Final Report -...

54
Final Report Team 2: Dwell Senior Design Project 5/10/18 Kyra Black Cameron Carley Kyle Sutton Nathaniel Veldboom

Transcript of Final Report -...

Final Report

Team 2: Dwell

Senior Design Project

5/10/18

Kyra Black

Cameron Carley

Kyle Sutton

Nathaniel Veldboom

Copyright © 2018, Calvin College, Kyra Black, Cameron Carley, Kyle Sutton, Nathaniel Veldboom

EXECUTIVE SUMMARY

This project will satisfy the capstone requirements of Calvin College's engineering program. The name of

the group is Team 2: Dwell. It is comprised of four Civil & Environmental engineering students: Kyra

Black, Cameron Carley, Kyle Sutton, and Nate Veldboom. This project report further outlines the project

goals, research conducted, design decisions, and final design choices to be used in the shelter prototype

and the base camp layout.

The Shelter Design Competition, hosted by John Brown University and sponsored by Samaritan's Purse,

established the set of guidelines and criteria for which the disaster shelter is designed. The competition's

scenario is in response to the 2015 earthquake in Nepal, which measured a 7.8 magnitude on the Moment

Magnitude Scale. The shelter is designed to be a transitional shelter (lasting 1 to 3 years) for victims of

natural disasters and is not intended to provide permanent residence.

The team's design decisions are based on the requirements set forth by the competition and the

environmental conditions of Nepal. The frame is largely made of 1" Schedule 80 and Schedule 40 PVC.

The shelter cover is constructed using a series of heavy-duty tarps and insulated with double bubble foil

insulation. The shelter has a footprint of 16x10ft (5x3meters) and is roughly 8 feet (2.4 meters) in height.

The shelter accommodates a family of four and is designed to withstand wind speeds of 50 mph (75

km/hour) and earthquake tremors/aftershocks. The shelter kit is required to be easily transported and

constructed with basic tools.

The camp layout is based on requirements set forth by the competition and follows the basic humanitarian

standards established by The Sphere Handbook. The camp layout accommodates 5000 people in 1250

shelters and is designed with an egalitarian view, that everyone should have equal access to resources.

The camp layout is set up in triangular and hexagonal units, each with access to facilities such as water

tanks, showers, toilets, refuse bins, and medical centers.

The disaster relief shelter is efficient. The total cost of the shelter is approximately $1275. Broken down

into components: the material cost is $1135.32, the manufacturing cost is $97.43, and the transportation

cost is approximately $42 per shelter kit. Per a standard 40x8x8.5 ft shipping container, approximately 60

shelters can be shipped at once.

1

TABLE OF CONTENTS EXECUTIVE SUMMARY ........................................................................................................................... i

Table of Figures and Tables .......................................................................................................................... 3

1. Project Management ............................................................................................................................. 4

1.1 Introduction ......................................................................................................................................... 4

1.2 Team Members ................................................................................................................................... 4

Kyra Black ............................................................................................................................................ 4

Cameron Carley .................................................................................................................................... 4

Kyle Sutton ........................................................................................................................................... 4

Nathaniel Veldboom ............................................................................................................................. 4

1.3 Team Organization .............................................................................................................................. 4

1.4 Schedule .............................................................................................................................................. 5

1.5 Budget ................................................................................................................................................. 5

2. Project Overview .................................................................................................................................. 6

2.1 Background ......................................................................................................................................... 6

2.2 Existing Shelters ................................................................................................................................. 7

2.3 Project Requirements .......................................................................................................................... 9

Emergency Design Shelter Prototype Requirements ............................................................................ 9

Base Camp Layout Requirements ....................................................................................................... 10

3. Design Decisions .................................................................................................................................... 11

3.1 Framing ............................................................................................................................................. 11

3.2 Cover ................................................................................................................................................. 12

3.3 Insulation........................................................................................................................................... 13

3.4 Structural Anchor .............................................................................................................................. 14

3.5 Bolt Design ....................................................................................................................................... 15

3.6 Floor Tiles ......................................................................................................................................... 16

3.7 Cross Bracing .................................................................................................................................... 17

4. Prototype Criteria .................................................................................................................................... 18

4.1 Physical Requirements ...................................................................................................................... 18

4.2 Strength requirements and Weather Resistance ................................................................................ 19

4.3 Heat Loss and Ventilation Requirements .......................................................................................... 20

4.4 Life Span Requirements .................................................................................................................... 20

4.5 Assembly Requirements ................................................................................................................... 20

4.6 Packability Requirements ................................................................................................................. 20

4.7 Reusability and Expandability .......................................................................................................... 20

4.8 Cost ................................................................................................................................................... 21

2

4.9 Cultural Appropriateness .................................................................................................................. 22

5. Camp Plan ............................................................................................................................................... 23

5.1 Description ........................................................................................................................................ 23

5.2 Cost Estimate .................................................................................................................................... 28

6. Modifications/ Improvements ................................................................................................................. 28

6.1 Bolted Connections ..................................................................................................................... 28

6.2 Insulation..................................................................................................................................... 29

6.3 Ventilation ................................................................................................................................... 29

6.4 Lighting ....................................................................................................................................... 30

6.5 Durability .................................................................................................................................... 30

7. Christian Perspective .............................................................................................................................. 31

8. Competition Results ................................................................................................................................ 32

9. Conclusion .............................................................................................................................................. 32

Acknowledgements: .................................................................................................................................... 33

References: .................................................................................................................................................. 34

Table of Appendices: .................................................................................................................................. 35

A. Calculations ..................................................................................................................................... 35

B. Camp Plan ....................................................................................................................................... 35

C. Competition Scoring Matrix ........................................................................................................... 35

D. Construction Directions .................................................................................................................. 35

Appendix A1: Wind Calculations ............................................................................................................... 36

Code: ASCE 7-10: 27.3.2 Velocity Pressure: ......................................................................................... 36

Total Loads on Each Wall When Resisting Wind: ................................................................................. 36

Appendix A2: Anchoring Calculations ....................................................................................................... 37

Appendix A3: Bolt Design Calculations ..................................................................................................... 38

Appendix B1: Idealized & Site-Specific Camp Plans................................................................................. 39

Appendix B2: Large Scale B-Unit with Encampment and Storage Areas .................................................. 41

Appendix B3: Camp Plan Component Dimensions .................................................................................... 42

Appendix B4: Encampment & Storage Area Dimensions .......................................................................... 45

Appendix B5: Encampment & Storage Area Spatial Distribution .............................................................. 47

Appendix C: Competition Scoring Matrix .................................................................................................. 48

3

TABLE OF FIGURES AND TABLES

Figure 1: Nepal’s Geographic Location ….................................................................................................. 6

Figure 2: Disaster relief tents in Nepal 1 month after 2015 earthquake …................................................. 7

Figure 3: Bamboo and metal sheet shelter ….............................................................................................. 8

Figure 4: Samaritan’s Purse corrugated iron shelter …............................................................................. 9

Table 1: Decision matrix for frame material …......................................................................................... 11

Figure 5: Aerial view of assembled frame …............................................................................................ 12

Table 2: Decision matrix for insulation material ....................................................................................... 14

Figure 6: Diagram of weighted bags resisting overturning …....................................................................15

Figure 7: Visual representation of bolted 3-way joint ............................................................................... 16

Table 3: Results of Design Calculations for ¼ inch diameter grade 5 steel bolts ..................................... 16

Figure 8: Visual representation of interlocking foam tiles ........................................................................ 17

Figure 9: Visual representation of cross bracing …................................................................................... 18

Table 4: Physical Requirements Summary …........................................................................................... 18

Figure 10: StaadPro model of final design …............................................................................................. 19

Table 5: Breakdown of Material Cost ....................................................................................................... 21

Table 6: Time and cost to drill and cut parts …......................................................................................... 22

Figure 11: Augustus B. Woodward’s Plan of Detroit & Fernando Romero’s Border City …................... 23

Figure 12: Modular units of camp plan …................................................................................................. 24

Figure 13: Idealized Camp Plan ................................................................................................................ 25

Figure 14: SU-30 Design Vehicle ............................................................................................................. 26

Figure 15: Site-specific camp plan variant …............................................................................................ 27

Table 7: Cost Estimate for Camp Plan ….................................................................................................. 28

Figure 16: Metal collar used to guide drill press for drilling joint connections ........................................ 29

4

1. PROJECT MANAGEMENT

1.1 INTRODUCTION

Calvin College is a Christian, liberal arts college in Grand Rapids, Michigan. Calvin has a four-year

ABET-accredited engineering program. Within this program, Senior Design is required of all senior

engineering students to connect the concepts learned in class to a “real-world” problem. The intention of

the senior design project is to transition students into a career as a practicing engineer, but also to offer

support, by means of advisors, to aid in the transition. The project scope included competing in a disaster

relief shelter competition sponsored by John Brown University and Samaritan’s Purse. This competition

included designing and building a shelter prototype and designing a camp plan, to meet the competition

requirements. The team, project, and criteria are outlined in the following report.

1.2 TEAM MEMBERS

KYRA BLACK

Kyra is a Senior Civil/Environmental Engineering Major. She enjoys tutoring Calculus and giving tours

in the Calvin College Ecosystem Preserve. This past summer she interned with RWG Engineering LLC

doing site design. Upon graduation, she hopes to work in site design and land development.

CAMERON CARLEY

Cameron is a Civil/Environmental Engineering major with a Geography minor from Livonia, Michigan.

He enjoys travel, photography, and urbanism. Last summer, he worked as a business intern at Central

Detroit Christian Community Development Corporation in Detroit, Michigan, and has interned at civil

engineering firms in the private and public sectors in the past. After graduation, he plans to attend the

University of Michigan to pursue a Master of Urban and Regional Planning.

KYLE SUTTON

Kyle is a Civil/Environmental Engineering major with a business minor from Aurora, Ohio. This past

summer he interned with Spectrum Health in their Real Estate and Facility Development division as an

architectural planner. Kyle plans on working in engineering or business/finance upon graduating in May

of 2018.

NATHANIEL VELDBOOM

Originally from the small Northern MI town of East Jordan, Nate is on track to graduate from Calvin

College as a Civil/Environmental Engineering major and with a minor in Mathematics in 2018. Nate has

worked several internships ranging from serving as on-site inspector to testing storm outfalls. Nate plans

on pursuing work in some field of civil engineering following graduation.

1.3 TEAM ORGANIZATION

Each of the team members had a specific role to play during the design process. Kyle Sutton and Nate

Veldboom modeled the proposed shelter and performed calculations to select parts needed, helped with

the writing of the report, and built the shelter prototype. Cameron Carley took on the responsibility of

5

designing the camp layout for the competition. He researched all the requirements listed in the Sphere

Handbook and designed the camp plan in AutoCAD. Kyra Black kept the team organized through

overseeing the schedule, budget, parts order forms, and required reports and presentation. Design

decisions were made by the team or by the person who was most experienced in that area of the project. If

disagreement arose, everyone’s perspective was made clear, and each member was expected to decide

based on what was best for the project.

Though the immediate team consists of four students, there are many other supporting members including

the team faculty advisor, Professor De Rooy, and the other senior design professors.

1.4 SCHEDULE

This project was on a tight schedule due to the competition deadlines. A project report was required by

April 2nd, and the final design and shelter required by April 18th. Therefore, the team divided the project

into sections to be completed to meet these deadlines. The first section was research. The team collected

information about Nepalese culture, its weather and terrain, materials that could be used for the shelter,

and necessary camp plan elements. A greater understanding of these components aided the team in

making decisions about the design of the shelter. This phase was finished by the end of January.

The next steps were to design and build. Using the information collected during the research phase, the

team brainstormed design alternatives for the shelter itself. After designing two or three shelter

alternatives, the team chose the best option to build. After the basic design was chosen, the team began to

order parts and build the prototype. After refining the final design, a final prototype was built to bring to

the competition. The design and build phase began at the end of January and was finalized with the final

design that was taken to the competition.

The final stage was presentation. The team brought the shelter to John Brown University on April 18th

for testing and presentation. Presentations were also given for the Engineering Department’s Senior

Design Night, and the American Society of Civil Engineers (ASCE) May luncheon.

1.5 BUDGET

The team’s budget primarily revolved around the constraints placed on the competition by John Brown

University, which helped compensated the team for their final shelter through a stipend of $1000. This

stipend was not effective until after the completion of the competition in April. The competition entrance

fee was $250, and the final shelter was required to cost no more than $1500. The team received the Eric

DeGroot Memorial Fund monies ($1200) to cover the competition entrance fee and the shelter prototype

material cost. Therefore, the team’s goal was to remain within a budget of $1200, not including the

expected stipend.

6

2. PROJECT OVERVIEW

2.1 BACKGROUND

Figure 1. Nepal’s Geographic Location1

The country of Nepal is the target country for this disaster relief shelter. Nepal is landlocked

between China and India (Figure 1). It is a very mountainous country, with a portion of the Himalayan

mountain range enclosed within its borders. Consequently, the country goes from 0 to 9000 meters in

elevation, of which 5000 meters and below are habitable. Nepal also experiences 5 seasons – spring,

summer, monsoon, fall, and winter. Nepal did not become a democratic republic until 2008 after a century

of isolation and conflict. As a result, Nepal is one of the least developed countries in the world.2 In April

2015, a 7.8 magnitude earthquake hit Kathmandu, the capital of Nepal. Thousands of buildings were

reduced to rubble and thousands of people lost their lives. The United Nations estimated that 6.6 million

people were affected by the earthquake in some way3. Samaritan’s Purse, an international relief

organization, began distributing relief items soon after. They also began teaching the local people about

earthquake-resistant construction and how to build their own temporary structures using provided shelter

kits4. As Nepal continues to rebuild, Samaritan’s Purse has sponsored the competition hosted by John

1 “Map of Nepal”. WELNepal. 2011. WELNepal. Web 20 Nov. 2017. <http://www.welnepal.org/homeMap.html>.

2 Proud, Richard, Zuberi, Matinuzzaman. “Nepal”. Encyclopǽdia Britannica. 24 March 2017. Encyclopǽdia

Britannica, Inc. Web. 7 Dec. 2017. <https://www.britannica.com/place/Nepal/The-people>.

3 “Nepal Earthquakes: Devastation in Maps an Images.” BBC News World. 15 May 2015. BBC. Web. 13 Nov.

2017. <http://www.bbc.com/news/world-asia-32479909>.

4 “Sheltering Nepal”. Samaritan’s Purse. 26 Nov. 2015. Samaritan’s Purse. Web. 13 Nov. 2017.

<https://www.samaritanspurse.org/article/sheltering-nepal/>.

7

Brown University to bring awareness to the struggles that face the Nepalese people as well as bring new

solutions to the problems of temporary housing and disaster relief.

2.2 EXISTING SHELTERS

The team researched disaster relief shelters currently used in Nepal to aid in the decision-making process.

Three shelters currently used are a tent, a bamboo and metal sheet construction, and a corrugated iron

shelter kit distributed by Samaritan’s Purse.

First, a tent-like structure was easy to construct after the earthquake struck Nepal in April 2015. Shown

below in Figure 2, the Nepalese people built shelters quickly out of salvaged materials. Tents in general

are easy to construct and portable, making them easy to move in a disaster situation, and are durable and

waterproof. Tents are also affordable: the United Nations High Commissioner for Refugees (UNHCR)

canvas tent design costs approximately $200 to manufacture5. For Nepal specifically, the framing system

must be strong enough to withstand an earthquake. The tent must also retain heat well to keep its

inhabitants warm in higher elevations.

Figure 2. Disaster relief tents in Nepal 1 month after 2015 earthquake.6

Second, the bamboo and metal sheet structure, shown in Figure 3, is currently being used in Nepal. The

materials are affordable as bamboo is readily available in Nepal. The framing would be able to withstand

an earthquake as bamboo is very strong. There are also specific instructions for assembling the shelter,

5 Laylin, Tafline. “10 refugee shelters I love, for the good and the bad”. Green Prophet. 14 March 2014. Green

Prophet. Web. 6 Dec. 2017. <https://www.greenprophet.com/2014/03/pros-and-cons-10-refugee-shelters/>.

6 Sokol, Brian. “Struggling amid the ruins a month after Nepal quake”. Al Jazeera. 25 May 2015. Al Jazeera media

Network. Web 26 March 2018. <https://www.aljazeera.com/indepth/inpictures/2015/05/struggling-ruins-month-

nepal-quake-150525062223409.html>.

8

but it takes 1 to 3 days to construct, which would not be conducive to quick assembly in a disaster

situation7. The continued concern is heat retention and adequate insulation.

Figure 3. Bamboo and metal sheet shelter

Third, Samaritan’s Purse has implemented a shelter kit in Nepal, shown in Figure 4. The kit consists of

corrugated, galvanized iron sheeting, plastic tarpaulin, rope or cord, and other non-food items such as

basic tools, blankets, and cookware. It is easy to construct as well as cost-effective. Samaritan’s Purse,

along with distributing supplies, implemented a program to instruct those receiving the shelters on how to

build it themselves. The shelter is strong and durable8. However, it is unclear whether more insulation

would be needed for temperatures at higher elevations.

7 Frearson, Amy. “Prototype shelter for Nepal earthquake victims could be built by unskilled workers in three days”.

Dezeen. 11 July 2015. Dezeen. Web. 6 Dec. 2017. <https://www.dezeen.com/2015/07/11/prototype-bamboo-shelter-

nepal-earthquake-victims-built-by-unskilled-workers-three-days/>.

8 “Sheltering Nepal”. Samaritan’s Purse. 26 Nov. 2015. Samaritan’s Purse. Web. 6 Dec. 2017.

<https://www.samaritanspurse.org/article/sheltering-nepal/>.

9

Figure 4. Samaritan’s Purse corrugated iron shelter

2.3 PROJECT REQUIREMENTS

The design competition at John Brown University imposed numerous constraints and requirements

concerning the emergency shelter prototype and base camp layout. As the competition was in response to

the 7.8 magnitude (Richter scale) earthquake that struck Nepal in 2015, requirements surrounding the

prototype and base camp layout were tailored for that specific environment and culture.

EMERGENCY DESIGN SHELTER PROTOTYPE REQUIREMENTS

Regarding the emergency shelter, the prototype had to accommodate a family of four with a minimum

allocation of 37.7 ft2 (3.5 m2) of floor space per person. The height within the structure had to allow a

head clearance of 6.6 ft (2 m) for at least 70% of the floor space, and the maximum footprint of the

structure allowed was 16’ x 20’ (5m x 6m). Additionally, the prototype had to demonstrate cultural

appropriateness for use in Nepal, so as not to inhibit any social, cultural, or religious requirements.

The physical performance of the structure was expected to withstand wind loads of 50 mph (75 km/hour)

and seismic earthquake loads similar in magnitude to what struck Nepal (7.8 Moment Magnitude scale) in

2015. The shelter had to be versatile and responsive to the scenario environmental conditions that vary

seasonally, geographically, and diurnally. Furthermore, the structure had to shield occupants from

substantial rainfall (4 inches per hour), promote adequate airflow ventilation in various temperatures, and

retain heat in temperature fluctuations due to day/night and summer/winter variations. It was also

expected that assembly of the structure be straightforward with simple hand tools, be upgradeable to a

more permanent structure, preferably with readily available local materials, and be reusable.

The expected life-span of the structure had to be a minimum of one year, and cost less than $1500 in

materials to construct. The structure’s overall weight had to not exceed 440 lbs. (200 kg), and the design

of the structure had to maximize efficiency of space when shipping and storing numerous structures in 8’

x 40’ shipping containers.

10

BASE CAMP LAYOUT REQUIREMENTS

The base camp layout was mandated to accommodate 5000 people in 1250 shelters. The main

considerations regarding the camp layout were road/walk ways, water and waste requirements, and

arrangement of shelters and support facilities. An estimate for the cost of construction of the camp was

required, and it was assumed that no site preparation costs were necessary.

11

3. DESIGN DECISIONS

3.1 FRAMING

The framing of a structure served two purposes; shape and support. The frame supported the weight of the

building, the internal and external loads applied, and provided a structure to inhabit. The framing also

formed the overall shape of a building, which influenced the use of the space as well as the loads it can

endure. The competition, as previously elaborated, tested external loads such as wind/rain and seismic

loads. The shelter had to withstand an earthquake simulation with no failure and little to no deformation.

Framing materials of the shelter were considered with respect to characteristics such as strength, cost,

weight, and ease of access in the areas the shelter may be employed. Material strength was given the

highest priority, so the structure would not fail under loading. Next, priority was given to material weight

and cost because these characteristics were the most constrained within the competition as the structure

had to be below 440 pounds and cost less than $1,500. The final, least vital design consideration was

given to ease of access, so the shelter could be easily replicated or repaired if necessary. The frame was

expected to be the sturdiest of the shelter kit materials and last the lifetime of the shelter, thus ease of

access was given lowest priority.

Materials considered included wood, bamboo, steel, aluminum, fiberglass, and polyvinyl chloride (PVC).

Table 1 shows the decision matrix for materials considered and different categories on which the

materials were judged. Each material factor was evaluated on a scale from 1 (the worst grade) to 4 (the

best grade and the material with the highest score was chosen as our frame material.

Table 1. Decision matrix for frame material

Material Cost Weight Strength Durability Ease of

Use

Ease of

Access

Total

Importance 20 20 20 20 10 10 100

Wood 3 1 2 2 3 4 230

Bamboo 2 2 2 3 3 4 250

Steel 1 1 4 3 1 1 200

Aluminum 1 2 3 3 1 1 200

Fiberglass 1 4 1 2 1 1 180

PVC 4 3 2 3 3 1 280

Wood is the most common structural material. It is locally abundant in most parts of the world and is easy

to work with in construction and joining of members. It is also strong and durable enough to last through

the various weather conditions. However, wood is heavy and sometimes stronger than is required and thus

may contribute to over-designed structures.

Bamboo (technically a grass) was seriously considered as a framing material. Like wood, it is easy to

work with and also very strong and durable given treatment. If the bamboo is chemically treated, it can be

protected from several types of degradation and greatly increases the expected lifespan of the material.

The material is also locally grown but must be harvested at the right time and treated properly to serve as

structural members.

12

Metal is another common structural material, though not as common for single-family dwellings. It is the

strongest of materials considered and, depending on the type of connection, can be easy to construct. The

type of metals examined are steel and aluminum. However, it is (depending on the type of metal) heavy

and expensive compared to the other materials considered.

Fiberglass rods were considered for their flexibility and strength. This material is commonly used in tents

because it is lightweight, flexible, and resists the bending stress of the structure. The material would not

be a candidate for the body of the shelter but would be ideal for the roof. A uniform material for the entire

frame is desired and thus fiberglass was not used in the shelter prototype.

Polyvinyl chloride (PVC) was the material chosen to construct the frame for the shelter prototypes. It is

strong and flexible enough to resist loads and absorb shock and not break. It is also the lightest of the

materials considered and the most cost effective. On top of all these aspects, it comes in a variety of sizes

with pre-fabricated joints for easy construction. PVC is very durable and does not rot or rust when

exposed to the elements over time. Since it is flexible over long spans, it does require more bracing and

more structure to support it.

Of all the materials considered, PVC was the material chosen to construct the frame. The frame itself was

composed of 178 ft of 1” Schedule 80 PVC, 58 ft of 1” Schedule 40 PVC, and 52 PVC joints. The

Schedule 80 PVC made up the body of the frame because it was thicker, hence stronger and not as

flexible, than Schedule 40 PVC. The body of the shelter sustained many of the loads, such as wind, rain,

snow, earthquake tremors, and the self-weight. The Schedule 40 PVC was used for the roof members

because it was more flexible than the Schedule 80 PVC and could form the curve of the roof. And to keep

the frame together, many of the members and joints were bolted (elaborated in section 3.5 Bolt Design) to

prevent members from slipping out of joints. The PVC frame was expected to withstand the conditions

applied. Refer to Figure 5 for an aerial photo of the frame when constructed.

Figure 5. Aerial view of assembled frame

3.2 COVER

The cover of the shelter formed the walls, ceiling, and floor, ultimately separating the occupants from the

outside environment. The cover had to be able to resist wind loads or transfer the load to the frame,

waterproof the shelter, insulate from temperature changes, block light, and provide adequate ventilation

13

for its inhabitants. Ultimately, two types of the cover were considered; a series of tarps or canvas material

or solid panels.

The series of tarps were layered over the frame forming a skin. Tarpaulin, also referred to as a tarp, is

canvas or polyester coated in polyurethane so it is flexible, strong, and waterproof. Tarps also come in

various thicknesses and coatings depending on the intended uses. The perimeter is lined with grommets to

secure it or tie it down. These characteristics made tarps an ideal choice because they could be

manipulated to cover many different shapes and sizes. The limitation of tarps was that, if it is not a single

piece, the seams where the tarp is layered are not waterproof and could expose the inhabitants to the

elements.

Solid panels could be joined together to form a structure or form the walls of a structure. The types of

panels considered include plain plywood, corrugated metal, and structural insulation panels (SIP).

Plywood is cheap, strong, and easily accessible. It does however need to be treated to prevent rot or

waterproofed with another material. Corrugated metal is a viable option and is used in current shelter kits.

It is strong and flexible, but it does not provide good insulation and is expensive and heavy, especially

considering the required size of the shelter. SIPs are an ideal form of panels because it is a sandwich of a

rigid insulation core between a layer of structural board. This board can be plywood, metal, or cement and

the core could be some sort of foam or honeycomb structure. All types of panels considered were not

chosen due to factors such as weight, cost, and packability (the panels are not compact and are large).

Tarpaulin was chosen to cover the shelter. The cover was composed of various sized tarps, each covering

a portion of the shelter prototype including the floor. The tarps ranged in size and were attached to the

shelter with the use of PVC clips that lock onto the frame. Heavy-duty tarps were chosen because the

shelter was expected to last 1-3 years and the diverse conditions observed in Nepal warranted the tougher,

albeit more expensive, version.

3.3 INSULATION

An integral portion of any habitable structure is insulation, particularly in areas plagued by extreme

temperatures. As Nepal can range in temperature from 36° to 100° Fahrenheit, proper insulation was a

crucial part of a successful and hospitable disaster shelter. Without proper insulation, the structure would

struggle to maintain comfortable temperatures during instances of extreme temperature differences

between the interior and exterior of the shelter. Choosing an insulation was essential to creating a shelter

prototype with little to no heat loss. The different types of insulation considered included Foamular, a

rigid foam insulation, mylar blankets, and double bubble insulation. Table 2 shows the decision matrix

for the three insulation options, including the categories in which they were judged. Each material factor

was evaluated on a scale from 1 (the worst grade) to 4 (the best grade) and the material with the highest

score was chosen as our insulation material.

14

Table 2. Decision matrix for insulation material

Material Cost Weight Packability Durability Effectiveness Ease of

Assembly

Total

Importance 20 20 10 20 20 10 100

Foamular 1 2 2 2 4 2 220

Mylar

blanket

4 4 4 2 1 3 290

Double

bubble

Insulation

3 3 3 4 3 3 320

Foamular is a commonly used rigid foam insulation. Because of its rigidity, Foamular would not be very

squishable and may be more likely to dent or break, hence lowering its rating in the packability and

durability categories. Its lack of flexibility would also make it hard to assemble or attach to the structure.

At 135 lb. and $468 for the necessary quantity, Foamular is the heaviest and most expensive option.

However, it is the most effective option with an R-value of 5.

Mylar blankets are commonly used by runners recovering after a marathon or by patients in shock. It

captures body heat by reflecting heat back to the user instead of releasing it. The blankets are very light,

packable, and affordable. The quantity needed would weigh approximately 4 lb. and cost $16. Its

flexibility would allow for easy assembly with the structure. However, because they are so thin, the

blankets would not be very durable or effective (with an R-value less than 1).

Double Bubble insulation is a step up from a mylar blanket. It is thicker with a bubble wrap-like layer

sandwiched between two layers of mylar or foil, giving it reflective, heat-capturing ability similar to a

mylar blanket. It would be more effective than a mylar blanket with an approximate R-value of 1.

Additionally, it reflects 96% of heat instead of letting it pass through. Its flexibility and thickness make

Double Bubble durable, packable, and easy to assemble with the structure. For the quantity needed,

Double Bubble reaches a median 30 lb. and $177. Hence the team decided that Double Bubble was the

best insulation option for the shelter prototype.

3.4 STRUCTURAL ANCHOR

The structural anchoring prevented the shelter from moving or tipping, especially during monsoon season

when there are high winds. The design wind velocity the structure was tested on is 75 km/hour. To anchor

the structure, three methods were considered; tie-down with a stake, stake as part of the frame, and

weighted bags.

Tie-down stakes are common in smaller structures like tents. This method relies on the tension of a cable

between two stakes placed on either side of the tent, effectively holding it in place. This method was not

chosen for a multitude of reasons; it increased the footprint of the shelter, it requires constantly tense

cords, and based on the size of the shelter, many tie-downs would be required. Additionally, the soil

conditions in Nepal vary greatly and due to changing conditions, such as saturated soils, the stakes would

not provide enough resisting force to keep the cord in tension.

Stakes that are part of the frame protrude down into the ground and hold the shelter in place. The stakes

are effective in preventing the shelter from sliding along the ground as well as from overturning caused

by high winds. This method can be limited depending on the ground/soil conditions. The stakes would not

be utilized if the ground surface is too solid to be penetrated such as rock or hard clay.

15

Weighted bags placed along the frame of the shelter is the simplest method of anchoring the structure.

The bags are sand bags, but the material filling the bags, providing the weight, could be anything locally

available such as soil, sand, or aggregate. These could be placed around the perimeter of the shelter on the

frame and/or the tarps to form a waterproof barrier. Since it could not always be assumed that stakes

could be implemented due to unpredictable soils, the design scenario for the weighted bags was to be

resisting to a wind into a 16-foot side. The loading due to wind calculations are outlined in Appendix A1.

Refer to Figure 6 for a diagram of this design situation.

Figure 6. Diagram of weighted bags resisting overturning

Assuming the weighted bags to be a uniform weight along the perimeter of the structure, the bags needed

to be approximately 9 lb/ft, including a factor of safety of 2. Refer to Appendix A2 for the development

of the associated calculations.

The preferred method to anchor the system was a combination of weighted bags and stakes attached to the

frame. The stakes were placed at the four corners and at the centers of the two long edges. The weighted

sand bags were placed around the perimeter of the shelter, laying both on the frame and tarp walls. The

combination of the two anchoring methods was expected to withstand the wind loads as well as the

earthquake simulations.

3.5 BOLT DESIGN

After initial testing and assembly of the PVC frame, the team quickly ascertained that a system fastening

all joints in place would need to be employed to prevent members from disconnecting from joints when

placed under stress. Candidates for this task included deliberations between manually gluing each joint or

using hex bolts as pins, which would be slipped through predrilled holes of the PVC members and their

corresponding joints. A system employing glue was quickly ruled out due to the irreversibility of

permanently attaching members to joints. Therefore, the team decided to employ a fastening system by

use of hex bolts. Refer to Figure 7 below for a visual representation of a bolted joint and member.

16

Figure 7. Visual representation of bolted 3-way joint

The design criteria for the hex bolts hinged mostly on the ability for the bolts to resist failure while in

double shear. Using data from the StaadPro model to find the maximum axial force for any member, the

team found the required bolt size and grade to avoid failure. Refer to Appendix A3 for a development of

those associated calculations. After completing the accompanying calculations, the team decided to use ¼

inch diameter, 2-inch-long hex bolts composed of Grade 5 steel plated with zinc. The bolts were found to

be more than sufficient to resist the require shear, and the zinc plating allowed the bolts to be resistant to

rust and corrosion. Nearly all members were bolted in their joints, with the exception of the arched

schedule 40 PVC members in their connections to the top of the walls on the longest sides of the shelter.

Table 3 shows the results of the calculations associated with the bolt design. As Table 3 shows, the

selected bolts were more than capable of resisting the forces they will be subjected to during maximum

loading. The team was comfortable with this overdesign of bolt strength, as the ¼ inch diameter bolts

were a standard size for use, and there was not a significant price difference for lessening diameter bolts.

Table 3. Results of Design Calculations for ¼ inch Diameter Grade 5 Steel Bolts

Area of Bolt

(in2)

Max Axial

Force (lbs)

Factor of

Safety

Max Shear

Stress

Calculated

(psi)

Ultimate

Tensile

Strength

Required (psi)

Actual Tensile

Strength of ¼

inch diameter

Grade 5 steel

bolts (psi)

.04909 32 3 977.8 1629.7 120,000

3.6 FLOOR TILES

A critical component of any living space is an effective and comfortable floor. Quality flooring is

especially significant regarding heat retention, as conductive heat loss can be problematic through the

17

contact of the living space and the ground. It is also important in stopping the spread of disease by

keeping things dry. When evaluating alternatives for flooring, the team came up with three main options.

The options consisted of simply a heavy-duty tarp, rubber floor tiling, or foam tiling. Heavy-duty tarp

alone was quickly ruled out due to the lack of comfort and thermal retention such a flooring system would

offer. While rubber tiles would provide considerable comfort, stability, and longevity, it too was decided

against due to its higher price and weight. Consequently, the team decided to select foam tiling as the

preferred flooring. Foam tiling would allow the occupants of the shelter to have a comfortable and

insulating floor without compromising the financial costs and weight of the flooring. The selected foam

flooring was an interlocking system of 2’ x 2’ and ½ inch thick mats. Refer to Figure 8 for a visual

representation of the foam tile mats while set-up.

Figure 8. Visual representation of interlocking foam tiles

3.7 CROSS BRACING

A key component of any structure, is providing efficient and effective cross bracing. Cross bracing gives

structural members much needed support, and provides more pathways for loads to reach the ground. To

find the best cross members, the team decided primarily between using steel rods, nylon string, and

ratchet straps. Steel rods were ruled out due to their excessive weight, cost, and difficulty to connect.

Nylon string also proved difficult to connect to the frame, and did not provide as much structural support

as the other options. Consequentially, the team decided on ratchet straps for use in cross bracing, as they

were reasonably priced, were relatively easy to use and connect, and provided an adequate amount of

support to the structure. The ratchet straps had a metal S-hook on both ends, and could be fastened to

various members along the frame. The proposed method is the attachment in an “X” like pattern on the

center two panels along the 16 ft long sides, and on the corner panels for both the front and back of the

frame. This arrangement provided great structural reinforcement to the framing. Refer to Figure 9 for a

visual representation of the cross bracing connecting to the proposed locations.

18

Figure 9. Visual representation of cross bracing

4. PROTOTYPE CRITERIA

The completed shelter met all criteria outlined in the Project Requirements. The following sections

outline that the criteria have been met in all areas.

4.1 PHYSICAL REQUIREMENTS

The shelter had to meet certain physical requirements. Below, Table 4 summarizes the met requirements.

First, the shelter had to fit on the 16 ft x 20 ft (5 m x 6 m) shake table and in the heat retention testing area

with a height of no more than 10 ft (3 m). The designed prototype was 16x10x8 ft (5 m x 3 m x 2.4 m).

Second, the shelter had to house 4 people comfortably, meaning that each person needed 37.7 ft2, totaling

approximately 151 ft2. The prototype was 161 ft2 total, giving each person 40.4 ft2. It also had to have 6.6

ft of head space for 70% of floor space. The designed prototype had 6.6 ft or more for 96.9 percent of the

floor space. Lastly, the full package housing the shelter had to not exceed 440 lb. (200 kg) in total. The

designed shelter weighed about 385 lb. (174.6 kg).

Table 4. Physical requirements summary

Item: Requirements: Actual:

Dimensions Less than 16ft x 20ft 16ft x 10ft

Space/person 37.7 ft2 40.4 ft2

Total Area 151 ft2 161.5 ft2

Head Space 6.6ft for 70% 6.6ft for 96.9%

Weight 440 lb. 384.7 lb.

19

4.2 STRENGTH REQUIREMENTS AND WEATHER RESISTANCE

To model the various components of this project, the team used two main programs to model the shelter

portion, and base camp layout portion. Regarding the modeling of the shelter, the program StaadPro was

employed as the program of choice. This program was chosen as all members of the team were familiar

with the program from class curriculum at Calvin and knew that it would suit the purposes of our design

well. Through the model, the team could test varied sizes of PVC piping in addition to the effects of

changing the wall thickness under design loads. The design loads for the shelter were based primarily off

the wind loads the shelter would be subjected to at the competition. According to the competition design

criteria, the shelter was expected to withstand a 50 mph (75 km/hour) wind. With that load as a baseline,

the structure was tested under that design criteria with varying members. Refer to Figure 10 below, for a

snapshot of the model showing performance against the simulated wind load. This model shows the

decided final members, which were 1” PVC schedule 80 piping. The cross-webbing portions modeled of

the structure were nylon ratchet straps which acted as cross bracing for the structure. These ratchet straps

functioned as valuable components of the structure, increasing resistance to wind loads. The wind load

was modeled as 7.5 lb/ft (10.2 N/m) load on the windward side for every member off the ground. This

instance rendered a maximum deflection of 5.2 inches (13.2 cm) which the team deemed acceptable for

use. Therefore, according to modeling and extra measures built into the structure, the shelter prototype

met the strength requirements and would remain upright and usable in high winds. In addition to high

winds, the shelter was designed with large quantities of rainfall in mind. The shelter was covered with

waterproof, heavy duty tarps. The floor also had a layer of tarp that created a lip on all sides to protect

from rain seeping into the structure. Therefore, the shelter was completely rain proof against possible 4

in/hr rainfall.

Figure 10. StaadPro model of final design

20

4.3 HEAT LOSS AND VENTILATION REQUIREMENTS

It was required that the shelter be capable not only of ventilation but also retaining heat. The zipper door

was designed to be folded up for added ventilation. The shelter was designed so that the tarps would be

customizable as well. They could be folded up to create a gap for air movement and folded back down to

retain heat. The insulation added was also detachable, but when attached, it prevented most heat loss by

reflecting heat back into the shelter. The foam floor tiles were also chosen to retain as much heat as

possible.

4.4 LIFE SPAN REQUIREMENTS

The shelter was required to last one to three years. The materials used to construct the shelter were

specifically chosen with longevity in mind. For example, bamboo was not chosen, in part, because it must

be treated properly to last a few years. However, all the materials chosen for the shelter prototype were

made of plastics and metal both of which were long lasting and durable. For example, the tarping used

was expected to last between 1 to 3 years. If for any reason the shelter is no longer needed or usable, most

of the materials used are also recyclable (if done properly). This prototype should easily last one to three

years, if not more, provided that it is able to withstand the weather and any other unforeseen

circumstances.

4.5 ASSEMBLY REQUIREMENTS

The designed shelter had to be easy and rapid to assemble without technical knowledge. The team’s

prototype took approximately 1 hour to construct with 4 people. It required no more than a hammer and

comes with a set of simple directions for assembly (see Appendix D).

4.6 PACKABILITY REQUIREMENTS

The shelter had to be easily stored, transported, and flat packed into a, 8x40-ft shipping container. The

designed shelter was easily packed into an 8x2.5x2-ft plywood box. The box was fitted with handles for

easy transportation to the disaster location. It also could be packed efficiently into a shipping container,

leaving limited space for shifting. Sixty kits would fit into one shipping container. There could be 3 boxes

wide, 5 boxes long, and 4 boxes high.

4.7 REUSABILITY AND EXPANDABILITY

The team had to design the shelter so that it was reusable in the event of another disaster and so that it

could be added upon using local materials and methods. The designed shelter was easily reusable because

of its durability and packability. There were also many ways for it to be expanded upon. The tarp used for

cover was specifically designed so that it could be attached and reattached in a different configuration. If

a larger structure is needed, two frames could be built side by side and tarps added as needed. Insulation

could also be attached and reattached if it is not needed in the summer time. If more insulation is needed,

local straw could be used as a supplement. The anchoring system could also be supplemented using the

extra sand bags included in the kit. If a more permanent structure is needed, corrugated sheet metal could

be added to the roof. The designed shelter could be modified and expanded in many ways.

21

4.8 COST

The shelter had to cost $1500 or less to fabricate including labor and material costs. Table 5 includes a

breakdown of material costs.

Table 5. Breakdown of material cost

Shelter Materials Cost

sch. 40 pvc connections $ 129.87

pvc sch. 40 $ 26.30

pvc sch. 80 $ 185.69

floor tiles $ 159.70

tarping $ 167.94

bolts $ 33.61

sandbags $ 15.35

zipper kit $ 19.97

zip ties $ 3.98

duct tape $ 7.98

aluminum tape $ 7.49

bungee cords $ 32.45

ball cords $ 19.90

ratchet straps $ 39.96

insulation $ 177.00

box $ 100.71

shower curtains $ 7.42

Total: $ 1,135.32

Therefore, total material cost was approximately $1135.32. In addition to buying material, supplementary

manufacturing was required. All connections and pipes were cut and/or drilled, and insulation was cut to

size. The team recommended inserting grommets for the insulation connections as well, adding time to

possible manufacturing costs. The box in which all the parts were packed was also built. Table 6 shows

the estimated time to cut and drill parts and the resulting approximate cost based on an average factory

worker’s wage of $12.16.

22

Table 6. Time and cost to manufacture

Time/action (s) Quantity Total time (hr) Total Cost

Drilling PVC

connectors and pipe 30 322 2.6833 $33.84

Cutting PVC pipe 36 166 1.6600 $20.93

Cutting Insulation 15 21 0.0875 $1.10

Insert grommets 30 100 0.833 $10.51

insert zippers 300 2 0.167 $2.10

box assembly

0.5 $6.31

packing

0.250 $3.15

25% overhead $19.49 Total: $97.43

In addition, using an average build time of 30 minutes for the box in which the parts would be

transported, manufacture costs are an additional $6.31. An additional 25% contingency for overhead costs

would bring the manufacture costs to $97.43.

Once the boxes would be packed, Samaritan’s purse would need them shipped to Nepal via a 8 ft x 40 ft

shipping container. This shipping cost would be between $2000 and $25009. If 72 kits fit into one

shipping container, the shipping cost for each box would be $42 at most.

Therefore, the total cost of one shelter, including shipping costs was approximately $1275, which met the

cost criteria.

4.9 CULTURAL APPROPRIATENESS

The designed shelter should accommodate the culture in which it is being used. To design for the culture

in Nepal, the prototype was designed to have three rooms. As per Nepalese custom, there was a common

room at the front and two small bedrooms – one for women and the other for men. These rooms were

separated using shower curtains or hanging tarps to provide privacy. The overall structure of the shelter, a

rectangular building with a peak, also followed standard residential architecture in Nepal.

9 “2018 International Container Shipping Rates and Costs.” MoverDB.com, MoverDB.com, 8 Jan 2018,

moverdb.com/container-shipping/.

23

5. CAMP PLAN

5.1 DESCRIPTION Architecture and urban planning go hand in hand. The design of a structure and the relationships between

structures and the rest of the built environment can have an impressive influence on the lives of those

within them. Therefore, the team took seriously its charge to design the shelter and the camp plan to

provide as dignified and pleasant an experience as possible in the disaster situation.

The inspiration behind this design was found partly in the street design of Downtown Detroit by Augustus

B. Woodward, and partly in Mexican architect Fernando Romero’s conceptual design of a binational

border city between the United States and Mexico:

Figure 11. Augustus B. Woodward’s Plan of Detroit10 & Fernando Romero’s Border City11

The guiding principles for the design came from the team’s deeply held beliefs in egalitarianism,

accessibility, and dignity for all, as well as adherence to the guidelines presented in the Sphere Handbook.

The belief that all ought to have equal access to goods and services was manifest in the plan’s triangle-

hexagon modular layout. The plan made use of the proportionality of triangles and spatial efficiency of

hexagonal packing to allow for relatively easy and direct access to resources in the camp.

The team designed two camp plans: one idealized, and one specialized for Nepalese geography. The

former assumed a relatively large swath of flat (slopes between 1-6%) land, which was only likely to exist

in the lowland portion of Nepal, near the border with India. The latter displayed perhaps the most superior

aspect of the team’s design: versatility. With the team’s modular approach, this camp plan could be

adjusted to almost any topography. The plan was built out of modular units, differing in size, which could

be arranged to twist around intrusive geographical features, such as mountains or valleys.

10 Unknown – Dickens, Asbury & Forney, John W., eds. (1832) “Plan of Detroit (Map). American State Papers.

Vol. 6: Public Lands. 1:6,000. Washington, DC: Gales &Seaton. P. 299. OCLC 2053058. OL7014594M. LCCN

</noinclude> 09033892 – via Archive.org.

11 Fernando Romero et al. Border City, www.fr-ee.org/project/73/Border+City. Accessed 1 Apr. 2018.

24

The main modular units are shown below, and are, left to right, the A-Unit, B-Unit, and C-Unit:

Figure 12. Modular units of camp plan

An A-Unit is roughly triangular and the most basic of the units, containing fifteen 10’ x 16’ (5 m x 3 m)

shelters along the periphery of the triangle, along with three outhouses and two 25-gal (100-L) trash cans

in the center. The shelters were spaced 9 ft (3 m) apart from each other, meeting the minimum separation

of 6 ft (2 m) specified by the Sphere Handbook. The three outhouses met the requirement of a maximum

of 20 people per toilet and were very close to living quarters (far less than 160 ft (50 m) from dwellings).

To accommodate human waste, pits would be dug in the initial stages of construction. The two 25-gal

(100-L) trash cans met the minimum of one per 10 households and would be emptied into nearby

communal dumpsters.

In additional storage areas (see Appendix B3), communal dumpsters, wash basins, and water tanks could

be located. The wash basins met the minimum of one wash basin per 100 people. For potable water,

inhabitants of the camp would get water from water tanks located near the shelters. All of these were

located well beneath the maximum distance to water of 1650 ft (500 m). The sizes of the water tanks were

1200-gal (4500-L) and 5000-gal (19000-L), which accommodated all inhabitants and would require

refilling weekly to give the minimum 4 gallons (15 liters) of water per person per day, according to

Sphere Handbook guidelines.

A B-Unit is simply three A-Units arranged in a semicircular fashion, with 12 ft (4 m) wide walking paths

separating the A-Units. Towards the top of the B-Unit in Figure 12 is a half-hexagon shaped area that

could be used for locating wash basins, potable water tanks, and communal dumpsters. The communal

dumpsters were sized to hold all the refuse accumulated in a week from 25-gal (100-L) trash cans in the

adjacent A-Units.

Finally, a C-Unit is simply two B-Units arranged opposite of each other. The spacing between them was a

minimum of 100 ft (30 m), easily meeting the Sphere requirement of 100 ft (30 m) of firebreak between

every 1000 ft (300) m of built-up area.

Arranging these modules into a whole, the team arrived at this triangular-hexagonal idealized camp plan,

sized approximately 2300 ft (700 m) across:

25

Figure 13. Idealized camp plan

At its essence, the idealized camp plan was 12 C-Units arranged in a fashion resembling a honeycomb or

snowflake. Between C-Units were 24 ft (7 m) wide roadways intended for an SU-30 design vehicle,

which are roughly the size of delivery trucks (Figure 14). With this design vehicle in mind, the curb

radius for 60° turns was 60 ft (20 m), for 90° turns was 50 ft (15 m), and for 120° or greater turns was 30

ft (9 m)12. This would allow delivery trucks to turn right without swerving into the opposing lane.

However, cars were not expected to constantly use these roads, and, in their presence and absence, were

intended for pedestrian traffic and right-of-way.

A larger version of the idealized camp plan, along with the site-specific camp plan, can be found in

Appendix B1. For a larger version of a B-Unit in the camp plan, with all components visible, see

Appendix B2. For dimensions of all the components listed in the legend, see Appendix B3. For the

dimensions of the encampment and storage areas in the idealized camp plan, see Appendix B4. Finally,

for the spatial arrangement of the encampment and storage areas in the idealized camp plan, see

Appendix B5.

12 Garber, Nicholas J. Traffic and Highway Engineering, 5th Edition. Cengage Learning, 2015. [Bookshelf Online]

F

FF

F

F F

MM M

MM M

U

+

SHELTER

OUTHOUSE

REFUSE CONTAINER (100 L)

WATER TANK (4,500 L)

WATER TANK (5,000 gal)

WASH BASIN (5 ct.)

COMMUNAL REFUSE CONTAINER

SHELTER AREA BOUNDARY

ROAD AREA BOUNDARY

MEDICAL FACILITY

BATHING/LAUNDRY FACILITY

+F/M/U

26

Figure 14. SU-30 Design Vehicle13

Also included in the roadway design were roundabouts at the confluence of six roadways. Multiple

options existed for filling these circular areas. Included in the team’s design were shower/laundry

facilities, segregated by gender: male, female, and unisex. The female facilities were located in

conspicuous locations to prevent the women from feeling isolated and endangered, and to deter potential

attackers from intruding into those facilities. The unisex facilities were intended for families and mita.

Mita are transgender individuals with legal “third-gender” status in Nepalese society, and out of the

team’s commitment to dignity for all people, designed a safe shower/laundry facility for their use. In the

center of the camp, a medical center was located to provide for immediate and preventative care for all

people in the camp, along with distributing necessary goods to occupants.

Finally, understanding the need to adapt to Nepal’s very site-specific topography, an example of one

modified site plan is shown below:

13 Urban Street Design Guide, National Association of City Transportation Officials,

https://nacto.org/publication/urban-street-design-guide/design-controls/design-vehicle/. Accessed 1 Apr. 2018.

27

Figure 15. Site-specific camp plan variant

This variant used a minimum modular size of B-Units, given the spaciousness between mountains.

However, if the terrain is even steeper, a minimum of an A-Unit could be used as well. This site-specific

variant was spacious enough to include all relevant features with adequate spacing, just like the idealized

camp plan, though was not as accessible for all by geography.

28

5.2 COST ESTIMATE

The cost estimate for the idealized camp plan is found below. Including all the shelters, the camp plan

would cost approximately $2.2 million dollars. In estimating the medical facilities and shower facilities,

the cost per square foot of a shelter was scaled to the area of each facility, since they would likely be

constructed from similar materials and in a similar style. The prices for other materials given were

determined through research online and used prices shown.

Table 7. Cost Estimate for Camp Plan

Item Qty. Cost/Unit Cost

Water tank, 5000 gal 24 $1,999.99 $48,000

Water tank, 4500 L 18 $990 $17,820

Refuse container, 100L 178 $24.60 $4,379

Dumpster, 20 cyd 12 $4,000 $48,000

Outhouse 250 $700 $175,000

Wash basin 12 $372.50 $4,470

Medical facility 1 $101,200 $101,200

Shower facility 13 $14,231.25 $185,006

Shelter 1250 $1,265 $1,581,250

Total: $2,165,125

6. MODIFICATIONS/ IMPROVEMENTS

To improve aspects of the shelter design, the team has outlined several components of the shelter that can

be enhanced for a better overall shelter.

6.1 BOLTED CONNECTIONS

One of the biggest challenges facing the team for this project was implementing a consistent and reliable

method for drilling holes through members and connections. As none of the members of the team had a

background in using drill presses or drill mills, this provided a steep learning curve. In an effort to achieve

consistency in drilling joints, the team machined a metal collar, which guided the drill press, to minimize

error when drilling joint holes. Refer to Figure 16 for a picture of this metal collar with an undrilled 3-

way joint fitted in.

29

Figure 16. Metal collar used to guide drill press for drilling joint connections

Manufacturing errors were still present despite precautions taken in to account for them. The joints and

members are still operational despite this, but more difficult to work as the assembly became more

challenging. For this reason, the team believes this could be an area that could be vastly improved should

the shelter ever be mass produced.

6.2 INSULATION

As previously outlined in the report, Nepal temperatures can vary drastically depending on the time of

year and elevation. To keep the shelters isolated from the extreme temperature variations inhabitants

could face, insulation was a key factor. The current insulation includes the double bubble foil insulation

which is effective in preventing heat from passing through it by reflecting approximately 96% of the

radiant heat it encounters14. However, this insulation does not perform well in slowing the way heat

passes through it. As a result, the team recommends that inhabitants improve this by implementing their

own form of insulation to help bolster the heat retention capability of the shelter. Such a material that

could be used, would be straw, which is readily available in areas of Nepal and is well known insulation.

6.3 VENTILATION

The shelter is efficient in the categories of heat retention and water-proofing, but the tradeoff is

ventilation. The only existing point for ventilation is the front door which may lead to poor air circulation.

The team recommends to mitigate this issue by rolling up the insulation and the outside tarp under

appropriate weather conditions so as to let the wind permeate the tarping exteriors. Or, if it is dry outside,

lower the bottom tarp to create more ventilation points. It is advised in future designs to implement

retractable flaps or openings to better facilitate air flow.

14 “Double Bubble Insulation - Foil/Foil - 4' x 75' (300 Sq Ft).” Ecofoil, www.ecofoil.com/Double-Bubble-Foil-

Insulation-Foil-Both-Sides-4-x-75-300-sq-ft.

30

6.4 LIGHTING

A short-coming of the shelter is the lack of lighting when inside the shelter. The lack of lighting can be

similarly attributed to the effective insulation and water-proofing. Besides the entry way, there are no

points in which light can enter the structure. The combination of tarping and insulation block nearly all

light from the outside and thus, during poor weather or night-time, the interior of the shelter can be very

dark. The team recommends using a non-flammable light source such as a lantern or a product such as the

gravity light to provide light to the interior. Future designs may be able to include such objects or

incorporate a simple light source into the structure’s frame.

6.5 DURABILITY

The shelter was meant to be a transitional shelter and not a permanent dwelling place. That being said, the

materials used in the shelter prototype are durable, but can be improved to have a longer lifespan and

implemented beyond the transitional phase. Attributes such as replacing the layered, taped holes on the

insulation with grommets for example would fit into this category. Additional recommendations to

increase the durability of the shelter materials would be to combine the insulation and tarp to reduce the

number of components. And similarly, create a single tarp to fit over the structure, minimizing the

number of components needed and the number of fasteners required. The bungie cords can be replaced

with paracord to fasten the tarp to the frame without concern of the bungie cords losing tension. The tarps

can also be upgraded to withstand UV exposure better over the lifespan of the structure so as to not lose

strength or performance. All of the listed above are options the team recognizes can impact the durability

of the structure.

31

7. CHRISTIAN PERSPECTIVE

The team’s Christian faith guided their participation in the competition as well as their design decisions.

The following design norms outline specific ways that the team applied their Christian perspective to the

design of their shelter and camp plan.

7.1 DESIGN NORMS

Cultural appropriateness was the first and most relevant of the design norms. Since the team was

designing something that will be used in a different culture, understanding the cultural context was

important so that the object met an actual need in a way that was natural and fitting for people in Nepal.

Designing without cultural appropriateness could be, at best, a waste of time, and at worst, an injurious

act to those whom the team sought to serve.

Transparency was another very important design norm. Transparency was essentially being open and

upfront about the capabilities of the design and whether or not it adequately met all the requirements and

fit the cultural situation. The team had no desire to deceive or mislead competition officials or the people

of Nepal. In order to best serve the team's clients, the team sought to be upfront with any concerns and

costs about the design.

Stewardship implies that the team produced a quality product given the budget allowed for each shelter,

and chose materials and methods required to erect these structures that have minimal impact on the local

and global environments. Stewardship required the team to answer questions relating to the life-cycle of

its product. What will happen to the materials after the product's useful life is over? Will the disposal of

the shelter lead to undue hardship among any people in Nepal?

Integrity is doing exactly what one says one will. This means that the team was obligated to follow

through on design promises and requirements. It also means that the team would not inflate expectations

or say that the design would be able to do things that it will not do. Integrity means not taking shortcuts or

the easy way out in design.

Justice was an enormous consideration in the team's design. As the team designed for a people who have

been afflicted by natural disaster. Justice in the team's design ensured that the team's product attempted to

rectify as many wrongs as possible that the Nepalese people have endured.

Caring goes above and beyond the concerns of justice. Not only was it important for the team to design in

terms of what met the needs of earthquake-survivors, but also what would provide them with the highest

quality of life. The team hoped to make living in the shelter as comfortable of an experience as possible,

given the disaster situation and constraints.

Trust was crucial for the team to be successful in this project. The team was entrusted to make a design

that thousands of people may live in for 1 to 3 years. The team designed their shelter in a way that future

inhabitants could trust that it would not collapse during inclement weather.

Humility was the understanding that the team was not always correct, and that seeking out wisdom from

others was crucial. For the team, this meant understanding and realizing that there was only so much that

a team with limited knowledge of the target area and people, could do on its own. This design norm

motivated the team to seek out knowledge from others who were more qualified in terms of Nepal-

related or disaster-relief-related knowledge.

32

8. COMPETITION RESULTS

The team competed over the days of April 19 to 21 of 2018 against nine other teams from various

universities. The team was judged over the following criteria; report, presentation, cost, physical

parameters such as height, weight, wind-loading, seismic-loading, heat-retention, rain resistance, aspects

of functionality such as ease of assembly, ventilation, privacy, durability, packaging, livability,

upgradability, and cultural appropriateness. To measure many of the criteria mentioned, the shelter

prototype underwent tests such as the shake table, heat retention booth, wind-loading machines, rain

machines, and judge examinations.

The team placed second overall and won several individual awards as scored by the panel of judges is

found in Appendix C. The individual awards include Best Camp Plan, Lightest Shelter, and Best

Report/Presentation.

9. CONCLUSION

The team has designed a shelter prototype and camp plan to provide Nepal with a usable and culturally

appropriate response to a disaster. The team’s efforts may contribute to the recovery period in Nepal, in

the event of another earthquake or natural disaster. The shelter provided enough living space for a family

of four. It was water-proof, could withstand high winds and earthquake tremors/aftershock, and provided

insulative cover in the cold temperatures. The prototype was lightweight, durable, packable, and cost

effective. Additionally, the camp plan was all inclusive and modular to fit a specific situation and terrain.

As a result of the above analysis, the team believed that all of the project constraints given by John Brown

University were met. The team has learned a great deal of the humanitarian relief efforts, of being a part

of a team, and are proud of the competition results achieved.

33

ACKNOWLEDGEMENTS:

The team would like to thank the Eric DeGroot Engineering Fund for their support to our project

and for the continuous support to Senior Design Teams.

The team would like to acknowledge the faculty advisor, Professor De Rooy, as well as the

Calvin College Engineering Program for the support and opportunity to pursue this competition.

The team would like to thank Jim and Marcia Vander Meulen for providing transportation to and

from the competition site.

The team would like to thank Rick Blauwkamp for providing a trailer to transport the shelter

prototype to and from the competition site.

The team would like to thank Michelle and Wyman Dobbs for hosting and feeding the team while

at the competition.

The team would like to thank Samaritan’s Purse and Intertek for sponsoring the competition as

well as John Brown University for hosting the competition on their campus.

The team would like to thank Bob DeKraker for ordering and managing shelter components.

The team would like to thank Phil Jasperse for his consultations and support in the manufacturing

of the shelter prototype and components.

34

REFERENCES:

“2018 International Container Shipping Rates and Costs.” MoverDB.com, MoverDB.com, 8 Jan 2018,

moverdb.com/container-shipping/.

“Double Bubble Insulation - Foil/Foil - 4' x 75' (300 Sq Ft).” Ecofoil, www.ecofoil.com/Double-Bubble-

Foil-Insulation-Foil-Both-Sides-4-x-75-300-sq-ft.

Fernando Romero et al. Border City, www.fr-ee.org/project/73/Border+City. Accessed 1 Apr. 2018.

Frearson, Amy. “Prototype shelter for Nepal earthquake victims could be built by unskilled workers in

three days”. Dezeen. 11 July 2015. Dezeen. Web. 6 Dec. 2017.

<https://www.dezeen.com/2015/07/11/prototype-bamboo-shelter-nepal-earthquake-victims-built-

by-unskilled-workers-three-days/>.

Garber, Nicholas J. Traffic and Highway Engineering, 5th Edition. Cengage Learning, 2015. [Bookshelf

Online]

Laylin, Tafline. “10 refugee shelters I love, for the good and the bad”. Green Prophet. 14 March 2014.

Green Prophet. Web. 6 Dec. 2017. <https://www.greenprophet.com/2014/03/pros-and-cons-10-

refugee-shelters/>.

“Map of Nepal”. WELNepal. 2011. WELNepal. Web 20 Nov. 2017.

<http://www.welnepal.org/homeMap.html>.

“Nepal Earthquakes: Devastation in Maps and Images.” BBC News World. 15 May 2015. BBC. Web. 13

Nov. 2017. <http://www.bbc.com/news/world-asia-32479909>.

Proud, Richard, Zuberi, Matinuzzaman. “Nepal”. Encyclopǽdia Britannica. 24 March 2017.

Encyclopǽdia Britannica, Inc. Web. 7 Dec. 2017. <https://www.britannica.com/place/Nepal/The-

people>.

“Sheltering Nepal”. Samaritan’s Purse. 26 Nov. 2015. Samaritan’s Purse. Web. 13 Nov. 2017

<https://www.samaritanspurse.org/article/sheltering-nepal/>.

Sokol, Brian. “Struggling amid the ruins a month after Nepal quake”. Al Jazeera. 25 May 2015. Al

Jazeera media Network. Web 26 March 2018.

<https://www.aljazeera.com/indepth/inpictures/2015/05/struggling-ruins-month-nepal-quake-

150525062223409.html>.

Unknown – Dickens, Asbury & Forney, John W., eds. (1832) “Plan of Detroit (Map). American State

Papers. Vol. 6: Public Lands. 1:6,000. Washington, DC: Gales &Seaton. P. 299. OCLC 2053058.

OL7014594M. LCCN </noinclude> 09033892 – via Archive.org.

Urban Street Design Guide, National Association of City Transportation Officials,

https://nacto.org/publication/urban-street-design-guide/design-controls/design-vehicle/. Accessed

1 Apr. 2018.

35

TABLE OF APPENDICES:

A. CALCULATIONS A1. Wind Calculations

A2. Anchoring Calculations

A3. Bolt Design Calculations

B. CAMP PLAN B1. Idealized & Site-Specific Camp Plans

B2. Large Scale B-Unit with Encampment and Storage Areas

B3. Camp Plan Component Dimensions

B4. Encampment & Storage Area Dimensions

B5. Encampment & Storage Area Spatial Distribution

C. COMPETITION SCORING MATRIX

D. CONSTRUCTION DIRECTIONS

36

APPENDIX A1: WIND CALCULATIONS

CODE: ASCE 7-10: 27.3.2 VELOCITY PRESSURE:

𝑞𝑧 = 0.00256𝐾𝑧𝐾𝑧𝑡𝐾𝑑𝑉2 (𝑙𝑏

𝑓𝑡2) (27.3-1)

𝑞𝑧 = Velocity Pressure

𝐾𝑧 = Velocity Pressure Exposure Coefficient

𝐾𝑧𝑡 = Topographic Factor Defined

V = Basic Wind Speed

𝐾𝑑 = Wind Directionality Factor

From Table 27.3-1: Height Above Ground Level is 0-15 feet, and has Exposure C. Therefore 𝐾𝑧 = 0.85

From Section: 26.8.2: All conditions not met. Therefore 𝐾𝑧𝑡 = 1.0

From John Brown University Design Guidelines: V = 46.6 mph (75 Km/Hour)

From Table 26.6-1: For Arched Roofs, 𝐾𝑑 = 0.85

𝑞𝑧 = 0.00256 𝑥 (0.85) 𝑥 (1.0) 𝑥 (0.85) 𝑥 (46.6)2 = 4.02 𝑙𝑏

𝑓𝑡2 (192.17 𝑁

𝑚2)

TOTAL LOADS ON EACH WALL WHEN RESISTING WIND:

Area of Side Wall: 16ft x 6ft = 96 ft2

Area of Front and Back Wall: 10ft x 6ft + 17.3 ft2 = 77.3 ft2

Total Load on a Side Wall: 4.02 lb/ft2 x 96 ft2 = 385.9 lb (1,716.7 N)

Total Load on Front and Back Wall: 4.02 lb/ft2 x 77.3 ft2 = 310.8 lb (1,382.3 N)

37

APPENDIX A2: ANCHORING CALCULATIONS

From Appendix A1: Load on Side Wall due to Wind = 385.9 lb

Factor of Safety = 2

Figure A2. Diagram of design scenario for overturning

Overturning Moment = 385.9 lb x 3ft = 1157.7 lb-ft

Factored Overturning Moment = 1,157.7 lb-ft x 2 = 2,315.4 lb-ft

Uniform Weight of Bags = Bw

Therefore,

Bw x (10ft x 5ft) x 2 + Bw x 16ft x 10ft = 2,315.4 lb-ft

Solving for Bw: Uniform Weight of Bags necessary to avoid over tipping is 8.9 lb/ft

Bw = 8.9 lb/ft

38

APPENDIX A3: BOLT DESIGN CALCULATIONS

Refer to Figure A3 for a Diagram of the Bolt in double shear.

Figure A3. Diagram of Bolt in Double Shear

P = Maximum Axial Load

d = Diameter of Bolt

From Modeling on StaadPro, maximum axial load, P, is equal to 32 lbs.

P = 32 lbs

Selected Bolt Diameter = 0.25”, d = .25 in

Factor of Safety = FS = 3

Solve for Ultimate Tensile Strength Required = Tr, where Tr is 60% of the Maximum Shear Stress

Max Shear Stress, 𝜏= 𝑃 𝑥 𝐹𝑆

2 𝑥 𝜋

4(𝑑2)

= 32 𝑙𝑏 𝑥 3

2 𝑥 𝜋

4(.25𝑖𝑛)2

= 977.8 psi

𝜏 = Tr x 0.6

Solving for Tr, Ultimate Tensile Strength Required is 1629.7 psi

𝜏

Using Grade 5 Steel ¼ inch diameter bolts as the design bolt, the actual Ultimate Tensile Strength of this

bolt is 120,000 psi.

Since 60 % of the Ultimate Tensile Strength of a bolt is the maximum shear stress a bolt can handle, this

particular bolt can withstand a shear stress of 72,000 psi. Since 72,000 psi is much greater than 1629.7

psi, the selected bolts will be more than capable of resisting failure in shear. The team is comfortable with

this overdesign as there is not a significant difference in price between varying sizes of bolts, and ¼-inch

diameter bolts are a standard size of use.

39

APPENDIX B1: IDEALIZED & SITE-SPECIFIC CAMP PLANS

For clarity, larger figures of the idealized and site-specific camp plans are included in this appendix.

Figure B1. Idealized Camp Plan

F

FF

F

F F

MM M

MM M

U

+

40

Figure B2. Site-Specific Camp Plan

+

F

F

F

F

F

F

MM M

MM M

U

41

Appendix B2: Large Scale B-Unit with Encampment

and Storage Areas

Smaller elements, like the 25-gal (100-L) trash bins, are difficult to see in the previous appendix, and thus

are shown in a larger form below. A B-Unit with several additional encampment and storage areas, along

with the boundaries with the roadway, are shown.

Figure B3. Large Scale B-Unit from Idealized Camp Plan

42

Appendix B3: Camp Plan Component Dimensions

The following figures depict the dimensions of individual components in both the idealized and site-

specific variant camp plan. All length units are in feet.

Figure B4. Shelter Dimensions

Figure B5. Outhouse Dimensions

Figure B6. 25-Gal (100-L) Trash Bin Dimensions

16'

10'

5'

3'

1.7'

1.7'

43

Figure B7. 1200-Gal (4500-L) Water Tank Dimensions

Figure B8. 5000-Gal (19000-L) Water Tank Dimensions

Figure B9. Wash Basin Dimensions

DIA 12.1'

DIA 19.8'

3.3'

2.0'

44

Figure B10. Medical Facility Dimensions

Figure B11. Shower/Laundry Facility Dimensions

+160'

80'

60'

30'

45

APPENDIX B4: ENCAMPMENT & STORAGE AREA

DIMENSIONS

The following figures depict the dimensions of the types of encampment and storage areas in the idealized

camp plan. All length units are in feet.

Figure B12. Encampment Area E1 Dimensions

Figure B13. Encampment Area E2 Dimensions

Figure B14. Encampment Area E3 Dimensions

130.91'

167.82'

21.31'

E1

167.8'

112.4'

55.4'E2

167.8'

105.4'

62.5'E3

46

Figure B15. Storage Area S1 Dimensions

Figure B16. Storage Area S2 Dimensions

Figure B17. Storage Area S3 Dimensions

70.6'

44.4'

40.8'

S1

100.4'

67.9'32.5'

S2

12'48.5'

55.4'

S3

47

APPENDIX B5: ENCAMPMENT & STORAGE AREA SPATIAL

DISTRIBUTION

The figure below shows the spatial distribution of encampment and storage areas in the idealized camp

plan. For site-specific variant camp plans, new encampment and storage areas may need to be created to

suit the specific geography and topography.

Figure B18. Chart of Encampment & Storage Areas in Idealized Camp Plan

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E1

E3E3

E3E3E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

E2

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S1

S2

S2

S2

S2

S2

S2

S3

S3

S3

S3S3

S3

S3

S3

S3

S3 S3

S3

48

APPENDIX C: COMPETITION SCORING MATRIX

49

Appendix D: Construction Directions

A: Roof B: Floor

A1.) Assemble, connect, and bolt 5 arch sec-

tions as shown.

A2.) Connect 5 arch sections together in order

shown.

B2.) Drive stakes into ground and connect floor

frame to stakes.

B1.) Assemble, connect, and bolt floor mem-

bers together as shown.

B3.) Place the floor tarp on top of the bottom

frame with the holes aligned. Insert the columns

into the floor frame and tie the edges of the

floor tarp up onto the members as shown.

50

A4.) Place the front and back tarps, connecting them to

the frame using the bungee cords. Leaving the tarps on

top so that they do not hang down.

B4.) Lay the floor tiles in place A3.) Attach the insulation panels to the mem-

bers as shown.

51

C2.) Roll down the insulation and connect the remain-

ing panels. Connect the ratchet straps in a an “X” for-

mation, as shown below, on the 2 largest front and back

panels and 2 middle panels on each side.

C3.) Fold front and back tarps down to ground

and connect/tighten to frame with ball cords as

shown.

C6.) In the meantime, fill sand bags to 3/4s full and

place on floor frame, between the insulation and the floor

tarping.

C5.) Put the shower curtains in place to divide into

rooms

C1.) Lift the roof up and place onto the col-

umns.

C: Entire Structure

C4.) Put the roof tarp in place and secure the bottom to

the frame using ball cords. Secure the front and back with

ratchet straps and bungee cords.