FGRU URAN 08.12.2015 rev.02

3
Activity ID Activity Name Duration Start Finish INSTALLAT INSTALLATION OF STANDBY FGRU 458d 09-Nov-15 08-Feb-17 MILESTON MILESTONES 38d 09-Nov-15 16-Dec-15 A1000 Receipt of LOI 0d 09-Nov-15 A1010 Kick off Meeting 0d 08-Dec-15 08-Dec-15 A1020 Submission and Approval of DCI 8d 08-Dec-15 15-Dec-15 A1030 Submission of WCP/Insurance 1d 16-Dec-15 16-Dec-15 A1040 Contract Signing 1d 08-Dec-15 08-Dec-15 ENGINEE ENGINEERING 114d 08-Dec-15 30-Mar-16 A1050 Submission and approval of Overall Plot plan 15d 08-Dec-15 22-Dec-15 A1060 Submission and approval of Soil report 15d 06-Jan-16 20-Jan-16 A1070 Submission and approval of design mix 15d 21-Jan-16 04-Feb-16 A1080 Submission and approval of Foundation drawing of Compressor Shed 15d 05-Feb-16 19-Feb-16 A1090 Submission and approval of Shed Structure drawing 21d 23-Feb-16 14-Mar-16 A1100 Submission and approval of Process design basis 10d 20-Dec-15 29-Dec-15 A1110 Submission and approval of PFD 10d 30-Dec-15 08-Jan-16 A1120 Submission and Approval of P&ID of the Package 10d 05-Jan-16 14-Jan-16 A1130 Submission and Approval of Process datasheet of Compressor 31d 15-Jan-16 14-Feb-16 A1140 Submission and Approval of Mechanical datasheet of Compressor 31d 15-Jan-16 14-Feb-16 A1150 Submission and Approval of datasheet of Motor 31d 15-Jan-16 14-Feb-16 A1160 Foundation drawing & design calculation for Standby Flare Gas Compressor 15d 17-Feb-16 02-Mar-16 A1170 Submission and approval of datasheet of EOT crane 10d 09-Mar-16 18-Mar-16 A1180 Submission and Approval of PMS 10d 16-Dec-15 25-Dec-15 A1190 Submission and Approval of VMS 10d 16-Dec-15 25-Dec-15 A1200 Submission and Approval of Process datasheet of Cooler 21d 15-Feb-16 06-Mar-16 A1210 Submission and Approval of Process datasheet of Compressor KODs 15d 26-Jan-16 09-Feb-16 A1220 Submission and approval of Foundation drawing of Compressor auxillaries(Lube oil cooler, KODs etc) 15d 10-Feb-16 24-Feb-16 A1230 Submission and approval of Layout of OWS line 21d 07-Jan-16 27-Jan-16 A1240 Submission and approval of datasheet of Field Instruments 15d 20-Feb-16 05-Mar-16 A1250 Submission and approval of datasheet of MOV 15d 15-Feb-16 29-Feb-16 A1260 Submission and approval of Datasheet of ESDV 15d 15-Feb-16 29-Feb-16 A1270 Submission and approval of Electrical design basis 10d 15-Feb-16 24-Feb-16 A1280 Submission and approval of Electrical load list 10d 25-Feb-16 05-Mar-16 A1290 Submission and approval of SLD 10d 06-Mar-16 15-Mar-16 A1300 Submission and approval of Electrical & Instrumentation C 15d 16-Mar-16 30-Mar-16 A1310 Submission and approval of electrical cable sizing 15d 16-Mar-16 30-Mar-16 A1330 Submission and approval of Instrument index 15d 25-Jan-16 08-Feb-16 A1340 Submission and approval of I/O list 10d 09-Feb-16 18-Feb-16 A1350 Submission and approval of Instrument cable schedule 15d 19-Feb-16 04-Mar-16 A1360 Submission and approval of F&G layout & datasheet 15d 08-Mar-16 22-Mar-16 A1370 Submission and approval of PLC based panel 15d 19-Feb-16 04-Mar-16 A1380 Submission and approval of Piping GAD 21d 28-Jan-16 17-Feb-16 A1390 Submission and approval of Equipment layout 15d 22-Feb-16 07-Mar-16 Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar 2016 2017 08-Feb- 16-Dec-15, MILESTONES Receipt of LOI 30-Mar-16, ENGINEERING PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE CLIENT- ONGC-URAN PROJECT SCHEDULE LSTK- SAVAIR ENERGY LTD. Actual Work Remaining Work Critical Remaining Work Milestone Summary Page 1 of 3 TASK filter: All Activities © Primavera Systems, Inc.

description

scheduling

Transcript of FGRU URAN 08.12.2015 rev.02

Page 1: FGRU URAN 08.12.2015 rev.02

Activity ID Activity Name Duration Start Finish

INSTALLATION OF STANDBY FGRUINSTALLATION OF STANDBY FGRU 458d 09-Nov-15 08-Feb-17

MILESTONESMILESTONES 38d 09-Nov-15 16-Dec-15

A1000 Receipt of LOI 0d 09-Nov-15

A1010 Kick off Meeting 0d 08-Dec-15 08-Dec-15

A1020 Submission and Approval of DCI 8d 08-Dec-15 15-Dec-15

A1030 Submission of WCP/Insurance 1d 16-Dec-15 16-Dec-15

A1040 Contract Signing 1d 08-Dec-15 08-Dec-15

ENGINEERINGENGINEERING 114d 08-Dec-15 30-Mar-16

A1050 Submission and approval of Overall Plot plan 15d 08-Dec-15 22-Dec-15

A1060 Submission and approval of Soil report 15d 06-Jan-16 20-Jan-16

A1070 Submission and approval of design mix 15d 21-Jan-16 04-Feb-16

A1080 Submission and approval of Foundation drawing of Compressor Shed

15d 05-Feb-16 19-Feb-16

A1090 Submission and approval of Shed Structure drawing 21d 23-Feb-16 14-Mar-16

A1100 Submission and approval of Process design basis 10d 20-Dec-15 29-Dec-15

A1110 Submission and approval of PFD 10d 30-Dec-15 08-Jan-16

A1120 Submission and Approval of P&ID of the Package 10d 05-Jan-16 14-Jan-16

A1130 Submission and Approval of Process datasheet of Compressor

31d 15-Jan-16 14-Feb-16

A1140 Submission and Approval of Mechanical datasheet of Compressor

31d 15-Jan-16 14-Feb-16

A1150 Submission and Approval of datasheet of Motor 31d 15-Jan-16 14-Feb-16

A1160 Foundation drawing & design calculation for Standby FlareGas Compressor

15d 17-Feb-16 02-Mar-16

A1170 Submission and approval of datasheet of EOT crane 10d 09-Mar-16 18-Mar-16

A1180 Submission and Approval of PMS 10d 16-Dec-15 25-Dec-15

A1190 Submission and Approval of VMS 10d 16-Dec-15 25-Dec-15

A1200 Submission and Approval of Process datasheet of Cooler 21d 15-Feb-16 06-Mar-16

A1210 Submission and Approval of Process datasheet of Compressor KODs

15d 26-Jan-16 09-Feb-16

A1220 Submission and approval of Foundation drawing of Compressor auxillaries(Lube oil cooler, KODs etc)

15d 10-Feb-16 24-Feb-16

A1230 Submission and approval of Layout of OWS line 21d 07-Jan-16 27-Jan-16A1240 Submission and approval of datasheet of Field Instruments 15d 20-Feb-16 05-Mar-16

A1250 Submission and approval of datasheet of MOV 15d 15-Feb-16 29-Feb-16A1260 Submission and approval of Datasheet of ESDV 15d 15-Feb-16 29-Feb-16

A1270 Submission and approval of Electrical design basis 10d 15-Feb-16 24-Feb-16

A1280 Submission and approval of Electrical load list 10d 25-Feb-16 05-Mar-16

A1290 Submission and approval of SLD 10d 06-Mar-16 15-Mar-16

A1300 Submission and approval of Electrical & Instrumentation Cable layout15d 16-Mar-16 30-Mar-16

A1310 Submission and approval of electrical cable sizing 15d 16-Mar-16 30-Mar-16

A1330 Submission and approval of Instrument index 15d 25-Jan-16 08-Feb-16

A1340 Submission and approval of I/O list 10d 09-Feb-16 18-Feb-16

A1350 Submission and approval of Instrument cable schedule 15d 19-Feb-16 04-Mar-16

A1360 Submission and approval of F&G layout & datasheet 15d 08-Mar-16 22-Mar-16

A1370 Submission and approval of PLC based panel 15d 19-Feb-16 04-Mar-16

A1380 Submission and approval of Piping GAD 21d 28-Jan-16 17-Feb-16

A1390 Submission and approval of Equipment layout 15d 22-Feb-16 07-Mar-16

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2016 2017

08-Feb-17, INSTALLATION OF STANDBY FGRU

16-Dec-15, MILESTONES

Receipt of LOI

30-Mar-16, ENGINEERING

PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE

CLIENT- ONGC-URAN

PROJECT SCHEDULE LSTK- SAVAIR ENERGY LTD.

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 1 of 3 TASK filter: All Activities

© Primavera Systems, Inc.

Page 2: FGRU URAN 08.12.2015 rev.02

Activity ID Activity Name Duration Start Finish

A1400 Submission and approval of Piping Isometrics 15d 12-Mar-16 26-Mar-16

A1410 Submission and approval of Flexibility analysis 15d 12-Mar-16 26-Mar-16

A1420 Submission and approval of Torsional analysis 10d 15-Mar-16 24-Mar-16

PROCUREMENTPROCUREMENT 349d 08-Dec-15 20-Nov-16

A1430 Placement of order for Soil Investigation 5d 23-Dec-15 27-Dec-15

A1440 Placement of Order for Screw Compressor package 10d 08-Dec-15 17-Dec-15

A1450 Placement of Order for EOT crane 20d 15-Feb-16 05-Mar-16

A1460 Reciept of EOT crane at site 140d 06-Mar-16 23-Jul-16

A1470 Placement of order of Piping items 10d 12-Mar-16 21-Mar-16

A1480 Reciept of Piping items at Ambernath 84d 22-Mar-16 13-Jun-16

A1490 Placement of order of Valves 15d 26-Dec-15 09-Jan-16

A1500 Placement of order of Control valves 25d 06-Mar-16 30-Mar-16

A1510 Reciept of valves at site 140d 10-Jan-16 28-May-16

A1520 Reciept of Control valves at site 196d 31-Mar-16 12-Oct-16

A1525 Placement of order of PLC panel 216d 05-Mar-16 06-Oct-16

A1530 Placement of order of ESDV 25d 01-Mar-16 25-Mar-16

A1535 Receipt of PLC panel at site 7d 07-Oct-16 13-Oct-16

A1540 Reciept of ESDV at site 196d 26-Mar-16 07-Oct-16

A1550 Placement of order of PSV 10d 06-Mar-16 15-Mar-16

A1560 Reciept of PSV at site 140d 16-Mar-16 02-Aug-16

A1570 Placement of Order for Fire detection items 15d 14-Aug-16* 28-Aug-16

A1580 Reciept of Fire detection item at site 84d 29-Aug-16 20-Nov-16

A1590 Placement of order of RMC/Cement & TMT bar 2d 23-Feb-16 24-Feb-16

A1600 Receipt of RMC/Cement & TMT bar at site 2d 25-Feb-16 26-Feb-16

A1610 Placement of order of instruments & Fittings 20d 23-Mar-16 11-Apr-16

A1620 Placement of order of Instrument and electrical Cables 20d 05-Mar-16 24-Mar-16

A1630 Receipt of Cables, JBs at site 70d 25-Mar-16 02-Jun-16

A1640 Placement of order of JBs 7d 05-Mar-16 11-Mar-16

A1650 Receipt of Instruments & Fittings at site 70d 12-Apr-16 20-Jun-16

A1660 Receipt of compressor package 336d 18-Dec-15 17-Nov-16

CONSTRUCTIONCONSTRUCTION 458d 09-Nov-15 08-Feb-17

A1670 Site mobilization for soil Investigation 2d 04-Jan-16 05-Jan-16

A1680 Starting Soil grading activity at site 15d 30-Dec-15 13-Jan-16

A1690 Pre fabrication of Structural shed at Ambernath works 35d 17-Mar-16 20-Apr-16

A1700 Pre fabrication of spools at ambernath works 80d 14-Jun-16 01-Sep-16

A1710 Pre fabrication of pipe support at ambernath works 35d 02-Sep-16 06-Oct-16

A1720 Site Mobilization for Civil and Structural works 1d 22-Feb-16 22-Feb-16

A1730 Tapping of Suction & Discharge line 20d 22-Feb-16 12-Mar-16

A1740 Compressor Shed Foundation casting work 30d 23-Feb-16 23-Mar-16

A1750 Erection of Compressor house shed 60d 21-Apr-16 19-Jun-16

A1760 Installation of EOT crane 10d 20-Jun-16 29-Jun-16

A1765 Lighting 12d 03-Jul-16 14-Jul-16

A1770 Commissioning of crane 2d 30-Jun-16 01-Jul-16

A1780 Raft & pedestal foundation work for Cooler, Oil seperators 40d 26-Mar-16 04-May-16

A1790 Underground piping work for OWS line 60d 15-Apr-16 13-Jun-16

A1800 Erection of Compressor auxillaries at its location 28d 04-Oct-16 31-Oct-16

A1805 Earthing 15d 04-Oct-16 18-Oct-16

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2016 2017

20-Nov-16, PROCUREMENT

08-Feb-17, CONSTRUCTION

PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE

CLIENT- ONGC-URAN

PROJECT SCHEDULE LSTK- SAVAIR ENERGY LTD.

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 2 of 3 TASK filter: All Activities

© Primavera Systems, Inc.

Page 3: FGRU URAN 08.12.2015 rev.02

Activity ID Activity Name Duration Start Finish

A1810 Raft & Pedestal foundation casting of Compressor & Motor 40d 07-May-16 15-Jun-16

A1820 Erection of Compressor package 20d 25-Nov-16 14-Dec-16

A1825 Feeder Modification 12d 06-Dec-16 17-Dec-16

A1830 Installation of Pipe supports at site 15d 04-Oct-16 18-Oct-16

A1835 Hot Tapping 20d 09-Oct-16 28-Oct-16

A1840 Interconnection piping work 20d 15-Dec-16 03-Jan-17

A1850 Cleaning & Flushing 3d 04-Jan-17 06-Jan-17

A1860 Hydrotesting 4d 07-Jan-17 10-Jan-17

A1870 Installation and calibration of Instruments 21d 11-Jan-17 31-Jan-17

A1880 Laying of cable trays 40d 10-Sep-16* 19-Oct-16

A1885 Panel Erection and commisioning 7d 10-Sep-16 16-Sep-16

A1890 Laying and termination of Cables 40d 20-Oct-16 28-Nov-16

A1900 Loop checking of Instrument cables 6d 29-Nov-16 04-Dec-16

A1910 DCS modification 21d 09-Nov-15 29-Nov-15

A1920 Precommissioning 7d 11-Jan-17 17-Jan-17

A1930 Commissioning & PGTR 3d 18-Jan-17 20-Jan-17

A1940 Punch points 10d 21-Jan-17 30-Jan-17

A1950 Handing over 9d 31-Jan-17 08-Feb-17

Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2016 2017

PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE

CLIENT- ONGC-URAN

PROJECT SCHEDULE LSTK- SAVAIR ENERGY LTD.

Actual Work

Remaining Work

Critical Remaining Work

Milestone

Summary Page 3 of 3 TASK filter: All Activities

© Primavera Systems, Inc.