Fidic 1992 Risk Clauses

download Fidic 1992 Risk Clauses

of 8

Transcript of Fidic 1992 Risk Clauses

  • 7/27/2019 Fidic 1992 Risk Clauses

    1/8

    1

    FIDIC 4th

    Edition 1987/1992 SOME OF THE IMPORTANT CONTRACT

    CLAUSES, BOTH TERMS & CONDITIONS, WHICH HAVE ATTENDANT

    RISKS FOR THE CONTRACTOR ARE OUTLINED HEREBELOW WITH MY

    COMMENTS FOR YOUR REFERENCE.

    Clause 2.1 Engineers Duties and Authority

    The Contractor must ensure that the Engineer has obtained the specific

    approval of the Employer before acting on any of the Engineers

    requirements, say for additional works / variations, otherwise the

    contractor runs the risk of not being paid for a disputed variation.

    However in the event that an instruction is issued by the Engineer

    which the Contractor believes to be a variation, but which is contested

    by the Engineer, the contractor is duty bound to comply, but must

    make his stand very clear that he considers the Engineers requirement

    to be a variation involving time and cost and submit his claim inaccordance with clauses 44 or 53, otherwise he runs the risk of losing

    his right to time and costs under the contract.

    Clauses 2.2 Authority of the Engineers Representative

    And 2.3 The Engineer may delegate to the Engineers Representative any of the

    duties and authorities vested in the Engineer. The Contractor must

    make sure that he receives a copy of such delegation, otherwise he runs

    the risk that he will act in accordance with the Resident Engineers

    instructions but without having appropriate recourse under the

    contract.

    Clause 2.5 Instructions in Writing

    Any oral instruction issued by the Engineer must be confirmed within

    7 days by the Contractor in writing to the Engineer, and such

    confirmation must not be contradicted by the Engineer in writing

    within 7 days, otherwise the Contractor runs the risk of not being able

    to recover costs and / or time.

    Clause 3.1 Assignment of Contract

    The Contractor shall not, without the prior consent of the Employer,

    assign the Contract or any part thereof, etc. otherwise the Contractor

    runs the risk of being in breach of a main condition of the contract, andbeing terminated under clause 63.1.

    Clause 4.1 Subcontracting

    The Contractor shall not subcontract the whole of the Works, and in

    addition shall not subcontract any part of the works without the prior

    consent of the Engineer, failing which he risks termination under

    clause 63.1.

    Clause 6.3 Disruption of Progress

    The Contractor must give Notice to the Engineer whenever planning or

    execution of the Works is likely to be delayed or disrupted unless any

    further drawing or instruction is issued by the Engineer within a

  • 7/27/2019 Fidic 1992 Risk Clauses

    2/8

    2

    reasonable time. Failure to give such notice may well place at risk the

    Contractors entitlement for any requests for additional time and / or

    costs.

    Clause 7.3 Permanent Works Designed by Contractor

    The Contractor remains liable for his design even if approved by theEngineer, and therefore runs the risk of any cost or delay arising from

    any fault in the design to the extent that it is not covered by Insurance.

    Clause 8.1 Contractors General Responsibilities

    The Contractor shall provide all things necessary and shall execute and

    complete the Works with due care and diligence, failure of which

    render him liable to additional costs.

    The Contractor has a duty to give prompt notice to the Engineer of any

    error, fault, or other defect in the design of or Specification of the

    Works which he discovers, otherwise he runs the risk of any resultant

    additional costs or delays.Clause 8.2 Site Operations and Method of Construction

    The Contractor shall take full responsibility (the risk) for the adequacy,

    stability, and safety of all site operations and methods of construction.

    Clause 10.1 Performance Security

    This tends to be an on demand bond. The risk here is that an

    unscrupulous Employer may well call upon the bond in circumstances

    when he is not contractually entitled to do so, and the Contractor has

    no remedy except to go to the Courts to try to stop the calling of the

    bond, which is an extremely difficult task. This can be time consuming

    and costly, with the added risk that if the Employer calls the bonds

    when he is in financial difficulties, it will be too late if a year later the

    Courts or Arbitrators decide that the calling of the bonds was wrongful,

    at which stage, the Employer may have already gone into liquidation.

    This is why it is important to contract with a reputable Employer. A

    further risk here arises under clause 60.2, that in the event that the

    Contractors performance security is delayed, the Engineer does not

    have to certify any amount for payment whilst the performance

    security is outstanding.

    Clause 11.1 Inspection of SiteThe Contractor shall be deemed to have based his Tender on the data

    made available by the Employer. The risk here is that if it is

    established during the construction period that the information

    provided by the Employer was incorrect, the Contractor will only be

    able to seek recompense for time and cost if he can demonstrate to an

    arbitral tribunal that it was not practicable for him to have carried out

    during the tender period, having regard to considerations of cost and

    time, the type of inspection and examination required to have

    established the accuracy or otherwise of the information provided.

    Clause 12.1 Sufficiency of Tender

  • 7/27/2019 Fidic 1992 Risk Clauses

    3/8

    3

    The Contractor runs the risk that his prices may not have taken into

    consideration all his obligations under the Contract.

    Clause 12.2 Not Foreseeable Physical Obstructions or Conditions

    The Contractor must forthwith (immediately) give Notice to the

    Engineer of any unforeseeable physical obstructions or conditions heencounters, failing which he runs the risk that his claim for time and

    cost may not be entertained.

    Clause 14.1 Programme to be Submitted

    The Contractor must pay particular attention to the preparation of the

    programme. Although the FIDIC conditions do not refer to the Critical

    Path, most applications for an Extension of Time under Clause 44 do

    refer to the impact of a delaying event on the critical path. Therefore

    care must be taken to ensure that the programme covers the full

    contractual period with the minimum of float, (zero float is preferable),

    otherwise the Contractor will run the risk that he may not be able torecover time and cost for any delaying event for which otherwise he

    would have been entitled, as the delay may be such as to take up only

    part or all of the float.

    Clauses 15.1 Contractors Superintendence and Employees

    And 16.1 If the Contractor does not provide the necessary superintendence,

    skilled technical assistants and the necessary level of skilled workforce,

    the Contractor runs the risk of delays and losses.

    Clause 17.1 Setting-out

    If the Contractor does not carry out the setting out properly and with

    the proper survey equipment, he runs the risk of having to remedy any

    errors at his own cost.

    Clause 19.1 Safety, Security, and Protection of the Environment

    If the Contractor does not pay attention to safety and environmental

    issues, he runs the risk of being subjected to fines imposed by the

    Authorities, as well as stop work orders, either by the relevant

    Authorities or by the Engineer.

    Clause 20.1 Care of the Works

    Clause 20.2 Responsibility to Rectify Loss or Damage

    The Contractor carries the risk of caring for the Works, and for thematerials and plant for incorporating therein, to the extent that such

    risks are not the Employers risks under clause 20.4, are not covered by

    the exclusions and exceptions under clauses 21.4 and 22.2 respectively,

    or are not covered under the insurance policies stipulated in clauses 21

    through to 25.

    Clause 20.4 Employers Risks

    The Contractor retains the risk for any riot, commotion, or disorder

    solely restricted to the Employees of the Contractor or of his

    sub-contractors, for any loss or damage arising from any part of the

  • 7/27/2019 Fidic 1992 Risk Clauses

    4/8

    4

    works that have been designed by the Contractor, and for any operation

    of the forces of nature that an experienced contractor could reasonably

    have been expected to take precautions.

    Clause 21.1 Insurance of Works and Contractors Equipment

    The Contractor carries the risk for any excesses or deductiblesstipulated in the insurance policies for the items that are not covered in

    clauses 20.4, 21.4, and 22.2.

    Clause 22.1 Damage to Persons and Property

    The Contractor carries the risk of indemnifying the Employer against

    all losses and claims which are not included in the exceptions defined

    in clause 22.2 and which are not covered by the insurance policies

    stipulated in the Contract.

    Clause 23.1 Third Party Insurance (including Employers Property)

    Clause 23.2 Minimum Amount of Insurance

    The Contractor carries the risk of liability for any amount over andabove the minimum amount stipulated in the Appendix to Tender as

    well as any deductible stipulated in the insurance policy.

    Clause 24.1 Accident or Injury to Workmen

    Clause 24.2 Insurance Against Accident to Workmen

    The Contractor carries the risk for any exclusions or deductibles

    stipulated in the insurance policy.

    Clause 25.2 Adequacy of Insurances

    The Contractor carries the risk of inadequate insurance cover and

    therefore additional costs in the event that there are significant changes

    to the nature, extent, or programme for the execution of the Works and

    he neglects to inform the insurers.

    Clause 26.1 Compliance with Statutes, Regulations

    The Contractor carries the risk of penalties and liability in the event

    that he fails to conform in all respects with the rules, regulations,

    statutes, ordinances, or other laws of duly constituted authorities,

    public bodies, etc.

    Clause 29.1 Interference with Traffic and Adjoining Properties

    The Contractor carries the risk of liability arising from interfering

    unnecessarily or improperly with the convenience of the public, oraccess to, use and occupation of roads / properties.

    Clause 30.1 Avoidance of Damage to Roads

    Clause 30.2 Transport of Contractors Equipment or Temporary Works

    The Contractor is deemed to have priced the risk of damaging any

    roads or bridges, or the cost of strengthening the same to avoid

    damage.

    Clause 32.1 Contractor to Keep Site Clear

  • 7/27/2019 Fidic 1992 Risk Clauses

    5/8

    5

    Failing which, the contractor runs the risk of being fined or having a

    stop work order imposed on the site, in the event that the state of the

    site constitutes a safety hazard.

    Clause 36.4 Cost of Tests not Provided for

    Clause 37.4 RejectionThe Contractor runs the risk of paying for additional tests required by

    the Engineer in the event that the test results show that the materials,

    plant, or workmanship are not in accordance with the provisions of the

    Contract. Breach of Clause 37.4 further carries the risk of termination

    under clause 63.1(c).

    Clause 38.2 Uncovering and Making Openings

    In the event that the Contractor covers up work in breach of clause

    38.1, he runs the risk of having to pay for all costs arising from his

    having to carry out any of the Engineers instructions in this regard,

    such as uncovering the work, making openings, etc.Clause 39.1 Removal of Improper Work, Materials or Plant

    Breach of this clause by the Contractor exposes him to a two fold risk.

    The first is that the Contractor may have to pay for the costs of another

    contractor brought in by the Employer to do this work (clause 39.2),

    and the second, a much more serious risk, is termination under clause

    63.1(c).

    Clause 41.1 Commencement of Works

    If the Contractor fails to commence the works without reasonable

    excuse, he runs the risk of termination in accordance with clause

    63.1(b)(i).

    Clause 42.2 Failure to Give Possession

    This would entitle the Contractor to Claim an Extension of Time for

    completion under clause 44. However, the Contractor runs the risk that

    the Engineer may not make a determination (he is not bound to) in

    relation to the Contractors claim, in the event that the Contractor does

    not give adequate notice under the provisions of clause 44.2.

    Clause 44.2 Contractor to Provide Notification and Detailed Particulars

    In the event that the Contractor fails to provide notification and

    detailed particulars, the Contractor runs the risk that the Engineer maynot make a determination (the clause says the Engineer is not bound

    to) in relation to the Contractors claim for an Extension of Time.

    Clause 45.1 Restriction on Working Hours

    The Contractor is to note that working nights or on public holidays,

    runs the risk of disapproval by the Engineer, or of the local authorities

    for noise pollution / disturbance.

    Clause 46.1 Rate of Progress

    If the Contractors rate of progress is slow, for issues that do not entitle

    him to an extension of time, he runs the risk of either termination under

  • 7/27/2019 Fidic 1992 Risk Clauses

    6/8

    6

    Clause 63.1(b)(ii), or being asked to expedite the Works to comply

    with the Time for Completion at his own cost.

    Clause 47.1 Liquidated Damages for DelayIf the Contractor fails to comply with the Time for Completion, he runs

    the risk of having liquidated damages levied against him, which

    depending on the period of delay, can amount to as much as 10% of

    the contract sum.

    Clause 49.4 Contractors Failure to Carry Out Instructions

    During the Defects Liability Period, the Contractor shall, within a

    reasonable time, carry out any instructions of the Engineer to execute

    any remedial works required as a result of faulty materials, plant or

    workmanship, failing which he runs the risk of being liable to the

    Employer of the costs of instructing another contractor to carry out thework.

    Clause 51.1 Variations

    The Contractor shall carry out any variations validly issued to him by

    the Engineer under the Contract, which shall be valued at the rates and

    prices set out in the Contract. The Contractor here runs the risk that if

    his overhead and profit is not uniformly distributed throughout his

    rates, the Employer / Engineer may decide to omit or vary a highly

    priced item, or increase the quantities of a low priced item, resulting in

    reduced profitability or loss for the Contractor.

    Clause 52.2 Notice required for Variations

    No varied work instructed to be done by the Engineer shall be valued

    under sub-clauses 52.1 & 52.2 unless, within 14 days of the date of

    such instruction and, other than in the case of omitted work, before the

    commencement of the varied work, notice shall have been given of the

    intention to claim extra payment or a varied price or rate. The

    Contractor here runs the risk that if he does not give his notice as

    required under the clause, he will not be able to claim for the varied

    work.

    Clause 53.4 Failure to ComplyTo successfully lodge a claim under the Contract, the Contractor must

    give the required notices and detailed information required under

    clauses 53.1, 53.2, and 53.3. Failing which, the Contractor runs the risk

    of being paid an amount that will not exceed such amount as can be

    verified by contemporary records.

    Clause 54 Contractors Equipment, Temporary Works, and Materials

    Although the Employer has an obligation to assist the Contractor in

    importing his equipment and materials into the country, this remains at

    the Contractors risk.

    Clause 57.2 Breakdown of Lump Sum Items

  • 7/27/2019 Fidic 1992 Risk Clauses

    7/8

    7

    The Contractor runs the risk of any mistakes during his quantity take

    off to arrive at any lump sum price items in the Contract.

    Clause 59 Nominated Subcontractors

    The concept of the Nominated Subcontractor arises from the

    Employers desire to secure preferential rates from specialistsubcontractors. The latter are keener to offer more competitive prices

    directly to the Employer either due to repeat business with or

    guaranteed payments from the Employer.

    The Contractors mark up onto the nominated subcontractors price for

    co-ordination and attendance tends to be minimal varying from 2.5%

    to 12.5%. This is normally not enough to cover his risk, for once he

    has given his acceptance to the nomination, the Contractor becomes

    fully liable for the performance of the nominated subcontractor to the

    same extent that he is liable for his own domestic subcontractors

    performance.The only advantage to the Contractor of such an arrangement is the

    reduction in the payment risk as he does not have to pay the nominated

    subcontractor until after the corresponding payment is received by the

    Employer. However, this is becoming more and more a thing of the

    past, as many jurisdictions have now outlawed pay when paid clauses

    such as the United Kingdom, Australia, and Singapore, to name but a

    few.

    Clause 60.5 Statement at Completion

    In his statement at completion, the Contractor must include all claims

    on any matter arising out of or in connection with the Contract or

    execution of the Works, otherwise he runs the risk of being barred

    from raising these claims at any time in the future, unless such issues

    arise after the date of the Statement of Completion.

    Clause 60.10 Time for Payment

    The General Conditions of Contract allow the Contractor two remedies

    for delayed payments. Interest at the rate stated in the Appendix to

    Tender, and the Contractors entitlement to slow down or suspend the

    Works under clause 69. These rights are sometimes deleted in the

    Conditions of Particular Application, with the Contractor running therisk of potentially damaging delays and costs as a result of payments

    that are excessively and unduly delayed.

    Clause 63.1 Default of Contractor

    Many of the risks related to this clause have already been highlighted

    earlier. Suffice it to say here that the Contractor must remain vigilant

    and be aware of any notice issued to him under the Contract which

    could lead to the invoking of this clause by the Engineer.

    Clause 65.2 Special Risks

    This refers to clause 20.4(b) and excludes rebellion, revolution,

    insurrection, or military or usurped power, or civil war, unless they

  • 7/27/2019 Fidic 1992 Risk Clauses

    8/8

    8

    relate to the country in which the Works are to be executed. This

    transfers the risk back on to the Contractor in a situation where he has

    ordered materials from abroad and which are unavoidably delayed as a

    result of any one of these risks taking place in the country of origin of

    these materials.Clause 66.1 Release from Performance

    If any circumstance outside the control of both parties arises after the

    issue of the Letter of Acceptance which renders it impossible or

    unlawful for either or both parties to fulfill his or their contractual

    obligations, or under the law governing the Contract the parties are

    released from further performance, then the Parties shall be discharged

    from the Contract.

    Clause 67.1 Engineers Decision

    If the Contractor is not satisfied with the Engineers decision under thisclause he must give notice of his intention to commence arbitration

    within 70 days of receiving such decision, otherwise the Engineers

    decision becomes final and binding.

    Clause 70 Changes in Cost and Legislation

    The Contractors risk related to changes in costs either as a result of

    price fluctuation or changes in legislation is transferred to the

    Employer to the extent stated in the Conditions of Particular

    Application.

    Clause 71 Currency Restrictions

    Clause 72 Rates of Exchange

    The Contractors risk related to currency restrictions and changes in

    the rates of exchange of a foreign currency where the Contract

    provides that part or whole payment is made in that currency is

    transferred to the Employer.