Technology Layer. Technology Layer Metamodel Technology Layer Concepts.
FF Physical Layer Components - Fieldbus · PDF fileFF has the physical layer specification as...
Transcript of FF Physical Layer Components - Fieldbus · PDF fileFF has the physical layer specification as...
Name Chakravarthy Akella
Job Title Dy. Manager S&S
Company Pepperl+Fuchs
Bangalore
FF – Physical Layer Components
© 1994 – 2011 Fieldbus Foundation 2
Agenda
- Introduction
- FF Basics
- FF Zone1 and Zone2 Topologies
- System commissioning and maintenance
© 1994 – 2011 Fieldbus Foundation 3
Conventional Instrumentation
4-20mA technique:
Ethernet TCP/IP
Ethernet/TCP/IP Internet/Intranet Work
station
Operations Maintenance
PC/VME Management
Factory
level
Cell-
level
Field-
level
Ex
© 1994 – 2011 Fieldbus Foundation 4
Fieldbus Instrumentation
Ethernet TCP/IP
Operations Maintenance
Cell-
level
PC/VME Management
Ethernet/TCP/IP Internet/Intranet Work
station
Factory
level
Fieldbus EX Fieldbus
Field-
level
© 1994 – 2011 Fieldbus Foundation 5
Expanded View of Process & Instruments
1. Self Diagnostics and communication capabilities of microprocessor based
fieldbus devices helps reduce downtime and improve plant safety.
2. Plant operation and Maintenance personnel can be notified and corrective
actions taken quickly and safely.
Fieldbus Extends View to Field Instrument Traditional 4-20mA View stops at I/O Subsystem
PV
Control System Network
4-20mA
Control System Network
H1
Analog Controller Fieldbus Controller
PV , Mode , Variables , Alarm
Diagnostics , Etc I/O Subsystem
© 1994 – 2011 Fieldbus Foundation 6
FF Design Guides
International Codes and Standards
International Electro technical Commission (IEC)
IEC 61158-1 Introductory Guide
IEC 61158-2 Physical Layer Specification and Service Definition
IEC 61158-3 Data Link Layer (DLL) Service Definition
IEC 61158-4 Data Link Layer (DLL) Protocol Specification
IEC 61158-5 Application Layer Service Specification
IEC 61158-6 Application Layer Protocol Specification
IEC 61158-7 System Management
IEC 61158-8 Conformance Testing
IEC 600079-11 (IEC 60079-27) Fieldbus Intrinsically Safe Concept (FISCO)
© 1994 – 2011 Fieldbus Foundation 7
Foundation Fieldbus Design Guides
Foundation Fieldbus compliance Specification
www.fieldbus.org
FF-569 Host Interoperability Support Test
FF-831 Fieldbus Specification for Power Supplies and Conditioners
FF-844 Fieldbus Specification for Cable
FF 846-1.1 Fieldbus Device Couplers used at Zone2 and Zone1
AG 181 System Engineering Guidelines (Rev 3.1)
© 1994 – 2011 Fieldbus Foundation 8
Fieldbus Physical Layer Design Guides
FF has the physical layer specification as per IEC 61158-2:
Transmission rate of 31.25 kBit/s
Total cable (Trunk + Spurs) distance of 1900m maximum
Maximum spur length 120 m upto 12 devices
Up to 32 devices per segment (Host + 31 field)
Manchester II coding used to transmit data
Data transmission by a ± 9mA modulation signal
Minimum working voltage 9 Volts ( Range is 9-32V) and average current consumption 20mA per device
© 1994 – 2011 Fieldbus Foundation 9
Output Cable Length
No. of communication elements Max. spur output cable length
1 – 12 120m
13 – 14 90m
15 – 18 60m
19 – 24 30m
25 – 32 1m
© 1994 – 2011 Fieldbus Foundation 12
Where is Exe protection required at the
Process Field
■Field Enclosure mounted at Zone2, and Zone1
-Mechanical Impact test
-IP rating
-Material Grade
-Drop test
-Vibration test
■Any Fieldbus cable system installed at Zone2, Zone1
- IS cables ( for operational reasons)
- non-IS cables
- Armor or conduit wiring are common practice
© 1994 – 2011 Fieldbus Foundation 13
Application - Zone1 installations
Non-IS(EEx e)
– Trunk and spurs must be installed in increased safety EEx e
IS ( Limted Power and High Power)
Limited power
– ENTITY and FISCO concepts
High Power
– HPT
Trunk has to be installed in increased safety
Spurs are intrinsically safe
Allows the use of Non IS Power Supplies and IS FieldBarrier
– HPT-IS
Trunk and Spurs are IS
© 1994 – 2011 Fieldbus Foundation 14
Application Area - Zone 1 (EEx d)
Segment Protector Ex me
Zone 1
16..32V
16..32V
230VAC
Fieldbus
Power Hub
Ex e
Instruments
Ex d
Live Disconnect Switch
© 1994 – 2011 Fieldbus Foundation 15
User Benefit : Design guidelines
© 1994 – 2011 Fieldbus Foundation 16
© 1994 – 2011 Fieldbus Foundation 17
IS Fieldbus
High power ( Exe + IS )
High Power IS
Refer AG 181-3.1
-Limited Power
-High Power
© 1994 – 2011 Fieldbus Foundation 20
Application Area - Zone1 IS ENTITY
20..35V 230VAC
Zone 0/1
V = 10.5V
I = 70mA
ENTITY Device Trunk cable < 200m
Number of devices less than 2
No load sharing Redundancy at Power Supply
9V
23mA
ENTITY FF
Power Supply
© 1994 – 2011 Fieldbus Foundation 21
Application Area - Zone1 IS FISCO
20..35V 230VAC
Zone 0/1
V = 12.5V
I = 100mA(IIC)
I = 245mA (IIB)
FISCO Device Trunk cable < 400m
Number of devices less than 5
No load sharing Redundancy at Power Supply
9V
23mA
FISCO FF Power
Supply
© 1994 – 2011 Fieldbus Foundation 22
Can FISCO/ENTITY power supply be Redundant?
© 1994 – 2011 Fieldbus Foundation 23
Standby FISCO Concept
Zone 0/1
FISCO Device Trunk cable < 400m
Number of devices less than 5
No load sharing Redundancy at Power Supply
Same limitations as per FISCO concept
9V
23mA
FISCO FF Power
Supply
A
B
© 1994 – 2011 Fieldbus Foundation 24
© 1994 – 2011 Fieldbus Foundation 25
Zone 1
Zone 0/1
Ex e
Ex ia (FISCO + Entity)
FieldBarrier
16..32V
16..32V
230VAC
Fieldbus
Power Hub
Application Area - Zone1 IS - HPT
Exd Trunk live disconnect switch
© 1994 – 2011 Fieldbus Foundation 26
High power trunk or FieldBarrier concept
Trunk is Ex e( increased safety) and Spurs intrinsically safe
Spurs as per FISCO or Entity IS
Longest cable run possible 1900m(Trunk+Spurs) and 120m Spur
No limitation of voltage and current on trunk
Redundant power supplies possible
Trunk could be live disconnect with approved Exd Switch
Hazardous area application with the least difficulties
Application Area - Zone1 IS HPT
© 1994 – 2011 Fieldbus Foundation 27
DART Application : IS Fieldbus
The first step
Simplifying
validation
MAX power + FISCO
High Power Trunk Intrinsic Safety
© 1994 – 2011 Fieldbus Foundation 28
Simple DART circuit
Ex ib IIC
Time to turn-off: 5…10 µs
© 1994 – 2011 Fieldbus Foundation 29
IF
UF
PF
Initial
Phase Critical Phase
Spark duration tF: 5 µs…2 ms t
U
di/dt
Typical Spark – Physics
Spark voltage
Spark current
© 1994 – 2011 Fieldbus Foundation 30
IF
UF
PF
Initial
Phase Critical Phase
Spark duration with DART tF ≤ 5 µs
U,
I, P
t
Typical Spark – Turned Off by DART
© 1994 – 2011 Fieldbus Foundation 31
DART High Power Intrinsic safety
Provides 8…50 W, intrinsically safe
Detects sparks as they occur
Limits the energy during a fault
Could be used at Conventional(50W) and Fieldbus(8W)
Applications
A completely intrinsically safe fieldbus segment in
gas groups IIB and IIC with real power redundancy and advanced
diagnostics.
The Intrinsically Safe High-Power Trunk
© 1994 – 2011 Fieldbus Foundation 32
DART (HPT-IS) FIELDBUS STRUCTURE
IS Segment Protector
Zone 1/ Zone2
22.5V
360mA
Intrinsically Safe –
Trunk up to 1000m
DCS
-------
Upto 16 IS devices
Each Spur upto
120m
© 1994 – 2011 Fieldbus Foundation 33
Fieldbus Design and validation
Factory Acceptance Tests
– Termination
– Communication
– Parameter measurements
– Segment operation – all typical segments
Site Acceptance Tests
– Network validation
– Noise – Watch out for Frequency Drives
– Electrical characteristics
– Grounding and shielding
– System Functional Tests
– Cable check
– Device parameters measurements
– Signal patterns etc
© 1994 – 2011 Fieldbus Foundation 34
Commissioning until now
Always on the critical path
Manual, step-by-step procedure
Labor intensive
Requires
– Screw driver
– Check sheet
– Pencil
– Multimeter - FF testers
– Oscilloscope
Connect one device at a time
Disconnect after testing
Test Report
© 1994 – 2011 Fieldbus Foundation 35
Integrated and Portable Advanced Diagnostics
Portable Advanced Diagnostics Integrated at Fieldbus Supply
Advanced Diagnostics
Stand Alone
© 1994 – 2011 Fieldbus Foundation 36
Maintenance View
Alarm window view
Network view
Segment-specific status of the physical layer
ADM status view with PRM TAG
FF-Segment
FF-Host
© 1994 – 2011 Fieldbus Foundation 37
Simple Commissioning Steps with ADM
Verify address setting
Wire up devices in the right location
Check shielding
Activate communication
Use automated work procedures
– Testing
– Documentation
All devices at once
Wiring remains undisturbed!
Commissioning Wizard
Test
Report
x
© 1994 – 2011 Fieldbus Foundation 38
Commissioning Wizard
With Expert System Support
Takes snapshot
Identifies wiring erros
Ensures compliance with
AG181 and IEC 61158-2
Recommends limits for ADM messages
Stores limits in non-volatile memory
Automatic Tag Readout
Creates baseline report:
Snapshot of all measurements
Complete documentation
Saves 80% of pre-commissioning time
© 1994 – 2011 Fieldbus Foundation 40
Diagnostic Menu
Expert System delivers clear text
information for fast fault finding
1 Active messages
2 Actionable information with
solution guideance based on
expert system
3 History with timestamps
When the failure…
… occured
… disappeared
Export function for external
analysis and storage
1
2 2
3
© 1994 – 2011 Fieldbus Foundation 41
Online monitoring
Clean layout shows boundaries
Displays measurement values
Highlights violations with color coding:
Issues diagnostic messages
Good value
Maintenance required
Out of specification
© 1994 – 2011 Fieldbus Foundation 42
Online trending and history
Monitoring
Reveals long term changes
Exports into many formats
© 1994 – 2011 Fieldbus Foundation 43
Built-in fieldbus oscilloscope
ADM provides expert tools
for fast fault finding
For diagnosing complex scenarios
For the fieldbus expert
With fieldbus specific triggers
Captures up to 10 shots in a row
© 1994 – 2011 Fieldbus Foundation 44
Questions
© 1994 – 2011 Fieldbus Foundation 45
THANK YOU