GOVERNMENT OF BANGLADESH ADB KfW IFAD COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities within the overall CCRIP Design] Volume I: Main Report Asia and the Pacific Division Report No: ------ November 2012

Transcript of Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT...

Page 1: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

GOVERNMENT OF BANGLADESH

ADB – KfW – IFAD

COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP)

Final Project Design Report [for IFAD funded Activities within the overall CCRIP Design]

Volume I: Main Report

Asia and the Pacific Division

Report No: ------

November 2012

Page 2: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

ii

Table of Contents

Fiscal year iii Currency and Equivalents iii Units and Conversions iii Abbreviations, Acronyms and Glossary iii Map of the CCRIP Project Districts vi Executive Summary vii

Design and Monitoring Framework (DMF or Logframe) x I. STRATEGIC CONTEXT AND RATIONALE .................................................................. 1

A. Background .............................................................................................................. 1 B. Country and Rural development and poverty context .................................................... 2 C. Rationale ................................................................................................................. 4 D. Scaling-up ............................................................................................................... 9

II. PROJECT DESCRIPTION ....................................................................................... 10 A. Project area, poverty and target group ...................................................................... 10 B. Project Goal and Objective (“Impact and Outcome”) ................................................... 12 C. Components ........................................................................................................... 12 D. Lessons learned and compliance with IFAD policies ..................................................... 16

III. PROJECT IMPLEMENTATION ................................................................................ 18 A. Approach ............................................................................................................... 18 B. Organisational Framework ....................................................................................... 19 C. Planning, monitoring and evaluation, learning and knowledge generation ...................... 20 D. Financial management, disbursement, procurement and governance ............................ 23 E. Supervision ............................................................................................................ 29 F. Risk identification and mitigation .............................................................................. 29

IV. PROJECT COSTS, FINANCING, BENEFITS ............................................................. 30 A. Project Costs .......................................................................................................... 30 B. Summary benefit and economic analysis .................................................................... 31 C. Sustainability ......................................................................................................... 34

KEY FILE TABLES

Table 1: Rural poverty and agricultural sector issues

Table 2: Organisational capabilities matrix

Table 3: Complementary donor initiative / partnership potential

Table 4: Target group priority needs and project proposals

Table 5: Stakeholder matrix / project actors and roles

Volume II: Annexes

1. Country and Rural Context Background 2. Poverty, Targeting and Gender

3. Country Performance and Lessons Learned 4. Value Chain Development and Infrastructure 5. Detailed Project Description

6. Review of Rural Infrastructure Needs Under CCRIP 7. List of community (village) markets and union/village roads selected for development 7A. Project Cost and Financing 7B. Summary and Detailed Cost Tables 8A. Structural Design: Road Infrastructure 8B. Detailed Cost: Roads Infrastructure 8C. Unit Costs: Market Infrastructure

9A. Structural Design: Market Facilities 9B. Structural Design: Ghats

Page 3: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

iii

9C. Detailed Costs: Market Facilities

10. Institutional Aspects and Implementation Arrangements 11. Compliance with IFAD policies 12. Planning, Monitoring, Evaluation and Knowledge Management

13. Financial Management and Disbursement Arrangements 14. Procurement 15. Beneficiary Calculation 16. Economic And Financial Analysis 17. Draft Project Administration Manual 18. Contents of Project Life File

Page 4: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

iv

Fiscal Year

1 July to 30 June

Currency and Equivalents Currency Unit = Bangladesh Taka (BDT) October 2012 USD 1.00 = BDT 82.00

Units and Conversions 1 lakh (lk.) = 100,000 1 crore (cr.) = 10,000,000 1 acre = 0.407 ha 1 decimal = 0.01 acre

Abbreviations, Acronyms and Glossary

ADB Asian Development Bank

ADP Annual Development Plan

AE Assistant Engineer

Aman Main rice crop grown during the rainy season

Aus Early rice crop grown during the early part of the rainy season

BARI Bangladesh Agricultural Research Institute

BBS Bangladesh Bureau of Statistics

BC Bitumen carpeted

Boro Irrigated rice crop grown during the winter season

BIDS Bangladesh Institute of Development Studies

BRRI Bangladesh Rice Research Institute

BUET Bangladesh University of Engineering and Technology

BWDB Bangladesh Water Development Board

CARE An international NGO

CBO Community Based Organisation

CC Climate Change

CCP Community Collection Point

CDSP Char Development and Settlement Project

Char Newly accreted land

COSOP Country Strategic Opportunities Paper (IFAD)

DAE Department of Agricultural Extension

DC Deputy Commissioner (head of district administration)

DD Deputy Director

DFID Department for International Development (UK)

DLS Department of Livestock Services

DPHE Department of Public Health Engineering

DTW Deep Tubewell

EIRR Economic Internal Rate of Return

ERD Economic Relations Division

FAO Food and Agriculture Organisation

FY Financial year

GB Grameen Bank

GDP Gross Domestic Product

Ghat A Bangla word of boat landing boat platform

GMC Growth market centre

GoB Government of Bangladesh

HBB Herringbone brick bond

Haat A Bangladesh word for a rural market or bazaar, which assembles everyday with small number of buyers/sellers but meets twice a week in a large-scale where buyers/sellers from wider areas converge to do business

Page 5: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

v

hh/HH household

HIES Household Income and Expenditure Survey

HILIP Hoar Infrastructure and Livelihood Improvement Project

IFAD International Fund for Agricultural Development

IRRI International Rice Research Institute

JICA Japan International Cooperation Agency

Khal Drainage channel (natural or man-made)

Kharif Summer cropping season

LCS Labour Contracting Society

LGD Local Government Division (of MLGRD&C)

LGED Local Government Engineering Department

M&E Monitoring and Evaluation

MIDPCR Market Infrastructure Development Project in Charland Regions (IFAD)

MFMSFP Micro Finance for Marginal and Small Farmers Project (IFAD)

MFTSP Micro Finance and Technical Support Project (IFAD)

MFI Microfinance Institution

MIS Management Information System

MLGRD&C Ministry of Local Government Rural Development and Cooperatives

MMC Market Management Committee

MOF Ministry of Finance

MoU Memorandum of Understanding

MTR Mid-Term Review

NATP National Agricultural Technology Project (World Bank – IFAD)

NGO Non–Governmental Organisation

O&M Operation and Maintenance

p.a. per annum

PCR Project Completion Review

PD Project Director

PAM Project Administration Manual

PKSF Palli Karma-Sahayak Foundation, Government established apex funding agency for MFIs/NGOs

PMO Project Management Office

PSC Project Steering Committee

PY Project Year

QA Quality Assurance

Rabi Winter cropping season

RCC Reinforced cement concrete (e.g. road)

RIMS Results and Impact Management System

SAE Sub-Assistant Engineer

SCBRMP Sunamganj Community Based Resource Management Project

SDC Swiss Development Cooperation

TA Technical Assistance

UE Upazila Engineer

UNO Upazila Nirbahi (Executive) Officer

UP Union Parishad

Upazila Sub-district

USAID United States Agency for International Development

WFP United Nations World Food Programme

XEN Executive Engineer (of LGED)

Page 6: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

vi

Map of the CCRIP Project Districts

Page 7: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

vii

Executive Summary

1. Background: The Coastal Climate Resilient Infrastructure Project (CCRIP) jointly funded by ADB, KfW, IFAD and Government of Bangladesh is a merger between the former Sustainable Market Infrastructure for Livelihoods Enhancement project (SMILE) of IFAD and the Climate Resilient Infrastructure Improvement in Coastal Zone Project (CRIICZP) of ADB/KfW. The overall design of CCRIP project had already been accepted by all three

donor agencies and the Government, and approved by ADB Board in September 2012. ADB, KfW, and IFAD have signed an aide memoire on June 19, 2012 accepting the overall scope, financing and implementation aspects of the project. Later on, the Government confirmed the aide memoire. This project design report (PDR) presents the final design of IFAD funded activities as part of the overall project design. CCRIP is the first of two projects to be funded under the new Country Strategic Opportunities Program (COSOP)

2012–2018 of the International Fund for Agricultural Development (IFAD).

2. Rationale: Bangladesh is expected to be among those countries to be seriously affected by the adverse effects of climate change. Today, Bangladesh is already one of the most disaster prone countries among the least developed countries. Severe flooding and cyclones during the monsoon season is regularly causing serious damage to crops and

properties, with severe adverse impact on rural livelihoods. Climate change is expected to increase the severity and frequency of cyclones and floods causing widespread destruction

of land, roads, houses and other assets. In addition to the adverse climate change effects, rural producers, especially the poor and the small producers, suffer from two sets of constraints that limit the development of their livelihoods: a) poor road and market infrastructure that limits access to larger markets, increases cost of production because of higher input and transportation costs, and lowers prices due to remoteness; and b) limited access to demand-driven financial services, especially seasonal agricultural credit and loan for microenterprises, and limited access to good technology and inputs, knowledge and

support services such as vaccination services for livestock etc.

3. CCRIP will build climate resilient road infrastructure, cyclone shelters, and improve access to market to address acute poverty and climatic vulnerability in 12 south-western districts. By joining the ADB/KfW funded project and forming the CCRIP, IFAD will be able to render the former SMILE to a climate smart project in addition to the focus on connectivity and accessibility for smallholder producers. This is fully aligned with the COSOP objectives 1

and 2.

4. Currently, the above two sets of constraints are being addressed at a comparatively small scale by two IFAD-funded projects: MIDPCR for rural infrastructure development; and FEDEC for agricultural and ME lending, and value chain development. The CCRIP project will scale-up MIDPCR‟s successful experiences mainly in rural roads (Union and village roads), boat landing platforms (ghats) and community (village) markets which are strategically located in the designated project areas. The experiences of MIDPCR, CDSP (I,

II, and III), SCBRMP and similar rural infrastructure development projects have demonstrated that paved roads and markets improve communication and benefit households income through higher farm prices, increased wages, enhanced investment in agri-business and trade, better access to higher quality inputs, support services, credit and reduced cost of production and transport. Access to child education and primary health care also improves due to better transport facilities, especially in wet season. Overall, protection and enhancement of livelihoods is greatly expected. Moreover, MAPP, which will

be designed as the follow-on project of FEDEC in 2014 to scale up the value chain and financial services development in the same area and to complement CCRIP “hardware” investments. CCRIP and MAPP each, will be implemented by specialized agencies: LGED

for infrastructure and PKSF for rural finance and value chain development.

5. CCRIP Project Area: The IFAD funded activities under CCRIP will be implemented in 32 Upazilas of 12 South-western districts (Satkhira, Khulna, Bagerhat, Gopalganj, Madaripur,

Shariatpur, Pirojpur, Jhalkati, Barisal, Bhola, Borguna, and Patuakhali). These district are known as very poor, least developed and vulnerable to natural disasters such as tidal surges, cyclones, and floods. The 32 Upazilas have been selected on the basis of seven indicators related to poverty, vulnerability, remoteness and quality and scale of infrastructure. IFAD expects that activities (“sub-projects”) funded by ADB (Upazila roads and growth centre markets) and KfW (cyclone shelters and disaster preparedness capacity building) should also be implemented in these 32 upazilas to maximize project impacts.

Page 8: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

viii

6. Target groups and expected benefits: The project target group comprises the population in

the catchment areas of project markets and user of roads, in particular, small and marginal farmers, small traders and micro-entrepreneurs, landless people and poor women. It is estimated that 3.5 million people will benefit from the project. Direct

beneficiaries include 5,000 people contracted to LCS (of which at least 80% will be very poor women, with priority for women-headed households); 162,400 traders in the markets under the project; 52,600 transport owners; and 235,000 households living in the areas of influence of roads/markets. The benefits will come in the form of being able to use all weather communications, increased sales, reduced cost of transportation, higher farm price, future investments opportunities in agri-business and trading, and improved quality of agricultural inputs and support services. The improved road access is expected to

encourage private investors to increase investments and service providers to expand into the project areas.

7. The project goal (ADB: Impact) of CCRIP is to achieve „Improved livelihoods (higher incomes and food security) for poor households (women and men) in selected Upazilas of 12 coastal districts”. The development objective (ADB: Outcome) is to achieve “enhanced climate resilience of coastal road and market infrastructure and people in

selected Upazilas of 12 project districts”.

8. Components: The project will have the following three components:

1. Improved Road Connectivity: The outcome of this component is „Improved road connectivity for men and women living in project Upazilas to access markets and social services‟. Under this component, 130 km upazila road (ADB funded), 501 km union and village roads (IFAD funded) along with associated small bridges and culverts (2,455 meters) will be built. Roads will adopt climate resilient and or climate

adaptation features. Roads that benefit highest the number of people, connect project markets (see below) and other important markets and remote villages will receive high priority.

2. Improved Market Services: The outcome of this component is „Enhanced marketing of farm and non-farm produce in project markets‟. This component will build/improve physical markets (common shed, fish shed, open paved/raised area, women section, toilet bloc, internal drainage etc), build „commodity collection points (CCP), build boat

landing platform (ghats), form market management committees (MMCs), and create employment for the poor women (LCS members). The plan is to develop 88 growth

centres and large rural markets (ADB funded), and 197 community (village) markets, 5 CCPs. 15 women sections and 38 boat landing platform (IFAD funded), and for LCS group and MMC management system.

3. Enhanced climate change adaptation capacity: The outcome of this component is

„Rural communities and local authorities are able to cope with volatile climate events and meet their basic needs during climatic shocks.‟ The following activities, funded by KfW, are planned under this component: a) construction or extension of 15 cyclone shelters; b) improvement of 10 existing shelters; c) upgrading 15 km access tracks; and d) complementary support measures to enhance capacity for disaster preparedness. In addition, IFAD will fund the training of LCS in construction skills and on social issues, and MMC members on planning, supervision of works and

management of the markets.

9. Project management: A Project Management Office (PMO) at the LGED headquarters in Dhaka and three regional project offices (RPOs) located in Khulna, Madaripur and Barisal district headquarters will be established. A technical assistance team will assist the LGED

officials in Dhaka, 12 districts and upazila level to implement the project. The PMO will be responsible for implementation of all project activities, supervision and monitoring, quality control and project progress, train staff members, and gather lessons and disseminate

knowledge generated from the project. IFAD and ADB will jointly monitor and supervise the project.

10. Selection and implementation of IFAD funded infrastructure: It is important to note that IFAD funded union and village roads and community (village) markets have already been selected through a rigorous process and are part of the approved DPP (“development project pro-forma”, the Government‟s project report). The PMO with the help of XENs and Upazila

engineers will finalize cost estimations for individual roads before tendering out and developing a master plan for the development of each selected market. Basic engineering design and

Page 9: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

ix

typical unit cost estimation for roads and markets have already been completed. The selected

roads and markets are ready for development. The PMO will prepare annual implementation plan only. No additional selection exercise will be necessary unless a unforeseen incidence occurs. Since the selection of IFAD funded roads and markets is already final they will not be

linked with the selection of ADB funded subproject. It is clearly emphasised that this approach aims at avoiding any delays of implementation of IFAD funded activities due to subprojects‟ selection and related studies of ADB/KfW funded activities.

11. Project costs and financing: CCRIP‟s total cost of US$150.0 million will be financed by IFAD for up to US$40.5 million during the current PBAS period 2013-2015. The additional financial needs will be, as applicable, funded as a second loan from the 2016-18 PBAS and will be submitted to the Executive Board in 2016 for approval. The current co-financing for CCRIP will

be in the amounts of US$50 million by ADB, US$8.8 million by KfW and US$31.2 million by GoB. ADB‟s funding breaks up as follows: US$20 million from ADB‟s Special Funds resource (loan), US$20 million through ADB Strategic Climate Fund loan and a US$10 million grant. KfW will provide its funding to the project of as a grant. The Government of Bangladesh will finance LGED staff salaries and operating costs, land acquisition and resettlement costs as well as identifiable taxes and duties as no taxes or duties could be financed out of the proceeds of the

IFAD loan.

12. Timeframe: The anticipated duration of the project would be six (6) years beginning July 2013.

13. Project implementation and coordination: The project implementation will be led by the Local Government Engineering Department (LGED) of the Ministry of Local Government Rural Development and Cooperatives (MLGRDC). Overall coordination will be through an Inter-Ministerial Steering Committee, chaired by the Secretary of the Local Government Division of

MLGRDC and represented by relevant line ministries and agencies including the Economic Relations Division (ERD) of the Ministry of Finance. The project will also participate in District and Upazila Development Coordination Committees.

14. Sustainability and exit strategy: The roads will be maintained beyond project period by LGED with resources from the Government. The markets will remain the property of the Government and be managed by the MMCs, whose head is the Union Parishad chairman. Based on the experience of MIDPCR and similar infrastructure projects, project benefits are

expected to become sustainable when the local rural economy is linked and integrated with national economy due to improved connectivity in terms of infrastructure and market

networks.

Page 10: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

x

CCRIP: Design and Monitoring Framework (DMF or Logframe)

Design Summary Performance targets and indicators Monitoring Mechanism & Information Sources

Assumptions

Project Goal [ADB: Impact]

Project Goal

Improved livelihoods (higher incomes and food security) for poor households (women and men) in selected Upazilas of 12 coastal districts

ADB - by 2021:

Household incomes in project areas increased by 20% in 2012 prices (2012 baseline: Tk70,000)

IFAD - by 2018 (from baseline):

20 % increase of households reporting improvements in household asset ownership index (RIMS)

30 % reduction in the prevalence of child malnutrition (RIMS)

60 % increase in incomes in 50%of poor households from a range of farm, fishery and non-farm sources, disaggregated by sex

Bangladesh Bureau of Statistics

Multiple Indicator Cluster Survey (MICS) of the RIMS surveys

Impact surveys at baseline, mid-term and completion

Qualitative assessment (PRA) with target HHs in project

Upazilas/Unions/Villages.

Development objective [ADB: Outcome]

Enhanced climate resilience of coastal road and market infrastructure and people in selected Upazilas of 12 project districts.

[Project Target: Overall approximately 600,000 HHs; 3.5 million people]

By 2018:

< 5# of days of inundation of infrastructure reduced (baseline 20 days)

60 % more beneficiaries reporting improved food security, by women/men (RIMS)

50 % reduced loss of lives and assets during disaster

Independent evaluation of robustness and resilience of infrastructure design .

CCRIP project assessment report after each monsoon season and natural disaster event. IFAD annual supervision report . PRA after each monsoon season and natural disaster event .

Climate change related impacts are within predicted level

COMPONENT 1: Improved Road Connectivity

Outcome 1: Improved road connectivity for men and women living in project Upazilas to access markets and social services.

By 2018, ADB:

Increased average traffic volume per day on project roads (target: 500; baseline: 200 )

Reduced average vehicle operating costs on project roads (target: BDT 10 / km; baseline BDT15 /km )

IFAD (from baseline):

50% increase in average traffic volume per day on project roads

25% reduced transportation costs on project roads

50% reduced travel time

Traffic data surveys (volume and price)

Transport worker and user surveys

Government sustains or increases funds for road and market maintenance.

Investments in polder protections by other programmes and projects continue

Page 11: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

xi

Design Summary Performance targets and indicators Monitoring Mechanism & Information Sources

Assumptions

OUTPUTS:

Upazila, union and village roads upgraded to climate resilience standards

Bridges and culverts built

By 2018, ADB funded:

130 Km Upazila road upgraded and climate proofed

780 meters of bridges and culverts in Upazila roads

IFAD funded:

160 Km union road upgraded

341 Km village road completed or upgraded

2245 m length of bridges and culverts

Independent monitoring of construction of roads, bridges and culverts

Site inspections

Environmental assessment

Project reports and MIS

No major delays due to price

escalation of materials and labour

Public procurement process remains adequate and adheres to ADB/IFAD requirements

Sufficient availability of labour

Roads properly maintained

LGED remains committed to apply acquired knowledge

COMPONENT 2: Improved market services

Outcome 2: Enhanced marketing of farm and non-farm produce in project markets

By 2018, ADB funded:

90% increase in the volume of goods marketed in growth centre markets, (baseline: 23,000kg in 2012)

% increase of traders (disaggregated by sex)

IFAD (from baseline):

20% additional income from construction of infrastructure

50% increase in the volume of goods marketed in village markets

25% increase of traders (disaggregated by sex)

Market surveys (at baseline, mid-term and completion)

Services of MAPP are reinforcing CCRIP interventions

OUTPUTS:

Market infrastructure expanded and upgraded

Women market sections built

Boat landing (facilities) platforms (ghats) built

Market Management Committees (MMC) established

LCS formed, trained and employed

By 2018, ADB funded:

88 growth center and rural markets;

All 88 growth centers and rural markets have a women section.

IFAD funded:

197 community (village) markets of different categories

15 community markets with a women section

5 Community collection points built

38 new landing ghats built

5,000 poor women and men employed in construction of markets through LCS (IFAD)

Site inspections and surveys

Adequate functioning of MMCs

Climate trends do not reduce on- and off-farm productivity, or quality ; production levels remain stable

Public policy continues to allow

procurement of works with the participation of LCS

COMPONENT 3: Enhanced Climate Adaptation Capacity

Outcome 3: Rural communities and local authorities are able to cope with volatile

Climate resilient rural infrastructure management plan is operational

Qualitative surveys: Focus group discussions and key informant

Local Government maintains emergency and recovery plans

Page 12: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

xii

Design Summary Performance targets and indicators Monitoring Mechanism & Information Sources

Assumptions

climate events and meet their basic needs during climatic shocks

% of population using shelters during natural disasters [Target: -- %]

interviews after completion of shelters

Post-climate shock surveys, PRA on effectiveness of response, management of shelters

OUTPUTS:

Village authorities develop and LGED approve climate resilient rural infrastructure management plan

LGED pilots sustainable road maintenance plan

Climate disaster shelters built/improved

LGED and local Government are trained on climate-proofing of rural infrastructure

Knowledge management framework for climate change developed

Innovations on garbage management tested

KM effective

By 2018

LGED approved plan by 2015

Sustainable road maintenance plan

15 of multipurpose cyclones built/extended

10 existing cyclone shelters improved

15 km of cyclone shelter access tracks upgraded

5 killas constructed

100 training units on climate proofing infrastructure ; > 15% female participant

>4 knowledge products published

>3 Rural radio programs developed

LGED reports, workshop minutes

Project reports

Site inspections and surveys

Management & maintenance plans are integrated into policies and enforced

Page 13: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

1

I. STRATEGIC CONTEXT AND RATIONALE

A. Background

1. This project design report (PDR) represents the final design of IFAD funded activities under the overall scope and design of the Coastal Climate Resilient Infrastructure Project (CCRIP) jointly funded by ADB, KfW, IFAD and Government of Bangladesh. A six members IFAD

mission1 , which was working from 1 October to 3 November 2012 in the project area, prepared the project design report (PDR) that presents overall project activities and management system in order to (i) offer greater details of IFAD funded activities, (ii) address observations and recommendations of the QE review on the IFAD „Briefing Note‟ of CCRIP and (iii) refine activities along with project targets, cost estimates, co-financing arrangements, and implementation modalities.

2. The design of CCRIP is the outcome of a merger of the Sustainable Infrastructure for

Livelihoods Enhancement (SMILE) project of IFAD and Climate Resilient Infrastructure

Improvement in Coastal Zone Project (CRIICZP) of ADB and KfW – had been accepted by all three donor agencies and the Government, and approved by ADB Board in September 2012. ADB, KfW, and IFAD signed an aide memoire on June 19, 2012 accepting the overall scope, financing and implementation aspects of the project. Later, the Government of Bangladesh confirmed the aforementioned aide memoire.

3. ADB, KfW and IFAD had designed independently from each other CRIICZP and SMILE, respectively, until May 2012, when both agencies met and decided to merge the projects. It had become clear at that time that the scope of the two project was similar and both projects were designated to be implemented in the same 12 districts. The main intention of the merger was to generate synergies from (i) a joint focus on rural transport and market infrastructure development, (ii) a common project area, (iii) a reduction of adverse impacts of climate change on livelihoods, and (iv) reduced management costs.

4. The objectives of CCRIP place considerable emphasis on adaptation to climate change and assistance to livelihoods through rural infrastructure development, which is fully aligned with the COSOP and the priorities of the Government of Bangladesh. ADB and IFAD agree to bring

together their dedicated loans and grants under a collaborative co-financing arrangement. Total project costs would amount to about USD 150 million while the outreach would increase from 430 000 households (as it was assessed for SMILE) to about 600 000 households or 3.5 million people under CCRIP in 12 selected districts in coastal, south-west

Bangladesh. Out of this large target group, it is estimated that at least 46% or 1.6 million people are poor or very poor.

5. Furthermore, IFAD and its national partners in Bangladesh designed the concept of CCRIP together with the Micro-enterprise and Agriculture Promotion Project (MAPP) as part of the project pipeline under the new COSOP 2012-2018. Both, the project pipeline and the new COSOP 2012-2018 were approved by the OSC in December 2012 and subsequently by the

Government of Bangladesh in a validation meeting held in Dhaka in January 2012. The COSOP for Bangladesh for 2012-2018 including the two project concept notes were also supported by the IFAD Executive Board in April 2012.

6. IFAD has scheduled the presentation of the loan and grant for CCRIP to the Executive Board in April 2013. The ADB loans and grants and the KfW grant have been approved during October 2012. It is expected that the financial resources of both, ADB and IFAD would be

available during 2013, maybe within a small time gap of a few months.

7. The final design mission a) finalized selection of community (village) markets and union/village roads to be built/upgraded under the project, b) updated engineering design and costs by incorporating climate resilient and adaptation features, c) finalized allocation

1 Mr. Dewan A.H. Alamgir (Mission Leader), Prof. Dr. Shamsul Hoque (Rural Infrastructure Engineer), Mr. Harry W. Denecke (Rural Infrastructure Engineer), Ms. Alexandra Sokolova (Economist), Ms Lakshmi Moola (Finance Officer, IFAD) and Mr. Shankar Achutan Kutty (Regional Procurement Adviser, IFAD). Mr. Thomas Rath (Country Program Manager, IFAD) joined the mission as of 8 October 2012 and participated in the wrap-up meeting on 22 October 2012. Mr. Golam Md Hashibul Alam, Country Program Officer, IFAD, supported the mission and participated in various meetings. Mr. Rezaul Karim Khan, ADB Task Manager for CCRIP project participated the mission from 17 to 22 October, 2012 and attended wrap-up meeting on 22 October 2012.

Page 14: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

2

and related cost tables for the components funded by IFAD, d) revised the project

management including accounting, financial management, and procurement systems and e) updated financial, economic analysis related to IFAD funding and in line with IFAD‟s requirements. Prior to the arrival of the mission, LGED with IFAD‟s assistance conducted a survey of community (village) markets and roads as per criteria agreed previously. The PDR includes final list of markets and roads to be developed/upgraded under the project.

8. The final design of IFAD funded activities, management system and co-financing had been

approved at a wrap-up meeting held on 22 October 2012 chaired by ERD and attended by representatives from ADB, LGED as the executing agency, and various Bangladesh Government departments. LGED is committed finalizing the project DPP as per design presented in this report.

B. Country and Rural development and poverty context

9. Overview. CCRIP will be implemented in 12 south-western coastal and low-lying districts of

the country, where people are poor and vulnerable to natural disaster and where recent development activities had only limited effects. The project plans to build climate resilient and or adaptive road and market infrastructure in about 32 Upazilas (sub-districts)2, which

will help boosting agricultural development and food security while reducing rural poverty. Poverty has been a pervasive problem in rural Bangladesh because of limited availability of land and other natural resources, low agricultural productivity, lack of non-farm economic

opportunities, high population density and poor governance. Bangladesh is home to the third highest number of poor people world-wide. About 80% of the population live in rural areas and are mainly engaged in agriculture and related non-farm activities. More than two thirds of the rural population are landless or functionally landless (i.e. owning less than 0.2 hectares of land), 44% are below the national poverty line and 29% are classified as very poor.

10. Climate change. Bangladesh is expected to be among those countries to be seriously

affected by the adverse effects of climate change. Today, Bangladesh is already one of the most disaster prone countries among the least developed countries. Two-thirds of the country lies less than 5 meters above sea level, making it one of the most flood prone countries in the world. Severe flooding during the monsoon season causes regularly serious damage to crops and properties, with severe adverse impact on rural livelihoods. Climate change is expected to increase the severity and frequency of cyclones and floods which will

likely cause more widespread destruction of land, roads, houses and other assets.

11. National water adaptation master plan: Bangladesh prepared national water management plan (NWMP)3 in 2001. The coordination of the activities under the NWMP lies with the National Water Resources Council (NWRC) part of the Ministry of Water Resources. The NRWC through its Executive Committee can issue directives as needed to enhance the different stakeholders implementing projects and programmes to be congruent with the policies and strategies of the NWMP. Within the Ministry of Water Resources the Water

Resources Planning Organization (WARPO) maintains a database to facilitate the work of the NWRC.

12. The NWMP report states that in the dry season less rainfall than usual may be expected while during the wet season rainfall could increase by 29% until 2050 as a result of climate change. Relative sea level rise (versus land levels) is stated to be difficult to predict as it is the combined effect of sedimentation (land accretion), land subsidence, and increase in amplitude of the tidal waves (from 1.8 to now already 3.0 m approximately). The range of

sea level rise based on different studies and assumptions is from 6.5 – 44 cm by the year

2050.

13. Other impacts of climate change are the expected increase in intensity and frequency of cyclones or storm surges. The consequences are already taken into account as needed e.g. by constructing cyclone shelters. The magnitude and impact of saline water intrusion is more difficult to assess in view of increased rainfall and uncertain river discharges. The potential

2 IFAD funded activities will be in 32 selected upazilas whereas ADB funded roads and market development subprojects could be in any of the 82 upazilas of 12 project districts including IFAD selected 32 upazilas. IFAD proposes that CCRIP gives priorities to subproject proposals located in these 32 upazilas in order to obtain maximum synergies. 3 (http://www.warpo.gov.bd/nwmp.html).

Page 15: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

3

impacts of climate change have been taken into consideration while designing infrastructure

under CCRIP as explained in relevant sections and annexes.

14. Economic outlook. In spite of all its limitations, Bangladesh has continued to accumulate economic gains over the past decade with a steady economic growth of 5–6% annually, a relatively low inflation and fairly stable domestic debt, interest rates and exchange rates. However, growth has not reached the rate of 7.5%, which would be needed for Bangladesh to graduate to a middle-income status country within the next 10 years4. After a slowdown

in GDP growth to 5.7% during 2008/095, growth recovered to 6.0% in 2009/10 with a 6.3% forecast for 2010/11. The inflation rate has been increasing to double digit figures (i.e. more than 12%) in 2011/12 which has become a major concern for the consumers and also the Government. The high inflation hurts mostly the poor and people with a fixed income.

15. Increased import6 and decreased inflow of foreign direct investment (FDI) and aid have shifted the balance of payments into a deficit (net outflow of USD 586 million for July to

November 2011, compared with surplus of USD1,585 million for the same period a year earlier). After a long period of stability, the value of the Bangladesh Taka has depreciated over the last six months from Taka 70 to Taka 83 per USD 1 in January 2012, which causes the upswing in import costs and deteriorates the current account balance. The national

macro-economic management has been under severe stress lately. Besides, the fall of the stock market index has caused massive losses for small investors.

16. Agriculture. Rural development in Bangladesh is explicitly linked to the development of

agriculture and the farming community. Most programmes aim at infrastructure development, higher agricultural production, improved access to financial services, better farm prices, lower input prices and improvement in school education and health services. Over the last decades, agricultural growth has been around 4% per annum. The country is currently almost rice self-sufficient in a normal year: rice production increased from 10 million tons in 1971 up to 33.9 million tons in 2009/10. There is, however, no room for complacency as Bangladesh has to import rice in times of large flooding and severe droughts

- especially if they occur during the critical crop growing period. Due to the dense population and the continued loss of arable land, caused by urbanisation and other reasons7, the need persists to enhance the productivity of rice cultivation and other staple food.

17. Among agricultural commodities, fruits, vegetables and fisheries are considered to be more profitable than rice which in turn is encouraging farmers to diversify production away from

rice. Consultations with farmers reveal that they are increasingly looking for more profitable

commodities. The price of rice remains usually steady at the time of harvest, whereas cost of inputs and labour goes up causing a drop of the net profitability of rice production. CCRIP may contribute to reduce production costs, simply by lowering transport costs through better connectivity to farm areas.

18. Land holdings are becoming increasingly fragmented as farms are inherited by and divided among the sons and daughters (54% of converted land is used for house construction), and more land (especially that of the larger land owners) is sold or rented out as people move

into non-farm occupations8. Although staple food production has kept pace with the growing population, it is expected that with rising incomes the demand for better quality foods – fruit, vegetables, meat, milk, eggs and fish – will increase as well. Diversification into these higher value products will put further pressure on land for paddy rice and on the national goal of rice self-sufficiency. Agriculture also suffers from severe damage caused by natural disasters and climate change.

4 Bangladesh: Strategy for Sustained Growth, World Bank 2007 projected that a rate of growth of GDP of 7.5% would result in the country joining the ranks of middle-income countries within a decade (by 2016). 5 20008/09 and similar numbers in the text refer to the financial year in Bangladesh starting 1 July and ending 30 June of the following year. 6 Imports grew to 36% during July 2010 to January 2011, partly due to rising commodity prices and large fuel imports for power plants. 7 It is estimated that about 0.56% of agricultural land is converted into non-agricultural use annually. (Source: Md Abul Quasem (2011). „Conversion of Agricultural Land to Non-Agricultural Use in Bangladesh: Extent and Determinants”, Bangladesh Development Studies, Vol. XXXIV, March 2011, No. 1). 8 Source: Md Abul Quasem (2011). „Conversion of Agricultural Land to Non-Agricultural Use in Bangladesh: Extent and Determinants”, Bangladesh Development Studies, Vol. XXXIV, March 2011, No. 1. See also Hossain, Mohabub and Abdul Bayes (2009). Rural Economy & Livelihoods: Insights from Bangladesh. A H Development Publishing House, Dhaka, Bangladesh.

Page 16: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

4

19. In the context of poverty and development, the concept for the CCRIP project has been

developed to contribute to the development of agriculture by building climate resilient infrastructure, improving access to local and “outside” markets, reducing production costs and dealing with inconveniences related to communication. The COSOP 2012-18 reflects GoB‟s priorities and the concept of the CCRIP (former SMILE project) is fully in line with the Government‟s sixth five-year plan. In the sixth five-year plan rural roads and markets, agriculture, livestock, community-based fisheries, etc. are all focal areas for pro-poor

growth. The plan emphasises the need to create employment opportunities for rural poor and women in agriculture and livestock and building rural infrastructure for ensuring good prices. Annex 1 and Annex 2 offer for further discussions on poverty and country social and economic conditions.

20. The broad directions for development over a longer time-span are set out in the Perspective Plan for Bangladesh 2010-2021. Amongst other things, this plan would like to see genuine

devolution of power to the local Government level, and also says that in the process of socio-economic development of the country, agriculture will still continue to play a vital role in the long run in terms of food security, generation of income and employment for multitudes living in the countryside and eradicating poverty.

21. Poverty in the CCRIP area. While national headcount rates of poverty declined from 49% to 40% between 2000 and 2005 (using the upper poverty line), those in the southwest changed very little. The World Bank attributed the widening gap between the south-west

and, in particular, the eastern part of the country, to the lack of access of the southwest to the development opportunities in form of garment industry and remittances. In particular, the incidence of poverty measured by head count rate (HCR) shows that the Barisal division is a lot poorer than the national average: 26.7% of people in Barisal division are below the lower poverty line (and considered extreme poor) compared to a national average of 17.6%. The Khulna and Dhaka divisions are slightly better off except for three project districts in the Dhaka division – Gopalganj, Madaripur and Shariatpur. The Barisal region is one of the

poorest regions in the country where 25% of population live at the lowest wealth quintile. Furthermore, other social indicators - such as access to sanitation, safe drinking water, and access to primary health care - are worse than the national average in the targeted districts. Female-headed households are also high in the area. Salinity in river water and soil is on the rise in three project districts of Khulna division. Discussions with numerous village groups revealed the following main reasons for poverty in the project area: less productive land;

one crop instead of three crops such as in other parts of the country; frequent natural

disasters including floods and river erosion; negligible non-farm employment; and poor infrastructure. Poor people tend to migrate from the targeted project area to Dhaka and other places to avoid hardship. See Annex 2 for detail discussion on poverty.

22. A similar pattern emerges in terms of sources of livelihoods notwithstanding some differences in within and between Upazilas: a) field crops (rabi and aman rice, oil seeds, pulses, jute); b) vegetables, fruits and spices; c) livestock, pond fisheries, shrimp and open

water fisheries including sea fishing; d) small trade; e) petty jobs; and f) agricultural labour.

C. Rationale

23. Vulnerability to Climate change. The rationale of the project has been well elaborated in the overall CCRIP design document and aide memoire signed by GOB/IFAD/ADB/KfW. Bangladesh is one of the most vulnerable countries to climate variability and change because of its geographical location, low deltaic floodplain and hydro-meteorological influence or

erratic monsoon rainfall and other extreme climate events. Climate change threatens the significant achievements made by Bangladesh in the last two decades in raising incomes and

reducing poverty. By 2050, climate change impact could make an additional 14% of the country extremely vulnerable to flooding and dislocate more than 35 million people in the coastal districts. The climate change impact will aggravate the infrastructure vulnerability as a result of sea level rise, increased wet season rainfall; increased annual temperatures and increased frequency of severe cyclones. The culmination of these impacts will be a rapid

deterioration of rural infrastructure. The project will pilot and demonstrate ways to mainstream climate resilience in rural infrastructure.

24. The area suffers under river erosion (almost all of the Bangladesh rivers flow through the project districts), and low-lying river char areas where crop intensity is low (some areas produce only one crop per year). Two major cyclones (Sidr in 2007 and Aila in 2009) affected several of the designated project Upazilas resulting to large-scale losses of lives,

Page 17: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

5

livelihoods, houses and rural infrastructure. The frequency of such natural disasters and

floods is expected to increase with climate change. The low-lying coastal zone is highly vulnerable both to the normal tidally enhanced monsoon floods and to regular impact from tropical cyclones. Fifty eight (58) tropical cyclones have impacted Bangladesh during the period (1960-2010). Of these, 28% hit the coast of Sundarban (Satkhira, Khulna and Bagerhat), 22% west central coast (Borguna, Patuakhali, Barisal, Bhola and Meghna estuary), 26% east central coast (Noakhali and Chittagong) and 24% south-eastern coast

(Chittagong, Cox‟s Bazaar and Teknaf). The vulnerability of the physical infrastructure to the impacts of the current climatic environment is a consequence of the impact of monsoonal rainfall and floods and in addition, the severe rainfall, flood and wind effects of tropical cyclones. The climate changes as predicted thus far will increase this vulnerability as a result of sea level rise, increased wet season rainfall, increased annual average temperatures and increased frequency of strong cyclones. Therefore, the people would require climate resilient

infrastructure, social and economic opportunities to protect and develop lives and livelihoods.

25. The focus of the project is placed on climate-proofing of rural infrastructure in 12 rural coastal districts vulnerable to climate change. The project, while enhancing longevity and sustainability of rural infrastructure, will improve livelihoods in 12 rural coastal districts of

Bangladesh. The project primarily addresses acute rural poverty in South-western Bangladesh by reducing adverse impact of climate change by building resilient and adaptive infrastructure and improving access to market to enhance livelihoods. The South-Western

districts of Bangladesh are poor due to poor connectivity, predominance of small-scale agriculture as the main source of income, absence of industries and related job opportunities, limited availability foreign remittance as compared to the Eastern part of the country, adverse effects of natural disasters, especially in coastal Upazilas.

26. Specific impacts of climate change on infrastructure: A common understanding is that with increased water level and frequency of cyclones roads need to be strengthened and raised for physical protection and reduction of number of days of inundation. Scientific

predictions on the extra rainfall resulting from climate change impact on the drainage capacity, which may have to be enlarged. The consequences for design of union and village roads are discussed in detail in Annex 5. They differ as to the development within or outside polders. Areas protected from flooding (polders) will take into account the extra rainfall, areas not protected from flooding (chars) will take into account both the extra rainfall and sea level rise. Eventually the detailed designs will be assessed by the project‟s hydrologist.

27. Constraints faced by the poor and small producers. During the development of the COSOP 2012, IFAD‟s portfolio was reviewed in terms of its effectiveness and relevance for poverty reduction and rural development in Bangladesh. The process concluded that poverty reduction should remain priority for Bangladesh and consequently, for IFAD. The rural population, especially the poor and small producers, remains the core target group for IFAD. Within the population, IFAD funded projects target in particular poor women and men, landless, small and marginal farmers, other professional groups such as fishers, small

traders and other small producers. In almost all situations, these groups depend directly or indirectly on agriculture for supporting their livelihoods and are producers and consumers at the same time. As such, the development of agriculture benefits all categories of rural population in the form of higher income and productivity, and improved livelihood opportunities. Table 1 presents priorities of various groups of beneficiaries

28. Besides the above constraints caused by climate change, rural producers, especially the poor and the small producers, suffer basically from three sets of constraints that inhibit the

development of their livelihoods: a) poor transport and market infrastructure that limits access to larger markets, increases cost of production because of higher input and

transportation costs, and lowers commodity prices due to remoteness; b) limited access to demand driven financial services, especially seasonal agricultural credit and loans for microenterprises, and limited access to appropriate technology and inputs, and knowledge and support services such as vaccination services for livestock etc.; and c) vulnerability to

the effects of climate change. Lack of all-weather road connections limits their access to markets, increases the cost of production because of higher transportation costs, lowers commodity prices due to the remoteness, and hinders access to education and health services. Poor road connectivity also restricts their access to financial services, technology, and development support services provided by various agencies. During extreme climatic events, the poor lose their assets as well as livelihood options. Often after extreme conditions, men tend to migrate, leaving their families behind. Poverty incidence is

widespread, with many households headed by women. The women are more vulnerable than

Page 18: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

6

men because of (i) poorer access to education and health services, and economic

opportunities; (ii) limited mobility; and (iii) other social restraints.

Table 1: Priority needs of different occupational and social groups

Prioritized Needs Wage labor

Small farmer

/producer

Small trader

Women/

children

Businessmen/ well off class

Employment opportunity √ √

Potable water √ √ √ √ √

Irrigation water √ √

Rural access road √ √ √ √ √

Market infrastructure √ √ √ √ √

Educational institutions √ √ √

Electricity √ √ √

Hospitals √ √ √

Cyclone shelters √ √

Loan with lower interest rate than NGOs

√ √ √ √

Source: Field interviews by IFAD design mission

29. Infrastructure. The lack of adequate transportation and marketing infrastructure in the project area is limiting the development opportunities for agricultural commodities value chains and impacting negatively farmers‟ and traders‟ income. With regard to agricultural value chain development, the current situation is characterized by:

Weak and unbalanced linkages among value chain stakeholders, who are dominated by very few input suppliers. These suppliers rarely visit remote villages and markets or supply them with low quality inputs. This in turn results in low yields and low quality. Moreover, a

handful of buyers, mainly wholesalers, often purchase the crops just after harvest when they are generally at their lowest price level or at prices which were fixed unilaterally;

Very limited access to improved technologies and technical advisory services leading to a low quality of the crops;

Limited access to adequate financial products such as agricultural loans. Branches of most

agricultural banks are inadequate due to poor communications, which puts additional

burden on developing satisfactory terms and conditions for farmers. Microfinance institutions may also not be present in remote villages; and

Unattractive market facilities affecting the increase in local agricultural production and sales. Annex 4 offers additional discussions on agricultural value chain development issues.

30. The construction of adequate infrastructure is seen as a necessary but not sufficient condition for the establishment of sustainable value chains. Once the required infrastructure is in place, other critical value chain factors such as access to financial services, technology and

extension, high quality inputs, market information and buyers need to be addressed by dedicated projects such as MAPP.

31. Harsh weather conditions such as storms and inundations are affecting already livelihoods today. Climate change is expected to aggravate the current, negative impacts especially on the poor. Infrastructure like roads are often flooded or destroyed after storms and rendered unusable, with high repair and maintenance costs to follow. During the design of SMILE in spring 2012, IFAD and ADB/KfW decided to join SMILE and CRIICZP given the similarity of

these projects. Implementing one jointly funded project, IFAD will be able to render the SMILE project to a climate-smart one (i.e. CCRIP) and add value to the original focus of connectivity (roads) and accessibility (markets) for smallholder producers. Moreover, by this approach, CCRIP addresses the COSOP objectives 1 and 2.

32. Impact of infrastructure in IFAD funded projects. Based on results of the on-going, IFAD funded Market Infrastructure Project in Charland Regions (MIDPCR) activities, the construction

of roads and markets combined with the provision of technical assistance and advisory services have led to the following changes:

Sale prices increased as a result of an increased competition among a larger group of buyers;

Page 19: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

7

Production and marketing costs for some inputs and crops decreased due to factors such

as access to improved technologies, equipment, other inputs and affordable transportation due to an increased volume of trade;

Yields increased and the quality of production improved, and

Access to adequately designed financial products and services improved.

33. Such changes represent triggers for a substantial increase in farmers‟ and producers‟ income and for a structured and sustainable value chain development.

34. Table 2 illustrates the changes in production yields and in farmers‟ net income for six products after two years of MIDPCR support: infrastructures, provision of technical advisory services, linkages among value chain stakeholders, introduction of improved technologies and access to adequate financial products. Although it is difficult to attribute the results to different project activities, at least a part of the incremental income can be safely attributed to the infrastructure activities. A more detailed analysis on value chain and financial services has

been prepared in the working paper 1 for CCRIP and placed in project life file (PLF).

Table 2: Changes in yield and net income for six selected products

Baseline Current situation

Change

Product Yield/ dec.

Prod cost / kg

Mkt cost / kg

Selling price per kg

Income per kg

Yield / kg

Prod cost / kg

Mkt cost / kg

Selling price per kg

Income per kg

Yield 'dec.

Net income per kg

kg/dec. Taka Taka Taka Taka kg/dec. Taka Taka Taka Taka % %

Paddy-Rice 9

6.89

1.33

12.56

4.33 12

9.17

3.67

17.92

5.08

33

17.31

Fish 10 33.40

10.50

92.40

48.50 24

40.75

7.21

119.79

71.83

140

48.11

Tomato 73 2.12

0.93

10.55

7.49 172

1.89

0.78

10.38

7.70

136

2.81

Cucumber 77 3.73

1.43

9.22

4.06 150

4.48

1.03

10.82

5.31

95

30.55

Country bean 43

2.72

1.74

15.58

11.12 95

2.11

1.08

17.87

14.68

121

32.10

Mungbean 4 22.50

7.00

65.75

36.25 9

13.33

5.56

62.22

43.33

125

19.54

Source: MIDPCR (value chain component) 35. The experience of the Char Development and Settlement Project (CDSP) phases I to III,

Sunamganj Community Based Resource Management Project (SCBRMP) and rural infrastructure development projects funded by other agencies demonstrate that paved roads and markets improve communications and subsequently livelihoods. The main benefits to the households comprise better access to markets to sell own produce and purchase inputs,

improved access to agricultural and financial services, leading to increased production and higher farm gate prices, higher agricultural labour wage rates, increased investments in agri-business and trade, and additional private investments in markets.

36. The access to school education and primary healthcare is usually improved with better communication, especially during the wet season, when river and canals are difficult to cross, pathways and roads are inundated. Poor women particularly benefit from health care services

as their mobility within the area increases greatly. Another benefit from all-weather roads is the protection of lives and livelihoods (as roads include embankments and drainage systems).

37. Overall, protection and enhancement of livelihoods would be greatly enhanced if adequate

transport and market infrastructure were in place in the Southwest and other disadvantaged areas in Bangladesh. The demand for adequate infrastructure from the population is enormous, especially from the poor population. Following the demand, CCRIP will focus on building rural markets and roads in some of the poorest and most vulnerable Upazilas in

South-western districts of the country. For more details, Annex 3 offers a discussion on experiences and lessons in IFAD-financed projects in Bangladesh.

38. Value chain development. Once the infrastructure is being addressed, the implementation of a project addressing the constraints for agricultural and non-farm production and marketing faced by the IFAD target group becomes important. This will be the task of the Micro-enterprise and Agricultural Promotion Project (MAPP), as outlined by the approved

Page 20: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

8

COSOP 2012-18. MAPP will follow CCRIP one year later, as the approval for this loan is

scheduled for the Executive Board in April 2014.

39. MAPP will scale-up the successful experience of rural enterprise development (RED) activities of MIDPCR (besides the market and road development) and FEDEC, another IFAD-funded project. The latter is implemented by PKSF and provides microfinance and agricultural and micro-enterprise loans, while it promotes technologies and facilitates training and other support services to rural small producers. Building MAPP “on top” of CCRIP is part of the

COSOP‟s programmatic approach. CCRIP will expand the infrastructure approach of MIDPCR into 32 Upazilas of 12 districts, MAPP will expand the successful activities of FEDEC, MFSTP, MFMSFP and the RED activities of MIDPCR into the entire CCRIP area and probably throughout the country. MAPP will build on the physical infrastructure of CCRIP as a foundation to promote better access to agricultural and microenterprise loans as well as the promotion of agricultural technology and support services. This means that the two new projects will serve

the same communities and will capitalize on the comparative advantages of two implementing agencies – LGED in infrastructure and PKSF in financial, technological and support services.

40. The rationale for the above described, programmatic approach, i.e. designing two complementary projects with a distinct focus on infrastructure and access to finance and value

chain development, was developed during the development of the new COSOP, when all partners concluded that the project activities of MIDPCR cannot be simply replicated in a larger area like CCRIP would cover. The combination of infrastructure and value chain

development activities would simply overwhelm LGED‟s capacities as an engineering institution. The promotion of value chain activities at a larger scale requires a specialised institution with sufficient capacities. It was therefore decided to separate infrastructure development and value chain activities into two distinct projects, but connect them through the same geographical area. LGED would design and implement infrastructure activities in CCRIP.

41. LGED has a proven track record as a solid and fast implementer for infrastructure projects in

rural areas, with IFAD and other international agencies. After successful projects such as SCBRMP and MIDPCR, LGED has mainstreamed the use of Labour Contracting Societies (LCS) in their institutional policies and implementation approach. The LCS approach substitutes the usual contractors for small infrastructure works by forming community groups of mainly destitute women – the Labour Contracting Societies or LCS. These women receive a wage and premium for the work accomplished and then can build their own development path by either

continuing this works or investing it in agricultural or other economic activities.

42. PKSF would be leading the value chain activities in MAPP, which would start implementation by 2014. PKSF is one of the four largest microfinance institutions in Bangladesh, besides BRAC, Grameen Bank and ASA. It works as an apex organisation for microfinance institutions and has developed a number of promising new approaches within the IFAD country program. PKSF led projects like MFTSP, MFMSMFP and FEDEC have piloted efficient ways for linking microfinance with smallholder agriculture, for example, through agricultural loans and

livestock insurance. PKSF has developed a large micro-enterprise loan program with FEDEC where value chains for agriculture and non-agricultural business proliferate and grow at an impressive pace. PKSF is interested to work with IFAD to scale up these successful experiences to a national scale. See also Annex 3 for detail discussion on IFAD Bangladesh portfolio and lessons learned.

43. Complementarity and synergies. The rationale for merging SMILE and CRIICZP projects lies in their complementarity and in obtaining synergies. Both projects had been designed to

work in the same project area and focus on roads and market improvements, although they would support different types of roads and markets. While ADB funds will be improving mainly

Upazila roads, large markets and growths centres, the IFAD funds will be used to build union and village roads and community (village) markets. By their scope of works, both projects will complement each other.

44. CCRIP has placed considerable emphasis on climate change adaptation and resilience. This

would benefit also the IFAD funded roads, now designed with climate resilient and adaptation features in villages. Climate adaptation standards would apply for union and village roads in vulnerable areas and link them to the higher level road network (upazila) and markets.

45. The challenge for CCRIP is to obtain synergies between ADB-funded Upazila roads and growth centres development and IFAD funded village markets and union/village roads to create a maximum impact for the rural poor and other dwellers. The ideal situation would be to

Page 21: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

9

implement all activities, i.e. large and minor roads and market improvements, within the

same most vulnerable Upazilas. Compromises are likely to be made for the selection of the sub-projects due to the limited availability of resources, different types of roads and markets, number of Upazilas and locations of roads and markets that are already fixed because existing markets will be improved and roads will be built on existing alignments The final design mission took into consideration the needs and maximum possible linkages of selected union/village roads and village markets with the proposed upazila roads and growth centres to

be built by ADB funds. By this, close links and hence, the project is expected to create synergies in terms of transport and marketing are expected to develop.

46. The merger of the two projects is expected to generate efficiency gains, as only one project management unit will be needed and one technical assistance team. Admittedly, due to the large size of the project, the units need to strengthened, for example 2 deputy project directors will be needed to coordinate the implementation of the ADB and IFAD funded

operations. However, the required staffing of the PMO will be less than for two single projects.

47. In the same vein, the coordination requirements at LGED headquarter and at its district and upazila offices are expected to decrease with one project management structure, one project administration manual and a well aligned financial management system. There will be one

AWPB and procurement plan, one annual supervision and audit, one mid-term review and one M&E and knowledge management plan and so forth.

48. LGED has a proven track record to implement large infrastructure project and MIDPCR and

SCBRMP experiences show that the procurement of contractors alongside with contracting LCS have been well managed within one project.

D. Scaling-up

49. Pathways. The new COSOP foresees to scale-up successful projects and approaches to a level where high impact and high efficiency gains can be obtained. Scaling–up requires an early definition of its pathway or sequence of steps to be taken to ensure that they are

appropriate in the context of Bangladesh. The dimension, drivers, spaces and risks of up-scaling are presented below following IFAD guidelines and framing questions approach.

50. Scale and Dimension. The scaling-up of MIDPCR activities is mainly the expansion to a larger project area in terms of a horizontal replication from 5 to 12 districts. This represents an increase in terms of scale of operations, which is expected to deliver considerable impact

on poor rural livelihoods. LGED has implemented successfully other operations of similar scale. In terms of vertical scaling-up, the main issue for policy dialogue will include the

confirmation of Government funds for road and market maintenance. Other project features such as the women market section and the organisation of market management committees (MMC) will be monitored and successful practice distilled for the attention of policy makers and eventual inclusion in national policies.

51. Drivers and spaces. The models and implementation modalities for scaling-up are being delivered by MIDPCR. Supervision, mid-term review and project surveys confirm the success

of the LCS approach for market infrastructure development. LGED under the Ministry of Local Government, Rural Development and Cooperatives (LGRD&C) has taken the leadership for implementing CCRIP by replicating successful MIDPCR approaches. This opens up also opportunities for policy dialogue and further scaling up. LGED and LGRD&C are monitored and held accountable by the Government of Bangladesh against the project targets as per a Government ratified Development Project Pro-forma (DPP).

52. The policy space is probably the most relevant one for this project. LGED through LGRD&C

has promoted CCRIP and its precedent concepts namely SMILE and CRIICZP. It received full support through the inclusion of CCRIP in the planning cycle of the Government. The wrap up meeting for the design of CCRIP was chaired and concluded by the Economic Relation Department (ERD). The institutional space is clearly addressed with LGED as the lead implementing agency with a proven track record. ADB and KfW are the partners that support the scaling up financially with additional resources, which will allow reaching up to 3.5 million people. In addition, the financial resources will include the provision of technical assistance to

boost the capacities of LGED. The learning space will be devised through the M&E and KM frameworks as detailed in the design report. MIDPCR produced significant knowledge in areas dealt with constructions and their management that has been fed directly into the CCRIP design. A dedicated PMO and its branches in the districts will be set up as per usual and successful practice by LGED to be supported by a technical assistance team. The PMO will be

Page 22: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

10

staffed with current LGED personnel to ensure that experiences and learning remain within

LGED and be used for similar interventions in the future.

53. Risks. The risk that is usually associated with a larger geographical replication includes that the institutions are not well suited for implementation and may be overwhelmed with the new challenge without proper training and coaching. CCRIP balances this in two ways. First, project management is designed in a way that a dedicated deputy project director who is well familiar with union/village road construction and LCS works will coordinate IFAD funded

activities. Secondly, the MIDPCR approaches like LCS, MMC and women section have been well documented and there is a wealth of experienced project staff who will be ready to deal with the implementation and to train new staff. This can be done as CCRIP will cover districts where MIDPCR is already working such as Bhola, Patuakhali and Barisal. Last and most importantly, CCRIP will not scaling up the value chain approach and will focus on engineering works for which LGED has a proven track record in the country, and with IFAD and other

donor agencies.

II. PROJECT DESCRIPTION

A. Project area, poverty and target group

54. Project Upazila selection process. To reduce high incidence of poverty in the south-western region of Bangladesh, the project will cover selected vulnerable Upazilas in Satkhira,

Khulna, Bagerhat, Gopalganj, Madaripur, Shariatpur, Pirojpur, Jhalkati, Barisal, Bhola, Borguna, and Patuakhali districts. IFAD had evaluated data for 77 Upazilas from 13 districts to identify project upazilas. The criteria and weighting of scores aim to reflect an emphasis placed on poverty, vulnerability to disaster, remoteness and present level of infrastructure development in order to ensure that poor, vulnerable, remote (char and low-lying areas) and least developed Upazilas are identified and included in the project area. In addition, quantitative data are used for scoring, field observations are used when quantitative data are

insufficient to possibly include those Upazilas that were excluded by quantitative scores. The data sources are BBS/WFP/World-Bank poverty maps, LGED inventory on rural roads and markets, district and union information, and field observations. The following criteria have been applied for the selection of project Upazilas (See Working Paper 2 to obtain detailed information on the evaluation process and data used for the selection of Upazilas) and were completed and validated by field observations:

percent of population below poverty line,

agricultural labour rate, vulnerability to tidal surge, storm, floods and river erosion, remoteness, poor communication (percent of paved road to total road), road density by population, percent of undeveloped markets, and

55. The process has produced a list of the least developed and most vulnerable Upazilas. In

qualitative terms, the coastal, flood-prone, char, low-lying, and infrastructure-poor Upazilas have received the highest priority, which is in line with GoB and IFAD policies with regards to poverty reduction and targeting of vulnerable communities. In Bhola and Patuakhali, two districts under MIDPCR, the project will continue to complement the MIDPCR project, where several Upazilas that are still poor in communication even after MIDPCR have been included

through the same selection process. Annex 5 offers additional information and further detailed project description.

56. The process led to selection of 32 Upazilas form 12 districts (See Table 3). IFAD will fund activities in these 32 selected vulnerable upazilas while ADB funded subprojects may be selected from any of upazila subjected to the outcome of the approval process during implementation. It means that ADB‟s design process did not identify specific Upazilas for implementation of sub-projects from 12 project districts as all Upazilas are eligible to submit a

proposal for sub-projects. IFAD has suggested that if the ADB funded upazila roads and growth centres and large markets were developed in above identified vulnerable Upazilas, CCRIP could increase significantly its impact on the basis of the complementarity of the project components and activities.

57. The IFAD final design mission validated the selected markets and roads in order to support expediting the start-up of the project implementation, as no time would be required anymore

Page 23: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

11

to select the project sites and launch feasibility studies. The selected markets and roads will

become part of the DPP to be approved by the Government prior to implementation of the project.

58. CCRIP will not “spread thin” its resources over too many Upazilas and instead, it will follow a strategy of having rather a significant impact and reduced management costs by working in fewer and well selected Upazilas. Table 3 provides a full list of the target districts and upazilas of the IFAD funded activities in CCRIP.

Table 3: Project Area: Districts and Upazilas

District Project Upazilas Names of CCRIP Upazilas

1 Barisal 3 Uzirpur, Banaripara and Babuganj

2 Bhola 3 Charfasion, Borhanuddin, and Lalmohan

3 Patuakhali 5 Sadar, Galachipa, Rangabali, Kalapara, and Mirzaganj

4 Borguna 4 Amtali, Betagi, Bamna, and Patherghata

5 Pirojpur 2 Matbaria and Zianagar

6 Jhalkati 1 Kathalia

7 Madaripur 2 Shibchar and Rajoir

8 Gopalganj 2 Tungipara and Kotalipara

9 Shariatpur 2 Zanjira and Naria

10 Bagerhat 2 Sarankhola and Moralganj

11 Khulna 3 Botiagata, Dacope, and Koyra

12 Satkhira 3 Shymnagar, Ashashuni, and Kaliganj

Total: 12 32 32

59. Target group. The target group will be the population in the catchment areas of project

markets as road communication and markets benefit everybody irrespective of income and profession. It is expected that small and marginal farmers, small traders and micro-

entrepreneurs, landless people and poor women will particularly benefit. The economy and livelihoods in the selected Upazilas is predominantly dependent on agriculture (rice, jute, vegetables, fish, livestock, pulses and oil seeds) and agricultural labour.

60. Targeting. The Upazila selection process has ensured the inclusion of very poor and vulnerable Upazilas to allow that most of the project benefits reach the poor (geographical

targeting). The second level of targeting has focus on rural markets and connecting roads in the least developed villages/unions within each Upazila, especially rural markets from char,

low-lying and disaster prone (floods/tidal surge) and infrastructure poor villages. LGED has carried out Upazila level survey before the final design mission to identify markets and connecting roads in remote unions/villages within the selected Upazilas. The IFAD final design mission has verified the survey data and finalized selection or markets and roads. A household level targeting will apply at the time of implementation for the specific activities such in the case of the Labour Contracting Societies (LCS), whereby destitute women and men will be organised as wage labour to carry out the infrastructure works.

61. Gender Issues. IFAD attaches great importance to addressing issues in the project design process that affect the women, especially the poor women to help them engage in economic opportunities and enhance their capacity and mobility. The experience of MIDPCR and also SCBRMP show that poor women can benefit in a number of ways: LCS members who constructed markets received wage and profits; poor women received IGA training and loans from MFIs; training on constructions of markets (masonry) have enabled them to work in

other construction works; number of women buyers and sellers has increased and; the

mobility of women in the project area has increased due to road communication. It is noted in MIDPCR and SCBRMP project areas that the improved communications have given women an increased access to health services. Similar opportunities are expected to be available for the poor women in CCRIP.

62. Appendix 7 of the ADB/IFAD/KfW report outlines a summary Gender Action Plan for planning and monitoring purpose. The project will target the poorest women to create employment

opportunities and livelihood support by involving them in construction of markets and some roads and linking them with microfinance institutions and another IFAD-funded value chain development project (MAPP) to be implemented by PKSF in the project areas. The gender action plan presents income generating opportunities, capacity building for technical skills as well as for women empowerment. Especially the latter aligns fully with the COSOP objective 3.

Page 24: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

12

Targets will need to be set at or before projects start aiming that the women obtain equal

opportunities in all project activities. See also Annex 2 and Working Paper 2 in the Project Life File for further discussion on gender issues.

63. Safeguards. IFAD project design report, specifically in the environmental and social assessment note, addressed the potential environment and social issues for implementation of community (village) markets and rural roads. Design and implementation arrangements will not be in conflict with the ADB environmental and social safeguards standards

B. Project Goal and Objective (“Impact and Outcome”)

64. There are some differences in terminologies and structure of project design and monitoring framework (DMF) or project logframe between IFAD and ADB. IFAD follows a four-tier framework - Project Goal, Project Objective, Outcome and Output, as opposed three-tier design and monitoring framework – Impact, Outcome and Output - of ADB. IFAD has accepted the overall CCRIP DMF (Impact and Outcome) along with approved indicators but adapted it to

the IFAD structure and added several indicators to meet IFAD‟s requirements. Resources have been allocated to conduct appropriate studies to measure additional indicators.

65. Accordingly, the project goal (ADB: Impact) of CCRIP is to achieve „Improved livelihoods (higher incomes and food security) for poor households (women and men) in selected Upazilas of 12 coastal districts”. The development objective (ADB: Outcome) is to achieve “enhanced climate resilience of coastal road and market infrastructure for people in selected Upazilas of

12 project districts”.

C. Components

66. The ADB/KfW/IFAD report (page 13-16) presents the overall description of all project components referred to as “outputs”. The project have three components - 1) Improved Road Connectivity, 2) Improved Market Services, and 3) Enhanced Climate Adaptation Capacity, and Project management. Each component is briefly described below:

Component 1: Improved Road Connectivity

67. The outcome of this component is „Improved road connectivity for men and women living in project Upazilas to access markets and social services‟. The outputs under this component are: upgrading of upazila roads (ADB funded); and improvement or partly newly constructed

BC union roads (Scenario B9: Climate resilient; Scenario C10: Climate adaptive) and village roads (Scenario B only, with either a BC, RCC or block pavement) along with associated minor bridges and culverts. The project will build 130 km of upazila roads by utilizing ADB resources.

With IFAD funding the project will build approximately 501 km of union and village roads, 2455 meters of associated small bridge/culverts and individual bridge (see table 4). The exact quantities will depend on actual cost during implementation. Prior to final design mission in October 2012, LGED conducted a survey in all project Upazilas on the basis of which the IFAD design mission has finalized the list of proposed union and village roads. Priority has been given to those roads that benefit the highest number of people and connect village markets

(see below) with each other and growth centres.

68. The survey and mission field visits confirmed that most of the proposed roads are within existing embankments. It has been agreed that union roads within embankments will be of Scenario B type and outside embankments and in low-lying char will be of Scenario C type. In all cases, the actual road type will be chosen on a case to case basis. In the case of village roads, Type B roads will be built only.

69. Three different types of union and village roads are envisioned under the project: a)

Bituminous roads; b) Reinforced Concrete Cement (RCC) roads where roller (road compacting machine) cannot be taken and in flood prone areas; and c) block roads where frequent flooding is expected. The selection of roads type will depend on it suitability for prevalent local situation. In some areas, HBB roads may be upgraded to bituminous or even RCC roads.

9 Scenario B: 600 mm above highest flood level under normal climatic condition; plus additional climate proofing design parameters such as extension of sub-base up to slope, embankment protection based on variable impacts (such as flood, erosive flood, wave action and overtopping). 10 Scenario C: Additional (above scenario B) 200 mm to address forecasted climate conditions for next 20 years.

Page 25: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

13

70. The project will aim to strike a balance between the proportion of village BC roads and RCC

roads, which will depend on the local conditions. The unit costs of BC roads are lower than those of RCC roads, but the former is less durable and requires a higher maintenance than RCC roads. Commonly, RCC roads will be built in those areas where the machinery for BC roads such as rollers cannot be moved because of the narrowness of the road or the area is so remote that transporting machines and materials is difficult for construction and maintenance. The advantage of RCC roads is that they are durable and resilient to flood and tidal surges,

while they require very little maintenance as compared to other road types. The mission will provide basic designs of all road types in the main report.

71. The project target for road/bridge constructions will be divided according to the demand from 32 project upazilas. The names, connecting points, LGED identification numbers and lengths of selected roads by project upazilas have been identified through a survey and are available in Annex 7. LGED has incorporated this list in the project DPP for Government approval. It is

important to stress that CCRIP activities will not overlap with other projects in terms of roads selected. The project will recruit poor women for road-side tree plantations and maintenance for a two years period.

72. Table 1 below presents physical targets for construction under this component. According to

design mission estimates that adopted scenario B and scenario C for union roads and scenario B for all village roads, CCRIP under this component will build 160 km union roads and 341 km of village roads, 2,445 meters of small-bridge/culverts including 110 meters of individual

bridges. A total of 5 km of block road is planned in the whole project area, which will be suitable for areas which are frequently submerged. However, if these are not required, the target can be converted into RCC or BC village roads. As given in Annex 7, the demand for paved roads is varied due to past investments. The identification has also avoid overlapping with other projects in the selection of roads. See Annex 7A for physical total and annual targets and Annex 7B (XL file electronic version) for Tables extracted from COSTAB.

Table 1: Project targets under Component 1

Description Infrastructure type or activity Quantity

Component 1:

Improved Road Connectivity

Upazila road (km) 130

Union Road (Scenario B and Scenario C) (km) 160

Village Road [All Scenario B: BC, RCC and block road] (km) 341

Total road length (km) 631

Small bridge/culverts/individual bridge (m) 2455

73. All union roads are planned as BC roads. Village roads may be BC, RCC and block roads. See

Annex 8A for structural design of transport infrastructure, Annex 8B detail cost calculation for various road types (XL file), and 8C for unit costs for both transport and market infrastructure

(XL file).

74. The construction and rehabilitation of roads will be by contractors while block roads will be constructed by LCS. Since the small local contractors do not have the financial capacity to purchase and maintain expensive equipment, CCRIP will acquire compacting machinery (rollers) to be owned and managed by LGED, who will rent it out to local contractors.

75. LCS members will be trained (25 members per LCS for one km of block road). The project will also do road-side tree plantation in 75 km by LCS members, as has successfully been done

under MIDPCR.

Component 2: Improved Market Services

76. The outcome of this component is „Enhanced marketing of farm and non-farm produce in local markets and growth centres‟. The outputs of this component include: improved community (village) market facilities (multi-purpose shed, fish shed, open paved/raised area, women section, toilet block, internal road and drainage), improved hygienic conditions, functioning MMCs, employment for poor women as LCS members; construction of commodity collection

points (CCP) for farmers and fishermen who live in remote locations and want to bring their produce for sale to be transported to nearby markets.

Page 26: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

14

77. IFAD so far fielded three missions that visited all project upazilas and almost all proposed

village markets. The following four different types of community (village) markets have been identified:

Type I: Special markets (approx. more than 200 permanent shops): They are large rural markets known for transacting specific commodities in large quantities. For example, in Amtali Upazila, Fakir haat, is situated near the sea and is an important fish landing centre. In addition to the typical items, it needs a large landing platform (“ghat”) for the fish catch

and sheds to accommodate the numerous fishing boats at a given time in order to sort and pack large quantities of fish. Such markets will have unique design and unit cost.

Type II: Medium market (approx. more than 100 permanent shops): They are important rural markets that serve 7-10 villages and act as assembly markets where a large number of traders (beparis) assemble to buy farm produces to be transported to distant and larger markets. This type of markets will have two sheds, one open platform, toilet block, internal

roads and drainage system, and garbage pit.

Type III: Small village markets (approx. 10-50 shops): They are located in remote areas and normally serve 3-4 villages. They are usually poorly connected to larger markets due

to insufficient roads network. This type of markets will have one shed, open sale platform, toilet block, internal roads and drainage system, and garbage pit.

CCPs, managed by sellers of farm produce, are information spots in rural areas where farmers/fishers assemble their products to be transported by buyers. CCPs provide access

to sellers and buyers and are simple facilities allowing for motorized vans and alike to on and off load goods.

78. The experience of MIDPCR and similar projects indicate that physical improvement of rural market facilitates the access of villagers including the poor to markets and moreover, they may obtain higher price for their farm produce. In addition, improved markets facilitate the purchase of farm inputs. The CCRIP project is also expected achieve similar benefits.

79. CCRIP project will expand and develop 197 community (village) markets among the three

aforementioned categories, build 5 additional commodity collection points and 38 ghats (Table 4) (all IFAD funded). Besides, the project will improve 88 growth centres and large rural markets with ADB funds.

80. LGED with IFAD have already identified the community (village) markets to be developed in

each Upazila. The list is presented in Annex 7 and LGED has incorporated it in the project DPP. The selection of sites within a market and size of market infrastructure may vary for each

market. CCRIP will prepare a master plan for each market before construction, and development cost for each market is expected to vary. IFAD/LGED has used the following selection criteria for this purpose:

81. Basic pre-conditions: i) the market is strategically located and serves as an assembly market to benefit a large number of villages and connect other larger market and growth centres; ii) the location is not vulnerable to river erosion in the short and medium term; iii) there is considerable potential for development in terms of availability of space and placing

suitable layouts; iv) the market stakeholders (UNO, UP, market leaseholder, and MMC) support the proposed construction; and v) there is an agreement to share lease income with the MMC as per GoB rules.

82. Secondary criteria: Markets which meet the basic pre-conditions have been prioritized according to the following criteria: i) the potential for poor women to participate in the construction of the market and as buyers and sellers; ii) stakeholders share a part of the

development cost to be used for the further expansion of the works; and iii) stakeholders

agree to reserve a part in all sections of the markets for temporary sellers, especially for women and small producers. As practiced in the MIDPCR project, markets will be built in collaboration with MMCs. MMCs will also be responsible for properly maintaining the markets for which they receive 25% of the lease revenues , in accordance with GoB rules. This practice is expected to ensure sustainable operations of the markets.

83. The project will not acquire any land for market development, because all development

activities will be carried out on Government owned land only.

Infrastructure for markets

84. Type I: Special market: Beside from special needs such as large ghat and large fish platform, or any different structure, a special market will have other common structures similar to a

Page 27: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

15

large market (see below). Demand for special structures has to be determined for each such

market. That is design and structures will be unique for each such market.

85. Type II: Medium markets: Subject to availability of land, a medium market under CCRIP may receive the following package of infrastructure: a) a fish shed; b) a multi-purpose shed; c) an open air platform; d) internal, paved roads; e) internal drainage and a garbage collection pit; f) a toilet block; g) a women section (8-12 shops); h) a boat landing ghat, if the market is located near a river or canal; and i) a paved truck parking area.

86. Type III: Small markets: Subject to availability of land, a small market under CCRIP can receive the following package of infrastructure: a) one to two sheds; b) an open air platform; c) a toilet block; d) internal road and drainage; and e) a ghat and truck parking space, if needed.

87. Community collection points: Subject to the needs, a community collection point may receive the following infrastructure: a) a ghat, if market is located near to a river or canal; b) a paved

truck parking space for three trucks; and c) an open air platform or simply paved space with or without shed.

88. Women section: The women‟s market section is a special facility provided women, especially

widows and other independent women. It may host 8-10 shops. The need a for women‟s market section may not be limited to special markets but also some large markets may need this facility.

89. Project Target for Markets Development: Table 4 presents project targets for this component.

The detail annual plan is presented in Annex 7A and 7B.

78. Structural design and unit costs: The structural design for each structure of markets is given in Annex 9A and Annex 9B (ghats). The detail cost calculation for individual structure of markets and unit costs for all types of markets are given in Annex 9C and Annex 8C respectively. MIDPCR/LGED has electronic version of the drawing and design information.

Table 2: Project target for main activities under Component 2

Component 2:

Improved Market Services

Community (Village)Markets and growth centres

Growth centres and large rural markets (#) 88

Type I: Special markets (#) 4

Type II: Medium markets (#) 33

Type III: Small markets (#) 160

Community Collection Points (#) 5

Women market sections (#) 15

Boat landing platform (ghat) 38

79. All markets and collection points except special markets will be built by LCS groups. The project will form LCS groups at the rate of one group of 25 poor women per market who will

be trained in construction and management. Each market will have a market management committee (MMC), which will supervise the construction and later manage the market and do routine maintenance. MMCs will be trained by the project. See Annex 7A and Annex 7B for details plan for LCS and MMC as well as training for these two groups.

80. Functions of MMCs; As per GOB rules each rural market should have a 11-member MMC

headed by Chairman of respective Union Parishad (UP). Other members include representative of shop owners, local UP member, female UP member, representative of land

administration department (Tahsildar), and representatives from temporary traders, rickshaw pullers etc. MMCs are supposed to ensure security of buyers and sellers and cleanliness of the markets, and do routine maintenance. However, often the MMCs are not active at all. The project, based on the experience of MIDPCR, will organize training courses for MMC members to help them participate in market development process, supervise LCS works and more importantly, strengthen their institutional capacity so that they perform well beyond the

project period. Special attention will be given to receiving 25% of the annual market lease funds from the Office of UNO and use that for routine maintenance and future development.

Page 28: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

16

81. The cost for each type of market has been reviewed and COSTAB has been revised

accordingly.

Component 3 - Enhanced climate change adaptation capacity

82. The outcome of this component is „Rural communities and local authorities are able to cope with volatile climate events and meet their basic needs during climatic shocks.‟ Resources from three agencies – ADB, KfW and IFAD – will be utilized to finance activities under this component. The following activities are planned under this component to be financed by KfW

and/or ADB: a) Construction or extension of 15 cyclone shelters; b) Improvement of 10 existing shelters; c) Upgrading of 15 km access tracks; d) Construction of about 5 livestock shelters - killas in selected locations; e) Enhancement of LGED MIS/GIS system enhanced; e) Design and operate special web-portal (SCF financed); f) Establishment of Communities of Practice - CoP; g) Organization about 100 training sessions on climate-proofing of rural infrastructure and knowledge management; h) Development of a climate change assessment

and adaptation strategy; and i) Development of a climate resilient rural infrastructure management plan for LGED.

94. Resources from IFAD will be allocated to train:

a) LCS members ( ca. 5000 persons) on construction of village markets and RCC roads and social issues; and b) MMC of 197 village markets on:

- participation in development of village markets,

- supervision of LCS works and

- management of markets beyond project period.

95. Innovation, Rural Radio, Studies and Project Design: IFAD has mobilized USD one million in grant to be placed under project management unit to carry out activities under two specific categories:

a) Innovation: i) development of bio-digester based garbage management in two markets, ii) research on climate resilient slope protection, and iii) introduction of quality test protocols for

road and market constructions. The three activities will be contracted out to reputed national academic institution(s) (See Annex 5 for concept notes of the three innovative activities); iv) rural radio for mass information on agricultural, markets, cultural and social topics as well as

project related information.

b) The project will conduct a baseline survey, impact and environmental studies. These will be managed by the PMO.

IFAD will manage directly, with the concurrence of GoB, a portion of the grant resources to finance the Mid-Term Review of CCRIP and the design of the forthcoming IFAD-funded project in Bangladesh.

D. Lessons learned and compliance with IFAD policies

Lessons Learned

81. The ongoing and recently completed projects offer the most relevant lessons learned in terms of project activities, implementation processes and the selection of institutions. The most relevant lessons for CCRIP can be summarised as follows (see also Annex 3):

82. Small-scale infrastructure in terms of rural markets and communication roads showed

impressive impact on the local economy and employment. The trade volume increased substantially within a short period of time, while cost of transport could be halved and local

wages doubled with the increased demand for labour. Prices increased as demand increased due to more buyers arriving from far away. The village roads built in Sunamganj have boosted the local economy and improved livelihoods. A study carried out by SCBRMP found a major change in terms of increased use of light-motorized vehicles, increased cropping intensity and expanded area under crops, especially with high value cash crops grown, and sales of crops. The cost of transporting crops and fertilizer could be halved, and more labour was being hired for both farm and non-farm businesses. Survey respondents reported increased employment

opportunities, increased wages and income, better access to education and health services, and finally, greater mobility of women. Land values near the road had more than doubled. Similar benefits have been found in the MIDPCR project area. Additional benefits would

Page 29: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

17

include a decrease in losses of perishable products as goods are sold more rapidly, decreased

transport time and costs and increased value of land and construction of other facilities (such as shops) in the area around the market. These points form also the justification of scaling up markets and communication infrastructure in the CCRIP project.

83. The on-going IFAD-funded SCBRMP project has pioneered the construction of village (community) roads using reinforced concrete (RCC). Unlike conventional bitumen road pavements, concrete roads are submersible and can withstand flooding. It has also

successfully tested use of concrete blocks in flood prone areas. Maintenance seems easier for this type of roads, as LCS can recover and place back dislocated concrete blocks after floods.

84. Roads would preferably be BC, RCC and Block roads. These roads require less maintenance and are more durable than brick based roads. RCC and Block roads are more climate resilient than the BC type as they withstand better flooding and inundation with salt or brackish water. Earthen roads may be replaced by a paved road if justified.

85. Climate resilience design requires higher and wider road shoulders (see ADB/IFAD/KFW report) and may also require adding culverts in the road infrastructure to cope with higher extreme discharge volumes than previously foreseen. In addition, water control gates may be

added at the culverts for improved water control.

86. The use of LCS as a principal mechanism for constructing markets and some village roads is an effective way of targeting the poorest women. A baseline survey for MIDPCR showed that 68% of the women members were the principal bread-winners for their families with two-

thirds of respondent households. The use of LCS instead of a commercial contractor for construction of markets and roads creates employment, enhances skills, increases cash in the hands of the poorest women and boosts their self-esteem. All village markets and block roads under CCRIP are expected to be built by LCS.

87. Agricultural development and financial services remain critical to ensure food security and employment. IFAD-funded projects show that the combination of agricultural development with access to financial services and adequate extension services augment the scale of impact

and sustainability of a new technology. A value-chain approach can ensure the input supply and diversification alongside the promotion of technology to assist farmers and micro-entrepreneurs to enhance profits, generate business and employment. Microfinance including microcredit remains critical although the financial services have expanded greatly in the country but the emphasis needs to be on developing demand driven services and customizing

the service as much as possible.

88. Management issues. It is important that the right institutions and the right mix of activities are chosen to successfully implement a project and ensure impact. LGED‟s core competence is implementation of infrastructure projects, and it has skillfully implemented both SCBRMP and MIDPCR infrastructure components whereas it struggled to deal with MFIs and managing value chain activities. In addition, combining infrastructure with financial services and value chain development means also managing very diverse activities under one project. It seems to be more efficient to separate financial services and value chain development from

infrastructure and to have LGED focusing mainly on infrastructure.

Compliance with IFAD policies

86. Targeting: CCRIP has followed IFAD‟s policy on targeting by applying a rigorous geographical targeting process for the selection of the least developed and most vulnerable Upazilas. CCRIP will also employ a specific focus on household level targeting to reach the most destitute echelon of the population which are very poor men and women headed households, as only they will be selected for participating in LCS and related construction works.

87. Gender: CCRIP‟s approach is compatible with IFAD‟s gender policy. Poor and destitute women will directly benefit as they will participate in LCS for the construction of markets and selected village roads. The experience in MIDPCR and SCBRMP confirm that by obtaining own income and learning new skills women feel socially and economically empowered leading to a strong rise in gender equalities. Besides, the construction of roads contributes to increased social and physical mobility, access to additional wage employment, access to village markets as buyers

and sellers and access to school and health services. See Annex 2 for detail discussion on gender. In the ADB/IFAD/KfW report, appendix 7, a detailed gender action plan is presented.

88. Land: There will not be any relocation of housing settlement to build roads and markets under CCRIP project component 1.2 (union and village roads) and 2.2 (village market development), and as such, no acquisition of land is foreseen. All roads and markets will be built on existing

Page 30: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

18

alignment and khas land (or land donated) for market development respectively.

Resettlement or eviction has neither been an issue in MIDPCR project nor is it foreseen in the CCRIP project component 1.2 and 2.2. The other component 1.1 and 2.2 foresee some limited land acquisition and resettlement. This will be dealt with in line with ADB land settlement frameworks as detailed in the report.

89. Environmental assessment: There is no major environmental concern in CCRIP. In fact, the development of markets with internal roads, drainage and garbage collection system will

improve the micro-environment in and around the markets. Since the markets are expected to be managed by MMC, the cleanliness in markets is expected to be maintained beyond the project period. The project must remain constantly vigilant about design specifications of culverts/bridges so that water flows in canals and small rivers are not obstructed due to narrowing width of culverts/bridges built by the project. The design mission has prepared an environmental note (see Annex 11). As per GoB rules, it is mandatory to receive an

environmental clearance from the Department of Environment by submitting a properly done environmental assessment report. This will be conducted right at the beginning of the project, as has been the case in HILIP, when funds will have been allocated under the CCRIP budget.

90. Private sector: The project may not have direct participation from the corporate private sector

but the second IFAD-funded MAPP project is expected to work with and promote private sector as part of value chain development activities. However, road and market constructions will promote business of small farmers, traders and other producers who in effect supply to

large markets as part of supply chain. It has been found in MIDPCR and other similar project areas that with good roads and improved markets large companies such as pharmaceutical, seed, fertilizer, processed food, consumer durables, construction material companies expand their marketing networks even in formerly disconnected remote areas. Therefore, the project in fact would assist larger business as well as increase access to better quality goods and services in rural areas.

Donor and GOB policy harmonisation

91. The project fits very well with the Government‟s sixth five-year plan. The COSOP 2012 reflects GoB‟s priorities and the Project Concept Note (PCN) of CCRIP is fully in line with it as well. In the sixth five-year plan (6FYP), rural roads and markets, agriculture, livestock and community-based fisheries are all focal areas for pro-poor growth. The 6FYP emphasises the need to create employment opportunities for rural poor and women in agriculture and

livestock and to build rural infrastructure to develop the rural economy.

92. The broad directions for development over a longer time-span are set out in the Perspective Plan for Bangladesh 2010-2021. Amongst other things, this plan would like to see genuine devolution of power at the local Government level, and also states that in the process of socio-economic development of the country, agriculture will still continue to play a vital role in the long run in terms of food security, generation of income and employment for rural poor and poverty eradication.

93. Other donors are also supporting the development of infrastructure in the project area.

CCRIP intends to complement rather than overlap these initiatives. The World Bank will fund a Coastal Embankment Improvement Project (2013-18) which will strengthen polders in a number of Upazilas within the CCRIP project districts. CCRIP Upazilas will benefits where embankments will protect the whole Upazilas and in these cases there will be less needs to raise the level of union/village roads, which in turn would save costs and eventually may increase lengths of roads. The design assumption is that any roads within a polder will consider scenario B that is less expensive to construct.

94. More information on lessons learnt can be found in Annex 3 “country performance and lessons learned”, Annex 4 “value chain development and infrastructure” and Annex 6 “review of rural infrastructure needs under CCRIP”. These provide detailed insights and justifications for the proposed IFAD funded interventions under CCRIP.

III. PROJECT IMPLEMENTATION

A. Approach

95. The overall project development approach has been explained in the ADB/IFAD/KfW CCRIP project document. The Upazila roads, growth centres, large markets and cyclone shelters funded by ADB/KfW will be built contractors selected through competitive bidding process.

Page 31: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

19

The project will follow the successful strategy of MIDPCR regarding the construction of

union/village roads and community (village) markets funded by IFAD. The union/village roads excluding block roads will be implemented by contractors recruited by LGED/XEN office in each project district following routine LGED contracting procedures. Block roads construction and road-side plantation will be done by LCS groups.

96. All community (village) markets except the Type I: Special markets will be constructed by LCS composed mostly of poor women (destitute women will be given preference) recruited

and trained by the project. MIDPCR has developed a set of strict standard guidelines for the formation, training, management and assistance from LGED, and profit sharing in LCS groups. CCRIP will follow also the management guidelines for market development under MIDPCR. Women sections and ghats will be built by LCS and contractors, respectively.

97. Prior to starting development of a market, an agreement will be signed with the respective Market Management Committee (MMC) formed according to GoB rules and regulations. The

11-member MMC is headed by UP chairman and represented by permanent shop-owners, women, temporary traders, van/rickshaw pullers, farmers etc.. The project, in collaboration with MMC and other local participants, prepares a „master plan‟ for each market, which is later approved by UNO to be accepted for development by the project. The MMC supervises the

construction and takes over management of the market. Each market is leased out by the respective UNO and 25% the lease value will be transferred to the MMC for routine maintenance of the market.

98. IFAD funded union and village roads and community (village) markets have already been selected through a rigorous process and are part of approved DPP. The PMO with the help of XEN and Upazila Engineer will finalize cost estimation for individual road before recruitment of contractor(s) and develop master plan for development of each selected market. These roads and markets are ready for development. The PMO will prepare annual implementation plan only. No additional selection exercise will be necessary unless any unforeseen incidence happens. It is important to note that since the selection of IFAD roads and markets is already

final they should not be linked with future subproject selection under ADB funded activities. There should not be any delay of implementation of IFAD funded activities due to any delay in subproject selection and analysis under ADB/KfW funded activities.

B. Organisational Framework

99. The project management, supervision and financial management have been devised in the ADB/IFAD/KfW report (page 19-20). In addition, a project administration manual has been

prepared incorporating implementation procedures of IFAD funded activities.

100. The executing agency will be Local Government Engineering Department (LGED) in the Local Government Division of the Ministry of Local Government, Rural Development, and Cooperatives. A project steering committee will provide policy guidance for project implementation.11 The committee will meet twice a year to review the progress of project implementation.

101. A Project Management Office (PMO) will be established at the LGED headquarters in Dhaka, with three Regional Project Offices (RPOs) located in Khulna, Madaripur, and Barisal district headquarters. The PMO will be responsible for overall management, implementation and monitoring and the RPOs will be responsible for progress supervision, monitoring of LCS works, quality control, impact monitoring and for maintaining close links with other stakeholders, for example, UNO, MMCs, UP. The construction of roads under the Improved Road Connectivity Component except for the block roads will be outsourced to professional

contractors. LGED district XENs and Upazila Engineers would be responsible for managing

these contracts. The PMO will be assisted by consultants with expertise in engineering design and supervision, climate resilience, economics and finance, social and gender development, participatory approaches, environmental and climate assessment, monitoring and evaluation, and local governance. The LGED district offices, headed by executive engineers, will be responsible for implementing subprojects under the guidance of the PMO. The project will need to coordinate with Bangladesh Water Development Board for development

11

The secretary of the Local Government Division will chair the committee, which will include representatives

from the Local Government Division; LGED; Roads and Highways Department; Planning Commission and Implementation, Monitoring, and Evaluation Division of the Ministry of Planning; Economic Relations Division and Finance Division of the Ministry of Finance.

Page 32: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

20

interventions. See also Figure 1: Project Organization Structure. See Annex 10 for further

details.

102. GOB will provide 179 fulltime staff members for the project in all four tiers of project management, namely at PMO, RPOs, XEN offices and Upazila Engineer‟s offices. A TA team comprising of international and national professional staff and support staff (8 international and 37 national professional staff, and 16 support staff with a total of 1967 men-months) will directly work as design and supervision consultants and management support

consultants.

103. Additional Human resources: The IFAD design mission has analysed functions, skill requirements and responsibilities of each tier of technical and support staff. The mission has recommended the following additional project staff financed from IFAD resources:

i. One full time Market planner at PMO level (Dhaka) to develop a master plan for each community (village) market in collaboration with LGED Upazila office and

respective market management committee;

ii. One part-time financial management specialist (Chartered accountant) at PMO to set up a double entry and software based accounting system and assist the project

keep records and prepare reports according to ADB/IFAD/KfW‟s requirements. This will complement services of financial management specialist in the ADB funded TA team;

iii. One accounts assistant to strengthen accounts keeping;

iv. One full time GIS specialist and one full-time hydrologist at PMO; and

v. 32 Sub-assistant engineers, one in each project upazila, to ensure full supervision and quality of construction of all IFAD funded infrastructure.

C. Planning, monitoring and evaluation, learning and knowledge generation

104. Planning and implementation. The PMO will be responsible for overall implementation and achieving the quantitative and qualitative targets of the project. Specifically, it will perform

the following functions:

Start Up: a) Recruit and mobilize all staff members as per plan of the project; b) train all staff members as per plan; c) recruit TA team; d) procure goods and services as

per plan; d) conduct start-up workshops as planned; e) Install accounting and financial management system; d) Install full management system;

Studies: a) Conduct baseline study; b) Conduct RIMS studies (baseline, mid-term and completion); and c) Conduct environmental study and receive environmental clearance

from the Department of Environment;

Planning: a) Prepare an annual plan for CCRIP to be cleared by ADB/IFAD/KfW; b) revise DPP;

Implementation: a) Develop village markets and union/village roads already selected by IFAD/LGED; b) prepare a road maintenance plan ; c) Prepare master plans for each market and prepare/customize engineering design for each market by following typical

designs already prepared during the final design mission; c) Customize design for union/village roads already selected; e) Select upazila road subprojects and growth centres and large markets, and complete analysis and design; f) Authorise tendering of all construction works; g) Perform all activities related to LCS, MMC, staff development and similar.

Supervision: a) Upazila engineers will supervise progress and quality of work done by the LCS groups and contractors; b) Professional staff members from RPOs will perform

additional supervisions of construction works; c) Engineers from TA team will perform independent monitoring of construction works.

Financial payment: Payments against goods and services will be made by the PMO through XENs after clearance from RPOs and Upazila Engineers.

Fund withdrawal: PMO will be responsible for the function.

Progress report: PMO will prepare all reports including financial reports for all activities. It will prepare quarterly reports and annual reports to be presented to to

IFAD, ADB and KfW.

Page 33: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

21

Coordination: PMO will be responsible for coordination with IFAD, ADB/KfW, LGD,

MLGRDC, ERD and other stakeholders of the project.

105. Monitoring and evaluation. The design and monitoring framework guides the project monitoring and evaluation along with indicators and tools The PMO will have a Monitoring Specialist and an assistant to a) organize the baseline survey by a consulting firm, b) organize three RIMS Studies – at start-up, mid-term and completion of the project, c) conduct studies on impacts of markets development, LCS, construction of roads, and other

project impact, d) prepare case studies, and e) mid-term and completion project impact studies. The team will carry out daily monitoring of progress and quality of (i) LCS activities and training, and (ii) MMC activities and training. The quality/supervision engineers of the TA team will perform independent monitoring of construction works. The PMO will prepare reports to be shared with ADB/IFAD/KfW. Details are referred to in Annex 12 and PAM.

106. Women Empowerment in Agriculture Index (WEAI) which was launched earlier this year by

USAID, IFPRI and Oxford Poverty and Human Development Initiative was piloted in Bangladesh and its use has now been scaled up by the Government in the national system. The WEAI is being considered by IFAD‟s gender team as a tool for strengthening IFAD‟s impact assessment studies and will be considered for application in CCRIP.

107. Learning and Knowledge management. The project is expected to produce important lessons and knowledge in areas such as market waste management using bio-digester, protection of slopes of roads, quality assurance for constructions by developing engineering

testing protocols, management of rural infrastructural project, impact on livelihoods, overall impact of the project, appropriateness of various types of roads (RCC, BC, block road), role of and impact on LCS and poverty, complementary role of value chain project etc. These will be gathered in the form of implementing three pilot initiatives mentioned earlier, impact studies, case studies, field visit observations, progress reports, newsletters, occasional papers etc. The project will share them with IFAD/KfW/ADB, Government and other national and international stakeholders by widely distributing, publishing them on websites as well

organizing seminars and workshops. It will use IFAD‟s knowledge management network to publish all activities as well as studies and publications. IFAD will have a KM Specialist in Bangladesh who may also be involved in disseminating project information and other documents and publications. See Annex 12 for further discussion on planning, M&E and knowledge management.

108. The project will support the recently start rural community radio initiative in Bangladesh to

enhance the dissemination of important information for farmers and small producers such as market days, commodity prices, weather forecast and messages for extension of crop, fish and livestock production. CCRIP will explore collaboration with the FAO-supported Krishi radio. This activity will be funded from the built-in IFAD grant.

109. Supervision and evaluation: IFAD, ADB and KfW will carry out joint supervisions. Besides ADB/IFAD/KfW annual supervision mission, an independent mid-term and final evaluation will also be conducted. As in the case of MIDPCR and other projects, mission reports will be

the important sources of knowledge about the progress, quality, lessons and impact of the project.

Page 34: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

22

Figure 1: Project Organization Structure

Local Government Division (LGD)

Ministry of Local Government, Rural Development and Cooperatives

Project Steering

Committee

Chairperson – Secretary, LGD Local Government

Engineering Department Chief Engineer

Project Management Office 1 Project Director; 2 Deputy Project Directors

Regional Project Office

(Barisal) Deputy Project Director

Regional Project Office

(Khulna) Deputy Project Director

Regional Project Office

(Madaripur ) Deputy Project Director

Project Implementation Units

(ADB/SCF – 12 districts, KfW 3 districts and IFAD - 12 districts) Executive Engineers, Upazila Engineers at Upazila Offices

Project Stakeholders (Upazila/Union Parishad Chairpersons, Market Management Committees, Beneficiaries

Design and

Supervision

Consultants

and

Management

Support

Consultants

Page 35: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

23

D. Financial management, disbursement, procurement and governance

Financial management and disbursement.

110. The mission has sought to ensure that the financial management arrangements proposed for CCRIP are sufficient for the effective and efficient usage of funding in alignment with those of the other financiers. To this end the Financial Management Assessment Questionnaire (FMAQ) at Design and the Risk Analysis using the Guidelines for Financial Management at

Design, conducted for SMILE, has been revisited and updated (See Annex 13). Additionally, this mission visited a village in the Noakhali District of the MIDPCR project to further explore the workings of the Labour Contracting Societies (LCS) to assess the sufficiency of the financial management systems and ensure that arrangements are adequate to mitigate risks of funds flow to the ultimate beneficiaries.

111. The mission has reached the conclusion that fiduciary risk is rated at medium and the financial management arrangements, as they exist in MIDPCR, would not provide the

maximum assurance that the funds are used, efficiently and effectively, for the purposes intended. Therefore, the areas in which change is recommended are – (1) procurement and

installation of a multi-lingual accounting software before implementation begins; (2) hiring of a financial management specialist or a chartered accountancy consulting firm, on a part-time basis to ensure the appropriate use of the system and of the financial management arrangements; (3) ensuring that sufficient accounting staff, with appropriate qualifications

and experience, are recruited; and (4) to maintain sufficient liquidity in the accounts, payments will be made from the PMO to the District bank account based on receipt of a certified summary sheet of works performed by contractors from the XEN. Note that the financial management risks assessed (see Annex 13, Appendix 3) are mitigated by the fact that IFAD and the collaborating co-financier (ADB) will assign the responsibility to a “quasi-independent” Project Management Unit (PMO) within the LGED structure.

112. Budgeting: The PMO will be responsible for the budgeting as part of the AWPB exercise.

With respect to Government of Bangladesh (GoB) financing, the counterpart funds are budgeted in the DPP and released in four instalments. Occasional delays in release of GoB funds are noted.

113. Funds flow and Disbursement Arrangements: The Project will use the revolving fund method for the Designated Account advances. Advances to the Designated Account(DA), for

the Loan and the Grant, will be transferred in USD to two separate accounts held in USD at Bangladesh Bank. The funds from this account will be transferred to an operational account

that is Project Account (held in a commercial bank in Taka) to be administered by the Project Director (PD) who will, based on type of expenditure and utilization, transfer funds to the 12 district bank accounts (held at commercial banks) administered by the respective Executive Engineers (XENs), who will follow the funds flow chart (See Annex13, Appendix 1).

114. Documentation of expenditures made from the DA will be done, at a minimum, on a monthly

basis following the statement of expenditures thresholds indicated in the Letter to the Borrower (LTB). To align IFAD with ADB, the SOE threshold is set at USD 100 000 equivalent for all categories of expenditures. Direct payments from IFAD may be made to suppliers/ contractors/consultants per the instructions in the LTB.

115. Funds, for all activities, except contracts performed by contractors, will be transferred to the District Office Bank Accounts (maintained separately for the Project), at the start of each quarter or as per requirement from those offices. These requisitions must be prepared based

on realistic forecasts for the upcoming quarter and must be net of the closing cash balance of the quarter just ended. To avoid delays in reporting from sub levels to the PMO, they will need to send only Excel files of their Cash Book (clearly indicating Category & Component of expenditure and source of funding), Bank Statement and bank Reconciliation Statement to the PMO on a monthly basis. It will be the responsibility of the PD and the Accountant to ensure that there is no build-up of idle funds in the project sub-accounts.

116. Funds for contractor payments: To ensure an efficient utilization of funds between 12

districts and limit the amounts of unutilized resources, the payments for all contractors will be made on receipt of a summary of contractors bills passed for payment at the District Offices.. The summary sheet, certified by Upazila and District engineers, will be prepared and submitted by the XEN to the PD, who will review and approve the payment to the

Page 36: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

24

District bank account via electronic transfer. The summary sheet will be sent to the PMO on

an expedited basis.

117. As the accounting system is expected to be in place before implementation begins, retroactive financing is recommended for the procurement of the software, the hiring of the project finance manager, the 2 accountants and training costs for the same.

118. Internal Controls: Internal control systems at the PMO were assessed based on those in existence for the on-going project also implemented by LGED and found to be weak with

respect to segregation of duties; retention of records; security of information. The risks have been mitigated by ensuring the following is in place (as described in Section F) before implementation commences. Assessments of the internal controls will also be included in the TORs for the internal audit department of LGED. Procedural aspects related to Financial Management and Disbursements are detailed in the live document – the Project Implementation Manual (PAM), allowing for revisions when these controls are assessed to be

risky.

119. Financial Accounting and Reporting: GoB and all institutions under its purview maintain their records per Bangladesh Accounting Standards. The last Report on the Observance of

Standards and Codes (ROSC) is dated (2003) but significantly states that gaps exist between the Bangladesh Accounting Standards and International Accounting Standards. It is noted that GoB maintains accounts using single-entry, cash basis accounting. At a minimum IFAD expects that projects maintain their books using IPSAS cash basis. As the

single-entry account is deemed insufficient for this project, the procurement of an off the shelf accounting software, with local language capabilities should be in place before implementation commences. The mission had requested and received a demo of an off the shelf software and found the requirements compatible with the project. All finance and accounting staff at the PMO will be trained on double-entry accounting to build capacity to international standards. The project accounts will reflect all financial transactions during the project period, both of the IFAD loan/grant and other sources of financing by project

component and separately by standard expenditure categories. Reporting requirements are detailed in the PAM.

120. Internal audit: The LGED internal audit unit has 15 internal auditors that prepare an annual work plan with respect to Districts and Projects selected for audit. In the internal audit of Districts, both, GoB and Donor funded projects are examined. The financial capacity

and staffing of the IA department is adequate to perform this task. It is possible that a

project might not get selected for internal audit and therefore clarification was sought and the following recommendations are made on the basis of the responses: (1) the project may request the internal audit cell to perform an internal audit on the project. IFAD recommends that in the event the project is not chosen for internal audit, a request will be made in all years after the first year of implementation; (2) draft TORs for the internal audit will be provided by the PMO (with the assistance of the Donors) to the Audit and Accounts Cell; and (3) in the event that IFAD is not satisfied with the internal audit arrangements and

reporting, IFAD can recommend the hiring of an external chartered accountancy firm to conduct an internal audit.

121. External Audit: The external audit for all donor-financed programmes/projects is conducted by the Foreign-Aided Projects Audit Directorate (FAPAD). FAPAD will also conduct the audit for CCRIP. TORs, to ensure that all financiers‟ requirements are being met, will be harmonized and presented to FAPAD before the audit exercise commences. Prior audit works of FAPAD have been rated as satisfactory, thereby showing FAPAD‟s compliance with

its TORs and IFAD Project Audit Guidelines. FAPAD will utilize International Standards of Auditing when undertaking its audit work. As the fiscal year end of CCRIP will be June 30,

the audited financial statements are due at IFAD no later than December 31 (within six months). The audit report will contain a separate management letter with an opinion on the Internal Control system of CCRIP and related audit observations; separate opinions on certified Statements of Expenditure (SOE), the Special Account and the Project Financial

statements; a statement as to the adequacy of the accounting system and internal controls and whether IFAD funds have been used for their intended purpose; a confirmation that SOEs correctly reflect the expenditures incurred; and commencing with the second year audit a follow-up on the implementation of prior year recommendations. Annex 14 on Procurement, and are presented in details in Working Paper 4. Figure 2 further below show the flow of funds in CCRIP.

Procurement

Page 37: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

25

122. Procurement of goods, works and services financed from resources provided or administered

by IFAD will be undertaken in accordance with IFAD‟s Procurement Guidelines and Handbook (dated September 2010, or as amended from time to time). In all cases whereby procurement is packaged along with goods, works and services financed by ADB, the procurement would be undertaken in conformity with ADB‟s Procurement Guidelines (2010, as amended from time to time) and ADB‟s Guidelines on the Use of Consultants (2010, as amended from time to time).

123. International Competitive Bidding (ICB) shall be undertaken in accordance with the rules and regulation for ICB as established by the World Bank in line with the provisions of the IFAD Procurement Guidelines. Goods and Civil works and goods procured using NCB will follow the Public Procurement Act, 2006 and Public Procurement Rules, 2008 of the Government of Bangladesh. All procurement to be financed by IFAD proceeds require the details of the procurement, types of procurement methods, the need for pre or post-qualification,

estimated cost, prior or post review requirements to be respectively included in the Procurement Plan to be submitted by the PCO. IFAD‟s approval of the procurement plan is mandatory and any changes or modifications must be communicated and approved by IFAD.

124. All procurement for goods, works and services financed from resources funded or

administered by IFAD require bidding documents and the contracts to include a provision requiring suppliers, contractors and consultants to permit IFAD to inspect their accounts ,records and other documents relating to the bid submission and contract performance, and

to have them audited by IFAD-appointed auditors.

Page 38: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 39: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

27

Figure 2: Flow of Funds

International Fund for

Agricultural Development

(loan & grant) (IFAD Loan, IFAD Grant)

Asian Development Bank

(ADB Loan, SCF Loan, SCF

Grant)

Kreditanstalt fuer

Wiederaufbau

(KfW Grant)

Commercial Bank (Approved by Ministry of Finance)

Project Account (LGED)

(Operated by Project Director)

Regional Project Offices Project Implementation

Units (District Executive

Engineers)

National Suppliers of Works, Goods and

Services (Project Area)

National Suppliers of

Works, Goods and Services (Dhaka)

Foreign Suppliers of

Works, Goods and Services

(International)

Commercial Bank (Approved by Ministry of Finance)

Disposition Fund (LGED)

(Operated by Project Director)

Legend: Foreign currency flows

Local currency flows

Page 40: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

28

125. All advance contracting and retroactive financing of resources provided or administered by

IFAD regarded as an exception by the IFAD General Conditions must be clearly established (detailed cost and procurement packages) in the Project Design Document and approved by the IFAD and will be undertaken in conformity with provision of IFAD General Conditions and

IFAD Procurement Guidelines and Procurement Handbook (2010, as amended from time to time). The issuance of invitations to bid under advance contracting and retroactive financing will be subject to IFAD prior review and no objection. The approval of advance contracting and retroactive financing does not commit IFAD to finance the Project.

126. Procurement of civil works should be undertaken in sizable bid packages ensuring road works are not split to accommodate contractors financial capacities to qualify for the bidding or to intentionally avoid seeking IFAD prior review. Any civil works which are to be split into

small bid packages due to specific implementation consideration must to clearly established and highlighted in the procurement plan.

127. Civil works undertaken by the Labour Contracting Societies (LCS) which would be formed through a defined selection criteria, contracted directly by the CCRIP Project. The selection criteria and the operational and implementation arrangement for the LCS would be defined in the Project Administration Manual. While the LCS has been accessed as incapable of handling

implementation, administration, financial management and procurement of the activities, the Project Administrative Manual (PAM) shall define the roles and responsibilities of the intermediaries who will assist the LCS in performing the activities.

128. Procurement of materials and goods by the LCS for the civil works contracted would be undertaken in accordance with the provision of the IFAD Procurement Guidelines and shall be largely limited within the markets in each district. Any requirement for the Project to purchase specific goods from markets in outside of the district shall be justified and

documented by the Project. This justification should provide details of materials and goods to be purchased and reasons for the purchase which included a comparative analysis of the cost of procuring the materials in markets outside the district where these activities are implemented.

129. As highlighted in the FM section, a double entry accounting software would be introduced and this ERP software would facilitate in the tracking of monitoring of contracts, inventories and vendors payments. The software however would be managed by the PMO which requires

manual monitoring of these contracts by the District and Upazila Offices.

130. IFAD shall introduce as a control measure as part of its annual supervision mission or as separate mission biennial reviews of the LCS contract performance with regards to the implementation of activities contracted which includes the accounting and procurement of goods and materials carried out by the LCS (with the assistance of the intermediaries).

131. IFAD will undertake to review the provisions for the procurement of good, works and

services to ensure that the procurement process is carried out in conformity with its Procurement Guidelines. The extent to which these review procedures will be applied to CCRIP will be defined in the letter to the Borrower/Recipient and the procurement plan.

132. Project Procurement Thresholds. International Competitive Bidding (ICB) shall be the mandatory procurement method for activities estimated to cost: (i).Goods estimated to cost above USD 200,000 or equivalent; (ii). Civil works estimated to cost above USD 1,000,000.00 or equivalent; and (iii). Services estimated to cost above USD 100,000 or

equivalent. All other threshold shall be defined in the letter to the borrower/recipient.

Governance

133. A framework for good governance has been included in the ADB project document and the PAM. These address important governance aspects such as anti-corruption, accountability, assessment of financial management and procurement system, internal and external audit and institutional arrangement for project implementation. This framework aims to ensure: (i) transparency, with information in the public domain; (ii) accountability in the use of

resources; and (iii) participation with the people having a voice in decisions that may affect them. The involvement of affected communities in all stages of projects can simultaneously improve development outcomes and reduce the scope for fraud and corruption. Key features of this framework are:

Inclusive targeting of women and disadvantaged households.

Local level participation in planning with participation from Union Parishad (UP)

representatives.

Page 41: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

29

Community and participatory monitoring of project activities, training of MMC, and

LCS members in accounting and management, making payments in public to LCS members.

Audits of project accounts – both internal and external.

IFAD supervision and support, including spot checks by regular supervision missions, implementation support for financial management and procurement, and technical audits if needed.

Regular outcome surveys will provide information on how well project outputs are being delivered – both in terms of coverage and quality.

Reporting of results to IMSC, ADB, IFAD and KfW and to local Government institutions, with key information published on a project website.

Complaints and remedies mechanism including circulation of phone numbers of project group leaders and project managers.

134. In addition, the ADB/IFAD/KfW report presents a detailed Gender Action Plan (appendix 7) covering issues from women involvement in the infrastructure construction to enhance their capacities and empower them. The environmental examination (appendix 8) assist the

design in assessing the potential impact of project interventions. The resettlement

framework (appendix 10) will assist in dealing with issues of land acquisition for the infrastructure improvements which are eventually needed.

E. Supervision

135. The main responsibility of project supervision will remain with the PMO. LGED is charged with detailed preparation of tender documents for Market Development (physical) and Transport Infrastructural works. After an independent evaluation of bidders and awarding of

contracts, supervision staff is assigned to supervise the implementation of contractors. The staff in charge must be fully independent and be given adequate allowances to function independently. They should be provided with transport (motorbikes + fuel), a small digital GPS equipped camera, technical equipment, allowances to stay at sites, do routine supervision and make surprise visits. They should report their findings of contractors‟ performance to the RPO and PMO and call on LGED to intervene as needed according to prevailing procedures.

136. IFAD, KFW and ADB jointly will conduct regularly supervision and review missions to verify the performance of the project and to monitor physical progress as well impact. It also provides detailed technical and management recommendations to PMO, which were found very useful and effective in MIDPCR. All partners will conduct the MTR, impact studies and a final project completion review as per standard practice.

F. Risk identification and mitigation

137. The revised project design and monitoring framework reflects the summary of some of the key risks which have been presented in the ADB/KfW/IFAD draft final report (page 25 and appendix 11). The risks and proposed mitigation measures are presented in Table 5.

Table 3: Risk analysis

Design and Monitoring Framework

Risk Probability of occurrence

Impact on project

objectives

Mitigating measures

Goal

Natural disasters destroys project investments

Medium-high High Coordinate with other agencies/projects for protection/climate adaptation measures and post-disaster rehabilitation; Accelerate construction works after disasters creating employment for the poor.

Real price of rice and other essential commodities consumed by the poor increases relative to wage increases.

Medium Medium MAPP project starts as planned and expands activities in project areas. MAPP will support diversification and commercialisation of smallholder production.

Page 42: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

30

Design and Monitoring Framework

Risk Probability of occurrence

Impact on project

objectives

Mitigating measures

Development Objective

Lower than expected economic growth accompanied with inflation

Medium Low CCRIP and MAPP project complement each other to boost the local economy and render it more resilient to external shocks.

Outcome

Project roads and markets are damaged by tidal surges, floods in some Upazilas

Medium High Climate standards being introduced; strong supervision for road and market construction; hydrological issues properly considered in design, especially for construction sites located near rivers.

Outputs

Price escalation reduces project output

Medium Medium Price & physical contingency have been included in total project costs. GoB rules for price escalations will be enforced and supervised.

Performance of implementing agencies including corruption

High High Internal and external audit being implemented and followed up; IFAD direct supervision assesses regularly the compliance of fiduciary aspects

GOB rules do not allow

direct procurement of services from LCS groups

Low Medium Assurance to recruit LCS is sought

for from GoB. Alternative will be to use contractors.

Limited availability of khas land for market development

Low Medium Only markets with assured khas land will be accepted for development; proper agreement will be signed with MMCs prior to development.

IV. PROJECT COSTS, FINANCING, BENEFITS

A. Project Costs

138. Project costs are estimated as of October 2012 prices. Estimates for vehicles, equipment, salaries, local technical assistance, DSA, operation and maintenance were based on recent data provided by LGED. The costs of the IFAD-funded activities were estimated by the IFAD team using revised 2012 LGED rate schedule. The costs of the ADB- and KfW-funded activities were finalized and presented during a joint fact-finding mission of ADB, IFAD and KfW in June 2012. Both teams used the same technical assumptions in the cost estimations of their respective activities: number of project years, physical contingencies, exchange rate

and inflation rates. The costs of union and village roads were estimated on the basis of “B” and “C” scenarios; the “C” scenario applies only on the areas outside polders; village roads are all estimated on the basis of scenario “B”. During the final design mission carried out by IFAD, the IFAD-funded activities were updated in order to keep consistency between unit costs and to avoid duplication of the project activities. The project is estimated to cost $150.0 million.

Page 43: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

31

Table 4: Components Project Cost Summary

% % Total

(BDT Million) (US$ Million) Foreign Base

Local Foreign Total Local Foreign Total Exchange Costs

A. Improved Road Connectivity

1. Upgraded Upazila Roads 2,314.1 257.1 2,571.2 28.2 3.1 31.4 10 23

2. Upgraded Union and Village Roads 4,122.0 458.0 4,580.0 50.3 5.6 55.9 10 42

Subtotal 6,436.1 715.1 7,151.2 78.5 8.7 87.2 10 65

B. Improved Market Services

1. Upgraded Grow th Centers and Large Markets 748.6 83.2 831.8 9.1 1.0 10.1 10 8

2. Upgraded Community Markets 558.0 62.0 620.0 6.8 0.8 7.6 10 6

Subtotal 1,306.6 145.2 1,451.8 15.9 1.8 17.7 10 13

C. Enhanced Climate Change Adaptation Capacity

1. Enhanced Capacity and Know ledge Management 193.2 21.5 214.7 2.4 0.3 2.6 10 2

2. Upgraded Climate Disaster Shelters 582.9 64.8 647.7 7.1 0.8 7.9 10 6

Subtotal 776.2 86.2 862.4 9.5 1.1 10.5 10 8

D. Project Management 1,194.6 369.9 1,564.5 14.6 4.5 19.1 24 14

Total BASELINE COSTS 9,713.5 1,316.4 11,029.9 118.5 16.1 134.5 12 100

Physical Contingencies 873.1 95.5 968.6 10.6 1.2 11.8 10 9

Price Contingencies 2,177.3 270.6 2,447.9 1.4 0.2 1.6 11 1

Total PROJECT COSTS 12,763.9 1,682.6 14,446.4 130.5 17.4 147.9 12 110

Interest During Implementation - 205.0 205.0 - 2.2 2.2 100 2

Total Costs to be Financed 12,763.9 1,887.6 14,651.5 130.5 19.6 150.0 13 112

139. The CCRIP is estimated to have an overall cost of US$ 150.0 million (total investment and incremental recurrent project costs including physical and price contingencies), of which ADB will be financing US$ 20 million through ADB‟s Special Funds resource (loan), another US$20

million through ADB Strategic Climate Fund loan and a US$10 million grant, both to be administered by ADB. For the outputs proposed to be financed in parallel by KfW, KfW will provide a grant of €7.157 million (US$ 8.8 million). The Government of Bangladesh will provide US$31.2 million equivalent, including LGED staff salaries and operating costs, land acquisition and resettlement costs as well as identifiable taxes and duties as no taxes or duties could be financed out of the proceeds of the IFAD loan.

140. IFAD financing. The IFAD loan for CCRIP will be in the amount of approximately US$39.5

million is herewith presented for approval by the IFAD Executive Board. An IFAD grant of US$1.0 million has been included in the project and will finance: a) innovation research, rural radio program and knowledge management, b) baseline survey, c) impact studies, d) RIMS studies, e) studies for the mid-term review and project completion, and f) studies to support the design of the next IFAD funded project

141. The financing plan is presented in Table 5. The details of project cost, financing and annual targets over the project period are presented in Annex 7A and 7B (XL file).

Table 5: Financing Plan by Components (US$ Million)

Components by Financiers

(US$ Million) ADB SCF Loan SCF Grant IFAD First Loan To be determined a/

IFAD Grant KfW The Government Total

Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount %

A. Improved Road Connectivity

1. Upgraded Upazila Roads 15.1 43.2 13.5 38.7 - - - - - - - - - - 6.3 18.1 34.9 23.3

2. Upgraded Union and Village Roads - - - - - - 32.8 52.9 17.5 28.2 - - - - 11.8 18.9 62.1 41.4

Subtotal 15.1 15.5 13.5 13.9 - - 32.8 33.8 17.5 18.1 - - - - 18.1 18.6 97.0 64.7

B. Improved Market Services

1. Upgraded Growth Centers and Large Markets 4.3 38.4 4.9 43.3 - - - - - - - - - - 2.1 18.3 11.2 7.5

2. Upgraded Community Markets - - - - - - 5.5 65.6 1.5 17.4 - - - - 1.4 17.0 8.4 5.6

Subtotal 4.3 22.0 4.9 24.8 - - 5.5 28.0 1.5 7.4 - - - - 3.5 17.7 19.6 13.1

C. Enhanced Climate Change Adaptation Capacity

1. Enhanced Capacity and Knowledge Management - - - - 0.8 31.1 0.3 10.8 0.1 1.9 1.0 37.1 0.3 9.6 0.3 9.4 2.7 1.8

2. Upgraded Climate Disaster Shelters - - - - - - - - - - - - 7.3 82.8 1.5 17.2 8.8 5.8

Subtotal - - - - 0.8 7.4 0.3 2.6 0.1 0.4 1.0 8.8 7.5 65.5 1.8 15.3 11.5 7.7

D. Project Management - - 1.6 7.9 9.1 46.2 0.9 4.4 0.4 2.3 - - 1.3 6.6 6.4 32.6 19.7 13.2

Total PROJECT COSTS 19.4 13.1 19.9 13.5 10.0 6.7 39.5 26.7 19.5 13.2 1.0 0.7 8.8 6.0 29.8 20.1 147.9 98.6

Interest During Implementation 0.6 28.7 0.1 3.2 - - - - - - - - - - 1.5 68.0 2.2 1.4

Total Disbursement 20.0 13.3 20.0 13.3 10.0 6.6 39.5 26.3 19.5 13.0 1.0 0.7 8.8 5.9 31.2 20.8 150.0 100.0

a/ Additional financial needs will be, as applicable, funded as a second loan from the 2016-2018 PBAS and will be submitted to the Executive Board in 2016 for approval.

B. Summary benefit and economic analysis

142. Given the merging of the Sustainable Market Infrastructure for Livelihoods Enhancement

(SMILE) Project with the Climate Resilient Infrastructure Improvement in Coastal Zone Project (CRIICZP) co-financed by ADB, the initial analysis carried out for the SMILE has been updated to include additional activities funded by ADB. The analysis of the ADB-funded activities has been done by the ADB team and included in the Bank‟s project documents

Page 44: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

32

submitted to the Board. The CCRIP analysis aims to consolidate the analyses of both IFAD-

and ADB-funded activities.

Beneficiaries

143. The beneficiaries include (i) LCS groups; (ii) market operators, traders, and market users (iii) road users (i.e., bus and truck owners and operators, passengers, and businesses using freight services); and (iii) communities in the areas of influence of subprojects who will have improved access to services and increased employment opportunities.

144. An overall estimate of 3.5 million people will benefit from the project. Direct beneficiaries include: 5,000 participants contracted to LCS (at least 80% of who will be very poor women, with priority for women-headed households); 162,400 traders in the markets under the

project; 52,600 transport owners; and 235,000 households members living in the areas of influence of subprojects. See Annex 15 for detail estimation.

145. Given the nature of investments and the interconnection between them, the same beneficiaries within the community might benefit from different investments.

Table 8: CCRIP beneficiaries

Beneficiary type Beneficiaries (#)

Nature of benefits

I. Overall beneficiaries

1 Households in market and road catchment areas

[125 Unions:583 300 HH]

3.5 million Improved transport and access to market, educational institution, health services; improved livelihoods opportunities due to increased investments.

II. Direct beneficiaries, of which

1 LCS members for construction of markets and block road (at least 80% are poor women)

5,000 Assured employment as day labour; profit from LCS contracts; skill development; investments in income generating activities.

2 Permanent shop owners and temporary traders (growth centers, community markets, and collection points)

162,400 Increased sales due to increased buyers and future investments; increased profits

3 Transport owners 52,600 Increases in income

4

HHs living within market and

road catchment area

[455,000 HH]

2,730 800

Improved access to buyers, better price,

improved access to good quality inputs and support services.

HH: households

Benefits

146. Quantified Benefits. The project is expected to generate substantial net incremental benefits to farmers and rural entrepreneurs (shop keepers, traders, transport owners). The benefit stream comprises the following elements:

147. Market infrastructure development benefits. Improved and expanded market infrastructure (Growth Market Centers, village markets sheds, drainage systems, sanitary

latrines, garbage pits, etc.) will have two categories of direct beneficiaries: (i) permanent traders (shop-keepers); and (ii) temporary traders of daily morning/afternoon markets and more, importantly of haat days (twice a week). Impact assessment of the MIDPCR project,

as well as the field visits and interviews conducted by the ADB and IFAD missions,

demonstrate that the incremental benefits for market infrastructure investments

will come from: (i) reduction in spoilage of perishable products; (ii) increased

sales, through higher volume and value of the agricultural produce traded; and (iii)

increased number of traders at the village markets.

148. Upazila, village and union roads construction: The project will be building mainly three types of roads: (i) upazila roads; (ii) village roads and (iii) union roads. The benefits from

Page 45: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

33

these rural roads are mainly derived from the generated commercial activities. The

estimation of the benefits is made on the basis of the earnings expected from these new activities. Incremental benefits from these investments will be: (i) from upazila roads - vehicle operating cost savings from the existing traffic using the roads as well as from the

new traffic generated; (ii) from village roads - increased volume of transported goods (mainly agricultural production) and reduced transportation costs; and (iii) from union roads - increased traffic, reduced transportation costs for goods and passengers (due to the vehicle operating cost savings).

149. Agriculture production benefits: Farmers living within the market catchment area and the road catchment area will be able to increase the volume of the agricultural production sold due to the increased traffic and will be able to fetch higher selling prices due to larger

numbers of buyers coming to the market and hence higher demand for the agricultural production. In addition, farmers will also benefit from the reduced transportation costs and better access to markets and inputs contributing to higher productivity at the household level.

150. Benefits to the transport owners: Construction of the village and union roads will have an impact on the small private entrepreneurs/vehicle owners. The vehicles operating on this

type of rural roads will be of two types: (i) motorized vehicles (mainly CNG/Tempo/Motor cycle) and (ii) non-motorized vehicles (such as rickshaw/ rickshaw van). The results of the MIDPCR impact assessment study demonstrate that, even if the average fare per km decreases, it is more than compensated by the volume of traffic generated by a new road (and the number of additional journeys per vehicle) as well as by the travel time and the vehicle operating costs savings. The motorised vehicles will also benefit from the increased fuel efficiency while for the non-motorised vehicles the improved smooth surface of the road

will reduce the pain and the difficulty of the driver to pedal the rickshaw.

151. Income Generating Activities undertaken by the LCS members: Some of the Local Contracting Societies‟ members will be willing to invest a portion of wage and profit received after the completion of the construction works (about 10% of the construction cost) in sustainable income generating activities. A recent report on impact market assessment of the MIDPCR project (September 2011) demonstrates that almost 89% of the households participating in the LCS had invested some of their income in different IGA activities.

152. Non-quantified Benefits. In addition to the quantifiable benefits, the project interventions will yield some benefits related to the project activities that are much more difficult to

quantify in monetary terms; thus they were not included in the economic analysis. However, they certainly amount to substantial socio-economic values. Among the non-quantified benefits are the following:

a. Improved communication, better access to a wide range of social services including

both educational and health facilities through improvement of the road network;

b. Improved hygiene standards in the markets. During the interviews with the MIDPCR traders, many of them recalled the problems of the old market, when they had to move around in knee-deep mud in the monsoon and in dust in the dry season. The market improvements in terms of better water supply, toilet facilities, general cleanliness and security make the market more attractive to customers and vendors;

c. Human lives saved with the cyclone shelters. Assessing the economic benefit of a cyclone shelter is fraught with difficulty, as it is difficult to predict how many people and the type and number of livestock that will actually use a shelter in any given circumstance and perceived risk. Furthermore, it is extremely difficult to

attach a monetary value to a human life, compared with that of financial damage to or loss of assets.

d. Capacity building of Market Management Committees and Banik Samities

(Shopkeepers associations) and their higher involvement in market maintenance and functioning.

e. Increased possibilities of income generation for women and positive impact on women‟s empowerment through LCS activities and development of women‟s market sections in the markets and increased women‟s trade.

Page 46: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

34

Financial and Economic analysis and sensitivity

153. The detailed financial and economic analysis is presented in Annex 16 of the project design documents. The financial analysis aims at demonstrating that income-generating activities on farm (related to the main commodities supported by the project) and off-farm (mainly

trade), as proposed in CCRIP, are profitable and sustainable. While the economic analysis aims at demonstrating that, from an economic perspective, the project as a whole is viable, taking into account, as much as possible, all quantifiable and additional costs and benefits in with and without project situations.

154. For the purpose of the financial analysis, a number of indicative economic activities, which will benefit from CCRIP, were identified during the project design process. In total eight illustrative models (six crop models, one livestock model/dairy and one fishery model) were

prepared to illustrate the impact of the potential investments on agricultural production within markets and roads catchments areas.

155. For the economic analysis, the incremental quantifiable benefit stream comprises following elements: (i) benefits from upazila, village and union roads improvements; (ii) benefits from growth market centres (GCM) and village market infrastructure development; (iii)

agriculture (crop, livestock and fish) production benefits.

156. The illustrative crop, livestock and fishery models prepared for the purpose of the financial analysis (as described above) have been used for the calculation of the overall benefit stream from the agricultural production, on the basis of economic prices. In addition to that, for the economic analysis, three separate models have been developed to illustrate the benefits from roads and market infrastructure development. The models are presented in the relevant Appendix of the Annex 10 of the project documents.

157. Cost Stream. In order to estimate the project's economic viability, in the form of the

Economic Internal Rate of Return (EIRR), the cash flow calculated includes the project base costs (as extracted from the COSTAB tables) with their physical contingencies but without taxes and price contingencies (therefore in constant BDT). The costs include all investments for all project components as well as their replacement (for transportation, office and computer equipment/materials, etc.) and recurrent costs (mainly operation and maintenance for transportation, equipment and materials).

158. Project Estimated Return. The base case Economic Internal Rate of Return (EIRR) is

estimated at 16% over 20 years. The base case net present value of the project‟s net benefit stream, discounted at 12%, is BDT 2,414 million.

159. Sensitivity analysis. Sensitivity analysis assessed the effect of variations in benefits and costs and for various lags in the realisation of benefits. A number of scenarios were tested to establish the economic viability of the total project in the event of adverse factors. The EIRR is relatively stable with regard to cost increases, benefit reductions and lags. Even in the

case of extreme delays of the realisation of project benefits of two years or a relatively unsustainable nature of project benefits, represented by an annual 20% decrease of benefits, the EIRR remains equal or above the assumed opportunity cost of capital of 12%.

C. Sustainability

160. Three aspects of sustainability of the project are defined as follows:

Sustainability of benefits to the population in general and direct beneficiaries in particular

is defined as the continuity and the enhancement of benefits due to better access to transport and market infrastructure;

Sustainability of transport and market infrastructure is defined as good usable conditions of physical infrastructure; and

Sustainable management of market is defined as clean and properly maintained markets where number of buyers and sellers and sales increase over time.

161. Sustainability of benefits. The benefits to the households in the catchment areas in the

form of access to health services and schools, access to better agricultural inputs and processed goods, increase in mobility and so forth are expected to be sustainable although may periodically be hampered due to poor maintenance. As seen in MIDPCR, roads and improved markets lead to increases in sales by traders in the markets, new shops and houses in their vicinity and additional investments in production. The number of motorized traffic is also expected to increase and continue. The increase in prices of agricultural

Page 47: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

35

commodities due to an increased number of buyers is expected to continue once supply

chains are established. Prices could decrease due a natural disaster but would recover quickly. Similar to MIDPCR, additional investments in high value agriculture such as livestock and fisheries are expected to increase and continue when good inputs such as fingerlings

and support services such as animal health care are available in a reliable fashion. These aspects of impact are expected to be further strengthened due to the implementation of MAPP, which will bring agricultural finance and value chain development activities.

162. Sustainable infrastructure. The responsibility of road maintenance rests with LGED, which receives an annual budget to maintain roads constructed under various projects. However, the availability of resources may be uneven and not on time, which could cause the creation of potholes along the BC roads. To reduce such incidence the project would give emphasis

on good quality construction as planned; and independent monitoring will be critical in this respect. Construction of RCC roads reduces maintenance problems.

163. Sustainability of market management. Cleanliness and proper repair and maintenance of markets depends on the capacity and responsiveness of MMCs. The project will construct garbage pits, and MMCs need to ensure that the market leasee (Ijarader) cleans the markets after hat days. The project will train market committees and encourage them to

elect active persons in the MMCs. The repair and maintenance will depend on lease value and availability of 25% lease value to MMCs. IFAD should negotiate with GOB to ensure regular competitive bidding to lease out the markets.

164. Exit Strategy. The exit strategy is built in the design: roads will be handed over to LGED/GOB and markets will be taken over by UNO but will be managed by MMCs, where the UP chairmen are ex-officio presidents.

165. Assurances. Government confirmed that maintenance funds for all constructions built

under CCRIP will be allocated throughout and beyond the project implementation period, in the amount that is sufficient to ensure that investments remain at the level of its original construction quality.

166. In addition, Government agreed to develop sustainable road maintenance plan for all constructions under CCRIP by 1. quarter in 2014 .

Page 48: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

36

KEY FILE TABLES: Table 1: Rural poverty and agricultural sector issues

Priority area Major Issues Actions needed

Rural poverty

80% population lives in the rural areas, 44% live below the national poverty line and 29% are classified as very poor.

Over 30 % of the net cultivable area is in the coastal region*, but these vast cultivable lands are in great threat due to rapid climate change and natural disasters.

Two major tidal surge and storms (Aila and Sidr) affected the coastal areas resulted major loss of lives, livelihoods, houses and rural infrastructure.

Low intensity of crop cultivation (in some areas only one crop per year) and fishing and they remain frequently unemployed due to tidal flooding and other natural disasters resulting food insecurity in the areas.

Low crop productivity and less cropping intensity due to increased salinity, incidences of pests & diseases, drought, tidal surges, cyclone, submergence, large fallow lands/water bodies, land degradation and unemployment.

Disease of poultry and livestock

Employment generation through expanding local businesses

Extended safety net program Skill development for self-employment and IGAs through

training Easy access to potable water and re-excavation of fresh

water ponds Land ownership increase; distribute khas land Access to health facility Ensure vaccination and other input services for poultry. Build physical protection from floods and cyclones.

Agriculture

Mostly single crop Aman cultivated due to saline water and scarcity of fresh water in dry season, therefore, farming is possible only for 4-6 months.

In some places no vegetable is grown due to acute salinity. Scarcity of quality fry, seeds as well as limited access to water bodies and which

are almost controlled by the elite (Government lease). Limited access to good technology and inputs, knowledge and support services

such as vaccination services for poultry and livestock. Virus attack and risk of washing away of fish, shrimp and other crops due to

heavy rain fall, tidal surge. Submergence of rural access road hinders carrying the perishable commodities. Increases cost of production because of higher input costs, and lower price due to

remoteness Limited access to demand driven financial services, especially seasonal

agricultural credit and loan for microenterprises

Improve water control system. Introduction of saline friendly profitable crops/diversified

crops with appropriate technologies. Expansion of existing agricultural products with

establishment of network with DAE, DoF and DLS Quality fry, seeds, fertilizer and other inputs need to

ensure. Establishment of value chain and linkage among all

stakeholders (the farmers, input suppliers, buyers/traders) build their capacity, which is likely to reduce producers operating cost and increase net income.

Access to financial services (NGOs and Bank)

Markets

Poor road network cost high transport cost, poor marketing facilities. No shed and have to sit with produces in open space as a result cannot stay

longer in the market, rather obliged to sell earlier in the rainy season and other inconvenient circumstances (no water and toilet facilities).

Less buyer and whole seller comes because of poor connecting road with market. Inactiveness of MMC and thus poor management and maintenance of markets Market leasing system does not provide incentives for investment or

maintenance.

Construction of rural access road and market infrastructure.

Access to toilet facilities and water for drinking and cleaning.

Women friendly environment such as separate place for women temporary and permanent sellers.

Strengthen market management committees Reform leasing system to reduce costs of access to

markets and provide incentives for investment and maintenance

Gender equalities

Women are disadvantaged and destitute group with inadequate access to education and health facilities.

Less skilled and depend on manual work for minimal wage. Over burdened with household responsibilities along with scarcity of potable

water, fuel wood, poor housing and sanitation

Year round employment opportunities and skill development training for the destitute women in market development, some access roads and tree plantation as well as maintenance

Women friendly market environment for buying and

Page 49: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

37

Priority area Major Issues Actions needed

Less wage than male which varies 60-80 Taka Dowry is practiced everywhere. Limited access to assets and employment opportunities Less participation in market due to unfriendly environment for selling and buying Limited mobility due to submerged road in the rainy season

selling (particular space for temporary as well as permanent women sellers need to allocate).

Training on IGAs (poultry, cattle rearing, vegetable gardening, handicrafts and so on)

More access to potable water, health services and education.

Increase awareness among men and women about gender

issues and legal rights.

BCAS 2010, Assessing long term impacts of vulnerabilities on crop production due to climate change in the Coastal areas in Bangladesh

Page 50: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

38

KEY FILE TABLES: Table 2: Organisational capabilities matrix

Organisation Strengths Weaknesses Opportunities Threats

LGED Outreach – offices in all districts and Upazilas; staff in all Upazilas

Capacity to implement large rural infrastructure projects using contracted staff.

Experience of implementing similar project (MIDPCR)

Interface with local Government, and remit to support local Government.

Flexible approach to use of LCS Skilled human resources; Established management system (financial

management and program management) Efficient management

Centralised management in Dhaka

Large number of projects stretch management resources and weaken quality control

.To utilise the capacity of LGED for developing the coastal region and disaster prone region.

Utilise the enhanced capacity

of UPs and greater availability of funds to assume greater responsibility for local development and maintenance of existing infrastructure.

Ensuring the secondment of committed staff to CCRIP

Maintaining quality of management

Attempts of undue influence of local politician on infrastructure selection

Local Government (Upazila and Union)

Local presence and contact with local people

Responsible for delivering a number of Government services such as safety nets

Knowledge about local infrastructure needs and demand; Can assist CCRIP in market and road identification

UP can complement CCRIP project by paying for part of market development costs, e.g. earth filling

UP chairman is ex-officio president of MMC Regulatory, justice and disaster

management functions.

Limited financial resources. Election often on political

grounds. Are not always pro-poor

oriented. Not all UP chairmen

members are active in local development

Informal partnership with UPs may help speedy and smooth implementation of CCRIP project.

Involvement helps enlist local support for the project.

Utilise growing UP resources to supplement CCRIP expenditure

Opportunity to transfer some of infrastructure maintenance functions to them.

Political interference. .

Page 51: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

39

KEY FILE TABLES: Table 3: Complementary donor initiative / partnership potential

Major Donor Project Geographical Area Remarks

JICA South-Western Rural Development Project

Core activities: Construction of 110 upazila roads, 18 union roads, amounting to 1034 km of roads.

Project budget: USD 140 million

14 districts of 3, i.e. Greater Barisal, Greater Khulna, Faridpur

The roads built under CCRIP are typical village and Union roads. There is no overlap, moreover the information is known in local LGED offices and must be verified.

World Bank Emergency Cyclone Recovery and Restoration Project (ECRRP)

Core activities: 1. New construction of Multi-purpose Cyclone Shelters; 2. Rehabilitation of existing cyclone shelters; 3. Roads connecting population centers with cyclone shelters (it includes construction of Killa‟s (mounds) to provide for shelter of livestock and ponds for drinking water)

Project budget: USD 121 million

Coastal Areas, 9 districts In as far as the area covered by CCRIP is located within areas covered by the World Bank project; CCRIP does not construct cycle shelters; coordination for rehabilitation of roads should be established.

World Bank Coastal Embankment Improvement Project (2013-18) which will strengthen polders in a number of Upazilas within the CCRIP project districts

17 upazilas in South-western districts

Feasibility studies are being conducted.

ADB Participatory Small-Scale Water Resources Project (PSWRP)

Core activities: construction of canals, regulators, rubber dams, flood mitigation of areas smaller than 1000 ha

Project budget: USD 82 million

61 districts (all districts except for 3 hill districts)

CCRIP must consult with ADB where projects are bordering rural roads rehabilitated by CCRIP and for operation of water control gates

DANIDA Rural Roads & Market Access Infrastructure Development Project (RRMADP)

Core activities: labour-based (LCS) construction of earthen roads, small structures, carpeting of roads (combination of LCS and contractors); functional training of women, navigable canals (excavation)

Project budget: DKK 170 million

Patuakhali, Borguna, Laxmipur)

(9 Upazilas)

There is no overlap, CCRIP should consult the project for information on their intervention areas. (www.rrmac.net)

(www.lged.gov.bd)

FAO Several Projects

Country-wide Consult with FAO on available knowledge on specific

topics (agricultural data, markets, trade, livestock, fisheries)

Page 52: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

40

KEY FILE TABLES: Table 4: Target group priority needs and project proposals

Typology Poverty level and causes Coping strategies Priority needs Support from other programs

Project response

Extreme poor (no homestead and arable land)

Landless Food crisis almost throughout

the year Limited wage labor work in the

rural area Affected by any kind of natural

disaster No or very little access to

micro-credit and bank Housing structure is weak

(mostly with local materials and tin which they received as relief after Aila and Sidr)

Open pit toilet Crisis of potable water due to

salinity No livestock, only some poultry Many HHs are female headed

(abandoned, widow, disable husband)

Limited health access and suffer from various diseases

Children go to school but high drop out

Daily wage labor work in agricultural field, fish ponds, earth cutting for road, house and other purposes

Seasonal migration (both national and international) and permanent migration for searching temporary employment

Starvation or consumption cut GoB safety nets through union

parishad (40-day program for the extreme poor, twice per year), VGD, VGF cards

Women work in others house as maid-minimal pay

Make local quilt and mat with local materials

Children become involved with earning

Women collect fuel wood from Sundarban

Catch fish and fry in river (twice within 24 hours according to ebb and flow tide)

Employment generation Self employment Access to potable water Development of rural

roads and markets Food assistance Training on IGA Health support

ASA, BRAC, GRAMEEN, World Vision, UNDP and other local organizations provide loan, training on IGAs.

- Employment generation for the destitute women in LCS; - IGAs through MAPP implemented by PKSF in the CCRIP project areas - Improved infrastructure will increase local employment opportunities - Health services may improve due to better access

Poor (homestead land)

No arable land but homestead land

Food crisis almost 6 months of the year

Insufficient wage laboring work for the year round relative to need

Very few have livestock and poultry

Little access to NGO and no access to Bank

House is made with local materials and ring slab sanitation

Crisis of potable water due to salinity

Same as extreme poor Take dadon (advance sale of

crops/fish)

Employment generation Self employment Access to potable water Development of rural

roads and markets Food assistance Training on IGA Health support

ASA, BRAC, GRAMEEN, World Vision, UNDP and other local organizations provide loan, training on IGAs

Employment generation for the destitute women in LCS; - IGAs through MAPP implemented by PKSF in the CCRIP project areas Improved infrastructure will increase local employment opportunities Health services will be improved

Page 53: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

41

Typology Poverty level and causes Coping strategies Priority needs Support from other programs

Project response

Chronic debt Vulnerable to natural disaster

Marginal farmer /functional poor (up to 1.5 acre land)

Vulnerable to natural disaster, probability of crop damage by heavy rain and water logging

Virus attack on shrimp and wash away by flood, lack of quality fry

Food crisis for 1-2 months (due to salinity mostly one crop is cultivated)

Poor access to health facilities and potable water

No or limited access to agricultural information or technology

Less price of produce due to undeveloped market and thus less bargaining scope

High carrying cost because of earthen road that is totally difficult in monsoon

Lack of cold storage facility at the local level, therefore bound to sell to the fixed customer/businessmen

Limited access to Bank

Loan from NGO with high interest

Loan from Bank by mortgaging the land

Seasonal migration Rear poultry & livestock Small trading based on local

production Very few HH have petty job

holders in NGO and Government level

Sell land

Agricultural development through access to extension services including inputs

Development of market and rural roads for better price and easy transportation

SME loan Access to potable water

Improved infrastructure will increase the volume of production and transaction

Agricultural and fisheries extension services will be increased with improved communication

Input supply will be improved

Value chain activities under MAPP; NE loan under MAPP

Access to health service and education will be improved

Middle class (1-5 acre)

Vulnerable to natural disaster, probability of crop damage by heavy rain and water logging

Virus attack on shrimp No or limited access to

agricultural information or technology

Less price of produce due to undeveloped market and thus

less bargaining scope about the price

High carrying cost because of earthen road that is totally difficult in monsoon

Lack of storage facility at the local level, therefore forced to sell to fixed

Business Own boat, nets, cold storage,

lease in land Service holder HH member Own livestock, poultry Access loan to bank, NGO Sell land

Improved access to information and services regarding agriculture and fish production

Developed market and rural connecting roads

Improved economic opportunities

Improved infrastructure will increase the volume of production and transaction

Agricultural and fisheries extension services will be increased with improved

communication Value chain support

and agri/ME loan under MAPP

Page 54: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

42

Typology Poverty level and causes Coping strategies Priority needs Support from other programs

Project response

customer/businessmen.

Non-poor (above 5 acre)

Vulnerable to natural disasters Own assets and business Poor rural access road and

market facilities, input services

Access to bank loan Businessmen Move to the town and lease

out the lands

Better infrastructure Improved infrastructure will increase the volume of production and transaction;

ME loan and value chain support under MAPP

Page 55: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Main Report

43

KEY FILE TABLES: Table 5: Stakeholder matrix / project actors and roles

Component Activity Coverage Perennial Institution(s) Involved

Potential Contractors/ Periodic Inputs

Other Possible Partners in Execution

Transport infrastructure

Construction of Union and

village roads

Construction of block road

Construction of bridges and box culverts for Union and village

roads

31 Upazilas 12 project

districts (mostly coastal and flood prone areas)

LGED via district level

XEN and Upazila Engineers. Funds disbursed from the PMU HQ to XENs.

Construction

contractors

Collaboration with Small

Scale Water project of ADB/IFAD;

Collaboration with MAPP project of PKSF/IFAD

Market development

Selection and development of four types of rural markets (Special, Large, small and collection points)

Construction of rural markets

Formation of LCS and training

Train MMCs

Build boat landing ghats

31 Upazilas 12 project districts (mostly coastal and flood prone areas)

LGED (CCRIP PMU via its offices at the Upazila level)

Union Parishads

LCS groups

MMCs

Labour Contracting Societies (LCS)

BUET on design of village roads

Incorporate experience

of MIDPCR and SCRMB project .

Management Support

Project management

Project coordination

Staff development training

Monitoring and evaluation

Conduct surveys, impact studies, environmental assessment

Lesson learning and

dissemination

12 project districts

LGED CCRIP PMU

Project Steering Committee

District Development Coordination Committee

Upazila Development

Coordination Committee

Consulting firms

specialised in M&E, environmental assessment

International training providers

Academic & research

institutions

Other donor agencies including LCG

Page 56: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annexes

Annexes

1. Country and Rural Context Background

2. Poverty, Targeting and Gender

3. Country Performance and Lessons Learned

4. Value Chain Development and Infrastructure

5. Detailed Project Description

6. Review of Rural Infrastructure Needs Under CCRIP

7. List of community (village) markets and union/village roads selected for development

7A. Project Costs and Financing

7B. Summary and Detailed Cost Tables

8A. Structural Design: Road Infrastructure

8B. Detailed Cost: Road Infrastructure

8C. Unit Costs: Road and Market Infrastructure

9A. Structural Design: Market Facilities

9B. Structural Design: Ghats

9C. Detailed Costs: Market Facilities

10. Institutional Aspects and Implementation Arrangements

11. Compliance with IFAD Policies

12. Planning, Monitoring, Evaluation and Knowledge Management

13. Financial Management and Disbursement Arrangements

14. Procurement

15. Beneficiary Calculation

16. Financial and Economic Analysis

17. Draft Project Administration Manual

18. Contents of Project Life File

Page 57: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 58: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 1

Annex 1

Country and Rural Context Background

Page 59: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 60: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 1

1

Annex 1

Country and Rural Context Background

Poverty and Economic Growth

1. Introduction: The Coastal Climate Resilient Infrastructure Project (CCRIP) jointly funded by ADB, KfW, IFAD and Government of Bangladesh is a merger between former Sustainable Infrastructure for Livelihoods Enhancement (CCRIP) project of IFAD and Climate Resilient Infrastructure Improvement in Coastal Zone Project (CRIICZP) of ADB/KfW. It will be implemented in 12 south-western districts though IFAD funded activities will be limited to 32

coastal and low-lying upazilas, which are poor and vulnerable to natural disasters and suffer from low level of past development activities. The country and rural context analysis prepared during design of the CCRIP project remains valid for CCRIP. The final design mission of IFAD updated wherever necessary to reflect merged project. The IFAD-funded activities plans to contribute to overall development of 32 Upazilas (sub-districts), especially in agricultural development to reduce rural poverty. These activities will also complement other activities of CCRIP. The country had undertaken projects with similar activities with

good success. CCRIP will contribute to bringing the level of development South-western part

to that of Eastern part of the country. That means CCRIP will be implemented in wider country development context. Note that the analysis presented here also complements analysis prepared by ADB/KfW PPTA team.

2. Population and poverty: Poverty is a pervasive problem in rural Bangladesh because of limited land and other natural resources, low agricultural productivity, lack of non-farm economic opportunities, high population density, and overall governance factors. Bangladesh

has the third highest number of poor people in the world. With a population of over 150 million1 living in an area of 147,570 square kilometres (or 1,045 persons per square kilometre), Bangladesh is one of the most densely populated countries in the world. About 80% of the population lives in rural areas and is mainly engaged in agriculture and related non-farm activities. More than two thirds of the rural population is landless or functionally landless (owning less than 0.2 hectares of land), 44% are below the national poverty line

and 29% are classified as very poor2. Many people have an inadequate diet and suffer from periods of food shortage – half of all rural children are chronically malnourished, and 14% suffer from acute malnutrition.

3. Climate change and Poverty: Bangladesh would be one of the worst affected countries to temperature rise and climate change. Bangladesh is one of the most disasters prone of the least developed countries. Two-thirds of the country is less than 5 meters above sea level, making it one of the most flood prone countries in the world. Severe flooding during a

monsoon causes significant damage to crops and property, with severe adverse impacts on rural livelihoods. Climate change seems likely to increase the destruction by monsoon floods, while the frequency of cyclones may increase. Between 1970 and 1998, 171 large-scale water-related hazards such as cyclones, storm-surges, droughts, floods, and river erosion disasters killed an estimated half million people and affected more than 400 million. The poor are hit hardest because they live at greater density in the most poorly constructed housing in settlements on lands prone to hazards. The project areas are most vulnerable to

natural disasters.

4. Two areas within Bangladesh stand out as being particularly at risk to climate change. The coastal belt of the Jamuna-Padma-Megna delta is among the world‘s largest and most populated river delta. Although continued supplies of river sedimentation may limit land loss resulting from sea level rise, drainage problems will increase where protection schemes

exist. Salinity levels are likely to rise in delta rivers in the dry season, mainly due to

increased upstream abstraction of water.

5. Economic growth and inflation: Bangladesh had continued economic gains over the past decade with steady annual economic growth of 5% to 6%, relatively low inflation and fairly stable domestic debt, interest rates and exchange rates. However, growth has not reached the rate of 7.5% that is needed for Bangladesh to graduate to middle-income status within

1 Bureau of Statistics of the Government of the People‘s Republic of Bangladesh. 2001. Population Census Preliminary Report (2001–2008) 2 Household Income and Expenditure Survey 2005, Bangladesh Bureau of Statistics.

Page 61: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 1

2

the next 10 years3. After a slowdown in GDP growth to 5.7% in 2008/09, growth recovered

to 6.0% in 2009/10 with 6.3% forecast for 2010/114. But the inflation rate has been increasing and reached double digit figures (more than 12%) in 2011/12 that has become a major concern for the consumers and the government. The high inflation is hurting the poor and fixed income groups of the society.

6. Macro-economic management: Together with increased imports (growth of 36% from July 2010 to January 2011 - partly due to rising commodity prices and large fuel imports for

power plants), and lower inflows of FDI and aid, have meant that the balance of payments has moved into a deficit (net outflow of USD 586 million July to November 2011, compared with surplus of USD 1,585 million for the same period a year earlier).

7. After a long period of stability, the value of the Bangladesh Taka (Bangladesh currency) has depreciated over the last six months from Taka 70 per USD to Taka 83 per USD in January 2012 making the imports expensive and deteriorating current account. GoB macro-economic

management has been under severe stress lately. At the time of final design mission (October 2012) the exchange was Taka 82 for one US dollar. Besides, massive fall of stock market index has been responsible for massive loss to small investors.

8. Government expenditure on subsidies on food, fuel and fertiliser are being driven up by rising commodity prices, and the government has ambitious plans for investment in infrastructure and services. Although tax revenues have increased at 9.3% of GDP, they are low as compared to other countries in South Asia. It has been difficult to increase direct

taxes, and much revenue has to be raised from sales taxes. The fiscal position remains weak with a government deficit of 3-4% of GDP.

9. Export and Remittance: Bangladesh has managed to maintain its exports in garments and reported to clinch the No. 2 position after China (excluding EU countries) by replacing India. But remittance growth has slowed down because of fewer people are leaving for overseas jobs, mainly in middle-eastern countries. Annual remittance through official channel has stood USD 12 billion in 2010/11.

Agricultural sector

10. Long-term growth scenario: Since CCRIP project aims to directly contributing to agricultural sector and assisting farming families, it is important to have correct perspective of agricultural sector. Agricultural production has increased substantially in Bangladesh over

the past 20 years. Cropping is dominated by rice and annual rice production has grown from 10 million tons in 1971 to just under 33.9 million tons in 2009/105. Agricultural sector

growth was 4.4% in 2009/10, an increase from 4.1% in the previous year. Expansion of farm output has come from a transformation of rice production from extensive low input subsistence systems to highly intensive high input systems using modern rice varieties, a large increase in fertiliser use, and a substantial increase in irrigation during the dry winter. The country is now more or less self-sufficient in rice in a normal year. There is, however, no room for complacency as Bangladesh has to import rice following bad floods or droughts at critical crop growth periods, and with continued population growth and loss of land to

urbanisation (about 1% of land per year), there is an ever increasing need to produce more rice every year.

11. Diversity and Subsidizes: In the light of the soaring food prices seen globally in 2008, the Government became concerned that imports may no longer be available at affordable prices; a new policy of self-sufficiency is being purposed by the present government. Although there is some scope to increase production, the yield gap between research and farmers‘ output for the major rice crops has narrowed. Agricultural land is decreasing due to

increasing population and urbanization, within agriculture land is being diverted away from staple cereal crops to uses such as horticulture, fish ponds, and to grow maize to feed poultry. To increase production while keeping prices as low as possible, the government has also expanded a programme of subsidies for inputs (fertilizer, fuel and seeds). These subsidies account for over three-quarters of government expenditure for agriculture. But subsidies in urea fertilizer have been reduced by increasing price from Taka 12 per Kg to

Taka 20 per Kg. This may also reduce wasteful use of urea.

3 Bangladesh: Strategy for Sustained Growth, World Bank 2007 projected that a rate of growth of GDP of 7.5% would result in the country joining the ranks of middle income countries within a decade (by 2016). 4 Bangladesh Quarterly Economic Update, ADB, June 2010. 5 Quarterly Economic Update, ADB, June 2010

Page 62: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 1

3

12. Profitability: Within agricultural commodities fruits/vegetables and fisheries are more

profitable than rice that is encouraging farmers moving away from rice production. Consultations with farmers reveal that increasingly they are looking more profitable commodities compared to rice. The price of has remained steady, sometimes low at the time of harvest, whereas cost of inputs and labour has gone up by making rice production less profitable. The project such as CCRIP may contribute to reducing cost of production.

13. Land holdings are becoming increasingly fragmented as farms are divided between sons on

inheritance, and land (especially that of the larger land owners) is sold off or rented out as people move into non-farm occupations. Agriculture is increasingly in the hands of marginal and functionally landless farmers6, many of whom produce primarily for subsistence. Although staple food production has kept pace with rising population, with rising incomes there is increasing demand for better quality foods – fruit, vegetables, meat, milk, eggs and fish. Diversification into these higher value products puts further pressure on land for paddy

and on the national goal referring to the self-sufficiency in rice. Agriculture also has to take the brunt of damage from natural disasters and climate change.

14. GoB Development plan: The broad directions for development over a longer time-span are set out in the Perspective Plan for Bangladesh 2010-2021. Amongst other things, this plan

would like to see genuine devolution of power to the local government level, and also says that in the process of socio-economic development of the country, agriculture will still continue to play a vital role in the long run in terms of food security, generation of income

and employment for the multitudes living in the countryside and for eradicating poverty. More elaborate plans are available at the 6th five-year plan, which clearly identifies rural and agricultural development as the priorities for the government. Rural infrastructure development and broadening access to financial service are important elements in the plan.

Donor programmes

15. The World Bank: The World Bank‘s Country Assistance Strategy for FY2011 to FY2014 has the overall objective of promoting accelerated, sustainable and inclusive growth along with

stronger governance. Sectors identified for support include infrastructure, dealing with climate change (including water management) and agricultural and food security. The on-going NATP (co-financed by IFAD) is likely to have a second phase. Two World Bank on-going projects a) Coastal Embankment Improvement Project (CEIP) and b) Emergency Cyclone Recovery and Restoration Project (ECRRP) with focus of building embankments and

cyclone shelters will have complementary effects on CCRIP as they are implemented in the

same area.

16. ADB: ADB‘s Country Operations Business Plan for 2011-13 includes investments in agricultural and natural resources and in transport infrastructure. Pipeline projects (including those planned in 2010) include a crop diversification project in the southwest of the country, climate resilient infrastructure in the coastal belt and a rural infrastructure improvement project.

17. USAID: Under its Feed the Future programme USAID is planning two projects: one with

focus in rural infrastructure and another one for value chain development in South-western districts although exact scope of the projects is under development.

18. EU: The European Union‘s Bangladesh Country Strategy Paper (2007-2013) identifies food security as a focal sector. The specific objective of the EU food security programmes is to eliminate food insecurity through holistic and integrated concepts and by strategically strengthening the capacities and responsibilities of decentralized government institutions for participatory planning and implementation of food security interventions. This is achieved

through a focus on innovative approaches and interventions by primarily targeting extreme poor and food insecure women who have not benefited from mainstream poverty reduction programmes. EC interventions link food security with education, health, good governance and Disaster Risk Reduction.

6 In 1960, 84% of land was operated by the 48% of farmers who had medium and large size holdings (over 2.5 acres of land. By 2005, only 12% of farmers still operated over 2.5 acres, and 60% of all land was in the hands of the 88% farmers with less than this amount of land (BBS, Agricultural Census 1960, Agricultural Sample Survey 2005)

Page 63: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 1

4

COUNTRY DATA

Bangladesh

Land area (km2 thousand) 2008 1/ 130 GNI per capita (USD) 2008 1/ 520

Total population (million) 2008 1/ 160.00 GDP per capita growth (annual %) 2008 1/ 5

Population density (people per km2) 2008 1/ 1,229.2 Inflation, consumer prices (annual %) 2008 1/ 9

Local currency Taka (BDT) Exchange rate: USD 1 = BDT ***ADD RATE***

Social Indicators Economic Indicators

Population growth (annual %) 2008 1/ 1.4

GDP (USD million) 2008 1/ 79 554

Crude birth rate (per thousand people) 2008 1/ 21 GDP growth (annual %) 1/

Crude death rate (per thousand people) 2008 1/ 7 2000 5.9

Infant mortality rate (per thousand live births) 2008 1/ 43 2008 6.2

Life expectancy at birth (years) 2008 1/ 66

Sectoral distribution of GDP 2008 1/

Total labour force (million) 2008 1/ 76.77 % agriculture 19

Female labour force as % of total 2008 1/ 41 % industry 29

% manufacturing 18

Education % services 53

School enrolment, primary (% gross) 2007 1/ 93.8

Adult illiteracy rate (% age 15 and above) 2008 1/ 45 Consumption 2008 1/

General government final consumption expenditure (as %

of GDP)

5

Nutrition

Household final consumption expenditure, etc. (as % of

GDP)

79

Daily calorie supply per capita n/a Gross domestic savings (as % of GDP) 16

Malnutrition prevalence, height for age (% of children under 5)

2007 1/

43.2a

Malnutrition prevalence, weight for age (% of children under 5)

2007 1/

41.3

Balance of Payments (USD million)

Merchandise exports 2008 1/ 15 369

Health Merchandise imports 2008 1/ 23 860

Health expenditure, total (as % of GDP) 2007 1/ 3.4 Balance of merchandise trade -8 490

Physicians (per thousand people) 1/ n/a

Population using improved water sources (%) 2006 1/ 80 Current account balances (USD million)

Population using adequate sanitation facilities (%) 2006 1/ 36 before official transfers 2008 1/ -8 758

after official transfers 2008 1/ 1 032

Agriculture and Food Foreign direct investment, net 2008 1/ 973

Food imports (% of merchandise imports) 2008 1/ n/a

Fertilizer consumption (hundreds of grams per ha of arable

land) 2007 1/ 1,912.5

Government Finance

Food production index (1999-01=100) 2007 1/ 117 Cash surplus/deficit (as % of GDP) 2008 1/ -1

Cereal yield (kg per ha) 2008 1/ 3 972 Total expense (% of GDP) a/ 2008 1/ 11

Present value of external debt (as % of GNI) 2008 1/ 20

Land Use Total debt service (% of GNI) 2008 1/ 1

Arable land as % of land area 2007 1/ 61

Forest area as % of total land area 2007 1/ 7 Lending interest rate (%) 2008 1/ 16

Agricultural irrigated land as % of total agric. land 2007 1/ n/a Deposit interest rate (%) 2008 1/ 9.7

a/ Indicator replaces "Total expenditure" used previously.

1/ World Bank, World Development Indicators database CD ROM 2010

Page 64: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

Annex 2

Poverty, Targeting and Gender

Page 65: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 66: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

1

Annex 2

Poverty, Targeting and Gender

A. Poverty Issues7 Overview of poverty incidence and food security

1. Bangladesh has made commendable economic and social progress since independence in terms of economic growth, poverty reduction, increasing domestic food production and women empowerment. The economy currently grows at a rate of around 6% per annum, poverty has been reduced by more than half and rice production tripled. Bangladesh achieved gender parity in education, especially primary and secondary education in terms of enrolment and completion. Nevertheless, poverty is still ubiquitous and Bangladesh remains a low income country with substantial inequality, marginalization, exclusion and deprivation.

2. The Bangladesh Bureau of Statistics (BSS) conducted the Households Income Expenditure

Survey in 2010 to ascertain inter alia the incidence of poverty, which provides the recent estimates of poverty-stricken people in rural and urban areas. In making poverty estimates BBS used the Cost of Basic Needs (CBN) Method, whereby any household with per capita expenditure below a given poverty line is considered as poor. Poverty measurement includes two types of poverty lines. These are upper poverty line and lower poverty line.

Understandably, the upper poverty line represents a higher level of per capita household expenditure than the lower poverty line. The survey reveals that 31.5 per cent of people are living below the upper poverty line, while the percentage of people living below the lower poverty line is 17.6 per cent. Often they are referred to as extreme poor, ultra- poor and/or hard core poor. The following table presents incidences of poverty in seven Divisions8.

Table 1: Head Count Rate (HCR) of Incidence of Rural and Urban Poverty 2010 Division Lower Poverty Line Upper Poverty Line

National Rural Urban National Rural Urban

National 17.6 21.1 7.7 31.5 35.2 21.3

Barisal 26.7 27.3 24.2 39.4 39.20 39.90

Chittagong 13.1 16.2 4.0 26.2 31.00 11.80

Dhaka 15.6 23.5 3.8 30.50 38.80 18.00

Khulna 15.4 15.2 16.4 32.10 31.00 35.80

Rajshahi 16.0 16.4 14.4 29.70 29.00 32.60

Rangpur 27.7 29.4 17.20 42.30 44.50 27.90

Sylhet 20.7 23.5 5.5 28.10 30.50 15.00

Source: BBS (2011), Preliminary Report on Household Income and Expenditure Survey-2010

3. The above table shows that incidence of poverty in rural areas is higher than urban areas and

rural poverty is the highest in Rangpur followed by Barisal, Sylhet & Dhaka, Rajshahi and Chittagong and Khulna. Further disaggregation of poverty data for Dhaka Division is likely to provide evidence for considerably higher incidence of poverty in greater Faridpur (which falls under the Dhaka Division) region including Shariatpur, Madraipur and Gopalgonj districts9 as

road communications are relatively underdeveloped in these three low-lying districts and they are geographically separated from the Dhaka city (the main growth center of the country) by the mighty river Padma. While coastal districts of south-west namely, greater Barisal and Khulna regions, remain vulnerable to cyclones and tidal surges, which are induced by climate change and tend to cause tremendous loss and damages to lives, crops and livestock. The

coastal districts of the South-west also experience sea intrusion and increasing salinity, which

significantly contribute damaging potentials of food crop production.

7 Prepared by Mahbubul Islam Khan, IFAD Consultant 8 Administratively, Bangladesh is divided into seven Divisions, which are sub-divided into 64 Districts and 465

Upazilas. Further estimates of incidence of poverty at districts level are likely to be available after 3-4 months, when BSS is expected to releases relevant disaggregated poverty data and information. 9 Districts are further sub-divided into Upazilas (sub-districts). Each district has a Sadar Upazila. In terms of road communications and overall development, Sadar Upazila tends to be ahead of other Upazilas of the same district.

Page 67: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

2

4. Despite remarkable increases in domestic food grain production over the past decades

Bangladesh still remains a food deficit country. In normal years with no major natural calamities, food production falls short of requirement and Bangladesh needs to import around 3.0 million tons of food grain annually to meet the shortfall in aggregate domestic production. Annual import goes significantly up in case of crop failure caused by natural hazards such as floods, cyclones etc. There are also problems in relation to food entitlement. In some underdeveloped geographic pockets with depressed agriculture, some sections of rural

population tend to suffer from seasonal food shortages (e.g. during the Bengali months of Bhadra to Kartik, which corresponds to mid-August to mid-November) despite availability of food grain in the markets because of low purchasing power. Char (i.e. newly raised land) and low lying areas (which are most vulnerable to floods) including parts of Shariatur, Madaripur and Gopalganj districts and coastal areas of the South-West including parts of Satkhira, Khulna and Bagerhat contain some of these food insecure pockets. Many parts of greater Faridpur,

Khulna and Barisal suffer from very high to high relative food insecurity10.

5. Poverty Indicators: Some other poverty indicators are given below:

Per cent of Headship of HH

Figure: 1, Source: National Institute of Population Research and Training (NIPORT), BDHS 2007, MIDPCR, Mitra and Associates 2009

1. Figure 1 states that according to BDHS (2007) only 13% of households are headed by

women. The proportion of female headed households is slightly higher in rural areas than urban areas respectively 13.2 and 11.4. Similarly, the baseline survey of MIDPCR conducted in 5 districts of project areas which showed 93% of male headed household and rest 7% are the female headed households.

Incidence of poverty (CBN) by selected HH characteristics by CBN method

(Lower poverty level) (Upper poverty level)

Figure: 2, 3, Source: Bangladesh Bureau of Statistics (BBS), Household Income and Expenditure Survey (HIES) 2010

2. Figure 2 and 3 show that in 2010, the Head Count Rate of incidence of poverty using the

lower poverty line is estimated at 14.6 per cent for the female headed households whereas it is 17.9 per cent for the male headed households. In the rural area, the HCR of female headed households is 17.3 per cent whereas it is 21.5 per cent for the male headed households. In

10 Government of Bangladesh & World Food Program (2004) The Food Security Atlas of Bangladesh: Towards a poverty and hunger free Bangladesh (2004)

Page 68: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

3

urban area these rates are 5.5 per cent and 7.9 per cent respectively. 29.3% female headed

households belong to the upper poverty level in the rural areas and 17.5% in the urban areas.

Source of drinking water Access to sanitation

Figure: 4, 5, Source: NIPORT, BDHS 2007

3. According to the BDHS 2007, access to an improved source of drinking water (figure 4) in Bangladesh is 97 per cent and 2.8 per cent having access to non-improved sources. Non-

improved sources of drinking water are higher (3.5%) in rural areas than in the urban areas (0.5%). On the other hand, non-improved sanitation facility (figure 5) is 74.6 in the country following with 62.5 per cent in the urban and 78 per cent in the rural areas.

Wealth quintiles

Figure: 6, Source: NIPORT, BDHS 2007

4. Figure 6 shows that among the administrative divisions‘ people living in Dhaka are more likely to fall in the highest (28%) wealth ranking group than other divisions. In contrast Rajshahi and Barisal are the more poverty prone area having 28% and 25% of lowest wealth quintile respectively.

Nutrition status of children

Figure: 7, Source: NIPORT, BDHS 2011, Preliminary Report

5. This figure shows that rural children are more likely to be stunted (45%), wasted (18.2%) and underweight (43%) than urban children 36%, 14.4% and 33.4% respectively.

Page 69: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

4

Place of delivery

6. BDHS survey 2011 (BDHS 2011 preliminary report) reveals that delivery at home is highest in both rural and urban areas respectively 77% and 50.5% than in a public, private and NGO facility. In addition, it shows that 90.1% of delivery takes place at home among the lowest wealth ranking group.

Basic Characteristics of holdings classified by area size (sex of the HH head and district wise)

Figure: 8, Source: BBS, Census of Agriculture 2008

7. The figure 8 describes well the land holding (including farm and non-farm) pattern in the proposed 12 districts of Bangladesh where a very less portion of lands are owned by female headed households.

Current poverty reduction strategy for rural areas

8. The government‘s poverty reduction and improving food security strategy in rural areas includes pursuing growth-oriented policies both in agriculture and rural non-farm sectors. It also spends considerable amount of resources in implementing a wide range of safety net programs including direct employment creation during lean periods.

Distribution of Households receiving Social Safety Net Program benefits by division,

2010 (% of HHs receiving benefit)

Figure: 9, Source: BBS, HIES 2010

9. Figure 9 shows that highest numbers of rural households of Khulna division (43.27%) have benefited by the social safety net program and the lowest rural households (22.85%) have been benefited in Rajshahi division.

10. The government supports agriculture through providing highly subsidized crop, livestock and

fisheries research and extension services and channelling loans to farmers through specialized

agricultural banks namely, Bangladesh Krishi Bank (BKB) and Rahjshahi Krishi Unnayan Bank (RAKUB). It builds rural infrastructure such as village, union, upazila roads, markets and further develops rural growth centres, mainly through Local Government and Engineering

Page 70: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

5

Department (LGED). It supports rural cooperatives through the Bangladesh Rural

Development Board (BRDB). The government also develops relatively large surface water irrigation systems. On the other hand, the prolific Bangladeshi NGOs collectively operate a countrywide rural network mainly to provide financial services such as microcredit to the poor. The government provides loan funds to NGOs through an independent organization named Palli Karma Sahayak Foundation (PKSF), an apex financial organization formed by the government, which mainly wholesales loan funds to NGOs. Some NGOs provides primary

health and education services alongside the government in rural areas.

Target group: social and economic conditions and opportunities

11. The population of the market catchment areas under the CCRIP project represent the target group as well as the primary beneficiaries of the project. They are mostly small-scale producers (such as farmers, artisans), small-scale traders, agricultural and off-farm labourers.

Women and girls will constitute a half of the primary beneficiaries. The existing constraints of different occupational groups related to poor communication and undeveloped markets are as follows as gathered through FGDs with sample beneficiaries:

12. Poor farm and off-farm labours: Agricultural production is limited in the coastal areas because

of increasing water salinity and soil salinity as well as scarcity of good quality irrigation water in dry season. According to the FGD participants most of the villagers belong to either poor or extreme poor groups. Some of them are landless; some own only the homestead land and suffer from food insecurity for 4-6 months during the year. Single crop Aman rice, shrimp cultivation and Rabi (vegetable/fruits) create 4-6 months of employment opportunities for the labourers in most of the project Upazilas in Bagerhat, Satkhira and Khulna districts. For the remaining months they stay unemployed or under-employed. As a result, some catch fry, fish from the river, collect fuel wood from the Sundarbans, work as domestic help, pull van and rickshaw, migrate to different places to find temporary employment. Some women make mat and local quilt. In places where scarcity of drinking or sweet water is acute, women are seen to supply water from the ponds to the shops in plastic jar and bucket. During the field visit (May) many families were found where the male members had left the village for Gopalgonj to harvest paddy. Some extremely poor women also leave villages with men from the same locality. Usually the women cook for the labours and receive rice as payment. Some rural poor men and women in Khulna district have been found working in rice mill and fish processing industries which were established in Khulna city about 2 years ago. Many poor men also go to Dhaka, Khulna and other big cities to pull rickshaw and van. During the FGDs, the poor groups urged for employment generation at local level in order to ensure their livelihoods. The CCRIP project would generate employment opportunities for the poor and destitute women in LCS who will receive a daily wage as well as the share of profit. They can invest their profit money in income generating activities. Skill development training will be provided which is likely to generate further working opportunities in other infrastructure related projects.

13. Small farmers/producers: This group of rural population have small amount to 1.5 acres of

cultivable land but may face food insecurity if crop is damaged by natural disasters. They commonly borrow from NGOs and local moneylenders (dadon, advance money against production). They also cultivate as sharecroppers and involve in small trading. This group of people lack access to quality input and services. One fish farmer said ―due to the earthen road and huge distance we cannot get the quality fry…most of them die during carrying…even what happened after Aila, some NGOs and government provided us fry of fish and shrimp; however, most of them died before reaching to our locality…so whole the relief or assistance became meaningless/worthless”. Moreover, the small farmers sell their commodities in the local markets but receive lower prices due to the poor infrastructure and high transport cost. It also takes much time to carry to the market during unfriendly environment to sell the produces. There is no shed in the market where producers can sit with their commodities. All sellers irrespectively male and female have mentioned the problem which compels them to sell quickly to leave the place earlier. They also reported that agricultural officers and fisheries officers are reluctant to visit their villages. They expect a better road will increase availability of agricultural technologies for rice, fish, poultry, and livestock and so on which will increase their productivity. Commodity price would increase as more buyers/wholesalers would come and more shop would be constructed in the market once the market infrastructure is developed.

14. Small traders: Input suppliers, vegetable/fish sellers, wood suppliers, vendors and the

shopkeepers have been consulted in the market areas and villages. They need to travel catchment areas to buy goods but face serious difficulties due to undeveloped, muddy rural roads. Particularly it becomes hazardous during monsoon. Many poor women run tea shops,

Page 71: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

6

tailoring shops and grocery shops. They have to depend on haat days (twice in a week) for most of their income earning. They expect if the market is constructed and access road is developed more people would come for buying and selling which would increase their earning as well. They do not have any water and toilet facilities in the market. Poor women also sell cosmetics, women clothes, household utensils etc. by hawking. But poor road communication hampers their business expansion two ways: 1) difficult to sell by walking on earthen road as no vehicle is available, 2) difficult to visit town or sadar to buy their business material which is time consuming and results high cost. As a result, they make less profit.

15. Households that own 1.5 to five acres of cultivable land are considered as middle class. They

are involved in business, job, agriculture and fisheries production. They usually do not face food crisis and have access to Bank and NGOs. People of this group lease fish ponds and also own fish storage in the local market. They buy fish from the small producers and keep in the storage to bring to the big markets by boat. Usually small producers cannot afford to take

their small production to the big market due to the high carrying cost and other requirement to keep the fish fresh.

16. The people who have more than 5 acres of arable land are considered as non-poor. According to the FGD participants, 10% of households could be considered non-poor. They own permanent shops, lease out the lands to others and manage bigger businesses.

17. Other professional groups: A very small number of people are employed as health workers,

certified village healer (Rural Medical Practitioner), NGO workers and teachers. The FGDs report death of patients as they could not be taken to doctors due to poor road communication, especially in the wet season. Rural government clinics were found that provide basic health care, mostly by poorly trained health workers, not doctors. Moreover, in most of the undeveloped villages do not have high school, so the students travel long distance. Many poor households cannot afford to manage their transport cost. Only the rich

families usually rent house and stay to the near the educational institutions. This is one of the major reasons of drop out of the students after primary school. Therefore, it is expected to improve rural people‘s access to health, education and other services through the proposed project.

18. People of different occupational groups suffer from some common problems irrespective of

their economic condition and land holdings such as frequent natural disasters, scarcity of

drinking water, poor communication system, access to market, technology, inputs and services, health facilities, educational institutions and so on. Particularly children and women suffer the most related to health and education services. From 10 out of 12 villages visited, villagers reported death of children and pregnant women. Only the well-off families can afford to take the pregnant women to the health complex in advance before the expected delivery date.

19. Therefore, the development of markets and roads is expected to hugely benefit the whole community, especially the farmers, small traders, poor people and destitute women. The expected outcome of CCRIP project is increased employment, increased wages and higher income, better access to education and health services, and greater mobility of women. Land values near the road would also increase. Convenience and comfortable environment for selling and buying of products would encoureage increased busiess.

20. Special care will be taken to make CCRIP markets women friendly. Women‘s representation in

market management committee will be ensured. Each market will have a separate hygienic

toilet facility for women and girls. Labour Contracting Societies (LCSs) comprising women labourers will be engaged in project construction work. Potential markets and connecting roads will be chosen in strategic places for development to maximize catchment areas and number of potential beneficiaries.

How the target groups manages risks and vulnerabilities

21. For poor families illness is the most frequent cause of crisis that imposes a significant additional burden on scarce household resources. Other socio-economic shocks include litigation, payment of dowry, loss of livestock etc. Limited crop production due to salinity, problems of road network and communication, poor human health and nutrition, lack of employment opportunities, problems in fishing activities, population migration, unsafe

Page 72: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

7

drinking water and problems of agro-based industries are the major socio-economic

constraints. Natural calamities such as floods, cyclones, tidal surge etc. which affect certain geographic areas cause crisis by damaging/destroying asset base of households. Since people do not have ample employment opportunities round the year, their food security situation is vulnerable. Majority of the people in coastal areas are involved in crop cultivation and fishing and they remain frequently unemployed due to tidal flooding and other natural disasters resulting food insecurity in the areas. Poor families find it difficult to cope with natural

calamities. Poor families often respond to crisis by taking loans preferably, from friends and relatives. They tend to use savings and capital and sell livestock and lease/mortgage out land. Advance labour sale and male migration are part of the coping strategies employed by extremely poor households. As a coping strategy of crisis period many poor people migrate to different places either temporary (seasonal) or permanent in within country as well as abroad. The following table shows the migration trend in Bangladesh:

Per cent of HH reporting migration

Total Rural Urban

Total 12.28 13.72 8.33

Within country 3.97 4.84 1.62

Abroad 8.60 9.25 6.85

Source: BBS, HIES 2010

Needs assessment for livelihoods support related to infrastructure and market access

22. Investment in physical market infrastructure and connecting roads can bring a thrust to the development of livelihoods in catchment areas. Rural markets and connecting roads, if developed properly in a planned way, can potentially become local growth centres. Local markets create economic opportunities and generate employment and income. Climate smart

rural infrastructure helps reducing damages attributable to natural calamities. Improved markets and connectivity will enable small-scale producers to reduce hardship in and costs of transporting their products to and from markets. It can also attract more wholesalers and retailers leading to better prices and access to tertiary markets. Small-scale producers in

catchment areas of will need capacity building on improved marketing practices such as cleaning, grading, packaging etc.to fetch better prices for their products. Improved markets with better road connectivity are likely to improve access to agricultural inputs too. All these

will create stronger incentives for local level producers. The following prioritized needs have been found from field visits:

Priority needs of different occupational groups

Prioritized Needs Wage

labour

Small farmer

/producer

Small

trader

Women

/children

Businessmen

/well off class

Employment opportunity √ √

Potable water √ √ √ √ √

Irrigation water √ √

Rural access road √ √ √ √ √

Market infrastructure √ √ √ √ √

Educational institutions √ √ √

Electricity √ √ √

Hospitals √ √ √

Cyclone centres √ √

Economic support with less

interest than NGOs

√ √ √ √

Experience of MIDPCR

23. Impact studies in MIDPCR areas showed that investments in market and small-scale roads infrastructure developments brought development opportunities in people‘s livelihoods in rural

areas. Improved infrastructures contribute to additional private investments in agriculture and other business. It has also been observed that due to market and communication system

Page 73: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

8

development, production in agriculture sector increase, employment opportunities improve;

labour productivity and their income also increase. 24. Out of targeted 65 markets under MIDPCR, 12 markets have women‘s market areas. The

labour contracting societies completed all market construction including market sheds, open space, drain, internal road and toilets. According to the Annual Super vision mission September, 2011, 2741 poor women participated in the construction work who received training from the project staff. Among them 1,199 LCS members joined the project NGO MFIs

groups for training on income generating activities and micro-finance services. All LCS members got paid work of about 50-160 days in a year during the construction period and made taka 5-38,000 profit. More than 90% ex-LCS members invested the profits to IGA. The skills they acquired during construction of the market and roads enabled many women to find other employment.

25. More than 90% microcredit groups are women and have been receiving training and financial services from the project NGOs that included training on fisheries, livestock, and vegetable production. DAE also organize training for women and provide technical assistance for homestead gardening. Members of LCS under MIDPCR acknowledged that their involvement with market development activities assisted them in their social development. Members of

LCS became self-sufficient or able in earning their livelihoods and earned respectable position in the society. LCS members are also happy that they need not to pay toll for selling their

products in the market they constructed. MMC has issued identity cards to LCS team members to avail toll free support. These developments also increased access to common property resources for the rural poor.

26. A short-term impact study of MIDPCR showed that, on average, women had earned Taka

7,469 in wages and had received Taka 9,569 in profit share. Living on own land has increased 16.94% and remarkably reduced living on others land (35.74%). Wages and profit money

have been divided between productive enterprises (34% in total, with 19% being used to buy cattle), 28% was used for household investments (leasing-in land 9%, land purchase 5% and house building 6%), and 38% for consumption (29% for food). The number of cattle owned by sample households increased by 169% and goats by 140%. This shows that benefits from LCS have been partly used to support families (the percentage of children going to school increased from 74% to 86%) and partly for purchase of assets.

27. In addition, ―Impact assessment on rural market‖ (2011) found that the number of traders

has increased by 44% (4,223) on a hat day and 33% (2,019) on a non-hat day. In addition, ―Short term impact survey report on the existing group member of NGOs‖ (2011) has revealed that more adult family members (7.3%) are now engaged in IGA activities and 14% small and medium enterprise established and 22% enterprises expanded by loans from NGO-MFIs. Food insecurity for more than three months has been reduced from 32% (2008) to 20%

(2012).

B. Gender Analysis11

28. The south-western region of Bangladesh is one of the natural disaster prone areas, and particularly, Bagerhat, Khulna, Satkhira viisted by the inception mission and project formulation mission were severely affected by SIDR and AILA. The mission also visited Gopalganj, Madaripur and Shariatpur districts from 1st February to 5th February. The mission

conducted FGDs with groups comprised of rural poor women, UP members (women), traders/shopkeepers where women discussed situation regarding poverty, land ownership, housing and sanitation, access to potable water, health facilities, education etc. along with their various kinds of vulnerability as poor and as destitute women. These included life as

widows, life as women abandoned by husband and having disabled male household head. In addition, women‘s perception towards construction related work and willingness to engage as

contractual labour road and market construction also have been discussed. This report represents findings of the FGDs and review of some previous and on-going infrastructure development projects to provide gender related inputs to CCRIP project design.

29. Market infrastructure development offers a range of opportunities to support women

empowerment. The Sustainable Market Infrastructure for Livelihoods Enhancement (CCRIP) project will be implemented in 32 coastal and flood prone Upazilas with high incidence of

11 Prepared by Sinora Chakma, Consultant (Gender Specialist), IFAD

Page 74: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

9

poverty, poor communication and market facilities in south-western region in Bangladesh. The

project proposes to develop women section, separate toilet facilities and create employment through construction work and maintenance as well as skill development of the poor women.

Poverty situation of the visited areas 30. Disasters: All houses built with weak materials were damaged by the SIDR in Khulna and

Bagerhat. On the other hand, the village of Satkhira district was affected by the AILA. These

disasters had resulted loss of human lives, livestock and damaged communication infrastructure along with destroyed water and sanitation system. Many people became impaired. The people of these locations geographycally vulnerable in terms of lack diversified income earning opportunities that ensure earning for throughout the year. Among them women are the most vulnerable as women and as poor. Therefore, it was really difficult for the rural poor to cope with such kind of calamities receiving almost no support from

government except food (not adequate). 31. Female-headed households: Female headed households have been found who are either

widow or abandoned due to husband‘s second marriage. Usually men migrate to outside the locality to work in agricultural fields, brickfields, construction etc. and other works. It is

common that they get marry again in the new place and rarely come back to village. As a result, many women became head of the household and responsible to manage livelihoods of

the children and in some cases old parents. 32. Religious diversity: Hindu and Muslim communities have been found in the area of Khulna,

Bagerhat and Satkhira district except Christian community found in Khulna area. Poor people have no arable land, even most of them live on khas or others land. Poultry rearing is common, but livestock raising is not practiced by the poor people due to absence of adequate grass and trees as well as the poor health services of the livestock department.

33. Housing and access to water: The poverty status of the rural people appear clear with their

weak housing structure and katcha sanitation system particularly in Khulna and Bagerhat districts. There were insufficient government and non-governmental supports have been provided to the victims of SIDR and AILA. Scarcity of potable water due to salinity is common problem in the region. Since there is no tube well, people have to depend on the pond water,

which is sweet but requires boiling. Therefore, women need to spend 2-3 hours to collect water from distant place (mostly pond) which is much difficult during rainy season since the

road became muddy and submerged. 34. Dowry: Dowry is practiced in all the places; however, it has been observed that everybody is

aware about the negative aspects of early marriage and known about the actual age of marriage for men and women.

35. Health service: Due to the geographical location the people are vulnerable to health hazards

in regards to working in saline water, scarcity of potable water, poor infrastructure and natural disasters. Among the basic services poor people mostly face lack access to health facilities. They depend on pharmacies for medication as well as midwives for delivery; however, in case of serious situation many people die in these localities due to absence of proper communication with the hospital. The rural women stated that as the only

communication system with the town is boat especially at night time and in the rainy season it is difficult to hire a boat regarding high charge or even in the day time they need to wait until the boat is full to move. They also shared that as it takes long time to move many patients die even on the boat. Therefore, this poor communication system costs high for the

poor to get health services which often causes of death of pregnant women and new born babies.

36. Schooling: Poor women cannot afford money to send their children to school though they get

free book, nevertheless, it is difficult to manage the cost for dress and other related materials for schooling.

37. Access to microcredit: Among the three visited places of Khulna, Bagerhat and Shatkhira, only

the poor women of Satkhira district have access to NGO for savings and micro- credit. These

women make mat with local materials and sell it to the local market. It requires 2 days to make a mat which is sold for 200 tk and above. On the other hand, other two villagers do not

Page 75: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

10

have any involvement with NGOs due to their irregular income which prevents them to fulfil

the requirement of access to loan. Income-generating activities 38. In coastal and riverine areas the employment opportunity is very limited and the rural poor

households of these areas have to depend upon fisheries and off-farm labour. Due to salinity

they can only produce Aman paddy, some vegetable and fish, mainly shrimp. Poor and destitute women lack access to wage employment. As the rural communication system is poor there are no or very limited commercial business/offices/NGO activities exist which can generate employment opportunities for the rural women. Thus, women of these locations have involved in agriculture labour, in construction especially earth work, domestic help and some in factories. However, these type of work is not available for the whole year in order to

manage livelihoods. Since there are very few well-off households at the rural level, only one or two women can get access to work on a regular basis, it means that the women cannot earn money despite of their physical ability to work. Destitute women are paid rice or food according to the time they spent. As a result, when a very few number of women get any long termed work to anybody‘s household are considered lucky. Only one woman out of 27

expressed that she goes to the town of Morelgonj and Bagerhaat to work in offices and others house during rainy season when there is no work in the village. However, as it requires

transport cost and other support, other women cannot follow her. The communication infrastructure of the adjacent villages of Baniashanta bazaar, Khulna and Bohorbunio bazaar, Bagerhat are poorly developed with submersible rural roads that have some connectivity during the dry season and boats which acts as the main source of communication during the flood season.

39. Among three areas only the women of the adjacent villagers of Khajra bazaar, Satkhira have

been involved producing mat commercially with local materials. It is one of the major IGA activities for the women. However, many poor women cannot buy the raw materials to produce the mat and thus excluded from the earning activities.

40. Women also involve in small trading comprises temporary selling of consumer goods for

example, bangles, cosmetics, saree and other women‘s accessories. Some sit in shop and

some sell it by hawking to the adjacent villages. Some women also have been found to operate restaurant business, temporary teashop/sweetmeat, grocery shop and tailoring shop.

These women sometimes own a small shop which have seen in Banishanta market and in other places. Some women run their small trade at household level.

41. Women of the visited villages of Shariatpur, Madaripur and Gopalganj districts normally take

care of HHs and participate in agricultural production, harvesting and processing. Women

from this village do work for road construction etc. although LGED has LCS groups from other areas. Access to finance is relatively easy from MFIs, where most major and local MFIs offer loans.

42. Sometimes the nature of the income generating work in local level is very risky for the

women. For instance, most of the destitute women of Baniashanta manage their livelihoods for six months by fishing from the river which starts from late February or early March when

the water comparatively less cold. They need to spend much time in the water and particularly three months of fish breeding period (March-May) is their most vulnerable period. Since fishing is prohibited at that time, they catch fish at night carefully, otherwise possibility to caught by the coast guards. This kind of working nature often causes different kinds of

physical hazards. Nevertheless, rest of the six months they hardly can manage food for three times a day.

43. In all places wage discrimination by sex in all kinds of wage labour have been noticed which

varies from 50-100 tk per day. 44. Coping strategies of the destitute women with the vulnerability: Usually in the lean season

men migrate to outside and some young girls also go to work as factory workers. However, extreme poor and destitute women cannot migrate. They stated that since their relatives and

neighbours are also poor they cannot help each other. Moreover, they are excluded from NGO support due to absence of regular income and thus inability to repay the loan. Thus, their children are compelled to engage in labour and they reduce food intake or fast.

Page 76: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

11

45. In all places, the poor women have urged for creating working opportunity and showed their keen interest to involve in construction work to cope with their vulnerabilities.

Women and the market 46. Many rural communities particularly the coastal zone areas lack road links and all-weather

access to market centres and services. Poor women come to the market for both buying and selling purposes. They have no social or cultural restriction to visit the market and can visit the market without men‘s accompany. Mostly the poor women come to the market to sell their own agriculture produce such as vegetables, egg etc. Woman‘s membership in Market Management Committee has been found only in Khajra bazar, Shatkhira who operates a big shop in the market.

47. The sample markets faces the following problems:

a) Lack of transport and fully depend on walking to carry products due to absence of road; b) Rainy season is the toughest season for them to visit market (roads become muddy and

submerged); c) Time consuming;

d) No water as well as toilet facilities at market, if has, the toilets are locked by the committee;

e) No separate/remarked space for the women seller; f) In rainy season they need to sit with commodities in open space which is muddy as well; g) Less profit of the poor shop owners because of toll and rent of the shops as well as the

charge for carrying water from distant places; h) Lack of capital to expand their small trade;

i) Requires high cost to visit the next developed market.

Problems with working in construction work 48. Women of three locations have experience to work in earthen road. The problems they faced

during the construction are:

a) Threat of exclusion from the male leader in construction work if they fail/refuge to carry

excess than usual which is possible for men, but hard for the women worker; b) No water and toilet facilities during work particularly if there is no house along the working

site; c) Problems with taking care of young child; d) Less wage than the male worker.

Lessons learned from other projects 49. To complement the proposed CCRIP project some similar projects have been reviewed to

show the effectiveness and impact of such intervention on the destitute women to enhance their livelihoods.

Char Development and Settlement Project (CDSP-III): CDSP is the first and up to now the only project in Bangladesh where the woman‘s name has been included on the ―khatian‖ (the official document of title to khas land). The project also treats landless female-headed households as a priority category in land settlement activities. In addition,

CDSP-III NGOs have formed groups consisting exclusively of women covering almost 100% of all female settlers in the project area.

Market Infrastructure Development in the Charland Regions (MIDPCR): The poor destitute women have access to wage employment during construction of rural market, rural road and maintenance. Training on IGAs and micro-credit support their economic development became sustainable. More women are encouraged to engage in such works and involve in small trading through increased mobility to market having separate places to sit with commodities, separate corner for the women and small shop allocated for the women shopkeepers and access to separate toilet and water facilities. According to the

supervision mission September, 2011, 2741 poor women participated in the construction work who received training from the project staff. Among them 1,199 LCS members joined the project NGO MFIs groups for training on income generating activities and micro-finance

Page 77: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 2

12

services. All LCS members got paid work of about 50-160 days in a year during the

construction period and made taka 5-38,000 profit. More than 90% ex-LCS members invested the profits to IGA.

Sunamganj Community Based Resources Management Project (SCBRMP): Through the LCS groups, women (56 per cent) and men (44 per cent) were trained and employed in road construction work. More women than men were also involved in managing the construction of Concrete Block Roads (CBR), an innovation designed by the project. The

work is organized through the LCS and COs and women members were coordinating and managing the construction work, went to markets to purchase cement and other materials, and kept accounts. Women and men were paid the same wage for the construction work. The roads were maintained by 100 per cent women workers who were mainly women heads of households, earning around US$33 a month. The roads, apart from improving access to markets, also improved attendance of girls and boys in school and access to

emergency health services. The impact of above mentioned projects prove that women‘s positions have been

improved in terms of access to better income-earning opportunities, savings and micro-credit loans. These have improved their living standards, food security and access to health facilities, children‘s education etc. Women have got the ownership of land rights,

decision making power at household level as well as public sphere, women‘s mobility has been increased and now more women are aware about the issues related to violence

against women. Proposed intervention and expected outcome of the project 50. The project will replicate experience of building rural markets under MIDPCR by LCS.. The

CCRIP project foresees the following benfits to poor women:

a) Wage employment generation for the vulnerable group particularly local destitute women

as they will be engaged (using LCS scheme) in village road construction and maintenance,

rural market improvement and maintenance. All LCS will have women leaders and the

male members will be skilled construction workers, masons and their work assistants;

b) They will receive IGA training from PKSF partner NGOs in addition to financial services;

c) More women will be encouraged to engage in trading in women friendly market

infrastructure (access to separate toilet facilities and water, separate space for trading, toll

free trading for the LCS members) as well as improved rural roads will enhance their

capacity to spend much time for productive works.

d) Income generating activities would be increased which will enhance poor people‘s

sustainable livelihoods by skill development of the women workers, possessing household

assets which will provide them a regular income and make them empower to take decision

at household level and public level;

e) NGO activities and other government services such as health facilities, education will be

enhanced since the road communication will be improved;

f) Poverty situation will be improved at rural level when vulnerable people will be able to

intake adequate food, establish access to the basic services;

g) Women‘s participation in the MMCs will be reflected through women‘s membership in

MMCs;

h) Moreover, through this project the LCS members will receive training on construction and

maintenance. Later on this skill of construction work will enable women to work in future

construction work by other donor funded projects.

Page 78: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 3

Annex 3

Country Performance and Lessons Learned

Page 79: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 80: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 3

1

Annex 3

Country Performance and Lessons Learned

IFAD Portfolio and Institutional Mechanism

1. The recently completed, on-going and recently designed IFAD funded projects belong to

projects under 2006 COSOP that created excellent development impacts in terms of poverty reduction and provided major lessons and inputs for designing follow-on projects including the present SMIL project. The project under IFAD Bangladesh portfolio focus broadly in three intervention areas:

Microfinance services and value chain development although a number of value chain development initiatives are grouped with rural infrastructure projects: Three projects – MFTSP, MFMSFP, and FEDEC implemented by PKSF- fall under this category. All these

three projects are primarily financial services projects through PKSF and its partner organization but include also agricultural technology transfer, training and value chain

development of farm and non-farm subsectors. MFTSP and MFMSF projects were closed in 2011 and 2012 and FEDEC is due to complete in 2014.

Rural infrastructure projects: Rural infrastructure includes Union and village roads (all weather and submergible roads), rural physical markets development, small embankment

and irrigation infrastructure. The on-going SCBRM and MIDPCR implemented by LGED focus on rural infrastructure in haor basin (SCBRM) and coastal areas (MIDPCR). SCBRM developed rural roads (all weather, and submergible roads) using LCS in one of the environmentally fragile zone of Bangladesh. MIDPCR has developed rural roads and markets in coast areas with very good results. Participatory Small-scale Water Development Project Phase III (SW-III) co-funded with the Asian Development Bank (ADB) where LGED builds minor irrigation structure (closed and open irrigation channels,

sluice gates and minor embankments) to boost agricultural production. SCBRMP promoted self-help group approach of microfinance, which was later dropped due to poor performance. MIDPCR has assisted MFIs to provide microfinance services to groups of landless, and small and marginal farmers where it built markets. It has also managed a small value chain development program through an international NGO (INGO). Two other

major infrastructure focused projects – HILIP, which is a follow-on of SCBRMP project and CDSP-IV, which is replication of CDSP project – have just started implementation.

Although the lead agency for CDSP-IV is WDB but it has significant LGED component to build roads, markets, cyclone shelters etc. similar to MIDPCR.

Agriculture and natural resources management: MIDPCR has an agricultural development component implemented by DAE of Ministry of Agriculture (MOA). DAE, DLS and DoF also implement the National Agricultural Technology Development Project (NATP), co-financed with the World Bank. SCBRMP promotes high-value crops in haor areas, which will be

taken over by HILIP. One important activity under SCBRMP, which will be also expanded under HILIP, is management of beel (small water bodies within haor basin) by the poor people that increases access of the poor people to natural resources. Three projects under PKSF have directly financed farmers, and trained farmers on agricultural production technologies and promote many agricultural commodities with impressive success.

2. Two important institutions LGED and PKSF implement bulk of directly managed IFAD projects with huge success. LGED has a proven capacity to implement large and complex projects

which link livelihoods development with rural infrastructure. LGED‘s use of Labour Contracting

Societies (LCS) has channelled a share of construction work to the poorest women. PKSF has built a huge reputation in the management of micro-finance and calls more than 250 microfinance institutions (MFI) its partner organisations. By this, PKSF plays a key role in the microfinance sector in Bangladesh. It now faces fresh challenges in developing broader approaches to poverty reduction and has ventured into value chain projects, vocational training and the promotion of employment for the poor. BWDB has vital expertise in water

engineering but faces institutional constraints in efficiently managing projects. Institutions that make up the Ministry of Agriculture, DAE and the National Agricultural Research System (NARS) have a great outreach and well established roles in leading this key sector. However, they have acknowledged problems in their human resources, with administrative tasks that leave DAE staff with little time to support development projects.

Page 81: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 3

2

Past results, impact and performance

3. Data from project surveys provide evidence of the impact of projects in terms of better livelihoods, increased income and improved food security. Table 1 below summarises some of the improvements in food security reported in these surveys, while Table 2 presents data on the change in child malnutrition.

Table 1: Changes in food security

Project Indicator Change Notes

Aquaculture Development Project Per cent of households reporting improvement

14% (control group 1%) Final impact survey 2006

Smallholder Agricultural Improvement Project

Decline in average length of period of food shortage

44%

(control group 29%)

Final impact survey, 2009

Micro Finance and Technical Support Project

Per cent of households reporting improvement

8.5% Impact over a 4 year period 2004-08

Micro Finance for Marginal and Small Farmers Project

Per cent of households reporting improvement

8% Mid-term impact survey 2004-08

Sunamganj Community Based Resource Management Project

Per cent of households reporting improvement

Members of BUG* 15%

Members of CO** 17%

BUG over 2 years

CO over 6 years

*BUG: Beel (water body) User Group; ** CO: community organisations; Source: COSOP 2013-18

Table 2: Sunamganj - child malnutrition indicators

Percentage of children 2006 2010

Chronic malnutrition (height-for-age < -2SD) 56.7 47.9

Acute malnutrition (weight-for-height < -2SD) 15.3 15.4

Underweight (weight-for-age < -2SD) 58.6 54.6

Source: RIMS anchor indicator surveys, SCBRMP, Mitra Associates as quoted in COSOP 2013-18

4. Three projects through PKSF have greatly expanded microfinance services to the poor, landless, marginal and small farmers, and micro-entrepreneurs. Agricultural technologies promoted by PKSF and other projects have made good impacts in boosting production and

reducing cost of production. Value chain development activities, although small in terms of

resources compared to respective project resources, showed evidence for growth in sales and profitability and opportunities for expansion.

Lessons learned

5. The present and recently completed projects show most relevant lessons for designing new projects in terms of project activities, process of implementation and institutional choices. The COSOP completion review 2006-2011 suggests the following as perhaps the most critical lessons by sector:

Agricultural development remains critical to ensure food security and employment, whilst

the support to enter the non-farm sector for employment is increasingly important for poverty reduction. IFAD funded projects show that the combination of agricultural development with access to financial services and adequate extension services augment the scale of impact and sustainability of a new technology. Extension services need to be specialised and could be delivered by both DAE and the private sector. A value-chain approach can ensure the input supply and diversification alongside the promotion of technology to assist farmers and micro-

entrepreneurs to enhance profits, generate business and employment.

Microfinance including microcredit remains critical although the financial services have expanded greatly in the country but the emphasis needs to be on developing demand driven services and customizing the service as much as practicable. The Self Help Group approach to micro-credit does not deliver the benefits in terms of poverty reduction, and is un-sustainable than the more usual Bangladesh microfinance model. Seasonal loans for agriculture meets well farmers‘ demand, but needs close monitoring to ensure repayments. Increasingly larger

loans for agriculture and microenterprises, and MFIs are better equipped to provide such follow-up than commercial banks. Savings and insurance products including livestock insurance remain important to cope with financial and natural shocks. A number of pilot projects in livestock insurance and savings products show great opportunities for further expansion.

Page 82: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 3

3

Value Chain Development: A number of IFAD projects (FEDEC, MFMSFP, MIDPCR and

MFTSP) have had success in using a value chain approach to developing enterprise and livelihoods. These activities include dairy farming, poultry such as backyard chickens, ducks an crops such as maize and horticulture particularly, tomatoes, brinjal, gourds and other vegetables, soybeans, mustard, oilseed crops, etc. The strategy of linking producers to service providers and markets has resulted in adoption of new technologies, increased yields, higher producer prices and significantly higher profits. The current project will also adopt such a

value chain approach in identifying opportunities for livelihood protection.

Small-scale infrastructure in terms of rural markets and communication roads showed impressive impact on the local economy and employment. The trade volume increased substantially within a short period of time, while cost of transport could be halved and local wages doubled with the increased demand for labour. Prices increased as demand increased due to more buyers arriving from far away. The village roads built in Sunamganj have boosted

the local economy and improved livelihoods. A study carried out by SCBRMP found a major switch to the use of light motorized vehicles, increased cropping intensity and area under crops, especially high value crops grown for the market, and sales of crops. The cost of transporting crops and fertilizer had halved, and more labour was being hired for both farm

and non-farm businesses. Survey respondents reported increased employment opportunities, increased wages, higher income, better access to education and health services, and greater mobility of women. Land values near the road had more than doubled.

Rural Markets: Rural markets have been successfully developed in relatively remote coastal areas by the Market Infrastructure Development Project in Charland Regions (MIDPCR). Even before the link roads are complete, benefits from market development include: (i) an increase in the number of buyers and sellers (including women) by at least 25-50 percent; (ii) an increase in the number of wholesalers coming to the market leading to greater competition (iii) a greater choice, variety and quality of goods; (iv) a good environment not only for selling and buying but also for community members to meet; (v) decrease in losses of perishable produce

as goods are sold more rapidly; (vi) decrease in cost and time spent on transport; and (vii) increase in value of land and construction of other facilities (such as shops) in the area around the market. A survey recorded an increase in average sales per trader of 32% (from Tk11,755 to Tk15,475 per week). Based on this data and the increase in numbers of traders, the overall increase in volume of trade was reported to be 75%.

Type of construction: The on-going IFAD project in the Haor Basin, the Sunamganj

Community Based Resource Management Project (SCBRMP) has pioneered the construction of village (community) roads using reinforced concrete (RCC). Unlike conventional bitumen road pavements, concrete roads are submersible and can withstand flooding. Not only does this make them suitable for the flooding conditions of Sunamganj, but embankments do not need to be built to keep roads above flood levels. Such embankments can obstruct the flow of water and cause additional environmental problems as they block the free flow of water and can cause water logging. SCBRMP‘s further innovation was to make the roads from concrete

blocks rather than RCC. This reduces the cost and because of the more labour intensive nature of using this technology it creates additional employment for women and enables them to adopt a more flexible work schedule. The block pavement is less vulnerable to major subsidence of the base structure. Even if the road is entirely eroded by flood water, the blocks (which represent most of the value in the road) can be recovered and the road re-laid. This makes it particularly suitable for flood prone locations.

Labour Contracting Society: The use of Labour Contracting Societies as a principal

mechanism for constructing village roads and other small schemes was an effective way of targeting the poorest women. A baseline survey for MIDPCR showed that 68% of the women

members were the principal bread-winners for their families with two-thirds of respondent households. Households of women involved in the LCS generally did not even own land for a homestead and all had incomes that would place them in the poorest 10% category. Almost all of these households suffered from some period of food shortages, with 41% per cent

experienced these shortages all year round. A follow-up survey of MIDPCR LCS found that, on average, women had earned Tk7,469 in wages and had received Tk9,569 in profit share. Wages and profit money have been divided between productive enterprises (34% in total, with 19% being used to buy cattle), 28% was used for household investments (leasing-in land 9%, land purchase 5% and house building 6%), and 38% for consumption (29% for food). The number of cattle owned by sample households increased by 169% and goats by 140%. This shows that benefits from LCS have been partly used to support families (the percentage of

children going to school increased from 74% to 86%) and partly for purchase of assets.

Page 83: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 3

4

Women also reported improved confidence and a better standing in their families and in the

wider community.

Natural resources management and community fishery is a successful poverty reduction approach. Secure long term leases for community fisheries can move fishing households from poverty all the way to prosperity, as shown in SCBRM project. Despite support from MoL, the transfer of water bodies to community management is a difficult and lengthy process, and may require some support by international agencies. Regular leadership elections via a secret ballot

help ensuring that leadership in fishery groups remains accountable to members.

Women empowerment. The use of LCS instead of a commercial contractor for construction of markets and roads creates employment, enhances skills and cash in the hand of the poorest women and boosts their self-esteem. Technical and skills training in agriculture has had limited impact on women as agriculture is mostly managed by men. Decision making power remains a key issue for gender. Although women benefit from membership of micro-finance groups, the

realized gains are limited as men still dominate most major decisions.

Project management issues: It is important that right institutions and right mix of activities are chosen to implement projects to ensure smooth implementation and impacts. LGED‘s core

competence is implementation of infrastructure project, and it has skilfully implemented both SCBRMP and MIDPCR infrastructure component whereas it struggled to deal with MFIs and managing value chain activities. In addition, combining infrastructure with financial services and value chain development is also packaging wildly diverse activities under on project

although there may be demand for these activities. Whereas it has been found perfectly alright to deliver financial services combined with value chain activities under PKSF both in terms of match between activities as well as implementation capacity where PKSF and its partner organizations are competent to manage financial service programs. Therefore, it is only prudent to separate financial services and value chain development from infrastructure and give LGED to manage infrastructure project only such as CCRIP.

Page 84: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 4

Annex 4

Value Chain Development and Infrastructure

Page 85: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 86: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 4

1

Annex 4

Value Chain Development and Infrastructure12

1. In a selection of 30 poor, remote and with a limited infrastructure network Upazilas within 12

districts located in the South-West of Bangladesh, the situation with regards to value chain development can be assessed with the following data: (i) yield and income per hectare; (ii) market and storage facilities, and (iii) financial services.

Yield and income per hectare. The most important crops and production in the sample of Upazilas are: paddy/rice; fish/shrimp farming; potato; tomato; cucumber; onion; country bean, and vegetables. The current situation can be described as follows: a/ weak and unbalanced linkages between value chain stakeholders dominated by very

few input suppliers rarely visiting remote villages and markets or supplying them with low quality inputs resulting in low yield and low quality production, and by a handful of

buyers, mainly wholesalers, purchasing local production just after harvest when

unilaterally-fixed prices are at their lowest; b/ very limited access to improved technologies and technical advisory services which

result in constant low quality production.

Considering the lack of appropriate roads and adequate markets combined with low levels of production and below-average quality, buyers have no incentive to frequently visit these

Upazilas and villages and when a few number of them come, generally just after harvesting season, they offer the lowest prices possible; suppliers have no incentive to establish a business through an agent so that farmers cannot access to high quality inputs. Lack of expertise and advisory services provided either by agricultural extension officers or by stakeholders of the value chain maintains the production at a low yield and poor quality.

As a result of such a situation, selling prices are kept low; production costs per kg produced remain at a high level because cost of inputs and seeds is high and yield is low; transportation and marketing are expensive due to poor road and market connections, hence a low net profit for farmers. Low quality of production results also in a very limited bargaining power vis-à-vis wholesalers and collectors, hence low selling prices.

Market and storage facilities. The proportion of under-developed markets in the 30

selected Upazilas ranges from 65 to 100% (with total number of markets ranging from 9 to 80). Unattractive market facilities for all value chain stakeholders are hampering any increase in local agricultural production and sales. With regards to storage facilities, the situation varies from Upazila to Upazila and from district to district with district sadars having sometimes up to 40 storage facilities with a capacity of 12 000 tons and above and some districts having less than 5 storage facilities

amounting to a maximum capacity of 3 000 tons (14 districts on the 29-sampled districts). Lack of storage facilities of adequate capacity constitutes a hindering factor for the increase of any agricultural production. Due to this lack of storage facilities, farmers and producers (i) cannot store part of their production after harvest waiting for market prices to be higher than at harvest time; (ii) have to sell their production either to wholesalers with a limited bargaining power or to local markets at low prices, and (iii) have limited

incentives to produce more.

In one village visited, main crop after rice is potato. Price ranges from Taka 8/kg (during harvest time) to Taka 16/kg three months after harvest season. Most producers are selling at harvest time at the lowest price because of a lack of storage facility in the village allowing to store and wait for a higher price. Due to the remoteness of the village, only a handful of wholesalers are coming only a few times during harvest season to pick-up the

village‘s production. The construction of a paved road combined with a collectively managed storage facility could enable these potato producers to store their production and target higher selling prices.

12 Prepared by Thierry Mahieux, Consultant, IFAD

Page 87: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 4

2

Financial services. Excluding district sadars (centres), the presence in rural areas of

financial service providers is moderate to low (ranging from 4 branches of financial institutions to 30 branches in one single district). Financial institutions include (i) microfinance institutions that are extending micro-credit loans mainly for trade activities (high interest rate short-term credits with inventories as collateral and daily or weekly repayments), however some of them have started to provide agricultural loans; (ii) commercial banks extending short- and long-term loans for individuals and enterprises

able to provide sufficient collaterals (commercial bank branches are mainly to be found in district sadars), and (iii) agricultural state-owned banks which are extending agricultural loans at subsidized interest rate (ranging from 10 to 13% depending on the type of activity financed – 10% for crop production, 11% for poultry, 12.5% for fisheries and 13% for dairy production) and are also extending joint)liable group loans to women‘s groups at an interest rate of 11% per year with a 52-week repayment schedule. Repayment rates range

from a mere 70% for agricultural banks to 99.9% for microfinance institutions. If microfinance institutions can be found in many villages, even in some of the most remote ones, access to adequate financial services for producers and farmers is constrained by the low density of other financial service providers‘ network. Interviews

with branch managers of agricultural banks indicate that in most cases, their loan officers are waiting for clients to come to bank‘s branches and only when loan applications have

been reviewed and screened a first time at the level of the branch, they visit potential borrowers (in one district, there are only 10 credit officers for 5 branches covering 16 unions and approximately 50 to 60 villages).

2. Sustainable and profitable agricultural activities in remote villages are constrained by several factors, the most important being the lack of proper infrastructures such as all-year long practicable paved roads connecting markets to main roads, thus facilitating the distribution of

goods locally produced to new markets; rehabilitated markets with adequate facilities for exposing and storing goods complying with health and hygiene standards that will boost sales and consequently production; collection points enabling a decrease in production and transportation costs for farmers and producers and facilitating linkages with buyers, and finally storage facilities enabling farmers and producers to store part of their production waiting for higher market prices and enabling them to change their distribution pattern and to

increase their production. Improved communication, storing and marketing facilities would strengthen linkages between value chain stakeholders (suppliers, producers, buyers, and

technical and financial service providers). 3. The focus of CCRIP on infrastructures aims at addressing a major constraint identified during

the mission field visits but also in the IFAD-supported MIDPCR, implemented in the same region. As a result of the construction of connecting paved roads from secondary markets to

main roads, the rehabilitation of existing markets, and the construction of located collection points and eventually small storage facilities, access to technical and financial service providers and to other value chain stakeholders in a sustainable and balanced way would be facilitated and improved. Consequently, strengthened value chains would start evolving according to market principles with limited further involvement from projects.

4. Although pre-requisite and necessary, the implementation of infrastructures is not a sufficient

condition for the establishment of sustainable value chains. Other activities would have to be implemented as well such as:

a/ assistance to value chain stakeholders to enter into contractual arrangements and close

collaboration (forward contracts could be developed as a way to strengthen the relationship between buyers/processors and producers). These contractual arrangements

could also include the provision of technical assistance and advisory services by buyers and suppliers to farmers and producers;

b/ assistance to service providers to develop their network and to adapt their products to the requirements of activities financed. In particular, in light of an increasing production of higher quality, suppliers will have incentives to provide better inputs and to establish a point of services in these villages. As a result of improved market linkages, increased level of better quality production and roads, loan officers will have incentive to visit these

Upazilas/villages and promote new financial products such as agricultural loans or warehouse financing in case of storage facilities.

Page 88: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 4

3

c/ provision of technical assistance for quality improvement and higher marketability of

products (labels, packaging); d/ assistance for the identification of new markets and the implementation of new distribution

networks; e/ assistance to all stakeholders to establish value chains governed by market principles as

well as to implement a more even distribution of the product‘s profit margin between all stakeholders.

5. These activities would be implemented within the next IFAD-supported project focusing on

value chain development. However, the sole implementation of these additional activities disconnected from infrastructure development activities would barely have any impact at all as infrastructure represents the main bottleneck and major issue for most villages in the CCRIP targeted area.

6. Although non-negligible, the impact of infrastructure development activities carried out under

CCRIP on value chains is difficult to assess. However, based on results from the on-going MIDPCR activities, the construction of roads and collection points as well as the rehabilitation of markets combined with the above-mentioned provision of technical assistance and advisory

services have led to the following changes: (i) increase in selling prices as a result of an increased competition between a larger number of buyers; (ii) decrease in production and

marketing costs due to numerous factors such as access to improved technologies, equipment and inputs; access to cheaper transportation due to an higher volume traded; (iii) increase in yield and quality of production, and (iv) improved access to adequately designed financial products and services. Such changes are triggering factors for a substantial increase in farmers‘ and producers‘ income and for structured and sustainable value chain development.

7. It can be expected that part of the changes identified result from activities related with

infrastructure development and part results from activities related to the provision of technical and financial services to all value chain stakeholders. The following table illustrates for 6 products the changes in production‘s yields and in farmers‘ net income two years after the implementation of different activities (infrastructures, provision of technical advisory services, linkages among value chain stakeholders, introduction of improved technologies, access to adapted financial products) in the same region as the CCRIP one. Although difficult to

breakdown between the impact of the different activities implemented, part of this incremental income can be allocated to infrastructure activities.

Table 1: Changes in yield and net income for 6 selected products

Yield Prod. Costs Mark. cost Sales Net income Yield Prod. Costs Mark. cost Sales Net income Yield Net Income

(Kg/dec) (Kg/dec)

Paddy/Rice 9 62 12 113 39 12 110 44 215 61 33 56

Fish 10 334 105 924 485 24 978 173 2.875 1.724 140 255

Tomato 73 155 68 770 547 172 325 135 1.785 1.325 136 142

Cucumber 77 287 110 710 313 150 672 155 1.623 796 95 154

Country bean 43 117 75 670 478 95 200 103 1.698 1.395 121 192

Mung bean 4 90 28 263 145 9 120 50 560 390 125 169

Changes

%

Products

(Taka/dec)

Baseline survey in 2009 Current situation as of Dec. 2011

(Taka/dec)

8. The following table shows the current yield and income for a group of farmers (average) as

well as the yield and income for the best performing farmer among the group and compares them with the yield and income any farmer could achieve when complying with best practices (access to high quality inputs and supplies and improved crop management; adoption of improved varieties; soil and water testing) in a proper environment (connecting paved roads,

rehabilitated markets). To avoid distortion, selling prices have been kept similar (although competition among buyers and production of higher quality would result in a substantial increase in selling prices. The table shows data for crops and products cultivated in the CCRIP projected area.

Page 89: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 4

4

Table 2: Impact of adoption of best practices vs. current crop management

Net profit Yield

Paddy/rice Average farmers 11.450 21.400 32.850 57.000 24.150 3,6

Best farmer 13.420 22.000 35.420 60.000 24.580 3,8

Best practices 26.331 25.600 51.931 95.000 43.069 6,0 78,3 66,7

Fish Average farmers 108.500 6.000 114.500 988.000 873.500 9,8

Best farmer 139.925 10.000 149.925 1.852.500 1.702.575 18,5

Best practices 153.203 12.000 165.203 1.976.000 1.810.797 19,8 107,3 102,0

Tomato Average farmers 56.540 50.800 107.340 210.000 102.660 21,0

Best farmer 58.500 52.800 111.300 225.000 113.700 22,5

Best practices 95.925 67.800 163.725 600.000 436.275 60,0 325,0 185,7

Cucumber Average farmers 69.800 43.750 113.550 195.000 81.450 13,0

Best farmer 67.725 44.000 111.725 202.500 90.775 13,5

Best practices 68.970 44.000 112.970 225.000 112.030 15,0 37,5 15,4

Potato Average farmers 70.640 31.400 102.040 180.000 77.960 15,0

Best farmer 72.980 33.000 105.980 198.000 92.020 16,5

Best practices 103.040 37.000 140.040 306.000 165.960 25,5 112,9 70,0

Onion Average farmers 31.040 36.776 67.816 115.267 47.451 10,9

Best farmer 31.967 35.560 67.527 117.504 49.977 11,1

Best practices 29.601 36.700 66.301 167.318 101.017 16,0 112,9 46,8

Country bean Average farmers 8.450 12.150 20.600 75.000 54.400 3,0

Best farmer 12.290 14.700 26.990 87.500 60.510 3,5

Best practices 26.042 18.000 44.042 125.000 80.958 5,0 48,8 66,7

Mung bean (*) Average farmers 14.367 22.100 36.467 56.000 19.533 0,8

Best farmer 16.470 20.250 36.720 70.000 33.280 1,0

Best practices 14.910 20.250 35.160 70.000 34.840 1,0 78,4 25,0

(*) yield in kg/ha

Category Products Inputs

cost

Labor/renting

cost

Changes (%) Total

expenditures Revenues

Net profit

(Taka/ha)

Yield

(t/ha)

9. Table 2 shows the potential for increase in both production and income for different crops and

products when applying best practices to current crop management. However, as previously indicated, adoption and implementation of best practices alone would not be sufficient without

improved infrastructures.

10. Interviews conducted in villages and markets during the inception mission field visits with

local farmers (in most cases, they are also retailers at the local market) show that farmers project an increase of the selling price about Taka 2 to 5/kg for paddy as a result of the development of infrastructure and the larger number of buyers. They also estimate that their production cost per kg produced would decrease (farmers‘ estimation varies between 5 and 20%).

Page 90: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

Annex 5

Detailed Project Description

Page 91: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 92: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

1

Annex 5

Detailed Project Description

I. Upazila Selection Criteria, Process and Results

I.1 Upazila Selection Criteria

1. The Upazila selection was done in consultation with MIDPCR/LGED during the preliminary design mission and confirmed at the time of detail design mission and final design mission. Seven indicators (criteria) were used to select 32 Upazilas in 12 districts by evaluating 77 Upazilas from 13 districts. The indicators and corresponding weight in scores reflect emphasis

on poverty, vulnerability to disaster, remoteness and present level of infrastructure development to ensure that poorer, vulnerable, remote (char and low-lying areas) and least developed Upazilas are identified and selected as project areas. In addition to quantitative data used for scoring, field observations were used when quantitative data were inadequate to include deserving Upazilas that were excluded by quantitative scores. The sources of data are BBS/WFP/World-Bank poverty maps, LGED inventory on rural roads and markets, district and union information, and field observations. See Working Paper 2 for Upazila selection process.

I.2 Project Upazilas and Unions

2. Upazilas: By using seven criteria 32 Upazilas have been selected (Table 1). Amtail upazila of Borguna district is expected to be divided by the government into two Upazilas. In that situation the newly formed and named Upazila will also be taken up as a new project Upazila. However, that would not change the project activities as the same geographical area will be administratively divided into two upazilas only.

Table 1: Selected Project Districts and Upazilas

District Upazilas Names of CCRIP Project Upazilas

1 Barisal 3 Uzirpur, Banaripara and Babuganj

2 Bhola 3 Charfasion, Borhanuddin, and Lalmohan

3 Patuakhali 5 Sadar, Galachipa, Rangabali, Kalapara, and Mirzaganj

4 Barguna 4 Amtali, Betagi, Bamna, and Patherghata

5 Pirojpur 2 Matbaria and Zianagar

6 Jhalkathi 1 Kathalia

7 Madaripur 2 Shibchar and Rajoir

8 Gopalganj 2 Tungipara and Kotalipara

9 Shariatpur 2 Zanjira and Naria

10 Bagerhat 2 Sarankhola and Moralganj

11 Khulna 3 Botiagata, Dacope, and Koyra

12 Sathkhira 3 Shymnagar, Ashashuni, and Kaliganj

Total: 12 32 32

3. Unions: The above 32 Upazilas have 204 Unions. Initial estimation shows that the union and

village roads and community (village) markets will be constructed in about 125 Unions.

However, the exact names and numbers of project unions can be determined at the time of

implementation of the project.

II. Markets and Roads Selection Criteria and Process

II.1 Introduction

4. One important activity was done by LGED before the final design mission was to conduct a survey in 32 project Upazilas to select a) three types of markets – Type I: Special community (village) market, Type II: medium community (village) markets, Type III: Small village markets, and community collection points (CCP) (see below for definitions) , and b) roads

(union and village roads) for development under CCRIP (IFAD funded part). LGED used an

Page 93: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

2

elaborate questionnaire (See Working Paper no. 2) to collect information about markets and

potential roads as per strategy and criteria decided by IFAD and LGED (see below). A summary list of markets and roads had been prepared, which was used during final design mission to verify and identify markets and roads for development. Besides, it was used by the final design mission for consultation with potential project beneficiaries and recommend appropriate infrastructure. The process has led to selection of community (village) markets and union and village roads to be developed by IFAD loan. See Annex 7 for final list of

community markets and union/village roads under CCRIP. LGED has included the list in DPP.

II.2 Market Types

5. Market types: The CCRIP project Upazilas have a total of 967 undeveloped village/rural markets, i.e. on an average 32 rural markets but vary between 9 to 61 markets depending in the size of the upazila, and numerous informal ‗community collection points‘, spread all over the Upazilas. Four different types of markets have been identified:

Type I: Special type market that needed unique infrastructure such as large ghat and fish shed as the concern market is an important fish landing center, for example, Fakirhat in Amtali.

Type II: Medium market: Several (3-5) markets are locally considered ‗large markets‘ with often more than 100 permanent shops, several hundred small temporary sellers assemble during two haat-days every week to do business; and organize cattle market. These large markets act as assembly markets, which serve 10 to 20 villages, where farmers bring their

commodities on haat-days and outside (from the same or other Upazilas or districts) buyers (called bepari) come to buy agricultural commodities to ‗export‘ to other districts.

Type III: Small markets: On the other hand, smaller rural markets may have 5-50 small shops, may or may not have haat-days, and serve small population of 2-5 villages. Smaller volumes of commodities are transacted in these markets but have potential to grow to bigger markets, if developed.

Community collection points (CCP): The community collection points are not formal

markets but informal places - often on the sides of road, bank of rivers/canal etc., where farmers call the buyers with vehicles to collect fish, vegetables and other commodities. This allows the farmers to harvest and sell every day and need not to go to markets or wait for haat-days. Although these places are important and convenient business places

but there is no infrastructure such as shed, truck or boat-ghat to convenient keep, load or unload commodities. Small improvement may allow farmers/buyers do business more

conveniently.

II.3 Market selection strategy

6. Although demand is very high to build markets much more than availability of resource the basic strategy is as follows (See Annex 7, 7A and 7B of Project Design Report for exact number of markets taken for development and annual plan):

a) A few special markets in the whole project area; b) One large market in each Upazila, which is strategically located (for example, next to good

road, bank of a river that connect to growth centres or several other smaller markets), already serve as assembly markets, serve a large population of 10-20 villages, and attract a large number of buyers and sellers;

c) 5-8 smaller village markets that serve 3-5 villages, connect to large markets; and d) A few conveniently located community collection points, which are already used by the

local communities (farmers, fishers) as business transaction points, to be developed on

pilot basis.

II.4 Market Selection criteria

7. Basic pre-conditions for markets: In addition to definitions and features mentioned above of large markets, small markets and collection points each selected market irrespective of size must meet the following basic pre-conditions:

a) It must not be vulnerable to river erosion in short/medium term; b) It has land (khas land or private land to be donated for the market) for development and

placing suitable layouts; c) Market stakeholders (UNO, UP, Ijarader, and MMC) support the proposed development or

construction; and d) An agreement by UNO to share lease income with the MMC as per GoB rules.

Page 94: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

3

8. Secondary criteria: Markets that meet the basic pre-conditions will be prioritized according to

the following criteria:

a) Potential for poor women to participate in construction of the market as well as buyers/sellers;

b) Stakeholders share a part of development cost that would expand development works; and c) Stakeholders agree to reserve part of all sections of the markets for temporary sellers,

especially for women and small producers.

II.5 Infrastructure for markets

9. Type I: Special market: One or two unique infrastructure and infrastructure commonly allocated for a large market (see below);

10. Type II: Medium markets: Subject to availability of land, a large market under CCRIP can receive the following package of infrastructure: a) A fish shed; b) multi-purpose shed; c) an open raised platform; d) internal paved roads; e) internal drainage and garbage collection pit;

f) toilet block; g) women section (6-8 shops); h) a ghat, if at the bank of river/canal; and i) paved truck parking area.

11. Type III: Small markets: Subject to availability of land, a small market under CCRIP can receive the following package of infrastructure: a) one to two multi-purpose sheds; b) open platform; c) toilet block; d) internal road and drainage; e) ghat and or truck parking space.

12. Community collection points: Subject to the needs, a community collection point may receive

the following infrastructure: a) ghat, if next to a river/canal; b) paved truck parking space for three trucks; and c) a raised platform or simply paved space with or without shed.

II.6 Selection of Rural Roads

13. The selection of roads under CCRIP project has been determined by selection of markets. Thereafter, the feeder roads connecting the villages within the service area of the markets are identified and assessed as for their conditions., i.e. rural roads connecting the selected markets have been taken up for development. However, due to resources constraints not all

connecting roads could be taken up. The objective is to connect the selected rural markets with growth centres, or with large markets under the project or with already developed markets. It has been observed that large markets may be already next to paved roads, that is, roads connecting large markets need not to be selected. Mostly, smaller markets

connected by earthen roads or HBB will be selected for development. However, the situation may vary in each Upazila and the actual determination will be done by conducting a final survey or re-checking of information of the survey already done.

14. Three different types of roads are envisioned under the project: a) Bituminous roads; b) RCC roads where roller can not be taken and flood prone areas; and c) block roads where frequent or surge floods or submersible situation is expected. The proportion of block roads is expected to be small under CCRIP. In some areas, present HBB roads may be improved to bituminous or RCC roads.

15. Subject to availability of resources, each Upazila on an average will receive 5 km of union

roads, and about 10-11 km of village roads. A total of 5km of block roads will be built. In some Upazilas, demand for paved roads may be lower due to past development where the plan is to focus on developing markets. The PMO may vary the lengths and types of road for each Upazila depending on needs and physical circumstances and location of roads. See Annex 7 for selected union and village roads.

III. Lessons from MIDPCR Project

III.1 Market Development (physical aspects)

16. The following observations from the field visits (MIDPCR) will have impact of market design for the CCRIP project. The new design and cost estimates have taken these factors into consideration:

i. Often the garbage shed was found too small and this has been enlarged and reflected in the budget.

ii. A women‘s market toilet has been added as optional for those situations where women need more privacy.

Page 95: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

4

iii. Open drains will be provided with a bar screen to filter out solid waste prior to discharging

the effluent onto public water or land. For larger or special markets a primary treatment may be included prior to discharging the effluent onto open water or land.

iv. Solar panels will be provided to market places.

Solar panel based electric supply This is becoming very popular in rural areas due to absence or poor quality of rural electric supply systems; load shedding is very high and therefore, to get uninterrupted power supply for the whole day, alternatively shop keepers are using generator based electric supply. This is for a limited time available often up to 10pm but markets remain open until 12pm. The quality of power generation is also not good, voltage fluctuation affects electric appliances and the rate (10-15 Taka/per night) is increasing steadily due to increasing fuel price. Nowadays a solar system is easily available and affordable and recommended is that CCRIP promotes renewable energy based electric system. For women market section it is needed to increase security; market surveys revealed that in remote areas about 60-70% permanent shops have a solar system. Costs of solar based system are as follows:

20 WP (2 points system) - 2 energy bulbs - taka 12,600/= 40 WP (4 points system) - 4 energy bulbs - taka 22,800/= 65 WP (6 points system) - 6 energy bulbs - taka 34,700/= 85 WP (8 points system) - 8 energy bulbs - taka 43,500/=

One typical shed would need at least 6 points system and one women shop within WMS would need 1 shared point system.

III.2 Union and village roads

17. The following three issues have been considered when designing transport infrastructure:

i. Considering the fact that it would be better strategy to upgrade the polder system by incorporating the climate resilient and adaptation features than the infrastructures within the polder and also taking into cognizance that in the road hierarchy, union and village roads lie at the bottom tier and are not so sensitive to inundation due to availability of boat based connectivity during that period – all the village roads would be improved considering the Scenario B where instead of raising crest-level climate proofing

embankment protection would be provided by enhanced slope protection with some

additional measures adjacent to structures and the union road would be improved with Scenario B and C by assessing polder-protectivity and vulnerability potentials of specific road on a case by case basis. In case of full crest level rising with Scenario C, if widening of base width is not possible due to land acquisition problem, road improvement with Scenario B option would prevail.

ii. Roads would preferably be BC, RCC and Block roads. These roads require less maintenance

and are more durable than brick based roads. RCC and Block roads are more climate resilient as they withstand better flooding and inundation with salt or brackish water. Earthen roads may be replaced by a paved road if justified.

iii. Climate resilience design may also require adding culverts in the road infrastructure to cope with higher extreme discharge volumes than previously foreseen. In addition water control gates may be added at the culverts for improved water control. This will be studied by the proposed hydrologists.

III.3 Modification of design and construction

18. The following small but important recommendations should be considered during design,

construction and management of markets, as gathered from visits to MIDPCR markets:

i. To reduce random cracks at the interface between brick wall and floor slab, the slab should be extended up to the plinth edge

ii. To provide better access to tin shed a step and ramp should be provided

iii. Raised level of shed: to provide better ventilation, height of tin shed should be raised by at least 600mm.

iv. To strengthen tin shed and thereby to minimize its blown away potential particularly during the storm, extra flat bar bracings should be provided on the roof-top along each row of nut-bolt connecting interface.

Page 96: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

5

v. To give a better look at the fish shed, instead of providing plain plaster wall, a pointed

brick wall should be used

vi. For large market instead of providing 1.5mx1.5m dustbin (garbage place), a 3mx1.75m should be provided

vii. To minimize heat absorption and radiation related problems a neat finishing for open shed should be avoided

viii. To provide more shops for women, smaller sized shop (like kiosk – 2.4mx2.1m) with tin

shed – semi-pacca (to be consistent with other structures) should be considered (women shops are small capital based businesses like tea stall/tailoring/readymade garment/stationary, etc.)

ix. To increase privacy the entrances of gents & ladies toilet should be placed in opposite direction

x. To increase riding quality, blocks of CC block-road should be laid lengthwise aligning with

travel direction

xi. Put a small information plate in each market

xii. For better operation and maintenance of the market and thereby to extend the lifetime of all structures, MMC should be given a checklist regarding all important daily and periodic maintenance activities (when to whitewash walls, painting of truss, clean roof, etc.)

IV. Component 1 – Improved Road Connectivity

19. The following section should be read as complementary to the project design report and

Working Paper (WP) No. 5 and WP 6.

IV.1 IFAD funded Activities under Component-1

20. See Annex 7, 7A and 7B of the Project Design report for detail activities under this component. Four activities are planned:

a) Construction of union (Scenario B and Scenario C) and village roads (Scenario B) (BC, RCC, or block road) as per target;

b) Road-side tree plantation, and

c) Formation and training of LCS groups, if block road is built in an Upazila. The LCS training

will be for block road construction.

d) Purchase of equipment and test instruments (see procurement policies)

Feeder roads

21. Roads include union and village roads that are served (or service areas) by markets. From field surveys it would appear that the number of feeder roads fall mostly in the range of 3-10,

these are roads serving a particular market. On average about 5 feeder roads provide the access to markets for the service areas. The status of the roads varies from poor – moderate – good. The types of roads are BC, RCC, CC, HBB, BFS, Block roads, Earthen Roads. Accordingly the distance over which road rehabilitation/construction is needed also varies per service area of the market place. The project will not construct new roads.

22. In case road rehabilitation is required than roads will be built as BC, RCC or Block roads. This is the preference based on long-time experience in the concerned Upazilas. Brick based

roads, HBB or BFS, would be gradually phased out. The local population often favours BC roads, followed by RCC roads.

23. In case access is difficult or impossible for rollers than BC roads are no option. The same is true when inundation with salty or brackish water occurs. In these cases the preferred road is the RCC road.

Overview of road types

24. Theoretical overview of possible road types connecting one administrative level with the same

or a lower level, those that actually occur, and the road types envisaged to be rehabilitated or built under CCRIP. It concerns roads that are normally within LGED‘s mandate.

Page 97: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

6

Project roads

25. The project will limit its intervention in the rural road infrastructure to two levels: Union Roads and Village Roads. The road types for these two levels will be mainly BC, RCC, and Block Roads. What type of road will be built depends on the economic data (villages‘ importance and location in the service area of the particular market) and the relative cost. In addition, accessibility for rollers may prohibit the use of BC roads at both levels and salt water inundation may make RCC the only feasible option.

26. The following five (5) combinations are possible:

Administrative level Union Width, in m Village Width, in m

Road Type

BC 3.00 BC 2.55

RCC 3.00 RCC 2.40

Block road - Block road 2.45

27. At the Union level no Block roads and RCC roads will be built. But village roads could be BC,

RCC, or Block Road

Structural Designs

28. The drawings are given in Annex 8A for relevant road types that will be used under CCRIP. In case occasionally a different road is needed, then the designs are available in LGED and these

were found adequate. The structural design of ghat is given in Annex 9B. Based on these designs BOQs were made and costs calculated as given in Annex 8B and Annex 8C.

Road inventory per market place

29. After the identification of the market place that will be reconstructed as part of Market Development, the service area is determined based on maps. The road engineers do a survey of the status of the roads for the service area and measure length of roads that need construction or rehabilitation based on field surveys, maps and interviews with the village

populations. Maps used would be mostly of two scales: location map (within polder) about 1:20000 and for the detailed field survey about 1:5000 (or 1:2000 as needed).

Observations on feeder roads and choice of roads

30. The number of access or feeder roads that connect a market with its service area varied over CCRIP‘s proposed intervention area and ranges mostly from 3-10; the number of villages served by these roads varied from about 5-15. The length of roads that need rehabilitation

varied from mostly 3-15 km. A precise assessment will take place in the period July-October 2012.

31. Existing feeder roads are of the following type: BC (bituminous), HBB (herring bone brick), BFS (brick flat soling), CC (concrete), Block roads (concrete blocks), Earthen roads). Invariably the preference of the local communities for the rehabilitation of existing roads, when needed, goes to BC and RCC roads. Rehabilitation and/or upgrading of roads will be assessed later. A justifiable investment will be proposed that relates the importance of the

road as for trade volumes transported, traffic density, traffic categories, etc. with the potential benefit for the villages depending on the road for their communication, selling/buying goods and other services.

32. Other factors also determine the eventual choice for the road type and relate to local conditions. For instance, small earthen roads leading to more remote villages may not allow

the passage of heavy equipment as rollers and this excludes BC roads. For areas frequently flooded and/or where salt or brackish water is often inundating roads, BC is excluded and RCC

or Block roads may be a better solution.

33. The preference of LGED is to gradually phase out brick based roads (HBB and BFS). The reason is that these roads are subject to vandalism and that they would deteriorate rather fast. These factors will also be taken into account when deciding which road type is selected. In principle road building (rehabilitation) under CCRIP will be limited to BC, RCC, Block roads; however, back roads connecting smaller communities with more major roads (Union roads,

RCC-village roads) may need a cheaper solution and occasionally BFS or HBB may be the choice.

Page 98: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

7

34. In general, the preference is for RCC roads because of lack of accessibility for rollers, and

problems associated with boat based transport and lack of proper landing facilities. Moreover, maintenance work would also be difficult later on due to unavailability of rollers.

Roads requiring rehabilitation

35. The impression from field visits differed as to the distances over which roads need rehabilitation since the sample differed, visiting three different areas.

36. On average there would be about 5 feeder roads leading to a market connecting 5-15 villages

(service area around market).

Boat landing places or ghats and bridges

37. The hydrologist advises the road engineers on the construction of ghats and bridges.

38. The engineers prepare designs, BOQs, and so on.

Hydrology

39. Climate resilient design requires a hydrological assessment to verify if past design criteria are

adequate for future circumstances. It is possible that e.g. more drainage capacity (more

culverts) is required to evacuate faster flood waters. An allowance of about 10% is made on top of the customary drainage capacity (combined width of culvert openings or cross—drainage capacity). This is a climate resilient design feature. Hydrological studies should conclude on eventual designs and probably more water control gates may be required; this has been allowed for in the budget (about 50 gates). As for the ghats, a hydrological evaluation of the concerned river section should conclude on the stability of the river section

and the location of the ghat.

Hydrology input

40. Besides the road engineers, CCRIP should receive technical inputs from hydrologist(s) to complement the road infrastructure staff. They will reassess the width and location of culverts needed, the need to add or replace water control gates, the type of water control gate, the O&M of water control gates, location of boat landing places in view river stability, location of bridges, advise on dimensions of bridges, culverts and ghats whilst maintaining cross-sections

of river, khals, drains.

41. For the studies the hydrologist(s) make use of maps (from the GIS-section) and coordinates

with BWDB who are the custodian of the polder in which many of the project‘s intervention areas are located. The hydrologist interviews farmers as to their perceptions on water control and the possible impact the project may have on their farm holdings.

42. The future impact of climate change is verified for the concerned areas and proposals made as

to how to mitigate to some extent the effects; however, the project limits its mitigation effort to affordable interventions as e.g. adding culverts to add discharge capacity to evacuate extreme floods, design of bridges and ghats possibly adapted.

O&M of Water Control Gates

43. Operation of the water control gate will arranged for in a similar way as existing gates or a special arrangement may be put into place. In general LGED coordinates with BWDB on opening or closing of the gates; the actual operation may be arranged for by a WMG or left to

a trusted nearby farmer.

Preparation of tender documents, awarding contracts

44. A detailed BOQ is prepared and maps are attached indicating exact locations where roads are

to be constructed, and so on. A condition is that LCS is used as much as possible for the execution the work; moreover is detailed other inputs, e.g. by LGED as for rollers, surveyors, and so on. This is all prepared according to prevailing conditions and in the proper legal format. After receiving the bids the evaluation follows and the contract is awarded.

O&M of Transport Infrastructure - Roads & Ghats

45. Market Management Committees will primarily be responsible for road maintenance of market internal road network by the utilization of 25% share of lease money to be received from upazila out of market auction fees. Besides, as per commitment the periodic maintenance of village and union market access roads would be the responsibility of Union Parishad, and to some extend it would be the obligation of LEGD as the said infrastructure developer.

Page 99: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

8

Cost of road rehabilitation

46. The cost is given in Annex 8B and Annex 8C. the embankment is not included since the project will not built new roads, rather repair or upgrade existing roads. Costs include the standard allowance for drainage structures (culverts) of 7.5 m / km (Village roads) or 10 m /km (Union roads). In consideration of natural flow obstruction potential, in general more structures should be provided if the road is aligned in the E-W direction as compared to the road that is oriented along the N-W direction. Standard approach is also to include one gate /

km. Anticipating the outcome of proposed hydrological assessments to be made for each sub-project, one additional water control gate has been budgeted for per km for the CCRIP project.

IV.2 Road Side Tree Plantation

47. Trees will be planted on both sides of roads where trees are not already planted. This procedure will be same as practiced under MIDPCR. The budget for tree plantation includes

cost of saplings and payments to LCS members (poor women) for a period of two years to protect the trees. Besides, as a climate adaptation measure, grass turfing and shrub would be used on embankment slope above palisading.

IV.3 LCS for Block Road construction

48. Block roads will be constructed by LCS members. One group of 25 poor women will be contracted for one km roads. They will be given training for three days on a) social issues, and b) block construction and road construction. The training will conducted by Upazila

engineer and Upazila Sub-assistant engineer as per module developed by MIDPCR.

V. Component 2 – Improved Market Services

V.1 Activities under the component

49. See Annex 7A and 7B for actual plan and project targets. The following activities are planned under this component:

a) Construction of Special Markets by contractors;

b) Construction of large market by LCS groups;

c) Construction of small markets by LCS groups; d) Construction of collection points e) Construction of women sections; f) Construction of ghats; g) Formation and training of LCS; and

h) Formation and training of MMcs

50. As for the market development component the physical aspects are mentioned here.

51. Types of markets: a) Type I: Special market, b) Type II: Medium market, c) Type III: Small markets and d) Community collection points (CCPs).

52. Typical facilities: The typical facilities include: open roofed building on pillars with a raised ground floor, fish-shed, multi-purpose shed, women‘s section, toilet block, open sales

platform, open V-drain, deep tubewell, solar panels, and garbage place. Typical designs are attached. For the different market types, the only variation is the size and number of facilities. Sometimes the Market Management Committee requested that an office is built for them but

this is not normally included.

53. CCPs are simple paved parking places where villagers can bring their goods to buyers that transport them further to markets. CCPs serve remote areas where fewer people live otherwise not connected with markets. A truck stand provides space for about 3 trucks. Boat

landing facilities may constitute part of a CCP or market place and this has been treated above.

54. Structural designs: All designs are similar to previously used designs (MIDPCR), except for modifications as enlarging the garbage place, entrance to toilet block for women and men now placed opposite each other, drains evacuates waste water first in a stilling pit (treatment) and thereafter onto public water bodies, solar panels, raised ground floor. The structural designs

Page 100: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

9

for each item, e.g. different types of sheds are given in Annex 9A. The unit cost for markets

and details BOQs and costs are given in Annex 8C and Annex 9C.

55. O&M Market Development (physical): The Market Management Committee (MMC) is in charge of the O&M of the facilities. The tasks include a weekly inspection, especially after a haat day. In case repairs are necessary the MMC prepares a maintenance report with estimated costs. Through the contribution of the leaseholder and others (shop owners) the money should be secured to pay for the maintenance. This will mostly concern small amounts and a dedicated

craftsman should be identified and the works to be done agreed with. MMC further supervises the repair. Routine maintenance as e.g. painting, plasterwork, and so on, will also be handled by the MMC in a similar way.

Physical Infrastructure

Type I: Special markets 56. Special markets are wholesale markets that serve large areas for wholesale but also serve

directly end-consumers. There are few of them and they are functioning facilities; however, often deferred maintenance requires that facilities are rehabilitated. The facilities they include are the same as for large markets and this is discussed below. The major difference is that

wholesale markets often need a boat landing platform (ghat) and that one extra fish shed is provided. In addition the V-drain‘s effluent requires some simple form of waste water treatment (bar screen and one stilling pit as primary treatment); also protective gloves for the cleaners/sweepers are foreseen); this is further investigated, the cost is estimated as a lump

sum. A women‘s section may be added, see below.

Type II: Medium markets 57. The majority of markets would be large markets and have typically more than 100 shops. They

include the following facilities:

− multi-purpose shed to sell agricultural produce or other items. − fish-shed exclusively for selling fish, prawns, shrimp. − a toilet block located at a small distance from the market for both men and women; a

new feature is that the entrance for men and women will now be built opposite to each other at opposite site of the block providing more privacy.

− deep tubewell, built at the market place or a near as possible to provide for drinking water and for water to clean the concrete floor and sheds and the open sales platform.

− open sales platform: this is a paved area where sellers and buyers do business and

where there is no need for a building with a roof.

− internal road: separating sales areas. − V-drain (or sometimes U-drain): the market facilities are cleaned by sweepers and

they flush the waste towards the open drain that evacuates the effluent into a khal, pond, or onto land. A new feature is that prior to discharging the effluent, the waste water passes through a bar screen (filter) where solid waste (plastic bags, wood, branches, etc.) accumulates. This is from time to time removed. Depending on the size of the market a simple form of primary treatment may be added.

− Garbage pit: garbage is deposited in the pit and sometimes burned or destroyed using bleaching powder. A new feature is that it is now somewhat larger than before.

− Paved area: to serve as parking facility for loading and offloading goods from trucks. − Raising the floor level of covered market facilities. This is a new feature and was

requested by MMCs since this separates more clearly the open sales platform and covered areas to avoid spill over of goods and enhances cleanliness. It involves additional earth work.

Type III: Small markets

58. Small markets have typically 5-50 shops. The difference between a large market and a small market is that in the latter case often no special fish shed is needed and that the internal road and V-drain are shorter.

Community Collection Points (CCPs) 59. CCPs are located in more remote areas at road sides or near river banks and provide farmers

with an opportunity to take their goods to buyers using e.g. trucks for further transport. They consist basically of a paved platform and truck stand (paved parking area for three trucks). Occasionally a ghat may be constructed as well when located near a river, khal or canal.

Women’s market section 60. The women‘s market section is a special facility to provide for women more privacy especially

in case of widows, destitute, other independent women. It may host 8-10 shops. The need for

Page 101: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

10

a women‘s market section may not be limited to special markets but also some large markets

may need this facility. Due to security reason, preferably women section should be provided at the market‘s front area.

V.2. DRAINAGE OF MARKET FACILITIES AND POSSIBLE TREATMENT OF WASTE WATER

Specific drainage design per market type

61. Per market type the drainage and possible treatment of waste water are elaborated below. 62. Community collection points: The drainage of the small paved parking places does not

require special facilities as the rainwater will flow from this paved area to adjacent areas (land, ditches); there is no hazardous waste.

63. Small Markets: Small Markets are drained by a small drain (u- or v-shaped) often of concrete and surrounding the market facility. In present designs the drainage effluent flows often to

(agricultural) land or is directly discharged onto open water bodies (canals, khals, ponds). The volume of effluent is minor during dry periods but is larger when it rains.

64. Proposed is to investigate new designs that may include a small flow field where sediment and waste can deposit and from where the effluent can be directly discharged onto public water bodies. At the bottom end of the drain a small flow field can be constructed, e.g. 5*5 m2. This

flow field may be a small depression or basin of about 10 cm below the adjacent ground surface. In case of no or low rainfall then the flushing water of the Small Market places will settle in the small basin. Later a cleaner/sweeper can collect some solid waste and bring it to the garbage pit for destruction.

65. At the lower end of the small basin a screen may be placed to filter out some of the solid waste as plastic bags, paper, tree branches, etc. After passing through the flow field the effluent discharges on the adjacent land and from there it discharges onto canals, khals, and

ponds in case of higher discharge volumes during rainfall.

66. The flow field may be fenced by a low vegetative fence to clearly separate this from the surrounding area and to avoid easy access by children and animals.

67. Medium markets: For medium markets the new designs are similar as for the Small Markets

albeit of a larger size. The basin size may be 10*10 m2. Other features are similar.

68. In case of some Very Large Markets, it may be considered to include a small sedimentation basin before the waste water enters into a flow field. This is very much a site-specific design

and should be assessed in relation to the effluent volumes (in dry periods and during the monsoon period) and the amount and type of waste.

69. Special Markets: Special Markets are few in number. They are always of the size of Very Large Markets and often function as wholesale markets. No standard designs are used to establish or rehabilitate the market facilities. Similarly the design of the drainage system and the possible treatment of waste water are dimensioned as per the requirements for the specific Special Market. The volumes of the effluent are larger; therefore the sedimentation tank and

flow field are larger as well.

70. Appropriate designs for Special Markets may go beyond the above mentioned sedimentation tank and fenced flow field. In addition to possible treatment of the waste water from the Special Market, this may be combined with treatment of waste water from the village or town

where the Special Market is located. For instance a Chinese Dome digester may be opportune to construct. There are millions of these treatment facilities operating in China. In case the construction of a Chinese dome would be considered than this requires the involvement of a

relevant Bangladesh university engaging their relevant department and research staff; this activity would be an R&D component under the CCRIP project (See Annex ...)

71. More information can be found at websites as: http://www.sswm.info/category/implementation-tools/wastewater-treatment/hardware/semi-centralised-wastewater-treatments/h

http://en.wikipedia.org/wiki/Septic_tank

Page 102: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

11

http://watsanexp.ning.com/dewatstechnologies/biogas-system/chinese-dome-digester Hygienic aspects 72. At all market facilities the cleaners or sweepers, who are flushing the markets with hoses often

using water from a tube well, need to be provided with protective clothing, gloves, hose, rake, broom, wheelbarrow. This will prevent them from touching directly the waste, for instance when taking it to the garbage places. This will also have an educational impact on the visitors of the market places as they watch how the cleaners are handling waste water and will induce them to handle more careful waste themselves.

Other issues

73. Land availability: In virtual all cases sufficient khas land is available to construct the market infrastructure. If not, voluntary donations of land complete the space needed for the market. The project will not engage in land acquisition. In case of donated low land, raising by dredge

fill may be considered if land development cost is within the allocated budget.

74. Slaughter places: At some markets a simple facility exists for slaughtering animals as cows, goats. These facilities fall under the responsibility of the Ministry of Local Government,

respectively District, Upazila and Union Parishad levels. Monitoring is by the Department of Livestock Services. CCRIP will not include slaughter facilities in its project and will not engage in upgrading slaughtering facilities.

V.3 Formation of LCS and training 75. One LCS group of 25 poor women and men will formed for construction of one market. They

will be trained for a period of three days on a) social issues, b) construction of markets and

management of contracts. The training will be provided by LCS officer and Upazila sub-assistant engineer. CCRIP will follow LCS manual prepared under MIDPCR project. A revised version has been annexed with PAM.

V.4 Formation of MMC and training 76. Each market has a MMC. The project will sign an agreement with MMC. Members of MMCs will

be trained on market management and supervision of LCS works and future repair and

maintenance. CCRIP will follow the same procedure regarding as developed and practiced in MIDPCR project.

VI. Project Management

VI.1 Staffing, Management and Supervision

77. Staffing: The Project Management Unit (PMO) charged to implement CCRIP is part of the LGED. As described in the main report a TA team will assist the design and implementation of the project. IFAD has included additional staff members (See Appendix 1 for TOR) for

strengthening supervision and monitoring, use of GIS and application of hydrological inputs.

Supervision of implementation of contracts

78. Independent supervision is of crucial importance to safeguard the quality of the work and a small additional budget has been proposed to ascertain that the staff engaged in supervision is given the facilities they need to stay independent. Supervision engineers are appointed (by LGED) and provided all the facilities they need to check the performance of the contractors.

GIS

79. More than before the use of satellite imagery for maps and hydrological studies is recommended. Involving the GIS Unit of LGED is an efficient working method as the GIS Unit of LGED possesses the required software (ARCGIS), and to some extent satellite imaginary and digital maps. At the GIS Unit Maps are available from Landsat (2010), resolution 30 * 30 m. Scales used may be about 1 : 20000 (regional studies, polders) and more detailed scales like 1 : 5000 to fit the detailed surveys for the detailed assessment of rural infrastructure and

to prepare for tender documents. For the project‘s needs the available topographical details for the markets and the feeder roads are insufficient, moreover there is sometimes a mismatch for instance between the location of a particular market as given on the maps and the real location. To prepare better maps a surveyor needs to assess the coordinates in the field (using

Page 103: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

12

a GPS) and together with pictures (Google Earth) and Upazila maps, a map must be prepared

that show all important locations (villages, markets, roads, schools, and so on). At present a reconnaissance survey of the roads and markets exists but this needs to be updated to be done by the surveyors and Upazila level engineers. Thereafter, the BOQs can be prepared with maps attached to clearly indicate e.g. which road sections need to be rehabilitated. The maps also serve for impact assessment studies as villages and their population are indicated, distances to reach markets presented, and so on.

80. A printer is available and can be used to make prints to be used for field visits and for office work. Sufficient budget must be allocated to make use of GIS (prints, electronic copies, acquiring GIS data, and so on, estimated at about USD 10000.)

Geodetical instruments required

81. In addition to available geodetical instruments some additional instruments are required: Total stations (3), ranging rods, staffs, measuring tapes, chains, Handheld GPS (32); to be specified

later, estimated as lump sum (USD 80000).

VI.2 Innovation and piloting

82. As mentioned in the PDR, IFAD has mobilized one million USD grants for various activities. Three innovation or action research/pilot activities with a total resource of USD 150,000 will be implemented. All three pilots will be conducted by reputed Bangladeshi academic institution(s)

to be identified during implementation. Three brief concept notes are described below, which will be further elaborated during implementation:

A. Investigation of Prospects for Sustainable Waste Management of Markets

Present situation

83. A typical market in the rural areas covered by the CCRIP project consists of a fish-shed, multi-purpose shed, toilet block, women‘s section, open sales platform, internal road and open drains, and sometimes a slaughter place. Also livestock is brought to some markets for sale

(killas). On normal days, markets may receive 200-1000 visitors, and on haat days, this may reach 5000-10000 visitors depending on the area served by the market. In addition, markets are often surrounded by shops and restaurants. All these facilities produce waste, partly

organic and partly non-organic.

84. Waste is now often cleaned from markets and surrounding areas by sweepers using brooms and/or flushed towards the drain (U- or V-shaped) and then conveyed to flow fields, khals or ponds. Solid waste is sometimes put in garbage pits or dumped on open spaces.

85. At present, the waste management practices are not hygienic, pollute the environment and facilitate transmitting diseases among humans.

Justification and Objectives

86. As a result of the project intervention, it is expected that markets will attract more buyers and sellers and thus produce more waste than before. To enhance more hygienic conditions, better waste collection and treatment is needed. Therefore, it is recommended to test opportunities

for anaerobic waste treatment (bio-digester) at two different locations, namely for a very large market and for a medium sized market. Apart from improving the cleanliness and hygienic conditions of the markets by proper removal of waste, it should be investigated if the products of the waste treatment (methane and digested slurry) are beneficial and can be sold to

potential consumers. Thus the proposed tests have two objectives:

i. Improving aesthetic and hygienic conditions of markets through environmentally safe

removal of waste, and

ii. Assessing the commercial value of methane and digested slurry derived from biodigester.

Page 104: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

13

Description of requirements and of research activities

87. Major issues are :

a. Inventory by researchers of factors that will determine the choice of options for a bio-

digester based facilities: size of market, estimated production of biodegradable organic waste, potential location of bio-digester facility, potential consumers of products of the bio-digester, and so on;

b. Inventory of bio-based digesting facilities, e.g. Chinese dome digester by researchers, and design of bio-digester facilities by researchers with assistance by consultants, procurement of gas analyzer by researchers;

c. Design of garbage facilities by researchers;

d. Engaging the MMC: awareness building for the justification of the test, the role of the MMC shall be discussed and agreed on, employing a cleaner (provide with protective clothing, gloves, mask, broom, rake, wheelbarrow, bleaching powder, hose, etc.) to work under the supervision of the MMC, data recording and processing; tasks to be carried out by the

researchers;

e. Construction of bio-digester facilities for treating biodegradable organic waste, and of garbage facility for non-biodegradable organic waste by LGED;

f. Procedures for management of the bio-digester facility, collection and storage of waste, draining of the markets and separating the solid waste from the effluent, sell of the products of the bio-digester, ultimate disposal of non-bio-degradable solid waste, and so on;

g. Reporting of activities and research test results;

h. Conclusions to be drawn by the engaged researchers on the potential of application of the

test results to other locations and the conditions needed for a sustainable operation of treatment for biodegradable organic waste and non-biodegradable organic waste.

Topical information

LGED Bio-gas project

http://watsanexp.ning.com/dewatstechnologies/biogas-system/chinese-dome-digester

http://en.wikipedia.org/wiki/Septic_tank http://en.wikipedia.org/wiki/Septic_drain_field

B. Investigation of Climate Resilient Slope Protection of Embankments: Prospects of biotechnology for environmental friendly slope protection

Present situation

88. The traditional practice to protect embankments against erosion in Bangladesh is to use cement concrete (CC) blocks, sand bags, stone or wood revetments, geotextile, geo-bags and tree plantation. Usually, cement concrete (CC) blocks are used where storm surge is high, sand bags or wood revetments are used where flow of water is moderately high. Protection of

embankment by plantation is another practice, but it is not effective during cyclone and flood because of overturning or uprooting of plants.

Background, justification and objectives

Background

89. Embankment stability can be augmented by using bioengineering techniques which techniques may be an alternative option for embankment protection.

Bio-engineering techniques are being increasingly favored to control soil erosion in general

and for slope protection in particular.

Page 105: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

14

The technique envisages use of appropriate vegetation, single plants or sown, with

minimum artificial human intervention resulting in economical and ecological benefits. Jute geotextile (JGT) is a suitable technique given its special features.

90. Plantation of long rooted fast growing vegetation system along the slope of embankments and

river banks may be a solution to solving the problem of erosion. The vegetation cover not only serves the purpose of slope protection but also contributes to the green technology and

provides for green jobs. Thereby It could reduce pollution and as well as preventing erosion of embankments and dykes.

91. Selected vegetation types must be suitable to environmental parameters as hydrology, soil, flood tolerance that influence and regulate the growth and propagation of the vegetation. Different plant species relate to different habitats given their peculiar characteristics. For the proposed test they should be tolerant to the prevailing aquatic and terrestrial conditions in

order to guarantee their survival and propagation. Suitable plant species can be found in the coastal belt. The aquatic environment of coastal area is very unique and adaptive species have developed in the course of time. Plants in the coastal belt survive in different and often very dynamic conditions that vary depending on the distance from the sea or floodplains. Also

interaction with fish environments occurs; environments may be biotic or a-biotic.

92. As the vegetation root system needs often several months to grow, during that time, the soil erosion can be protected or minimized by using of geo-jutes. If geo-jute is laid over the

exposed surface it will prevent soil erosion and water will flow off the side slope without causing erosion. As the geo-jute will degrade over time, vegetation roots will grow and resume the function of geo-jutes. Geo-jute prevents the displacement of soil particles and eventually provides mulch to enhance vegetation growth.

93. Suitable vegetation must be selected that can survive even if submerged for several weeks; in addition plants should be salt tolerant as water inundating the land may be saline depending on the location. To identify and confirm that plant species are suitable, field trials are

necessary.

94. In view of climate change more inundation of embankments may occur. Moreover increased rainfall and rainfall intensity may accelerate erosion of embankments. Adequate and cost effective side slope protection is required for future circumstances.

Justification

95. The present methods used to provide for slope protection have disadvantages as they are

relatively expensive and are often not sustainable as they break down or whither in the course of time and are subject to vandalism. Alternative options are sought and need investigation to assess their suitability.

Objective

96. The objective of the proposed test is to identify suitable plant species that provide for an adequate sustainable and environmentally safe and economically feasible anti-erosion cover of embankments and dykes adapted to local conditions of flooding and saline water, thereby

making road embankments more climatic resilient.

Possible Outcomes

97. LGED as well as BWDB would be able to implement other road and flood embankment infrastructures with appropriate climate resilient slope protection measures.

Description of requirements and of research activities

98. Major issues are :

Inventory and selection by scientists of plant species that may be suitable for the most occurring conditions as prevalent in the CCRIP project area;

Identification of some sectors of embankments and dykes that are suitable for testing plant species;

Engaging the WMO (Water Management Organizations): -awareness building of the justification of the test, -the role of the WMO discussed and agreed on, -engaging a WMO member to work under the supervision of the WMO, -data recording and processing; tasks to be prepared by involved researchers;

Page 106: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

15

Acquiring cover material (geo-textile) and plant species and transport to sites.

Preparation of sites by LGED;

Reporting of activities and research test results;

Conclusions to be drawn by the engaged researchers on the potential of amplifying the results of the test to other locations and the conditions needed for use of specific plant species for slope protection.

C. Introduction of quality tests protocols for road and market rehabilitation

Present situation

99. The customary rules and regulations that apply need a reassessment as well as improvement with respect to supervision and use of different quality control (destructive and non-destructive) testing instruments. Rehabilitation of roads includes widening and elevating existing roads, and construction of small bridge and culverts along the roads. Traditional construction methods do not focus on proper selection of soil and proper methodology for

widening and elevating existing roads. As a result, within a very short time, roads loose

serviceability. Construction of bridges and culverts need Reinforced Cement Concrete (RCC). Market rehabilitation also needs RCC foundation and columns. Usually main focus for RCC works is given on strength of concrete. However, to make RCC resilient to climate change, durability should be a main focus for RCC in coastal regions where intrusion of saline water into porous concrete corrodes reinforcement resulting in increased volume of reinforcement. Thus RCC may disintegrate. During high tides and floods approach road of bridges and

culverts may wash away. Adoption of proper methodology is needed for approach roads.

Improvement of existing protocols

Background

100. Sea level rise caused by global warming may locally cause inundation, drainage congestion and salinity intrusion especially when coinciding with storm surge inundation. Sea level rise is a growing threat for the coastal regions of Bangladesh. Bangladesh is one of the mostly densely populated countries of the world where 28% of the population are living in the

coastal area. The trend in the number and severity of tropical cyclones hitting the Bangladesh coast is increasing. Higher population density increases vulnerability to climate

change especially water related disasters in Bangladesh. Most of the casualties from cyclones in Bangladesh, as in other parts of the world, are caused by storm surges and because of climate change the height of storm surges may increase leading to more intensive coastal flooding.

101. To make the coastal region climate resilient, most of the rural roads and markets need rehabilitation. Putting soils on existing earthen crest and vegetated slope is usually done which is eroded during the monsoon. Therefore, sustainable methodology should be developed in this regards. Before construction of flexible or rigid pavement, locally available soil is placed on top of road and compacted. Performance of the road depends on type of soil, moisture content during compaction, compaction characteristics of soil, relative compaction achieved in field, etc. All factors are equally important for durability of roads in

coastal region. For example fat clay or lean clay may become soft during monsoon or flooding. At that time, even light traffic could damage the serviceability of road. Therefore a comprehensive quality control program should be developed for such a situation where construction works are carried out by unskilled labors. Portable, easy and simple instruments should be developed for quality control of compaction in the field. Trainings are needed for

LGED engineers for identification of soil as per USCS and AASHTO.

102. Construction of bridges and culverts is also a part of road rehabilitation which involves

quality of control and specification of RCC. Market rehabilitation also needs RCC in foundation and column upon which tin shade is built. Many cyclone shelters were built in coastal areas of Bangladesh after deadliest cyclone of 1991 which took thousands of lives. However most of cyclone shelters are now in a dilapidated condition due to poor maintenance and poor quality of concrete during construction. Bridges, culverts and markets would not be durable for the same reason. Mean compressive strength of concrete of these

structures is as low as 21 MPa which is good enough from strength consideration. However, concrete which is directly exposed to saline water and superstructure is exposed to air where humidity and salinity is high all year round. Therefore durability of concrete must be

Page 107: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

16

considered during design and construction of any infrastructure in coastal regions. To

achieve mean compressive strength of 21 MPa, ACI (American Concrete Institute) recommended a water-cement ratio of concrete of 0.68. That means concrete with water-cement ration 0.68 can produce sufficiently strong concrete but not durable. That is why from durability consideration ACI recommended maximum permissible water-cement ratio to be 0.45. High water cement ratio leads to porous concrete which allows ingress of sea water containing sulfate, chloride and other salts to concrete. Corrosion of reinforcement takes

place after ingress of sea water into concrete. Most of the reactions lead to products volume more than reactant volume. Thus concrete disintegrates due to expansion, cracks appear and finally spalling of concrete occurs. Use of brick chips in concrete may be another reason of high permeability of concrete. Use of saline water as mixing water of concrete also induces corrosion of reinforcement. Other reasons may be (1) Use of improper materials (aggregates), (2) Use of old stored cement, (3) Improper concrete mix design, (4) Poor

construction control, (5) Insufficient cover to reinforcement, (6) High permeable concrete due to excess use of water (7) Poor compaction of concrete, (8) Distortion or displacement of forms, (9) Disturbances during placement leading to uneven and inadequate cover, (10) Inadequate curing and (11) Lack of proper supervision.

103. During high tides and floods, approach road of bridges and culverts may be washed away. Adoption of proper methodology is needed for approach roads.

104. Therefore, it is necessary to prepare a guideline of RCC construction in coastal areas so that

low cost, durable concrete can be produced by local people. In addition to ACI method of mix design, it is necessary to investigate new mix proportions for durable RCC using local sand of FM less than 1.5. Use of fly ash and admixture should be investigated to make durable, impermeable and self compacting concrete. Quality control system should be formulated for local people so that they can produce durable concrete.

Justification

105. The durability issue of conventional method of construction and maintenance needs to be

reassessed. Maintenance costs of rural roads and markets would be minimized by adopting proper methodology of construction of roads which would be the outcome of this research. To produce durable RCC, cost of construction may increase by certain percentages. However, elimination of maintenance cost would compensate the initial higher cost of construction.

106. he proposed R & D has the following objectives:

i. To prepare guidelines for sustainable rehabilitation of roads in coastal regions.

ii. To develop portable equipment for quality control of field compaction iii. To prepare guidelines for making durable RCC needed in market rehabilitation and

construction of bridges and culverts. iv. To prepare proper guidelines for sustainable construction of approach roads on two sides

of bridges.

Description of requirements and of research activities

107. Major issues are :

Provide training to LGED engineers on identification of soil as per USCS and AASHTO, material tests and field tests for quality control using destructive and non-destructive modern equipment particularly which would be procured under CCRIP project.

Collection of soil samples of roads and borrow pits from coastal regions.

Identification of soil samples as per USCS and AASHTO.

Determination of compaction characteristics and soaked CBR of collected samples.

Development of portable device to measure relative compaction of soil.

Development of correlation curves for the portable device to apply in field.

Small scale model test on base widening of road embankment and formulation of proper methodology for application in field.

Series of trial mixes using local sand, Sylhet sand, stone chips, brick chips and w/c ratio as

parameter to find out durable cost effective mix proportion which would be implemented in the field.

Page 108: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

17

Water penetration test of trial concrete cylinders to compare permeability of concrete.

Preparation of guidelines for sustainable rehabilitation of roads in coastal regions.

Preparation of guidelines for making durable RCC.

Preparation of proper guidelines for sustainable construction of approach roads on two sides of bridges.

Reporting of activities and research.

Conclusions drawn by the engaged researchers on climate resilient road construction and

market rehabilitation.

Page 109: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

18

Appendix 1 of Annex 5

A. Impact of climate change as relevant for CCRIP – IFAD components

The context of the mission, the main emphasis of the project and the time available did not permit to provide for an elaborate and detailed analysis of the impact of global warming for the

project area. Only major observations are given and the consequences for the project analyzed.

1. Brief overview of climate change phenomena

There are several effects of global warming that impact on climate. The impact on climate

further impacts on phenomena as sea levels, rainfall intensity and volume, storms (cyclones), temperature, river water levels and discharges, salinity, and so on. Detailed and scientific information is to be found a. o. in the 4th IPCC report of the UN.

According to information obtained (WB, BWDB, others) the consequences for the CCRIP project

area in Bangladesh can be summarized as follows:

Sea level rise: two possible scenarios resulted from discussions and were found in literature:

Sea level rise would be 7 mm/year over the next 20 years. Given a land subsidence of

about 3 mm/year, the combined result is a sea level rise of 1 cm / year or 20 cm over 20 years.

Sea level rise would amount to 0.50 m for the year 2050.

Rainfall

There would be an increase in rainfall and this is projected for the year 2050 to be as follows: 26% for the months of March, April and May and 13% for the months of June, July and August. Given an annual rainfall ranging from some 1700 – 2000 mm in the project

area, this means a significant extra amount of rainfall.

Cyclones

The frequency of cyclones and their intensity would increase, and consequently rainfall

increases (see above).

Temperature

There would be an increase in temperature; however, the magnitude is not precisely

known.

River water levels and discharges

There would be an impact on river discharge that may increase as a result of an increase in temperature in the catchments with additional snowmelt but a precise quantification could not be obtained. In addition more abstractions from the rivers may reduce the volume somewhat that reaches the delta and the coastal belt in Bangladesh.

Salinity

More salinity intrusion may occur as drainage by the river systems is somewhat impeded temporarily and the salinity propagates to more upstream parts in the system. Also flooding with slightly more saline water may occur temporarily.

2. Relevance for CCRIP – IAFD components

Sea level rise

Location and impact

Sea level rise at the river mouth is supposed to be about 20 cm over the next 20

years. This will impede the drainage by rivers somewhat and results in a back water curve. Given a river slope or rather a fall in river water levels of average a few cm/km, the impact of the sea level rise is only felt over a limited distance inland. The sea level rise comes on top of the tidal amplitude (e.g. 3 m) and propagates upstream in the river and affluent systems. It is expected that no more noticeable effect is felt for instance 15-20 km from the shores.

Page 110: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

19

The possible impact on areas depends on their location:

areas protected by embankments (polders) or sea dykes will experience little or no impact

areas unprotected by embankments (chars) will witness the impact, the severity of which depends on the distance from the river mouth or shore.

Drainage capacity

Drainage from polders is based on tidal sluice gates that drain whenever the outside

(river) water level is lower than the inside (polder) water level. In case drainage would be significantly impeded than the solution is to add drainage capacity by adding sluice gates or vents.

Increased rainfall

Impact on polders

To drain the extra rainfall resulting from climate change will require increasing the

drainage capacity. Inside the polder this could mean to add or enlarge the capacity of culverts allowing for the excess water to reach the drainage outlet or sluice gates faster. In addition the tidal sluice gates capacity may have to be enlarged. To avoid over-drainage and to retain water when needed, some water control gates may be constructed on the culverts to provide for better water control.

Impact on chars

As chars are lands without hardly any water control, the extra rainwater will be evacuated by the natural khals towards the sea. Unless the chars are empoldered, not much can be done to improve water control. In general the extra rainfall will result in higher water levels at the lower lying parts of the chars. In the lower parts higher water levels as compared to the present situation will occur temporarily. It is difficult to estimate this impact as also the sea level rise is felt mostly in the lower parts of the chars. An order of magnitude could be that water levels may rise 20-40 cm temporarily

during some days/weeks in the monsoon.

3. Consequences for design

Polders

As far as the components ―Markets development‖ and ―Communication infrastructure‖ are located within polders, the consequences or ―Climate Resilient Design‖ are as follows:

Roads:

add additional drainage capacity (culverts) to accommodate the efficient evacuation of extra rainfall

add water control gates to improve water control

However, no raise in crest levels of roads is required inside polders.

Increased rainfall may have a positive impact on salinity levels inside polders and possibly more saline water (if any) may be evacuated through the tidal sluice gates.

Markets:

Some markets located in the lower lying parts of the polders may need a slight rise in the floor level of e.g. 20-40 cm.

Chars

As far as the components ―Markets development‖ and ―Communication infrastructure‖ are located within chars, the consequences or ―Climate Resilient Design‖ are as follows:

Roads:

It is not possible to advise on a blanket approach of e.g. 20 cm rise in crest levels as this depends on the actual land levels and location. The ultimate recommendation as to the designs should be taken by the

Page 111: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

20

project‘s hydrologist after seeking advice from BWDB, local inhabitants and

based on the latest information of impact of climate change in the project areas. Moreover, it would not be realistic to here and there increase slightly a road section rehabilitated under the project.

As there is likeliness that roads may be submerged more frequently it is recommended that roads are surfaced with e.g. RCC that is less susceptible to damage from submergence and from submergence with

saline water; this is a ―Climate Resilient Design‖ feature.

Markets:

Some markets located in the lower lying parts of the chars may need a rise in the floor level of e.g. 20-60 cm; this is a ―Climate Resilient Design‖ feature.

Preference and sequence of implementation

There is a strong preference to give priority for market infrastructure and transportation infrastructure to be implemented in the polders first, as the polders

are protected against flooding by rivers and sea.

In case market infrastructure and transportation infrastructure is to be implemented in char land, than it is recommended to do this towards the end of the project since more knowledge on climate change effects will be available and it will be possible to prepare more accurate designs.

Apparently out of the 32 Upazila‘s only 4 harbour char land within their boundaries and delaying the project implementation in these four Upazila‘s will have virtually no impact on the project‘s achievements.

B. Additional Staffing related IFAD components and their TORs and staffing set-up in relation to the three operational levels and financiers

B.1 TOR Hydrologist

Background

The CCRIP project is to develop market facilities and the connecting rural infrastructure. The rural roads are almost all existing roads. According to the local government administrative set-up, distinguished are Regions, Districts, Upazilas, Union Parishads and Villages. The project‘s (IFAD part) transportation infrastructure component will rehabilitate/upgrade roads at two levels: Union

and Village roads to connect villages with market places and between markets. The roads traverse the area that is mostly part of a polder where sluice gates allow for some measure of water control. The polders are operated by BWDB. The roads infrastructure creates consequences for the water management of the polder, e.g. related to the obstruction of flow, impeded drainage, impact on storage, water management, storm water management (cyclones), and retention of water. Together with roads, bridges and culverts are constructed or rehabilitated. Culverts may be provided with water control gates.

Proposed are two Senior Hydrologists. One Senior Hydrologist is engaged through ADB funding

and the TOR is given in the concerned chapter of the CCRIP. Below is the TOR of the Senior Hydrologist engaged trough IFAD.

Senior Hydrologist

Duties

1. Primary responsibility for defining the hydrological factors to be considered in the detailed design of the roads and associated bridges/culverts structures for the finally selected subprojects;

2. Collect and analyze relevant hydrological data and in consultation with the road design and structures engineers, assess the requirement for additional cross-drainage capacity on

Page 112: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

21

project roads in order to maintain natural drainage under present and forecast climate

change conditions;

3. Establish technical design criteria as for the hydrological aspects for construction of roads, bridges, culverts and ghats, especially in respect of embankment orientation or possible obstruction of natural flow of runoff, site-specific designs, protection measures, cross drainage capacity;

4. Assessment of preferred locations for culverts, this may be at existing locations or

elsewhere;

5. Obtain the needed survey information from the GIS unit of LGED, Dhaka;

6. Prepare analysis of hydrological and meteorological data and verify findings with other stakeholders as BWDB; identify climate change effects in relation to the analysis and results from scientific studies by international and national specialized agencies;

7. Assess the impact of climate change for project areas and assist in designing climate

resilient infrastructure;

8. Determine the expected discharge for average and wet years and the consequences for flood control identifying command areas and using the customary catchment area-

discharge formulas and local experience;

9. Design of dimensions of culverts;

10. Advise design engineers on dimensions of bridges, ghats;

11. Verify that planned bridges, culverts, ghats do not narrow and alter the cross-sections of

rivers and khals;

12. Verify BOQ for culverts with cost estimate in view of recommended dimensions;

13. Determine if culverts need to be provided with a water control gate given climate resilient demands e.g. resulting from increased rainfall;

14. Select the type and dimensions of water control gate (e.g. sliding gate, automatic valves, flap gate, and so on);

15. To determine the sizes of the culvert and possible water control gate, a series of detailed

interviews with farmers affected by the culvert must be held;

16. Determine if water control gates may also serve for the purpose of water retention for part of the year (boro season);

17. Enhance the establishment of a water control gate beneficiary group;

18. Discuss with farmers if salinity is a problem for them and if the operation of the water control gate can help to reduce the problem;

19. With respect to bridges, assess where bridges may be built or rehabilitated and the consequences for water management, if any;

20. Establish contacts with the concerned staff of BWDB, ADB, DANIDA, WB, JICA, others to coordinate interventions and efforts;

21. Consult with the relevant Disaster Management Agencies at the administrative levels for information regarding the flood levels of cyclones for project areas and to design for additional culverts as necessary;

22. The Hydrologist will work in close collaboration with LGED engineers at HQ, and at District, Upazila and Union level and with respective administrations;

23. Design the operation and maintenance of water control gates with beneficiaries and local government officials and LGED staff;

24. Examine the surface water quality/quantity (ponds) and groundwater quality in the project

area and identify suitable sources for providing safe drinking water for growth centers/rural markets and cyclone shelters as well as for cement concreting works;

25. Advise on the location of tubewells (DTW) providing safe drinking water for villagers;

26. For the studies the Hydrologist makes use of maps (from LGED‘s GIS-section) and coordinate with BWDB who are the custodian of the polders in which many of the project‘s intervention areas are located;

27. The Hydrologist interviews farmers as to their perceptions on drainage and water control and the possible impact the project may have on their farm holdings;

28. The Hydrologist identifies if Water Management Organizations (WMOs) are engaged with the water management of areas of polders that area traversed by roads subject to

Page 113: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

22

rehabilitation by CCRIP; together with the WMG the water control is investigated and

concluded on possible addition of culverts with gates and on the operation of these.

29. The future impact of climate change is verified according to the latest insights and updated standard design criteria as applied by GOB‘s concerning agencies for the project‘s intervention areas, and proposals are made as to how to mitigate to a reasonable extent the impacts. However, the project limits its mitigation effort to affordable interventions as e.g. adding culverts to add discharge capacity to evacuate extreme floods, water control

gates, adapted designs of bridges and ghats.

30. The Hydrologist establish contacts with other projects and stakeholders intervening in the same areas as CCRIP, e.g. Blue Gold, and so on to collaborate on issues of mutual interest and in the interest of the project‘s target population.

31. The Hydrologist perform any other related work, as may be reasonably instructed by the Project Director LGED;

32. The Senior Hydrologist will work under the supervision of the Project Director, LGED, Dhaka.

Duty Station

The Senior Hydrologist will generally be stationed in the PMO, LGED HQ Dhaka, but will be expected to be periodically based in each of the RPOs, and to visit construction sites when

requested. The Senior Hydrologist will support the PD, two Deputy PDs, road structures design engineer and other national and international staff of CCRIP. The Senior Hydrologist liaises with relevant units in LGED, on all hydrological aspects of the project activities.

The Senior Hydrologist communicates intensively with BWDB and other agencies responsible for water control and flood mitigation at the various levels in the water conveyance system and with river water management authorities.

The duty station is Dhaka (40%) with frequent travel to the project Upazila‘s and Unions (60%). The Senior Hydrologist will be attached to the Project Management Office (PMO) at LGED HQ, Dhaka. The GIS-Unit will facilitate his/her work and he/she will work in close collaboration with the Director of the GIS-Unit concerning aspects of mapping. Transport is made available by LGED.

Duration: The duration of employment of the Senior Hydrologist is 5 years. Qualifications: a) M.Sc. Degree in Water Resources Engineering, with special emphasis on

hydrology especially surface water hydrology; b) Fully familiar with computer data processing, Hydrological models, MS Office (Word, Excel); c) Familiar with GIS software, especially ARCGIS; and d) Experience: 3-6 years relevant work experience.

B. 2. TOR: Sub-Assistant Engineer Upazila level

TOR for additional civil engineers at Upazila level within LGED by IFAD; in total 32 Sub-Assistant

Engineers are attached for the duration of the project. Upazila level: Sub-Assistant Engineer (Upazila Infrastructure Supervision Engineer)

Duties

(i) Works under the supervision of the XEN and the Upazila Engineer and Assistant Engineer

(ii) Cooperate closely with the Project Director, the XEN and the Upazila Engineer in preparing,

planning, coordinating and monitoring project implementation;

(iii) Assists the XEN and the Upazila Engineer in preparing district-wise sub-project appraisal reports (SARs) for the districts covered by the Project. The XEN submits these SARs to the

Project Director of LGED, for approval of the co-financiers;

(iv) Advises in the preparation of specifications incorporating climate resilience measures in consultation with the Project Director, the XEN and the Upazila Engineer, in accordance with Government requirements, and co-financiers guidelines;

(v) Advises and assist the XEN and the Upazila Engineer in preparing a detailed project implementation plan and Annual Plans of Operation taking account of the need for timely completion of preparatory tasks, and of the construction constraints imposed by the

monsoon season;

Page 114: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

23

(vi) Assists the XEN in the preparation of detailed designs and budgets;

(vii) Assists the XEN and the Upazila Engineer on any modifications required to standard designs and technical specifications used by LGED in order to meet project requirements, particularly in relation to enhanced climate resilience measures;

(viii) Assists the PMO, the XEN and the Upazila Engineer to establish and operate a system for monitoring and reporting on the performance of planned routine and periodic road maintenance in the Project area

(ix) Assists the XEN and the Upazila Engineer on pre-qualification of contractors, preparation of standard contract documents, contract packaging, management of survey and design consultants, tender evaluation and contract award;

(x) Assists the XEN, the PMO and the Upazila Engineer to select the rural infrastructure sub-projects to be improved by the Project, in accordance with the selection criteria established and agreed by the co-financiers and GOB for the Project;

(xi) Assists on land acquisition and assist the XEN in participation, employment-generation and BME aspects of the project;

(xii) Assists the XEN and the Upazila Engineer in the engagement of ―Construction Observers‖

to assist monitoring of subproject works and/or where necessary intensity of monitoring is difficult to achieve by other team staff.

(xiii) Assists the XEN and the Upazila Engineer with preparation of reports describing progress, performance and future plans, and identifying any actions to be taken to ensure timely

achievement of the project‘s outputs and objectives;

(xiv) Assists with the preparation of the completion report at the end of assignment;

(xv) At the level of the Upazila assists the Upazila Engineer on matters as: selection of sub-projects, design of road and market rehabilitation, identifying land necessary for development in consultation with MMC, conducting surveys, preparing BOQs, preparing tender documents, engaging LCS, independent day-to-day supervision of execution of works, checking sub-grade strength, testing construction materials and finished items,

reporting all test results, quantity estimation for billing purposes, ensuring construction site conditions as per environmental requirements, awareness building among villagers, engaging MMCs, and so on.

(xvi) Assists with any other duties as may be reasonably assigned by the XEN and the Upazila Engineer.

Duty Station: Upazila Capital / Engineer’s Office Duration: The duration of employment of the Sub-Assistant Engineer is 5 years. Qualifications: Diploma Degree in Civil Engineering ; Relevant Experience: 2-5 years in road

construction and market infrastructure.

B. 3. TOR GIS Specialist Background on GIS More than is the case now the use of satellite imagery for maps and hydrological studies is recommended when rehabilitating or constructing infrastructure. Involving the GIS Unit of LGED is an efficient working method as the GIS Unit of LGED possesses the required software (ARCGIS),

satellite imaginary and digital maps. At the GIS Unit Maps are available from Landsat (2010), resolution 30 * 30 m. Scales used may be about 1 : 20000 (regional studies, polders) and more detailed scales like 1 : 5000 to fit the detailed surveys for the detailed assessment of rural

infrastructure and to prepare for tender documents. A printer is available and can be used to make prints to be used for field visits and for office work. Sufficient budget must be allocated to make use of GIS (prints, electronic copies, acquiring GIS data, and so on, estimated at about USD 10000.)

Geodetical instruments required In addition to available geodetical instruments some additional instruments are required: Total stations (3, for three Regions), Handheld GPS (32 for the 32 participating Upazilas), ranging rods, staffs, measuring tapes, chains; to be specified later, estimated as lump sum (USD 80000). Duties

Page 115: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 5

24

The GIS specialist:

1. Works under the supervision of the Unit In-charge of LGED´s GIS Unit; 2. Prepares the maps as required by CCRIP; 3. Acquires data from satellite imagery as available within the GIS Unit; 4. Assess the adequacy of these data and recommends purchase of hardware and software as

needed;

5. Create maps and graphs, using GIS software and related equipment; 6. Gather, analyze, and integrate spatial data from staff and determine how best the information

can be displayed using GIS; 7. Analyze spatial data for geographic statistics to incorporate into documents and reports; 8. Compile geographic data from a variety of sources including censuses, field observation,

satellite imagery, aerial photographs, and existing maps;

9. Makes field visits to verify maps with ground truth data; 10. Train the Upazila‘s Sub-assistant engineers and surveyors on the use of the GPS systems and

on data transmission to LGED GIS Unit at HQ. 11. Any other related work, as may be reasonably instructed by the PD-CCRIP or Senior-Assistant

Engineer in charge of LGED‘s GIS Unit.

Duty Station The duty station is Dhaka (80%) with travel to the project Upazila‘s and Unions (20%). The GIS Specialist will be attached to the Project Management Office (PMO) at LGED HQ, Dhaka. The GIS-Unit will facilitate his/her work and he/she will work under the supervision of the Unit In-charge of the GIS-Unit concerning the aspects of mapping. Field visits‘ cost will be reimbursable based on customary allowances related to the professional‘s salary.

Duration: The duration of employment of the GIS Specialist is 5 years.

Qualifications

M. Sc. Degree in GIS or Geography; B. Sc. Degree in Engineering, Natural resources, Computer Science or equivalent;

Preferably a combination of education and experience or extensive professional experience

as advanced user of GIS; He/she preferably has 6-8 years experience using various GIS software (primarily ESRI,

ArcGIS, Arc/Info Workstation, and ArcView), as well as various geographic data formats and standard data conversion and transformation methods, for geographic analysis;

Must have a high degree of computer literacy, must be familiar with databases for storing data, running queries, and report writing.

Page 116: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 6

Annex 6

Review of Rural Infrastructure Needs under CCRIP

Page 117: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 118: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 6

1

Annex 6

Review of Rural Infrastructure Needs under CCRIP13

1. Introduction: Experiences indicate that market and transport infrastructure facilities assist

producers to take commodities to nearest markets, which play very important roles for sustainable development of any area. These infrastructures contribute significantly to improving livelihoods in the area. For Bangladesh, it is truer as the country is vulnerable to common natural hazards such as cyclones, floods and droughts. These problems are further

accelerated due to climate change and are becoming threats to sustainable livelihoods of poor people in Bangladesh. MIDPCR showed that investments in market and small-scale roads infrastructure developments bring development opportunities in people‘s livelihoods in rural areas. The infrastructure for example boost farm gate prices, facilitate taking products to nearby markets, enhance access to good quality inputs and increase demand for products from other markets. Improved infrastructures contribute to additional private investments in agriculture and other business. It has also been observed that due to market and

communication system development, production in agriculture sector increase, employment

opportunities improve; labour productivity and their income also increase.

2. GOB and Donor Rural Infrastructure Projects: As per the Rural Development Strategy of Bangladesh, GOB and development partners (including WB, ADB, JICA, DANIDA and Govt. Of Netherlands) under several projects financed growth centres, hat bazaars (markets) and rural roads for facilitating rural development. MIDPCR and similar other projects showed that market infrastructures and rural roads serve as ―nerve centres‖ for economic growth. Infrastructures

assist to increase availability of agricultural technologies to small farmers and helped to disseminate a range of technologies for rice, other crops, poultry, livestock and fish and are reaching people. Innovations in pro-poor infrastructure development such as involving poor and destitute women in market infrastructure development and certain sections of village roads through labour contracting societies (LCS) benefited extreme poor women. Members of LCS (formed and operated under MIDPCR) acknowledged that their involvement with market

development activities assisted them in their social development. Members of LCS became self-sufficient or able in earning their livelihoods and earned respectable position in the society. LCS members are also happy that they need not to pay toll for selling their products in the market they constructed. MMC has issued identity cards to LCS team members to avail toll

free support. These developments also increased access to common property resources for the rural poor.

3. Lessons Learned from Infrastructure Projects: In view of the achievements of MIDPCR

and success stories of other infrastructure projects and considering needs of poor people the Government of Bangladesh (GOB) and IFAD is planning to implement an infrastructure development project. The will be called ―Sustainable Market Infrastructure for Livelihoods Enhancement (CCRIP)‖ and implemented in initially identified 12 districts in the south-west part of Bangladesh. To gather first-hand information and to identify possible needs of rural people and similarities of the needs in relation the lessons learned from other infrastructure projects, inception mission members visited six districts (Madaripur, Gopalganj, Shariatpur,

Bagerhat, Khulna and Satkhira) out of proposed 12 districts. Mission members visited several existing markets and communication facilities connecting these markets to existing growth centres and upazila road network. Six upazilas one from each districts visited by the mission members are: Zanjira (Shariatpur), Shibchar (Madaripur) and Kotalipara (Gopalpur), Morrelganj (Bagerhat), Dacope (Khulna) and Assasuni (Satkhira). Successes of MIDPCR were guiding points for discussion. The mission assessed views of possible such developments in the

proposed project and participation of project beneficiaries in project implementation. Beneficiaries and representatives of Govt. institutions appreciated approach of the inception mission and expressed needs of market and road infrastructure developments. They appreciated roles of LGED in such works and offered their full cooperation in project implementation and subsequent operation and management of the infrastructures if developed in their area. Institutional arrangements such as MMC and LCS introduced under MIDPCR may be practiced in these areas without any resistance. Most important infrastructures requested

by the stakeholders and endorsed by the inception mission are provided with justification for sustainable development of possible project area (Annex 1).

13 Prepared by Dr. Abdul Ghani, Consultant, IFAD

Page 119: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 6

2

4. Through detail discussions among LGED management and Inception Mission, about 32 upazilas

have initially been selected from proposed 12 districts for implementation of CCRIP. However, this is very preliminary idea and will require confirmation by GOB and IFAD managements during project formulation. Infrastructures that may be considered under CCRIP for providing effective development opportunities with brief importance are mentioned as;

5. Market Infrastructures Development: Market development under CCRIP will include rural markets (haat-bazaars) and smaller assembly markets. Rural (village and union level)

markets are smaller than major growth centres and wholesale markets. Market infrastructures will be selected on the basis that they assist to channel significant volumes of products from producers to buyers and consumers in other project districts and the country. A flexible approach will be adopted in selecting types of infrastructures. However, entire market area should have paved areas to avoid uncomfortable movement of people due to mud during the rainy season. Areas will also be reserved for women in parts of the market used by temporary

traders. As in MIDPCR, markets will be constructed by female LCS.

6. At some places there will be need for sheds at assembly centres (informal collection centres) and paved areas for parking of trucks. Some markets may need fish landing centres and require foreshore development of the river banks and construction of landing platform (ghats).

Needs for such requirements may be finalized during more detail assessment.

7. Institutional Aspect: Along with physical infrastructures, market institutions will be developed in the project area which will include Market Management Committees (MMCs),

collection centre committees and other stakeholder groups. Market Management Committees will manage operation and maintenance of markets; adopt improvement actions for further development by the best use of 25% share of lease money to be received from upazila out of market auction fees. For this purpose. Engagement of LCS should be ensured instead of a commercial contractor for construction of markets and roads (where applicable as per LGED procedure) to create employment and to enhance skills and financial capacity of the poorest women in the project area. Technical skills training for such construction and construction

management will be ensured by LGED.

8. Infrastructure Requirement: Initial estimate indicates that 32 upazilas may be included from the proposed 12 districts in this project. For 32 upazilas, taking 1-2 Type II: Community (Village) markets and 5-6 Type III: smaller market/centres would require about 32 Type II and about 160 Type III small markets and 10 commodity collection points (CCP) along with

market accessories.. Market infrastructures would also require women‘s section, collection

points, MMC buildings, multi-purpose sheds, fish sheds, and toilet blocks with water supply, tubewells, open sale platform, internal roads (CC), drains, garbage pits paved area/parking area (HBB) and land rising. Actual numbers and volumes of works will be planned and cost will be estimated during formulation mission and finalized during project appraisal/design.

9. Transport Infrastructure: Experiences and outcome of several similar projects indicate that transport or communications infrastructures facilitate development of interior area and contribute significantly in improved livelihood of poverty prone areas. Therefore, CCRIP will

include development of union and village (community) roads, along with bridges, culverts and ghats (landing platforms). These roads will be planned to connect rural markets to the upazila and district road network, and to other larger markets, growth centres and to farms. Experience of MIDPCR will be used in building roads and other infrastructures. Services of Labour Contracting Societies (LCS) composed of the poorest women will be utilized wherever is possible. Depending on the local conditions, roads will be constructed as BC, RCC and Block material types. Sizes of bridges, culvers and ghats will be decided as per LGED standards.

However, local people during discussion with inception mission requested that wherever possible these structures should have provision for water conservation and flood protection.

There should also be provision of sluices and inlet structures so that interested farmers can use them for irrigation and water retention through field level committees. Number and length of these transport infrastructures will be decided during formulation mission and LGED approved design

10. Standard will be followed for construction. Boat landing ghats will also be developed where markets are served by water transport. Small-scale water management interventions will be piloted in CCRIP, and would take place alongside road development. This could improve khals (canals) alongside or crossing project roads to enable them to store water for irrigation, supply water for aquaculture and drain agricultural land.

Page 120: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 6

3

11. Tree Plantation: Tree plantation besides roads and embankments is considered as national

program for conservation of environment, bio-diversity and poverty reduction. Tree plantation under social forestry program has made significant progress in Bangladesh. It is one of the popular activities implemented by LCS, NGOs and GOB departments. There should be provision of road side plantation and maintenance by LCS under CCRIP. Tree plantation will be done following Tree Plantation Manual 9 and 1124 saplings will be planted per km of road (on both sides) for types of roads. Two women will be engaged in the first year and one woman for

subsequent years per km of road for taking care of trees. This will provide employment opportunity for destitute women and will assist them in their improved livelihood.

12. Brief on some of the proposed infrastructure: Brief on some of the proposed infrastructure is given below:

13. Market Infrastructures: Markets such as growth centres, major and small markets and assembly centres along with improved transportation and communication networks serve as

development centres for rural area. It will also assist farmers to get inputs at fair price and ensures opportunities for fair price for farm and non-farm products. Under this project 37 major (Type I and Type II), 160 small markets (Type III) and 5 collection points will be developed.

14. Market connecting roads: Roads connecting markets to villages and to growth centres and or or to upazila roads will be constructed under CCRIP. About 650 km of union and 341 km of village roads may be constructed under CCRIP in proposed 32 upazilas. Design of the roads

and relevant infrastructures will be as per LGED approved procedures.

15. Bridges and culverts: To ensure free flow of water in the project area, required number of bridges and culverts will be constructed during road improvements. As per LGED procedures, there should be provision of cross-drainage. A total gap of 10 meters per km of road is considered for Union road and 7.5 meter per km gap for drainage per km of Village road is considered. Therefore, proposed Union and Village roads would have requisite amount of culverts/bridges. Bridges and culverts will be constructed on the gaps following LGED standard

design.

16. Slope protection: Slope protection for proposed 501 km of roads, 197 markets (Type I, II, and III), ghats (landing plat forms) and approaches of bridges/culvers will be required for safety of the infrastructures from possible erosions and wave actions. As per present approved procedure, LGED will consider 300 square meters of protection per km of Union and 100

square meters per km of Village roads.

17. Tree Plantation: Tree plantation along 500 km roads under CCRIP will provide opportunities for income generating activities for LCS and will also ensue routine maintenance for road sides and road shoulders.

18. Earthworks: All roads will be developed on existing road alignments where some earth work exist. Re-sectioning and additional earthwork will be required. Estimated cost for earth work is Taka 5.75 Lakh for Union roads and Taka 1.00 Lakh for Village roads. Earth work during road improvement will also provide employment opportunities for local people.

19. Land Acquisition: No land acquisition should be undertaken for this project as most roads are supposed to be on existing road alignments. Moreover, attempts should be made to recover lands if grabbed by local people over time, which was part of existing roads. However, for realignment and widening some sections of roads and embankments, minimum possible amounts of land may be acquired. Existing LGED provisions allow land acquisition to the extent of about 820 square meters per km Union roads and market places and 410 square meters per km for Village roads.

20. Open Sales Platform: There will be open sales platforms in each market and assembly centres especially at landing places where farmers and fishermen bring their products by boats. At each landing place there should be provision of truck stand and sheds for providing safe place for agricultural products and sellers. These places are expected to be used all over the year and sheds will be of special help during rainy season. All sales platforms should be paved to avoid muddy condition.

21. Drains: There should be provision of well-designed drainage systems at each and every market and assembly centres for good working conditions. There should not be water stagnation in any of the markets and assembly centres for ensuring good working environment and protecting from breeding places for mosquitoes. Like MIDPCR, CCRIP should also provide support for drainage system development.

Page 121: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 6

4

22. Toilet Blocks: In each improved market, there should be toilet blocks for men and women but

with separate entrances. Size of toilets as approved by LGED is 6 x 5 meters. In each market, there should be one toilet for females and two for males and an n urinal for males. There should also be washing facilities in each unit. Designs of toilet blocks will be as per LGED provision and as implemented under MIDPCR. A preliminary list of major items to be included in the project is prepared using LGED guidelines and is provided in Annex 2.

23. Labour Contracting Societies (LCS): Under MIDPCR, it has been proved that construction works

(markets and sections of roads) completed by LCS are cheaper and of better quality than generally constructed by local contractors. Furthermore, it assists LCS members in earning their livelihoods and IGAs. Profits earned through construction works provide them capital for initiating business and other IGAs. Experiences of LCS may be replicated in CCRIP for ensuring sustainable income generation by poor and destitute women and for improvement in their livelihoods.

24. Environmental and Social Issues for CCRIP: Improved market system development, road communication, afforestation programs, construction works carried out by LCS, paved market places and assembly centres will contribute to better working environment in the project area. Income generating activities to be promoted during implementation of CCRIP and continued

contribution of the services out of infrastructures will continue providing IGAs to poor women and agricultural producers. Improved communication system will assist project area people to avail health services mostly available at upazila level and improved market places. Increased

income of common people and additional products and better price of the products will contribute to intake of more nutritious foods that will further assist to maintain healthy lives. Increased income will encourage producers and stakeholders to send their children to schools and in purchasing radio, television and other facilities for amusements and receiving messages from communication media. All these facilities will contribute to improved livelihood, which is one of the objectives of CCRIP.

25. Conclusions and next steps for CCRIP: Based on the above and contribution of other sections

of CCRIP, it may be mentioned that CCRIP on implementation will contribute positively in sustainable improved livelihood in the project and adjacent areas. Therefore, CCRIP should move to next phase of project preparation (Project Formulation) phase.

Page 122: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 6

5

Appendix 1 of Annex 6

Inception Mission visited 12 upazilas of six districts and interacted with stakeholders to estimate their priority infrastructure requirement for the proposed CCRIP project. Request of the stakeholders with justification and comments of the mission is summarized as:

A. Findings of Field Visits

Serial No.

Required Structure

Reasons for Requirement with Comments

1 Paved union and village roads

In most places, conditions of union and village roads connecting to upazila are bad and become unusable during rainy season. Most people in all six upazila visited demanded road improvement. This

will facilitate connecting to nearest growth centre and upazila headquarter. Communication among adjacent markets will also improve.

2 Access to health centre

People of these remote villages suffer from health supports. Even if there is limited health service facilities, most people can not reach

health centres due to bad communication and shortage of transport

facilities. Pregnant women and elderly people suffer most. Therefore, development of road network will assist farmers and villagers to avail health services available at upazila level.

3 Bridges & culverts

There are strong demands for bridges and culverts along with all season paved roads. Bridges and culvers will ensure free flow of

existing water bodies and canals and in removing drainage congestion.

4 Embankment In places where market is along river site, there was demand for embankment and protective works. Proposed embankments may be road cum embankment.

5 Sluice gates Farmers of Morrelganj, Dacope and Assasuni need sluice gates along with road improvement for storing sweet water during later part of rainy season and for protecting their area from inflow of saline water during dry season.

6 Ponds and

ghats

Most people in coastal area still depend on ponds for their household

water uses and for drinking water. Therefore, demanded adequate no. of ponds in the villages especially near the markets to be developed under CCRIP. These are required to provide clean water and for improving health condition.

Stakeholders demanded landing platform (ghat) for loading and unloading commodities at market sites. These will facilitate movement of goods and people.

7 Drainage system

Drainage congestion is also common in many exiting markets and stakeholders demanded for drainage system development. It will also assist in improved hygienic condition and will reduce mosquito problem in market area.

8 Improved crop

varieties

In remote areas visited by mission members, improved and HYV

seeds are not available. Stakeholders feel HYV seeds will be available

with improvement of roads and markets. The project may facilitate agricultural extension services.

9 Afforestation along roads

and embankments

Farmers, shop owners and LGIs believe plantation along roads and embankment slopes will provide job opportunities to local poor

people and will also contribute to improved environment. As usual, LGED may include LCS for afforestation program for roads and embankment.

10 Coordination committees

Upazila and union level public representatives, Upazila Nirbahi Officer, village leaders and farmers assured the inception mission that they will coordinate among themselves for effective operation

and management of infrastructures that will be built under CCRIP in

Page 123: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 6

6

Serial

No.

Required

Structure

Reasons for Requirement with Comments

their areas.

11 NGO support and union and upazila

NGO are working in the six upazila visited and their supports will be available if arrangements can be made.

12 Flood problem Flood due to heavy rain and inflow of surge during rainy season is problem in certain areas (Morrelganj, Assasuni) and will require flood protection measures as part of infrastructure development.

13 Homestead farming

Homestead farming is becoming popular but shortage of quality seeds is a constraint. NGOs may be involved in CCRIP or similar projects may assist project area people in improving homestead farming.

14 IGAs People especially poor women will like to get training on IGAs and adopt it. NGOs and extension department may assist in developing

IGAs.

15 Tubewells Tubewells are required for drinking water and as well as for irrigation purpose.

16 Market development

Market improvement was of high demand even above road development in some places. The project will address this.

17 Paved market Entire market area should be paved as unpaved patches in market place make most part of the market muddy during rainy season. Fish market area may be muddy even during dry season if do not have

paved floors.

18 Toilets at market

Toilet with water supply facilities is very much required for good market and to make it clean and hygienic. Toilet facilities at markets established under MIDPCR will be included under CCRIP.

19 MMCs Most markets have management committees but will require

formalizing with upazila management and have timely election to

make them functional. Thus committees should avail share of income from leasing of markets by UNO.

20 LCS In all the sites visited in all six upazilas, local people informed that they will have no objection formation of LCS with destitute women

and allow them to work for construction of markets and roads, plantation along roads and embankments, and operate shops in the markets.

21 Truck stand and sheds

Construction of landing places along water bodies and truck stands for carrying agriculture (crops, fish) products. There should be sheds in such places to provide shelter for goods and sellers during rainy

season.

22 O&M responsibility

Stakeholders agreed to take part in O&M of the facilities to be created in their area and to follow standard LGED procedure for such works.

Page 124: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

Annex 7

List of community (village) markets and union/village roads

selected for development

Page 125: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 126: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

1

Annex 7

List of community (village) markets and union/village roads

selected for development

A. Selected Community (Village) markets (IFAD Funded)

Coastal Climate Resilient Infrastructure Project (CCRIP)

Selected IFAD funded Small and Medium Sized Community (village) Markets

SL. No. District Upazilla Name of Rural Market Market Type

1 Barisal Babugonj Postoffice Hat Medium

2 Barisal Babugonj Uttar Baherchar Small

3 Barisal Babugonj Rahamatpur Medium

4 Barisal Babugonj Steamerghat Bazar Small

5 Barisal Uzirpur Gutia Bazar Medium

6 Barisal Uzirpur Jugirkanda(Galla) Bazar) Small

7 Barisal Uzirpur Habibpur Bazar Small

8 Barisal Uzirpur Nayakandi Hat Small

9 Barisal Uzirpur Daberkool Bazar Medium

10 Barisal Uzirpur Solok Hat Small

11 Barisal Uzirpur Ganteswar Bazar Small

12 Barisal Uzirpur Saudi Bazar Small

13 Barisal Banaripara Naya Bazar Small

14 Barisal Banaripara Awar hat Medium

15 Barisal Banaripara Khalishakota Hat Small

16 Barisal Banaripara Janatar hat Medium

17 Barisal Banaripara Gaba Hat Small

18 Barisal Banaripara Guachitra Cow Hat Small

19 Barisal Banaripara Sher-e-Bangla Bazar Small

20 Barisal Banaripara Manik Miar Hat (Doctor Hat) Small

21 Bhola Lalmohan Harigonj Small

22 Bhola Lalmohan Peshkar Hat Medium

23 Bhola Lalmohan Patoari Hat Small

24 Bhola Lalmohan Chatla Bazar Small

25 Bhola Lalmohan Janata Bazar Small

26 Bhola Borhanuddin Mainkar Hat Medium

27 Bhola Borhanuddin Darun Bazar Small

28 Bhola Borhanuddin Sikder Hat Small

29 Bhola Borhanuddin Jaoyer Hat Small

30 Bhola Borhanuddin Janata Bazar Small

31 Bhola Borhanuddin Talukder hat Small

32 Bhola Charfassion Uttar Charmanika Bazar Medium

33 Bhola Charfassion Bhuyar Hat Small

34 Bhola Charfassion Pangashia Bazar Small

35 Bhola Charfassion Char Lulin Bangla Bazar Small

36 Bhola Charfassion Daser hat Small

37 Bhola Charfassion Nazirmajhi Hat Small

38 Bhola Charfassion Kukrimukri Hat Small

39 Patuakhali Sadar Pajakhali Hat Medium

40 Patuakhali Sadar Choto Beghai Officer hat Medium

Page 127: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

2

SL. No. District Upazilla Name of Rural Market Market Type

41 Patuakhali Sadar Moddho Titkata Small

42 Patuakhali Sadar Tafalbaria bazar Small

43 Patuakhali Sadar Satghar Bazar Small

44 Patuakhali Sadar Katakhali Small

45 Patuakhali Kalapara Patua Bazar Medium

46 Patuakhali Kalapara Tegachia Hat Small

47 Patuakhali Kalapara Muktijoddha Hat Small

48 Patuakhali Kalapara Pakhimara Bazar Small

49 Patuakhali Kalapara Dablugonj Small

50 Patuakhali Galachipa Amkhola Hat Medium

51 Patuakhali Galachipa Chiknikandi Medium

52 Patuakhali Galachipa Siba Ismail Mridhar hat Small

53 Patuakhali Galachipa Naluabagi hat Small

54 Patuakhali Galachipa Gazalia Hat Small

55 Patuakhali Galachipa Bangla Bazar Small

56 Patuakhali Rangabali Rangabali Natun Bazar (Kachiabunia)

Medium

57 Patuakhali Rangabali Moudubi Medium

58 Patuakhali Rangabali Charbestin Bazar Small

59 Patuakhali Rangabali Horidra Khali Bazar Small

60 Patuakhali Rangabali Tulatali Bazar Small

61 Patuakhali Mirzaganj Khalisakhali Bazar Medium

62 Patuakhali Mirzaganj Gabua Bazar Medium

63 Patuakhali Mirzaganj Chaita Bazar Small

64 Patuakhali Mirzaganj Sishur Hat Small

65 Patuakhali Mirzaganj Bhutiar Hat Small

66 Patuakhali Mirzaganj Kalagachia Bazar Small

67 Barguna Amtali(With

Taltali) Fakir hat Medium

68 Barguna Amtali(With

Taltali) Amragasia Bazar Medium

69 Barguna Amtali(With

Taltali) Munsir hat Bazar Small

70 Barguna Amtali(With

Taltali) Uttar Purba Tepura Bazar Small

71 Barguna Amtali(With

Taltali) Kabirazpara Small

72 Barguna Amtali(With

Taltali) Koroibaria Bazar Small

73 Barguna Amtali(With

Taltali) Dafadar Hat Small

74 Barguna Betagi Mayer hat Medium

75 Barguna Betagi Mier hat Medium

76 Barguna Betagi DC hat Small

77 Barguna Betagi Kabil Akon Bandthghat Bazar Small

78 Barguna Betagi Laxmipura Bazar Small

79 Barguna Betagi Mpr Hat Small

80 Barguna Betagi Kumrakhali Hat Small

Page 128: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

3

SL. No. District Upazilla Name of Rural Market Market Type

81 Barguna Bamna Bukabunia Bazar Medium

82 Barguna Bamna Gudhigata Bazar Small

83 Barguna Bamna Sonakhali Bazar Small

84 Barguna Bamna Ramna Baikalin Bazar Small

85 Barguna Patharghata Nasnapara Medium

86 Barguna Patharghata Miah Medium

87 Barguna Patharghata Sofilpur Small

88 Barguna Patharghata Baro Tengra Small

89 Barguna Patharghata Horidra Khali Bazar Small

90 Barguna Patharghata Badurtala Hat Medium

91 Pirojpur Mothbaria Tearkhali Bazar Medium

92 Pirojpur Mothbaria Amragachia Bazar Medium

93 Pirojpur Mothbaria Amtoli hat Small

94 Pirojpur Mothbaria Jawtala hat Small

95 Pirojpur Mothbaria Vagirathpur bazar Small

96 Pirojpur Mothbaria Kulurhat Medium

97 Pirojpur Mothbaria Boro Masua Small

98 Pirojpur Zianagar Chandipur Bazar Medium

99 Pirojpur Zianagar Ghoserhat Medium

100 Pirojpur Zianagar Lahuri hat Small

101 Pirojpur Zianagar Pather hat Small

102 Pirojpur Zianagar Chowkider hat Small

103 Jhalakati Kathalia Ghoser Hat Medium

104 Jhalakati Kathalia Marichbunia Hat Small

105 Jhalakati Kathalia Kathalia Bazar Small

106 Jhalakati Kathalia Kachua Bazar Small

107 Jhalakati Kathalia Tarabunia Bazar Small

108 Jhalakati Kathalia Sonar Bangla Bazar Small

109 Madaripur Rajoir Lundi bazar Small

110 Madaripur Rajoir Boiragir bazar Medium

111 Madaripur Rajoir Kodalia Natun bazar Small

112 Madaripur Rajoir Lakhanda bazar Small

113 Madaripur Rajoir Vandaria bazar Small

114 Madaripur Rajoir Chander bazar Small

115 Madaripur Shibchar Mollarhat Small

116 Madaripur Shibchar Kamlapur hat Small

117 Madaripur Shibchar Kalatolahat bazar Small

118 Madaripur Shibchar Kawarhat bazar Small

119 Madaripur Shibchar Korokchar Natun bazar Small

120 Madaripur Shibchar Saheberbazar (Gostir hat) Medium

121 Madaripur Shibchar Garirhat bazar Small

122 Madaripur Shibchar Farazirhat bazar Small

123 Sariatpur Janjira Kajirchar Small

124 Sariatpur Janjira Durger hat Small

125 Sariatpur Janjira Taher Madbar Bazar Small

126 Sariatpur Janjira Budair hat Small

Page 129: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

4

SL. No. District Upazilla Name of Rural Market Market Type

127 Sariatpur Janjira Laukhola Bazar Medium

128 Sariatpur Janjira Rup babur Hat Small

129 Sariatpur Naria Nowadda Bangla Bazar Medium

130 Sariatpur Naria Mohiskhola Small

131 Sariatpur Naria Talipara Natun Hat Small

132 Sariatpur Naria Majir Hat Small

133 Sariatpur Naria Joy Bangla Bazar Small

134 Sariatpur Naria Char Atra Bazar Small

135 Sariatpur Naria Chandipur Bazar Small

136 Gopalgonj Kotalipara Wapda Hat Medium

137 Gopalgonj Kotalipara Suagram Hat Small

138 Gopalgonj Kotalipara Pererbari hat Medium

139 Gopalgonj Kotalipara Kushla Small

140 Gopalgonj Kotalipara Ramnagar Small

141 Gopalgonj Kotalipara Narayankhanna Small

142 Gopalgonj Kotalipara Kacharivita Bazar Small

143 Gopalgonj Tungipara Gopalpur Hat Medium

144 Gopalgonj Tungipara Modhukhali Hat Small

145 Gopalgonj Tungipara Korfa Small

146 Gopalgonj Tungipara Borni Hat Small

147 Gopalgonj Tungipara Dumuria Hat Small

148 Khulna Koyra Surikhali Small

149 Khulna Koyra Khorolkati Small

150 Khulna Koyra Zhiligata Medium

151 Khulna Koyra Vandarpol Medium

152 Khulna Koyra Suti Small

153 Khulna Dacope Banishanta Bazar Small

154 Khulna Dacope Pankhali Bazar Small

155 Khulna Dacope Moukhali bazr Small

156 Khulna Dacope Badua bazar Small

157 Khulna Dacope laxmikhola bazar Small

158 Khulna Batiaghata Titukhali Hat Small

159 Khulna Batiaghata Baintala Hat Small

160 Khulna Batiaghata Dhadua Bazar Small

161 Khulna Batiaghata Sukhdara Medium

162 Khulna Batiaghata Taliamara Medium

163 Satkhira Shyamnagar Munshiganj Medium

164 Satkhira Shyamnagar Bangshipur Medium

165 Satkhira Shyamnagar Garkumarpur Small

166 Satkhira Shyamnagar Patakhali Small

167 Satkhira Shyamnagar Chaltaghata Small

168 Satkhira Shyamnagar Verar Hat Small

169 Satkhira Shyamnagar Nildumur Small

170 Satkhira Assasuni Bisot Medium

171 Satkhira Assasuni Kalabagi Medium

172 Satkhira Assasuni Maddham Chapra Small

Page 130: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

5

SL. No. District Upazilla Name of Rural Market Market Type

173 Satkhira Assasuni Puijala Small

174 Satkhira Assasuni Gabtala Small

175 Satkhira Assasuni Bashukhali Small

176 Satkhira Assasuni Paithali Small

177 Satkhira Kaligonj Moutala (Large Market) Medium

178 Satkhira Kaligonj Gorrer Hat Small

179 Satkhira Kaligonj Sannasir Chalk Small

180 Satkhira Kaligonj Jerrongacha Hat Small

181 Satkhira Kaligonj Tarail Medium

182 Satkhira Kaligonj Kadamtala Hat Small

183 Satkhira Kaligonj Kakshiali Bazar Small

184 Bagerhat Sharankhola Amragachia Bazar Medium

185 Bagerhat Sharankhola Khantakata Medium

186 Bagerhat Sharankhola Nalbunia Hat Small

187 Bagerhat Sharankhola Lakurtala Small

188 Bagerhat Sharankhola Chutukhar Hat Small

189 Bagerhat Sharankhola Taltaly Hat Small

190 Bagerhat Sharankhola Chaltabunia Small

191 Bagerhat Morrelgong S.B Bazar Small

192 Bagerhat Morrelgong Pachgoan Hat Medum

193 Bagerhat Morrelgong Jewdara Hat Medium

194 Bagerhat Morrelgong Boulpur Hat Medium

195 Bagerhat Morrelgong Lakmikhali Small

196 Bagerhat Morrelgong Madrasha Hat Small

197 Bagerhat Morrelgong Khawlia Hat Small

Page 131: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

6

B. Selected Union Roads (IFAD Funded)

Coastal Climate Resilient Infrastructure Project (CCRIP)

Selected IFAD funded Union Roads

Sl. No.

Zilla Upazila Name of Village Market

Road ID Road Name

Total Length Road (Km)

Proposed Length (KM)

1 Barisal Babugonj Rahamatpur 506033004 Rahamatpur Bazer- Madhabpasha UP

6.1 2.5

2 Barisal Banaripara Sher-e-

Bangla Bazar 506103012

Baisari College via PG School (Tetla to Sher-e-Bangla Bazar)

9.10 2.50

3 Barisal Banaripara Janata Bazar 506103003

South Illuhar Boro Bridge to Chander hat via Illuhar High School

11.16 2.00

4 Barisal Uzirpur Habibpur Hat 506943003 Habibpur Bazar to Kuralia bazar via Munsir Taluk Road.

4 1.75

5 Barisal Uzirpur Daberkool

Hat 506943004

Chowdhurir Hat to Hastisunda via Daberkool Road

7.61 2.00

6 Barisal Uzirpur Gondeshar 506943007

Uzirpur to Gondeshar Bazar via Bamrail UP Office

12.27 0.50

7 Barisal Uzirpur Gondeshar 506943003 Guria Nutan Hat -Gondeshar Bazr Via Sikarpur Road

12.6 2.00

8 Bhola Lalmohan Harigonj Hat 509543010 Charvuta UP-Chatla Bazar

5.85 2.50

9 Bhola Lalmohan Peshkar Hat 509543012

Nazirpur Bazar-Paschim Char Umed via Farashgonj UP

12.69 2.00

10 Bhola Borhanuddin Janata Bazar 509213007

Dorgha (Hakimuddin Bazar) to Tobgi UP office via Dalal Bazar road

6.00 2.00

11 Bhola Charfassion Bhuyar hat 509253026

RHD-Kaliakandi GPS to Jalil road Dinar Khea ghat via Bhuyar hat

8.5 2

12 Bhola Charfassion Pangashia

bazar 509253015

Usmangonj UP to Kasemmiar Hat via Pangasia bazar

6.10 1.50

13 Bhola Charfassion Char Lulin

Bangla Bazar 509253059

Muzibnagar Janatar Bazar Launchghat to South side of WAPDA embankment road

15.00 2.00

14 Patuakhali Sador Pajakhali Hat 578953034 Lohalia Up-Patuakhali H/Q.

9.15 2

Page 132: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

7

Sl. No.

Zilla Upazila Name of Village Market

Road ID Road Name

Total Length Road (Km)

Proposed Length (KM)

15 Patuakhali Sador Moddho

Titkata Hat 578953033

BaraBighai Up-Patukhali GPS-Shechasebak Bazer-Marichbunia UP.

10.00 2.00

16 Patuakhali Sador Katakhali Hat 578953001

Jainkati UP-Dholkhali (Sluice Launchghat)Bazer-Via Chandanbaria Bhuria rKhayaghat-Katakhali launchghat Road.

13.53 2.00

17 Patuakhali Kalapara Patua Bazar 578663007 PatuaHat-Dhakhali.U.P (College)

9.6 2

18 Patuakhali Kalapara Old Mohipur

Bazar 578663005

Khapravanga UP to Dalbugonj Hat

9.50 2.00

19 Patuakhali Kalapara Muktijoddha

Hat 578663004

Lalua UP-Nilgonj UP Via Mithagong UP.

16.80 2.00

20 Patuakhali Galachipa Chiknikandi

Hat 578573008

Chiknikandi UP-Amkhola UP

8.3 2

21 Patuakhali Galachipa Siba Ismail Mridhar Hat

578573030 Chottosiba FRB to Barosiba Launchghat .

7.10 2.00

22 Patuakhali Galachipa Naluabagi hat 578573022 Naluabagi Bazar-R&H road via UP Office

11.80 2.00

23 Patuakhali Rangabali Rangabali

Natun Bazar (Kachiabunia)

578583025 Barobaisdia U.P. to Rangabali U.P.

4.86 2.5

24 Patuakhali Rangabali Moudubi Hat & Tulatolir

Hat 578583013

Chailtabunia UP-Borrobaisda UP-Moudube Mukharbandha Shelter.

17.05 2.00

25 Patuakhali Mirzaganj Khalisakhali

Bazar 578763012

Mazidbaria UP office-Khalishakhali bazar Rd.

4.2 2.00

26 Patuakhali Mirzaganj Gabua Bazar 578763018

Kakrabunia UP office-kumrakhali-H/O Rashid Judge-Gazipurhat Rd.

8.90 1.30

27 Patuakhali Mirzaganj Chaita Bazar 578763001

Chaita Bazar-Chaita Madrasha-Bazita Madrasha at Shishurhat.

4.50 2.00

28 Barguna Amtoli Fakir hat 504093016 Taltali UP -Fakir's Hat via Amkhola

Road

11.5 2

29 Barguna Amtoli Amragachia

Bazar 504093021

Amragachia Bazar-Kukua UP

7.15 2.00

30 Barguna Betagi Laxmipura

Bazar 504473001

Betagi UP-Laxmipura Bazar

6.5 2

31 Barguna Betagi Kabil Akon

Bazar 504473019

Hosnabad UP-Sonar Bangla Bazar

4.27 2.00

32 Barguna Patharghata Boro Tengra

Bazar 504853002

Patharghata - Tengra bazar

3.98 2

Page 133: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

8

Sl. No.

Zilla Upazila Name of Village Market

Road ID Road Name

Total Length Road (Km)

Proposed Length (KM)

33 Barguna Patharghata Natchnapara

Bazar 504853004

Natchnapara UP - Natchnapara Bazar

1.20 1.20

34 Barguna Patharghata Miah Bazar 504853008 Lemua GC- C&B Bazar via Hemontopur

6.00 1.50

35 Barguna Patharghata Badurtala

Bazar 504853001

Patharghata - Horinbaria-Badurtala

8.70 2.00

36 Barguna Patharghata Miah Bazar 504853014 Raihanpur UP - Pipulia Bazar Via Zamirtala

4.10 1.00

37 Barguna Bamna Bukabunia

Bazar 504193002

Bukabunia UP - Kholpatua GC via Sonakhali Bazar

8 2.5

38 Barguna Bamna Gudhigata

Bazar 504193005

Gudhigata bazar - Ramna UP via Uttar Kakchira Bazar

7.74 2.00

39 Perojpur Mothbaria Amragachia

Bazar 579583002

Amrgachia UP- Amtoli hat at ch. 700-1750m & 2750-5250m

5.25 2

40 Perojpur Mothbaria Jawtala Hat 579583011

Mirukhali UP-Jawtala bazar via Vagirathpur bazar at ch. 5040-7790m.

8.79 2.00

41 Perojpur Mothbaria Tearkhali

Bazar 579583016

Gulishakhali UP to 22 Kura Bazar via H/O Hasem Howlader

11.30 2.50

42 Perojpur Mothbaria Kulur Hat 579583009

Betmore UP-Amtoli hat via Khunerhat road at ch. 3600m-5600m.

5.60 2.00

43 Perojpur Zianagar Chandipur

Hat 579883006

Balipara UP-Battala hat via Uttar Kalaron Dhakil madrasha & Nuria Dhakil Madrasha road.

9.60 2.00

44 Perojpur Zianagar Pother Hat 579883006

Balipara UP-Battala hat via Uttar Kalaron Dhakil madrasha & Nuria Dhakil Madrasha road.

9.60 2.00

45 Perojpur Zianagar Luhuri Hat 579883001

Parerhat GC (Chalna)- Goperhat via parerhat UP & Luhuri hat road.

9.10 2.00

46 Jhalokati Kathalia Marichbunia

Hat 542433010

Patikelghata UP Office - Datterpasuribunia Barzar - Tarabunia Bazar - Khaikhali GC.

8.076 1.5

47 Jhalokati Kathalia Ghoser Hat 542433009 Patikelghata UP Office - Jhorekhai atun Hat Road.

9.17 2

Page 134: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

9

Sl. No.

Zilla Upazila Name of Village Market

Road ID Road Name

Total Length Road (Km)

Proposed Length (KM)

48 Jhalokati Kathalia Tarabunia

Bazar 542433010

Patikelghata UP office to Dattar Pasurbunia Pazar to Tarabunia Bazar to Koikhali GC.

8.07 2

49 Jhalokati Kathalia Kachua Bazar 542433011

Souljalia UP Office - Binapani Bazar via Dogona Bazar Road.

2 1.5

50 Madaripur Rajoir Chander Bazar

354803008 Hossenpur UP-Kabirajpur UP road

5.5 2.50

51 Madaripur Shibchar Kamlapur Hat 354873011 Boheratola UP office-Baburhat via Vennatola bazar

5.64 2.00

52 Madaripur Shibchar Krokchar

Natun Bazar 354873014

UZR-1,Bhadrason UP office-Korokchar natun bazar road via minakandi GPS,Uttar Korokchar hat & Beshai Dhonirkandi GPS

5.73 2.00

53 Madaripur Shibchar Garir Hat 354873009

Bashkandi UP Office -Chowdhurir hat road via Garirhat

6.28 2.00

54 Shariatpur Janjira Kaziarchar

Bazar 386943016

Bilashpur U.P.-Kaziarchar Bazar Road

2.50 2.50

55 Shariatpur Janjira Durgarhat 386943005 Kazirhat-Durgerhat road

8.56 2.00

56 Shariatpur Naria Mohishkhola

Bazar 386653004

Bhojeswar-Mohishkhola Bazar road from ch. 4320m to 5820m.(UNR)

5.82 2.00

57 Shariatpur Naria Telipara

Nutan Hat 386653007

Bhumkhara-Gulmaize road from ch. 2800m to 5700m.(UNR)

9.25 2.00

58 Shariatpur Naria Char Artra

Bazar 386653017

Charatra UP - Khas Bazar road.

3.125 2

59 Gopalgonj Kotalipara Wapda hat & Suagram hat

335513001 Pubra WAPDA hat-Suagram UPC Road

3.50 2.50

60 Gopalgonj Kotalipara Suagram hat 335513013 Suagram UPC-Kandi bazar road.

3.00 2.00

61 Gopalgonj Tungipara Dumuria Hat 335913003 Beltala-Chinguri-Labutola-Dumuria UP road

6.81 2.00

62 Gopalgonj Tungipara Gopalpur Hat 335913002 Gopalpur UP-Guadhana Silna GC Road

7.82 2.72

63 Gopalgonj Tungipara Gopalpur Hat 335913008 Gopalpur UP-Borauhati Road

1.70 1.70

64 Bagerhat Sharankhola Amragachia

Bazar 201773003

West Nalbunia-Rajapur Road

3.39 2.00

65 Bagerhat Sharankhola Amragachia

Bazar 201773001

Dhansagar UP-Rajapur GC road

5.00 2.00

Sl. No.

Zilla Upazila Name of Village

Road ID Road Name Total

Length Proposed

Length

Page 135: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

10

Market Road (Km)

(KM)

66 Bagerhat Morrelgong S.B Bazar 201603009 Morrelgonj Upazila HQ-Baharbunia Union HQ road.

10.65 2.00

67 Bagerhat Morrelgong Pachgoan Hat 201603005 Baharbunia UP-Herma GC road.

7.75 2.00

68 Khulna Batiaghata Titukhali Hat 247123003 Batiaghata UP at Hetalbunia - Mailemara hat

6.46 2.34

69 Khulna Batiaghata Taliamara

Bazar 247123013

Baliadanga UP office (West) - Taliamara Hat

1.70 1.70

70 Khulna Batiaghata Dhadua Bazar 247123005 Baliadanga UP office - Khoria Hat

2.09 2.09

71 Khulna Dacope Banishanta

Bazar 247173002

Banisanta UP office to Banisanta Bazar road

12.67 2.50

72 Khulna Dacope Badua 247173006 Dacope UP Office to Badua UP office

road

13.20 2.50

73 Khulna Koyra Suti Bazar 247533003 Koyra UP - Suti Bazar

5.80 2.00

74 Khulna Koyra Suti Bazar 247533010 Hogla GC- Maharajpur UP - Suti Bazar

14.58 2.20

75 Sathkhira Assasuni Bichat Bazar 287043004 Ekshora Bazar-Bichat Bazar (Anulia UP) Raod.

3.00 2.00

76 Sathkhira Assasuni Gabtala and

Maddam Chapra

287043001 Kadakati UP-Gabtala hat-Kadakati GC Raod.

3.76 2.00

77 Sathkhira Shyamnagar Bangshipur 287863006

Isswarypur UP-Gumantali-

Jabakhali Hat Road.

7.95 1.00

78 Sathkhira Shyamnagar Bangshipur 287863013

Banshipur-Paranpur-Ramjannagar Road.

8.45 2.00

79 Sathkhira Shyamnagar Garkumarpur 287863015 Padmapukur UP-Garkumarpur Bazar Road.

4.50 2.00

80 Sathkhira Kaligonj Moutala 287473012

Moutala UP-Sankarkati hat via Krisnanagar UNR Road

0.00 2.00

81 Sathkhira Kaligonj Kadamtala 287473010 Ratanpur UP - Bagmari Bazar Via Kadamtala Road.

6.30 1.00

Grand Total: 600.45 160.00

Page 136: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

11

C. Selected Village Roads (IFAD Funded)

Coastal Climate Resilient Infrastructure Project (CCRIP)

Selected IFAD Funded village Roads

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

1 Barisal Babugonj Postoffice Hat 506034058 Amirgoer Hat - Mirgonj via Moydaner Hat

8.00 3.00

2 Barisal Babugonj Uttar

Baherchar 506034027

Baherchar Hat - Baherchar Hospital

2.00 2.50

3 Barisal Babugonj Uttar

Baherchar 506034073

Rakudia Polli Biddut subcentre (RHD) - Baherchar bazer

5.00 2.00

4 Barisal Babugonj Steamer

Ghat Bazar 506035080

LGED raod to Steamer Ghat Bazar and construction of market adjacent bridge

0.50 0.50

5 Barisal Uzirpur Gutia Bazar 506944022 Gutia Bazar to Kamlapur Hat

8.00 2.00

6 Barisal Uzirpur Gutia Bazar 506945161

Gutia Degree College to Masimkhan Dighi westside mosque starting from Milbari of Dohorpara Village

2.00 1.50

7 Barisal Uzirpur Jugirkanda

(Gala) Bazar 506945013

Jugirkanda to DC road

4.00 2.50

8 Barisal Uzirpur Jugirkanda

(Gala) Bazar 506944045

Jugirkanda

Madrasha to Mohila College GCCR Raod

2.50 1.50

9 Barisal Uzirpur Solok Hat 506945071

Dhamura-Babarkhana- Sholok Hat road

1.80 1.50

10 Barisal Uzirpur Solok Hat 506944044

Solok Hat to North Solok Hazi MA Rashid High School via Solok hat

4.00 2.00

11 Barisal Uzirpur Solok Hat 506945156

Babarkhana to Kangshi Alhaj Adam Ali Madrasha and extended upto Uzirpur -Dhamura road viaTashilder bari and H/O Sajahan Member.

2.50 2.50

12 Barisal Uzirpur Habibpur Hat 506945139 West Keshabkati to Bapary Bari RNGPS

1.50 1.20

13 Barisal Uzirpur Daberkul Hat 506945023

Fakir Hat (H/O Halim Khalifa) to Gazirpar (Surater Bari)

2.00 1.50

14 Barisal Uzirpur Saudi Bazar 506945011

Saudi Bazar to Mozam Sanirbar Khal Via H/O Hazi Answer Uddin Howlader with link road to Mozam Mohammadia Zame Mosque

1.20 1.20

Page 137: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

12

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

15 Barisal Uzirpur Nayakandi

Hat 506945103&108

Nayakandi Bazar to Natherkandi Sluice Gate

3.00 2.00

16 Barisal Banaripara Khalishakota

Hat 506104040

Simultala to Khalishakota Bazar via Khalishakota High School Starting from Madarkati GPS

3.00 1.50

17 Barisal Banaripara Khalishakota

Hat 506105054 & 506105084

Khalishakota Hat to Chakhar UP office via H/O Farid Mohuri and extended upto H/O Matiar Rahman Roypasia

5.00 2.50

18 Barisal Banaripara Khalishakota

Hat 506104006

Khalishakota to Haque Saheber Hat Via Sonahar Dasher Bari.

3.00 2.00

19 Barisal Banaripara Guachitra Cow Hat

506105073

Madarkati to Saliabakpur Road starting from Chakhar- Guachitra RHD at Alhaj Safder Ali Khan to Madarkati GPS

1.50 1.50

20 Barisal Banaripara Guachitra Cow Hat

506105081

Chowaripara (Starting from Guachittra- Banaripara RHD) to

Saliabakpur via H/O Abdul Latif and H/O Mr. Mohabbad.

2.20 1.00

21 Barisal Banaripara Gaba Bazar 506104032 Alta Faizul Haque Bridge to Sunil Sarkar

4.50 1.50

22 Barisal Banaripara Naya Bazar 506105013

Chowlakati Pravatia to Zangalia Primary School (Azad Market to Naya Bazar)

3.00 2.50

23 Barisal Banaripara Naya Bazar 506105085

Nayabazar to west side of Chalitabari GPS (Naya Bazar to Mirere Hat)

1.50 0.50

24 Barisal Banaripara Manik Miar

Hat 506105078

H/O Maola Kazi - Nurul Haque Sarder Dridge- H/O Nazar Ali- Laskarpur

2.00 2.00

25 Barisal Banaripara Auhar Hat 506104024 Digihar Hat to Auhar Hat

3.50 1.50

26 Bhola Lalmohan Harigonj Hat 509545005 Horigonj Road-H/Q Alomgir Chairman-Dipshika School

1.65 1.65

27 Bhola Lalmohan Peshkar Hat 509545152 Farashganj UP road-house of Unus Fakir

1.50 1.50

28 Bhola Lalmohan Patowari Hat 509544020 Degir par-Patoari hat

2.65 2.65

29 Bhola Lalmohan Chatla Bazar 509545053 Mongol Sikder RHD-Chatla Bazar

3.12 2.48

30 Bhola Lalmohan Janata Bazar 509544029

RHD (Muslim Bazar) to Lalmohon-Bhola R&H via Janata Bazar

6.85 3.00

Page 138: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

13

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

31 Bhola Borhanuddin Mainkar Hat 509215168 Mainker hat kikobad road-lakkipur GPS

3.00 0.50

32 Bhola Borhanuddin Darun Bazar 509215056 DC road to wapda via vheri bad via Darga Mosque

1.50 1.00

33 Bhola Borhanuddin Janata Bazar 509214017 Chaire gess ails to kazir hat via abul bazar

2.29 1.00

34 Bhola Borhanuddin Janata Bazar 509215029 RHD near Patowari Bari to Lamchidali Road

2.55 2.50

35 Bhola Borhanuddin Jaoyer Hat 509214015 Jaya bazar wapda road

2.00 1.50

36 Bhola Borhanuddin Jaoyer Hat 509215076 Jaya Santer Hat to Sikder Char

4.25 2.50

37 Bhola Borhanuddin Sikder Hat 509215005 Topgi Khaishabari to RHD

2.50 2.00

38 Bhola Borhanuddin Talukder Hat 509214003 DC road - Majir Shop - Taluker Hat

2.05 2.00

39 Bhola Borhanuddin Sikder Hat 509214010 Kachia-Sikder hat-Kachia co road

2.30 2.00

40 Bhola Charfassion Uttar

Charmanika bazar

509254037

North manika Red crisent Cyclone shelter to Kachhopia Done

1.80 1.80

41 Bhola Charfassion Uttar

Charmanika bazar

509254009 Manika Embankment to Subid Char

6.10 2.20

42 Bhola Charfassion Pangashia

bazar 509254003

Pangashia Bazar to Moulovi Bazar Road

6.00 1.50

43 Bhola Charfassion Daser Hat 509254099 Chairman Hat Road to Madraz Shamraj Via Daser Hat

4.50 3.00

44 Bhola Charfassion Nazirmajhi

Hat 509255012

Ghosher Hat to WAPDA Veri Bundth via Nazirmajhi Hat

2.40 2.40

45 Bhola Charfassion Kukrimukri

Hat 509254046

East side of Kukri Bazar to H/O Elahi Bokshi

2.60 2.60

46 Patuakhali Sador Choto Beghai Officer Hat

578955249 Chottobeghi U.O. to UZR (Hartibaria GPS)

2.00 2.00

47 Patuakhali Sador Tafalbaria

Bazar 578954122

Utter Purbo

Baruanbaria Padhabari Mosque -Tafalbaria Abual Member Bari - Hazikhali Bazer Road.

6.00 3.00

48 Patuakhali Sador Satghar Bazar

578954094 Sathgar bazer to janata H/S

3.00 3.00

49 Patuakhali Kalapara Tegachia Hat 578665149

Utter charpara Abdul Bari khan house-Lamupara wapda (Chapakhali bazar to Tegachia bazar)

4.00 3.00

50 Patuakhali Kalapara Pakhimara

Bazar 578664004

Ghoyatala Launch Ghat to Ghoyatala Sluice Road

7.96 3.00

51 Patuakhali Galachipa Amkhola Hat 578574102 Amkhola U.P.office-Musarikati Sluice

5.20 2.00

Page 139: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

14

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

52 Patuakhali Galachipa Gazalia Hat 578574108 Gazalia hat-Kalaraja Hat.

5.90 3.00

53 Patuakhali Galachipa Bangla Bazar 578574024 Nizamul Chatra-H/O Hashem Shikh

2.75 2.75

54 Patuakhali Rangabali Charbestin

Bazar 578584175

Char Montaz Sluice Bazar - Charbestin Bazar

13.00 3.43

55 Patuakhali Rangabali Horidra Khali

Bazar 578585068

Gohin khali C. Shelter-Horidrakhali

4.57 3.00

56 Patuakhali Mirzaganj Gabua Bazar 578764100

RHD at Gabua Bazer Near the H/O. Pr.A.Rob How to Karam Ali Bridge.

1.00 0.60

57 Patuakhali Mirzaganj Chaita Bazar 578764047 Bazita High School-Shishurhat-Dargabarihat.

2.26 2.26

58 Patuakhali Mirzaganj Kalagachia

Bazar 578764014

Kalagachia Bazar to Kalikapur GPS via H/O Habib Sikder

1.18 1.18

59 Patuakhali Mirzaganj Bhutiar Hat 578764007

Buittarhat-Santespur Reg. P.S-East Rampur Lunchghat Rd.

2.10 2.10

60 Patuakhali Mirzaganj Sisur Hat 578764047 Bagita to Sisur Hat to Dargabari Hat Road

2.26 2.26

61 Barguna Amtoli Munshir hat 504094027 Munshir hat-Chalitabunia G.P.S

4.80 2.50

62 Barguna Amtoli Tepura Bazar 504094030 South Tepura Madrasha -H/O Abdul Rahim mirdha

5.25 2.50

63 Barguna Amtoli Dafadar Hat 504094029 Dulpukuria Bridge to Advocate Awlad Road

6.75 2.00

64 Barguna Amtoli Koroibaria

Bazar 504095312

Koroibaria Bazar to Amtali-Taltali Road via Uttar Jharakhali Nurani madrasha

8.00 2.00

65 Barguna Amtoli Koroibaria

Bazar 504094066

Alibandar Kheyaghat bridge to Bogir Bundth Ghat via Uttar Jharakhali GPS

6.00 2.00

66 Barguna Amtoli Kabirajpara

Hat 504095270

Laupara Burir Khor - Kabirajpara Nidra Road

1.85 1.85

67 Barguna Betagi Mayer Hat 5044096 Mayer Hat-Gourichana

6.00 2.00

68 Barguna Betagi Miar Hat 504474276

Buramajumder UP Office (Miar hat) -Mirzagonj Border via H/O Barek Mirdha -Kazir Hat

1.25 1.25

69 Barguna Betagi DC Hat 504474029 Deshantarkati High School to Christian Para Road

2.00 2.00

70 Barguna Betagi DC Hat 504474033 DC Hat-Mira Bari 2.40 2.00

71 Barguna Betagi Laxmipura

Bazar 504474280

Khontakata-Laxmipura-Akon Bari Bridge

1.75 1.75

Page 140: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

15

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

72 Barguna Betagi MPr Hat 504474249

MPr hat(UP office) to Talgachia GPS to Deshantarkathi Christan Para Church road

4.50 2.50

73 Barguna Betagi Kumrakahali

Hat 504475025

Kumrakhali Bazar to Kapali Bari Uttar

Kazirabad GPS Kazirabad Islamia Dhakhil Madrasha

3.30 2.00

74 Barguna Patherghata Boro Tengra

Bazar 504854007

Tengra Bazar -Baleswar Road

1.10 1.10

75 Barguna Patherghata Badurtala

Bazar 504854011

Charlatimara- Badurtala

2.10 2.10

76 Barguna Patherghata Horidra Khali

Bazar 504855037

Horidrakhali Bazar

to Pathargahta-Kakchira RHD road

1.50 1.50

77 Barguna Patherghata Safilpur Bazar

504854047

Safilpur bazar-Karim Munshi House via Chan Chowkider House

4.75 2.00

78 Barguna Patherghata Safilpur Bazar

504855134 Sofilpu Bazar to Kamarer hat

4.00 3.00

80 Barguna Bamna Gudhigata

Bazar 504194009

Chalavanga -Gudhigata bazar

2.26 2.26

81 Barguna Bamna Sonakhali

Bazar 504195011

Bamna Bukabunia -

Sonakahali Bazar 1.77 1.77

82 Barguna Bamna Ramna Baikalin Bazar

504195001

Khazurarar Khal Bridge- Kholpatua bazar (Road Cum Embankment)

3.97 3.00

83 Barguna Bamna Bukabunia

Bazar 504195020

Bukabunia Bazar - Latabunia High School road

(Muchibari to Singrabunia Mujib Nagar through Halta river bank embankment)

3.30 3.30

84 Perojpur Mothbaria Amtoli Hat 579585057 Amtoli bazar-WAPDA

1.50 1.50

85 Perojpur Mothbaria Jawtala bazar 579584038 Jawtala bazar R&H- house of Fazil Howlader road.

3.29 2.50

86 Perojpur Mothbaria Tearkhali

bazar 579584076

Tearkhali bazar-Bandoppara R&H road.

5.10 3.00

87 Perojpur Mothbaria Boro Masua

Bazar 579584009

Nizamia Bazar - Masua Kheyaghat WAPDA

3.00 2.60

88 Perojpur Mothbaria Boro Masua

Bazar 579584112

Tushkhali - Boro Masua Road - Mothbaria-Boro Masua RHD (Starting from LGED bridge, Dhondoa Khal at North Mithakhali via H/O Hazi Yasin Howlader and Hazi Abdul Hamid Akond)

3.00 3.00

Page 141: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

16

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

89 Perojpur Zianagar Gosher Hat 579884022 Gosherhat bazar -Khajurtola bazar r oad.

5.75 3.00

90 Perojpur Zianagar Chowkider

Hat 579884008

Balipara GC-Chowkider hat Embankment .

3.96 3.00

91 Jhalakati Kathalia Kachua 542434040 Sonarbangla Bazar - Centerer Hat Road

1.80 1.80

92 Jhalakati Kathalia Sonar Bangla

Bazar 542435156

Sonarbangla Bazar to Souljariar Kheyaghat

2.50 2.50

93 Jhalakati Kathalia Kathalia Bazar

542434047

Kathalia UP Office to Chechrirampur Hat via Chnader Hat.

4.33 3.00

94 Madaripur Rajoir Bairagir bazar

354804025 Bairagir bazar-Damer Char Bazar road

4.70 2.50

95 Madaripur Rajoir Bairagir bazar

354804085 Bairagir bazar-Ragdi bazar road

0.20 0.20

96 Madaripur Rajoir Lundi bazar 354804036 Mostofapur pacca road-Charu Boser Dighirpar road

4.00 1.20

97 Madaripur Rajoir Lundi bazar 354805041&

5079

Purbo Lundi Mosque-Pochim Lundi GPS road & Lundi more-Mia bari road

1.60 1.60

98 Madaripur Rajoir Lundi bazar 354805079 Nayanagar to Malek Memorial H/School via Krisnopur Road

2.00 2.00

99 Madaripur Rajoir Lundi bazar 3548054090 Kabirajpur GC to Sreenodi GC road

4.00 2.50

100 Madaripur Rajoir Vandaria

bazar 354805072

Boulgram Baulirkatcha-Macharong GPS via Vandaria bazar road

2.50 1.50

101 Madaripur Rajoir Kodalia

Nutun bazar 354804030

Bharot R&H-Kodalia bazar road

1.50 1.50

102 Madaripur Rajoir Kodalia

Natun bazar 354804092

Kodalia bazar to Chourashi bridge road

2.00 2.00

103 Madaripur Rajoir Lakhanda

bazar 354805081

Lakhanda Bazar to Christopolli Road

2.00 2.00

104 Madaripur Shibchar Mollarhat

bazar 354875317

Banglabazarhat-Mollarhat via J.K GPS & Purankandi GPS road

5.00 2.00

105 Madaripur Shibchar Korokchar

Natun bazar 354875129

UNR-8, House of Tarai Hawlader-UZR-6 House of Anil bala via H/O Anower Khan road

2.15 2.15

106 Madaripur Shibchar Charjanajat Khasherhat

354875095

Charjanajat Khasherhat-Nepaler Kheyaghat road via H/O of Golap Khan

2.50 2.00

107 Madaripur Shibchar Charjanajat Khasherhat

354874027 Charjanajat Khasherhat-Bazlu Sarker's House road

2.50 2.00

Page 142: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

17

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

108 Madaripur Shibchar Kolatola Hat 354875313

Kolatolahat-Lal Chander more via Golam Jahangir RNGPS

3.20 2.00

109 Madaripur Shibchar Karokchar

Natun bazar 354875314

Korokchar natun bazar-Joynagor bazar road

1.45 1.00

110 Madaripur Shibchar Kawer Hat 354875315 Kawerhat to Kabirazpur GC via

Gosaidia

2.00 2.00

111 Madaripur Shibchar Farazir Hat 354874005

UZR-12, near Sheruail Bazar to Surjer, Hat h/o Khaleque Hazi via H/O Habibi Master

3.05 2.00

112 Madaripur Shibchar Saheberbazar (Gostir hat)

354875203

Shariatpur R&H road near the H/O Sarwar Bepari to Mithu Hazirkandi road

1.95 1.00

113 Madaripur Shibchar Garir Hat 354875311 Garirhat-Baburhat via Sonjoy pals bridge

3.00 1.00

114 Sariatpur Janjira Laukhola

Bazar 386945071

Laukhola Bazar-

Bango Bazar road from ch. 0.00m to 5000m.(VR)

5.00 2.00

115 Sariatpur Janjira Taher

Madbar Bazar 386945043

Taher Mathbor hat-Shibchar Border via Hazi Abdul Mozid Reg. Pry.school.

2.00 2.00

116 Sariatpur Janjira Taher

Madbar Bazar 386944029

Taher Madbor hat-UNR 04 road

1.50 1.50

117 Sariatpur Janjira Bodair hat 386944010 Janjira Bilashpur-UZR-Boderhat road

1.52 1.51

118 Sariatpur Janjira Laukhola

Bazar 386945011

Laukhola Bazar to Gopalpur via Khoratola

2.50 2.50

119 Sariatpur Janjira Rupbabur

Hat 386944402

Dubishaheber Hat via Monai Saiyal Kandi

4.00 2.50

120 Sariatpur Naria Nowadda

Bangla Bazar 386655127

Holaishar-Ghorishar UP via Bangla Bazar road from ch. 0.00m to 1750m.(VR)

1.75 1.75

121 Sariatpur Naria Mohishkhola

Bazar 386655133

Mohishkhola Bazar

East side-Naria Battala road from ch. 0.00m to 460m.(VR)

0.46 0.46

122 Sariatpur Naria Mohishkhola

Bazar 386655120

Moroler Baor-Mohiskhola road from ch. 0.00m to 1000m.(VR)

1.00 1.00

123 Sariatpur Naria Mohishkhola

Bazar 386655038

Mohiskhola to Budair Hat road

1.70 1.70

124 Sariatpur Naria Telipara Bazar

386655151 Manda-Golar Bazar road

3.00 1.50

125 Sariatpur Naria Majir Hat 386665026

Nasashan GPS-Akon Kandi road from ch. 0.00m to 2000m.(VR)

2.00 2.00

Page 143: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

18

Sl. No.

Zilla Upazilla Name of

Rural Market Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

126 Sariatpur Naria Joy Bangla

Bazar 386654085

Joy Bangla Bazar-Char Atra UP road

4.00 2.40

127 Sariatpur Naria Joy Bangla

Bazar 386654086

Joy Bangla Bazar-Nowpara road

4.32 2.00

128 Sariatpur Naria Chandipur

Bazar 386655143

Chandipur Bazar-Padma River Bank road

0.45 0.45

129 Gopalgonj Kotalipara Perarbari Hat 335514028 Pirarbari hat-Nabagram UP Road

3.00 2.00

130 Gopalgonj Kotalipara Wapda Hat 335514042 WAPDA hat R&H - Bandabari Bazar Road

3.00 2.00

131 Gopalgonj Kotalipara Narrayan Khanna

Bazar

335515034

Narrayan Khanna Bazar -WAPDA Embankment at Satla Road

3.00 2.00

132 Gopalgonj Kotalipara Wapda Hat 335515030 Bujurgikona Bazar-Baro Dakhinpar via Wapda hat Road

3.00 2.00

133 Gopalgonj Kotalipara Kacharivita

Bazar 335515101

Shibpur kheyaghat to Kacharivita Bazar

2.00 2.00

134 Gopalgonj Kotalipara Kacharivita

Bazar 335514029

Kacharivita Bazar - Kandi Bazar - WAPDA Embankment

2.50 1.50

135 Gopalgonj Tungipara Korfa 335914016 Pakurtia Bazar-Karfa Bazar Road

2.50 2.00

136 Gopalgonj Tungipara Dumuria 335915010 Chhota Dumuria Road

2.00 2.00

137 Bagerhat Sharankhola Khantakata

Hat 201774040

Khontakata-Charerper

3.10 1.50

138 Bagerhat Sharankhola Nalbunia Hat 201774007 Nalbunia-Baniakhali road

6.04 1.50

139 Bagerhat Sharankhola Nalbunia Hat 201774055

Janerpar Engoluddin House to Abdul Latif Akon house road

1.00 1.00

140 Bagerhat Sharankhola Lakurtala 201774022 Jilbunia-Lakurtala road

5.51 1.50

141 Bagerhat Sharankhola Chhutukhar

Hat 201774005

Pallanbari -Khejurbaria road

3.80 1.50

142 Bagerhat Sharankhola Taltaly Hat 2011774047 Taltoly Bazar-Nalbunia (Bezitana) Bazar road

2.85 1.00

143 Bagerhat Sharankhola Chaltabunia 201775047 Chaltabunia-Terabaka-Khuriaskhali road

4.50 2.00

144 Bagerhat Morrelgong Jewdara Hat 201604083

Gulishkhali Bazar to Gorarbazar via Amurbunia Forest Office.

10.34 2.00

145 Bagerhat Morrelgong Boulpur Hat 201605002 Boulpur-Madurkati road.

4.57 2.00

146 Bagerhat Morrelgong Pachgoan Hat 201605023 Panchakaran Bazar to Amurdanga road

2.00 2.00

147 Bagerhat Morrelgong Lakmikhali 201604106

Madrasha Bazar-Dewatala Bazar via H/O Anawer Member

3.50 2.00

148 Bagerhat Morrelgong Madrasha

Hat 201604053

Goalbunia Bazar (at Goalbunia High school)-Joy Bangla Bazar.

7.62 2.00

Page 144: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

19

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

149 Bagerhat Morrelgong Khawlia Hat 201605031

Gabtola Cyclone center-Khawlia bazar via H/O Jobbar Mia road

1.40 1.40

150 Khulna Dacope Banishanta

Bazar 247174028

Khajuria WDB Gora

N/H/O Krishnapada to Dhangmari Biswashnath P/School via Binapani GPS

7.00 2.34

151 Khulna Dacope Pankhali Bazar

247174009 Pankhali Ferry Ghat to Laxmikhola Bazar road

7.45 2.00

152 Khulna Dacope Moukhali

Bazar 247174006

Yasin School near Hoglabunia Khal road

2.00 1.50

153 Khulna Dacope Laxmikhola

Bazar 247175171

Khatail CARE Pucca Road to Khatail near Kali Mondir

2.00 1.00

154 Khulna Batiaghata Titukhali Hat 247124038 Titukhali Hat - Sukdara Hat

4.10 2.00

155 Khulna Batiaghata Baintala Hat 247124018 Baintala Hat - Narayanpur School

2.60 1.00

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

156 Khulna Batiaghata Baintala Hat 247125040 Nijgram -Baintala Hat

1.80 1.80

157 Khulna Batiaghata Dhadua Bazar

247124019 Dhadua Primary School - Joypur Hela Battala

2.60 2.60

158 Khulna Koyra Surikhali 247534070 Hatiardanga Culvert - Patnikhali Foot Bridge

3.90 2.00

159 Khulna Koyra Khorolkati 247534063 Malikhali UZR - Khorolkati Bazar

6.50 1.50

160 Khulna Koyra Zhiligata 247534062 Kashirkhal Bridge - 6No. Koyra Launch Ghat

6.70 2.00

161 Sathkhira Assasuni Kalabagi 287044031 Khashbagan-Sreedharpur-Kharihati Road.

5.92 2.00

162 Sathkhira Assasuni Puijala 287044040 Mohishkur-Puijala via Boudirghat Raod.

9.55 2.00

163 Sathkhira Assasuni Gabtala 287044089 Gabtala-Agordari

Road. 5.47 1.00

164 Sathkhira Assasuni Madham Chapra

287044115

Mahsharkati-Baushuli via Baddach Chapra Road.

2.00 2.00

165 Sathkhira Assasuni Paitholi 287044054 Sweetpur Pry. School-Gazirhat Road.

5.56 1.00

166 Sathkhira Assasuni Bisot 287044141

Manikkhali Ferryghat-Kallyanpur-Khayaghat Road.

3.20 1.00

167 Sathkhira Assasuni Madham Chapra

287044150 Chapra R&H-Maddhan Chapra Kheyaghat Raod.

4.00 1.00

Page 145: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

20

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

168 Sathkhira Assasuni Basukhali 287044116 Baliapur more-Basukhali Road.

2.70 1.00

169 Sathkhira Shyamnagar Munshiganj 287864062 Munshiganj Bazar-Garrage Hat Bridge Road.

5.00 2.50

170 Sathkhira Shyamnagar Chaltaghata

Hat 287864001

Chaltaghata-Bhurulia

2.40 1.00

171 Sathkhira Shyamnagar Verar Hat 287865051 Mindi Nagar - Kalindi

5.50 2.50

172 Sathkhira Shyamnagar Nildumur Hat 287864024 Nildumur-Porakatla GPS

3.10 2.50

173 Sathkhira Shyamnagar Patakhali 287865112 Patakhali WDB-Sardar Bari Road.

1.25 1.25

174 Sathkhira Kaligonj Gorrer Hat 287475201 Gorrerht - Probajpur Road

3.00 1.00

175 Sathkhira Kaligonj Jerrongacha

Hat 287475241

Jherrongacha-Charapattala-Moutala-Uvakur Road

3.50 2.50

176 Sathkhira Kaligonj Tarail 287474017 East Trali UZR - Kashibati GPS Road

3.30 2.00

177 Sathkhira Kaligonj Tarail 287475276 Jafourpur - Tetulia Via Nonamath Road

3.00 1.00

178 Sathkhira Kaligonj Sannasir

Chalk Bazar 287474038

Kazla LGED road - Sannasir Chalk Bazar Road

6.10 2.50

179 Sathkhira Kaligonj Moutala 287475256 Zhurukhamar H/Q.-Sontosh Dr. House Road.

2.50 1.00

Sl. No.

Zilla Upazilla Name of

Rural Market

Road ID Road Name

Total Length Road (Km)

Proposed Length Road (Km)

180 Sathkhira Kaligonj Kakshiali

Bazar 287474020

Bagbati GPS to Shuilpur BGP road

1.65 1.65

Total: 603.90 341.00

Page 146: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

21

D. Selected location for ghat

Coastal Climate Resilient Infrastructure Project (CCRIP)

Ghats Improvements Subprojects

Sl. No.

District Upazila Union Name of the Ghat Name of the Connecting

Market

1 Barisal Babugong Dehergati Uttar Baherchar Uttar Baherchar

2 Barisal Uzirpur Otra Gala Ghat Jugirkanda (Gala) Bazar

3 Barisal Uzirpur Gutia Gutia Hat Gutia Hat

4 Barisal Uzirpur Bamrail Ghonteswar Bazar Ghonteswar Bazar

5 Barisal Banaripara Chakhar Nayabazar Nayabazar

6 Barisal Banaripara Chakhar Khalishakota Hat Khalishakota Hat

7 Bhola Charfassion Muzibnagar Char Lulin Bangla Bazar ghat

Char Lulin Bangla Bazar ghat

8 Patuakhali Sador Borobighai Moddho Titkata Bazar Ghat

Moddho Titkata

9 Patuakhali Kalapara Lalua Muktijoddha Hat

Ghat Muktijoddha Hat

10 Patuakhali Galachipa Amkhola Amkhola Hat Ghat Amkhola Hat

11 Patuakhali Rangabali Choto Baisdia Gohinkhali Bazar Ghat

Gohinkhali Bazar

12 Patuakhali Mirzaganj Madhabkhali Chaita Bazar Ghat Chaita Bazar

13 Barguna Amtali (Taltali) Nishanbaria Fakir Hat Fakir Hat

14 Barguna Patharghata Nachnapara Nachnapara Nachnapara

15 Barguna Betagi Hosnabad Kabilaknad

Bundthghat Bazar

Kabilaknad Bundthghat

Bazar

16 Barguna Bamna Ramna Kholpatua Bazar Ramna Baikalin Bazar

17 Perojpur Mothbaria Mirukhali Vagirathpur Ghat Vagirathpur Bazar

18 Perojpur Mothbaria Boro Masua Boro Masua Khal Boro Masua Bazar

19 Perojpur Zianagar Parerhat Luhuri Hat Ghat Luhuri Hat

20 Perojpur Zianagar Balipara Chandipur Bazar Ghat

Chandipur Bazar

21 Jhalokati Kathalia Patikelghata Ghoser Hat Ghoser Hat

22 Jhalokati Kathalia Kathalia Kathalia Bazar Kathalia Bazar

23 Madaripur Rajoir Badorpasha Sankardirpar bazar Ghat

Takerhat Sankardirpar

24 Madaripur Shibchar Vadrason Chrok Natun Char Hat

Chrok Natun Char hat

25 Sariatpur Janjira Mulna Laukhola ghat Laukhola Bazar

26 Sariatpur Naria Ghorishar Bangla Bazar River Bank ghat

Nowadda Bangla Bazar

27 Sariatpur Naria Char Atra Char Atra River

Nank ghat Char Atra Bazar

28 Gopalgonj Tungipara Gopalpur Gopalpur Hat Ghat Gopalpur Hat

29 Gopalgonj Tungipara Dumuria Dumuria Bazar Ghat

Dumuria Bazar

30 Gopalgonj Kotalipara Pirarbari Hat Pirarbari Hat

31 Bagerhat Sharankhola Khantakata Khantakata Khantakata

32 Bagerhat Morrelgonj Baharbunia S.B. Bazar S.B. Bazar

33 Bagerhat Morrelgonj Nishanbaria Jewadhara Hat Jewadhara Hat

Page 147: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

22

Sl. No.

District Upazila Union Name of the Ghat Name of the Connecting

Market

34 Khulna Dacope Banisanta Banisanta Bazar Banisanta Bazar

35 Khulna Koyra Moharajpur Suti Bazar Suti Bazar

36 Sathkhira Assasuni Anulia Bisot Bisot Market

37 Sathkhira Assasuni Budhata Maddham Chapra Maddham Chapra Market

38 Sathkhira Shyamnagar Burigoalini Nildumur Nildumur Bazar

D. Selected Community Collection Points

Coastal Climate Resilient Infrastructure Project (CCRIP)

Selected Community Collection Points

Sl. No.

District Upazila Union Name of the Collection

Point Main Commodities

1 Barisal Banaripara Banaripara Jambo Dip Sand,Timber, Poultry, Nursary

Seedlings

2 Bhola Charfassion Zinnagar Chakbazar Rice, Rabi crops , Vegetables

3 Patuakhali Rangabali Choto Baisdia Koralia Fish, Rice, Water Melon

4 Barguna Patharghata Patharghata

Sadar Patharghata

BFDC Hilsha and Sea Fish

5 Sathkhira Assasuni Budhata Mohiswar Kati Fish

Page 148: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

23

E. Second priority list of village road, CCPs and ghat

List of VR (second priority)

District Upazila market Road ID name Total lenngth

proposed length for constrcution

Bhola Lalmohan Kalirpak Bazar

509545206 Chowmohani Bazar to Kalirpack bazar (Romagonj)

3.5 2.5

Bhola Lalmohan Kalirpak Bazar

509545061 Lalmohan UP Office to Kalirpack Bazar

1.05 1.05

Bhola Lalmohan Chad Miar Hat 505945022 Madrasha Bazar Road to Veribundth Road

4.5 3.5

Bhola Borhanuddin Dolan Hat

509215058 DC road to Arindabari 2.2 2.2

Bhola Borhanuddin Mollar Hat

509215030 Nannu Bakli Bari to Banglabazar Road

3.1 3.1

Barguna Amtoli

Azimpur Bazar

504094053

Kukua UP office to Kukua hat via Sugandhi Sluice Gate Road

5.00 5.00

Barguna Patherghata

Karamatpur Bazar 504854031

Singrabunia Robin Master Shop to Karamatpur Bazar

3.40 3.40

Naria Andarmanik Bazar

386655157 Andarmanik-Thakur Kandi road from ch. 0.00m to 3000m.(VR)

3.00 2.50

Dacope Batbunia GC 2471774010

Batbunia GC - Laxmikhola Bazar via Kacharibari

6.60 1.00

Sathkhira Shyamnagar Noabenki 287864033 Noabenki Bazar-Saffurannesa H/S Road.

1.50 1.50

Sathkhira Shyamnagar Noabenki 287864060 Biralaxmi Madrasa-Jhapa WAPDA Road

2.00 2.00

Sathkhira Kaligonj Nalta 287474020 Bagbati GPS - Shuilpur BGP Road.

1.65 1.00

Sathkhira Kaligonj Nalta 287475003 Nalta Girls School - Nalta College Road.

1.50 1.00

barguna betagi Mollar Hat 504474282 khaner hat rhd to kathaltali madrasha via h/o sujan chairman

4.10 4.10

Shariatpur Janjira Banga Bazar 386943009 Joynagar Hat to Banga Bazar via Gopalpur Launch Ghat

Rpad

7.78 2.00

Shariatpur Naria Andarmanik Bazar

386653015 Andarmanik-Budairhat road from ch. 0.00m to 1600m.(UNR)

2.85 2.00

Gopalgonj Kotalipara Ramshil Bazar

335513010 Ramshil UP-Batra bazar road

2.8 2

Sathkhira Kaligonj Nalta GC 287473009 Nalta UP-Khanzia Bazar via Ghorapota UNR Road.

0.00 2.00

Barisal

Uzirpur Solok Hat 506945074

Jugihati Chowkder Bari Mosque to Damader Kati Trimukhi Road via Atak

4 1.00

Gopalgonj Kotalipara Chowdhory Hat

335514053 Pijuri School to Gopalpur Sluice gate

2.80 3.00

Page 149: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

24

Patuakhali Mirzaganj

Chaita Bazar

578764021 New market HRS-Shishurhat-dargabari hat Rd.

3.85 3.00

List of Ghat

2 Barisal Babugong Chadpasa Post Office Ghat Post Office Ghat

12 Barisal Banaripara Chakhar Haque Shaheber Hat Kahlishakota Hat

13 Patuakhali Rangabali Char Montaz

Sluice Bazar Ghat Sluice Bazar

23 Perojpur Mothbaria Amragachia Baleshwer River Ghat Gulbunia Hat

30 Jhalokati Kathalia Kathalia Amribunia Ghat Kathalia Bazar

33 Sariatpur Janjira Borokandi Kazirhat Kazirhat

GCM

36 Gopalgonj Kotalipara Ramshil Ramshil Ramshil Bazar

37 Gopalgonj Kotalipara Bandhabari Bandhabari Bandhabari GC

38 Gopalgonj Kotalipara Kolabari Kaligonj Kaligonj GC

48 Khulna Batiaghata Baliadanga Bujbunia Birat

53 Sathkhira Shyamnagar Gabura Gabura Gabura Bazar

2 Barisal Babugong Steamer Ghat Bazar Steamer Ghat Bazar

4 Barisal Uzirpur Otra Habibpur Bazar Ghat Habibipur Bazar

5 Barisal Uzirpur Borakota Daberkool Hat Daberkool Hat

7 Barisal Uzirpur Solok Solok Hat Solok Hat

9 Barisal Banaripara Iluhar Janata Bazar Janata Bazar

10 Barisal Banaripara Banaripara Gava Hat Gava Hat

11 Barisal Banaripara Udaykati Sher-e-bangla Hat Sher-e-bangla Hat

12 Barisal Banaripara Chakhar Haque Shaheber Hat Kahlishakota Hat

15 Barguna Betagi Bibichini DC Hat DC Hat

21 Barguna

Amtali

Kukua Amragachia Bazar Amragachia Bazar

23 Barguna Patharghata Patharghata Sadar

Tengra bazar Tengra bazar

27 Barguna Bamna Bukabunia Bukabunia Bukabunia

34 Jhalokati Kathalia Souljalia Centerer Hat Kachua

37 Gopalgonj Tungipara Borni Borni Hat Ghat Borni Hat

39 Bagerhat Sharankhola Southkhali Chaltabunia Hat Chaltabunia Hat

42 Bagerhat Morrelgonj Jewadhara Mdrasha Hat Mdrasha Hat

Collection Point

1 Barisal Babugong Rahamatpur

Rahamatput Rice, Jute, Rabi crops , Vegetables

2 Barisal Uzirpur

Otra

Habibpur Hat Fish, Rice , Fruits

Page 150: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7

25

Barisal Banaripara Chakhar Chakhar Bus Stand Timber & Agricultural Produce

3 Bhola Lalmohan Dhaligaournagar

Kamarer Khal ghat Rice, Rabi crops , Fish, Vegetable

4 Bhola Lalmohan Dhaligaour

nagar

Batir Khal ghat Rice, Rabi

crops , Fish, Vegetable

7 Patuakhali Rangabali Char Montaz

Char Montaz Sluice Fish, Rice, Water Melon

8 Patuakhali Rangabali Boro Baisdia

Moudubi Nichkata bazar

Fish, Rice, Water Melon

9 Barguna Amtali Amtali Sadar

Bandra Rice, Rabi crops , Water Melon

10 Barguna Amtali Holdia Sugandhi Water Melon, Rice, Rabi crops

12 Jhalokati Kathalia Kathalia Kathalia Rice, Jute, Rabi crops , Vegetables

13 Jhalokati Kathalia

Souljalai

Kachua Bazar Fish, Rice , Fruits

14 Gopalgonj Kotalipara Kalabari Khejurbari

Fish & Water mellon

15 Gopalgonj Tungipara Gopalpur Mittrodanga Fish

16 Bagerhat Sharankhola Khantakata Bhandhagata Paddy, Fish.

17 Bagerhat Sharankhola Dhansagar Pollimongal Vegetables, Paddy and Fish.

19 Sathkhira Shyamnagar Bhurulia Khanpur Paddy, Fish, Vegetables

Page 151: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 152: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7A

Annex 7A

Project Costs and Financing

Page 153: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 154: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7A

1

Annex 7A

Project Costs and Financing

I. Main Assumptions

1. Introduction. This section describes the assumptions underlying the derivation of project costs, estimated programme costs and financing plan. Project costs were updated at the final design stage in October 2012, following the merging of the Sustainable Market Infrastructure for Livelihoods Enhancement (SMILE) with the Climate Resilient Infrastructure Improvement in

Coastal Zone Project (CRIICZP). 2. Project Period. The proposed project would be financed over a six-year period beginning in July 2013. 3. Inflation. Consolidating the strong recovery that emerged in fiscal year 2010 and

benefiting from external demand that remained favourable, the Bangladesh economy is forecast to

remain on a sustainable growth path, expanding by an average of 6.3 percent a year in fiscal years 2011-16. The increasing trend in annual average inflation started from November 2009 continued till the end of fiscal year 2011. The Bangladesh Bank has been taking measures to reduce inflationary pressure and is expecting to keep the inflation target at 7.5 percent in fiscal year 2012-13. The base rate of inflation has been set at 7.5 percent for the project period. For international foreign inflation, an annual average of 0.5 percent was applied.

4. Exchange Rate. Since the removal of its currency peg against the US dollar in May 2003, the Taka has been depreciating gradually reaching Taka 82 BDT to USD 1.00 in 2012. The base exchange rate for this analysis has been set at Taka 82 to USD 1.00. 5. Price and Physical Contingencies. Price contingencies are calculated on the basis of estimated inflation rates and applied depending on the estimated percentage of local versus

foreign currency element of each cost item. Price contingencies using the inflation parameters

described above have been applied to most goods and services that would be procured under the project. A physical contingency rate of 10% has been assumed for civil works and a rate of 5% for a limited portion of project costs in particular vehicles, equipment, trainings, workshops and studies; no physical contingencies were applied to TA costs as they have been estimated with reasonable certainty.

6. Taxes and Duties. The estimate of taxes and duties was based on the rates in effect at the time of project design in conformity with the principle that no taxes or duties would be financed out of the proceeds of the IFAD loan. In line with the practice of externally financed projects in Bangladesh, the government would finance identifiable taxes and duties.

7. Basis for Cost Estimates. Project costs are estimated as of October 2012 prices. Estimates for vehicles, equipment, salaries, local technical assistance, DSA, operation and

maintenance were based on recent data provided by LGED. The costs of the IFAD-funded activities were estimated by the IFAD team using revised LGED rate schedule. The costs of the ADB- and KfW-funded activities were finalized and presented during a joint fact-finding mission of ADB, IFAD

and KfW in June 2012. Both teams used the same technical assumptions in the cost estimations of their respective activities: number of project years, physical contingencies, exchange rate and inflation rates. The costs of union and village roads were estimated on the basis of ―B‖ and ―C‖

scenarios; the ―C‖ scenario applies only on the areas outside polders; village roads are all estimated on the basis of scenario ―B‖. During the final design mission carried out by IFAD, the IFAD-funded activities were updated in order to keep consistency between unit costs and to avoid duplication of the project activities. 8. Expenditure Accounts. Almost all items procured under the project will be purchased locally. The foreign exchange allowance reflects the fact that vehicles, equipment and office

supplies would be imported into Bangladesh. 9. Programme Structure. The project has three components, as follows: (i) Improved Road Connectivity; (ii) Improved Market Services; (iii) Enhanced Climate Change Adaptation Capacity and Project Management.

Page 155: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7A

2

II. Project Costs

10. The total investment and incremental recurrent project costs, including physical and price contingencies, is estimated at USD 150.0 million (BDT 14,664.0 million). Table 1 below presents the project costs by components, while the other summary tables and detailed cost tables are found in Appendices 1 and 2 to this Annex.

Table 1: Components Project Cost Summary

% % Total

(BDT Million) (US$ Million) Foreign Base

Local Foreign Total Local Foreign Total Exchange Costs

A. Improved Road Connectivity

1. Upgraded Upazila Roads 2,314.1 257.1 2,571.2 28.2 3.1 31.4 10 23

2. Upgraded Union and Village Roads 4,122.0 458.0 4,580.0 50.3 5.6 55.9 10 42

Subtotal 6,436.1 715.1 7,151.2 78.5 8.7 87.2 10 65

B. Improved Market Services

1. Upgraded Grow th Centers and Large Markets 748.6 83.2 831.8 9.1 1.0 10.1 10 8

2. Upgraded Community Markets 558.0 62.0 620.0 6.8 0.8 7.6 10 6

Subtotal 1,306.6 145.2 1,451.8 15.9 1.8 17.7 10 13

C. Enhanced Climate Change Adaptation Capacity

1. Enhanced Capacity and Know ledge Management 193.2 21.5 214.7 2.4 0.3 2.6 10 2

2. Upgraded Climate Disaster Shelters 582.9 64.8 647.7 7.1 0.8 7.9 10 6

Subtotal 776.2 86.2 862.4 9.5 1.1 10.5 10 8

D. Project Management 1,194.6 369.9 1,564.5 14.6 4.5 19.1 24 14

Total BASELINE COSTS 9,713.5 1,316.4 11,029.9 118.5 16.1 134.5 12 100

Physical Contingencies 873.1 95.5 968.6 10.6 1.2 11.8 10 9

Price Contingencies 2,177.3 270.6 2,447.9 1.4 0.2 1.6 11 1

Total PROJECT COSTS 12,763.9 1,682.6 14,446.4 130.5 17.4 147.9 12 110

Interest During Implementation - 205.0 205.0 - 2.2 2.2 100 2

Total Costs to be Financed 12,763.9 1,887.6 14,651.5 130.5 19.6 150.0 13 112

III. FINANCING

11. The CCRIP is estimated to have an overall cost of US$ 150.0 million (total investment and incremental recurrent project costs including physical and price contingencies), of which ADB will be financing US$ 20 million through ADB‘s Special Funds resource (loan), another US$20 million through ADB Strategic Climate Fund loan and a US$10 million grant, both to be administered by ADB. For the outputs proposed to be financed in parallel by KfW, KfW will provide a grant of

€7.157 million (US$ 8.8 million). The Government of Bangladesh will provide US$31.2 million equivalent, including LGED staff salaries and operating costs, land acquisition and resettlement

costs as well as identifiable taxes and duties as no taxes or duties could be financed out of the proceeds of the IFAD loan. 12. IFAD financing. For the project activities proposed by IFAD, IFAD will provide two loans equivalent to US$59.0 million and a grant equivalent to US$1.0 million. IFAD first loan of approximately USD 40 million will be allocated in its three-year PBAS cycle of 2013-15. This has

already been notified to ERD. From PBAS cycle of 2016-2018, IFAD will provide an additional USD 20 million loan. IFAD grant will finance: a) rural radio program and knowledge management, b) baseline survey, c) several impact studies, d) RIMS studies, e) mid-term review and project closing report mission, and f) design of MAPP project.

13. Table 2 below provides a summary by project components of the proposed financing arrangement.

Page 156: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7A

3

Table 2: Financing Plan by Components (US$ Million)

ADB SCF Loan SCF Grant IFAD First Loan IFAD Second Loan IFAD Grant KfW The Government Total

Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount %

A. Improved Road Connectivity

1. Upgraded Upazila Roads 15.1 43.2 13.5 38.7 - - - - - - - - - - 6.3 18.1 34.9 23.3

2. Upgraded Union and Village Roads - - - - - - 32.8 52.9 17.5 28.2 - - - - 11.8 18.9 62.1 41.4

Subtotal 15.1 15.5 13.5 13.9 - - 32.8 33.8 17.5 18.1 - - - - 18.1 18.6 97.0 64.7

B. Improved Market Services

1. Upgraded Grow th Centers and Large Markets 4.3 38.4 4.9 43.3 - - - - - - - - - - 2.1 18.3 11.2 7.5

2. Upgraded Community Markets - - - - - - 5.5 65.6 1.5 17.4 - - - - 1.4 17.0 8.4 5.6

Subtotal 4.3 22.0 4.9 24.8 - - 5.5 28.0 1.5 7.4 - - - - 3.5 17.7 19.6 13.1

C. Enhanced Climate Change Adaptation Capacity

1. Enhanced Capacity and Know ledge Management - - - - 0.8 31.1 0.3 10.8 0.1 1.9 1.0 37.1 0.3 9.6 0.3 9.4 2.7 1.8

2. Upgraded Climate Disaster Shelters - - - - - - - - - - - - 7.3 82.8 1.5 17.2 8.8 5.8

Subtotal - - - - 0.8 7.4 0.3 2.6 0.1 0.4 1.0 8.8 7.5 65.5 1.8 15.3 11.5 7.7

D. Project Management - - 1.6 7.9 9.1 46.2 0.9 4.4 0.4 2.3 - - 1.3 6.6 6.4 32.6 19.7 13.2

Total PROJECT COSTS 19.4 13.1 19.9 13.5 10.0 6.7 39.5 26.7 19.5 13.2 1.0 0.7 8.8 6.0 29.8 20.1 147.9 98.6

Interest During Implementation 0.6 28.7 0.1 3.2 - - - - - - - - - - 1.5 68.0 2.2 1.4

Total Disbursement 20.0 13.3 20.0 13.3 10.0 6.6 39.5 26.3 19.5 13.0 1.0 0.7 8.8 5.9 31.2 20.8 150.0 100.0

Page 157: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 158: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

Summary Cost Tables

1. Components Project Cost Summary

2. Expenditure Accounts Project Cost Summary

3. Expenditure Accounts by Components – Totals Including Contingencies

4. Project Components by Year – Totals Including Contingencies

5. Expenditure Accounts by Year – Totals Including Contingencies

6. Components by Financiers

7. Disbursement Accounts by Financiers

8. Expenditure Accounts by Financiers

Page 159: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 160: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

1

Summary Cost Tables

Table 1: Components Project Cost Summary

% % Total

(BDT Million) (US$ Million) Foreign Base

Local Foreign Total Local Foreign Total Exchange Costs

A. Improved Road Connectivity

1. Upgraded Upazila Roads 2,314.1 257.1 2,571.2 28.2 3.1 31.4 10 23

2. Upgraded Union and Village Roads 4,122.0 458.0 4,580.0 50.3 5.6 55.9 10 42

Subtotal 6,436.1 715.1 7,151.2 78.5 8.7 87.2 10 65

B. Improved Market Services

1. Upgraded Grow th Centers and Large Markets 748.6 83.2 831.8 9.1 1.0 10.1 10 8

2. Upgraded Community Markets 558.0 62.0 620.0 6.8 0.8 7.6 10 6

Subtotal 1,306.6 145.2 1,451.8 15.9 1.8 17.7 10 13

C. Enhanced Climate Change Adaptation Capacity

1. Enhanced Capacity and Know ledge Management 193.2 21.5 214.7 2.4 0.3 2.6 10 2

2. Upgraded Climate Disaster Shelters 582.9 64.8 647.7 7.1 0.8 7.9 10 6

Subtotal 776.2 86.2 862.4 9.5 1.1 10.5 10 8

D. Project Management 1,194.6 369.9 1,564.5 14.6 4.5 19.1 24 14

Total BASELINE COSTS 9,713.5 1,316.4 11,029.9 118.5 16.1 134.5 12 100

Physical Contingencies 873.1 95.5 968.6 10.6 1.2 11.8 10 9

Price Contingencies 2,177.3 270.6 2,447.9 1.4 0.2 1.6 11 1

Total PROJECT COSTS 12,763.9 1,682.6 14,446.4 130.5 17.4 147.9 12 110

Interest During Implementation - 205.0 205.0 - 2.2 2.2 100 2

Total Costs to be Financed 12,763.9 1,887.6 14,651.5 130.5 19.6 150.0 13 112

Page 161: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

2

Table 2: Expenditure Accounts Project Cost Summary

% % Total

(BDT Million) (US$ Million) Foreign Base

Local Foreign Total Local Foreign Total Exchange Costs

I. Investment Costs

A. Civil Works

Upazila Roads 2,229.3 247.7 2,477.0 27.2 3.0 30.2 10 22

Union, Village and Block Roads 3,933.9 437.1 4,371.0 48.0 5.3 53.3 10 40

Grow th Centers and Large Markets 720.0 80.0 800.0 8.8 1.0 9.8 10 7

Village Markets and Collection Points 507.4 56.4 563.8 6.2 0.7 6.9 10 5

Landing Stages (Ghats) 37.6 4.2 41.8 0.5 0.1 0.5 10 -

Climate Disaster Shelters 568.1 63.1 631.3 6.9 0.8 7.7 10 6

Subtotal 7,996.4 888.5 8,884.9 97.5 10.8 108.4 10 81

B. Vehicles & Equipment

Vehicles 35.8 66.5 102.4 0.4 0.8 1.2 65 1

Field Equipment 46.9 31.3 78.2 0.6 0.4 1.0 40 1

Office Equipment 11.6 7.7 19.4 0.1 0.1 0.2 40 -

Subtotal 94.3 105.5 199.9 1.2 1.3 2.4 53 2

C. Consulting Services

International - 246.6 246.6 - 3.0 3.0 100 2

National 439.8 - 439.8 5.4 - 5.4 - 4

Support Staff 153.5 - 153.5 1.9 - 1.9 - 1

Equipment, Surveys and Operating Expenses 95.6 10.6 106.3 1.2 0.1 1.3 10 1

Subtotal 688.9 257.2 946.1 8.4 3.1 11.5 27 9

D. Training, Workshop, Studies 256.4 28.5 284.9 3.1 0.3 3.5 10 3

E. Land Acquisition 220.5 - 220.5 2.7 - 2.7 - 2

F. LGED Staff and Operating Costs - - - - - - - -

Total Investment Costs 9,256.5 1,279.7 10,536.2 112.9 15.6 128.5 12 96

II. Recurrent Costs

A. Infrastructure Maintenance

Roads 272.9 30.3 303.2 3.3 0.4 3.7 10 3

Markets 43.0 4.8 47.8 0.5 0.1 0.6 10 -

Climate Disaster Shelters 14.8 1.6 16.4 0.2 0.0 0.2 10 -

Subtotal 330.7 36.7 367.4 4.0 0.4 4.5 10 3

B. Salaries and allow ances 108.0 - 108.0 1.3 - 1.3 - 1

C. Vehicles operation and maintenance 18.3 - 18.3 0.2 - 0.2 - -

Total Recurrent Costs 457.0 36.7 493.7 5.6 0.4 6.0 7 4

Total BASELINE COSTS 9,713.5 1,316.4 11,029.9 118.5 16.1 134.5 12 100

Physical Contingencies 873.1 95.5 968.6 10.6 1.2 11.8 10 9

Price Contingencies 2,177.3 270.6 2,447.9 1.4 0.2 1.6 11 1

Total PROJECT COSTS 12,763.9 1,682.6 14,446.4 130.5 17.4 147.9 12 110

Interest During Implementation - 205.0 205.0 - 2.2 2.2 100 2

Total Costs to be Financed 12,763.9 1,887.6 14,651.5 130.5 19.6 150.0 13 112

Page 162: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

3

Table 3: Expenditure Accounts by Components – Totals Including Contingencies (US$ Million)

Improved Market Enhanced Climate

Improved Road Services Change Adaptation

Connectivity Upgraded Capacity

Upgraded Growth Enhanced

Union Centers Capacity Upgraded

Upgraded and and Upgraded and Climate

Upazila Village Large CommunityKnowledge Disaster Project

Roads Roads Markets Markets ManagementShelters Management Total

I. Investment Costs

A. Civil Works

Upazila Roads 33.6 - - - - - - 33.6

Union, Village and Block Roads - 59.3 - - - - - 59.3

Grow th Centers and Large Markets - - 10.8 - - - - 10.8

Village Markets and Collection Points - - - 7.6 - - - 7.6

Landing Stages (Ghats) - - - 0.6 - - - 0.6

Climate Disaster Shelters - - - - - 8.5 - 8.5

Subtotal 33.6 59.3 10.8 8.2 - 8.5 - 120.4

B. Vehicles & Equipment

Vehicles - - - - - - 1.3 1.3

Field Equipment - - - - - - 1.0 1.0

Office Equipment - - - - - - 0.2 0.2

Subtotal - - - - - - 2.5 2.5

C. Consulting Services

International - - - - - - 3.0 3.0

National - - - - - - 5.4 5.4

Support Staff - - - - - - 1.9 1.9

Equipment, Surveys and Operating Expenses - - - - - - 1.3 1.3

Subtotal - - - - - - 11.7 11.7

D. Training, Workshop, Studies - - - - 2.7 - 0.9 3.6

E. Land Acquisition - - - - - - 3.0 3.0

F. LGED Staff and Operating Costs - - - - - - - -

Total Investment Costs 33.6 59.3 10.8 8.2 2.7 8.5 18.1 141.2

II. Recurrent Costs

A. Infrastructure Maintenance

Roads 1.3 2.9 - - - - - 4.2

Markets - - 0.4 0.2 0.0 - - 0.7

Climate Disaster Shelters - - - - - 0.2 - 0.2

Subtotal 1.3 2.9 0.4 0.2 0.0 0.2 - 5.0

B. Salaries and allow ances - - - - - - 1.4 1.4

C. Vehicles operation and maintenance - - - - - - 0.2 0.2

Total Recurrent Costs 1.3 2.9 0.4 0.2 0.0 0.2 1.6 6.7

Total PROJECT COSTS 34.9 62.1 11.2 8.4 2.7 8.8 19.7 147.9

Page 163: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

4

Table 4: Project Components by Year – Totals Including Contingencies (US$ Million)

Totals Including Contingencies

2013 2014 2015 2016 2017 2018 Total

A. Improved Road Connectivity

1. Upgraded Upazila Roads 3.0 5.7 10.6 9.9 4.9 0.9 34.9

2. Upgraded Union and Village Roads 5.9 11.8 21.0 18.3 3.7 1.3 62.1

Subtotal 9.0 17.5 31.6 28.2 8.6 2.1 97.0

B. Improved Market Services

1. Upgraded Grow th Centers and Large Markets 1.7 3.7 5.5 0.1 0.1 0.1 11.2

2. Upgraded Community Markets 1.6 2.4 2.5 1.8 0.1 0.1 8.4

Subtotal 3.3 6.2 7.9 1.9 0.2 0.2 19.6

C. Enhanced Climate Change Adaptation Capacity

1. Enhanced Capacity and Know ledge Management 1.3 0.6 0.4 0.3 0.1 0.1 2.7

2. Upgraded Climate Disaster Shelters - 4.1 2.4 1.5 0.6 0.1 8.8

Subtotal 1.3 4.7 2.9 1.8 0.7 0.1 11.5

D. Project Management 5.0 3.6 3.7 3.6 2.9 1.0 19.7

Total PROJECT COSTS 18.5 31.9 46.1 35.5 12.3 3.5 147.9

Page 164: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

5

Table 5: Expenditure Accounts by Year – Totals Including Contingencies (US$ Million) 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Civil Works

Upazila Roads 3.0 5.7 10.5 9.6 4.8 - 33.6

Union, Village and Block Roads 5.9 11.8 20.9 17.8 2.8 - 59.3

Grow th Centers and Large Markets 1.7 3.7 5.4 - - - 10.8

Village Markets and Collection Points 1.5 2.3 2.3 1.6 - - 7.6

Landing Stages (Ghats) 0.1 0.1 0.1 0.1 - - 0.6

Climate Disaster Shelters - 4.1 2.4 1.5 0.6 - 8.5

Subtotal 12.3 27.8 41.6 30.6 8.2 - 120.4

B. Vehicles & Equipment

Vehicles 1.3 - - - - - 1.3

Field Equipment 1.0 - - - - - 1.0

Office Equipment 0.2 - - - - - 0.2

Subtotal 2.5 - - - - - 2.5

C. Consulting Services

International 0.5 0.7 0.7 0.6 0.4 0.1 3.0

National 0.5 1.2 1.2 1.2 1.0 0.3 5.4

Support Staff 0.3 0.3 0.3 0.4 0.3 0.2 1.9

Equipment, Surveys and Operating Expenses 0.2 0.3 0.3 0.3 0.1 0.0 1.3

Subtotal 1.6 2.6 2.5 2.4 1.9 0.6 11.7

D. Training, Workshop, Studies 1.7 0.7 0.5 0.4 0.2 0.1 3.6

E. Land Acquisition 0.3 0.5 0.7 0.7 0.5 0.1 3.0

F. LGED Staff and Operating Costs - - - - - - -

Total Investment Costs 18.3 31.6 45.4 34.2 10.9 0.9 141.2

II. Recurrent Costs

A. Infrastructure Maintenance

Roads - - 0.3 0.8 0.9 2.1 4.2

Markets 0.0 0.0 0.1 0.2 0.2 0.2 0.7

Climate Disaster Shelters - - 0.0 0.1 0.1 0.1 0.2

Subtotal 0.0 0.0 0.4 1.0 1.2 2.4 5.0

B. Salaries and allow ances 0.2 0.3 0.3 0.3 0.3 0.2 1.4

C. Vehicles operation and maintenance 0.0 0.0 0.0 0.0 0.0 0.0 0.2

Total Recurrent Costs 0.3 0.3 0.7 1.3 1.5 2.6 6.7

Total PROJECT COSTS 18.5 31.9 46.1 35.5 12.3 3.5 147.9

Page 165: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

6

Table 6: Components by Financiers (US$ Million)

ADB SCF Loan SCF Grant IFAD First Loan IFAD Second Loan IFAD Grant KfW The Government Total

Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount %

A. Improved Road Connectivity

1. Upgraded Upazila Roads 15.1 43.2 13.5 38.7 - - - - - - - - - - 6.3 18.1 34.9 23.3

2. Upgraded Union and Village Roads - - - - - - 32.8 52.9 17.5 28.2 - - - - 11.8 18.9 62.1 41.4

Subtotal 15.1 15.5 13.5 13.9 - - 32.8 33.8 17.5 18.1 - - - - 18.1 18.6 97.0 64.7

B. Improved Market Services

1. Upgraded Grow th Centers and Large Markets 4.3 38.4 4.9 43.3 - - - - - - - - - - 2.1 18.3 11.2 7.5

2. Upgraded Community Markets - - - - - - 5.5 65.6 1.5 17.4 - - - - 1.4 17.0 8.4 5.6

Subtotal 4.3 22.0 4.9 24.8 - - 5.5 28.0 1.5 7.4 - - - - 3.5 17.7 19.6 13.1

C. Enhanced Climate Change Adaptation Capacity

1. Enhanced Capacity and Know ledge Management - - - - 0.8 31.1 0.3 10.8 0.1 1.9 1.0 37.1 0.3 9.6 0.3 9.4 2.7 1.8

2. Upgraded Climate Disaster Shelters - - - - - - - - - - - - 7.3 82.8 1.5 17.2 8.8 5.8

Subtotal - - - - 0.8 7.4 0.3 2.6 0.1 0.4 1.0 8.8 7.5 65.5 1.8 15.3 11.5 7.7

D. Project Management - - 1.6 7.9 9.1 46.2 0.9 4.4 0.4 2.3 - - 1.3 6.6 6.4 32.6 19.7 13.2

Total PROJECT COSTS 19.4 13.1 19.9 13.5 10.0 6.7 39.5 26.7 19.5 13.2 1.0 0.7 8.8 6.0 29.8 20.1 147.9 98.6

Interest During Implementation 0.6 28.7 0.1 3.2 - - - - - - - - - - 1.5 68.0 2.2 1.4

Total Disbursement 20.0 13.3 20.0 13.3 10.0 6.6 39.5 26.3 19.5 13.0 1.0 0.7 8.8 5.9 31.2 20.8 150.0 100.0

Page 166: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

7

Table 7: Disbursement Accounts by Financiers (US$ Million)

ADB SCF Loan SCF Grant IFAD First Loan IFAD Second Loan IFAD Grant KfW The Government Total

Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount %

A. Civil Works

Upazila Roads 15.1 44.8 13.5 40.2 - - - - - - - - - - 5.0 15.0 33.6 22.4

Union, Village and Block Roads - - - - - - 32.8 55.4 17.5 29.6 - - - - 8.9 15.0 59.3 39.5

Landing Stages (Ghats) - - - - - - 0.4 62.5 0.1 22.5 - - - - 0.1 15.0 0.6 0.4

Markets 4.3 23.4 4.9 26.4 - - 5.1 27.9 1.3 7.2 - - - - 2.8 15.0 18.4 12.3

Climate Disaster Shelters - - - - - - - - - - - - 7.3 85.0 1.3 15.0 8.5 5.7

Subtotal 19.4 16.1 18.4 15.3 - - 38.3 31.8 19.0 15.8 - - 7.3 6.0 18.1 15.0 120.4 80.3

B. Vehicles and Equipment - - 1.6 48.4 - - 0.7 21.3 0.3 9.5 - - - - 0.7 20.8 3.2 2.1

C. Consulting Services

Design and Supervision - - - - 6.2 75.2 - - - - - - 1.1 13.0 1.0 11.7 8.2 5.5

Management Support - - - - 2.2 74.1 0.2 6.4 0.1 4.7 - - 0.2 6.0 0.3 8.7 3.0 2.0

Subtotal - - - - 8.4 74.9 0.2 1.7 0.1 1.3 - - 1.3 11.2 1.2 10.9 11.2 7.5

D. Training, Workshops, Studies - - - - 1.6 43.5 0.3 7.8 0.0 1.2 1.0 27.8 0.3 8.9 0.4 10.8 3.6 2.4

E. Land Acquisition - - - - - - - - - - - - - - 3.0 100.0 3.0 2.0

F. LGED Staff and Operating Costs - - - - - - - - - - - - - - 1.4 100.0 1.4 0.9

G. Infrastructure Construction and Maintenance (Government) - - - - - - 0.0 0.2 0.0 0.1 - - - - 5.0 99.6 5.0 3.4

Total PROJECT COSTS 19.4 13.1 19.9 13.5 10.0 6.7 39.5 26.7 19.5 13.2 1.0 0.7 8.8 6.0 29.8 20.1 147.9 98.6

Interest During Implementation 0.6 28.7 0.1 3.2 - - - - - - - - - - 1.5 68.0 2.2 1.4

Total Disbursement 20.0 13.3 20.0 13.3 10.0 6.6 39.5 26.3 19.5 13.0 1.0 0.7 8.8 5.9 31.2 20.8 150.0 100.0

Page 167: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

8

Table 8: Expenditure Accounts by Financiers (US$ Million)

ADB SCF Loan SCF Grant IFAD First Loan IFAD Second Loan IFAD Grant KfW The Government Total

Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount % Amount %

I. Investment Costs

A. Civil Works

Upazila Roads 15.1 44.8 13.5 40.2 - - - - - - - - - - 5.0 15.0 33.6 22.4

Union, Village and Block Roads - - - - - - 32.8 55.4 17.5 29.6 - - - - 8.9 15.0 59.3 39.5

Grow th Centers and Large Markets 4.3 40.0 4.9 45.1 - - - - - - - - - - 1.6 15.0 10.8 7.2

Village Markets and Collection Points - - - - - - 5.1 67.5 1.3 17.5 - - - - 1.1 15.0 7.6 5.1

Landing Stages (Ghats) - - - - - - 0.4 62.5 0.1 22.5 - - - - 0.1 15.0 0.6 0.4

Climate Disaster Shelters - - - - - - - - - - - - 7.3 85.0 1.3 15.0 8.5 5.7

Subtotal 19.4 16.1 18.4 15.3 - - 38.3 31.8 19.0 15.8 - - 7.3 6.0 18.1 15.0 120.4 80.3

B. Vehicles & Equipment

Vehicles - - 0.8 67.3 - - 0.1 7.7 - - - - - - 0.3 25.0 1.3 0.8

Field Equipment - - 0.5 54.8 - - 0.3 25.2 - - - - - - 0.2 20.0 1.0 0.7

Office Equipment - - 0.2 65.9 - - 0.0 14.1 - - - - - - 0.0 20.0 0.2 0.2

Subtotal - - 1.6 62.1 - - 0.4 15.4 - - - - - - 0.6 22.5 2.5 1.7

C. Consulting Services

International - - - - 2.8 92.7 - - - - - - 0.2 7.3 -0.0 -0.0 3.0 2.0

National - - - - 3.1 56.7 0.4 7.1 0.4 6.5 - - 0.8 14.8 0.8 15.0 5.4 3.6

Support Staff - - - - 1.5 78.4 - - - - - - 0.1 6.6 0.3 15.0 1.9 1.3

Equipment, Surveys and Operating Expenses - - - - 1.0 77.3 - - - - - - 0.1 7.7 0.2 15.0 1.3 0.9

Subtotal - - - - 8.4 71.9 0.4 3.3 0.4 3.0 - - 1.3 10.7 1.3 11.1 11.7 7.8

D. Training, Workshop, Studies - - - - 1.6 43.5 0.3 7.8 0.0 1.2 1.0 27.8 0.3 8.9 0.4 10.8 3.6 2.4

E. Land Acquisition - - - - - - - - - - - - - - 3.0 100.0 3.0 2.0

F. LGED Staff and Operating Costs - - - - - - - - - - - - - - - - - -

Total Investment Costs 19.4 13.7 19.9 14.1 10.0 7.1 39.4 27.9 19.4 13.7 1.0 0.7 8.8 6.3 23.3 16.5 141.2 94.1

II. Recurrent Costs

A. Infrastructure Maintenance

Roads - - - - - - - - - - - - - - 4.2 100.0 4.2 2.8

Markets - - - - - - 0.0 1.7 0.0 1.1 - - - - 0.6 97.2 0.7 0.4

Climate Disaster Shelters - - - - - - - - - - - - - - 0.2 100.0 0.2 0.1

Subtotal - - - - - - 0.0 0.2 0.0 0.1 - - - - 5.0 99.6 5.0 3.4

B. Salaries and allow ances - - - - - - - - - - - - - - 1.4 100.0 1.4 0.9

C. Vehicles operation and maintenance - - - - - - 0.1 45.6 0.1 39.4 - - - - 0.0 15.0 0.2 0.2

Total Recurrent Costs - - - - - - 0.1 1.8 0.1 1.5 - - - - 6.5 96.7 6.7 4.4

Total PROJECT COSTS 19.4 13.1 19.9 13.5 10.0 6.7 39.5 26.7 19.5 13.2 1.0 0.7 8.8 6.0 29.8 20.1 147.9 98.6

Interest During Implementation 0.6 28.7 0.1 3.2 - - - - - - - - - - 1.5 68.0 2.2 1.4

Total Disbursement 20.0 13.3 20.0 13.3 10.0 6.6 39.5 26.3 19.5 13.0 1.0 0.7 8.8 5.9 31.2 20.8 150.0 100.0

Page 168: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

AR

ME

NIA

– F

AR

ME

R M

AR

KE

T A

CC

ES

S P

RO

GR

AM

ME

(FM

AP

)

DE

SIG

N D

OC

UM

EN

T - F

OR

MU

LA

TIO

N R

EP

OR

T

WO

RK

ING

PA

PE

R 6

: PR

OG

RA

MM

E C

OS

TS

AN

D F

INA

NC

ING

AP

PE

ND

IX 1

: SU

MM

AR

Y C

OS

T T

AB

LE

S

Detailed Cost Tables

1. Improved Road Connectivity

2. Improved Market Services

3. Enhanced Climate Change Adaptation Capacity

4. Project Management

Page 169: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 170: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

1

Detailed Cost Tables

Table 1: Improved Road Connectivity - (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 1.1. Upgraded Rural Roads

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Construction Cost

1. Upazila Roads

a. Roads km 10 20 40 40 20 - 130 170,731.71 1,707,317 3,414,634 6,829,268 6,829,268 3,414,634 - 22,195,122

b. Structures m 60 120 240 240 120 - 780 7,317.07 439,024 878,049 1,756,098 1,756,098 878,049 - 5,707,317

c. Drainage Improvement km 70 100 100 - - - 270 8,536.59 597,561 853,659 853,659 - - - 2,304,878

Subtotal 2,743,902 5,146,341 9,439,024 8,585,366 4,292,683 - 30,207,317

2. Union, Village and Block Roads

a. Union Roads BC type 'B' km 13 25 54 36 - - 128 109,756.10 1,426,829 2,743,902 5,926,829 3,951,220 - - 14,048,780

b. Union Roads BC type 'C' km 3 10 14 5 - - 32 128,048.78 384,146 1,280,488 1,792,683 640,244 - - 4,097,561

c. Village Roads BC km 28 57 106 80 - - 271 73,170.73 2,048,780 4,170,732 7,756,098 5,853,659 - - 19,829,268

d. Village Roads RCC km 7 16 22 20 - - 65 89,024.39 623,171 1,424,390 1,958,537 1,780,488 - - 5,786,585

e. Block Roads km 1 1 2 1 - - 5 58,536.59 58,537 58,537 117,073 58,537 - - 292,683

f. Structures

Bridges m - 30 40 40 - - 110 6,097.56 - 182,927 243,902 243,902 - - 670,732

Culverts and Small Bridges m 230 230 265 930 690 - 2,345 3,658.54 841,463 841,463 969,512 3,402,439 2,524,390 - 8,579,268

Subtotal 841,463 1,024,390 1,213,415 3,646,341 2,524,390 - 9,250,000

Subtotal 5,382,927 10,702,439 18,764,634 15,930,488 2,524,390 - 53,304,878

Total Investment Costs 8,126,829 15,848,780 28,203,659 24,515,854 6,817,073 - 83,512,195

II. Recurrent Costs

A. Maintenance Cost /a

1. Upazila/Union Roads sum - - 82,317 236,707 51,988 777,439 1,148,451

2. Union, Village and Block Roads sum - - 166,024 473,927 783,659 1,125,732 2,549,341

Total Recurrent Costs - - 248,341 710,634 835,646 1,903,171 3,697,793

Total 8,126,829 15,848,780 28,452,000 25,226,488 7,652,720 1,903,171 87,209,988

_________________________________

\a Estimated at 3% per year of cumulative construction costs.

Page 171: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

2

Table 2: Improved Market Infrastructure – (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 2.1. Upgraded Rural Markets

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Construction Cost

1. Growth Centers and Large Markets

a. Grow th Center Markets No 3 6 9 - - - 18 304,878.05 914,634 1,829,268 2,743,902 - - - 5,487,805

b. Village Markets No 10 25 35 - - - 70 60,975.61 609,756 1,524,390 2,134,146 - - - 4,268,293

Subtotal 1,524,390 3,353,659 4,878,049 - - - 9,756,098

2. Community Markets

Type 1: Special Markets No 1 1 1 1 - - 4 87,804.88 87,805 87,805 87,805 87,805 - - 351,220

Type 2: Large Package No 6 10 10 7 - - 33 42,682.93 256,098 426,829 426,829 298,780 - - 1,408,537

Type 3: Small package No 32 48 48 32 - - 160 30,487.80 975,610 1,463,415 1,463,415 975,610 - - 4,878,049

Collection Centers No 1 2 2 - - - 5 14,634.15 14,634 29,268 29,268 - - - 73,171

Women's Market Sections (in existing markets) No 3 4 4 4 - - 15 10,975.61 32,927 43,902 43,902 43,902 - - 164,634

Landing Stages (Ghats) No 8 10 10 10 - - 38 13,414.63 107,317 134,146 134,146 134,146 - - 509,756

Subtotal 1,474,390 2,185,366 2,185,366 1,540,244 - - 7,385,366

Total Investment Costs 2,998,780 5,539,024 7,063,415 1,540,244 - - 17,141,463

II. Recurrent Costs

A. Maintenance Cost /a

1. Grow th Center and Village Markets sum - 15,244 48,780 97,561 97,561 97,561 356,707

2. Community Markets sum - 6,866 23,537 39,439 48,951 57,183 175,976

3. Landing Stages (Ghats) sum - - 2,439 6,098 10,976 10,976 30,488

Total Recurrent Costs - 22,110 74,756 143,098 157,488 165,720 563,171

Total 2,998,780 5,561,134 7,138,171 1,683,341 157,488 165,720 17,704,634

_________________________________

\a Estimated at 1% per year of cumulative construction costs.

Page 172: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

3

Table 3: Enhanced Climate Change Adaptation Capacity – LGED trainings and workshops - Detailed Costs (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 3.1. LGED Workshops and Training /a

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. LGED Training on Climate Resilience

Training of Trainers /b event 2 - - - - - 2 767.07 1,534 - - - - - 1,534

Principles of Climate Resilience and Adapation event 2 - - - - - 2 608.54 1,217 - - - - - 1,217

Assessment of Road Condition event 2 - - - - - 2 434.76 870 - - - - - 870

Infrastructure Risk Assessment event 2 - - - - - 2 434.76 870 - - - - - 870

Climate Resilient Designs and Specif ications event 2 - - - - - 2 608.54 1,217 - - - - - 1,217

Bioengineering Protection of Earthw orks event 2 - - - - - 2 608.54 1,217 - - - - - 1,217

Quality Control in Construction and Maintenance event - 3 - - - - 3 608.54 - 1,826 - - - - 1,826

Climate Resilience/Adaptation Exposure Visit /c event - 1 - - - - 1 113,597.56 - 113,598 - - - - 113,598

Climate-proofing of Infrastructure Exposure Visit /d event 2 2 2 2 - - 8 50,740.85 101,482 101,482 101,482 101,482 - - 405,927

Development, Operation and Maintenance of Renew able Energy Systems event - 3 - - - - 3 608.54 - 1,826 - - - - 1,826

Subtotal 108,406 218,730 101,482 101,482 - - 530,100

B. LGED Workshops and Training on Knowledge Management

Know ledge Management Policy Workshop event 1 - - - - - 1 1,542.07 1,542 - - - - - 1,542

Know ledge Management Concepts Training event 3 3 3 - - - 9 434.76 1,304 1,304 1,304 - - - 3,913

Know ledge Management Exposure Visit /e event - 1 - - - - 1 4,652.44 - 4,652 - - - - 4,652

Subtotal 2,846 5,957 1,304 - - - 10,107

C. LGED Training on Safeguards

Environment and Social/Poverty Safeguards event 3 3 3 - - - 9 608.54 1,826 1,826 1,826 - - - 5,477

Gender and Development Training event 3 3 3 - - - 9 608.54 1,826 1,826 1,826 - - - 5,477

Subtotal 3,651 3,651 3,651 - - - 10,954

Total 114,904 228,338 106,437 101,482 - - 551,161

_________________________________

\a LGED - Local Government Engineering Department.

\b LGED trainers w ho w ill train local stakeholders.

\c Attendance for 10 persons for 10 days at seminars/w orkshops overseas.

\d Attendance for 5 persons for 1 days at seminars/w orkshops overseas.

\e Attendance for 2 persons for 5 days at seminars/w orkshops overseas.

Page 173: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

4

Table 3.2. Enhanced Climate Change Adaptation Capacity – Government and project Institutions workshops and trainings

- Detailed Costs (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 3.2. Government and Project Institutions Workshops and Training

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Climate Change

1. National Workshop on Climate Change Adaptation event 1 - - - - - 1 1,542.07 1,542 - - - - - 1,542

2. District Workshops on Climate Change Hazards event 3 3 3 - - - 9 273.78 821 821 821 - - - 2,464

3. Upazila Workshops on Climate Change Hazards, Impacts and Adaptation event 5 5 5 5 - - 20 273.78 1,369 1,369 1,369 1,369 - - 5,476

4. Project-level Workshops on Climate Change Hazards, Impacts and Adaptation event 5 5 5 5 - - 20 273.78 1,369 1,369 1,369 1,369 - - 5,476

5. Village Workshops on Climate Change Hazards, Impacts and Adaptation event 25 25 25 25 - - 100 273.78 6,845 6,845 6,845 6,845 - - 27,378

Subtotal 11,946 10,404 10,404 9,582 - - 42,335

B. Project Awareness and Implementation

1. Project Orientation Workshops /a event 9 - - - - - 9 601.22 5,411 - - - - - 5,411

2. Midterm Workshops /b event - - 3 - - - 3 273.78 - - 821 - - - 821

3. Sensitization Workshops event 5 5 5 5 - - 20 273.78 1,369 1,369 1,369 1,369 - - 5,476

4. Rural Market Participatory Planning Workshops event 5 5 5 5 - - 20 651.22 3,256 3,256 3,256 3,256 - - 13,024

5. Market Management Workshops event 15 15 15 15 - - 60 273.78 4,107 4,107 4,107 4,107 - - 16,427

6. Market Users and Stakeholders Workshops event 20 20 20 20 - - 80 601.22 12,024 12,024 12,024 12,024 - - 48,098

7. Local Contracting Society Aw areness Workshops event 5 5 5 5 - - 20 651.22 3,256 3,256 3,256 3,256 - - 13,024

Subtotal 29,423 24,012 24,834 24,012 - - 102,281

C. Local training for project staff (IFAD)

1. Accounting and documents management training /c event 2 - - - - - 2 304.88 610 - - - - - 610

2. Double entry accounting system training /d event - 1 1 - - - 2 1,219.51 - 1,220 1,220 - - - 2,439

3. Accounting softw are procurement, training and maintenance event 1 - - - - - 1 2,000.00 2,000 - - - - - 2,000

Subtotal 2,610 1,220 1,220 - - - 5,049

Total 43,979 35,635 36,457 33,595 - - 149,665

_________________________________

\a For upazila and union parishad chairpersons.

\b For upazila and union parishad chairpersons.

\c 2 days training; 25 per batch; 2 batches

\d 6 days; 25 per batch; 2 batches

Page 174: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

5

Table 3.3.: Enhanced Climate Change Adaptation Capacity – Beneficiaries workshops and trainings - Detailed Costs (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 3.3. Beneficiary Workshops and Training

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Income Generating Activities Training

Basic Income Generating Activities event 3 3 3 - - - 9 601.22 1,804 1,804 1,804 - - - 5,411

Specialized Income Generating Activities event 3 3 3 - - - 9 434.76 1,304 1,304 1,304 - - - 3,913

Management Training event 5 5 5 5 - - 20 800.61 4,003 4,003 4,003 4,003 - - 16,012

Marketing Training event 5 5 5 5 - - 20 767.07 3,835 3,835 3,835 3,835 - - 15,341

Market Linkages Workshops event 10 10 10 - - - 30 601.22 6,012 6,012 6,012 - - - 18,037

Market Linkages Visits event - 10 10 - - - 20 434.76 - 4,348 4,348 - - - 8,695

In-country Exposure Visits event 2 3 - - - - 5 1,329.88 2,660 3,990 - - - - 6,649

Subtotal 19,618 25,296 21,306 7,838 - - 74,059

B. Training and Visits on Marketing

Marketing/Selling Training /a event 3 3 3 - - - 9 434.76 1,304 1,304 1,304 - - - 3,913

Exchange Visits to Successful Markets event - 3 3 3 - - 9 434.76 - 1,304 1,304 1,304 - - 3,913

Subtotal 1,304 2,609 2,609 1,304 - - 7,826

C. General Market Users Workshops and Training

Market Users and Stakeholders Workshops event 3 3 3 - - - 9 601.22 1,804 1,804 1,804 - - - 5,411

Market Rules and Regulations Training event - 3 3 3 - - 9 434.76 - 1,304 1,304 1,304 - - 3,913

Market Operation and Maintenance Training /b event 6 6 6 - - - 18 434.76 2,609 2,609 2,609 - - - 7,826

Gender and Environment Aw areness Training /c event 3 3 3 - - - 9 434.76 1,304 1,304 1,304 - - - 3,913

Subtotal 5,716 7,021 7,021 1,304 - - 21,062

D. Women Market Users Workshops and Training /d

Women Market Section Users Workshops /e event 6 6 6 - - - 18 434.76 2,609 2,609 2,609 - - - 7,826

Environment and Social Safeguards Workshops event 3 3 3 - - - 9 434.76 1,304 1,304 1,304 - - - 3,913

Shop Management and Skills Development event 6 6 6 - - - 18 434.76 2,609 2,609 2,609 - - - 7,826

Market Management Committee and Banik Samity Functions Training event 6 6 6 - - - 18 434.76 2,609 2,609 2,609 - - - 7,826

Women Temporary Market Users Workshops event - 3 3 3 - - 9 273.78 - 821 821 821 - - 2,464

Subtotal 9,130 9,951 9,951 821 - - 29,854

E. Labor Contracting Society Workshops and Training

1. Orientation Workshops /f event 6 6 6 - - - 18 747.56 4,485 4,485 4,485 - - - 13,456

2. LCS Formation and Management Training event 9 9 9 - - - 27 608.54 5,477 5,477 5,477 - - - 16,430

3. Savings and Financial Management event 9 9 9 9 - - 36 601.22 5,411 5,411 5,411 5,411 - - 21,644

4. Procurement event 3 3 3 - - - 9 434.76 1,304 1,304 1,304 - - - 3,913

5. Contract Management event 3 3 3 - - - 9 434.76 1,304 1,304 1,304 - - - 3,913

6. Health and Hygiene event 9 9 9 9 - - 36 747.56 6,728 6,728 6,728 6,728 - - 26,912

7. Advanced Skill Development Training

Cold Bitumen Emulsion event 9 9 9 - - - 27 608.54 5,477 5,477 5,477 - - - 16,430

U-Drain Construction event 6 6 6 - - - 18 608.54 3,651 3,651 3,651 - - - 10,954

Herringbone Brick Block Pavement Construction event 6 6 6 - - - 18 608.54 3,651 3,651 3,651 - - - 10,954

Maintenance of Road Pavements event 6 6 6 - - - 18 608.54 3,651 3,651 3,651 - - - 10,954

Maintenance of Road Slopes and Shoulders event - 6 6 6 - - 18 608.54 - 3,651 3,651 3,651 - - 10,954

Tree Plantation and Maintenance event - 6 6 6 - - 18 608.54 - 3,651 3,651 3,651 - - 10,954

Subtotal 16,430 23,733 23,733 7,302 - - 71,199

Subtotal 41,140 48,443 48,443 19,441 - - 157,467

Page 175: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

6

F. MMC, WMS, training and exchange visits (IFAD)

Upazila Market Management w orkshop /g per upazila 25 37 37 25 - - 124 426.83 10,671 15,793 15,793 10,671 - - 52,927

Market User and Stakeholder w orkshop /h per market 76 114 76 - - - 266 426.83 32,439 48,659 32,439 - - - 113,537

Market Management Committee initial training /i per market 38 57 57 38 - - 190 243.90 9,268 13,902 13,902 9,268 - - 46,341

Subtotal 52,378 78,354 62,134 19,939 - - 212,805

G. LCS trainings for union and village roads and village markets (IFAD)

LCS group trainings for village markets event 39 59 59 39 - - 196 731.71 28,537 43,171 43,171 28,537 - - 143,415

LCS group trainings for block roads event 2 2 - - - - 4 731.71 1,463 1,463 - - - - 2,927

Subtotal 30,000 44,634 43,171 28,537 - - 146,341

Total Investment Costs 159,287 216,307 194,634 79,185 - - 649,413

II. Recurrent Costs

A. Operational costs related to the LCS market subproject preparation /j sum 3,902 3,902 3,902 3,902 3,902 - 19,512

Total Recurrent Costs 3,902 3,902 3,902 3,902 3,902 - 19,512

Total 163,190 220,209 198,537 83,088 3,902 - 668,926

_________________________________

\a For income generating activity trainees and market users.

\b To cover w ater supply, renew able energy, etc. Includes training related to climate disaster shelters (cyclone shelters, etc).

\c For all market stakeholders.

\d For users of w omen's market sections.

\e Orientation meetings for potential permanent users of w omen's market sections.

\f LCS objectives, management, operation, gender and environment aw areness.

\g 30 per batch, 1 day w orkshop; per Upazila

\h 30 per batch; 1 day w orkshop; per market

\i 20 per batch; 1 day training; per MMC or per market

\j Stationary, miscelaneous, operational costs; 10000 Taka per Upazilla per year

Page 176: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

7

Table 3.4.: Enhanced Climate Change Adaptation Capacity – Knowledge Management Development - Detailed Costs (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 3.4. Know ledge Management Development

Detailed Costs

(US$) Quantities Unit Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Knowledge Management Program

Web Page Design, Hosting and Maintenance sum 24,390 6,098 6,098 6,098 6,098 - 48,780

Expansion of LGED Management/Geographic Information Systems sum 30,488 - - - - - 30,488

Design of Field Data Collection System sum 30,488 - - - - - 30,488

Field Data Collection Equipment sum 97,561 - - - - - 97,561

Field Data Collection sum - 9,756 9,756 9,756 9,756 - 39,024

Subtotal 182,927 15,854 15,854 15,854 15,854 - 246,341

B. KM, implementation, support, design (IFAD) /a

KM and innovation /b sum 101,220 51,220 51,220 51,220 51,220 51,220 357,317

Studies and project design sum 645,067 - - - - - 645,067

Subtotal 746,287 51,220 51,220 51,220 51,220 51,220 1,002,384

Total 929,213 67,073 67,073 67,073 67,073 51,220 1,248,726

_________________________________

\a Baseline survey, MTR,

\b Sponsoring Rural Radio Program, KM activities, garbage management research, independent construction quality monitoring and Climate resilience slope protection research

Page 177: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

8

Table 3.5.: Enhanced Climate Change Adaptation Capacity – Climate disasters shelters - Detailed Costs (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 3.5. Climate Disaster Shelters

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Cyclone Shelters

Multipurpose Markets/Cyclone Refuges No - 2 1 - - - 3 304,878.05 - 609,756 304,878 - - - 914,634

New Cyclone Shelters No - 2 1 - - - 3 304,878.05 - 609,756 304,878 - - - 914,634

Improvement of Existing Cyclone Shelters No - 5 2 2 1 - 10 60,975.61 - 304,878 121,951 121,951 60,976 - 609,756

Improvement and Expansion of Existing Cyclone Shelters No - 4 2 2 1 - 9 243,902.44 - 975,610 487,805 487,805 243,902 - 2,195,122

Improvement of Cyclone Shelter Access Tracks km - 7 3 3 2 - 15 73,170.73 - 512,195 219,512 219,512 146,341 - 1,097,561

Livestock Cyclone Refuges (Killas) sum - 195,122 195,122 100,610 - - 490,854

Subtotal - 3,207,317 1,634,146 929,878 451,220 - 6,222,561

B. Water Supply

Mini Piped Systems No - 2 1 - - - 3 121,951.22 - 243,902 121,951 - - - 365,854

Hand-operated Deep Tubew ells No - 15 15 10 - - 40 3,048.78 - 45,732 45,732 30,488 - - 121,951

Subtotal - 289,634 167,683 30,488 - - 487,805

C. Renewable Energy Supply

Markets sum - 60,976 73,171 109,756 - - 243,902

Cyclone Shelters sum - 60,976 73,171 109,756 - - 243,902

Subtotal - 121,951 146,341 219,512 - - 487,805

D. Complementary Support Measures /a sum - 97,561 207,317 134,146 60,976 - 500,000

Total Investment Costs - 3,716,463 2,155,488 1,314,024 512,195 - 7,698,171

II. Recurrent Costs

A. Maintenance Cost /b sum - - 32,073 48,415 57,720 62,232 200,439

Total - 3,716,463 2,187,561 1,362,439 569,915 62,232 7,898,610

_________________________________

\a Includes ancillary facilties at social infrastructure sites, technical surveys, and community training in infrastructure operation and maintenance.

\b Estimated at 1% per year of cumulative construction costs of cyclone shelters, w ater supply, renew able energy supply and .

Page 178: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

9

Table 4.1.: Project management - Detailed Costs (USD) Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 4.1. Project Management

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Project Management Establishment

1. Project Management Office (Dhaka)

a. Vehicles and Equipment

Jeep (4 w heel drive) unit 4 - - - - - 4 112,956.10 451,824 - - - - - 451,824

Motorcycle unit 2 - - - - - 2 2,019.51 4,039 - - - - - 4,039

Subtotal 455,863 - - - - - 455,863

b. Office Equipment and Refurbishment

Desktop Computer and Peripherals unit 20 - - - - - 20 1,402.44 28,049 - - - - - 28,049

Laptop Computers unit 3 - - - - - 3 1,951.22 5,854 - - - - - 5,854

Printer (Heavy Duty) unit 1 - - - - - 1 2,151.22 2,151 - - - - - 2,151

Printer/Scanner/Copier (Small-scale) unit 5 - - - - - 5 365.85 1,829 - - - - - 1,829

Copier (Heavy Duty) unit 1 - - - - - 1 3,079.27 3,079 - - - - - 3,079

Copier (Small-scale) unit 3 - - - - - 3 365.85 1,098 - - - - - 1,098

Digital Camera unit 1 - - - - - 1 304.88 305 - - - - - 305

Airconditioning Unit unit 5 - - - - - 5 2,151.22 10,756 - - - - - 10,756

Office Refurbishment and Netw orking sum 1 - - - - - 1 30,487.80 30,488 - - - - - 30,488

Subtotal 83,609 - - - - - 83,609

c. Market planner (IFAD) month 12 12 12 6 - - 42 731.71 8,780 8,780 8,780 4,390 - - 30,732

d. Financial management specialist (IFAD) month 3 3 - - - - 6 1,333.33 4,000 4,000 - - - - 8,000

e. GIS Specialist (IFAD) month 12 12 12 12 12 - 60 609.76 7,317 7,317 7,317 7,317 7,317 - 36,585

f. Hydrologist (IFAD) month 12 12 12 12 12 6 66 853.66 10,244 10,244 10,244 10,244 10,244 5,122 56,341

g. Accounts assistant (IFAD) month 12 12 12 12 12 6 66 304.88 3,659 3,659 3,659 3,659 3,659 1,829 20,122

Subtotal 573,472 34,000 30,000 25,610 21,220 6,951 691,252

2. Regional Project Offices (ADB) /a

a. Vehicles and Equipment

Jeep (4 w heel drive) unit 2 - - - - - 2 112,956.10 225,912 - - - - - 225,912

Double-cab Pick-up (4 w heel drive) unit 2 - - - - - 2 35,756.10 71,512 - - - - - 71,512

Motorcycle unit 4 - - - - - 4 2,019.51 8,078 - - - - - 8,078

Subtotal 305,502 - - - - - 305,502

b. Field Equipment sum 652,439 - - - - - 652,439

c. Office Equipment and Refurbishment

Desktop Computer and Peripherals unit 8 - - - - - 8 1,402.44 11,220 - - - - - 11,220

Laptop Computers unit 2 - - - - - 2 1,951.22 3,902 - - - - - 3,902

Printer (Heavy Duty) unit 2 - - - - - 2 2,151.22 4,302 - - - - - 4,302

Printer/Scanner/Copier (Small-scale) unit 4 - - - - - 4 365.85 1,463 - - - - - 1,463

Copier (Heavy Duty) unit 2 - - - - - 2 3,079.27 6,159 - - - - - 6,159

Copier (Small-scale) unit 4 - - - - - 4 365.85 1,463 - - - - - 1,463

Digital Camera unit 2 - - - - - 2 304.88 610 - - - - - 610

LCD Projector unit 2 - - - - - 2 1,463.41 2,927 - - - - - 2,927

Airconditioning Unit unit 2 - - - - - 2 2,151.22 4,302 - - - - - 4,302

Office Refurbishment and Netw orking sum 2 - - - - - 2 18,292.68 36,585 - - - - - 36,585

Subtotal 72,934 - - - - - 72,934

Subtotal 1,030,876 - - - - - 1,030,876

Page 179: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

10

3. Project Implementation Units (ADB) /b

a. Vehicles and Equipment

Double-cab Pick-up (4 w heel drive) unit 9 - - - - - 9 35,756.10 321,805 - - - - - 321,805

Motorcycle unit 18 - - - - - 18 2,019.51 36,351 - - - - - 36,351

Subtotal 358,156 - - - - - 358,156

b. Office Equipment and Refurbishment

Desktop Computer and Peripherals unit 9 - - - - - 9 1,402.44 12,622 - - - - - 12,622

Printer/Scanner/Copier (Small-scale) unit 9 - - - - - 9 365.85 3,293 - - - - - 3,293

Survey Equipment set 9 - - - - - 9 2,439.02 21,951 - - - - - 21,951

Subtotal 37,866 - - - - - 37,866

Subtotal 396,022 - - - - - 396,022

4. Regional Project Office (IFAD) /c

a. Vehicles and Equipment

Double-cab Pick-up (4 w heel drive) unit 1 - - - - - 1 35,756.10 35,756 - - - - - 35,756

Motorcycle unit 2 - - - - - 2 2,019.51 4,039 - - - - - 4,039

Subtotal 39,795 - - - - - 39,795

b. Road Construction and Maintenance Equipment (PMU) /d

Road Roller (4-5 ton vibrating) No 4 - - - - - 4 47,560.98 190,244 - - - - - 190,244

Thermometer Set No 32 - - - - - 32 12.20 390 - - - - - 390

Rebound Hammer No 32 - - - - - 32 914.63 29,268 - - - - - 29,268

Digital Camera No 32 - - - - - 32 304.88 9,756 - - - - - 9,756

Salinity measurement kit No 25 - - - - - 25 400.00 10,000 - - - - - 10,000

Oddometer No 32 - - - - - 32 100.00 3,200 - - - - - 3,200

Moisture meter No 32 - - - - - 32 300.00 9,600 - - - - - 9,600

Plate compactor No 32 - - - - - 32 500.00 16,000 - - - - - 16,000

Ferro scanner No 1 - - - - - 1 25,000.00 25,000 - - - - - 25,000

Survey Equipment set 3 - - - - - 3 2,439.02 7,317 - - - - - 7,317

Subtotal 300,776 - - - - - 300,776

c. Office Equipment and Refurbishment

Desktop Computer and Peripherals unit 4 - - - - - 4 1,402.44 5,610 - - - - - 5,610

Laptop Computers unit 1 - - - - - 1 1,951.22 1,951 - - - - - 1,951

Printer (Heavy Duty) unit 1 - - - - - 1 2,151.22 2,151 - - - - - 2,151

Printer/Scanner/Copier (Small-scale) unit 2 - - - - - 2 365.85 732 - - - - - 732

Copier (Heavy Duty) unit 1 - - - - - 1 3,079.27 3,079 - - - - - 3,079

Copier (Small-scale) unit 2 - - - - - 2 365.85 732 - - - - - 732

Digital Camera unit 1 - - - - - 1 304.88 305 - - - - - 305

LCD Projector unit 1 - - - - - 1 1,463.41 1,463 - - - - - 1,463

Airconditioning Unit unit 1 - - - - - 1 2,151.22 2,151 - - - - - 2,151

Office Refurbishment and Netw orking sum 1 - - - - - 1 18,292.68 18,293 - - - - - 18,293

Subtotal 36,467 - - - - - 36,467

Subtotal 377,038 - - - - - 377,038

5. Project Implementation Units (IFAD) /e

a. Vehicles and Equipment

Motorcycle unit 12 - - - - - 12 2,019.51 24,234 - - - - - 24,234

b. Office Equipment and Refurbishment

Desktop Computer and Peripherals unit 3 - - - - - 3 1,402.44 4,207 - - - - - 4,207

Printer/Scanner/Copier (Small-scale) unit 3 - - - - - 3 365.85 1,098 - - - - - 1,098

Subtotal 5,305 - - - - - 5,305

Subtotal 29,539 - - - - - 29,539

6. Upazilla project office (IFAD)

a. Vehicles and Equipment

Motorcycle unit 32 - - - - - 32 2,019.51 64,624 - - - - - 64,624

b. Infrastructure supervision engineers for upazilla project off ice (32) month 192 384 384 384 384 192 1,920 365.85 70,244 140,488 140,488 140,488 140,488 70,244 702,439

Subtotal 134,868 140,488 140,488 140,488 140,488 70,244 767,063

Subtotal 2,541,815 174,488 170,488 166,098 161,707 77,195 3,291,790

B. Land Acquisition sum 243,902 487,805 670,732 670,732 487,805 128,049 2,689,024

Total Investment Costs 2,785,717 662,293 841,220 836,829 649,512 205,244 5,980,815

II. Recurrent Costs

A. LGED Staff and Operating Costs sum 195,122 243,902 243,902 243,902 243,902 146,341 1,317,073

B. Motorbikes operation and maintenance /f sum 22,537 22,537 22,537 22,537 22,537 22,537 135,220

C. Vehicles operation and maintenance at the regional project off ice /g sum 17,561 17,561 17,561 17,561 17,561 - 87,805

Total Recurrent Costs 235,220 284,000 284,000 284,000 284,000 168,878 1,540,098

Total 3,020,937 946,293 1,125,220 1,120,829 933,512 374,122 7,520,912

_________________________________

\a Quantities show n are for tw o off ices, one in Barisal and one in Khulna.

\b Quantities show n are for 9 districts under Barisal and Khulna Regional Project Offices.

\c Quantities show n are for one off ice in Perojpur.

\d For use by labor contracting societies contracted for road construction.

\e Quantities show n are for 3 districts under Perojpur Regional Project Office.

\f 3500Taka per month and per bike (fuel and maintenance costs)

\g 40000 per monthx3monthx12months

Page 180: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

11

Table 4.2.: Project management – Trainings and Workshops - Detailed Costs (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 4.2. Project Management Workshops, Training and Studies

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Project Management Workshops

Inception Workshop (National) event 1 - - - - - 1 1,542.07 1,542 - - - - - 1,542

Annual Workshops (National) event - 1 - 1 - - 2 1,542.07 - 1,542 - 1,542 - - 3,084

Midterm Workshop (National) event - - 1 - - - 1 1,542.07 - - 1,542 - - - 1,542

Completion Workshop (National) event - - - - 1 - 1 1,542.07 - - - - 1,542 - 1,542

Annual Review Workshops (Field Level) event 10 10 10 10 10 - 50 273.78 2,738 2,738 2,738 2,738 2,738 - 13,689

Subtotal 4,280 4,280 4,280 4,280 4,280 - 21,399

B. Surveys and Studies /a

Upazila/Union Roads and Grow th Center and Village Markets sum 243,902 60,976 60,976 60,976 60,976 - 487,805

C. Independent Safeguards Monitoring sum 121,951 48,780 48,780 48,780 48,780 48,780 365,854

Total 370,134 114,036 114,036 114,036 114,036 48,780 875,058

_________________________________

\a Baseline surveys, social/environmental assessments, impact evaluation, etc.

Page 181: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 7B

12

Table 4.3.: Project management – Consulting Services - Detailed Costs (USD)

Bangladesh

Coastal Climate Resilient Infrastructure Project

Table 4.3. Consulting Services

Detailed Costs

(US$) Quantities Base Cost

Unit 2013 2014 2015 2016 2017 2018 Total Unit Cost 2013 2014 2015 2016 2017 2018 Total

I. Investment Costs

A. Design and Supervision

1. International

Rural Infrastructure Specialist - Team Leader month 6 11 11 11 6 6 51 22,439.02 134,634 246,829 246,829 246,829 134,634 134,634 1,144,390

Quality Assurance Specialist - Deputy Team Leader month 3 5 4 3 3 - 18 22,439.02 67,317 112,195 89,756 67,317 67,317 - 403,902

Senior Road Engineer month 2 1 1 1 1 - 6 22,439.02 44,878 22,439 22,439 22,439 22,439 - 134,634

Procurement/Contracts Specialist month 2 0.5 0.5 0.5 0.5 - 4 22,439.02 44,878 11,220 11,220 11,220 11,220 - 89,756

Subtotal 291,707 392,683 370,244 347,805 235,610 134,634 1,772,683

2. National

Procurement/Contracts Specialist month 3 2 2 2 2 1 12 4,390.24 13,171 8,780 8,780 8,780 8,780 4,390 52,683

Resident Engineers - Construction Specialists (3) month 9 33 33 33 15 5 128 4,390.24 39,512 144,878 144,878 144,878 65,854 21,951 561,951

Road Design Engineers (4) month 12 12 12 12 12 3 63 4,390.24 52,683 52,683 52,683 52,683 52,683 13,171 276,585

Road Structures Engineers (2) month 6 3 3 3 3 1 19 4,390.24 26,341 13,171 13,171 13,171 13,171 4,390 83,415

Quality Assurance Engineers (3) month 5 33 33 33 33 11 148 4,390.24 21,951 144,878 144,878 144,878 144,878 48,293 649,756

Road Supervision/Quality Control Engineers (3) month 5 33 33 33 33 6 143 4,390.24 21,951 144,878 144,878 144,878 144,878 26,341 627,805

Hydrologist month 3 3 3 3 3 3 18 4,390.24 13,171 13,171 13,171 13,171 13,171 13,171 79,024

Water Supply Engineer month 2 3 2 1 1 - 9 4,390.24 8,780 13,171 8,780 4,390 4,390 - 39,512

Geotechnical Engineer month 2 3 2 1 1 - 9 4,390.24 8,780 13,171 8,780 4,390 4,390 - 39,512

Rural Market Planner month 3 2 2 2 2 2 13 4,390.24 13,171 8,780 8,780 8,780 8,780 8,780 57,073

Market Buildings Structural Engineer month 3 3 3 3 3 3 18 4,390.24 13,171 13,171 13,171 13,171 13,171 13,171 79,024

Market Buildings Supervision/Quality Control Engineers (3) month 5 33 33 33 33 - 137 4,390.24 21,951 144,878 144,878 144,878 144,878 - 601,463

Cyclone Shelters Structural Engineer month - 8 4 4 4 - 20 4,390.24 - 35,122 17,561 17,561 17,561 - 87,805

Cyclone Shelters Supervision/Quality Control Engineers (4) month - 44 44 33 22 - 143 4,390.24 - 193,171 193,171 144,878 96,585 - 627,805

Subtotal 254,634 943,902 917,561 860,488 733,171 153,659 3,863,415

3. Support Staff

Construction Observers sum 9,756 24,390 24,390 24,390 18,293 - 101,220

Office Engineers/Administrators (4) month 33 44 44 44 44 22 231 2,926.83 96,585 128,780 128,780 128,780 128,780 64,390 676,098

CAD Operators (4) month 24 16 16 16 16 11 99 2,926.83 70,244 46,829 46,829 46,829 46,829 32,195 289,756

Office Assistants (5) month 44 55 55 55 55 22 286 1,463.41 64,390 80,488 80,488 80,488 80,488 32,195 418,537

Subtotal 240,976 280,488 280,488 280,488 274,390 128,780 1,485,610

4. Equipment and Operating Expenses year 122,720 203,256 201,720 182,549 55,988 8,439 774,671

5. Surveys /a sum 45,732 45,732 45,732 45,732 45,732 - 228,659

Subtotal 955,768 1,866,061 1,815,744 1,717,061 1,344,890 425,512 8,125,037

B. Management Support

1. International

Project Institutional Adviser - Team Leader month 6 11 11 11 6 - 45 22,439.02 134,634 246,829 246,829 246,829 134,634 - 1,009,756

Climate Resilience Specialist month 2 1 1 1 - - 5 22,439.02 44,878 22,439 22,439 22,439 - - 112,195

Know ledge Management Development Specialist month 2 1 - - - - 3 22,439.02 44,878 22,439 - - - - 67,317

Project Economist month 1 0.5 0.5 - - - 2 22,439.02 22,439 11,220 11,220 - - - 44,878

Subtotal 246,829 302,927 280,488 269,268 134,634 - 1,234,146

2. National

Economist/Benefit Monitoring and Evaluation Specialist (Deputy Team Leader) month 3 3 3 3 3 3 18 4,390.24 13,171 13,171 13,171 13,171 13,171 13,171 79,024

Training Specialist month 6 6 6 6 6 - 30 4,390.24 26,341 26,341 26,341 26,341 26,341 - 131,707

Climate Resilience Specialist month 4 2 2 2 2 - 12 4,390.24 17,561 8,780 8,780 8,780 8,780 - 52,683

Environment Specialist month 2 2 2 2 2 2 12 4,390.24 8,780 8,780 8,780 8,780 8,780 8,780 52,683

Resettlement Specialist month 6 6 6 6 6 6 36 4,390.24 26,341 26,341 26,341 26,341 26,341 26,341 158,049

Gender Specialist month 6 6 6 6 6 - 30 4,390.24 26,341 26,341 26,341 26,341 26,341 - 131,707

Livelihoods Specialist month 2 1 - - - - 3 4,390.24 8,780 4,390 - - - - 13,171

Project Finance Specialist month 3 1 1 1 - - 6 4,390.24 13,171 4,390 4,390 4,390 - - 26,341

Subtotal 140,488 118,537 114,146 114,146 109,756 48,293 645,366

3. Support Staff

Off ice Manager/Administrator month 11 11 11 11 11 11 66 2,926.83 32,195 32,195 32,195 32,195 32,195 32,195 193,171

Office Assistants (2) month 22 22 22 22 22 22 132 1,463.41 32,195 32,195 32,195 32,195 32,195 32,195 193,171

Subtotal 64,390 64,390 64,390 64,390 64,390 64,390 386,341

4. Equipment and Operating Expenses year 49,854 46,024 42,183 36,817 17,646 8,439 200,963

5. Surveys /b sum 18,293 18,293 18,293 18,293 18,293 - 91,463

Subtotal 519,854 550,171 519,500 502,915 344,720 121,122 2,558,280

Total 1,475,622 2,416,232 2,335,244 2,219,976 1,689,610 546,634 10,683,317

_________________________________

\a Technical surveys, geotechncial surveys/investigations, etc.

\b Socio-economic, beneficiary needs surveys, etc.

Page 182: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8A

Annex 8A

Structural Design: Road Infrastructure

Page 183: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 184: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8A

1

Annex 8A

Structural Design: Road Infrastructure

Component 1 – Improved Road Connectivity

Feeder roads

1. Transport Infrastructure is the component that includes the areas served (or service areas) by markets. From field surveys it would appear that the number of feeder roads fall mostly in the range of 3-10, these are roads serving a particular market. On average about 5 feeder roads

provide the access to markets for the service areas. The status of the roads varies from poor – moderate – good. The types of roads are BC, RCC, CC, HBB, BFS, Block roads, Earthen Roads. Accordingly, the distance over which road rehabilitation/construction is needed also varies per service area of the market place. The project will not construct new roads. Thus, the embankment as road foundation is available and not included in the budget.

2. In case road rehabilitation is required than roads will be built as BC, RCC or Block roads. This is the preference based on long-time experience in the concerned Upazilas. Brick based

roads, HBB or BFS, would be gradually phased out. The local population often favours BC roads, followed by RCC roads.

3. In case access is difficult or impossible for rollers than BC roads are no option. The same is true when inundation with salty or brackish water occurs. In these cases the preferred road is the RCC road.

Overview of road types

4. Theoretical overview of possible road types connecting one administrative level with the same

or a lower level, those that actually occur, and the road types envisaged to be rehabilitated or built under CCRIP. It concerns roads that are normally within LGED‘s mandate.

Level number

Administrative level

Possible road types - connecting one level with same or a lower level

Actual occurrence of road types

CCRIP intervention Proposed road type

1 Upazila BC yes Yes

RCC yes Yes

CC no no

Block Road no no

HBB no no

BFS no no

Earthen road no no

2 Union Parishad BC yes yes

RCC yes yes

CC no no

Block Road no no

HBB yes no

BFS no no

Earthen road no no

3 Village road BC yes yes

RCC no yes

CC yes no

Block Road no yes

HBB yes no

BFS yes no

Earthen road yes no

Project roads

5. The project will limit its intervention in the rural road infrastructure to two levels: Union Roads and Village Roads. The road types for these two levels will be mainly BC, RCC, and Block Roads. What type of road will be built depends on the economic data (villages‘ importance and location in the service area of the particular market) and the relative cost. In addition accessibility for rollers may prohibit the use of BC roads at both levels and salt water

inundation may make RCC the only feasible option.

6. The following 5 combinations are possible:

Page 185: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8A

2

Administrative level Union Width, in m Village Width, in m

Road Type

BC 3.00 BC 2.55

RCC 3.00 RCC 2.40

Block road - Block road 2.45

7. Remark: at the Union level no Block roads will be built. Therefore, the following road types at

the two administrative levels will be considered under CCRIP:

Union Roads: BC, RCC

Village Roads: BC, RCC, Block Road

Designs

8. The drawings are given below for relevant road types that will be used under CCRIP. In case occasionally a different road is needed, than the designs are available in LGED and these were found adequate. Therefore, only the details of these roads are given below. In an attached

PDF the design of ghats are given. Based on these designs BOQs were made and costs calculated as given in Annex 8B and Annex 8C.

Union BC road

Union RCC road

Page 186: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8A

3

Village BC road

Village RCC road

Village Block road

Page 187: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8A

4

Village Block Road - plan of blocks with

Design Aspects of Transport Infrastructure

As per Bangladesh Gazette, volume 1, 6th November, 2003 – LGED has been given the mandated responsibility for development and maintenance of the following roads in rural areas:

Upazila Road: Roads connecting Upazila HQ/s with Growth Center/s or one Growth Center with another Growth Center by a single main connection or connecting Growth Center to Higher Road System, through shortest distance/route.

Union Road: Roads connecting Union HQ/s with Upazila HQs, growth centres or local markets

or with each other.

Village Road: Roads connecting Villages with Union HQs, local markets, farms and ghats or with each other or Roads within a Village.

Corresponding structural and geometric designs for each type of roads are also approved by the planning commission. These are as follows:

Village Road

HBB: 350mm thick 3 structural layers system and 3.7m crest width with 2.65m pavement and

0.525m shoulder on either side

BC: 425mm thick 4 structural layers system and 3.7m crest width with 2.55m pavement and 0.575m shoulder on either side

Block: 250mm thick 2 structural layers system and 3.7m crest width with 2.45m pavement and 0.625m shoulder on either side

RCC: 325mm thick 3 structural layers system and 3.7m crest width with 2.40m pavement and

0.650m shoulder on either side

Union Road

BC: 575mm thick 4 structural layers system and 5.5m crest width with 3.25m pavement and 0.125m shoulder on either side

RCC: 325mm thick 3 structural layers system and 5.5m crest width with 3.25m pavement and 0.125m shoulder on either side

Typical cross-sections for each type of road are available (some are relevant for CCRIP is in

Appendix…)

In CCRIP project, the similar structural and geometric design is adopted for implementation as well as for cost estimation but with a few modifications. First, from the standard structural design of pavement as presented above it is found that the same structural 3-layer system is adopted for both RCC type village and union roads though their traffic loading and geometric considerations are different. Bituminous carpeting (BC) is a multi-layered flexible pavement system, whereas the reinforced cement concrete (RCC) type rigid pavement is a 1 or 2-layered system. On RCC the

traffic load is basically distributed by slab action, whilst by the BC road the traffic load is distributed through an inter-granular locking mechanism over different layers of which the BC

Page 188: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8A

5

pavement is composed of. Considering these issues, it is proposed that in the CCRIP project, for

RCC village road where traffic load would be relatively light and also the pavement would be built on well stabilized old embankment, the brick flat soling (BFS) layer would be omitted. The preliminary design analysis revealed that this modification will not compromise the adequacy of load carrying capability of the pavement.

Second, typical drawings of standard block pavement design show that short side blocks (Plan-

375x225mm) laying arrangement is followed without any logical consideration. It is to be noted that the laying orientation of block has a significant bearing in deteriorating the riding comfort. It is obvious that if the long side of blocks is placed aligned with the vehicular travelling path it would reduce 40% transverse joints vis-à-vis jerking and jolting problems and thereby would improve riding quality. Finite element analysis of the paving block revealed that due to good aspect ratio and 150mm thick shape, the pressure of the vehicle wheels on the block will not

create cracks with the proposed orientation. This block arrangement is also being used in SCBRMP project area.

Selection of Pavement Type

HBB road: Though the conventional Herring Bone Brick (HBB) road is a low cost, easily

maintainable road and community involvement is possible in construction and maintenance works, it has got the following shortcomings:

- Due to the small foot print of building block (brick)

o HBB road is prone to settlement, particularly with soaked or saturated subgrade conditions

o Punching and pumping problems are common with wet subgrade, particularly for dynamic traffic loading conditions

o Stability of HBB road structure largely depends on support conditions; in general it performs better if it is built on well compacted dry subgrade with uniform support condition and for low level of traffic loading

- Performance of HBB road is very sensitive to the firmness of edge confinements which is very difficult to ensure for the road with tight right of way

- Due to thin shape of brick as well as its brittleness, HBB road is o Weak in impact loading particularly those induced by dynamic traffic stream o Prone to fatigue failure

- Limited scope of involving women in HBB road particularly in brick production

- Non-uniform riding quality of HBB road increases passenger discomfort, transport cost and vehicle depreciation

- Due to light weight, brick is more prone to washout by the current of flush flood water - As brick has good use in different civil works, it has got a high opportunity cost and

thereby associated with theft problem - Due to less durable and high settlement potential of HBB road, it requires frequent

maintenance work

Taking the above issues in cognizance it is decided that in the CCRIP (IFAD part) road infrastructure improvement work, the HBB type pavement would be avoided.

Block road: The block pavement system has many advantages to offer considering the local context. The major advantages of block road are :

- Construction process is simple and community (LCS) can do it without involving contractors;

- Block road is easily maintainable;

- Highly labour intensive, thereby create the scope of employment for the poor;

- Block road is in line with project objective to create scope for the poor to reduce poverty; - It has adaption potential with rising water level due to climatic change.

But it is also not above criticism. The following are the few major disadvantages or weaknesses of the block based road:

- Due to differential settlement, the riding quality of block road is relatively poor;

- Blocks need uniform support for even surface but it is too difficult to ensure; - The poor riding quality impacts on higher transportation cost and increase the

maintenance cost of transports as well, particularly for the manual vehicles; - Block roads are not carefree or fit and forgets type of structure, therefore it requires

regular maintenance.

Page 189: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8A

6

Considering these, it is recommended that the block pavement road would be chosen only for

improvement of village road and particularly where there is regular inundation problem.

RCC road: In general, RCC roads perform better as compared to the block and bituminous pavement roads. During field visits it is observed that RCC pavement road has been successfully constructed by involving LCS in MIDPCR project. The main hallmarks of RCC pavement are:

- Higher traffic load carrying potential;

- It is not so susceptible to side confinement or shoulder condition; - Due to its light-colour appearance and high reflectance characteristics, it provide better

night-time visibility as compared to BC road and thereby ensures roadway safety which is very important for rural road;

- Binding material i.e. cement is home grown ingredient; whereas bitumen is mostly imported;

- It is environmental friendly as it does not involved any heating; - Construction is not so weather susceptible as compared to BC; - More resistant to adverse climatic condition; - Unlike BC road, RCC road construction and maintenance works are contractor

independent; does not require involvement of heavy roller;

- Provide better skid resistance; - Long lasting and requires virtually zero maintenance; if constructed properly it could last

up to 15-18 yrs. without any major rehabilitation work; - Economical as compared to bituminous road, if life cycle cost (construction and

maintenance) is considered.

Considering these above advantages, though RCC is 20-25% costlier than that of BC road, this fit and forget typed rigid pavement is recommended:

- when road has to build on narrow right of way particularly where roller cannot be used for subgrade compaction

- for char land areas or isolated island where it is very difficult to take heavy machineries like 4-6 ton roller by trawler/boat

- for high type union road that is usually accessible by trucks and other heavy vehicles

The main problem associated with the rigid pavement is that after construction without damaging the structure it is not possible to lay any condition responsive cross drain pipe or channel at subsurface level for which the need may arise later on. Most importantly, construction of RCC

pavement needs very careful supervision particularly in maintaining water-cement ratio.

BC road: BC typed flexible pavement is a layered system with low flexural strength. A flexible pavement structure is typically composed of several layers of material. Each layer receives the loads from the above layer, spreads them out, then passes on these loads to the next layer below. Thus load is distributed on a large area and stress on the subgrade soil is kept within its bearing capacity. Because of low flexural strength, the pavement deflects momentarily under load but rebounds to its original level on removal of load. LGED is specialized in developing and

maintaining bituminous pavement in rural areas and considering this organizational strength as well as relative cost advantage over RCC pavement, it is recommended that majority of the CCRIP project roads would be of BC typed. It is to be noted that among different pavement types, the multi-layered BC road demands very stringent construction compliances and careful supervision. In general, BC pavement is very sensitive to quality of subgrade preparation & moisture content, type & gradation of aggregates, optimum bitumen content, temperature control in both heating & mixing ingredients, laying & compaction of bituminous mixes. Thereby, in every steps of BC road

construction work maintaining specified temperature is a very big challenge both for site engineers as well as for contractors. Moreover, BC construction is very susceptible to weather conditions;

both winter season and rainy day are unsuitable for construction. For quality assurance of this type of road - competent, sincere, honest and independent field engineers have to be deputed and proactively contractors/subcontractors have to be given a short motivational and construction specification related training. Besides, field engineers have to be equipped with appropriate quality

control logistics viz. temperature, moisture meter, level machine, camera etc.

Road inventory per market place

9. After the identification of the market place that will be reconstructed as part of Market

Development, the service area is determined based on maps. The road engineers do a survey of the status of the roads for the service area and measure length of roads that need

Page 190: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8A

7

construction or rehabilitation based on field surveys, maps and interviews with the village

populations. Maps used would be mostly of two scales: location map (within polder) about 1:20000 and for the detailed field survey about 1:5000 (or 1:2000 as needed).

Boat landing places or ghats and bridges

10. The hydrologist advises the road engineers on the construction of ghats and bridges.

11. The engineers prepare designs, BOQs, and so on.

Hydrology input

12. Besides the road engineers, CCRIP engages two hydrologists to complement to the road infrastructure staff and they will reassess the width and location of culverts needed, the need to add or replace water control gates, the type of water control gate, the O&M of water control gates, location of boat landing places in view river stability, location of bridges, advise on dimensions of bridges, culverts and ghats whilst maintaining cross-sections of river, khals,

drains.

13. For the studies the hydrologists make use of maps (from the GIS-section) and coordinates

with BWDB who are the custodian of the polder in which many of the project‘s intervention areas are located. The hydrologist interviews farmers as to their perceptions on water control and the possible impact the project may have on their farm holdings.

14. The future impact of climate change is verified for the concerned areas and proposals made as

to how to mitigate to some extent the effects; however, the project limits its mitigation effort to affordable interventions as e.g. adding culverts to add discharge capacity to evacuate extreme floods, design of bridges and ghats possibly adapted.

Page 191: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 192: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

Annex 8B

Detailed Cost: Road Infrastructure

Page 193: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 194: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

1

Annex 8B

Detailed Cost: Road Infrastructure

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 2.1.01 Clearing and grubbing by removal and disposal of LS 1 7000 7000

everything above ground level including overhanging

branches, removing of all foundation stumps, embedded logs,

tree roots and other material either to a depth of 0.3m below

the proposed surface elevation or to the level as shown on

the drawing, disposing of all materials resulting from clearing

and grubbing at a safe distance designated by the E-I-C, etc.

2 2.1.04.01 Earth filling work with specified soil in any type of cum Qnt from Earth calcultion 4000 1 4000

embankment including cutting, carrying, filling by throwing sheet

earth in layers not more than 150mm in each layer in proper Deduction for Box 1000 2.4 0.325 780 1 (-) 780

alignment, grade, camber and side slope in all types of soil 3220 102.65 330533

except rocky, gravelly and slushy including benching not

more than 30cm in vertical and 60cm in horizontal steps along

the sides while widening any embankment, etc. all complete

as per the direction of E-I-C. Earth shall be arranged by the

contractor at his own cost and it will include all necessary lead

& lift. Payment will be made on compacted volume.

3 2.1.08.01 Manual compaction of earth in 150mm thick compacted layers cum 4000 1 4000

by breaking clods to a maximum size of 25mm using wooden 4000 25.42 101680

drag or ladder and compacting using concrete drop hammer

(Durmus), watering or drying to obtain optimum moisture

content if necessary including supplying of wooden drag,

ladder, bamboo hammer, steel/concrete hammer and other

requisite tools, etc. all complete as per direction of the E-I-C.

85% compaction of the maximum dry density is to be

obtained by the standard compaction test (Rate is for each

layer of 150mm thick)

Detailed Estimation of Improvement of RCC Road with BFS (VR)

(See Appendix xx for relevant structural drawings)

Page 195: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

2

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

4 3.1.03 Earth work in box cutting on road crest up to 450mm depth sqm Ch:0+000-1+000 1000 2.4 2400 1 2400

with proper grade, camber and alignment maintaining super 2400 46.74 112176

elevation on curves, removing soil to a safe distance,

spreading the excavated earth on road flanks and slopes

uniformly including leveling, dressing, watering, compacting

the sub-grade by manual labour, etc. all complete as per

direction of the E-I-C.

5 3.1.06.02 Sand (FM 0.50) filling on the road bed in the improved sub- cum Ch:0+000-1+000 1000 2.15 0.1 215 1 215

grade with sand free from dust, earth, other vegetable 215 490.03 105356.45

growth and foreign materials including supplying all materials,

spreading, watering, compacting by appropriate mechanical

means to obtain a minimum soaked CBR 8% at minimum

compaction 98% of MDD (Modified), etc. all complete as per

direction of the E-I-C.

6 3.2.11.01 Single layer brick flat soling with 1st class or picked bricks, sqm Ch:0+000-1+000 1000 2.15 2150 1 2150

true to level, camber/super elevation and grade including 2150 270.8 582220

carrying bricks, filling the interstices tightly with sand of

minimum FM 0.80, etc. all complete as per direction of the E-I-C

7 4.2.03.01.1 Reinforced Cement Concrete work in bottom and top slab of cum Ch:0+000-1+000 1000 2.15 0.15 322.5 1 322.5

box culvert of any height with stone chips (Preferably stone 322.5 8357.91 2695425.98

chips from Madhyapara, Dinajpur), sand (minimum FM 1.80)

and cement having minimum 28 days ultimate cylinder

crushing strength of 210kg/cm2 (suggested mix proportion

1:2:4) excluding cost of reinforcement and its fabrication but

including cost of all other materials, shuttering, casting, curing

for 28 days and all incidental charges, etc. complete in all

respect as per direction of the E-I-C.

Bottom slab and approach slab

8 5.03.09 Providing polythene sheet (0.18mm thick) on floor in ground sqm Ch:0+000-1+000 1000 2.15 2150 1 2150

floor underneath the cement concrete, etc. all complete as 2150 17.81 38291.5

Page 196: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

3

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

per specifications and direction of the E-I-C. Sand of

minimum FM 1.2 to be used.

9 4.2.06.02 Supplying and fabrication of M.S High strength deformed kg 13464 1 13464

bar/ Twisted bar reinforcement of required size and length for 13464 67.96 915013.44

all types of RCC work including straightening the rod,

removing ruts, cleaning, cutting, hooking, bending, binding

with supply of 22 B.W.G. GI wire, placing in position,

including lapping, spacing and securing them in position by

concrete blocks (1:1), metal chairs, etc. complete including

cost of all materials, labour, local handling, laboratory test,

incidentals necessary to complete the work as per

specifications, drawings and direction of the Engineer.

Laboratory test for physical property, strength, elongation%

& bend to be performed as per ASTM. (Measurement will be

based on standard weight of 490 lbs./ft3 Chairs, laps and

separators will not be measures for payment. The cost of

these will be included in the unit rate)

10 3.2.15.02 Brick on end edging (125mm across) with 1st class/picked m Ch:0+000-1+000 1000 1000 2 2000

bricks including cutting trenches true to level & grade 2000 120.86 241720

including removing earth, re-filling & ramming the sides

properly & filling the gaps with local sand, etc. all complete as

per direction of the E-I-C.

11 3.2.56.01 Palisading work with double pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 3m long, 0.9m 50 4638.49 231924.5

c/c to be driven 2/3rd of the total length (3m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

Page 197: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

4

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

12 3.2.56.02 Palisading work with single pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 2m long, 0.9m 50 2793.86 139693

c/c to be driven 2/3rd of the total length (2m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

13 5.2 Suppying,fittings sign board (6'-0"x4'-0") fitted with strong no 1 2 2

Bamboo post at suitable place in the working area & writing 2 2500 5000

the name of project.contract amount & year of construction

etc.by synthetic enamel paint as per direction of the Engineer

in charge.

14 5.20.2 Preparation of Tender & Publishing as per PPR-2008 LS 1 5000 5000

TOTAL AMOUNT: 5 511 033.87

SAY: 5 511 034.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Fifty-Five Lac Eleven Thousand Thirty-Four) Only

Page 198: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

5

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 2.1.01 Clearing and grubbing by removal and disposal of LS 1 10000 10000

everything above ground level including overhanging

branches, removing of all foundation stumps, embedded logs,

tree roots and other material either to a depth of 0.3m below

the proposed surface elevation or to the level as shown on

the drawing, disposing of all materials resulting from clearing

and grubbing at a safe distance designated by the E-I-C, etc.

2 2.1.04.01 Earth filling work with specified soil in any type of cum Qnt from Earth calcultion 6000 1 6000

embankment including cutting, carrying, filling by throwing sheet

earth in layers not more than 150mm in each layer in proper Deduction for Box 1000 3.25 0.325 1056.25 1 (-) 1056.25

alignment, grade, camber and side slope in all types of soil 4943.75 102.65 507475.94

except rocky, gravelly and slushy including benching not

more than 30cm in vertical and 60cm in horizontal steps along

the sides while widening any embankment, etc. all complete

as per the direction of E-I-C. Earth shall be arranged by the

contractor at his own cost and it will include all necessary lead

& lift. Payment will be made on compacted volume.

3 2.1.08.01 Manual compaction of earth in 150mm thick compacted layerscum 6000 1 6000

by breaking clods to a maximum size of 25mm using wooden 6000 25.42 152520

drag or ladder and compacting using concrete drop hammer

(Durmus), watering or drying to obtain optimum moisture

content if necessary including supplying of wooden drag,

ladder, bamboo hammer, steel/concrete hammer and other

requisite tools, etc. all complete as per direction of the E-I-C.

85% compaction of the maximum dry density is to be

obtained by the standard compaction test (Rate is for each

layer of 150mm thick)

Detailed Estimation of Improvement of RCC Road (UNR)

(See Appendix xx for relevant structural drawings)

Page 199: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

6

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

4 3.1.03 Earth work in box cutting on road crest up to 450mm depth sqm Ch:0+000-1+000 1000 3.25 3250 1 3250

with proper grade, camber and alignment maintaining super 3250 46.74 151905

elevation on curves, removing soil to a safe distance,

spreading the excavated earth on road flanks and slopes

uniformly including leveling, dressing, watering, compacting

the sub-grade by manual labour, etc. all complete as per

direction of the E-I-C.

5 3.1.06.02 Sand (FM 0.50) filling on the road bed in the improved sub- cum Ch:0+000-1+000 1000 3.25 0.1 325 1 325

grade with sand free from dust, earth, other vegetable 325 490.03 159259.75

growth and foreign materials including supplying all materials,

spreading, watering, compacting by appropriate mechanical

means to obtain a minimum soaked CBR 8% at minimum

compaction 98% of MDD (Modified), etc. all complete as per

direction of the E-I-C.

6 5.03.09 Providing polythene sheet (0.18mm thick) on floor in ground sqm Ch:0+000-1+000 1000 3 3000 1 3000

floor underneath the cement concrete, etc. all complete as 3000 17.81 53430

per specifications and direction of the E-I-C. Sand of

minimum FM 1.2 to be used.

7 3.2.11.01 Single layer brick flat soling with 1st class or picked bricks, sqm Ch:0+000-1+000 1000 3 3000 1 3000

true to level, camber/super elevation and grade including 3000 270.8 812400

carrying bricks, filling the interstices tightly with sand of

minimum FM 0.80, etc. all complete as per direction of the E-I-C.

8 4.2.03.01.1 Reinforced Cement Concrete work in bottom and top slab of cum Ch:0+000-1+000 1000 3 0.15 450 1 450

box culvert of any height with stone chips (Preferably stone 450 8357.91 3761059.5

chips from Madhyapara, Dinajpur), sand (minimum FM 1.80)

and cement having minimum 28 days ultimate cylinder

crushing strength of 210kg/cm2 (suggested mix proportion

1:2:4) excluding cost of reinforcement and its fabrication but

including cost of all other materials, shuttering, casting, curing

for 28 days and all incidental charges, etc. complete in all

Page 200: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

7

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

respect as per direction of the E-I-C.

Bottom slab and approach slab

9 4.2.06.02 Supplying and fabrication of M.S High strength deformed kg 16120 1 16120

bar/ Twisted bar reinforcement of required size and length for 16120 67.96 1095515.2

all types of RCC work including straightening the rod,

removing ruts, cleaning, cutting, hooking, bending, binding

with supply of 22 B.W.G. GI wire, placing in position,

including lapping, spacing and securing them in position by

concrete blocks (1:1), metal chairs, etc. complete including

cost of all materials, labour, local handling, laboratory test,

incidentals necessary to complete the work as per

specifications, drawings and direction of the Engineer.

Laboratory test for physical property, strength, elongation%

& bend to be performed as per ASTM. (Measurement will be

based on standard weight of 490 lbs./ft3 Chairs, laps and

separators will not be measures for payment. The cost of

these will be included in the unit rate)

10 3.2.15.02 Brick on end edging (125mm across) with 1st class/picked m Ch:0+000-1+000 1000 1000 2 2000

bricks including cutting trenches true to level & grade 2000 120.86 241720

including removing earth, re-filling & ramming the sides

properly & filling the gaps with local sand, etc. all complete as

per direction of the E-I-C.

11 3.2.56.01 Palisading work with double pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 3m long, 0.9m 50 4638.49 231924.5

c/c to be driven 2/3rd of the total length (3m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

12 3.2.56.02 Palisading work with single pre-cast plate (1150mmx600mm) m 50 50 1 50

Page 201: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

8

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

fitted with RCC (1:2:4) post of 150mmx150mm, 2m long, 0.9m 50 2793.86 139693

c/c to be driven 2/3rd of the total length (2m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

13 5.2 Suppying,fittings sign board (6'-0"x4'-0") fitted with strong no 1 2 2

Bamboo post at suitable place in the working area & writing 2 2500 5000

the name of project.contract amount & year of construction

etc.by synthetic enamel paint as per direction of the Engineer

in charge.

14 5.20.2 Preparation of Tender & Publishing as per PPR-2008 LS 1 5000 5000

TOTAL AMOUNT: 7 326 902.89

SAY: 7 326 903.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Seventy-Three Lac Twenty-Six Thousand Nine Hundred Three) Only

Page 202: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

9

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 2.1.01 Clearing and grubbing by removal and disposal of LS 1 7000 7000

everything above ground level including overhanging

branches, removing of all foundation stumps, embedded logs,

tree roots and other material either to a depth of 0.3m below

the proposed surface elevation or to the level as shown on

the drawing, disposing of all materials resulting from clearing

and grubbing at a safe distance designated by the E-I-C, etc.

2 2.1.04.01 Earth filling work with specified soil in any type of cum Qnt from Earth calcultion 4000 1 4000

embankment including cutting, carrying, filling by throwing sheet

earth in layers not more than 150mm in each layer in proper Deduction for Box 1000 2.55 0.4 1020 1 (-) 1020

alignment, grade, camber and side slope in all types of soil 2980 102.65 305897

except rocky, gravelly and slushy including benching not

more than 30cm in vertical and 60cm in horizontal steps along

the sides while widening any embankment, etc. all complete

as per the direction of E-I-C. Earth shall be arranged by the

contractor at his own cost and it will include all necessary lead

& lift. Payment will be made on compacted volume.

3 2.1.08.01 Manual compaction of earth in 150mm thick compacted layerscum 4000 1 4000

by breaking clods to a maximum size of 25mm using wooden 4000 25.42 101680

drag or ladder and compacting using concrete drop hammer

(Durmus), watering or drying to obtain optimum moisture

content if necessary including supplying of wooden drag,

ladder, bamboo hammer, steel/concrete hammer and other

requisite tools, etc. all complete as per direction of the E-I-C.

85% compaction of the maximum dry density is to be

obtained by the standard compaction test (Rate is for each

layer of 150mm thick)

Detailed Estimation of Improvement of Bituminous Carpeting Road (VR)

(See Appendix xx for relevant structural drawings)

Page 203: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

10

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

4 3.1.02 Earth work in box cutting on road crest up to 300mm depth sqm Ch:0+000-1+000 1000 2.55 2550 1 2550

with proper grade, camber and alignment maintaining super 2550 42.1 107355

elevation at curves, removing soils to a safe distance or if

necessary, spreading the excavated earth on road flanks and

slopes uniformly including leveling, dressing, watering,

compacting the sub-grade minimum 300mm depth by

appropriate mechanical means to attain minimum compaction

98% of MDD Standard etc. all complete as per direction of the

E-I-C. Minimum soaked CBR requirement of the sub-grade is 4%.

5 3.1.06.02 Sand (FM 0.50) filling on the road bed in the improved sub- cum Ch:0+000-1+000 1000 2.55 0.15 382.5 1 382.5

grade with sand free from dust, earth, other vegetable 382.5 490.03 187436.48

growth and foreign materials including supplying all materials,

spreading, watering, compacting by appropriate mechanical

means to obtain a minimum soaked CBR 8% at minimum

compaction 98% of MDD (Modified), etc. all complete as per

direction of the E-I-C.

6 3.2.02.04 Providing compacted aggregate sand sub-base course with cum Ch:0+000-1+000 1000 2.4 0.1 240 1 240

38mm down Crusher run 1st class bricks/picked chips of 240 2319.44 556665.6

LAA value not exceeding 40 & locally available sand (Passing

<=15% through #200 sieve) mixed in proportion 1:1 by

volume placed in layer(s) to give a maximum compacted

thickness of 100mm in a single appropriate layer, mixing

properly, watering, compacting with 8~10 tonne road roller

to give compaction to 98% of MDD (modified) including

supplying of all materials, labourers, tools and equipment etc.

all complete as per direction of the E-I-C. Minimum CBR

requirement for sub-base course is 30%.

7 3.2.03.06 Providing, laying, spreading and compacting 38mm down cum Ch:0+000-1+000 1000 2.4 0.15 360 1 360

graded aggregates as specified in the relevant item of LGED 360 3771.96 1357905.6

road design standard or wet mix macadam specification (LAA

Page 204: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

11

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

value not exceeding 40% ) made of 1st class and Picked

bricks, combining brick chips of different sizes to provide

requisit grading and premixing the material with water at

OMC in mechanical mix plant at stack yard including carriage

of mixed material by tipper with proper covering to site,

laying in uniform layers of specified loose thickness not more

than 125mm with Grader in base course on well prepared

surface and compacting with 8~10 tonne road roller to

achieve soaked CBR not less than 80% at a degree of

compaction to minimum 98% (Modified Proctor) including

supplying all materials, carriage, labors, tools & equipment

etc. all complete as per direction of the E-I-C.

8 3.2.15.01 Brick on end edging (75mm across) with 1st class/picked m Ch:0+000-1+000 1000 1000 2 2000

bricks including cutting trenches true to level & grade 2000 71.02 142040

including removing earth, re-filling & ramming the sides

properly & filling the gaps with local sand, etc. all complete as

per direction of the E-I-C.

9 3.2.25 Prime coat with cut back bitumen to be prepared by cutting sqm Ch:0+000-1+000 1000 2.4 2400 1 2400

back 60/70 or 80/100 penetration grade straight run bitumen 2400 88.69 212856

(conforming to the requirements of ASTM/ AASHTO in the

ratio of 100 parts by volume of bitumen to 40-60 parts by

volume of kerosene depending on the porosity of the surface

and will be decided by field trials when correct amount will

be the quantity that is completely absorbed within 24 hours

including carefully cleaning of the surface of the granular

base material to be primed and spraying cut back bitumen at

a temperature from 100°C to 120°C by mechanical distributor

@1.2 litre/m2 etc. complete as per direction of the E-I-C

10 3.2.29.1 25mm thick compacted pre-mixed bituminous carpeting to be sqm Ch:0+000-1+000 1000 2.4 2400 1 2400

prepared using 20mm down stone-chips (LAA value not 2400 340.22 816528

Page 205: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

12

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

exceeding 35%) of gradation as specified, mixed with heated

bitumen of 80/100 or 60/70 penetration grade @85kg of

heated bitumen per cum of stone-chips. The bitumen and

stone-chips shall be separately heated to a temperature 140°C

– 155°C and 150°C – 170°C respectively before mixing. The

mixing shall be done at temperature between 140°C – 160°C

at a separate place away from the fire. The bitumen and

stone-chips mixture so prepared shall be laid uniformly in

proper camber, grade and super-elevation, only on the

prepared and accepted base or surface in a single appropriate

layer to give the specified compacted thickness. The mixture

should be rolled with appropriate by Steel Drum Roller (1-3

tons) & pneumatic multiple tire roller (8-10 tons) to full

compaction. The rolling temperature shall be maintained not

below 90°C including supplying of all materials, their carriage,

labourers, tools and equipment etc. all complete as per

direction of the E-I-C.

11 3.2.24.04 Providing tack coat with 60/70 or 80/100 penetration grade sqm Ch:0+000-1+000 1000 2.4 2400 1 2400

straight run bitumen complying with the requirements of 2400 52.48 125952

ASTM/AASHTO applied by mechanical @0.50kg/m2 and at a

temperature between 140°C and 160°C including heating bitumen,

surface cleaning, etc. all complete as per direction of the E-I-C.

12 3.2.34 7mm thick compacted pre-mixed bituminous seal coat to be sqm Ch:0+000-1+000 1000 2.4 2400 1 2400

prepared using 6.33mm down crushed stone of gradation as 2400 117.4 281760

specified in the relevant item of Road Design Standards –

2005, mixed with 80/100 or 60/70 penetration grade @96kg.

Of bitumen per m3 aggregate. The bitumen and chips shall be

separately heated to a temperature 140°C – 155°C and 150°C

– 170°C respectively. The mixing shall be done at

temperaturebetween 140°C – 160°C at a separate place away

Page 206: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

13

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

from the fire. The mixture of bitumen and chips so prepared

shall be laid uniformly on the road surface in appropriate

layer so as to produce the specified compacted thickness,

rolling at a temperature not bellow 130°C with appropriate

Steel Drum Roller (1-3 tons) & pneumatic multiple tire roller

(8-10 tons) to the desired compaction and blinding with dry

sand (Min FM-0.80) @0.005m3 per m2 of road surface,

including supplying of all materials, their carriage, labourers

tools and equipment etc. all complete as per direction of the

13 3.2.56.01 Palisading work with double pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 3m long, 0.9m 50 4638.49 231924.5

c/c to be driven 2/3rd of the total length (3m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

14 3.2.56.02 Palisading work with single pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 2m long, 0.9m 50 2793.86 139693

c/c to be driven 2/3rd of the total length (2m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

15 5.2 Suppying,fittings sign board (6'-0"x4'-0") fitted with strong no 1 2 2

Bamboo post at suitable place in the working area & writing 2 2500 5000

the name of project.contract amount & year of construction

etc.by synthetic enamel paint as per direction of E-I-C.

16 5.20.2 Preparation of Tender & Publishing as per PPR-2008 LS 1 5000 5000

TOTAL AMOUNT: 4 584 693.2

SAY: 4 584 693.0

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Forty-Five Lac Eighty-Four Thousand Six Hundred Ninety-Three) Only

Page 207: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

14

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 2.1.01 Clearing and grubbing by removal and disposal of LS 1 10000 10000

everything above ground level including overhanging

branches, removing of all foundation stumps, embedded logs,

tree roots and other material either to a depth of 0.3m below

the proposed surface elevation or to the level as shown on

the drawing, disposing of all materials resulting from clearing

and grubbing at a safe distance designated by the E-I-C, etc.

2 2.1.04.01 Earth filling work with specified soil in any type of cum Qnt from Earth calcultion 6000 1 6000

embankment including cutting, carrying, filling by throwing

earth in layers not more than 150mm in each layer in proper

alignment, grade, camber and side slope in all types of soil Deduction for Box 1000 3.25 0.45 1462.5 1 (-) 1462.5

except rocky, gravelly and slushy including benching not 4537.5 102.65 465774.38

more than 30cm in vertical and 60cm in horizontal steps along

the sides while widening any embankment, etc. all complete

as per the direction of E-I-C. Earth shall be arranged by the

contractor at his own cost and it will include all necessary lead

& lift. Payment will be made on compacted volume.

3 2.1.08.01 Manual compaction of earth in 150mm thick compacted layers cum 6000 1 6000

by breaking clods to a maximum size of 25mm using wooden 6000 25.42 152520

drag or ladder and compacting using concrete drop hammer

(Durmus), watering or drying to obtain optimum moisture

content if necessary including supplying of wooden drag,

ladder, bamboo hammer, steel/concrete hammer and other

requisite tools, etc. all complete as per direction of the E-I-C.

85% compaction of the maximum dry density is to be

obtained by the standard compaction test (Rate is for each

layer of 150mm thick)

Detailed Estimation of Improvement of Bituminous Carpeting Road (UNR)

(See Appendix xx for relevant structural drawings)

Page 208: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

15

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

4 3.1.04 Earth work in box cutting on road crest up to 450mm depth sqm Ch:0+000-1+000 1000 3.25 3250 1 3250

with proper grade, camber and alignment maintaining super 3250 52.27 169877.5

elevation at curves, removing soils to a safe distance or if

necessary, spreading the excavated earth on road flanks and

slopes uniformly including leveling, dressing, compacting the

sub-grade minimum 300mm by appropriate mechanical means

to attain minimum compaction 98% of MDD, Standard, etc.

all complete as per direction of the E-I-C. Minimum soaked

CBR requirement of the sub-grade is 4%.

Scheme Code : 50669-12-10037

5 3.1.06.02 Sand (FM 0.50) filling on the road bed in the improved sub- cum Ch:0+000-1+000 1000 3.25 0.25 812.5 1 812.5

grade with sand free from dust, earth, other vegetable 812.5 490.03 398149.38

growth and foreign materials including supplying all materials,

spreading, watering, compacting by appropriate mechanical

means to obtain a minimum soaked CBR 8% at minimum

compaction 98% of MDD (Modified), etc. all complete as per

direction of the E-I-C.

6 3.2.02.02 Providing compacted aggregate sand sub-base course with cum Ch:0+000-1+000 1000 3.25 0.05 162.5 1 162.5

38mm down Crusher run 1st class bricks/picked chips of Ch:0+000-1+000 1000 3.25 0.1 325 1 325

LAA value not exceeding 40 & sand of minimum FM 0.80 487.5 2443.11 1191016.13

mixed in proportion 1:1 by volume placed in layer(s) to give

a maximum compacted thickness of 100mm in a single

appropriate layer, mixing properly, watering, compacting

with 8~10 tonne road roller to give compaction to 98% of

MDD (modified) including supplying of all materials,

labourers, tools and equipment etc. all complete as per

direction of the E-I-C. Minimum CBR requirement for sub-

7 3.2.03.06 Providing, laying, spreading and compacting 38mm down cum Ch:0+000-1+000 1000 3 0.15 450 1 450

graded aggregates as specified in the relevant item of LGED 450 3771.96 1697382

road design standard or wet mix macadam specification (LAA

Page 209: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

16

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

value not exceeding 40% ) made of 1st class and Picked

bricks, combining brick chips of different sizes to provide

requisit grading and premixing the material with water at

OMC in mechanical mix plant at stack yard including carriage

of mixed material by tipper with proper covering to site,

laying in uniform layers of specified loose thickness not more

than 125mm with Grader in base course on well prepared

surface and compacting with 8~10 tonne road roller to

achieve soaked CBR not less than 80% at a degree of

compaction to minimum 98% (Modified Proctor) including

supplying all materials, carriage, labors, tools & equipment

etc. all complete as per direction of the E-I-C.

8 3.2.15.02 Brick on end edging (125mm across) with 1st class/picked m Ch:0+000-1+000 1000 1000 2 2000

bricks including cutting trenches true to level & grade 2000 120.86 241720

including removing earth, re-filling & ramming the sides

properly & filling the gaps with local sand, etc. all complete as

per direction of the E-I-C.

9 3.2.25 Prime coat with cut back bitumen to be prepared by cutting sqm Ch:0+000-1+000 1000 3 3000 1 3000

back 60/70 or 80/100 penetration grade straight run bitumen 3000 88.69 266070

(conforming to the requirements of ASTM/ AASHTO in the

ratio of 100 parts by volume of bitumen to 40-60 parts by

volume of kerosene depending on the porosity of the surface

and will be decided by field trials when correct amount will

be the quantity that is completely absorbed within 24 hours

including carefully cleaning of the surface of the granular

base material to be primed and spraying cut back bitumen at

a temperature from 100°C to 120°C by mechanical distributor

@1.2 litre/m2 etc. complete as per direction of the E-I-C

Scheme Code : 50669-12-10037

Page 210: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

17

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

10 3.2.29.1 25mm thick compacted pre-mixed bituminous carpeting to be sqm Ch:0+000-1+000 1000 3 3000 1 3000

prepared using 20mm down stone-chips (LAA value not 3000 340.22 1020660

exceeding 35%) of gradation as specified, mixed with heated

bitumen of 80/100 or 60/70 penetration grade @85kg of

heated bitumen per cum of stone-chips. The bitumen and

stone-chips shall be separately heated to a temperature 140°C

– 155°C and 150°C – 170°C respectively before mixing. The

mixing shall be done at temperature between 140°C – 160°C

at a separate place away from the fire. The bitumen and

stone-chips mixture so prepared shall be laid uniformly in

proper camber, grade and super-elevation, only on the

prepared and accepted base or surface in a single appropriate

layer to give the specified compacted thickness. The mixture

should be rolled with appropriate by Steel Drum Roller (1-3

tons) & pneumatic multiple tire roller (8-10 tons) to full

compaction. The rolling temperature shall be maintained not

below 90°C including supplying of all materials, their carriage,

labourers, tools and equipment etc. all complete as per

direction of the E-I-C.

11 3.2.24.04 Providing tack coat with 60/70 or 80/100 penetration grade sqm Ch:0+000-1+000 1000 3 3000 1 3000

straight run bitumen complying with the requirements of 3000 52.48 157440

ASTM/AASHTO applied by mechanical @0.50kg/m2 and at a

temperature between 140°C and 160°C including heating

bitumen, surface cleaning, etc. all complete as per direction of

the E-I-C.

12 3.2.34 7mm thick compacted pre-mixed bituminous seal coat to be sqm Ch:0+000-1+000 1000 3 3000 1 3000

prepared using 6.33mm down crushed stone of gradation as 3000 117.4 352200

specified in the relevant item of Road Design Standards –

2005, mixed with 80/100 or 60/70 penetration grade @96kg.

Of bitumen per m3 aggregate. The bitumen and chips shall be

Page 211: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

18

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

separately heated to a temperature 140°C – 155°C and 150°C

– 170°C respectively. The mixing shall be done at

temperaturebetween 140°C – 160°C at a separate place away

from the fire. The mixture of bitumen and chips so prepared

shall be laid uniformly on the road surface in appropriate

layer so as to produce the specified compacted thickness,

rolling at a temperature not bellow 130°C with appropriate

Steel Drum Roller (1-3 tons) & pneumatic multiple tire roller

(8-10 tons) to the desired compaction and blinding with dry

sand (Min FM-0.80) @0.005m3 per m2 of road surface,

including supplying of all materials, their carriage, labourers

tools and equipment etc. all complete as per direction of the

13 3.2.56.01 Palisading work with double pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 3m long, 0.9m 50 4638.49 231924.5

c/c to be driven 2/3rd of the total length (3m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

14 3.2.56.02 Palisading work with single pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 2m long, 0.9m 50 2793.86 139693

c/c to be driven 2/3rd of the total length (2m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

15 5.2 Suppying,fittings sign board (6'-0"x4'-0") fitted with strong no 1 2 2

Bamboo post at suitable place in the working area & writing 2 2500 5000

the name of project.contract amount & year of construction

etc.by synthetic enamel paint as per direction of the Engineer

Page 212: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

19

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

in charge.

16 5.20.2 Preparation of Tender & Publishing as per PPR-2008 LS 1 5000 5000

TOTAL AMOUNT: 6 504 426.9

SAY: 6 504 427.0

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Sixty-Five Lac Four Thousand Four Hundred Twenty-Seven) Only

Page 213: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

20

A. RCC Main Stair

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 5.20.2 Preparation of Tender & Publishing as per PPR-2008 LS 1 5000 5000

2 2.3.04.a Providing and maintaining fully equipped field office with LS 1 15000 15000

necessary furniture, office and survey equipment, etc. all

complete including removal of structures and clearing the site

on completion of the work. All materials and equipment shall

be the property of the contractor.

3 4.1.02 Making earthen ring/cross bundh of required height and LS 1 40000 40000

width to prevent water from entering in the working area for

any type of foundation with earth arranged and carried by

the contractor including bullah/bamboo palisading and

double tarja mat/drum sheets walling as and where

necessary, maintaining the same throughout the working

period, filling by throwing earth in layers, removal of

structure totally on completion of the bridge, etc. all complete

as per requirement and instruction of the E-I-C.

4 4.1.03 Earth work in excavation in foundation trenches in all sorts of cum pile cape 3 1.55 0.8 3.72 3 11.16

soil except rocky, gravelly, slushy or organic type, up to a 11.16 85.08 949.49

depth of 2m to the lines, grades and elevation as shown on

the drawing, removing boulders, logs and other

objectionable materials, clearing all loose materials, disposing

of all excavated materials to a safe distance designated by the

E-I-C for an initial lead of 20m, and cut to a firm surface

including bailing out water, removal of spoils to a safe

distance, back filling of sites of trenches up to original level,

shoring if necessary etc. all complete as per requirement and

instruction of the E-I-C. Back-filled materials shall be

Detailed Estimation of a Typical Ghat Facility

(See Appendix xx for relevant structural drawings)

Page 214: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

21

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

compacted to a density comparable with the adjacent

5 4.1.07 Pumping and bailing out water/de-watering of work site LS 1 10000 10000

including supply, operation and maintenance of requisite

number of water pumps. It should be carried out in such a

manner as to preclude possibilities of the movement of water

through or alongside any concrete being placed, etc. all

complete as per direction of E-I-C.

6 4.1.08 Sand filling on the prepared foundation bed with sand of cum pile cape 3 1.55 0.15 0.698 3 2.094

minimum FM 0.80 in difficult areas with 150mm in thickness in 2.094 771.76 1616.07

each layer including supplying, placing in conformity with the

profile and level as per design including watering,

compaction, etc. all complete as per direction of the E-I-C

7 4.1.09 Single layer brick flat soling with 1st class or picked kiln sqm pile cape 3 1.55 4.65 3 13.95

burnt bricks in foundation, filling the interstices tightly with 13.95 269.09 3753.81

sand of minimum FM 0.50, watering, leveling, dressing, etc. all

complete as per instruction of the E-I-C.

8 4.1.10.01.2 Cement concrete work in foundation with Portland cement, cum pile cape 3 1.55 0.075 0.349 3 1.047

sand (minimum FM 1.80) and 1st class/picked brick chips 1.047 6569.92 6878.71

20mm down graded (LAA value not exceeding 40), including

shuttering, mixing by concrete mixer machine, casting, laying

compacting and curing for the requisite period breaking

bricks into chips etc. all complete as per direction of the E-I-

C. Cylinder crushing strength of concrete should not be less

than 170kg/cm2 at 28 days of curing (Suggested Mix

Proportion 1:2:4). Additional quantity of cement to be added

if required to attain the strength at the contractors own cost.

9 4.1.10.02.1 Reinforced cement concrete work in well caps, pile caps, cum pile cape 3 1.55 0.5 2.325 3 6.975

bearing sheets, abutment base, etc. with Portland cement, pier 0.67 (3.14x0.45x0.4 0.107 6 0.642

sand (minimum FM 1.80) and 20mm down well graded 5)/4

crushed stone chips (Preferably stone chips from pier cape 3 0.8 0.45 1.08 3 3.24

Page 215: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

22

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

Madhyapara, Dinajpur), (LAA value not exceeding 30), 10.857 8852.89 96115.83

including shuttering, mixing by concrete mixer machine

casting, laying, compacting and curing, for 28 days, breaking

stone boulders into chips etc. all complete as per direction of

the E-I-C but excluding cost of reinforcement. Cylinder

crushing strength of concrete should not be less than

210kg/cm2 at 28 days of curing (suggested mix proportion

1:2:4). Additional quantity of cement to be added if required

to attain the strength at the contractor's own cost.

10 4.1.10.03.1 Reinforced cement concrete work in pre-cast RCC piles and cum pre-cast pile 8.25 0.225 0.225 0.418 24 10.032

pile heads with Portland cement, sand (minimum FM 1.80) 10.032 10226.5 102592.55

and 20mm down well graded crushed stone chips (Preferably

stone chips from Madhyapara, Dinajpur), (LAA value not

exceeding 30), including shuttering, mixing by concrete mixer

machine, casting, laying compacting, curing for the requisite

period breaking stone boulders into chips etc. all complete as

per direction of the E-I-C but excluding the cost of

reinforcement. Strength of concrete should not be less than

250kg/cm2 (suggested mix proportion 1:1.5:3). Additional

quantity of cement to be added if required to attain the

strength to be provided by the contractor at his own cost.

11 4.1.11.01.1 Labour for driving pre-cast RCC piles in any type of soil, m Labour charge driven 6 6 24 144

handling and keeping in position and driving with suitable 144 483.75 69660

monkey to the required depth including fitting and fixing steel

cap, etc. all complete as per direction of E-I-C.

225mmx225mm; From 0m to 6m

12 4.1.11.01.2 Labour for driving pre-cast RCC piles in any type of soil, m Labour charge driven 2.25 2.25 24 54

handling and keeping in position and driving with suitable 54 644.43 34799.22

monkey to the required depth including fitting and fixing steel

cap, etc. all complete as per direction of E-I-C.

Page 216: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

23

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

225mmx225mm; From 6m to 12m and above

13 4.1.24 Labour for breaking head of cast-in-situ bored pile/pre-cast cum Breaking 0.225 0.225 0.45 0.023 24 0.552

pile up to required length by any means and removing the 0.552 3967.29 2189.94

dismantled materials, such as, concrete to a safe distance

including scrapping and removing concrete from steel/MS

rods, preparation and making of platform where necessary,

carrying, all sorts of handling, stacking the same properly

after clearing, leveling and dressing the site and clearing the

river bed, etc. all complete as per direction of the E-I-C.

(Measurement will be given for the actual pile head volume to

14 5.05.17.05. Reinforced cement concrete works (1:2:4) to give a minimum cum Stair landing 3 1.075 0.2 0.645 1 0.645

Cylinder strength of 210kg/cm2 concrete from a machine 3 0.825 0.2 0.495 1 0.495

mixed typical batch with fresh cement, best quality coarse Beam 3 0.8 0.38 0.912 1 0.912

sand (minimum FM 2.5 and 20mm down graded crushed 3 1.2 0.38 1.368 1 1.368

stone chips (Preferably stone chips from Madhyapara, 3 0.4 0.34 0.408 1 0.408

Dinajpur) in/c cost of breaking chips, screening through Waist Slab 4.246 3 0.2 2.548 1 2.548

proper sieves, cleaning and washing thoroughly, centering, Step 3.893 3 0.2 2.336 1 2.336

shuttering with MS sheet and steel form, making shuttering Side Beam 3 0.325/2 0.14 0.068 23 1.564

fully leak proof, placing of reinforcement cage in position, Ground Floor 12.459 0.25 0.16 0.498 2 0.996

mixing the aggregates with mixer machine, casting in steel 11.272 10773.9 121443.18

forms, compacting by Mechanical vibrators and tapered rods

and curing for 28 days etc. all complete as per direction of the

E-I-C (Excluding the cost of reinforcements and its

fabrication) etc. all complete as per direction of the E-I-C.

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed

breadth and width of ribs to be measured only).

15 4.2.06.02 Supplying and fabrication of M.S High strength deformed kg 20mm dia MS Rod 699.5 1 699.5

bar/ Twisted bar reinforcement of required size and length for 16mm dia MS Rod 2414.18 1 2414.18

all types of RCC work including straightening the rod, 12mm dia MS Rod 244.16 1 244.16

removing ruts, cleaning, cutting, hooking, bending, binding 10mm dia Ms Rod 625.12 1 625.12

Page 217: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

24

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

with supply of 22 B.W.G. GI wire, placing in position, 8mm dia MS Rod 1039.68 1 1039.68

including lapping, spacing and securing them in position by 5022.64 67.96 341338.61

concrete blocks (1:1), metal chairs, etc. complete including

cost of all materials, labour, local handling, laboratory test,

incidentals necessary to complete the work as per

specifications, drawings and direction of the Engineer.

Laboratory test for physical property, strength, elongation%

& bend to be performed as per ASTM. (Measurement will be

based on standard weight of 490 lbs./ft3 Chairs, laps and

separators will not be measures for payment. The cost of

these will be included in the unit rate)

16 4.3.04 Providing nosing with MS angles (75mmx75mmx6mm) etc. kg Nosing 20.4 5 102

including cost of all materials, welding, carrying, etc. all 102 123.93 12640.86

complete as per design, drawing and direction of the E-I-C.

17 4.3.04.b Providing J-Hokes for boat landing ( 16mm dia Rod, 300mm kg J-Hokes 0.711 24 17.064

Long ) etc.including cost of all materials,welding,carring,etc.all 17.064 107.38 1832.33

complete as per design,drawing and direction of the E-I-C.

18 4.4.02 Supplying C.I. Shoe of 300mm dia including fitting, fixing etc. each C.I. Shoe 24 1 24

all complete as per direction of the E/C. (Weight of each 24 1536.4 36873.6

shoe is 1.0 cwt)

19 5.049.2 Site improvement as per direction of engineer in charge LS 1 5000 5000

20 5.2 Suppying,fittings sign board (6'-0"x4'-0") fitted with strong no 1 1 1

Bamboo post at suitable place in the working area & writing 1 2500 2500

the name of project.contract amount & year of construction

etc.by synthetic enamel paint as per direction of the Engineer

in charge.

TOTAL AMOUNT: 910 184.19

SAY: 910 184.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Nine Lac Ten Thousand One Hundred Eighty-Four) Only

Page 218: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

25

B. Ghat landing & C.C Road ( Width =2.40m )

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 2.1.04.02.3 Earth filling work with specified soil in any type of cum Internal C.C Road 138.75 1 138.75

embankment including cutting, carrying, filling by throwing Landing 6 3 1.5 27 1 27

earth in layers not more than 150mm in each layer in proper Protection area 5 1.8 1.5 13.5 2 27

alignment, grade, camber and side slope in all types of soil 192.75 102.65 19785.79

except rocky, gravelly and slushy including benching not

more than 30cm in vertical and 60cm in horizontal steps along

the sides while widening any embankment, etc. all complete

as per the direction of E-I-C upto lead 20m. Payment will be

made on compacted volume. Upto 3.50m lift from the toe of embankment

2 2.1.08.01 Manual compaction of earth in 150mm thick compacted layers cum 192.75 1 192.75

by breaking clods to a maximum size of 25mm using wooden 192.75 25.42 4899.71

drag or ladder and compacting using concrete drop hammer

(Durmus), watering or drying to obtain optimum moisture

content if necessary including supplying of wooden drag,

ladder, bamboo hammer, steel/concrete hammer and other

requisite tools, etc. all complete as per direction of the E-I-C.

85% compaction of the maximum dry density is to be

obtained by the standard compaction test (Rate is for each

layer of 150mm thick)

3 3.1.03 Earth work in box cutting on road crest up to 450mm depth sqm Box 25 2.65 66.25 1 66.25

with proper grade, camber and alignment maintaining super 6 3 18 1 18

elevation on curves, removing soil to a safe distance, 84.25 46.74 3937.85

spreading the excavated earth on road flanks and slopes

uniformly including leveling, dressing, watering, compacting

the sub-grade by manual labour, etc. all complete as per

direction of the E-I-C.

4 3.1.06.01 Sand (FM 0.80) filling on the road bed in the improved sub- cum Box 25 2.65 0.15 9.938 1 9.938

grade with sand free from dust, earth, other vegetable 6 3 0.25 4.5 1 4.5

growth and foreign materials including supplying all materials, 14.438 653.99 9442.31

Page 219: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

26

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

spreading, watering, compacting by appropriate mechanical

means to obtain a minimum soaked CBR 8% at minimum

compaction 98% of MDD (Modified), etc. all complete as per

direction of the E-I-C.

5 3.2.11.01 Single layer brick flat soling with 1st class or picked bricks, sqm Box 25 2.4 60 1 60

true to level, camber/super elevation and grade including 6 3 18 1 18

carrying bricks, filling the interstices tightly with sand of 78 270.8 21122.4

minimum FM 0.80, etc. all complete as per direction of the E-I-C.

6 3.2.15.02 Brick on end edging (125mm across) with 1st class/picked m Edging 25 25 2 50

bricks including cutting trenches true to level & grade 4.2 4.2 2 8.4

including removing earth, re-filling & ramming the sides 58.4 120.86 7058.22

properly & filling the gaps with local sand, etc. all complete as

per direction of the E-I-C.

7 5.03.09 Providing polythene sheet (0.18mm thick) on floor in ground sqm Polythene sheet 25 2.4 60 1 60

floor underneath the cement concrete, etc. all complete as 6 3 18 1 18

per specifications and direction of the E-I-C. Sand of 78 17.81 1389.18

minimum FM 1.2 to be used.

8 5.03.05 Mass concrete work in foundation with Portland cement, cum C.C work 25 2.4 0.1 6 1 6

sand (minimum FM 1.80) and 1st class/picked brick chips 6 3 0.15 2.7 1 2.7

20mm down graded (LAA value not exceeding 40), including 8.7 6569.92 57158.3

shuttering, mixing by concrete mixer machine, casting, laying

compacting and curing for the requisite period breaking

bricks into chips etc. all complete as per direction of the E-I-

C. Cylinder crushing strength of concrete should not be less

than 170kg/cm2 at 28 days of curing (suggested mix

proportion 1:2:4). Additional quantity of cement to be added

if required to attain the strength at the contractors own cost.

TOTAL AMOUNT: 124 793.75

SAY: 124 794.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (One Lac Twenty-Four Thousand Seven Hundred Ninety-Four) Only

Page 220: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

27

C. Earth Protection work of Brick Toe wall with Pre-Cast RCC pile

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 4.1.04 Earth work in excavation in foundation trenches in all sorts of cum 8 1 0.8 6.4 2 12.8

rocky, gravelly, slushy or organic type, up to a depth of 2m 0 1 0

to the lines, grades and elevation as shown on the drawing, 12.8 115.58 1479.42

removing boulders, logs and other objectionable materials,

clearing all loose materials, disposing of all excavated materials

to a safe distance designated by the E-I-C for an initial lead

of 20m, and cut to a firm surface including bailing out water,

removal of spoils to a safe distance, back filling of sites of

trenches up to original level, shoring if necessary etc. all

complete as per requirement and instruction of the E-I-C.

Back-filled materials shall be compacted to a density

comparable with the adjacent undisturbed material.

2 4.1.10.01.1 Cement concrete work in foundation with Portland cement, cum 8 0.5 0.075 0.3 2 0.6

sand (minimum FM 1.80) and 1st class/picked brick chips 0.6 5566.16 3339.7

20mm down graded (LAA value not exceeding 40), including

shuttering, mixing by concrete mixer machine, casting, laying

compacting and curing for the requisite period breaking

bricks into chips etc. all complete as per direction of the E-I-

C. Cylinder crushing strength of concrete should not be less

than 105kg/cm2 at 28 days of curing (Suggested Mix

Proportion 1:3:6). Additional quantity of cement to be added

if required to attain the strength at the contractors own cost.

3 4.1.10.03.1 Reinforced cement concrete work in pre-cast RCC piles and cum 3.5 0.15 0.15 0.079 18 1.422

pile heads with Portland cement, sand (minimum FM 1.80) 1.422 10226.5 14542.13

and 20mm down well graded crushed stone chips (Preferably

stone chips from Madhyapara, Dinajpur), (LAA value not

exceeding 30), including shuttering, mixing by concrete mixer

machine, casting, laying compacting, curing for the requisite

period breaking stone boulders into chips etc. all complete as

Page 221: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

28

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

per direction of the E-I-C but excluding the cost of

reinforcement. Strength of concrete should not be less than

250kg/cm2 (suggested mix proportion 1:1.5:3). Additional

quantity of cement to be added if required to attain the

strength to be provided by the contractor at his own cost.

4 4.1.10.04.2 Pre-cast driven 150mmx150mm pile with reinforced cement m 3.5 3.5 18 63

concrete having minimum cylinder crushing strength of 63 129.06 8130.78

305kg/cm2 at 28 days (suggested mix proportion 1:1.25:2.5)

with best quality fresh cement, best quality Sylhet sand

(minimum FM 2.5) and best quality 20mm down graded

crushed stone chips (Preferably stone chips from

Madhyapara, Dinajpur), screening through proper sieves,

cleaning and washing thoroughly, centering and shuttering

with MS sheet and steel form, placing of reinforcement cage

in position, mixing the aggregates with mixer machine, casting

in steel forms, using concrete or similar suitable chemicals,

compacting by mechanical vibrators and tapered rods and

curing for 28 days etc. all complete as per design & drawing

fitting and fixing the pile cap, driving the pile upto the design

depth as per standard practice or specified method, providing

all equipment, labour, materials including carrying etc. all

complete as per design, drawing and direction of the E-I-C.

(Excluding the cost of reinforcement and its fabrication)

Cost of driving (Size-150mmx150mm) up to 6 m

5 4.1.14.01 First class brick works in cement mortar (1:4) in staining of cum Brick wall 8 0.5 0.5 2 2 4

wells with sand (minimum FM 1.50) and cement, cutting 8 0.375 0.5 1.5 2 3

bricks to required sizes, hoisting and keeping in position the 8 0.25 1 2 2 4

MS bond rods and finished with flush pointing joints, 11 5019.12 55210.32

watering, etc. complete including cost of all materials but

excluding cost of MS bond rods and bottle nuts, etc. all

Page 222: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

29

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

complete as per direction of the E-I-C.

6 4.2.06.02 Supplying and fabrication of M.S High strength deformed kg 337 1 337

bar/ Twisted bar reinforcement of required size and length for 337 67.96 22902.52

all types of RCC work including straightening the rod,

removing ruts, cleaning, cutting, hooking, bending, binding

with supply of 22 B.W.G. GI wire, placing in position,

including lapping, spacing and securing them in position by

concrete blocks (1:1), metal chairs, etc. complete including

cost of all materials, labour, local handling, laboratory test,

incidentals necessary to complete the work as per

specifications, drawings and direction of the Engineer.

Laboratory test for physical property, strength, elongation%

& bend to be performed as per ASTM. (Measurement will be

based on standard weight of 490 lbs./ft3 Chairs, laps and

separators will not be measures for payment. The cost of

these will be included in the unit rate)

7 5.12.01 Minimum 12mm thick cement plaster (1:4) to dado and plinth sqm 8 1.5 12 2 24

wall up to 150mm below ground level with neat cement 1.5 0.3 0.45 18 8.1

finishing in/c washing of sand, finishing the edges and 32.1 179.52 5762.59

corners and curing for the requisite period etc. all complete as

per direction of the E-I-C (Sand of minimum FM 1.2 be used).

TOTAL AMOUNT: 111 367.46

SAY: 111 367.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (One Lac Eleven Thousand Three Hundred Sixty-Seven) Only

Total Construction Cost of Ghat (Main Stair, Landing & Access rd and Protection work): 1 146 345

In Word : Taka (Eleven Lac Forty Six Thousand Three Hundred Forty-Five) Only

Page 223: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

30

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 2.1.01 Clearing and grubbing by removal and disposal of LS 1 7000 7000

everything above ground level including overhanging

branches, removing of all foundation stumps, embedded logs,

tree roots and other material either to a depth of 0.3m below

the proposed surface elevation or to the level as shown on

the drawing, disposing of all materials resulting from clearing

and grubbing at a safe distance designated by the E-I-C, etc.

2 2.1.04.01 Earth filling work with specified soil in any type of cum Qnt from Earth calcultion 4000 1 4000

embankment including cutting, carrying, filling by throwing sheet

earth in layers not more than 150mm in each layer in proper Deduction for Box 1000 2.4 0.25 600 1 (-) 600

alignment, grade, camber and side slope in all types of soil 3400 102.65 349010

except rocky, gravelly and slushy including benching not

more than 30cm in vertical and 60cm in horizontal steps along

the sides while widening any embankment, etc. all complete

as per the direction of E-I-C. Earth shall be arranged by the

contractor at his own cost and it will include all necessary lead

& lift. Payment will be made on compacted volume.

3 2.1.08.01 Manual compaction of earth in 150mm thick compacted layers cum 4000 1 4000

by breaking clods to a maximum size of 25mm using wooden 4000 25.42 101680

drag or ladder and compacting using concrete drop hammer

(Durmus), watering or drying to obtain optimum moisture

content if necessary including supplying of wooden drag,

ladder, bamboo hammer, steel/concrete hammer and other

requisite tools, etc. all complete as per direction of the E-I-C.

85% compaction of the maximum dry density is to be

obtained by the standard compaction test (Rate is for each

layer of 150mm thick)

Detailed Estimation of Improvement of RCC Road without BFS (VR)

(See Appendix xx for relevant structural drawings)

Page 224: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

31

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

4 3.1.03 Earth work in box cutting on road crest up to 450mm depth sqm Ch:0+000-1+000 1000 2.4 2400 1 2400

with proper grade, camber and alignment maintaining super 2400 46.74 112176

elevation on curves, removing soil to a safe distance,

spreading the excavated earth on road flanks and slopes

uniformly including leveling, dressing, watering, compacting

the sub-grade by manual labour, etc. all complete as per

direction of the E-I-C.

5 3.1.06.02 Sand (FM 0.50) filling on the road bed in the improved sub- cum Ch:0+000-1+000 1000 2.15 0.1 215 1 215

grade with sand free from dust, earth, other vegetable 215 490.03 105356.45

growth and foreign materials including supplying all materials,

spreading, watering, compacting by appropriate mechanical

means to obtain a minimum soaked CBR 8% at minimum

compaction 98% of MDD (Modified), etc. all complete as per

direction of the E-I-C.

6 5.03.09 Providing polythene sheet (0.18mm thick) on floor in ground sqm Ch:0+000-1+000 1000 2.15 2150 1 2150

floor underneath the cement concrete, etc. all complete as 2150 17.81 38291.5

per specifications and direction of the E-I-C. Sand of

minimum FM 1.2 to be used.

7 4.2.03.01.1 Reinforced Cement Concrete work in bottom and top slab of cum Ch:0+000-1+000 1000 2.15 0.15 322.5 1 322.5

box culvert of any height with stone chips (Preferably stone 322.5 8357.91 2695425.98

chips from Madhyapara, Dinajpur), sand (minimum FM 1.80)

and cement having minimum 28 days ultimate cylinder

crushing strength of 210kg/cm2 (suggested mix proportion

1:2:4) excluding cost of reinforcement and its fabrication but

including cost of all other materials, shuttering, casting, curing

for 28 days and all incidental charges, etc. complete in all

respect as per direction of the E-I-C.

Bottom slab and approach slab

8 4.2.06.02 Supplying and fabrication of M.S High strength deformed kg 13464 1 13464

bar/ Twisted bar reinforcement of required size and length for 13464 67.96 915013.44

Page 225: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

32

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

all types of RCC work including straightening the rod,

removing ruts, cleaning, cutting, hooking, bending, binding

with supply of 22 B.W.G. GI wire, placing in position,

including lapping, spacing and securing them in position by

concrete blocks (1:1), metal chairs, etc. complete including

cost of all materials, labour, local handling, laboratory test,

incidentals necessary to complete the work as per

specifications, drawings and direction of the Engineer.

Laboratory test for physical property, strength, elongation%

& bend to be performed as per ASTM. (Measurement will be

based on standard weight of 490 lbs./ft3 Chairs, laps and

separators will not be measures for payment. The cost of

these will be included in the unit rate)

9 3.2.15.02 Brick on end edging (125mm across) with 1st class/picked m Ch:0+000-1+000 1000 1000 2 2000

bricks including cutting trenches true to level & grade 2000 120.86 241720

including removing earth, re-filling & ramming the sides

properly & filling the gaps with local sand, etc. all complete as

per direction of the E-I-C.

10 3.2.56.01 Palisading work with double pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 3m long, 0.9m 50 4638.49 231924.5

c/c to be driven 2/3rd of the total length (3m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

11 3.2.56.02 Palisading work with single pre-cast plate (1150mmx600mm) m 50 50 1 50

fitted with RCC (1:2:4) post of 150mmx150mm, 2m long, 0.9m 50 2793.86 139693

c/c to be driven 2/3rd of the total length (2m) of the post

made by 20mm down graded brick chips. Pre-cast plate to be

fitted with RCC post fixed necessary nuts and bolts at driving

Page 226: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8B

33

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

of post supplying all necessary nuts and bolts etc. Complete

as per direction of E-I-C.

12 5.2 Suppying,fittings sign board (6'-0"x4'-0") fitted with strong no 1 2 2

Bamboo post at suitable place in the working area & writing 2 2500 5000

the name of project.contract amount & year of construction

etc.by synthetic enamel paint as per direction of the Engineer

in charge.

13 5.20.2 Preparation of Tender & Publishing as per PPR-2008 LS 1 5000 5000

TOTAL AMOUNT: 4 947 290.87

SAY: 4 947 291.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Forty-Nine Lac Forty-Seven Thousand Two Hundred Ninety-One) Only

Page 227: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 228: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8C

Annex 8C

Unit Costs: Road and Market Infrastructure

Page 229: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 230: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8C

1

Annex 8C

Revised Unit Costs: Roads

Component 1 : Improved Road Connectivity

As per ADB design considerations, the transport infrastructure costs for Scenario B and Scenario C with climate resilient and adaptation features are estimated as follows:

I. Estimation of Unit Costs without full Climate Resilience Option (Scenario B)

Union Road (UNR) – modified LGED design type 8

Overall crest width 5.50m Unsealed verge 1.25m each side Carriageway 3.0m

A. Basic Pavement Cost for BC Surface (without Drainage Structures)

Item Length (m)

Thickness (m)

Width (m)

Quantity Unit Rate BDT*

Cost/km (BDT)

Improved Subgrade 1000 0.25 5.5 1375 m3 701.00 963,875

Sand-Aggregate Sub-base 1000 0.15 3.5 525 m3 3400.00 1,785,000

Brick Edging (both sides) 1000 2000 m 142.28 284,560

Base Aggregate (WBM) 1000 0.15 3 450 m3 4326.00 1,946,700

Prime Coat 1000 3 3000 m2 112.00 336,000

25mm Bituminous Carpet 1000 0.025 3 3000 m2 408.32 1,224,960

7mm Bituminous Seal 1000 0.007 3 3000 m2 137.65 412,950

Shoulders (Sub-base level) 1000 0.15 2 300 m3 130.00 39,000

Shoulders 1000 0.182 2.4 436.8 m3 130.00 56,784

Basic Pavement Cost 7,049,829

* LGED Schedule of Rates - July 2012 B. Engineering Cost for B-type Climate Proofing

Item Description Quantity Unit Rate BDT* Cost/km

(BDT)

Basic Pavement Cost (See A above)

Standard 0.925 km 7,049,829 6,521,092

Resilient Pavement Concrete (RCC) full width 0.075 km 10,045,045 753,378

Earthworks Protection (1) Turf (grass) 4000 m2 15.50 62,000

Earthworks Protection (2) Shrub (virtibra) 2000 m2 86.60 173,200

Earthworks Protection (3) Palisade + concrete 100 m 7700 770,000

Tree Plantation 750 nos. 25.0 18,750

Plantation Caretaking LCS based length-man 24 person-month

3600 86,400

Total Engineering Cost 8,384,820

* LGED Schedule of Rates - July 2012

Page 231: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8C

2

C. Road Safety and Social Safeguard Cost

Item Quantity Unit Rate BDT* Cost/km (BDT)

Site Facilities, Traffic Control and Sign Board LS LS 75,000 75,000

Road Safety:

Guard Post 60 nos. 2,467 148,020

KM Post 1 no. 14,675 14,675

Traffic Sign 6 nos. 6,793 40,758

Name Post 1 no. 2,760 2,760

Reflector painting & marking 8 sqm 1,200 9,600

Environment:

Dust control, toilet, tube-well, safety tools etc. LS LS 50,000 50,000

Cost for passing place 2 nos. 160,000 320,000

Sub-total 660,813

* LGED Schedule of Rates - July 2012

Total Unit Cost for Scenario B

Total (B+C) 9,045,633

Lump Sump (rounded) 9,050,000

Taka Ninety lacs fifty thousand

Village Road (VR) - Typical LGED design type

Overall crest width 4.00m

Unsealed verge 0.75m each side Carriageway 2.50m

A. Basic Pavement Cost for BC Surface (without Drainage Structures)

Item Length

(m) Thickness

(m) Width (m)

Quantity Unit Rate BDT* Cost/km (BDT)

Improved Subgrade 1000 0.25 3.7 925 m3

701.00 648,425

Sand-Aggregate Sub-base 1000 0.15 3 450 m3

2634.83 1,185,674

Brick Edging 1000 2000 m

142.28 284,560

Base Aggregate (WBM) 1000 0.15 2.5 375 m3

3198.55 1,199,456

Prime Coat 1000 2.5 2500 m2

112.00 280,000

25mm Bituminous Carpet 1000 0.025 2.5 2500 m2

408.32 1,020,800

7mm Bituminous Seal 1000 0.007 2.5 2500 m2

137.65 344,125

Shoulders (Sub-base level) 1000 0.125 0.7 87.5 m3 130.00 11,375

Shoulders 1000 0.225 1.2 270 m3 130.00 35,100

Basic Pavement Cost 5,009,515

* LGED Schedule of Rates - July 2012

Page 232: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8C

3

B. Engineering Cost for B-type Climate Proofing

Item Description Quantity Unit Rate BDT* Cost/km

(BDT)

Basic Pavement Cost (See A above)

Standard km 0.925 5,009,515 4,633,801

Resilient Pavement Concrete (RCC) full width km 0.075 6,249,355 468,702

Earthworks Protection (1) Turf (grass) m2 3000 15.50

46,500

Earthworks Protection (2) Shrub (virtibra) m2 1500 87

129,900

Earthworks Protection (3) Palisade + concrete m 50 7700

385,000

Total Engineering Cost 5,663,903

* LGED Schedule of Rates - July 2012

C. Road Safety and Social Safeguard Cost

Name of Item Quantity Unit Rate BDT Cost/km (BDT)

Site Facilities, Traffic Control and Sign Board LS LS 40,000 40,000

Road Safety

Guard Post 25 nos. 2,467 61,675

KM Post 1 no. 14,675 14,675

Traffic Sign 4 nos. 6,793 27,172

Name Post 1 no. 2,760 2,760

Reflector painting & marking 6 sqm 1,200 7,200

Environment

Dust control, toilet, tube-well, safety tools etc.

LS LS 25,000 25,000

Cost for passing place 2 nos. 95,000 190,000

Sub-total 368,482

* LGED Schedule of Rates - July 2012

Total Unit Cost for Scenario B

Total (B+C) 6,032,384

Lump Sump (rounded) 6,050,000

Taka Sixty lacs fifty thousand

Estimation of Unit Costs with full Climate Resilience Option (Scenario C) As per ADB estimates, the unit costs with full climate resilience option or scenario C are as follows:

Union Road – modified LGED design type 8

Overall crest width 5.50m

Unsealed verge 1.25m each side Carriageway 3.0m

Page 233: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8C

4

A. Standard Pavements Costs: Union Road Modified Type 8 (without Drainage

Structures)

Item Length

(m) Thickness

(m) Width (m)

Amount Unit Rate BDT

Cost/km (BDT)

Improved Subgrade 1000 0.25 5.5 1375 m3 660 907,500

Sand-Aggregate Sub-base 1000 0.15 3.5 525 m3 3400 1,785,000

Brick Edging 1000 2000 m 130 260,000

Base Aggregate 1000 0.15 3.0 450 m3 3600 1,620,000

Prime Coat 1000 3.0 3000 m2 100 300,000

25mm Bituminous Carpet 1000 0.025 3.0 3000 m2 350 1,050,000

Bituminous Seal with Tack Coat 1000 0.007 3.0 3000 m2 180 540,000

Shoulders (Sub-base level) 1000 0.15 2.0 300 m3 130 39,000

Shoulders 1000 0.182 2.4 436.8 m3 130 56,784

Total Standard Pavement 6,558,284

B. Total Engineering Cost Excluding Structures: Union Road Modified Type 8

Item Description Unit Amount/km Rate BDT Cost/km

(BDT)

Pavement Standard km 0.925 6,558,284 6,066,413

Resilient Pavement Concrete full width km 0.075 9,837,426 737,807

Earthworks preparation Additional width 2x3m m2 6000 25 150,000

Earthworks Additional m3 4000 120 480,000

Earthworks Protection (1) Turf m2 4240 14 59,360

Earthworks Protection (2) Special grass/shrub m2 2400 35 84,000

Earthworks Protection (4) Brick gabion m2 1200 1,000 1,200,000

Earthworks Protection (3) Palisade + concrete m 150 7,700 1,155,000

Total Cost 9,932,580

C. Total Engineering Cost for Each Union Road Passing Place

Item Length

(m) Thickness

(m) Width (m)

Amount Unit Rate BDT

Cost BDT

Improved Subgrade 27.0 0.25 2.5 16.88 m3 660 11,138

Sand-Aggregate Sub-base 27.0 0.15 2.5 10.13 m3 3400 34,425

Brick Edging 12.0 12.00 m 130 1,560

Base Aggregate 27.0 0.15 2.5 10.13 m3 3600 36,450

Prime Coat 27.0 2.5 67.50 m2 100 6,750

25mm Bituminous Carpet 27.0 0.025 2.5 67.50 m2 350 23,625

Bituminous Seal with Tack Coat 27.0 0.007 2.5 67.50 m2 180 12,150

Shoulders (Sub-base level) 12.0 0.15 2 3.60 m3 130 468

Shoulders 12.0 0.182 2.5 5.46 m3 130 710

Total Standard Pavement 127,275

Item Description Unit Amount Rate BDT Cost BDT

Standard Pavement Standard km 127,275

Earthworks preparation Additional width m2 67.5 25 1,688

Earthworks Additional m3 202.5 120 24,300

Earthworks Protection (1) Additional Turf m2 10 14 140

Total Cost 153,403

Page 234: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8C

5

Village Road with HBB Surfacing

Overall crest width 4.00m Unsealed verge 0.75m each side Carriageway 2.50m

A. Standard Pavements Costs: Village Road HBB Surfacing (without Drainage

Structures)

Item Length

(m) Thickness

(m) Width (m)

Amount Unit Rate BDT Cost/km (BDT)

Improved Subgrade 1000 0.25 4.0 1000 m3 660 660,000

Sand-Aggregate Sub-base 1000 0.125 3.0 375 m3 3400 1,275,000

Brick edging 1000 2000 m 130 260,000 Brick soling 1000 0.075 2.5 2500 m2 270 675,000

Sand cushion (included) 1000 2.5 m2 100 HBB 1000 0.125 2.5 2500 m2 460 1,150,000

Shoulders (Sub-base level) 1000 0.125 1.0 125 m3 130 16,250

Shoulders 1000 0.225 1.5 337.5 m3 130 43,875

Total Standard Pavement 4,080,125

B. Total Engineering Cost Excluding Structures: Village Road HBB Surfacing

Item Description Unit Amount/km Rate BDT Cost/Km

(BDT)

Standard Pavement Standard km 0.975 4,080,125 3,978,122

Resilient Pavement Concrete full width km 0.025 6,120,188 153,005

Earthworks preparation Additional width 2x3m m2 5000 25 125,000

Earthworks Additional m3 4000 120 480,000

Earthworks Protection (1) Turf m2 4000 14 56,000

Earthworks Protection (2) Special grass/shrub m2 2400 35 84,000

Earthworks Protection (3) Brick gabion m2 1520 1,000 1,520,000

Earthworks Protection (4) Palisade + concrete m 50 7,700 385,000

Total Cost 6,781,127

C. Total Engineering Cost for Each Village Road Passing Place

Item Length

(m) Thickness

(m) Width (m)

Amount Unit Rate BDT

Cost BDT

Improved Subgrade 27.0 0.25 2.0 13.5 m3 660 8,910

Sand-Aggregate Sub-base 27.0 0.125 2.0 6.75 m3 3400 22,950

Brick edging 12.0 12 m 130 1,560

Brick soling 27.0 0.075 2.0 54 m2 270 14,580

Sand cushion (included) 27.0 2.0 m2 100 -

HBB 27.0 0.125 2.0 54 m2 460 24,840

Shoulders (Sub-base level) 12.0 0.125 1.0 1.5 m3 130 195

Shoulders 12 0.225 1.5 4.05 m3 130 527

Total Standard Pavement 73,562

Item Description Unit Amount Rate BDT Cost BDT

Earthworks preparation Additional width m2 54 25 1,350

Earthworks Additional m3 135 120 16,200

Earthworks Protection (1) Turf m2 10 14 140

Total Cost 91,252

According to ADB design considerations, there would be further additional costs for following a staged construction approach of building up to ISG level and followed by the remainder of the pavement after 1-2 years are associated with the providing a sacrificial running surface of sub-base quality, only some (50%) of which will be re-used in the final construction.

Page 235: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 8C

6

D. Estimated Additional Costs for Staged Construction

EO Cost/km BDT

Item Upazila Rd Union Rd Village Road

Additional earthwork (0.5m) 330,000 330,000 240,000

Additional Sub-base (EO 50% of sub-base) 1,071,000 892,500 765,000

Total 1,401,000 1,222,500 1,005,000

Total Unit Cost for Scenario C

Items Union Road Village Road

Total Engineering cost (B) 9,932,580 6,781,127

Cost for passing place (C) 153,403 91,252

Additional cost for stage construction (D) 1,222,500 1,005,000

Total Cost 11,308,483 7,877,379

Unit Cost Summary for Scenario B (without full Climate Proofing)

Road Type Unit Basic Cost as per LGED Schedule of

rates 2012

Additional Cost for

Extra Features

Estimated Unit Cost/km (BDT)

BC Road (w-5.50m)-UNR km 7,049,829 2,000,171 9,050,000

BC Road (w-3.70)-VR km 5,009,515 1,040,485 6,050,000

RCC Road (w-5.50m)-UNR km 7,941,270 2,258,730 10,200,000

RCC Road (w-3.70)-VR km 6,021,691 1,278,309 7,300,000

Rural Block Road (w-3.7m) km 4,296,381 503,619 4,800,000

Unit Cost Summary for Scenario C (with full Climate Proofing)

Road Type Unit Basic Cost as per LGED Schedule of

rates 2012

Additional Cost for

Extra Features

Estimated Unit Cost/km (BDT)

BC Road (w-5.50m)-UNR km 7,049,829 3,950,171 11,000,000

BC Road (w-3.70)-VR km 5,009,515 2,990,485 8,000,000

RCC Road (w-5.50m)-UNR km 7,941,270 4,058,730 12,000,000

RCC Road (w-3.70)-VR km 6,021,691 2,978,309 9,000,000

Rural Block Road (w-3.7m) km 4,296,381 503,619 4,800,000

Note: See Annex 8B for detailed cost estimation.

Page 236: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9A

Annex 9A

Structural Design: Market Facilities

Page 237: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 238: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9B

Annex 9B

Structural Design: Ghats

Page 239: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 240: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9B

1

Annex 9B

Structural Design: Ghats

Page 241: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9B

2

Page 242: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9B

3

Page 243: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9B

4

Page 244: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

Annex 9C

Detailed Costs: Market Facilities

Page 245: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 246: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

1

Annex 9C

Detailed Costs: Market Facilities

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 5.02.01 Earthwork in excavation of canals, ponds, drains, etc. by cum Footing 1.71 1.71 1.2 3.509 6 21.054

excavating earth to the lines, grades and elevation as shown 1.55 1.55 1.2 2.883 3 8.649

in the drawing, filling baskets, carrying and disposing of all 7.6 0.575 0.45 1.967 2 3.934

excavated materials at a safe distance designated by the E-I-C Brick foundation (Inner 5.276 0.8 0.6 2.532 1 2.532

in all types of soils except rocky, gravelly, slushy or organic wall) 7.525 0.5 0.15 0.564 2 1.128

soil, leveling, dressing, etc. all complete for an initial excavation 6.624 0.5 0.15 0.497 1 0.497

depth of 2m and an initial lead not exceeding 20m, including 1.5 0.5 0.15 0.113 1 0.113

arranging for and supplying all necessary tools and equipment 5.874 0.8 0.6 2.82 1 2.82

at work site, etc. complete as per direction of the E-I-C. 40.727 85.08 3465.05

2 5.02.02 Sand filling in foundation trenches and inside plinth with sand cum Floor 1.975 2.088 0.3 1.237 6 7.422

(minimum FM 0.80) in 150mm layers in/c leveling, watering Veranadha floor 19.474 0.35 0.3 2.045 1 2.045

and consolidating each layer up to finished level etc. all Toilet floor 1.313 1.9 0.3 0.748 1 0.748

complete as per direction of the E-I-C. Dry density after Footing 1.21 1.21 0.075 0.11 6 0.66

compaction shall not be less than 95% of MDD. 1.05 1.05 0.075 0.083 3 0.249

Toilet foundation 5.276 0.5 0.075 0.198 1 0.198

Verandha foundation 7.024 0.375 0.075 0.198 2 0.396

5.874 0.375 0.075 0.165 1 0.165

Stair 7.525 0.5 0.075 0.282 2 0.564

6.624 0.5 0.075 0.248 1 0.248

1.5 0.5 0.075 0.056 2 0.112

Inner wall 5.874 0.5 0.075 0.22 1 0.22

13.027 810.2 10554.48

3 5.03.01 Single layer brick flat soling with 1st class or picked bricks, sqm Floor 1.975 2.088 4.124 6 24.744

true to level, camber/super elevation and grade including Veranadha floor 19.474 0.35 6.816 1 6.816

carrying bricks, filling the interstices tightly with sand of Toilet floor 1.313 1.9 2.495 1 2.495

minimum FM 0.80, etc. all complete as per direction of the E-I- Footing 1.21 1.21 1.464 6 8.784

C. 1.05 1.05 1.103 3 3.309

Detailed Estimation of a Typical RCC 6-Unit (Block @ 2.1m x 2.4m) Women Market Section with toilet

(See Appendix xx for relevant structural drawings)

Page 247: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

2

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

46.148 269.98 12459.04

4 5.03.05 Mass concrete work in foundation with Portland cement, cum Floor 1.975 2.088 0.075 0.309 6 1.854

sand (minimum FM 1.80) and 1st class/picked brick chips Veranadha floor 19.474 0.35 0.075 0.511 1 0.511

20mm down graded (LAA value not exceeding 40), including Toilet floor 1.313 1.9 0.075 0.187 1 0.187

shuttering, mixing by concrete mixer machine, casting, laying Toilet foundation 5.276 0.5 0.075 0.198 1 0.198

compacting and curing for the requisite period breaking Verandha foundation 7.024 0.375 0.075 0.198 2 0.396

bricks into chips etc. all complete as per direction of the E-I- 5.874 0.375 0.075 0.165 1 0.165

C. Cylinder crushing strength of concrete should not be less Stair 7.525 0.5 0.075 0.282 2 0.564

than 170kg/cm2 at 28 days of curing (suggested mix 6.624 0.5 0.075 0.248 1 0.248

proportion 1:2:4). Additional quantity of cement to be added 1.5 0.5 0.075 0.056 2 0.112

if required to attain the strength at the contractors own cost. Inner wall 5.874 0.5 0.075 0.22 1 0.22

4.455 6569.92 29268.99

5 5.02.05 Earth filling inside plinth in 150mm layers with earth available cum 75% of Sl-1 30.55 1 30.55

within 90m of the building site, watering, leveling and 30.55 219.99 6720.69

consolidating each layer up to finished level, etc. all complete

as per direction of the E-I-C.. Dry density after compaction

shall not be less than 90% of MDD.

6 5.04.02 Brick work with 1st class bricks in cement mortar (1:4) in cum Above Grade Beam up to 2.088 0.25 0.3 0.157 6 0.942

foundation and plinth, filling the interstices tightly with PL 5.924 0.25 0.3 0.444 3 1.332

mortar, raking out joints, cleaning and soaking bricks at least Toilet foundation 5.276 0.5 0.15 0.396 1 0.396

for 24 hours before use, washing of sand, curing for requisite 5.276 0.375 0.15 0.297 1 0.297

period, etc. all complete as per direction of the E-I-C. 5.276 0.25 0.6 0.791 1 0.791

(Minimum FM of sand: 1.2) Verandha 7.974 0.375 0.15 0.449 2 0.898

7.974 0.25 0.525 1.047 2 2.094

5.874 0.375 0.15 0.33 1 0.33

5.874 0.25 0.525 0.771 1 0.771

Stair 7.525 0.5 0.15 0.564 2 1.128

7.525 0.25 0.15 0.282 2 0.564

6.624 0.5 0.15 0.497 1 0.497

6.624 0.25 0.15 0.248 1 0.248

Page 248: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

3

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

Toilet stair 1.5 0.5 0.15 0.113 1 0.113

1.5 0.25 0.15 0.056 1 0.056

Inner wall 5.874 0.5 0.15 0.441 1 0.441

5.874 0.375 0.15 0.33 1 0.33

5.874 0.25 0.6 0.881 1 0.881

12.109 4919.32 59568.05

7 5.04.09.01 125mm brick work with 1st class bricks in cement mortar sqm Wall 2.4 2.7 6.48 6 38.88

(1:6) and making bond with connected walls in/c necessary 5.924 2.625 15.551 1 15.551

scaffolding, raking out joints, cleaning and soaking the bricks Toilet 1.5 2.1 3.15 2 6.3

at least for 24 hours before use, washing of sand, curing for Ground Floor 2.15 2.1 4.515 1 4.515

requisite period, etc. all complete as per direction of the E-I-C water Reservoir 1.05 0.6 0.63 2 1.26

for all floors. (Minimum FM of sand:1.2) deduction 0.75 2.1 1.575 -2 -3.15

H/W 0.6 0.6 0.36 -2 -0.72

62.636 674.32 42236.71

8 5.13.02 38mm thick artificial patent stone floor (1:2:4) with Portland sqm Floor 6.624 4.924 32.617 1 32.617

cement, best quality coarse sand (50% minimum FM 1.2 and Toilt floor 1.38 2.15 2.967 1 2.967

50% minimum FM 2.5) and 10mm down graded picked chips Roof 7.275 6.124 44.552 1 44.552

in/c chips screening, mixing, laying the concrete in alternate 80.136 344.74 27626.08

panels, compacting and finishing the top with neat cement,

curing for requisite period, etc. all complete as per direction

of the E-I-C.

9 5.05.01.01 Reinforced cement concrete works (1:2:4) having minimum cum Footing base 1.21 1.21 0.313 0.458 6 2.748

cylinder crushing strength 170kg/cm2 at 28 days with 1.05 1.05 1.103 3 3.309

Portland cement, best quality coarse sand (50% quantity of Column up to GL 0.057 9 0.513

sand of minimum FM 1.2 and 50% quantity of coarse sand of Above GL to Roof 0.25 0.25 3.45 0.216 9 1.944

minimum FM2.5) 20mm down graded picked brick chips in/c GB-1 & 2 5.924 0.25 0.375 0.555 3 1.665

breaking chips and screening, centering, shuttering, making GB-3 2.087 0.25 0.25 0.13 6 0.78

shuttering fully leak proof, placing of rod in position, mixing TB-1 5.924 0.25 0.375 0.555 3 1.665

the aggregates with mixer machine, pouring, casting, TB-2 2.087 0.25 0.3 0.157 6 0.942

compacting by vibrator machine and curing at least for 28 Roof 7.574 6.124 0.1 4.638 1 4.638

Page 249: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

4

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

days (excluding the cost of reinforcement and its fabrication) 2.9 1.875 0.075 0.408 1 0.408

etc. all complete as per direction of the E-I-C. 18.612 7206.69 134130.91

In individual and continuous footing of column, raft and floor

slab at plinth level.

10 5.06.01.02 Supplying and fabrication of M.S High strength deformed kg MS Rod 2810 1 2810

bar/ Twisted bar reinforcement of required size and length for 2810 67.96 190967.6

all types of RCC work in/c straightening the rod, removing

ruts, cleaning, cutting, hooking, bending, binding with

supply of 22 B.W.G. GI wire, placing in position, in/c lapping,

spacing and securing them in position by concrete blocks

(1:1), metal chairs, etc. complete in/c cost of all materials,

labour, local handling incidentals necessary to complete the

work as per specifications, drawings and direction of the E-I-

C. (Measurement will be based on standard weight of 490

lbs./ft3 Chairs, laps and separators will not be measures for

payment. The cost of these will be included in the unit rate)

M.S. Rod, deformed (grade 40) 275- grade deformed bar with

minimum fy=275 MPa: up to ground floor

11 5.049.2 Site improvement as per direction of engineer in charge LS 1 5000 5000

12 5.08.13 Supplying, fitting and fixing steel glazed window shutter with sqm H/W for toilet 0.6 0.6 0.36 1 0.36

frames as per design having ‘Z’ section (19mmx19mmx19mm) 0.36 3147.69 1133.17

in frame and ‘T’ section (19mmx19mmx3mm) for horizontal

dividers of shutters and F.I. bar (25mmx3mm) for middle

vertical members of frame in/c all cost of charges for

fabrication and manufacture by welding, riveting, etc.

supplying all essential fittings like stopper, handle, 300mm

long adjustable iron cleats, 50mm long pin hinges, 150mm

long clamps for fitting frame in/c supplying, fitting, fixing 3mm

thick glass panes by putty and painting the window with two

coats of synthetic enamel paint over a coat of anticorrosive

Page 250: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

5

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

priming, making necessary holes in wall and RCC work as

necessary, filling with CC (1:2:4:) and mending good the

damages, etc. all complete as per direction of the E-I-C and as

per drawing and design.

13 5.091.a Supply of Fittings,fixing uPVC door in position,making 8nos LS 1 5430 5430

holes in the existing wall or making special arrangement for

fixing with concrete work/royel plug and screw etc and

frame shutter hinges by clamp and lock etc.all complete as

per direction of the E-I-C.( Plastic door are Bangladeshi made

14 5.12.01 Minimum 12mm thick cement plaster (1:4) to dado and plinth sqm Outer side wall up to PL 7.174 0.45 3.228 1 3.228

wall up to 150mm below ground level with neat cement Floor 6.624 4.924 32.617 1 32.617

finishing in/c washing of sand, finishing the edges and Stair 23.174 0.45 10.428 1 10.428

corners and curing for the requisite period etc. all complete as Toilet inner wall 6.3 2.1 13.23 1 13.23

per direction of the E-I-C (Sand of minimum FM 1.2 be used). Water Reservoir 1.05 0.6 0.63 4 2.52

Stair side (0.500+0.250)/ 0.25 0.094 3 0.282

2 62.305 179.52 11184.99

15 5.12.02.01 Minimum 12mm thick cement plaster (1:6) to wall both inner sqm Wall 2.4 2.7 6.48 10 64.8

and outer surface, finishing the corner and edges in/c 2.1 2.625 5.513 6 33.078

washing of sand cleaning the surface, scaffolding and curing Toilet wall 1.5 2.1 3.15 2 6.3

for the requisite period etc. all complete as per direction of the Ground floor 2.4 2.1 5.04 2 10.08

E-I-C. (Sand of minimum FM 1.2 be used). Parapet wall 26.8 0.3 8.04 1 8.04

Deduction 0.75 2.1 1.575 -1 -1.575

H/W 0.6 0.6 0.36 -1 -0.36

120.363 143.96 17327.46

16 5.12.03.01 Minimum 6mm thick cement plaster (1:4) to ceiling RCC sqm Column 1 2.7 2.7 7 18.9

columns, beams, surface of stair case, sunshades, cornices, Roof 7.525 6.124 46.083 1 46.083

railings, drop wall, louvers, fins and finishing the corners and Toilet Roof 2.9 1.875 5.438 1 5.438

edges in/c washing of sand cleaning the surface, scaffolding Ground Floor 6.624 0.675 4.471 1 4.471

and curing for the requisite period etc. all complete as per 6.624 0.8 5.299 2 10.598

direction of the E-I-C. (Sand of minimum FM 1.2 be used). TB-1 2.088 0.65 1.357 2 2.714

Page 251: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

6

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

TB-2 2.088 0.525 1.096 4 4.384

92.588 126.33 11696.64

17 5.16.01.01 White washing three coats over a coat of priming with sqm Wall 2.4 2.7 6.48 10 64.8

slacked stone lime mixed with gums, blue. Lime mix prepared 2.1 2.625 5.512 6 33.072

at least 12 hours before use, in/c removing the floating Toilet wall 1.5 2.1 3.15 2 6.3

materials from the mixture, surface cleaning to free all foreign 2.4 2.1 5.04 2 10.08

materials before application of each coat. Applying one Parapet wall 26.8 0.3 8.04 1 8.04

vertical and one horizontal wash for each coat and successive Deduction 0.75 2.1 1.575 -1 -1.575

coat is to be applied after drying up of previous coat i/c cost H/W 0.6 0.6 0.36 -1 -0.36

of hair brush, providing necessary scaffolding and necessary Column 1 2.7 2.7 7 18.9

cleaning the plinth, floors, doors, windows, partions and Roof 7.525 6.124 46.083 1 46.083

ventilators by washing, rubbing as if necessary before and Toilet Roof 2.9 1.875 5.438 1 5.438

after the wash, polishing the surface with sand paper etc. all TB-1 6.624 0.675 4.471 1 4.471

complete for all floors i/c cost of all materials as per direction 6.624 0.8 5.299 2 10.598

TB-2 2.088 0.65 1.357 2 2.714

2.088 0.525 1.096 4 4.384

212.945 15.42 3283.61

18 5.18.07 Supplying, fitting and fixing of rolling shutter made of 24 sqm Rolling Shutter 2.088 3 6.264 2 12.528

SWG G.P. sheet unit minimum 69mm width having 10mm & 3.887 3 11.661 2 23.322

12mm dia circular folding at ends, rolled in machine, locked 1.912 3 5.736 2 11.472

together properly to form rolling shutter, top of the shutter to 47.322 4460.94 211100.6

be fitted with circular spring box made of 22 BWG sheet,

containing best quality spring made in China, nutted with

38mm GI pipe at one end and the other end nutted to shutter

in/c fitting the GI pipe again with 375mmx300mmx6mm

punkha at ends with side guide channel (side channel consist

of 50mmx100mmx6mm MS plate with 2x19mmx3mm F.I. bar,

middle channel consist of 2x150mmx6mm MS plate with

2x19mmx6mm) fixed to wall or column with MS clamps

(minimum 3x25mmx6mm), mending the damages, bottom end

Page 252: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

7

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

of shutter fitted to folded G.P. sheet (minimum 125mm width,

two layer) which is again fitted to 25mmx25mmx3mm angle,

providing handle both sides, (with F.I. bar 25mmx6mm

riveted) and locking arrangement both sides, painting two

coats with approved colour and brand of synthetic enamel

paint over a coat of priming etc. complete in all respect as per

drawing, design and as per direction of the E-I-C. (Rolling

shutter must be riveted at sides with G.P. sheet and patty).

19 7.03.03 Supplying, fitting and fixing, Bangladesh pattern BISF each Toilet 1 1 1

Standard simple type porcelain long pan (Model-323, size-

520x290x260mm) simple type of vitreous China with Siphon 1 6158.97 6158.97

and preparing the base of pan with cement concrete and with

wire net or rods including making holes in walls and floors

wherever required and mending good the damages,

supplying Porcelain Siphon (Low down) with all fittings,

fitting fixing the same in position with C.I. brackets including

supplying best quality 38mm dia PVC flush pipe with brass

coupling (not exceeding 1.80m in length), 12mm dia plastic

connection pipe with brass coupling, 12mm dia brass stop

cock, 12mm dia ball cock and pulling chain etc. all complete

as per direction of the E-I-C.

White [BISF STANDARD] long pan

(Model-314E, size-525x295x285mm, Bowl size-410x225x170mm)

20 7.05.01.01 Supplying, fitting and fixing "BISF STANDARD" glazed each Toilet 1 1 1

vitreous Wash Hand Basin hand basin (Model-213, size- 1 3296.63 3296.63

450x405x180mm, Bowl size-375x275x136mm) including fitting

fixing the same in position with heavy type C.I. brackets,

44mm dia PVC waste water pipe with brass coupling (not

exceeding 750mm in length), 12mm dia plastic connection

pipe with brass coupling, 12mm dia brass stop cock, 12mm

Page 253: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

8

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

dia C.P. pillar cock, 30mm dia C.P. Basin waste with chain

plug including making holes in walls and floors and fitting

with wooden blocks screws and mending good the damages

etc. all complete as per direction of the E-I-C.

White "BISF STANDARD

21 7.15.01 Supplying, fitting and fixing porcelain soap tray including each Toilet 1 1 1

making holes in walls and mending good the damages etc. all 1 199.6 199.6

complete as per direction of the E-I-C.

White "BISF STANDARD" (150mmx110mmx40mm size)

22 7.17.01 Supplying, fitting and fixing Glass plate Shelf (600mmx125mm) each Toilet 1 1 1

of 5mm thick glass with fancy C.P. brackets, screws and 1 608.79 608.79

frames including making holes in walls and mending good the

damages etc. all complete as per direction of the E-I-C.

Super quality

23 7.18.01 Supplying, fitting and fixing Towel rail with holder including each Toilet 1 1 1

making holes in walls and mending good the damages etc. all 1 766.18 766.18

complete as per direction of the E-I-C.

C.P. Towel rail (Size : 600mmx20mm) with C.P. holder (Super

quality)

24 7.19.02 Supplying, fitting and fixing super quality Mirror with hard each Toilet 1 1 1

boards at the back with all necessary fittings including making 1 572.78 572.78

holes in walls and mending good the damages etc. all

complete as per direction of the E-I-C

Belgium made Mirror (Size:450mmx300mm)

25 7.20.02 Supplying, fitting and fixing 5.49m long 100mm dia (inner) each Toilet 1 1 1

PVC "B" class pipe water grade (LIRA/AZIZ/ NATIONAL 1 4886.3 4886.3

POLYMER brand or equivalent) with all HCI fittings and

specials like plain bend, tees, reducing sockets, junctions,

door bends, 100mm dia cowls, anti-siphon (MAANCO

BRAND) including gasket and cement joints, PVC solution,

Page 254: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

9

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

making holes in walls and mending good the damages etc. all

complete as per direction of the E-I-C.

26 7.21.02 Supplying, fitting and fixing 3.66m long Ventilation pipe with each Toilet 1 1 1

all fittings and specials like 50mm plain bends, tees, 50mm dia 1 922.75 922.75

cowls etc. including gasket with cement joints and mending

good the damages etc. all complete as per direction of the E-I-C.

3.66m long 50mm dia PVC best quality Ventilation Pipe (B.S. 3505)

27 7.22.02.01 Supplying, fitting, fixing and laying 150mm/200mm dia PVC m Toilet 6 6 1 6

"B" class pipe water grade (LIRA / AZIZ / NATIONAL 6 1124.08 6744.48

POLYMER BRAND or equivalent) best quality sewerage pipe

including necessary fittings and joints with high class solution

and at the base and sides filling with best quality local sand all

around the pipe (not less than 25mm) upto the required

depth etc. complete as per type, plan and direction of the E-I-C.

28 7.24 Supplying, fitting and fixing 100mm dia C.I. Trap (Siphon each Toilet 1 1 1

trap or ‘P’ trap) including making holes in walls and floors 1 368.35 368.35

and mending good the damages etc. all complete as per

direction of the E-I-C.

29 7.25.06 Supplying, fitting and fixing GI pipe with all special fittings m Toilet 10 10 1 10

such as bends, elbows, sockets, reducing sockets, Tees, 10 280.69 2806.9

unions, jumnuts etc. including cutting trenches where

necessary and fitting the same with earth duly rammed and

fixing in walls with holder bats and making holes in floors and

walls and mending good the damages etc. all complete in all

respects as per direction of the E-I-C. 20mm dia GI Pipe

30 7.27.01 Supplying, fitting and fixing best quality and heavy type bib each Toilet 1 2 2

cock. 12mm dia Brass Bib Cock 2 463.43 926.86

31 7.34.01 Construction of masonry Inspection Pit (Inside each Toilet 1 1 1

measurement:600mmx600mm) with 250mm thick brick work 1 5190.92 5190.92

in cement mortar (1:4), 100mm thick RCC top slab (1:2:4)

Page 255: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

10

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

with 1% reinforcement, 450mm dia water sealed R.C.C./ M.H.

cover including necessary earth work, side filling, single layer

brick flat soling, 75mm thick Cement Concrete (1:3:6) in base

for making invert channel, 12mm thick cement plaster (1:2)

with neat cement finishing etc. all complete up to a depth of

0.75m and as per the direction of the E-I-C.

450mm dia water sealed R.C.C. Manhole Cover

32 7.39.a Construction of Ring Soak well,minimum 760mm dia each Toilet 1 2 2

ring,38mm thick ring,4-nos Ring used per soak well,One RCC 2 13942.5 27885

Cover,Highquality morter use for ring joint and earth

work,labour cost,including Vat,Tax, as per desig and

direction of the E-I-C.

33 8.01.02.04 Supplying, fitting and fixing main/sub-main switches with fuse each Market 1 1 1

on live side and neutral line on concealed iron frame 1 1542.81 1542.81

(Bangladeshi made of prior approved quality) etc. all

complete as per directions of the E-I-C.

250 Volts ICTP; 10 amps

34 8.03.01.04 Supplying, fitting and fixing energy meter with cutout teak each 1 1 1

wood board etc. all complete as per directions of E-I-C 1 6725.74 6725.74

(when the meter is not supplied by PDB).

500 Volts 3 phase; 60 amps

35 8.06.02.01 Supplying, fitting and fixing PVC insulated and sheathed m Market with toilet 100 100 1 100

round or flat wire (as per BSS 2004/61) from LT line to 100 19.18 1918

energy meter, energy meter to main switch/FDB sub-main

switch, CCB/ICDB individual lights, fans and socket outlet

points as per drawings and directions (Eastern/Paradise/Poly

cable or any equivalent prior approved quality) of the E-I-C.

PVC Insulated and non sheathed Round Single Core Cable (IYAL)

36 8.08 Supplying, fitting and fixing Distribution/Sub-Distribution sqm DB 0.75 0.6 0.45 1 0.45

board made of 18 SWG steel sheet metal enclosed with double 0.45 4978.47 2240.31

Page 256: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

11

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

cover, gray hammer painted on outside and enamel paint on

inside on rust proof prime coat with hinged front door with

lock and key arrangement for half concealed mounted board

having knock out for conduit entry and exit for 415/230V

TP&N/ SP&N operations. The board shall have solid neutral

and earth copper bus bar and also required size off 3 phase

copper bus bars. All bars shall have required number of holes

of 5mm for cable connections etc. all complete as per

drawing, design and direction of E-I-C.

37 8.09.06 Supplying, fitting and fixing 20mm thick switch board for fan each Women market 1 7 7

regulators, lighting switches two pin and at the three pin 7 21.09 147.63

socket outlets the switch board to be made of teak wood and

varnished on all sides etc. all complete as per directions of the

E-I-C. 100mmx100mm

38 8.17.04 Supplying, fitting and fixing PVC pipe for service line and m Women market & Toilet 100 100 1 100

sleeves for electrical wiring when it passes through wall etc. all 100 53.56 5356

complete as per directions of the E-I-C. 12mm dia

39 8.21.01 Supplying, fitting and fixing 250V capacitor type ceiling fan each Women market 1 7 7

complete with concealed condensers, canopies and required 7 2655.87 18591.09

length of rods, ceiling roses, wooden round blocks,

regulator, switches and required length of flexible wire etc. all

complete as per drawings and directions of the E-I-C.

1.422m sweep (best quality)

40 8.24 Supplying, fitting and fixing 5 Amps 2-pin socket with control each Women market 1 6 6

switch etc. complete as per drawing & directions of the E-I-C. 6 192.52 1155.12

41 8.25 Supplying, fitting and fixing 250 volts single phase 15 amps 3- set Market 1 6 6

pin combined switches and socket outlet (surface type) Toilet 1 1 1

mounted on beast quality locally made required size 18 SWG 7 269.4 1885.8

galvanized plain sheet board (75mm depth) etc. all complete

as per drawings and directions of the E-I-C.

Page 257: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

12

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

42 8.31 Supplying, fitting and fixing 1.22m long 40 watt fluorescent set Women market 1 12 12

tube light with necessary superior quality ballast, starter, 12 476.52 5718.24

condenser, holders, 18 SWG sheet steel stove enamel base,

etc. all complete as per drawing and directions of the E-I-C.

Each lamp is to be operated by one way switch. (Eastern or

prior approved quality)

43 8.35 Supplying fitting and fixing one way tumbler switch as per each Women market & Toilet 1 7 7

directions of the E-I-C. 7 41.89 293.23

44 8.41.02.03 Supplying, fitting and fixing the following electric lamp for each Women market & Toilet 1 2 2

garden/gate/room light and different places as per directions 2 43.48 86.96

of the E-I-C. Normal bulb 100 watt

TOTAL AMOUNT: 890 149.52

SAY: 890 150.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Eight Lac Ninety Thousand One Hundred Fifty) Only

Page 258: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

13

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 5.02.01 Earthwork in excavation of canals, ponds, drains, etc. by cum Footing 1.2 1.2 1.125 1.62 4 6.48

excavating earth to the lines, grades and elevation as shown Brick Stair 1.25 0.5 0.225 0.141 2 0.282

in the drawing, filling baskets, carrying and disposing of all 6.762 85.08 575.31

excavated materials at a safe distance designated by the E-I-C

in all types of soils except rocky, gravelly, slushy or organic

soil, leveling, dressing, etc. all complete for an initial

excavation depth of 2m and an initial lead not exceeding 20m,

including arranging for and supplying all necessary tools and

equipment at work site, etc. complete as per direction of the E-I-C.

2 5.02.02 Sand filling in foundation trenches and inside plinth with sand cum Footing 0.9 0.9 0.15 0.122 4 0.488

(minimum FM 0.80) in 150mm layers in/c leveling, watering Floor 5.25 2.575 0.3 4.056 1 4.056

and consolidating each layer up to finished level etc. all Brick stair 1.25 0.5 0.075 0.047 2 0.094

complete as per direction of the E-I-C. Dry density after 4.638 898.84 4168.82

compaction shall not be less than 95% of MDD.

3 5.03.01 Single layer brick flat soling with 1st class or picked bricks, sqm Footing 0.9 0.9 0.81 4 3.24

true to level, camber/super elevation and grade including Floor 5.25 2.575 13.519 1 13.519

carrying bricks, filling the interstices tightly with sand of Brick Stair 1.25 0.5 0.625 2 1.25

minimum FM 0.80, etc. all complete as per direction of the E-I-C. 18.009 270.8 4876.84

4 5.03.09 Providing polythene sheet (0.18mm thick) on floor in ground sqm Footing 0.9 0.9 0.81 4 3.24

floor underneath the cement concrete, etc. all complete as Floor 5.25 2.575 13.519 1 13.519

per specifications and direction of the E-I-C. Sand of Brick stair 1.25 0.5 0.625 2 1.25

minimum FM 1.2 to be used. 18.009 17.81 320.74

5 5.03.05 Mass concrete work in foundation with Portland cement, cum Footing 0.9 0.9 0.075 0.061 4 0.244

sand (minimum FM 1.80) and 1st class/picked brick chips Floor 5.75 2.575 0.075 1.11 1 1.11

20mm down graded (LAA value not exceeding 40), including Brick stair 1.2 0.5 0.075 0.045 2 0.09

shuttering, mixing by concrete mixer machine, casting, laying 1.444 6569.92 9486.96

compacting and curing for the requisite period breaking

Detailed Estimation of a Typical Toilet Block (Size : 5.75m x 3.07m )

(See Appendix xx for relevant structural drawings)

Page 259: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

14

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

bricks into chips etc. all complete as per direction of the E-I-

C. Cylinder crushing strength of concrete should not be less

than 170kg/cm2 at 28 days of curing (suggested mix

proportion 1:2:4). Additional quantity of cement to be added

if required to attain the strength at the contractors own cost.

6 5.02.05 Earth filling inside plinth in 150mm layers with earth available cum 75% of Sl no-01 5.14 1 5.14

within 90m of the building site, watering, leveling and 5.14 219.99 1130.75

consolidating each layer up to finished level, etc. all complete

as per direction of the E-I-C.. Dry density after compaction

shall not be less than 90% of MDD.

7 5.04.02 Brick work with 1st class bricks in cement mortar (1:4) in cum GL to PL 5.25 0.25 0.05 0.066 2 0.132

foundation and plinth, filling the interstices tightly with 2.575 0.25 0.2 0.129 2 0.258

mortar, raking out joints, cleaning and soaking bricks at least Brick stair 1.25 0.5 0.15 0.094 2 0.188

for 24 hours before use, washing of sand, curing for requisite 1.25 0.25 0.15 0.047 2 0.094

period, etc. all complete as per direction of the E-I-C. 0.672 4919.32 3305.78

(Minimum FM of sand: 1.2)

8 5.04.09.01 125mm brick work with 1st class bricks in cement mortar sqm Wall 5.25 2.1 11.025 2 22.05

(1:6) and making bond with connected walls in/c necessary 4.5 2.55 11.475 1 11.475

scaffolding, raking out joints, cleaning and soaking the bricks 2.575 2.4 6.18 2 12.36

at least for 24 hours before use, washing of sand, curing for Ground Floor 2.825 2.55 7.204 1 7.204

requisite period, etc. all complete as per direction of the E-I-C 1.5 2.55 3.825 3 11.475

for all floors. (Minimum FM of sand:1.2) Deduction (door) 0.75 2.1 1.575 -4 -6.3

1.25 2.1 2.625 -1 -2.625

1 2.1 2.1 -1 -2.1

H/W 0.6 0.6 0.36 -5 -1.8

51.739 674.32 34888.64

9 5.13.02 38mm thick artificial patent stone floor (1:2:4) with Portland sqm Floor 5.75 3.075 17.681 1 17.681

cement, best quality coarse sand (50% minimum FM 1.2 and Over Roof Slab 6.65 3.975 26.434 1 26.434

50% minimum FM 2.5) and 10mm down graded picked chips 44.115 344.74 15208.21

in/c chips screening, mixing, laying the concrete in alternate

Page 260: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

15

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

panels, compacting and finishing the top with neat cement,

curing for requisite period, etc. all complete as per direction

of the E-I-C.

10 5.05.01.01 Reinforced cement concrete works (1:2:4) having minimum cum Footing base 0.9 0.9 0.225 0.182 4 0.728

cylinder crushing strength 170kg/cm2 at 28 days with (0.900+0.275)/(0.900+0.275) 0.075 0.026 4 0.104

Portland cement, best quality coarse sand (50% quantity of 2 /2

sand of minimum FM 1.2 and 50% quantity of coarse sand of Column up to GL 0.275 0.275 0.525 0.04 4 0.16

minimum FM2.5) 20mm down graded picked brick chips in/c Column above GL to 0.25 0.25 3 0.188 4 0.752

breaking chips and screening, centering, shuttering, making GB-1 5.25 0.25 0.4 0.525 2 1.05

shuttering fully leak proof, placing of rod in position, mixing GB-2 2.575 0.25 0.25 0.161 2 0.322

the aggregates with mixer machine, pouring, casting, Lintel 5.25 0.125 0.15 0.098 2 0.196

compacting by vibrator machine and curing at least for 28 4.625 0.125 0.15 0.087 1 0.087

days (excluding the cost of reinforcement and its fabrication) Sunshade 0.7 0.375 (0.100+0.075 0.023 5 0.115

etc. all complete as per direction of the E-I-C. )/2

In individual and continuous footing of column, raft and floor Beam, FB-2 5.25 0.25 0.3 0.394 2 0.788

slab at plinth level. Beam, FB-1 2.575 0.25 0.15 0.097 2 0.194

Roof Slab 6.65 3.975 0.1 2.643 1 2.643

7.139 7206.69 51448.56

11 5.06.01.02 Supplying and fabrication of M.S High strength deformed kg MS Rod 1056 1 1056

bar/ Twisted bar reinforcement of required size and length for 1056 67.96 71765.76

all types of RCC work in/c straightening the rod, removing

ruts, cleaning, cutting, hooking, bending, binding with

supply of 22 B.W.G. GI wire, placing in position, in/c lapping,

spacing and securing them in position by concrete blocks

(1:1), metal chairs, etc. complete in/c cost of all materials,

labour, local handling incidentals necessary to complete the

work as per specifications, drawings and direction of the E-I-

C. (Measurement will be based on standard weight of 490

lbs./ft3 Chairs, laps and separators will not be measures for

payment. The cost of these will be included in the unit rate)

Page 261: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

16

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

M.S. Rod, deformed (grade 40) 275- grade deformed bar with

minimum fy=275 MPa: up to ground floor

12 5.08.13 Supplying, fitting and fixing steel glazed window shutter with sqm H/W (Toilet) 0.6 0.6 0.36 5 1.8

frames as per design having ‘Z’ section (19mmx19mmx19mm) 1.8 3147.69 5665.84

in frame and ‘T’ section (19mmx19mmx3mm) for horizontal

dividers of shutters and F.I. bar (25mmx3mm) for middle

vertical members of frame in/c all cost of charges for

fabrication and manufacture by welding, riveting, etc.

supplying all essential fittings like stopper, handle, 300mm

long adjustable iron cleats, 50mm long pin hinges, 150mm

long clamps for fitting frame in/c supplying, fitting, fixing 3mm

thick glass panes by putty and painting the window with two

coats of synthetic enamel paint over a coat of anticorrosive

priming, making necessary holes in wall and RCC work as

necessary, filling with CC (1:2:4:) and mending good the

damages, etc. all complete as per direction of the E-I-C and as

per drawing and design.

13 5.091.a Supply of Fittings,fixing uPVC door in position,making 8nos LS 4 5430 21720

holes in the existing wall or making special arrangement for

fixing with concrete work/royel plug and screw etc and

frame shutter hinges by clamp and lock etc.all complete as

per direction of the E-I-C.( Plastic door are Bangladeshi made

14 5.089.a Supplying,fitting,fixing MS door made of 10mm dia MS rod @ each MS Door 1 2 2

100mm c/c bothways,fitted with MS angles 2 5000 10000

(50mmx50mmx6mm) outer frame in/c fabricating ,MS clump

and door lock system,one lock,welding in each point and

painting two coats of synthetic enamel paint over a coat of

anticorrosive priming etc.all complete as per drawing and

design and direction of the E-I-C.

Page 262: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

17

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

15 5.12.01 Minimum 12mm thick cement plaster (1:4) to dado and plinth sqm Outer face GL to PL 5.75 0.45 2.588 2 5.176

wall up to 150mm below ground level with neat cement 3.075 0.45 1.384 2 2.768

finishing in/c washing of sand, finishing the edges and Inner wall 1.5 0.914 1.371 6 8.226

corners and curing for the requisite period etc. all complete as 1.625 0.914 1.485 1 1.485

per direction of the E-I-C (Sand of minimum FM 1.2 be used). 1 0.914 0.914 8 7.312

1.2 0.914 1.097 1 1.097

1 0.914 0.914 1 0.914

2.825 0.914 2.582 1 2.582

Brick Stair-Top 1.25 0.5 0.625 2 1.25

Side 0.25 0.3 0.075 4 0.3

" 0.25 0.15 0.038 4 0.152

Skirting (100mm) 1.5 0.1 0.15 2 0.3

1 0.1 0.1 3 0.3

4.5 0.1 0.45 1 0.45

1.2 0.1 0.12 2 0.24

Floor 1.5 1 1.5 5 7.5

2.125 1.2 2.55 1 2.55

3.25 1.2 3.9 1 3.9

1.625 1 1.625 1 1.625

door surface 1 0.125 0.125 1 0.125

1.25 0.125 0.156 1 0.156

0.74 0.125 0.092 4 0.368

Deduction 1 0.1 0.1 -1 -0.1

1.25 0.1 0.125 -1 -0.125

0.74 0.914 0.676 -3 -2.028

0.74 0.1 0.074 -5 -0.37

46.153 179.52 8285.39

16 5.049.2 Site improvement as per direction of engineer in charge LS 1 5000 5000

17 5.12.02.01 Minimum 12mm thick cement plaster (1:6) to wall both inner sqm Wall ( Out side) 5.75 2.55 14.663 2 29.326

and outer surface, finishing the corner and edges in/c 3.075 2.55 7.841 2 15.682

Page 263: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

18

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

washing of sand cleaning the surface, scaffolding and curing 1.5 2.45 3.675 2 7.35

for the requisite period etc. all complete as per direction of the Ground floor

E-I-C. (Sand of minimum FM 1.2 be used). " dress rm 1 2.45 2.45 2 4.9

1.5 1.636 2.454 6 14.724

1.625 1.636 2.659 1 2.659

1 1.636 1.636 8 13.088

1.2 1.636 1.963 1 1.963

1 1.636 1.636 1 1.636

2.825 1.636 4.622 1 4.622

1.125 1.636 1.841 1 1.841

0.125 2.1 0.263 4 1.052

4.5 2.45 11.025 1 11.025

1.2 2.45 2.94 2 5.88

Deduction 1 2 2 -2 -4

1.25 2 2.5 -2 -5

0.74 2 1.48 -8 -11.84

H/W 0.6 0.6 0.36 -10 -3.6

91.308 143.96 13144.7

18 5.12.03.01 Minimum 6mm thick cement plaster (1:4) to ceiling RCC sqm Ceiling 1.5 1 1.5 4 6

columns, beams, surface of stair case, sunshades, cornices, 2.125 1.2 2.55 1 2.55

railings, drop wall, louvers, fins and finishing the corners and 3.25 1.2 3.9 1 3.9

edges in/c washing of sand cleaning the surface, scaffolding Ground Floor 1.625 1 1.625 1 1.625

and curing for the requisite period etc. all complete as per 6.65 0.45 2.993 2 5.986

direction of the E-I-C. (Sand of minimum FM 1.2 be used). 3.075 0.45 1.384 2 2.768

Celing out side 6.65 0.1 0.665 2 1.33

3.975 0.1 0.398 2 0.796

Sunshade 0.7 0.5 0.35 5 1.75

0.7 0.375 0.263 5 1.315

Sunshade side 1.45 0.088 0.128 5 0.64

Lintel 0.6 0.125 0.075 20 1.5

Page 264: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

19

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

30.16 126.33 3810.11

19 5.16.01.01 White washing three coats over a coat of priming with sqm Wall ( out side) 5.75 2.55 14.663 2 29.326

slacked stone lime mixed with gums, blue. Lime mix prepared 3.075 2.55 7.841 2 15.682

at least 12 hours before use, in/c removing the floating Wall ( Inside ) 1.5 2.45 3.675 2 7.35

materials from the mixture, surface cleaning to free all foreign 1 2.45 2.45 2 4.9

materials before application of each coat. Applying one 1.5 1.636 2.454 6 14.724

vertical and one horizontal wash for each coat and successive 1.625 1.636 2.658 1 2.658

coat is to be applied after drying up of previous coat i/c cost 1 1.636 1.636 8 13.088

of hair brush, providing necessary scaffolding and necessary 1.2 1.636 1.963 1 1.963

cleaning the plinth, floors, doors, windows, partions and 1 1.636 1.636 1 1.636

ventilators by washing, rubbing as if necessary before and 2.825 1.636 4.622 1 4.622

after the wash, polishing the surface with sand paper etc. all 1.125 1.636 1.841 1 1.841

complete for all floors i/c cost of all materials as per direction 0.125 2.1 0.263 4 1.052

of the E-I-C. 4.5 2.45 11.025 1 11.025

1.2 2.45 2.94 2 5.88

Deduction 1 2 2 -2 -4

1.25 2 2.5 -2 -5

0.74 2 1.48 -10 -14.8

H/W 0.6 0.6 0.36 -10 -3.6

Ceiling 1.5 1 1.5 4 6

2.125 1.2 2.55 1 2.55

3.25 1.2 3.9 1 3.9

1.625 1 1.625 1 1.625

6.65 0.45 2.992 2 5.984

3.075 0.45 1.384 2 2.768

Celing out side 6.65 0.1 0.665 2 1.33

3.975 0.1 0.398 2 0.796

Sunshade 0.7 0.5 0.35 5 1.75

0.7 0.375 0.262 5 1.31

Sunshade side 1.45 0.088 0.128 5 0.64

Page 265: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

20

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

Lintel 0.6 0.125 0.075 20 1.5

118.5 15.42 1827.27

20 7.02.01.01 Supplying, fitting and fixing Bangladesh pattern BISF each 1 3 3

Standard porcelain long pan (Model-320, size- 3 5244.81 15734.43

540x425x270mm, Bowl size-390x210x190mm) with foot rest

with foot rest of vitreous China and preparing the base of

pan with cement concrete and with wire net or rods including

making holes wherever required and mending good the

damages, supplying 13.60 liters capacity C.I. cistern and

fitting fixing the same in position with C.I. brackets including

supplying best quality 40mm dia PVC flush pipe with brass

coupling (not exceeding 1.80m in length), 12mm dia plastic

connection pipe with brass coupling, 12mm dia brass stop

cock, 12mm dia ball cock and pulling chain etc. all complete

as per direction of the E-I-C.

21 7.04.01 Supplying "BISF STANDARD" quality glazed porcelain foot each 1 6 6

rest (Mode-305, size-260mmx227mmx35mm size) including 6 163.95 983.7

fitting fixing in position. White "BISF STANDARD

22 7.05.01.01 Supplying, fitting and fixing "BISF STANDARD" glazed each 1 2 2

vitreous Wash Hand Basin hand basin (Model-213, size- 2 3296.63 6593.26

450x405x180mm, Bowl size-375x275x136mm) including fitting

fixing the same in position with heavy type C.I. brackets,

44mm dia PVC waste water pipe with brass coupling (not

exceeding 750mm in length), 12mm dia plastic connection

pipe with brass coupling, 12mm dia brass stop cock, 12mm

dia C.P. pillar cock, 30mm dia C.P. Basin waste with chain

plug including making holes in walls and floors and fitting

with wooden blocks screws and mending good the damages

etc. all complete as per direction of the E-I-C.

White "BISF STANDARD

Page 266: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

21

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

23 7.15.01 Supplying, fitting and fixing porcelain soap tray including each 1 5 5

making holes in walls and mending good the damages etc. all 5 199.6 998

complete as per direction of the E-I-C.

White "BISF STANDARD" (150mmx110mmx40mm size)

24 7.17.01 Supplying, fitting and fixing Glass plate Shelf (600mmx125mm) each 1 2 2

of 5mm thick glass with fancy C.P. brackets, screws and 2 608.79 1217.58

frames including making holes in walls and mending good the

damages etc. all complete as per direction of the E-I-C.

Super quality

25 7.18.01 Supplying, fitting and fixing Towel rail with holder including each 1 2 2

making holes in walls and mending good the damages etc. all 2 766.18 1532.36

complete as per direction of the E-I-C.

C.P. Towel rail (Size : 600mmx20mm) with C.P. holder (Super

quality)

26 7.19.02 Supplying, fitting and fixing super quality Mirror with hard each 1 2 2

boards at the back with all necessary fittings including making 2 572.78 1145.56

holes in walls and mending good the damages etc. all

complete as per direction of the E-I-C

Belgium made Mirror (Size:450mmx300mm)

27 7.20.02 Supplying, fitting and fixing 5.49m long 100mm dia (inner) each 1 5 5

PVC "B" class pipe water grade (LIRA/AZIZ/ NATIONAL 5 4886.3 24431.5

POLYMER brand or equivalent) with all HCI fittings and

specials like plain bend, tees, reducing sockets, junctions,

door bends, 100mm dia cowls, anti-siphon (MAANCO

BRAND) including gasket and cement joints, PVC solution,

making holes in walls and mending good the damages etc. all

complete as per direction of the E-I-C.

28 7.21.02 Supplying, fitting and fixing 3.66m long Ventilation pipe with each 1 3 3

all fittings and specials like 50mm plain bends, tees, 50mm dia 3 922.75 2768.25

cowls etc. including gasket with cement joints and mending

Page 267: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

22

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

good the damages etc. all complete as per direction of the E-I-C.

3.66m long 50mm dia PVC best quality Ventilation Pipe (B.S. 3505)

29 7.22.02.01 Supplying, fitting, fixing and laying 150mm/200mm dia PVC m 10 10 1 10

"B" class pipe water grade (LIRA / AZIZ / NATIONAL 10 1124.08 11240.8

POLYMER BRAND or equivalent) best quality sewerage pipe

including necessary fittings and joints with high class solution

and at the base and sides filling with best quality local sand all

around the pipe (not less than 25mm) upto the required

depth etc. complete as per type, plan and direction of the E-I-C.

30 7.24 Supplying, fitting and fixing 100mm dia C.I. Trap (Siphon each 1 3 3

trap or ‘P’ trap) including making holes in walls and floors 3 368.35 1105.05

and mending good the damages etc. all complete as per

direction of the E-I-C.

31 7.25.06 Supplying, fitting and fixing GI pipe with all special fittings m 60 60 1 60

such as bends, elbows, sockets, reducing sockets, Tees, 60 280.69 16841.4

unions, jumnuts etc. including cutting trenches where

necessary and fitting the same with earth duly rammed and

fixing in walls with holder bats and making holes in floors and

walls and mending good the damages etc. all complete in all

respects as per direction of the E-I-C.

20mm dia GI Pipe

32 7.25.07 Supplying, fitting and fixing GI pipe with all special fittings m 25 25 1 25

such as bends, elbows, sockets, reducing sockets, Tees, 25 220.46 5511.5

unions, jumnuts etc. including cutting trenches where

necessary and fitting the same with earth duly rammed and

fixing in walls with holder bats and making holes in floors and

walls and mending good the damages etc. all complete in all

respects as per direction of the E-I-C. 12mm dia GI Pipe

33 7.27.01 Supplying, fitting and fixing best quality and heavy type bib each 1 7 7

cock. 12mm dia Brass Bib Cock 7 463.43 3244.01

Page 268: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

23

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

34 7.34.01 Construction of masonry Inspection Pit (Inside each 1 2 2

measurement:600mmx600mm) with 250mm thick brick work 2 5191.97 10383.94

in cement mortar (1:4), 100mm thick RCC top slab (1:2:4)

with 1% reinforcement, 450mm dia water sealed R.C.C./ M.H.

cover including necessary earth work, side filling, single layer

brick flat soling, 75mm thick Cement Concrete (1:3:6) in base

for making invert channel, 12mm thick cement plaster (1:2)

with neat cement finishing etc. all complete up to a depth of

0.75m and as per the direction of the E-I-C.

450mm dia water sealed R.C.C. Manhole Cover

35 7.36.02.a Construction of Septic Tank with 250mm thick masonry each 1 1 1

works in main and partition walls in cement morter(1:6) as 1 106356 106356.4

per approved plan over single layer brick flat soling and

250mm thick cememt concrete flooring (1:2:4),in/c 20mm

thick cement plaster (1:4) to inside of walls with neat cement

finishing ,25mm thick patent stone (1:2:4) flooring with neat

cement finishing including supplying fitting and fixing of two

RCC Tees and providing 450mm dia water sealed heavy type

C.I .M.H. cover with necessary locking arrangements,100mm

thick RCC (1:2:4) top slab with minimum 1% reinforcement

including centering,shuttering ,fabrication,casting,curing

etc.complete up to required depth.The item is inclusive of

necessary earth work in exacavation and shoring,bailing out

water and side filling including the cost of all materials,

operation and incidental charges etc.all complete as per the

approved plan and direction of the E-I-C. For 100 users with

3 manhole covers.

36 7.37.02 Construction of soak well with 250mm thick solid brick work each 1 1 1

(1:6) and 250mm honey comb brick work (1:6) as per design 1 57559.3 57559.26

over RCC (1:2:4) well curb with 1.5% reinforcement upto

Page 269: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

24

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

the depth as per drawing with 100mm dia water sealed heavy

type C.I. manhole cover with all locking arrangements, filling

the well upto the required depth with graded khoa and sand

including supplying and fabricating MS Rod, casting, curing

etc. The item is inclusive of necessary earth work in

excavation, side filling and bailing out water etc. all complete

as per drawing, design and direction of the E-I-C. For 100 users

37 7.40.02 Supplying, fitting and fixing plastic made overhead Water each 1 1 1

Tank of different capacity. 1 10862.3 10862.25

Supplying, fitting and fixing plastic made overhead Water

Tank of 1000 litres capacity made with 25mm thick plastic

composed sheet with plastic cover on top with locking

arrangements, providing inlet and outlet pipe with flanges

and plug, jum nuts, 40mm dia ball cock, 12mm dia 1.12m long

overflow pipe and with all other necessary fittings etc. all

complete in all respects as per direction of the E-I-C.

38 8.01.02.04 Supplying, fitting and fixing main/sub-main switches with fuse each 1 1 1

on live side and neutral line on concealed iron frame 1 1542.81 1542.81

(Bangladeshi made of prior approved quality) etc. all

complete as per directions of the E-I-C. 250 Volts ICTP; 10 amps

39 8.03.01.04 Supplying, fitting and fixing energy meter with cutout teak each 1 1 1

wood board etc. all complete as per directions of E-I-C 1 6725.74 6725.74

(when the meter is not supplied by PDB). 500 Volts 3 phase 60 amps

40 8.06.02.01 Supplying, fitting and fixing PVC insulated and sheathed m 150 150 1 150

round or flat wire (as per BSS 2004/61) from LT line to 150 19.18 2877

energy meter, energy meter to main switch/FDB sub-main

switch, CCB/ICDB individual lights, fans and socket outlet

points as per drawings and directions (Eastern/Paradise/Poly

cable or any equivalent prior approved quality) of the E-I-C.

PVC Insulated and non sheathed Round Single Core Cable (IYAL)

Page 270: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

25

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

41 8.08 Supplying, fitting and fixing Distribution/Sub-Distribution sqm DB 1 1.5 1.5 1 1.5

board made of 18 SWG steel sheet metal enclosed with double SDB 1 1 1 1 1

cover, gray hammer painted on outside and enamel paint on 2.5 4978.47 12446.18

inside on rust proof prime coat with hinged front door with

lock and key arrangement for half concealed mounted board

having knock out for conduit entry and exit for 415/230V

TP&N/ SP&N operations. The board shall have solid neutral

and earth copper bus bar and also required size off 3 phase

copper bus bars. All bars shall have required number of holes

of 5mm for cable connections etc. all complete as per

drawing, design and direction of E-I-C.

42 8.09.06 Supplying, fitting and fixing 20mm thick switch board for fan each 1 6 6

regulators, lighting switches two pin and at the three pin 6 21.09 126.54

socket outlets the switch board to be made of teak wood and

varnished on all sides etc. all complete as per directions of the

E-I-C. 100mmx100mm

43 8.17.04 Supplying, fitting and fixing PVC pipe for service line and m 80 80 1 80

sleeves for electrical wiring when it passes through wall etc. all 80 53.56 4284.8

complete as per directions of the E-I-C. 12mm dia

44 8.24 Supplying, fitting and fixing 5 Amps 2-pin socket with control each 1 6 6

switch etc. complete as per drawing & directions of the E-I-C. 6 192.52 1155.12

45 8.25 Supplying, fitting and fixing 250 volts single phase 15 amps 3- set 1 6 6

pin combined switches and socket outlet (surface type) 6 269.4 1616.4

mounted on beast quality locally made required size 18 SWG

galvanized plain sheet board (75mm depth) etc. all complete

as per drawings and directions of the E-I-C.

46 8.31 Supplying, fitting and fixing 1.22m long 40 watt fluorescent set 1 2 2

tube light with necessary superior quality ballast, starter, 2 476.52 953.04

condenser, holders, 18 SWG sheet steel stove enamel base,

etc. all complete as per drawing and directions of the E-I-C.

Page 271: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

26

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

Each lamp is to be operated by one way switch. (Eastern or

prior approved quality)

47 8.35 Supplying fitting and fixing one way tumbler switch as per each 1 8 8

directions of the E-I-C. 8 41.89 335.12

48 8.41.02.03 Supplying, fitting and fixing the following electric lamp for each 1 6 6

garden/gate/room light and different places as per directions 6 43.48 260.88

of the E-I-C. Normal bulb 100 watt

49 8.46.02.02 Supplying and installation of centrifugal pump with motor to each Pump 1 1 1

lift water from underground reservoir/deep tube-well to 1 6760.87 6760.87

different building. The motor with pump installed on concrete

foundation and supplying necessary anchor bolts, nuts and

other fixers in/c fitting and fixing the pumps and motors in

position etc. all. complete as per direction of the E-I-C.

(Japan/USA made or any equivalent prior approved quality)

220 volts single phase

TOTAL AMOUNT: 584 223.43

SAY: 584 223.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Five Lac Eighty-Four Thousand Two Hundred Twenty-Three) Only

Page 272: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

27

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 3.1.03 Earth work in box cutting on road crest up to 450mm depth sqm Drain 1 0.6 0.6 1 0.6

with proper grade, camber and alignment maintaining super 0.6 46.74 28.04

elevation on curves, removing soil to a safe distance,

spreading the excavated earth on road flanks and slopes

uniformly including leveling, dressing, watering, compacting

the sub-grade by manual labour, etc. all complete as per

direction of the E-I-C.

2 5.03.01 Single layer brick flat soling with 1st class or picked bricks, sqm drain 1 (0.054x2+0.21 0.725 1 0.725

true to level, camber/super elevation and grade including 0.725 270.8 196.33

carrying bricks, filling the interstices tightly with sand of

minimum FM 0.80, etc. all complete as per direction of the E-I-C

3 5.03.05 Mass concrete work in foundation with Portland cement, cum drain 1 (0.084x2+0.21 0.075 0.054 1 0.054

sand (minimum FM 1.80) and 1st class/picked brick chips 0.054 6569.92 354.78

20mm down graded (LAA value not exceeding 40), including

shuttering, mixing by concrete mixer machine, casting, laying

compacting and curing for the requisite period breaking

bricks into chips etc. all complete as per direction of the E-I-

C. Cylinder crushing strength of concrete should not be less

than 170kg/cm2 at 28 days of curing (suggested mix

proportion 1:2:4). Additional quantity of cement to be added

if required to attain the strength at the contractors own cost.

4 5.12.01 Minimum 12mm thick cement plaster (1:4) to dado and plinth sqm drain surface 1 (0.100x2+0.21 0.724 1 0.724

wall up to 150mm below ground level with neat cement 0.724 179.52 129.97

finishing in/c washing of sand, finishing the edges and

corners and curing for the requisite period etc. all complete as

per direction of the E-I-C (Sand of minimum FM 1.2 be used).

TOTAL AMOUNT: 709.12

SAY: 709

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Seven Hundred Nine) Only

Detailed Estimation of a Typical V-drain ( Length = 1.00m )

(See Appendix xx for relevant structural drawings)

Page 273: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

28

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 5.05.01.01 Reinforced cement concrete works (1:2:4) having minimum cum Cross drain top slab 2.4 0.6 0.1 0.144 1 0.144

cylinder crushing strength 170kg/cm2 at 28 days with 0.144 7206.69 1037.76

Portland cement, best quality coarse sand (50% quantity of

sand of minimum FM 1.2 and 50% quantity of coarse sand of

minimum FM2.5) 20mm down graded picked brick chips in/c

breaking chips and screening, centering, shuttering, making

shuttering fully leak proof, placing of rod in position, mixing

the aggregates with mixer machine, pouring, casting,

compacting by vibrator machine and curing at least for 28

days (excluding the cost of reinforcement and its fabrication)

etc. all complete as per direction of the E-I-C.

In individual and continuous footing of column, raft and floor

slab at plinth level.

2 5.06.01.02 Supplying and fabrication of M.S High strength deformed kg MS Rod 11 1 11

bar/ Twisted bar reinforcement of required size and length for 11 67.96 747.56

all types of RCC work in/c straightening the rod, removing

ruts, cleaning, cutting, hooking, bending, binding with

supply of 22 B.W.G. GI wire, placing in position, in/c lapping,

spacing and securing them in position by concrete blocks

(1:1), metal chairs, etc. complete in/c cost of all materials,

labour, local handling incidentals necessary to complete the

work as per specifications, drawings and direction of the E-I-

C. (Measurement will be based on standard weight of 490

lbs./ft3 Chairs, laps and separators will not be measures for

payment. The cost of these will be included in the unit rate)

M.S. Rod, deformed (grade 40) 275- grade deformed bar with

minimum fy=275 MPa: up to ground floor

TOTAL AMOUNT: 1 785.32

SAY: 1 785.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (One Thousand Seven Hundred Eighty-Five) Only

Detailed Estimation of a Typical Cross drain

(See Appendix xx for relevant structural drawings)

Page 274: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

29

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

1 10.02.01 Boring by using 100mm dia cutter and 38mm dia GI Pipe and m From 0.00 to 50.00m 50 50 1 50

other equipment capable of drilling up to a depth of 500m by 50 123.98 6199

water jet system through all sorts of strata, protection of

caving by supplying necessary casing pipe, collection of soil

samples at every 3m interval and at every change of strata

and preserve them for analysis, withdrawal of boring pipes &

casing pipes etc. all complete as per specification and direction

of the E-I-C. From 0.0m to 50m = 50m

2 10.02.02 Boring by using 100mm dia cutter and 38mm dia GI Pipe and m From 50.00 to 100.00m 50 50 1 50

other equipment capable of drilling up to a depth of 500m by 50 136.38 6819

water jet system through all sorts of strata, protection of

caving by supplying necessary casing pipe, collection of soil

samples at every 3m interval and at every change of strata

and preserve them for analysis, withdrawal of boring pipes &

casing pipes etc. all complete as per specification and direction

of the E-I-C. From 0.0m to 50m = 50m

3 10.02.03 Boring by using 100mm dia cutter and 38mm dia GI Pipe and m From 100.00 to 152.00m 52 52 1 52

other equipment capable of drilling up to a depth of 500m by 52 150.01 7800.52

water jet system through all sorts of strata, protection of

caving by supplying necessary casing pipe, collection of soil

samples at every 3m interval and at every change of strata

and preserve them for analysis, withdrawal of boring pipes &

casing pipes etc. all complete as per specification and direction

of the E-I-C. From 0.0m to 50m = 50m

4 10.02.04 Boring by using 100mm dia cutter and 38mm dia GI Pipe and m From 152.00 to 200.00m 48 48 1 48

other equipment capable of drilling up to a depth of 500m by 48 164.89 7914.72

water jet system through all sorts of strata, protection of

caving by supplying necessary casing pipe, collection of soil

samples at every 3m interval and at every change of strata

and preserve them for analysis, withdrawal of boring pipes &

Detailed Estimation of a Typical Deep Tubwell (Platfrom = 1.45m x1.45m ) Depth = 300m

(See Appendix xx for relevant structural drawings)

Page 275: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

30

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

casing pipes etc. all complete as per specification and direction

of the E-I-C. From 0.0m to 50m = 50m

5 10.02.05 Boring by using 100mm dia cutter and 38mm dia GI Pipe and m From 200.00 to 250.00m 50 50 1 50

other equipment capable of drilling up to a depth of 500m by 50 181.01 9050.5

water jet system through all sorts of strata, protection of

caving by supplying necessary casing pipe, collection of soil

samples at every 3m interval and at every change of strata

and preserve them for analysis, withdrawal of boring pipes &

casing pipes etc. all complete as per specification and direction

of the E-I-C. From 0.0m to 50m = 50m

6 10.02.06 Boring by using 100mm dia cutter and 38mm dia GI Pipe and m 50 meter 50 50 1 50

other equipment capable of drilling up to a depth of 500m by 50 198.36 9918

water jet system through all sorts of strata, protection of

caving by supplying necessary casing pipe, collection of soil

samples at every 3m interval and at every change of strata

and preserve them for analysis, withdrawal of boring pipes &

casing pipes etc. all complete as per specification and direction

of the E-I-C. From 0.0m to 50m = 50m

7 10.03.01 Supplying and lowering 38mm dia water grade PVC pipe each Hand pump 1 1 1

having wall thickness 2.5m to 3.0mm (‘D’ Class Aziz 1 2452.16 2452.16

pipe/equivalent), PVC sand trap of length 3.0m with cap, PVC

strainer of desired slot installing at the middle of the most

suitable water bearing strata. 38mm dia GI pipe of best quality

of length 1.52m with MS welded flat bar on each side to

prevent from rotation up to the desired depth, fitting fixing

the hand pump No. 6 etc. including the cost of solvent

cement, socket adapter, filling medium sand up to 18.0m

above strainer and the remaining portion with available soil

from boring etc. all complete as per standard specification and

direction of the E-I-C

Hand pump No. 6 complete set (EPL/RFL)

(Medium)/equivalent brand)

Page 276: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

31

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

8 10.03.02 Supplying and lowering 38mm dia water grade PVC pipe m 38mm dia GI pipe 3.04 3.04 1 3.04

having wall thickness 2.5m to 3.0mm (‘D’ Class Aziz 3.04 588.8 1789.95

pipe/equivalent), PVC sand trap of length 3.0m with cap, PVC

strainer of desired slot installing at the middle of the most

suitable water bearing strata. 38mm dia GI pipe of best quality

of length 1.52m with MS welded flat bar on each side to

prevent from rotation up to the desired depth, fitting fixing

the hand pump No. 6 etc. including the cost of solvent

cement, socket adapter, filling medium sand up to 18.0m

above strainer and the remaining portion with available soil

from boring etc. all complete as per standard specification and

direction of the E-I-C

38mm dia GI pipe 2.9mm thick (National Tubes/equivalent)

9 10.03.03 Supplying and lowering 38mm dia water grade PVC pipe m 38mm dia PVCpipe 297 297 1 297

having wall thickness 2.5m to 3.0mm (‘D’ Class Aziz 297 109.63 32560.11

pipe/equivalent), PVC sand trap of length 3.0m with cap, PVC

strainer of desired slot installing at the middle of the most

suitable water bearing strata. 38mm dia GI pipe of best quality

of length 1.52m with MS welded flat bar on each side to

prevent from rotation up to the desired depth, fitting fixing

the hand pump No. 6 etc. including the cost of solvent

cement, socket adapter, filling medium sand up to 18.0m

above strainer and the remaining portion with available soil

from boring etc. all complete as per standard specification and

direction of the E-I-C

38mm dia water graded PVC pipe having thickness 2.5-

3.00mm (‘D’ class Aziz brand/equivalent) pipe sand trap

10 10.03.04 Supplying and lowering 38mm dia water grade PVC pipe m 5 5 1 5

having wall thickness 2.5m to 3.0mm (‘D’ Class Aziz 5 113.39 566.95

pipe/equivalent), PVC sand trap of length 3.0m with cap, PVC

strainer of desired slot installing at the middle of the most

suitable water bearing strata. 38mm dia GI pipe of best quality

of length 1.52m with MS welded flat bar on each side to

Page 277: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

32

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

prevent from rotation up to the desired depth, fitting fixing

the hand pump No. 6 etc. including the cost of solvent

cement, socket adapter, filling medium sand up to 18.0m

above strainer and the remaining portion with available soil

from boring etc. all complete as per standard specification and

direction of the E-I-C

38mm dia water graded PVC strainer having thickness 2.5 –

3.0mm (‘D’ class Aziz brand/equivalent) of recommended slot

size

11 10.03.05 Supplying and lowering 38mm dia water grade PVC pipe each 1 65 65

having wall thickness 2.5m to 3.0mm (‘D’ Class Aziz 65 56.71 3686.15

pipe/equivalent), PVC sand trap of length 3.0m with cap, PVC

strainer of desired slot installing at the middle of the most

suitable water bearing strata. 38mm dia GI pipe of best quality

of length 1.52m with MS welded flat bar on each side to

prevent from rotation up to the desired depth, fitting fixing

the hand pump No. 6 etc. including the cost of solvent

cement, socket adapter, filling medium sand up to 18.0m

above strainer and the remaining portion with available soil

from boring etc. all complete as per standard specification and

direction of the E-I-C. 38mm dia socket adapter

12 10.03.06 Supplying and lowering 38mm dia water grade PVC pipe each 1 1 1

having wall thickness 2.5m to 3.0mm (‘D’ Class Aziz 1 60.01 60.01

pipe/equivalent), PVC sand trap of length 3.0m with cap, PVC

strainer of desired slot installing at the middle of the most

suitable water bearing strata. 38mm dia GI pipe of best quality

of length 1.52m with MS welded flat bar on each side to

prevent from rotation up to the desired depth, fitting fixing

the hand pump No. 6 etc. including the cost of solvent

cement, socket adapter, filling medium sand up to 18.0m

above strainer and the remaining portion with available soil

from boring etc. all complete as per standard specification and

direction of the E-I-C. 38mm dia socket adapter

Page 278: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 9C

33

SL Item Code Description of Work Unit Location / Length Width Height / Area / No of Total Qty Unit Amount

Component Depth Volume of Works Rate

1 2 3 4 5 6 7 8 9 10 11 12 13

13 10.05.02 Complete development of the tube well to obtain sand & LS 1 2000 2000

turbidity free water at a satisfactory yield, etc. all complete as

per specifications and direction of the E-I-C.

For wells beyond 200m depth

14 10.06 Furnishing design of the production well by testing of water LS 1 2000 2000

and soil samples collected from the observation well in/c. test

for ‘Arsenic’ etc. all complete as per direction of the E-I-C.

(excluding the cost of actual fees for testing which will be paid

to the contractor separately by the department).

15 10.08 Construction of C.C. (1:2:4) platform of size 1.40mx1.00m and each 1 1 1

1.00m long drain as per design and standard specifications 1 3837.8 3837.8

including cost of sanitary seal, neat cement finishing,

transport etc. all complete as per specifications and direction

of the E-I-C.

TOTAL SCHEME AMOUNT: 96 654.87

SAY: 96 655.00

Note : Cost is made by using LGED Rate of Schedule 2011 and Estimation Software. In Word : Taka (Ninety-Six Thousand Six Hundred Fifty-Five) Only

Page 279: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 280: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 10

Annex 10

Institutional Aspects and Implementation Arrangements

[CCRIP will have a common institutional aspects and implementation arrangements as described in ADB project document as well as summarized in the main text of PDR.]

Page 281: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 282: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Sustainable Market Infrastructure For Livelihood Enhancement (CCRIP) Project Project Design Report – Detailed Design Mission

Annex 11

Annex 11

Compliance with IFAD policies

Page 283: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 284: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 11

1

Annex 11

Compliance with IFAD policies

Targeting: CCRIP has followed IFAD‘s policy on targeting by applying a rigorous geographical targeting process for the selection of the least developed and most vulnerable Upazilas. CCRIP will also employ a specific focus on household level targeting to reach the most destitute echelon of the population which are very poor men and women headed households, as only they will be selected for participating in LCS and related construction works.

Gender: CCRIP‘s approach is compatible with IFAD‘s gender policy. Poor and destitute women will directly benefit as they will participate in LCS for the construction of markets and some village roads. Having their own income and learning new skills will empower women socially and economically. MIDPCR and SCBRMP reports uniformly confirm a strong development of gender equalities following project activities. Besides, the construction of roads contributes to increased social and physical mobility, access to additional wage employment, access to village markets as buyers and sellers and access to school and health services. See Annex 2 for detail discussion on

gender. In the ADB/IFAD/KfW report, appendix 7, a detailed gender action plan is presented.

Land: There will not be any relocation of housing settlement to build roads and markets under CCRIP project component 1.2 (union and village roads) and 2.2 (village market development), and as such, no acquisition of land is foreseen. All roads and markets will be built on existing alignment and khas land (or land donated) for market development respectively. Resettlement or eviction has neither been an issue in MIDPCR project nor is it foreseen in the CCRIP project component 1.2

and 2.2. The other component 1.1 and 2.2 foresee some limited land acquisition and resettlement. This will be dealt with in line with ADB land settlement frameworks as detailed in the report. Environmental assessment: There is no major environmental concern in CCRIP. In fact, the development of markets with internal roads, drainage and garbage collection system will improve the micro-environment in and around the markets. Since the markets are expected to be managed

by MMC, the cleanliness in markets is expected to be maintained beyond the project period. The project must remain constantly vigilant about design specifications of culverts/bridges so that water flows in canals and small rivers are not obstructed due to narrowing width of culverts/bridges built by the project. The design mission has prepared an environmental note. As per GoB rules, it is mandatory to receive an environmental clearance from the Department of

Environment by submitting a properly done environmental assessment report. This will be conducted right at the beginning of the project, as has been the case in HILIP, when funds will

have been allocated under the CCRIP budget. Private sector: The project may not have direct participation from the corporate private sector but the second IFAD-funded MAPP project is expected to work with and promote private sector as part of value chain development activities. However, road and market constructions will promote business of small farmers, traders and other producers who in effect supply to large markets as part of supply chain. It has been found in MIDPCR and other similar project areas that with good

roads and improved markets large companies such as pharmaceutical, seed, fertilizer, processed food, consumer durables, construction material companies expand their marketing networks even in formerly disconnected remote areas. Therefore, the project in fact would assist larger business as well as increase access to better quality goods and services in rural areas.

Page 285: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 11

2

IFAD’S TARGETING POLICY - CHECKLIST FOR DESIGN

Updated November 2012

DESIGN

1. Does the main target group - those

expected to benefit most- correspond to IFAD‘s target group as defined by the Targeting Policy (poorer households and food insecure)?

CCRIP has followed IFAD‘s policy on targeting. The

target group will be the population in the catchment areas of project markets, with particular benefits for small and marginal farmers, small traders, landless people and poor women.

2. Have target sub-groups been identified and

described according to their different socio-economic characteristics, assets and livelihoods - with attention to gender and youth differences? (matrix on target group characteristics completed?)

Key File 4 in the PDR presents the target group

priority needs and project proposals. See also annex 2.

3. Is evidence provided of interest in and likely

uptake of the proposed activities by the

identified target sub-groups? What is the evidence? (matrix on analysis of project components and activities by principal beneficiary groups completed?)

Key File 4 in the PDR presents the target group

priority needs and project proposals. Furthermore,

lessons learned from previous interventions provide evidence for the successful uptake of the activities and the expected impact the activities can bring to the livelihoods of the target group.

4. Does the design document describe a feasible and operational targeting strategy in line with the Targeting Policy, involving some or all of the following measures and methods:

4.1 Geographic targeting – based on poverty data or proxy indicators to identify, for area-based projects or programmes, geographic areas (and within these, communities) with high concentrations of poor people

CCRIP has followed IFAD‘s policy on targeting by applying a rigorous geographical targeting process for the selection of the least developed and most vulnerable Upazilas.

4.2 Direct targeting - when services or resources are to be channelled to specific individuals or households

CCRIP design ensures that poor households at the village and community levels can access services (trading, technical advice, transport) on improved

markets and through better roads. The village focus specifically strengthenes access for remote living households. Women receive special attention through

the provision of wpmen sections where it was demanded and suitable .

4.3 Self targeting – when goods and services respond to the priority needs, resource endowments and livelihood strategies of target groups

Self targeting takes place in the labour contracting societies – LCS, as only destitute (predominantly) women and men accept this type of hard labour in construction works, which enables them to start an

own development path, as shown successfully by MIDPCR and SCBRMP.

4.4 Empowering measures - including information and communication, focused capacity- and confidence-building measures,

organisational support, in order to empower and encourage the more active participation and inclusion in planning and decision making of

people who traditionally have less voice and power

In order to ensure good governance and appropriate targeting, participation from Union Parishad representatives will be ensured and a complaints and

remedies mechanism, including circulation of phone numbers of project group leaders and project managers, will be developed to ensure.

4.5 Enabling measures –to strengthen

stakeholders’ and partners’ attitude and commitment to poverty targeting, gender equality and women’s empowerment, including policy dialogue, awareness-raising and capacity-building

CCRIP foresees capacity building activities for MMCs,

LCS, local and project staff for awareness building, technical, organisational and management related subject matters..

4.6 Attention to procedural measures - that could militate against participation by the intended target groups

The MMC procedures , for example , have been developed and revised during the implementation of MIDPCR. They contain measures to ensure proper

Page 286: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 11

3

participation of the target group in the market

management.

4.7 Operational measures - appropriate project/programme management arrangements, staffing, selection of implementation partners

and service providers

A gender specialist will be part of the PMO and will ensure appropriate targeting.

5. Monitoring targeting performance. Does the design document specify that targeting performance will be monitored using participatory M&E, and also be assessed at mid-

term review? Does the M&E framework allow for the collection/analysis of sex-disaggregated data and are there gender-sensitive indicators against which to monitor/evaluate outputs, outcomes and impacts?

An appropriate M&E system will be developed at the start of implementation, and will monitor the progress of activities and the quality of the results. Where possible and relevant, information will be collected at

sex-disaggregated level. In fact, the TORs (see annex B of the Programme Administration Manual) for the gender specialist include the development of a gender based monitoring system. The logframe and gender action plan (see Appendix 7 of the ADB/IFAD/KfW report) contains specific gender-specific targets which will be carefully monitored.

Page 287: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 11

4

IFAD’s KEY FEATURES OF GENDER-SENSITIVE DESIGN AND IMPLEMENTATION

Updated November 2012

Design

1. The project design report contains – and project implementation is based on - gender-disaggregated poverty data and an analysis of gender differences in the activities or sectors concerned, as well as an analysis of each project activity from the gender perspective to

address any unintentional barriers to women‘s participation.

A detailed Gender Analysis has been conducted (see Annex 2 of the PDR) and Key file 1 of the PDR summarizes the major gender issues and actions needed.

2. The project design report articulates – or the project implements – actions with aim to:

Expand women‘s economic empowerment through access to and control over

productive and household assets; Strengthen women‘s decision-making role in

the household and community, and their representation in membership and leadership of local institutions;

Achieve a reduced workload and an equitable workload balance between women

and men.

The project will target the poorest women to create employment opportunities and livelihood support by involving them in construction of

markets and some roads and linking them with

microfinance institutions and another IFAD-funded value chain development project to be implemented by PKSF in the project area. The Gender Action Plan (see Appendix 7 of the ADB/IFAD/KfW report) presents income generating opportunities, capacity building for technical skills as well as for women

empowerment.

3. The project design report identifies at least one gender-specific objective which explains what the project will deliver from a gender perspective, supported by clear budget

allocations.

The project will help poor women to engage in economic opportunities and enhance their capacity and mobility. Appropriate resources are allocated to each activity in support of this

objective.

4. The project design report describes the key

elements for operationalizing the gender strategy, with respect to the relevant project components.

The Gender Action Plan (GAP) (see Appendix

7 of the ADB/IFAD/KfW report) integrates action areas, targets and indicators for gender equality and women‘s benefits within the various components of the project.

5. The design document describes - and the project implements - operational measures to ensure gender- equitable participation in, and benefit from, project activities. These will generally include:

5.1 Allocating adequate human and financial resources to implement the gender strategy

LGED will ensure implementation of the GAP and will be supported by the PMO and MSC team. Adequate budget is allocated to implement these strategies.

5.2 Ensuring and supporting women’s active participation in project-related decision-

making bodies and committees

A separate consultation awareness and

participation plan (CAPP) will be prepared for the project to provide methodology and

processes for continued consultations with various stakeholders particularly the poor and vulnerable groups during the course of project implementation.

5.3 Ensuring that project/programme management arrangements (composition of the project management unit/programme coordination unit, project terms of reference for staff and implementing partners, etc.) reflect attention to gender equality and

women’s empowerment concerns

A focal point on gender and development within the PMO will be established. Besides, the project will recruit/promote more women‘s participation at various project levels and ensure application of GOB minimum quotas

5.4 Ensuring direct project/programme outreach The capacities of field staff will be built to

Page 288: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 11

5

to women (for example through appropriate

numbers and qualification of field staff), especially where women’s mobility is limited

ensure gender responsiveness (see GAP,

appendix 7 of the ADB/IFAD/KfW report).

5.5 Identifying opportunities to support strategic partnerships with government and

others development organizations for networking and policy dialogue

A knowledge management framework will be developed to support policy dialogue.

6. The project‘s logical framework, M&E, MIS and learning systems specify in design – and project M&E unit collects, analyses and

interprets sex- and age-disaggregated performance and impact data, including specific indicators on gender equality and women‘s empowerment.

The Programme logical framework has indicators to monitor and evaluate gender-disaggregated performance and impact The

PMO will ensure establishing the MIS system with sex-disaggregated data collection, gender based analysis, and review and reporting on the implementation of the GAP within all reports.

Page 289: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 11

6

Environmental and Social Assessment note

A. IFAD ESAP Administrative Procedures: As for all IFAD initiated projects, the project design is

subject to IFAD‘s own internal EA process. This ESSN comprises the first step in this process.

The environmental review is based on the relevant documentation of IFAD Environmental and

Social Assessment Procedures (ESAP), notably the chapter on Rural Roads. The review is given per component.

In general three categories are distinguished in IFAD‘s ESAP:

Category A: The programme/project may have significant environmental and social implications that are sensitive, adverse, irreversible or unprecedented and affect an area broader than the

sites or facilities subject to physical interventions. A formal ESIA is likely to be required for the whole programme/project or one or more components. Category B: The project may have some environmental and social impacts on human populations or environmentally significant areas but which are site-specific and less adverse than Category A. While no formal ESIA is required, environmental analysis will be undertaken in the course of project implementation.

Category C: The project will have negligible environmental and social implications – no further

environmental analysis is specifically required.

Component 1. Improved Road Connectivity The road connectivity component is for the most part a ―Category C‖ intervention. It concerns

rehabilitation of existing roads. A general summary (IFAD ESAP) of direct negative effects include: -soil erosion, -damage at borrow sides, -disturbance of drainage, -water contamination, -air pollution. Regarding CCRIP of these only ―disturbance of drainage‖ is impacting on the existing water management of surrounding lands. In the case of the project this concerns that roads may impede the drainage of adjacent lands.

Disturbance of drainage, Hydrological aspects Since the project will rehabilitate only existing roads that traverse the polders already, no new roads will disrupt and interfere with the internal drainage systems of polders. The rural roads system is provided with bridges and culverts. The need for culverts and the design of their

dimensions will be determined and designed during implementation stage. Existing culverts will remain in place in general, but additional culverts may be built. Investigated will be the opportunity to provide the culverts with a water control gate. This gate will be used to ease the

discharge excess water but also may serve as water retention facility, when closed. Through this added facility any possible negative effect from the roads on water control even of previous interventions will be remedied for. Construction of ghats may reduce the canal cross-section impeding discharge when improperly designed; site section for ghats depends on the river stability in the concerned section. To study both impacts the project will engage hydrologists to ascertain that adequate designs are made and

that locations for ghats are selected that do not affect river morphology. Increase in traffic Additional impact may come from somewhat increased traffic but this impact is estimated as to be very minor.

Component 2. Improved Market Services

At the market place there are some interventions that may impact on the environment. Toilet blocks They are provided with the customary septic tanks. When full, they will be emptied and the waste deposited in a safe manner in dump sites, thereafter covered with soil.

Open drain Surrounding the market facilities an open drain is constructed, shaped as V-drain or U-drain. During the market hours and at the end of market days, especially haat days, the rubbish and waste from the open sales platform and from the floors of the covered market sheds, is flushed into the drain by sweepers. This waste water contains leftovers of agricultural crop produce, from

Page 290: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 11

7

multi-purpose sheds and fish-sheds, pieces of the products traded there, like fish, prawns. In

addition minor human waste, paper and plastic bags may end up in the drain. There is no toxic waste. The drain often evacuates its effluent towards small reservoirs or khals or onto agricultural land. This situation may be undesirable as children may play around these places and animals may drink from it. The project will mitigate negative effects by installing at the lower end of the drain a bar screen

(filter) is placed where the solid waste accumulates. This solid waste will be removed from time to time and deposited in a garbage dump, eventually to be burned or covered with bleaching powder to destroy it. After passing through the screen the drain water flows to a pit where it stays for several hours allowing the particles to settle to the bottom and the greases to float to the top. The solids drawn off the bottom and skimmed off the top may be deposited in the garbage dump. The remaining water may be evacuated to khals or elsewhere without causing a health hazard. The

amount of waste is small for most markets. For special markets, very large or wholesale markets, possibly a special facility should be built like a septic tank in analogy with the toilet blocks. The pit should be fenced. Improved market, road infrastructure, putting a tree plantation along both sides of the improved

roads and paved market places would contribute to a better working environment in the project area. In fact development of markets with internal roads, drainage and garbage collection system

will improve the environment in and around markets. Enhanced cleanliness At the market facilities special will be given to cleaning of the facilities and safe removal of the small waste. Upgrading of the deteriorated facilities therefore will have a positive impact on the environment. The markets will be managed by a legally formalized Market Management Committee (MMC) and part of their tasks is to ascertain the cleanliness of markets; this improves the present

situation and impacts positively on the environment.

B. Other Agency demands

Bangladesh National EA Legislation: National legal requirements for EA are outlined in the 1997 Environmental Conservation Act and the 1998 Environmental Conservation Rules and Regulations.

EA is a mandatory requirement for all major infrastructure including submersible embankments on floodplains.

CCRIP project is only rehabilitating existing roads and market facilities and is not impacting on

the environment

LGED EA Guidelines: In respect to the LGED (potentially the implementing partner for project infrastructure), there is an MoU between the DoE and LGED indicating that LGED would undertake EAs for all their infrastructure projects. LGED have their own EA guidelines (currently being updated) which would be applied to any infrastructure proposals under the current project.

CCRIP project is only rehabilitating existing roads and market facilities and is not impacting on

the environment

(Treated above: IFAD EA Administrative Procedures: As for all IFAD initiated projects, the project design has been subject to IFAD‘s own internal EA process. This ESSN comprises the first

step in this process.)

International Agreements: The GoB has formally committed itself internationally to biodiversity and wetland conservation goals through its signing of (i) the Convention on Biological Diversity; and (ii) the Ramsar Convention.

CCRIP project is only rehabilitating existing roads and is not impacting on the environment nor is

it impacting on biological diversity or wetlands.

Page 291: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 292: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 12

Annex 12

Planning, Monitoring, Evaluation and Knowledge Management

Page 293: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 294: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 12

1

Annex 12

Planning, Monitoring, Evaluation and Knowledge Management

A. Project Orientation and Review

1. Orientation meetings for all CCRIP project staff: All CCRIP project staff members will receive a one day orientation training at the start of the project. The objective of the training will be to development a clear understanding of project objectives, project components, financial arrangements, implementation methodologies, monitoring and evaluation requirements, LCS activities and market management. This orientation will also discuss about

IFAD procedures and requirements.

2. District monthly review meetings: Regular review meetings will be held over the project period to discuss progress, resolve operational problems and ensure quality and timeliness of project implementation. All district and upazila CCRIP staff members, XEN and Upazila engineers will attend these meetings. It will be an important supervision and monitoring tool for the project.

3. Staff capacity building. For capacity building of project staff several training courses on LCS

management, MMC management, accounting and procurement have been planned. All such hands-on training will help project staff members to internalize project activities and procedure and help maintain quality and timely completion of project activities.

4. Annual review and planning workshops. These workshops will be organized annually in each District in order to provide an opportunity for implementing agencies, project staff, key stakeholders and selected project beneficiaries to review project performance and to recommend improvements for incorporation during future implementation of the project.

B. Annual Work Plan and Budget (AWPB)

5. The AWPB will represent the key planning document for the Project. It will serve as the instrument for identifying and integrating management priorities for implementation, forecasting procurement requirements and facilitate the mobilization of staff and resources when needed. It will act as the management tool to control costs and assess achievements. A draft AWPB will be prepared for discussion using the schedules and format recommended by

IFAD. CCRIP will integrate government and IFAD planning processes. Annual planning for projects implemented by LGED is based on the Governments process for its overall Annual Development Plan. In the last quarter of the financial year (March to June) the project will draw up an Annual Work Plan (AWP). This plan will outline the activities and budget for each project year as set out in the Development Project Proforma (the Government‘s Project Document) but may also include works carried over from the previous AWP.

(a) A draft AWPB will be prepared for discussion using the schedules and format

recommended by IFAD;

(b) Although annual in scope, the AWPB will be disaggregated into quarterly segments for monitoring purposes;

(c) A finalized version of the draft will be delivered to PSC no later than 90 days before the beginning of the relevant Project Year for its review and endorsement;

(d) The AWPB will be submitted to IFAD for its no-objection no later than 60 days before the beginning of the relevant Project Year;

(e) This AWPB will be incorporated into the government‘s overall revised ADP.

(f) If required, the PMO may propose adjustments in the AWPB during the relevant Project Year, which will become effective upon approval by the PSC and IFAD.

C. Monitoring & Evaluation

6. CCRIP will have a comprehensive M&E system to generate management information and provide LGED and IFAD with evidence of results and impact against logframe indicators and

IFAD‘s Results and Impact Management System (RIMS). The PMO will include an Monitoring Evaluation and Knowledge Management (MEK) specialist based at PMO. He/she will be responsible for baseline and RIMS surveys, annual outcome surveys and collection of regular monitoring data, as well as project reporting, MIS and knowledge management.

Page 295: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 12

2

7. M&E Specialist will review the Project Log Frame and develop a plan for monitoring each of

the key indicators listed in the Log-Frame. An indicative list to guide project staff on the data to be collected for each log-frame indicator, method of collection, frequency and responsibility for collection will be developed and given in the PIM (final design mission). The Monitoring and Evaluation tasks will involve the following elements:

a) Activity monitoring: Project implementation offices (Upazila, District and Region) will generate monthly reports on activities and outputs, which will be collated by the PMO in a

consolidated report. Reporting will show progress relative to annual and project targets disaggregated by gender, where appropriate. With over three-quarters of project expenditure on civil works, monitoring of construction contracts will be a key element of such activity monitoring and MIDPCR/LGED has a well-established process for such monitoring involving a series of contract milestones. This will need to cover contracts implemented by Labour Contracting Societies (LCS) as well as by contractors.

b) Process monitoring: the project will monitor the functioning of institutions established and supported by the project. This includes Labour Contracting Societies (LCS), and Marketing Management Committees (MMCs). Each of these has their own role and structure and need different monitoring approach. However, there are some common

themes such as targeting of membership, selection of leaders, decision process and financial management. MIDPCR project has developed manuals for LCS management and MMC, which will be used by CCRIP.

c) Outcome monitoring will gather information on outcome and objective level logframe indicators. A series short studies will be done to see impacts on LCS, impact of road construction on traffic, impact of market development on livelihood, management of MMCs etc. MIDPCR has done similar studies, which will be repeated in CCRIP. In particular outcome monitoring will aim to collect evidence of impacts of improvements in physical infrastructure to changes in farm production, expansion of business, availability of inputs, new investments in the markets, wage employment, etc., resulting in increased sales,

which in turn will result in increased income and improved food security, reduction in vulnerability, leading finally to reduced poverty.

d) Impact monitoring will gather information on IFAD‘s anchor indicators regarding asst ownership and reduction in child malnutrition and other 2nd level indicators given in IFAD‘s Results & Impact Management System. Reporting will include information on household

assets, food security and malnutrition indicators (anthropometric data) among children

less than five years old. RIMS data will be gathered from a sample of the population of the project area as a whole, and so include households who are only direct beneficiaries of the project. Additional indicators will relate the anchor indicators to the results of project interventions and thus enable a degree of attribution of change. The project will report on RIMS Level 1 indicators of project outputs and activities on an annual basis. After the MTR, ratings for the effectiveness and sustainability of each component will be included. These ratings will be justified by evidence from indicators of project outcomes14.

Table 1: Key elements of the M&E system

Component Activity/output Process Outcome Impact

Transport infrastructure Contract monitoring Selection and recruitment Traffic surveys

RIMS anchor

indicator survey

Market development LCS contract monitoring Beneficiary Case Studies MMC monitoring

LCS records MMC feedback MMC records (minutes, accounts records, bank accounts)

Traffic surveys LCS outcome survey Market/trader outcome survey Market user feedback

8. Some M&E activities would be contracted to external agencies. This includes the monitoring

of the RIMS anchor indicator which would be contracted to an agency experienced in collection of anthropometric data. MTR and final impact studies will be outsourced. Short studies and case studies will be conducted by the M&E section.

14 This is as per the RIMS Handbook of November 2007

Page 296: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 12

3

D. Reporting

9. The PMO will design a reporting system to track the project physical, financial performance and emerging impact.

A consolidated Physical and Financial Monthly Progress Report (MPR) will be prepared by the PMO which will consolidate all the physical progress made on each of the five project components. This report will also report on overall expenditures on the Project under each component.

A Quarterly Progress Reports (SMPR) will be prepared, which consolidates the monthly reports of the past three months adding any additional financial, procurement, training and TA and physical progress on all five project components.

An Annual Project Progress Report (APR) will be prepared within one month of the end of the Project Year to cover the entire financial year. These reports will be presented to PSC and IFAD.

The PMO will develop specific reporting formats for each component of the project and train project staff in their use and consolidation.

The Upazila and Zone offices will regularly identify success stories or failures and report these for inclusion in the reports.

E. Knowledge management

10. Knowledge Management (KM) activities will use project data and results in order to draw lessons and disseminate experiences. The M&E Specialist will be responsible for knowledge

management and learning. The first of the uses of M&E data is for internal project review and planning workshops. KM activities will aim to share project results and lessons within LGED and with other agencies. This will involve contributions to LGED and IFAD newsletters, posting key information and reports on the CCRIP page of the LGED website, and experience sharing workshops both organised by the project and by other agencies. Wider dissemination will come from participation in IFAD knowledge forums.

Page 297: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 298: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

Annex 13

Financial Management and Disbursement Arrangements

Page 299: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 300: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

1

Annex 13

Financial Management and Disbursement Arrangements

1. Country Specifics: The TI index rates Bangladesh at 2.7/10 and ranks the country at 120/183 in 2011. While the PEFA finalized in December 2011 is not a public document, the mission has reviewed the World Bank‘s ―Operational Risk Assessment‖ (ORA) of Local Government Engineering Department (LGED) conducted in August 2009. LGED is the Lead Project Agency (LPA). The ORA has assessed fiduciary risks of the LPA at the HQ and the

District levels. It is to be noted that while donor-funded projects work within the LGED structure and utilizing LGED procedures, they do have reasonable autonomy within that structure to make improvements in procedures.

2. The mission has sought to ensure that the financial management arrangements proposed for CCRIP are sufficient to ensure the effective and efficient usage of financing and

harmonization with the ADB – the collaborating co-financer. Additionally, as LGED is

currently implementing three projects where IFAD is the lead donor agency – MIDPCR,

SCBRMP and HILIP, the proposed financial management arrangements for CCRIP will draw

from the best practices observed and will be tailored to suit the specific requirements of CCRIP. To this end the Financial Management Assessment Questionnaire (FMAQ) at Design (See Appendix 2) and the Risk Analysis (See Appendix 3) using the Guidelines for Financial Management at Design, conducted for CCRIP, have been revisited and updated. Additionally, this mission visited a village in the Nowakhali District of the MIDPCR project to further explore the workings of the Labour Contracting Societies (LCS) to assess the sufficiency of the financial management systems and ensure that arrangements are

adequate to mitigate risks of funds flow to the ultimate beneficiaries.

3. Budgeting: The PMO will be responsible for the budgeting as part of the AWPB exercise. With respect to Government of Bangladesh (GoB) financing, the counterpart funds are budgeted in the DPP and released in installments. Occasional delays in release of GoB funds are noted. GoB funds will be monitored during supervisions to ensure that the funds are released in a timely manner.

4. Funds flow and Disbursement Arrangements: The Project will use the revolving fund

method for the Designated Account advances. The modalities, with respect to revolving fund will be detailed in the Letter to the Borrower (LTB). Advances to the Designated Account(DA), for the Loan and the Grant, will be transferred to two separate accounts held in USD at Bangladesh Bank. The funds from this account will be transferred to an operational account aka Project Account (held in a commercial bank in Taka) to be administered by the Project Director (PD) who will, based on type of expenditure and

utilization, transfer funds to the 12 district bank accounts (held at commercial banks) administered by the respective Executive Engineers (XENs), who will follow the funds flow chart (See Appendix 1).

5. Documentation of expenditures made from the DA will be done, at a minimum, on a monthly basis following the statement of expenditures thresholds indicated in the LTB (it is recommended that USD 100 000 be applied as the SOE threshold as this is aligned with ADB). Direct payments from IFAD may be made to suppliers/ contractors/

consultants per the instructions in the LTB.

6. The Borrower/Recipient shall make the proceeds of the Financing available to the Project Parties upon terms and conditions specified in the Financing Agreement or otherwise

approved by the Fund for the purpose of carrying out the Project. Payments for all project procurement and other administrative/ operational expenses will be made directly from the Project Account. Payments for all staff salaries will be paid by the GoB through its

disbursement channels.

7. Funds, for all activities, except contracts performed by contractors, will be transferred to the District Office Bank Accounts (maintained separately for the Project), at the start of each quarter or as per requirement from those offices. These requisitions must be prepared based on realistic forecasts for the upcoming quarter and must be net of the closing cash balance of the quarter just ended. To avoid delays in reporting from sub levels to the PMO, they will need to send only Excel files of their Cash Book (clearly indicating

Category & Component of expenditure and source of funding), Bank Statement and bank

Page 301: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

2

Reconciliation Statement to the PMO on a monthly basis. It will be the responsibility of the

PD and the Accountant to ensure that there is no build up of idle funds in the project sub-accounts.

8. Funds for contractor payments: To ensure an efficient utilization of funds between 12 districts and limit the amounts of unutilized resources, the payments for all contractors will be made on receipt of a summary of contractors bills passed for payment at the District Offices.. The summary sheet, certified by Upazilla and District engineers, will be prepared

and submitted by the XEN to the PD, who will review and approve the payment to the District bank account via electronic transfer. The summary sheet will be sent to the PMO on an expedited basis.

9. It is understood that under GOB regulations, any expenditure which is not entirely met from IFAD funding will have to be processed through the district bank accounts as the XEN is the Drawing and Disbursement Officer at the District Level. The PD may, in consultation

with IFAD Country Programme Manager, change the allocation of funds amongst the various District Office Bank Accounts, with a view to ensure the smooth, efficient and transparent flow of funds.

10. As the accounting system is expected to be in place before implementation begins, retroactive financing is recommended for the procurement of the software, the hiring of the part time project financial management specialist, the accountant and 2 accountants assistants and training costs for the same.

11. Taxation As per the Fund‘s policy, none of the proceeds of its Financing can be utilized for the payment of Taxes during the course of project implementation. The Government of Bangladesh will cover the payment of taxes on all procurement (goods, services, works) undertaken by the project, according to the Financing Agreement.

12. Internal Controls: Internal control systems at the PMO were assessed based on those in existence for the on-going project also implemented by LGED and found to be weak with respect to segregation of duties; retention of records; security of information. The risks

have been mitigated by ensuring the mitigating measures as described in Paragraph 27 are in place before implementation commences. Assessments of the internal controls will also be included in the TORs for the internal audit department of LGED. Procedural aspects related to Financial Management and Disbursements are detailed in the live document – the Project Administration Manual (PAM), allowing for revisions when these

controls are assessed to be risky.

13. Staffing: The PMO will have one Accounts Officer and two Accounts Assistant who will be responsible for all financial management and accounting matters relating to the Project including book keeping, financial reporting, coordination with auditors and internal auditors, vendor payments, bank reconciliations and bank operation, funds flow to sub accounts, monitoring of expenditure against budgets, preparation of Withdrawal Applications etc. An Accounts Assistant at each of the twelve District offices will maintain electronic records relating to the project, oversee and reconcile bank operations, prepare

periodic financial reports and handle routing of LCS payments, monitor expenditure against budgeted expenditure, etc. and prepare reports for the PMO at periodic intervals. The 32 Upazila offices will not have any accounting staff, but Excel accounting records will be utilized throughout project duration. Detailed Terms of Reference of Financial Staff at all levels are included in the PAM.

14. Financial Accounting and Reporting: GoB and all institutions under its purview maintain their records per Bangladesh Accounting Standards. The last Report on the

Observance of Standards and Codes (ROSC) is dated (2003) but significantly states that gaps exist between the Bangladesh Accounting Standards and International Accounting Standards. It is noted that GoB maintains accounts using single-entry, cash basis accounting. At a minimum IFAD expects that projects maintain their books using IPSAS cash basis. As the single-entry account is deemed insufficient for this project, the procurement of an off-the-shelf accounting software is crucial. It will have a few pre-

formatted input screens, simple menus, and the forms will be displayed in both English and Bengali. The software should be in place before implementation commences. The mission had requested and received a demo of a software and found the requirements compatible with the project. All finance and accounting staff at the PMO will be trained on double-entry accounting and on the software to build capacity to international standards. The project accounts will reflect all financial transactions during the project period, both of

Page 302: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

3

the IFAD loan/grant and other sources of financing by project component and separately

by standard expenditure categories. Reporting requirements are detailed in the PAM. Additionally, the minimum requirements for the accounting software will be included in the PAM.

15. All subsidiary ledgers, contract registers, and fixed asset registers will be electronic throughout project life. The project will maintain accounts and records until the Financing

Closing Date, and shall retain such accounts and records for at least ten (10) years thereafter. The project will implement double-entry accounting and IPSAS cash in order to meet international standards. The accounting records will be maintained centrally at the PMO in Dhaka. Accounts from the District level will be transferred to the PMO for consolidation and issuance of financial statements at reporting dates. The Borrower/Recipient shall deliver to the Fund detailed financial statements of the

operations, resources and expenditures related to the Project for each Fiscal Year prepared in accordance with IPSAS cash basis to the Fund and deliver such financial statements to the Fund within four (4) months of the end of each Fiscal Year. In addition, the borrower/recipient will submit each Quarter and once every half-year the consolidated, unaudited financial statements. The financial Statements shall be prepared in IFAD‘s

standard financial reporting formats (enclosed to the Project Administration Manual).

16. The LGED Unified Financial Management System (UFMS), while available does not satisfy

the needs of minimum requirements as it is based on single entry accounting and would have to undergo customization to enable project use.

17. Internal audit: The ORA of the World Bank assessed LGED‘s internal audit function, which has the responsibility to conduct the function on all projects under implementation and on Districts offices. The ORA states – ―the checklist for internal audit developed by internal audit cell at LGED contains the inspection of internal oversight of management controls that includes checking of proper segregation of duties, financial operations contains bank

control, safeguard of cash, the asset control includes tracking of organizational assets, inventory etc. The checklist contains 79 itemized checks. All these ensure the internal oversight of fiduciary climate. Although this represents good progress, the internal audit unit still concentrates the majority of its work at the transaction level rather than reviewing control systems and procedures.‖ The report further states – ―This represents an operational risk that audits only verify the accuracy of the payments, and do not

identify areas that need strengthening in the control environment. Further, since the

internal audit unit also focuses its attention at the transaction level, it isn‘t identifying and correcting larger systemic issues.‖ While the capacity and staffing of the IA department is adequate to perform this task, it is headed by an Engineer and staff have either Bachelors or Master‘s degrees in a variety of disciplines. The IA unit prepares an annual work plan with respect to Districts and Projects selected for audit. In the internal audit of Districts, both, GoB and Donor funded projects are examined. It is possible that a project might not

get selected for internal audit and therefore clarification was sought and the following recommendations are made on the basis of the responses: (1) the project may request the internal audit cell to perform an internal audit on the project. IFAD recommends that in the event the project is not chosen for internal audit, a request will be made in all years after the first year of implementation; (2) draft TORs for the internal audit will be provided by the PMO (with the assistance of the Donors) to the Audit and Accounts Cell; and (3) in the event that IFAD is not satisfied with the internal audit arrangements and reporting,

IFAD can recommend the hiring of an external chartered accountancy firm to conduct an internal audit.

18. External Audit: The external audit for all donor-financed programmes/projects is conducted by the Foreign-Aided Projects Audit Directorate (FAPAD). FAPAD will also conduct the audit for CCRIP. TORs, to ensure that all financiers‘ requirements are being

met, will be harmonized and presented to FAPAD before the audit exercise commences. Prior audit work of FAPAD has been rated as satisfactory, thereby showing FAPAD‘s compliance with its TORs and IFAD Project Audit Guidelines. FAPAD will utilize International Standards of Auditing when undertaking its audit work. As the fiscal year end of CCRIP will be June 30, the audited financial statements are due at IFAD no later than December 31 (within six months). The audit report will contain a separate management letter with an opinion on the Internal Control system of CCRIP and related audit

observations; separate opinions on certified Statements of Expenditure (SOE), the Special Account and the Project Financial statements; a statement as to the adequacy of the

Page 303: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

4

accounting system and internal controls and whether IFAD funds have been used for their

intended purpose; a confirmation that SOEs correctly reflect the expenditures incurred; and commencing with the second year audit a follow-up on the implementation of prior year recommendations. Submission of the audit report after the due date, of six months after fiscal year end, may result in suspension of the financing.

19. Withdrawals from the Loan Account: Between the date of entry into force of the Financing Agreement and the Financing Closing Date, the Borrower/Recipient may request

withdrawals from the Loan Account and/or Grant Account of amounts paid or to be paid for Eligible Expenditures. The Fund shall notify the Borrower/Recipient of the minimum amount for withdrawals.

20. No withdrawal shall be made from the Loan and/or Grant Accounts until the first AWPB has been approved by the Fund and the Fund has determined that all other conditions specified in the Financing Agreement as additional general conditions precedent to withdrawal have

been fulfilled. The Financing Agreement may also establish additional specific conditions precedent to withdrawal applicable to particular categories or activities. Withdrawals to meet the costs of starting up the Project may be made from the date of entry into force of the Agreement, subject to any limits established in the Financing Agreement. In this

connection, the following additional provisions need to be kept in mind.

21. When the Borrower/Recipient wishes to request a withdrawal from the Loan and/or Grant Accounts or a Special Commitment, the Borrower/Recipient shall deliver to the Fund an

application in the form specified there for by the Fund, together with such documents and other evidence in support of such application as the Fund shall reasonably request.

22. The Borrower/Recipient shall furnish to the Fund satisfactory evidence of the authority of the person or persons authorised to sign such applications and the authenticated specimen signature of each such person. Under the provisions of the General Conditions (article IV, section 4.04(b)), the Fund requires the borrower‘s (or recipient‘s) representative, as designated in the financing agreement, to furnish satisfactory evidence of the authority

and authenticated specimen signatures of the individuals who will sign WAs on behalf of the borrower. This evidence must reach the Fund before the first WA is presented by the borrower and should be the original (photocopies, facsimiles or other means of transmission are not acceptable). A sample template is provided in annex 1 to the Loan Disbursement Handbook. In order to avoid delays in disbursements, this documentary

evidence should be furnished to IFAD as soon as possible after entry into force of the

financing agreement.

23. Each WA should be signed by such duly authorized individuals, and the Fund must be notified of any change in the signatories authorized to withdraw funds from the loan/grant account. The Fund must also be notified of the designated signatories for operating any designated and/or programme or other accounts, including changes thereto, whether or not these authorized signatories are included in the financing agreement. Such changes, as effected during the life of the project, must be communicated promptly to the Fund.

24. If the Borrower/Recipient requests a withdrawal from the Loan and/or Grant Accounts for amounts to be paid thereafter for Eligible Expenditures, the Fund may, before transferring such amount to the Borrower/Recipient, require that the Borrower/Recipient provide evidence satisfactory to the Fund showing that previous withdrawals have been properly spent for Eligible Expenditures. The Fund may place reasonable limits on the amount that the Borrower/Recipient may withdraw in advance or the overall balance of such advance withdrawals, and may require that such amounts be held in a freely convertible currency

and/or be held in an account designated for that purpose in a bank acceptable to the Fund.

25. Items to be financed are usually grouped into categories of expenditures and are shown as a schedule in the financing agreement. The financing schedule presents the amount allocated to each category and subcategory, and the percentage of financing of eligible project expenditures as assessed at the time of project design and approved by IFAD‘s Senior Management. Reallocation of funds from one category to another may be allowed,

unless the financing agreement prohibits this. During project implementation, should the need to reallocate financing resources among categories of expense arise, such reallocation would be processed in the applicable schedule(s) to the financing agreement after prior consultation and agreement between the borrower and the Fund.

26. Detailed withdrawal procedures, forms and templates are available in IFAD‘s Loan Disbursement Handbook and the Project Administration Manual.

Page 304: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

5

27. The mission has reached the conclusion that financial management risk is rated at

medium and the financial management arrangements, as they exist in MIDPCR, would not provide the maximum assurance that the funds are used, efficiently and effectively, for the purposes intended. Therefore, the areas in which change is recommended are – (1) procurement and installation of a multi-lingual (Bangla/English) accounting software before implementation begins; (2) hiring of a financial management specialist or a chartered accountancy consulting firm, on a part-time basis to ensure the appropriate use of the

system and of the financial management arrangements; (3) ensuring that sufficient accounting staff, with appropriate qualifications and experience, are recruited; and (4) to maintain sufficient liquidity in the accounts, payments will be made from the PMO to the District bank account based on receipt of a certified summary sheet of works performed by contractors from the XEN. If the mitigation measures are in place when implementation begins, the residual financial management risk is rated at low (See Appendix 3).

28. The Project should note IFAD’s Anti-corruption policy where zero-tolerance applies where it has determined, through an investigation performed by the Fund, the borrower or another competent entity, that fraudulent, corrupt, collusive or coercive actions have occurred in projects financed through its loans and grants, and it shall enforce a range of

sanctions in accordance with the provisions of applicable IFAD rules and regulations and legal instruments. 'Zero tolerance' means that IFAD will pursue all allegations falling under the scope of this policy and that appropriate sanctions will be applied where the allegations

are substantiated. This policy applies to IFAD-funded activities whether supervised directly by the Fund or by a cooperating institution. The Fund will continue to improve its internal controls, including controls inherent in or pertaining to its project activities, so as to ensure that it is effective in preventing, detecting and investigating fraudulent, corrupt, collusive and coercive practices. The Fund shall take all possible actions to protect from reprisals individuals who help reveal corrupt practices in its project or grant activities and individuals or entities subject to unfair or malicious allegations.

Page 305: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

6

Appendix 1 - Flow of Funds

Page 306: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

1

Appendix 2 – FMAQ at Design

Lead Implementing Entity is the Local Government Engineering Department (LGED)

Topic Response Remarks

1. Implementing Entity

1.1 Which entity is the LPA?

What is the entity’s legal status?

LGED; GoB entity

1.2 Will financial management of the

project be the responsibility of a the

LPA or be undertaken within the-PMO?

FM will be the responsibility of the PMO

created within LGED

1.3 Has the entity implemented a donor

financed project in the past - if so,

please provide details?

Yes, LGED has vast experience with several

donors including a long standing partnership

with IFAD.

About 40% of all

LGED projects are

donor-funded projects.

NOTE:

In the case of a Government Department, the FMS should initially focus on the status of the

country PFM systems in order to gauge level of fiduciary risks to which the proposed project

may be exposed.

Once an understanding of the PFM environment has been ascertained, the FMS should switch

focus down to project level and focus on the department(s) or unit(s) that will financially

administer the project.

TOPIC Response Remarks

2. Funds Flow/Disbursement

Arrangements

2.1 Does the Implementing Entity

have previous experience of using

imprest fund and donor funding

SOE procedures?

Were there any problems or issues

encountered by project staff in the

operation of the imprest fund or

SoE procedures in the past?

Yes, LGED has sufficient

experience.

Issues are related to

management of funds flow

and management of several

bank accounts.

Increased size of projects in the

country is leading to either (a) more

agencies being involved in a project;

or (b) more districts being covered as

part of the project. As the funds flow

in BD is decentralized to the district

level, this is a potential area of funds

lying idle with lesser performing

districts while the performing ones

stall implementation awaiting fund

transfers.

2.2 Does the Implementing Entity

have experience in the

management of disbursements

from IFAD or other donors?

Have there been the major

problems in the past in receipt of

funds by the entity?

YES, see 2.1 ; 2.no problems

encountered so far in

receiving IFAD funds;

The Designated Account (SAFE)

account, for all donor funded

projects, is opened at Bangladesh

Bank and then the funds flow into a

Taka operational account.

2.3 Does the entity have/need to

develop capacity to manage

foreign exchange risks?

No, GoB bears the foreign

exchange translation risks.

Page 307: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

2

TOPIC Response Remarks

2.4 Are the beneficiaries required to

contribute to project costs?

How are payments made for the

counterpart funds?

If counterpart funds are to be

contributed in kind (in the form of

labour), are proper guidelines

formulated to record and value the

labour contribution?

Beneficiaries do not provide

funds. The Labour

Contracting Societies (LCS)

provide labour in civil works

contracts assigned to them and

receive payment as wages and

a profit element which is

embedded into the contract

amount.

2. GoB transfer funds to

project through MOF to

project Operational Accounts

in Taka

3. Counterpart funds are not

contributed in kind, they

transfer funds to project

through same process as for

IFAD funds.

LCS activities are a unique creation

of LGED and guidelines for

implementation of LCS activities

exist at LGED for both GoB and

Donor funded projects.

2.5 Is part of the project implemented

by communities or NGOs?

Does the PMO have the necessary

reporting and monitoring features

built into its systems to track the

use of project proceeds by such

agencies?

Yes, in form of LCS for

market development and

infrastructure; NGOs do assist

LCS in the performance of

their activities.

2.Yes, LGED has guidelines

for use of LCS and these have

been modified further for use

by IFAD projects.

2.6

Describe (proposed) project funds

flow arrangements; (attach flow

chart and explanation of the flow

of funds from IFAD, government

and other financiers.)

Funds will flow from the

Donor into the Designated

Account. From Designated

Account the funds will be

transferred, in local currency

to a commercial bank, these

funds will be further

transferred to District

accounts or utilized for

payments See funds flow

chart.

Funds once transferred into the

operational account cannot be re-

converted into a convertible currency

i.e. cannot be deposited bank into the

DA.

To avoid the risk of idle funds, and

enhance utilization of the DA,

contractor payments will flow

expeditiously to the District account

based on a summary sheet of

payments due submitted by the XEN.

2.7 In which bank will the Imprest

Account be opened?

The Designated Account (DA)

is opened in Bangladesh

Bank,

2.8 Are the (proposed) arrangements

to transfer the proceeds of the

financing (from the government /

Finance Ministry) to the

Implementing Entity satisfactory?

No, it is noted that an

inefficient utilization of funds

occurs when more than 3-4

districts are involved as funds

remain idle. In the proposed

project, to alleviate idle funds,

the PMO will make payments

directly to contractors, thereby

centralizing a significant

portion of the resources.

See 2.6 above.

Page 308: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

3

TOPIC Response Remarks

3 Staffing

3.1 What is the (proposed)

organizational structure of the

accounting department? Attach an

organization chart.

It will be headed by a Finance

Manager who will be assisted

by 2 Accounts Officers and 2

Accounts Assistants.

As this project’s accounting staff will

also be responsible for the other

donors, the number of staff has been

increased. Additionally, as there is

no increase in staff levels at the

District levels, and capacity at the

District levels has been assessed as

moderately satisfactory, 2.6 above

has been recommended.

3.2 Identify the (proposed) accounts

staff, including job title,

responsibilities, educational

background and professional

experience. Attach job

descriptions and CVs of key

accounting staff.

Job descriptions will be

included in the Project

Implementation Manual.

3.3 Are there written position

descriptions that clearly define

duties, responsibilities, lines of

supervision, and limits of

authority for all of the officers,

managers, and staff?

Yes; the organizational

hierarchy and job descriptions

are clearly defined and are

similar across LGED projects

Will be included in the PIM

3.4 Is the finance and accounts staff

adequately qualified and

experienced?

No, the LGED deputed staff

have many yrs experience, but

is noted that qualifications

might be limited. At District

levels this is further amplified.

The arrangements will include the

hiring of a chartered accountant/firm

to assist the accounts staff on a

periodic basis to ensure that FM stays

on track.

3.5 Are the project accounts and

finance staff trained in IFAD

procedures?

Yes, training is received at

start-up; again before

implementation and refresher

training given from time to

time.

The arrangements as stated in 3.4

will facilitate the application of IFAD

procedures.

3.6 Are any Finance Staff appointed

on contract?

What is the duration of the

contracts

Indicate key positions not

contracted yet, and the estimated

date of appointment

No ; all accounts staff are govt

staff, all are deputed from

LGED to the Project.

The exception is 3.4 above, where it

is intended that a retainer contract

will be issued for one year. The aim

is to issue the contract before

implementation begins and allow for

the financing under retroactive

financing.

3.7 What is training policy for the

finance and accounting staff?

No documented training

policy as such. The training is

based on need.

CCRIP should have a clear,

documented FM training policy.

Training should be periodic and build

FM capacity of staff; the FMS should

develop the plan

3.8 Is there evidence that finance staff

are regularly transferred to other

Government departments

At what frequency are personnel

transferred?

Some evidence of transfers

but not a systemic problem

within LGED.

Page 309: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

4

TOPIC Response Remarks

3.9 Is the project finance and

accounting function staffed

adequately?

The bulk of the function rests

in the hands of the Accounts

Officer, while the accounts

assistants provide clerical

support.

While staffing levels are adequate,

there is an issue with the under-

utilization of the staff that are hired.

The recommendation is that

assignments of duties is done early in

the implementation.

4. Accounting Policies and

Procedures

4.1 Does the entity have an integrated

accounting system that allows for

the proper recording of project

financial transactions, including

the allocation of expenditures in

accordance with the respective

components, disbursement

categories, and sources of funds?

Will the project use the entity

accounting system?

LGED does have an

accounting system UFMS –

Unified Financial

Management Software,

however this is on the basis of

single entry accounting and

will have to be customized in

order to prove efficient for

project use. A recent WB

assessment determined that

the customization would take

time and it would still not

comply with IPSAS cash

basis.

CCRIP project staff need to be

trained on double entry accounting

system and project needs to

procure/install and implement

accounting software to be ready

when implementation begins.

4.2 Are controls in place concerning

the preparation and approval of

transactions, ensuring that all

transactions are correctly made

and adequately explained?

Yes, the Internal Controls for

accounting come from LGED;

the accounting manager and

PD verify and approve all

transactions prior to

recording; the FM manual of

project provides guidance

regarding approval criteria for

transactions. At the Districts

levels the segregation of

duties is observed to a lesser

degree.

At District levels, there is an

inordinate paper-trail to overcome

the lack of segregation of duties.

4.3 Is the chart of accounts adequate

to properly account for and report

on project activities and

disbursement categories?

The LGED Chart of Accounts

which is being used is

adequate to account for and

report on project activities.

CCRIP’s chart of accounts will be set

up in the accounting software.

4.4 Can cost allocations to the various

funding sources be made

accurately?

YES, it’s possible with the

accounting system and

allocations have been done

accurately so far; LGED

reports per component in its

own system

4.5 Are the General Ledger and

subsidiary ledgers reconciled and

in balance?

Single entry accounting, not

double entry, subsidiary

ledgers do not exist

CCRIP project needs to use double

entry accounting and also establish

subsidiary ledgers in its sys so that

it’s fully IFAD compliant

Page 310: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

5

TOPIC Response Remarks

4.6 Are all accounting and supporting

documents retained on a

permanent basis in a defined

system that allows authorized

users easy access?

Yes, project documents since

inception are retained in paper

form in binders and stored in

cabinets in office of the

Accounts Officer. However

the cabinets don’t have lock &

key, except 2 of them (with

accounting manager).

The accounting software will

mitigate the risk of unauthorized user

access.

Project Budgeting System

4.7 Who is responsible for preparation

and approval of project budgets?

The PMO is responsible for

this; The budget is then

approved by PD, sent to

LGED Chief Engineer, then to

inter-ministerial meet for

approval. Once all have

approved, it’s sent to IFAD

for approval.

4.8 Are project budgets prepared for

all significant project activities in

sufficient detail to provide a

meaningful tool with which to

monitor subsequent performance?

YES, budgets are broken

down by category,

component, and source of

funds

Where several sources of funds exist,

the AWPB should be further detailed

to show amounts from each source.

4.9 Are procedures in place to plan

project activities, collect

information from the units in

charge of the different

components, and prepare the

budgets?

Since project follows LGED

budgeting procedure, it has all

procedures in place to plan,

collect, and prepare budgets

Payments

4.10 Are all invoices stamped PAID,

dated, reviewed and approved,

and clearly marked for account

code assignment?

YES; they are reviewed and

approved, although no stamp

bearing PAID symbol was

seen on the documents.

The project needs to buy a stamp

with PAID marked on it so that

things are more clear and

straightfwd; this is standard

procedure in the area of payments;

high risk of re-using invoices to pay

again/fraud*

Financial Policies And

Procedures

4.11 What is the basis of accounting

(e.g., cash, accrual)?

Cash basis, not per IPSAS or

GAAP

To mitigate this an accounting

software has been recommended,

4.12 What accounting standards are

followed?

Single entry, use the GOB

accounting standards.

CCRIP will use international

standards as recommended by IFAD

from the start; IPSAS cash basis and

staff need to be trained on this.

4.13 Does the project have an adequate

policies and procedures manual to

guide activities and ensure staff

accountability?

Yes, a PIM defining

procedures will exist,

additionally LGED has a

manual for donor-funded

projects.

Page 311: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

6

TOPIC Response Remarks

4.14 Do procedures exist to ensure that

only authorized persons can alter

or establish a new accounting

principle, policy or procedure to

be used by the entity?

Yes, LGED procedures

regarding accounting policy

change apply; however, use of

procedures is N/A; the scope

for changing govt accounting

policy is very limited; also,

too many steps would be req’d

for change to take place;

change would require LGED

mgmt approval

4.15 Is there a written policies and

procedures manual covering all

routine project financial

management activities?

Are manuals distributed to

appropriate personnel?

LGED procedures for donor

funded projects exist for

routine project financial

management activities.

This manual is distributed to

appropriate personnel.

The project will have a PIM

specifically describing procedures for

this project.

Cash and Bank

4.16 Does the organization maintain an

adequate, up-to-date cashbook,

recording receipts and payments?

Yes.

4.17 Are bank and cash reconciled on a

monthly basis?

Mostly, some months may be

missing; but reasons exist for

missed months

4.18 Indicate names and positions of

authorized signatories of project

bank accounts.

Only the PD is the authorized

signatory on the project bank

accounts. At the District levels

the XEN (Executive Engineer)

is the only authorized

signatory,

It is recommended to have 2

signatories, a co-signer for better IC*

Safeguard over Assets

4.19 Is there a Fixed Asset accounting

system, with a Fixed Asset

Register, fully implemented - as

part of an integrated accounting

system

Is the system maintained up to

date ?

Yes, the FA register and FA

issue register exist; they’re

updated constantly. It is

maintained manually.

The accounting software will assess

the risk of manual maintenance of

assets. FA register for Districts can

be in XL; data from XL entered into

PMO software*

4.20 Are there periodic physical

reconciliation of fixed assets and

stocks?

Periodic physical

reconciliations exist, but the

periodicity has not been

defined in any document.

PIM will clarify the periodicity of

physical reconciliation of assets and

stocks.

Page 312: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

7

TOPIC Response Remarks

Other

4.21 Has the project advised

employees, beneficiaries and other

recipients to whom to report if

they suspect fraud, waste or

misuse of project resources or

property?

Advised verbally, no written

instructions or procedures;

this is a weakness to be

corrected in CCRIP

CCRIP should have written

whistleblower policy in FM and PIM

*

4.22 Do policies and procedures clearly

define conflict of interest and

related party transactions (real and

apparent) and provide safeguards

to protect the organization from

them?

PD states that integrity and

honesty is verbally

communicated and expected

of staff anyway. No written

policy or procedure; project is

at risk

CCRIP needs to correct this

weakness *

4.23 Do controls exist for the

preparation of the project payroll

and are changes to the payroll

properly authorized?

Yes; but the payroll rec done

once per year only; only 1

person deals with whole

payroll process; the method of

payment involves 2 cheques

and controls could be

tightened further

The payroll process involves

collecting cheque from GoB

Treasury, depositing it into project

acct. then project issues separate

cheques for employees to pay them.

Bearer cheques are issued to

employees to pay them. The accts

assistant is also payroll assist. He

records and issues bearer cheques.

However, process is approved by PD

and accounts mgr.*

5. Internal Control and Internal

Audit

5.1 Segregation of duties - are the

following functional

responsibilities performed by

different units or persons: (i)

authorization to execute a

transaction; (ii) recording of the

transaction; and (iii) custody of

assets involved in the transaction?

Yes. SoD exists. The PD is

only one who gives

authorization to undertake a

transact; recording done by

accounts manager; custody is

held by admin officer (he’s

also in charge of FA register)

5.2 Are the functions of ordering,

receiving, accounting for, and

paying for goods and services

appropriately segregated?

1.order done by PD only

2.only Admin Officer receives

the asset when it arrives

3.accounting manager accts

for it 4.PD approves the

payment for the purchase,

normally by cheque; PD has

many roles to play in the

project, he is sole authorizer

to undertake an activity and to

pay for it

Page 313: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

8

TOPIC Response Remarks

5.3 Are bank reconciliations prepared

by someone other than those who

make or approve payments?

The bank rec done by

accounts mgr, the PD is only 1

who approves payments, the

accounts assistant or mgr can

make the payments (whether

for salaries or purchases); in

this case, accounts mgr can

make the payment and do the

bank rec, an IC risk

CCRIP project should improve

segregation of duties and utilize skills

of staff more efficiently. For internal

control purposes some of the duties

can be delegated to accounts

assistants.

5.4 Is there an internal audit

department in the LPA?

LGED has Internal Audit (IA)

dept that does IA of all

projects of LGED; the IA of

projects covers the

district/sub-district levels of

projects as well

IA may not audit the project during

it’s life, therefore a request for IA

will be requested in Year 2, 3, 4 and

5. If IA is found to be insufficient, an

external firm will be hired to perform

an internal audit.

5.5 What are the qualifications and

experience of internal audit

department staff?

15 staff have varying degrees

at the Bachelor’s and Master’s

level.

5.6 To whom does the internal auditor

report?

Chief engineer of LGED

5.7 Will the internal audit department

include the project in its work

program?

Not automatically. IA

prepares an annual work plan

to include x number of

projects and x number of

Districts. When a District is

included, all projects in the

District are audited, however

it is possible for the project to

not receive an internal audit

See 5.4 above.

5.8 Are actions taken on the internal

audit findings?

YES, followup actions are

always taken on

recommendations as it is a

govt matter / public funds

involved

Investigations of staff at different

levels are prescribed treatment per

the regulations of the IA Department

6. External Audit

6.1 Who is the external auditor of the

entity?

FAPAD, they do audits of all

donor financed project in

Bangladesh

6.2 Are there any delays in audit of

the entity? When are the audit

reports issued?

No, FAPAD is able to meet

IFAD deadlines.

6.3 Is the audit of the entity conducted

according to the International

Standards on Auditing?

Yes, ISA used for project

audit

Page 314: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

9

TOPIC Response Remarks

6.4 Were there any major accountability issues brought out in the audit report of the past three years?

Were there any issues noted in

prior audit reports related to the

operation of project imprest

accounts or use of SOE

procedures?

As per 2011 audit review: CF

for FY not properly reported –

only end bal shown; possible

ineligible exp of $40k,

overstatement of exp in the

PFS leading to qualified

opinion;

2.the SA and SOE were

unqualified, no issues noted

there

Audit observations remain in the

subsequent audits even after they

have been resolved. IFAD will work

with FAPAD to resolve the issue.

6.5 Will the entity auditor audit the

project accounts or will another

auditor be appointed to audit the

project financial statements?

LGED is audited externally by

Auditor-General of

Bangladesh, but FAPAD

audits only foreign-aided

(donor) projects of GoB.

FAPAD is a division of AG

dept. So, the entity (LGED)

auditor is not the same one as

for the project . However,

both auditors are related,

FAPAD is part of AG of GoB.

6.6 Has the project prepared

acceptable terms of reference for

an annual project audit?

The project does not direct or

advise FAPAD on how to

audit; FAPAD has plenty of

experience in auditing donor

financed project and so TORs

don’t need to be made for

them; they know what to do,

how to do it. However, minor

advice, such as how to audit a

particular line item or area of

the PFS, can be given to

FAPAD by project staff

Project will provide, informally, the

TORs for the IFAD audit to FAPAD.

7. Reporting and Monitoring

7.1 Does the reporting system need to

be adapted to report on the project

components?

Adapted in the excel based

system

Will be adapted in the accounting

software.

7.2 Does the project have established

financial management reporting

responsibilities that specify what

reports are to be prepared, what

they are to contain, and the

frequency of production?

The PD stated that Standard

Operating Procedures wrt to

FM reporting are already

established. These come from

LGED. The FM manual lists

these reporting responsibilities

and reports; project has

reporting experience for both

GoB and IFAD

Page 315: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

10

TOPIC Response Remarks

7.3 What is the frequency of

preparation of financial

statements? Are the reports

prepared in a timely fashion so as

to be useful to management for

decision making?

Annual and Quarterly

frequency; the annual PFS are

audited, the Quarterly ones are

unaudited and meant to satisfy

IFAD req’d. The PD uses both

in order to make decisions.

Quarterly reports are more

timely, but reliance is less as

they’re unaudited.

7.4 Do the financial reports compare

actual expenditures with budgeted

and programmed allocations?

Both the Quarterly and annual

PFS compare actuals vs

budgeted expenditures

7.5 Are financial reports prepared

directly by the automated

accounting system or are they

prepared by spread sheets or some

other means?

Done in XL, manually; no

software exists

Accounting software will be in place

for CCRIP

7.6 (In case of need of consolidated

financial statements) Is the

accounting system sufficiently

equipped to ensure proper

consolidation of entities’ financial

data?

Manual consolidation of

entries done at PMO level

Risk of accounting/calculation errors

here; Accounting software will

mitigate this risk

8. Information Systems

8.1 Is the financial management

system computerized?

NO

8.2 Can the system produce the

necessary project financial

reports?

N/A

8.3 Is the staff adequately trained to

maintain the system?

N/A

8.4 Are adequate systems in place to

“back up” financial records?

The project has manual

backup of records; the XL

sheets are stored on pen drives

and CDs and stored in

accounting manager’s office;

the book records unfortunately

don’t have any backup, only

single copies exist for them;

high risk strategy

CCRIP should start out with a

computerized FM sys/software that

does auto-backup on a weekly or

monthly basis; in addition, there

should not be any manual recording

or records; the data s/b backed up on

external media and stored at a

separate location than the PMO; also,

it depends if software will be

LGED’s software and therefore

connected to central servers (central

backup), or stand-alone (own

backup)*

Page 316: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

11

Appendix 2 – Risk Analysis at Design

Lead Project Agency = Local Government Engineering Dept

Implementing Agency = PMO

Risk Risk

Assessment*

Proposed Mitigation

Inherent Risks

1. National and EA environment M- World Bank country level appraisal (CAR)

indicates that public sector FM is ―weak‖ and ―high risk‖. Therefore financial arrangements will not use the primary PFM systems. An Operational Risk Assessment of LGED, conducted by the World Bank, However, the LPA for the project is a government

department with enhanced FM and much experience of donor-funded projects. Donor

funded projects are controlled and managed via a PMO/PMO. Due to the fact that both entities are exceptional relative to other govt entities, the risk is reduced to low medium. Mitigation action would involve implementing

improvements to the IC system of existing PMO.

Control Risks

2. Funds flow/disbursement

arrangements

Need for Imprest Accounts(s)

Use of Direct Payments

Need for the Statement of Expenditure.

M

The funds are controlled by the PD and XEN, a simple and tight structure. As most project

implementation occurs at district level, the XEN controls majority of the funds. Given that there are 12 Districts, the risk of idle funds is high. Additionally, The ORA pointed out that as the District XEN is involved in the selection of the projects, the procurement and contracting,

invoice preparation/approval, payment

authorization and that he has the ability to open commercial bank accounts represents a significant control weakness due to the lack of segregation of duties. Mitigation actions payments for contractors will be made by the PMO to District accounts on the basis of a

summary sheet of contractor payments prepared by the District office.

3. Staffing

M

PMO is generally appropriately staffed.

The PMO staff have gained experience with IFAD FM rules and procedures. Staff mainly composed of deputed LGED officials with many years‘ experience. Under utilization of staff is an issue at the PMO. The ORA has stated that while overall capacity of the

accounting staff in the organization is weak, at the District/Upazilla levels where a significant amount of the activities are conducted, the capacity of the accounting staff is the lowest.

Mitigation actions would include increased staff training on FM, recruitment of qualified staff at District levels. Ensure that duties of financial staff are detailed and assigned when implementation begins. To assist the accounting staff at the PMO level, a

chartered accountant/firm will be hired on a

Page 317: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

12

Risk Risk

Assessment*

Proposed Mitigation

Inherent Risks

retainer basis to ensure that staff are capacitated to be able to fulfil their functions within the structure. The accounting assistants, at the PMO level, have been increased to 2 from 1.

4a. LPA - Accounting Policies and Procedures

M

LPA primarily involved in project implementation process by making local payments and in claiming reimbursement –

Single entry cash basis which does not follow international standards. Mitigation action would be by pre agreement by IFAD of the process and approval procedure. LPA also responsible for ensuring that assets are

entered into its Asset Register as they are

created – Mitigation action would be requiring internal and external auditor to verify periodically

4b. PMU - Accounting Policies and Procedures

M

PMO staff is experienced in single entry accounting which is manually maintained. All records from the Upazilla and District levels are submitted to the PMO, which then

manually re-enters the information into the excel based system. Accounting staff, with prior experience on donor funded projects are experienced in financial recording and reporting for IFAD funded projects.

Mitigation actions involve intensive training of staff on double-entry accounting and IPSAS cash. Ensure accounting software is up and running at implementation, which follows IPSAS cash basis. The Accounts

Assistants at the PMO will be required to

disseminate the training to the District Level Accounts staff.

5. Internal Audit

M IA of the project conducted by LPA internal auditor. IA has experience with IFAD funded projects. However, not geared to provide

continuous routine ―internal audit check―– therefore cannot be relied on. Additionally, staff in IA are not chartered accountants, but a combination of degrees varying from bachelors to masters. Mitigation action if the IA is found to be insufficient to meet the needs of the project, an external firm

will be hired for internal audit of the project.

6. External Audit

L A division of the SAI, FAPAD, will audit the

project annual Financial Statements.

Extensive experience with donor-financed projects and satisfactory assessment by

IFAD CFS indicates that FAPAD can be relied on.

7. Reporting and Monitoring

M

LPA/PMO has satisfactory record with

previous and current IFAD projects. However single-entry accounting used. Field office information is transmitted to the HQ, which is then re-entered into the system

Page 318: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 13

13

Risk Risk

Assessment*

Proposed Mitigation

Inherent Risks

heightening the risk of error. Mitigation action would involve use of double-entry accounting and IPSAS cash basis for reporting purposes. Accounting system will be introduced. The payment, for contractors, based on a summary sheet of completed works will allow for accounting of

contractor payments at the PMO level expeditiously. This method also allows for a check and balance with the record keeping between the PMO and District levels.

8. Information Systems

H

PMO has manual recording and reporting system in place. Security of records could be improved. No computerized system

being utilized. Risk is higher in field offices.

Mitigation action is to ensure the procurement, installation and use of packaged accounting software before implementation begins.

Overall Control Risk

(before mitigation action)

M

As the PMO is created within the LPA and has significant autonomy with respect to policies/procedures followed; staffing levels; independent consultant hiring;

installation of systems, the PMO risk is assessed herein.

* H=High, M=Medium, L=Low. Use of (+) and (-) indicates higher and lower rating within

each band

Residual risk at Design is assessed as LOW if all mitigation measures are in place.

Page 319: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 320: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

Annex 14

CCRIP Project: Procurement

Page 321: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 322: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

1

Annex 14

CCRIP Project: Procurement

Introduction

01. The Government of Bangladesh, responding to concerns of the donor community or streamlining the country‘s public procumbent system, undertook an array of reforms in order to strengthen the public procurement regime. The Country Procurement Assessment Report issued by the World Bank basically paved way to the issuance of Public Procurement Regulations in 2003,

providing a unified procurement processing system. The PPR, 2003 was supplemented by Public Procurement Processing and Approval Procedures (PPPA), a revised Delegation of Financial Powers (DOFP) and several Standard Tender Documents (STDs) and Standard Request for Proposal Documents for the procurement of goods, works and services. Further later, in order to intensify the improvement measures in the public procurement system, the House of the Nation enacted the much desired law, the Public Procurement Act (PPA) 2006. Under the Act of 2006, the Public Procurement Regulations (PPR) 2008 was framed and issued, which replaced the Public

Procurement Regulations, 2003 which until then continued to have effect.

02. The public procurement systems shares the similar common principle such as value for money, fair treatment, non-discrimination, integrity, transparency and competition and social and industrial development as subscribed by the IFAD Procurement Guidelines. The Preamble to the PPA, 2006, for example, says that the objective of this law has been to provide for procedures to be followed for ensuring transparency and accountability in the procurement of goods, works and

services using public funds and for ensuring equal treatment and a free and fair competition amongst all persons wishing to participate in public procurements. While considerable flexibility is given to government departments with regard to purchases and contracting, accountability remains at the core of concerns of the Bangladeshi public procurement legal regime as the preamble to the Procurement Act.

03. An assessment of the procurement capacity of LGED, the Lead Agency for carrying out procurement under CCRIP undertaken by the ADB and IFAD as described below.

LGED PROCUREMENT CAPACITY ASSESSMENT

Part A. General Agency Resource Assessment

Response

A.1. Is there a procurement department?

Because of the nature of the job decentralized in the whole country, the procurement is being conducted by several procuring entities of LGED working in different levels as such LGED does not have a separate procurement department exclusively responsible for the procurement. However, LGED has a procurement unit in the Headquarter. The procurement unit provides policy issues and directives related to procurement to all procuring entities of the department.

A.2. What procurement does it undertake?

LGED undertakes all kinds of public procurement related to goods, works and services mainly for developing urban and rural infrastructures as well as small scale water resources projects.

A.3. Are the staff provided with written job descriptions?

Yes.

A.4. How many years experience does the head of the procurement unit have in a direct procurement role?

30 years.

A.5. How many staff in the procurement department are:

10 (ten) nos.

i. Full Time? 10 (ten) nos.

ii. Part Time? -

iii. Seconded? -

A.7. Do the staff that will be Yes, the procuring entities those who will be involved in the

Page 323: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

2

involved with the procurement have English language skills sufficient

procurement have sufficient proficiency in English. It may be mentioned here that the whole procurement document in terms of bidding document, specification, public procurement law and rules are being practiced in English. The LGED procuring entities are being continuously trained up with the procurement law, rules and bidding documents and contract management. Hence, English language will not be at all any problem for LGED procuring entities.

A.8. Is the number and qualifications of the staff sufficient to undertake the additional procurement that will be required under the proposed project?

The Ministry of Planning has been conducting 3-week long residential training course for developing the knowledge and skill of the procuring entities for major procuring departments of Bangladesh. LGED is one of those departments receiving that kind of extensive training on procurement. Most of the Procuring entities of LGED have been trained on that course. Some of the LGED officers have completed post-graduation degree on procurement from the abroad. In addition, some engineers of the department were trained on procurement under FIDIC condition. Besides, LGED has been conducting different kinds training courses on procurement for all levels of staff involved with the procurement. With national and international training and huge procurement practice in different national and foreign aided projects, the capacity of LGED officials and staff has developed sufficiently at a level to undertake additional procurement proposed under the project.

A.9. Does the unit have adequate facilities such as PCs, internet connections, photocopy facilities, printers etc. to undertake the expected procurement?

As mentioned earlier that the LGED procurement unit provides procurement directives and policy guidelines for procurement but that unit does not involve with the procurement. However, the unit is equipped with facilities of PCs, internet connections, photocopy facilities, printers etc. The procurement under the proposed project will be undertaken by the Project Management Office (PMO). The PMO will be equipped with adequate facilities such as PCs, Internet Connections, photocopy facilities, printers etc for smooth implementation of procurement.

A.10. Is there a procurement training program?

As mentioned earlier, there are various training programs on procurement arranged by the Ministry of Planning and LGED for the officials and staff responsible for procurement This kind of training programs continues round the year.

Part B. Agency Procurement Processes, Goods and Works

B.2. If the above is yes, what where the major challenges?

Some major challenges are as follows :

Procurement of consultants usually causes delay, which leads to start-up delay in civil works and goods;

Designing realistic procurement plan after considering all uncertainties.

B.3. Is there a procurement process manual for goods and works?

Yes. All public procurements are being undertaken in accordance with the Public Procurement Ruleas-2008 supported by Public Procurement Act-2006. Comprehensive procurement process for goods, works and services are described in that document. All those documents are available in the Central Procurement Technical Unit (CPTU) website: www.cptu.gov.bd

B.4. If there is a manual is it up to date and does it cover foreign assisted procurement?

Yes. The public procurement rules are amended from time to time and those amendments are notified to all procuring entities through notification in the Government Gazette. All amendments are also available in the CPTU website. Such document is used for foreign assisted procurement if that document is acceptable to the concerned donor. Otherwise, customized procurement documents are prepared with concurrence of the donor and that document is used for foreign assisted procurement.

Page 324: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

3

B.5. Is there a systematic process to identify procurement requirements (1 year or more)

Yes. Considering the available resources against prioritized requirement, all procuring entities of LGED have to submit the annual procurement plans to the head of procuring entity for approval at the dead end of the year for the following year. Procurement requirements are determined from the procurement plan. However, such plans are modified time to time depending on the availability of resources or other reasons.

B.6. Who drafts the specifications?

The Maintenance Unit and Quality Control Unit jointly publish standard general specifications of civil works with rates at the dead end of the financial year for the following year. The specifications and rates are updated in each year with the assistance of experts working in those units.

B.7. Who approves the specification?

The Head of Procuring Entity i.e. the Chief Engineer approves the specification.

B.8. Are there standard bidding documents in use and have they been approved for use on ADB funded projects?

Yes. Under the purview of the Public Procurement Rule , the standard bidding documents have been prepared by the Central Procurement Technical Unit (CPTU) for all kind of procurements. These documents are available in the CPTU website: www.cptu.gov.bd Those standard bidding documents are used for foreign aided procurements if those are acceptable to the donor. Otherwise, customized bidding documents are prepared in concurrence with the donor for the foreign aided procurement. Most of the donors including ADB accepted the bidding documents of CPTU for National Competitive Bidding (NCB).

B.9. Who drafts the bidding documents?

Central Procurement Technical Unit (CPTU) is responsible for preparation and modification of Standard Bidding Documents. The project management office is responsible for making customized bidding documents acceptable to the respective donors.

B.10. Who manages the sale of the document?

In case of works procurement, the District Executive Engineer (Procuring Entity) manages the sale of all bidding documents. The biding documents are sold at least by the following offices:

1. The Executive Engineer of the district (procuring Entity); 2. The Upazilla Engineer of the Upazilla where the site is

located; 3. Superintending Engineer of the concerned LGED region;

and 4. The Project Director, of the concerned project.

However, records of all sales are available at the office of the Procuring Entity. The Project Director becomes the procuring entity for the case of goods and services and he/she manages the sales of bidding document of those procurement. .

B.11. Are all queries from bidders replied to in writing?

Yes.

B.12. Is there a minimum period for preparation of bids and if yes how long?

Yes. The minimum period for preparation of tender for NCB procurement is 28 days since the publication of the tender in the newspaper but the same is 42 days for ICB procurement.

B.13. Does the bidding document state the date and time of opening and how close is it to the deadline for submission?

Yes. Within 3 (three) hours since opening.

B.14. Is the opening public? Yes.

B.15. Can late bids be accepted?

No.

B.16. Can bids be rejected at bid opening?

No.

B.17. Are minutes taken? Yes

Page 325: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

4

B.18. Who may have a copy of the minutes?

The bidders or their authorized representatives those who attend the opening of the tender.

B.19. Are the minutes free of charge?

Yes.

B.20. Who undertakes the evaluation (individual(s), permanent committee, ad-hoc committee)?

The evaluations are undertaken by permanent Tender Evaluation Committees formed as per the Public Procurement Rules and subsequent directives by the procurement unit.

B.21. What are the qualifications of the evaluators in respect to procurement and the goods and works under evaluation?

Minimum Graduate in Engineering

B.22. Is the decision of the evaluators final or is the evaluation subject to additional approvals?

The evaluators can only recommend to the appropriate approving authority (determined in accordance with the Government Delegation of Financial Power) for approval.

B.23. Using at least three real examples how long between the issue of the invitation for bids and contact effectiveness?

Maximum 4 (four) months.

B.24. Are there processes in place for the collection and clearance of cargo through ports of entry?

Yes.

B.25. Are there established goods receiving procedures?

Yes.

B.26. Are all goods received recorded as assets or inventory in a register or similar?

Yes.

B.27. Is the agency/procurement department familiar with letters of credit?

Yes.

B.28. Does the procurement department register and track warranty and latent defects liability periods?

Yes.

Part C. Agency Procurement Processes, Consulting Services

C.1. Has the agency undertaken foreign assisted procurement of consulting services recently (last 12 months, or last 36 months)?

Yes.

C.2. If the above is yes what where the major challenges?

Delay in getting concurrence from the development partners in various layers of procurement process such as: EOI, RFP, Technical Evaluation, Financial Evaluation, Combined Evaluation,

Page 326: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

5

Contract Negotiation, Agreement etc.

C.3. Is there a procurement process manual for consulting services procurement?

Yes.

C.4. Is the manual up to date and does it cover foreign assisted projects?

Yes.

C.5. Who identifies the need for consulting services requirements?

LGED and the development partners.

C.6. Who drafts the ToR? LGED and the development partners.

C.7. Do the ToR followed a standard format such as background, tasks, inputs, objectives and outputs?

Yes.

C.8. Who prepares the request for proposals?

The designated Project Director of LGED

C.9. Are assignments advertised and expressions of interest called for?

Yes.

C.10. Is a consultants’ selection committee formed with appropriate individuals in terms of

The Proposal Evaluation Committee (PEC) is a permanent committee formed by the Head of Procuring Entity.

C.11. What criteria is used to evaluate EOIs?

The major criteria are as follows:

Consultancy firm’s facilities and area of expertise;

Similar assignment;

Experience in similar operating environments and conditions;

Professional qualifications and adequate resources;

Managerial strength and financial capacity.

C.13. Do firms have to pay for the proposal document?

No.

C.14. Does the evaluative criteria follow a pre-determined structure and is it detailed in the RFP?

Yes.

C.15. Are pre-proposal visits and meetings arranged?

Yes.

C.16. Are minutes prepared and circulated after pre-proposal meetings?

Yes.

C.17. To who are minutes distributed?

The consulting firms or their authorized representatives those who present in the meeting and those consulting firms who received RFP documents.

C.18. Are all queries from consultants answered to in writing?

Yes.

C.19. Are the financial and technical proposals in separate envelopes?

Yes.

C.20. Are proposal securities required?

No.

C.21. Are technical proposals opened in public?

Yes.

Page 327: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

6

C.22. Do the financial proposals remain sealed until technical evaluation is completed?

Yes.

C.23. Are minutes of technical opening distributed?

Yes.

C.24. Who determines the final technical ranking and how?

The Proposal Evaluation Committee determines the final technical ranking according to predetermined evaluation criteria.

C.25. Are the technical scores published and sent to all firms?

Technical scores are disclosed/published prior to opening financial proposal.

C.26. Is the financial proposal opening public?

Yes.

C.27. Are there minutes taken and distributed of financial proposal opening?

Yes.

C.28. How is the financial evaluation completed?

Financial Evaluation is carried out in accordance with the procurement guidelines. In general, arithmetical calculations are checked and corrected. If any work was proposed in the technical proposal but not priced in the financial proposal must be loaded by the highest price of the participating firms. All taxes and provisional sum must be taken out from the financial proposal for cost comparison.

C.29. Are face to face contract negotiations held?

Yes

C.30. How long after financial evaluation is the selected firm to negotiate?

3 (three) week.

C.31. What is the usual basis for negotiation?

Methodology of Works;

Work plan:

Organization and staffing:

Deliverable;

Proposed contract price etc.

C.32. Are minutes of negotiation taken and signed?

Yes.

C.33. How long after negotiations until the contract is signed?

2 (two) months.

C.34. Are advance payments made?

Yes

C.35. Is there an evaluation system for measuring the outputs of consultants?

No. However, the LGED officials are aware of this evaluation system and capable of managing a balance between the expenditure against the consultant input compared to delivered output.

Part D. Process Oversight and Control

D.1. Is there a standard statement of ethics and are those involved in procurement required to formally commit to it?

Yes.

D.2. Are those involved with procurement required to declare any potential conflict of interest and remove

Yes.

Page 328: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

7

themselves from the procurement process?

D.3. Is the commencement of procurement dependent on external approvals (formal or de-facto) outside of the budgeting process?

Yes.

D.4. Who approves procurement transactions and do they have procurement experience and qualifications?

According to delegation of financial power of the Government, different layers of approving authority ranging from district level Executive Engineer, Project Director, HOPE, Line Ministry and Cabinet Committee approves procurement transactions within their financial power.

D.5. Which of the following actions require approval outside of the procurement unit or a permanent evaluation committee and who grants the approval?

a) Bidding document, invitation to pre-qualify or request for proposal

HOPE and Development Partner

b) Advertisement of an invitation for bids, pre-qualification or call for expressions of interest

HOPE.

c) Evaluation reports As per delegation of financial power, HOPE or Line Ministry or Cabinet Committee (CCGP) and Development Partner.

d) Notice of award HOPE and Development Partner.

e) Invitation to consultants to negotiate

HOPE and Development Partner.

f) Contracts HOPE and Development Partner.

D.6. Is contractual performance systematically monitored and reported upon?

Yes

D.7. Does the agency monitor and track its contractual payment obligations?

Yes

D.8. On average how long is it between receiving a firm’s invoice and making payment?

2(two) week.

D.9. What is the standard period for payment included in contracts?

2 (two) week.

D.10. When payment is made late are the beneficiaries paid interest?

Yes, if the claim is justified.

D.11. Are payments authorized by the same individuals empowered to approve invitation documents, evaluations and contracts?

No.

D.12. Is there a written auditable trail of procurement decisions attributable to

No.

Page 329: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

8

individuals and committees?

D.13. Are procurement decisions and disputes supported by written narratives such as minutes of evaluation, minutes of negotiation, notices of default/withheld payment?

Yes

D.14. Is there a formal non-judicial mechanism for dealing with complaints?

Yes

D.15. Is a complaints resolution mechanism described in national procurement documents?

Yes

Part E. Records Keeping

E.1. Is there a referencing system for procurement files?

Yes

E.2. Are original contracts secured in a fire and theft proof location?

Yes

E.3. Are copies of bids or proposals retained with the evaluation?

Yes

E.4. Are copies of the original advertisements retained with the pre-contract papers?

Yes

E.5. Is there a single contract file with a copy of the contract and all subsequent contractual correspondence?

Yes

E.6. Are copies of invoices included with contract papers?

Invoices are not included in the contract but are kept in separate files containing the copy of the contract and related correspondences.

E.7. For what period are records kept?

5 (five) years.

Arrangements for Procurement under the Project

04. Procurement of goods, works and services financed from resources provided or

administered by IFAD will be undertaken in accordance with IFAD‘s Procurement Guidelines and Handbook (dated September 2010, or as amended from time to time). In all cases whereby procurement is packaged along with goods, works and services financed by ADB, the procurement would be undertaken in conformity with ADB‘s Procurement Guidelines (2010, as amended from time to time) and ADB‘s Guidelines on the Use of Consultants (2010, as amended from time to time).

05. International Competitive Bidding (ICB) shall be undertaken in accordance with the

rules and regulation for ICB as established by the World Bank in line with the provisions of the IFAD Procurement Guidelines. Goods and Civil works and goods procured using NCB will follow the Public Procurement Act, 2006 and Public Procurement Rules, 2008 of the Government of Bangladesh. All procurement to be financed by IFAD proceeds require the details of the procurement, types of procurement methods, the need for pre or post-qualification, estimated cost, prior or post review requirements to be respectively included in the Procurement Plan to be submitted by the Implementing Agencies. IFAD‘s approval of the procurement plan is mandatory

and any changes or modifications must be communicated and approved by IFAD.

06. National Competitive Bidding. The procedures to be followed for national competitive bidding shall be those set forth for the National Open Tendering Method in the Government‘s Public

Page 330: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

9

Procurement Rules, 2008 (as updated and issued pursuant to the Bangladesh Public Procurement

Act, 2006) with the clarifications and modifications described in the following paragraphs required for compliance with the provisions of the Procurement Guidelines.

Anti-Corruption. Definitions of corrupt, fraudulent, collusive and coercive practices shall reflect the latest IFAD Board-approved Anti-Corruption Policy definitions of these terms and related additional provisions (such as conflict of interest, etc.).

IFAD shall jointly apply and extend debarment and sanctions

Location of Bid Submission. Submission of bids to ‗primary‘ and ‗secondary‘ locations, or ‗multiple droppings‘ of bids, shall not be required or allowed. Advertisements and bidding documents shall specify only one location for delivery of bids.

Rejection of All Bids and Rebidding. Bids shall not be rejected and new bids solicited without IFAD‘s prior concurrence.

Member Country Restrictions. No restriction applicable to IFAD resources, unless procurement is packaged along with goods, works and services financed by ADB, in which case the procurement would be undertaken in conformity with ADB‘s Procurement Guidelines and ADB‘s Guidelines on the Use of Consultants

Lottery. A lottery system shall not be used to determine a successful bidder, including for the purpose of resolving deadlocks.

Qualification Requirements. A successful bidder must be determined by an assessment process that shall include the application of qualification requirements to all bids.

07. All procurement for goods, works and services financed from resources funded or administered by IFAD require bidding documents and the contracts to include a provision

requiring suppliers, contractors and consultants to permit IFAD to inspect their accounts ,records and other documents relating to the bid submission and contract performance, and to have them audited by IFAD-appointed auditors.

08. All advance contracting and retroactive financing of resources provided or administered by IFAD regarded as an exception by the IFAD General Conditions must be clearly established (detailed cost and procurement packages) in the Project Design Document and approved by the IFAD and will be undertaken in conformity with provision of IFAD General Conditions and IFAD Procurement Guidelines and Procurement Handbook (2010, as amended from time to time). The issuance of invitations to bid under advance contracting and retroactive financing will be subject to IFAD prior review and no objection. The approval of advance contracting and retroactive

financing does not commit IFAD to finance the Project.

09. Procurement of civil works should be undertaken in sizable bid packages ensuring road works are not split to accommodate contractors financial capacities to qualify for the bidding or to intentionally avoid seeking IFAD prior review. Any civil works which are to be split into small bid packages due to specific implementation consideration must to clearly established and highlighted in the procurement plan.

10. Civil works undertaken by the Labour Contracting Societies (LCS) which would be formed

through a defined selection criteria, contracted directly by the CCRIP Project. The selection criteria and the operational and implementation arrangement for the LCS would be defined in the Project Administration Manual. While the LCS has been accessed as incapable of handling implementation, administration, financial management and procurement of the activities, the Project Administrative Manual (PAM) shall define the roles and responsibilities of the intermediaries who will assist the LCS in preforming the activities.

11. The contract detailed to be signed with the LCS, should ensure transfer liabilities and accountabilities to the intermediaries rather than maintaining these liabilities and accountability with the LCS. LGED should also explore options to use lump sum contract for LCS activities which can minimise the use of schedule rates. Lump sum contract for LCS activities would increase

Page 331: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

10

efficiency gains and minimising transaction cost currently attributed to lengthy procedural

requirement for preparing the running bills.

12. Independent Quality Monitoring and Assessment would be introduced to minimise risk and ascertain periodic information on the progress of the schemes.

13. Procurement of materials and goods by the LCS for the civil works contracted would be undertaken in accordance with the provision of the IFAD Procurement Guidelines and shall be largely limited within the markets in each district. Any requirement for the Project to purchase

specific goods from markets in outside of the district shall be justified and documented by the Project. This justification should provide details of materials and goods to be purchased and reasons for the purchase which included a comparative analysis of the cost of procuring the materials in markets outside the district where these activities are implemented.

14. IFAD shall introduce as part of fiduciary processes through its supervision mission or as separate mission, biennial reviews of the LCS contract performance with regards to the

implementation of activities contracted which includes the accounting and procurement of goods and materials carried out by the LCS (with the assistance of the intermediaries). This review shall include the performance of the intermediaries .

15. IFAD will undertake to review the provisions for the procurement of good, works and services to ensure that the procurement process is carried out in conformity with its Procurement Guidelines. For the purposes of IFAD‘s Procurement Guidelines, the following procurement decisions shall be subject to prior review by the Fund for the award of any contract for goods,

equipment, materials, works, consultancy and services under CCRIP.

a. Procurement of goods, materials and works

i. Prequalification documents and shortlist when prequalification is undertaken;

ii. Bid Documents for goods, materials and works;

iii. Evaluation Report and Recommendation for Award; and

iv. Contract and amendments.

b. Procurement of consultancy services and services

i. Prequalification documents and shortlist when prequalification is

undertaken;

ii. Request for Proposal;

iii. Technical evaluation report;

iv. Combined (technical and financial) evaluation report and the

recommendation for award; and

v. Contract and amendments.

16. Project Procurement Thresholds. International Competitive Bidding (ICB) shall be the mandatory procurement method for activities estimated to cost: (i).Goods estimated to cost above USD 200,000 or equivalent; (ii). Civil works estimated to cost above USD 1,000,000.00 or equivalent; and (iii). Services estimated to cost above USD 100,000 or equivalent.

17. Prior or Post Review. Except as IFAD may otherwise agree, the prior or post which

applies to various procurement of good, works and consultant recruitments shall be defined as follows:

Procurement Method Prior or Post Comments

Procurement of Goods and Works

ICB Works Prior ICB Goods Prior NCB Works

Prior Except procurement valued

below USD 150,000 NCB Goods

Prior Except procurement valued

below USD 100,000 Shopping for works (quotations) Post Shopping for goods (quotations) Post Direct Works

Post Except first contract in each

district

Page 332: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

11

Direct Goods Prior

Except procurement valued below USD 5,000

Recruitment of Consulting Firms

Quality- and Cost-Based Selection (QCBS) Prior

Except procurement valued below USD 100,000

Fixed Budged Selection (FBS) Prior

Except procurement valued below USD 100,000

Least Cost Selection (LCS) Prior

Except procurement valued below USD 100,000

Selection Based of Consultants Qualification Prior

Except procurement valued below USD 60,000

Sole Source Selection (SSS) Prior

Except procurement valued below USD 30,000

Recruitment of Individual Consultants

Individual Consultants Prior

Except procurement valued below USD 30,000

III. GOVERNANCE AND ANTI-CORRUPTION (GAC)

18. Anticorruption measures will include (a) undertake necessary measures to create and sustain a corruption-free environment for activities under the Project; (b) institute, maintain and ensure compliance with internal procedures and controls for activities under the Project, following

international best practice standards for the purpose of preventing corruption, money laundering activities, and the financing of terrorists, and shall require all relevant ministries and agencies to refrain from engaging in any such activities; (c) comply with requirements of IFAD‘s Policy on Preventing Fraud and Corruption in Its Activities and Operations (2005, as amended to date); (d) ensure that the Good Governance Framework is implemented in a timely manner. is actively engaged to allow potential Project beneficiaries and other stakeholders to channel and address any complaints they may have on the implementation of the Project;

Page 333: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 14

12

Appendix 1

Eighteen Month Procurement Plan

(a draft procurement plan will be included in the PAM)

Page 334: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 15

Annex 15

Beneficiary Calculation

Page 335: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 336: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 15

1

Annex 15

Beneficiary Calculation

A. Direct beneficiaries

1. Number of LCS members (IFAD)

Number of LCS

per km / market

/ CCP

Number of LCS

for the project

Number of

Number of

LCS

members

for the

unit amount

Upgraded rural roads road construction km 4 1 4 100

road maintenance km 0 1 0 0

Upgraded rural markets Type 3: small market construction no. 160 1 160 4 000

Type2: large market construction no. 32 1 32 800

Type1: assembly market no. 4 0 0 0

collection points no. 5 1 5 125

Total 5 025

2. a. Market traders (IFAD) Type 2: Large markets 33

traders/ large market

permanent shops 100

temp traders 500

total per market 600

total for project 19 800

Type 3: Small markets 160

traders/ small market

permanent shops 50

temp traders 150

total per market 200

total for project 32 000

Type 1: Assembly markets 4

permanent shops 200

temp traders 1 000

total per market 1 200

total for project 4 800

Collection points 5

producers per point 40

total for project 200

Total participants 56 800

2. b. Markets traders (ADB)

Growth center market 18

Village market 70

Type 1 88

permanent shops 200

temp traders 1 000

total per market 1 200

total for project 105 600

Volume of work

Page 337: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 15

2

3. a. Transport owners (IFAD)

Assumptions were taken from the Impact assessment on improved market connecting roads and ghats conducted for MIDPCR

in the project area

The transport owners benefiting from union and village roads will be mainly of two types: (i) motorized vehicles (CNG/Tempo/Motor cycle) and

(ii) non-motorized vehicles (rikshaw/ rikshaw vans)

The survey has been carried out on different sections (average 5km) of 40 different roads situated within the project area

It has been assumed that there are :

2 hat days

5 non-hat days

Total km of road 495

49.5

One transport owner = one hhd

WOP WPPercentage

changeWOP WP

Motorized

hat day 121 292 5 990 14 454

non-hat day 93 197 4 604 9 752

average trafic 101 224 111% 5 000 11 095

number of vehicles 442 673

Non-motorized

hat day 310 464 15 345 22 968

non-hat day 250 369 12 375 18 266

average trafic 267 396 74% 13 224 19 609

number of vehicles 3 182 3 456

Total 4 129

3. b. Transport owners (ADB)

Assumptions were taken from the Impact assessment on improved market connecting roads and ghats conducted for MIDPCR

in the project area

The transport owners benefiting from union and village roads will be mainly of two types: (i) motorized vehicles (CNG/Tempo/Motor cycle) and

(ii) non-motorized vehicles (rikshaw/ rikshaw vans)

The survey has been carried out on different sections (average 5km) of 40 different roads situated within the project area

It has been assumed that there are :

2 hat days

5 non-hat days

Total km of road 130

13

One transport owner = one hhd

WOP WPPercentage

changeWOP WP

Motorized vehicles

Annual average daily traffic 433 846 98% 56 290 109 980

Number of vehicles 7 458 3 437

Non-motorized vehicles

Annual average daily traffic 2220 3328 75% 288 600 432 640

Number of vehicles 104 167 45 067

Total 48 504

The evaluation of RIIP does not include pedestrian traffic. For rhe purpose of the present analysis, a 30% increase in pedestrian traffic is assumed.

Source:

Local Government Engineering Department. August 2009. Rural Infrastructure Improvement Project (RIIP) Rural Development Project – 25.

Results of Terminal Surveys on Benefit Monitoring and Evaluation. Table 10.2.

4. a. Communities in the areas of influence of subprojects / beneficiaries (IFAD)

Market catchment area Number of markets Total hhds

Type2:Large 7 1 400 32 44 800

Type3: Small 4 800 160 128 000

Type 1: Special 10 2 000 4 8 000

Total hhds 180 800

Assumption: 60% of the hhds will be farm holding hhds, that will be able to benefit from the increased agriculture production income

Total beneficiaries hhds within market catchment area 108 480

2) Road catchment area

Beneficiaries (hhds) per 500km 16 667 1hhd=6 people

Total market and road catchment area 125 147

4. a. Communities in the areas of influence of subprojects / beneficiaries (ADB)

Market catchment area Number of markets Total hhds

Type 1: Special 10 2 000 88 176 000 *All ADB will be type 1

Total hhds 176 000

Assumption: 60% of the hhds will be farm holding hhds, that will be able to benefit from the increased agriculture production income

Total beneficiaries hhds within market catchment area 105 600

2) Road catchment area 1hhd=6 people

Beneficiaries (hhds) per 130km 4 333

Total market and road catchment area 109 933

Total direct beneficiaries IFAD 191 100

Total direct beneficiaries ADB 264 037

B. Indirect beneficiaries

h'holds people

Population of the 125 unions

583 333 3500000

Per project area (500km)Per sample survey

section(10km)

Total transport owners benefiting

from union and village roads

Per sample survey section(1km) Per project area (130km)Total transport owners benefiting

from union and village roads

Page 338: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

Annex 16

Financial and Economic Analysis

Page 339: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 340: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

1

Annex 16

Financial and Economic Analysis

INTRODUCTION

1. This Annex presents the financial and economic analysis. The financial analysis aims at demonstrating that income-generating activities on farm (related to the main commodities supported by the project) and off-farm (mainly trade), as proposed in the Coastal Climate Resilient Infrastructure Project (mentioned hereafter as CCRIP), are profitable and therefore sustainable. While the economic analysis aims at demonstrating that, from an economic

perspective, the project as a whole is viable, taking into account, as much as possible, all quantifiable and additional costs and benefits in with and without project situations.

2. The main focus of the project is to provide climate resilient communication and market infrastructure which is critical for rural economic growth, market and value chain development

in the coastal districts. Furthermore, the project is expected to enhance the climate change adaptation capacity of the villages within the project area.

3. The main project physical outputs are: (a) transport infrastructure including upazilla, union and

village roads and bridges; and (b) market infrastructure including growth center markets, rural markets, collection points and boat landing stages within the market area; (c) cyclone shelters.

4. This working paper is structured as follows: (i) data sources and general assumptions; (ii)

summary of the project benefits; (iii) financial analysis; (iv) economic analysis; and

(v) sensitivity analysis.

I. DATA SOURCES AND GENERAL ASSUMPTIONS

5. Sources. The data used in this analysis have been collected from various sources, including the Local Government Engineering Department (LGED), the Market Infrastructure Development Project in Chartland Regions (MIDPCR), donor agencies operating in Bangladesh, local

agricultural practitioners as well as IFAD and ADB missions‘ estimates. Additional data were

collected through interviews with farmers and traders during field visits. In particular, information was collected on labor and input requirements for various operations, capital costs, prevailing wages, yields, farm gate and market prices of agriculture produce and farm-to-market transport costs.

6. Given the merging of the Sustainable Market Infrastructure for Livelihoods Enhancement (SMILE) Project with the Climate Resilient Infrastructure Improvement in Coastal Zone Project

(CRIICZP) co-financed by ADB, the initial analysis carried out for the SMILE has been updated to include additional activities funded by ADB. The analysis of the ADB-funded activities has been done by the ADB team and included in the Bank‘s project documents submitted to the Board. The CCRIP analysis aims to consolidate the analyses of both IFAD- and ADB-funded activities.

7. On the subject of Bangladesh national currency (Bangladesh Taka [BDT]), it should be noted

that official currency exchanges into foreign currencies are free. Therefore, the official

exchange rate of BDT 82 = USD 1 (average actual rate for May 2012) has been used throughout the present analysis.

8. Prices. Input and output prices have been collected during the field visits in the project area in May 2012 and expressed in constant terms over the project period. Economic prices have

been calculated on an import parity basis for rice and for some of the fertilizers (TSP, MOP and Urea). International price estimations have been based on the World Bank‘s Global Commodity Price Projections. Non-traded goods were converted into their approximate economic values using a Standard Conversion Factor (SCF) of 0.93 as trade controls (tariffs and non-tariff barriers) distort relative prices1.

1 Asian Development Bank project (PSSWRP) designed in 2009 used an SCF of 0.91 and a SWR of 0.9.

Page 341: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

2

9. The estimation of the investment costs for the road and market infrastructure has been carried

out according to three possible scenarios: (A) upgrading from present conditions to existing LGED standards; (B) upgrading from present conditions to existing climate-resilient standards; and (C) upgrading from present conditions to future climate-resilient standards, over a 20-year horizon. The analysis of markets and upazilla roads is based on upgrading to future climate-resilience standards only (scenario ―C‖), as there will be no other standard applied. Union roads will be built according to scenario B and C; for the purpose of the present analysis, a weighted

average was calculated for the unit costs of the union roads. 10. Cost of Labour. The standard salary for agricultural unskilled labour in the project areas is

about BDT 250 per day. Given the lack of precise information on rural employment in the project area and consequently on the real opportunity cost of agricultural labour, a Shadow Wage Rate Factor (SWRF) of 0.75 has been used in the economic analysis to reflect the high

demographic pressure and low opportunity costs of unskilled labour in the project area. Labour is assumed to be provided partly by the family and partly as hired temporary or seasonal labour.

11. The list of prices used in the analysis could be found in the Table 1 of the Appendix to this Working Paper.

II. PROJECT BENEFITS

12. Quantified Benefits. The project is expected to generate substantial net incremental benefits to farmers and rural entrepreneurs (shop keepers, traders, transport owners). The benefit stream comprises the following elements:

13. Market infrastructure development benefits. Improved and expanded market infrastructure (Growth Market Centers, village markets sheds, drainage systems, sanitary latrines, garbage pits, etc.) will have two categories of direct beneficiaries: (i) permanent

traders (shop-keepers); and (ii) temporary traders of daily morning/afternoon markets and more, importantly of haat days (twice a week). Impact assessment of the MIDPCR project, as well as the field visits and interviews conducted by the ADB and IFAD missions, demonstrate that the incremental benefits for market infrastructure investments will come from: (i)

reduction in spoilage of perishable products; (ii) increased sales, through higher volume and value of the agricultural production traded; and (iii) increased number of traders at the village

markets. 14. Upazila, village and union roads construction: The project will be building mainly three

types of roads: (i) upazilla roads; (ii) village roads and (iii) union roads. The benefits from these rural roads are mainly derived from the generated commercial activities. The estimation of the benefits is made on the basis of the earnings expected from these new activities. Incremental benefits from these investments will be: (i) from upazilla roads - vehicle operating cost savings from the existing traffic using the roads as well as from the new traffic generated;

(ii) from village roads - increased volume of transported goods (mainly agricultural production) and reduced transportation costs; and (iii) from union roads - increased traffic, reduced transportation costs for goods and passengers (due to the vehicle operating cost savings).

15. Agriculture production benefits: Farmers living within the market catchment area and the

road catchment area will be able to increase the volume of the agricultural production sold due

to the increased traffic and will be able to fetch higher selling prices due to larger numbers of

buyers coming to the market and hence higher demand for the agricultural production. In addition, farmers will also benefit from the reduced transportation costs and better access to markets and inputs contributing to higher productivity at the household level.

16. Benefits to the transport owners: Construction of the village and union roads will have an

impact on the small private entrepreneurs/vehicle owners. The vehicles operating on this type

of rural roads will be of two types: (i) motorized vehicles (mainly CNG/Tempo/Motor cycle) and (ii) non-motorized vehicles (such as rickshaw/ rickshaw van). The results of the MIDPCR impact assessment study demonstrate that, even if the average fare per km decreases with the project, it is more than compensated by the volume of traffic generated by a new road (and the number of additional journeys per vehicle) as well as by the travel time and the vehicle operating costs savings. The motorised vehicles will also benefit from the increased fuel efficiency while for the non-motorised vehicles the improved smooth surface of the road will

reduce the pain and the difficulty of the driver to pedal the rickshaw.

Page 342: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

3

17. Income Generating Activities undertaken by the LCS members: Some of the Local

Contracting Societies‘ members will be willing to invest a portion of wage and profit received after the completion of the construction works (about 10% of the construction cost) in sustainable income generating activities. A recent report on impact market assessment of the MIDPCR project (September 2011) demonstrates that almost 89% of the households participating in the LCS had invested some of their income in different IGA activities.

18. Non-quantified Benefits. In addition to the quantifiable benefits, the project interventions will yield some benefits related to the project activities that are much more difficult to quantify in monetary terms; thus they were not included in the economic analysis. However, they certainly amount to substantial socio-economic values. Among the non-quantified benefits are the following:

Improved communication, better access to a wide range of social services including both educational and health facilities through improvement of the road network;

Improved hygiene standards in the markets. During the interviews with the MIDPCR traders, many of them recalled the problems of the old market, when they had to move

around in knee-deep mud in the monsoon and in dust in the dry season. The market improvements in terms of better water supply, toilet facilities, general cleanliness and security make the market more attractive to customers and vendors;

Human lives saved with the cyclone shelters. Assessing the economic benefit of a cyclone shelter is fraught with difficulty, as it is difficult to predict how many people and the type and number of livestock that will actually use a shelter in any given circumstance and perceived risk. Furthermore, it is extremely difficult to attach a monetary value to a human life, compared with that of financial damage to or loss of assets.

Capacity building of Market Management Committees and Banik Samities (Shopkeepers

associations) and their higher involvement in market maintenance and functioning. Increased possibilities of income generation for women and positive impact on women‘s

empowerment through LCS activities and development of women‘s market sections in the markets and increased women‘s trade.

III. FINANCIAL ANALYSIS

19. Rice, vegetables, livestock and fish production constitute the livelihood basis for most of the

smallholder households. A number of indicative economic activities, which will benefit from CCRIP, were identified during the project design process. In total eight illustrative models (six crop models, one livestock model/dairy and one fishery model) were prepared to illustrate the impact of the potential investments on agricultural production within markets and roads catchments areas.

Agricultural Models

20. Crop models. Agricultural products considered in the analysis are the most popular for the

project area. For the purpose of the analysis several models have been prepared, including: paddy/rice, tomatoes as a proxy for winter vegetables, and lady‘s fingers as a proxy for summer vegetables. Paddy is the main staple crop grown in the project area. The production is sold by farmers mainly as paddy, soon after the harvest time. Generally, about 60% of the household paddy production is sold at the local markets, the rest is home consumed. In the

analysis two main paddy varieties were considered: amon (rainfed) and boro (irrigated). Vegetables are grown for local sales (about 70%) and household consumption. For both paddy

and vegetables, the activity models illustrate the impact of improved roads and markets in terms of reduced transportation costs and higher selling price due to larger number of buyers coming to the market and hence higher demand for the agricultural production. It can be also expected that due to better roads farmers will benefit from better access to inputs. However, given the CCRIP will be focused on the infrastructure while the following MAPP project will implement value chain development activities in the same project area, at this stage it has

been conservatively assumed that the benefits from increased agricultural production would be expected but will not be quantified. Incremental increases are expected to range from BDT 936 for aman (local variety) to BDT 1,859 for boro high yield variety. The models are presented in Table 2 of the Appendix.

21. Livestock and fish pond models. Livestock are traditionally an important part of the integrated farming system in Bangladesh. The ownership pattern of livestock indicates that about 87 percent of the rural households, which belong to landless, marginal or smallholder

Page 343: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

4

groups rear livestock and poultry. The most critical problem for livestock rearing is the lack of

preventive and curative health care services. Only about 5 percent of the animals are de-wormed and about 10 percent may have preventive vaccination, whereas if only de-worming is done 70-80 percent of animal health problem can be prevented. The model (one dairy cow with one calf) illustrates that better access to veterinary services and better husbandry due to the improved roads leads to increase in milk production and income. The incremental revenue is BDT 925 and the return to labour (with project) is BDT 139. The model is presented in Table 3

of the Appendix. 22. For both livestock and fisheries, the dominant factor determining a household‘s income is its

access to market. How quickly and frequently a household can take its products to market determines the size of its income from livestock and fisheries. If livestock products and fish are not easily marketed, households have little incentive to increase their output, since production

is only for home consumption. 23. Small-scale fish farming is an important opportunity to generate income and is a significant

nutritional source providing protein-rich food all year. The model illustrates the approach

commonly implemented on a small scale that is local fish pond farming. The main types of cultivated fish are carp, tilapia and catfish. The model illustrates carp production. In the warm climate of Bangladesh growth is rapid and the fish attain marketable size within 4 month,

providing farmers with a rapid return on their investment and labor. The model is presented in Table 4 of the Appendix.

24. Table 5 presented in the Appendix shows the summary results of the crop models and the

comparison of income in the without and with project scenario for the selected agricultural products.

IV. ECONOMIC ANALYSIS

25. Benefit Stream. The analysis attempts to identify quantifiable benefits related to the activities undertaken following the implementation of the components of the project. The incremental quantifiable benefit stream comprises following elements: (i) benefits from upazilla, village and union roads improvements; (ii) benefits from GCM and village market infrastructure

development; (iii) agriculture (crop, livestock and fish) production benefits.

26. The illustrative crop, livestock and fishery models prepared for the purpose of the financial analysis, and described above, have been used for the calculation of the overall benefit stream, using economic values. In addition, three separate models have been developed to illustrate the benefits from roads and market infrastructure development.

27. Road development. Incremental benefits were computed for upazilla, union and village roads

(601 km) following two methods: (i) increases in transported goods (agricultural production)

for the roads with low volume of traffic, such as village roads connecting the village with the next village market and (ii) vehicle operating costs savings for union and upazilla roads generating more traffic. The construction costs as well as routine and periodic maintenance costs of the union and village roads are estimated on the basis of technical information given by the concerned executive engineers.

28. Upazilla road model. The model is based on the vehicle operation cost savings method. The

analysis has been carried out by ADB assuming that the savings will accrue to both existing traffic and to traffic generated by improvements made to the road. Existing traffic is based on traffic counts undertaken on subproject roads. Generated traffic is estimated according to the results of the monitoring and evaluation carried out for the Rural Infrastructure Improvement Project (RIIP). This analysis was meant for a 5.2 km upazilla road connecting a village road to the upazilla roads network. The estimated investment costs for the upazilla roads under the

project are based on the scenario ―C‖ (see paragraph 9). The model results in an economic rate of return (ERR) of 13 percent over 20 years and is presented in Table 6 of the Appendix.

29. Village road model. The model illustrates the possible incremental benefits from the

rehabilitation of a village road of 4 km. It is assumed that the beneficiaries within the road catchment area are about 200 households per km of road. The benefits would be derived from increased volume of transported products for sale and reduced transportation costs of vehicles.

The volumes of transported products for selected beneficiaries are those reported in the crop budgets presented in earlier sections. The estimated investment cost is BDT 22.3 million (USD

Page 344: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

5

272,195). Annual costs for road O&M are assumed to be five percent of the investment costs

starting two years after the investment. The model results in an economic rate of return (ERR) of 13 percent over 20 years. The model is presented in Table 7 of the Appendix.

30. Union road model. The model is based on the vehicle operating cost savings method. The

benefits are estimated by computing the probable savings of vehicle operating cost per km for the existing and incremental traffic, which are assumed to be 20 percent in case of improved

union roads. The growth rate of traffic is assumed to be a constant increase of 5 percent per year plus the generated traffic in terms of a doubling of the traffic volume in the year following the development. The analysis was carried out for a 5 km union road connecting a small town to a hat bazar. The model results in an economic rate of return (ERR) of 13 percent over 20 years. The model is presented in Table 8 of the Appendix.

31. Growth Center Markets (GCM) development. The economic analysis of the CGM is based on the estimation of quality deterioration savings. The benefits are expected to come from spoilage reduction and from the increase of market turnover. The reduction of spoilage is estimated on the basis of prices paid for a range of perishable commodities typically traded in

the project area. The model results in an economic rate of return (ERR) of 15 percent over 20 years. The model is presented in Table 9 of the Appendix.

32. Market infrastructure development. For each selected market, the project would support infrastructure improvements chosen by the Market Management Committee. Therefore, in this analysis the most common single investments that have an economic impact were selected and their expected benefits assessed against their costs. During field visits, it was apparent that the investment most badly needed in most of the markets is a hard surface that allows a clean and dry display of the goods of the temporary traders and also a comfortable passage for the buyers. Another investment that was regularly demanded as a high priority was the

construction of covered sheds with open sides, usually without platforms. Such sheds provide shelter for a limited number of temporary traders and their goods, and are mainly useful in the rainy season to protect goods from the rain and mud. For markets that operate at or around lunch-time, the sheds also provide protection against the sun in the dry season.

33. The market benefit analysis is based on the spoilage reduction method, which assesses the

effects of market infrastructure improvements in terms of the reduction in physical waste of traded produce. This method captures the benefits realized by both the traders and the buyers, is applicable to all types of produce and measures actual economic benefits. Investment and maintenance costs (assumed to be at 4 percent) were discounted to obtain the economic costs. The data was based on recent supervision reports and impact market assessment of rural market1. The detailed calculations are presented in Table 10 of the Appendix.

34. Cost Stream. In order to estimate the project's economic viability, in the form of the Economic Internal Rate of Return (EIRR), the cash flow calculated includes the project base costs (as extracted from the COSTAB tables shown in Table 11 of the Appendix) with their physical contingencies but without taxes and price contingencies (therefore in constant BDT). The costs include all investments for all project components as well as their replacement (for transportation, office and computer equipment/materials, etc.) and recurrent costs (mainly operation and maintenance for transportation, equipment and materials).

35. Project Estimated Return. The base case Economic Internal Rate of Return (EIRR) is estimated at 16 percent over 20 years. The base case net present value of the project‘s net benefit stream, discounted at 12 percent, is BDT 2,414 million. The summary of the economic analysis is presented in Table 13 of the Appendix.

36. Sensitivity analysis. Sensitivity analysis assessed the effect of variations in benefits and

costs and for various lags in the realisation of benefits. A number of scenarios were tested to establish the economic viability of the total project in the event of adverse factors. The EIRR is relatively stable with regard to cost increases, benefit reductions and lags. Even in the case of extreme delays of the realisation of project benefits of two years or a relatively unsustainable nature of project benefits, represented by an annual 20% decrease of benefits, the EIRR

1 Market Infrastructure Development Project in Charland Regions, Impact Assessment of Rural Markets. This report, prepared by the IFAD Mid-Term Review Mission, is based on data collected and analysed, and reports prepared by the MIDPCR PMU on the improvement status of the initial batch of 18 rural markets, 2010.

Page 345: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

6

remains equal or above the assumed opportunity cost of capital of 12%. The results of the

sensitivity analysis are presented in the Table 14 of the Appendix.

Table 1: Financial and economic prices

Unit Financial Economic

Outputs

Crop Production

Paddy kg 20 27

Chili (dry) kg 100 93

Okra (Lady's Finger) kg 30 28

Aubergine (Brinjel) kg 37 34

Tomato kg 40 37

Potato kg 20 19

Wheat Bran kg 25 23

Fish kg 125 116

By-product

Husk kg 25 23

Straw kg 0.4 0.37

Output: Livestock

Cow Milk lt 40 37

Culled Cow (200tk/kg) head 30,000 27,900

Male Calf 12 months head 11,000 10,230

Female Calf 12-36 months head 11,000 10,230

Male Calf 14 months head 20,000 18,600

Female Calf 12-36 months (WP) head 20,000 18,600

Day-old chick head 65 60

Hen (up to 4 month) head 150 140

Culled Chicken kg 80 74

Eggs unit 5 4

Manure (cow dung) kg 1 0.9

Manure (compost) kg 0.4 0.37

Inputs

Seed

Seed rice - local kg 35 33

Seed rice - hyv kg 50 47

Seed - local potato kg 6 5.6

Seed - Okra kg 45 42

Seedling - tomato 80 units 50 47

Labour

Ploughing (power tiller including diesel and labour) acre 2,000 1,860

Fertilizer & pesticide application day 100 93

Transport- farm to market - carried by hand kg 1 0.9

Transport cost per passenger ( farm to market, rickshaw van) kg 3 2.98

Transport cost (goods, farm to market, rickshaw van) km/mound 20 19

Labour - rice crops day 250 188

Labour - other crops (mostly female) day 150 140

Fertilizers, Pesticdes, etc.

Fertilizer (Urea) kg 20 43

Fertilizer (MOP) kg 20 46

Fertilizer (TSP) kg 25 48

Organic matter lt 1 0.93

Pesticide (2-3 times-max 500ml/acre) kg 276 257

Insecticide kg 80 74

Fungicide kg 370 344

Bags unit 10 9.3

Investment Costs: Livestock

Cow in calf head 20,000 18,600

Oilseeds cake kg 20 19

Wheat bran kg 14 13

Husbandry Costs (Annual): Livestock

Straw kg 0.40 0.37

Oil Cake kg 25 23

Wheat Bran kg 30 28

Rice bran kg 4 3.7

Feed (chicken) kg 20 19

Salt kg 10 9

Veterinary services (cattle) CU 450 419

Vaccination (Chicken) bird 2 1

Napier grass kg 1 0.5

Page 346: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

7

Table 2: Crop models

Unitwithout project with project without project with project without project with project without project with project without project with project without project with project

Yields Main product kg 1,800 1,800 2,000 2,000 1,000 1,000 1,350 1,350 950 950 1,100 1,100

By-product ( straw) kg 3,240 3,240 3,600 3,600 1,700 1,700 2,295 2,295

Crop Seed/Seedlings (local) kg 15 15 15 15 40 40

Inputs Seed/Seedlings (improved) kg 10 10 10 10 5 5

Fertilizer (urea) kg 50 50 20 20 20 20 20 20 15 15 20 20

Fertilizer (TSP) kg 10 10 15 15 15 15 25 25 30 30 30 30

Fertilizer (MOP) kg 10 10 10 10 0 0 0 0 15 15 20 20

Gypsum kg 5 5 5 5 0 0 0 0

Organic manure (cow dung) kg 600 600 600 600

Pesticide kg 1 1 1 1

Sacks/baskets No 36 36 40 40 20 20 27 27 95 95 55 55

Machine hire cultivation times 1 1 1 1 1 1 1 1 1 1 1 1

Fertilizer/pesticides application days 1 1 1 1 1 1 1 1 1 1 1 1

Transport (rickshaw/van) kg/km 1,890 1,890 2,060 2,060 1,050 1,050 1,395 1,395 1,050 1,050 1,175 1,175

Hired agricultural labour pers/days 13 13 13 13 9 9 9 9 10 10 7 7

Family labor pers/days 18 18 18 18 15 15 15 15 24 24 25 25

Irrigation times 1 1 1 1 0 0 0 0 2 2 0 0

Input/ Main Product TK/kg 20 21 20 21 20 21 20 21 40 42 30 32

Output By-product TK/kg 0 0 0 0 0 0 0 0

Prices

Seed/Seedlings (local) TK/kg 35 35 35 35 50 50 45 45

Seed/Seedlings (improved) TK/kg 50 50 50 50

Fertilizer (urea) TK/kg 20 20 20 20 20 20 20 20 20 20 20 20

Fertilizer (TSP) TK/kg 25 25 25 25 25 25 25 25 25 25 25 25

Fertilizer (MOP) TK/kg 20 20 20 20 20 20 20 20 20 20 20 20

Organic manure (cow dung) TK/md

Pesticide TK/kg (l) 276 276 276 276 276 276 276 0

Sacks/baskets TK/each 10 10 10 10 10 10 10 10 10 10 10 10

Machine hire cultivation TK/acre 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000

Hired agricultural labour TK/day 250 250 250 250 250 250 250 250 250 250 250 250

Transport (rickshaw/van) Tk/kg 3.2 2.9 3.2 2.9 3.2 2.9 3.2 2.9 3.2 2.9 3.2 2.9

Gross Main product sold TK/acre 21,600 22,680 24,000 25,200 12,000 12,600 16,200 17,010 26,600 27,930 23,100 24,255

Main product home consumed

Output By-product TK/acre 0 0 0 0

Sub-total TK/acre 21,600 22,680 24,000 25,200 12,000 12,600 16,200 17,010 26,600 27,930 23,100 24,255

Costs Seed/Seedlings (local) TK/acre 2,000 2,000

Seed/Seedlings (improved) TK/acre 500 500 500 500 225 225

Fertilizer (urea) TK/acre 1,000 1,000 400 400 400 400 400 400 300 300 400 400

Fertilizer (TSP) TK/acre 250 250 375 375 375 375 625 625 750 750 750 750

Fertilizer (MOP) TK/acre 200 200 200 200 0 0 0 0 300 300 400 400

Organic manure (cow dung) TK/acre 0 0 0 0 0 0 0 0 0 0 0 0

Pesticide TK/acre 0 0 0 0 0 0 0 0 276 276 276 0

Sacks/baskets TK/acre 360 360 400 400 200 200 270 270 950 950 550 550

Machine hire cultivation TK/acre 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000 2,000TK/acre

Transport (rickshaw/van) TK/acre 6,048 5,443 6,592 5,933 3,360 3,024 4,464 4,018 3,360 3,024 3,760 3,384

Hired agricultural labour pers/days 3,250 3,250 3,250 3,250 2,250 2,250 2,250 2,250 2,500 2,500 1,750 1,750

Family labor pers/days

Irrigation cost TK/acre 3,000 3,000 3,000 3,000 3,000 3,000

Sub-total TK/acre 16,108 15,503 16,717 16,058 8,585 8,249 10,509 10,063 15,436 15,100 10,111 9,459

Net benefit TK/acre 5,492 7,177 7,283 9,142 3,415 4,351 5,691 6,947 11,164 12,830 12,989 14,796

Incremental net benefit

Boro (local) Boro (HYV) Aman (local)

1,6661,859 936 1,2561,685 1,807

Okra - summer vegTomato - winter vegAman (local)

Page 347: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

8

Table 3: Livestock/dairy model

FINANCIAL ANALYSIS

LIVESTOCK MODEL

Assumptions: without with

Herd of 1 adult animal unit unit cost project project

Cow age at first calving month 36 36

Subsequent calving intervals month 18 18

Calves per pregnancy no. 1.0 1.1

Calves survival rate % 80% 85%

Adult deaths and natural losses (annually) % 6% 4%

Deaths through disease outbreaks % 0% 0%

Herd composition at the beginning of the indicated year: Y1 Y1

Adult cows no. 1 1

Heifers no. - -

Calves no. 1 1

Adult bulls no. - -

Inflows (sale and/or consumption) no. amount

without with without with

project project project project

Milk sales l 40 110 132 4 400 5 280

Manure (dry) kg 1 450 450 450 450

Cow no. 30 000 0.1 0.1 3 750 3 750

Male calf (14 months old) no. 11 000 0.5 0.5 5 500 5 500

Total Inflows 14 100 14 980

OutflowsPayment for bull service no. 150 2 2 300 300

Napier grass /a kg - 4 838 4 838 - -

Rice straw /b kg - - - - -

Oilseed cake kg 20 110 110 2 200 2 200

Wheat bran kg 30 110 110 3 300 3 300

Salt kg 10 1 1 10 10

Veterinary services lumpsum 1 1 450 405

6 260 6 215

Total Outflows

Cash flow 7 840 8 765

Incremental cash flow before financing (=after financing) n/a 925

Table 4: Fish pond model

FINANCIAL ANALYSIS

FISH POND MODEL

(per 1 acre pond per year)

Assumption:

harvest is done by a fisherman-byer quantity amount

Cowdung is from the farm without with without with

WP the harvest increase by 10% unit project project project project

Use of fert. Might increase WP unit cost Y1 Y1 Y1 Y1

Inflows

Carpe (three harvests) kg 110 120 132 13,200 14 520

Total Inflows - 13 200 14 520

Outflows

Fingerlings piece 3 500 500 1 500 1 500

Supplementary feed (rice bran/ oil cake) kg 25 30 30 750 750

lumpsum - - -

Urea fertiliser kg 20 15 15 300 300

TSP fertiliser kg 25 15 15 375 375

Lime (gypsum) kg 25 25 10 625 250

Cowdung kg 300 300 - -

Family labour pers.day 11 11

Hired labour: pond preparation pers.day 250 3 3 750 750

- - -

Total Outflows 4 300 3 925

Cash flow 8 900 10 595

Page 348: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 349: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

12

Table 5: Summary of financial benefits

WOP WP \a Incremental

Boro (local) 5,492 7,177 1,685

Boro (HYV) 7,283 9,142 1,859

Aman (local) 3,415 4,351 936

Aman (local) 5,691 6,947 1,256

Tomato - winter veg 11,164 12,830 1,666

Okra - summer veg 12,989 14,796 1,807

Fish production 8,900 10,595 1,695

Livestock/dairy production 7,840 8,765 925

\aWOP - without project, WP - with project at full production

Activity modelNet Benefit

Table 6: Upazilla road model

Subproject Economic Cash Flows (BDT million)

Scenario C - Upgrade to 20-Year Climate Adaptation Standards

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Operational Days per Year 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360

Benefits

Existing traff ic 0.000 0.000 1.928 2.754 2.754 2.919 3.094 3.280 3.476 3.685 3.906 4.140 4.389 4.652 4.931 5.227 5.541 5.873 6.226 6.599

Generated traff ic 0.000 0.000 3.757 7.514 9.392 9.956 10.553 11.187 11.858 12.569 13.323 14.123 14.970 15.868 16.820 17.830 18.899 20.033 21.235 22.510

Total Benefits 0.000 0.000 5.685 10.268 12.146 12.875 13.647 14.466 15.334 16.254 17.229 18.263 19.359 20.521 21.752 23.057 24.440 25.907 27.461 29.109

Costs

Construction costs 26.208 39.312 0.000

Maintenance costs

Routine 0.000 0.000 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966

Periodic 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

Subtotal Maintenance costs 0.000 0.000 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966

Land Acquisition 6.481

Total Costs 32.689 39.312 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966

Net Cash Flow -32.689 -39.312 3.719 8.302 10.180 10.909 11.682 12.501 13.369 14.289 15.264 16.298 17.393 18.555 19.786 21.091 22.475 23.941 25.496 27.143

Economic Internal Rate of Return 14.7

Allocation of Project Overhead Costs 4.158 2.471 2.308 2.180 1.620 0.865

Net Cash Flow -36.846 -41.783 1.410 6.122 8.561 10.045 11.682 12.501 13.369 14.289 15.264 16.298 17.393 18.555 19.786 21.091 22.475 23.941 25.496 27.143

Economic Internal Rate of Return 13

Page 350: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

13

Table 7: Village road model

Description Beneficiaries Cropping

pattern (acres)

Production

(kg/acre)

Number of beneficiaries 200

Rice production 1 1000.00

Vegetables production (tomato) 1 950.00

Sub-total production 200 1950.00

Volume, tons

Economic Price,

BDT/tonne Value, BDT

Rice producers 200 26,661 5,332,132

Vegetables producers 190 37,200 7,068,000

Total 390 12,400,132

Parameters Unit WOP WP

Number of beneficiaries (1km) no 200 200

Total volume of production ton 390 390

Rice producers ton 200 200

Vegetables producers ton 190 190

Total value of production BDT 12,400,132 13,020,139

Rice producers 5,332,132 5,598,739

Vegetables producers 7,068,000 7,421,400

Total volume of sales ton 253 253

Rice producers 120 120

Vegetables producers 133 133

Average journey km 4 4

Volume of sales transported ton/km 1,012 1,012

Total value of sales transported BDT 8,146,879 8,554,223

Rice producers 3,199,279 3,359,243

Vegetables producers 4,947,600 5,194,980

Net income from sales BDT 4,358,131 5,510,446

Rice producers 1,026,347 1,409,366

Vegetables producers 3,331,784 4,101,080

Incremental net income from sales BDT

Transportation costs, rikchshaw van per km BDT/ton/km 3 3

Volume of transportation by richshaw van ton/km 1,012 1,012

Total transportation costs by richshaw van BDT/km 3,012 3,012

Total transportation costs (4km) BDT 12,047 12,047

1,152,315

ECONOMIC ANALYSIS VILLAGE ROAD (BDT)

Page 351: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

14

Village road model

PY 1 PY 2 PY 3 PY 4-20 PY 5 PY 6-20

Incremental net revenue (1 km) 230,463 460,926 691,389 921,852 1,152,315

Incremental net revenue (4 km) 921,852.10 1,843,704.19 2,765,556.29 3,687,408.38 4,609,260.48

Economic Investment costs /a

Village road, BC, BDT 22,320,000

Recurrent Costs

Operation and maintenance /b 223,200.0 223,200.0 223,200.0 223,200.0

Sub-total recurrent costs - - 223,200.0 223,200.0 223,200.0 223,200.0

Total Incremental Costs 22,320,000 223,200 446,400 446,400 446,400 446,400

Net benefit (22,320,000) 698,652 1,397,304 2,319,156 3,241,008 4,162,860

a/ Shadow Price Factor Capital 0.78

b/ 5% of the investment costs for road rehabilitation after the end of the investment period

Internal rate of return 13%

NPV (BDT ) 1,047,074

EIRR CALCULATION. VILLAGE ROAD

Page 352: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 353: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

16

Table 8: Union road model

Year Investment Cost per km

Total

Investment

Cost

Maintenanc

e Cost per

km

(Financial)

Total

Maintenance

Cost

Total

Economic

Cost

Current

Traffic

Benefits

Generated

Traffic

Benefits

Total

Benefits Cash Flow

1 10.50 52.50 - 52.50 5.74 5.74 (46.760)

2 1.05 5.25 5.25 8.61 0.29 8.90 3.647

3 1.05 5.25 5.25 9.04 0.43 9.47 4.221

4 1.05 5.25 5.25 9.49 0.45 9.94 4.692

5 1.05 5.25 5.25 9.96 0.47 10.43 5.185

6 1.05 5.25 5.25 10.46 0.50 10.96 5.708

7 1.05 5.25 5.25 10.98 0.52 11.50 6.253

8 1.05 5.25 5.25 11.53 0.55 12.08 6.829

9 1.05 5.25 5.25 12.11 0.58 12.69 7.437

10 1.05 5.25 5.25 12.72 0.61 13.33 8.076

11 1.05 5.25 5.25 13.36 0.64 14.00 8.746

12 1.05 5.25 5.25 14.03 0.67 14.70 9.448

13 1.05 5.25 5.25 14.73 0.70 15.43 10.182

14 1.05 5.25 5.25 15.47 0.74 16.21 10.957

15 1.05 5.25 5.25 16.24 0.77 17.01 11.764

16 1.05 5.25 5.25 17.05 0.81 17.86 12.612

17 1.05 5.25 5.25 17.90 0.85 18.75 13.503

18 1.05 5.25 5.25 18.80 0.90 19.70 14.445

19 1.05 5.25 5.25 19.74 0.94 20.68 15.430

20 1.05 5.25 5.25 20.73 0.99 21.72 16.467

NPV: 4.91 (BDT Million)

ERR: 13%

ECONOMIC ANALYSIS UNION ROAD (BDT Million)

Page 354: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 355: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

18

Table 9 : Growth Center Markets

Subproject Economic Cash Flows (BDT million)

Scenario C - Upgrade to 20-Year Climate Adaptation Standards

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Operational Days per Year 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360 360

Benefits

Existing traff ic 0.000 0.000 1.928 2.754 2.754 2.919 3.094 3.280 3.476 3.685 3.906 4.140 4.389 4.652 4.931 5.227 5.541 5.873 6.226 6.599

Generated traff ic 0.000 0.000 3.757 7.514 9.392 9.956 10.553 11.187 11.858 12.569 13.323 14.123 14.970 15.868 16.820 17.830 18.899 20.033 21.235 22.510

Total Benefits 0.000 0.000 5.685 10.268 12.146 12.875 13.647 14.466 15.334 16.254 17.229 18.263 19.359 20.521 21.752 23.057 24.440 25.907 27.461 29.109

Costs

Construction costs 26.208 39.312 0.000

Maintenance costs

Routine 0.000 0.000 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966

Periodic 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

Subtotal Maintenance costs 0.000 0.000 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966

Land Acquisition 6.481

Total Costs 32.689 39.312 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966 1.966

Net Cash Flow -32.689 -39.312 3.719 8.302 10.180 10.909 11.682 12.501 13.369 14.289 15.264 16.298 17.393 18.555 19.786 21.091 22.475 23.941 25.496 27.143

Economic Internal Rate of Return 14.7

Allocation of Project Overhead Costs 4.158 2.471 2.308 2.180 1.620 0.865

Net Cash Flow -36.846 -41.783 1.410 6.122 8.561 10.045 11.682 12.501 13.369 14.289 15.264 16.298 17.393 18.555 19.786 21.091 22.475 23.941 25.496 27.143

Economic Internal Rate of Return 13

Page 356: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

19

Table 10 : Village Market

Haat days Other days Haat days Other days

Permanent shops (BDT)

Margin per shop and per day 815 82 856 86

Number of shops 99 20 109 22

160,806 8,040 185,731 9,287

Margin per week

Temporary traders (BDT)

Margin per trader and per day 285 29 299 30

Number of traders 434 43 477 48

247,183 6,180 285,496 7,137

Margin per week

Annual margin per market (BDT 000,000)

Annual margin for all permanent shops

Annual margin for all temporary traders

Total

Incremental margin 3.403 (BDT 000,000) 41,500 (USD)

195,017

8.78

13.17

21.95 25.36

292,633

15.22

10.14

253,362

ECONOMIC ANALYSIS MARKET DEVELOPMENT (BDT)

With ProjectWithout Project

168,846

PY1 PY2 PY3 PY4 PY5 PY6 PY7 PY8 PY9-PY20

Investment costs per market 4,613,453

Maintenance costs 230,673 230,673 230,673 230,673 230,673 230,673 230,673 230,673

Replacement costs 2,306,726

Total costs 4,613,453 230,673 230,673 230,673 230,673 230,673 2,537,399 230,673 230,673

Benefits per market 340,300 680,600 1,361,200 2041799 2722399.23 3,402,999 3,402,999

Cash flow -4,613,453 -230,673 109,627 449,927 1,130,527 1,811,127 185,000 3,172,326 3,172,326

EIRR 24%

EIRR CALCULATION MARKET DEVELOPMENT

Page 357: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

20

Table 11 : Incremental Economic Project Costs (BDT Million)

PY1 PY2 PY3 PY4 PY5 PY6 PY7 PY8 PY9 PY10 PY11 PY12 PY13 PY14 PY15 PY16 PY17 PY18 PY19 PY20

Investment Costs

A. Improved Road Connectivity

1. Upgraded Upazila Roads 247.5 464.2 851.4 774.4 387.2 -

2. Upgraded Union and Village Roads 485.5 881.7 1,607.2 1,559.3 227.7 -

B. Improved Market Services

1. Upgraded Growth Centers and Large Markets 137.5 302.5 440.0 - - -

2. Upgraded Community Markets 133.0 197.1 197.1 138.9 - -

C. Enhanced Climate Change Adaptation Capacity

1. Enhanced Capacity and Knowledge Management 105.9 46.9 34.6 24.0 5.6 4.2

2. Upgraded Climate Disaster Shelters - 335.2 194.4 118.5 46.2 -

D. Project Management 399.3 271.6 281.5 271.6 211.3 78.6

Total Investment Costs 1,508.7 2,499.2 3,606.2 2,886.8 878.0 82.8

Recurrent Costs 20.6 26.8 56.8 106.2 119.6 206.8 206.8 206.8 206.8 206.8 206.8 206.8 206.8 206.8 206.8 206.8 206.8 206.8 206.8 206.8

Replacement costs

Field equipement 82.1 82.1

4WD (Jeep, pick up) 90.8 90.8

Motorbikes 11.6 11.6

Office equipment 13.0 13.0

Total Replacement Costs - - - - - - 106.7 90.8 - - - - - - 106.7 90.8 - - - -

TOTAL PROJECT COSTS 1,529.3 2,526.0 3,663.1 2,992.9 997.6 289.5 313.5 297.6 206.8 206.8 206.8 206.8 206.8 206.8 313.5 297.6 206.8 206.8 206.8 206.8

INCREMENTAL ECONOMIC PROJECT COSTS (BDT Million)

Table 12 : Project Incremental Net Economic Benefits (BDT Million)

PY1 PY2 PY3 PY4 PY5 PY6 PY7 PY8 PY9 PY10 PY11 PY12 PY13 PY14 PY15 PY16 PY17 PY18 PY19 PY20

Total Incremental Net Benefits

Roads 0 26 113 300 538 741 903 1,013 1,077 1,115 1,155 1,197 1,241 1,289 1,338 1,390 1,446 1,504 1,565 1,630

Markets 0 38 143 321 516 697 844 937 969 973 977 982 987 992 997 1,003 1,009 1,015 1,021 753

Agricultural production 0 0 24 127 325 512 640 640 640 640 640 640 640 640 640 640 640 640 640 640

TOTAL 0 65 279 747 1,378 1,949 2,387 2,590 2,685 2,727 2,771 2,818 2,868 2,920 2,975 3,033 3,094 3,158 3,226 3,022

PROJECT INCREMENTAL NET ECONOMIC BENEFITS (BDT Million)

Page 358: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 16

21

Table 13 : Calculation of the overall EIRR of the CCRIP (BDT Million)

PY1 PY2 PY3 PY4 PY5 PY6 PY7 PY8 PY9 PY10 PY11 PY12 PY13 PY14 PY15 PY16 PY17 PY18 PY19 PY20

Total Incremental Net Benefits 0 65 279 747 1,378 1,949 2,387 2,590 2,685 2,727 2,771 2,818 2,868 2,920 2,975 3,033 3,094 3,158 3,226 3,022

Total Incremental Costs 1,529 2,526 3,663 2,993 998 290 313 298 207 207 207 207 207 207 313 298 207 207 207 207

Cash flow -1,529 -2,461 -3,384 -2,246 381 1,660 2,073 2,293 2,478 2,520 2,565 2,612 2,661 2,713 2,661 2,735 2,887 2,952 3,020 2,816

IRR 16%

NPV 2,414

Calculation of the overall EIRR of the CCRIP (BDT Million)

Table 14 : Sensitivity analysis

EIRR

Base case 16%

Costs overrun by 20% 13%

Decrease in benefits by 20% 12%

Benefits delayed by tw o years 13%

Summary of sensitivity analysis

Page 359: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 360: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 17

Annex 17

Draft Project Administration Manual

[see combined PAM (ADB/IFAD)]

Page 361: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 362: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 17

1

Annex 17

Draft Project Administration Manual

Table of Contents

I. Introduction to Manual (PAM-II)

II. Project Objective and Components

III. Project Area and Target Population

IV. Component 1: Improved Road Connectivity

V. Component 2: Improved Market Services

V.1 Market Development V.2 Market development by LCS

V.3 Market Management Committee

VI. Component 3: Enhanced climate change adaptation capacity

VII. Innovation and Research

VIII. Project Targets and Finance

IX. Project Management

X. Financial Management and Procurement

X.1 Financial Management and Disbursement X.2 Procurement Management

APPENDICES

Appendix 1: List of selected union/village roads, community (village) markets, CCPs and ghats Appendix 2A: Annual project physical targets and financial plans

Appendix 2B: Detailed COSTAB Appendix 3A: Structural design of roads Appendix 3B: Detailed cost calculation of roads

Appendix 3C: Unit cost Appendix 4A: structural design of market elements Appendix 4B: structural design of ghat Appendix 4C: Detail cost of calculation for individual market structure and unit cost for all types of markets. Appendix 5: Various formats for management of LCS groups

Appendix 6: Sample Agreement with MMC Appendix 7: Total Project Staffing and TOR for additional staff members financed by IFAD Appendix 8: IFAD Financial Management Manual Appendix 9: IFAD Procurement Manual

Page 363: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 364: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 18

Annex 18

Contents of Project Life File

Page 365: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities
Page 366: Final Project Design Report Volume I: Main Report · 2013-03-28 · COASTAL CLIMATE RESILIENT INFRASTRUCTURE PROJECT (CCRIP) Final Project Design Report [for IFAD funded Activities

Bangladesh: Coastal Climate Resilient Infrastructure Project (CCRIP) Project Design Report – Final Design Mission

Annex 18

1

Annex 18

Contents of Project Life File

1. COSOP 2012-2018

2. Preliminary design mission Aide Memoire

3. Preliminary design document (inception mission report)

4. Design mission Aide Memoire