FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1...

58
1 FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS FOR FY 2011 MINISTRIES, DEPARTMENTS AND AGENCIES (MDAs) FEDERAL CAPITAL TERRITORY (FCT) S/N ITEM/SERVICE NAME OF COMPANY IMPLEMENTING AGENCY COST DATE DURATION 1 Variation of the Contract Sum for the provision of Engineering Infrastructure to Kubwa Satellite Town (Districts 4&5), Abuja Messrs. S.C.C Nigeria Limited Ministry of Federal Capital Territory N 42,683,490,832.49 2/11/11 2 Years 2 Variation of the Contract Sum for the provision of Engineering Infrastructure to Karshi Satellite Town (Districts 1&2), Abuja Messrs. S.C.C Nigeria Limited Ministry of Federal Capital Territory N 28,220,048,498.00 2/11/11 80 Weeks 3 Award of Contract for the Rehabilitation of Lower Usuma Dam (LUD) Water Treatment Plant (Phase II) Messrs. Cupero (Nigeria) Ltd. Federal Capital Territory N 1,018,980,566.82 16/11/11 18 Months 4 Award of contracts for the Operation, Maintenance and Training of Staff for Wupa Basin Sewage Treatment Plant Messrs. SCC (Nigeria) Limited Federal Capital Territory N 1,586,451,516.76 07/12/11 2 Years (from 16th April 2011 to 15th April 2013)

Transcript of FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1...

Page 1: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

1

FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS FOR FY 2011 MINISTRIES, DEPARTMENTS AND AGENCIES (MDAs)

FEDERAL CAPITAL TERRITORY (FCT)

S/N

ITEM/SERVICE NAME OF COMPANY IMPLEMENTING

AGENCY COST DATE DURATION

1 Variation of the Contract Sum for the provision of Engineering Infrastructure to Kubwa Satellite Town (Districts 4&5), Abuja

Messrs. S.C.C Nigeria Limited

Ministry of Federal Capital Territory

N42,683,490,832.49

2/11/11

2 Years

2 Variation of the Contract Sum for the provision of Engineering Infrastructure to Karshi Satellite Town (Districts 1&2), Abuja

Messrs. S.C.C Nigeria Limited

Ministry of Federal Capital Territory

N28,220,048,498.00 2/11/11

80 Weeks

3 Award of Contract for the Rehabilitation of Lower Usuma Dam (LUD) Water Treatment Plant (Phase II)

Messrs. Cupero (Nigeria) Ltd.

Federal Capital Territory

N1,018,980,566.82 16/11/11

18 Months

4 Award of contracts for the Operation, Maintenance and Training of Staff for Wupa Basin Sewage Treatment Plant

Messrs. SCC (Nigeria) Limited

Federal Capital Territory

N1,586,451,516.76

07/12/11

2 Years (from 16th April 2011 to 15th April 2013)

Page 2: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

2

5 Award of Contract for the Supply of 28 Units of Waste Compacting Trucks (1 x Garbage Body 20 + 1.5m3 Capacity, Mounted on Mercedes Benz 3340, 6x4 Chasis with Euro Engine)

Messrs. Geodetics Offshore Services Limited

Federal Capital Territory Administration

N1,071,577,507.41

14/12/11

6 Months

6 Award of Contract for the Establishment of Plant Nursery, Tree Planting, Landscaping and Beautification of Umaru Musa Yar ‘Adua Expressway, Airport Road, FCT, Abuja

Messrs. Kashton Concepts (Nig) Ltd

Federal Capital Territory Administration

N1,451,605,114.64

14/12/11

18 Months

7 Award of contract for the supply of 2 Heavy Duty Recovery Equipment MB Chasis, 50 Ton Hydraulic Wrecker, with a dual 50,000lbs

Messrs. Balyn Auto (Nigeria) Ltd.,

Federal capital Territory

N180,999,000.00

21/12/11

8 weeks

8 Award of contract for the supply of 8 units of 3000MX and 4 units LN50 Motorized Street Sweepers

Messrs. Linens ‘’N’’ Moore (Nigeria) Limited

Federal Capital Territory

N405,677,546.40

21/12/11

6 Months

9 Award of Contract for the Supply of 8No. Light Duty Recovery Equipment for the FCT Directorate of Road Traffic Services (DRTS) under the Transportation Secretariat

Messrs Balyn Auto

(Nigeria) Limited Federal Capital Territory

N151,515,000.00

18/01/12

6 Weeks

Page 3: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

3

10 Award of Contract for the Supply of 2 units Mercedes Benz with Muller Canal Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting Installation

Messrs Maxtraco

Integrated Concepts

Limited

Federal capital Territory

N130,963,218.75

18/01/12

6 Months

11 Award of Contract for the Development of Phase II of District I Abuja North Phase IV West of the Federal Capital City (FCC)

Messrs. Salini

(Nigeria) Limited Federal Capital Territory

N25,954,847,809.80

25/01/12

48 Months

12 Award of Contract for the Supply of 35 Operational Vehicles for the FCT Directorate of Road Traffic Services (DRTS)

Messrs. Elizade

Nigeria Limited Federal Capital Territory

N239,400,000.00

01/02/12

4 Weeks

13 Award of Contract for the Supply of 6 units of 30 Tonnes Mercedes Benz Diesel Engine RORO Trucks

Messrs. Yae

International Limited Federal Capital Territory

N203,590,497.36 29/02/2012

6 Months

TOTAL N103,299,147,108.43

Page 4: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

4

MINISTRY OF AVIATION

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of contract for Procurement, Installation and Commissioning of ILS/DME in 5 Airports and DVOR/DME in 5 Airports

Messrs. Salbodi Group Ltd/Indra Sistemas S.A

Ministry of Aviation

N1,590,361,027.20 07/12/11 10 Months

2

Direct/repeat Procurement of additional 696No. of SCA 120IN Heat Proximity Clothing form the Original Equipment Manufacturers

Messrs. Sancheong Products of South Korea Through Messrs. Plastisol BV of the Netherlands (Accredited Representatives in Nigeria)

Ministry of Aviation

USD1,577,136 payable at the prevailing Exchange Rate at the time of opening the Letter of Credit

07/12/11 4 Months

TOTAL USD1,577,136.00 N1,590,361,027.20

Page 5: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

5

MINISTRY OF COMMUNICATIONS TECHNOLOGY

1

AWARD OF CONTRACT FOR THE PROVISION OF ICT-ENABLED LEARNING THROUGH THE SCHOOLS ACCESS PROGRAM BY UNIVERSAL SERVICE PROVISION FUND WITH THE COMPLETION PERIOD OF 36 WEEKS

S/N NAME OF FIRM/CONTRACTOR IMPLEMENTING AGENCY

No. of

Schools

Project Cost

N

Date

i Messrs. Zinox Technologies

Ltd

Ministry of

Communication

Technology

70 N1,166,621,253.00 14/09/11

ii Messrs. Edtek Learning

ServicesLtd.

Ministry of

Communication

Technology

60 N999,961,074.00 14/09/11

iii Messrs. MDS Technologies Ministry of

Communication

Technology

60 N999,961,074.00 14/09/11

iv Messrs. Chips,Bites and

Bytes Ltd.

Ministry of

Communication

Technology

60 N999,961,074.00 14/09/11

v Messrs ICS Ltd. Ministry of

Communication

Technology

55 N916,630,948.50 14/09/11

Page 6: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

6

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

2 Award of contract for the Construction of the National Information Technology Center by Galaxy Backbone Plc

Messrs. Sageto (Nig) Ltd.

Ministry of Communications Technology

N7,274,638,250.51 07/12/11 104 weeks

3 Award of Contract for the for the Provision of IT and Connectivity services to the scale-up of the CGS to Local Government Areas

Messrs. Galaxy Backbone Plc

Presidency /Galaxy Backbone

N391,272,598.98 17/08/11

TOTAL N14,115,659,740.79

vi Messrs Dialogue Global Links

Ltd.

Ministry of

Communication

Technology

42 N699,972,751.80 14/09/11

vii Messrs Sidmach

Technologies

Ministry of

Communication

Technology

40 N666,640,716.00 14/09/11

TOTAL 387 N6,449,748,891.30

Page 7: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

7

FEDERAL MINISTRY OF EDUCATION

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the Execution of the Pilot Phase of the Nigerian Universities Electronic Teaching and Learning Platform in 12 Universities, 2 (1 Federal and 1 State) from each of the 6 Geo-Political Zones

Messrs. Richfield Technology Ltd

Ministry of Education

N325,274,000.00 16/11/11 8 Weeks

2i Award of Contract for the Procurement of Furniture for Lecture Theatres for 13 faculties( Arts, Engineering, Physical Sciences, Veterinary Medicine, Pharmacy, Agriculture, Social Sciences, Education, Business Administration, Dentistry, Medicine, Health Sciences & Technology and Law) in the University of Nigeria, Nsukka

Messrs. Zito Phranzlo International Ltd.

Ministry of Education

N453,871,600.00 16/11/11 40 Weeks

2ii Award of Contract for the Procurement of Ubiquitous Wireless Network for the ICT Backbone Infrastructure for the

Messrs. BCX Networks Ltd., working with Wavion Wireless

Ministry of Education

N275,243,678.00 16/11/11 12 Weeks

Page 8: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

8

Campuses of the University of Nigeria, Nsukka

Network of Israel, Business Connection of South Africa and Xiruus Inc. of USA

3 AWARD OF CONTRACT FOR THE PRINTING AND DISTRIBUTION OF ENGLISH LANGUAGE, MATHEMATICS, ACTIVITY-BASED SCIENCE, BASIC SCIENCE AND TECHNOLOGY AND SOCIAL STUDIES TEXTBOOKS PRIMARIES 1 AND 2 PUPILS; AND LIBRARY RESOURCE MATERIALS FOR JUNIOR SECONDARY SCHOOL (JSS) STUDENTS IN PUBLIC SCHOOLS NATIONWIDE BY UBEC

S/N DESCRIPTION OF PROJECT (BOOKTITLE)

PUBLISHER/CONTRACTOR QUANTITY (No. OF COPIES)

TOTAL COST (N) DATE DURATION

i Printing and Distribution of of Macmillan New Pry. Maths. Books 1 for 16 States

Macmillan 640,000 256,320,000.00 30/11/11

6 weeks

ii Printing and Distribution of Macmillan New Pry. English Lang. Book 1 for 16 States

Macmillan 640,000 229,248,000.00

iii Printing and Distribution of Think and Do: Activity-Based Science Book for Pry. 1 for 34 States and the FCT

Macmillan 1,225,000 429,975,000.00

iv Printing and Distribution of Macmillan Brilliant Primary Social Studies Book 1 for 20 States

Macmillan 1,826,000 547,800,000.00

v Printing and Distribution of Macmillan New Pry. Maths. Book 2 for 16 States

Macmillan 640,000 256,320,000.00

Page 9: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

9

vi Printing and Distribution of Macmillan New Pry. Eng. Lang. Book 2 for 16 States

Macmillan 640,000 229,248,000.00 30/11/11

6 weeks

vii Printing and Distribution of Think and Do: Activity-based Science Book for Pry. 2 for 34 States and the FCT

Macmillan 1,225,000 429,975,000.00

viii Printing and Distribution of Macmillan Brilliant Primary Social Studies Book 2 for 20 States

Macmillan 1,826,000 547,800,000.00

ix Printing and Distribution of 160 Assorted Titles Library Resource Materials of various Quantities for the 36 States and the FCT

Macmillan 4,144,000 1,528,763,049.00

x Printing and Distribution of Evans Brothers Publishers Basic Science Books 1 for 5 States

Evans Brothers 415,000 132,800,000.00

xi Printing and Distribution of Evans Brothers Publishers Basic Science Books 2 for 5 States

Evans Brothers 415,000 132,800,000.00

xii Printing and Distribution of Evans Brothers Publishers Social Studies Books 1 for 11 States

Evans Brothers 747,000 242,775,000.00

xiii Printing and Distribution of Evans Brothers Publishers Social Studies Books 2 for 11 States

Evans Brothers 747,000 242,775,000.00

Page 10: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

10

xiv Printing and Distribution of Heinemann Basic Science & Technology Book 1 for 15 States

Heinemann 1,245,000 373,500,000.00 30/11/11

6 weeks

xv Printing and Distribution of Heinemann Basic Science Technology Book 2 for 15 States

Heinemann 1,245,000 373,500,000.00

xvi Printing and Distribution of University Press Plc Basic Science & Technology Book 1 for 12 States

University Press Plc 830,000 336,150,000.00

xvii Printing and Distribution of University Press Plc Basic Science &Technology Book 2 I for 12 States

University Press Plc 830,000 348,600,000.00

TOTAL 6,638,349,049.00

TOTAL N7,692,738,327.00

Page 11: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

11

FEDERAL MINISTRY OF ENVIRONMENT

S/N PROJECT DESCRIPTION NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST

DATE DURATION

1 Award of Contract for the Remediation of Sludge Pits at Kaduna Refinery and Petrochemical Company (KRPC) dumpsites and Improvement of the lives of the Impacted Communities

Messrs. Osprey Investment Group Ltd.

Ministry of Environment /Kaduna Refining and Petrochemical Company(KRPC)

N 1,811,005,875.00 14/09/11 43 Weeks

2 AWARD OF FOUR (4) CONTRACTS FOR THE EXECUTION OF EROSION CONTROL WORKS IN THE SOUTH EAST GEO-

POLITICAL ZONE OF THE COUNTRY

S/N Lot No

PROJECT DESCRIPTION NAME OF

FIRM/CONTRACTOR IMPLEMENTING

AGENCY COST DATE DURATION

i 6 Sakamori/Nwangene Flood

Control and Dredging in

Anambra State

Messrs. Benefaf

International Ltd.

Ministry of

Environment

N1,230,015,404.31

18

Months

ii 4 Nanka Recednt Landslide in Anambra State

Messrs. Rhino Maritime Services & Construction Ltd.

Ministry of Environment

N1,111,456,582.53 12 Months

Page 12: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

12

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

3 Award of Contract for the Channelization of Asa River and its Tributaries in Ilorin, Kwara State

Messrs Ambico Sendirian (Nigeria) Limited

Ministry of Environment

N1,233,761,817.20 04/04/12 12 Months

11 Obinagu/Akpulu/Enugueze-

Umunneobagu Erosion Control

in Enugu State.

Messrs. Nostro

Ventures Ltd.

Ministry of

Environment

N1,482,687,008.88 14/09/11

15

Months

15 Channelization of Iyi Okwu and

Iyi Udele Stream in Ebonyi

State.

Messrs City Central

Group

Ministry of

Environment

N1,544,233,440.75 14

Months

TOTAL N5,368,392,436.47

Page 13: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

13

TOTAL N8,413,160,128.67

FEDERAL MINISTRY OF FINANCE

S/N PROJECT DESCRIPTION

NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the Design, Procurement and Implementation of an Enterprise Resource Planning (Enterprise Finance and Accounts) Software for the Federal Inland Revenue Service

Messrs. Computer Warehouse Group Limited

Federal Inland Revenue Service (FIRS)

N150,000,000.00 10/08/11 12 Months

2 Award of contract of the 2No. A30 Sea Princess Boats with Back Up Spare Parts and Training of Crew Members

Messrs. John Holt Plc

Ministry of Finance N270,000,000.00 19/10/11 6 Weeks

3 Award of contract for consultancy services for stages 1 and 2 in respect of the construction of new Federal Inland Revenue Service (FIRS) Headquarters building in Abuja

Messrs. ATO Architects as consultant architects and their team of other consultants:

Ministry of Finance/ FIRS

N733,427,476.78 07/12/11 6 Months

Page 14: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

14

Structural Engineers, Messrs. IAA Associates Ltd; Mechanical Engineers, Messrs. Molecular Consultants and Associates; Electrical Engineers, Messrs. Molecular Consultants and Associates; and Quantity Surveyors, Messrs. Sea Surveyors Ltd

4 Award of Contract for the Construction of Senior Management Quarters at Jabi Lakeside, Abuja for the Nigeria Customs Service

Messrs Afdin Construction Limited

Ministry of Finance N6,677,406,192.03 inclusive of 5% VAT

11/04/12 104 weeks

5

Award of contract for the procurement of 1No. Cessna Citation CJ4 Acquisition Aircraft

Messrs Africair Incorporated

Ministry of

Finance/Nigeria

Customs Service

N1,737,503,898.90

(Equiv. to

USD11,123,584.50)

inclusive of 5% VAT

16/05/12 4 Months

TOTAL N9,568,337,567.71

Page 15: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

15

FEDERAL MINISTRY OF HEALTH

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1 Procurement of contraceptive by the United Nations Fund for Population Activities (UNFPA) for the Federal Ministry of Health

United Nations Fund for Population Activities (UNFPA)

Ministry of Health USD3,000,000.00 Federal Government counterpart funding

07/12/11

2 AWARD OF CONTRACTS FOR DIRECT PROCUREMENT OF ANTI-RETROVIRAL (ARV) DRUGS AND OTHER COMMODITIES

S/N Project Description Contractors

Implementing Agency

Contract Sum Date Completion Period

i Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug

Messrs. Emcure Nigeria Limited

Federal Ministry of Health

N124,500,000.00

07/12/11 2 weeks

ii Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug

Messrs. Strides Vital Nigeria Limited

N126,990,000.00

iii Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug

Messrs. Ranbaxy Nigeria Limited

N112,050,000.00

iv Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug

Messrs. Evans Medical Plc

N136,651,200.00

Page 16: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

16

v Supply of 50,576 packs of Lamivudine/Zidovudine/Nevirapine ARV MDG Branded Drug

Messrs. May & Baker Nigeria Plc

N129,480,000.00

vi Supply of 55,000 tablets of Cotrimoxazole tablets and 108,108 100ml suspension of co-trimoxazole

Messrs. Clarion Medical limited

N145,860,000.00

vii Supply of 428,000 tests Double Check Gold

Messrs. Biotec Laboratory Products

N194,033,880.00

viii Supply of 428,000 tests of Determine Test kits

Messrs. Acouns Nigeria Limited

N194,033,880.00

ix Supply of 428,000 Stat Pak Test Kits

Messrs. Chembio Diagnostics Limited

N194,033,880.00

TOTAL N1,357,632,840.00

TOTAL USD3,000,000.00 N1,357,632,840.00

Page 17: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

17

MINISTRY OF INTERIOR

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the Automation of the Citizenship and Business Department of the Ministry of Interior on a Public Private Partnership(PPP) using Buil Operate and Transfer (BOT) Model

Messrs. Anchor Dataware Solutions

Ministry of Interior

N455,055,743.87 25/01/12 Concession

Period of 5

years

TOTAL N455,055,743.87

FEDERAL MINISTRY OF LAND, HOUSING AND URBAN DEVELOPMENT

1 AWARD OF CONTRACT FOR THE CONSTRUCTION OF 6No. NEW FEDERAL GOVERNMENT SECRETARIATS IN EACH GEO-

POLITICAL ZONE OF THE FEDERATION

S/N Project Title/Location Contractors

Implementing Agency

Project Cost Date Completion Period

i Federal Government Secretariat, Awka, Anambra State

Messrs. Cosco Investment (Nig) Ltd Ministry of Lands,

Housing and Urban Development

N2,561,268,866.56

07/12/11 100 weeks ii Federal Government

Secretariat, Yenagoa, Bayelsa State

Messrs. Trenure (Nig) Ltd

N2,563,476,419.85

Page 18: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

18

iii Federal Government Secretariat, Gombe, Gombe State

Messrs. Vic Phranc (Nigeria) limited

N2,293,261,561.05

iv Federal Government Secretariat, Lafia, Nassarawa State

Messrs. Faplins (Nig) Ltd

N2,229,968,101.20

v Federal Government Secretariat, Osogbo, Osun State

Messrs. Golden Construction Company Limited

N2,548,444,283.80

vi Federal Government Secretariat, Gusau, Zamfara State

Messrs. Sageto Ltd N2,528,673,102.10

TOTAL N14,725,092,334.56

MINISTRY OF NIGER DELTA

1 AUGMENTATION OF THE CONTRACTS FOR THE EAST-WEST ROAD PROJECT, SECTIONS I, II-I AND II-II (MINISTRY OF NIGER

DELTA AFFAIRS)

S/N

PROJECT DESCRIPTION CONTRACT SUM

CONTRACTOR

DATE COMPLETION PERIOD

i

East-West Road, Section I (Warri-Kaiama) in Delta State

Revised Contract Sum From N64,125,000,000.00 To N112,166,400,493.60

Setraco

10/08/11 28 Months

Page 19: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

19

Ii

East-West Road, Section II-I (Port-Harcourt-Ahoada-Kaiama ) in Rivers State

Revised Contract Sum From N29,922,478,839.19 To N48,973,303,132.78

Setraco

10/08/11 28 Months

iii

East-West Road, Section II-II (Ahoada-Kaiama) in Rivers/Bayelsa State

Revised Contract Sum From N44,883,718,258.18 To N84,759,913,053.64

Setraco

10/08/11 28 Months

N245,899,616,680.02

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

2 Award of the Phase II Contract for the Construction of Ogriagbene – Torugbene 3.675Km Road with spurs to Edegbene and Torugbene townships in Delta State

Messrs. Setraco (Nig.) Limited

Ministry of Niger Delta Affairs

N3,453,476,572.13 09/11/11 12 Months

3 AUGMENTATION OF CONTRACTS FOR THE ENGINEERING CONSULTANCY SERVICES TO INCORPORATE FULL RESIDENT SUPERVISION OF

THE CONSTRUCTION OF FOUR (4) ROAD PROJECTS IN THE NIGER DELTA REGION

S/N Project Title Consultant

Implementing Agency

Revised Contract Sum

Date Completion

Period

Page 20: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

20

i Construction of Oriagbene-Torugbene Road

Messrs. Jon Khan Ltd.

Ministry of Niger Delta Affairs

N112,937,829.59

09/11/11

24 Months

ii Re-construction of Benin-Abraka Road

Messrs. Agbomire Engineering Consultants

N126,543,689.80

12 Months

Iii Construction of Odorobo-Kpakiama Bomadi Road

Messrs. Auspoint Ltd.

Ministry of Niger Delta Affairs

N115,663,821.44

09/11/11

18 Months

Iv Construction of Mbato Junction, Okputuite, Orie Market, Omara Road

Messrs. Techs Engineering Associates

N187,788,747.43

30 Months

TOTAL N583,184,097.26

S/N

ITEM/SERVICE NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

4 Ratification of the President’s Approval for the take over of the 18.7km Gbaregolor-Ogriagbene Road in Bomadi LGA of Delta State from the Delta State Government

Messrs. Setraco (Nigeria)Limited

Ministry of Niger Delta Affairs

N7,348,335,298.50 30/11/11 24 Months

TOTAL N257,284,612,647.91

Page 21: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

21

MINISTRY OF PETROLEUM RESOURCES

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the Dismantling and Reconstruction of Tank 13 and Rehabilitation of Tank 11, 12, & 22 at NNPC Depot, Mosimi

Messrs. Adano Engineering Co. (Nig.) Ltd.,

Ministry of Petroleum Resources

N3,904,635,594.84 30/11/11 20 Months

2

Award of Contract for the Execution of the Outstanding Works for Gas Supply to PHCN Power Plant, Papalanto

Messrs. MORPOL Engineering Services Limited/JAIHIND Projects Ltd.,

Ministry of Petroleum Resources

N1,015,094,003.11 Plus USD20,234,439.59 payable at the prevailing exchange rate at the time of payment Plus 5% VAT of N202,512,997.10

30/11/11 7 Months

3

Award of contract for the execution of the outstanding works for gas supply to PHCN Power Plant, Alaoji

Messrs. Oil serve Limited

Ministry of Petroleum Resources

N2,582,787,557.23 Plus USD8,216,198.44 Equivalent to N3,815,217,323.00 Plus 5% VAT of N190,760,866.10

21/12/11 7 Months

4 Award of contract for the construction of the NPDC Head Office Building at Oko Village, Benin City

Messrs. Bouygues (Nigeria) Limited

Ministry of Petroleum Resources

N14,196,623,377.35 21/12/11 24 Months

TOTAL USD28,450,638.03 N21,699,140,532.53

Page 22: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

22

MINISTRY OF POWER

1 AWARD OF CONTRACT FOR THE DESIGN, MANUFACTURE, SUPPLY, INSTALLATION AND COMMISSIONING OF 2NO. TRANSMISSION 330/132KV & 32/33KV SUB-STATIONS FOR THE TRANSMISSION COMPANY OF NIGERIA (TCN) PLC

S/N LOT NO. PROJECT

DESCRIPTION NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST

BUDGETARY PROVISION

DATE DURATION

i Lot 2010-21

Design, Manufacture, Supply, Installation and Commissioning of 2x150MVA,330/132KV Plus 2x60MVA,132/33KV Sub-Station at Akure with TurnIn/Turn out of One Circuit and 2x330KV Line Bay Extensions at Osogbo and Benin North Sub-stations

Messrs. Matelec ECL/S.A.L.

Ministry of Power

USD19,025,537.45 Plus N1,573,779,429.43 payable at the prevailing exchange rate at the time of payment inclusive of a provisional sum of N505,050,433.43 for 5% VAT on onshore payments,compensations and Contingency

Provided in 2011 Appropriation

10/08/11 24 Months

ii Lot 2010-22

Design, Manufacture, Supply, Installation and Commissioning of 2x150MVA,330/132K

Messrs. Matelec ECL/S.A.L.

Ministry of Power

USD15,129,749.22 Plus N1,267,800,811.75 payable at the

Provided in 2011 Appropriation

10/08/11 24 Months

Page 23: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

23

V Plus 2x60MVA,132/33KV Sub-Station at Olorunsogo

prevailing exchange rate at the time of payment inclusive of a provisional sum of N377,182,637.80 for 5% VAT on onshore payments,compensations and Contingency

USD34,155,286.67

Plus

N1,772,851,245.18

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

2 Award of Contract for the Supply of Aluminium Conductor Composite Core Reinforced (ACCCR)

Messrs. Composite Technology Corporation

Ministry of Power USD1,627,464.00 Plus N24,853,002.74 inclusive of 5% VAT

30/11/11 32 weeks

3 Revision of the Contract Sum for the Provision of Project Management Consultancy Service on the 3rd Benin-Onitsha 330kv Double Circuit

Messrs. Colenco Power Engineering Ltd.,

Ministry of Power USD2,610,413.16 Plus N204,452,067.90

30/11/11 30th June, 2012

Page 24: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

24

Transmission Line Project

4 AWARD OF CONTRACTS FOR THE PROVISION OF PROJECT MANAGEMENT CONSULTANCY SERVICE FOR 2010 HIGH VOLTAGE TRANSMISSION LINE AND SUB-STATION PROJECTS FOR THE TRANSMISSION COMPANY OF NIGERIA (MINISTRY OF POWER)

S/N COMPANY PROJECT MANAGEMENT CONSULTANCY SERVICE LOCATIONS

CONTRACT SUM DATE COMPLETION PERIOD

1 Messrs. Jiyoda Engineering Ltd

Erukan-Omotosho 330kv DC Transmission Line (132km) and Omotosho-Epe-Aja 330kv Double Circuit (DC) Transmission Line (135km)

N281,869,932.31 30/11/11

24 Months

2 Messrs. London Power Associates Ltd

2x150MVA, 330/132KV + 2x60MVA, 132/33KV Substation at Omotosho, 2x150MVA, 330/132KV + 2X60MVA, 132/33KV Substation at olorunsogo, 4x330kv Line Bay Extension at Erunkan 330/132kv Substation, 6x330kv Line Bay Extension at Omotosho Substation and 2x330kv Line Bay Extension at Aja 330/132kv Substation

USD1,463,293.68 Plus N76,477,693.77

3 Messrs. Fichtner

Engineering/Metr

osource Nigeria

Ltd

Benin North- Oshogbo 330kv DC Transmission Line with one Single Circuit turning in and out to New Akure (260km), 2x150MVA, 330/132KV + 2x60MVA, 132/33KV Substation at Akure, 2x330kv Line Bay Extension at Benin North and Oshogbo 330/132kv Substations

USD1,455,789.00 Plus N114,691,710.00

4 Messrs. AF-Colenco/Colenco Nigeria Ltd

Kano-Katsina 330KV DC Transmission Line (180km), 2x150MVA, 330/132KV + 2x60MVA, 132/33KV Substation at Katsina and 2x330kv line Bay Extension

USD1,896,503.00 Plus N110,376,420.00

Page 25: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

25

+ 1x75 MVAr Reactor at Kano 330/132kv Substation 30/11/11

24 Months

5 Messrs. Gopa- Intec International/UE SL

Kaduna Power Plant-Mando Road 330kv DC Transmission Line and 2x330kv Line Bay Extension at Mando and Akwanga – Lafia 132kv Transmission Line, 2x30/40MVA, 132/33kv Substation

€1,147,500.00 Plus N49,279,545.00

6 Messrs. Arcon Engineers/Afcon Offshore

Reinforcement with 1x150MVA, 330/132/33KV Transformer each at Kano AND Birni-Kebbi and Rehabilitation of Sokoto-Tlata Mafara 132kv Double Circuit Transmission Line

USD1,190,722.00 Plus N86,580,821.25

7 Messrs. Gopa- Intec International/UE SL

Extension of Kainki 330kv Substation with 330kv Single Circuit River Crossing and 1x150MVA, 330/132 Substation at Kainji, and Kainji –New Bussa 132kv DC Transmission Line, 2x30/40MVA, 132/33KV Substation at New Bussa , and Reinforcement with 1x60MVA, 132/33KV Transformer each at Hadejia, Katsina and Kontagora

€1,053,425.00 Plus N47,515,545.00

8 Messrs. Trans Africa/Elens Consult

Ikeja West – Ayobo 132kv DC Transmission Line with associated 2x60MVA, 132/33KV Substation at Ayobo and 2x60MVA, 132/33KV Substation at Odogunyan and Ikorodu-Odogunyan –Shagamu 132kv DC Transmission Line

USD888,811.00 Plus N131,628,210.00

30/11/11

24 Months

9 Messrs. Markcillio Engineering and Cobra 91 Limited

Onitsha-Oba-Nnewi-Ideato-Okigwe 132KV DC Transmission Line, 2x60MVA, 132/33KV Substation at Oba and 2x60MVA, 132/33KV at ideato

€691,470.00 Plus N72,412,425.31

10 Messrs. Energy Giants Drn Ltd

New Abeokuta-Igbo Ora- Lanlate and Tee off from Igbo Ora-Igangan, 132kv DC Transmission Lines (110km), 2x60MVA, 132/33KV Substation at Lanlate, 2x60MVA, 132/33JV Substation at Igangan and 132kv Switching Station at Igbo Ora

USD1,226,188.16

Page 26: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

26

11 Messrs. Great Northern Industries and Metanoya Group/Enzani

1x30/40MVA, 132/33KV Substation at Kwanar Dogara ant turn in and out of Zaria-Kano 132 132KV Transmission line at Kwanar Dangora, 2x30/40MVA, 132/33kv Substation at Tamburawa Water Supply and turn in and out of Zaria-Kano 132KV Transmission Line at Tamburawa water Supply

USD939,449.00 Plus N63,531,880.31

12 Messrs. Amal Engineering Services Ltd

Katsina-Dutsinma-Kankara-Malunfashi 132kv Transmission Line (173km), 2x30/40MVA, 132/33kv Substation at Kurfi, 2x30/40MVA,132/33KV Substation at Dutsinma, 2x30/40MVA, 132/33KV Substation at Kankara, 2x30/40MVA, 132/33KV Substation at Malunfashi, 2x132kv Line Bay Extension at Katsina 132/33kv Substation

N209,481,557.88 30/11/11

24 Months

13 Messrs. FM Chidez Ltd/GIT

Ganmo-Shongal 132kv DC Transmission Line (120km), 2x60MVA, 132/33KV Substation at Shongai, and 2x132kv Line bay Extension at Ganmo

USD888,856.92 Plus N63,525,000.00

14 Messrs. Pat-Sam & Partners

Owerri-Aboh Mbaise 132kv DC Transmission Line (26km), 2x60MVA, 132/33KV Substation at Aboh Mbaise, 2x132kv Line Bay Extension at Owerri 132kv Substation at Amasiri, 2x60MVA, 132/33KV Substation at Afikpo, 2x132kv Line Bay Extension at Nenwe 132/33kv Substation and 2x60MVA, 132/33KV Substation at Mpu

N249,359,029.50

15 Messrs. Yaroson & Partners

5.5km 1323kv Underground Cable from Golf Course Asokoro to Central Area 132kv Substation and 4.4 km 132kv Overhead Line from Katampe 330kv Substation to Golf Course Asokoro, 2x60MVA, 132/33KV Substation at Kukwaba with 6x33kv Outgoing Feeders, Daura-Dambatta 132kv DC Transmission Line (60km), 2x30/40MVA, 132/33KV Substation at Dambatta and 2x132kv Line Bay Extension at Daura 132/33kv Substation

N244,419,245.60

Page 27: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

27

16 Messrs. Derekson/Teshmont Ltd

Oshogbo-Ede 132kv DC Transmission Line (15km), 2x60MVA, 132/33KV Substation at Ede, 2X132KV Line Bay Extension at Oshogbo, 2x30/40MVA, 132 Substation at Efon Alaye and 2x132kv Line Bay Extension at Oke Agbe

N253,053,399.48 30/11/11

24 Months

5 AWARD OF CONTRACTS FOR THE CONSTRUCTION OF TRANSMISSION LINES AND SUBSTATIONS FOR THE TRANSMISSION

COMPANY OF NIGERIA(TCN)

S/N Project Description Contractors

Implementing Agency

Contract Sum Date Completion Period

i Lot 2011 – 1 Engineering, design, manufacture, Supply, Construction and Commissioning of the 235km 2nd Kaduna-Kano 330kv Double Circuit Transmission Line

Messrs. National Power Construction Corporation

Ministry of Power/Transmission Company of Nigeria (TCN)

USD42,968,950.21 Payable at prevailing rate at the time of exchange Plus N4,154,133,631.19

07/12/11 24 Months ii Lot 2011 – 2 Engineering, design, manufacture, Procurement, Supply, Construction and Commissioning of the 150 km Delta-Portharcourt 330kv Double Circuit Transmission Line

Messrs. Icomm Tele Ltd/PPP International Ltd

USD27,079,493.25 Plus N3,627,601,391.33

iii Lot 2011-3 Abakaliki-Amasiri 132kv Double Circuit Transmission Line

Messrs. Flour Engineering/Eurafric Energy Ltd

Ministry of Power/Transmission Company of Nigeria (TCN)

USD6,044,617.26 Plus N898,080,164.52

07/12/11 24 Months

Page 28: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

28

iv Lot 2011-4 Keffi-Kwoi-Kachia 132kv Double Circuit Transmission Line

Messrs. Aster Infrastructures

USD9,495,089.71 Plus N1,587,493,882.99

v Lot 2011-5 Ugwuaji-Nnenwe 132kv Double Circuit Transmission Line

Messrs. Ashtavinayaka Energy Infra Pvt Ltd/Bran Engineering Ltd

USD3,732,770.65 Plus N511,793,146.63

vi Lot 2011-6 132kv Double Circuit Transmission Line Nnewi MBO

Messrs. Dorman Long Engineering/Genesis/Power Projects Ltd Nnenwe-Mpu

USD2,858,534.87 Plus N643,790,391.31

vii Lot 2011 – 7 Engineering, design, manufacture, Supply, Construction and Commissioning of the 50km Omuaran -Egbe 330kv Double Circuit Transmission Line

Messrs. Aravali Infra Power Limited/Alicon Ventures Nig. Ltd

USD3,088,924.41 Plus N621,321,904.69

viii Lot 2011 – 8 Engineering, design, manufacture, Procurement, Supply, Construction and Commissioning of the 90km Obajana-Okeagbe 330kv Double Circuit Transmission Line

Messrs. Everest Infra Energy Ltd/Dyehnum ventures Ltd

Ministry of Power/Transmission Company of Nigeria (TCN)

USD7,743,804.84 Plus N803,692,934.38

07/12/11 24 Months

ix Lot 2011 – 9 Engineering, design, manufacture, Supply, Construction and

Messrs. Skipper Electricals/Summit Energy

USD25,545,146.96 Plus N3,471,734,877.83

Page 29: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

29

Commissioning of the 180km Yola-Song-Little Gombi-Mubi-Gulak 330kv Double Circuit Transmission Line

x Lot 2011 – 10 Design, manufacture, Supply,and Commissioning of 2x330kv Lines Bay Extension in each of Kaduna (Mando) and Kano( Kumbotso) 330/132kv substation

Messrs. Exernegia Power Africa Bigen

USD4,212,379.53 Plus N500,823,961.92

xi Lot 2011-11 2x330kv Line bays extension in each of Delta (Ughelli) and portharcourt 330/132kv substation

Messrs. MBH Power Ltd

USD4,401,074.24 Plus N551,133,551.17

xii Lot 2011 – 13 Design, manufacture, Supply, Construction and Commissioning of 2x60MVA, 330/132kv substation at Kachia

Messrs. Esterbag Engineering Limited

Ministry of Power/Transmission Company of Nigeria (TCN)

USD6,031,516.62 Plus N437,340,330.79

07/12/11 24 Months

xiii Lot 2011 – 16 Design, manufacture, Supply, Commissioning of 2x60 MVA, 132/33kv substation at Okeagbe and 2x132kv line bays extension at Obajana

Messrs. Power Contral & Appliances

USD5,612,652.66 Plus N687,987,881.45

xiv Lot 2011 – 17 Design, manufacture, Supply, and Commissioning of 2x60MVA, 132/33kv substation at Song and

Messrs. Qingdao Wuxio Grwa Company ltd/Ahmin Technology and Power System

USD6,506,881.47 Plus N676,045,227.30

Page 30: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

30

2x132kv Lines Bay Extension at Yola

xv Lot 2011 – 18 Design, manufacture, Supply, and Commissioning of 2x60MVA, 132/33kv substation at Little Gombi

Messrs. Shandong Taikai

USD4,852,409.00 Plus N711,474,893.72

xvi Lot 2011 – 19 Design, manufacture, Supply, and Commissioning of 2x60MVA, 132/33kv substation at Mubi

Messrs. Hyundi/Richfield

USD5,534,586.81 Plus N574,978,088.57

xvii Lot 2011-20 2X60MVA, 132/33kv substation at Gulak

Concepts Engineering Pvt India/Chanref (Nig) Ltd

USD5,333,749.93 Plus N1,044,144,867.47

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

6 Revision of the Contract Sum for the Rehabilitation of Makeri-Pankshin 132kv single circuit transmission line project

Messrs. Mogabs

(Nigeria) Ltd

Ministry of Power Revised Contract Sum

USD2,390,900.00

payable at the prevailing exchange rate at the time of payment

Plus

14/03/2012 10 Months

Page 31: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

31

N235,785,213.25

7 Award of Contract for the design, manufacture and supply of 10No. Mobile Transformer Oil filtration Machines

Messrs. Globe

Core Ltd.

Ministry of Power €673,781.49

payable at the prevailing exchange rate at the time of payment

Plus

N17,905,155.68 inclusive of port clearance and delivery to Transmission Company of Nigeria Plc stores at Ojo, Lagos

14/03/2012 6 Months

8

AWARD OF CONTRACTS FOR THE CONSTRUCTION OF 5NOs. SUB-STATIONS FOR THE TRANSMISSION COMPANY OF NIGERIA (TCN) PLC

S/N

PROJECT SCOPE COMPANY CONTRACT SUM

IMPLEMENTING

AGENCY

DATE

COMPLETION PERIOD

Page 32: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

32

1 Lot 2011-12 Engineering, Manufacture, Supply, Construction and Commissioning of 2x60MVA, 132/33KV Substation at Kwoi and 2x132KV line Bays extension at Keffi

Messrs. Liaoning

Efacec Electrical

Equipment Co. USD5,739,384.54 Plus N694,464,562.83

Ministry of

Power/

Transmission

Company of

Nigeria (TCN)

14/03/2012

24 Months

2 Lot 2011-14 Engineering, Manufacture, Supply, Construction and Commissioning of 2x60MVA, 132/33KV Substation at Nnenwe and 2x132KV line Bays extension at Ugwuaji

Messrs. Metro

Elektrik USD5,955,066.60 Plus N825,826,590.01

3 Lot 2011-125 Engineering, Manufacture, Procurement, Supply, Construction and Commissioning of 2x60MVA, 132/33KV Substation at Egbe and 2x132KV line Bays extension at Omuaran

Messrs. TBEA-

Henyang USD5,634,240.14 Plus N740,273,654.32

4 Lot 2011-33 Engineering, Manufacture, Procurement, Supply, Construction and Commissioning of 2x60MVA, 132/33KV Substation at Ose LGA Headquarters and 2x132KV line Bays extension at Okeagbe

Messrs. Junot

Engineering

Services Ltd

€5,148,815.00 Plus N779,567,357.90

Ministry of

Power/

Transmission

Company of

Nigeria (TCN)

14/03/2012

24 Months 5 Lot 2011-34

Engineering, Manufacture, Procurement, Supply, Construction and Commissioning of 2x60MVA, 132/33KV Substation at Gagarawa, Jigawa State

Messrs. Power

Control &

Appliances Ltd

USD4,071,959.14 Plus N635,653,940.81

Page 33: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

33

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

9 Award of Contract for the completion and commissioning of the Umuahia-Ohafia, Umuahia-Mbalano and Ohafia-Arochukwu 132kv Single Circuit Transmission Lines for the Transmission Company of Nigeria Plc (TCN)

Messrs. KEC International Limited

Ministry of Power/TCN

USD7,564,756.88 Payable at prevailing exchange rate Plus N1,007,539,148.49 inclusive of a provisional sum of N379,143,721.26 for 5% VAT, 10% Contingency sum and 2.5% for Right of Way Compensation

28/03/12 18 Months

TOTAL USD250,741,666.31 €8,714,991.49 N31,565,674,477.78

MINISTRY OF TRADE AND INVESTMENT

APPROVAL OF THE SUM OF N15,000,000,000.00 (FIFTEEN BILLION NAIRA) TO THE FGN-ASSISTED PUBLIC MASS TRANSIT REVOLVING FUND (PMTF) SHEME FOR ONWARD LENDING TO ELIGIBLE AND CREDIBLE TRANSPORT OPERATORS ACROSS THE COUNTRY UNDER PHASE II OF

THE FEDERAL GOVERNMENT OF NIGERIA ASSISTED PUBLIC MASS TRANSIT REVOLVING FUND (PMTF)

S/N

Transport Operator

Mass Transit Capacity Qty Unit Price (Initial N)

Unit Price (BPP Recommended N)

Total Cost (N)

Page 34: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

34

1

Elizade Motors

Toyota Coaster (Petrol) 30 80 12,500,000.00 11,875,000.00 950,000,000.00

Toyota Coaster (Diesel) 30 20 13,600,000.00 12,920,000.00 258,400,000.00

Sub-total

1,208,400,000.00

2

Innoson Vehicle Manufacturing Co. Ltd

Innoson IVM660A 26 100 6,900,000.00 6,555,000.00 655,500,000.00

Innoson IVM6800 35 50 8,800,000.00 8,360,000.00 418,000,000.00

Innoson IVM660A 98 (48 standing)

- 19,000,000.00 18,050,000.00

Sub-total

1,073,500,000.00

3 Viramsum Motors

Tata 59 200 13,000,000.00 12,350,000.00 2,470,000,000.00

Sub-total

2,470,000,000.00

4 VON Auto Nig. Ltd.

Asok Leyland 42 240 13,000,000.00 12,350,000.00 2,964,000,000.00

Sub-total

2,964,000,000.00

Page 35: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

35

5 Barbedos Motors Ltd

Mercedes 50 50 40,000,000.00 38,000,000.00 1,900,000,000.00

Sub-total

1,900,000,000.00

6 Yutong Hong

Kong Ltd

Yutong (City Bus) 40 100 13,017,600.00 12,366,720.00 1,236,672,000.00

Yutong (Coach) 59 50 19,161,600.00 18,203,520.00 910,176,000.00

Sub-total

2,146,848,000.00

7

Globe Motors Ltd

Hyundai Super C 38 (8 standing)

300 8,957,550.00 8,509,672.50 2,552,901,750.00

Hyundai Super Aero 64 (14 standing)

5 17,824,375.00 16,933,156.25 84,665,781.25

Hyundai Luxury 71 (21 standing)

5 26,398,125.00 25,078,218.75 125,391,093.75

Sub-total

2,762,958,625.00

8

Anambra Motor Manufacturing Co. Ltd

Anamco (Marcopolo) 52 5 31,275,000.00 29,711,250.00 148,556,250.00

Anamco (Mascarello) 27 5 11,902,500.00 11,307,375.00 56,536,875.00

Page 36: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

36

Sub-total

205,093,125.00

9 Leyland Nig. Ltd

Leyland Busan (City Bus)

38 (21 standing)

10 9,916,830.00 9,420,988.50 94,209,885.00

Leyland Busan Coastliner

30 20 7,770,000.00 7,381,500.00 147,630,000.00

Sub-total

241,839,885.00

GRAND TOTAL 1,240

14,972,639,635.00

FEDERAL MINISTRY OF TRANSPORT

S/N ITEM/SERVICE NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the Fast Tracking of the Development of the Phase 4 Port Facilities, at Onne Port Complex, for NPA / Ministry of Transport (MT)

Messrs. Intels (Nig.) Ltd.

Ministry of Transport

USD370,481,720.42

26/10/11

40 Months

2 Award of Contracts for the construction of Yenagoa Jetty and Terminal Facilities at

Messrs. Combined Building Services Limited

National Inland Waterways Authority/Ministry of Transport.

N1,311,636,134.50

26/10/11

Page 37: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

37

Yenagoa, Bayelsa State for National Inland Waterways Authority/Ministry of Transport.

14 Months

3.0 REQUEST FOR THE REVISION OF THE ESTIMATED TOTAL COST (RETC) FOR THE DREDGING OF LOWER RIVER NIGER FROM WARRI IN DELTA STATE TO BARO IN NIGER STATE (LOTS 1-5)

3.1 Warri to Bifurcation of Forcados and River Nun = 154km

Messrs Fung Tai (Nig.) Ltd.

Ministry of Transport/NIWA

N6,069,422,355.00

2/11/11

2 Years

3.2 Warri to Bifurcation of Forcados and River Nun to Onitsha =116km

Messrs Dredging Int. Ltd.

N5,363,766,897.55

3.3 Onitsha to Idah = 118km

Messrs Van Oord (Nig.) Ltd.

N10,399,867,317.00

3.4 Idah to Jamata = 108km

Messrs Van Oord (Nig.) Ltd.

N13,806,242,793.00

3.5 Jamata to Baro = 76km

Messrs William Llyods Tech. Co. Ltd.

N7,695,412,970.00

TOTAL 572KM

N43,334,712,332.55

4 Re-Development of the Port Facilities at Bullnose, Lagos Port Complex, Apapa

Messrs Eko Support Services Limited

Ministry of Transport/NPA

USD124,400,000.00

Lease Period of 20 years

Page 38: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

38

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

5 Award of Contract for the Re-Construction of Apapa Dual Carriageway within Apapa Quays, Lagos

Messrs. Sanju Sunny (Nigeria) Limited

Nigerian Ports Authority /Ministry of Transport

N2,113,656,976.26

09/11/11 12 Months

6 Augmentation of the Contract for the Rehabilitation of TinCan Island Port (Quay Wall and Quay Apron)

Messrs. Johnak

Engineering

Limited

Nigerian Ports Authority(NPA)/ Ministry of Transport

N3,642,611,404.44

inclusive of all taxes

16/11/11 12 Months

7 Award of Contract for the Design, Supply, Installation and Commissioning of New Signalling and Communication Solutions for the Eastern Line including 2 Branch Lines for the Ministry of Transport and Nigeria Railway Corporation (NRC)

Messrs. A3 &

O/ANSALDO

Limited

Ministry of Transport/NRC

N5,616,459,436.22

30/11/11 14 Months

8 Award of Contract for the Supply of Fire and Salvage Equipment for the Ministry of Transport/NPA

Messrs. Jagsul

(Nigeria) Limited Ministry of Transport/ NPA

N136,500,000.00

30/11/11 4 weeks

9

Augmentation of the contract sum for the Rehabilitation of Lagos Harbour Moles

Messrs. China Civil

Engineering and

Construction

Corporation

(CCECC) Ltd

Ministry of Transport/Nigeria Ports Authority

Revised Estimated

Total Cost

N20,035,710,566.72 07/12/11 21 Months

Page 39: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

39

10 Award of contract for the Re-Construction of 1.6km Dual Carraigeway within Apapa Quays, Lagos

Messrs. P.W.

(Nigeria) Limited Ministry of Transport

N3,000,819,175.42

21/12/11 18 Months

11 Award of Contract for the Procurement of 2No. Fast Moving Passenger Ferries (Catamaran) by the National Inland Waterways (NIWA)

Messrs. Karflex

Fisheries Limited Ministry of Transport/ NIWA

N168,455,700.00

inclusive of all

taxes 25/01/12 6 Months

12

Award of Contract for the Strategic Concessioning Partnership with NIMASA to provide Platforms for tracking Ships and Cargoes, enforcement of Regulatory Compliance and Surveillance of the entire Nigerian Maritime Domain

Messrs. Global

West Vessel

Specialist Nigeria

Limited (GWVSL) Federal Ministry of Transport/Nigerian Maritime Administration and Safety Agency (NIMASA)

Initial Investment of

the sum of

USD103,400,000.

00 inclusive of all

taxes on a

Contractor-

financed Supply,

Operate and

Transfer

Concession

01/02/12

10 years and renewable for further two terms of 5 years and no more

13 Augmentation of the Contract for the Rehabilitation of Onitsha Port Complex and Installation of Cargo Handling Equipment for Ministry of Transport/National Inland Waterways Authority (NIWA)

Messrs. InterBau Construction Limited

Ministry of

Transport/National

Inland Waterways

Authority (NIWA)

N483,512,696.26

15/02/12 Extended Completion period of 3 Months

14 Award of Contract for the Rehabilitation of Julius Berger Terminal ‘C’ at Old Port, Warri, Delta State for the Ministry of Transport and Nigerian Ports Authority

Messrs. Julius Berger Nigeria Plc

Ministry of

Transport/Nigeria

Ports Authority

N9,406,510,158.05 29/02/2012 25 Months

Page 40: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

40

15 Award of Contract for the provision of Consultancy Services for the Study and Design of Yola-Makurdi Navigational Route Lot 2

Messrs. Enviplan International Limited

Ministry of

Transport/ National

Inland Waterways

Authority

N221,036,330.00 inclusive of all taxes

14/03/2012 20 Months

16 Award of Contract for the Rehabilitation of AMS Terminal ‘B’ at Old Port, Warri, Delta State

Messrs. China Harbour Engineering Company Limited

Ministry of

Transport/ Nigerian

Ports Authority

N7,022,310,942.78 inclusive of all taxes

14/03/2012 9 Months

TOTAL USD598,281,720.42 N96,493,931,853.20

FEDERAL MINISTRY OF WATER RESOURCES

S/N PROJECT DESCRIPTION

NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the rehabilitation and expansion of Ogbia Central Water Supply Scheme

Messrs. NAIRDA Limited

Ministry of Water Resources

N4,522,864,505.00 17/08/11 18 Months

2 Augmentation of Contract Sum for the Construction of Agaie/Lapai Earth Dam in Niger State.

Messrs. Infiouest International Ltd.

Ministry of Water Resources /UNRBDA

Revised Contract Sum From N1,536,802,608.00 To N2,055,444,192.75

14/09/11

3 Months

3 Award of contract for the completion of Nkari Dam Project in Akwa Ibom State

Messrs. A.G Vision Ministry of Water Resources

N2,911,284,239.73 07/12/11 24 Months

Page 41: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

41

4 Augmentation of contract for the construction of Ogbese Multi-purpose Dam Project in Ekiti State

Messrs. Foundation Solid (Nigeria) Limited

Ministry of Water Resources

N7,802,436,568.66 07/12/11 36 Months

5 Award of contract for the repairs to the Goronyo Dam emergency spillway

Messrs. Gilmor Engineering (Nig) Limited

Ministry of Water Resources

N3,882,146,985.99 07/12/11 8 Months

6 Award of contract for the Construction of Ogwashi-Uku Multipurpose Earth Dam Phase II

Messrs. Nelson Benjamin Limited

Ministry of Water Resources

N3,615,323,794.01 07/12/11 24 Months

TOTAL N24,789,500,286.14

FEDERAL MINISTRY OF WORKS

S/N PROJECT DESCRIPTION

NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the Reinstatement of washout and completion of the rehabilitation of Sokoto Illela road including repairs of Usman Danfodiyo University Road in Sokoto State

Messrs. Mothercat Limited

Ministry of Works N2,256,354,874.62 17/08/11 24 Months

Page 42: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

42

2 AWARD OF SEVEN (7) CONTRACTS FOR THE CONSTRUCTION AND REHABILITATION OF ROADS SPREAD IN FOUR (4) GEO-

POLITICAL ZONES OF THE COUNTRY( SOUTH WEST, SOUTH EAST, SOUTH SOUTH & NORTH EAST)

S/N

PROJECT DESCRIPTION NAME OF

FIRM/CONTRACTOR IMPLEMENTING

AGENCY COST DATE DURATION

i Rehabilitation of Ijebu Igbo-Olomi (Oyo State Border) Road in Ogun State

Messrs. A.A Duhu & Sons Limited

Ministry of Works

N1,381,556,046.26 17/08/11

13 Months

ii Rehabilitation of Ondo-Ore Road in Ondo State

Messrs. Chrisbrown International Limited

Ministry of Works

N1,799,786,661.75 9 Months

Iii Rehabilitation of Odo-Oba-Takie-Gambari-Otte Oyo State Border Along Ibadan-Oyo-Ogbomosho-Ilorin Road 45.3km (Route 20) in Oyo State

Messrs. Coduc (Nigeria) Limited

Ministry of Works

N2,136,669,265.50 17/08/11

9 Months

Iv Reconstruction/Rehabilitation of Gbongan-Owo-Oyo road in Oyo State

Messrs. Kopek Construction Limited

Ministry of Works

N6,917,558,164.42 18 Months

V Rehabilitation of Spur from Onitsha-Owerri Road To Okija-Ihembosi-Afor Ukpor-Ebenator-Ezinifite in Nnewi South LGA in Anambra State

Messrs. Fodiac Engineering Co. Ltd

Ministry of Works

N1,786,546,349.60 9 Months

Page 43: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

43

Vi Construction of 15 km Inter-State Road from Aivegunle, Okoko Edo LGA in Edo State

Messrs. Fame Highway Company Limited

Ministry of Works

N1,428,007,350.00 12 Months

Vii Construction of Jalingo-Kuna-Lau Road in Taraba State Section II

Messrs. Amitech Interglobal Engineering Limited

Ministry of Works

N1,430,875,575.94 16 Months

3 AUGMENTATION OF CONTRACTS FOR THE DUALISATION OF ABUJA-ABAJI-LOKOJA ROAD SECTIONS I&II IN THE

FEDERAL CAPITAL TERRITORY

S/N

PROJECT DESCRIPTION NAME OF

FIRM/CONTRACTOR IMPLEMENTING

AGENCY COST DATE DURATION

i Augmentation of Contract No. 5862 for the Dualisation Abuja-Abaji Section I (International Airport Link Road Junction to Sheda Village Junction)

Messrs. Dantata and Sawoe Construction Company (Nigeria) Limited

Ministry of Works

Reviewed Contract Sum N28, 666, 721,831.64

28/09/11

24 to 30 Months

ii Augmentation of Contract No. 5863 for the Dualisation Abuja-Abaji Section II (Sheda Village Junction to Abaji)

Messrs. RCC (Nigeria) Limited

Reviewed Contract Sum N31, 236, 905,170.83

Page 44: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

44

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

4 Award of contract for the for the Construction of the Oju/Loko-Oweto Bridge (Phase 1) to link Oju/Loko to Oweto in Nassarawa/Benue States along Traffic Route F238

Messrs. Reynolds Construction Company Ltd.

Ministry of Works N36,118,910,405.94 19/10/11 48 Months

5 Award of Contracts for Repairs of Third Mainland Bridge, Phase II Additional Works involving the Repairs of 8No. Expansion Joints to Eliminate noticed Super-Structure Sources of Stresses on the already Compromised Foundation Structures of the Bridge in Lagos

Messrs. Borini Prono Construction Co. Ltd.,

Ministry of Works N1,055,447,608.16 23/11/11 9 Months

6 COMPLETION OF CONTRACT NOS. 5884 AND 5885 FOR THE DUALISATION OF ABUJA-ABAJI-LOKOJA ROAD SECTION III (ABAJI – KOTON KARFE) AND SECTION IV (KOTON KARFE – LOKOJA) – REVISION AND AUGMENTATION FOR REVISED SCOPE OF WORKS, ADDITIONAL WORKS

AND VARIATION

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

6a Completion of Contract No. 5884 for the Dualization of Abuja-Abaji-Lokoja Road Section III (Abaji – Koton Karfe)

Messrs. Bulletine Construction Company Limited

Ministry of Works N25,827,333,686.52

23/11/11 24 Months

6b Completion of Contract No. 5885 for the Dualisation of Abuja – Abaji – Lokoja Road Section IV (Koton Karfe –

Messrs. Gitto Construzioni Generalli Nigeria Limited

N31,087,756,036.84 23/11/11

Page 45: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

45

Lokoja)

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

7 Award of contract for additional works to address the gully erosion at Chainages 9+700 and 11+400 be executed on the contract for the Rehabilitation of Onitsha – Enugu Dual Carriageway Section II; Anambra State Border – Enugu Road

Messrs. CCC (Nigeria) Limited

Ministry of Works N710,135,133.75 07/12/11 24 Months

8 Augmentation of contract for the Rehabilitation of Obiozora-Uburu-Mpu-Ishiagu-Portharcourt Expressway Road

Messrs. Setraco (Nigeria)Limited

Ministry of Works N8,367,343,094.25 07/12/11 12 Months

TOTAL N122,304,280,253.55

Page 46: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

46

PRESIDENCY

S/N PROJECT DESCRIPTION

NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of contract for the extension of the services of the National Management Consultants (NMC) for the management of the warehouses in the 6 Geo-political zones

Messrs. ETAT Consulting Limited

Presidency N115,857,000.00 30/11/11 9 Months (from 1st April, 2011

TOTAL N115,857,000.00

OFFICE OF THE SECRETARY TO THE GOVERNMENT OF THE FEDERATION (OSGF)

S/N PROJECT DESCRIPTION

NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the reclamation works at the site of the Federal University of Technology, Otuoke, Bayelsa State

Messrs. Azikel Dredging and Construction

Presidency/OSGF N4,997,862843.75 07/09/11 7 Months

TOTAL N4,997,862843.75

Page 47: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

47

POLICE SERVICE COMMISSION

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of contract for the construction OF Police Service Commission Corporate Head Office Building, Abuja

Messrs. Vita Construction Nigeria Ltd

Presidency/Police Service Commission

N3,486,867,519.53 07/12/11 15 Months

TOTAL N3,486,867,519.53

NIGERIA EXTRACTIVE INDUSTRY TRANSPARENCY INITIATIVE (NEITI)

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1a Award of Contract for the conduct of Oil and Gas Industry Audit (2009 to 2011)

Messrs Sada Idris & Co.

Presidency/NEITI

N226,613,000.00 18/01/12

9 Months

1b Award of contract for the conduct of Solid Minerals Industry Audit (2009 t0 2010)

Messrs Haruna Yahaya & Co.

N137,000,000.00

TOTAL N363,613,000.00

Page 48: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

48

INDEPENDENT NATIONAL ELECTORAL COMMISSION(INEC)

S/N ITEM/SERVICE

NAME OF COMPANY

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the printing of forty (40) Million Permanent Voters Cards

Messrs ACT Technologies Limited

Independent National Electoral Commission (INEC)

N2,600,000,000.00 at the rate of N65.00 per Card

11/04/12 7 Months

TOTAL N2,600,000,000.00

NATIONAL EMERGENCY MANAGEMENT COMMISSION (NEMA)

S/N PROJECT DESCRIPTION

NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the procurement of 23No. Mobile Intensive Care Ambulances for the National Emergency Management Agency (NEMA)

Messrs. Longevity Services Limited

Presidency/NEMA N667,000,000.00 at N29,000,000.00 each unit

17/08/11 5 Months

2 Award of Contract for the Procurement of 1No. Bell 429 DPIFR EMS Configuration with Special Equipment and Bell Standard Installed Kits, Avionics, Specialized

Messrs. Sea jewel Energy Limited

Presidency/NEMA USD9,594,603.17 Plus N508,394,035.50

30/11/11 8 Months

Page 49: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

49

Equipment, Accessories and Spare Parts and Emergency Medical Service Configuration

TOTAL USD9,594,603.17 N1,175,394,035.50

MILLENNIUM DEVELOPMENT GOALS (MDGs)

S/N PROJECT DESCRIPTION

NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST DATE DURATION

1 Award of Contract for the completion of Otuoke Hospital in Bayelsa State

Messrs. Avandale Services Limited

Presidency/MDGs N2,835,746,571.75 17/08/11 12 Months

2 AWARD OF CONTRACTS FOR THE SUPPLY OF PROJECT VEHICLES FOR TECHNICAL ASSISTANTS FOR THE 113 LOCAL GOVERNMENTS MDGs CONDITIONAL GRANTS SCHEME SCALE-UP

S/N PROJECT

DESCRIPTION NAME OF

FIRM/CONTRACTOR IMPLEMENTING

AGENCY COST

ZONE/REGION

QTY DATE DURATION

Page 50: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

50

S/N PROJECT DESCRIPTION NAME OF FIRM/CONTRACTOR

IMPLEMENTING AGENCY

COST DATE DURATION

3 Award of Contract for the Extension of the Services of the National Management Consultants

Messrs. ETAT Consulting Limited

Presidency/ OSSAP-MDGs

N248,004,847.24 30/11/11 9 Months (from 1st April, 2011)

1 Toyota Hilum (Tropicalised), 2.7 Eng. Capacity, Shell Spec

Messrs Elizade (Nig) Ltd

Presidency/MDGs

N128,417,625.00 North Central 23 17/08/11

2 Weeks

2 Toyota Hilum (Tropicalised), 2.7 Eng. Capacity, Shell Spec

Messrs. Elizade (Nig) Ltd

N128,340,000.00 North West 23

3 Toyota Hilum (Tropicalised), 2.7 Eng. Capacity, Shell Spec

Messrs. Ivory-Link International (Nig) ltd

N118,800,000.00 South West 20

4 Toyota Hilum (Tropicalised), 2.7 Eng. Capacity, Shell Spec

Messrs. R.T Briscoe (Nig) Ltd

N106,115,000.00 South South 19

5 Toyota Hilum (Tropicalised), 2.7 Eng. Capacity, Shell Spec

Messrs. Development Management System System Ltd

Presidency/MDGs

N106,305,000.00

North East

19

17/08/11

2 Weeks

Grand Total N580,977,625.00

104

Page 51: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

51

(NMC) for the Completion of Quickwins 2008/2009 Projects

TOTAL N3,664,729,043.99

NIGER DELTA DEVELOPMENT COMMISSION (NDDC)

1 Award of Contracts for Forty-Five (45) Infrastructural Development Projects in Nine (9) States of the Niger Delta Region (NDDC)

S/N PROJECT DESCRIPTION SCOPE

STATE/ LOCATION

NAME OF CONTRACTOR

BPP REVIEWED PROJECT COST

COMPLETION PERIOD

1 Construction of Ihie Ukwu Road Network

15.37km Road, asphaltic concrete surface, culverts and lined drains

Abia State Oneplus Holding Nig. Ltd

N1,967,699,553.75 72 Dry weeks

2 Construction of Ikot Ekwere Ndukpoise Road

28.5km asphaltic concrete carriageway, 40m long bridge of 2x20m spans, 11.0m wide, ring culverts RC offshoot drains

Nsit Ubuim LGA, Akwa Ibom State

Ewobros & Company Nig. Ltd

N3,128,468,773.50 120 Dry weeks

3

Construction of Mkpot Okoroba Ekang Road

28km + 85 Bridge, ring and box culverts, RC offshoot drains, asphaltic concrete way, span deck on pile and 85m bridge works

Cross Rivers State

John Davis Construction Ltd.

N7,679,353,819.73 104 Dry weeks

4 Construction of Bulo Ndoro Shore Protection works

9.47km shore protection works, dredging of sharp sand to fill the entire area, fixing of geotextile

Delta State Cawa Marine & Oil Services Ltd

N6,178,174,054.53 72 Dry weeks

Page 52: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

52

materials

5 Construction of Oloa Ossissa AtuOkpai-Osume-Alala Uno Road and Bridge

15km of asphaltic concrete carriageway concrete carriageway, 120m bridge, ring and box culvert, 3,500m of rectangular concrete line drain

Delta State Inter-Bau Construction Nig. Ltd

N3,997,940,111.46 130 Dry weeks

6 Construction of Oboro Shore Protection Works

RENO matters revetment, concrete landing apron, installation of concrete sheet piles

Delta State Osmoserve Global Ltd

N2,816,589,905.05 116 Dry weeks

7 Construction of St Saviour and other adjoining streets

13.3km earth work, 13.3km asphaltic concrete carriageway, ring and box culverts RC drains, stone base filling

Edo State Deastern Elec. & Mech Eng Services

N3,174,362,343.60 86 Dry weeks

8 Construction of Assa Ubrielem Okwu Abasiri River Umuoka Umuokabia Road

9.5km + 200m bridge Ring and boxculverts, RC offshoot drains, Asphaltic concrete carriageway, span deck on pile and bridge works

Imo State FEW Western Energy Ltd

N4,149,264,426.44 72 Dry weeks

9

Construction of Shore Protection and sandfilling of Ataba to Aba-Ijong

Supply and placement of rock-filled PVC coated Renomattress, placement of geotextile filter fabric, concrete beam with reinforcement and shuttering, corrosion treatment of U channel and other metal accessories

Rivers State Atafranc Nig. Ltd.

N9,996,134,955.95 104 Dry weeks

10 Construction of Asukoyet Ikuku Asukama Road and Bridge

Site clearing and earth works, ring and box culverts, RC offshoot drains, asphaltic concrete concrete carriageway,

Andoni LGA, Rivers State

Zcubes Nig Ltd N3,606,805,509.55 72 weeks

Page 53: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

53

span deck on pile, bridge work

11

Construction of Borokiri Okirika Road and Bridge

Site clearing and earth works, ring and box culverts, RC offshoot drains, asphaltic concrete concrete carriageway, span deck on pile, bridge work

Rivers Zerock Construction Ltd

N16,787,393,981.88 130 Dry weeks

12

Sandfilling and shore Protection of Iko town

3 HA Sandfilling + 1.651km shore line, tree planting construction of Perimeter containment bund wall, Dewatering, pumping sumps and temporary drain, pre dredge and post dredge

Eastern Obolo LGA, Akwa Ibom State

Hydrodram Nig. Ltd

N2,220,469,674.08 78 Dry weeks

13

Construction of Burutu Reclamation Works

Dredging including construction of 9, 013m bund wall/berm, reclamation works including sand filling to a height of 10.416m

Delta State Hingla Integrated Concept Ltd

N6,554,429,788.98 104 Dry weeks

14 Construction of Obianuku Ogume Road with bridge

25km of asphaltic concrete carriageway, 3No bridges of various spans, drain and culverts

Delta State Mphasis Fulcrum Ltd

N5,248,122,738.08 134 Dry weeks

15 Construction of Ojobo Shore protection works

Includes Sheet pilling works, 4,400m

Delta State Interfaze Global Services Ltd

N5,499,079,996.58

16 Construction of inter town connection connecting itc line linking thirteen villages

Clearing of 61.3km HT line, HT overhead materials, transformer substation materials, connection of 132kv Transformers

Edo Fiphs Invest Ltd N2,981,407,434.32 160 Dry weeks

17 Construction of Obukofia ring road Egbema

27.49km of asphaltic concrete carriageway, single cell culverts: 90mm 2Nos, 1200mm 3Nos,

Ohaji/Egbema LGA, Imo State

O.K Isokariri 7 Sons Nig Ltd

N2,667,805,051.38 72 Dry weeks

Page 54: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

54

reinforced concrete side drain-5200 meters, reinforced concrete side drain -5200 meters, reinforced concrete external 3x2x1.5m trapezoidal drains- 1000meters, 2000m precast concrete kerbs along the edges of the road

18 Construction of Ikot Isong-Ekpene Obom-Ndon Eyo-Nya Odiong Road

14.7km of asphaltic concrete carriageway, 175m bridges of various spans, ring and box culverts, 18,000 of RC side drains

Akwa Ibom State

ET-Dicks Nig Ltd

N3,377,567,117.76 156 Dry weeks

19

Otuan Erosin Control Project

Sand filling of embankment- 8733m3, Geotextile covering, PVC coated galvanized Renomattress, 1No Landing aporon

Bayelsa State Neoman International Ventures Ltd

N2,622,046,533.75 72 Dry weeks

20

Construction of Nigerian Army Jetty

Sheet pilling works, concrete jetty, slip way, asphaltic concrete way, buildings to serve as workshop/warehouse, cafeteria, base clinic, 2 nr Guest house, fire station, 2 admin blocks, 4 nr security watch towers, fule dump, helipad, parade ground, fencing water supply and fire fighting installation

Delta Simoka Marine Ltd

N4,731,900,048.33 104 Dry weeks

21 Construction of Erema Ring Road

18.919km of asphaltic Concrete carriageway, 5No. single cell culverts, 5 double cell boxes culverts, crush stone base

Rivers Ahiahu Cost & Co Ltd

N3,409,156,163.06 76 Dry weeks

Page 55: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

55

course 150mm thick and 37,838m lined drains

22 Emergency shore protection

Okrika LGA, Rivers State

Roudo Nig. Ltd N11,151,432,936.00

23 Construction of Udo Ofunama Road

46.5km Edo State Japul Mines & Product Ltd

N6,062,172,454.15 86 Dry weeks

24 Emergency shore protection & Land reclamation

Reclamation 1,124,600m2 Sandfilling 4,413m, Landing Aprons 8no

Itak Abasi, Okutitak & Akputuwa, Akwa Ibom State

Zement & Zement Nig. Ltd

N7,322,249,908.34 24 Months

25 Construction of 330/132/33kv Transmission Substation at Ikot Ekpene and Associated Transmission Lines

Installation of 330/132/33kv Transmission Substation at Ikot Ekpene and Associated 132kv & 33kv transmission lines and substations to different parts of Akwa Ibom State

Ikot Ekpene LGA, Akwa Ibom State

Income Electrix Ltd

N7,289,223,123.30 120 Dry weeks

26 Construction of Ogoloma Shore Protection

2.851km Okrika LGA, Rivers State

Edvic Ltd N4,808,822,700.00 88 Dry weeks

27

Construction of Adiabo- Eseku Road

13.41km asphaltic concrete single carriageway, 1.5m shoulders, 240m long bridge, 160m x 900m pipe culvert, 150mm thick grouted triangular drains

Cross River State

John Davids Construction Ltd

N4,366,411,760.00 72 Dry weeks

28 Construction of Adiabo-Okurikang-Uken Road Odukpani LGA in Cross Rivers State

3.79km Cross Rivers State

Zenith Construction Ltd

N535,112,567.00 26 weeks

Page 56: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

56

29 Construction of Ubafan Adakagbene Setreboubou Road and Bridges in Delta State

15.18km Delta State Wintima Company (Nig) Ltd

N8,976,265,831.01 185 weeks

30 Erosion control and sandfilling of Onuegbum in Bayelsa State

Erosion Control Bayelsa State Trenuer (Nig) Ltd

N2,679,452,580.00 98 weeks

31 Construction of Foreshore protection of Opobo Community in Opobo LGA of Rivers State

Supply and placement of rockfilled PVC coated Reno Mattress

Rivers State Valdon Logistics Ltd

N2,818,902,569.57 28 weeks

32 Phase 1 of the Emergency Shore protection and Reclamation works Ayama in Bayelsa State

Reclamation Bayelsa State Dredging International

N2,131,580,000.00 30 weeks

33 Phase 1 of the Emergency Shore protection and Reclamation works in Famgbe in Bayelsa State

Reclamation Bayelsa State Dredging International

N2,641,580,000.00 30 weeks

34 Construction of Agge Shore protection Ekeremor LGA in Bayelsa State

2.1km of Shoreline Bayelsa State Beks Kimse (Nig) Ltd

N3,565,500,049.13 80 weeks

35 Construction of Nsasak Junction Akon Road in Akwa Ibom State

30km Akwa Ibom State

Seyang Ltd N5,819,165,840.52 156 weeks

36

Construction of Ajagba -Kiribo Road in Ondo State

13.43km Ondo State Don Frat Jercess Limited

N1,304,259,671.93 52 weeks

Page 57: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

57

37 Rehabilitation of inter town connection (ITC) Line linking 13 villages and construction of 2x30MVA substation at Ugo in Orhiomwon LGA, Ondo State

2x30MVA 132/33kv Edo State Tehinnah Investment Ltd

N1,645,053,094.01 160 weeks

38 Construction of Umuojima Omuma Link road/drain

14.3km Ugwunagbo LGA, Abia State

M/s Decka Eng & Tech. Serv. Ltd.

N1,166,254,364.00 52 Dry weeks

39 Construction of Ugwali-Obokwe-Umuekechi-Uratta Road

9.93km

Ukwa West/Aba South LGA, Abia State

M/s Alliance Logistics Ltd

N1,239,249,986.00 72 Dry weeks

40 Construction of Ozoro Township Road

12.4 km Ikoko North LGA, Delta State

M/s S.O Olutu & Sons Nig. Ltd

N2,431,686,005.50 102 Dry weeks

41 Reclamation Awoye-Moleletin

2.93km – Reclamation 1,043, 288.48m2 Sandfilling

Ilaje LGA, Ondo State

M/s Dreging Atlantic Ltd

N8,193,235,703.73 104 Dry weeks

42 Construction of Okwuzi-Ugada Road/Bridge

9.5km ONELGA, Rivers State

M/s Jocari Invest Ltd

N3,914,142,601.90 78 Dry weeks

43 Construction of Rumuekpe-Ogbele-Abua Road

15.7km with Bridge Emohua and Abua LGA

M/s Jam Services Ltd

N3,805,221,590.19 120 Dry weeks

44 Emergency shore protection & Land reclamation

Reclamation 1,124,600m2 Sandfilling 4,413m, Landing Aprons 8no

Itak Abasi, Okotitak & Akputuwa, Akwa Ibom State

Zement & Zement Nig Ltd

N7,322,249,908.34 24 Months

Page 58: FEDERAL EXECUTIVE COUNCIL (FEC) APPROVED CONTRACTS … · 2020-04-29 · Master Flusher Type 160E 1 unit with High Pressure Jetting Installation and 1 unit without High Pressure Jetting

58

45 Construction of 330/132/33kv Transmission Substation at Ikot Ekpene and Associated Transmission Lin

Installation of 330/132/33kv Transmission Substation at Ikot Ekpene and Associated 132kv & 33kv transmission lines and substations to different parts of Akwa Ibom State

Ikot Ekpene LGA, Akwa Ibom State

Income Electrix Ltd

N7,289,223,123.30 120 Dry weeks

TOTAL 15%

N211,273,620,349.68 N31,691,043,052.45