Proposal for building a FEMA Emergency Shelter/Student Recreation Center on the West Plains Campus of Missouri State University

Transcript of FEMA Center

Page 1: FEMA Center

FEMA Emergency Shelter/Student Recreation Center

Presentation

Page 2: FEMA Center

PROJECT: Site

2 FEMA Emergency Shelter/Student Recreation Center

Page 3: FEMA Center

3 FEMA Emergency Shelter/Student Recreation Center

PROJECT: Design

Page 4: FEMA Center

Provide a Safe Tornado Shelter for Area Residents There is no available tornado-safe shelter for the 1,669 students, staff, faculty, residents,

and business workers that are within a five minute radius of this location. This project will provide the needed shelter 24-7 and mitigate injury and loss of life in the event of a tornado by providing accessibility to a shelter.

Promote Student Engagement through Extra-Curricular Activities Through massive amounts of national research over an extended period of time, we know

that students who are engaged in extracurricular activities are significantly more likely to succeed academically than those who simply commute to campus.  Because of this, Missouri State University-West Plains has dreamed for years of providing a more complete collegiate experience for students by constructing a multi-purpose facility.  In fact, a multi-purpose facility has been included in both the Master Plan Visioning Guide and Long Range Plan for years.  The proposed shelter would accomplish much of what has been envisioned for students by providing multiple indoor recreational opportunities in the heart of the campus.  The fact that the federal government would provide much of the funding is a substantial bonus to the original dream.

4 FEMA Emergency Shelter/Student Recreation Center

PROJECT: Description

Page 5: FEMA Center

5 FEMA Emergency Shelter/Student Recreation Center

Recreational Activities – Basketball, Volleyball and Racquetball

Page 6: FEMA Center

6 FEMA Emergency Shelter/Student Recreation Center

Student Life Activities – Concerts & Special Events

Page 7: FEMA Center

7 FEMA Emergency Shelter/Student Recreation Center

Student Life Activities -Presentations & Debates

Page 8: FEMA Center

8 FEMA Emergency Shelter/Student Recreation Center

Recreational & Student Life Activities -???

Page 9: FEMA Center

Total Project Costs: $2,221,114

Total Federal Project Share: $1,320,149 (59.4%)

Total University Responsibility: $900,965 (40.6%)

Non-Federal Project Share (University Responsibility): $440,050

Non-FEMA Eligible Costs (University Responsibility): $460,915

All calculations are estimates on the University responsibility.

Actual prices will not be known until the project is publicly bid.

Price estimates are based upon local FEMA emergency shelter projects.

9 FEMA Emergency Shelter/Student Recreation Center

PROJECT: Estimated costs

Page 10: FEMA Center

The University is unable to fund approximately $901,000 from University reserves.

An auxiliary bond (loan) is a method to fund the University’s financial responsibility for project costs.

Terms of the bond:

25 year

5%

Approximate annual payment: $64,000

10 FEMA Emergency Shelter/Student Recreation Center

PROJECT: Bonding

Page 11: FEMA Center

$25 fee per semester (fall, spring & summer).

Same guidelines as the Capital Projects Fee and Student Activity Fee. Students taking only online classes will not be assessed the fee.

A+ eligible.

Fee would begin for the Fall 2010 semester.

Estimated annual fee income based upon Spring, Summer, Fall 2009 enrollment.

$88,250

Estimated annual bond payment (25 years, 5%).

$64,000

Additional income would be utilized for student employees, Custodial staff, utilities, operating expenses, equipment, etc…

Adjust fee if needed after long-term analysis.

If a student fee is not approved, the project will not take place.

11 FEMA Emergency Shelter/Student Recreation Center

PROJECT: Student Recreation Center Fee

Page 12: FEMA Center

Student Recreation Center Fee Vote: March 2010

Board of Governors Approve Fee Resolution/FEMA Contract: April 2010

Design Development: September 2010

Construction Documents: December 2010

Bidding & Negotiation: March 2011

Construction Dates: Estimated Construction Begins May 2011 Estimated Construction Completion August 2012

12 FEMA Emergency Shelter/Student Recreation Center

PROJECT: Estimated Timeline

Page 13: FEMA Center

13 FEMA Emergency Shelter/Student Recreation Center