FIRE & FLOODS

23
FIRE & FLOODS RECOVERING FROM CALIFORNIA’S NEW NORMAL Residents assess damaged culvert 2 THE PANEL Kate Giberson Harris & Associates Enrique Saavedra, PE County of Monterey Frank Lopez, PE Harris & Associates Director, Environmental Planning + Compliance Senior Civil Engineer Senior Director, Engineering Services

Transcript of FIRE & FLOODS

Page 1: FIRE & FLOODS

1

FIRE & FLOODSRECOVERING FROM CALIFORNIA’S NEW NORMAL

Residents assess damaged culvert

2

THE PANEL

Kate GibersonHarris & Associates

Enrique Saavedra, PECounty of Monterey

Frank Lopez, PEHarris & Associates

Director, Environmental Planning + Compliance

Senior Civil Engineer Senior Director, Engineering Services

Page 2: FIRE & FLOODS

3

OUR PRESENTATION

1. The Setting

2. The Repair 

3. The Permits 

4. The FEMA Factor

5. Lessons Learned

6. Questions/Discussion

“Beauty Beyond the Disaster” by Li Liu

4

THE SETTINGFIRE + RAIN

Page 3: FIRE & FLOODS

5

BACKGROUND + TIMELINE OF EVENTS

DAMAGE2016‐2017 WINTER STORMS2016 SOBERANES FIREREMOTE LOCATION

6

• Big Sur, Monterey County

• Rocky Creek flows down canyon

• Project site 3 miles inland from Highway 1

PALO COLORADO CANYONREMOTE LOCATION

Page 4: FIRE & FLOODS

7

PALO COLORADO CANYONREMOTE LOCATION

www.californiacoastline.org

8

Palo Colorado Road

Residence

PALO COLORADO CANYONESTABLISHED COMMUNITY

Page 5: FIRE & FLOODS

9

2016 SOBERANES FIRE

10

2016 SOBERANES FIRE

CALFIRE photo, August 7, 2016

“Big Sur Volcano” by Peter NicholsWater taken from nearby lake to fight fire, kcra.com

Page 6: FIRE & FLOODS

11

2016 SOBERANES FIRE

12

2016 SOBERANES FIRE

Before After

Brandon Creek

Rocky Creek

Brandon Creek

Rocky Creek

Page 7: FIRE & FLOODS

13

2016‐2017 WINTER STORMS / ATMOSPHERIC RIVERS

14

2016‐2017 WINTER STORMS 

Page 8: FIRE & FLOODS

15

2016‐2017 WINTER STORMS 

16

2016‐2017 WINTER STORMS

Page 9: FIRE & FLOODS

17

THE REPAIRDESIGNING A SOLUTION

18

Page 10: FIRE & FLOODS

19

THE DAMAGE

20

THE DAMAGERocky Creek Culvert (upstream side)

Page 11: FIRE & FLOODS

21

THE DAMAGE

22

THE DAMAGE

Palo Colorado Road

Page 12: FIRE & FLOODS

23

DYNAMIC SITE CONDITIONS

Palo Colorado Road Slope Repair Site (where diverted creeks converged and crossed roadway)

24

DESIGN APPROACHROAD MAP

Cost

Meet with Permitting Agencies

Engage Design Team

Present Design Alternatives

Submit 30% Design & Cost 

Estimate

Develop 80% Design

Develop 100% Design

Coordinate with Permitting Agencies

Coordinate with FEMA + Cal OES

Page 13: FIRE & FLOODS

25

DESIGN SOLUTIONSPRIORITIZE ALTERNATIVES FOR ROCKY CREEK

Pipe CulvertRestore: Existing Condition (replace in kind)

Box Culvert

Metal Arch Culvert

4

3

1

2 Bridge on Slab

Accessibility

Permitting Cost

Schedule

Constructability

Factors

Alternatives Considered:

26

INTEGRATED APPROACHPRODUCING FINAL DESIGN PLANS

Final Design

Civil Design + Structural

Constructability

Permitting

Page 14: FIRE & FLOODS

27

CONSTRUCTABILITYROCKY CREEK ARCH CULVERT – 80% VS. 100% DESIGN

80% Design Section

Design Footing Type  Excavation Amount (CY) 

Excavation Depth (ft) 

Excavation Width (ft) 

80%  Spread Footing  10,000  32  34 

100%  “U‐Shaped” Footing  8,000  28‐32  24 

100% Design Section

Rocky Creek

Palo Colorado Road

100% Design Section

28

THE PERMITSSTRATEGIES + CHALLENGES

Page 15: FIRE & FLOODS

29

Site Characteristics

• Rocky Creek = perennial

• Brandon Creek = intermittent

• Dominated by coast redwood

• Steelhead and California red‐legged frog habitat

The Fire and Flood Factor

• Highly disturbed site conditions

• Substantial sediment deposits

• Emergency repair actions

ENVIRONMENTAL CONTEXT

Sediment filled Brandon Creek

30

PERMITS + AUTHORIZATIONS

USACE – Nationwide Permit

RWQCB – Water Quality Certification 

CDFW – Streambed Alteration Agreement

Coastal Development Permit

ESA Section 7 Consultation

NHPA Section 106 Consultation

Page 16: FIRE & FLOODS

31

EARLY AGENCY COORDINATION

Early Outreach Goals

Jurisdictional Delineation

Project Design    Buy‐In

Identify Preferred Mitigation 

Brandon Creek Culvert (upstream side)

32

COLLABORATIVEALTERNATIVES ANALYSIS

Bridge•Environmentalagency preference

•Cost‐prohibitive

Arch Culvert

•Proposed Project

•Constructible and fundable  

•Natural bottom

•Minimizes cut and fill

Box Culvert

•Cost‐effective

•Difficult to construct

•Concrete bottom

Rocky Creek Culverts (downstream side)

Page 17: FIRE & FLOODS

33

THE FEMA FACTOR

34

FEDERAL, STATE, COUNTY, COMMUNITY RESPONSE

Page 18: FIRE & FLOODS

35

Eligibility Criteria

• Direct result of declared disaster

• Located within the designated disaster area

• Must be the legal responsibility of the applicant

THE FEMA FACTORMONTEREY COUNTY IS ELIGIBLE

36

Eligible Work (Categories A‐G)

• Emergency Work

A. Debris removal

B. Emergency protective measures

• Permanent Work

C. Roads & Bridges

D. Water Control Facilities

E. Buildings & Equipment

F. Utilities

G. Parks & Recreation Facilities

THE FEMA FACTORTHE PROJECT IS ELIGIBLE

Page 19: FIRE & FLOODS

37

Subrecipient

PDADisasterEvent

Governor’sRequest

Declaration

Applicants’Briefing

Submissionof Request

Kick‐offMeeting

Formulationof Projects (PW)_

ProjectReview

Recipient

Approval

FundingClose Out

THE PUBLIC ASSISTANCE PROCESS

Preliminary Damage Assessment

Project Worksheet

38

Repair or Replacement Projects – FEMA pays

• Restore to pre‐disaster design, function and capacity

• Possibly upgrade necessary to meet the requirements of reasonable codes and standards

Improved Projects – County pays

• Improve above/beyond pre‐disaster condition

THE FEMA FACTORCHALLENGE #1  REPLACE OR IMPROVE? 

Agency Reimbursement Cost

FEMA 75% $3.75M

State 18.5% $925K

County 6.5% $325K

*Based on estimated construction cost of $5M

Page 20: FIRE & FLOODS

39

THE FEMA FACTORCHALLENGE #2 OTHER DISASTERS

Hurricane Maria, Puerto Rico (September 2017)

Hurricane Irma and Jose, Florida (September 2017)

Hurricane Harvey, Houston (August 2017)

40

THE FEMA FACTORCHALLENGES

FEMA Project Review

FEMA/Regulatory Agency Meeting

Governor’s Request

Declared Federal Emergency

FEMA Site Visit 

Regulatory Agency Input

Project Worksheet submitted to EHP 

Sec 106 Consultation Complete

FEMA Staff Deployed to Other Disasters (July‐December 2017)

ESA Consultation  

TBD

Jan 2017June 2018AprilMarchJan 2018July  Sept April  May March

EHP = FEMA Environmental and Historic Preservation

Construction CompleteOctober 31, 2018

Page 21: FIRE & FLOODS

41

IT’S A GO!

42

DIVERTING THE CREEK 

Page 22: FIRE & FLOODS

43

SUCCESS!

44

• This is for description text, you have options for bullets or paragraph.

• Second level

• Involvement during emergency repairs

• Collaboration

• Engineering

• Environmental

• Regulatory Agencies

• FEMA

• Documentation

DESIGN ENVIRONMENTAL FEMA

LESSONS LEARNED

• Early technical input involving all permitting agencies    

• USACE

• RWQCB

• CDFW

• Verify wetland delineation early

• Documentation

• Understanding  the process and what’s allowed 

• Regulatory agency involvement for “Codes & Standards” justification 

• Documentation

Page 23: FIRE & FLOODS

45

AFTER THE BIG SUR FIRE & FLOOD 

DAMAGE/REPAIR2016‐2017 WINTER STORMS2016 SOBERANES FIREREMOTE LOCATION

THANK YOUQUESTIONS/DISCUSSION