Federal Guidelines for Dam Safety.pdf
-
Upload
nuncapierdaslafe123 -
Category
Documents
-
view
225 -
download
0
Transcript of Federal Guidelines for Dam Safety.pdf
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
1/58
Selecting and Accomodating
Inow Design Floods for Dams
April 2004
Federal
GuidelinesforDamSafety
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
2/58
FEDERAL GUIDELINES FOR DAM SAFETY:SELECTING AND ACCOMMODATINGINFLOW DESIGN FLOODS FOR DAMS
prepared by theINTERAGENCY COMMITTEE ON DAM SAFETY
U.S. DEPARTMENT OF HOMELAND SECURITYFEDERAL EMERGENCY MANAGEMENT AGENCYOCTOBER 1998
Reprinted April 2004
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
3/58
PREFACE
In April 1977, President Carter issued a memorandum directing the review of federal dam safety activities by an
ad hoc panel of recognized experts. In June 1979, the ad hoc interagency committee on dam safety (ICODS)
issued its report, which contained the first guidelines for federal agency dam owners. The Federal Guidelines for
Dam Safety (Guidelines) encourage strict safety standards in the practices and procedures employed by federal
agencies or required of dam owners regulated by the federal agencies. The Guidelines address management practices and procedures but do not attempt to establish technical standards. They provide the most complete and
authoritative statement available of the desired management practices for promoting dam safety and the welfare of
the public.
To supplement the Guidelines, ICODS prepared and approved federal guidelines in the areas of emergency action
planning; earthquake analysis and design of dams; and selecting and accommodating inflow design floods for
dams. These publications, based on the most current knowledge and experience available, provided authoritativestatements on the state of the art for three important technical areas involving dam safety. In 1994, the ICODS
Subcommittee to Review/Update the Federal Guidelines began an update to these guidelines to meet new dam
safety challenges and to ensure consistency across agencies and users. In addition, the ICODS Subcommittee on
Federal/Non-Federal Dam Safety Coordination developed a new guideline, Hazard Potential Classification
System for Dams.
With the passage of the National Dam Safety Program Act of 1996, Public Law 104-303, ICODS and its
Subcommittees were reorganized to reflect the objectives and requirements of Public Law 104-303. In 1998, the
newly convened Guidelines Development Subcommittee completed work on the update of all of the following
guidelines:
•
Federal Guidelines for Dam Safety: Emergency Action Planning for Dam Owners
• Federal Guidelines for Dam Safety: Hazard Potential Classification System for Dams
•
Federal Guidelines for Dam Safety: Earthquake Analyses and Design of Dams
• Federal Guidelines for Dam Safety: Selecting and Accommodating Inflow Design Floods for Dams
• Federal Guidelines for Dam Safety: Glossary of Terms
The publication of these guidelines marks the final step in the review and update process. In recognition of the
continuing need to enhance dam safety through coordination and information exchange among federal and state
agencies, the Guidelines Development Subcommittee will be responsible for maintaining these documents and
establishing additional guidelines that will help achieve the objectives of the National Dam Safety Program.
The members of all of the Task Groups responsible for the update of the guidelines are to be commended for their
diligent and highly professional efforts:
Harold W. Andress, Jr.
Chairman, Interagency Committee on Dam Safety
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
4/58
SELECTING AND ACCOMMODATING INFLOW DESIGN
FLOODS FOR DAMS
TASK GROUP
David Achterberg**
DOI, Bureau of Reclamation
Jerrold W. Gotzmer*
Federal Energy Regulatory Commission
Ronald Spath*
Federal Energy Regulatory Commission
Ming Tseng*U.S. Army Corps of Engineers
Donald E. Woodward*
USDA, Natural Resources Conservation Service
Norman Miller
USDA, Natural Resources Conservation Service
Sam A. Shipman
Tennessee Valley Authority
*Chair of Task Group that completed final document
**Member of Task Group that completed final document
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
5/58
TABLE OF CONTENTS
I. INTRODUCTION ..............................................................................................................................1
A. Purpose ...............................................................................................................................1
B. Background .............................................................................................................................1
1. Early Periods.................................................................................................................12. Transition .....................................................................................................................23. Current Practices ..........................................................................................................2
C. Scope .......................................................................................................................................3
1. General .........................................................................................................................32. Philosophy and Principles ............................................................................................3
3. Content .........................................................................................................................4
II. DEFINITIONS OF TERMS ............................................................................................................5
III. SELECTING INFLOW DESIGN FLOODS ..............................................................................11
A. Introduction............................................................................................................................11B. Hazard Potential Evaluation ..................................................................................................11
1. General ........................................................................................................................12
2. Hydrologic Modes of Failure .....................................................................................12a. Overtopping.....................................................................................................12
b. Erosion in Earth Spillways..............................................................................12
c. Overstressing of Structural Components .......................................................133. Defining the Hazard Potential ....................................................................................13
4. Evaluating the Consequences of Dam Failure ...........................................................14
5. Studies to Define the Consequences of Dam Failure .................................................156. Incremental Hazard Evaluation for Inflow Design Flood Determination .................17
7. Criteria for Selecting the Inflow Design Flood...........................................................19
C. PMFs for Dam Safety ............................................................................................................21
1. General ........................................................................................................................212. PMP.............................................................................................................................21
D. Floods To Protect Against Loss of Benefits During the Life of the Project-
Applicable Only to Low-Hazard Dams .............................................................................22
IV. ACCOMMODATING INFLOW DESIGN FLOODS ...............................................................23
A. Introduction ...........................................................................................................................231. General .......................................................................................................................23
2. Guidelines for Initial Elevations ................................................................................23
3. Reservoir Constraints .................................................................................................23
4. Reservoir Regulation Requirements ..........................................................................235. Evaluation of Domino-like Failure ............................................................................24
i
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
6/58
TABLE OF CONTENTS (Continued)
B. Spillway and Flood Outlet Selection and Design ..................................................................25
1. General .......................................................................................................................252. Gated or Ungated Spillways ......................................................................................25
3. Design Considerations ...............................................................................................26
C. Freeboard Allowances ...........................................................................................................271. General .......................................................................................................................27
2. Freeboard Guidelines .................................................................................................28
Appendix A - References by Top ....................................................................................................... A-1
Appendix B – Inflow Design Flood Selection Procedures
Figure 1. Illustration of Incremental Increase Due to Dam Failure
Figure 2. Illustration of Incremental Area Flooded by Dam FailureFigure 3. Regions Covered by PMP Studies
ii
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
7/58
I. INTRODUCTION
A. Purpose
The purpose of these Guidelines is to provide thorough and consistent procedures forselecting and accommodating Inflow Design Floods (IDFs). The IDF is the flood flow
above which the incremental increase in water surface elevation downstream due to
failure of a dam or other water retaining structure is no longer considered to present an
unacceptable additional downstream threat.
B. Background
Current practice in the design of dams is to use the IDF that is deemed appropriate for thehazard potential of the dam and reservoir, and to design spillways and outlet works that
are capable of safely accommodating the floodflow without risking the loss of the dam or
endangering areas downstream from the dam to flows greater than the inflow. However,
there are many dams whose discharge capabilities were designed using methods that arenow considered unconservative and potentially unsafe.
Inflow design flood selection began primarily as a practical concern for protection of a
dam and the benefits it provides. The early 1900's saw an increase in the Nation's social
awareness that was demonstrated by various legislative acts designed to protect the publicfrom certain high risk activities. The same era witnessed an increase in the number and
size of dams built. When the "big dam" era began in the 1930's, safety clearly became a
more dominant factor. It was recognized that dams needed to be designed to
accommodate water flows that might be greater than the anticipated "normal" flow.
1. Early Periods. Before 1900, designers of dams had relatively little hydrologic data ortools to indicate flood potential at a proposed dam site. Estimates of flood potential were
selected by empirical techniques and engineering judgment based on high water marks orfloods of record on streams being studied.
Later, engineers began examining all past flood peaks in a region to obtain what washoped to be a more reliable estimate of maximum flood-producing potentials than alimited record on a single stream. Designers would base their spillway design on these
estimates, sometimes providing additional capacity as a safety factor. Some spillways
were designed for a multiple of the maximum known flood, for example, twice the
maximum known flood. The multiples and safety factors were based on engineering
judgment; the degree of conservatism in the design was unknown.
By the 1930's, it became apparent that this approach was inadequate. As longer
hydrologic records were obtained, new floods exceeded previously recorded maximumfloods. With the introduction of the unit hydrograph concept by Sherman in 1933, it
became possible to estimate floodflows from storm rainfall. The design of dams began to
be based upon the transposition of major storms that had occurred within a region, i.e.,
1
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
8/58
transfer and centering of relevant storm rainfall patterns over the basin above the dam site being evaluated. It was recognized that flood peaks are dependent on topography, size of
individual watersheds, and chance placement of the storm's center over the watershed. In
addition, within meteorologically similar areas, observed maximum rainfall values could
provide a better indication of maximum flood potentials than data on flood dischargesfrom individual watersheds. If, in the judgment of the designer, the storm was not
representative of what might occur, rainfall amounts were increased to represent a more
severe event, and the dam was designed accordingly.
2. Transition. Engineers next turned to hydrometeorologists to determine if upper limitsfor rates of precipitation could be established on a rational basis. Careful consideration
was given to the meteorology of storms that produced major floods in various parts of thecountry. The large scale features of the storm and measures of atmospheric moisture,
such as dewpoint temperatures, were considered as well as the rainfall depth-area-
duration values produced by these storms. It was then possible to increase the storm
dewpoint temperature and other factors affecting rainfall to the maximum appropriatevalues. This increase resulted in estimates of probable maximum precipitation (PMP),
and thus introduced the concept of a physical upper limit to precipitation. When
translated to runoff, the estimated floodflow is known as the probable maximum flood(PMF).
At first, the terms maximum possible precipitation and maximum possible flood were
used. However, the terminology was changed to probable maximum to recognize theuncertainties in the estimates of the amount of precipitation, and the most severe
combination of critical meteorological and hydrologic conditions that are reasonably
possible in the region. Today, the PMF is generally accepted as the standard for the safety
design of dams where the incremental consequences of failure have been determined to be unacceptable.
In the late 1940's, the ability to estimate the consequences of dam failure, including the
loss of life, was still quite limited. The height of the downstream flood wave and theextent of wave propagation were known to be a function of dam height and reservoir
volume. Thus, early standards for dam design were based upon the size of the dam in
terms of its height, the reservoir storage volume, and the downstream development.
The practice of setting inflow design flood standards based upon the size of a dam, its
reservoir volume, and current downstream development resulted in an inconsistent level
of design throughout the country. The determination of the consequences of a dam failureis more complex than can be evaluated by these simple relationships.
3. Current Practices. In 1985, the National Academy of Sciences (NAS) published astudy of flood and earthquake criteria which contained an inventory of current practices
in providing dam safety during extreme floods. The inventory showed considerable
diversity in approach by various federal, state, and local government agencies,
2
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
9/58
professional societies, and private firms. While the inventory shows a fair consensus onspillway requirements for dams having a high-hazard potential, there is a wide range of
criteria being applied to dams with lower hazard classifications.
Several observations about the evaluation of hydrologic conditions were made in the NAS study. Use of PMP for evaluating spillway capacity requirements for large, high-
hazard dams predominates, although some state agencies have standards that do notrequire such dams to pass the full estimated PMF based on the PMP. The influence of the
principal federal dam-building and dam safety agencies is evident in the majority of the
standards for large, high-hazard dams, but the practices of those agencies have had lesseffect on current state standards for small dams in less hazardous situations.
As a result of inspections authorized by Public Law 92-367, the National Dam InspectionAct, and carried out by the U.S. Army Corps of Engineers from 1977 to 1981, several
states have adopted the spillway capacity criteria used in those inspections. Several other
states have adopted the standards used by the Natural Resources Conservation Service(formerly the Soil Conservation Service) for the design of smaller dams constructed
under that agency's programs.
Most agencies draw a distinction between design criteria that are applied to existing dams
and those that are applied to new dams. However, because dam failures present the same
consequences to life and property, it is desirable that existing dams meet the criteriaestablished for new dams.
Today, hydrologically safe designs should be based on current state-of-the-art criteria.
Now that engineers can estimate downstream flood levels resulting from dam failure,
safety design standards can be tied specifically to a detailed evaluation of the impacts of a
flood if a dam were to fail. Although debate continues over the proper criteria and degreeof conservatism warranted when evaluating and designing modifications to existing
dams, and when designing new dams, criteria used by dam designers, regulators, andowners now focus on ensuring public safety.
C. Scope
1. General. These Guidelines are not intended to provide a complete manual of all
procedures used for estimating inflow design floods; the selection of procedures isdependent upon available hydrologic data and individual watershed characteristics. All
studies should be performed by an engineer experienced in hydrology and hydraulics,
directed and reviewed by engineers experienced in dam safety, and should contain a
summary of the design.
2. Philosophy and Principles. The basic philosophy and principles are described insufficient detail to achieve a reasonable degree of uniformity in application, and to
achieve a consistent and uniform nationwide treatment among federal agencies in thedesign of dams from the standpoint of hydrologic safety.
3
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
10/58
3. Content. The following topics are discussed in these Guidelines:
• Selecting the IDF - The selection of the appropriate IDF for a dam is related to the
hazard potential classification and is the result of the incremental hazard
evaluation.
• Accommodating the IDF - Site-specific considerations are necessary to establishhydrologic flood routing criteria for each dam and reservoir. The criteria for
routing the IDF or any other flood should be consistent with the reservoir
regulation procedure that is to be followed in actual operation.
4
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
11/58
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
12/58
Flood Plain: The downstream area that would be inundated or otherwise affected by the
failure of a dam or by large flood flows.
Flood Routing: A process of determining progressively the amplitude of a flood wave as
it moves past a dam and continues downstream.
Flood Storage: The retention of water or delay of runoff either by planned operation, as
in a reservoir, or by temporary filling of overflow areas, as in the progression of a flood
wave through a natural stream channel.
Freeboard: Vertical distance between a specified stillwater reservoir surface elevation
and the top of the dam, without camber.
Foundation: The portion of the valley floor that underlies and supports the dam
structure.
Gate: A movable water barrier for the control of water.
Hazard: A situation which creates the potential for adverse consequences such as loss of
life, property damage, or other adverse impacts. Impacts in the area downstream of a damare defined by the flood waters released through spillways and outlet works of the dam or
waters released by partial or complete failure of the dam. There may also be impacts
upstream of the dam due to backwater flooding or landslides around the reservoir
perimeter.
Hazard Potential Classification: A system that categorizes dams according to the
degree of adverse incremental consequences of a failure or misoperation of a dam. TheHazard Potential Classification does not reflect in any way on the current condition of the
dam (i.e., safety, structural integrity, flood routing capacity).
Hydrograph, Flood: A graphical representation of the flood discharge with respect to
time for a particular point on a stream or river.
Hydrology: One of the earth sciences that encompasses the natural occurrence,
distribution, movement, and properties of the waters of the earth and their environmentalrelationships.
Hydrometeorology: The study of the atmospheric and land-surface phases of thehydrologic cycle with emphasis on the interrelationships involved.
Inflow Design Flood (IDF): The flood flow above which the incremental increase in
downstream water surface elevation due to failure of a dam or other water impounding
structure is no longer considered to present an unacceptable additional downstream
threat. The IDF of a dam or other water impounding structures is the flood hydrograph
6
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
13/58
used in the design or evaluation of a dam, its appurtenant works, particularly for sizingthe spillway and outlet works, for determining maximum height of a dam, freeboard, and
flood storage requirements. The upper limit of the IDF is the probable maximum flood.
Intake: Placed at the beginning of an outlet-works waterway (power conduit, watersupply conduit), the intake establishes the ultimate drawdown level of the reservoir by the position and size of its opening(s) to the outlet works. The intake may be vertical or
inclined towers, drop inlets, or submerged, box-shaped structures. Intake elevations are
determined by the head needed for discharge capacity, storage reservation to allow forsiltation, the required amount and rate of withdrawal, and the desired extreme drawdown
level.
Inundate: To overflow, to flood.
Inundation Map: A map showing areas that would be affected by flooding from an
uncontrolled release of a dam's reservoir.
Landslide: The unplanned descent (movement) of a mass of earth or rock down a slope.
Maximum Wind: The most severe wind for generating waves that is reasonably possible
at a particular reservoir. The determination will generally include results of meteorologicstudies which combine wind velocity, duration, direction, fetch, and seasonal distribution
characteristics in a realistic manner.
Meteorological Homogeneity: Climates and orographic influences that are alike or
similar.
Meteorology: The science that deals with the atmosphere and atmospheric phenomena,
the study of weather, particularly storms and the rainfall they produce.
One-Percent-Chance Flood: A flood that has 1 chance in 100 of being equaled or
exceeded during any year.
Orographic: Physical geography that pertains to mountains and to features directly
connected with mountains and their general effect on storm path and generation ofrainfall.
Outlet Works: A dam appurtenance that provides release of water (generally controlled)from a reservoir.
Probable Maximum Flood (PMF): The flood that may be expected from the most
severe combination of critical meteorologic and hydrologic conditions that are reasonably
possible in the drainage basin under study.
7
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
14/58
Probable Maximum Precipitation (PMP): Theoretically, the greatest depth of precipitation for a given duration that is physically possible over a given size storm area
at a particular geographical location during a certain time of the year. Reservoir
Regulation Procedure (Rule Curve): Refers to a compilation of operating criteria,
guidelines, and specifications that govern the storage and release function of a reservoir.It may also be referred to as operating rules, flood control diagram, or water control
schedule. These are usually expressed in the form of graphs and tabulations,
supplemented by concise specifications and are often incorporated in computer programs.In general, they indicate limiting rates of reservoir releases required or allowed during
various seasons of the year to meet all functional objectives of the project.
Reservoir Rim: The boundary of the reservoir including all areas along the valley sides
above and below the water surface elevation associated with the routing of the IDF.
Risk: The relationship between the consequences resulting from an adverse event and its
probability of occurrence.
Risk-based Analysis: A procedure in which the consequences and risks of adverse
events and alternatives for mitigation are evaluated and arranged in a manner thatfacilitates a decision on the action to be taken. A risk-based analysis may be the basis for
the selection of the IDF for a particular dam.
Seiche: An oscillating wave in a reservoir caused by a landslide into the reservoir or
earthquake-induced ground accelerations or fault offset.
Sensitivity Analysis: An analysis in which the relative importance of one or more of the
variables thought to have an influence on the phenomenon under consideration isdetermined.
Settlement: The vertical downward movement of a structure or its foundation.
Significant Wave Height: Average height of the one-third highest individual waves.
May be estimated from wind speed, fetch length, and wind duration.
Spillway: A structure over or through which flow is discharged from a reservoir. If the
rate of flow can be controlled by mechanical means, such as gates, it is considered acontrolled spillway. If the geometry of the spillway is the only control, it is considered an
uncontrolled spillway. Definitions of specific types of spillways follow:
Service Spillway: A spillway that is designed to provide continuous or frequentregulated or unregulated releases from a reservoir without significant damage to
either the dam or its appurtenant structures. This is also referred to as principal
spillway.
8
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
15/58
Auxiliary Spillway: Any secondary spillway which is designed to be operatedinfrequently, possibly in anticipation of some degree of structural damage or
erosion to the spillway that would occur during operation.
Emergency Spillway: A spillway that is designed to provide additional protection against overtopping of dams, and is intended for use under extremeflood conditions or misoperation or malfunction of the service spillway and/or the
auxiliary spillway.
Spillway Capacity: The maximum spillway outflow which a dam can safely pass with
the reservoir at its maximum level.
Stillwater Level: The elevation that a water surface would assume if all wave actions
were absent.
Storm: The depth, area, and duration distributions of precipitation.
Storm Center: Location of the storm pattern such that the precipitation falls on a specific
drainage basin to create the runoff at the site under consideration.
Storm Transposition: The application of a storm from its actual location of occurrence
to some other area within the same region of meteorological homogeneity. Storm
transposition requires the determination of whether the particular storm could occur over
the area to which it is to be transposed.
Surcharge: The volume or space in a reservoir between the controlled retention water
level and the maximum water level. Flood surcharge cannot be retained in the reservoir but will flow out of the reservoir until the controlled retention water level is reached.
Toe of the Dam: The junction of the downstream slope or face of a dam with the ground
surface; also referred to as the downstream toe. The junction of the upstream slope with
the ground surface is called the heel or the upstream toe.
Topographic Map: A detailed graphic delineation (representation) of natural and man-
made features of a region with particular emphasis on relative position and elevation.
Tributary: A stream that flows into a larger stream or body of water.
Unit Hydrograph: A hydrograph with a volume of one inch of direct runoff resulting
from a storm of a specified duration and areal distribution. Hydrographs from otherstorms of the same duration and distribution are assumed to have the same time base but
with ordinates of flow in proportion to the runoff volumes.
Watershed: The area drained by a river or river system.
9
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
16/58
Wave Runup: Vertical height above the stillwater level to which water from a specific
wave will run up the face of a structure or embankment.
Wind Setup: The vertical rise of the stillwater level at the face of a structure or
embankment caused by wind stresses on the surface of the water.
10
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
17/58
III. SELECTING INFLOW DESIGN FLOODS
A. Introduction
Many thousands of dams have been constructed in the United States, and new dams continue to
add to this total. The proper operation of dams to withstand natural forces, including extreme
hydrologic events, is an important matter of public safety and concern.
In today's technical world, extreme hydrologic events resulting in dam failures are classified as"low-probability, high-consequence" events. In addition, the potential for losses due to increased
downstream development may increase the consequences of a dam failure.
There has been a growing concern and increased attention to dam safety over the past two
decades, primarily as a result of a number of catastrophic dam failures. As a result, the inspection
of non-federal dams authorized by Public Law 92-367, the National Dam Inspection Act,identified some 2,900 unsafe dams of which 2,350 had inadequate spillway capacities. Since
there are approximately 23,772 high and significant-hazard dams in the present NationalInventory of Dams, the number of dams which have inadequate spillways could be significantlyhigher.
The adequacy of a spillway must be evaluated by considering the hazard potential, which wouldresult from failure of the project works during flood flows. (See Chapter II for a definition of
hazard potential.) If failure of the project works would present an unacceptable downstream
threat, the project works must be designed to either withstand overtopping for the loadingcondition that would occur during a flood up to the probable maximum flood, or to the point
where a failure would no longer cause an unacceptable additional downstream threat.
The procedures used to determine whether or not the failure of a project would cause anunacceptable downstream threat vary with the physical characteristics and location of the project,
including the degree and extent of development downstream.
Analyses of dam failures are complex, with many historical dam failures not completelyunderstood. The principal uncertainties in determining the outflow from a dam failure involve
the mode and degree of failure. These uncertainties can be circumvented in situations where it
can be shown that the complete and sudden removal of the dam would not result in unacceptableconsequences. Otherwise, reasonable failure postulations and sensitivity analyses should be used.
Suggested references regarding dam failure studies are listed in Appendix A. If it is judged that a
more extensive mode of failure than that normally recommended for the type of structure under
investigation is possible, then analyses should be done to determine whether remedial action isrequired. Sensitivity studies on the specific mode of failure should be performed when failure is
due to overtopping.
B. Hazard Potential Evaluation
A properly designed, constructed, and operated dam can be expected to improve the safety ofdownstream developments during floods. However, the impoundment of water by a dam can
11
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
18/58
create a potential hazard to downstream developments greater than that which would existwithout the dam because of the potential for dam failure. There are several potential causes of
dam failure, including hydrologic, geologic, seismic, and structural.
These Guidelines are limited to the selection of the inflow design flood (IDF) for the hydrologic
design of a dam.
1. General. Once a dam is constructed, the downstream hydrologic regime may change, particularly during floods. The change in hydrologic regime could alter land use patterns to
encroach on a flood plain that would otherwise not be developed without the dam.
Consequently, evaluation of the consequences of dam failure must be based on the dam
being in place, and must compare the impacts of with-failure and without-failure
conditions on existing development and known and prospective future development when
evaluating the downstream hazard potential.
2. Hydrologic Modes of Failure. Many dam failures have resulted because of an inability tosafely pass flood flows. Failures caused by hydrologic conditions can range from sudden, withcomplete breaching or collapse, to gradual, with progressive erosion and partial breaching.
The most common modes of failure associated with hydrologic conditions include overtop-ping,erosion of earth spillways, and overstressing the dam or its structural components. The following
paragraphs describe briefly each of the modes of failure caused by hydrologic conditions.
a. Overtopping. Overtopping of a dam occurs when the water level in the reservoir exceeds the
height of the dam and flows over the crest. Overtopping will not necessarily result in a failure.Failure depends on the type, composition, and condition of the dam and the depth and duration of
flow over the dam.
Embankment dams are very susceptible to failure when overtopped because of potential erosion.
If the erosion is severe, it can lead to a breach and failure of the dam. During overtopping, the
foundation and abutments of concrete dams also can be eroded, leading to a loss of support andfailure from sliding or overturning. In addition, when a concrete dam is subjected to overtopping,
the loads can be substantially higher than those for which the dam was designed. If the increased
loading on the dam itself due to overtopping is too great, a concrete dam can fail by overturningor sliding.
b. Erosion in Earth Spillways. High or large flows through earthen spillways adjacent to damscan result in erosion that progresses to the dam and threatens it. Erosion can also cause
headcutting that progresses toward the spillway crest and eventually leads to a breach.
Discontinuities in slope, nonuniform vegetation or bed materials, and concentrated flow areascan start headcuts and accelerate the erosion process. Flood depths that exceed the safe design
parameters can produce erosive forces that may cause serious erosion in the spillway.
12
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
19/58
Erosion that occurs due to flow concentrations can start where roads or trails are devoid ofvegetation or have ruts that run parallel to the spillway flow. A varied mix of earth materials,
unlevel cross sections, uneven stands of vegetation, and obstructions such as trash accumulations
can cause turbulent, concentrated flow conditions that start gullies that can widen and migrate
upstream to breach the spillway crest.
Runoff brought into a spillway channel by a side inlet may also disrupt the desirable uniformflow pattern and increase the erosion in the channel.
The probability of failure of an earthen auxiliary spillway due to erosion is increased when thecapacity of the service spillway inlets (outlet works) or gates are reduced due to trash
accumulations. These accumulations reduce the available capacity through these appurtenances
and increase the volume, depth, frequency, and duration of flow in the auxiliary spillway.
c. Overstressing of Structural Components. As flood flows enter the reservoir, the reservoir
will normally rise to a higher elevation. Even though a dam (both concrete and earthembankment dams) may not be overtopped, the reservoir surcharge will result in a higherloading condition. If the dam is not properly designed for this flood surcharge condition, either
the entire dam or the structural components may become overstressed, resulting in an
overturning failure, a sliding failure, or a failure of specific structural components (such as theupstream face of a slab and buttress dam). Embankment dams may be at risk if increased water
surfaces result in increased pore pressures and seepage rates, which exceed the seepage control
measures for the dam.
3. Defining the Hazard Potential. The hazard potential is the possible adverse incremental
consequences that result from the release of water or stored contents due to failure of the dam or
misoperation of the dam or appurtenances. Hazard potential does not indicate the structuralintegrity of the dam itself, but rather the effects if a failure should occur. The hazard potential
assigned to a dam is based on consideration of the effects of a failure during both normal andflood flow conditions.
Dams assigned the low hazard potential classification are those where failure or misoperationresults in no probable loss of human life and low economic and/or environ-mental losses. Losses
are principally limited to the owner's property.
Dams assigned the significant hazard potential classification are those dams where failure or
misoperation results in no probable loss of human life but can cause economic loss,
environmental damage, disruption of lifeline facilities, or can impact other concerns. Significanthazard potential classification dams are often located in predominantly rural or agricultural areas
but could be located in areas with population and significant infrastructure.
13
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
20/58
Dams assigned the high hazard potential classification are those where failure or misoperationwill probably cause loss of human life.
The hazard potential classification assigned to a dam should be based on the worst-case
failure condition, i.e., the classification is based on failure consequences resulting from the
failure condition that will result in the greatest potential for loss of life and property
damage. For example, a failure during normal operating conditions may result in the releasedwater being confined to the river channel, indicating a low-hazard potential. However, if the dam
were to fail during a floodflow condition, and the resultant incremental flood flow would be a
potential loss of life or serious damage to property, the dam would have high-hazard potentialclassification.
In many cases, the hazard potential classification can be determined by field investigations and areview of available data, including topographic maps. However, when the hazard potential
classification is not apparent from field reconnaissance, detailed studies, including dambreak
analyses, are required. These detailed studies are required to identify the floodflow conditionabove which the additional incremental increase in elevation, due to failure of a dam, is no
longer considered to present an unacceptable threat to downstream life and property.
The hazard potential classification of a project determines the level of engineering review and
the criteria that are applicable. Therefore, it is critical to determine the appropriate hazard
potential of a dam because it sets the stage for the analyses that must be completed to properlyevaluate the integrity of any dam.
4. Evaluating the Consequences of Dam Failure.
There have been about 200 notable dam failures resulting in more than 8,000 deaths in the
Twentieth Century. Dam failure is not a problem confined to developing countries or to acompilation of past mistakes that are unlikely to occur again.
Many dam owners have a difficult time believing that their dams could experience a rainfallmany times greater than any they have witnessed over their lifetimes. Unfortunately, this attitude
leads to a false sense of security because floods much greater than those experienced during anyone person's lifetime can and do occur.
Estimates of the potential for loss of human life and the economic impacts of damage resulting
from dam failure are the usual bases for defining hazard potential. Social and environmental
impacts, damage to national security installations, and political and legal ramifications are noteasily evaluated, and are more susceptible to subjective or qualitative evaluation. Because their
actual impacts cannot be clearly defined, particularly in economic terms, their consideration as
factors for determining the hazard potential must be on a case-by-case basis.
In most situations, the investigation of the impacts of failure on downstream life and property is
sufficient to determine the appropriate hazard potential rating and to select the appropriate IDFfor a project. However, in determining the appropriate IDF for a project, there could be
14
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
21/58
circumstances beyond loss of life and property damage, particularly when a failure would haveminimal or no impact on downstream life and property, which would dictate using a more
conservative hazard potential and IDF. For example, the reservoir of a dam that would normally
be considered to have a low-hazard potential classification based on insignificant incremental
increases (in elevation) due to a failure may be known to contain extensive toxic sediments. Ifreleased, those toxic sediments would be detrimental to the ecosystem. Therefore, a low-hazard
potential classification would not be appropriate. Instead, a higher standard should be used for
classifying the hazard potential and selecting the IDF.
5. Studies To Define the Consequences of Dam Failure.
The degree of study required to sufficiently define the impacts of dam failure for selecting an
appropriate IDF will vary with the extent of existing and potential downstream development, the
size of the reservoir (depth and storage volume), and type of dam. Evaluation of the river reach
and areas impacted by a dam failure should proceed only until sufficient information is generatedto reach a sound decision, or until there is a good understanding of the consequences of failure.
In some cases, it may be apparent from a field inspection or a review of aerial photographs,Flood Insurance Rate Maps, and recent topographic maps, that consequences attrib-utable to damfailure would occur and be unacceptable. In other cases, detailed studies, including dambreak
analyses, will be required. It may also be necessary to perform field surveys to determine the
basement and first floor elevations of potentially affected habitable structures (such as residentialand commercial).
When conducting dambreak studies, the consequences of the incremental increase due to failureunder both normal (full reservoir with normal streamflow conditions prevailing) and floodflow
conditions up to the point where a dam failure would no longer significantly increase the threat
to life or property should be considered. For each flood condition, water surface elevations with
and without dam failure, flood wave travel times, and rates of rise should be determined. Thisevaluation is known as an incremental hazard evaluation (See Appendix B, Flowchart 2). Sincedambreak analyses and flood routing studies do not provide precise results, evaluation of the
consequences of failure should be conservative.
The type of dam and the mechanism that could cause failure require careful consideration if a
realistic breach is to be assumed. Special consideration should be given to the following factors:
• Size and shape of the breach
• Time of breach formation
• Hydraulic head
• Storage in the reservoir
• Reservoir inflow
15
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
22/58
In addition, special cases where a dam failure could cause domino-like failure of downstreamdams resulting in a cumulative flood wave large enough to cause a threat should be considered.
The area affected by dam failure during a given flow condition on a river is the additional areainundated by the incremental increase in flood elevation due to failure over that which would
occur normally by flooding without dam failure. The area affected by a flood wave resulting
from a theoretical dam breach is a function of the height of the flood wave and the downstreamdistance and width of the river at a particular location. An associated and important factor is the
flood wave travel time. These elements are primarily a function of the rate and extent of dam
failure, but also are functions of channel and floodplain geometry and roughness and channelslope.
The flood wave should be routed downstream to the point where the incremental effect of a
failure will no longer result in unacceptable additional consequences. When routing a
dambreak flood through the downstream reaches, appropriate concurrent inflows should be
considered in the computations. Downstream concurrent inflows can be determined using one ofthe following approaches:
• Concurrent inflows can be based on historical records if these records indicate that the
tributaries contributing to the flood volume are characteristically in a flood stage at the
same time that flood inflows to the reservoir occur. Concurrent inflows based onhistorical records should be adjusted so they are compatible with the magnitude of the
flood inflow computed for the dam under study.
• Concurrent inflows can be developed from flood studies for downstream reaches when
they are available. However, if these concurrent floods represent inflows to a downstream
reservoir, suitable adjustments must be made to properly distribute flows among thetributaries.
• Concurrent inflows may be assumed equal to the mean annual flood (approximately
bankfull capacity) for the channel and tributaries downstream from the dam. The mean
annual flood can be determined from flood flow frequency studies. As the distancedownstream from the dam increases, engineering judgment may be required to adjust the
concurrent inflows selected.
In general, the study should be terminated when the potential for loss of life and property
damage caused by routing floodflows appears limited. This point could occur when the following
takes place:
• There are no habitable structures, and anticipated future development in the floodplain islimited.
• Floodflows are contained within a large downstream reservoir.
16
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
23/58
• Floodflows are confined within the downstream channel.
• Floodflows enter a bay or ocean.
The failure of a dam during a particular flood may increase the area flooded and also alter the
flow velocity and depth of flow as well as the rate of rise of flood flows. These changes in floodflows could also affect the amount of damage. To fully evaluate the hazard created by a dam, a
range of flood magnitudes needs to be examined. Water surface profiles, flood wave travel times,
and rates of rise should be determined for each condition.
The results of the downstream routing should be clearly shown on inundation maps with the breach-wave travel time, maximum depth of flow, and maximum velocity, indicated at critical
downstream locations. The inundation maps should be developed at a scale sufficient to identify
downstream habitable structures within the impacted area. The current recommended method
for dambreak analysis is the unsteady flow and dynamic routing method used in the
National Weather Service (NWS) model.
Most of the methods used for estimating dambreak hydrographs, including the widely used NWS
model, required selecting the size, shape, and time of formation of the dam breach as input parameters for the computations. Therefore, sensitivity analyses are considered necessary.
Sensitivity analyses, based on varying flood inflow conditions and breach parameters, should be
performed only to the extent necessary to make a decision.
Dambreak studies should be performed in accordance with accepted Guidelines. Refer to
Appendix A for a list of sources of information related to dambreak studies.
6. Incremental Hazard Evaluation for Inflow Design Flood Determination. The appropriateIDF for a project is selected based on the results of the incremental hazard evaluation. This
evaluation involves simulating a dam failure during normal and floodflow conditions and routing
the water downstream. The additional down-stream threat due to the incremental increase inwater surface elevation from dam failure is assessed for each failure scenario.
To evaluate the incremental increase in consequences due to dam failure, begin with the normalinflow condition and the reservoir at normal full reservoir level with normal streamflow
conditions prevailing. That condition should be routed through the dam and downstream areas,
with the assumption that the dam remains in place. The same flow should then be routed throughthe dam with the assumption that the dam fails.
The incremental increase in downstream water surface elevation between the with-failure and
without-failure conditions should then be determined, i.e., how much higher would the water
downstream be if the dam failed than if the dam did not fail? The consequences that could result
should then be identified. If the incremental rise in flood water downstream results inunacceptable additional consequences, assess the need for remedial action.
17
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
24/58
If the study under normal flow conditions indicates no adverse consequences, the same analysesshould be done for several larger flood levels to determine the greatest unacceptable
consequences. Under each incrementally larger inflow condition, identify the consequences of
failure. For each larger assumed flood inflow condition (which can be percentages of the
probable maximum flood (PMF)):
• assume the dam remains in place during the nonfailure conditions; and
• assume the dam fails when the peak reservoir elevation is attained for the assumed inflow
condition.
It is not appropriate to assume that a dam fails on the rising limb of the inflow hydrograph.
For example, current methods cannot accurately determine the extent of overtopping that anearth dam can withstand or how rapidly the dam will erode and ultimately breach from
overtopping. Therefore, until such methodologies are available and proven, a conservative
approach should be followed which assumes that failure occurs at the peak of the floodhydrograph. The assumption should also be made that the dam has been theoretically modified tocontain or safely pass all lower inflow floods. This is an appropriate assumption because this
procedure requires that the dambreak analyses start at the normal operating condition, with
incremental increases in the flood inflow condition for each subsequent failure scenario up to the point where a failure no longer constitutes unacceptable additional consequences. In summary,
before selecting larger floods for analysis, determine what failure at a lower flood constituted a
threat to downstream life and property.
The above procedure should be repeated until the flood inflow condition is identified such that a
failure at that flow or larger flows (up to the PMF) will no longer result in unacceptable
additional consequences. The resultant flood flow is the IDF for the project. The maximum IDFis always the PMF, but in many cases the IDF will be substantially less than the PMF.
A PMF should be determined if it is needed for use in the evaluation. If a PMF value is already
available, it should be reviewed to determine if it is still appropriate. The probable maximum precipitation (PMP) for the area should be determined either through the use of the
Hydrometeorological Reports (HMR's) developed by the NWS or through the services of aqualified hydrometeorologist. In addition, the hydrologic characteristics of the drainage basin
that would affect the runoff from the PMP into the reservoir should be determined. After this
information is evaluated, the PMF can be determined.
Once the appropriate IDF for the dam has been selected (whether it is the PMF or somethingless), it should then be determined whether the dam can safely withstand or pass all floodflowsup through the IDF. If it can, then no further evaluation or action is required. If it cannot, then
measures must be taken to enable the project to safely accommodate all floods up through the
IDF to alleviate the incremental increase in unacceptable additional consequences a failure mayhave on areas downstream.
18
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
25/58
It is important to investigate the full range of flood flow conditions to verify that a failure underflood flows larger than the selected IDF up through the PMF will not result in any additional
hazard. In addition, once the design for remedial repairs is selected, the IDF should be verified
for that design.
Appendix B provides specific guidance and procedures, including a comprehensive
flowchart, for conducting an incremental hazard evaluation to select the appropriate IDF
for a dam and determine the need for remedial measures.
7. Criteria for Selecting the Inflow Design Flood. Ideally, dams should be able to safely
accommodate floodflows in a manner that will not increase the danger to life and propertydownstream. However, this situation is not always the case, and may not always be achievable.
There are various methods or reasons for selecting the inflow design flood and determining
whether the dam can safely accommodate the flood. The method chosen may be determined by
the amount of time and/or funds available to conduct an evaluation. For example, if time andfunds are scarce, a conservative inflow design flood (e.g., the PMF) can be selected.
Sometimes, inflow design flood selection is straightforward, i.e., given certain criteria, a specific
inflow design flood must be used, due to political decisions and policies established by
government agencies. For example, statutes may require that a flood such as the PMF, a specific
fraction of the PMF, or a flood of specific frequency be selected for a dam with a certain hazardclassification. Fortunately, the most widely accepted approach involves incremental hazard
evaluations to identify the appropriate IDF for a dam.
There is not a separate IDF for each section of a dam. A dam is assigned only one IDF, and it is
determined based on the consequences of failure of the section of the dam that creates thegreatest hazard potential downstream. This should not, however, be confused with the design
criteria for different sections of a dam which may be based on the effect of their failure on
downstream areas.
The PMF should be adopted as the IDF in those situations where consequences attributable to
dam failure for flood conditions less than the PMF are unacceptable.
A flood less than the PMF may be adopted as the IDF in those situations where the consequencesof dam failure at flood flows larger than the selected IDF are acceptable. In other words, where
detailed studies conclude that the risk is only to the dam owners' facilities and no increased
damage to downstream areas is created by failure, a risk-based approach is acceptable.Generally, acceptable consequences exist when evaluation of the area affected indicates thefollowing:
19
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
26/58
• There are no permanent human habitations, known national security installations, or
commercial or industrial developments, nor are such habitations or commercial orindustrial developments projected to occur within the potential hazard area in the
foreseeable future.
• There are permanent human habitations within the potential hazard area that would beaffected by failure of the dam, but there would be no significant incremental increase
in the threat to life or property resulting from the occurrence of a failure during
floods larger than the proposed IDF. For example, if an impoundment has a small
storage volume and failure would not add appreciably to the volume of the outflow flood
hydrograph, it is likely that downstream inundation would be essentially the same with or
without failure of the dam.
The consequences of dam failure may not be acceptable if the hazard potential to thesehabitations is increased appreciably by the failure flood wave or level of inundation. When a
dambreak analysis shows downstream incremental effects of approximately two feet or
more, engineering judgment and further analysis will be necessary to finally evaluate the
need for modification to the dam. In general, the consequences of failure are considered
acceptable when the incremental effects (depth) of failure on downstream structures are
approximately two feet or less. However, the two-foot increment is not an absolute
decision-making point. Sensitivity analyses and engineering judgment are the tools used in
making final decisions. For example, if it is determined that a mobile home sitting on blocks
can be moved and displaced by as little as six inches of water, then the acceptable incremental
impact would be much less than two feet. As a second example, if a sensitivity analysisdemonstrates that the largest breach width recommended is the only condition that results in an
incremental rise of two feet, then engineering judgment becomes necessary to determine whether
a smaller breach having acceptable consequences of failure is more realistic for the givenconditions, e.g., flow conditions, characteristics of the dam, velocity in vicinity of structures,
location, and type of structures.
In addition, selection of the appropriate magnitude of the IDF may include consideration of
whether a dam provides vital community services such as municipal water supply or energy.Therefore, a higher degree of protection may be required against failure to ensure those services
are continued during and following extreme flood conditions when alternate services are
unavailable. If losing such services is economically acceptable, the IDF can be less conservative.However, loss of water supply for domestic purposes may not be an acceptable public health
risk.
Flood frequency and risk-based analyses may be used to hold operation and maintenance
costs to a reasonable level, to maintain public confidence in owners and agencies
responsible for dam safety, and to be in compliance with local, state, or other regulations
20
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
27/58
applicable to the facility. Generally, it would not be an appropriate risk to design a dam havinga potential for failure at a flood frequency of less than once in 100 years.
When determining the effect flood inflows will have on dam safety, a hydrologic approach may be used. Simply stated, when determining the effect flood inflows will have on dam safety, the
following approach establishes the IDF for the project, and either:
• determines whether an existing project can safely accommodate the IDF; or
• determines how a new project will be designed to safely accommodate the IDF.
Because the entire spectrum of floods up to the PMF level generally needs to be considered inselecting the IDF, it is usually necessary to determine the PMP magnitudes and to develop the
PMF based on that information.
The effort involved in conducting PMP and PMF analyses is quite detailed. Depending on thesignificance of the study being pursued, these analyses should be directed by an engineer trained
and experienced in this specialized field.
The incremental hazard evaluation procedure presented in the previous section is the most direct
method for selecting an inflow design flood. However, there are times when selection becomesdifficult and it may be necessary to conduct further analyses with a risk-based approach. The
incremental hazard evaluation is, in essence, a risk-based approach.
C. PMFs for Dam Safety. The PMF is the upper limit of floods to be considered when selecting
the appropriate IDF for a dam.
1. General. A deterministic methodology should be used to determine the PMF. In thedeterministic methodology, a flood hydrograph is generated by modeling the physical
atmospheric and drainage basin hydrologic and hydraulic processes. This approach attempts to
represent the most severe combination of meteorologic and hydrologic conditions consideredreasonably possible for a given drainage basin. The PMF represents an estimate of the upper
limit of run-off that is capable of being produced on the watershed. Refer to Appendix A for a
list of sources of information related to flood studies.
2. PMP. The concept that the PMP represents an upper limit to the level of precipitation theatmosphere can produce has been stated in many hydrometeorological documents. The
commonly used approach in deterministic PMP development for non-orographic regions is to
determine the limiting dew point temperature at the surface (used to obtain the moisture
maximization factor) and to collect a "sufficient" sample of extreme storms. These extremestorms are moved to other parts of the study area. The latter are done through a method known as
storm transposition, i.e., the adjustment of moisture observed in a storm at its actual site of
occurrence to the corresponding moisture level at the site from which the PMP is to bedetermined. Storm transposition is based on the concept that all storms within a meteorologically
21
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
28/58
homogeneous region could occur at any other location within that region with appropriateadjustments for effects of elevation and moisture supply. The maximized transposed storm
values are then enveloped both depth-durationally and depth-areally to obtain PMP estimates for
a specific basin. Several durations of PMP should be considered to ensure the most appropriate
duration is selected.
In orographic regions, where local influences affect the delineation of meteorologicalhomogeneity, transposition is generally not permitted. Alternative procedures are offered for
these regions that are less reliant on the adequacy of the storm sample. Most of these procedures
involve development of both nonorographic and orographic components (sometimes anorographic intensification factor is used) of the PMP. Orographic and nonorographic PMPs are
then combined to obtain total PMP estimates for an orographic basin. Currently, generalized
PMP estimates are available for the United States (see Figure 3).
As our understanding and the availability of data increases, the "particular" PMP estimates that
appear in NWS HMRs may require adjustment to better define the conceptual PMP for a specificsite. Therefore, it may be appropriate to refine PMP estimates with site-specific or regional
studies. The results of available research, such as that developed by the Electric Power Research
Institute, should be considered in performing site-specific studies. Because these studies can become very time consuming and costly, the benefit of a site-specific study must be considered
carefully. Currently, generalized NWS PMP estimates are available for the entire conterminous
United States, as well as Alaska, Hawaii, and Puerto Rico.
D. Floods To Protect Against Loss of Benefits During the Life of the Project - Applicable
Only to Low-Hazard Dams
Dams identified as having a low-hazard potential should be designed to at least meet a minimum
standard to protect against the risk of loss of benefits during the life of the project, hold operationand maintenance costs to a reasonable level, maintain public confidence in owners and agenciesresponsible for dam safety, and be in compliance with local, state, or other regulators applicable
to the facility. Floods having a particular frequency may be used for this analysis. In general, itwould not be appropriate to design a dam having a low-hazard potential for a flood having an
average return frequency of less than once in 100 years.
22
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
29/58
IV. ACCOMMODATING INFLOW DESIGN FLOODS
A. Flood Routing Guidelines
1. General. Site-specific considerations should be used to establish flood routing criteria foreach dam and reservoir. The criteria for routing any flood should be consistent with the reservoir
regulation procedure that is to be followed in actual operation. The general guidelines to be used
in establishing criteria are presented below and should be used if applicable.
2. Guidelines for Initial Elevations. In general, if there is no allocated or planned flood controlstorage (i.e., run-of-river), the flood routing usually begins with the reservoir at the normal
maximum pool elevation. If regulation studies show that pool levels would be lower than thenormal maximum pool elevation during the critical inflow design flood (IDF) season, then the
results of those specific regulation studies should be analyzed to determine the appropriate initial
pool level for routing the IDF.
3. Reservoir Constraints. Flood routing criteria should recognize constraints that may exist on
the maximum desirable water surface elevation. A limit or maximum water surface reachedduring a routing of the IDF can be achieved by providing spillways and outlet works with
adequate discharge capacity. Backwater effects of floodflow into the reservoir must specifically
be considered when constraints on water surface elevation are evaluated. Reservoir constraintsmay include the following:
• Topographic limitations on the reservoir stage which exceed the economic limits of dike
construction; public works around the reservoir rim, which are not to be relocated, such
as water supply facilities and sewage treatment plants; dwellings, factories, and other
developments around the reservoir rim, which are not to be relocated. If there is a loss ofstorage capacity caused by sediment accumulation in portions of the reservoir, then this
factor should be accounted for in routing the IDF. Sediment deposits in reservoir
headwater areas may build up a delta, which can increase flooding in that area, as well asreduce flood storage capacity, thereby having an effect on routings.
• Geologic features that may become unstable when inundated and result in landslides,
which would threaten the safety of the dam, domestic and/or other developments, ordisplace needed storage capacity.
• Flood plain management plans and objectives established under federal or state
regulations and/or authorities.
4. Reservoir Regulation Requirements. Considerations to be evaluated when establishing floodrouting criteria for a project include the following:
23
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
30/58
• Regulation requirements to meet project purposes, the need to impose a maximum
regulated release rate to prevent flooding or erosion of downstream areas and control rateof drawdown, the need to provide a minimum regulated release capacity to recover flood
control storage for use in regulating subsequent floods, the practicability of evacuatingthe reservoir for emergencies and for performing inspection, maintenance, and repair.Spillways, outlet works, penstocks, and navigation locks for powerplants are sized to
satisfy project requirements and must be operated in accordance with specific instructions
if these project works are relied upon to make flood releases, subject to the following
limitations:
o Only those release facilities which can be expected to operate reliably under theassumed flood condition should be assumed to be operational for flood routing.
Reliability depends upon structural competence and availability for use.Availability and reliability of generating units for flood release during major
floods should be justified. Availability of a source of auxiliary power, for gate
operation, effects of reservoir debris on operability and discharge capacity ofgates and other facilities, accessibility of controls, design limits on operating
head, reliability of access roads, and availability of operating personnel at the site
during floods are other factors to be considered in determining whether to assume
release facilities are operational. A positive way of making releases to the naturalwatercourse by use of a bypass or wasteway must be available if canal outlets are
to be considered available for making flood releases. Bypass outlets for
generating units may be used if they are or can be isolated from the turbines bygates or valves.
o In flood routing, assumed releases are generally limited to maximum values
determined from project uses, by availability of outlet works, tailwater conditionsincluding effects of downstream tributary inflows and wind tides, and
downstream nondamaging discharge capacities until allocated storage elevationsare exceeded. When a reservoir's capacity in regulating flows is exceeded, then
other factors, particularly dam safety, will govern releases. During normal flood
routing, the rate of outflow from the reservoir should not exceed the rate of inflowuntil the outflow begins to exceed the maximum project flood discharge capacity
at normal pool elevation, nor should the maximum rate of increase of outflow
exceed the maximum rate of increase of inflow. This is to prevent outflowconditions from being more severe than pre-dam conditions. An exception to the
above would be where streamflow forecasts are available and pre-flood releases
could reduce reservoir levels to provide storage for flood flows.
5. Evaluation of Domino-like Failure. If one or more dams are located downstream of the site
under review, the failure wave should be routed downstream to determine if any of the
24
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
31/58
downstream dams would breach in a domino-like action. The flood routing of flows entering themost upstream of a series of such dams may be either dynamic or level pool. The routing through
all subsequent downstream reservoirs should be a dynamic routing. Tailwater elevations should
consider the effect of backwater from downstream constrictions.
B. Spillway and Flood Outlet Selection and Design
1. General. Spillways and flood outlets should be designed to safely convey major floods to thewatercourse downstream from the dam. They are selected for a specific dam and reservoir on the
basis of release requirements, topography, geology, dam safety, and project economics.
2. Gated or Ungated Spillways. An ungated spillway releases water when-ever the reservoir
elevation exceeds the spillway crest level. A gated spillway can regulate releases over a broad
range of water levels.
Ungated spillways are more reliable than gated spillways. Gated spillways provide greater
operational flexibility. Operation of gated spillways and/or their regulating procedures shouldgenerally ensure that the peak flood outflow does not exceed the natural downstream flow that
would occur without the dam.
The selection of a gated or ungated type of spillway for a specific dam depends upon site
conditions, project purposes, economic factors, costs of operation and maintenance, the IDFitself, and other considerations.
The following paragraphs focus on considerations that influence the choice between gated and
ungated spillways:
•
Discharge capacity - For a given spillway crest length and maximum allowable watersurface elevation, a gated spillway can be designed to release higher discharges than anungated spillway because the crest elevation may be lower than the normal reservoir
storage level. This is a consideration when there are limitations on spillway crest length
or maximum water surface elevation.
• Project objectives and flexibility - Gated spillways permit a wide range of releases and
have capability for pre-flood drawdown.
• Operation and maintenance - Gated spillways may experience more operational problemsand are more expensive to construct and maintain than ungated spillways. Constant
attendance or several inspections per day, by an operator during high water levels, ishighly desirable for reservoirs with gated spillways, even when automatic or remotecontrols are provided. During periods of major flood inflows, the spillway should be
closely monitored. Gated spillways are more subject to clogging from debris and
jamming from ice, whereas properly designed ungated spillways are basically free fromthese problems. Gated spillways require regular maintenance and periodic testing of gate
operations. However, ungated spillways can have flashboards, trip gates, and stop log
25
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
32/58
sections, which can have operational problems during floods and may require constantattendance or several inspections per day during high water levels.
• Reliability - The nature of ungated spillways reduces dam failure potential associatedwith improper operation and maintenance. Where forecasting capability is unreliable, or
where time from the beginning of runoff to peak inflow is only a few hours, ungated
spillways are more reliable, particularly for high-hazard structures. Consequences of
failure of operation equipment or errors in operation can be severe for gated spillways.
• Data and control requirements - Operational decisions for gated spillways should have
real time hydrologic and meteorologic data to make proper regulation possible.
• Emergency evacuation - Unless ungated spillways have removable sections, such as
flashboards, trip gates, or stop log sections, they cannot be used to evacuate a reservoir
during emergencies. The capability of gated spillways to draw down pools from the top
of the gates to the spillway crest can be an advantage when emergency evacuation toreduce head on the dam is a concern.
• Economics and selection - Designs to be evaluated should be technically adequatealternatives. Economic considerations often indicate whether gated or ungated spillways
are selected. The possibility of selecting a combination of more than one type of spillway
is also a consideration. Final selection of the type of crest control should be based on acomprehensive analysis of all pertinent factors, including advantages, disadvantages,
limitations, and feasibility of options.
3. Design Considerations. Dams and their appurtenant structures should be designed to give
satisfactory performance. These Guidelines identify three specific classifications of spillways(service, auxiliary, and emergency) and outlet works that are used to pass floodwaters, each
serving a particular function. The following paragraphs discuss functional requirements.
Service spillways should be designed for frequent use and should safely convey releases from a
reservoir to the natural watercourse downstream from the dam. -Considerations must be given to
waterway free-board, length of stilling basins, if needed, and amount of turbulence and other performance characteristics. It is acceptable for the crest structure, discharge channel (e.g., chute,
conduit, tunnel), and energy dissipator to exhibit marginally safe performance characteristics for
the IDF. However, they should exhibit excellent performance characteristics for frequent andsustained flows, such as up to the 1-percent chance flood event. Other physical limitations may
also exist that have an effect on spillway sizing.
26
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
33/58
Auxiliary spillways are usually designed for infrequent use and it is acceptable to sustain limiteddamage during passage of the IDF. The design of auxiliary spillways should be based on
economic considerations and should be subject to the following requirements:
•
The auxiliary spillway should discharge into a watercourse sufficiently separated fromthe abutment to preclude abutment damage and should discharge into the main stream a
sufficient distance downstream from the toe of the dam so that flows will not endanger
the dam's structural integrity or usefulness of the service spillway. The auxiliary spillwaychannel should either be founded in competent rock or an adequate length of protective
surfacing should be provided to prevent the spillway crest control from degrading to the
extent that it results in an unacceptable loss of conservation storage or a largeuncontrolled discharge which exceeds peak inflow.
Emergency spillways may be used to obtain a high degree of hydrologic safety with minimal
additional cost. Because of their infrequent use, it is acceptable for them to sustain significant
damage when used and they may be designed with lower structural standards than those used for
auxiliary spillways.
An emergency spillway may be advisable to accommodate flows resulting from misoperation or
malfunction of other spillways and outlet works. Generally, they are sized to accommodate aflood smaller than the IDF. The crest of an emergency spillway should be set above the normal
maximum water surface (attained when accommodating the IDF) so it will not overflow as a
result of reservoir setup and wave action. The design of an emergency spillway should be subjectto the following limitations:
• The structural integrity of the dam should not be jeopardized by spillway operation.
Large conservation storage volumes should not be lost as a result of degradation of the
crest during operation. The effects of a downstream flood resulting from uncontrolled
release of reservoir storage should not be greater than the flood caused by the IDF
without the dam.
Outlet works used in passing floods and evacuating reservoir storage space should be designedfor frequent use and should be highly reliable. Reliability is dependent on foundation conditions,
which influence settlement and displacement of waterways, on structural competence, onsusceptibility of the intake and conduit to plugging, on hydraulic effects of spill-way discharge,
and on operating reliability.
C. Freeboard Allowances1. General. Freeboard provides a margin of safety against overtopping failure of dams. It is
generally not necessary to prevent splashing or occasional overtopping of a dam by waves underextreme conditions. However, the number and duration of such occurrences should not threaten
the structural integrity of the dam, interfere with project operation, or create hazards to
personnel. Freeboard provided for concrete dams can be less conservative than for embankment
27
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
34/58
dams because of their resistance to wave damage or erosion. If studies demonstrate that concretedams can withstand the IDF while overtopped without significant erosion of foundation or
abutment material, then no freeboard should be required for the IDF condition. Special
consideration may be required in cases where a powerplant is located near the toe of the dam.
The U.S. Bureau of Reclamation has developed guidelines (See Appendix A) that provide
criteria for freeboard computations.
Normal freeboard is defined as the difference in elevation between the top of the dam and the
normal maximum pool elevation. Minimum freeboard is defined as the difference in pool
elevation between the top of the dam and the maximum reservoir water surface that would resultfrom routing the IDF through the reservoir. Intermediate freeboard is defined as the difference
between intermediate storage level and the top of the dam. Intermediate freeboard may be
applicable when there is exclusive flood control storage.
2. Freeboard Guidelines. Following are guidelines for determining appropriate freeboard
allowances:
• Freeboard allowances should be based on site-specific conditions and the type of dam
(concrete or embankment). Both normal and minimum freeboard requirements should be
evaluated in determining the elevation of the top of the dam. The resulting higher top of
dam elevation should be adopted for design. Freeboard allowances for wind-wave actionshould be based upon the most reliable wind data available that are applicable to the site.
The significant wave should be the minimum used in determining wave runup, and the
sum of wind setup and wave runup should be used for determining requirements for thiscomponent of freeboard.
•
Computations of wind-generated wave height, setup, and runup should incorporateselection of a reasonable combined occurrence of pool level, wind velocity, winddirection, and wind durations based on site-specific studies. It is highly unlikely that
maximum winds will occur when the reservoir water surface is at its maximum elevation
resulting from routing the IDF, unless the reservoir capacity is small compared to floodvolume because the maximum level generally persists only for a relatively short period of
time (a few hours). Consequently, winds selected for computing wave heights should be
appropriate for the short period the pool would reside at or near maximum levels. Normal pool levels persist for long periods of time. Consequently, maximum winds should be
used to compute wave heights.
•
Freeboard allowance for settlement should be applied to account for consolidation offoundation and embankment materials when uncertainties exist in computational methods
or data used yield unreliable values for camber design. Freeboard allowance forsettlement should not be applied where an accurate determination of settlement can be
made and is included in the camber. Freeboard allowance for embankment dams for
estimated earthquake-generated movement, resulting seiches, and permanent
embankment displacements or deformations should be considered if a dam is located in
28
-
8/20/2019 Federal Guidelines for Dam Safety.pdf
35/58
an area with potential for intense seismic activity. Reduction of freeboard allowances onembankment dams may be appropriate for small fetches, obstructions that impede wave
generation, special slope and crest protection, and other factors.
•
Freeboard allowance for wave and volume displacement due to potential landslides,which cannot be economically removed or stabilized, should be considered if a reservoir
is located in a topographic setting where the wave or higher water resulting from
displacement may be destructive to the dam or may cause serious downstream damage.
• Total freeboard allowances should include only those components of freeboard which can
reasonably occur simultaneously for a particular water surface elevation. Components of
freeboard and combinations of those components, which have a reasonable probability ofsimultaneous occurrence, are listed in the following paragraphs for estimating minimum,
normal, and intermediate freeboards. The top of the dam should be established toaccommodate the most critical combination of water surface and freeboard components
from the following combinations.
For minimum freeboard combinations, the following components, when they can reasonably
occur simultaneously, should be added to determine the total minimum freeboard requirement:
• Wind-generated wave runup and setup for a wind appropriate for the maximum reservoir
stage for the IDF.
• Effects of possible malfunction of the spillway and/or outlet wor