Final HRP Floor plans 2.PDF
-
Upload
hasnyan-haider -
Category
Documents
-
view
19 -
download
1
Transcript of Final HRP Floor plans 2.PDF
--- - 10
27
1000
9740
2346
3824 16506 16368
3824 16506 4168 8240 3960
2915
2493
2225
2678
1775
1208
6
16483 3848 1913 2120 5560 2840 2060
20330 16368
12
3
4 5 6 78 9 10
11
12
13
14
15
16
17
1
4
-
---
-
---
1
4
-
---
-
---
Scale
Sheet No.
Drawn by
Date
Project number 60 Severn Street
28/02/2015
S12777192Hasnyan Haider
Specification
Title
1 : 100First Floor1
1 : 50First Floor - Callout 121 : 50
First Floor - Callout 23
1 : 50First Floor - Callout 34
1) Stairs: designed from the ground floor for access to the first floor,designed in accordance to Building regulations Approved document K. 12rises then a landing, with hand railings on either side for safety. (HMGovernment 2013) Figure 92) Internal ladder: added as a mitigation process for reducing risk. Also foraccess to the flat roof for the maintenance of the PV panels.3) Rehearsal room 1: 16 meters squared to meet client’s requirements.4) Sun pipe: interview with Sue Hayhow lead to the implication of a sun pipeto optimise natural lighting.5) Dry store: this was needed for the commercial kitchen, designed in thecommercial kitchen for easy access. Size is adequate for the kitchen.6) Mason internal room: interview with Stephen Scaysbrook found that freemasons add a small room before rehearsal rooms for the knight.(Scaysbrook 2015)7) Rehearsal room 2: this room was designed to be larger in size than theclient’s requirements because interview with Sue Hayhow recognised theissue of wasted space and using space more efficiently.8) Commercial kitchen: rule of thumb was applied in designing commercialkitchen, 2.5 square feet per chair/person. All equipment added, with ductsystems for ventilation. (Poss Sector 2008) Figure 109) Female toilets: predominantly less women in the facility due to the factwomen cannot join the free masons. Only one cubicle is necessary, also onemirror and sink unit. Female toilets include grey water reuse system, sinkunit connected to toilet for better sustainability.10) External windows: added to improve and optimize natural lighting in thefacility. UPVC double glazed windows for a better thermal efficiency and lifeexpectance then previous single glaze sash windows. Technical issue withdepth of wall causing issue with window specification (HM Government 2010)Figure 1111) Turning circle: hallways meet requirements for wheel chairs two turnaround, minimum 1500mm diameter, designed turning circle for floor plan2000 millimetre diameter. Added to meet requirements of the DDA 1995.(HM Government 2010) Figure 112) Cold store: was added for the commercial kitchen’s need. Both coldand dry store was needed for storage of products.13) Storage room: a storage room was added for the convenience of theusers of the facility, as the survey was undergoing I noticed there was aneed for space for storage.14) Office room: as the previous design of the building included offices, anew designed office was added. Interview with Sue Hayhow found that thiswas a convenient design aspect for the facility. (Sue Hayhow 2015)15) Timber suspended floor: feasibility study was conducted and due tothere being a timber suspended floor in place on the previous design alreadythe option to add and extend a new one was more feasible. Added insulationimproved the overall thermal efficiency of the building along with fire andsound layers. Figure 1216) Ventilation in walls: ventilation was added to the internal walls inaccordance to approved document F. (HM Government 2014) Figure 1317) Rain water harvesting tank: sustainable feature added to design, mosteffective sustainable feature to add to building due to location, PV panels didnot have the correct sun path to be used efficiently.
2
A1@ 1:100
First Floor Plans