Kristie Berryman Phone Number: 817-408-4850 Email: kristie.berryman@granburyisd
Final Presentation - wiki.scel-hawaii.org Final Presentation Verification Subsystem December 5, 2015...
Transcript of Final Presentation - wiki.scel-hawaii.org Final Presentation Verification Subsystem December 5, 2015...
Final Presentation
Verification Subsystem
December 5, 2015May Chen and Kristie Lee
Background & Motivation
● Background○ Perform quality assurance
■ Process validation■ Documentation verification
● Motivation○ Establish an efficient & uniform methodology for testing
2
Overview
3
● Goals● Updated Block Diagram● Draft Schematic of Verification Board● Methods● Obstacles● Final Status● Remaining Problems● Future Improvements
Goals
● Overall Goal:
○ Build verification board that can verify Apple Hardware
● Semester Goal:
○ Have a design ready to be sent out for fabrication
■ Min: Hardware
■ Max: Unit test hardware
4
Block Diagram - Apple Verification Procedure
5
6
Memory Card
Programmer
Humidity
Barometer (Pressure)Power Supply
(LED)
Arduino
3.3V Voltage Regulators
Solar Irradiance
GPS XBEE
Solar Panel
Battery Charger
5V Boost Controller
5V ON/OFF Switch
ATmega328P-PUTemperature
Switch (LED)
AppleVerification Board
Power & GND Check
MCU
Current
Sensors
Block Diagram - Verification Board (VB)
EAGLE Schematic - Draft
7
EAGLE Schematic - Draft
8
Verification Board
Secondary Board
Methods● Research
○ Researched datasheets of sensors and ATmega328P ○ Analyzed schematics of different designs○ Communicated with design teams
● Documentation○ Documented compilation of information & research○ Assembled quality assurance checklist○ Documented design specifications
● Design○ Analyzed sensor modules for test specifications○ Design verification board using EAGLE CAD
9
Obstacles Encountered
● Project definition
○ Prioritization
○ Verification board specifications
● Inexperience
○ Quality Assurance
○ Hardware design
10
Final Status● Verification Board
○ Implementation of MCU ready to apply on VB○ Draft schematic of board (WIP)
● Quality Assurance Checklist○ Can be applied to general hardware tests
● Documentation○ Easy-to-read compilation of
information & research■ Apple
■ ATmega328P-PU
11
Remaining Tasks
● Verification Board:
○ Complete EAGLE schematic & board
○ Fabricate, build, & test
○ Implement firmware
12
Future Improvements● Verification Board
○ Expand to verify Cranberry/Dragonfruit
● Quality Assurance Checklist
○ Make more specific for each design
○ Include measurements & ideal values
● Documentation
○ Comprehensive “user manual” for Apple & ATmega328P-PU
○ Expand to cover Cranberry/Dragonfruit
13
Thank you!