final 3 n 4

download final 3 n 4

of 15

Transcript of final 3 n 4

  • 8/7/2019 final 3 n 4

    1/15

    Lab No. 3

    Generator:

    Almost all the hydraulic turbine-driven generators used are synchronous alternatingcurrent machines, which produce electrical energy by the transformation of the rotational

    mechanical energy. The electrical and mechanical design of each generator must confirm

    to the electrical requirements of the power distribution system to which it will be

    connected, and also to the hydraulic requirements of its specific plant. The electrical

    characteristics of the generator used in our design are:

    SN. Specifications Ratings

    1 MVA 7.2

    2 KV 11

    3 Phase 3

    4 Frequency 505 Power Factor 0.85

    6 No. of Poles 18

    7. RPM 333

    Generator excitation system:

    Brushless excitation system was used for the excitation of the generator as it is

    the best excitation system for medium sized power plant due to the absence of carbon

    brushes, brushless system requires less maintaince and its outage time is less.

    Generator neutral grounding:We preferred to select the resistance grounding method . Its value is selected such

    that the value of Xcg >> Rn or Xcg/Rn>>1. Since the value of resistance was very

    high, the distribution transformer method for generator neutral grounding was done.

  • 8/7/2019 final 3 n 4

    2/15

    Low voltage busbars:

    We employed 11 KV medium voltage single bus bar arrangement and unit

    Generator Transformer Scheme was used. Unit Generator scheme is a conventional

    scheme preferred for medium sized power plants in a small power system where the plant

    size is significant for the system. With the use of individual transformer for each

    generator unit, unit protection of generator and transformer becomes easy. Overall

    protection system becomes simple and easy to locate the faults.

    High voltage busbars (66 kv):

    We have chosen the Modified Main And Transfer Bus scheme considering its

    reliability, flexibility, availability in operation and protection simplicity.

    This type of scheme has many advantages as follows:

    Flexible operation Load can be shifted to any bus during maintaince of other bus.

    Periodic Maintence of breaker can be done without interrupting the powersupply.

    Breakers:

    The circuit breakers are used to protect the equipment during the fault condition.

    The rated voltage and the breaking current are the parameter that calls for the desired

    circuit breaker to be used in the protective scheme of an electrical system. We have used

    the vaccum circuit breakers as the generator breakers (synchronizing breaker), SF6 circuit

    breakers at the HV side and ACB at the station transformer side. A VCB breaker suffers

    from the current chopping phenomenon. So to avoid this we have used the surge arrestor

    in parallel with each of its phases.

    Transformer:

    We have used 3 phase delta / star transformer to step up the voltage from 11 kv to

    transmission line voltage i.e. 66 KV. The MVA capacity of the transformer is 7 MVA.

    Station transformer of 11/ 0.4 KV delta /star is used to supply power for the auxillaries.

  • 8/7/2019 final 3 n 4

    3/15

    Calculation of resistance grounding

    Generator : MVA rating =7.2 MVA, 11KV, 0.85 pf, 377.9 A

    Capacitance of terminals of generator with respect to ground Co= 0.135 F for 11 KV

    level.

    Capacitance of surge capacitance = 0.25 F

    Other capacitances are negligible.

    Cg = 3(C0 + Cs) = 1.155 F

    Xcg =#

    $@/A= 2756 = Rn

    The value of Rn is in range of high resistance , hence distribution transformer is selected.

    A distribution transformer of ratio 11/ % is selected.

    Transformation ratio = 13.23

    A neutral resistor to be inserted in secondary is

    Rn= Rn/n

    2= 15.74

    Rating of Distribution transformer

    The fault current that flows in secondary resistor is

    Isec(max)= Vsec(max)/ Rsec = 480/15.74 = 30.5 A

    The thermal rating of the transformer should be

    KVA = Esec rated * Isec max = 14.6 KVA

    Hence,

    Dry type transformer = 15 KVA, 11/ %

  • 8/7/2019 final 3 n 4

    4/15

    Lab No. 4

    Type Of Transmission Line Circuit

    In our Scheme we used the double Transmission line circuit for the power evacuation.

    From the standard table of ACSR conductors,The current carrying capacity of the line is 430 A at 20

    0C. For reliable operation

    and for maintenance purpose, we used parallel feeders and each feeder is capable of

    carrying full load current which is 115 A. Also while using double circuit the capacity to

    evacuate the power increases.

    Line current =#&"

    $#"

    High Voltage Bus Bar Scheme Selection:We have chosen the Modified Main And Transfer Bus scheme considering its

    reliability, flexibility, availability in operation and protection simplicity.

    This type of scheme has many advantages as follows:

    Flexible operation

    Load can be shifted to any bus during maintaince of other bus.

    Periodic Maintence of breaker can be done without interrupting the powersupply.

    Fig: Modified Main and Transfer Bus

  • 8/7/2019 final 3 n 4

    5/15

    Modes of Operation:Normal operation ( Main Bus Operation) :

    For maintenance of circuit breaker 1 - :

  • 8/7/2019 final 3 n 4

    6/15

    Fault occurring at Main Bus:

    Calculation of Fault current and Fault MVA level

    The fault occurs at various points as shown in the figure:

    Fig: 1

    For the generator capacity of 7.2 MVA and synchronous speed 333 RPM the per unit sub-

    transient reactance of the generator selected from the graph below is 22.5%.

  • 8/7/2019 final 3 n 4

    7/15

    Generator Sub-Transie

    Similarly for the transforme

    transformer impedance is sel

    Transformer Impedanc

    t Reactance

    r capacity of 8MVA and high voltage windi

    cted from the table below as 9.87%.

    e

    g 33KV the

  • 8/7/2019 final 3 n 4

    8/15

    With reference to, ACSR conductor table, for Bear conductors, the line reactance is taken

    to be 0.220 /km.

    Length of the line =50km

    Total reactance of the line= 0.220 /km * 50km = 11

    Now, we take,

    Base KV (on LV side of transformer) =11 KV

    Base KV (on HV side of transformer) =72 KV

    Base MVA = 7.2 MVA

    Base reactance (on LV side) = (base kv)2/ base MVA = (11 2 / 7.2)

    = 16.8

    Base reactance (on HV side) = (base kv) 2/ base MVA = (72 2 / 7.2)

    = 720

    Base Current =$#"

    ###"= 377.9 A

    PU reactance of Transmission line =##

    $"= 0.01563 pu

    PU reactance of Transformer (PU new ) = PU old *(Base KV old /Base KV new )2

    *(Base MVA new /Base MVA

    old )

    =0.096*(11/11) 2 *(7.2/7) =0.0987 pu

    Now,

    Xpu (generator) =0.225pu

    Xpu (Transformer) =0.0987pu

    Xpu (line) =0.01563pu

  • 8/7/2019 final 3 n 4

    9/15

    Calculations of Fault at different positions:

    Fault at position 1:

    1

    IJ { - % -

    -

    - %

    =0.10633

    I fault (pu) =#"

    "#"= 9.403 pu

    Ifault

    (actual) = Ifault

    (pu) * Base Current = 9.403 * 377.9 A

    = 3554 A

    Fault MVA = Base MVA / (X pu ) eq =67.713 MVA

    Fault at position 2:

    L VH V

    (Xpu

    )eq

    = 0.225 pu

    I fault (pu) = 1

  • 8/7/2019 final 3 n 4

    10/15

    Fault at Position 3:

    3

    IJ

    { - % -

    -

    =0.00763

    Ipu =#

    """= 131.04A

    Iact = 131.04 * 57.73

    = 7565.40 A

    Fault MVA = Base MVA / (Xpu

    )eq

    =943.64 MVA

    Fault at Position 4:

    L V H V

    4

    Xpu = 0.225 + 0.0.0987 = 0.3237 pu

    Ipu =#

    "$

    % pu

    Iact = 3.089 * 57.73 A =178.34 A

    Fault MVA = Base MVA / (X pu ) eq=22.24 MVA

    0.225 0.09870.021

    0.021

    0.225 0.0987

  • 8/7/2019 final 3 n 4

    11/15

    Fault at Position 5:

    c b 55

    Xpu = 0.01563 pu

    Ipu =#

    ""#' pu

    Iact = 63.97 * 57.73 = 3693.5 A

    Fault MVA = Base MVA / (X pu ) eq=46.065 MVA

    Fault at Position 6:

    c b 56

    Xpu =#

    !

    !

    \a

    Ipu =#

    ""#&$' \a

    Iact = 70.15 * 57.73 = 4049.76 A

    Fault MVA = Base MVA / (Xpu

    )eq

    =505.263 MVA

    0.021

    0.0210.0987

    0.0987

    0.225

    0.225

  • 8/7/2019 final 3 n 4

    12/15

    Ratings Of Circuit Breakers:

    CB Rate

    Volt

    KV

    Rated

    insulaton

    level KV

    Freq

    uency

    Normal

    Current

    A

    Breaking

    Current

    KA

    Making

    Current

    KA

    Short time

    Rating

    Current

    Rated

    Impulse

    Current

    1 12 60 50 400 8 20.4 8 20.4

    2 72.5 325 50 800 12.5 31.875 12.5 31.875

    3 72.5 325 50 800 12.5 31.875 12.5 31.875

    4 12 60 50 400 8 20.4 8 20.4

    5 72.5 325 50 800 12.5 31.875 12.5 31.875

    6 72.5 325 50 800 12.5 31.875 12.5 31.875

    7 72.5 325 50 800 12.5 31.875 12.5 31.875

    8 0.6 325 50 800 12.5 31.875 12.5 31.875

    9 0.6 325 50 800 12.5 31.875 12.5 31.875

    10 72.5 325 50 800 12.5 31.875 12.5 31.875

    Conclusion

    Hence by the end of the report we designed the 12 MW DhuncheHydropower Project on the basis of Medium Hydropower Project (NEA 1997)Method. In this report we also calculated the catchments area, head, thedischarge and output of the plant. This report also include turbine selection on thebasis of various criteria ,SLD using different bus bar ,neural grounding , excitationschemes used in various power plants existing in Nepal. Report include faultcurrent calculation at different bus bar and circuit breaker ratings.

  • 8/7/2019 final 3 n 4

    13/15

    The Table for the proper selection of breaker is shown below

  • 8/7/2019 final 3 n 4

    14/15

    ACSR CONDUCTOR IS : 398 [PART-II

    Code Name

    Resistance

    At 20oC

    Tensile

    StrengthOverall

    Diameter

    Current Rating Inductive Reactance

    Calculated

    Breaking LoadIn Still Air With Wind 30 MM 50 MM

    Ohm/km N/mm2 Mm A A Spacing Spacing

    MOLE 2.718 407 4.50 40 70 0.352 0.374 3.97

    SQUIRREL 1.374 771 6.33 76 120 0.325 0.355 7.61

    GOPHER 1.098 952 7.09 85 130 0.318 0.349

    WEASEL 0.9116 1136 7.77 95 150 0.314 0.345 11.12

    FERRET 0.6795 1503 9.00 115 175 0.308 0.339

    RABBIT 0.5449 1860 10.05 135 200 0.305 0.335 18.25

    MINK 0.4565 2207 11.00 165 250 0.302 0.353

    HORSE 0.3977 6108 13.95 185 270 0.296 0.327

    BEAVER 0.3841 2613 12.00 176 257 0.299 0.327

    RACOON 0.3656 2746 12.30 180 260 0.298 0.329 26.91

    OTTER 0.3434 2923 12.60 185 270 0.297 0.328

    CAT 0.3020 3324 13.50 195 290 0.296 0.327

    DOG 0.2745 3299 14.20 205 305 0.283 0.315 32.41

    LEOPARD 0.2193 4137 15.85 275 395 0.259 0.282

    COYOTE 0.2214 4638 16.86 260 380 0.238 0.268

    TIGER 0.2221 5758 16.50 265 385 0.240 0.271

    WOLF 0.1844 6880 18.10 305 425 0.235 0.266 67.34

    LYNX 0.1589 7950 19.60 335 470 0.230 0.261

    PANTHER 0.1375 9127 21.00 370 510 0.225 0.256 89.67

    LION 0.1223 10210 22.30 405 560 0.222 0.252

    BEAR 0.1102 11310 22.90 430 590 0.220 0.250

    GOAT 0.08989 13780 26.00 495 665 0.213 0.224

    SHEEP 0.07771 15910 28.00 554 745 0.210 0.240

    KUNDAH 0.07213 9002 26.82 575 775 0.211 0.242 88.79

    DEER 0.06786 18230 29.90 590 800 0.207 0.237

    ZEBRA 0.06915 13245 28.62 610 812 0.205 0.237 130.32

  • 8/7/2019 final 3 n 4

    15/15