

1

Annual Review of 2006 EFY

performance and 2007

EFY Planning Workshop

WoW 24 30 54 2 27,000.0 Esara Woreda

4Whole System in the Room

(WSR) workshop W oH 40 10 50 2 24,785 Duna Woreda

Total 64 40 104 51,785.0

Remark

No. of

Workshop

Days

Total Cost of

Workhop/Meetin

g (in Birr)

S/N Type of Workshop/meeting Organizer

Number Attended

1st Quarter

Page 23: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

17

5.1.2.3 Procurements made in the Regions

COWASH aims at building the physical capacity of the implementing institutions so as to

implement the CMP approach in a meaningful and sustainable manner. Much of the

procurement is to be made by the new woredas as the old woredas have already procured

many of the required materials in the previous implementation years of the project. However,

much of the procurements in the new woredas and zones have not been made in the reporting

period as the preparation of the regional annual plans is delayed. Anyhow, few procurements

rolled over from 2006 EFY were made in SNNPR woredas with the funds leftover from 2006

EFY. Procurement has not been made in the other project regions.

In the reporting period, the new woredas of SNNPR procured some (office and field) materials.

The items procured were desktop computers(3), laptop computer(4), printer(4), photocopy

machine(3), filing cabinet(3), motorbike(2), digital camera(3), stabilizer(9), and set of artisan

tools (15). Arbaminch Zuria woreda has also procured one handheld GPS for collecting X-Y

coordinates of the water points and institutional latrines constructed in the woreda. The office

equipments in the new wordas were procured with an estimated cost of Birr 311,068 allocated

from the woredas, zones and regional government while the cost of the GPS was covered from

the GoF contribution. Comparison with the plan was not made as there was no any plan

approved during the reporting period..

Table 4: Materials procured in SNNP region in the First Quarter of 2007 EFY

1 Desktop Computer with UPS No. 3 37,430 Esara & Tocha WWO & WEO

2 Laptop Computer No. 4 61,115 Esara, Tocha & Gorche WWO

3 Printer No. 4 23,825 Esara, Tocha & Gorche WWO

4 Photocopy Machine No. 3 82,810 Esara, Tocha & Gorche WWO

5 Filing cabinet No. 3 16549.99 Esara, Tocha & Gorche WWO

6 Motorbike No. 2 76,497 Tocha & Gorche WWO

7 Artisan tools Set 15

8 Digital Camera No. 3 8,941

9 Stablizer No. 9 3,900

10 Hand held GPS No. 1 7,000 A/Zuriya WWO

318,068

Total cost of the

material

procured in Birr

Quantity

Procured in

the 1st

Quarter

Beneficiary Office(s) of the

material procuredRemarkS/N

Total

Material or Equipment Unit

The water quality test kits planned to be procured in 2006EFY by Amhara region were

accomplished in the reporting period. The region has procured 20 Water Quality Test Kits

rolled over from 2006EFY for woredas.

Page 24: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

18

5.2 RESULT 2 OF COMPONENT 2: FINANCIAL AND PROCUREMENT SERVICES

DELIVERED FOR CMP INTERVENTION AT ALL LEVELS IN THE SELECTED

REGIONS

5.2.1 Output 1: Flow of Funds for CMPs Functional

Some indicators are set to measure the achievement of the output, viz., 1) number of fund

transfer requests done to the financier; 2) number of BoFED audit reports produced

(disaggregated by regions); 3) amount of funds transferred to WASHCOs and 4) amount of

funds settled by WASHCOs.

Opening of bank accounts in new regions, zones and woredas is among the major activities to

be accomplished during the first quarter of the reporting period. Accordingly, Benishangul

Gumuz (BSG) region BoFED has opened account to receive GoF funds and the project zones

and woredas are in the process of opening accounts in the nearby Commercial Bank of Ethiopia

branches. The two new zones and four woredas of Oromia region are expected to open bank

accounts.

According to the funding agreements made between the beneficiary regional Finance Bureaus

and Embassy of Finland, a COWASH region is expected to submit four fund transfer requests

to the Embassy of Finland per year. A new region can request fund for the first and second

quarters of a fiscal year, at a time, for the first year while an old region can request only for a

quarter.

However, only two of the project regions (Amhara and BSG) have made fund transfer requests

in the reporting period. Many of the regions didn’t submit fund transfer requests as their

woredas and zones have leftover funds to accomplish the rolled over activities. Delay in the

preparation and approval of the annual plan was one of the reasons for not requesting fund

transfer. On the date of Sept. 10, 2014, BSG region received EURO 324,796 equivalent to

Birr 8,332,614.38 from Government of Finland as per the core plan prepared for the region.

The project regions are expected to audit the project fund utilization of 2006 EFY in the

reporting period. However, all of the regions except SNNPR have not started the auditing.

SNNPR has submitted the 2006 EFY audit report of 2 woredas (Misha and Duna) and one zone

(Hadiya) and they are finalizing the audit report, which was started in the last quarter of

2006EFY, for Chencha and Arbaminch Zuria woredas, Gamogofa zone and Water Bureau. The

2006 EFY audits were made together with the auditing of the 2005 EFY fund utilization.

Amhara, Tigray and Oromia regions are expected to carry out auditing of the 2006 EFY fund

utilization in the second quarter of the fiscal year.

As WASHCOs have been using the investment fund transferred during the previous fiscal year

there were no many investment fund transfers to MFIs. Complete information on investment

fund transferred to, via MFIs, and amount settled by WASHCOs in each region will be reported

in the annual report of the project.

Page 25: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

19

5.2.2 Output 2: Linkages Created with Private Sector in the Supply of Materials,

Equipment, Tools and Services

Number of new artisans trained by COWASH for WaSH facility construction in the woredas

(disaggregated by sex) and number of awareness raising workshops organized for the private

sector are set to measure the achievement of the output.

Usually, some activities are included in the annual plans of regions and woredas to create

linkage with the private sector at the regional, zonal and woreda levels. The major ones are:

training of artisans; organizing awareness raising workshops to the private sector (pump,

spare parts and construction materials suppliers) on the availability of market opportunities;

carrying out market surveys in the Woredas; and informing communities on the prices of

construction materials, equipment, tools and services based on market surveys made in the

woredas. However, many activities have not been performed in the reporting period due to

delay in the preparation of the annual plans and other priority areas.

5.3 RESULT 3 OF COMPONENT 2: SUSTAINABLE COMMUNITY AND

INSTITUTIONAL ACCESS TO SAFE WATER, SANITATION AND HYGIENE IN

THE TARGET WOREDAS INCREASED

5.3.1 Output 1: Access to Improved Water Sources for Communities and Institutions

Increased

Three indicators are set to measure the achievement of the output. These are, a) number of

new CMP applications submitted to WWT(disaggregated by communal and institutional);

b) number of new CMP applications approved by WWT (disaggregated by communal and

institutional); and c) number of new water schemes constructed(disaggregated by communal

and institutional).

The delay in the preparation and approval of 2007 EFY has been hindering the preparation and

approval of applications form communities and institutions. Therefore, there were no

applications submitted to and approved by WWTs in the reporting period. Besides, as the

reporting period is characterized by a rainy season in the majority of the project woredas and

delay in the approval of the annual plans, there were no many construction activities carried

out in the quarter. Anyhow, 20 On-Spot Springs started in the last quarter of 2006EFY were

completed in Misha and Gorche woredas of SNNP region. The water points are benefiting more

than 7,658 rural people. There were no constructions completed in the other COWASH regions.

On aggregate, until 10th Oct. 2014,, a total of 5,054 water points (4,760 by communities and

294 by institutions) were constructed in 63 woredas through the CMP approach with the

support of COWASH project. Majority of these water points (4,150) were constructed in

Amhara, 224 in Tigray, 199 in SNNPR and 481 in Oromia woredas. In terms of scheme type,

majority of them (71.8 %) are hand dug wells with Afridev hand pump followed by on spot

springs (26.9 %); very small proportion of these water points are shallow wells and hand dug

wells with Rope Pump. The 4,760 community water supply schemes have benefitted over 1.2

million rural people of the project woredas – 1 million in Amhara, 0.60 million in Tigray, 0.64

million in SNNPR and 0.8 million in Oromia region. The 294 institutional water supply schemes

have benefitted 89,887 students and teachers and 12,968 staff of health institutions and

clients.

Page 26: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

20

Table 5: Number of new (community, school and health institution) water points constructed until end of Oct. 10, 2014

HDW

with RPHDW SPD SW DW RWH Total

Populatio

n Served

Popn.

having

Access

within

1.5km

HDW with

RPHDW SPD SW DW RWH Total

Populat

ion

Served

Popn.

having

Access

within

1.5km

HDW

with

RP

HDW SPD SW DW RWH TotalPopulation

Served

Popn.

Having

Access

within

1.5Km of

Amhara 15 3,020 864 13 0 0 3,912 998,578 988,578 0 0 0 0 0 0 0 15 3,020 864 13 0 0 3,912 998,578 988,578

Tigray 0 85 90 33 0 0 208 59,589 59,589 0 0 0 0 0 0 0 0 85 90 33 0 0 208 59,589 59,589

SNNPR 0 8 161 0 0 0 169 56,451 51,114 0 0 20 0 0 0 20 7,658 3,497 0 8 181 0 0 0 189 64,109 54,611

Oromia 0 252 199 0 0 0 451 79,776 73,014 0 0 252 199 0 0 0 451 79,776 73,014

Subtotal 15 3,365 1,314 46 0 0 4,740 1,194,394 1,172,295 0 0 20 0 0 0 20 7,658 3,497 15 3,365 1,334 46 0 0 4,760 1,202,052 1,175,792

Amhara 0 181 10 0 0 0 191 66,686 0 0 0 0 0 0 0 0 181 10 0 0 0 191 66,686

Tigray 0 8 1 2 0 3 14 4,113 0 0 0 0 0 0 0 0 8 1 2 0 3 14 4,113

SNNPR 0 5 3 0 0 0 8 7,109 0 0 0 0 0 0 0 0 5 3 0 0 0 8 7,109

Oromia 0 16 6 0 0 0 22 11,979 0 0 0 0 0 0 0 0 16 6 0 0 0 22 11,979

Subtotal 0 210 20 2 0 3 235 89,887 0 0 0 0 0 0 0 0 0 210 20 2 0 3 235 89,887

Amhara 0 44 3 0 0 0 47 8,074 0 0 0 0 0 0 0 0 44 3 0 0 0 47 8,074

Tigray 0 0 1 1 0 0 2 100 0 0 0 0 0 0 0 0 0 1 1 0 0 2 100

SNNPR 0 1 1 0 0 0 2 445 0 0 0 0 0 0 0 0 1 1 0 0 0 2 445

Oromia 0 7 1 0 0 0 8 4,349 0 0 0 0 0 0 0 0 7 1 0 0 0 8 4,349

Subtotal 0 52 6 1 0 0 59 12968 0 0 0 0 0 0 0 0 0 52 6 1 0 0 59 12,968

Amhara 15 3,245 877 13 0 0 4,150 0 0 0 0 0 0 0 15 3245 877 13 0 0 4,150

Tigray 0 93 92 36 0 3 224 0 0 0 0 0 0 0 0 93 92 36 0 3 224

SNNPR 0 14 165 0 0 0 179 0 0 20 0 0 0 20 0 14 185 0 0 0 199

Oromia 0 275 206 0 0 0 481 0 0 0 0 0 0 0 0 275 206 0 0 0 481

Grandtotal 15 3,627 1,340 49 0 3 5,034 0 0 20 0 0 0 20 15 3,627 1,360 49 0 3 5,054

B. School

c. Health Institution

Total Water Points (Community + School + Health Institution)

A. Community

Region

Number of Water Points Constructed in COWASH Woredas

Cumulative2004-2006 EFY 2007 EFY Q1

Note: HDW with RP - Hand dug well with Rope Pump; SW - Shallow Well

HDW - Hand dug well with Afridev pump; DW - Deep well

SPD - Spring On Spot; RWH - Roof water harvesting

Page 27: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

21

5.3.2 Output 2: Access to Sanitation for Household and Institutions Increased and

Hygiene Behavior Improved

Percentage of ODF kebeles in the COWASH intervention woredas (disaggregated by project

regions), number of new institutional latrines constructed (disaggregated by institutions) are

the indicators of measuring the achievement of the output.

A number of sanitation and hygiene activities have been planned in the previous fiscal years

and some important achievements have been observed in the last three years of

implementation of COWASH. In the reporting quarter, sanitation and hygiene activities have

not been implemented as the approval of the regional annual plans have not been approved.

The cumulative number of institutional latrines constructed until end of the reporting period,

disaggregated by project regions, is presented in Table – below.

Since the launching of COWASH, a total of 99 latrines (61 for schools and 38 for health

facilities) were constructed in the COWASH woredas of the four project regions (Amhara,

Tigray, SNNPR and Oromia) through the CMP approach (Table 6). This accounts 86.8 % of the

114 institutional latrines target set for end of 2006 EFY. A total of more than 63,412 students

and teachers (51.0% female) and 2,367 health extension workers and clients of the facilities

(50.4% female) are using these latrines. The total number of latrines constructed is less than

the figure indicated in the 2006 EFY annual report as Tigray region wrongly included 8 on-

going latrines in its annual report.

Table 6: Number of Institutional Latrines Constructed until end of Oct. 10, 2014

M F T M F T M F T

Amhara 45 25,082 24,117 49,199 0 45 25,082 24,117 49,199

Tigray 9 2,914 2,963 5,877 0 9 2,914 2,963 5,877

SNNPR 2 858 787 1,645 0 2 858 787 1,645

Oromia 5 2,245 4,446 6,691 0 5 2,245 4,446 6,691

Subtotal 61 31,099 32,313 63,412 0 0 0 0 61 31,099 32,313 63,412

Amhara 27 228 206 434 0 27 228 206 434

Tigray 3 20 38 58 0 3 20 38 58

SNNPR 0 0 0 0 0 0 0 0 0

Oromia 8 925 950 1,875 0 8 925 950 1,875

Subtotal 38 1,173 1,194 2,367 0 0 0 0 38 1,173 1,194 2,367

Amhara 72 25,310 24,323 49,633 0 0 0 0 72 25,310 24,323 49,633

Tigray 12 2,934 3,001 5,935 0 0 0 0 12 2,934 3,001 5,935

SNNPR 2 858 787 1,645 0 0 0 0 2 858 787 1,645

Oromia 13 3,170 5,396 8,566 0 0 0 0 13 3,170 5,396 8,566

Grandtotal 99 32,272 33,507 65,779 0 0 0 0 99 32,272 33,507 65,779

No. of

Latrines

Population Served

2007 EFY Q1

No. of

Latrines

Population

Served

2004-2006 EFY

No. of

Latrines

Population Served

Total (School + Health Institution)

Cumulative

Number of Latrines Constructed in COWASH Woredas

A. School

B. Health Institution

Region

Page 28: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

22

5.3.3 Output 3: Sustainability of Communal and Institutional Water Schemes in the

Targeted Woredas Strengthened

Three indicators are set to measure the achievement of the output. These are: i) number of

CMP schemes with trained pump attendants and caretakers (disaggregated by sex); ii) number

of water points rehabilitated (disaggregated by communal and institutional); and

iii) percentage of WASHCOs with more than 50% women members.

A number of activities are expected to be accomplished every year for the attainment of this

output. The main ones are: i) facilitate WASHCOs' legalization as per the regional legalization

regulations; ii) maintain or repair water schemes; iii) provide refresher trainings for members

of existing (old) WASHCOs in O&M management, environment, sanitation, hygiene and

gender; iv) carry out refresher training for existing pump attendants and caretakers and their

replacements in Operation and Maintenance (O&M); and v) assist communities to conduct post

construction public audit annually. However, many of these activities have not been performed

in the reporting period as the annual plans of the regions were delayed and rainy season in

much of the project woredas. Data on the percentage of WASHCOs with 50% or more female

members and trained pump attendants and caretakers are to be indicated in the annual

reports.

Altogether, 315 water points (309 for community and 6 for schools) were rehabilitated in

COWASH woredas between 2004 EFY and first quarter of 2007 EFY. The regional

disaggregation shows that 288 of the water points rehabilitated are in Amhara, 12 in Tigray, 8

in SNNPR and 7 in Oroimia regions (Table 7). The water points rehabilitated benefited over

79,263 rural people and 2,314 students and teachers in the CMP kebeles of project woredas.

Page 29: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

23

Table 7: Number of Water Points Rehabilitated until end of Oct.10, 2014

HDW

with RPHDW SPD SW DW RWH Total

Populatio

n Served

HDW with

RPHDW SPD SW DW RWH Total

Populati

on

Served

HDW

with RPHDW SPD SW DW RWH Total

Population

Served

Amhara 0 206 78 0 0 0 284 68,850 0 0 0 0 0 0 0 0 206 78 0 0 0 284 68,850

Tigray 0 7 5 0 0 0 12 3,000 0 0 7 5 0 0 0 12 3,000

SNNPR 0 4 4 0 0 0 8 6,855 0 0 4 4 0 0 0 8 6,855

Oromia 0 3 2 0 0 0 5 558 0 0 3 2 0 0 0 5 558

Subtotal 0 220 89 0 0 0 309 79,263 0 0 0 0 0 0 0 0 0 220 89 0 0 0 309 79,263

Amhara 0 4 0 0 0 0 4 1080 0 0 0 0 0 0 0 0 4 0 0 0 0 4 1,080

Tigray 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

SNNPR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Oromia 0 2 0 0 0 0 2 1234 0 0 2 0 0 0 0 2 1,234

Subtotal 0 6 0 0 0 0 6 2314 0 0 0 0 0 0 0 0 0 6 0 0 0 0 6 2,314

Amhara 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Tigray 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

SNNPR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Oromia 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Amhara 0 210 78 0 0 0 288 0 0 0 0 0 0 0 0 0 210 78 0 0 0 288

Tigray 0 7 5 0 0 0 12 0 0 0 0 0 0 0 0 0 7 5 0 0 0 12

SNNPR 0 4 4 0 0 0 8 0 0 0 0 0 0 0 0 0 4 4 0 0 0 8

Oromia 0 5 2 0 0 0 7 0 0 0 0 0 0 0 0 0 5 2 0 0 0 7

Grandtotal 0 226 89 0 0 0 315 0 0 0 0 0 0 0 0 0 226 89 0 0 0 315

c. Health Institution

Total Rehabilitated (Community + School + Health Institution)

Cumulative

Number of Water Points Rehabilitated in COWASH Woredas

A. Community

B. School

Region2004-2006 EFY 2007 EFY Q1

Note: HDW with RP - Hand dug well with Rope Pump; SW - Shallow Well

HDW - Hand dug well with Afridev pump; DW - Deep well

SPD - Spring On Spot; RWH - Roof water harvesting

Page 30: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

24

5.3.4 Output 4: Potable Water Quality Ensured in Targeted Woredas

Number of water quality tests (post construction) made on CMP water schemes (new and

rehabilitations); number of chlorination made (post construction) on CMP water schemes (new

and rehabilitations) and number of CMP water schemes with Water Safety Plans are the

indicators set to measure the achievement of the output.

Some of the major activities to be performed to attain the output are: i) chlorination of water

schemes before taken into use; ii) carrying out testing of water quality of water schemes

before taken into use and periodically; iii) train WASHCOs in Water Safety Planning;

iv) conduct periodic water safety planning by WASHCOs; v) procure water quality testing kits

for woredas; and vi) train woreda staff on the use of water quality testing kits. These activities

are planned to be accomplished every fiscal year. However, a number of these activities have

not been conducted in the reporting period due to the delay in the approval of annual plans

and rainy season in many of the project woredas.

With the view to sustain the water points and maintain the quality of the water, training of

trainers on Guided Learning on Water and Sanitation (GLOWS) and Water Safety Planning

(WSP) was given in the reporting period by MetaMeta and, accordingly, GLOWS/WSP will be

piloted in some kebeles of all project regions.

Page 31: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

25

6 FINANCIAL UTILIZATION PERFORMANCE

In this chapter, the financial utilization performance of Component 1 (C-1) and Component 2

in the reporting period is described.

6.1 FINANCIAL PERFORMANCE OF COMPONENT 1

In this chapter, the financial utilization performance of Component 1 (C-1) is presented. The

financial utilization performance of Component 2 will be presented in the detailed quarterly

report of the project that is to be prepared upon receipt of the regional performance reports.

The COWASH expenditures started to build-up already during 2003 Ethiopian Fiscal Year (EFY).

The financial plan and usage of C-1 until the end of the reporting period (September 2007 EFY)

are presented as follows.

6.1.1 Cumulative expenditures

The total C-1 five year budget is EUR 3,730,410 (Table 8). The total usage at the end of

September 2014 is EUR 2,216,845(59.0%). The usage of the fee component, the reimbursable

and capacity building and sector support component are 59.0%, 54.0% and 96.0, respectively.

In the consultancy contract, the reimbursable cost is only a lump sum including the TA-related

reimbursable costs and capacity building costs. Accordingly, the total usage of all reimbursable

(including capacity building support) costs is about 60 %. This shows that the budget for whole

5 years of the project seems to be adequate.

Table 8: Total C-1 Usage Follow-up compared to the 5 year budget (2004-2008 EFY)

Page 32: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

26

Figure 1 below illustrates that the budget utilization of C-1 lags behind when compared to the

planned budget utilization. The budget utilization from the total COWASH 5 year budget at the

end of September 2014 is less by EUR 490,000.

The main reason for the low budget utilization is the delayed approval of the revised COWASH

Project Document and delayed signing of the revised COWASH country level agreement. The

delay of these basic documents has prevented the recruitment of the Junior Professional

Officer, Crosscutting Specialist and the Communications Specialist and the works planned for

them to undertake has been postponed to Phase II. Therefore, many activities planned for

these specialists (climate risk screening inclusion into the CMP implementation process,

crosscutting review of the CMP documents, development of the public audit process, case

study of the women leadership in CMP implementation and other crosscutting issues) have

been postponed and will be implemented in Phase II.

Figure 1. Illustration of the C-1 Budget Utilization based on the 5 year budget period

(2004-2008 EFY)

The revised total budget of the Phase I (up to the end of September 2014) consultancy

contract for C-1 was EUR 2,486,940. From this amount, EUR 1,397,637 was agreed as the fee

budget and EUR 1,150,095 for the reimbursable costs (Second contract amendment June 17,

2014). In the original contract, the consultant’s fee tender included only the international long

and short term consultants and home office coordination. In April 2013, the MFA and the

consultant agreed (Amendment 1) to change “The Ministry's Standard Terms of Payment of

Fees and Reimbursement of Costs, 1.5.2004 (Kolpakkoehdot)” to a new “The Ministry's

Standard Terms of Payment of Fees and Reimbursement of Costs dated on 1.6.2012”. In this

agreement, amendment No 1 the local long term, local short term and Junior Professional

Officer fee-costs were agreed to be included into the “Fee” part of the budget.

Table 9 below illustrates the Component 1 usage of the revised C-1 budget of Phase I.

Page 33: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

27

Table 9. Comparison of the C-1 budget use to the amended Phase I budget of C -1

As can be seen from Table 9 above, the C-1 budget utilization is 89 % and the fee utilization is

about 89 %. The TA-related reimbursable costs usage is 88 % and capacity building support

budget utilization is 95 %. It was estimated that a total of about EUR 270,095 can be

transferred from Phase I to Phase II.

6.1.2 Comparison of the budget utilization with the 3 - months budget of 2007 EFY

The comparison of the 2007 EFY first quarter budget and expenditures is presented in Table 10

below. The explanations for the differences are included under the ‘Explanations’ column of the

table. A total of EUR 204,740 (EUR 113,577 for Fees, EUR 59,375 for Reimbursables and EUR

31,788 for national level capacity building and sector support) was allocated for the reporting

period. Accordingly, about EUR 212,189 was utilized for the planned activities. This represents

about 104.0% of the total allocated for the quarter.

Page 34: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

28

Table 10: Comparison of budget and expenditures of 2007 EFY First Quarter

6.2 FINANCIAL PERFORMANCE OF COMPONENT 2

The financial performances of Project Regions (Amhara, Tigray, SNNPR and Oromia) are

elaborated hereunder. The quarterly financial utilization performance of the regions could not

be presented as the annual financial plans of the regions have not been approved in the

reporting period. Anyhow, the cumulative funds received and utilized by some regions are

presented below.

6.2.1 Financial Performance of Amhara region

As per the revised funding agreement signed between the Bureau of Finance and Economic

Development of Amhara National Regional State and Embassy of Finland, capacity building and

some operational costs are covered from GoF and all investment funds and some operational

costs are covered from GoE.

While all the investment funds from GoE is being channeled to the communities through

Amhara Credit and Saving Institution (ACSI) with a commission of 3% the capacity building

fund from the Finnish Government has been channeled through the government financial

structure.

So far, BoFED of Amhara region has received about Birr 303.00 million (7,177,051.71 Euro or

Birr 179.24 million from Government of Finland including Birr 4,291,860.92 RWSEP savings

and Birr 123.71 million from Amhara Regional Bureaus) for the implementation of planned

activities in the woredas, zones and sector bureaus in the region. Of this amount,

approximately Birr 292.00 million (Birr 168.29 million from GoF and all of the GoE

contribution) has been transferred to beneficiaries of the project until Oct.10, 2014. This

accounts 96.4 % of the total received from the two funding sources-GoF and GoE/Regional

bureaus.

Page 35: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

29

From the total funds transferred to beneficiary sector offices, woredas and zones, about

Birr 233.57 million (80.0 %) has been utilized until end of the reporting period (Table 11). In

terms of fund source, Birr 130.68 million (72.9%) and Birr 102.89 million (83.2%) of GoF and

GoE funds transferred, respectively, has been utilized by beneficiaries of the project.

As indicated in Table 41 below, a total of about Birr 58.43 million (Birr 37.61 million from GoF

and Birr 20.82 million from GoE) is available in the beneficiary sector offices for the first

quarter of 2007 EFY.

Table 11: Funds received, transferred and utilized in Amhara Region until end of Oct.10, 2014

Received

(%)

Transferred

(%)

GoF (2004 EFY,

2005EFY, 2006EFY &

RWSEP saving)

179,238,149.79 168,290,039.09 130,683,903.24 48,554,246.55 37,606,135.85 72.9 77.7

Regional Bureaus

(2004, 2005, 2006EFY

& Balance from 2003

EFY -ACSI )

123,714,027.82 123,714,027.82 102,891,061.42 20,822,966.40 20,822,966.40 83.2 83.2

Total 302,952,177.61 292,004,066.91 233,574,964.66 69,377,212.95 58,429,102.25 77.1 80.0

Usage from

Budget Source

Received from

Source to

date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance

from

Received

Balance

from

Transferred

Note: Of the Birr 179,238,149.79 received from GoF (including the RWSEP savings), Birr 17,051,151.25 is exchange rate gain. All of the exchange rate gains have been added to the annual budgets and

transferred to beneficiary sector offices.

The region will receive Euro 1,214,030 equivalent to Birr 30,223,762.46 in the second quarter

of the fiscal year.

6.2.2 Financial Performance of Tigray Region

The funding arrangement in Tigray is governed by the funding agreement signed between the

Bureau of Plan and Finance of Tigray National Regional State and Embassy of Finland. All the

investment and some operational costs are covered by the Tigray National Regional State

while the (human and physical) capacity building fund is contributed from the Finland

Government. The investment funds and capacity building funds are being channeled in

different ways. All the investment funds from the regional government are being channeled to

the communities through Dedebit Credit and Saving Institution (DECSI) with a commission of

5% while the capacity building fund from the Finnish Government has been channeled through

the government financial structure.

Total funds received from sources (GoE and GoF) and transferred to and utilized by sector

offices to date (end of Oct.10, 2014) in Tigray are indicated in Table 12 below.

Page 36: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

30

Table 12: Funds received, transferred and utilized in Tigray until end of Oct.10, 2014

Received

(%)

Transferred

(%)

GoF19,058,931.22 15,262,305.29 13,395,341.60 5,663,589.62 1,866,963.69 70.3 87.8

GoE27,434,580.64 27,434,580.64 17,029,457.80 10,405,122.84 10,405,122.84 62.1 62.1

Total 46,493,511.86 42,696,885.93 30,424,799.40 16,068,712.46 12,272,086.53 65.4 71.3

Usage from Budget

Source

Received

from Source

to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance from

Received to

date

Balance from

Transferred

to date

Note: Of the Birr 19,058,931.29 received from GoF, Birr 1,672,808.39 is exchange rate gain deposited at BoPF account and not yet utilized. The utilization of this fund will be decided by RWSC

Tigray region received a total of Euro 777,418.77 (equivalent to about Birr 19,058,931.22 of

which about Birr 1.67 million is exchange rate gain) from the Finland Government until end of

Oct.10, 2014- Euro 150,021 (Birr 3.4 million) in 2004 EFY and Euro 459,206.77 (Birr 11.2

million) in 2005 EFY and Euro 168,161 at the beginning of first quarter of 2007 EFY. In total,

the region received about Birr 46.50 million from the two sources for the implementation of

COWASH project in the region - Birr 19.06 million from GoF and Birr 27.43 million from GoE.

Much of this amount has been transferred to beneficiaries of the project. Until end of the

reporting period (Oct.10, 2014), 65.4 % of the amount received (70.3 % of the GoF and 62.1

% of the GoE) or 71.3 % of the transferred (87.9 % of GoF and 62.1% of GoE) has been

utilized for investment (construction of water supply schemes and institutional latrines),

(physical and human) capacity building and covering the operational costs of the project.

6.2.3 Financial Performance of SNNP Region

The funding arrangement in SNNPR is governed by the funding agreement signed between the

Bureau of Finance and Economic Development of Southern Nations Nationalities and Peoples’

Regional State and Embassy of Finland. All the investment, some operational costs and all the

physical capacity building of the new woredas and zones and are covered by the SNNPR while

the (human and physical) capacity building fund for the old woredas, zones and regional sector

offices and all the human capacity building funds for the new woredas and zones is contributed

from the Finland Government. The investment and capacity building funds are being channeled

in different ways. All the investment funds from the regional government are being channeled

to the communities through Omo Microfinance Institute (OMFI) with a commission of 3% while

the capacity building fund from the regional state and Finnish Government has been channeled

through the government financial structure.

Total funds received from sources (GoE & GoF) and transferred to and utilized by sector offices

until end of the reporting period in SNNPR are indicated in Table 13 below.

Page 37: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

31

Table 13: Funds received, transferred & utilized in SNNPR until end of 10 Oct. 2014

Received

(%)

Transferred

(%)

GoF16,084,498.38 15,076,691.26 11,610,201.50 4,474,296.88 3,466,489.76 72.2 77.0

GoE19,073,780.00 15,033,415.14 10,491,126.94 8,582,653.06 4,542,288.20 55.0 69.8

Total 35,158,278.38 30,110,106.40 22,101,328.44 13,056,949.94 8,008,777.96 62.9 73.4

Usage from Budget

Source

Received from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries to

date

Balance from

Received to

date

Balance from

Transferred to

date

Note: Of the Birr 16,084,498.38 received from GoF, Birr 1,007,802.12 is exchange rate gain deposited at BoFED account and not yet utilized. The utilization of this fund will be decided by RWSC and once it is

decided the fund will be included in the annual budget of 2007 EFY.

The SNNPR BoFED received a total of Euro 649,675 (equivalent to about Birr 16,084,494.38)

from the Finland Government- Euro 207,752 (Birr 4,722,037) in 2004 EFY, Euro 219,769 (Birr

5,383,519.70) in 2005 EFY and Euro 222,154 (Birr 5,978,941.68) in 2006 EFY. Until end of

Oct.10, 2014, the region received about Birr 35.16 million from the two sources for the

implementation of COWASH project in the region - Birr 16.10 million from GoF and Birr 19.10

million from GoE. Of this amount, approximately Birr 30.11 million (Birr 15.07 million from GoF

and Birr 15.03 million from GoE) or 85.6 % of the amount received has been transferred to

beneficiary offices. Until 10th Oct. 2014, 62.9 % of the amount received (72.2 % of the GoF

and 55.0 % of the GoE received) or 73.4 % of the transferred (77.0 % of GoF and 69.8 % of

GoE transferred) was utilized by beneficiary institutions in SNNP region.

6.2.4 Financial Performance of Oromia region

The funding arrangement in Oromia is governed by the funding agreement signed between the

Bureau of Finance and Economic Development of Oromia National Regional State and Embassy

of Finland. All the investment and some operational costs are covered by Oromia regional

government while all the (human and physical) capacity building fund and some operational

costs are contributed from the Finland Government. Funds are being channeled in two ways:

all the investment funds from the regional government are being channeled to the

communities through Oromo Credit and Saving Share Company (OCSSCo) with a commission

of 4% while the capacity building funds from the Finnish Government has been channeled

through the government financial structure.

The total fund received and utilized until end of the reporting period, by source, in Oromia

region is presented in Table 14.

The region has received Euro 603,267 (Birr 14,838,248.47) GoF contribution from Ministry of

Foreign Affairs (MFA) of Finland and Birr 23.71 million from the regional government. About

94.1 % of the amount received from the two sources (95.4% of the GoF and 93.3% of the

GoE) was transferred to beneficiary sector offices as per their annual plans approved by the

Regional WaSH Steering Committee (RWSC). Of the total amount of funds transferred to

beneficiary sector offices, 85.6 % (93.8 % of the GoF and 80.3 % of the GoE) has been

utilized. Until end of July 7, 2014, 80.5 % (89.5 % of the GoF and 74.9 % of the GoE) of the

amount received from the sources (GoF and GoE) has been utilized by beneficiary sector

offices including RSU.

Page 38: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

32

Table 14: Funds received, transferred and utilized in Oromia Region until end of Oct.10, 2014

Received

(%)

Transferred

(%)

GoF 14,838,248.47 14,150,357.00 13,279,408.00 870,949.00 1,558,840.47 89.5 93.8

GoE 23,706,573.62 22,112,971.00 17,755,968.00 4,357,003.00 5,950,605.62 74.9 80.3

Total 38,544,822.09 36,263,328.00 31,035,376.00 5,227,952.00 7,509,446.09 80.5 85.6

Usage from Budget

Source

Received from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance from

Received to

date

Balance from

Transferred

to date

Note: Of the Birr 14,838,248.47 received from GoF, Birr 1,207,005.70 is exchange rate gain.

Of this, about Birr 664,273.35 is not yet utilized.

6.2.5 Financial Performance of BSG region

Benishangul Gumuz region has received Euro 324,796 equivalent to Birr 8,332,614.38 for the

first time for the implementation of COWASH activities in the region. The fund was requested

based on a core plan prepared by COWASH FTAT in collaboration with the regional water

bureau. However, funds have not been utilized until end of the reporting period. The hiring of

the RSU staff was on progress and funds will be transferred to beneficiary offices as per the

detailed annual plan to be approved in the second quarter of the fiscal year.

Page 39: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

33

7 PROJECT COORDINATION WITH KEY STAKEHOLDERS

The scaling-up of the CMP approach at the national level requires having meetings and

discussions with different WaSH stakeholders thereby sharing the success of the CMP approach

and raising awareness and generating funds for investments. Cognizant of this fact, COWASH

has been participating in a number of meetings and discussions held during the reporting

period at the national level to promote and share experience on the CMP approach and to

attract more funds for CMP. The major meetings and/or discussions that COWASH has

participated are presented hereunder.

Water Sector Working Group (WSWG)

WSWG WRM-TC kick-off meeting was held on August 14, 2014. Besides, WSWG proposed the

5-year Capacity Building Plan for MoWIE. DAG-WTWG chair sent the plan to development

partners (DPs) for comments. The plan was commented by COWASH and several additional

proposals were incorporated in the plan.

Local Capacity Development Facility (LCDF) Meeting

COWASH participated in a meeting on the development of Local Capacity Development Facility.

It was found out that currently SNV, PANE and RiPPLE are working together in LCDF project.

The required funding for the project is covered by SNV as donor and quality control works are

being done by SNV. COWASH is mentioned as a collaborator in the LCDF project document and

hence its grassroots level service provision experience is expected to be a springboard for the

project so as to avoid duplication of efforts in service provision. PANE tried to organize a

meeting in September, but it could not be successful as the month was not convenient for

TAG.

MSF and JTR Meeting

COWASH CTA drafted the MSF 7 and JTR 9 concept paper for NWCO actions. The meeting of

development partners on MSF 7 and JTR 9 could not be made due to busy schedule of NWCO

staff. Anyhow, JTR 9 and MSF 7 are planned to be organized in November and December

2014, respectively.

MDG Achievement Celebration

The MoWIE Minister established a team to prepare MDG target celebration event. COWASH

CTA became also member of this team. The Team developed a brochure on the MDG

achievement in Ethiopia on water and sanitation and started to prepare communication

strategy and event program. Later on the MDG celebration event idea was cancelled as it was

found out that the data on the water supply access figures was not accurate and transparent

enough to conclude the achievements in a way that the results would be also comparable and

debatable at global level. This event was postponed to the last quarter of 2015.

Discussions with different national and international organizations and experts

Several unofficial discussions were held with MoWE/WSSD/NWCO/GIS directorate on

the development of OWNP and GIS-based mapping of water points

COWASH CTA took part in the Federal Micro and Small Enterprise Development Agency

debriefing meeting on Business Plan Model that was organized by the WSP on July 1, 2014.

COWASH FTAT participated in the COWASH follow-up meetings held in the Embassy of Finland.

Page 40: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

34

COWASH CTA held meeting with MetaMeta to plan the future COWASH RSU staff

training on GLOWS/WSP. Accordingly, RSU staff and some regional water bureau and

COWASH FTAT were trained on GLOWS/WSP by MetaMeta.

Several meetings were held with the Consultants who are preparing the O&M manual

and carrying out Training Impact Research

COWASH CTA conducted Planning meeting with Quest consult.

COWASH FTAT held follow-up and supervision meeting with SNNP Water Bureau Head and relevant regional COWASH stakeholders.

CMP promotion meeting with local NGO called WCDO and the NGO is willing to include CMP into their food security concept note for financiers.

COWASH CTA conducted meeting with SNV on joint projects.

COWASH FTAT held meeting with WHO consultant on WSP was held in July 2014.

Meeting conducted on July 10, 2014 with IRC on their role in WASH in Ethiopia and on CMP in particular.

COWASH CTA participated in a meeting with UNICEF on CMP development.

COWASH CTA participated in the meeting with Water.org and WaterAid on WaterCredit workshop.

COWASH FTAT participated in a meeting held on SNNP implementation at Embassy of

Finland.

COWASH Steering Committee meeting was conducted through the facilitation of

COWASH FTAT

COWASH FTAT participated in a meeting conducted with South Pole on the ‘Result

Based Financing’

A meeting was conducted on UNICEF-SNV coordination on CMP Implementation Manual

approval and finalization process

COWASH CTA participated in the Stockholm World Water Week exhibition and assisted

in erecting MoWIE stand

A meeting with M-Birr Ethiopia was held and the possibilities to use mobile payments in

COWASH was discussed

COWASH CTA met the IRC auditor Mr. Bert L.M. Van Woersen and discussed the IRC

performance in Ethiopia

COWASH CTA participated in a meeting with Oromia Water Bureau Head (Ato Motuma)

with Anu Eskonheimo on COWASH in Oromia and CTA presented Oromia progress in

the last fiscal years

A meeting was conducted with Open University (OU) on WASH Capacity Building in Ethiopia. OU

has been contracted by World Vision in WASH +project to be responsible of the capacity building

component.

Page 41: FIRST QUARTER PERFORMANCE REPORT OUTPUT BASED€¦ · 1 EXECUTIVE SUMMARY The COWASH project has two components. Component 1 strives to strengthen the federal level capacity for implementation

35

8 CHALLENGES

Like the previous fiscal year, different kinds of challenges have been faced during the reporting period. The major ones that require the

attention of National WaSH Steering Committee (NWSC) and Regional WaSH Steering Committee (RWSC) are indicated as follows.

Challenges Measures taken

Delay in preparation and approval of regional annual plans: The 2007 EFY annual plans of

COWASH in the regions were expected to be prepared before the end of 2006 EFY. However, the

plans are not still approved in the regions. The delay in the approval of the regional annual plans will

also delay the implementation of some of the federal level activities. The delay in the preparation

and approval of annual plans hampers the implementation rate and budget utilization of woredas

thereby affecting the contribution of COWASH in accelerating the GTP/UAP WASH targets.

COWASH provided technical assistance to

all the regions in the preparation of their

annual plans. Planning templates and unit

costs were prepared by COWASH FTAT and

sent to regions timely.

Delay in sending quarterly reports: Quarterly performance reports are expected from regions to

prepare project performance report at the federal level and submit to the pertinent bodies timely.

However, quarterly reports from the regions are delayed and this takes much time to prepare the

performance report of the project at the federal level. Quality of the regional reports is also a

problem that is delaying the finalization of federal level reports.

The problem persists in the reporting

quarter. COWASH FTAT has been assisting

RSUs in preparing regional reports and

providing feedback on the reports sent to

COWASH FTAT.

Lack of field vehicle: Though it was late for more than 2 years, Tigray and Oromia RSUs have got

field vehicles to provide technical assistance to the woredas and zones. However, the procurement of

SNNPR RSU car took much time and the staff could not carry out fieldworks to the woredas and

zones. Many of the woredas have no vehicle to assist WASHCOs and KWTs to carry out CMP

activities at the grassroots level.

SNNPR has paid 30% of the price of the

car but the private company could not still

submit the car. One reason raised was the

rise of price of car at the international

market. COWASH FTAT have been

discussing with regions to speed up the

procurement of the cars.