Final Report
-
Upload
richard-stone -
Category
Documents
-
view
116 -
download
0
Transcript of Final Report
Solar Panel Cleaning
System
Design Project II: Exercise 3
Arthur Mallet Dias
Harry Garstka
Loic Gueganton
Richard Stone
Harri Worman
UNIVERSITY OF BRISTOL
ENGINEERING DESIGN
27 March 2015
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 2 of 40
Table of Contents
Executive Summary ......................................................................................................................................... 4
Nomenclature Used Throughout Report .......................................................................................................... 4
1. Introduction and Design Specification .................................................................................................... 5
Introduction .................................................................................................................................... 5
Brief ............................................................................................................................................... 5
Stakeholder Needs .......................................................................................................................... 5
Research ......................................................................................................................................... 6
1.4.1 Selected Base Module ................................................................................................................ 6
1.4.2 Consumable Use in Current Solutions ....................................................................................... 6
Design Specification ...................................................................................................................... 7
2. Design Alternatives and Proposed Solution............................................................................................ 8
Idea Generation Process ................................................................................................................. 8
Results from Idea Generation ......................................................................................................... 8
Down Selection Process ................................................................................................................. 8
Proposed Solution ........................................................................................................................ 10
2.4.1 Modifications Made to Initial Design and Resultant Advantages Offered .............................. 10
2.4.2 Potential Problems Arising Due to Modifications ................................................................... 10
3. Design Definition of Proposed Solution ............................................................................................... 11
Final Design ................................................................................................................................. 11
Presentation of Final Design Including Operation Procedure ...................................................... 12
Orthographic Projection Showing Key Dimensions .................................................................... 13
General Assembly Drawing with Parts List ................................................................................. 14
4. Proving Calculations and Technical Feasibility .................................................................................... 15
Structural Analysis ....................................................................................................................... 15
4.1.1 Material Selection .................................................................................................................... 15
4.1.2 Stiffness Calculation ................................................................................................................ 15
Gearbox Calculation..................................................................................................................... 17
4.2.1 Force and Torque Required to Move Up Panel ...................................................................... 17
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 3 of 40
4.2.2 Gearbox Ratio Required .......................................................................................................... 18
Energy Analysis of Device Operation .......................................................................................... 18
Battery Power Usage .................................................................................................................... 19
Manufacturing Considerations ..................................................................................................... 19
Actuation and Control Systems Used ........................................................................................... 20
5. Cost Analysis ........................................................................................................................................ 21
Comparison to Other Methods ..................................................................................................... 21
Device Manufacture Cost ............................................................................................................. 21
Machining Costs .......................................................................................................................... 22
Running Costs .............................................................................................................................. 22
Payback Period ............................................................................................................................. 22
6. Evaluation ............................................................................................................................................. 23
Evaluation against Specification .................................................................................................. 23
Commercial Feasibility ................................................................................................................ 24
Improvements and Uncertainties .................................................................................................. 24
Overview and Conclusion ............................................................................................................ 25
Bibliography .................................................................................................................................................. 26
Appendix A – Gallery of 15 Rejected Ideas ................................................................................................ 27
Appendix A – Gallery of 15 Rejected Ideas ................................................................................................ 28
Appendix A – Gallery of 15 Rejected Ideas ................................................................................................ 29
Appendix A – Gallery of 15 Rejected Ideas ................................................................................................ 30
Appendix B – Idea Down Selection ............................................................................................................. 31
Appendix C – Spreadsheet Used In Energy Analysis ................................................................................. 32
Appendix D – Components Used For Prototype ........................................................................................ 33
Appendix E – Software Code ....................................................................................................................... 34
Appendix F – Cost Analysis Sources and Assumptions ............................................................................. 37
Appendix G – Evaluation Diagrams ............................................................................................................ 40
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 4 of 40
EXECUTIVE SUMMARY
The following report outlines the process and result of designing a cleaning robot for use in the solar industry,
to autonomously clean solar panels. It contains an exploration into the design process used, a definition of the
final design solution, the functionality and operation of the device justified with relevant calculations, and a
business case for its commercial viability in the market.
The report begins with an explanation of the steps taken to reach the design solution, including the scope of
research conducted, and a detailed design specification which was referred back to throughout the report.
Convergent and divergent idea techniques were used to generate a range of ideas and filter them down to
reach to the final design; an adjustable rail-mounted cleaning robot to fit any panel size or configuration.
The final solution was then defined through the use of detailed technical drawings and CAD renderings with
operation descriptions. No water was used in the operation of the device. The device was composed mostly
of aluminium, styrene, and HDPE, using omnidirectional wheels and an Arduino chip to move around and
clean the panel, being guided by the rails.
After the device had been defined, a full energy was performed, and it was found that the 12V battery would
need to be swapped out and recharged every 380 panels on average. Cost calculations followed, and the cost
per panel was determined to be 3.81p, with an expected price of 20p, assuring commercial viability.
Our final design solution was then rigorously checked against the design specification outlined earlier in the
report. A self-critical evaluation was then performed, identifying weaker areas of the design, for example the
inability to efficiently clean bird excrement from the panel. From this evaluation, aspects of the device to
improve were outlined for future development.
NOMENCLATURE USED THROUGHOUT REPORT
The terms ‘solution’ and ‘device’ are used interchangeably throughout this report.
Cell
A solar ‘cell’ is a photoelectric cell which converts light energy directly into electricity.
These are the smallest unit capable of performing this function, making them the building
blocks of all photovoltaic devices.
Panel
The term ‘panel’ is used interchangeably with the term ‘module’, both throughout this
report and in industry. These are comprised of an assembly of multiple solar cells, all in an
integrated group and oriented in one plane. A typical panel size is 1×1.6 m, which is made
up of 60 cells.
Table
A ‘table’ is a collection of modules, again all orientated in one plane, which are all mounted
on a supporting structure. A table is comprised of many modules extending in the
horizontal direction, and one or two modules extending in the vertical direction.
Portrait
orientation
Since modules are almost always rectangular in shape, they will have one long side and one
short side. When the long side is facing vertical and the short side horizontal, this is
considered to be a ‘portrait orientation’ of the module.
Landscape
orientation
Likewise, when the short side of the module is facing vertical and the long side horizontal,
this is considered to be a ‘landscape orientation’.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 5 of 40
1. INTRODUCTION AND DESIGN SPECIFICATION
Introduction
In today's climate of a mounting desire for energy production and increasing environmental concerns,
renewable sources such as solar energy are encountering widespread use. Solar energy systems work by
harnessing light energy transmitted from the sun’s radiation, and converting this into electricity through the
use of photovoltaic (PV) panels.
There is a major issue associated with PV panels, however, concerning the accumulation of dust and
contamination on their surfaces; which, over time, can lead to a significant reduction in their energy
generation capability, in addition to causing potentially irreversible damage to the panel. This report will
outline the design and build process of a device to autonomously clean the surfaces of solar panels, in order
to combat this problem.
Brief
It is assumed that the proposed solution is required to support a business case for developing a solar panel
cleaning product, which could be sold to companies specializing in solar farm installation and maintenance.
Therefore, maximising the internal rate of return over the lifecycle of the solution is the core design driver
for this project. In turn, this can be achieved by optimising the device to incur the lowest possible financial
cost during its operation.
Many factors have a significant influence on financial operating costs. For
example, minimising consumable use and the need for skilled labour will
reduce the expenses incurred by the device. Likewise, autonomous operation
of the device is essential as it also links back to reducing labour costs. A
graphical depiction of how two factors influence the final design are
illustrated in Figure 1.
It is also beneficial for the design to be adaptable, as this will mean it could be used by different operators for
a larger number of panel types, ultimately supporting the business case further. This will be pursued as a
secondary design driver throughout the development of the solution.
Stakeholder Needs
The question and answer session gave the opportunity for initial engagement with the client. Following this,
a 20,000 module, 5MWp site was chosen as a typical case for which the proposed system would be required
to clean. A rough estimate of the price to clean a panel for this type of site using current cleaning methods
was given to be around 25 pence. Time taken is not a priority.
Sources of water and mains electricity are not always available at solar farms, imposing two limitations on
the design. Firstly, it means the device must be battery powered. Factors such as the repeated cyclic
conversion of kinetic energy to irrecoverable gravitational potential energy (GPE) as the system traverses
Low cost
Operational simplicity
Autonomous operation
Figure 1: A hierarchy showing how
many design factors ultimately link
back to minimising financial cost.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 6 of 40
vertically across the panels must therefore be considered, as this decreases the efficiency of the power output.
Similarly, water consumption must be minimised due to logistic constraints, and this will be explored in
greater depth in Section 1.4.2 next.
Research
Research was conducted into a range of areas in order to understand the design requirements, which are
pivotal in designing the most suitable cleaning system for the brief given. From this, a detailed design
specification (given in Section 1.5) was produced, which captured all findings.
1.4.1 Selected Base Module
Research was conducted on a range of popular manufacturers to determine the extent to which their panels
were used in the UK, the amount of data available on them, and their similarity to the standard panel
dimensions of 1×1.6 m. The Suntech STP2XX range [1] was agreed upon as the basis for the design, being
in widespread use throughout the UK [2] and with a large amount of datasheets available online.
1.4.2 Consumable Use in Current Solutions
Over the lifetime of the cleaning system, initial setup costs will become negligible, and instead the operating
costs will be dominated by consumable expenses. Therefore, it was necessary to investigate the financial
impact of these consumables on the cleaning operation, the findings of which are presented in Table 1. The
normalised cost of labour evidently imposes the most substantial contribution to overall financial costs.
1 Where normalised costs are per module, this is for a typical 20,000 module site as described in the Q&A. 2 Using the example given with the 5MWp Toyota installation from the Q&A session. 3 This is the mean value of two separate quotes given for different delivery locations; one was for a delivery
to a site near the water depot, and the other for a delivery approximately 80 miles away. 4 This setup involves a Hyundai HY1000Si-LPG 1 kW petrol generator connected to a rectifier, which is used
to provide DC power to charge the battery after it has been depleted.
Table 1: Costing of common consumables used during solar panel cleaning operations.
Consumable Expenditure Per Normalised cost Per1
Labour
£ 8.00 Person/Hour £ 0.331 1×1.6 m module
Assumptions: Only unskilled labour is required so wages can be relatively
cheap at £8/hour; 18,000 modules takes two weeks to clean with 10 workers2;
Workers clean for 7 hours per day for 5 days per week.
2,000 L water bowser
delivery to site
£ 391.153 Delivery £ 0.059 1×1.6 m module
Assumptions: 300 mL used per module; Quote from water-direct.co.uk [3].
DC power used to
recharge battery4
(up to) 2.7
litres of petrol 9 hours use £ 0.360 kWh
Assumptions: A 1 kW inverter generator is used [4]; Generator is operating at
maximum efficiency; Petrol price is a standard UK rate of £1.20/litre.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 7 of 40
Design Specification
Table 2: Requirements Specification Key: D/W = Demand/Wish; Wt. = Weighting; H/M/L = High/Medium/Low; Mod. = Modified
# D/W Wt. Requirement Source Acceptance Criteria / Method of Testing Mod.
Performance
1 D
Must be able to clean the entire
surface area of a 1640×992 mm
Suntech ‘STP265S-20/Wem’
module
Research
A visual check of the panel surface will be performed
and all dust and bird excrement must be removed after
the cleaning process
18/2/15
2 D Must be able to clean one whole
solar panel table autonomously Brief
The final design must clean a table of 10 by 2 panels
unassisted
3 D Must not damage solar panels
during cleaning Q&A
After cleaning, there will be no visible defects on the
panels, and their peak power output must not deteriorate
4 W H Desirable be able to clean panels
without a water supply Research
Functionality will be tested without water to check there
is no deterioration in cleaning quality 22/2/15
5 W M
Should be able to clean more than
one type of panel from a given
manufacturer
Brief The design will successfully clean two separate models
(Suntech 250w and 265w)
6 W L
Desirable to be able to clean
panels from more than one
manufacturer
Brief Both 265w polycrystalline variants of panels from
Suntech and Q Cells will be cleaned successfully
7 D Must be able to traverse gaps
between tables autonomously Brief
The device will traverse gaps between tables without
any manual intervention from any workers 13/2/15
8 D
Must be able to remain in
continuous use for an acceptable
period of time before failure
Brief At least 3000 tables must be cleaned by a single device
before breakdown 09/2/15
Physical Characteristics
9 D
Must only require one worker to
operate and handle, whilst
remaining safe and comfortable
for them
Research
No individual part of final design will weigh more than
15 kg, and will be labelled as appropriate depending on
the shape, to conform to LOLER legislation [5]
14/2/14
10 Must not require anyone working
at height to be attached to panel Research
Workers will be able to be fully attach the device to the
panel whilst remaining standing on the ground
11 D Must be easy to transport between
the depot and solar farm site Q&A
The device, together with all associated parts, must fit
inside a container from a standard box truck, with
dimensions 6096×2400×2375 mm [6]
14/2/15
12
Must be able to withstand
vibrations encountered during
worst case transport conditions
Q&A
Device must show no deterioration in operation after
test stated in MIL-STD-810G Section 2.1.2: Vibrations
Encouraged During Transportation (Mission/field
transportation) [7].
Economics
13 D Must maximise internal rate of
return to support business case Brief
Price charged per panel must be less than 25 pence to be
beat current competitors
14 D Must have a long product life Brief Product lifetime must exceed 10 years
Environmental
15 D
Must be able to operate as normal
within a standard range of
temperatures in the UK
IEC
SPECS
Between the temperatures of 5°C and 40°C, the device
should show no reduction in performance or failure
16 D Must not release any chemicals
onto the ground during operation Q&A
The only acceptable by-product of the design, if any,
can be water
Legislation
17 D Must not be excessively loud for
any workers operating [8]
Maximum noise level must not exceed 85 dB in
accordance with the Control of Noise at Work
Regulations 2005
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 8 of 40
2. DESIGN ALTERNATIVES AND PROPOSED SOLUTION
Idea Generation Process
The necessary functions required from the device were split device into three categories: method of cleaning,
method of movement across panels, and method of traversing gaps between tables. A morphological chart
(shown below in Table 3) was derived to encompass all of these, after which brainstorming was employed to
generate a range of ideas, with each following a different permutation of the functions. By the end of this
process, 15 unique design ideas had been created, ranging from simple concepts like a rail mounted scrubber
to less conventional methods such as utilizing recyclable polystyrene film to cover the panels entirely. See
Appendix A for a full list of the 15 ideas generated.
Table 3: The morphological chart used, with paths taken to achieve the two final designs highlighted in red and blue.
Cleaning
method Air/water jet Mop Scrubbing
Rollers /
Rotational Vacuum Wiping
Movement
across panel Wheels Suckers Rails
Caterpillar
tracks Detachable
pulleys
Hovering /
flying
Traversing
tables
Three bar
mechanism Make a
bridge
Spring
system Attachment
rails Flying Big wheels
Results from Idea Generation
After sketching the ideas out, it became apparent that there was universal difficulty in traversing the
gaps between tables autonomously, due to the large distances involved. Although feasible solutions
were produced, none were economically viable, and as a result this requirement was removed.
As all the ideas were viable with or without water, it was decided to omit the use of water in all designs
to save on consumable costs, to ensure specification Requirement ⑬ was met.
The removal of water from the solutions created a new problem of how to remove stubborn dirt or bird
excrement from the panels. After a brief brainstorm, the use of a sensor to identify and forward the
location of dirt/excrement to a manual cleaner was considered.
In addition, due to lacking the water to wash away frost from the panels, operating in near-zero
temperatures would no longer be possible with this no-water approach.
Since labour is the largest consumable cost (see 1.1.3), requiring only one worker to use the device was
set as an additional requirement. Taking into account the existing requirement to have the operator
move the device manually between tables, this meant that the device had to be portable by one person,
and must therefore have a minimal weight.
Down Selection Process
After these decisions had been made, all of the 15 ideas underwent down selection. The down selection
techniques used (and in brackets, the number of ideas they each eliminated) were: checking against the
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 9 of 40
specification (3); technical feasibility calculations (3); and a weighted ranking table (7). These are all
individually explored in more detail below.
1) Firstly, all 15 designs were checked against the specification, ruling out any ideas which did not meet
the requirements. This stage eliminated three of the less conventional ideas, with recyclable covers for
the panels and two preventative methods being removed from the fifteen.
2) Basic technical calculations were then carried out to remove any unfeasible ideas. Three more ideas
were eliminated, including the helicopter, which required a power output of 7kW just to remain in
hover; see Appendix B for the full calculation.
3) Finally, a series of pairwise comparisons were performed on all of the main design drivers, in order to
evaluate their relative importance. These were all then employed as weighted evaluation criteria to rank
the remaining nine ideas. A sample of this ranking being applied to three ideas is shown in Table 4.
The top two highest ranked ideas from this table became the final design ideas which were taken forward into
the final development stage. These two ideas are shown in Figure 2 and Figure 3 below.
Table 4: A sample of the weighted ranking table, applied to three design ideas (out of nine in total). Idea 4 was
one of the two final ideas chosen to proceed to the development stage, due to its high weighted score.
Evaluation criteria Wt.* Idea 4 Idea 8 Idea 13
Score/5 Wt. Score Score/5 Wt. Score Score/5 Wt. Score
No. of workers required 3 5 15 4 12 4 12
Skilled labour required 3 5 15 2 6 4 12
Degree of autonomy 3 5 15 3 9 5 15
Ease of use/set-up 3 3 9 3 9 3 9
Power/water consumption 2 4 8 3 6 3 6
Simplicity of design 2 4 8 4 8 4 8
Quality of cleaning 2 2 4 2 4 2 4
Overall adaptability 1 4 4 3 3 2 2
Robustness of design 1 3 3 3 3 2 2
* Wt. = Weighting / Weighted Total: 81 Total: 60 Total: 70
Figure 2: The first final design idea. A rotating scrubber would be
moved around the panel using a system of two detachable pulleys.
Figure 3: The second final design idea. A rail mounted wiper
spanning the vertical distance of the table would move
horizontally across the panels.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 10 of 40
Proposed Solution
The wiper design was ultimately favoured over the pulley system, primarily due to its greater autonomous
capability. Whereas the pulley system could only operate on limited widths of a table at a time before it would
have to be manually reattached to the next adjacent section, the wiper could run continuously across long
spans of a table. However, several refinements still had to be made to resolve remaining issues before a
satisfactory final design was reached, and these are detailed below.
2.4.1 Modifications Made to Initial Design and Resultant Advantages Offered
Vertical motion across the panels was incorporated to resolve potential cleaning
difficulties arising from solely horizontal motion. A uniform downwards pressure must
be exerted by the wiper across the whole vertical height of the panels in order to clean
them effectively, but this would be difficult to achieve due to the panels’ inclination.
Wheels were incorporated to provide this vertical motion, however they still need to
cope with the horizontal motion required across panels, and so omnidirectional wheels
similar to those shown in Figure 4 were chosen to be the most suitable for this purpose.
The device would be guided by a second pair of parallel vertical rails, preventing the
motion of the wheels from deviating from a straight vertical line. These rails would
feature quick-release clips on one end to assist their attachment to the top of the panel,
to ensure they could be handled safely by a single worker, in accordance with
Requirement ⑩.
A feature from one rejected idea, an extendable coil acting as a loaded spring which
allowed the rail span to be varied (Figure 5), was modified into a telescopic approach.
A wheel assembly similar to that found in modern roller coasters was also incorporated
into the final design, to secure the rails against the panel edge.
The fixed wiper was replaced with a detachable rotating brush to help increase cleaning
effectiveness further. The detachability element also allows for brushes of varying
widths to be installed on the device (namely 1 m or 1.6 m to accommodate for both
portrait and landscape panel orientations), which conforms to Requirements ⑤ and ⑥
concerning adaptability.
2.4.2 Potential Problems Arising Due to Modifications
There are geometric issues associated with the pair of vertical rails remaining parallel to each other. The
design must ensure this condition is met, otherwise kinematic constraints will be introduced which will
prevent the device from moving up the rails. Lateral bracing between the rails could fix this issue.
The issue of repeated cyclic conversion of kinetic energy to irrecoverable GPE arises due to the vertical
motion across the panels. This introduces inefficiencies into the device which would increase power
consumption, therefore extra care needs to be taken to ensure that the battery life of the device remains
high enough to be in use for a substantial time before it needs recharging.
Figure 4: A typical
omnidirectional
wheel [13].
Figure 5: An initial
approach to varying
the rail dimensions.
Figure 6: The proposed
wheel assembly.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 11 of 40
3. DESIGN DEFINITION OF PROPOSED SOLUTION
Final Design
Four ultrasonic
sensors to detect
perimeter of
table, allowing
for autonomous
movement of
device.
Housing for cable between main
device and stepper motors in rails.
Retractable reel ensures there is
never any slack obstructing device.
Supplies power from main device
to steppers (in yellow).
Telescopic rails to provide
adaptability for different
table configurations.
Rail struts provide
lateral bracing and
rigidity to eliminate
kinematic constraints.
Hinges and quick
release clips allow
rails to be detached
from main device.
Detachable brush allows
for brushes of different
widths to be installed to fit
panel orientation.
Easy access to inside of
the device allows for
battery replacement
during operation. Handles
on the main housing for
easy pick up.
Interlocking gears to
drive brush. Gear train
for wheels and brushes
are different so they
can rotate at a different
RPM.
Stepper motors placed in
each end of the rail, used
to move a predetermined
distance horizontally
Omnidirectional wheels
allowing movement in
two directions without
compromising surface
cleaning
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 12 of 40
Presentation of Final Design Including Operation Procedure
1•Module on the ground with support rails.
2
•One operator picks up the device and place it on the bottom right of a table.
3
•Rails are hooked on to the top of the panel removing the need to work at height.
4
•Rails are attached to the module with quick release clips.
5
•Rails are hooked on to the bottom of the panel and length adjusted if needed.
6
•Operator presses start on the top of the device.
7
•Device moves up the panel and cleans. Detection of excriment is recorded.
8
•Ultrasonic sensor is activated. The device stops moving.
9
•The stepper motors are activated and the device moves right one panel width.
10
•The device then moves down the panel. Process is repeated.
11
•Repeated until the ultrasonic sensor detects the edge on the panel.
12
•The device moes to the bottom of the panel ready to be removed.
1 2
3 4
5
7 8
9
10
11 12
6
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 13 of 40
Orthographic Projection Showing Key Dimensions
Solar Panel Cleaning Device
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 14 of 40
General Assembly Drawing with Parts List
Solar Panel Cleaning Device
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 15 of 40
4. PROVING CALCULATIONS AND TECHNICAL FEASIBILITY
Structural Analysis
Structural analysis was focused on the critical components of the design such as the rails. Further development
would include analysis and material selection for the reaming components. However, in order to prove the
technical feasibility of the design, this approach was deemed sufficient
4.1.1 Material Selection
The weight of the rails had to be minimised in order to remain safe for one worker to handle them, in
accordance with Requirement ⑧. However, they also had to be as stiff as possible to ensure no kinematic
constraints were introduced into the device. Therefore, the rails were modelled as light, stiff ties for purposes
of material selection. From this, the relevant Ashby material index [9] could be derived, which was:
𝑀 =
𝐸
𝜌
Eq. (1)
This index was used to display all materials with a high stiffness to weight ratio, and therefore determine
which general class of materials would be suitable for use in the rails. Aluminium was chosen due to satisfying
this ratio, in addition to being relatively inexpensive and readily available from most stockists.
A specific grade of aluminium was then chosen, which matched closest to the required material properties.
Since the rails would be circular hollow sections, the aluminium used had to be formable so that it could be
extruded into the necessary shape; it also had to be weldable so that wheel assembly housing could be joined
to either end of the rails. Finally, it had to offer a high corrosion resistance, as the rails would be exposed to
the outside environment. Neither machinability nor strength were sought after characteristics. Using these
criteria, and the aluminium database provided on www.aluminium.matter.org.uk [10], Aluminium 1200 was
selected to be the most suitable grade to use for the rails.
4.1.2 Stiffness Calculation
The rails spanning the vertical distance across panels would experience some deflection under their own self
weight. This must be minimised to ensure no kinematic constraints are introduced to the device as it moves
across them.
Objective: Calculate the worst case deflection/span ratio for the
pair of vertical rails.
Free body diagram of model used, showing all forces:
The UDL resulting from the self-weight of the beam is shown in
Figure 7 to the right.
Assumptions:
The beam is modelled as being flat for simplicity, instead of being inclined at 32° to the horizontal as it
would be in practice.
The beam is fixed at both ends, due to the welds joining the rails to the wheel assemblies.
Figure 7: A free body diagram of the model used.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 16 of 40
The self-weight of the beam can be modelled as a uniformly distributed load.
The worst case deflection occurs when the 1×1.6 m panels are in the portrait orientation, and there are
two panels per table in the vertical direction (i.e. the span of each rail is 3.2 m).
Data used:
Density of aluminium is 2700 kg/m3
Young’s modulus of aluminium is 70 GPa
Circular hollow section used for rails has an inner and outer diameter of 28 mm and 30 mm respectively
Formulae used:
𝜔 = 𝜌𝑔𝐴 = 𝜌𝑔
𝜋(𝑑𝑜𝑢𝑡𝑒𝑟2 − 𝑑𝑖𝑛𝑛𝑒𝑟
2)
4
Eq. (2)
Where: ω = UDL (N/m); ρ = density of aluminium (kg/m3); 𝑔 = acceleration due to gravity (m/s2); A =
area of each rail section (m2); 𝑑𝑖𝑛𝑛𝑒𝑟 = inner diameter of each rail (m); 𝑑𝑜𝑢𝑡𝑒𝑟 = outer diameter of each rail
(m).
𝐼 =
𝜋 (𝑑𝑜𝑢𝑡𝑒𝑟4 − 𝑑𝑖𝑛𝑛𝑒𝑟
4)
64
Eq. (3)
Where: I = second moment of area of each rail section (m4); 𝑑𝑖𝑛𝑛𝑒𝑟 = inner diameter of each rail (m); 𝑑𝑜𝑢𝑡𝑒𝑟
= outer diameter of each rail (m).
𝛿𝑚𝑎𝑥 =
𝜔𝑙3
384𝐸𝐼
Eq. (4)
Where: 𝛿𝑚𝑎𝑥 = maximum deflection at mid-point of beam (m); ω = UDL (N/m); l = span of beam (m); E
= Young’s modulus of aluminium (N/m2); I = second moment of area of each rail section (m4).
Calculations and result:
𝜔 = 2700 × 9.81 ×
𝜋(0.032 − 0.0282)
4= 2.41 𝑁/𝑚
Eq. (5)
𝐼 =
𝜋 (0.034 − 0.0284)
64= 9.59 × 10−9 𝑚4
Eq. (6)
𝛿𝑚𝑎𝑥 =
2.41 × 3.23
384 × 70 × 109 × 9.59 × 10−9= 3.06 × 10−4 𝑚 = 0.3 𝑚𝑚
Eq. (7)
𝐷𝑒𝑓𝑙𝑒𝑐𝑡𝑖𝑜𝑛/𝑆𝑝𝑎𝑛 𝑟𝑎𝑡𝑖𝑜 =
3.06 × 10−4
3.2≈ 1: 10,000
Eq. (8)
Conclusion:
Considering this is a conservative estimate due to assuming the rails lie flat, in addition to taking into account
the worst case deflection possible, this is an extremely small deflection/span ratio which will not introduce
any kinematic constraints into the device.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 17 of 40
Gearbox Calculation
All energy analysis for the proposed solution was performed using a spreadsheet, due to the ease of
automatically calculating a range of values; please refer to Appendix C to see this in its entirety. Numerous
motors were trialled for use in the device by inputting their operating torque, RPM and power rating into the
spreadsheet, and analysing the resultant breakdown of energy expenditure produced. This process allowed a
single, optimised motor to be chosen for the device based on its energy characteristics, which ended up being
an 80 W, 12 V DC motor from RS Components [11] (RS Stock Number: 321-3192).
4.2.1 Force and Torque Required to Move Up Panel
Objective: Calculate the minimum force and torque required for
the device to be able to move vertically up the panel.
Free body diagram of model used, showing all forces:
All forces and the torque acting on a single wheel of the device
are shown in Figure 8 to the right.
Assumptions:
The coefficient of friction between the glass panel surface and rubber device tyres is 0.6.
The device moves up the panels at a low velocity, i.e. the situation can be treated as a static case.
Equivalent inertial force (during initial acceleration) and aerodynamic drag are both negligible.
Rolling resistances on the device tyres are negligible, since they are not pneumatic.
Data used:
Coefficient of friction between panel surface and device tyres is 0.6
Mass of device, excluding rails, is estimated to be 10 kg
Typical inclination angle of panels, given in the Q&A session as 32°
Diameter of device tyres is 100 mm (therefore radius is 0.05 m)
Formulae used:
𝐹 = 𝑚𝑔(sin 𝜃 + 𝜇 cos 𝜃) Eq. (9)
Where: F = required force (N); m = mass of device excluding rails (kg); g = acceleration due to gravity
(m/s2); μ = coefficient of friction; θ = inclination angle of panel (°).
𝜏𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = 𝐹𝑟 Eq. (10)
Where: 𝜏𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = required torque (Nm); r = wheel radius (m).
Calculations and result:
𝐹 = 10 × 9.81 (sin 32 + 0.6 cos 32) = 102 𝑁 Eq. (11)
𝜏𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = 102 × 0.05 = 5.1 𝑁𝑚 Eq. (12)
Figure 8: A free body diagram of the model used.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 18 of 40
Conclusion:
This result alone infers no design implications. It must be followed through with a gearbox calculation in
order to produce a meaningful outcome.
4.2.2 Gearbox Ratio Required
Objective: Calculate a suitable gear ratio which provides enough torque for the device to be able to move
vertically up the panel, whilst maintaining a suitable speed.
Data used:
A torque of 5.1 N is required to move vertically up the panel, as given in Eq. (12)
A desired vertical speed going up the panels of 0.25 m/s is chosen (discussed in Section 4.3)
The DC motor chosen has an output RPM of 8311, and a maximum output torque of 0.092 Nm
Formulae used:
𝐺𝑅 = (
2𝜋
60 𝑅𝑃𝑀𝑚𝑜𝑡𝑜𝑟)
𝑟𝑤ℎ𝑒𝑒𝑙
𝑣
Eq. (13)
Where: = gear ratio required; 𝑣 = desired velocity (m/s).
𝜏𝑎𝑡𝑡𝑎𝑖𝑛𝑒𝑑 = 𝐺𝑅 𝜏𝑚𝑜𝑡𝑜𝑟 Eq. (14)
Where: 𝜏𝑎𝑡𝑡𝑎𝑖𝑛𝑒𝑑 = torque attained with gearbox (Nm); 𝜏𝑚𝑜𝑡𝑜𝑟 = output torque of motor (Nm).
Calculation and result:
𝐺𝑅 =
2𝜋
60× 8311 ×
0.05
0.25= 174
Eq. (15)
Using a combination of two 30/10 and two 50/10 spur gears, a gear ratio of 225 can be achieved:
𝐺𝑅𝑎𝑡𝑡𝑎𝑖𝑛𝑎𝑏𝑙𝑒 = 3 × 3 × 5 × 5 = 225 Eq. (16)
𝜏𝑎𝑡𝑡𝑎𝑖𝑛𝑒𝑑 = 225 × 0.092 = 20.7 𝑁𝑚 Eq. (17)
𝜏𝑟𝑒𝑠𝑒𝑟𝑣𝑒 𝑓𝑎𝑐𝑡𝑜𝑟 =
20.7
5.1= 4.06 𝜏𝑎𝑡𝑡𝑎𝑖𝑛𝑒𝑑 ≫ 𝜏𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑
Eq. (18)
Conclusion:
The reserve factor associated with this torque produced is 4, which is well within an acceptable limit; the
device should never be expected to fail in moving vertically up the panels.
Energy Analysis of Device Operation
When deciding the vertical and horizontal speed for the device to move along the panel, two factors had to
be considered; power consumption, and labour costs. Since labour costs are considerably higher than power
costs (refer to Section 1.4.2), a relatively fast speed of 0.25 m/s for both vertical and horizontal motion was
chosen. Although a slower device would have been more energy efficient, the lower operating cost resulting
from the increased speed supported the business case design driver of Requirement ⑬.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 19 of 40
With the device travelling vertically up and down the tables, GPE losses can be calculated. Two portrait
panels per table in the vertical direction were assumed in this calculation, as this maximum height difference
created the worst case scenario for energy losses. Using the spreadsheet, and 0.25m/s device speed, the mean
energy per panel was calculated to be 445J, with 9% of all energy being expended as irrecoverable GPE.
This inefficiency was accepted as a satisfactory value, since it was likely that the vertical motion would
improve cleaning quality. Additionally, this loss did not make up a significant proportion of the total energy
output; a much greater proportion of energy went into rotating the roller brushes, with an estimated power
consumption of approximately 40W during cleaning. This is required to overcome large friction losses during
rotation, due to the small downwards pressure exerted by the brushes on the panel.
Battery Power Usage
A 12V, 7000mAh, rechargeable NiMH D battery pack from RS
Components [12] (RS Stock Number: 777-0387) was selected to power the
12V, 80W DC motor due to its high capacity. With a current rating of 11A,
the average current supplied to the motor was assumed to be approximately
7A, although in practice this could vary and would need to be measured
empirically for a more precise value. At these estimated levels of current
drawn from the battery pack, it could be expected to deliver enough current
to clean approximately 380 panels before becoming fully depleted.
Despite its high capacity, the battery has a very low duration. There are two feasible solutions to overcome
this problem: connecting more than one battery in series, and charging batteries on site. Taking a portable
1kW petrol generator to the site, and connecting it to a rectifier, would be necessary if recharging was
implemented. In order for this to work, an additional battery pack and a small amount of petrol would need
to be brought with each device. The cost of this additional battery would be outweighed by saved labour costs
by negating the need to wait for charging times. Additionally, the device has been designed for the battery to
be easily removable and replaceable, so this would not present an issue to the workers efficiency wise.
Manufacturing Considerations
It was decided standard parts would be used where possible in order to keep costs low. Details of the
manufacturing processes required to make the few bespoke parts can be seen in greater detail in Sections 5.2
and 5.3. The final design exhibited a high degree of modularity; for example, the brush length and rails could
both be varied depending on the two possible panel orientations.
Issues arising due to the kinematic constraints of the device might hinder its technical feasibility. There are
two major kinematic constraints associated with this design, listed below:
i. Rails and their guiding holes
Because the device guiding holes which slide along the rails are set at a fix distance apart, the distance
separating the rails needs to be constant along its entirety. The prototype included an additional plate at
the top and bottom of the rails (see Appendix G) which fixed the distance between the rails. This, in
Figure 9: The battery used for
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 20 of 40
conjunction with the rungs along the rails, acted as lateral bracing and increased the rails’ stiffness,
resulting in a rigid design and ensuring the concept is technically feasible.
ii. When the wheels are traversing from one module to the next
There may be issues with the rail wheels making a true connection with the second table. During
prototype testing this became an apparent issue. The groove of the wheel running along the side of the
device may not fit straight into the slot of the second table if not perfectly inline.
Actuation and Control Systems Used
Figure 10 illustrates the control system
implemented in the device. The
prototype manufactured proves the
system is feasible, including the feature
of detecting bird excrement via infrared
reflective sensor. The location could
then be recorded by calculating the
distance travelled from the device
starting point. This information could be
passed on to the operator via SMS
message. However, this last step was not
implemented in the prototype and would
need further development before
implementation. Figure 10 also includes
‘clicker switches’ which would be
placed in each rail. These would be
activated by pressure as an alternative to
the ultrasonic sensors if they were to fail.
Figure 11 illustrates the circuit diagram
for the device, as it would be connected
in the design. No problems were
encountered during the use of Arduino
for the prototype project development,
and as a result the use of Arduino has
been included in the final design.
However, it may be more feasible to
replace the Arduino chip with a bespoke
Integrated Circuit for use in the final
design, as these are better suited to being
mass produced.
Figure 10: The control system used by the device
Figure 11: Circuit diagram for device with Arduino
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 21 of 40
5. COST ANALYSIS
For sources, detailed notes, and a full list of the assumptions used for all the tables below, see Appendix F.
Comparison to Other Methods
To show that the device will be competitive against other solutions currently on the market, the ranking table
above was created, considering three aspects of importance to customers. The average weighted rank
considers the ranking in cost to be twice as important as the other factors. The device is shown to be much
cheaper and easier to set up relative to other solutions.
Device Manufacture Cost
Shown above is the full parts list as per Section 3.3, with all associated costings calculated, giving a total cost
of £2,271 for each device. The parts have been split into two sections, those that can be sourced directly to
an external supplier (see Appendix F), and those that will need to be manufactured according to the following
Section 6.3. Higher quality parts have been sourced where possible, and the expense of £1,110 on machining
the parts should ensure that Requirement ⑭ is met.
Table 5: A table comparing a range of the most popular cleaning methods. See Appendix F
Table 6: The full costing for the manufacture of our device. See 6.3 for a breakdown of machining
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 22 of 40
Machining Costs
Running Costs
When on site, the device will spend 34% of its time being manually moved between tables, assuming a table
of 20 panels and a moving time of 100 seconds. As a result, one employee can be expected to manage the
operation of three devices at a time. With the assumption of a half hour travel time to and from the site each
day, a 35 hour working week, and 14.4 seconds spent cleaning each panel, the cost per panel is only 3.81p.
This creates a profit of 16.19p per panel, confirming that the price of 20p is viable as per Requirement ⑬.
Payback Period
Using the assumptions listed above, a total of 1500 panels can be cleaned by each device per day in use, for
4500 total. With the manufacturing cost for each device known, a payback period can be calculated; for the
full table see Appendix F. The profit over time has been marked in green below. With the start-up cost being
three devices (£6812), only 9.5 days are required, assuming non-stop cleaning for six hours per day. To mirror
the situation of solar panel cleaning companies, an additional graph, for their theoretical existing product with
a cost only 5p greater, has been added, with no start-up cost assumed. Even with the cost to implement the
design, it has resulted in more profit than its previous method in only 31 days.
Table 7: A brief guide to the machining and costs required for each part. See Appendix F for a more detailed breakdown.
Table 8: A breakdown of the running costs to run our device on a daily basis.
Figure 12: A graph showing expected payback periods and marginal profits, with three devices in operation.
Overtakes after 31
days
Payback period of 9.5 days
-10000
-5000
0
5000
10000
15000
20000
25000
30000
0 10 20 30 40 50
Pro
fit
(£)
Days in Use
New Design Compared With Existing Costlier Method
Example
System With
Cost
8.8p/Module
Our Device
With Cost
3.8p/Module
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 23 of 40
6. EVALUATION
Evaluation against Specification
Table 9 evaluates the final design against the product specification. This process highlighted areas of
uncertainty which would need further development if the concept was taken further.
Table 9: Meeting The Specification Key: ‘R’ = Requirement number from Specification; Y/N/P/U = Yes/No/Partially/Unknown
R Met? Discussion
1 P Having no access to the 265w Suntech panel was a hindrance. However, the prototype is capable of cleaning all areas of
the demonstration panel. As the device doesn't use water bird excrement and tough dirt might still be an issue.
2 Y The device can move autonomously around demonstration panel will ease. Therefore it can be assumed that it will meet
this specification point.
3 P
Like with Requirement 1, this cannot be fully tested without the 265w Suntech panel. However upon inspection of the
demonstration white board after device operation, no visible flaws could be seen. Additionally, the loads exerted by the
device are below the maximum allowed on the panel as declared in [1].
4 Y
The device cleans without water. It is able to clean all dust off the panel, however it is unable to clean some bird
excrement. It will be described in 7.4 as an improvement that will be added to the device in order to counter this. For
now, a reflectance sensor is being used to identify where the excrement is and tags it on a counter.
5 Y
The two driving factors for the design were cost and modularity. By having extendable rails the two identified lengths
can be catered for and cleaned. By having replaceable wheels, like different heads for a screwdriver the necessary wheel
design can be selected for the appropriate support structure. This wish was fulfilled.
6 Y As previously mentioned, the ability to extend the rails and swap the rail wheels means the device is capable of cleaning
between panels with vertical length 2.6m - 3.2m (all commercial panels). This wish was fulfilled.
7 N This specification point was ruled out early in the design process as mentioned in 3.2. Instead the device is manually
moved from one table to the next.
8 U Unable to test this as the prototype is not a fair reflection of the final design in terms of build quality.
9 Y
Both the mass and moment of inertia of the device have been set to an acceptable level with regards to LOLER
legislation [5]. Heavy components are all at the centre of the device, whilst the rails are kept lightweight. The only
components which increase the overall inertia significantly are the steppers used to drive the rail.
10 Y Specification point fulfilled.
11 Y Dimensions can be seen from the working drawings that this module fits into the selected van.
12 U This cannot be checked currently as we have not made the final device. However the prototype has been designed to be
as rigid and structurally sound as possible. If needed a transportation box could be manufactured to be placed in the van.
13 Y As shown in Section 6.4 and 6.5
14 U
Currently we do not have the final design so cannot test this. Provided the system is taken care of when moving it from
transport vehicle to cleaning the device should not fail. The most likely part to fail is the rails do to bending. However
added struts increase rigidity. Replacement of brushes would extend device lifetime.
15 P
Due to the electronics being able to operate within these temperatures, the most likely issue to do with temperature
would be kinematic constraints. The rise in temperature could make the rails expand meaning that the “guide holes” on
the device would need to be able to cater for this. Another kinematic constraint issue could be the gears inside the
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 24 of 40
R Met? Discussion
gearbox expanding causing gear locking. Material selection would need to be further investigated here for a further
iteration.
16 Y No fluids are supplied to the device. This desire was fulfilled.
17 Y
The use of relatively low power motors (due to low mass of the device) means that noise levels during operation will be
below 85dB. The generator used to recharge the battery may need to be looked at further for this may produce
substantial noise.
Commercial Feasibility
As has been discussed in Section 6, with the price per panel set at 20p and the cost at only 3.81p, the profit is
16.19p per panel. Not only has this satisfied Requirement ⑬, but it has achieved profit at a significant margin,
while remaining cheaper than the other cleaning solutions on the market. Although the manufacturing cost of
£2,271 for each of the three suggested devices could be seen as unappealing to more frugal investors, the fact
that only 42,000 panels (see Appendix F) must be cleaned to repay this £6,812 investment can make this a
viable venture for more local businesses. Thinking critically about the assumptions for these calculations, the
significant buffer given by the 16.19p profit per panel means that even if the internal costs for a company are
wildly different to the predictions, the solution can be remain confident of being economically viable.
Improvements and Uncertainties
From the conclusions drawn in table 9 and information gathered during the prototype build, areas of
uncertainty and improvement were highlighted. Table 10 elaborates on the further development needed.
Table 10: Issues and uncertainties with suggested improvements. Key: I/U = Issue/Uncertainty no.; Apx = Appendix
I/U Issue or Uncertainty Development Needed Diagram
1
Effective cleaning of bird
excrement
Development of a modular/add on water system which deploys water when
excrement is detected would solve the issue. n/a
2 Ultrasonic sensors failing. Integration of emergency trigger switches in the end of the rails to stop
device if sensors fail. Prototype code has proved it is feasible. n/a
3 Kinematic constraints of the rail. Inclusion of rungs between the rails help. However, the prototype proved that
one solid piece (rather than two) at the end of the rail improves stability. Apx G: 1
4 Low battery capacity
Operator could bring spare battery packs and a portable ~1kW petrol
generator to site connected to a rectifier, so that a full battery is always
available at any one time
n/a
5
Small strip of panel surface is not
cleaned due to gaps in the brush.
De-align the front and back brackets which mount the brush bearings to the
device, ensuring front and back brush do not miss the same 'strip' of panel. n/a
6 Cantilever solar panel frames. Development of the wheel assembly on rail would solve this issue. Apx G: 2
7
Gaps in tables might stop the
device from moving.
Larger wheels running along the panels might be able to move across smaller
gaps. Designs for such components would need to be developed. n/a
8
Current telescopic arm design
might not be technically feasible.
Prototype building highlighted an alternative method. Rail endings should
move freely along rail with fasteners to hold the ends in the correct position. Apx G: 1
9
Technical feasibility of the cable
housing hasn’t been demonstrated.
Build a prototype demonstrating the cable reel can hold the cable under
tension at all time, ensuring it retracts when needed. n/a
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 25 of 40
Overview and Conclusion
The two driving objectives for the design were modularity (Requirement ⑤ and ⑥), and reducing cost. As
a result the design is able to be used for a comparatively low cost compared to market contenders. The
elimination of water and the low mass of the device reduce consumable costs at the expense, respectively, of
not cleaning bird excrement and not being able to house a larger battery. This had to be done to compromise
for low cost in line with specification point ⑬. For sites with a lot of bird activity, it is likely that the use of
the device will be sub-optimal unless the addition of a water compartment is included as mentioned in Section
7.4.
Despite these flaws, the information stated in the report suggests that the design altogether remains
commercially and technically feasible. Table 9 illustrates that the device has met most of the design
requirements, and the objective evaluation listed here reflects its potential success in industry. In Table 10,
the areas in greatest need of improvement are highlighted, making development on the design a simple and
viable path to explore for the future.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 26 of 40
BIBLIOGRAPHY
[1] Suntech Power, “Multicrystalline products,” 21 April 2014. [Online]. Available:
http://shangde.fanyacdn.com/imglibs/files/stp265_wem(mc4_265_260_255).pdf. [Accessed 29
January 2015].
[2] EvoEnergy, “Case studies,” 16 July 2012. [Online]. Available:
http://www.evoenergy.co.uk/business/case-studies/. [Accessed 29 January 2015].
[3] Water Direct, “Water Supplies,” 23 October 2012. [Online]. Available: http://www.water-direct.co.uk/.
[Accessed 05 February 2015].
[4] Hyundai Power Equipment, “Hyundai HY1000Si-LPG Dual Fuel 1kW Inverter Generator,” 04
September 2012. [Online]. Available: http://hyundaipowerequipment.co.uk/hyundai-hy1000si-lpg-
dual-fuel-1kw-inverter-generator/. [Accessed 05 February 2015].
[5] GOV.UK: Health and Safety Executive, “Lifting equipment at work,” 12 March 2013. [Online].
Available: http://www.hse.gov.uk/pubns/indg290.pdf. [Accessed 03 March 2015].
[6] MV Commercial Ltd., “Box Vehicles,” 19 December 2010. [Online]. Available:
http://www.mvcommercial.com/box-vehicles.html. [Accessed 04 February 2015].
[7] “MIL-STD-810: Environmental Engineering Considerations and Laboratory Tests,” United States
Military Standard, 2008.
[8] GOV.UK: Health and Safety Executive, “Noise Regulations,” 20 November 2012. [Online]. Available:
http://www.hse.gov.uk/noise/regulations.htm. [Accessed 07 February 2015].
[9] M. Ashby, in Materials Selection in Mechanical Design, Butterworth-Heinemann, 1992, p. 109.
[10] aluSELECT, “Wrought Alloy Applications,” 01 October 2002. [Online]. Available:
http://aluminium.matter.org.uk/aluselect/01_applications.asp. [Accessed 18 March 2015].
[11] RS Components, “DC Motor, 80.16 W, 12 V dc, 6.35mm Shaft Diameter, 8311 rpm,” 6 October 2014.
[Online]. Available: http://uk.rs-online.com/web/p/dc-motors/3213192/. [Accessed 15 March 2015].
[12] RS Components, “NiMH D HT × 10 7000mAh 12V Pack,” 06 October 2014. [Online]. Available:
http://uk.rs-online.com/web/p/d-rechargeable-battery-packs/7770387/. [Accessed 15 March 2015].
[13] Omni-directional wheel image, [Online]. Available: http://www.robotshop.com/en/100mm-
omnidirectional-wheel-brass-bearing-rollers.html. [Accessed 23 March 2015].
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 27 of 40
APPENDIX A – GALLERY OF 15 REJECTED IDEAS
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 28 of 40
APPENDIX A – GALLERY OF 15 REJECTED IDEAS
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 29 of 40
APPENDIX A – GALLERY OF 15 REJECTED IDEAS
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 30 of 40
APPENDIX A – GALLERY OF 15 REJECTED IDEAS
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 31 of 40
APPENDIX B – IDEA DOWN SELECTION
Sample calculation for Helicopter Idea 12: Actuator Disk Theory
Objective: Calculate the minimum power output for the helicopter to remain hovering above the panels.
Assumptions:
Thrust loading and velocity are uniform across the rotor disk
Viscous effects such as drag are ignored
Air is incompressible
Data used:
Helicopter mass, including mass of motor and water supply tank, is estimated to be 40 kg
Length of each rotor blade is estimated to be 0.4 m
Density of air at sea level is 1.225 kg/m3
Formula used:
𝑃 = √𝑇3
2𝜌𝐴
Eq. (19)
Where P = power output required for hover (W), T = thrust from rotor blades (equal to the total weight of the
helicopter) (N), ρ = density of air at sea level (kg/m3), A = disk area swept out by rotor blades (m2).
Calculation and result:
𝑃 = √(40 × 9.81)3
2 × 1.225 × 𝜋 × 0.42 = 7004 𝑊
Eq. (20)
A list of all design ideas eliminated as part of the down selection process. Idea 4 was the final one chosen.
Idea # Main Reason for Rejection
1 Repeated vibrations induced may cause damage or fatigue to the panels
2 Design is too complex; likely to have many problematic maintenance issues and/or high possibility
of breaking down
3 Actuation systems required would be too complex to incorporate into design; not very feasible
5 Tracks prevent full cleaning coverage of panel
6 Issues due to manoeuvrability due to large turning circle which would be required
7 Operating cost of running pump and filter system continuously would be too high
8 Too much power would be required to lift hovercraft off surface of panel
9 Orientation of panel may present issues; requires lots of pre-installation
10 Would not be autonomous as continuous human interaction would be required
11 Wasteful in long term as polystyrene would degrade so consumable expenses will be high
12 Too much power would be required to provide necessary lift (see below)
13 Three-stage telescopic handle would be very difficult to manufacture
14 Design offers no advantages over current methods of cleaning
15 Would be difficult to clean whole area of panel thoroughly; not very feasible as a large torque
would be required to swing mechanism
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 32 of 40
Conclusion:
Clearly, a required power of 7 kW is unfeasible when compared to other cleaning methods, which only require
power on the order of a few watts to operate effectively. This would incur massive running costs due to the
large amounts of consumables required, rendering this idea not viable for a business case.
APPENDIX C – SPREADSHEET USED IN ENERGY ANALYSIS
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 33 of 40
APPENDIX D – COMPONENTS USED FOR PROTOTYPE
0.00 10.00 20.00 30.00 40.00 50.00
Ultrasonic Sensor
Normal Motor
Stepper Motor
Micro Switches
Omnidirectional Wheels
Rail's bar 3m Axles
Gears
Belt
Belt Pulleys
Bearings 20mm (Brushes)
Bearings 10mm (Axles)
PVC Pipe for Brushes
Components Used For Prototype Costing
Quantity
Price/Unit (£)
Total Price (£)
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 34 of 40
APPENDIX E – SOFTWARE CODE
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 35 of 40
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 36 of 40
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 37 of 40
APPENDIX F – COST ANALYSIS SOURCES AND ASSUMPTIONS
To obtain the price per panel for these cleaning methods, we posed as a representative of the 30,000 module
Hullavington solar farm in the UK (postcode SN14 6ED), and requested quotes from a range of companies
for each other the methods. This is summarised in the table below.
For the time taken per module and relative difficulty to set up, information was gathered from the online
discussions with the company representatives above. In addition, an employee of the solar farm industry who
installs panels on a daily basis, Steven Smith, was contacted for his verdict and opinion on the times we had
generated from the email discussions. These were then adjusted to give the values in the table above.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 38 of 40
In the table above, the sources for the individual cost and retailer have been numbered above, and correspond
to the sources in the table below. The mass column above was calculated from CAD files for those parts that
would be machined, or the masses provided by the suppliers for those parts that were bought directly. For
several items, no mass was provided online, and so where a star (*) is marked next to the mass, this value has
been estimated based on similar products. The material cost above is not a generic price found online, but is
the validated cost as sourced from the suppliers in the table below. The machining costs shall be discussed in
a subsequent table.
Solar Panel Cleaning System
Design Project II: Exercise 3
MEng Engineering Design Year 2
27 March 2015
Arthur Mallet Dias, Harry Garstka,
Loic Gueganton, Richard Stone, Harri Worman
Page 39 of 40
For the machining costs in the report (Table 7), the work required from the external machinist was considered
to be either skilled or unskilled. Skilled work was charged at £40 per hour, and unskilled at £20. the own
estimates and assumptions from the familiarity with the part designs was used to give a time required to
complete the part.
For Table 8, looking at the running costs, no new sources were added but a number of assumptions and
references were used. An assumption of £20 per hour was made for the labour, and a cost of petrol of £25 for
an hour of driving. As the work is unskilled, both of these terms are obviously overestimated, and this was
done to ensure we weren’t basing the commercial viability off assumptions that any possibility of being
flawed. The electricity cost was referencing Section 1.4.2 where it had previously been determined. The
device was assumed to be in use for six hours per day, with an hour travelling time, and with a speed per
panel of 14.4 seconds while in use. The size of the farm was irrelevant to the calculations here as the device
was already assumed to be in constant use.
For the payback period graph Figure 12, no additional sources were used here either, but the assumptions
were identical to Table 8 (see paragraph above). Cleaning 1500 panels per day (per six hours, being at 14.4
seconds per panel), the revenue was calculated by multiplying this number of panels by 20p. The cost was
simply this number of panels multiplied by 3.81p. The profit was then simply the difference between the two,
as expected. The start-up cost of £6,812 was then subtracted from this profit to give the profit over time. For
the example device used by solar cleaning companies already, the same process was used, as the device was
cleaning at the same speed, but the cost was 8.81p per panel, with no start-up cost. As a result, profit increases
slower, but starts at £0 as opposed to -£6,812, eventually being surpassed by the design at 31 days.