Final Evaluation of the Heart of Exmoor Scheme€¦ · Rural Focus (UK) Ltd. Registered in England...

70
Final Evaluation of the Heart of Exmoor Scheme Exmoor Moorland Landscape Partnership Scheme 2011-2015

Transcript of Final Evaluation of the Heart of Exmoor Scheme€¦ · Rural Focus (UK) Ltd. Registered in England...

  • FinalEvaluationoftheHeartofExmoorScheme

    ExmoorMoorlandLandscapePartnershipScheme2011-2015

  • i

    Contents

    Foreword ii

    ExecutiveSummary iii

    1. Introduction 1Purposeofthisreport 1LandscapePartnershipSchemes 1Themethodologyfollowed 2

    2. Background 6OriginandaimsoftheScheme 6Timelineandkeystages 10Administrationandstaffing 11Costsandfunding 11In-kindsupportbypartnersandvolunteers 12DistinctivefeaturesoftheScheme 13

    3. ProjectsandOutputs 14Programme1:ReconnectingPeople 14Programme2:ReconnectingLivelihoods 20Programme3:ReconditioningMoorlandCharacter 24WhatwasnotcoveredbytheScheme 28OverallfindingsontheScheme’soutputs 29

    4. Outcomesandimpacts 30Conservingorrestoringthebuiltheritageandnaturalfeatures 32Conservingandcelebratingculturalassociationsandactivities 36Encouragingaccess,learningandinvolvement 39Improvingunderstandingofcraftsandotherskillsthroughtraining 44OverallfindingsontheScheme’soutcomesandimpacts 46

    5. UnderstandingwhathasmadetheSchemesuccessful 47Schemedesign 47Projectmonitoring 48Governanceandleadership 48Partnershipworking 49AdministrationandtheroleoftheNPA 50Schemestaff 52Resourcingandfinancialmanagement 53Timescales 55

    6. ThefuturelegacyoftheScheme 56Continuationofactivityfromprojects 56NextstepsforExmoor’smoorlandheritage 59

    7. Overallconclusionsandlessonsforthefuture 60AchievementsoftheHeartofExmoorScheme 60Lessonslearnt 62Lookingtothefuture 64

    Photographs on the cover are as follows (clockwise from top left): JohnWibberley presenting ExmoorHorn breed prizes at Dunster Show © Jason P Ball; Accessible walk with off-road Trampers (mobilityscooters)©National Trust;Wartimeheritageon showatNorthHillBigAdventure©SteveGuscott; StDubricius School visit an archaeological dig © Jason P Ball; Education at an Exmoor Mires Projectrestorationsite©SteveGuscott;andExmoorPony©JasonPBall.

    ReportpreparedbyRobertDeaneandLouiseTricklebank,February2016

    RuralFocus(UK)Ltd.RegisteredinEnglandandWales(No.9533053).Shuffshayes,Langford,Cullompton,DevonEX151RQwww.rural-focus.co.uk

    Versioncontrol:Finalreportsubmitted100316

  • ii

    ForewordAsaTrusteeoftheExmoorSocietyIchairedtheExmoorMoorlandLandscapePartnership(HeartofExmoor)forfiveyears,whichhasnowcometoanend.ThisHeartofExmoorSchemewasoriginallyinformedandinspiredbytheExmoorSociety'sresearchdocumentcalled'MoorlandsataCrossroads'whichcameoutin2004.ItthentooksixyearsfortheSchemetocometofruition.ThesuccessfulfiveyearsoftheSchemeareduetotheenormousgenerosityandcommitmentoftheHeritageLotteryFundandweareverygratefultothem.Noneofthiswouldhavebeenpossiblewithoutthem.Theywereencouragingthroughouttheprocessandaboveall,understandingandflexible.IwouldliketoexpressmygratitudetoallmembersoftheLandscapePartnershipwhocontributedmatchedfunding,bothin-kindandwithfunds.Hugethankstootothethousandsofdedicatedvolunteerswhohelpedwithsomanyoftheprojects.TheSchemewasrunbyasmallbutdynamicteamwhopunchedwayabovetheirweightexceedingtheirtargetseveryquarter.Weareimmenselygratefultothem.Throughoutthefiveyearswehaveworkedhardtoensureanongoinglegacyforeveryproject,apledgethatwhentheschemecomestoanendtheprojectscouldcontinue,carriedforwardbylocalresidents,professionalsandvolunteers.Beingamemberofthisskilledandknowledgeablegroup,allcontributingwithsuchinspirationandenthusiasmtosuchasuccessfuloutcome,hasbeenanhonourandapleasureforme.Ihopethat,inthefuture,therewillbemorepartnershipsabletoachievesimilarpositiveresults.Thereissomuchmoretobedone!

    ArabellaAmoryChair,ExmoorMoorlandLandscapePartnership

  • iii

    ExecutiveSummary

    TheHeartofExmoorScheme(officiallyknownastheExmoorMoorlandLandscapePartnershipScheme)wasaHeritageLotteryFundedLandscapePartnershipSchemethatsoughttoconserveandcelebrateExmoor’smoorlandheritagethroughafive-yearprogrammeofactivityfrom2011to2015.

    TheSchemefocussedonthemoorlandlandscapeswithinExmoorNationalParkwhichcoveranareaof232km2.Itsoughttoinvolvepeoplelivingwithin25kmofExmoorinitsactivities(seethemaptotheright)

    ThisevaluationreporttakesstockofalltheScheme’sactivitiesandobjectivelyassesseshowwellithasdelivereditsobjectives,achieveditsoutcomesandleftlong-lastinglegacies.

    ObjectivesandstructureoftheScheme

    TheScheme’sLandscapeStrategy,publishedin2007,identifiedthatExmoor’smoorlandwassufferingfromthreetypesofdisconnectionwhichpreventeditsheritageoflandscape,wildlifeandhistorybeingproperlyconservedandappreciated.Theseweredisconnectionsfrommodernlife,disconnectionsfromthepastandphysicalisolation.

    TheSchemeaddressedtheseissuesthroughthreeprogrammes,containing19projects:

    Programme1: ReconnectingPeople 11projects

    Programme2: ReconnectingLivelihoods 4projects

    Programme3: ReconditioningMoorlandCharacter 4projects

    OperationandfundingoftheScheme

    TheSchemewasrunbyaLandscapePartnershipof14locallyactiveorganisationsandemployedateamoffourprojectstaff,withmanyotherorganisationsbeinginvolvedinprojectactivities.TheSchemewashostedbytheNationalParkAuthority.

    Ithadatotalbudgetof£1.2millionwhichwasraisedfromtheHeritageLotteryFund(55%),NationalParkAuthority(23%),RuralDevelopmentProgrammeforEngland(9%)andavarietyofothersourcesincludingtheExmoorSociety,ExmoorTrust,EnvironmentAgencyandHistoricEngland.

    TheSchemewasunusualincomparisonwithmanyotherLandscapePartnershipSchemes.ThestartoftheSchemewasdelayedanditssizewasreducedduetocutsinthebudgetsofseveralpartnerorganisations.However,mid-waythroughitsplannedthreeyearsofoperationitwasextendedforafurthertwoyears,allowingsomeprojectstobereinstated.

  • iv

    Projectactivitiesandoutputs

    Thelargemajorityofthetargetoutputssetforeachoftheprojectsweremetandmanywereexceededbyalargemargin.ExamplesofthenumbersofpeoplewhoparticipatedindifferentpartsoftheSchemearegivenintheboxbelow.

    ThemostsuccessfulelementsoftheSchemewerethoseinvolvingpeoplewhowerenotpreviouslyfamiliarwithmoorlandheritage,manyfromlocalcommunities,inactivelearningabout,andcelebratingin,thehistory,landscapeandwildlifeofExmoor’smoorland.

    InnovativeapproachesthatweredevelopedduringtheSchemeincludedtheuseofvideos,digitalreconstructionimagery,historicalre-enactments,publicarchaeologyprojectsandweb-basededucationalresources.ThesegavetheSchemeafreshnessandenergythatwasdifferenttowhathadgonebefore.

    Activitiesthatwerelesssuccessfulthananticipatedwerethosethatencouragedmoorlandmanagerstoengagemorewiththepublicortoreviewtheissuesfacingtheirareasofmoorland.

    HeadlineexamplesofSchemeactivity

    • Morethan7,000schoolchildrenvisitedmoorlandwiththeirteacherslearningaboutitsheritagethroughitshistory,science,geographyandothersubjects

    • 4,350peopleattendedeventscelebratingExmoor’smoorlandwildlifeincludingattheannualBogstaticfestivalandaseriesofBigAdventureDaysandover3,000peopletookpartinthe2014ExmoorPonyFestival

    • Over900peopleattended17communityarchaeologyevents,seeingfirsthandtheevidenceofprehistoricusesofmoorlandandover120peopleofallagestookuptrowelsorsurveytapestoundertakearchaeologicalexcavationsorsurveysonmoorland

    • Morethan500agriculturalstudentsandmoorlandmanagersreceivedtrainingonmoorlandmanagement.AlargeproportionofExmoor’smoorlandownersandgrazierssharedknowledgeofmoorlandmanagementwitheachother

    • Overall,volunteerscommittedmorethan5,000daystocelebratingorconservingExmoor’smoorlandheritage

    TheScheme’simpactonExmoor’smoorlandheritage

    IntermsofthedifferencethattheSchememade,comparedtothesituationthatexistedpreviously,themostsignificantimpactswere:• Theincreasedawarenessthatmanymembersofthepublicinthetowns

    andvillagesaroundExmoorhadofExmooritselfandinparticulartheirlocalmoorlandheritage,especiallyitswildlifeandhistory.Forthesepeople,moorlandisn’ttheremoteandforbiddingplaceitmayhaveseemedbefore.

    • Thewayinwhichvolunteerswereinvolvedinthecoredeliveryofmanyprojects,takingonnewskillsandresponsibilitiesthathelpedshapewhatisknownandunderstoodaboutthemoorland’secologyandhistory.Manyofthesepeoplenowfeeltheyhavemoreofapersonalstakeinthemoorlandanditsheritage.

    Inanumberofareas,theSchemewasgenuinelyinnovative,pilotingapproachesthatwerenewtoExmoor.Theseincluded:• Developingpublicarchaeologyprojectsthatallowedlocalcommunities

    touncoverevidenceofpastlivesandlandscapes• Usingdigitalreconstructionsofpastlandscapessothattheybecame

    morerealandeasiertoimagine• Usingvideoandsoundrecordingstohelppeopleinterpretthenatural

    environmentinnewways• Makinguseofthepracticalskillsandcontactsoflocal‘moorkeepers’to

    co-ordinatemoorlandmanagement

    InotherareasofitsactivitytheSchemesupported,andaddedvalueto,theactivitiesofitspartnersratherthanundertakeoriginalwork.Itprovidedtheresourcesandanindependentapproachthatincreasedjointworkingbetweendifferentgroups.

    TheSchemefocussedontheareasofgreatestneedandthetopicswhereitcouldachievemost.Asintended,ithadrelativelyfewimpactsontheoveralllandscapecharacterofthemoorland(awayfromasmallnumberofhighprofilesiteswhereitimprovedlandscapequality).Italsohadfewdealingswithtourismandrecreationbusinessesandthereforedidnothaveasignificantimpactonthearea’svisitororheritageeconomies.

  • v

    LessonslearnedfromthewaytheSchemehasbeenrun

    TheLandscapePartnershiphasbeeneffectiveatdevelopingaclearstrategyfortheSchemeandmanagingitsdelivery.Theinvolvementofthecharitablesector,includingsmalllocalcharities,hasbeennotable.TheNationalParkAuthorityhasplayedacriticalrole,providingthebackofficeadministrationandfinancialmanagementoftheScheme,whileenablingtheSchemetohaveanindependentidentityandwaysofworking.

    ResponsibilityforrunningmostoftheprojectswasdelegatedfirmlytothefourSchemestaff(incomparisontomanyotherLandscapePartnershipSchemesinwhichprojectsarerunbypartners,supportedbythestaff).Thestaffwerehighlyregardedbypartnersandpeopleparticipatinginprojectsandtheywereabletousetheirskillsandenthusiasmtogoodeffect.However,thereisadangerthatwiththeirdeparture,theirknowledgeandmomentumwillbelost.

    TheSchemehasovercomeand,insomeways,benefitedfromadelaytoitsstartandanextensiontoitsoperation.WhilesomeofitsobjectiveswerealreadybeingaddressedbythetimetheSchemestartedin2011(particularlydialoguewithownersandgraziersovermoorlandmanagement),itwasabletouseitssecondPhasetoenhancesuccessfulthemesofworkfromitsfirstPhase.

    IncomparisonwithmostLandscapePartnershipSchemes,theHeartofExmoorSchemehasbeenrelativelysmall(the£662,500receivedfromHLFbeingatthelowerendofgrantsawardedtoLandscapePartnerships).Itbearsfavourablecomparisonwithotherlargerschemesandisjudgedtohavemadeeffectiveuseoftheresourcesithadavailabletoit.

    TheScheme’slegacyforthefutureofExmoor’smoorlandheritage

    Theevaluationreportidentifiesthemanylegacyactivitiesthatshouldbecontinuedandtheconditionsneededforthistohappen,providingachecklistfortheScheme’spartnerstoreview.

    ItishopedthatthatmanyofthehighprofilepublicactivitiesthatweresupportedbytheScheme,suchastheExmoorPonyFestival,Bogtasticevent,communityarchaeologyprojectsanduseofvolunteerswillbecontinuedbypartnerorganisations.MuchoftheknowledgeofmoorlandheritagegeneratedduringtheperiodoftheSchemewillremainaccessiblefromrecordsandpublications,manyofthemavailableonline,maintainedbytheNationalParkAuthority.However,thefutureofsomeactivities,suchasuseofmoorlandandteachingresourcesbylocalschoolsandtheprovisionof‘moorkeeper’posts,iscurrentlyuncertainpendingfundingdecisions.

    ThiswasthefirstexperienceonExmooroftheHLF’sLandscapePartnershipProgramme.Confidencehasbeengainedofwhatcanbeachievedfromatime-limitedinjectionofexternalfunding.Newapproachestodeliveringdiscreteprojectsaspartofalargerlandscape-focussedoverallstrategyhaveprovedsuccessful.Arangeofpartnershaveseenthebenefitsofcontributingtheirownin-kindskillsandmanpowertoasharedendeavour.

    ItwouldbeashameifthemomentumgainedfromtheHeartofExmoorSchemewaslostasaresultofthedissolvingoftheLandscapePartnership.TheopportunityexiststobuildontheachievementsoftheHeartofExmoorSchemeandaddressotherlandscapechallengesonExmoor.

  • 1

    1. Introduction

    Purposeofthisreport1.1. TheHeartofExmoorScheme(officiallyknownastheExmoor

    MoorlandLandscapePartnershipScheme)wasaHeritageLotteryFunded(HLF)LandscapePartnershipScheme.Inanutshell,thisSchemehasaimedtoconserveandcelebrateExmoor’smoorlandheritagethroughafive-yearprogrammeofactivityfrom2011to2015.

    1.2. AstheHeartofExmoorSchemecomestoaclose,thisfinalevaluationtakesstockofallitsactivitiesandobjectivelyassesseshowwellithasdelivereditsobjectives,achieveditsoutcomesandleftlong-lastinglegacies.TheHLF,asmajorityfunder,requiresthatafinalevaluationiscarriedoutandhasproducedguidanceonhowthisshouldbedone1.

    1.3. Thefollowingchaptersofthisreportsetout:

    • ThebackgroundtoLandscapePartnershipSchemesandtheevaluationprocessinChapter1;

    • ThecontextandhistoryoftheSchemeinChapter2;• Asummaryoftheprojectsthatwereundertakenandofthe

    targetoutputsachievedinChapter3;• TheoutcomesoftheSchemeandtheimpactthatithashadon

    Exmoor’smoorlandheritageinChapter4;• FactorscontributingtotheScheme’ssuccessinChapter5;• ThelegacythattheSchemewillhaveonthefutureofExmoor’s

    moorlandheritageinChapter6;• Overallconclusionsincludinglessonslearntandwhatthismeans

    forthefutureoftheExmoor’smoorlandheritageinChapter7.

    1HLFEvaluationGuidance:LandscapePartnerships(February2013–revisedJuly2014)

    LandscapePartnershipSchemes1.4. TheLandscapePartnershipProgrammeisoneoftheHeritageLottery

    Fund’sflagshipprogrammesfordistributingtheNationalLottery’smoneyforgoodcauses.ItisthemostsignificantgrantschemeavailableacrosstheUKforlandscape-scaleconservationprojectsandsince2003ithascommitted£177mto99LandscapePartnershipschemes.

    1.5. TheProgrammeplaysanimportantroleinmeetingtheUK’sobligationsundertheEuropeanLandscapeConventiontorecogniselandscape“asanessentialcomponentofpeople’ssurroundings,anexpressionofthediversityoftheirsharedculturalandnatural

    heritage,andafoundationoftheiridentity.”Thisemphasisesboththepeople-centrednatureoflandscapeasaconceptaswellasthewayitintegratesourappreciationandcareforothernaturalbenefitsoftheenvironmentsuchasbiodiversity,thehistoricenvironmentandculture.

    1.6. LandscapePartnershipSchemesareexpectedtoprotectandimprovetheconditionofnaturalandculturalheritageand,atthesametime,givepeopleandcommunitiesnewanddeeperopportunitiestounderstand,enjoyandgetinvolvedinthisheritage.ThedetailedobjectivessetoutbytheHLFhaveevolvedoverthelast10years,butwhentheHeartofExmoorSchemewasawardeditsfunding,LandscapePartnershipSchemeswereexpectedtocontributeto,andleavealastinglegacy,infourareas.TheseareshowninFigure1.1.

  • 2

    Figure1.1.TheaimsofLandscapePartnershipSchemes

    TheHLF’sfouroutcomesforLandscapePartnershipSchemeswhentheHeartofExmoorSchemewasapprovedwereasfollows:

    • Conservingorrestoringthebuiltheritageandnaturalfeaturesthatcreatethehistoriccharacterofthelandscape;

    • Conservingandcelebratingtheculturalassociationsandactivitiesofthelandscapearea;

    • Encouragingmorepeopletoaccess,learnabout,becomeinvolvedinandmakedecisionsontheirlandscapeheritage;

    • Improvingunderstandingoflocalcraftandotherskillsbyprovidingtrainingopportunities.

    HLFevaluationguidance

    1.7. EvaluationiscentraltodeliveringLandscapePartnershipSchemes.ItshouldbeplannedattheoutsetandbepartoftheongoingreportingprocessratherthananafterthoughtattheendoftheScheme.

    1.8. UndertakingafinalevaluationandsubmittingareportsettingoutthefindingsisarequirementbyHLFbeforeitsignsofftheScheme.HLF’sguidance2makesclearthattheevaluationreportshouldtellthestoryofthescheme.ItshouldhaveawidepotentialreadershipandbeaccessibletomembersoftheLandscapePartnership,beneficiariesandotherorganisationswhomightbeabletolearnfromthePartnership’sexperience.

    1.9. Astheguidancestipulates,theevaluationreportshouldshowtheimpactofindividualprojectsandtheSchemeasawholeandisanopportunityto:

    • DemonstratetoHLFthatLotterymoneyhasbeenwellspent(securingpaymentofthefinal10%oftheHLFgrant);

    2HLFEvaluationGuidance:LandscapePartnerships(February2013–revisedJuly2014)

    • ProvetotheLandscapePartnershipandothers(includingotherswhocontributedmatchfundingorgavetheirtimeandenergytothescheme)thatthisisthecase;and

    • BeclearaboutitslastingbenefitssothatPartnershipmembersandotherswillbemotivatedtocontinuethework,andindicateitsweaknessessothatthey–andperhapsotherLandscapePartnershipSchemes–canavoidthem.

    Themethodologyfollowed1.10. ThisfinalevaluationhasbeenundertakeninlinewithHLF’s

    evaluationguidance,withtheSchemestaffandpartnersmakingsignificantinputs.ExternalconsultantshaveindependentlyreviewedandanalysedevidenceoftheScheme’sperformanceinordertoprovideabalancebetweentellingthestoryoftheSchemeaccuratelyandprovidingobjectivity.

    1.11. Theevaluationdrawsonarangeofsourcesofevidence.SomeofthesearequantitativeandarecompareddirectlywiththenumericalobjectivessetoutintheDeliveryPlanagreedwiththeHLFinAugust2010.Additionalquantitativeinformationhasbeengeneratedfromasurveyofpeoplewhohaveparticipatedorbenefittedfromprojectactivities.Othersourcesofevidencearemorequalitative,drawnfromtheviewsandexperienceofprojectpartnersandstaff.

    1.12. TheintegrityoftheevaluationisassuredbyusingalogicalpathwaythatdemonstrateshowtheinputsandactivitiesofeachoftheconstituentprojectshavecontributedtotheScheme’sresults,outcomesandlegacies.ThislogicchainisshowndiagrammaticallyinFigure1.2.

    1.13. Thisreportmakesanimportantdistinctionbetweenoutputsandoutcomes.

    • OutputsaretheactivitiesthatwereundertakendirectlybytheScheme(e.g.holdinganeventorproducingareport).TheyaredescribedinChapter3.

  • 3

    • Outcomesarethechangesthathappenedasaresultoftheseactivities(e.g.improvingpeople’sknowledge).TheyaredescribedinChapter4.

    Figure1.2.Diagrammaticrepresentationoftheevaluationcomponents

    1.14. ThisEvaluationReportfollowstheHLF’sguidanceandisaccompanied

    byanEvidenceReport(Appendix1)describingthefulldatasetofprojectoutputandoutcomemeasures.

    1.15. Theevaluationhasbeenundertakeninthreemainstagesofwork,whichare:

    1. Reviewofevidence2. Analysis3. Draftandfinalreporting

    1.16. AsignificantamountofevidencehasbeencollatedthroughoutthefiveyearsoftheSchemeandreviewedduringtheevaluation.Thisincludes:

    • Projectoutputdata• QuarterlySchemeReportssubmittedtoHLF• ExmoorMoorlandLandscapeStrategy(2007)• SchemeDeliveryPlan(2010)• ProjectImplementationPlans• Phase2bidtoHLF• ProjectsummariespreparedbytheSchemestaff• Projectevaluationreports(various)

    1.17. WhilethisinformationsetsoutmuchoftheintentionfortheScheme,chartstheprogressoftheevolutionoftheSchemeandprovidesthequantitativedataneededtounderstandifoutputsweremet,itisimportantthatthisfinalevaluationdrawstogethermorequalitativeinformationabout,notonlyindividualprojects,buttheSchemeasawholeasitcomestoaclose.

    1.18. Inordertodothis,amixtureofkeyinformantinterviews,postersandanonlinesurveyhavebeenusedtogatherinformationandopinionsfromthewiderangeofstakeholdersinvolvedintheScheme.ThesehaveincludedtheSchemestaff,Partnershipmembers,projectpartnersandstaffandthosewhohaveattendedandparticipatedinevents.Figure1.3summarisestheengagementexercisesundertakenaspartofthisevaluation.Someoftheinterviewswerecarriedoutbyindividualsoutsideoftheconsultants’evaluationteam.

    1.19. Theinformationfromtheengagementexerciseswasthenanalysed,alongwiththeinformationthathadbeengeneratedbytheSchemestaff.

    ExmoorponiesfeedingonHeatherMoorland©JasonPBall

    Involvingprojectstaff,partnerorganisationsandvolunteers/participants

    Projectactivities

    Inputs Outputs Outcomes

    Evaluationindicators: Mostlyquantitativemeasuresofimmediateresults

    Evaluationindicators: Quantitativeandqualitativeassessmentsoflonger-termchangesarisingfromindividualprojects,programmesandthescheme asawhole

    LegacyImpacts

    Good thingsthatwillcarryonhappening afterthescheme hasfinished

    Effects causedbytheScheme

  • 4

    Figure1.3.SourcesofevidencegatheredduringtheevaluationExercise StakeholderstargetedInterviewswithPartnershipmembers–undertakenbyPhilipKiberd

    • RepresentativesofbodiesontheLandscapePartnership

    InterviewswithNationalParkAuthoritystaff-undertakenbyNaomiGriffiths(PrendConsulting)

    • NationalParkAuthoritystaffwhohavesupportedandworkedalongsidetheSchemestaff

    Schemestaffinterviews • TheSchemestaffOnlinesurvey(part1)withthoseorganisingandrunningprojects

    • Projectpartners

    Onlinesurvey(part2)withthoseparticipatinginprojects

    • Individualswithdirectinvolvementinprojects

    • Individualswithlessdirectinvolvementinprojects

    Advisorypanelmeetings • A‘soundingboard’ofpeopleworkinglocallywhohaveobservedtheSchemeduringitsoperation

    Celebrationevent-exercises • RepresentativesofbodiesontheLandscapePartnership

    • Otherprojectpartners• Organisationswithlessdirect

    involvementintheScheme

    ‘Keyinformant’Interviews

    1.20. Aseriesofkeyinformantinterviewshavebeenundertakenaspartoftheevaluation.Somewerein-depth,one-to-oneinterviews,whilstotherswereamixtureofquestionsbeingposedandrespondedtoinwriting.

    1.21. Theconsultants’evaluationteamcarriedoutindepthsemi-structuredinterviewswiththeSchemestaff(theSchemeManager,MoorlandEducationandOutreachOfficerandMoorlandHeritageOfficer)inearlyDecember2015.

    1.22. RepresentativeofallorganisationsintheLandscapePartnershipattheendoftheSchemewereinterviewedbyPhilipKiberd,aconsultantwhohadhelpedwritethebidtoextendtheScheme.Themajorityofthesewereone-to-oneinterviews.InterviewquestionsweresenttoPartnershipmembersbeforetheinterviewsotheyhadtimetocollecttheirthoughts.ItwasnotpossibletofindasuitabletimetointerviewtheEnvironmentAgencyPartnershiprepresentativesandsoawrittenresponsetothequestionsposedwasreceived.NoresponsewasreceivedfromEnglishHeritage/HistoricEngland.Anumberofface-to-faceinterviewswerealsoconductedwithpeoplewhohadbeeninvolvedintheScheme,butnotasmembersoftheLandscapePartnership.

    1.23. The‘keyinformant’intervieweeswere:

    • ArabellaAmory-PartnershipChair• RichardAndrews-NaturalEngland• HelenBooker-RSPB• VictoriaEveleigh-Moorlandponyherdowner• SiriFrost/Mary-RoseLane-EnvironmentAgency• SuaadGeorge-CentreforHumanRights• JulianGurney-NationalTrust• NickLapthorn-FieldStudiesCouncil• SandraMansell-ExmoorPonySociety• SusanMay-ExmoorTrust• RachelThomas-ExmoorSociety• ChristinaWilliams-MollandEstate

    1.24. Inaddition,membersofstaffattheNationalParkAuthoritywhohadbeeninvolvedintheSchemewereinterviewedbyNaomiGriffithsfromPrendConsulting.

  • 5

    Onlinesurvey

    1.25. AshortonlinesurveyusingGoogleFormswasdevisedandthelinksenttoover250contactsheldontheScheme’sdatabase.Thesurveywaslivefrom11December2015until3February2016and62responseswerereceived.

    1.26. Figure1.4showstheageofrespondentsandtheirbackground.Themajoritywereagedbetween36and65withfewerpeopleovertheretirementageorunder35.Nearly70%ofpeoplelivedinorclosetoExmoorandathirdlivedfurtherawaybuthadaprofessionalinvolvementinmoorlandorotheraspectsoftheScheme.

    Figure1.4.Characteristicsofrespondentstothesurvey

    1.27. Thereweretwopartstothesurveytargetingdifferentaudiences.

    OnewasforthosewhohadattendedorheardaboutanyoftheScheme’seventsoractivitiestoidentifyhowunderstandingandexperienceofmoorlandhaschangedandhowpeoplemightvisitandenjoyitinfuture.Thiswascompletedby30people(48%ofrespondents).

    1.28. Theotherpartofthesurveytargetedthosewhohavehelpedtoorganiseorhostaneventorotheractivity,inordertounderstandtheirexperienceofassistingtheSchemeandwhattheythinkithasachieved.Thiswascompletedby32people(52%ofrespondents).

    1.29. AcopyofthesurveyquestionsandresultsisprovidedintheTechnicalAnnexthataccompaniesthisreport.

    Celebrationevent

    1.30. ACelebrationEventwasheldfortheSchemeon27November2015atLyntonTownHall.ItwasanopportunityforallthoseinvolvedintheScheme,inavarietyofcapacities,tocometogetherandshareinthesuccessoftheSchemeasitdrewtoaclose.Attendedbyaround95individuals,andcomingtwoweeksafterthestartofthefinalevaluation,theopportunitywastakentoadvertisethefactthatanevaluationwastakingplaceandthattheviewsandopinionsofthosewhohadbeeninvolved,inwhatevercapacity,werewelcomed.Opportunitiestocontributewereviatheonlinesurveyorbycontactingtheevaluationteamdirectly.Posterswerealsoondisplay,withaseriesofquestionsabouttheSchemeandattendeeswereencouragedtogivetheiropinionsthenandthere.

    EvaluationAdvisoryPanel

    1.31. AnAdvisoryPanelwassetuptoactasa‘soundingboard’forthefinalevaluationprocess.ThePanelwasmadeupof:

    • JennyCarey-Wood–Ex-managerofNorthDevon+andcurrentmanageroftheNorthDevonAONB

    • NaomiMarley–EditorandMDoftheExmoorMagazineandCEOofLighthouseCommunications

    • GrahamWills–ExNPAofficer(ledonsubmittingtheoriginalapplicationfortheSchemetoHLF)

    1.32. ThemembersoftheSoundingBoardhadnotbeendirectlyinvolvedinthedeliveryoftheScheme,butwereeitherheavilyinvolvedinitsinceptionorcloselyfollowedtheprogressoftheScheme,givingthemadistinctperspectiveonthesuccessoftheScheme.

    AninitialmeetingoftheAdvisoryPanelwasheldonthe14December2015attheNationalParkAuthorityofficesinDulverton.Emergingfindingsfromtheevaluationwerediscussed.AsecondmeetingoftheAdvisoryPaneltookplaceon25February2016toreviewtheheadlinefindingsinthedraftEvaluationReportpriortothefinalisationoftheReportandpresentationtothePartners.

    Under21,2%21to35,10%

    36to50,24%

    51to65,44%

    66to80,19%

    Noanswer,2%Ageofrespondents

    Localresidents,69%

    VisitorstoExmoor,6%

    Professionalinvolvement,

    35%

    Other,5%

    Backgroundofrespondents

  • 6

    2. Background2.1. ThischapterprovidesashortnarrativeonhowtheSchemestarted

    andtheissuesthatitsoughttoaddress.Itmapstheareasitcoveredandthekeyaudiencesithopedtoengagewith.Itsadministration,staffingandfundingaredescribed.

    OriginandaimsoftheScheme2.2. TheoriginsoftheSchemelieinthedecisionbyExmoorNationalPark

    Authorityin2004tocommemoratethe50thanniversaryofthedesignationoftheNationalParkwithafocusonthemoorlandlandscapethatliesatitsheart.Aseriesofpaperswereprepareddescribingtheconditionofthedifferentspecialqualitiesofthemoorland.ForemostamongthesewasareportcommissionedbytheExmoorSociety,thelocalcharitythatchampionsthepurposesoftheNationalParkdesignation.The‘MoorlandsataCrossroads’reportconcludedthatmoorlandwasneitherwellunderstoodnoringoodconditionanditmadeaseriesofrecommendationstoaddressthesepoints.

    2.3. TheNationalParkAuthorityrespondedquicklytotheserecommendationsandproposedthecreationoftheExmoorMoorlandsLandscapePartnershipandabidtotheHeritageLotteryFund’s(HLF)LandscapePartnershipsProgramme.ThePartnershipwasformedfrom14locallyactiveorganisationscoveringstatutorybodies,businessesandthevoluntarysector(Figure2.1).WiththeexceptionofActiveExmoor(aninitiativewhichfinishedshortlyafterthePartnershipwasformed),allpartnershaveremainedinvolvedintheSchemealthough,aswillbedescribedlaterinthisreport,theyhavetakendifferentroles.ButterflyConservationandVisitExmoorwerenotpartnersduringSchemedeliverybutdidconnectwithprojectactivities.

    2.4. DuringtheplanningphaseoftheSchemeextensiveconsultationswithpartners,stakeholders,usersandthepublicatlargewerecarriedout.TheseshapedtheunderstandingoftheissuesandopportunitiesthatExmoorfacedandinturnhelpedshapetheprioritiesthatindividualprojectswouldneedtoaddress.NinekeydocumentsunderpinnedtheapplicationtoHLFfortheHeartofExmoorScheme(Figure2.2).

    Figure2.1.MembershipoftheLandscapePartnership• ActiveExmoor• EnglishHeritage• EnvironmentAgency• ExmoorNationalPark

    Authority• ExmoorSociety• ExmoorTrust

    • FieldStudiesCouncil• TheNationalTrust• NationalFarmersUnion• NaturalEngland• RoyalSocietyfortheProtectionofBirds

    (RSPB)• WestSomersetCollege

    Figure2.2ResearchunderpinningtheScheme

    DocumentspreparedspecificallyfortheapplicationforHLFfunding:• AccessPlan,AudienceDevelopmentPlanandTrainingPlan(allFebruary

    2007,LandUseConsultantsandResourcesforChange)• ConservationandRestorationPlan(February2007,ENPA)

    OtherdocumentsthatinfluencedthedesignoftheScheme:• MoorlandsataCrossroads–theStateoftheMoorlandsofExmoor,2004.

    AreporttotheExmoorSocietybyLandUseConsultants• ExmoorNationalParkLandscapeCharacterAssessment2007.ENPA• ExmoorNationalParkManagementPlan2007–2012.ENPA,July2007• GreaterExmoorSustainableEconomicDevelopmentStrategy2007.The

    NewEconomicsFoundation,February2007• TheStateofFarmingonExmoor2004.CentreforRuralResearchatthe

    UniversityofExeter.

  • 7

    2.5. ThekeyconclusionsontheissuesfacingExmoor’smoorlandarisingfromthesedocumentsaresummarisedinFigure2.3.

    Figure2.3.KeyconclusionsarisingfromthepreparatoryresearchfortheScheme

    • LackofknowledgeaboutExmoor’smoorlandandpoortransportandaccessibilitywerekeybarrierspreventingpeoplelivinginthetownsandvillagesclosetoExmoorgainingthemanyphysical,educationalandspiritualbenefitsthatthemoorlandcanoffer.

    • Therehadbeenalossofmoorlandmanagementskillsandknowledgeamongstfarmersandthereweregapsintheincentivesneededtomaintainthecharacteristicvegetationinagoodstate.

    • TheconditionofsomeoftheiconicwildlifeofExmoor,includingtheExmoorpony,wasnotwellknown.Therewasaneedtoimproveanddisseminatethisknowledge,andtherewereopportunitiestoinvolvelocalcharitiesandvolunteersinthiswork.

    • Therewaslittlepublicunderstandingoftherichculturalheritageofthemoorlandandtherewaslittlemonitoringoftheconditionofarchaeologicalsites.

    2.6. ThefindingsofthepreparatoryresearchandconsultationswerebroughttogetherintheLandscapeStrategythatwaspublishedbytheNationalParkAuthorityinSeptember2007.ThissetouttherationaleandobjectivesoftheproposedSchemeonbehalfoftheLandscapePartnershipandoutlinedtheprojectsthatcouldbeusedtoaddresstheissuesraised3.TheoriginalaimsandobjectivesoftheSchemearesummarisedinthetexttakenfromtheLandscapeStrategyshowninFigure2.4.

    3ExmoorMoorlandLandscapePartnership(2007).ExmoorMoorlandLandscapeStrategy.September2007.

    Figure2.4.TheoriginalaimsandobjectivesoftheScheme

    OurLandscapePartnershiphasbeenbroughttogethertoundertakeaseriesofinterlinkedprogrammestoconservethelandscapeheritageofthemoorlandofExmoor.

    Wewanttoforgenewconnectionsbetweenthemoorlandandthepeoplewholivearoundandvisitit.Wewanttoensurethatthemoorlandlandscapeanditsheritageremaineconomicallyandsociallyrelevanttolocalcommunitiesandtovisitors.OurPartnershipisaboutshapingthefuturehistoryofthisuniquelandscapebyweavingitbackintothelivesoflocalcommunities.

    OurPartnershipisunashamedlyaboutpeople-reconnectingthemtotheirmoorlandheritage-helpingthemaccess,understand,enjoyandcelebratetheirmoorlandheritageandsotogivethemconfidencetoparticipateinitsconservation.Inthiswaythefuturemanagementof,andsupportfor,thisremarkablelandscapeheritage-anislandoftranquillity,peace,opennessandwildnessinanotherwiseover-crowdedsouthernBritain-willbeassured.Itwillbecometreasuredinnewwaysandvitaltopeople'swell-beingandrecreation/re-creationandsobesafeguardedforposterity.

    Coupledwiththisreconnectionisaprogrammeoflandscapereconditioning,enhancingthequalitiesthatmakeitspecialtopeople-itswildness,remoteness,andtranquillity-characteristicsveryrare,andveryvaluable,inourover-crowdedisland.

    OurLandscapePartnershipaimstouseExmoor'smoorlandresourcestotellitsinspirationalstorytoanewgenerationofresidentsandvisitors.Itwillusethemoorland'swidehorizonstoexpandpeople'spersonalhorizons.Itwillbringanexperienceanddeeperunderstandingofourcountryside,landscapeandsocialhistory,andthenaturalprocessesthatcontinuetoshapeourenvironment.Itwillworkwiththelandowners,farmersandotherorganisationswhoarethestewardsofourmoorlandheritagetoaddressthechallengesofthefuture.

    Source:LandscapeStrategypublishedSeptember2007

  • 8

    2.7. ThecentralthesisdescribedintheLandscapeStrategywasthatExmoor’smoorlandsweresufferingfromdisconnectionwhichcouldbeseeninthreedimensions.AddressingthesechallengesbecametheobjectivesoftheScheme.• Disconnectionfrommodernlife.Localtraditionsofusingthe

    moorlandsforwildfood(suchaswhortleberries)hadvirtuallydiedout,grazingofmoorlandwasincreasinglyperipheraltothemodernfarmingeconomyanddeclininglevelsofpublictransportmeantthatthemoorlandswereeffectivelyinaccessibletomanypeopleinnearbytowns.

    • Disconnectionfromthepast.Despitetheemergenceofnewarchaeologicalevidenceoftheuseofthemoorlandsoverseveralmillennia,publicunderstandingoftheirculturalsignificancewasindecline.

    • Disconnectedfromitself.Theincreasingfragmentationoftheremainingmoorlandblocks,surroundedbymodernfarmland,separatestheminthelandscapeandisolatespopulationsormoorlandwildlifespecies.

    2.8. ThesethreeobjectiveswererelateddirectlytothethreeprogrammesaroundwhichtheSchemewasstructured:ReconnectingPeople;ReconnectingLivelihoods;andReconditioningMoorland.

    2.9. TheSchemewasdesignedtooperateintwogeographicalareas.TheextentofthemoorlandlandscapewhichtheSchemesoughttoenhancewasdefinedby20‘moorlandunits’thathadbeenagreedseparatelybytheMoorlandInitiativeBoardestablishedbytheNPA.Theseareasofmoorlandandassociatedhabitatcover232km2withinthe694km2ofExmoorNationalPark.ThetargetareaforparticipationandinfluenceoftheScheme(its‘audience’)wasdefinedasthetownsandvillageswithin25kmoftheNationalPark.TheseareasareshowninFigure2.5.

    FarleyWateronBrendonCommon©JasonPBall

  • 9

    Figure2.5.ThelocationandphysicalextentoftheScheme

  • 10

    Timelineandkeystages2.10. ThestoryofthedevelopmentanddeliveryoftheSchemeisnot

    altogetherstraightforwardandtheScheme’sevolutionhasinfluencedthewayithasdelivereditsobjectives.Figure2.6summarisesthekeystagesintheScheme’sdevelopmentanddelivery.

    2.11. During2006and2007,theNationalParkAuthoritytooktheleadinformingthePartnershipanddrawinguptheLandscapeStrategyandotherdocumentstosupportthebidtoHLF’sLandscapePartnershipProgramme.ThePartnershipsoughtfundingof£1.2millionfromtheHLFtoaddressthesedisconnections.

    2.12. HLFapprovedfundingin2008butin2009theNPAdecidedtoputplansfortheSchemeonhold.Thiswasaperiodofgreateconomic

    uncertaintyfollowingthe‘bankingcrash’andcutsinpublicfunding.TheNPAhadreceivedacutinitscorebudgetandtherewasuncertaintyovertheavailabilityofothermatchedfunding.

    2.13. AreducedrangeofprojectswereagreedwithHLFin2010andtheSchemewaslaunchedinJanuary2011for15projectsunderthreeprogrammesoverathree-yearperiod.

    2.14. BythestartofthesecondyearoftheScheme,ithadbecomeclearthatthesuccessoftheSchemewarrantedanextension.InMay2013aproposalwasmadetoreinstatefiveprojectsthathadbeenomittedin2011.FundingforthesebeganinJanuary2014forafurthertwoyears.ProjectactivitiesstoppedinDecemberandtheSchemewascompletedinMarch2016.

    Figure2.6.Schemetimeline

  • 11

    Administrationandstaffing2.15. AdministrationoftheSchemewasundertakenbyExmoorNational

    ParkAuthority.Itprovidedthe‘accountablebodystatus’(i.e.itlookedafterthemoney),officeaccommodationandlinemanagementfacilitiesforthreeofthestaff(seebelow).ItisworthnotingthatalthoughitprovidedtheseimportantservicestotheScheme,theAuthoritydiscouragedtheperceptionthatitwastheleadpartyinthePartnership(discussedmorefullyinChapter5).

    2.16. AtthestartoftheScheme,thePartnershipappointedafull-timeSchemeManagertoleaddeliveryoftheprojects,reportingtothePartnership.DuringthefirstmonthsoftheScheme,threeothermembersofstaffwereappointed.TheSchemestaffwereasfollows:

    • SchemeManager:JasonBall.Full-time.OverallresponsibilityforSchemeadministration.Managedeightprojects

    • MoorlandEducationandOutreachOfficer:DavidRolls.Full-time.Managedsixprojects

    • MoorlandHeritageOfficer:FayeBalmond.Initiallytwoandahalfdaysaweek,increasedtofourdaysaweekandthenfull-timeinthesecondphaseoftheScheme.Managedfiveprojects

    • ExmoorPonyOfficer:LinziGreen.EmployedbyandbasedattheMoorlandMousieTrust’sExmoorPonyCentre.Workedpart-time(onedayaweekonaverage)

    • Administrativesupport:TheNationalParkAuthorityprovidedfinancialmanagementsupportasrequiredduringthefiveyearsoftheScheme.Additionalpart-timeadminsupportwasprovidedtotheSchemeManagerforashortperiodin2012-2013withextrafinancesupportduringPhase2

    Costsandfunding2.17. Theoverallcostoftheschemewas£1.17million,threequartersof

    whichwasallocatedtothefirstphase(2011-2013)andtheremaindertothesecondphase(2014-2015).AsFigure2.7shows,corerunningcostsaccountedfor45%oftotalspending(staffsalariesof36%andsupportcostsof9%).Programme1(ReconnectingPeople)accountedfor21%ofcosts,Programme2(ReconnectingLivelihoods)for12%andProgramme3(ReconditioningMoorland)for18%.Acontingencyof4%wasavailableforunforeseencosts.FinalexpenditureagainstthesebudgetedamountsisreviewedinChapter5.

    Figure2.7.Breakdownofbudgetedcosts

    ComponentPhase12011-13

    Phase22014-15 Overall Split

    Programme1 £178,075 £70,200 £248,275 21%Programme2 £136,400 £0 £136,400 12%Programme3 £180,900 £32,350 £213,250 18%Salarycosts £263,828 £158,600 £422,428 36%Supportcosts £63,400 £36,400 £99,800 9%Contingency £41,130 £10,100 £51,230 4%Totalcost £863,733 £307,650 £1,171,383 100%

    2.18. TheHeritageLotteryFundhasbeenthemajorityfunderoftheScheme(£662,500),supportedbytheNationalParkAuthorityanditsPartnershipFund(£282,398ofwhich£21,924wasin-kind),WesternSomersetLocalAction(£77,161)andLeader4TorridgeandNorthDevon(£26,807).ThelattertwowerepartoftheRuralDevelopmentProgrammeforEnglandandcontributingtoProgramme2inthefirstphaseoftheScheme.

    2.19. Inaddition,individualprojectsweresupportedfinanciallybyavarietyofpartnerstothetuneof£88,565.TheHeathcoatandAmoryTrustscontributed£42,000viaTheExmoorSociety,andtheExmoorTrustcontributed£13,000.EnglishHeritagehadprovided£11,000tothe

  • 12

    NationalParkAuthoritythroughitsMonumentManagementSchemeandthiswaschannelledthroughtheScheme.TheEnvironmentAgencycontributed£10,000andNaturalEnglandputin£1,000.SouthWestWaterprovided£4,035,mostthroughtheExmoorMiresProject.Buglifeprovided£2,240andtheMalcolmMacEwenTrust£2,000.

    Figure2.8.SourcesofincometotheScheme

    Seeparas.2.18to2.20fortheamountsofincomein£pounds.

    In-kindsupportbypartnersandvolunteers2.20. TheSchemereliedheavilyonpartnersprovidingtheirtimetoattend

    meetings,toadministerprojectsandprovideotherresourcesforwhichnofinancialchargewasmadetotheScheme.SomeoftheseinputswereallocatedafinancialvalueandincludedintheSchemebudgetsuchastheNationalParkAuthority’slogisticalandadministrativecontributions(£21,924)andtheEnvironmentAgency’ssupportforecologicalsurveytraining(£5,050).

    2.21. Anelementofthetimecontributedbyvolunteerstothedeliveryofprojectswasincluded,calculatedusingratesagreedwithHLF(valuedat£51,550).Inadditionincome‘earned’ateventssuchasfromcateringandentryfeescontributed£4,800.TheseamountsareallincludedinFigure2.8.

    2.22. However,manyofthein-kindcontributionsmadebypartnersandvolunteerswerenotvaluedfinancially.These‘uncosted’inputsincludethefollowing(thislistisnotexhaustive):

    • TheNationalParkAuthority(memberandseniorstaffinvolvement)

    • ExmoorSociety(chairingthePartnership)

    • TheMoorlandMousieTrust(hostingtheExmoorPonyOfficer)

    • NaturalEngland,RSPB,FieldStudiesCouncil,NationalTrustandExmoorMiresProject(allinvolvedinadvisingandcontributingtoevents)

    • ThetotalamountofvolunteertimecontributedtotheSchemehasbeencalculatedatover5,000days(givingatheoreticalvalueusingtheHLFrates–notincludedinthebudget-ofover£400,000).

    HeritageLotteryFund 55%

    ENPA(cash)12%

    WesternSomersetLocalAction 6%Leader4TorridgeandNorthDevon 2%ENPA(inkind) 2%

    9%

    5% 4% 1%

    4%Projects23%

    Matchedprojectfunding

    ExmoorPartnership/SustainableDevt.Fund

    Contributorstomatchedprojectfunding

    ExmoorSociety(fromcharitabletrusts)Valueofinkindcontributions (various)

    ExmoorTrust

    Coreschemefunding

    Others(includingSouthWestWater,EnvironmentAgencyand'earned'income)

  • 13

    DistinctivefeaturesoftheScheme2.23. BeforedescribingtheSchemeindetailinthefollowingchapters,

    attentionshouldbedrawntotwowaysinwhichithasbeendifferentfrommanyotherLandscapePartnershipSchemesthatwereawardedfundingatthesametimeastheHeartofExmoorScheme.

    • Firstly,theSchemetookplaceoverfiveyearsintwophases.ThreeyearswastheexpectedtimespanforLandscapePartnershipSchemeswhentheHeartofExmoorSchemewasapproved(nowmostSchemesareapprovedforafiveyearprogramme).However,itsearlysuccesspromptedanextensionoftwoyears.ThismeantthattheHeartofExmoorSchemehadlongerthanexpectedtodeliveritsobjectivesbutincludedaperiodofreflectionandreviewhalfwaythrough.

    • Secondly,adecisionwastakenaftertheLandscapeStrategyhadbeenpreparedbutbeforetheSchemestartedtodropthreelargelandscapeenhancementprojectsthathadbeenplanned.Thiswasforreasonsofcostandpotentialduplicationwithotherinitiatives.

    2.24. ThesefactorsinfluencedmanyofthesubsequentimpactsoftheSchemeandareconsideredinmoredetaillaterinthereport.

    Swaling(controlledheatherburning)onMollandMoor,2012©JasonPBall

  • 14

    3. ProjectsandOutputs

    3.1. TheSchemehasoperatedthroughthreemainprogrammeelements,eachofwhichhascontainedanumberofprojects.Theseprogrammeelementsareasfollows:

    1.ReconnectingPeople

    2.ReconnectingLivelihoods

    3.ReconditioningMoorlandCharacter

    3.2. Thischapterrunsthrougheachoftheseprogrammesinturn,describingtheiroriginalrationale(thereasonswhytheywereneeded)andsummarisingtheactivitiesandoutputsofindividualprojects.TheTechnicalAnnexthataccompaniesthisreportprovidesmoredetaileddescriptionsofalloftheprojects.

    Programme1:ReconnectingPeople3.3. Thefirstofthethreeprogrammeswasthelargest,involvingoverhalf

    oftheprojects(11of19)and42%oftheScheme’sprojectbudget(i.e.notincludingsalariesandotheroverheads).TheseprojectsarelistedinFigure3.1.EightoftheseprojectstookplaceinthefirstphaseoftheScheme(2011-2013),someofthem,suchasTheMoorlandClassroom,continuingduringthesecondphase(2014-15),withthefinalthreeinFigure3.1takingplaceonlyinthesecondphase.AdministrationoftheprojectsinthisprogrammewasundertakenbytheMoorlandEducationandOutreachOfficerandtheMoorlandHeritageOfficer.

    Originalrationale

    3.4. ThesupportingevidencefortheSchemeidentifiedagrowingdisconnectbetweenresidentsandvisitorstoExmooranditsmoorlandheritage.

    3.5. Changingmarketsanddiminishingagriculturalsupportwasresultinginfarmersabandoningmoorlandgrazing,climatechangewasalteringthemoorlandenvironment,changinglifestylesresultedinlocalcommunitieslosingtheirlinkswiththemoorsandhavingaverylowawarenessofthemoorland,whilstvisitornumberstomanypartsofthemoorwereeitherstaticorfallingatatimewhenvisitordemandswerechanging.

    3.6. TheLandscapeStrategy4setoutthedesirefortheLandscapePartnershipto“forgenewconnectionsbetweenthemoorlandandthepeoplewholivearoundandvisitit.Wewanttoensurethatthe

    moorlandlandscapeanditsheritageremaineconomicallyandsocially

    relevanttolocalcommunitiesandtovisitors.OurPartnershipis

    aboutshapingthefuturehistoryofthisuniquelandscapebyweaving

    itbackintothelivesoflocalcommunities.”

    3.7. The‘ReconnectingPeople’programmeattemptedtoaddressthisdesirethroughthe11projectslistedinFigure3.1.ThelocationsofmanyoftheprojectsandtheiractivitiesareshowninFigure3.4.

    3.8. AsummaryoftheissuesandopportunitiesthatrelatetothisprogrammeisgiveninFigure3.3below.Theprojectsummaries(seetheTechnicalAnnextothisReport)identifythespecifickeyissuesandopportunitiesthatthe11projectssoughttoaddressinturn.

    4TheExmoorMoorlandLandscapePartnershipLandscapeStrategy(2007)

  • 15

    Figure3.1.Projectsinthe‘ReconnectingPeople’programmeProject Objective BudgetReachingOut Helpingpeoplefromlocal

    communitiesconnectwithExmoor'smoorland

    £22,900

    VolunteersfortheMoor

    Encouragingandsupportingvolunteers

    £7,225

    TheMoorlandClassroom

    Supportingschoolvisitsandeducationalactivities

    £55,600

    AccessforAll Helpingpeoplewithdisabilities,accessormobilityissuestovisitmoorland

    £11,600

    MoortoSea Helpingcommunities'downstream'ofExmoorunderstandwhymoorlandisimportant

    £10,000

    Exmoor'sTreelessForest

    Research,conservationandlearningabouttheformerRoyalForest

    £11,750

    DiscoveringPrehistory

    Encouragingunderstandingofthemoorland’sprehistory

    £16,500

    ViewsoftheMoor

    Recordinghowthemoorlandhaschangedoverthecenturies

    £42,500

    CommunityArchaeology

    Supportingcommunitygroupstocarryoutarchaeologicalfieldworkandresearch

    £42,000

    NewEcologists Engagingpeopleofallagesinsurveyingandconservingmoorlandwildlife

    £23,700

    ManagingExmoor'smoorlandknowledge

    Capturingandsharinggoodpracticebyprojectsandvolunteers

    £4,500

    Figure3.2.Examplesof‘ReconnectingPeople’projectlocations

  • 16

    Figure3.3.IssuesandopportunitiesidentifiedpriortotheSchemethatthe‘ReconnectingPeople’programmesoughttoaddress

    • LowawarenessofExmoor’smoorlandandalackofunderstandingofwhatitoffers.(AccessPlan)

    • VisitornumberstoExmoor’smoorlandarestaticorfalling.(AccessPlan)

    • Moorlandviewedasaremoteand‘threateningplace’.(AccessPlan)

    • Difficultaccessforthosewithmobilityproblemsorwithoutaprivatecar.(AccessPlan)

    • Engagingthoselivingwithin25kmofExmoorNationalParkprovidesthebiggestopportunitytoexpandtheaudience.(AudienceDevelopmentPlan)

    • Limitednumberofvolunteers.(ConservationandRestorationPlan)

    • Lackofco-ordinationofvolunteers(TrainingPlanandConservationandRestorationPlan)

    • Volunteeringopportunitiesarelimitedbyflexibility,typeofopportunitiesandaccessibility.(TrainingPlan)

    • Facilitiesforvisitingvolunteergroupsarelimited.(ConservationandRestorationPlan)

    • Opportunitiesforvolunteertrainingidentifiedinclude:traditionalskillssuchashedgingandwalling,wildlifesurveyingandvisitorsurveys.(TrainingPlan)

    • Ahighproportionofelderlyresidentswhoarelowusersbecauseofalackoftransport,mobilityissuesandlowincome.(AudienceDevelopmentPlan).

    • Useofthemoorlandbyschoolsinthehinterlandisverylow.(AudienceDevelopmentPlan)

    • Lackofunderstandingoftherelevanceofmoorlandheritagetothecurriculum.(TrainingPlan)

    • Alreadyrelativelygoodcurriculum-basedmaterialsavailableonExmoor’snaturalheritage,includingmoorland.(TrainingPlan)

    • FewyoungpeopleinHigherEducationintheareaaroundExmoorexperiencethemoorlandaspartoftheircourse.(TrainingPlan)

    • OpportunitiestoincreasethenumberofinitiativestobringyoungpeopletoExmoorwholiverelativelyclose.(TrainingPlan)

    • AdirectcorrelationbetweenthedistancefromtheNationalParktowherepeopleliveandtheirlevelofengagement.(AudienceDevelopmentPlan)

    • Asignificantnumberofvisitorsvisitedthecoastasapreferenceoverthemoorland(AudienceDevelopmentPlan)

    • AstrongeraffinityexistsbetweenthesettlementsandvisitorsaroundthecoastalmarginsoftheNationalParkthanmorecentrallywithinthearea.(AudienceDevelopmentPlan)

    • Surveyandresearchisalowpriorityforfunding.(ConservationandRestorationPlan)

    • Surveyworkisreliantonvolunteersandthereisashortageofpeopleskilledinidentifyingdifficultgroupssuchaslowerplantsandinvertebrates.(ConservationandRestorationPlan)

    • Thereisinsufficientknowledgeoftheculturalheritageresource,especiallysiteswithpalaeo-environmentalsignificance.(ConservationandRestorationPlan)

    • Keygapsincurrentknowledgeandunderstandingofthemoorlandinclude:earlyprehistoriclandscapesthatsurviveonthemoorlande.g.stonesettingswhichareuniquetoExmoor;theprocessofreclamationandagriimprovementonmoorland(Mesolithictopresent);theEnclosureoftheRoyalForestinthe19thcentury;theuseofthemoorlandsduringWorldWarII;understandingthemoorlandarchaeology,inparticularpastunsustainablepracticesandhistoricstockinglevelsandvegetationchange,particularlyonthecommonsandwidermoorland.(AccessPlan)

  • 17

    Mainfocusofactivitiesandoutputs

    3.9. Figure3.4providesasummaryofhowthetargetoutputsforthisProgrammethatwereagreedbetweentheLandscapePartnershipandtheHLFwereachieved.Thelargemajorityoftargetoutputswerecomfortablyachievedwithsome,suchasthenumbersofschoolandcommunitygroupsvisitsandarchaeologicalfieldworksessions,beingachievedbyalargemargin.

    3.10. FulldetailsofalltheprojectsundertheReconnectingPeopleprogrammecanbefoundintheTechnicalAnnexthataccompaniesthisreportincludingasummaryofthepurposeoftheproject,keyissuestargeted,locationsandtargetaudiences,fundinganddeliverypartners,activitiesundertaken,achievementoftargets,outcomesachieved,lessonslearnedandlegacyactivity.

    3.11. Theprogrammecontainedadiversemixtureofprojectsbothintermsofsubjectmatter(fromconservationtoculturalheritage)andvisibilityofprojects,withbothhighprofileprojectsandthosethatprovidedthefoundationsformanyotherprojectsintheprogrammeandtheSchemeasawhole.

    3.12. Reachingout,VolunteersfortheMoorandManagingExmoor’sMoorlandKnowledgewerethreesuchcross-cuttingprojects.Underlyingmanyofthemoorland’sissues,andprovidingasignificantbarriertoreconnectingpeopletothem,wasthelowlevelofengagementandawarenessofmoorlandheritageamongstmanydifferentsectionsofsociety,particularlythoseincommunitiesimmediatelysurroundingtheNationalParkboundary.TheReachingOutprojectattemptedtoaddressthis.Bytargetingallagegroupsinsurroundingcommunitiesthroughanumberofdifferentmechanisms,itaimedtoraiseawarenessandengagepeoplewiththemoorland,openingthedoorformanyotherprojectsnotonlyinthisprogrammebuttheSchemeasawhole.Hostingandsupportingeventssuchascommunitygroupvisitstomoorlandandlargerfamilyeventssuchas‘GowildonGrabbist’formedthebasisofthisproject.

    3.13. TheVolunteersfortheMoorprojectaddressedtheissueofengagementatadeeperlevel,whilstalsofullycapturingtheenthusiasmandenergyofthosecommunitiesthatalreadyhadsomelevelofappreciationandawarenessofthemoors.WhilstvolunteeringwasalreadytakingplacewithintheNationalParkandonmoorland,thisprojectplacedgreateremphasisonmatchingthetheskillsandknowledgeofvolunteerstothetasksavailable.Thisgavevolunteersaspecialroleininfluencingtheplanninganddeliveryofprojects.Volunteertrainingtookplace,alongsidesupportingandworkingwithotherprogrammesandinturn5,000volunteerdaysweresupportedbytheproject.

    3.14. TheManagingExmoor’sMoorlandKnowledgeproject,whichwasbroughtintoPhase2,cutacrossnotonlytheReconnectingPeopleprogramme,buttheSchemeasawhole.ItsoughttoensurethattheknowledgebuiltupasaresultoftheoutputsfromeachprojectwascapturedalongwithgoodpracticeaboutdevisingandsettingupeventsandactivitiesundertakenaspartoftheScheme.Theoriginalideahadbeentoprovideadigitalcatalogueor‘routemap’ofalltheknowledgethatwasavailableonExmoor’smoorland.However,itbecameclearthatthiswouldduplicateothersourcesofinformation(suchastheHistoricEnvironmentRecordmaintainedbytheNationalParkAuthority).Asaresult,itwasagreedtofocusoncollatinginformationonspecifictopicsthroughaseriesofonlinecasestudiesandvideosandbysupportingcommunityknowledgesharingevents.

    3.15. AnothergroupofprojectsunderthisprogrammeextendedtheworkoftheReachingOutprojectbytargetingspecificgroupsofpeopleandtryingtotacklethebarriersthatpreventedtheirengagementwithmoorlandheritage.AccessforAlltriedtotacklethebarrierstovisitingmoorland,particularlythosefacedbythedisabled.Tasterdays,newresourcesandtwonewaccessibleroutesdesignedforoff-roadmobilityscooters(Trampers)–oneatSimonsbathandtheotheratHeddonValley–werecreatedbyworkingwithdisabilitygroups,charitiesandorganisations.

  • 18

    3.16. TheMoorlandClassroomprojectsupportedandencouragedschoolvisits,educationalactivitiesandlearningexperiencesbothintheclassroomandonthemoor.ItssuccessmeantthatitbecameoneoftheflagshipprojectsfortheSchemeasawhole,successfullyengagingmorethan7,000pupilsand,throughitsonlineresources5andteachertrainingprogramme,helpingtofosterlongertermenthusiasmandengagementwithmoorlandheritage.

    3.17. TheMoortoSeaprojecttookaninnovativeapproachtoengagementtakingaspecificphysicalfeature–inthiscasetheRiverExe–asawaytoreachoutandengageoutlyingcommunitieswho,withdistancefromthemoor,wereinevitablylessengaged.Throughamixtureofevents(suchasBogtastic),outreachprojectsandroadshows(suchastheSpiritoftheExeFestival)andtheSoundsoftheExeartsproject6,theimportanceofconservingandrestoringExmoor’swetlandhabitatsandwaterresourcestodownstreamcommunitieshasbeenhighlighted.

    3.18. AnotherinnovativeprojectunderthisprogrammewasNewEcologists.Focussingonresolvingbothuntappedenthusiasmforvolunteeringandalsotheneedforfurtherecologicalsurveyandresearchworktobeundertaken,thisprojectworkedwith21partnerstoproducenewonlineresources,undertakeoutreacheventsandsupportwildlifesurveysincludingthecitizensciencesurvey‘ExmoorWildWatch’.Throughtheseactivitiessome4,350individualswereinvolvedin38ecologyroadshows,29familyecologydays,52schoolandcollegevisits,52ecologysurveytrainingsessions,12Bioblitzeventsand28wildlifesurveys.AnannualExmoorWildlifeForumwasestablishedwhichisplannedtocontinuebeyondtheScheme.

    3.19. Knowledgeofthemoorland’sculturalheritagewashighlightedasakeygapinunderstandingandfourprojectsintheprogrammesoughttoaddressthis.TheExmoor’sTreelessForestprojectandCommunityArchaeologyprojectbothfocussedonusingvolunteerstocarryoutconservationandsurveywork.Bothprojectsincluded

    5Seehttp://www.exmoor-nationalpark.gov.uk/learning/the-moorland-classroom6ForoutputsoftheSoundsoftheExeproject,seehttps://www.youtube.com/user/ExmoorNP

    trainingvolunteersandinthecaseofCommunityArchaeologythisincludedfairlyadvancedtechniquesincludingphotographicandgeophysicalsurvey.Bothprojectsaddedsignificantlytocurrentknowledgeofthesitesthattheyfocussedonandthisinformationwassharedamongstcommunitygroups,schoolsandthelocalpopulation.

    3.20. TheViewsoftheMoorprojectlookedathowpeoplehaveviewedExmoor’smoorlandheritage,particularlywithinlivingmemory,producingreconstructionsanddocumentingoralhistories.TheViewsofExmoorExhibitionhelpedtocelebrateandbringaliveExmoor’smoorlandheritageandbringawarenessofExmoor’sspecialqualitiestoawideraudience.

    3.21. TheDiscoveringPrehistoryprojectfocussedonincreasingunderstandingofaparticulartimeperiodofmoorlandheritage–prehistory.Fieldtripsandeventswereorganisedanddeliveredtoawiderangeofgroups,includingschools,universities,localsocieties,youthgroupsandthegeneralpublicthroughcommunityarchaeologytoencouragepeopletoengagewithExmoor’smoorlandprehistory.

    Schoolchildreninthemoorlandclassroom,PinkeryBog©SteveGuscott

  • 19

    Figure3.4.Achievementoftargetoutputs–Programme1:ReconnectingPeople

    0% 50% 100% 150% 200% 250% 300%

    500people attendinganeventorfieldtrip

    30field trips

    10talkstolocalgroups

    10guidedwalks

    20volunteers trainedinwallingtechniques

    5volunteersengagedinsurvey andresearch

    15businesses engaged

    9visits byschool/community groups

    30communities contacted

    30schools contactedalongtherivercorridors

    90people benefitingfromimproved access

    12guidedwalksforwheelchairusers

    12outreacheventsfordisability groups

    15morevolunteersworkingregularly

    15visits touniversities orcolleges

    15presentationstoyouthgroups

    36community groupscontacted

    100schools receiveresourcepacks

    3summerschools (15students attending)

    108term-timeeducationdays

    30schools engagedeachyear

    24tasterevents(30attendeesperevent)

    30groupvisitstomoorland

    150community/youth groupscontacted

    Discover-

    ing

    Prehistory

    Exmoor’sTreeless

    Forest

    MoortoSe

    aAccessfo

    rAll

    Volunteersfo

    rthe

    Moor

    TheMoorla

    nd

    Classroom

    ReachingOut

    Proportionoftargetachieved

    513%

    386%

    344%

    1,289%

    150%

    0% 50% 100% 150% 200% 250% 300%

    DelivertrainingonKMStostaff&volunteers

    KMSprocesses andprotocols agreed.

    TransferinformationtotheMoorlandKMS

    DeviseMoorlandKnowledgeMan.System

    10wildlife groupsofferedmentoringtraining

    4wildlife surveys

    2Bioblitzevents

    24Identificationandsurveytrainingworkshops

    20school andcollegevisits

    2educationresources

    12familyecologydays

    12ecologyroadshows

    1cross-community conference

    2loans boxescreated

    6community heritageopendays

    10school visits; inc.summerfieldwork

    24volunteertrainingsessions

    2summerfieldwork sessions

    20visits tositesandmonuments

    250people attendingroadshows

    12roadshowsheld

    3exhibitions held

    Digitalarchivedeveloped

    30schools andcommunity groupvisits

    6reconstructions prepared

    ManagingExmoor's

    Moorla

    nd

    Know

    ledge

    NewEcologists

    CommunityArchaeology

    View

    softheM

    oor

    Proportionoftargetachieved

    300%

    850%

    700%

    350%

    Thefocus oftheprojectchanged(producing casestudies ratherthancataloguedrecords)andthesetargetswerenolongerappropriate

  • 20

    Programme2:ReconnectingLivelihoods3.22. Thesecondprogrammeinvolvedfourprojectsandaccountedfor23%

    oftheScheme’sprojectbudget(thesmallestofthethreeprogrammes).ThefourprojectsareshowninFigure3.5andlocationsofkeyactivitiesareshowninFigure3.6.

    3.23. AlloftheseprojectstookplaceinthefirstphaseoftheScheme(2011-2013)usingsignificantmatchedfundingfromtheRuralDevelopmentProgrammeforEngland(WesternSomersetLocalActionandLeader4TorridgeandNorthDevon).SeveralofthemcontinuedintoPhase2usingfundingfromPhase2projects.

    3.24. AlloftheprojectsinthisprogrammewereadministeredbytheSchemeManager.

    FIgure3.5.Projectsinthe‘ReconnectingLivelihoods’programme

    Project Objective Budget

    Moorkeepers Employinglocalpeopleaspart-time'moorkeepers'

    £65,800

    EmpoweringMoorlandManagers

    Helpingmoorlandmanagerstoworktogether

    £12,300

    MoorSkills Providingapprenticeshipsandatrainingprogramme

    £47,500

    DemonstrationMoors

    Runningaprogrammeofdemonstrationevents

    £10,800

    Figure3.6.Examplesof‘ReconnectingLivelihoods’projectlocations

  • 21

    Originalrationale

    3.25. TheLandscapeStrategyidentifiedthatthemoorlandhadbecomeeconomicallydisconnectedfrommostofthefarmsthatsurroundedit,makingitdifficulttoachievetherightlevelsoflivestockgrazingneededtomaintainthemoorlandheritage.TheresearchundertakentopreparefortheSchemehadidentifiedarangeofissuesandopportunities(Figure3.7).Toaddressthese,thePartnershipsoughttousethisProgrammetoworkwiththepeoplewhoearnalivingfrommoorlandto:• Conserveandcelebrateculturalassociationsandactivities;• Encouragemorepeopletoaccess,learnabout,becomeinvolved

    inandmakedecisionsontheirlandscapeheritage;and• Improveunderstandingoflocalcraftandotherskillsby

    providingtrainingopportunities.

    3.26. Theprincipaltargetaudienceforthisprogrammewastheownersandgraziersofmoorland.Partnersindeliveringtheprogrammeincludedlocalcollegesprovidingland-basedtrainingqualifications,theExmoorHillFarmingNetworkandtheNationalParkAuthority’srangerservice.

    Mainfocusofactivitiesandoutputs

    3.27. Alloftheprojectsinthisprogrammeweredirectedatprovidingmoorlandownersandmanagerswiththeknowledgeandskillstoundertakemoorlandmanagementpracticesthatbothmaintainedthemoorlandheritageandalsometpracticalfarmingrequirements.Incontrast,fundingofpracticalconservationworktookplaceinProgramme3.

    3.28. AsnotedinFigure3.7,keyissuesfacingmoorlandmanagerswerethelackoflabour,lackofskillsandlackofknowledge.Labourisaparticularconstrainttothepracticeofmoorlandswaling(controlledburningtostimulateregrowthofheather)becauseitcoincideswithlambingonfarms.Manymoorlandmanagersareover60andthere

    wasfelttobeaneedtopassonskillsandknowledgeofmoorlandlivestockmanagementtoyoungpeople.

    Figure3.7.IssuesandopportunitiesidentifiedpriortotheSchemethatthe‘ReconnectingLivelihoods’programmesoughttoaddress

    • Labouronfarmsislimitedandtodelivermoorlandmanagementistimeconsuming.(ConservationandRestorationPlan)

    • ThereisashortageofskilledwallersinNorthDevonwheremostofthewallsonExmoormoorlandarefound.(ConservationandRestorationPlan)

    • Noincentivesexisttoreplacefencesbyrebuildingwallsorstone-facedbanksasthedifferencebetweenthecostandthegrantaidistoogreat.(ConservationandRestorationPlan)

    • Knowledgeoftechniquesforrestorationofimprovedgrasslandtouplandheathlandislimited.(ConservationandRestorationPlan)

    • Thecessationorlimitedavailabilityoftrainingforyoungpeopleonland-basedmanagement.(TrainingPlan)

    • Barrierstotrainingbyfarmersincludethecostoftrainingincludinginsuranceandassessmentfees,thetimeawayfromthefarmincludingthecostofrelieflabour,andtheneedfortrainingtoberelevanttoeconomicandpracticalrealities.(TrainingPlan)

    3.29. Therewerealsoseentobeopportunitiestoenhanceknowledgeandexchangebestpracticebetweencurrentmoorlandmanagersandconservationbodies.Topicssuitableforthisknowledgeexchangeincludedthenumbersandtypesoflivestockbestsuitedtodifferentmoorlandareas,newmachineryavailabletocontrolscrubandequipmentneededtosafelyundertakemoorlandswaling.

    3.30. Asetoftargetsfortheoutputstobeachievedwasagreedforeachoftheprojects,involvingeitherthenumbersofpeoplewhowouldbeinvolvedorthenumbersofmeetingsoreventsthatwouldtakeplace.TheseareshowninFigure3.8.Thelargemajorityofthesetargets

  • 22

    wereachieved,withafewbeingachievedearlyintheprogrammeandgoingontobeexceededverysignificantly.

    3.31. Twooftheprojects–MoorkeepersandMoorSkills–involvedfocussedactivityonafewspecificindividuals.TheconceptofemployingMoorkeeperstogivefarmersdirectresponsibilityandresourcestoco-ordinategrazing,swaling,recreationalmanagementandenvironmentalmonitoringhadbeendiscussedonExmoorforseveraldecades.TheSchemeprovidedtheopportunitytotestanddeveloptheconceptwithfundingtoemploythreepart-timepostsonthreeareasofmoorland,initiallyduringPhase1butsubsequentlycontinuedinPhase2withfundingfromtheChangingMoorlandproject(are-instatedprojectinProgramme3).Thejobdescriptionforthemoorkeepersandtheirresponsibilitiesneededtobedefinedthroughdialoguewithmoorlandowners(distinguishingtherolefromNationalParkrangersandNationalTrustrangersforinstance)andthisprocesstooklongerthananticipated,leadingtoadelaytomakingtheappointments.Eventuallythreepeoplewereappointedononedayaweekcontracts:OneontheMineheadMoorlands(alocalfarmcontractor),MollandMoor(anexistinggrazingtenant)andHoldstoneDown(aNationalTrusttenantandco-owner).

    3.32. TheMoorkeeperpostswerealsosupportedfromtheprojectbythepurchaseofmachineryandequipmentthatwassharedbetweenthemsuchas‘brackenbruisers’,swalingequipment,personalprotectiveequipment(PPE)andherbicidesprayingequipment.

    Figure3.8.Achievementoftargetoutputs–Programme2:ReconnectingLivelihoods

    3.33. TheMoorSkillsprojectwasdesignedtoprovidethreeyoungpeople

    withapprenticeshipsinmoorlandmanagement(includingsupervisedfarmworkanddayreleaseclassroomtraining)leadingtoaqualificationthatwouldhelpthemgetsubsequentemployment.WestSomersetCollegeinMineheadagreedtohelpdevelopadistinctivemoorlandmanagementcurriculumandbetheaccreditedtrainingprovider,part-fundedbythescheme.However,thischangedwhenthethreestudentsidentifiedfortheapprenticeshipsmovedtoBridgwaterCollegeatCannington.OneofthestudentssubsequentlydroppedoutandwasreplacedbyastudentfromDevon.These

    0% 100% 200% 300%

    3eventsforstudents onlandmanagement

    3demonstrations bycontractors&equipmentmanufacturers

    18demonstration events

    20moorlandmanagersattendingtrainingonmoorlandmanagement

    12meetings(8moorlandmanagerspermeeting)

    30students developingmoorskills

    15Localmoorlandmanagerstoreceivetrainingtobe“MoorlandTutors”

    3local18-19yearolds receive18monthstraining

    20guidedwalksrunbyMoorkeepers

    6trainingdaysattendedbyMoorkeepersandMoorSkills apprentices

    3Moorkeepersemployed

    Demonstratio

    nMoors

    Empowering

    Moorla

    nd

    Managers

    MoorS

    kills

    Moorkeepers

    Proportionoftargetachieved

    1,667%

    3moorkeepers employed

    6trainingdaysattendedbymoorkeepers andmoorskills apprentices

    20guidedwalksrunbymoorkeepers

    3local18-19yearoldswillreceive18monthstrainingas“MoorKeepersApprentices”

    15LocalMoorlandManagerstoreceivetrainingtobe“MoorlandTutors”

    30students developingmoorskills

    12meetings(8MoorlandManagerspermeeting)

    20MoorlandManagersattendingtrainingonmoorlandmanagement

    18demonstration event

    3demonstrations bymoorland contractorsandmanufacturersofspecialist equipment

    3eventsforstudentsonlandmanagement

    Moorland

    managers

    viewinga

    demonstration

    ofabracken

    ‘biobaler’

    ©JasonPBall

  • 23

    changesrequiredconsiderableunexpectedworkbytheSchemeManager.

    3.34. AnothertargetoutputoftheMoorSkillsprojectwasprovidingon-sitetrainingforfarmstudentsonmoorlandmanagement.ThiswasdeliveredbythefarmunitatWestSomersetCollege.Againsttheoriginaltargetof30students,over500studentsreceivedthetraining.

    3.35. IthasbeenanticipatedthattherewouldbeastronglinkbetweentheMoorkeepersandMoorSkillsprojects,withtheMoorkeepersprovidingon-the-jobexperiencefortheapprentices.Althoughanumberoftrainingdaysdidtakeplace,meetingthetarget,thispartoftheMoorkeepers’rolewasnotfullydeveloped.

    3.36. TheexperienceoftheMoorSkillsprojectshowsthechallengesofarrangingday-releaseapprenticeshipsinremoteruralareaswhereissuesoftransportandthelimitedavailabilityofhostemployerscanbesignificantbarriers.Toacertaindegree,theprojectadaptedtothesechallengesbymovingfromprovidinghighlevelsoftrainingtoafewstudentstolowerlevelsoftrainingtomanymorestudents.

    3.37. AnoverallaspirationfortheMoorSkillsprojecthadbeentocreateaself-sustainingprogrammeofmoorlandtrainingatWestSomersetCollege,withinitialpumpprimingbytheprojecttodevelopthecurriculumbeingmaintainedbystudents’tuitionpayments.However,themomentumofmoorlandtraininghasnotbeenmaintainedbythecollegeandtheprogrammehasceased.

    3.38. Theothertwoprojectsinthisprogramme–EmpoweringMoorlandManagersandDemonstrationMoors–tookplacethroughthefacilitationofmeetingsandeventsinvolvingmoorlandowners,managersandenvironmentalbodiessuchasNaturalEngland.Inpractice,therefewdifferencesbetweentheactivitiesofthetwoprojects,sothateventsorganisedunderoneprojecttendedtocontributetooutputtargetsintheother.Examplesincluded:

    • AworkshoponscrubmanagementonBrendonCommonorganisedbytheBrendonCommonersAssociation

    • AdemonstrationofswalingequipmentandtechniquesonNorthHill,publicisedbytheExmoorHillFarmingNetwork

    • Annualmeetingstomonitorprogressandplanformoorlandswaling,organisedbytheNationalParkAuthority

    • AmeetingtoreviewevidenceondifferentgrazingregimesonMollandMoororganisedbytheGrazetheMoorProject

    3.39. Lesssuccessfulaspectsoftheprogrammeweretheattemptstoencouragemoorlandownersandgrazierstointeractmorewiththepublic,leadingguidedwalksandactingas‘moorlandtutors’.Mostmoorlandownersandgraziersdon’tseethisastheirrole,beinghappytoleaveittotheNationalParkrangersandNationalTrustwardensandorganisationssuchastheExmoorSociety.Asaresultthetargetoutputof15moorlandmanagersreceivingtrainingtobe‘moorlandtutors’wasnotmet.

    FarmersandothershearingaboutthearchaeologyofBrendonCommon©JasonPBall

  • 24

    Programme3:ReconditioningMoorlandCharacter3.40. Thefinalprogrammeinvolvedfourprojectsandaccountedfor36%of

    theScheme’sprojectbudget.TheseprojectsareshowninFigure3.9andlocationsofkeyactivitiesareshowninFigure3.10.

    3.41. ThefirstthreeprojectstookplaceinPhase1oftheSchemeandthefourth,TheChangingMoorland,wasaddedinPhase2.TheseprojectswereadministeredbytheSchemeManager(thefirst,thirdandfourthprojectsinFigure3.9)andtheMoorlandHeritageOfficer(thesecond).

    Figure3.9.Projectsinthe‘ReconditioningMoorlandCharacter’programme

    Project Objective Budget

    ReconditioningMoorlandCharacter

    Restorationoflandscapesandheritagelandmarks

    £100,000

    ConservingtheMoorlandPast

    Fundingconservationworkatmoorlandarchaeologicalsites

    £32,500

    PromotingExmoorPonies

    Helpingponyownerssupportthebreed

    £48,400

    TheChangingMoorland

    Undertakingconservationworkonmoorlandwherechangeisoccurring

    £32,350

    Figure3.10.Examplesof‘ReconditioningMoorlandCharacter’projectlocations

  • 25

    Originalrationale

    3.42. TheLandscapeStrategypublishedinSeptember2007summarisedthepurposeofthisprogrammeas“tobringExmoor’smoorlandsintomorefavourablecondition–recreating‘showroomcondition’and

    makingitfitterforpurpose”.Itdistinguishedreconditioningexistingareasofmoorlandfromtherestorationofformermoorland.Althoughitmadeclearthatlargescalemoorlandrestorationwasnotanobjectiveofthescheme,itdidsetoutanobjectiveto‘roughenup’thelandscapecharacteroffarmlandsurroundingmoorlandtoprovidehabitatandvisuallinksbetweenmoorland.

    3.43. TheissuesandopportunitiesthathadbeenidentifiedduringtheresearchpriortodevelopingtheschemearesummarisedinFigure3.11.Aswellastheseissues,thisprogrammealsorespondedtomanyoftheissuesidentifiedintheothertwoprogrammes.

    Figure3.11.IssuesandopportunitiesidentifiedpriortotheSchemethatthe‘ReconditioningMoorlandCharacter’programmesoughttoaddress

    • Therearecurrentlynofundingstreamsavailableforprojectswherevisualimprovementofthelandscapeinordertoenhancepublicenjoymentistheoverridingaim.(ConservationandRestorationPlan)

    • Thereisashortageoffundingforculturalheritageconservationwork

    • ThereisnomarketforyoungExmoorponiessolittleincentivetokeepthem

    3.44. TheoriginalproposalfortheschemesubmittedtoHLFin2007andapprovedforfundinginApril2008containedsixprojectsbutthreeofthesewereomittedfromtheschemewaswasstartedin2011.Thesethreeomittedprojectsinvolvedmappingtranquillityonmoorland,theestablishmentofnaturallinksonfarmlandbetweenmoorlandblocksanddevisingandevaluatingmoorlandrestorationtechniques.Thedecisiontodroptheseprojectswaspartlyduetocost,partlyduetoanassessmentofalternativewaysofdeliveringthem(thenatural

    linksprojectpotentiallybeingdeliverablethroughagri-environmentschemefunding)andpartlyduetoanassessmentofpriorities(leadingtotheomissionofthetranquillitymappingproject).

    3.45. TheopportunitytoreinstateprojectsinthesecondphaseoftheschemeledtotheChangingMoorlandprojectbeingincluded.Thistooksomeofitsinspirationfromtheoriginalideatoexaminemoorlandrestorationtechniques(butfocussingmoreonaddressingchangingconditionsonmoorland)andalsoallowedcontinuedfundingtosuccessfulprojectsfromPhase1suchasMoorkeepers.

    3.46. Thetargetaudiencesforthisprogrammewerewide,includingmoorlandownersandgraziersandthecommunitieswithinthedefinedlandscapepartnershiparea.ThekeypartnersinvolvedindeliveringthefourprojectsincludedtheNationalParkAuthority,theMoorlandMousieTrust(whichemployedtheExmoorPonyOfficer),ExmoorPonySociety,theExmoorSocietyandLyntonandLynmouthTownCouncil(thelattertwocontributingsignificantmatchedfundingforpartsoftheReconditioningMoorlandCharacterproject).

    Mainfocusofactivitiesandoutputs

    3.47. Thisprogrammeisdifferentfromtheothersinthatitprovidedtheresourcestomakephysicalimprovementstomoorlandandtoconserveimportantheritagefeaturesofthemoorland(suchastheExmoorponyherds).LikeProgramme1italsoprovidedwaysofpromotingbetterpublicunderstandingof,andinvolvementin,theseactivities.ItalsoincludedelementsofProgramme2incloseworkingwithmoorlandownersandgraziers.

    3.48. Aswiththeotherprogrammes,anumberofoutputtargetswereagreedsothatprogressoftheprojectscouldbemonitored.Theseincludedthenumberofsitesandfeaturesonwhichreconditioningworkhadtakenplace,thenumberofpeopleinvolvedinconservation,monitoringortrainingandthenumberofmeetingsandothereventsheld.ThesetargetsandtheirachievementareshowninFigure3.12.

  • 26

    Figure3.12.Achievementoftargetoutputs–Programme3:ReconditioningMoorlandCharacter

    3.49. Eachofthefourprojectsinthisprogrammeaddressedadifferentaspectofmoorlandreconditioning.TheReconditioningMoorlandCharacterprojectsupportedconservationworkthroughfivemajorprojects(below)andprovidedsmallergrantstomoorlandownerstoenhancethelandscape.Thesesmallergrants,typicallyofbetween£1,000and£5,000each,coveredactivitiessuchashedgebankrepairalonghistoricallysignificantmoorlandboundariesandfencingofhighbiodiversityvaluegrasslandtofacilitategrazing.

    3.50. Thefivemajorlandscapereconditioningprojectswereasfollows:

    • TheundergroundingofelectricitypowerlinesatHawkcombeHead,removingamajorvisualintrusioninthelandscape.ThemaincapitalfundingcamefromWesternPowerandtheschemeprovidedfundingtoenhancethequalityofthenecessaryarchaeologicalsurveyingandmitigationwork

    • ThereplacementoftheroofanddoorstotheWorldWarIIRadarStationonNorthHill.ThisprovidedthesettingforaWWIIinterpretiveexhibitionwithcostumedre-enactors

    • TheconsolidationandconservationofHoarOakCottage,anabandonedhouseinaremotemoorlandlocation.TheprojectwasundertakenwiththeFriendsofHoarOakCottage,communityactiongroupExmoorUprisingandtheExmoorSociety

    • TheredesignandlandscapingofthecarparkattheValleyofRocks.Thepreviouscarparkingwaspoorlydesignedandvisuallyintrusiveinthispopularvisitordestination.ThecostwassharedbetweenLyntonandLynmouthTownCouncil,theExmoorPartnershipFundandtheScheme

    • TheundergroundingofpowerandtelecomscablesattheValleyofRocks

    3.51. AsignificantproportionofthefundingforthisprojectcamefromtheHeathcoatandAmoryTruststhroughtheExmoorSociety.

    0% 50% 100% 150% 200%

    40people benefitfrompracticalmoorlandskillstraining

    40people involved inthemoorlandmanagementchallenges

    3moorlandmanagementchallenges

    6practicalmoorlandmanagementdemonstrations

    8farmer-ledactivities/workshops

    10practicaltrainingsessions

    20practicalconservationsessions

    20MoorlandUnitmeetings

    15events/fetesattended

    2newherdscreated

    2herdssafeguarded

    30Exmoorponydays

    30primaryschool visited

    8landowners engagedinmonitoringandconserving activities

    20volunteers involvedinmonitoringandconserving activities

    10additional featuresareidentified andimpactsmitigated

    3prioritysitesrestoredTheChangingM

    oorla

    ndProm

    otingExmoorP

    onies

    Conservin

    gthe

    Moorla

    ndPast

    Reconditioning

    Moorla

    nd

    Character

    Proportionoftargetachieved

    443%

    3prioritysitesrestored

    10additional featuresorelementsareidentified andtheimpactmitigated

    20volunteers involved inmonitoring andconserving activities

    8landowners engagedinmonitoringandconserving activities

    40people involved inthemoorlandmanagementchallenges

    40people benefitfrompracticalmoorlandskills training

    Involvingsurveyand interviews

    465%

  • 27

    3.52. TheConservingtheMoorlandPastprojectsoughttoaddressthreatstoScheduledAncientMonumentsandotherarchaeologicalsitesonmoorland.Itincludedfourelements:

    • PracticalconservationworkwasundertakenbyspecialistcontractorsonScheduledMonuments(suchasthesprayingofbrackentopreventrootdamagetoburiedstructures)andusedfundingfromEnglishHeritage’sMonumentManagementSchemewhichhadbeendelegatedtotheNationalParkAuthority.Thisworkwouldhavebeenundertakenanyway.

    • Geophysicalsurveyswereundertaken(byspecialistcontractorswhoweresupportedbyvolunteers)onthreePrincipalArchaeologicalLandscapesonmoorland:PorlockAllotments,CheritonRidgeandBradimoor.Thesesurveysleadtonewdiscoveriessuchasamedievalsettlementandhavebeenwrittenupandpublished.

    • Archaeologicalsurveysandreportswerecommissionedandpublishedcoveringvalleymires,theSimonsbathtower,theHoaroakcottage/sheepfold,peatcuttingonPorlockAllotmentandtheNorthHillRadarStation.

    • TheconservationofthedoorsonWWIINorthHillRadarStation.

    3.53. ExmoorPonieshaveaspecialplaceonExmoor,the21free-livingherdsonmoorlandbeingpopularattractionswithlocalpeopleandvisitors.Theyalsohavedistinctiveandancientgeneticcharacteristicsandcontinuetobevaluablemoorlandgrazinganimals.ThePromotingExmoorPoniesprojectsoughttocelebrateandimproveunderstandingofthisculturalimportanceandsecuretheirfuturebyholdingpubliceventsandworkingwithherdowners.Itemployedapart-timeExmoorPonyOfficer,hostedbytheMoorlandMousieTrustwhichisalocalcharitythatrunstheExmoorPonyCentre.

    3.54. TheprojectfacedsignificantbarriersasaresultoffrictionsbetweenindividualsandorganisationsthatsupportExmoorPoniesaswellascontroversyoverclaimsofthepony’sgeneticorigins.Diplomacywasrequiredtoaddressthesebeforetheaimsoftheprojectcouldbe

    addressed.Dialoguebetweenorganisations,facilitatedbytheExmoorPonyOfficerandSchemeManager,wassuccessfulinachievingjointworkingbetweentheMoorlandMousieTrustandExmoorPonySociety,leadingdirectlytotheExmoorPonyFestivalheldin2012.TheFestivalhasbeenrepeatedannuallysincethenwithagrowingattendance(3,000peopletookpartinninedaysofeventsin2014).TheFestivalin2015wasrunbythenewlyformedExmoorPonyFestivalTrust.ArangeofotherschoolvisitsandpubliceventstopromotethebreedtookplaceinPhase1oftheScheme.

    3.55. Aseparatestrandoftheprojectinvolvedworkingwithherdownerstosupporttheconservationofthebreed.Areportwascommissionedfromlocalvet,PeterGreen,intothepracticalissuesfacingfree-livingponies.Thereportprovedcontroversialamongstsomepeoplebecauseitreviewedstudiesonthegeneticstatusofthebreedbutithassupportedjointworkingbetweenherdowners(anewrepresentativegrouphassubsequentlybeenestablishedandtwonewherdshavebeenregisteredwiththeExmoorPonySociety).

    3.56. TheoriginalSchemesubmittedto,andapprovedby,HLFin2008hadinvolvedthreelargeprojectsthatsoughttoaddressthelandscape-scalethreatsandopportunitiesonmoorland.ThereviewoftheSchemeundertakenin2009/10haddroppedtheseprojectsbecauseoftheircostandtheavailabilityofalternativefundingfromagri-environmentschemes(seebelow).However,whentheLandscapePartnershipsubmittedaproposalforPhase2oftheSchemein2013,elementsoftheoriginalthreeprojectswereincludedinanewChangingMoorlandproject.Thisfocussedonareasofmoorlandthatwerefacingsignificantenvironmentalthreats(suchasencroachmentofscrub)oropportunities(suchastherewettingofmirehabitats).

    3.57. Theprojectincludedareviewoftheissuesaffectingallareasofmoorlandbasedonthedescriptionsforthe20MoorlandUnitsthathadbeenpreparedbytheNationalParkAuthorityin2011.ThereviewwasoriginallyintendedtobedonethroughmeetingswithmoorlandownersandgraziersineachoftheUnits.Howeverlowattendanceatthesemeetingsmeantthatanonline/papersurvey

  • 28

    wasusedtocollectinformationbackedupbytelephonecalls.TheresultsofthereviewhavebeenpassedtotheAuthority.

    3.58. Theprojectalsoinvolvedsupportingpartnersbyaddingvaluetoexistingactivities,suchas:

    • TheMoorlandBirdSurveyundertakenbytheRSPB(helpingtopayforequipmentanddisseminationoftheresults)

    • Conservationworkontheheathland/woodlandinterfaceonGrabbistHillledbytheNationalTrustandCrownEstate(payingformeetingandtrainingtoreviewchange)

    • ControlofinvasivescrubintheHeddonValleybytheNationalTrust(supportingtraining,providingequipmentandfacilitatingco-ordinationwithneighbouringlandowners)

    WhatwasnotcoveredbytheScheme3.59. Therewereanumberoftopicsthatmighthavebeenincludedinthe

    Scheme’sactivitiesbutwereeitherdeliberatelyexcludedorwerelessevidentthanhadoriginallybeenintended.Thereasonsbehindthesegapsinprojectactivityareexaminedingreaterdetailinthefollowingchapter.Insummary,thesegapswereasfollows:

    Landscape-scaleenhancement

    3.60. Oneofthethreefacetsofthemoorland’sdisconnectionthathadbeenidentifiedbythepreparatoryresearchwasthephysicalseparationbetweenmanyofthemoorlandblocksandthesharplandscapeandecologicalboundarythatoccurredwheremoorlandabuttedfarmland.However,thethreeprojectsthatweredesignedtoaddresstheseissuesweredroppedfromtheSchemewhenitwasreviewedin2008.Thereasonsbehindthisareexaminedinthefollowingchapter(Figure4.2).

    Livingculture

    3.61. Theculturaldisconnectionidentifiedinthepreparatoryresearchdrewattentiontothedeclininglocaltraditionsofmoorlandusebylocalcommunities.However,therewasrelativelylittleactivityonthesetopicscomparedtothegreateremphasisonunderstandingthemoorland’sprehistory(anexceptionbeingthephotographiccompetitionincludedintheViewsoftheMoorproject).Thereasonsbehindthisareconsideredinthefollowingchapter(Figure4.7).

    Theheritageeconomy

    3.62. Finally,theSchemehadrelativelylittleinteractionwiththebusinessesthattakeadvantageofthemoorland’sheritagesuchasthetourism,hospitality,recreationandspecialityfoodssectors.Thereasonsbehindthisareexaminedinthefollowingchapter(Figure4.9).

    TheExmoorPonyOfficerandchildrenattheGetWildonGrabbistevent©JasonPBall

  • 29

    OverallfindingsontheScheme’soutputs3.63. Overitsfiveyearsofactivity,theSchemehasdeliveredabroadrange

    ofactivitiesacrossitsthreeprogrammesand19projects.ThelargemajorityofthetargetoutputsthatweresetbytheLandscapePartnershipandHLFweremetandmanywereexceededbyalargemargin.SomeoftheheadlinefiguresontheoutputsachievedbytheSchemearelistedinFigure3.13.

    Figure3.13.HeadlineresultsofSchemeactivity

    • Morethan7,000schoolchildrenvisitedmoorlandwiththeirteacherslearningaboutitsheritagethroughitshistory,science,geographyandothersubjects

    • 4,350peopleattendedeventscelebratingExmoor’smoorlandwildlifeincludingattheannualBogstaticfestivalandaseriesofBigAdventureDays

    • Over3,000peopletookpartinninedaysofeventsinthe2014ExmoorPonyFestival

    • Over900peopleattended17communityarchaeologyevents,seeingfirsthandtheevidenceofprehistoricusesofmoorland

    • Over120peopleofallagestookuptrowelsorsurveytapestoundertakearchaeologicalexcavationsorsurveysonmoorland

    • Morethan500agriculturalstudentsandmoorlandmanagersreceivedtrainingonmoorlandmanagement

    • AlargeproportionofExmoor’smoorlandownersandgrazierssharedtheirknowledgeofmoorlandmanagementwitheachother

    • Overall,volunteerscommittedmorethan5,000daystocelebratingorconservingExmoor’smoorlandheritage

    3.64. ThemostsuccessfulelementsoftheSchemewerethoseinvolvingpeoplewhowerenotpreviouslyfamiliarwithmoorlandheritage,manyfromlocalcommunities,inactivelearningabout,andcelebratingin,thehistory,landscapeandwildlifeofExmoor’smoorland.

    3.65. InnovativeapproachesthatweredevelopedduringtheScheme(andwereoftennotplannedfromtheoutset)includedtheuseofvideos,digitalreconstructionimagery,historicalre-enactments,publicarchaeologyprojects,archaeologyloanboxesandweb-basededucationalresources.ThesegavethewholeSchemeafreshnessandenergythatmarkeditoutfrompreviousactivitiesonmoorland.

    3.66. Activitiesthatwerelesssuccessfulthananticipatedwerethosethatencouragedmoorlandmanagerstoengagemorewiththepublic(asleadersofwalksoras‘moorlandtutors’)ortoreviewtheissuesfacingtheirareasofmoorland(withpoorattendanceatmeetings).

    3.67. ActivitieswhichwerenotablebytheirabsencefromtheSchemewerecelebrationsofthelivingculturalassociatedwithmoorland;largescaleenhancementofhabitatsorlandscapecharacter;andanysignificantlevelsofengagementwithtourismandrecreationbusinesses.

  • 30

    4. Outcomesandimpacts

    4.1. AssetoutinChapter3,thelargemajorityofthequantifiabletargetoutputsforeachofthe19projectshavebeensuccessfullymetorexceeded.Whilstthesetargetoutputshavebeenhelpfulasawayofmonitoringprogress,theyareonlypartofthepictureandarenotnecessarilythebestwayofmeasuringtheoverallbenefitsoftheprogrammesorSchemeasawhole.

    4.2. ThemostimportantresultiswhetherachievingthesetargetoutputshasledtosuccessfulSchemeoutcomesandinturnhadanimpactontheissuesthattheSchemewasdesignedtoaddressinthefirstplace.

    4.3. TheHLFEvaluationGuidance(2014)statesthat:“OutcomesarethedifferenceyourSchemehasmade;itsimpactsonthelandscapeand

    heritagefeatures,anditsbenefitsforthepeoplewholiveorwork

    thereorenjoyitasvisitors.”

    4.4. WhentheSchemewasapproved,LandscapePartnershipSchemeswererequiredtoaddressfouroutcomes.Thesewere:

    • Conservingorrestoringthebuiltheritageandnaturalfeaturesthatcreatethehistoriccharacterofthelandscape;

    • Conservingandcelebratingtheculturalassociationsandactivitiesofthelandscapearea;

    • Encouragingmorepeopletoaccess,learnabout,becomeinvolvedinandmakedecisionsontheirlandscapeheritage;

    • Improvingunderstandingoflocalcraftandotherskillsbyprovidingtrainingopportunities.

    4.5. InthisChapter,theseoutcomesaretakeninturnandanassessmentismadeofwhethertheSchemehassuccessfullyachievedthemandaddressedtheissuesidentifiedwhentheSchemewassetup.Aseriesofchartsshowtheviewsofprojectpartnerswhorespondedtotheonlinesurveyundertakenforthisevaluation.

    Attributingprojectsandactivitiestothefouroutcomes

    4.6. TheLandscapeStrategypreparedin2008showedhoweachoftheprojectsinPhase1oftheSchemehelpedtodeliverthefouroutcomesandthisprocesswasrepeatedforthePhase2projectsinthebiddocumentpreparedfortheHLFinMay2013.ThisisshownbytheticksinFigure4.1(ticksinbracketsshowingpartialdeliveryofthatoutcome).Thecolouredfillshowstheprimaryoutcome(s)foreachproject,asselectedbythisevaluation.

    Figure4.1.MatchingprojectswithHLFoutcomes

  • 31

    4.7. Figure4.1showsthatalloftheprojectsaimedtoaddressmorethanoneoutcome(manysoughttoaddressthreeandsomefouroutcomes).Variousprojectsoftencontributeddifferentelementstothesamesite-basedinitiativeortoworkundertakenbypartners(forinstancesupporttomoorlandownersandgrazierstookplacethroughseveralprojectsinProgrammes2and3).ThismeantthatthestructureoftheSchemewasrelativelycomplexwithahighlevelofintegration(whichcanberegardedasapositivething)butwithariskofduplicationanddoublecounting(whichisnot).

    4.8. AbroaderpatternisevidentfromFigure4.1,suggestingthattheReconnectingPeopleprogrammesoughtparticularlytoaddressthesecondandthirdHLFoutcomeswhereastheReconnectingLivelihoodsprogrammefocussedonthefourthHLFoutcomeandtheReconditioningProgrammefocussedonthefirstHLFoutcome.

    Digitalreconstruction,imagining

    thestonesettingatLanacombe

    (nowopenmoorland)duringthe

    lateNeolithic/earlyBronzeage,

    preparedfortheScheme

    ©PeterLorimer

  • 32

    Conservingorrestoringthebuiltheritageandnaturalfeatures

    Theissuesthatneededtobeaddressed

    4.10. ThisoutcomeaddressestheconditionofExmoor’smoorlandheritage,coveringboththenaturalheritage(e.g.landscapecharacter,biodiversityandnaturalresources)andarchaeologicalheritage(e.g.buildings,boundaries,man-madelandformsandthehistoriclandscapeasawhole).Itfocussesmainlyonimprovingthephysicalstatusofthisheritagebutalsoincludesresearchandmonitoringinformationsupportingitsconservation.

    4.11. ThereweretwomainissuesfacingthisoutcomeatthestartoftheScheme.Firstlymoorlandmanagementwasconstrainedbypoorcommunicationbetweenfarmersandconservationbodiesandbyalackofmanpowerandskills.Andsecondly,protectionofmoorlandarchaeologyandthehistoriclandscapewasconstrainedbylimitedknowledgeofwhatwasthereandbyissuesaffectingmoorlandmanagement.

    4.12. ThisoutcomeandtheseissueswereatthecentreofalloffourprojectsintheReconditioningMoorlandsprogrammesandwerealsoaddressedbytheMoorkeepersprojectintheReconnectingLivelihoodsprogrammeandtheCommunityArchaeologyprojectintheReconnectingPeopleprogramme(andotherstoalesserextentasshownbyticksinFigure4.1).

    Whatwasachieved

    4.13. ThechangestothephysicalconditionofExmoor’smoorlandheritagebroughtaboutbytheSchemearelimited.OverthelargemajorityofthemoorlandareaitwouldbedifficulttoidentifyanyphysicalchangesinthelandscapeorhabitatsthatweretheresultoftheScheme.Thereareseveralreasonsforthis.

    • Firstly,theissuesfacingagriculturalmanagementbygrazingandswaling(controlledheatherburning)aredeep-seatedeconomic

    issueswhichaSchemelastingfouryearswasneverlikelytobeabletosolve(andwhichtheSchemeneverclaimedtodo).

    • Secondly,thedecisiontodropthreelargeprojectsfromtheReconditioningProgrammewhentheSchemewasreviewedin2009/10meantthattheresourcesavailabletotheSchemeinthisareawererelativelysmall(seeFigure4.2).

    • Thirdly(andlinkedtothedecisiontodroptheprojectsfromtheScheme),otherlargerandlonger-standingpolicyinterventionssuchasSSSIdesignationsandagri-environmentschemesaremuchmoresignificantinfluencesontheconditionofnaturalheritage.

    • Finally,intheperiodbetweenthepreparationoftheLandscapeStrategyin2008andthestartoftheSchemein2011,significantprogresshadbeenmadeinimprovingdialoguewithfarmersonExmoorthroughtheExmoorHillFarmProject(latterlytheHillFarmingNetwork)andtheworkoftheMoorlandInitiativeBoard.Thismeantthatimprovedcommunicationwasalreadytakingplace,leavinglessfortheSchemetodo.

    Controllingtrafficduringmoorlandswaling©JasonPBall

  • 33

    Figure4.2.ImpactoftheSchemeonlandscape-scaleenhancement

    Oneofthethreefacetsofthemoorland’sdisconnectionthathadbeenidentifiedbythepreparatoryresearchandwhichformedastrandintheLandscapeStrategywasthephysicalseparationbetweenmanyofthemoorlandblocksandthesharplandscapeandecologicalboundarythatoccurredwheremoorlandabutt