final 3 n 4
-
Upload
sudip-pyakurel -
Category
Documents
-
view
218 -
download
0
Transcript of final 3 n 4
-
8/7/2019 final 3 n 4
1/15
Lab No. 3
Generator:
Almost all the hydraulic turbine-driven generators used are synchronous alternatingcurrent machines, which produce electrical energy by the transformation of the rotational
mechanical energy. The electrical and mechanical design of each generator must confirm
to the electrical requirements of the power distribution system to which it will be
connected, and also to the hydraulic requirements of its specific plant. The electrical
characteristics of the generator used in our design are:
SN. Specifications Ratings
1 MVA 7.2
2 KV 11
3 Phase 3
4 Frequency 505 Power Factor 0.85
6 No. of Poles 18
7. RPM 333
Generator excitation system:
Brushless excitation system was used for the excitation of the generator as it is
the best excitation system for medium sized power plant due to the absence of carbon
brushes, brushless system requires less maintaince and its outage time is less.
Generator neutral grounding:We preferred to select the resistance grounding method . Its value is selected such
that the value of Xcg >> Rn or Xcg/Rn>>1. Since the value of resistance was very
high, the distribution transformer method for generator neutral grounding was done.
-
8/7/2019 final 3 n 4
2/15
Low voltage busbars:
We employed 11 KV medium voltage single bus bar arrangement and unit
Generator Transformer Scheme was used. Unit Generator scheme is a conventional
scheme preferred for medium sized power plants in a small power system where the plant
size is significant for the system. With the use of individual transformer for each
generator unit, unit protection of generator and transformer becomes easy. Overall
protection system becomes simple and easy to locate the faults.
High voltage busbars (66 kv):
We have chosen the Modified Main And Transfer Bus scheme considering its
reliability, flexibility, availability in operation and protection simplicity.
This type of scheme has many advantages as follows:
Flexible operation Load can be shifted to any bus during maintaince of other bus.
Periodic Maintence of breaker can be done without interrupting the powersupply.
Breakers:
The circuit breakers are used to protect the equipment during the fault condition.
The rated voltage and the breaking current are the parameter that calls for the desired
circuit breaker to be used in the protective scheme of an electrical system. We have used
the vaccum circuit breakers as the generator breakers (synchronizing breaker), SF6 circuit
breakers at the HV side and ACB at the station transformer side. A VCB breaker suffers
from the current chopping phenomenon. So to avoid this we have used the surge arrestor
in parallel with each of its phases.
Transformer:
We have used 3 phase delta / star transformer to step up the voltage from 11 kv to
transmission line voltage i.e. 66 KV. The MVA capacity of the transformer is 7 MVA.
Station transformer of 11/ 0.4 KV delta /star is used to supply power for the auxillaries.
-
8/7/2019 final 3 n 4
3/15
Calculation of resistance grounding
Generator : MVA rating =7.2 MVA, 11KV, 0.85 pf, 377.9 A
Capacitance of terminals of generator with respect to ground Co= 0.135 F for 11 KV
level.
Capacitance of surge capacitance = 0.25 F
Other capacitances are negligible.
Cg = 3(C0 + Cs) = 1.155 F
Xcg =#
$@/A= 2756 = Rn
The value of Rn is in range of high resistance , hence distribution transformer is selected.
A distribution transformer of ratio 11/ % is selected.
Transformation ratio = 13.23
A neutral resistor to be inserted in secondary is
Rn= Rn/n
2= 15.74
Rating of Distribution transformer
The fault current that flows in secondary resistor is
Isec(max)= Vsec(max)/ Rsec = 480/15.74 = 30.5 A
The thermal rating of the transformer should be
KVA = Esec rated * Isec max = 14.6 KVA
Hence,
Dry type transformer = 15 KVA, 11/ %
-
8/7/2019 final 3 n 4
4/15
Lab No. 4
Type Of Transmission Line Circuit
In our Scheme we used the double Transmission line circuit for the power evacuation.
From the standard table of ACSR conductors,The current carrying capacity of the line is 430 A at 20
0C. For reliable operation
and for maintenance purpose, we used parallel feeders and each feeder is capable of
carrying full load current which is 115 A. Also while using double circuit the capacity to
evacuate the power increases.
Line current =#&"
$#"
High Voltage Bus Bar Scheme Selection:We have chosen the Modified Main And Transfer Bus scheme considering its
reliability, flexibility, availability in operation and protection simplicity.
This type of scheme has many advantages as follows:
Flexible operation
Load can be shifted to any bus during maintaince of other bus.
Periodic Maintence of breaker can be done without interrupting the powersupply.
Fig: Modified Main and Transfer Bus
-
8/7/2019 final 3 n 4
5/15
Modes of Operation:Normal operation ( Main Bus Operation) :
For maintenance of circuit breaker 1 - :
-
8/7/2019 final 3 n 4
6/15
Fault occurring at Main Bus:
Calculation of Fault current and Fault MVA level
The fault occurs at various points as shown in the figure:
Fig: 1
For the generator capacity of 7.2 MVA and synchronous speed 333 RPM the per unit sub-
transient reactance of the generator selected from the graph below is 22.5%.
-
8/7/2019 final 3 n 4
7/15
Generator Sub-Transie
Similarly for the transforme
transformer impedance is sel
Transformer Impedanc
t Reactance
r capacity of 8MVA and high voltage windi
cted from the table below as 9.87%.
e
g 33KV the
-
8/7/2019 final 3 n 4
8/15
With reference to, ACSR conductor table, for Bear conductors, the line reactance is taken
to be 0.220 /km.
Length of the line =50km
Total reactance of the line= 0.220 /km * 50km = 11
Now, we take,
Base KV (on LV side of transformer) =11 KV
Base KV (on HV side of transformer) =72 KV
Base MVA = 7.2 MVA
Base reactance (on LV side) = (base kv)2/ base MVA = (11 2 / 7.2)
= 16.8
Base reactance (on HV side) = (base kv) 2/ base MVA = (72 2 / 7.2)
= 720
Base Current =$#"
###"= 377.9 A
PU reactance of Transmission line =##
$"= 0.01563 pu
PU reactance of Transformer (PU new ) = PU old *(Base KV old /Base KV new )2
*(Base MVA new /Base MVA
old )
=0.096*(11/11) 2 *(7.2/7) =0.0987 pu
Now,
Xpu (generator) =0.225pu
Xpu (Transformer) =0.0987pu
Xpu (line) =0.01563pu
-
8/7/2019 final 3 n 4
9/15
Calculations of Fault at different positions:
Fault at position 1:
1
IJ { - % -
-
- %
=0.10633
I fault (pu) =#"
"#"= 9.403 pu
Ifault
(actual) = Ifault
(pu) * Base Current = 9.403 * 377.9 A
= 3554 A
Fault MVA = Base MVA / (X pu ) eq =67.713 MVA
Fault at position 2:
L VH V
(Xpu
)eq
= 0.225 pu
I fault (pu) = 1
-
8/7/2019 final 3 n 4
10/15
Fault at Position 3:
3
IJ
{ - % -
-
=0.00763
Ipu =#
"""= 131.04A
Iact = 131.04 * 57.73
= 7565.40 A
Fault MVA = Base MVA / (Xpu
)eq
=943.64 MVA
Fault at Position 4:
L V H V
4
Xpu = 0.225 + 0.0.0987 = 0.3237 pu
Ipu =#
"$
% pu
Iact = 3.089 * 57.73 A =178.34 A
Fault MVA = Base MVA / (X pu ) eq=22.24 MVA
0.225 0.09870.021
0.021
0.225 0.0987
-
8/7/2019 final 3 n 4
11/15
Fault at Position 5:
c b 55
Xpu = 0.01563 pu
Ipu =#
""#' pu
Iact = 63.97 * 57.73 = 3693.5 A
Fault MVA = Base MVA / (X pu ) eq=46.065 MVA
Fault at Position 6:
c b 56
Xpu =#
!
!
\a
Ipu =#
""#&$' \a
Iact = 70.15 * 57.73 = 4049.76 A
Fault MVA = Base MVA / (Xpu
)eq
=505.263 MVA
0.021
0.0210.0987
0.0987
0.225
0.225
-
8/7/2019 final 3 n 4
12/15
Ratings Of Circuit Breakers:
CB Rate
Volt
KV
Rated
insulaton
level KV
Freq
uency
Normal
Current
A
Breaking
Current
KA
Making
Current
KA
Short time
Rating
Current
Rated
Impulse
Current
1 12 60 50 400 8 20.4 8 20.4
2 72.5 325 50 800 12.5 31.875 12.5 31.875
3 72.5 325 50 800 12.5 31.875 12.5 31.875
4 12 60 50 400 8 20.4 8 20.4
5 72.5 325 50 800 12.5 31.875 12.5 31.875
6 72.5 325 50 800 12.5 31.875 12.5 31.875
7 72.5 325 50 800 12.5 31.875 12.5 31.875
8 0.6 325 50 800 12.5 31.875 12.5 31.875
9 0.6 325 50 800 12.5 31.875 12.5 31.875
10 72.5 325 50 800 12.5 31.875 12.5 31.875
Conclusion
Hence by the end of the report we designed the 12 MW DhuncheHydropower Project on the basis of Medium Hydropower Project (NEA 1997)Method. In this report we also calculated the catchments area, head, thedischarge and output of the plant. This report also include turbine selection on thebasis of various criteria ,SLD using different bus bar ,neural grounding , excitationschemes used in various power plants existing in Nepal. Report include faultcurrent calculation at different bus bar and circuit breaker ratings.
-
8/7/2019 final 3 n 4
13/15
The Table for the proper selection of breaker is shown below
-
8/7/2019 final 3 n 4
14/15
ACSR CONDUCTOR IS : 398 [PART-II
Code Name
Resistance
At 20oC
Tensile
StrengthOverall
Diameter
Current Rating Inductive Reactance
Calculated
Breaking LoadIn Still Air With Wind 30 MM 50 MM
Ohm/km N/mm2 Mm A A Spacing Spacing
MOLE 2.718 407 4.50 40 70 0.352 0.374 3.97
SQUIRREL 1.374 771 6.33 76 120 0.325 0.355 7.61
GOPHER 1.098 952 7.09 85 130 0.318 0.349
WEASEL 0.9116 1136 7.77 95 150 0.314 0.345 11.12
FERRET 0.6795 1503 9.00 115 175 0.308 0.339
RABBIT 0.5449 1860 10.05 135 200 0.305 0.335 18.25
MINK 0.4565 2207 11.00 165 250 0.302 0.353
HORSE 0.3977 6108 13.95 185 270 0.296 0.327
BEAVER 0.3841 2613 12.00 176 257 0.299 0.327
RACOON 0.3656 2746 12.30 180 260 0.298 0.329 26.91
OTTER 0.3434 2923 12.60 185 270 0.297 0.328
CAT 0.3020 3324 13.50 195 290 0.296 0.327
DOG 0.2745 3299 14.20 205 305 0.283 0.315 32.41
LEOPARD 0.2193 4137 15.85 275 395 0.259 0.282
COYOTE 0.2214 4638 16.86 260 380 0.238 0.268
TIGER 0.2221 5758 16.50 265 385 0.240 0.271
WOLF 0.1844 6880 18.10 305 425 0.235 0.266 67.34
LYNX 0.1589 7950 19.60 335 470 0.230 0.261
PANTHER 0.1375 9127 21.00 370 510 0.225 0.256 89.67
LION 0.1223 10210 22.30 405 560 0.222 0.252
BEAR 0.1102 11310 22.90 430 590 0.220 0.250
GOAT 0.08989 13780 26.00 495 665 0.213 0.224
SHEEP 0.07771 15910 28.00 554 745 0.210 0.240
KUNDAH 0.07213 9002 26.82 575 775 0.211 0.242 88.79
DEER 0.06786 18230 29.90 590 800 0.207 0.237
ZEBRA 0.06915 13245 28.62 610 812 0.205 0.237 130.32
-
8/7/2019 final 3 n 4
15/15