Fill Dams Notes
-
Upload
sheikh-nouman-mohsin-ramzi -
Category
Documents
-
view
218 -
download
0
Transcript of Fill Dams Notes
-
7/29/2019 Fill Dams Notes
1/11
Dams are among the oldest structures built by humans for collective use. A dam is a
barrier that is constructed across a river or stream so the water can be held back or
impounded to supply water for drinking or irrigation, to control flooding, and to
generate power. The main kinds of dams are earth fill, rock fill, concrete gravity,
concrete arch, and arch gravity. The last three types are all made of concrete, reinforced
concrete, or masonry. (The term masonry can mean concrete, bricks, or blocks of
excavated rock.) Fill dams include all dams made of earth materials (soil and rock) that
are compacted together. One type of fill dam called a tailings dam is constructed of fine
waste that results from processing rock during mining; at mine sites, this soil-like waste
is compacted to form an embankment that holds water for the mining and milling
processes or to retain the tailings themselves in water.
Of the main categories of dams listed above, all have been built since ancient times
although many refinements were developed in the nineteenth and twentieth centuries
with improved engineering technology. Dams that leak have failed to do their job, either
because they simply can't hold water or because the water seeping through them eats
materials away from the inside of the dam causing it to fail structurally. In modern
times, most fill dams are also built with zones including a clay center or core, filter and
drainage layers, coarser materials sandwiching the clay core, and rock on the upstream
(water) face to prevent erosion. These zones can be seen clearly when a cross section iscut from the upstream to the downstream side of the dam. All fill dams depend on
weight to remain stable.
Fill embankments are usually less expensive to construct than concrete dams. Soil or
rock are present at the site, and construction techniques, though complex, are also less
costly than for concrete construction. For these reasons of available materials, low cost,
and stability with mass, fill dams are often built across broad water courses. They also
are more flexible than concrete structures and can deform without necessarily failing iffoundation materials under the dam compress with the weight of the dam and the water.
History
-
7/29/2019 Fill Dams Notes
2/11
Quite naturally, early dam builders began by using plentiful materials like sand, timber
and brush, and gravel. Their construction method consisted of carrying the materials by
the basketful and loosely dumping the fill, so many of these dams may have survived
only a few years. Scientists have not been able to pinpoint dates for the earliest dam
construction, but they do know dams were needed where food was grown and in areas
prone to flooding.
Design of fill dams is based on experience; while failures are unfortunate and sometimes
catastrophic, they are also the best teachers, and many engineering advances have been
founded on careful study of earlier failures. The engineers of ancient India and Sri
Lanka were the most successful pioneers of fill dam design and construction, and
remains of earth dams can still be seen in both countries. In Sri Lanka, long
embankments called tanks were built to store irrigation water. The Kalabalala Tank was
37 mi (60 km) long around its perimeter.
The most famous earth fill dam recently constructed is the Aswan High Dam that was
built across the Nile River in Egypt in 1970-1980. An earth fill dam was also the victim
of a spectacular failure in June 1976 when the Teton Dam in Idaho eroded from within
due to incorrect design of the zones inside the dam that allowed seepage, failure, and
flooding of the valley downstream. Although earth dams tend to be short and broad,
Nurek Dam in Tajikistan is 984 ft (300 m) high.
Raw Materials
The materials used to construct fill dams include soil and rock. Soil is classified by
particle size from the smallest, submicroscopic particles called clay; silt, which is also
very fine; sand ranging from fine to coarse, where the fine grains are the smallest soil
particles our eyes can see; and gravel. Coarser fragments called cobbles and boulders are
also used in dam construction but usually as protective outer layers.
Specific soil types and size ranges are needed to construct the zones within the dam, and
explorations of the dam foundation area, the reservoir where the water will be stored,
and surrounding areas are performed not only for design of the dam but to locate
construction materials. The costs of fill construction rise dramatically with the distance
-
7/29/2019 Fill Dams Notes
3/11
materials are hauled. Samples of potential construction materials are tested in a soil
laboratory for grain size, moisture content, dry density (weight), plasticity, and
permeability. Clay is not only very fine in size but has chemical characteristics that cause
it to stick together. The combination of fine size and plastic behavior also causes the clay
to be less permeable to water. If clay is available near the site, the dam can be built with
an impermeable core or central zone that prevents water from passing through the dam;
otherwise, the dam must be designed so water can seep slowly and safely through a
different combination of materials in its zones.
Water is also a raw material. The various soil types have compaction characteristics that
can be determined in the laboratory and used during construction. Soil can be
compacted to its best functional density by adding moisture and weight and impact,
called compactive effort. Large vibrating rollers press thin layers of soil into place after
an optimal amount of water has been added. The water and weight bond the soil
particles together and force smaller particles into spaces between larger particles so
voids are eliminated or made as small as possible to restrict seepage.
Increasingly, fill dams also include geotextiles and geomembranes. Geotextiles are
nonwoven fabrics that are strong and puncture-resistant. They can be placed between
lifts as the dam is raised to strength weak materials. They are also used as filter fabrics
to wrap coarser drain rock and limit the migration of fine soil into the drainage material.
Geomembranes are made of high-density polyethylene (HDPE) plastic and are
impermeable. They can be used to line the upstream face of a fill dam or even to line the
entire reservoir.
Feasibility and
Preliminary Design
A specific need for a dam, whether it is water supply, storage of tailings or other
materials, or flood control, stimulates the process of designing and building a fill dam.
The need and the location are usually closely connected, so several sites may be
considered. During feasibility studies, engineers identify these sites, make preliminary
cost comparisons, decide on a probable design, and chose the best site for exploration.
-
7/29/2019 Fill Dams Notes
4/11
Feasibility certainly refers to the cost of building the dam, but it also includes the
technical practicalities of site suitability, design, construction, and long-term
maintenance and safety.
After a feasible site is chosen, a preliminary design of the dam is developed. The location
of the dam is superimposed on a topographical map so the dimensions of the top of the
dam relative to the tops of the adjacent hills and the proposed water level can be shown
as well as the extent of the base of the dam in the stream channel. The proposed water
level elevation shows the extent of the reservoir and determinesalong with the shape
of the basinthe quantity of water that the reservoir will hold. Quantities of water
stored and materials used in constructing the dam help determine the value of the
project and its costs. Sometimes multiple iterations of site selection, pre-design, and
cost estimating are needed. Ideally, the foundation area under the dam will not require
much excavation or grouting to prevent seepage, and the materials inside the reservoir
area can be excavated and used to build the dam so that more reservoir storage is gained
at the same time as soil or rock are excavated to construct the embankment.
When the optimal site is chosen on paper, an exploration program is developed and
performed. During the exploration, test borings are drilled along the line of the axis of
the dam across its proposed width, along or near the proposed upstream and
downstream toes of the dam, at the site of the proposed spillway, and in the reservoir
area. The borings are excavated deep into the foundation to evaluate its strength and
permeability (potential for seepage) properties. As the borings are drilled through the
overlying soil, it is also sampled and tested in the laboratory so it can be evaluated as
potential dam construction material. Field tests of permeability are also performed at
the site of the dam and in the reservoir area. If it is the source for construction
materials, test pits are also dug in the reservoir area so that the volume of available soil
(and related costs) can be estimated.
Design
After the field exploration and laboratory testing are complete, the engineering team
begins final design of the dam based on the preliminary assumptions, the findings in the
-
7/29/2019 Fill Dams Notes
5/11
field, and any changes in design or economics that are based on field findings. In
designing a fill dam, engineers look at five critical considerations: the mass of the dam
that will make it stable; design of a core and other interior zones to prevent seepage
through the dam; design of a cutoff wall or other seepage prevention under the dam;
erosion protection on the upstream face; and economics.
Fill dams are typically shaped like triangles with the apex or point at the top or crest of
the dam and the broad base on the floor of the creek channel. The width of the base in
cross section provides friction to prevent sliding, and the total mass of the dam makes it
strong enough to resist the weight of water behind it. The foundation area is cleaned of
soft, permeable, and compressible soil; and a cut-off wall is cut down to rock or firm
soil. The cut-off wall can be constructed of steel sheet piling or concrete, but, for most
fill dams built since about 1960, the cut-off wall is simply an extension of the clay core.
Where foundation rock or soil contains voids or fractures, a series of holes may be
drilled into the foundation, and concrete grout is injected in the holes to seal the
fractures and help cut off seepage.
The zones of a fill dam may consist of a number of distinct layers from the center of the
dam and moving upstream toward the water and a different set of layers from the center
moving downstream. Materials for the zones are selected for strength properties and
permeability characteristics, and the placement of one zone next to another is carefully
governed by sets of calculations based on these properties. Filter and drainage zones are
included so that any water succeeding in reaching the inside of the dam is channeled
around the core and out through drainage layers at the base of the dam.
The upstream (water) face of the dam is sometimes protected with a concrete slab or an
asphalt face. More commonly, cobble- and boulder-sized stones are placed on this face
near the water surface; this facing is called riprap and prevents wave action at the water
surface from eroding the dam construction materials. Other facilities for controlling the
water level and any water movement through or over the dam, like an emergency
spillway, are also designed specifically for the dam's location, uses, type and materials of
construction, and water inflows into the reservoir.
-
7/29/2019 Fill Dams Notes
6/11
The economics of dam construction are considered throughout the design process.
Construction materials must be available at or near the site. Rock can be placed at
steeper angles than soil, and it weighs more; so a dam built mostly of rock can be
smaller in design section. Excavating and moving rock can be more expensive than soil,
however, so the design engineers must consider cost factors. Other materials like
asphalt, concrete, steel, and cement for grouting are also expensive. The proper balance
of safety and economy must be determined by the engineers. Large earthmoving
machines have made construction of zoned, fill dams more
Cross section of a typical fill dam.
economical than construction of concrete dams at many sites.
The Construction Process
1. Fill dams are constructed in the dry season when water levels in the river orstream are lower, rainfall on sources of fill material is less likely, and conditions
are better for operating large construction equipment. Before construction
actually begins, the site is surveyed to locate the dam alignment on the existing
ground, the areas that will be excavated, and the borrow areas or sources for the
soil or rock used in construction. Construction management facilities are set up;
usually, the construction manager (a field engineer with years of similarexperience) will work out of a trailer on site. Depending on the site, it may be
necessary to install instruments to monitor the effects of dam construction on
adjacent hillsides or other features and to measure groundwater levels
throughout construction in the foundation and surroundings. And, of course, the
flow of the stream that is being dammed through the site must be stopped. This
-
7/29/2019 Fill Dams Notes
7/11
can be done by a variety of methods including diverting the stream, perhaps to
flow through a neighboring channel, or stopping it upstream with a temporary
dam or cofferdam.
2. Before construction of the dam begins, the foundation area must be prepared. Inrare cases, dams can be constructed directly on the existing materials in the
channel floor; at most sites, these materials are compressible (and would cause
the dam to settle irregularly) and permeable (allowing water to pass under the
dam). The foundation area also includes the abutments, which are the hillsides
forming the two ends of the dam. Soil and soft or highly fractured rock are
excavated, sorted by type, and stockpiled for later use in dam construction. The
surface of the foundation bedrock is cleaned to a surprising degree; it is broomed
and hosed with water so that any voids or irregularities are visible and cleaned ofsoft soil. The foundation is carefully inspected before any construction work;
additional exploratory drilling may be done if there are any questions about the
foundation's condition. If the rock is fractured or contains voids or holes, these
are sealed with cement grout that is injected through small diameter drill holes in
a process called dental work.
3. The base of the dam must go down into the ground before it rises above it. Atrench that is the full width of the dam (across the channel) is cut into firm rock.
The trench is called a keyway or cutoff wall and may have several benches or
notches into rock. It prevents the dam from sliding along a smooth foundation
and also creates a longer path for any seepage to try to flow under the dam. The
impervious clay that will make up the core of the dam is placed in the keyway and
compacted and raised, layer by layer, until the top of the keyway or base of the
majority of the foundation is reached.
4. The soil in the keyway and all the zones of the dam are raised to the same levels atthe same time. Ramps may have to be cut
-
7/29/2019 Fill Dams Notes
8/11
Aeriol view of a planned fill dam.
into the keyway area for the construction equipment, and then they must be built
up to the working surface of the rising top of the dam. Whenever possible, roads
are cut in from the two sides (abutments) of the dam for the easiest access;
eventually, an access road will be built on the crest of the dam and extending onto
these abutments.
Large earthmovers haul the specific type of soil needed to raise the zone of thedam they are working on. The soil is spread in thin layers, usually 6-8 in (15.2-
20.3 cm) thick, sprayed with water to the correct moisture content, and
compacted with sheepsfoot rollers (compactive rollers with prongs resembling
animal hooves mounted in rows around the roller that press and vibrate the soil
firmly in place). If gravel is used in construction, a vibrating roller is used to
vibrate the grains together so their angles intermesh and leave no openings.
Throughout the compaction process, inspectors approve the soil that is hauled onsite and hauled to the particular zone of the dam. They reject material that is
contaminated with grasses, roots, trash, or other debris; and they also reject soil
that does not appear to be the proper grain size for that zone of the dam. For
quality control, samples are collected and tested in the laboratory (for large dams,
an on-site soil lab is installed in a construction trailer) for a variety of
-
7/29/2019 Fill Dams Notes
9/11
classification tests. Meanwhile, the inspector uses a nuclear density gauge to test
the soil for density and moisture content when it has been placed and compacted.
The nuclear density gauge uses a very tiny radioactive source to emit radioactive
particles into the soil; the particles bounce back onto a detector plate and indicate
the moisture and density of the soil in place. The process is not harmful to the
environment or the operator (who wears a badge to monitor radioactive
exposure) and provides data without having to excavate and sample. If the
compaction requirements are not met, that layer of soil is excavated, placed
again, and recompacted until its moisture and density are suitable.
Construction of the fill dam proceeds layer by layer and zone by zone until the
height of each zone and, eventually, the crest of the dam are reached. If the entire
dam cannot be built in one construction season, the dam is usually designed in
phases or stages. Completing a construction stage (or the entire dam) is often a
race against time, the weather, and the project budget.
5. Some earth dams have instruments installed in them at the same time as fillplacement is done, and the instruments are constructed to the surface in layers
and zones, just like the fill. The condition of the dam is monitored throughout its
lifetime, as required by federal, state, and local laws and by standards of
engineering practice. Types of instruments vary depending on the location of the
dam; almost all dams have settlement monuments that are surveyed to measure
any settlement in the surface or zones of the dam, slope indicators to show if the
sloping faces inside or on the surface of the dam are moving, and water-level
indicators to monitor the water level in the dam's zones. Dams in seismically
active areas may also be equipped with instruments to measure ground shaking.
6. Fill dams may have a variety of other facilities, depending on their, size, use, andlocation. An emergency spillway is required at all dams to allow for flood watersto flow over an escape route, rather than over the top of the dam. Other spillways
for production of hydroelectric power may be designed and constructed at power-
generating dams, and inlet and outlet tunnels are needed to release water for
irrigation and drinking-water supplies at embankments built for those purposes.
At fill dams, it is usually desirable to place these other facilities in excavations
-
7/29/2019 Fill Dams Notes
10/11
through the foundation or abutment rock; the process of compacting earth
against structures that actually pass through the fill is tricky and allows for
seepage paths.
7. Sometimes the reservoir area is also cleared when it is to be filled with water,particularly if lumber can be harvested. It is not necessary (and it is much too
expensive) to clear it of all shrubs and grass. The process of filling the reservoir is
relatively slow, so most wildlife will move as the water level rises; areas of
concern include habitats for rare or endangered species, and drowning of these
habitats has been a concern in the construction of a number of dams.
When the dam is complete, the water that was diverted from the stream channel is
allowed to fill the reservoir. As the water rises, it is also rising in portions of the dam,
and instruments within the dam are monitored carefully during the reservoir-filling
period. Monitoring of the dam's performance, both by instruments and simple
observation, is performed routinely; and safety plans are filed with local emergency
services so that sudden changes in instrument readings or the appearance of the dam or
its reservoir triggers actions to alert and evacuate persons living in the path of flood
waters downstream. Repairs are also performed routinely.
Quality Control
Quality engineering is essential in the construction of a fill dam because the materials
used have lower strength properties than the steel and concrete required for concrete
dams and because placement ultimately determine strength, potential for problems like
seepage and settlement, and finally performance and safety. The geotechnical project
engineer occupies the key role of making sure the design and earth materials match to
make a safe product; but many other professionals including geologists, construction
technicians, other engineers, and the representatives of overseeing agencies are fully
committed to the same purpose.
Byproducts/Waste
There are no byproducts in fill dam construction, although fill is sometimes generated
for building access roads and other support structures. Waste is also minimal to
-
7/29/2019 Fill Dams Notes
11/11
nonexistent; excavation of excess soil and especially rock is very expensive as is hauling
these materials so waste is engineered out of the design.
The Future
Primarily due to environmental concerns, design and construction of any dam in the
future will be a much-studied and controversial process. Fill dams, however, tend to be
perceived as more environmentally friendly because they are made of earth materials
and blend into the scenery better than monolithic concrete structures. Fill dams have
proven useful and less expensive solutions to meeting human needs for water supply,
and vast improvements in engineering technology have improved their safety record in
the late twentieth century. Although many costs and agendas must be considered in
building dams, fill dams have and will continue to prove themselves allies in the needs
to provide drinking water, irrigation supply, and flood control.
Read more:How fill dam is made - material, making, history, used, processing,
dimensions, product, History, Raw Materials, Feasibility and Preliminary Design,
Design, The Construction Process, Quality Controlhttp://www.madehow.com/Volume-
5/Fill-Dam.html#ixzz1QNa2XyYE
http://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYEhttp://www.madehow.com/Volume-5/Fill-Dam.html#ixzz1QNa2XyYE