Brainworks Capital Management Interim Financial Results 30 June 2013
Financial management 2013
-
Upload
reanne-claudine-laguna -
Category
Documents
-
view
4.923 -
download
8
description
Transcript of Financial management 2013
Solutions Manual
CHAPTER 21-FINANCIAL RISK MANAGEMENT
II. Multiple Choice Questions
1. D 2. D 3. B
Problem 3
ProbabilitySales Volume
(units)Expected Sales Volume (units)
0.10 2,000 2000.30 6,000 1,8000.30 8,000 2,4000.20 10,000 2,000 0.10 14,000 1,4001.00 7,800
EV of contribution [7,800 x (12 – 8)] P31,200Less: Additional fixed overhead 20,000EV of additional cash profit per annum P11,200
(a) Calculation of expected value of NPV of project
Year Cash Flow DCF @ 10% PV of Cash Flow
0 P (40,000) 1.0000 P (40,000)1 – 6 11,200 4.3550 48,776
6 3,000 0.5645 1,694Expected NPV P 10,470
(b) Calculation of minimum volume of sales per annum required to justify the project
At break-even, the NPV would be zero. Taking the cost of the equipment and its residual value, the minimum required PV of annual cash profit would be as under:
PV of capital outlay P40,000PV of residual value 1,694PV of actual cash profit required for NPV of 0 P38,306
Discount factor of 1 per annum 6 years @ 10% is 4.355
Annual cash profit required (P38,306/4.355) P 8,796Annual (cash) fixed costs 20,000
P28,796
21-1
Chapter 21 Financial Risk Management
Annual contribution required for NPV = 0
Contribution per unit = P4
Sales required to break-even:
Problem 4
Annual cash inflow (P4,500 x 2.9137) P13,112Less: Project cost 12,000Net present value P 1,112
(a) Sensitivity for Project Cost
If the project cost is increased by P1,112, the NPV of the project will become zero. Therefore, the sensitivity for project cost is:
(b) Sensitivity for Annual Cash Inflow
If the present value of annual cash inflow is lower by P1,112, the NPV of the project will become zero. Therefore, the sensitivity for annual cash flow is:
(c) Sensitivity for Cost of Capital
Let “x” be the annuity factor which gives a zero NPV (i.e., “x” is the IRR)
- P12,000 + P4,500 x = 0P4,500 x = P12,000
x = P12,000/P4,500x = 2.6667
Hence, x = 2.6667 and at 18% for 4 years, the annuity factor is 2.6667.
21-2
P28,796P4 = 7,199 units
P1,112P12,000 = 9.27%x 100
P1,112P13,112 = 8.48%x 100
29%18% − 14%
14%= =Sensitivity %
Financial Risk Management Chapter 21
Analysis:
The cash inflow is more sensitive, since only 8.5% change in cash inflow will make the NPV of the project zero.
Problem 5
PV of SavingsYear 1 (P60,000 x 0.9259) P 55,554Year 2 (P70,000 x 0.8573) 60,011
P115,565Less: PV of Running Cost
Year 1 (P20,000 x 0.9259) P18,518Year 2 (P25,000 x 0.8573) 21,432 39950
Net savings 75,615Less: Purchase cost of plant 70,000Net present value P 5,615
(a) Sensitivity for Plant Cost
If the purchase cost of plant increases by P5,615, the NPV of the project will become zero. Therefore, the sensitivity for plant cost is:
(b) Sensitivity for Running Cost
If the present value of running cost increases by P5,615, the NPV of the project will become zero. Therefore, the sensitivity for running cost is:
(c) Sensitivity for Savings
If the savings decrease by P5,615, the NPV becomes zero. Therefore, the sensitivity for savings is:
Analysis: Savings is the most sensitive.
21-3
8.02%P5,615P70,000 =x 100
14.06%P5,615P39,950 =x 100
4.86%P5,615
P115,565 =x 100