FES Construction Phase Method Statement

21
FES Construction Phase Method Statement Emergency Standby Electricity Generation Facility

Transcript of FES Construction Phase Method Statement

Page 1: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Emergency Standby Electricity Generation

Facility

Page 2: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Overview of Site Plans and Site Access Requirements

FES are constructing an Emergency Standby Generator Facility together with a new access off Swindon Road. The Site is to

be constructed on a field at the back of the existing WPD Sub Station with a long access road back to Swindon Road. This

Construction Phase Method Statement will detail how FES plan on delivering this project safely.

This Method Statement will cover the following points:

• Health and Safety

• Project Delivery Team

• SMSTS/SSSTS

• Project Deliveries

• Deliveries to and from site

• Traffic Management Plan

• Site General Layout Drawing

• Site Boundaries-Perimeter Fencing

• Emergency Arrangements

• Wheel Washing

• Appointment of sub-contractors

• Site Welfare & Accommodation

Page 3: FES Construction Phase Method Statement

FES Construction Phase Method Statement

• Security Hut

• Civils Construction Scope

• Project Duration/Programme/Site Hours

Health and Safety-

Our Construction Phase, Health, Environmental and Quality Plan will be devised by FES Contracts Manager Barry

McFadden and reviewed and approved by FES Support Services Health and Safety Manager Peter McEwan.

It is the policy of FES Ltd to promote a health and safety culture throughout the Company which is committed to the

prevention of injuries and ill health of our employees, sub-contractors and others who may be affected by our work

activities and to prevent any damage or loss to property, plant and equipment.

The highest standards of health and safety will be reflected in the design and/or installation of systems and equipment to

our clients.

The Company believes that this policy can be achieved by compliance with statutory requirements and the provision of

competent resources for the control of health and safety risks. Health and safety will never be compromised by other

objectives. This supports Clients Safety Plans, Policies and requirements.

The Company will maintain a system of communications to ensure that mandatory instructions, reports and guidance on

all health and safety matters are effectively circulated to appropriate levels of staff.

Page 4: FES Construction Phase Method Statement

FES Construction Phase Method Statement

The Company will produce health and safety plans and set performance standards.

The planning will provide for:

• Identifying hazards and assessing risks, and specifying the measures to eliminate or control them.

• Design of safe systems of work i.e. Method Statements.

• Training and supervision.

• Assessment and approval of sub-contractors and other agencies.

• Dealing with serious danger and emergencies.

The Company will establish and maintain an organisation structure with clearly defined responsibilities and authority for

individuals in the effective control of health and safety, and will actively promote employee participation in the

establishment and observance of measures to improve their health and safety at work.

The Company will monitor and measure health and safety performance to ensure that standards are being met and

management controls are working by means of:

• Inspections of premises, places of work and systems of work.

• Inspections of plant, tools and equipment.

• Investigation of any serious accidents, fires and dangerous occurrences.

• Recording of health surveillance, injuries, ill health and accident loss.

Page 5: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Every employee must co-operate with us to enable all statutory duties to be complied with, the successful implementation

of this policy requires total commitment from all levels of employees.

Each individual has a legal obligation to take reasonable care for his or her own health and safety and for the safety of

other people which may be affected by his or hers acts or omissions.

Full details of the organisation and arrangements for health and safety will be set out in separate documents.

This policy will be regularly monitored to ensure that all objectives are achieved.

It will be reviewed and if necessary, revised in the light of legislative or organisational changes.

FES Ltd will continue to improve health and safety in our management and performance.

Page 6: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Hinksford Construction Management Plan-

The following organogram depicts how FES will be delivering the project with the appointment of key personnel and their

respective roles.

Charlie Easton is in overall control of these STOR Projects for and on the behalf of FES as our Divisional Director supported

by Bruce Totten as Divisional Manager.

With regards the operations team this is headed by our Operations Manager Ryan Halliday who will be in charge of the

running of this and all STOR Projects that may run concurrently with Hinksford with Contracts Manager Barry McFadden

focusing solely on this particular site.

All of the appointed FES key personnel have Site Management Safety Training Scheme (SMSTS) accreditation or Site

Supervisors Safety Training Scheme accreditation and have extensive knowledge and experience of managing,

delivering and organising construction projects across all sectors.

Page 7: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Page 8: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Project Deliveries-

The following drawing details the route for all deliveries travelling from north or south direction from the main M6

motorway to site via Wolverhampton. This will be issued to all sub-contractors/suppliers and site visitors accompanied

with the Traffic Management Plan.

Page 9: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Page 10: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Upon arrival in Hinksford all traffic shall access the site via Swindon Road turn into site by way of the new site access road

which will replace the existing field entrance. This is marked by way of the red perimeter line on the attached sketch.

Page 11: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Phase 1-

Access into the Field will be through the existing Gate off Swindon Road as indicated by the blue hatched area on the

drawing below-T-17-1653-001. This will remain the only Entrance to the Site for the duration of the works (Phase 1) and a

Traffic Management Plan is provided to warn other road users of the Construction Site Entrance as highlighted on Drawing

T-17-1653-001. The signage will be in place for approximately 44 weeks.

There are works to be carried out at this Entrance to open up the access by removing sections of the existing hedge to

create the new wider Site Entrance with pavement and kerb alterations. This will require a partial lane closure (Phase 2).

Page 12: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Page 13: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Phase 2

For the new amendments to the Site Entrance to be constructed, we will need to close the lane nearest the Site Entrance

for a short duration. We have prepared an additional Traffic Management Plan to include a Traffic Light System whilst

these works are carried out, refer to Drawing T-17-1653-002, which will be on site for approximately 3 weeks.

Page 14: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Page 15: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Hinksford Traffic Management Plan-

The following drawing is FES’ Traffic Management Plan for the site which will coordinate all vehicular and pedestrian

traffic for the site. Encompassed within the Traffic Management Plan will be considerations for speed limits onsite,

directional traffic signage, warning signage at the site entrance and also throughout the site, positions of mini generator

feeding the water bowser for the wheel wash supply at the site entrance where all vehicles will arrive and depart the site.

In addition there will be signage for the site offices, welfare facilities and site parking for visitors and staff and a clearly

defined area for loading and unloading of materials.

Page 16: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Page 17: FES Construction Phase Method Statement

FES Construction Phase Method Statement

The drawing below is a General Arrangement drawing of the proposed site detailing positions of all generators, auxiliary

generator, transformers, welfare hut, security arrangements, DNO metering sub-station, switch room/control room, gas

metering house and gas boiler house.

The red line details the perimeter fencing which shall cordon off the site at all times and ensure that the site is secure at all

times.

Page 18: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Emergency Arrangements-As part of our Site Induction all operatives will be informed of the local Muster Point and FES

will also have an emergency telephone in case of an emergency.

In the case of an emergency the nearest A&E Department is the New Cross Hospital, Wolverhampton.

Address:

Emergency Department (A&E),

Urgent and Emergency Care,

New Cross Hospital

Wolverhampton Road,

Wolverhampton,

West Midlands,

WB10 0QP

Tel: 01902 307 999

Page 19: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Directions to the hospital are as follows:

New Cross Hospital is located near Wednesfield on the eastern side of Wolverhampton.

From the North – take J11 off the M6 then follow Cannock Rd/A460 to Wolverhampton (go through 4 roundabouts). Turn

left to Bushbury Road and continue onto Church Street. Keep left at the fork then turn left onto Wolverhampton Road

then take the 2nd left to New Cross Hospital.

From the South – take J10a off the M6 then follow the M54. Take the slip road to Cannock Rd/A460 off the M54. At the

roundabout take the first exit onto Cannock Rd/A460 to Wolverhampton (go through 4 roundabouts). Turn left to

Bushbury Road and continue onto Church Street. Keep left at the fork then turn left onto Wolverhampton Road then take

the 2nd left to New Cross Hospital.

From Wolverhampton City Centre – take the ring road St. Patricks/A4150 then turn left onto the Wednesfield Rd/A4124

then continue to follow Wednesfield Rd/A4124 then take slight left into Wolverhampton Rd then take the 2nd left into

New Cross Hospital.

Page 20: FES Construction Phase Method Statement

FES Construction Phase Method Statement

Vehicle Wheel Washing-To ensure not only site welfare and housekeeping is maintained to a high standard FES are also

determined to have al little impact on the local community and roads as possible. To this end the site will have a security

hut with a signing in and out register and at this juncture all vehicles will undergo a thorough wheel wash prior to site

egress whilst the final road construction works are being carried out.

Appointments of sub-contractors-to ensure all sub-contractors maintain similar standards set by FES we will only appoint

sub-contractors who are appointed off of our existing approved contractors list. Each contractor is subject to a thorough

vetting regime and this is reviewed on an annual basis.

Site Welfare and Accommodation-FES anticipate no more than 12-14 operatives onsite at any one time but we have

made a provision for 20 number operatives, within this there are facilities including, but not limited to rest area, canteen,

drying area, medical facilities, male and female WC’s, hot water potable water, microwave ovens, fridges and personal

lockers.

Security Hut-FES will provide a security hut for the signing in and out of all operatives, deliveries and materials. This will be

manned by our onsite security adviser.

Civils Contractor-FES has again appointed a Civil Contractor to carry out the Civils package and have passed all required

quality checks. This Civil contractor CML’s works will include the following facets:

• Design of hard standing areas;

• Design of surface water drainage;

• Surface water attenuation design;

Page 21: FES Construction Phase Method Statement

FES Construction Phase Method Statement

• External works construction specification;

• Design of entrance roads / Section 278 works;

• Design of foundation bases and reinforcement;

• Earthworks / ground remediation design;

• Earthworks cut / fill layout; and

• Service duct locations and details;

Project Duration/Programme/Site Hours-This project will commence pre-Christmas 2017 and will be complete after a 44

week programme with all works carried out during normal working hours unless out of hours works may be required by

agreement with all parties. By normal working hours we understand these to be:

• Mon-7:30am – 6pm,

• Tue-7:30am – 6pm

• Wed-7:30am – 6pm

• Thu-7:30am – 6pm

• Fri-7:30am – 6pm.

We have also provision where we’d offer our contractors out of hours working at weekends if need be between the

hours of:

• Sat-8:00am – 3pm

• Sun-8:00am – 3pm

This programme will be circulated throughout all sub-contractors. FES shall monitor the programme by way of weekly

progress meetings with each sub-contractor and then compile a progress report to our client on a fortnightly basis.