ID Task Name Resource Names Work Cost Duration Start Finish 1 1 Collect, Refurbish and Recycle Project 8,891 hrs $910,768.00 162 days Sun 9/17/17 Mon 4/30/18 2 1.1 Project Management 52 hrs $7,020.00 9 days Sun 9/17/17 Wed 9/27/17 3 1.1.1 Project Kick-Off (Milestone) 0 hrs $0.00 0 days Sun 9/17/17 Sun 9/17/17 4 1.1.2 Assess risk Project Manager 4 hrs $540.00 1 day Mon 9/18/17 Mon 9/18/17 5 1.1.3 Develop scope management plan Project Manager 8 hrs $1,080.00 1 day Tue 9/19/17 Tue 9/19/17 6 1.1.4 Collect requirements Project Manager 4 hrs $540.00 1 day Wed 9/20/17 Wed 9/20/17 7 1.1.5 Conduct time planning Project Manager 8 hrs $1,080.00 1 day Thu 9/21/17 Thu 9/21/17 8 1.1.6 Develop project management plan Project Manager 20 hrs $2,700.00 3 days Fri 9/22/17 Tue 9/26/17 9 1.1.7 Develop cost management plan Project Manager 8 hrs $1,080.00 1 day Wed 9/27/17 Wed 9/27/17 10 1.2 Plan project 179 hrs $16,915.00 101 days Mon 9/25/17 Mon 2/12/18 11 1.2.1 Conduct collection center prep 52 hrs $5,620.00 8 days Mon 10/2/17 Wed 10/11/17 12 1.2.1.1 Identify potential locations for collection centers Project Support 40 hrs $2,400.00 5 days Mon 10/2/17 Fri 10/6/17 13 1.2.1.2 Obtain permits needed operations within the locations Local Fees[$2,500.00],Project Support 12 hrs $3,220.00 3 days Mon 10/9/17 Wed 10/11/17 14 1.2.2 Marketing 83 hrs $8,655.00 101 days Mon 9/25/17 Mon 2/12/18 15 1.2.2.1 Create contract for marketing consultation Contract Specialist 8 hrs $480.00 1 day Mon 9/25/17 Mon 9/25/17 16 1.2.2.2 Signed contract for a marketing/communication plan (milesto 0 hrs $0.00 0 days Mon 9/25/17 Mon 9/25/17 17 1.2.2.3 Design website Marketing Consultant 24 hrs $3,240.00 3 days Mon 10/2/17 Wed 10/4/17 18 1.2.2.4 Create social media ads Marketing Consultant 8 hrs $1,080.00 1 day Thu 10/5/17 Thu 10/5/17 19 1.2.2.5 Create user survey Marketing Consultant 8 hrs $1,080.00 1 day Fri 10/6/17 Fri 10/6/17 20 1.2.2.6 Marketing plan execution begins (milestone) 0 hrs $0.00 0 days Tue 10/10/17 Tue 10/10/17 21 1.2.2.7 Implement marketing plan 35 hrs $2,775.00 89 days Wed 10/11/17 Mon 2/12/18 22 1.2.2.7.1 Publish project website Project Support 4 hrs $240.00 1 day Wed 10/11/17 Wed 10/11/17 23 1.2.2.7.2 Deliver project ad to local radio and TV stations Project Support 14 hrs $840.00 3 days Wed 10/11/17 Fri 10/13/17 24 1.2.2.7.3 Publish ad in local newspapers Project Support 4 hrs $240.00 1 day Thu 10/12/17 Thu 10/12/17 25 1.2.2.7.4 Advertise project on Facebook, Twitter and instagram Project Support 4 hrs $240.00 1 day Thu 10/12/17 Thu 10/12/17 26 1.2.2.7.5 Re-assess marketing 9 hrs $1,215.00 81 days Mon 10/23/17 Mon 2/12/18 27 1.2.2.7.5.1 Re-assess marketing 1 Project Manager 1 hr $135.00 1 day Mon 10/23/17 Mon 10/23/17 28 1.2.2.7.5.2 Re-assess marketing 2 Project Manager 1 hr $135.00 1 day Mon 11/6/17 Mon 11/6/17 29 1.2.2.7.5.3 Re-assess marketing 3 Project Manager 1 hr $135.00 1 day Mon 11/20/17 Mon 11/20/17 30 1.2.2.7.5.4 Re-assess marketing 4 Project Manager 1 hr $135.00 1 day Mon 12/4/17 Mon 12/4/17 31 1.2.2.7.5.5 Re-assess marketing 5 Project Manager 1 hr $135.00 1 day Mon 12/18/17 Mon 12/18/17 32 1.2.2.7.5.6 Re-assess marketing 6 Project Manager 1 hr $135.00 1 day Mon 1/1/18 Mon 1/1/18 33 1.2.2.7.5.7 Re-assess marketing 7 Project Manager 1 hr $135.00 1 day Mon 1/15/18 Mon 1/15/18 FinalProject Page 1

Transcript of FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

Page 1: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

1 1 Collect, Refurbish and Recycle Project 8,891 hrs $910,768.00 162 days Sun 9/17/17 Mon 4/30/182 1.1 Project Management 52 hrs $7,020.00 9 days Sun 9/17/17 Wed 9/27/173 1.1.1 Project Kick-Off (Milestone) 0 hrs $0.00 0 days Sun 9/17/17 Sun 9/17/174 1.1.2 Assess risk Project Manager 4 hrs $540.00 1 day Mon 9/18/17 Mon 9/18/175 1.1.3 Develop scope management plan Project Manager 8 hrs $1,080.00 1 day Tue 9/19/17 Tue 9/19/176 1.1.4 Collect requirements Project Manager 4 hrs $540.00 1 day Wed 9/20/17 Wed 9/20/177 1.1.5 Conduct time planning Project Manager 8 hrs $1,080.00 1 day Thu 9/21/17 Thu 9/21/178 1.1.6 Develop project management plan Project Manager 20 hrs $2,700.00 3 days Fri 9/22/17 Tue 9/26/179 1.1.7 Develop cost management plan Project Manager 8 hrs $1,080.00 1 day Wed 9/27/17 Wed 9/27/1710 1.2 Plan project 179 hrs $16,915.00 101 days Mon 9/25/17 Mon 2/12/1811 1.2.1 Conduct collection center prep 52 hrs $5,620.00 8 days Mon 10/2/17 Wed 10/11/1712 1.2.1.1 Identify potential locations for collection centers Project Support 40 hrs $2,400.00 5 days Mon 10/2/17 Fri 10/6/1713 1.2.1.2 Obtain permits needed operations within the locations Local Fees[$2,500.00],Project

Support12 hrs $3,220.00 3 days Mon 10/9/17 Wed 10/11/17

14 1.2.2 Marketing 83 hrs $8,655.00 101 days Mon 9/25/17 Mon 2/12/1815 1.2.2.1 Create contract for marketing consultation Contract Specialist 8 hrs $480.00 1 day Mon 9/25/17 Mon 9/25/1716 1.2.2.2 Signed contract for a marketing/communication plan (milestone) 0 hrs $0.00 0 days Mon 9/25/17 Mon 9/25/1717 1.2.2.3 Design website Marketing Consultant 24 hrs $3,240.00 3 days Mon 10/2/17 Wed 10/4/1718 1.2.2.4 Create social media ads Marketing Consultant 8 hrs $1,080.00 1 day Thu 10/5/17 Thu 10/5/1719 1.2.2.5 Create user survey Marketing Consultant 8 hrs $1,080.00 1 day Fri 10/6/17 Fri 10/6/1720 1.2.2.6 Marketing plan execution begins (milestone) 0 hrs $0.00 0 days Tue 10/10/17 Tue 10/10/1721 1.2.2.7 Implement marketing plan 35 hrs $2,775.00 89 days Wed 10/11/17 Mon 2/12/1822 1.2.2.7.1 Publish project website Project Support 4 hrs $240.00 1 day Wed 10/11/17 Wed 10/11/1723 1.2.2.7.2 Deliver project ad to local radio and TV stations Project Support 14 hrs $840.00 3 days Wed 10/11/17 Fri 10/13/17

24 1.2.2.7.3 Publish ad in local newspapers Project Support 4 hrs $240.00 1 day Thu 10/12/17 Thu 10/12/1725 1.2.2.7.4 Advertise project on Facebook, Twitter and instagram Project Support 4 hrs $240.00 1 day Thu 10/12/17 Thu 10/12/17

26 1.2.2.7.5 Re-assess marketing 9 hrs $1,215.00 81 days Mon 10/23/17 Mon 2/12/1827 1.2.2.7.5.1 Re-assess marketing 1 Project Manager 1 hr $135.00 1 day Mon 10/23/17 Mon 10/23/1728 1.2.2.7.5.2 Re-assess marketing 2 Project Manager 1 hr $135.00 1 day Mon 11/6/17 Mon 11/6/1729 1.2.2.7.5.3 Re-assess marketing 3 Project Manager 1 hr $135.00 1 day Mon 11/20/17 Mon 11/20/1730 1.2.2.7.5.4 Re-assess marketing 4 Project Manager 1 hr $135.00 1 day Mon 12/4/17 Mon 12/4/1731 1.2.2.7.5.5 Re-assess marketing 5 Project Manager 1 hr $135.00 1 day Mon 12/18/17 Mon 12/18/1732 1.2.2.7.5.6 Re-assess marketing 6 Project Manager 1 hr $135.00 1 day Mon 1/1/18 Mon 1/1/1833 1.2.2.7.5.7 Re-assess marketing 7 Project Manager 1 hr $135.00 1 day Mon 1/15/18 Mon 1/15/18

FinalProject

Page 1

Page 2: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

34 1.2.2.7.5.8 Re-assess marketing 8 Project Manager 1 hr $135.00 1 day Mon 1/29/18 Mon 1/29/1835 1.2.2.7.5.9 Re-assess marketing 9 Project Manager 1 hr $135.00 1 day Mon 2/12/18 Mon 2/12/1836 1.2.3 Manage recycle and refurbish contracts 44 hrs $2,640.00 13 days Mon 10/2/17 Wed 10/18/1737 1.2.3.1 Create contract for heavy machinery Contract Specialist 8 hrs $480.00 1 day Mon 10/2/17 Mon 10/2/1738 1.2.3.2 Create contract for collection center personnel Contract Specialist 8 hrs $480.00 1 day Tue 10/3/17 Tue 10/3/1739 1.2.3.3 Create contract with electronics refurbishment company Contract Specialist 8 hrs $480.00 1 day Wed 10/4/17 Wed 10/4/17

40 1.2.3.4 Create contract with electronics recycling company Contract Specialist 8 hrs $480.00 1 day Thu 10/5/17 Thu 10/5/17

41 1.2.3.5 Signed contract for electronics recycling company and refurbishing company (milestone) 0 hrs $0.00 0 days Thu 10/5/17 Thu 10/5/1742 1.2.3.6 Create contract for transportation of mobile teams Contract Specialist 12 hrs $720.00 2 days Thu 10/12/17 Fri 10/13/17

43 1.2.3.7 Signed contract for mobile electronic refurbish/ collection teams (milestone) 0 hrs $0.00 0 days Wed 10/18/17 Wed 10/18/1744 1.3 Collect and process electronics 8,492 hrs $871,803.00 123 days Thu 10/12/17 Sat 3/31/1845 1.3.1 Setup collection centers 62 hrs $195,658.00 121 days Fri 10/13/17 Fri 3/30/1846 1.3.1.1 Acquire collection center facilities Collection Facility[5 Building],Project Support4 hrs $40,740.00 1 day Mon 10/9/17 Mon 10/9/1747 1.3.1.2 Assign staff Project Support 8 hrs $480.00 1 day Tue 10/10/17 Tue 10/10/1748 1.3.1.3 Develop physical collection plan Project Manager 8 hrs $1,080.00 1 day Tue 10/10/17 Tue 10/10/1749 1.3.1.4 Obtain refurbishing equipment Refurbishing Equipment[10],Collection Center 1 Support - Non Certified,Collection Center 2 Support - Non Certified,Collection Center 3 Support - Non Certified,Collection Center 4 Support - Non Certified,Collection Center 5 Support - Non Certified4 hrs $6,520.00 1 day Thu 10/12/17 Thu 10/12/1750 1.3.1.5 Obtain heavy equipment and associated materials Heavy equipment[5],Collection

Center 1 Support - Certified,Collection Center 2

4 hrs $106,548.00 1 day Fri 10/13/17 Fri 10/13/17

51 1.3.1.6 Obtain Tractor-trailers Tractor-trailer[5],Project Support 4 hrs $36,240.00 1 day Fri 10/13/17 Fri 10/13/17

52 1.3.1.7 Collection center setup with all equipment and trailers for collection (milestone) 0 hrs $0.00 0 days Mon 10/16/17 Mon 10/16/1753 1.3.1.8 Conduct budget analysis 30 hrs $4,050.00 111 days Fri 10/27/17 Fri 3/30/1854 1.3.1.8.1 Re-assess cost 22 hrs $2,970.00 101 days Fri 10/27/17 Fri 3/16/1855 1.3.1.8.1.1 Re-assess cost week 2 Project Manager 2 hrs $270.00 1 day Fri 10/27/17 Fri 10/27/1756 1.3.1.8.1.2 Re-assess cost week 4 Project Manager 2 hrs $270.00 1 day Fri 11/10/17 Fri 11/10/1757 1.3.1.8.1.3 Re-assess cost week 6 Project Manager 2 hrs $270.00 1 day Fri 11/24/17 Fri 11/24/1758 1.3.1.8.1.4 Re-assess cost week 8 Project Manager 2 hrs $270.00 1 day Fri 12/8/17 Fri 12/8/1759 1.3.1.8.1.5 Re-assess cost week 10 Project Manager 2 hrs $270.00 1 day Fri 12/22/17 Fri 12/22/1760 1.3.1.8.1.6 Re-assess cost week 12 Project Manager 2 hrs $270.00 1 day Fri 1/5/18 Fri 1/5/1861 1.3.1.8.1.7 Re-assess cost week 14 Project Manager 2 hrs $270.00 1 day Fri 1/19/18 Fri 1/19/1862 1.3.1.8.1.8 Re-assess cost week 16 Project Manager 2 hrs $270.00 1 day Fri 2/2/18 Fri 2/2/1863 1.3.1.8.1.9 Re-assess cost week 18 Project Manager 2 hrs $270.00 1 day Fri 2/16/18 Fri 2/16/1864 1.3.1.8.1.10 Re-assess cost week 20 Project Manager 2 hrs $270.00 1 day Fri 3/2/18 Fri 3/2/18

FinalProject

Page 2

Page 3: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

65 1.3.1.8.1.11 Re-assess cost week 22 Project Manager 2 hrs $270.00 1 day Fri 3/16/18 Fri 3/16/1866 1.3.1.8.2 Project expense rollup Project Manager 8 hrs $1,080.00 1 day Fri 3/30/18 Fri 3/30/1867 1.3.2 Receive electronics 4,070 hrs $274,725.00 112 days Thu 10/19/17 Fri 3/23/1868 1.3.2.1 All centers are open for business (milestone) 0 hrs $0.00 0 days Thu 10/19/17 Thu 10/19/1769 1.3.2.2 Collection Center 1 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/1870 1.3.2.2.1 Bi-Weekly Collection 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/1871 1.3.2.2.1.1 Bi-Weekly Collection 1 74 hrs $4,995.00 10 days Mon 10/23/17 Fri 11/3/1772 1.3.2.2.1.1.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 10/23/17 Fri 11/3/1773 1.3.2.2.1.1.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 10/23/17 Fri 11/3/1774 1.3.2.2.1.1.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 10/30/17 Thu 11/2/1775 1.3.2.2.1.1.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 11/3/17 Fri 11/3/1776 1.3.2.2.1.2 Bi-Weekly Collection 2 74 hrs $4,995.00 10 days Mon 11/6/17 Fri 11/17/1777 1.3.2.2.1.2.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 11/6/17 Fri 11/17/1778 1.3.2.2.1.2.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 11/6/17 Fri 11/17/1779 1.3.2.2.1.2.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 11/13/17 Thu 11/16/1780 1.3.2.2.1.2.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 11/17/17 Fri 11/17/1781 1.3.2.2.1.3 Bi-Weekly Collection 3 74 hrs $4,995.00 10 days Mon 11/20/17 Fri 12/1/1782 1.3.2.2.1.3.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 2 days Mon 11/20/17 Wed 11/22/1783 1.3.2.2.1.3.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 4 days Mon 11/20/17 Fri 11/24/1784 1.3.2.2.1.3.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 7 days Mon 11/27/17 Wed 12/6/1785 1.3.2.2.1.3.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 12/1/17 Fri 12/1/1786 1.3.2.2.1.4 Bi-Weekly Collection 4 74 hrs $4,995.00 10 days Mon 12/4/17 Fri 12/15/1787 1.3.2.2.1.4.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 12/4/17 Fri 12/15/1788 1.3.2.2.1.4.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 12/4/17 Fri 12/15/1789 1.3.2.2.1.4.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 12/11/17 Thu 12/14/1790 1.3.2.2.1.4.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 12/15/17 Fri 12/15/1791 1.3.2.2.1.5 Bi-Weekly Collection 5 74 hrs $4,995.00 10 days Mon 12/18/17 Fri 12/29/1792 1.3.2.2.1.5.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 12/18/17 Fri 12/29/1793 1.3.2.2.1.5.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 12/18/17 Fri 12/29/1794 1.3.2.2.1.5.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 12/18/17 Thu 12/28/1795 1.3.2.2.1.5.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 12/29/17 Fri 12/29/1796 1.3.2.2.1.6 Bi-Weekly Collection 6 74 hrs $4,995.00 10 days Mon 1/1/18 Fri 1/12/1897 1.3.2.2.1.6.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 1/1/18 Fri 1/12/1898 1.3.2.2.1.6.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/1/18 Fri 1/12/1899 1.3.2.2.1.6.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 1/8/18 Thu 1/11/18100 1.3.2.2.1.6.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Mon 1/8/18 Mon 1/8/18

FinalProject

Page 3

Page 4: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

101 1.3.2.2.1.7 Bi-Weekly Collection 7 74 hrs $4,995.00 10 days Mon 1/15/18 Fri 1/26/18102 1.3.2.2.1.7.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 1/15/18 Fri 1/26/18103 1.3.2.2.1.7.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/15/18 Fri 1/26/18104 1.3.2.2.1.7.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 1/22/18 Thu 1/25/18105 1.3.2.2.1.7.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 1/26/18 Fri 1/26/18106 1.3.2.2.1.8 Bi-Weekly Collection 8 74 hrs $4,995.00 10 days Mon 1/29/18 Fri 2/9/18107 1.3.2.2.1.8.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 1/29/18 Fri 2/9/18108 1.3.2.2.1.8.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/29/18 Fri 2/9/18109 1.3.2.2.1.8.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 2/5/18 Thu 2/8/18110 1.3.2.2.1.8.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 2/9/18 Fri 2/9/18111 1.3.2.2.1.9 Bi-Weekly Collection 9 74 hrs $4,995.00 10 days Mon 2/12/18 Fri 2/23/18112 1.3.2.2.1.9.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 2/12/18 Fri 2/23/18113 1.3.2.2.1.9.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 2/12/18 Fri 2/23/18114 1.3.2.2.1.9.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 2/19/18 Thu 2/22/18115 1.3.2.2.1.9.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 2/23/18 Fri 2/23/18116 1.3.2.2.1.10 Bi-Weekly Collection 10 74 hrs $4,995.00 10 days Mon 2/26/18 Fri 3/9/18117 1.3.2.2.1.10.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 2/26/18 Fri 3/9/18118 1.3.2.2.1.10.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 2/26/18 Fri 3/9/18119 1.3.2.2.1.10.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 3/5/18 Thu 3/8/18120 1.3.2.2.1.10.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 3/9/18 Fri 3/9/18121 1.3.2.2.1.11 Bi-Weekly Collection 11 74 hrs $4,995.00 10 days Mon 3/12/18 Fri 3/23/18122 1.3.2.2.1.11.1 Administer Survey to all patrons Collection Center 1 Support - Non Certified10 hrs $675.00 10 days Mon 3/12/18 Fri 3/23/18123 1.3.2.2.1.11.2 Inspect electronics for hazardous material Collection Center 1 Support - Non Certified20 hrs $1,350.00 10 days Mon 3/12/18 Fri 3/23/18124 1.3.2.2.1.11.3 Assess electronics and sort by refurbish or recycleCollection Center 1 Support - Non Certified40 hrs $2,700.00 4 days Mon 3/19/18 Thu 3/22/18125 1.3.2.2.1.11.4 Create collection report Collection Center 1 Support - Non Certified4 hrs $270.00 1 day Fri 3/23/18 Fri 3/23/18126 1.3.2.3 Collection Center 2 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/18183 1.3.2.4 Collection Center 3 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/18184 1.3.2.4.1 Bi-Weekly Collection 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/18185 1.3.2.4.1.1 Bi-Weekly Collection 1 74 hrs $4,995.00 10 days Mon 10/23/17 Fri 11/3/17186 1.3.2.4.1.1.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 10/23/17 Fri 11/3/17187 1.3.2.4.1.1.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 10/23/17 Fri 11/3/17188 1.3.2.4.1.1.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 10/30/17 Thu 11/2/17189 1.3.2.4.1.1.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 11/3/17 Fri 11/3/17190 1.3.2.4.1.2 Bi-Weekly Collection 2 74 hrs $4,995.00 10 days Mon 11/6/17 Fri 11/17/17191 1.3.2.4.1.2.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 11/6/17 Fri 11/17/17192 1.3.2.4.1.2.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 11/6/17 Fri 11/17/17

FinalProject

Page 4

Page 5: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

193 1.3.2.4.1.2.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 11/13/17 Thu 11/16/17194 1.3.2.4.1.2.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 11/17/17 Fri 11/17/17195 1.3.2.4.1.3 Bi-Weekly Collection 3 74 hrs $4,995.00 10 days Mon 11/20/17 Fri 12/1/17196 1.3.2.4.1.3.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 4.7 days Mon 11/20/17 Fri 11/24/17197 1.3.2.4.1.3.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 6.41 days Mon 11/20/17 Tue 11/28/17198 1.3.2.4.1.3.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 6.8 days Wed 11/22/17 Thu 11/30/17199 1.3.2.4.1.3.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 12/1/17 Fri 12/1/17200 1.3.2.4.1.4 Bi-Weekly Collection 4 74 hrs $4,995.00 10 days Mon 12/4/17 Fri 12/15/17201 1.3.2.4.1.4.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 12/4/17 Fri 12/15/17202 1.3.2.4.1.4.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 12/4/17 Fri 12/15/17203 1.3.2.4.1.4.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 12/11/17 Thu 12/14/17204 1.3.2.4.1.4.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 12/15/17 Fri 12/15/17205 1.3.2.4.1.5 Bi-Weekly Collection 5 74 hrs $4,995.00 10 days Mon 12/18/17 Fri 12/29/17206 1.3.2.4.1.5.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 12/18/17 Fri 12/29/17207 1.3.2.4.1.5.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 12/18/17 Fri 12/29/17208 1.3.2.4.1.5.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 12/18/17 Thu 12/28/17209 1.3.2.4.1.5.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 12/29/17 Fri 12/29/17210 1.3.2.4.1.6 Bi-Weekly Collection 6 74 hrs $4,995.00 10 days Mon 1/1/18 Fri 1/12/18211 1.3.2.4.1.6.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 1/1/18 Fri 1/12/18212 1.3.2.4.1.6.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/1/18 Fri 1/12/18213 1.3.2.4.1.6.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 1/8/18 Thu 1/11/18214 1.3.2.4.1.6.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Mon 1/8/18 Mon 1/8/18215 1.3.2.4.1.7 Bi-Weekly Collection 7 74 hrs $4,995.00 10 days Mon 1/15/18 Fri 1/26/18216 1.3.2.4.1.7.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 1/15/18 Fri 1/26/18217 1.3.2.4.1.7.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/15/18 Fri 1/26/18218 1.3.2.4.1.7.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 1/22/18 Thu 1/25/18219 1.3.2.4.1.7.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 1/26/18 Fri 1/26/18220 1.3.2.4.1.8 Bi-Weekly Collection 8 74 hrs $4,995.00 10 days Mon 1/29/18 Fri 2/9/18221 1.3.2.4.1.8.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 1/29/18 Fri 2/9/18222 1.3.2.4.1.8.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/29/18 Fri 2/9/18223 1.3.2.4.1.8.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 2/5/18 Thu 2/8/18224 1.3.2.4.1.8.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 2/9/18 Fri 2/9/18225 1.3.2.4.1.9 Bi-Weekly Collection 9 74 hrs $4,995.00 10 days Mon 2/12/18 Fri 2/23/18226 1.3.2.4.1.9.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 2/12/18 Fri 2/23/18227 1.3.2.4.1.9.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 2/12/18 Fri 2/23/18228 1.3.2.4.1.9.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 2/19/18 Thu 2/22/18

FinalProject

Page 5

Page 6: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

229 1.3.2.4.1.9.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 2/23/18 Fri 2/23/18230 1.3.2.4.1.10 Bi-Weekly Collection 10 74 hrs $4,995.00 10 days Mon 2/26/18 Fri 3/9/18231 1.3.2.4.1.10.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 2/26/18 Fri 3/9/18232 1.3.2.4.1.10.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 2/26/18 Fri 3/9/18233 1.3.2.4.1.10.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 3/5/18 Thu 3/8/18234 1.3.2.4.1.10.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 3/9/18 Fri 3/9/18235 1.3.2.4.1.11 Bi-Weekly Collection 11 74 hrs $4,995.00 10 days Mon 3/12/18 Fri 3/23/18236 1.3.2.4.1.11.1 Administer Survey to all patrons Collection Center 3 Support - Non Certified10 hrs $675.00 10 days Mon 3/12/18 Fri 3/23/18237 1.3.2.4.1.11.2 Inspect electronics for hazardous material Collection Center 3 Support - Non Certified20 hrs $1,350.00 10 days Mon 3/12/18 Fri 3/23/18238 1.3.2.4.1.11.3 Assess electronics and sort by refurbish or recycleCollection Center 3 Support - Non Certified40 hrs $2,700.00 4 days Mon 3/19/18 Thu 3/22/18239 1.3.2.4.1.11.4 Create collection report Collection Center 3 Support - Non Certified4 hrs $270.00 1 day Fri 3/23/18 Fri 3/23/18240 1.3.2.5 Collection Center 4 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/18241 1.3.2.5.1 Bi-Weekly Collection 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/18242 1.3.2.5.1.1 Bi-Weekly Collection 1 74 hrs $4,995.00 10 days Mon 10/23/17 Fri 11/3/17243 1.3.2.5.1.1.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 10/23/17 Fri 11/3/17244 1.3.2.5.1.1.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 10/23/17 Fri 11/3/17245 1.3.2.5.1.1.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 10/30/17 Thu 11/2/17246 1.3.2.5.1.1.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 11/3/17 Fri 11/3/17247 1.3.2.5.1.2 Bi-Weekly Collection 2 74 hrs $4,995.00 10 days Mon 11/6/17 Fri 11/17/17248 1.3.2.5.1.2.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 11/6/17 Fri 11/17/17249 1.3.2.5.1.2.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 11/6/17 Fri 11/17/17250 1.3.2.5.1.2.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 11/13/17 Thu 11/16/17251 1.3.2.5.1.2.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 11/17/17 Fri 11/17/17252 1.3.2.5.1.3 Bi-Weekly Collection 3 74 hrs $4,995.00 10 days Mon 11/20/17 Fri 12/1/17253 1.3.2.5.1.3.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 8.84 days Mon 11/20/17 Thu 11/30/17254 1.3.2.5.1.3.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 9.72 days Mon 11/20/17 Fri 12/1/17255 1.3.2.5.1.3.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 7 days Mon 11/27/17 Wed 12/6/17256 1.3.2.5.1.3.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 12/1/17 Fri 12/1/17257 1.3.2.5.1.4 Bi-Weekly Collection 4 74 hrs $4,995.00 10 days Mon 12/4/17 Fri 12/15/17258 1.3.2.5.1.4.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 12/4/17 Fri 12/15/17259 1.3.2.5.1.4.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 12/4/17 Fri 12/15/17260 1.3.2.5.1.4.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 12/11/17 Thu 12/14/17261 1.3.2.5.1.4.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 12/15/17 Fri 12/15/17262 1.3.2.5.1.5 Bi-Weekly Collection 5 74 hrs $4,995.00 10 days Mon 12/18/17 Fri 12/29/17263 1.3.2.5.1.5.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 12/18/17 Fri 12/29/17264 1.3.2.5.1.5.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 12/18/17 Fri 12/29/17

FinalProject

Page 6

Page 7: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

265 1.3.2.5.1.5.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 12/18/17 Thu 12/28/17266 1.3.2.5.1.5.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 12/29/17 Fri 12/29/17267 1.3.2.5.1.6 Bi-Weekly Collection 6 74 hrs $4,995.00 10 days Mon 1/1/18 Fri 1/12/18268 1.3.2.5.1.6.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 1/1/18 Fri 1/12/18269 1.3.2.5.1.6.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/1/18 Fri 1/12/18270 1.3.2.5.1.6.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 1/8/18 Thu 1/11/18271 1.3.2.5.1.6.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Mon 1/8/18 Mon 1/8/18272 1.3.2.5.1.7 Bi-Weekly Collection 7 74 hrs $4,995.00 10 days Mon 1/15/18 Fri 1/26/18273 1.3.2.5.1.7.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 1/15/18 Fri 1/26/18274 1.3.2.5.1.7.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/15/18 Fri 1/26/18275 1.3.2.5.1.7.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 1/22/18 Thu 1/25/18276 1.3.2.5.1.7.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 1/26/18 Fri 1/26/18277 1.3.2.5.1.8 Bi-Weekly Collection 8 74 hrs $4,995.00 10 days Mon 1/29/18 Fri 2/9/18278 1.3.2.5.1.8.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 1/29/18 Fri 2/9/18279 1.3.2.5.1.8.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/29/18 Fri 2/9/18280 1.3.2.5.1.8.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 2/5/18 Thu 2/8/18281 1.3.2.5.1.8.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 2/9/18 Fri 2/9/18282 1.3.2.5.1.9 Bi-Weekly Collection 9 74 hrs $4,995.00 10 days Mon 2/12/18 Fri 2/23/18283 1.3.2.5.1.9.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 2/12/18 Fri 2/23/18284 1.3.2.5.1.9.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 2/12/18 Fri 2/23/18285 1.3.2.5.1.9.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 2/19/18 Thu 2/22/18286 1.3.2.5.1.9.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 2/23/18 Fri 2/23/18287 1.3.2.5.1.10 Bi-Weekly Collection 10 74 hrs $4,995.00 10 days Mon 2/26/18 Fri 3/9/18288 1.3.2.5.1.10.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 2/26/18 Fri 3/9/18289 1.3.2.5.1.10.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 2/26/18 Fri 3/9/18290 1.3.2.5.1.10.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 3/5/18 Thu 3/8/18291 1.3.2.5.1.10.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 3/9/18 Fri 3/9/18292 1.3.2.5.1.11 Bi-Weekly Collection 11 74 hrs $4,995.00 10 days Mon 3/12/18 Fri 3/23/18293 1.3.2.5.1.11.1 Administer Survey to all patrons Collection Center 4 Support - Non Certified10 hrs $675.00 10 days Mon 3/12/18 Fri 3/23/18294 1.3.2.5.1.11.2 Inspect electronics for hazardous material Collection Center 4 Support - Non Certified20 hrs $1,350.00 10 days Mon 3/12/18 Fri 3/23/18295 1.3.2.5.1.11.3 Assess electronics and sort by refurbish or recycleCollection Center 4 Support - Non Certified40 hrs $2,700.00 4 days Mon 3/19/18 Thu 3/22/18296 1.3.2.5.1.11.4 Create collection report Collection Center 4 Support - Non Certified4 hrs $270.00 1 day Fri 3/23/18 Fri 3/23/18297 1.3.2.6 Collection Center 5 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/18298 1.3.2.6.1 Bi-Weekly Collection 814 hrs $54,945.00 110 days Mon 10/23/17 Fri 3/23/18299 1.3.2.6.1.1 Bi-Weekly Collection 1 74 hrs $4,995.00 10 days Mon 10/23/17 Fri 11/3/17300 1.3.2.6.1.1.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 10/23/17 Fri 11/3/17

FinalProject

Page 7

Page 8: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

301 1.3.2.6.1.1.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 10/23/17 Fri 11/3/17302 1.3.2.6.1.1.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 10/30/17 Thu 11/2/17303 1.3.2.6.1.1.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 11/3/17 Fri 11/3/17304 1.3.2.6.1.2 Bi-Weekly Collection 2 74 hrs $4,995.00 10 days Mon 11/6/17 Fri 11/17/17305 1.3.2.6.1.2.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 11/6/17 Fri 11/17/17306 1.3.2.6.1.2.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 11/6/17 Fri 11/17/17307 1.3.2.6.1.2.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 11/13/17 Thu 11/16/17308 1.3.2.6.1.2.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 11/17/17 Fri 11/17/17309 1.3.2.6.1.3 Bi-Weekly Collection 3 74 hrs $4,995.00 10 days Mon 11/20/17 Fri 12/1/17310 1.3.2.6.1.3.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 11/20/17 Fri 12/1/17311 1.3.2.6.1.3.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 11/20/17 Fri 12/1/17312 1.3.2.6.1.3.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 11/27/17 Thu 11/30/17313 1.3.2.6.1.3.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 12/1/17 Fri 12/1/17314 1.3.2.6.1.4 Bi-Weekly Collection 4 74 hrs $4,995.00 10 days Mon 12/4/17 Fri 12/15/17315 1.3.2.6.1.4.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 12/4/17 Fri 12/15/17316 1.3.2.6.1.4.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 12/4/17 Fri 12/15/17317 1.3.2.6.1.4.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 12/11/17 Thu 12/14/17318 1.3.2.6.1.4.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 12/15/17 Fri 12/15/17319 1.3.2.6.1.5 Bi-Weekly Collection 5 74 hrs $4,995.00 10 days Mon 12/18/17 Fri 12/29/17320 1.3.2.6.1.5.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 12/18/17 Fri 12/29/17321 1.3.2.6.1.5.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 12/18/17 Fri 12/29/17322 1.3.2.6.1.5.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 12/18/17 Thu 12/28/17323 1.3.2.6.1.5.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 12/29/17 Fri 12/29/17324 1.3.2.6.1.6 Bi-Weekly Collection 6 74 hrs $4,995.00 10 days Mon 1/1/18 Fri 1/12/18325 1.3.2.6.1.6.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 1/1/18 Fri 1/12/18326 1.3.2.6.1.6.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/1/18 Fri 1/12/18327 1.3.2.6.1.6.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 1/8/18 Thu 1/11/18328 1.3.2.6.1.6.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Mon 1/8/18 Mon 1/8/18329 1.3.2.6.1.7 Bi-Weekly Collection 7 74 hrs $4,995.00 10 days Mon 1/15/18 Fri 1/26/18330 1.3.2.6.1.7.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 1/15/18 Fri 1/26/18331 1.3.2.6.1.7.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/15/18 Fri 1/26/18332 1.3.2.6.1.7.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 1/22/18 Thu 1/25/18333 1.3.2.6.1.7.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 1/26/18 Fri 1/26/18334 1.3.2.6.1.8 Bi-Weekly Collection 8 74 hrs $4,995.00 10 days Mon 1/29/18 Fri 2/9/18335 1.3.2.6.1.8.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 1/29/18 Fri 2/9/18336 1.3.2.6.1.8.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 1/29/18 Fri 2/9/18

FinalProject

Page 8

Page 9: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

337 1.3.2.6.1.8.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 2/5/18 Thu 2/8/18338 1.3.2.6.1.8.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 2/9/18 Fri 2/9/18339 1.3.2.6.1.9 Bi-Weekly Collection 9 74 hrs $4,995.00 10 days Mon 2/12/18 Fri 2/23/18340 1.3.2.6.1.9.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 2/12/18 Fri 2/23/18341 1.3.2.6.1.9.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 2/12/18 Fri 2/23/18342 1.3.2.6.1.9.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 2/19/18 Thu 2/22/18343 1.3.2.6.1.9.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 2/23/18 Fri 2/23/18344 1.3.2.6.1.10 Bi-Weekly Collection 10 74 hrs $4,995.00 10 days Mon 2/26/18 Fri 3/9/18345 1.3.2.6.1.10.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 2/26/18 Fri 3/9/18346 1.3.2.6.1.10.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 2/26/18 Fri 3/9/18347 1.3.2.6.1.10.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 3/5/18 Thu 3/8/18348 1.3.2.6.1.10.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 3/9/18 Fri 3/9/18349 1.3.2.6.1.11 Bi-Weekly Collection 11 74 hrs $4,995.00 10 days Mon 3/12/18 Fri 3/23/18350 1.3.2.6.1.11.1 Administer Survey to all patrons Collection Center 5 Support - Non Certified10 hrs $675.00 10 days Mon 3/12/18 Fri 3/23/18351 1.3.2.6.1.11.2 Inspect electronics for hazardous material Collection Center 5 Support - Non Certified20 hrs $1,350.00 10 days Mon 3/12/18 Fri 3/23/18352 1.3.2.6.1.11.3 Assess electronics and sort by refurbish or recycleCollection Center 5 Support - Non Certified40 hrs $2,700.00 4 days Mon 3/19/18 Thu 3/22/18353 1.3.2.6.1.11.4 Create collection report Collection Center 5 Support - Non Certified4 hrs $270.00 1 day Fri 3/23/18 Fri 3/23/18354 1.3.3 Recycle/ Refurbish electronics 2,400 hrs $192,000.00 115 days Mon 10/23/17 Fri 3/30/18355 1.3.3.1 Refurbish electronics 2,400 hrs $192,000.00 115 days Mon 10/23/17 Fri 3/30/18356 1.3.3.1.1 Collection Center 1 480 hrs $38,400.00 115 days Mon 10/23/17 Fri 3/30/18357 1.3.3.1.1.1 Repair electronics week 1 Technician CC 1 40 hrs $3,200.00 10 days Mon 10/23/17 Fri 11/3/17358 1.3.3.1.1.2 Repair electronics week 3 Technician CC 1 40 hrs $3,200.00 10 days Mon 11/6/17 Fri 11/17/17359 1.3.3.1.1.3 Repair electronics week 5 Technician CC 1 40 hrs $3,200.00 10 days Mon 11/20/17 Fri 12/1/17360 1.3.3.1.1.4 Repair electronics week 7 Technician CC 1 40 hrs $3,200.00 10 days Mon 12/4/17 Fri 12/15/17361 1.3.3.1.1.5 Repair electronics week 9 Technician CC 1 40 hrs $3,200.00 10 days Mon 12/18/17 Fri 12/29/17362 1.3.3.1.1.6 Repair electronics week 11 Technician CC 1 40 hrs $3,200.00 10 days Mon 1/1/18 Fri 1/12/18363 1.3.3.1.1.7 Repair electronics week 13 Technician CC 1 40 hrs $3,200.00 10 days Mon 1/15/18 Fri 1/26/18364 1.3.3.1.1.8 Repair electronics week 15 Technician CC 1 40 hrs $3,200.00 10 days Mon 1/29/18 Fri 2/9/18365 1.3.3.1.1.9 Repair electronics week 17 Technician CC 1 40 hrs $3,200.00 10 days Mon 2/12/18 Fri 2/23/18366 1.3.3.1.1.10 Repair electronics week 19 Technician CC 1 40 hrs $3,200.00 10 days Mon 2/26/18 Fri 3/9/18367 1.3.3.1.1.11 Repair electronics week 21 Technician CC 1 40 hrs $3,200.00 10 days Mon 3/12/18 Fri 3/23/18368 1.3.3.1.1.12 Repair electronics week 23 Technician CC 1 40 hrs $3,200.00 5 days Mon 3/26/18 Fri 3/30/18369 1.3.3.1.2 Collection Center 2 480 hrs $38,400.00 115 days Mon 10/23/17 Fri 3/30/18370 1.3.3.1.2.1 Repair electronics week 1 Technician CC 2 40 hrs $3,200.00 10 days Mon 10/23/17 Fri 11/3/17371 1.3.3.1.2.2 Repair electronics week 3 Technician CC 2 40 hrs $3,200.00 10 days Mon 11/6/17 Fri 11/17/17372 1.3.3.1.2.3 Repair electronics week 5 Technician CC 2 40 hrs $3,200.00 10 days Mon 11/20/17 Fri 12/1/17

FinalProject

Page 9

Page 10: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

373 1.3.3.1.2.4 Repair electronics week 7 Technician CC 2 40 hrs $3,200.00 10 days Mon 12/4/17 Fri 12/15/17374 1.3.3.1.2.5 Repair electronics week 9 Technician CC 2 40 hrs $3,200.00 10 days Mon 12/18/17 Fri 12/29/17375 1.3.3.1.2.6 Repair electronics week 11 Technician CC 2 40 hrs $3,200.00 10 days Mon 1/1/18 Fri 1/12/18376 1.3.3.1.2.7 Repair electronics week 13 Technician CC 2 40 hrs $3,200.00 10 days Mon 1/15/18 Fri 1/26/18377 1.3.3.1.2.8 Repair electronics week 15 Technician CC 2 40 hrs $3,200.00 10 days Mon 1/29/18 Fri 2/9/18378 1.3.3.1.2.9 Repair electronics week 17 Technician CC 2 40 hrs $3,200.00 10 days Mon 2/12/18 Fri 2/23/18379 1.3.3.1.2.10 Repair electronics week 19 Technician CC 2 40 hrs $3,200.00 10 days Mon 2/26/18 Fri 3/9/18380 1.3.3.1.2.11 Repair electronics week 21 Technician CC 2 40 hrs $3,200.00 10 days Mon 3/12/18 Fri 3/23/18381 1.3.3.1.2.12 Repair electronics week 23 Technician CC 2 40 hrs $3,200.00 5 days Mon 3/26/18 Fri 3/30/18382 1.3.3.1.3 Collection Center 3 480 hrs $38,400.00 115 days Mon 10/23/17 Fri 3/30/18383 1.3.3.1.3.1 Repair electronics week 1 Technician CC 3 40 hrs $3,200.00 10 days Mon 10/23/17 Fri 11/3/17384 1.3.3.1.3.2 Repair electronics week 3 Technician CC 3 40 hrs $3,200.00 10 days Mon 11/6/17 Fri 11/17/17385 1.3.3.1.3.3 Repair electronics week 5 Technician CC 3 40 hrs $3,200.00 10 days Mon 11/20/17 Fri 12/1/17386 1.3.3.1.3.4 Repair electronics week 7 Technician CC 3 40 hrs $3,200.00 10 days Mon 12/4/17 Fri 12/15/17387 1.3.3.1.3.5 Repair electronics week 9 Technician CC 3 40 hrs $3,200.00 10 days Mon 12/18/17 Fri 12/29/17388 1.3.3.1.3.6 Repair electronics week 11 Technician CC 3 40 hrs $3,200.00 10 days Mon 1/1/18 Fri 1/12/18389 1.3.3.1.3.7 Repair electronics week 13 Technician CC 3 40 hrs $3,200.00 10 days Mon 1/15/18 Fri 1/26/18390 1.3.3.1.3.8 Repair electronics week 15 Technician CC 3 40 hrs $3,200.00 10 days Mon 1/29/18 Fri 2/9/18391 1.3.3.1.3.9 Repair electronics week 17 Technician CC 3 40 hrs $3,200.00 10 days Mon 2/12/18 Fri 2/23/18392 1.3.3.1.3.10 Repair electronics week 19 Technician CC 3 40 hrs $3,200.00 10 days Mon 2/26/18 Fri 3/9/18393 1.3.3.1.3.11 Repair electronics week 21 Technician CC 3 40 hrs $3,200.00 10 days Mon 3/12/18 Fri 3/23/18394 1.3.3.1.3.12 Repair electronics week 23 Technician CC 3 40 hrs $3,200.00 5 days Mon 3/26/18 Fri 3/30/18395 1.3.3.1.4 Collection Center 4 480 hrs $38,400.00 115 days Mon 10/23/17 Fri 3/30/18396 1.3.3.1.4.1 Repair electronics week 1 Technician CC 4 40 hrs $3,200.00 10 days Mon 10/23/17 Fri 11/3/17397 1.3.3.1.4.2 Repair electronics week 3 Technician CC 4 40 hrs $3,200.00 10 days Mon 11/6/17 Fri 11/17/17398 1.3.3.1.4.3 Repair electronics week 5 Technician CC 4 40 hrs $3,200.00 10 days Mon 11/20/17 Fri 12/1/17399 1.3.3.1.4.4 Repair electronics week 7 Technician CC 4 40 hrs $3,200.00 10 days Mon 12/4/17 Fri 12/15/17400 1.3.3.1.4.5 Repair electronics week 9 Technician CC 4 40 hrs $3,200.00 10 days Mon 12/18/17 Fri 12/29/17401 1.3.3.1.4.6 Repair electronics week 11 Technician CC 4 40 hrs $3,200.00 10 days Mon 1/1/18 Fri 1/12/18402 1.3.3.1.4.7 Repair electronics week 13 Technician CC 4 40 hrs $3,200.00 10 days Mon 1/15/18 Fri 1/26/18403 1.3.3.1.4.8 Repair electronics week 15 Technician CC 4 40 hrs $3,200.00 10 days Mon 1/29/18 Fri 2/9/18404 1.3.3.1.4.9 Repair electronics week 17 Technician CC 4 40 hrs $3,200.00 10 days Mon 2/12/18 Fri 2/23/18405 1.3.3.1.4.10 Repair electronics week 19 Technician CC 4 40 hrs $3,200.00 10 days Mon 2/26/18 Fri 3/9/18406 1.3.3.1.4.11 Repair electronics week 21 Technician CC 4 40 hrs $3,200.00 10 days Mon 3/12/18 Fri 3/23/18407 1.3.3.1.4.12 Repair electronics week 23 Technician CC 4 40 hrs $3,200.00 5 days Mon 3/26/18 Fri 3/30/18408 1.3.3.1.5 Collection Center 5 480 hrs $38,400.00 115 days Mon 10/23/17 Fri 3/30/18

FinalProject

Page 10

Page 11: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

409 1.3.3.1.5.1 Repair electronics week 1 Technician CC 5 40 hrs $3,200.00 10 days Mon 10/23/17 Fri 11/3/17410 1.3.3.1.5.2 Repair electronics week 3 Technician CC 5 40 hrs $3,200.00 10 days Mon 11/6/17 Fri 11/17/17411 1.3.3.1.5.3 Repair electronics week 5 Technician CC 5 40 hrs $3,200.00 10 days Mon 11/20/17 Fri 12/1/17412 1.3.3.1.5.4 Repair electronics week 7 Technician CC 5 40 hrs $3,200.00 10 days Mon 12/4/17 Fri 12/15/17413 1.3.3.1.5.5 Repair electronics week 9 Technician CC 5 40 hrs $3,200.00 10 days Mon 12/18/17 Fri 12/29/17414 1.3.3.1.5.6 Repair electronics week 11 Technician CC 5 40 hrs $3,200.00 10 days Mon 1/1/18 Fri 1/12/18415 1.3.3.1.5.7 Repair electronics week 13 Technician CC 5 40 hrs $3,200.00 10 days Mon 1/15/18 Fri 1/26/18416 1.3.3.1.5.8 Repair electronics week 15 Technician CC 5 40 hrs $3,200.00 10 days Mon 1/29/18 Fri 2/9/18417 1.3.3.1.5.9 Repair electronics week 17 Technician CC 5 40 hrs $3,200.00 10 days Mon 2/12/18 Fri 2/23/18418 1.3.3.1.5.10 Repair electronics week 19 Technician CC 5 40 hrs $3,200.00 10 days Mon 2/26/18 Fri 3/9/18419 1.3.3.1.5.11 Repair electronics week 21 Technician CC 5 40 hrs $3,200.00 10 days Mon 3/12/18 Fri 3/23/18420 1.3.3.1.5.12 Repair electronics week 23 Technician CC 5 40 hrs $3,200.00 5 days Mon 3/26/18 Fri 3/30/18421 1.3.4 Establish off-site service 1,960 hrs $209,420.00 117 days Thu 10/12/17 Fri 3/23/18422 1.3.4.1 Acquire transportation Tech Van[12],Project Support 4 hrs $44,640.00 1 day Wed 10/18/17 Wed 10/18/17423 1.3.4.2 Create mobile service plan Project Manager 16 hrs $2,160.00 2 days Thu 10/12/17 Fri 10/13/17424 1.3.4.3 Obtain refurbishing equipment Refurbishing Equipment[12],Project Support4 hrs $7,740.00 1 day Fri 10/13/17 Fri 10/13/17425 1.3.4.4 Execute mobile service plan 1,936 hrs $154,880.00 110 days Mon 10/23/17 Fri 3/23/18426 1.3.4.4.1 Mobile electronic refurbish/collection teams begin (milestone) 0 hrs $0.00 0 days Thu 11/2/17 Thu 11/2/17427 1.3.4.4.2 Weekly Mobile Collection 1,936 hrs $154,880.00 110 days Mon 10/23/17 Fri 3/23/18428 1.3.4.4.2.1 Weekly Mobile Collection 1 88 hrs $7,040.00 5 days Mon 10/23/17 Fri 10/27/17429 1.3.4.4.2.1.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 10/23/17 Fri 10/27/17430 1.3.4.4.2.1.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 10/23/17 Fri 10/27/17431 1.3.4.4.2.1.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 10/27/17 Fri 10/27/17432 1.3.4.4.2.2 Weekly Mobile Collection 2 88 hrs $7,040.00 5 days Mon 10/30/17 Fri 11/3/17433 1.3.4.4.2.2.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 10/30/17 Fri 11/3/17434 1.3.4.4.2.2.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 10/30/17 Fri 11/3/17435 1.3.4.4.2.2.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 11/3/17 Fri 11/3/17436 1.3.4.4.2.3 Weekly Mobile Collection 3 88 hrs $7,040.00 5 days Mon 11/6/17 Fri 11/10/17437 1.3.4.4.2.3.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 11/6/17 Fri 11/10/17438 1.3.4.4.2.3.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 11/6/17 Fri 11/10/17439 1.3.4.4.2.3.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 11/10/17 Fri 11/10/17440 1.3.4.4.2.4 Weekly Mobile Collection 4 88 hrs $7,040.00 5 days Mon 11/13/17 Fri 11/17/17441 1.3.4.4.2.4.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 11/13/17 Fri 11/17/17442 1.3.4.4.2.4.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 11/13/17 Fri 11/17/17443 1.3.4.4.2.4.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 11/17/17 Fri 11/17/17444 1.3.4.4.2.5 Weekly Mobile Collection 5 88 hrs $7,040.00 5 days Mon 11/20/17 Fri 11/24/17

FinalProject

Page 11

Page 12: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

445 1.3.4.4.2.5.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 11/20/17 Fri 11/24/17446 1.3.4.4.2.5.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 11/20/17 Fri 11/24/17447 1.3.4.4.2.5.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 11/24/17 Fri 11/24/17448 1.3.4.4.2.6 Weekly Mobile Collection 6 88 hrs $7,040.00 5 days Mon 11/27/17 Fri 12/1/17449 1.3.4.4.2.6.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 11/27/17 Fri 12/1/17450 1.3.4.4.2.6.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 11/27/17 Fri 12/1/17451 1.3.4.4.2.6.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 12/1/17 Fri 12/1/17452 1.3.4.4.2.7 Weekly Mobile Collection 7 88 hrs $7,040.00 5 days Mon 12/4/17 Fri 12/8/17453 1.3.4.4.2.7.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 12/4/17 Fri 12/8/17454 1.3.4.4.2.7.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 12/4/17 Fri 12/8/17455 1.3.4.4.2.7.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 12/8/17 Fri 12/8/17456 1.3.4.4.2.8 Weekly Mobile Collection 8 88 hrs $7,040.00 5 days Mon 12/11/17 Fri 12/15/17457 1.3.4.4.2.8.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 12/11/17 Fri 12/15/17458 1.3.4.4.2.8.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 12/11/17 Fri 12/15/17459 1.3.4.4.2.8.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 12/15/17 Fri 12/15/17460 1.3.4.4.2.9 Weekly Mobile Collection 9 88 hrs $7,040.00 5 days Mon 12/18/17 Fri 12/22/17461 1.3.4.4.2.9.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 12/18/17 Fri 12/22/17462 1.3.4.4.2.9.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 12/18/17 Fri 12/22/17463 1.3.4.4.2.9.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 12/22/17 Fri 12/22/17464 1.3.4.4.2.10 Weekly Mobile Collection 10 88 hrs $7,040.00 5 days Mon 12/25/17 Fri 12/29/17465 1.3.4.4.2.10.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 12/25/17 Fri 12/29/17466 1.3.4.4.2.10.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 12/25/17 Fri 12/29/17467 1.3.4.4.2.10.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 12/29/17 Fri 12/29/17468 1.3.4.4.2.11 Weekly Mobile Collection 11 88 hrs $7,040.00 5 days Mon 1/1/18 Fri 1/5/18469 1.3.4.4.2.11.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 1/1/18 Fri 1/5/18470 1.3.4.4.2.11.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 1/1/18 Fri 1/5/18471 1.3.4.4.2.11.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 1/5/18 Fri 1/5/18472 1.3.4.4.2.12 Weekly Mobile Collection 12 88 hrs $7,040.00 5 days Mon 1/8/18 Fri 1/12/18473 1.3.4.4.2.12.1 Collect/ Refurbish electronics Mobile Technician[8%] 40 hrs $3,200.00 60 days Mon 10/23/17 Fri 1/12/18474 1.3.4.4.2.12.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 1/8/18 Fri 1/12/18475 1.3.4.4.2.12.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 1/12/18 Fri 1/12/18476 1.3.4.4.2.13 Weekly Mobile Collection 13 88 hrs $7,040.00 5 days Mon 1/15/18 Fri 1/19/18477 1.3.4.4.2.13.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 1/15/18 Fri 1/19/18478 1.3.4.4.2.13.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 1/15/18 Fri 1/19/18479 1.3.4.4.2.13.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 1/19/18 Fri 1/19/18480 1.3.4.4.2.14 Weekly Mobile Collection 14 88 hrs $7,040.00 5 days Mon 1/22/18 Fri 1/26/18

FinalProject

Page 12

Page 13: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

481 1.3.4.4.2.14.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 1/22/18 Fri 1/26/18482 1.3.4.4.2.14.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days Mon 1/22/18 Fri 1/26/18483 1.3.4.4.2.14.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day Fri 1/26/18 Fri 1/26/18484 1.3.4.4.2.15 Weekly Mobile Collection 15 88 hrs $7,040.00 5 days Mon 1/29/18 Fri 2/2/18485 1.3.4.4.2.15.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 1/29/18 Fri 2/2/18486 1.3.4.4.2.15.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 1/29/18 Fri 2/2/18487 1.3.4.4.2.15.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 2/2/18 Fri 2/2/18488 1.3.4.4.2.16 Weekly Mobile Collection 16 88 hrs $7,040.00 5 days Mon 2/5/18 Fri 2/9/18489 1.3.4.4.2.16.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 2/5/18 Fri 2/9/18490 1.3.4.4.2.16.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 2/5/18 Fri 2/9/18491 1.3.4.4.2.16.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 2/9/18 Fri 2/9/18492 1.3.4.4.2.17 Weekly Mobile Collection 17 88 hrs $7,040.00 5 days Mon 2/12/18 Fri 2/16/18493 1.3.4.4.2.17.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 2/12/18 Fri 2/16/18494 1.3.4.4.2.17.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 2/12/18 Fri 2/16/18495 1.3.4.4.2.17.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 2/16/18 Fri 2/16/18496 1.3.4.4.2.18 Weekly Mobile Collection 18 88 hrs $7,040.00 5 days Mon 2/19/18 Fri 2/23/18497 1.3.4.4.2.18.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 2/19/18 Fri 2/23/18498 1.3.4.4.2.18.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 2/19/18 Fri 2/23/18499 1.3.4.4.2.18.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 2/23/18 Fri 2/23/18500 1.3.4.4.2.19 Weekly Mobile Collection 19 88 hrs $7,040.00 5 days Mon 2/26/18 Fri 3/2/18501 1.3.4.4.2.19.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 2/26/18 Fri 3/2/18502 1.3.4.4.2.19.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 2/26/18 Fri 3/2/18503 1.3.4.4.2.19.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 3/2/18 Fri 3/2/18504 1.3.4.4.2.20 Weekly Mobile Collection 20 88 hrs $7,040.00 5 days Mon 3/5/18 Fri 3/9/18505 1.3.4.4.2.20.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 3/5/18 Fri 3/9/18506 1.3.4.4.2.20.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 3/5/18 Fri 3/9/18507 1.3.4.4.2.20.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 3/9/18 Fri 3/9/18508 1.3.4.4.2.21 Weekly Mobile Collection 21 88 hrs $7,040.00 5 days Mon 3/12/18 Fri 3/16/18509 1.3.4.4.2.21.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 3/12/18 Fri 3/16/18510 1.3.4.4.2.21.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 3/12/18 Fri 3/16/18511 1.3.4.4.2.21.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 3/16/18 Fri 3/16/18512 1.3.4.4.2.22 Weekly Mobile Collection 22 88 hrs $7,040.00 5 days Mon 3/19/18 Fri 3/23/18513 1.3.4.4.2.22.1 Collect/ Refurbish electronics Mobile Technician 40 hrs $3,200.00 5 days Mon 3/19/18 Fri 3/23/18514 1.3.4.4.2.22.2 Administer survey Mobile Technician 40 hrs $3,200.00 5 days? Mon 3/19/18 Fri 3/23/18515 1.3.4.4.2.22.3 Transport electronics to collection center Mobile Technician 8 hrs $640.00 1 day? Fri 3/23/18 Fri 3/23/18516 1.3.5 Collection centers close and refurbishment/collection of electronics end (milestone) 0 hrs $0.00 0 days Sat 3/31/18 Sat 3/31/18

FinalProject

Page 13

Page 14: FinalProject · Title: FinalProject Author: David Miranda Created Date: 10/9/2017 6:57:49 AM

ID Task Name Resource Names Work Cost Duration Start Finish

517 1.4 Breakdown project 168 hrs $15,030.00 21 days Mon 4/2/18 Mon 4/30/18518 1.4.1 Conduct cleanup/ shut down of areas within the project footprint Collection Center 1 Support - Non

Certified,Collection Center 1 Support - Certified,Collection

40 hrs $3,450.00 5 days Mon 4/2/18 Fri 4/6/18

519 1.4.2 Conduct hotwash Project Manager,Project Support 72 hrs $7,020.00 5 days Mon 4/9/18 Fri 4/13/18520 1.4.3 Post project assessment/review (milestone) 0 hrs $0.00 0 days Mon 4/16/18 Mon 4/16/18521 1.4.4 Closeout contracts Contract Specialist 40 hrs $2,400.00 5 days Mon 4/23/18 Fri 4/27/18522 1.4.5 Assess post project survey results Project Manager 16 hrs $2,160.00 2 days Mon 4/23/18 Tue 4/24/18523 1.4.6 Compile and publish survey results (milestone) 0 hrs $0.00 0 days Mon 4/30/18 Mon 4/30/18

FinalProject