Feasibility Report Ghandara Cement
Transcript of Feasibility Report Ghandara Cement
-
8/3/2019 Feasibility Report Ghandara Cement
1/8
FEASIBILITY REPORT
FEASIBILITY REPORT
OF CEMENT PROJECT
PORT LAND CEMENT
SUBMITTED TO:
MR. ZIA UR - REHMAN
SUBMITTED BY: SYED ABID HASSAN
REG#53124
S.ABID HASSAN Page 1 10/31/2011
-
8/3/2019 Feasibility Report Ghandara Cement
2/8
FEASIBILITY REPORT
PART# 1: COST OF THE PROJECT
(ALL FIG IN MILLION RUPEE
S.NO ITEMS AMOUNT LOCAL CURRENCY FOREIGN CURREN
1 LAND AND LAND DEVELOPMENT 500 500
2 BUILDINGS
FACTORY BUILDING 170 170
OFFICE BUILDING 120
FUEL TRUNCKROAD CONNECTION 90
TOTAL COST(CIVIL WORK) 380
3 PLANTS AND MACHINERY
MACHINERY 250 0
INSURANCE, TRANSPORTATION, LOCAL TAXES 27.5 20
INSTALLATION 57 27
TOTAL PLAN AND MACHINERY 334.5 57
4 VEHICLES 30 30
5 FURNITURE AND FIXTURE 2 2
6 ADMINISTRATIVE EXPENSES 2.4 2.4
26
7 CONTINGENCIES 26
8 INTEREST DURING CONSTRUCTION TO BE CALCULATED
9 WORKING CAPITAL 3.2 3.2
TOTAL PROJECTION 1,243.70
THE AMOUNT OF CONTINGENCIES HAS BEEN PROVIDED @2.5% OF COST
OF LAND & BUILDINGS, PLANTS & MACHINERY, VEHICLES AND
FURNITURE.
S.ABID HASSAN Page 2 10/31/2011
-
8/3/2019 Feasibility Report Ghandara Cement
3/8
FEASIBILITY REPORT
WORKING CAPITAL
PARTICULARS BASIS OF COMPUTATION AMOUNT
INVENTORY
PRODUCTION,MATERIAL, FUEL & AUXILLIARY 1% 1PARTS & SUPPLIES FOR REPAIR&MAINT ONE MONTH 0.5
FINISH GOODS ONE MONTH 0.98
ACCOUNTS RECEIVABLE 10 DAYS OF PRODUCTION 0.49
OTHER LIQUID ASSETS 0.21
TOTAL 3.18
MEANS OF FINANCING:
Debt-Equity will be 60:40 of total cost. The Foreign Currency loan will be obtained at
6%p.a. the local currency loan will be taken at 12%p.a. The project will be financedwith foreign exchange up to 30% of the amount of the debt is to be raised for the
project. The interest on local loan will be paid for 12 months and on foreign currency
loan for six months. The foreign loan amount has already been converted into local
currency on prevailing rate of foreign exchange.
SCHEDULE OF IMPLEMENTATION:
The project will be implemented over two and half year [i.e. 30 months]
ACTIVITY# ACTIVITY DURANTION SEQUENCE
1 LAND AND LAND DEVELOPMENT 04 MONTHS
2 CONSTRUCTION AND CIVIL WORK 12 MONTHS THIS ACTIVITY WILL START AFTER 1
3 PROCURE OF MACHINERY 8 MONTHS AFTER 3 MONTHS OF START OF
ACTIVITY 1
4ERECTION OF PLANT ANDMACHINERY 8 MONTHS THIS ACTIVITY WILL START AFTER
COMPLETION OF ACTIVITY 2
5 TEST, INSPECTION AND TRIAL RUN 3 MONTHS THIS ACTIVITY WILL START AFTER
ACTIVITY 4
Following information is also available:
Expenditure on land and building will mad 60%in 1st Quarter of year 1 and 40%
in the remaining period.
S.ABID HASSAN Page 3 10/31/2011
-
8/3/2019 Feasibility Report Ghandara Cement
4/8
FEASIBILITY REPORT
Expenditure on building will be made evenly over the period of construction.
The total expenditure on plant and machinery and erection will be made as: (a)
expenditure on procurement and receipt of machinery will be made as 40% inmonth 1, 40% in month 2 and 20% on receipt of machinery.(b) expenditure on
erection will be made evenly over the period of erection.
Expenditure of procurement of vehicle and furniture and fixture will be made as:
20% in 2nd Quarter of Year 1. 20% of 2nd Quarter of Year 2 remaining before the
commencement of commercial production.
Administrative expenses will be incurred evenly over the implementation period.
The amount of working capital will be provided on commencement of
commercial products.
PART-2: DISTRIBUTION OF
ADMINSTRATIVE COSTS, CONTENGENCIES
AND INTEREST DURING CONSTRUCTIONCEMENT PROJECT
Contengencies and administrative cost is to be distributed to all head except
the distributable heads of accounts.
Interest during construction on local currency loans will be distributed on
civil works and plant and machinery and interest on foreign currency will be
distributed on plant and machinery only.
S.ABID HASSAN Page 4 10/31/2011
-
8/3/2019 Feasibility Report Ghandara Cement
5/8
FEASIBILITY REPORT
PART-3: OPERATING RESULTS -
CEMENT PROJECT
Cement industry is minor-based industry. Its main Inputs are Limestone, Clay and
Gypsum. Basic input must be available in the vicinity of the project.
The methods of refining the raw mix before it charged to kiln used are:
(1)Dry Process.
(2)Wet Process.
The Wet Process is used to wet the raw material: (i.e. Calcium Carbonate and Plastic
clay. Wet process is expensive as compare to dry process.
1: OBJECTIVE:
The proposed project will have an installed capacity of 2000 tons per day. The project
will use dry process, which is a cost-saving project.
2. THE ACTUAL PRODUCTION PROGRAMME:
YEAR WORKING DAYS CEMENT PRODUCED
1 275 550,000.00
2 300 600,000.00
3 & THERE AFTER 330 660,000.00
3: SELLING ACTIVITIES:
The 30% of the production will be exported. The remaining production will be
consumed within the country. The cement will be made available in 50 Kg paper sacks /
bags.
The cement will be sold locally through the appointed dealers. At initial stage creation
of its own organization is not considered appropriate. Only 10 days inventory will be
maintained at the most as the holding of inventory for more than this time will reduce
its strength.
S.ABID HASSAN Page 5 10/31/2011
-
8/3/2019 Feasibility Report Ghandara Cement
6/8
FEASIBILITY REPORT
4: RAW MATERIAL / INPUT:
The raw mix used to produce will consist of 58% of Limestone and 48% of Clay. The
Gypsum is needed for the regulation of the setting time.
YEAR QUANTITY (TONS) PRICE(Ton)
LIMESTONE(58%) CLAY(41%) GYPSUM(1%)
1 319000 231000 Lime 160/Ton
2 348000 252000 Clay 50/ Ton
3 & Thereafter 382800 277200 Gyp 170/Ton
5: PACKAGING MATERIAL:
The cement will be packed in 50 Kg bag of Kraft Paper. It will cost Rs. 12 per Bag
(Quotation taken from Pakistan Paper Sec Hub Chowki)
YEARCEMENT PRODUCED
(TON) NO OF BAGS
1 550,000.00 11,000,000.00
2 600,000.00 12,000,000.00
3 & Thereafter 660,000.00 13,200,000.00
6: FUEL
Gas will be used and both electricity and gas is available in the area. Electricity will be
used in offices.
Total heating requirement at 100% capacity will be 13,200,000,000Kcal. (i.e.
Re.0.00015 approx Rs. 1.98M)
7: STORES AND SPARES:
It will be 0.5% in 1st year, 0.75% in 2nd Year and 1% of cost of machinery in 3rd and
subsequent years.
S.ABID HASSAN Page 6 10/31/2011
-
8/3/2019 Feasibility Report Ghandara Cement
7/8
FEASIBILITY REPORT
8: MAINTENANCE OF BUILDING:
It will be 0.5% in 1st year, 0.75% in 2nd Year and 1% of cost of machinery in 3rd and
subsequent years.
Insurance of the building will be covered from Habib Insurance @ 1% of the cost of
building and machinery.
9: MAN POWER , SALARIES AND WAGES:
SR.NO PERMANENT STAFF NO AMOUNT OF SALARIES
AND WAGES
1 ADMIN & GENERAL 35 6,300,000.00
2 ACCOUNTS 20 7,200,000.00
3 MARKETING 25 4,500,000.00
4PRODUCTION MANAGEMENT 25 10,500,000.00
5 PRODUCTION 225 27,000,000.00
6 AUXILIARY SERVICE 30 3,600,000.00
7 QUARY 200 24,000,000.00
8 TOTAL 560 83,100,000.00
NOTE:
Above amount include House Rent. 30 % of the strength will be provided with
accommodation.
A provision of 25% has to be provided for fringe benefits.
10: DEPRECIATION SCHEDULE:
S.ABID HASSAN Page 7 10/31/2011
-
8/3/2019 Feasibility Report Ghandara Cement
8/8
FEASIBILITY REPORT
SR. NO ITEMS DEP RATE
1 FACTORY BUILDING 5%
2 HOUSING COLONY 5%
3 PLANTS AND MACHINERY 10%
4 VEHICLES 20%
5 FURNITURE & FIXTURE 15%
S.ABID HASSAN Page 8 10/31/2011