Activity ID Activity Name Duration Start Finish
INSTALLATION OF STANDBY FGRUINSTALLATION OF STANDBY FGRU 458d 09-Nov-15 08-Feb-17
MILESTONESMILESTONES 38d 09-Nov-15 16-Dec-15
A1000 Receipt of LOI 0d 09-Nov-15
A1010 Kick off Meeting 0d 08-Dec-15 08-Dec-15
A1020 Submission and Approval of DCI 8d 08-Dec-15 15-Dec-15
A1030 Submission of WCP/Insurance 1d 16-Dec-15 16-Dec-15
A1040 Contract Signing 1d 08-Dec-15 08-Dec-15
ENGINEERINGENGINEERING 114d 08-Dec-15 30-Mar-16
A1050 Submission and approval of Overall Plot plan 15d 08-Dec-15 22-Dec-15
A1060 Submission and approval of Soil report 15d 06-Jan-16 20-Jan-16
A1070 Submission and approval of design mix 15d 21-Jan-16 04-Feb-16
A1080 Submission and approval of Foundation drawing of Compressor Shed
15d 05-Feb-16 19-Feb-16
A1090 Submission and approval of Shed Structure drawing 21d 23-Feb-16 14-Mar-16
A1100 Submission and approval of Process design basis 10d 20-Dec-15 29-Dec-15
A1110 Submission and approval of PFD 10d 30-Dec-15 08-Jan-16
A1120 Submission and Approval of P&ID of the Package 10d 05-Jan-16 14-Jan-16
A1130 Submission and Approval of Process datasheet of Compressor
31d 15-Jan-16 14-Feb-16
A1140 Submission and Approval of Mechanical datasheet of Compressor
31d 15-Jan-16 14-Feb-16
A1150 Submission and Approval of datasheet of Motor 31d 15-Jan-16 14-Feb-16
A1160 Foundation drawing & design calculation for Standby FlareGas Compressor
15d 17-Feb-16 02-Mar-16
A1170 Submission and approval of datasheet of EOT crane 10d 09-Mar-16 18-Mar-16
A1180 Submission and Approval of PMS 10d 16-Dec-15 25-Dec-15
A1190 Submission and Approval of VMS 10d 16-Dec-15 25-Dec-15
A1200 Submission and Approval of Process datasheet of Cooler 21d 15-Feb-16 06-Mar-16
A1210 Submission and Approval of Process datasheet of Compressor KODs
15d 26-Jan-16 09-Feb-16
A1220 Submission and approval of Foundation drawing of Compressor auxillaries(Lube oil cooler, KODs etc)
15d 10-Feb-16 24-Feb-16
A1230 Submission and approval of Layout of OWS line 21d 07-Jan-16 27-Jan-16A1240 Submission and approval of datasheet of Field Instruments 15d 20-Feb-16 05-Mar-16
A1250 Submission and approval of datasheet of MOV 15d 15-Feb-16 29-Feb-16A1260 Submission and approval of Datasheet of ESDV 15d 15-Feb-16 29-Feb-16
A1270 Submission and approval of Electrical design basis 10d 15-Feb-16 24-Feb-16
A1280 Submission and approval of Electrical load list 10d 25-Feb-16 05-Mar-16
A1290 Submission and approval of SLD 10d 06-Mar-16 15-Mar-16
A1300 Submission and approval of Electrical & Instrumentation Cable layout15d 16-Mar-16 30-Mar-16
A1310 Submission and approval of electrical cable sizing 15d 16-Mar-16 30-Mar-16
A1330 Submission and approval of Instrument index 15d 25-Jan-16 08-Feb-16
A1340 Submission and approval of I/O list 10d 09-Feb-16 18-Feb-16
A1350 Submission and approval of Instrument cable schedule 15d 19-Feb-16 04-Mar-16
A1360 Submission and approval of F&G layout & datasheet 15d 08-Mar-16 22-Mar-16
A1370 Submission and approval of PLC based panel 15d 19-Feb-16 04-Mar-16
A1380 Submission and approval of Piping GAD 21d 28-Jan-16 17-Feb-16
A1390 Submission and approval of Equipment layout 15d 22-Feb-16 07-Mar-16
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2016 2017
08-Feb-17, INSTALLATION OF STANDBY FGRU
16-Dec-15, MILESTONES
Receipt of LOI
30-Mar-16, ENGINEERING
PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE
CLIENT- ONGC-URAN
PROJECT SCHEDULE LSTK- SAVAIR ENERGY LTD.
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 3 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Duration Start Finish
A1400 Submission and approval of Piping Isometrics 15d 12-Mar-16 26-Mar-16
A1410 Submission and approval of Flexibility analysis 15d 12-Mar-16 26-Mar-16
A1420 Submission and approval of Torsional analysis 10d 15-Mar-16 24-Mar-16
PROCUREMENTPROCUREMENT 349d 08-Dec-15 20-Nov-16
A1430 Placement of order for Soil Investigation 5d 23-Dec-15 27-Dec-15
A1440 Placement of Order for Screw Compressor package 10d 08-Dec-15 17-Dec-15
A1450 Placement of Order for EOT crane 20d 15-Feb-16 05-Mar-16
A1460 Reciept of EOT crane at site 140d 06-Mar-16 23-Jul-16
A1470 Placement of order of Piping items 10d 12-Mar-16 21-Mar-16
A1480 Reciept of Piping items at Ambernath 84d 22-Mar-16 13-Jun-16
A1490 Placement of order of Valves 15d 26-Dec-15 09-Jan-16
A1500 Placement of order of Control valves 25d 06-Mar-16 30-Mar-16
A1510 Reciept of valves at site 140d 10-Jan-16 28-May-16
A1520 Reciept of Control valves at site 196d 31-Mar-16 12-Oct-16
A1525 Placement of order of PLC panel 216d 05-Mar-16 06-Oct-16
A1530 Placement of order of ESDV 25d 01-Mar-16 25-Mar-16
A1535 Receipt of PLC panel at site 7d 07-Oct-16 13-Oct-16
A1540 Reciept of ESDV at site 196d 26-Mar-16 07-Oct-16
A1550 Placement of order of PSV 10d 06-Mar-16 15-Mar-16
A1560 Reciept of PSV at site 140d 16-Mar-16 02-Aug-16
A1570 Placement of Order for Fire detection items 15d 14-Aug-16* 28-Aug-16
A1580 Reciept of Fire detection item at site 84d 29-Aug-16 20-Nov-16
A1590 Placement of order of RMC/Cement & TMT bar 2d 23-Feb-16 24-Feb-16
A1600 Receipt of RMC/Cement & TMT bar at site 2d 25-Feb-16 26-Feb-16
A1610 Placement of order of instruments & Fittings 20d 23-Mar-16 11-Apr-16
A1620 Placement of order of Instrument and electrical Cables 20d 05-Mar-16 24-Mar-16
A1630 Receipt of Cables, JBs at site 70d 25-Mar-16 02-Jun-16
A1640 Placement of order of JBs 7d 05-Mar-16 11-Mar-16
A1650 Receipt of Instruments & Fittings at site 70d 12-Apr-16 20-Jun-16
A1660 Receipt of compressor package 336d 18-Dec-15 17-Nov-16
CONSTRUCTIONCONSTRUCTION 458d 09-Nov-15 08-Feb-17
A1670 Site mobilization for soil Investigation 2d 04-Jan-16 05-Jan-16
A1680 Starting Soil grading activity at site 15d 30-Dec-15 13-Jan-16
A1690 Pre fabrication of Structural shed at Ambernath works 35d 17-Mar-16 20-Apr-16
A1700 Pre fabrication of spools at ambernath works 80d 14-Jun-16 01-Sep-16
A1710 Pre fabrication of pipe support at ambernath works 35d 02-Sep-16 06-Oct-16
A1720 Site Mobilization for Civil and Structural works 1d 22-Feb-16 22-Feb-16
A1730 Tapping of Suction & Discharge line 20d 22-Feb-16 12-Mar-16
A1740 Compressor Shed Foundation casting work 30d 23-Feb-16 23-Mar-16
A1750 Erection of Compressor house shed 60d 21-Apr-16 19-Jun-16
A1760 Installation of EOT crane 10d 20-Jun-16 29-Jun-16
A1765 Lighting 12d 03-Jul-16 14-Jul-16
A1770 Commissioning of crane 2d 30-Jun-16 01-Jul-16
A1780 Raft & pedestal foundation work for Cooler, Oil seperators 40d 26-Mar-16 04-May-16
A1790 Underground piping work for OWS line 60d 15-Apr-16 13-Jun-16
A1800 Erection of Compressor auxillaries at its location 28d 04-Oct-16 31-Oct-16
A1805 Earthing 15d 04-Oct-16 18-Oct-16
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2016 2017
20-Nov-16, PROCUREMENT
08-Feb-17, CONSTRUCTION
PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE
CLIENT- ONGC-URAN
PROJECT SCHEDULE LSTK- SAVAIR ENERGY LTD.
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 2 of 3 TASK filter: All Activities
© Primavera Systems, Inc.
Activity ID Activity Name Duration Start Finish
A1810 Raft & Pedestal foundation casting of Compressor & Motor 40d 07-May-16 15-Jun-16
A1820 Erection of Compressor package 20d 25-Nov-16 14-Dec-16
A1825 Feeder Modification 12d 06-Dec-16 17-Dec-16
A1830 Installation of Pipe supports at site 15d 04-Oct-16 18-Oct-16
A1835 Hot Tapping 20d 09-Oct-16 28-Oct-16
A1840 Interconnection piping work 20d 15-Dec-16 03-Jan-17
A1850 Cleaning & Flushing 3d 04-Jan-17 06-Jan-17
A1860 Hydrotesting 4d 07-Jan-17 10-Jan-17
A1870 Installation and calibration of Instruments 21d 11-Jan-17 31-Jan-17
A1880 Laying of cable trays 40d 10-Sep-16* 19-Oct-16
A1885 Panel Erection and commisioning 7d 10-Sep-16 16-Sep-16
A1890 Laying and termination of Cables 40d 20-Oct-16 28-Nov-16
A1900 Loop checking of Instrument cables 6d 29-Nov-16 04-Dec-16
A1910 DCS modification 21d 09-Nov-15 29-Nov-15
A1920 Precommissioning 7d 11-Jan-17 17-Jan-17
A1930 Commissioning & PGTR 3d 18-Jan-17 20-Jan-17
A1940 Punch points 10d 21-Jan-17 30-Jan-17
A1950 Handing over 9d 31-Jan-17 08-Feb-17
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar2016 2017
PROJECT TITLE- INSTALLATION OF STANDY BY COMPRESSOR PACKAGE
CLIENT- ONGC-URAN
PROJECT SCHEDULE LSTK- SAVAIR ENERGY LTD.
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 3 of 3 TASK filter: All Activities