FHWA Update Butch Wlaschin, P.E. Director, Office of Asset Management AASHTO Highway Subcommittee on...
-
Upload
myrtle-jenkins -
Category
Documents
-
view
214 -
download
1
Transcript of FHWA Update Butch Wlaschin, P.E. Director, Office of Asset Management AASHTO Highway Subcommittee on...
FHWA Update
Butch Wlaschin, P.E.Director, Office of Asset Management
AASHTO Highway Subcommittee on Construction 2010 Annual MeetingBurlington, Vermont
Presentation Overview
• Update on Recovery Act and Reauthorization
• Current Issues• FHWA Programs & Initiatives
Update - Recovery Act
Recovery Act Work Types by % of Contract Value
4.5%
5.3%
2.3%
7.5%
2.9%
50.8%
17.8%
5.0%
4.0%
Bridge Improvement
Bridge Replacement
New Bridge Construction
New Construction
Other
Pavement Improvement
Pavement Widening
Safety/Traffic Management
Transportation En-hancements
Average Wage Rates for Recovery Act Contracts
PUERTO R
ICO
TEXAS
ARKANSAS
NEW M
EXICO
MIS
SISSIP
PI
NORTH C
AROLI
NA
INDIA
NA
SOUTH D
AKOTA
IOW
A
MARYLA
ND
NEW H
AMPSHIR
E
SOUTH C
AROLI
NA
VERMO
NT
WIS
CONSIN
LOUIS
IANA
DELAW
ARE
WEST V
IRG
INIA
OHIO
DISTRIC
T OF C
OLU
MBIA
ARIZO
NA
NEW Y
ORK
MIS
SOURI
CONNECTIC
UT
ILLI
NOIS
NEVADA
MASSACHUSETTS
CALIFO
RNIA
$0
$10
$20
$30
$40
$50
$60
$70
Recovery Act - Total Contractor Work Hours (Month)
Recovery Act Expenditures vs. Obligations
(by Improvement Type)
ObligationsExpenditures
Update - Reauthorization
• On-going discussions with Hill• OST principles to be issued• Funding continues to be the problem• Most likely to see focus on performance• Safety, Livable Communities,
Sustainability, Performance• More to follow
Current Issues
• Project Labor Agreements• Pavement Marking Material Shortage• Alternate Bidding For Pavement
Type Selection
Project Labor Agreements• February 6, 2009 President Obama signed an Executive
Order titled “Use of Project Labor Agreement for Federal Construction Projects.”
• Encourages executive agencies to consider requiring the use of PLAs on large-scale direct Federal construction projects (defined as a project with a total cost of $25 million or more).
• May 7, 2010 – FHWA Administrator Mendez signed a memo titled: “Interim guidance on the use of Project Labor Agreements”– Provides factors for agencies to use in evaluating whether a
PLA is in the government’s interest– Allows Division Offices and States to approve PLAs on a
project-by-project basis in accordance with the memo
Pavement Marking Material Shortage
• In June 2010, State DOTs began to experience shortages of four key raw materials used to produce waterborne traffic paint, extruded and spray thermoplastics, and epoxy
• Only 50-60% of normal supply available; Industry indicated 6-8 week backlog in orders
• Shortages may last until the end of the 2010 calendar year.
• Not all states may perceive a shortage as paint suppliers honored long-term supply contracts for state maintenance contracts
• FHWA encourages our Division Offices to work with State DOTs on a case-by-case basis in accordance with contract requirements.
Alternate Bidding For Pavement Type Selection
• Equivalent designs• Discount rate• Uncertainty• Rehabilitation strategy• Subjective factors
• Commodity price adjustments
• I/D provisions• Materials quantities• Approval process
• Memo issued November 13, 2008• Clarifies and consolidates FHWA policy• Applies to Federal-aid on the NHS• Alt Bidding is “not encouraged” but can
be used in “rare instances”….
FHWA Programs & Initiatives
• Every Day Counts Initiative• TCM Steering Committee Update• Construction Program
Baseline Review• Construction Engineer
Training Course
Every Day Counts
• Design-Build • Construction Manager/General
Contractor (CM/GC)• Flexibilities in Utility
Accommodation & Relocation
Shortening Project Delivery Initiatives in Design and Construction
Accelerated Project Delivery Task Force
• AASHTO – ARTBA – AGC Task Force• Provides a two pronged approach for
addressing APD that complements the FHWA Every Day Counts initiative
• Provided initial recommendations to FHWA in March
• Developing a work plan of APD activities – to be completed by August.
Transportation Construction ManagementSteering Committee Update
• TCM focus on quality, efficiency, risk management
• Current TCM Activities– "A Guidebook for Selecting Highway Capital Project
Delivery Methods and Alternative Contracting Strategies”– 2nd International Construction Management Conference
February 2011, Orlando, FL (in conjunction w/ ARTBA)
– Sponsored NCHRP 10-38 “Alternate Quality Systems”
– Pooled fund program
Construction Program Baseline Review
• Purpose – enhance the delivery of the construction program for improved performance of the NHS
• Scope change – use of self assessment tool and regional peer exchange workshops to obtain construction program information
• Why? – faster results, less resource demand• Regional workshops – to identify, discuss
and recommend solutions to critical __construction-related topics (5 workshops planned)
- Formerly Construction Program Evaluations
Timeline - Oct 2010: Activity work plan
Jan 2011: RFP for support contract
Spring 2011: Self assessment tool development
Spring 2011: Plan and coordinate 1st regional peer exchange workshop
June 2011: Conduct self assessment for 1st regional group of states
July 2011: Conduct 1st peer exchange
Summer 2013 5 regional peer exchanges conducted over 2 years
Construction Program Baseline Review
Construction Engineer Training Course
• Phase 1 – an Academy concept originally scoped, work completed October 2009
• Scope being modified - training to be targeted towards CM’s and management practices– Development of a construction curriculum– Will look at developing a CM training course
• New outline to be vetted with AASHTO and TCCC by Fall 2010
• Phase 2 - Plan to initiate in summer 2011
Performance contracting is an approach where the owner agency specifies a set of clearly defined performance goals – rather than methods – for construction projects; and the contractor enjoys the freedom to define how to accomplish the goals. FHWA is piloting an implementation framework for Performance Contracting for Construction with up to six pilot states.
Become a Pilot State and receive:• Free technical assistance• Additional consideration for Highway for LIFE funds• Opportunity to be among the first to implement this new and
innovative contracting approach
For more information on Performance Contracting for Construction or to learn how to become a pilot state, visit http://www.fhwa.gov/construction/library.cfm or contact:
Mary Huie, Federal Highway Administration202-366-3039 | [email protected]
LEADERS WANTED: Become a Pilot State!