FINAL REPORT- Case Study Jamaica_Spandana Nakka

download FINAL REPORT- Case Study Jamaica_Spandana Nakka

of 30

Transcript of FINAL REPORT- Case Study Jamaica_Spandana Nakka

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    1/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    2/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    3/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    4/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    5/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    6/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    7/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    8/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    9/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    10/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    11/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    12/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    13/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    14/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    15/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    16/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    17/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    18/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    19/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    20/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    21/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    22/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    23/30

    Engineering Response to Global Sea Level Rise- Case Study, Port of Kingston, Jamaica, Dec 2010

    - 22 -

    Typical cross-sections

    Figure 24 Cross-section of Wet-Wet dike (Port Protector Spreadsheet)

    Materials (Port Protector Spreadsheet)

    Material Quantities

    Component Material Volume Component Material VolumeDike Foundation Concrete 2,401,926 Dike Foundation Concrete 437,526 Dike Toe Structural Fill 378,540 Dike Toe Structural Fill 68,954 Dike Core Concrete 1,089,737 Dike Core Concrete 198,503 Dike Structural Fill 5,838,232 Dike Material Structural Fill 1,063,471 Dike Armoring Rip Rap 1,910,860 Dike Armoring Rip Rap 348,075

    Component m3Concrete 4,127,691 Structural Fill 7,349,196 Riprap 2,258,935

    Wet- Wet Dike Wet- Dry Dike

    Total Materials

    Figure 23 Cross-section of Wet-Dry Dike (Port Protector Spreadsheet)

    Table 10 Individual material uantities for Wet-Wet & Wet-Dr Dike + Combination Port Protector S readsheet

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    24/30

    Engineering Response to Global Sea Level Rise- Case Study, Port of Kingston, Jamaica, Dec 2010

    - 23 -

    Cost Data

    Cost

    Component $ Component $Dike Foundation 208,967,534.01$ Dike Foundation 38,064,746.53$Dike Toe 6,435,186.12$ Dike Toe 1,172,209.50$Dike Core 94,807,153.80$ Dike Core 17,269,717.50$Dike Material 99,249,942.14$ Dike Material 18,078,999.25$Dike Armoring 99,364,734.38$ Dike Armoring 18,099,909.38$

    508,824,550.44$ 92,685,582.16$

    Total Cost 601,510,132.60$

    Wet- Wet Dike Wet- Dry Dike

    Table 11 Cost Data for Wet-Wet & Wet-Dry dike (Port Protector Spreadsheet)

    Time to construct (Man-hours)

    (Based on a 40 hour work week, year round construction, 200 person crew size) wet wet dike

    Labor (Man-Hours)

    Component Man-hours Component Man-hoursDike Foundation 36,028.89 Dike Foundation 6,562.89 Dike Toe 5,678.11 Dike Toe 1,034.30 Dike Core 16,346.06 Dike Core 2,977.54 Dike Material 87,573.48 Dike Material 15,952.06 Dike Armoring 16,346.06 Dike Armoring 5,221.13

    161,972.59 31,747.91

    Total Man-Hours 193,720.50

    Wet- Wet Dike Wet- Dry Dike

    Schedule (Years)

    Component Years Component YearsDike Foundation 0.07 Dike Foundation 0.01 Dike Toe 0.01 Dike Toe 0.00 Dike Core 0.03 Dike Core 0.01 Dike Material 0.17 Dike Material 0.03 Dike Armoring 0.03 Dike Armoring 0.01

    0.31 0.06

    Total Years 0.37

    Wet- Wet Dike Wet- Dry Dike

    Table 12 Man-hours for the construction of Wet-Wet & Wet-Dr Dike Port Protector S readsheet

    Table 13 Years to construct Wet-Wet & Wet-Dry Dike (Port ProtectorSpreadsheet)

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    25/30

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    26/30

    Engineering Response to Global Sea Level Rise- Case Study, Port of Kingston, Jamaica, Dec 2010

    - 25 -

    Typical cross-sections

    Figure 27 Cross-section of the vertical Seawall (Asia Hub)

    Material Quantities

    Material Quantities

    Component Material Volume Component Material VolumeSeawall core Concrete 169,908 Dike Foundation Concrete 1,475,384 Seawall Material Structural Fill 951,815 Dike Toe Structural Fill 307,890 Seawall Armoring Riprap 571,767 Dike Core Concrete 886,350

    Dike Material Structural Fill 1,615,396 Dike Armoring Rip Rap 1,088,216

    Component m3Concrete 2,531,642 Structural Fill 2,875,101 Riprap 1,659,983

    Vertical Sea Wall Wet- Dry Dike

    Total Materials

    Figure 26 Figure 15: Design cross-section of wet-dry dike. (Source: Port Protector

    spreadsheet)

    Table 14 Material quantities for Vertical Seawall & Wet-Dry dike + Combination(Port Protector Spreadsheet)

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    27/30

    Engineering Response to Global Sea Level Rise- Case Study, Port of Kingston, Jamaica, Dec 2010

    - 26 -

    Cost Data

    Labor

    Time to construct

    (Based on a 40-hour work week, year round construction, 250 person crew size)

    Labor

    Component Man-hours Component Man-hoursSeawall core 2,549.00 Dike Foundation 22,130.76 Seawall Material 14,277.00 Dike Toe 4,618.35 Seawall Armoring 8,577.00 Dike Core 13,295.25

    25,403.00 Dike Material 24,230.94 Dike Armoring 16,323.23

    Total Manhours 24,900.23 80,598.54

    Vertical Sea Wall Wet- Dry Dike

    Schedule (Years)

    Component Years Component YearsSeawall core 0.005 Dike Foundation 0.04 Seawall Material 0.03 Dike Toe 0.01 Seawall Armoring 0.02 Dike Core 0.03

    0.05 Dike Material 0.05 Dike Armoring 0.03

    Total Years 0.20 0.15

    Vertical Sea Wall Wet- Dry Dike

    Cost

    Component $ Component $Seawall core 14,781,953.00$ Dike Foundation 128,358,408.00$Seawall Material 16,180,847.00$ Dike Toe 5,234,130.00$Seawall Armoring 29,731,884.00$ Dike Core 77,112,450.00$

    60,694,684.00$ Dike Material 27,461,735.40$Dike Armoring 56,587,212

    294,753,935.41$Total Cost 355,448,619.41$

    Vertical Sea Wall Wet- Dry Dike

    Table 15 Cost data for Vertical Seawall & Wet-Dry dike (Port Protector Spreadsheet)

    Table 16 Man-hours for construction of Vertical Seawall & Wet-Dry dike (Port ProtectorS readsheet

    Table 17 Years to construct Vertical Seawall & Wet-Dry dike (Port ProtectorSpreadsheet)

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    28/30

    Engineering Response to Global Sea Level Rise- Case Study, Port of Kingston, Jamaica, Dec 2010

    - 27 -

    5.3 Alternative Selection As the Port of Kingston moves towards adapting to sea level rise, consideration should bealso given to the infrastructure which surrounds the port, or its contiguous community.The Port of Kingston Causeway is the most prone infrastructure to the SLR. As theCauseway is an important link of ground transport between the port and the other part of

    the island, it should also be protected.The Jamaican government has specified several areas as protected areas distributed acrossthe island. Invariably, these protected areas have biological significance, but all areentwined with the physical environment. (Figure 28).

    Figure 28 Protected Areas of Jamaica

    Figure 29 Cost comparison of

    both alternatives Figure 30 Schedule comparisons of both alternatives

    Based on the primary objectives, and the above cost, schedule data, (Figures 29 & 30)Alternative #2 seems a more viable option. Thus Selecting Alternative #2, we have,

    Pros:

    Protects the Port of Kingston Causeway. Since this causeway is an important link for the Tinson Pen airport as well, support

    could be expected from the aerodrome authority as well.

    http://www.monagis.com/files/Presentations/ATLAS.pdfhttp://www.monagis.com/files/Presentations/ATLAS.pdfhttp://www.monagis.com/files/Presentations/ATLAS.pdf
  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    29/30

    Engineering Response to Global Sea Level Rise- Case Study, Port of Kingston, Jamaica, Dec 2010

    - 28 -

    Does not intrude into the protected areas.Cons:

    Protects just the port infrastructure and not the adjacent community, Hence support is mainly expected from the stakeholders

    Lesser chances of funding from other sources, as the protection is intended to keeptrade going

    6 Schematic Design Development 1. Design-

    Source of funding is a major concern, considering Jamaica is a developing nation.The funding would have to be mainly from the ports stake-holders, who may or maynot be interested. The design could also be proposed to seek funding through NAPA,to protect the coastal infrastructure. The port authority is also not completely awareof the risks posed.

    2. Planning

    -Resources: Proper resources required for the construction should be planned, eitheravailable on site or transported from elsewhere. Since Port of Kingston itself exportscement in large quantities, concrete should be locally available.

    -Transportation: Transportation to the site is also a problem, since, the landtransportation is limited to just Port of Kingston causeway, with the airport on the other

    side of the port.- Equipment: The construction hauling and lifting equipment should be present on site.

    This leaves it to getting the concrete mixers, compactors etc.

    3. Temporary trade relocation

    Though this is not a convenient option, but during the construction the trade couldbe shifted to the adjacent terminals, or to the nearby Port Royal.

    6.1 Societal Impacts

    The following societal impacts should be expected from the dike project:- change in recreational use of the ship channel- change in property ownership and property values along the span of land

    adjacent to the shipping channels- change in aesthetics of the harbor area, which may negatively affect cruise

    tourism, for example

  • 8/6/2019 FINAL REPORT- Case Study Jamaica_Spandana Nakka

    30/30