First Power Production Results from the Wave Star Roshage...
Transcript of First Power Production Results from the Wave Star Roshage...
02-12-2010
1
First Power Production Results from theWave Star Roshage Wave Energy Converter
Laurent Marquis, Head of Development , Wave Star A/SMorten Kramer, R&D engineer, Wave Star A/S
Peter Frigaard, Head of Civil Engineering Department, Aalborg University
3rd International Conference on Ocean Energy, 6 October, Bilbao
02-12-2010
2
The Wave Star machinesThe Wave Star machines
Test machine at Aalborg University• Deployment: 2004-2005• Scale: 1/40• Float diameter: 0.25 m
Test machine at Nissum Bredning• Deployment: 2006-2010• Scale: 1/10Scale: 1/10 • Float diameter: 1.0 m
Test section at RoshageTest section at Roshage• Deployment: 2009->• Scale: 1/2• Float diameter: 5.0 m
2
02-12-2010
3
Wave Star make use of a unique conceptWave Star make use of a unique concept
• 2 rows with10 floats, 20 floats total• The floats are mounted on a machine which is founded on the seabed• All the moving parts are located above the waterlineg p• Hydraulic fluid is pumped from each float to a hydraulic motor, which drives a generator• The Wave Star machine can lift the floats out of the water into safety position
3
02-12-2010
4
4
Wave Star scale 1:40 Aalborg University, Denmark
02-12-2010
5
Normal operation
Storm protection mode
55
More than 4 years in operationand 15 storms without damage
Wave Star scale 1:10 Nissum Bredning, Denmark
02-12-2010
6
The location for the test section (photo taken before deployment)
6Energy Supply Chain June 20096
Roshage Pier, location for the Wave Star scale 1:2 test sectionHanstholm, Denmark
02-12-2010
7
The machine was built in Gdansk and towed to Denmark in August 2009
77
02-12-2010
8
The jacking system was tested in dry dock in Frederikshavn, Denmark
88
02-12-2010
9
The machine was installed on 18 September 2009
Vid
9
Video:Installation
02-12-2010
10
The 19th of September 2009 the installation was finalizedand the machine was placed in storm protectionp p
Video:Storm protection
10
02-12-2010
11
A bridge was built during the autumn 2009,and the first guests visited the plant during COP15and the first guests visited the plant during COP15.The machine has been supplying electricity to the grid since February 2010.
Video:Operation
11
02-12-2010
12
The Roshage test unit is a sectionof the complete machineof the complete machine
Parameter Roshage test unit Commercial Wave Star C5-600 kWNumber of floats 2 20Float diameter Ø5 m Ø5 mA l th 10 10Arm length 10 m 10 mWeight 1000 Tons 1600 TonsNominal electrical power 110 kW 600 kW
12
02-12-2010
13
Power measurements fromPower measurements fromthe Roshage test unit
Measured September 2010 (Control generation 3)
Measured June 2010 (Control generation 2)
30 30
( g )
Measured May 2010 (Control generation 1)
Simulation, Control generation 3
15
20
25
r(kW
)
15
20
25
r(kW
)5
10
15
Pow
er
5
10
15
Pow
er
Notes:
0 0.5 1 1.5 2 2.5 30
Significant wave height (m)
0 2 4 6 8 10 12 14 16
0
Wave power (kW/m)
13
Notes:• Power is 10 minute average values of harvested power from one float (hydraulic power leaving one cylinder)• The same data are shown in the figures, only the x-axis is different• A typical wave period for the Roshage location is used for the simulated curve
02-12-2010
14
Power measurements fromPower measurements fromthe Roshage test unit
Measured September 2010 (Control generation 3)Measured June 2010 (Control generation 2)
30 30
Measured May 2010 (Control generation 1)Simulation, Control generation 3ForskVE Limit Curve
15
20
25
r(kW
)
15
20
25
r(kW
)5
10
15
Pow
er
5
10
15
Pow
er
Notes:
0 0.5 1 1.5 2 2.5 30
Significant wave height (m)
0 2 4 6 8 10 12 14 16
0
Wave power (kW/m)
14
Notes:• Power is 10 minute average values of harvested power from one float (hydraulic power leaving one cylinder)• The same data are shown in the figures, only the x-axis is different• A typical wave period for the Roshage location is used for the simulated curve
02-12-2010
15
Approved byApproved byIf the measured production is above the limit,
b idi i d f E iN t
EnergiNet is a non-profit enterprise owned by the Danish Climate and Energy Ministry
Example of measured data from the Roshage test unit (10 min average values):
Measured production Limit for subsidiessubsidies are recieved from EnergiNet
PLC_Datetime AllDataValid Hs Tmean P_TwoFloats ForskVE_limit AboveLimit[%] [m] [s] [kW] [kW] [True/False]
21/09/10 09:20 100 2.08 4.72 48.98 34.24 True21/09/10 09:30 100 1.91 4.31 37.50 28.71 True21/09/10 09:40 100 1.94 4.10 38.02 29.80 True21/09/10 09:50 100 2.01 3.95 33.69 32.07 True21/09/10 10:00 100 2 03 4 47 39 91 32 85 True21/09/10 10:00 100 2.03 4.47 39.91 32.85 True21/09/10 10:10 100 2.17 4.23 42.91 37.42 True21/09/10 10:20 100 2.01 4.39 38.94 32.04 True21/09/10 10:30 100 2.01 4.14 39.84 32.02 True21/09/10 10:40 100 2.10 4.27 40.97 35.12 True21/09/10 10:50 100 2.03 4.01 41.76 32.55 True21/09/10 11:00 100 1.83 4.13 32.29 26.21 True21/09/10 11:10 100 1.97 4.28 37.60 30.71 True21/09/10 11:20 100 1.89 3.91 36.32 28.19 True21/09/10 11:30 100 1.97 4.34 36.78 30.64 True21/09/10 11:40 100 1.93 4.29 40.44 29.50 True21/09/10 11:50 100 1 96 4 34 38 75 30 35 True
15Power numbers in kW are measured harvested power (hydraulic power leaving the two cylinders).Wave climate is calculated using wave measurements at the location.
21/09/10 11:50 100 1.96 4.34 38.75 30.35 True/ /
02-12-2010
16
Power measurements fromPower measurements fromthe Roshage test unit
Measured September 2010 (Control generation 3)
Measured June 2010 (Control generation 2)
4
4.5
80
90
( g )
Measured May 2010 (Control generation 1)
Simulation, Control generation 3
2 5
3
3.5
4
wid
th (m
)
50
60
70
80
dth
ratio
(%)
1
1.5
2
2.5
Cap
ture
w
20
30
40
50
Cap
ture
wid
Notes:
0 2 4 6 8 10 12 14 160.5
1
Wave power (kW/m)
0 2 4 6 8 10 12 14 16
10
20
Wave power (kW/m)
16
Notes:• Power is 10 minute average values of harvested power from one float (hydraulic power leaving one cylinder)• The same data are shown in the figures, only the y-axis is different• A typical wave period for the Roshage location is used for the simulated curve
02-12-2010
17
Power matrix for a singlegWave Star C5 600 kW machine with 20 floats
Values inside the table are average electrical power to grid in kW.
Wave height Hm0 (m)
Wave period T0,2 (s)
2 - 3 3 - 4 4 - 5 5 - 6 6 - 7 7 - 8 8 - 9 9 - 10 10 - 11 11 - 12 12 - 13 0.0 - 0.5 0 0 0 0 0 0 0 0 0 0 0 0.5 - 1.0 0 49 73 85 86 83 78 72 67 63 59 1.0 - 1.5 54 136 193 205 196 182 167 153 142 132 1231.0 1.5 54 136 193 205 196 182 167 153 142 132 1231.5 - 2.0 106 265 347 347 322 294 265 244 224 207 193 2.0 - 2.5 175 429 522 499 457 412 372 337 312 288 267 2.5 - 3.0 262 600 600 600 600 540 484 442 399 367 340
3.0 - Storm protection
17
02-12-2010
18
Perspectives: Wave Star C5Perspectives: Wave Star C5 performance at different sites in Europe
Site Belmullet, IRNominal Power 1200 kWStorm protection Hs > 5 mAnnual production 4.29 GWh
Site EMEC,UKNominal Power 1200 kWStorm protection Hs > 5 mAnnual production 2.88 GWh
Site Wave Hub, UKNominal Power 1200 kW
Site Horns Rev 2,DKNominal Power 600 kWStorm protection Hs > 3 mAnnual production 1.41 GWh
Storm protection Hs > 5 mAnnual production 2.64 GWh Site SEM-REV, F
Nominal Power 1200 kWStorm protection Hs > 5 mAnnual production 2.37 GWh
Site Pilot Zone, PNominal Power 1200 kWStorm protection Hs > 5 mAnnual production 2.87 GWh
Site BIMEP, ES
Nominal Power 1200 kWStorm protection Hs > 5 mAnnual production 2.21 GWh
18
02-12-2010
19
C5 Wave Star and C10 Wave Star
• C5• 70 m long • 20 floats of Ø 5 m
•C10•140 m long •20 floats of Ø10 m
• ~ 10-15 m of water depth• 500 kW @ 2.5m Hs
•~ 20-30 m of water depth•6 MW @ 5.0m Hs
1919
Double size = 11 times more power
02-12-2010
20
Road Map for Cost of Energy for Wave Star WECBased on average wave energy potential at European sites
1.0
1.1
Based on average wave energy potential at European sites(WEC lifetime: 20 years, Interest of investment: 9%)
Development factorsEnergy production: 1.0Total investment: 1.0Maintenance: 1 0
0.7
0.8
0.9Maintenance: 1.0
0.5
0.6
€/kW
h
0.2
0.3
0.4 Development factorsEnergy production: 1.1Total investment: 0.5Maintenance: 0.8
Development factorsEnergy production: 1.5Total investment: 0 1
0.0
0.1
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Total investment: 0.1Maintenance: 0.5
2020
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021Year
02-12-2010
21
Activities in Wave Star at presentActivities in Wave Star at present
• The Roshage test section will actively be used as test platform for Power Take-Off optimization, test of other component/parts, and for gettingTake Off optimization, test of other component/parts, and for getting maintenance data.
• Improvement of the structural design of the C5-machine, and optimization and reduction of systems for future machinesand reduction of systems for future machines
• Focus on reducing production and development cost for the next projects: Expertise from similar industries
• Focus on increasing the Power Take-Off efficiency: In collaboration with innovative companies and universities
A t ith tilit• Agreement with utility company
• Find subsidiaries
21
02-12-2010
22
Wave Star cracks the nuts!Wave Star cracks the nuts!
To stay in the sea Take energy out of waves Cost decreasing More efficient PTO
The storm protection strategy effectively protects the Wave Star machines
The Roshage WEC is connected to the grid, and it has produced energy since
The energy costs for the first full WEC will not be competitive to other
The first test results have shown challenges in ensuring a high efficiency ofthe Wave Star machines.
The Roshage WEC has survived several storms with no severe damages and no service afterwards.
has produced energy since January 2010.
The measurementsfits the expected power curve.
competitive to other conventional sources of energy.
The calculated costs has already been decreased b 30 % b t f th t
ensuring a high efficiency of the complete power transmission to the electrical grid.
Projects on improvements i ithby 30 %, but further cost
reduction is needed.are on-going with universities.
22
02-12-2010
23
Please visit our website and get updated !updated !
2323www.wavestarenergy.com