Finance and Administration

Personal Service ContractingPSC Negotiations

April 2011

Page 2: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Agenda• Laws & PoliciesLaws & Policies

• Definition of PSC and MOADefinition of PSC and MOA

• Role of the LRC Government Contract Review Role of the LRC Government Contract Review Committee (GCRC)Committee (GCRC)

• Proof of Necessity (PON)Proof of Necessity (PON)

• PSC Process OverviewPSC Process Overview

• Critical components of a PSCCritical components of a PSC

• EO1/LOI (Letter of Intent)EO1/LOI (Letter of Intent)

Page 3: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Agenda• Competitive ExemptionsCompetitive Exemptions

• Start DatesStart Dates

• Importance of eMARSImportance of eMARS

• How to Stay Out of Trouble!How to Stay Out of Trouble!

• PSC QuestionsPSC Questions

• PSC Negotiations

• Questions

Page 4: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

KY Procurement Law KRS 45A

Model Procurement Code (MPC)Model Procurement Code (MPC)Drafted by ABA as a result of numerous public purchasing Drafted by ABA as a result of numerous public purchasing scandals: scandals: – Awards with no competitive process.Awards with no competitive process.

– Using sole source when competition exists.Using sole source when competition exists.

– Declaring emergencies when none exist.Declaring emergencies when none exist.

– Unduly restricting requirements to favor one vendor.Unduly restricting requirements to favor one vendor.

Became law in 1979

Page 5: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Statutes and Policies

KRS 45A.690KRS 45A.690 DefinitionsDefinitionsKRS 45A.695KRS 45A.695 PSC ProceduresPSC ProceduresKRS 45A.705KRS 45A.705 Government Contract ReviewGovernment Contract Review

Committee (GCRC)Committee (GCRC)FAP 111-43-00FAP 111-43-00 Personal Service ContractPersonal Service ContractFAP 111-44-00FAP 111-44-00 Memorandum of AgreementMemorandum of Agreement

GCRC Policies:GCRC Policies:

http://www.lrc.ky.gov/Statcomm/Contracts/homepage.htmhttp://www.lrc.ky.gov/Statcomm/Contracts/homepage.htm

Page 6: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Personal Service Contract - PSC

Personal service contract" means an agreement Personal service contract" means an agreement whereby an individual, firm, partnership, or whereby an individual, firm, partnership, or corporation is to perform certain corporation is to perform certain services requiring services requiring professional skill or professionalprofessional skill or professional judgment for a judgment for a specified period of time at a price agreed upon. It specified period of time at a price agreed upon. It includes all price contracts for personal services includes all price contracts for personal services between a governmental body or political between a governmental body or political subdivision of the Commonwealth and any other subdivision of the Commonwealth and any other entity entity in any amountin any amount..

KRS 45A.690(1)(g)KRS 45A.690(1)(g)

Page 7: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Professional Services

ExamplesExamples

Legal Services

Auditing Services

Medical Services

Training Services

Consulting Services

Page 8: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Memorandum of Agreement - MOAMemorandum of agreement" means any memorandum of

agreement, memorandum of understanding, program administration contract, interlocal agreement to which the Commonwealth is a party, privatization contract, or similar device relating to services between a state agency and any other governmental body or political subdivision of the Commonwealth or entity qualified as nonprofit under 26 U.S.C. sec. 501(c)(3) not authorized under KRS Chapter 65 that involves an exchange of resources or responsibilities to carry out a governmental function. It includes agreements by regional cooperative organizations formed by local boards of education or other public educational institutions for the purpose of providing professional educational services to the participating organizations and agreements with Kentucky Distinguished Educators pursuant to KRS 158.782

KRS 45A.690(1)(d)

Page 9: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC – MOA ExemptionsAgreements exempt from the definition of a PSC and

MOA are listed in KRS45A.690(1)(d) and KRS 45A.690(1)(g).

Examples:• Agreements between KYTC and political subdivisions

for road related projects.• Agreements between state agencies and the Auditor

of Public Accounts.• Some agreements between state agencies and state

universities (45A.690(1)(d)4.

Page 10: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC’s• Must go through competitive process (RFP) unless prior Must go through competitive process (RFP) unless prior

exemption approved by FAC. exemption approved by FAC. KRS 45A.695(3)KRS 45A.695(3)

• Must be filed with GCRC prior to the effective date. Must be filed with GCRC prior to the effective date. KRS 45A.695(2)KRS 45A.695(2)

• No work can be done until filed with GCRC. No work can be done until filed with GCRC. KRS 45A.695(1)KRS 45A.695(1)

• May not extend past the end of the biennium in which it is May not extend past the end of the biennium in which it is entered. entered. Policy Statement 99-4.Policy Statement 99-4.

Page 11: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

MOA’s

• Are used to establish a contract with a public entity. KRS 45A.690(1)(d).

• Shall be filed with the GCRC prior to the effective date. KRS 45A.695(2).

• May not extend past the end of the biennium in which they are created unless there is statutory authority to do so; or by exemption granted by the GCRC. Policy Statement 99-4.

Page 12: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Government Contract Review Committee• Committee Jurisdiction: Pursuant to KRS 45A.690 to

45A.725, the committee shall review:1) personal service contracts and price contracts whereby the contractor is to perform any professional service for a state agency;

• 2) memoranda of agreement, memoranda of understanding, program administration contracts, interlocal agreements to which the Commonwealth is a party, privatization contracts, or similar devices relating to services, between a state agency and any other governmental body or political subdivision of the Commonwealth that involves an exchange of resources or responsibilities to carry out a governmental function. 

Page 13: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

GCRC

Specifically, the committee shall:

• Examine the stated need for the service; • Examine whether the service could or should

be performed by state personnel; • Examine the amount and duration of the

contract or agreement; and • Examine the appropriateness of any exchange

of resources or responsibilities

Page 14: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

GCRCSenator Vernie McGaha Co-ChairSenator Vernie McGaha Co-Chair

Representative Dennis Horlander Co-ChairRepresentative Dennis Horlander Co-Chair

Sen. Julian CarrollSen. Julian Carroll Rep. Brent HousmanRep. Brent HousmanSen. Carroll GibsonSen. Carroll Gibson Rep. Brent YontsRep. Brent YontsSen. Paul HornbackSen. Paul Hornback Rep. Jesse CrenshawRep. Jesse Crenshaw

Staff: Kim Eisner Staff: Kim Eisner [email protected] [email protected] Ross Matt Ross [email protected] [email protected] BrookerRebecca Brooker [email protected] [email protected]

Page 15: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

GCRC

Each personal service contract, tax incentive Each personal service contract, tax incentive agreement, and memorandum of agreement agreement, and memorandum of agreement shall be filed with the committee prior to the shall be filed with the committee prior to the effective date and shall be accompanied by a effective date and shall be accompanied by a completed completed proof of necessity formproof of necessity form as as established by the committee by promulgation established by the committee by promulgation of an administrative regulation, or equivalent of an administrative regulation, or equivalent information if submitted electronicallyinformation if submitted electronically

KRS 45A.695(2)

Page 16: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Proof of NecessityThe proof of necessity form shall document: (a) The need for the service or benefit to the

Commonwealth of the tax incentive agreement; (b) For personal service contracts and memoranda of

agreement, the unavailability of state personnel or the nonfeasibility of utilizing state personnel to perform the service;

(c) The total projected cost of the contract or agreement and source of funding;

KRS 45A.695(2)

Page 17: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Proof of Necessity(d) The total projected duration of the contract

or tax incentive agreement; (e) Payment information, in detail; (f) In the case of memoranda of agreement or

similar device, the reason for exchanging resources or responsibilities; and

(g) Such other information as the committee deems appropriate.

KRS 45A.695(2)

Page 18: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

GCRC Policies• Policy Statement #98-1 Hourly Rate v. Travel Expense Policy Statement #98-1 Hourly Rate v. Travel Expense

PolicyPolicy• Policy Statement #99-1 Legal Services: Duties and Policy Statement #99-1 Legal Services: Duties and

Maximum Rate ScheduleMaximum Rate Schedule• Policy Statement #99-2 Appraisal Services: Duties and Policy Statement #99-2 Appraisal Services: Duties and

Maximum Rate ScheduleMaximum Rate Schedule• Policy Statement #99-3 Auctioneer Services: Duties and Policy Statement #99-3 Auctioneer Services: Duties and

Maximum Rate ScheduleMaximum Rate Schedule• Policy Statement #99-4 Multiyear Government ContractsPolicy Statement #99-4 Multiyear Government Contracts• Policy Statement #99-5 Auditing Services; Duties and Policy Statement #99-5 Auditing Services; Duties and

Maximum Rate ScheduleMaximum Rate Schedule• Policy Statement #00-6 Personal Service Contract Policy Statement #00-6 Personal Service Contract

Amendment PolicyAmendment Policy

Page 19: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

GCRC Disapproval• If the contract is disapproved all contract activity must

stop immediately. • The agency may request the Secretary of the FAC to

determine if the PSC shall:(a) Be revised to comply with the objections of the committee;(b) Be canceled and, if applicable, payment allowed for services rendered under the contract or amendment; or(c) Remain effective as originally approved.

• The Secretary of the Finance and Administration Cabinet shall notify the committee of the action taken within ten (10) days from the date the PSC was reviewed by the committee.

KRS 45A.705

Page 20: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC Process - RFPRequest for Proposal (RFP)Request for Proposal (RFP)

• Begins at the agency level with the creation of a Request for Proposal (RFP) in the state’s electronic procurement system. FAP 111-43-00-01(a).

• All RFPs for PSCs, including those less than $10,000, shall be submitted to OPS for review and approval prior to issuance, other than A&E.

• The RFP shall be submitted at least 7 days prior to the intended RFP “let date” (published date), and a “close date” a minimum of 7 calendar days after the “let date”.

Page 21: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC Process - RFP

• All RFP’s shall include Reciprocal Preference and Preferences for a Qualified bidder or the Department of Corrections, Division of Prison Industries. KRS 45A.490 – 494; KAR 200 5:400; KRS 45A.470; KAR 200 5:410.

• Agencies shall make cost the primary evaluation factor in the awarding of the contract, whenever appropriate. The scoring criteria shall be communicated to the prospective offerors in the RFP.

• Upon approval by OPS the RFP will be posted to the Vendor Self Service website, pursuant to the “let date” entered on the RFP.

Page 22: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC Process – Award and ApprovalFAP 111-43-00-01FAP 111-43-00-01

Upon completion of RFP process the Agency:Upon completion of RFP process the Agency:

• “…“…shall award a contract electronically from a bid evaluation in shall award a contract electronically from a bid evaluation in the state’s procurement system.”the state’s procurement system.”

• Shall provide the justification for award in a Determination and Shall provide the justification for award in a Determination and Finding document.Finding document.

• Shall print the contract and obtain vendor and agency Shall print the contract and obtain vendor and agency signatures. signatures.

• Shall submit the electronic contract to FAC via eMARS for Shall submit the electronic contract to FAC via eMARS for review, approval and filing with the GCRC.review, approval and filing with the GCRC.

Page 23: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC Process – Filing with GCRC

• PSC’s in PSC’s in FinalFinal phase in eMARS by the last phase in eMARS by the last business day of the month are placed on business day of the month are placed on the GCRC meeting agenda for the following the GCRC meeting agenda for the following month.month.

• No work may begin until the PSC is No work may begin until the PSC is filedfiled with the GCRC. KRS 45A.695with the GCRC. KRS 45A.695

Page 24: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Critical PSC Components

It Must Be Written To Be EnforcedIt Must Be Written To Be Enforced

FAP 111-43-00-01(d) FAP 111-43-00-01(d)

Terms and ConditionsTerms and Conditions• Scope of Work Scope of Work • Period of Performance Period of Performance • Pricing Pricing • Negotiated ItemsNegotiated Items

Page 25: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Critical PSC Components

Applicable Boilerplate Language

Including:

• Funding Out Provision

• Authorized to do Business in KY

• Reduction in Contract Worker Hours

Page 26: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Critical PSC Components

• Campaign Finance 45A.110(2) 45A.115 • Violations of KRS 45A.485• Access to Records 200 KAR 5:314;

45A.150• Payment Language 45A.695(7)• Cancellation Clause 45A.695(1)• Invoicing of PSCs 45A.695

Page 27: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

EO1/Letter of Intent (LOI)Letter of Intent (LOI) is a result of Gov. Beshear’s Smart

Government Initiative (SGI).

Implemented February 7, 2011.

Intended to ensure PSC’s are established only when necessary for services that cannot reasonably be performed by any other state agency or university.

More oversight is provided in the procurement of PSCs through the LOI process and a review of RFPs for professional services by FAC.

Approval of an EO1/LOI must be obtained prior to the PSC contracting process.

Page 28: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

EO1/LOI

• EO1’s for PSC’s less than $10,000 are reviewed and approved at the agency level.

• Agency shall file a LOI for PSC’s equal to or

greater than $10,000 with the FAC, OPS no less than 2 weeks prior to the intended RFP issue date.

Page 29: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

LOI Purpose and JustificationMust contain:• Description of Needed Service• Why service cannot be provided by a state

agency• Estimate of work involved• Estimate of contract cost per year – including

anticipated amendments• Contact person if other than the requestor

Page 30: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Competitive Exemption Requests

• Competitive Exemption Requests include:– Sole source;– Not practicable or feasible to bid;– Renewals; – Time and Balance extensions

Submitted to FAC, OPS for review and approval in the “For Agency Use Field” on the EO1/LOI.

Page 31: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Competitive Exemption Requests

PSC’s less than $10,000:

• Add to “For Agency Use Field” on EO1.• Email to FAC, OPS – Don Speer or Rose Caudle• FAC will enter document comment for the approval.

Page 32: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Competitive Exemption Requests• Sole Source-Justification for the sole source;

• Not Practicable or Feasible-Explanation why bidding is not feasible;

• Renewal–Current contract number, language from original RFP allowing renewals.

• Time and Balance Extension–Explanation why the contract must be extended beyond the original expiration date.

Page 33: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Emergency Start Date Request45A.695(1) “Except as provided in subsection (8) of this

section, no one shall begin work on a personal service contract”……..”until notification of the personal service contract is filed with the committee”

45A.096 – “emergency condition…… would seriously threaten the functioning of government, the preservation or protection of property, or the health or safety of any person”

• Submitted to FAC OPS for review and approval on Letter of Intent

• Not permitted for MOA’s.Not permitted for MOA’s.

Page 34: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Retroactive Start Date Request

• Required when an agency allows a vendor to begin work prior to the filing of the PSC with the GCRC even though an emergency condition did not exist

• Closely scrutinized by GCRC

• Submitted to FAC OPS for review and approval on Letter of Intent

• Not permitted for MOA’sNot permitted for MOA’s

Page 35: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Stay Out of Trouble!

• Know when work can begin.• Avoid Legislative Claims.• Know there is no minimum $ for PSC’s.

– PSC’s less than $10,000 are reported for informational purposes.

• Allow sufficient time for FAC review and approvals.• Limit Sole Source and Not Practicable to Bid requests

to true sole source and not practicable situations.• Understand that failure to plan or act does not

constitute an emergency.

Page 36: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PenaltiesAny willful violation of KRS 45A.690 to 45A.725 shall be a Class A misdemeanor.

KRS 45A.990(4)

Any employee or any official of the Commonwealth of Kentucky, elective or appointive, who shall take, receive, or offer to take or receive, either directly or indirectly, any rebate, percentage of contract, money, or other things of value, as an inducement or intended inducement, in the procurement of business, or the giving of business, for, or to, or from, any person, partnership, firm, or corporation, offering, bidding for, or in open market seeking to make sales to the Commonwealth of Kentucky, shall be deemed guilty of a Class C felony.

KRS 45A.990(6)

Page 37: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC [email protected]

502-564-7544

[email protected]

Finance and Administration CabinetOffice of Procurement Services

Room 096, Capitol AnnexFrankfort, KY 40601

Page 38: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Personal Service Contract

Negotiations

April 2011

Page 39: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC Negotiations

All agencies who enter into personal services contracts, including sole-source contracts, should negotiate fair and reasonable compensation with the vendor, prior to actual contract signature and award

Page 40: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC Negotiation ProcessThe general process for competitively bid personal services contract is as follows:• The agency must negotiate with the best evaluated (highest scoring) vendor first. • If negotiations are unsuccessful with the highest scoring vendor, then the agency may discontinue negotiations with that vendor and move on to the next highest-scoring vendor.

• However, the agency cannot go back and re-engage in discussions with a vendor with whom negotiations have been discontinued, so this decision should not be taken lightly.•The agency must include unsuccessful and/or successful negotiation outcomes on the Determination & Finding.

Page 41: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

PSC Negotiations – Budget Info• As a general best practice, agencies should not disclose the maximum budgeted amount during initial negotiations, because the tendency will be for vendors to go with the maximum amount proposed.

• This is important, regardless of whether the source of funding is state, federal or other, because state agencies have an obligation to be fiscally responsible and negotiate best value for any public expenditure of funds.

• KRS 45A.010(2)(f) requires that agencies provide for increased economy in state procurement activities by fostering effective competition. The practice of disclosing the budgeted amount upfront without any attempt at negotiations defeats the purpose of conducting a competitively negotiated procurement and is in conflict with 45A.010(2)(f).

Page 42: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

42

PSC Negotiation Topics• As a matter, of law, the agency may discuss anything in the RFP or the specific vendor’s response about which it has concerns, but it cannot provide a vendor with specific information about any other vendor’s proposals.

• In other words, the agency may generally indicate that other vendors have submitted a bid response, but cannot discuss the details (i.e. how many other vendors bid, the names of the other vendors, or the specific solution or price proposed by another vendor).

Page 43: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

43

PSC Negotiations

Contract Negotiations are not required to be conducted face-to-face, but will depend on practical circumstances, such as the actual dollar value of the underlying procurement, the complexity of the items being negotiated, and the timeframe under which the agency is operating. A negotiation may be conducted over the telephone if the agency wishes to do so.

Page 44: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

44

PSC Negotiation – Vendor Refusal

If a vendor refuses to negotiate, then the agency must determine whether it is in the best interests of the agency to continue with contract award to that particular vendor; or to discontinue negotiations with that vendor and move to the next if appropriate.

Page 45: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

45

PSC Negotiations – Price Increases

The price which a vendor proposes in their RFP response is considered as part of the evaluation process, but simply establishes a ceiling for negotiation and not a floor (so price negotiations typically focus on a reduction in price and not an increase).

Page 46: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

46

PSC Negotiations – What to Ask For

The agency should first ask a vendor to propose a lower price and task the vendor with the primary responsibility for coming back to the agency with a proposal for price reduction. However, if this approach is unsatisfactory, or if the agency is in a time-crunch, the agency may simply choose to ask the vendor to reduce their price by a certain amount or percentage.

Page 47: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

47

PSC Negotiations

Agencies should attempt to negotiate, even when the highest scoring vendor’s price is within the agency’s budget. Simply asking the vendor to come down in price based on reduced agency budgets, etc. may result in unanticipated cost savings.

Page 48: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

48

PSC Negotiations –Established Rates

Certain professional services, such as legal, have pre-defined rates which are typically “not to exceed” rates, so the agency may choose to negotiate for and pay a lower rate, but it may be harder to do so for such public and pre-defined rates.

Page 49: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

49

PSC Negotiations

Agencies are encouraged to have a procurement lead and a program lead on the negotiations team. The procurement lead should discuss the roles and responsibilities upfront and go through the following tips with the program lead, before the negotiation session is scheduled.

General Tips for Negotiations:– Be willing to negotiate in the first place– Set realistic goals for yourself – Don't get emotionally involved– Don’t be rushed into making a decision– Never be the first person to name a figure– Don't act too interested (give the impression you’re willing to walk away)

Agencies may consider not having legal counsel in the initial negotiation session (which typically involves the scope of work and price). Vendors tend to get more defensive and less likely to negotiate if legal counsel is involved upfront. However, the procurement lead could tell the vendor beforehand that, to the extent there are legal concerns about terms and conditions, etc., these will be handled in a follow-up session involving each side’s legal counsel.

Page 50: Finance and Administration Personal Service Contracting PSC Negotiations April 2011.

Negotiation Questions

??