Financing PPPs: Project Finance October 2007. P. 2 Index Section I. Brief Project Finance...
-
Upload
grace-hicks -
Category
Documents
-
view
214 -
download
0
Transcript of Financing PPPs: Project Finance October 2007. P. 2 Index Section I. Brief Project Finance...
Financing PPPs: Project Finance October 2007
P. 2
Index
Section I. Brief Project Finance Introduction
Section II. Risk Matrix
Section III. Case study: Cuenca Road Network Program
Project Finance
Section IBrief Project Finance Introduction
P. 4
Definition of Project Finance
Definition: A form of financing projects, primarily
based on claims against the financed asset or
project rather than on the sponsor of the project.
However, there are varying degrees of recourse
possible. Repayment is based on the future cash
flows of the project.
Sección I
Project Finance Introduction
P. 5
Financing Structure
Shareholders
Construction Joint Venture
Operating Company
CapitalDividends + interest
Principal + Interest
Payment
Payment
CV + CF
Insurance company
Service supplier 1 Service supplier 3 Service supplier 3 Service supplier n
ServiceContracts
Project Company (SPV)
Administration BanksConcessionAgreement
Financialcontracts
ConstructionContract
Operating & Maint.
Contract
Sección I
Project Finance Introduction
P. 6
Calendar: Process duration: 4 months
• Feasibility Study
• Contracts & Risk management
• Economic analysis and Financing structure
Financial Advisor: Banks
Financial Structure
Phase I
Risk analysis
Phase II
Financial closing
Phase III
• Term Sheet & IM
• Arrangers: Term Sheet & Contracts negotiation
• Financial closing
• Participants: Syndication
Sección I
Project Finance Introduction
P. 7
BBVA Project Finance Experience
Sección I
Project Finance Introduction
Leading Project Finance Bank in Spain
• BBVA enjoys a leading position in project financing in Spain:
- #1 Arranger in 2006- #1 Arranger in 2005- #1 Arranger in 2004- #1 Provider in 2003- #1 Financial Advisor in 2003
Leading Project Finance Bank in the World
• BBVA has played a top level role in the project financing in the world:
- #2 Transport Mandated Lead Arranger in 2006- #3 Wind Mandated Lead Arranger in 2006- #4 Water & Sewage Mandated Lead Arranger in 2006- #10 Power Mandated Lead Arranger in 2006
- #1 Financed Advisor in 2006- #2 Western Europe Mandated Lead Arranger in 2006- #6 Eastern Europe Mandated Lead Arranger in 2006- #10 North America Mandated Lead Arranger in 2006
P. 8
BBVA Project Finance Experience
Sección I
Project Finance Introduction
Roads
• BBVA has extensive experience financing the construction of new build motorways and the acquisition of existing roads. For example:
- BBVA has acted as Mandated Lead Arranger on the acquisition of most of the major recent motorway privatisations including the EUR 370 million Ionia Odos Road Project (2007), the EUR 1.06 billion Variante Sur Metropolitana (2006), Euro 8.3 billion APRR privatisation in France (2006), the USD 3.8 billion Indiana Toll Road (2006), the USD 1.8 billion Chicago Skyway (2004), the Euro 1.6 billion ENA privatisation in Spain (2003) and the CAD 2.3 billion ETR-407 acquisition financing in Canada (1999)
- BBVA has acted on some of the most innovative new build financings in North America and Europe including the Euro 232 million Eurolink N4/N6 - the first PPP toll road in Ireland (2003), the NOK 3.2 billion E18 motorway in Norway (2006) and the USD 400 million SR-125 (2003) in San Diego, the first private toll road in the US involving TIFIA funding
• BBVA’s experience includes real toll roads, shadow toll roads and availability based roads
• BBVA has extensive experience in Latin America. Portfolio includes projects in Argentina, Chile, Colombia and Mexico.
• BBVA is one of the world’s leading arrangers of infrastructure financings.
Other Transportation
• BBVA has acted as Mandated Lead Arranger on the financing of transportation infrastructure projects including high speed rail (TP Ferro high speed rail link between Span and France), light rail (Metro de Tenerife and Woolwich Arsenal Docklands Light Railway), container ports (Puerto de Málaga), airports (BAA), parkings (Icon Parkings) and passenger interchange stations (Intercambiador de Castilla).
Project Finance
Section IIRisk Matrix
P. 10
Main risksRisk Matrix
Building & Operational Risk:
► Building risk
► Demand risk
► Operating risk
Financial & Economic Risk:
Section II
► Interest rates risk► Inflation risk► Syndication risk
P. 11
Risk mitigation
Cost Construction Contract Fixed price
Delay Construction Contract Penalty clause
Technical performance Construction Contract Penalty clause
Operating Operation Contract Technical advisor will control the operation
Traffic Concession contract Fix tariff
Tariff / Law Concession contract Tariff will compensate traffic and law changes
Force Majeure Concession contract Concession agreement will cover these risk
Political risk Concession contract Concession agreement will cover these risk
Contracts will provide mechanisms to mitigate the risk:
Mitigation mechanismContract
Contractual structure & risk mitigation
Risk:
Section II
Risk Matrix
P. 12
Other risk mitigations
• Sponsors Technical & Financial solvency.
• EPC Contract.
Long warranty periods.
Penalty clauses.
• Operating & Maint. Contract.
Extension definition.
Length.
Cost limits.
• Due diligence. External advisors
• Insurance program
Section II
Risk Matrix
P. 13
Advisors & Insurance Program
Insurance program
External Advisors
Traffic Advisor
Insurance Advisor
Legal Advisor
Technical Advisor
Model Auditor
Construction
Operating
Damages
ALOP
Civil liability
ALOP
Civil liability
Force Majeure
Section II
Risk Matrix
Project Finance
Section IIICase study: Cuenca Province Road Network
P. 15
Project Description
Sección III
► Construction and maintenance of 458 km of roads in Cuenca province.
► Concession term: 17 years.
► Investments: Construction period: Eur 45 million investment Operational period: Eur 30 million CAPEX
► Shadow toll scheme.
► Concession company: “Conquense de Infraestructuras S.A.”
► Five shareholders who are the main construction companies in the province.
► Concession contract with the local authority.
Case Study
P. 16
Principal participants & contracts
Excelentísima Diputación Provincial de Cuenca
BBVA Arranger
Eptisa Technical advisor
Cuatrecasas / DLA Legal advisor
Heath Lambert Insurance advisor
Tool Ulle Demand advisor
PWC Model auditor
Other/AdvisorsSponsors/Shareholders5 Construction companies
Construction contract with a Joint Venture of all concession company shareholders.
Maintenance contract with a company formed by the five shareholders of the concession company.
Administrative contracts: concession contract, etc.
Insurance contracts
Financial contracts: Senior Loan, VAT Loan, Swaps, etc.
Contract structure
Sección III
Case Study
P. 17
Structure
Sección III
Concession Contract
Cuenca Local Authority
Conquense de Infraestructuras S.A.
Construction Joint Venture
Conquense de Conservación S.L.
Construction Contract
Maintenance Contract
BanksFinancing Contracts
Case Study
P. 18
Risks and Guarantees
Construction period
• Any construction risk
• Civil liability
Maintenance period
• Material Damage
• Civil liability
• Environment liability
• Terrorism
Construction Risk
Contingency
• Delays in project opening
• Overcost due to delays
Guaranties
• Sponsors guaranties and penalties
• Construction Insurance
Maintenance Risk
Contingency
• Unable to face debt service
• Maintenance overcost
Guaranties
• Sponsors guarantees and penalties
• CAPEX reserve accounts
• New bank maintenance budgets
• Contractor guarantees
• Sponsors experience
• Proven technology
Technological Risk
Insurance Risk
Sección III
Case Study
P. 19
Financial Risk
• Credit risk of the project
• 100% IRS of outstanding debt during the concession period.
• Conservative forecast
Legal risk
Contingencies
• Cancellation Management Contract
• Change in tariffs
Guaranties
• Grantor compensation
Sección III
Case Study Risks and Guarantees
P. 20
Other Project guarantees
Real Guarantees
Asset mortgage commitment
Pledges of:
• Management Contract
• Project Contracts
• IRS Contracts
• Insurance Contracts
Pledge of Concession company
Fulfill of financial ratios
Sección III
Case Study
P. 21
Project Strengths & Weaknesses
Project Strengths
• Sponsors experience
• Technical solvency
• Support of the sponsors
Project Weaknesses
• Legal changes
• Tariff changes
• Administrative problems (licenses & permits)
Main issues to obtain internal credit committees approvals
• Suitable financial structure
• Favorable legal and administrative framework
• Technological risk guarantees
• Public interest asset
• Correct risk distribution
Sección III
Case Study