FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/02_May_2016... · brief...
Transcript of FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/TOR/02_May_2016... · brief...
FEASIBILITY REPORT
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-1
CONTENTS
CHAPTER NO. PARTICULARS PAGE NO.
FEASIBILITY REPORT
I EXECUTIVE SUMMARY 3
II INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION
11
III PROJECT DESCRIPTION 15
IV SITE ANALYSIS 36
V PLANNING BRIEF 40
VI PROPOSED INFRASTRUCTURE 42
VII REHABILITATION & RESETTLEMENT (R&R) PLAN 44
VIII PROJECT SCHEDULE & COST ESTIMATES 47
IX ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS) 48
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-2
LIST OF FIGURES
FIGURE NO.
PARTICULARS PAGE NO.
1. LOCATION MAP 16
2. GEOLOGICAL MAP OF CUDDAPAH BASIN 19
3. GEOLOGICAL PLAN 24
4. SURFACE LAYOUT PLAN 26
5. CONCEPTUAL PLAN 30
6. INDEX PLAN 38
LIST OF ANNEXURES
ANNEXURE
NO. PARTICULARS PAGE NO.
1 LEASE AREA - GO COPY (G.O.MS.NO. 126) 49
2 MINING SCHEME FOR BARYTES OVER AN EXTENT OF
223.310 HA 54
3 ENVIRONMENTAL CLEARANCE FROM MOEF FOR
EXPANSION OF MANGAMPET BARYTES MINE 56
4
COMBINED CONSENT UNDER WATER ACT, AIR ACT AND
AUTHORIZATION UNDER HAZARDOUS WASTE RULES
OBTAINED FROM APPCB
64
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-3
CHAPTER – I
EXECUTIVE SUMMARY
1.0 INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION
M/s. Andhra Pradesh Mineral Development Corporation (APMDC) Limited, the State
Government entity is operating Mangampet Barytes Project since year 1978 in Mangampeta &
Govindampalli Villages, Obulavaripalli Mandal, YSR Kadapa District, Andhra Pradesh.
Initially there were 10 separate leases with APMDC in this area. Subsequently,
M/s. APMDC obtained Amalgamation of (10) mining leases into a single lease with the total
extent of 225.0139 Ha vide G.O.MS.No. 126 dated 19.12.2015 which is Co-terminus with the
expiry of first lease by 01.09.2018 (Annexure – 1) with further scope for renewal for 10 more
years.
Presently 3.0 MTPA capacity Barytes mine is operated in this lease area after obtaining
the following statutory clearances:
Scheme of Mining approved by Joint Director of Mines and Geology, Kadapa
Zone vide Lr.No 2276/MS-KDP/2013, dated 18.04.2015 for Barytes ore
production capacity of 3.0 MTPA. (Annexure – 2).
The Environmental Clearance obtained from MoEF for existing Barytes production
capacity of 3.0 MTPA including 0.1 MTPA Barytes Powder vide letter no. J-
11015/582/2007-IA.II (M), dated 30th December 2008 (Annexure – 3).
Combined consent under Water Act, Air Act and authorization under Hazardous
waste rules obtained from APPCB which is valid up to 31st December 2017
(Annexure – 4).
Considering the good demand for quality Barytes ore, now it is proposed to enhance the
Barytes ore production capacity from 3.0 MTPA to 5.0 MTPA and also increase the existing
pulverizing plant capacity to produce 0.30 MTPA Barytes powder from the existing level of
0.10 MTPA.
Mine movement and enhancement of production from this lease is planned along with
simultaneous working by surface chopping of adjacent new Dolomite lease area of 114.14 Ha of
APMDC up to 230m RL for which separate EC application is being made.
Since the waste material cannot be dumped in the lease area, additional land outside the
lease area is also acquired for these 2 projects.
Details of the lease area and outside lease area of the two adjacent projects of APMDC
is given below:
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-4
This project pertains to expansion of Barytes project for a total project area of
377.6326 Ha comprising 225.0139 Ha of lease area and 152.6187 Ha outside the lease
area.
MOEF&CC notification stipulates that, any change in production requires fresh
environmental clearance. Under the above circumstances APMDC has initiated action towards
obtaining environmental clearance for this expansion project.
Prior to obtaining environmental clearance, as per MOEF&CC notification of September
2006, Form I and Feasibility report have to be submitted along with proposed Terms of
reference (TOR) for the project for stipulating the TOR for the project by MOEF&CC, Govt. of
India.
This project falls under category A as per MoEF&CC notification in this respect, because
of mining lease being more than 50 Ha. Hence, Form – 1, proposed TOR and feasibility report
have to be submitted to MoEF&CC, New Delhi for their approval and prescribing TOR and
according EC after submission of EIA/EMP report to them.
This feasibility report for Mangampet Barytes Project of M/s. Andhra Pradesh
Mineral Development Corporation (APMDC) Limited is prepared in line with the guidelines
issued by MoEF&CC, vide their letter dated 30th September 2010 for the total project area
of 377.6326 Ha comprising 225.0139 Ha of lease area and 152.6187 Ha outside the lease
area mainly for dumping and its safety zone towards expansion of Barytes production
BARYTES LEASE AREA
BARYTES OUTSIDE
LEASE AREA
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-5
capacity from 3.0 MTPA to 5.0 MTPA and also to increase the existing pulverizing plant
capacity to produce 0.30 MTPA Barytes powder from the existing level of 0.10 MTPA for
obtaining TOR from MoEF&CC towards getting environmental clearance based on
modified scheme of mining submitted to authorities.
1.1 LOCATION DETAILS OF PROJECT:
Mangampeta Barytes Project of M/s. Andhra Pradesh Mineral Development Corporation
(APMDC) Limited is in Mangampeta & Govindampalli Villages, Obulavaripalli Mandal, YSR
Kadapa District, Andhra Pradesh. The barytes lease area is bounded by Latitude 14O 00’ 52.80”
to 14O 02’ 15.01” and Longitude 79O 17’ 55.48” to 79O 19’ 41.54” and falls in Survey in India
Topo Sheet No. 57 N/8.
The project area is approachable from State Highway (SH – 31) connecting Tirupathi and
Kadapa passing more than 400 m east of the lease area. The district Headquarters, Kadapa is
about 80 kms away from project and Tirupathi is about 69 km from the site. The nearest railway
station Koduru is about 9.0 km away from project. The nearest Airport is Tirupathi which is 69 km
away while the nearest port city Chennai is 190 km from the mine.
2.0 PROJECT DESCRIPTION:
2.1 BRIEF PROJECT PROFILE:
S.NO PARTICULARS DESCRIPTION
1. Name of project : Mangampet Barytes project of M/S. APMDC Limited
(Expansion of Baryte production capacity from 3.0 MTPA to
5.0 MTPA and increasing pulverizing unit capacity from 0.1
to 0.3 MTPA)
2. Project proponent : M/S. APMDC Limited
3. Area Project area - 377.6326 Ha
Lease area - 225.0139 Ha
Outside the lease area mainly
for dumping and its safety
zone - 152.6187 Ha
4. Type of Land Lease area - Non-Forest Land
Outside lease area – Major Part are Private Land
5. Location : Mangampeta & Govindampalli Villages, Obulavaripalli
Mandal, YSR Kadapa District, Andhra Pradesh
6. Topography : The maximum and minimum elevation of the lease area is
180m AMSL & 342m AMSL respectively
7. Production capacity : Expansion of Barytes production capacity from 3.0 MTPA
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-6
to 5.0 MTPA and increasing pulverizing unit capacity from
0.1 to 0.3 MTPA
8. Total Reserves : 47.32 Mil.t
9. Waste : Scheme period -18.92 Mil.Cu.m
Conceptual period -82.83 Mil.Cu.m
Total -101.75 Mil.Cu.m
10. Method of Mining : The mining operations will be through mechanized
opencast mining system, involving shovel-dumper
combinations, drilling and blasting etc.,
11. Bench parameters Presently the height of the bench is kept at 10 meters and
the width of the bench is more than 2 times the bench
height.
12. Ore end use : The Barytes ore and powder produced will be supplied to
the consumer industries
13. Waste management : The total proposed waste likely to be generated is 101.75
Mil.Cu.m. out of which about 7.00 Mil Cu.m will be utilized
for refilling in the worked out pit over an area of 32.3315 Ha
and the remaining waste of 94.75 Mil.Cu.m will be dumped
over an area of 169.3049 Ha both inside (36.3691 ha) and
outside the lease area (132.9358 Ha). Top soil will be used
for afforestation purposes. The inactive dumps will be
reclaimed. Necessary drains, retaining wall will be provided.
14. Life of mine : 10 years
15. Other industries in the area : Many pulverizing units & Ferrro alloy plant
16. Combined Manpower : Presently about 550 persons are employed directly and
about 1000 persons are getting indirect employment
17. Combined Water
Requirement
& source
The entire industrial water requirement will be met by the
mine discharge water, whereas the drinking water
requirement will be sourced from the bore well within project
area.
S.no Description Water requirement
Cu.m/day
1 Dust Suppression 200
2 Green Belt/Afforestation 25
3 Drinking & Domestic 55
TOTAL 280
18. Site services : APMDC have project office, Mine site / pit office, a Guest
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-7
House, Garage cum work shop, canteen, stores, 3 nos. of pulverizing mills, VTC, First Aid
Stations, Explosive Magazine, Ammonium Nitrate storage shed, Mixing shed for Anfo ,
Electronic weigh bridges , Two nos. of Diesel bunks of capacity 50 K L & 20 KL etc.
Besides, 57 nos. of different type of quarters, school, hospital, welfare centre, club etc., are
available for residential purpose of the employees. For the proposed expansion project all
these facilities will be suitably upgraded.
19. Mineral Transport : The hauling roads are with proper gradients of 1:16 are
properly designed
2.3 LAND USE PATTERN:
As already mentioned, the total project area is 377.6326 Ha comprising 225.0139 Ha of
mine lease area, 132.9358 Ha of dump area outside the lease and 19.6829 Ha of safety zone
around the dump outside the lease.
The land use pattern at the beginning of the scheme period, end of the scheme period
and the conceptual stage is given below:
Type of land use
At the beginning of
the Scheme Period
(Ha)
At the end of the ensuing
Modified Scheme Period
(2016-17 to 2017-18) (Ha)
Conceptual
period
(Ha)
Area of excavation 114.6638 129.9588 129.9588
Storage of top soil 0.0000 0.0000 0.0000
Waste Dump 32.2370 36.3691 36.3691
Mineral Storage 14.5243 13.3213 13.3213
Infrastructure (Office
building, Rest Shelter,
workshop, canteen,
magazine)
2.5117 2.5117 2.5117
Roads 1.3265 1.9000 1.9000
Railways Nil Nil Nil
Tailing pond Nil Nil Nil
Effluent treatment plant Nil Nil Nil
Mineral Separation plant 0.7500 2.0000 2.0000
Town ship area 2.1201 2.1201 2.1201
Others (Green belt &
Safety zone) 7.5000 9.0000 15.0000
Area utilized 175.6334 197.1810 203.1810
Undisturbed area 49.3805 27.8329 21.8329
Total lease area 225.0139 225.0139 225.0139
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-8
Besides an area of 132.9358 Ha outside the lease area will be utilized for dumping.
An area of 19.6829 Ha will be left as safety zone around the dump area.
Necessary NOC from the state Government is being obtained for utilizing outside the lease
area.
Thus the project area will be 377.6326 Ha (Mining lease area – 225.0139 + dump area –
132.9358 Ha + Safety zone around dump – 19.6829 Ha Ha).
Out of the total mined out area of 129.9588 Ha, about 32.3315 Ha will be backfilled, about
74.4854 Ha will be left as water reservoir and the balance 23.1419 Ha will remain as mined
out benches.
3.0 PROJECT LAYOUT IN RELATION TO IMPORTANT NATURAL FEATURES:
The project area is devoid of declared ecologically sensitive features like national parks,
biospheres, sanctuaries, etc., as mentioned earlier. No forest land is involved in the lease area.
The area also does not come under CRZ category.
In the 10 km buffer zone the following features are observed:
SI.No Particulars Details
1. Nearest villages Kapupalli – more than 260 m from the lease
boundary – Western direction
2. Nearest Highway Tirupathi – Kadappa Highway (SH‐31) –
more than 400 m – E
3. Nearest Railway station South Central main BG railway line
connecting Renigunta – Kadapa passess
9.0 km west of the site.
Koduru – 9.0 km, SE
4. Nearest Airport Tirupathi Airport – 69 km,
Chennai Airport – 190 km
5. Nearest water bodies Streams namely Gundala Eru – 2.2 km (S),
Mushti Eru – 5.0 km (S), Gundala Vanka – 8.0
km (SE) & Gunjana Eru – 3.1 km (SE)
confluence with Gunjana Vagu flowing 2.8 km
north. Few tanks are available in the area
which are interconnected
6. Notified Archaeologically important places,
Monuments
Nil within 10 km radius
7. Local Places of Historical and Tourism
Interest
Nil within 10 km radius
8. Environmental sensitive areas, Protected
areas as per Wildlife Protection Act, 1972
(Tiger reserve, Elephant reserve, Biospheres,
National parks, Wildlife sanctuaries,
community reserves and conservation
reserves)
Seshachalam Biosphere reserve – 10.7 km
from the lease boundary
9. Reserved / Protected Forests Seshachalam Extension RF – 7.3 km – SW,
Tunakonda RF – 7.3 km – S,
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-9
Kodur Extension RF – 6.0 km – E,
Maharajapuram Block RF – 6.8 km – NE,
Chitvel Extn. RF – 6.1 km – N.
10. Defence Installations Nil within 10km radius
11. Seismic Zone Zone – III (Moderate)
12. Other Industries in the area Many pulverizing units & Ferrro alloy plant
4.1 GREEN BELT PROPOSALS:
Plantation is carried out in all possible areas like near the office, along the roads, colony,
in the safety zone etc. Green belt development / plantation will be continued and ultimately major
part of the lease area including the dump area, backfilled mine out area will be reclaimed and
developed with greenery.
5.0 REHABILITATION AND RESETTLEMENT PLAN (R&R PLAN):
As already mentioned, the expansion will be carried out in the existing lease area only
and as such no additional area is required for mining during expansion. The entire lease area is
with APMDC. However, dumping will be carried out outside the lease area and as such the total
project area works out to 377.6326 Ha. Major part of 152.6187 Ha of land outside the lease area
are private lands for which necessary NOC is being obtained. There are no forest land in the
project area.
The area outside the lease is selected after avoiding the habituated Kapupalli and
Harijana wada village on the south western side. As such there will not be any home oustees.
Part of the private lands are already acquired and is in APMDC’s possession. The
remaining private lands consists of trees, bushes and some agricultural lands also. Balance
private lands are being acquired for which Preliminary notifications are also issued in many
cases. Subsequently, some settings in the form of dwellings were created by the locals to get
higher compensation. But the issue was brought out to the revenue authorities, who made site
visit and terming those structures as illegal.
For private lands to be utilised outside the lease area, necessary NOC from the District
collector is being obtained.
6.0 PROJECT SCHEDULE AND COST ESTIMATES:
This being a working mine, the envisaged expansion quantity will be achieved in a
phased manner. It is proposed to achieve the enhanced 5.0 MTPA barytes ore production in the
2nd year after commencement of expansion activities.
In the mining front all efforts will be made to utilize the existing machineries to the
maximum possible extent. Additional equipment’s for expansion and pulverizing plant will be met
through internal arrangements.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-10
The estimated production cost per MT of Barytes ore is expected to be Rs.1100 to
Rs. 1300/ per ton.
7.0 ANALYSIS OF PROPOSAL:
The existing mining operations in the area have already brought about positive impact
locally by way of employment generation, increase in income generation, creation of
infrastructural facility, marked improvement in the life style and living standards of the population
of the surrounding area.
There will be continued substantial improvement in case of local population in living
standards, receipt of per capita income, cultural patterns, living styles, educational standards,
etc. after expansion also.
As already mentioned earlier, the project will improve the social and physical
infrastructural patterns of this interior area in its own way resulting in overall improvement of HDI
(Human Development Index). Besides, the Central and State Government will also derive good
financial benefits by way of receipt of taxes, duties and cess.
In view of above aspects of the project, the project can be said to be beneficial to the
local community, the local region, the State and to the entire country on the whole.
* * * * * * * *
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-11
CHAPTER – II
INTRODUCTION OF THE PROJECT / BACKGROUND INFORMATION
2.0 BACKGROUND INFORMATION OF PROJECT:
M/s. Andhra Pradesh Mineral Development Corporation (APMDC) Limited, the State
Government entity is operating Mangampet Barytes Project since year 1978 in Mangampeta &
Govindampalli Villages, Obulavaripalli Mandal, YSR Kadapa District, Andhra Pradesh.
Initially there were 10 separate leases with APMDC in this area. Subsequently,
M/s. APMDC obtained Amalgamation of (10) mining leases into a single lease with the total
extent of 225.0139 Ha vide G.O.MS.No. 126 dated 19.12.2015 which is Co-terminus with the
expiry of first lease by 01.09.2018 (Annexure – 1) with further scope for renewal for 10 more
years.
Presently 3.0 MTPA capacity Barytes mine is operated in this lease area after obtaining
the following statutory clearances:
Scheme of Mining approved by Joint Director of Mines and Geology, Kadapa
Zone vide Lr.No 2276/MS-KDP/2013, dated 18.04.2015 for Barytes ore
production capacity of 3.0 MTPA. (Annexure – 2).
The Environmental Clearance obtained from MoEF for existing Barytes production
capacity of 3.0 MTPA including 0.1 MTPA Barytes Powder vide letter no. J-
11015/582/2007-IA.II (M), dated 30th December 2008 (Annexure – 3).
Combined consent under Water Act, Air Act and authorization under Hazardous
waste rules obtained from APPCB which is valid up to 31st December 2017
(Annexure – 4).
Considering the good demand for quality Barytes ore, now it is proposed to enhance the
Barytes ore production from 3.0 MTPA to 5.0 MTPA and also increase the existing pulverizing
plant capacity to produce 0.30 MTPA Barytes powder from the existing level of 0.10 MTPA.
Mine movement and enhancement of production from this lease is planned along with
simultaneous working by surface chopping of adjacent new Dolomite lease area of 114.14 Ha of
APMDC up to 230m RL for which separate EC application is being made.
Since the waste material cannot be dumped in the lease area, additional land outside the
lease area is also acquired for these 2 projects.
Details of the lease area and outside lease area of the two adjacent projects of APMDC
is given below:
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-12
This project pertains to expansion of Barytes project for a total project area of
377.6326 Ha comprising 225.0139 Ha of lease area and 152.6187 Ha outside the lease
area.
MOEF&CC notification stipulates that, any change in production requires fresh
environmental clearance. Under the above circumstances APMDC has initiated action towards
obtaining environmental clearance for this expansion project.
Prior to obtaining environmental clearance, as per MOEF&CC notification of September
2006, Form I and Feasibility report have to be submitted along with proposed Terms of
reference (TOR) for the project for stipulating the TOR for the project by MOEF&CC, Govt. of
India.
This project falls under category A as per MoEF&CC notification in this respect, because
of mining lease being more than 50 Ha. Hence, Form – 1, proposed TOR and feasibility report
have to be submitted to MoEF&CC, New Delhi for their approval and prescribing TOR and
according EC after submission of EIA/EMP report to them.
This feasibility report for Mangampeta Barytes Project of M/s. Andhra Pradesh
Mineral Development Corporation (APMDC) Limited is prepared in line with the guidelines
issued by MoEF&CC, vide their letter dated 30th September 2010 for the total project area
of 377.6326 Ha comprising 225.0139 Ha of lease area and 152.6187 Ha outside the lease
area mainly for dumping and its safety zone towards expansion of Barytes production
capacity from 3.0 MTPA to 5.0 MTPA and also to increase the existing pulverizing plant
BARYTES LEASE AREA
BARYTES OUTSIDE
LEASE AREA
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-13
capacity to produce 0.30 MTPA Barytes powder from the existing level of 0.10 MTPA for
obtaining TOR from MoEF&CC towards getting environmental clearance based on
modified scheme of mining submitted to authorities.
2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT:
This Barytes mining lease is operated by APMDC for the last 4 decades. Good
approach roads and various infrastructural facilities are already developed for this project and
scientific mechanised mining is adopted in this lease.
There are potential buyers in our country and also abroad to procure the quality Barytes
produced from this lease.
From the geological trend, quality barytes ore is expected in the area and the overall
reserve potential in the total mine lease area is expected to be good.
The lessee is having experience in mining and marketing of Barytes ore for the last 4
decades. As such, it can be seen that the project proponent is having versatile experience and
expertise in Barytes ore mining & marketing.
Considering all these aspects, it is identified now to go for this expansion.
PROJECT PROPONENT:
Name and Address of the applicant:
Mangampet Barytes Project
M/s. APMDC LIMITED,
H.No: 6-2-915, 3rd Floor, Rear Block, HMWSSB Building,
Khairatabad, Hyderabad - 500 004.
E-mail: [email protected]
Ph: 040 -23393154, 27427959
Fax: 040-23393152.
2.2 BRIEF DESCRIPTION OF NATURE OF PROJECT:
The project envisages increase in Barytes ore production capacity from 3.0 MTPA to
5.0 MTPA along with increasing the Pulverizing unit capacity to 0.3 MTPA from the existing
level of 0.10 MTPA for producing Barytes powder. The mining operations will be through
mechanized opencast mining system, involving shovel-dumper combinations, drilling and
blasting etc., as described in chapter III.
2.3 NEED FOR THE PROJECT & ITS IMPORTANCE TO THE COUNTRY AND / OR
REGION:
Baryte is the moderately soft crystalline mineral form of Barium sulphate (BaSO4). About
80% of barytes produced worldwide is used for oil and gas drilling as a weighting agent in the
drill mud, primarily to prevent the explosive release of gas and oil during drilling. Barytes is used
as filler and extender in paint industry, rubber products, paper industry, oil cloth, X-ray proof
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-14
plaster and rope finishes. It is also used in the manufacture of asbestos products required for
auto brake lining and other frictional materials, concrete aggregate as an absorber of gamma
and X-ray radiation required for reactor shielding etc,. It is a principle mineral of barium and is
also used as feedstock for producing various barium compounds and is utilized as filler,
extender and aggregate. Barium carbonate is used in glass industry as a flux to add brilliance
and clarity in eletro-ceramics and for removing inconvenient impurities in phosphoric acid.
Barium sulphate is used as pigment, extender and filler in rubber and paper industries. India
ranks second in the production of barytes in the world after China and is one of the important
exporters in the world market. Andhra pradesh alone accounts for 94% of the country’s
resource. The Mangampet deposit in Cuddapah district of Andhra pradesh is the single largest
barytes deposit in the world.
Andhra pradesh continued to be the premiere state in barytes production accounting for
almost the entire production of barytes from our country with very little production from
Rajasthan.
The Andhra Pradesh Mineral Development Corporation (APMDC) is the sole producer
in public sector and it accounted for about 94% of the total production in our country.
The worldwide demand for barytes would continue till petroleum products are preferred
as chief source of energy given their importance in the transportation and industrial end use
sectors. The future growth in petroleum usage suggests that petroleum exploration will continue
to grow and along with its barytes consumption, especially as more drilling has to be done per
unit of oil as hydro carbon discoveries become smaller and less productive with time. The
apparent domestic demand of barytes is estimated to be 2.09 milllion tonnes by 2016-17 and is
expected to grow at 9% growth rate.
Considering the presence of quality barytes ore mainly in mangampet region, increase
in production from this lease will help to meet the future demand of this mineral both in local
market and also for export.
As far the regional scenario is concerned, the local area blessed with this mineral, is
getting good uplift in terms of social condition betterment, industrial growth and local area
development due to mining and allied activities in this region. The State Government will also
be benefited financially through receipt of royalties, cess, duties, etc., due to project operations.
It can be concluded that on an overall basis, sustained industrial growth of the State can be
realized to full measure by the present proposal.
2.4 EMPLOYMENT GENERATION:
Presently about 550 persons are employed directly and about 1000 persons are getting
indirect employment due to trading, transport etc. Further scope for more employment
generation is envisaged due to the proposed expansion both in the direct and indirect front.
* * * * * * * *
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-15
CHAPTER – III
PROJECT DESCRIPTION
3.1 TYPE OF PROJECT:
This is an increase in barytes ore production capacity from 3.0 MTPA to 5.0 MTPA and
increasing the pulverizing plant capacity from 0.1 MTPA to 0.3 MTPA to produce barytes
powder. The barytes ore and the powder produced from this mine will meet the domestic and
export demand.
3.2 LOCATION:
Mangampeta Barytes Project of M/s. Andhra Pradesh Mineral Development Corporation
(APMDC) Limited is in Mangampeta & Govindampalli Villages, Obulavaripalli Mandal, YSR
Kadapa District, Andhra Pradesh. The barytes lease area is bounded by Latitude 14O 00’ 52.80”
to 14O 02’ 15.01” and Longitude 79O 17’ 55.48” to 79O 19’ 41.54” and falls in Survey in India
Topo Sheet No. 57 N/8.
The project area is approachable from State Highway (SH – 31) connecting Tirupathi
and Kadapa passing more than 400 m east of the lease area. The district Headquarters,
Kadapa is about 80 kms away from project and Tirupathi is about 69 km from the site. The
nearest railway station Koduru is about 9.0 km away from project. The nearest Airport is
Tirupathi which is 69 km away while the nearest port city Chennai is 190 km from the mine. The
location Map attached as Figure No - 1.
3.3 DETAILS OF ALTERNATE SITES CONSIDERED & THE BASIS OF SELECTING
THE SITE:
As far as mine expansion is concerned, since this is an expansion project in the existing
mining lease area for which lease already granted, question of alternate site does not arise.
3.4 SIZE OR MAGNITUDE OF OPERATION:
The current proposal of expansion of barytes ore mine capacity to 5.0 MTPA (ROM) and
enhancing the pulverizing plant capacity to 0.3 MTPA will be within a total project area of
377.6326 Ha comprising 225.0139 Ha of lease area and 152.6187 Ha of outside lease area
mainly for dumping and other infrastructures.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-16
Figure No - 1
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-17
3.5 PROJECT DESCRIPTION:
3.5.1.1 GEOLOGY:
A) REGIONAL GEOLOGY (CUDDAPAH SUPER GROUP)
The Cuddapah basin with easterly concave and N-S trending, located between latitudes
13˚30’N - 17˚00’N and longitudes 78˚00’E - 80˚00’E, is the repository of several mineral
deposits inclusive of Barites, all of vein types except the unique bedded type, the
Mangampet Barites deposit.
Cuddapah basin is characterized by quartzite-carbonate-shale cycles having an
aggregate thickness that is estimated to vary between 6 and 12 kms. The early
sediments of the Basin were interspersed with basic volcanic and sills. Felsic- volcanic
and tuffs are intercalated with sediments at many horizons.
The basin is well known for its mineral potential in the form of limestone and dolomites,
bedded and vein barytes, chrysotile asbestos and steatite, besides occurrences of base
metals, diamond, phosphorite, uranium and abundant building and ornamental stones.
The arcuate north, south and western boundary of the Cuddapah basin marks the
profound Eparchaean Unconformity on basement granites. The arcuate eastern margin
is marked by a prominent boundary thrust, which is parallel to the Nellore schist belt,
Eastern Ghats mobile belt and the East coast. The Geological map of Cuddapah Basin
is shown in Figure No - 2 and the stratigraphy is furnished in below table.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-18
The Stratigraphic Sequence of Cuddapah Super Group (After Raman and Ramamurthy-1997)
The western half of the basin is un deformed and consists of four sub-basins, the
Papaghni, Kurnool, Srisailam and Palnad. The Papaghni and Kurnool sub-basins are
geographically interlinked, but were sites of deposition at different times. The Papaghni sub-
basin containing lower Cuddapah sediments and the Kurnool sub-basin containing the younger
Kurnool sediments that overlie the Cuddapah sequence with a major unconformity. The eastern
half of the Cuddapah basin is occupied by the Nallamallai fold belt consisting of upper
Cuddapah.
Group Formation Lithology Thickness(m)
Kurnool Nandyal shale
Koilkuntla Limestone
Narji-Limestone
Bairenkonda quartzite
Shale
Limestone
Limestone
Quartzite
500
-------------------------------Unconformity----------------------------------------------
SrisailamQuarzite --------------- 600
------------------------------ Unconformity-----------------------------------------
Nallamala Cumbum
Baironkond
Phyllite, Shale
Quartzite, Shale
3500
------------------------------ Angular Unconformity-----------------------------------
Chitravati Gondikota Quartzite
Tadipatri
Pulivendla Quartzite
Quarzite, Shale, Sills
Shae, Tuffs, Barytes
Mineralization Quartzite
Conglomerate, Quartzite
6000
------------------Disconformity-----------------------------------------------------------
Papaghni Vempalli
Gulcheru Quartzite
Stromatalitic dolomite
Chert, bricca, intrusive
Coglomerate, Quartzite
2100
------------------Nonconformity---------------------------------------------------------------
Achaean gneisses, and Green schist’s
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-19
GEOLOGICAL MAP OF CUDDAPAH BASIN Figure No - 2
B) DETAILED DESCRIPTION OF GEOLOGY OF THE LEASE AREA:
The Mangampet barytes deposit occurs in the form of two lensoid bodies within the tuff
of Pullampet Formation, Nallamala Group of the Cuddapah Super Group. The lens occurring
near Mangampet village is termed as Northern lens and the other at 700m south of it is termed
as the Southern (smaller) Lens. The Mangampet Barytes project is confined to the Northern
lens of the Mangampet barites deposit.
The Mining Lease area forms a part of the Northern Lens (measuring 1220m in the
north-south direction and 900m in the east-west direction) of the Mangampet Barites Deposit. It
is the single largest and unique bedded Barytes deposit of its kind in the world.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-20
Carbonaceous tuff is the prominent rock Formation with interbands of crystal tuff,
dolomite, and dolomite tuff. The rock types associated with the Barites occurrence are well
exposed in the existing quarry.
The litho units in the area show NNW-SSE strike with gentle to moderate dips of 10°- 30°
towards ENE. The laminations in tuff and the bedding in Barytes trend N -S and N10°-30°W - S
10°-30°E direction with dips towards east in the south eastern part. The strike is E-W and NW-
SE in the NW of the deposit with gentler dips (5°-10°); the dips become steeper (40°-5 0°) and
are horizontal in synclinal trough portion.
A total of 67 diamond core Borehole with a total of 8200.89 m were drilled by the
Geological Survey of India. The data of the boreholes indicated a mineralized zone of 1220m
(strike length) with a maximum width of 900m for the northern lens. The deposit has an aerial
extent about 0.81sq.km with an average barites ore thickness of about 22.16m.The thickness of
the Over Burden as intersected in boreholes varies from 1.70 m (BH.MGP-6) to 181.05 m
(BH.MGP-43). The minimum & maximum thickness of the barites Ore body are 4.44m
(BH.MGP-56) in the northern end & 39.88m (BH No. MGP-26) respectively.
Based on the sub-surface data of the diamond core boreholes and the Geological
mapping conducted in the quarry and surround areas, the litho units at the deposit are
summarized below.
Litho units of the deposit
S.No Litho units Thickness(m)
1. Soil 0.50-3.00
2 Tuff( Hanging wall) 1.70-181.00
3 Barites with intercalation of tuff 1.50-60.00
4 Crystal tuff/dolomite( Foot wall) +1.0
5 Dolomite --
I. Soil:
The thickness of the soil in the ML area varies from 0.5m to 3.0m with an average
thickness of about 2.0m. The soil cover mostly masks the geology all over the area.
II. Tuff:
The carbonaceous Tuff, the prominent rock Formation, which contains inter-bands of
dolomite, dolomite tuff and crystal tuff of varying thickness and the barytes, occur within this
horizon. The tuff has a maximum thickness ofb181.05m (BHNo. MGP-35 & 43) above the
barites zone. Tuff is dark grey to black when fresh and is bleached to light grey or white color on
weathering or when exposed to surface. It is finely laminated, with well-developed cleavage. It
resembles ferruginous shale but has been established to be a tuff, a product of volcanism. It is
siliceous and contains specks and disseminations of pyrite which gives rise to yellow and brown
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-21
stains on weathered surfaces. Stringers of calcite, quartz and crystalline barytes are present in
the tuff. This tuff forms the hanging wall for the Barites bed with a sharp contact. Dolomite is
observed as inter-bands and lenses within the tuff.
III. Barites with intercalations of tuff:
Barytes, occurring below the tuff, is well exposed in the bottom parts of the existing
quarry. It shows discrete banding due to bedding which is in conformity with that in the overlying
tuff. The Barytes is of two types viz; the granular and the lapillar/rosette types with several
subtle variations.
1. Granular Barytes:
The granular variety is predominant in quantity and most important in view of high
specific gravity of 4.20 and above;+92% BaSO4%, low hardness and chemical inertness. It is
massive, fine-grained, grey granular/ saccharoidal barites within the tuff and confines to the
lower most horizon of the barites zone. It constitutes the commercial grades A & B.
2. Lapillar/ Rosette Barytes:
The lapillar/ rosette Barytes overlies the granular type and divisible into two distinct
varieties.
i. Tuff with barites lapilli:
This zone, varying in thickness from about 0.02m to 4.55m. It is dark grey, hard and
compact tuff with barites lapilli. The lapilli are aligned parallel to bedding. Pyrite occurs in the
form of lenses, clots and disseminations. This is commercially known as ‘C’ grade with specific
gravity of 4.0 to 4.09.
ii. Tuff with quartz-pyrite lapilli:
A light grey to dark grey tuff containing layers and disseminations of quartz and pyrite
lapilli overlies the barites lapilli. With a dull look and dark grey color, commercially the ‘D’ grade
has a specific Gravity of 3.50 to 3.99.
In general, the ‘A ‘grade variety is of granular type while the ‘D’ grade barytes is of rosette. For
marketing purpose, the barites is classified into
‘A’ Grade with Specific Gravity of 4.20 and above;
‘B’ grade with sp.gr of 4.10 to 4.19;
‘C’ grade with sp.gr of 4.0 to 4.09 while the
‘D’ grade with sp.gr. of 3.50 to 3.99
Based on the thicknesses of barites observed in face of workings and sub-surface data,
the thickness and proportions of the different grades of barites at the Mangampet barites
deposit is summarized below:
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-22
Grade Range of thickness(m) % of total in situ reserves
A
B
C
D
1.35 to34.65
1.50 to 13.15
3.35 to 17.20
0.8 to 16.25
62
13
08
17
The ‘A’ grade is at the lower part of the bed and is successively overlain by B, C & D
grades. B, C, D grades totally pinch out in some places. The maximum over burden is 181.05 m
(BH-MGP-43) over a barites bed of 18 m.
IV. Crystal tuff/ dolomite:
It is the foot wall rock immediately below the barites bed. It also occurs as lenses and
inter bands within the tuff as observed in drill data and the working faces. It is light to dark grey
in colour, fine to medium grained, hard, compact and massive in nature.
Dolomite is light grey, fine to medium grained, and siliceous, hard and compact rock and
at places containing disseminations of pyrite. It is traversed by thin vein lets of quartz and calcite
and occurs as inter bands and lenses within the tuff. The dolomite predominantly comprises
fine, equi-granular, anhedral and sub hedral grains of dolomite exhibiting a mosaic structure. It
underlies the crystal tuff and also forms the foot wall for the barites bed.
3.5.1.2 EXPLORATION:
The deposit was explored during 1974-78 by drilling 67 diamond core boreholes with a
total of 8200.89m at an interval of 105-150 m along the strike and 100-140 m across.
Subsequently, APMDC carried out the drilling involving 1356m in 19 boreholes along with the
logging and chemical analysis incidental for the exploration. The exploration carried out are
adequate and based on this the reserve estimations were done.
3.5.1.3 RESERVES:
The entire lease area is covered by Barytes. There is one working pit in the leased area.
The mineral is extracted from this pit. A total of 67 diamond core Borehole with a total of
8200.89 m at intervals of 105-150 m along the strike and 100-140 m across was drilled by the
Geological Survey of India. The Geological structure (folding along and across the strike)
furnished by the Geological Survey of India is used while preparing the borehole geological
cross-sections. 30 nos. of geological cross-sections were drawn based on the borehole
database. For the ensuing study, the depth–wise and grade-wise in-situ Geological reserves at
the Mangampet Barytes project of M/s APMDC are re-estimated/ assessed. The reserves
estimated up to the depth of drilling is codified into G2 stage as per UNFC norms with
Geological code of G2 (Refer Figure No – 3 for geological plan).
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-23
This Barytes deposit can be called as Unique bedded deposit, as per the UNFC
guidelines the ore deposits are classified under five types of deposits, out of which the existing
Mining Lease comes under Type – I (Bedded Stratiform and tabular deposits of regular &
irregular habit).
The Residual mineable reserves of 47.32 Mil.t of Barytes are established and
categorized under (122) and its details as per UNFC classification is given below:
CLASSIFICATION OF RESERVES
Classification Code
Quantity & Quality of Baryte
Quantity
(T) Grade
Total Mineral Resources (A+B)
A. Mineral Reserves
1. Proved Mineral Reserve
2. Probable Mineral Reserve
B. Remaining Resources
1. Feasibility Mineral Resource
2. Prefeasibility Mineral Resource
3. Measured Mineral Resource
4. Indicated Mineral Resource
5. Inferred Mineral Resource
6. Reconnaissance Resource
111
122
211
221 & 222
331
332
333
334
----
47328348.8
-----
-----
-----
-----
-----
-----
47328348.8
A’ Grade with Specific Gravity of 4.20
and above;
‘B’ grade with sp.gr of 4.10 to 4.19;
‘C’ grade with sp.gr of 4.0 to 4.09 while
the
‘D’ grade with sp.gr. of 3.50 to 3.99
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-24
GEOLOGICAL MAP Figure No - 3
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-25
3.5.1.4 MINING METHOD:
A) PRESENT MINE WORKING:
Presently opencast mechanized mining, employing deep hole drilling and blasting, using
heavy earth moving machinery like hydraulic excavators to excavate the blasted Ore and waste
and load the same into Dumpers is adopted. The waste / Barytes is hauled to waste Dumps and
Stock yards. Considering the geo-mining conditions such as basinal structure, steep gradient
and varying thickness of the ore, Shovel-dumper system is very flexible and also offers
convenient mining operations to deal with sudden occurrences of unworkable or poor quality
patches. The same methodology will be continued after expansion also.
Presently the height of the bench is kept at 10 meters and the width of the bench is more
than 2 times the bench height. The hauling roads are with proper gradients of 1:16 and benches
are properly designed along the strike direction by adopting best safety concepts. The efficient
trained manpower is engaged for the best possible exploitation of Barytes. The present mine
position is shown in Surface Layout plan Figure No - 4.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-26
SURFACE LAYOUT PLAN Figure No - 4
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-27
B) SCHEME PERIOD:
During this scheme period, it is proposed to continue with the existing 3.0 MTPA Barytes
ore production in year 1 (i.e 2016-17). During this period all necessary statutory approval
required for the proposed expansion capacity will be obtained, then it is proposed to achieve the
desired expanded production capacity of 5.0 MTPA in Year 2 of this scheme period
(i.e 2017-18).
Mine movement in this lease is planned along with simultaneous working by surface
chopping of adjacent Dolomite lease area of 114.14 Ha up to 230m RL. Besides, re-handling a
part of waste dump - 3 on northwest side is also proposed for further advancement of mine
benches in future.
The Modified Scheme of mining is prepared for the remaining 2 years i.e. 2016-17 to
2017-18. The year wise quantum of Barytes production and overburden and waste generated
are furnished in table below
YEAR WISE PRODUCTION PLANNED DURING THIS SCHEME
Year
Pit excavation Grand total
Ore
(Mil.T)
Insitu OB/
Side
burden
(M.Cum)
Re-handling
(M.Cum)
Topsoil
(M.Cum)
Waste
(M.Cum)
Strip
ratio
(Cum/T)
Waste
(M.tons)
Barytes
(M.tons)
Total
(M.tons)
2016-2017 3.00 7.29 0.32 0.14 7.75 2.58 14.84 3.0 17.84
2017-2018 5.00 10.83 0.47 0.36 11.66 2.33 22.33 5.0 27.33
Total 8.00 18.12 0.79 0.50 19.41 2.42 37.17 8.00 45.17
Note: The Tonnage conversion factor of 1.914 T/cu.m is assumed for waste
based on the Bulk density study conducted by APMDC
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-28
The production planned in the proposed period is around 8.0 MT (for 2016-17 & 2017-18)
by retaining the same position of the ramp for future expansion of the project. The pit needs to be
further expanded towards footwall (since some more ore is left against footwall i.e., western side),
towards northern side (i.e dump – 3) and towards eastern side.
The present layout of initial opening ensures systematic development, provides space for
future internal dumps i.e refilling and also gives a better stripping ratio.
The deposit is proposed to be opened along the strike (major portion) and it is envisaged
that local ramps will be suitably laid for transportation of Ore and overburden. Opening along
strike direction will provide comparatively longer face length.
Top OB benches on the high wall side are to be advanced there by creating space for
deepening of the quarry.
The anticipated rate of production per annum during this modified scheme period is
3.0 Mil.T and 5.0 Mil.T during 2016-17 and 2017-18 respectively.
C) CONCEPTUAL PERIOD:
Conceptually the project is planned to work up to a maximum depth of 220 m of ore
(considering surface chop level RL of 230m & floor RL of 10m). The pit is designed maintaining
400 pit slope.
Year wise production planned during conceptual period
Sl
No. Year
Planned during scheme period
Ore (Mil.T) OB (Mil.Cu.m)
1 2018-19 to 2025-26 39.32 82.83
Ultimately, out of the total mined out area of 129.9588 Ha, about 32.3315 Ha will be
backfilled, about 74.4854 Ha will be left as water reservoir and the balance 23.1419 Ha will remain as
mined out benches. Conceptual stage plan is given as Figure No - 5.
3.5.1.5 DUMP YARD DETAILS:
Dumps planned within and outside the Mining lease area in Dump-D1&2, located on the
Western side of pit. At present the dump occupies an area of 32.2370 Ha within the lease area
and 50.0782 Ha outside the lease area. The total insitu OB that is estimated to be accommodated
in the Dump - D1 & 2 is 18.92 Mil.Cu.m. The dump yard is planned to a maximum height of 100m
above Ground Level.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-29
The same dump will be utilized for dumping about 75.83 Mil.Cu,m quantity of waste out of
82.83 Mil.Cu,m of waste generated during the conceptual period. The remaining 7.00 Mil.Cu.m
will be utilized for refilling the worked out pit over an area of 32.3315 Ha on the Southern side of
the lease area.
Details of Accommodation of Insitu OB in Dump Yards
Sl.
No. Dump Yard Location
Area
(Ha)
Height of Dump
(m)
Total OB
(Mil.Cum)
1 Dump–D1&2
Inside the lease 36.3691
100 94.75
2 Outside the lease 132.9358
TOTAL 169.3049 94.75
YEAR INSITU OB
(MIL.CU.M)
OB REHANDLED
(MIL.CU.M) Dump Yard
2016-17 7.29 0.32
External dump– Dump–D1 & 2 2017-18 10.83 0.47
TOTAL 18.12 0.79
The top soil generated during the scheme period will be utilized for afforestation purposes.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-30
CONCEPTUAL PLAN Figure No – 5
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-31
3.5.1.6 DETAILS OF MACHINERY:
The details of machineries in the mine are as follows:
Sl.No Particulars HEMM
A)
1
2
3
OVERBURDEN
6.5Cum Diesel Hydraulic Shovels
50- 60 T Rear Dumpers
320-360HPDozers
6
30
4
B)
1
2
3
ORE
3.0 Cum. Diesel Hydraulic Shovels
35T Rear Dumpers
200HPDozer
5
8
2
C) 150-160mm Diesel RBH Drills 6
D)
1
2
3
4
5
6
7
8
9
10
11
ANCILIARYEQUIPMENT
0.9Cum Diesel Hydraulic Shovel
170 HP Motor Graders
28KLWater Sprinkler
8/10TCranes
40TCrane
3Cum Front end loader
Fuel/Lubricant Truck
Tyre Handlers
Fire Tender
Mobile Maintenance Van
Diesel Bowsers
1
3
4
5
1
3
4
2
1
3
3
D)
1
2
3
RECLAMATION
145HPMotorGraders
Farm Truck
28KL Water Sprinkler
1
1
1
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-32
3.5.2 PULVERISING PLANT:
The chemical composition of barytes produced from this lease area does not require any
beneficiation for quality improvement since the quality of barytes produced from this mine
is directly marketable to different consumers.
However barytes is subjected to pulverization for generation of powder of -200 mesh. The
below -200 mesh barytes being produced is used in oil-well drilling and paint industries.
At Mangampet project there are 3 nos. of 516 Model Raymond pulverizing mills installed
way back in the year 1978 with a capacity of 120 T/day/ mill. All the 3 mills are close to
one another with a combined capacity of about 360 TPD.
However it is proposed to increase the capacity of the pulverizing unit to a capacity of
1000 TPD.
The pulverizing plant process is given below:
Bigger lumps of bartyes are manually broken to 4 to 6” size and fed manually into primary
jaw crusher and sized to ½” to 1“approximately.
This sized material is fed through belt conveyor to a hopper of 3 T capacity.
From the hopper through automatic vibrator the material is fed into the mill (pulverizer)
have sets of 5 roller where the material is powdered.
Through an air fan driven by 65 HP motor the powdered Barytes are pneumatically
conveyed into cyclones. From the bottom of the cyclones barites powder are collected in
50 kg bags and marketed.
The dust is collected by 89 no of filter bags into dust collectors which is recycled back into
the process.
3.5.3 LAND USE PATTERN:
As already mentioned, the total project area is 377.6326 Ha comprising 225.0139 Ha of mine
lease area, 132.9358 Ha of dump area outside the lease and 19.6829 Ha of safety zone around the
dump outside the lease.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-33
The land use pattern at the beginning of the scheme period, end of the scheme period and
the conceptual stage is given below:
Type of land use
At the beginning of
the Scheme Period
(Ha)
At the end of the ensuing
Modified Scheme Period
(2016-17 to 2017-18) (Ha)
Conceptual
period
(Ha)
Area of excavation 114.6638 129.9588 129.9588
Storage of top soil 0.0000 0.0000 0.0000
Waste Dump 32.2370 36.3691 36.3691
Mineral Storage 14.5243 13.3213 13.3213
Infrastructure (Office
building, Rest Shelter,
workshop, canteen,
magazine)
2.5117 2.5117 2.5117
Roads 1.3265 1.9000 1.9000
Railways Nil Nil Nil
Tailing pond Nil Nil Nil
Effluent treatment plant Nil Nil Nil
Mineral Separation plant 0.7500 2.0000 2.0000
Town ship area 2.1201 2.1201 2.1201
Others (Green belt &
Safety zone) 7.5000 9.0000 15.0000
Area utilized 175.6334 197.1810 203.1810
Undisturbed area 49.3805 27.8329 21.8329
Total lease area 225.0139 225.0139 225.0139
Besides an area of 132.9358 Ha outside the lease area will be utilized for dumping.
An area of 19.6829 Ha Ha will be left as safety zone around the dump area.
Necessary NOC from the state Government is being obtained for utilizing outside the lease
area.
Thus the project area will be 377.6326 Ha (Mining lease area – 225.0139 + dump area –
132.9358 Ha + Safety zone around dump – 19.6829 Ha Ha).
Out of the total mined out area of 129.9588 Ha, about 32.3315 Ha will be backfilled, about
74.4854 Ha will be left as water reservoir and the balance 23.1419 Ha will remain as mined
out benches.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-34
3.5.4 LIFE OF THE MINE:
Considering a production level of 5.0 M T per annum, the balance life of the mine is as
indicated below.
Life of Mine
Total reserves - 47.32 Mil.T
Quantity mined during remaining 2 years of - 8.00 Mil.T
Mod. Scheme period
Balance reserves - 39.32 Mil.T
Avg. proposed production
during conceptual period - 5.0 MTPA
Balance years of production - 39.32/5.0
- 7.864 years
Therefore the life of mines - 2 + 7.864
- 9.864 years say 10 years
3.6 RAW MATERIAL REQUIRED ALONG WITH ESTIMATED QUANTITY, LIKELY
SOURCE, MARKETING AREA OF FINAL PRODUCTS, MODE OF TRANSPORT OF
RAW MATERIAL & FINISHED PRODUCT:
After expansion, about 5 MTPA of barytes will be produced from the mine. Out of this
about 0.3 MTPA barytes powder will be produced.
There is good market indigenously and as well as export. The barytes ore as well as the
powder will be transported by road.
3.7 RESOURCE OPTIMIZATION / RECYCLING AND REUSE ENVISAGED IN THE
PROJECT:
The entire ore produced can be marketed.
3.8 AVAILABILITY OF WATER ITS SOURCE, ENERGY/POWER REQUIREMENT & ITS
SOURCE
3.8.1 WATER REQUIREMENT:
Combined total water requirement for the Barytes mining project and the adjacent
Dolomite lease of APMDC is estimated to be 280 m3/day comprising 200 m3/day for dust
suppression, 25 m3/day for Green belt development and 55 m3/day for drinking & domestic
activities. The entire industrial water requirement will be met by the mine discharge water,
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-35
whereas the drinking water requirement will be sourced from the bore well within project area.
One RO plant with a treating capacity of 2000 LPH is installed by APMDC for supply of drinking
water to staff quarters, offices, canteen, Guesthouse and surrounding villages.
3.8.2 POWER REQUIREMENT:
The present power demand for barytes lease including the present pulverizing unit is
about 3500 KVA. After expansion, the combined power requirement for the barytes lease and
dolomite lease including the enhanced pulverizing facilities is estimated to be about 4200 KVA.
The power requirement is and will be met from the State grid and backup power from DG Sets.
Besides, Diesel pumps are also used for pumping mine pit water.
3.9 QUANTITY OF WASTES TO BE GENERATED (LIQUID & SOLID):
About 18.92 Mil.Cu.m of waste and 0.50 Mil.Cu.m of top soil is generated during the
present scheme period and 82.83 Mil.Cu.m during the conceptual period. Thus the total proposed
waste likely to be generated is 101.75 Mil.Cu.m out of which about 7.00 Mil Cu.m will be utilized
for refilling in the worked out pit over an area of 32.3315 Ha and the remaining waste of
94.75 Mil.Cu.m will be dumped over an area of 169.3049 Ha both inside (36.3691 Ha) and outside
the lease area (132.9358 Ha). Top soil will be used for afforestation purposes. Besides an area of
19.6829 Ha will form the safety zone around the dump area outside the lease where plantation,
retaining wall and garland drain will be developed. Necessary permissions/NOC from the District
collector is being obtained for utilizing outside the lease area. Most of the lands proposed outside
the lease area is already assigned to APMDC through various G.O’s and Preliminary Notification
letters.
The generation of sub-grade mineral is not anticipated from the lease area.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-36
CHAPTER – IV
SITE ANALYSIS
4.1 CONNECTIVITY:
The project area is situated 69 km north of the temple town Tirupati, in YSR district,
Andhra Pradesh. It is well connected to the nearby cities/ports by all-weather black top roads and
Rail. Kadapa-Tirupati State Highway (SH-31) passing more than 400 m east of the project site.
The nearest Rail head is Koduru on Chennai-Guntakal broad gauge section of South Central
Railway which is 9.0 km away from the project. The nearest town Koduru is 9.0 km away &
Kadapa, the district headquarters is about 80 km. The nearest Airport Tirupati is 69 km away
while the nearest port City Chennai is190 km away from the mine.
4.2 LAND FORM, LAND USE & LAND OWNERSHIP:
Out of total project area of 377.6326 Ha, lease area is 225.0139 Ha and 152.6187 Ha
outside lease area to be utilised mainly for dumping and other infrastructures. Necessary NOC
from the District collector is being obtained for land to be utilised outside the lease area.
The entire lease area of 225.0139 Ha is with APMDC. Almost the entire outside lease area
of 152.6187 Ha are private lands for which necessary NOC is being obtained. There are no forest
land in the project area.
Part of the private lands are already acquired and is in APMDC’s possession. The
remaining private lands consists of trees, bushes and some agricultural lands also. Balance
private lands are being acquired for which Preliminary notifications are also issued in many cases.
4.3 TOPOGRAPHY (ALONG WITH MAP):
The lease area is an undulating mound with altitudes varying from 180 m AMSL to 342 m
AMSL. General slope of the area is towards west. The outside lease area is more or less flat with
elevation in the range of 190 m to 220 m above AMSL.
The surface elevation of the area is shown in Figure No - 4.
4.4 PROJECT LAYOUT IN RELATION TO IMPORTANT NATURAL FEATURES:
The project area is devoid of declared ecologically sensitive features like national parks,
biospheres, sanctuaries, etc., as mentioned earlier. No forest land is involved in the lease area.
The area also does not come under CRZ category. For Index plan Refer Figure No – 6.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-37
In the 10 km buffer zone the following features are observed:
SI.No Particulars Details
1. Nearest villages Kapupalli – more than 260 m from the lease
boundary – Western direction
2. Nearest Highway Tirupathi – Kadappa Highway (SH‐31) –
more than 400 m – E
3. Nearest Railway station South Central main BG railway line
connecting Renigunta – Kadapa passess
9.0 km west of the site.
Koduru – 9.0 km, SE
4. Nearest Airport Tirupathi Airport – 69 km,
Chennai Airport – 190 km
5. Nearest water bodies Streams namely Gundala Eru – 2.2 km (S),
Mushti Eru – 5.0 km (S), Gundala Vanka – 8.0
km (SE) & Gunjana Eru – 3.1 km (SE)
confluence with Gunjana Vagu flowing 2.8 km
north. Few tanks are available in the area
which are interconnected
6. Notified Archaeologically important places,
Monuments
Nil within 10 km radius
7. Local Places of Historical and Tourism
Interest
Nil within 10 km radius
8. Environmental sensitive areas, Protected
areas as per Wildlife Protection Act, 1972
(Tiger reserve, Elephant reserve, Biospheres,
National parks, Wildlife sanctuaries,
community reserves and conservation
reserves)
Seshachalam Biosphere reserve – 10.7 km
from the lease boundary
9. Reserved / Protected Forests Seshachalam Extension RF – 7.3 km – SW,
Tunakonda RF – 7.3 km – S,
Kodur Extension RF – 6.0 km – E,
Maharajapuram Block RF – 6.8 km – NE,
Chitvel Extn. RF – 6.1 km – N.
10. Defence Installations Nil within 10km radius
11. Seismic Zone Zone – III (Moderate)
12. Other Industries in the area Many pulverizing units & Ferrro alloy plant
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-38
INDEX PLAN Figure No - 6
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-39
4.5 EXISTING INFRASTRUCTURE:
APMDC have project office, Mine site / pit office, a Guest House, Garage cum work shop,
canteen, stores, 3 nos. of pulverizing mills, VTC, First Aid Stations, Explosive Magazine,
Ammonium Nitrate storage shed, Mixing shed for Anfo , Electronic weigh bridges, Two nos. of
Diesel bunks of capacity 50 KL & 20 KL etc.
Besides, 57 nos. of different type of quarters, school, hospital, welfare centre, club etc.,
are available for residential purpose of the employees.
For the proposed expansion project all these facilities will be suitably upgraded.
4.6 SOIL CLASSIFICATION:
The texture is predominantly clayey in nature. The reaction of the soil is usually neutral.
4.7 CLIMATIC DATA FROM SECONDARY SOURCES:
The climate in & around the project area is characterized by hot summers with a maximum
temperature of 42°-45° C which lasts from March- June and mild winters with a minimum
temperature of 10°-18° C which extends from December to February.
The area received rainfall during south west and North east monsoons. The normal annual
rainfall of the Mandal varies from 750 to 850 mm. The predominant wind direction is blowing from
West, Northwest directions. The maximum wind speed recorded was 8.7 m/sec. Gusty winds and
cyclonic weather resulting from the depressions in the Bay of Bengal are not uncommon during
winter months.
4.8 SOCIAL INFRASTRUCTURE AVAILABLE:
Koduru is the nearest major human habitation (about 9.0 km from site). The area is better
developed with basic facilities. Almost all the villages in the region is well connected by road and
are electrified. Basic Medical facilities like dispensaries, hospitals, health center, public health
sub-centers etc., are available in many villages. Major medical facilities are available in Koduru,
Rajampet, Chitvel. Basic facilities namely primary, middle school to high school are available in the
entire study area. Colleges are available in Koduru, Rajampet.
* * * * * * * *
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-40
CHAPTER – V
PLANNING BRIEF
5.1 PLANNING CONCEPT:
Planning concept is based on the following criteria:
To achieve the increase in production within the existing lease area by continuing the
same opencast mining methodology, optimizing the equipment output and increasing the
size of the excavators and dumpers than increasing the fleet.
Ensuring working by surface chopping of adjacent Dolomite lease area of 114.14 Ha up to
230m RL for future expansion of this project in a phased manner.
Ensuring no major disturbance to the nearby surface water bodies and no obstruction of
water discharge to the downstream users.
Establishing the latest state of art pulverizing units within an enclosed shed with necessary
environmental control measures.
5.2 POPULATION PROJECTION:
The increase in production will marginally increase the manpower requirement both
directly and indirectly. The area in general is not densely populated and it can easily absorb the
additional increase in population due to this proposed expansion.
5.3 LAND USE PLANNING:
The land use patter at the beginning of the scheme period, end of the scheme period and
the conceptual stage is given below:
Type of land use
At the beginning of
the Scheme Period
(Ha)
At the end of the ensuing
Modified Scheme Period
(2016-17 to 2017-18) (Ha)
Conceptual
period
(Ha)
Area of excavation 114.6638 129.9588 129.9588
Storage of top soil 0.0000 0.0000 0.0000
Waste Dump 32.2370 36.3691 36.3691
Mineral Storage 14.5243 13.3213 13.3213
Infrastructure (Office
building, Rest Shelter,
workshop, canteen,
2.5117 2.5117 2.5117
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-41
magazine)
Roads 1.3265 1.9000 1.9000
Railways Nil Nil Nil
Tailing pond Nil Nil Nil
Effluent treatment plant Nil Nil Nil
Mineral Separation plant 0.7500 2.0000 2.0000
Town ship area 2.1201 2.1201 2.1201
Others (Green belt &
Safety zone) 7.5000 9.0000 15.0000
Area utilized 175.6334 197.1810 203.1810
Undisturbed area 49.3805 27.8329 21.8329
Total lease area 225.0139 225.0139 225.0139
Besides an area of 96.5667 Ha outside the lease area will be utilized for dumping.
An area of 19.6829 Ha will be left as safety zone around the dump area.
Necessary NOC from the state Government is being obtained for utilizing outside the lease
area.
Thus the project area will be 377.6326 Ha (Mining lease area – 225.0139 + dump area –
96.5667 Ha + Safety zone around dump – 19.6829 Ha Ha).
Out of the total mined out area of 129.9588 Ha, about 32.3315 Ha will be backfilled, about
74.4854 Ha will be left as water reservoir and the balance 23.1419 Ha will remain as mined
out benches.
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (PHYSICAL & SOCIAL):
SH- 31 connecting Tirupathi and Kadapa passes more than 400 m east of the lease
boundary. Since mining operations in this lease is being carried out for the last 4 decades, all the
infrastructural facilities are well established. These facilities will be suitably upgraded based on
the need. As far as social infrastructure is concerned, need based assessment of the locals will be
carried out and phase wise implementation will be carried out.
5.5 AMENITIES/FACILITIES:
All required amenities / facilities required for the mining activities like site office, rest
shelter, VTC, Canteen etc., are available at the site. These facilities will be suitably upgraded for
the expansion.
* * * * * * * *
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-42
CHAPTER – VI
PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA:
The project area does not fall in the notified industrial area.
6.2 RESIDENTIAL AREA (NON PROCESSING AREA):
There are no residential plots within the project area.
6.3 GREEN BELT:
Plantation is carried out in all possible areas like near the office, along the roads, colony,
in the safety zone etc. Green belt development / plantation will be continued and ultimately major
part of the lease area including the dump area, backfilled mine out area will be reclaimed and
developed with greenery.
6.4 SOCIAL INFRASTRUCTURE:
Good social infrastructural facility exists in the area. However, these facilities will be
suitably upgraded to meet the increased requirements.
6.5 CONNECTIVITY:
As mentioned in para 4.1, the mine is well connected with SH – 31 connecting Tirupthi and
Kadapa passing more than 400 m East of the lease area.
6.6 DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER):
Combined total water requirement for the Barytes mining project and the adjacent
Dolomite lease of APMDC is estimated to be 280 m3/day comprising 200 m3/day for dust
suppression, 25 m3/day for Green belt development and 55 m3/day for drinking & domestic
activities. The entire industrial water requirement will be met by the mine discharge water,
whereas the drinking water requirement will be sourced from the bore well within project area.
One RO plant with a treating capacity of 2000 LPH is installed by APMDC for supply of drinking
water to staff quarters, offices, canteen, Guesthouse and surrounding villages.
6.7 SEWERAGE SYSTEM:
The domestic wastewater is being passed through the soak pit. These measures will be
suitably augmented for expansion.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-43
6.8 INDUSTRIAL WASTE MANAGEMENT:
In the mining project no process effluent are generated.
6.9 SOLID WASTE MANAGEMENT:
The details of soild waste generation from the mine, and its management is given in para
3.9, Chapter – III.
6.10 POWER REQUIREMENT & SUPPLY/SOURCE:
The present power demand for barytes lease including the present pulverizing unit is
about 3500 KVA. After expansion, the combined power requirement for the barytes lease and
dolomite lease including the enhanced pulverizing facilities is estimated to be about 4200 KVA.
The power requirement is and will be met from the State grid and backup power from DG Sets.
Besides, Diesel pumps are also used for pumping mine pit water.
* * * * * * * *
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-44
CHAPTER – VII
REHABILITATION & RESETTLEMENT (R&R) PLAN
7.1 EXPANSION:
As already mentioned, the expansion will be carried out in the existing lease area only and
as such no additional area is required for mining during expansion. The entire lease area is with
APMDC land only and is presently used by APMDC. However, dumping will be carried out outside
the lease area and as such the total project area works out to 377.6326 Ha. Major part of
152.6187 Ha of land outside the lease area are private lands for which necessary NOC is being
obtained. There are no forest land in the project area.
The area outside the lease is selected after avoiding the habituated Kapupalli and Harijana
wada village on the south western side. As such there will not be any home oustees.
Part of the private lands are already acquired and is in APMDC’s possession. The
remaining private lands consists of trees, bushes and some agricultural lands also. Balance
private lands are being acquired for which Preliminary notifications are also issued in many cases.
Subsequently, some settings in the form of dwellings were created by the locals to get higher
compensation. But the issue was brought out to the revenue authorities, who made site visit and
terming those structures as illegal.
For private lands to be utilised outside the lease area, necessary NOC from the District
collector is being obtained.
7.2 EXISTING MINING OPERATIONS:
APMDC in the year 1999 submitted its requisition for acquisition of land and structures
within 300 m and later up to 500 m. At the time of acquisition of land and structures beyond 300 m
but up to 500 m, the villagers submitted a requisition to the District Collector, Kadapa not to
acquire the lands as they are being used for their livelihood and also undertaken that they will not
construct any structures beyond 300 m but up to 500 m. Accordingly, only structures were
acquired and the inhabitants of Reach-I to Reach-IV, Reach-V, Reach-X were relocated in
Rehabilitation & Resettlement centres (R&R Centres) I & II.
To accommodate the balance inhabitants of Reach-VI to IX and Reach –XI to XII, the
Corporation acquired 50 acres of land (25.05 acres in Sy.no.1095 of Mukkavaripalli Village and 30
acres in Sy.no.1/1 of Mangampet Village). The RR Centre – IV is allotted for Mangampet villagers
(Reach – V to IX) and construction of houses is going on.
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-45
7.3 FACILITIES PROVIDED UNDER R&R PACKAGES:
a. The Corporation provided employment for 237 who are falling under danger zone.
b. Payment of Rs. 53,000/- for 1448 structures and later increased to Rs. 1,00,000/-
during the meeting as announced by the Hon’ble Chief Minister on 21.04.2012.
c. The Corporation extended the payment of Rs.750/- per person per month subject to
a maximum of two persons in a family and is being continued.
d. Scholarship is also provided for all the school going children
e. Providing safe drinking water
f. In addition to the above, the Corporation extended to pay Rs.1.5 lakhs per family
who have vacated from the Danger Zone prior to the year 2007, for others who have
vacated after 2007, the Corporation has given option for Employment in the mine on
contract base or to purchase of 300 T of ‘A’ Grade subject to availability or to opt for
Rs.2.2 lakhs package.
This facility was extended to the balance 562 inhabitants who have not vacated the site.
The other benefits extended to the villagers and the amounts spent are furnished below:
Benefits extended to villagers under R&R package
Sl. No:
Package No. of
Persons availed
Amount paid to each (Rs)
Total Amount Paid in (Rs)
Nature of expenditure
1 House Construction Grant (One time)
396 100000.00 39600000.00 One time
2 House Transportation Charges (One Time)
510 10000.00 5100000.00 One time
3 Physically Handicapped persons (PHC) (Monthly)
36 750.00 27000.00 Recurring
4 Old Age Pensions (50 years above) (Monthly)
548 750.00 411000.00 Recurring
5 One Time Settlement for the displaced families who have shifted prior to October 2007. (One time)
562 150000.00 84300000.00 One time
6 Widow Pensions ( Monthly) 46 750.00 34500.00 Recurring
7 Dwcra Groups (One Time) 98 50000.00 4900000.00 One time
8 Scholarships for the year 2010-11
1st Class to 5th Class 316 1500.00 474000.00 Recurring
6th Class to 10th Class 253 2000.00 506000.00 Recurring
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-46
Intermediate 64 3000.00 192000.00 Recurring
Degree (B.Sc., B.A., B.Com.,) 24 5000.00 120000.00 Recurring
P. G. (M.Sc., M.A., M.B.A., ) 12 10000.00 120000.00 Recurring
B. Tech, M.B.B.S. 25 12000.00 300000.00 Recurring
The total employment provided on outsourcing for the beneficiaries of the danger zone is
detailed below:
Employment provided for the beneficiaries of Danger Zone
Spell Year OC BC SC ST Total
1st 2008 79 32 15 07 133
2nd 2011 166 56 24 01 247
3rd 2013 - 26 25 13 64
Total 245 114 64 21 444
7.4 PRESENT DEMANDS:
The land losers / structure losers who have vacated prior to 2007 are demanding that they
are to be paid compensation on par with those families who have evicted after 2007. Their main
contention is that by evicting premises early they helped the Corporation. Further, they are also
demanding that other benefits extended like 300 T of ‘A’ grade material supply etc. shall also be
extended to them.
It is also being represented by these PDF families that those who have evicted after 2007
have been paid Rs. 2.2 lakhs compensation and Rs. 1.10 lakhs for house construction and
transportation. The same financial package shall be extended to them also who have vacated
prior to 2007. The Corporation has agreed to enhance the compensation from Rs. 1.5 lakhs per
family to Rs. 2.2 lakhs and also agreed for other benefits excepting the supply of ‘A’ grade
material, house construction grant and transportation charges.
7.5 CONCLUSION:
This being a Government entity all the statutory rules will be followed and the locals
will be taken into confidence in this front.
* * * * * * * *
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-47
CHAPTER – VIII
PROJECT SCHEDULE & COST ESTIMATES
8.1 LIKELY DATE OF START OF CONSTRUCTION & LIKELY DATE OF COMPLETION:
This being a working mine, the envisaged expansion quantity will be achieved in a phased
manner. It is proposed to achieve the enhanced 5.0 MTPA barytes ore production in the 2nd year
after commencement of expansion activities.
8.2 ESTIMATED PROJECT COST ALONG WITH ANALYSIS IN TERMS OF ECONOMIC
VIABILITY OF THE PROJECT:
I) CAPITAL COST:
In the mining front all efforts will be made to utilize the existing machineries to the
maximum possible extent. Additional equipment’s for expansion and pulverizing plant will be met
through internal arrangements.
II) OPERATING COST (PRODUCTION COST):
The estimated production cost per MT of Barytes ore is expected to be Rs.1100 to
Rs. 1300/ per ton.
The selling price of the Barytes ore is largely dependent on the grade of the ore. Since it
can be ensured that better grade ore is consistently supplied to the customers, price at least 20%
higher than the production cost will be definitely obtained.
From the above it is clear that the project expansion is Techno economically viable
due to the following reasons:
Quality ore is available in the lease area
There is a good demand for the increased ore production
Good approach and better infrastructural facilities are already available to achieve the
expansion in shortest possible time.
Adequate project land is available.
No major social issues are anticipated.
The selling price is at least 20% more than the production cost and hence it is
economically viable.
* * * * * * * *
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-48
CHAPTER – IX
ANALYSIS OF PROPOSAL (FINAL RECOMMENDATIONS)
Financial & social benefits with special emphasis on the benefit to the local people
including tribal population, if any, in the area.
The existing mining operations in the area have already brought about positive impact
locally by way of employment generation, increase in income generation, creation of infrastructural
facility, marked improvement in the life style and living standards of the population of the
surrounding area.
There will be continued substantial improvement in case of local population in living
standards, receipt of per capita income, cultural patterns, living styles, educational standards, etc.
after expansion also.
As already mentioned earlier, the project will improve the social and physical infrastructural
patterns of this interior area in its own way resulting in overall improvement of HDI (Human
Development Index). Besides, the Central and State Government will also derive good financial
benefits by way of receipt of taxes, duties and cess.
In view of above aspects of the project, the project can be said to be beneficial to the local
community, the local region, the State and to the entire country on the whole.
* * * * * * * *
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-49
ANNEXURE – 1
LEASE AREA - GO COPY (G.O.MS.NO. 126)
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-50
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-51
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-52
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-53
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-54
ANNEXURE – 2
MINING SCHEME FOR BARYTES OVER AN EXTENT OF 223.310 HA
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-55
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-56
ANNEXURE – 3
ENVIRONMENTAL CLEARANCE FROM MOEF FOR EXPANSION OF
MANGAMPET BARYTES MINE
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-57
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-58
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-59
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-60
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-61
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-62
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-63
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-64
ANNEXURE – 4
COMBINED CONSENT UNDER WATER ACT, AIR ACT AND AUTHORIZATION
UNDER HAZARDOUS WASTE RULES OBTAINED FROM APPCB
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-65
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-66
BRIEF SUMMARY FOR MANGAMPET BARYTES PROJECT OF M/S. APMDC LIMITED - EXPANSION OF BARYTES PRODUCTION CAPACITY FROM 3.0 MTPA TO 5.0 MTPA AND INCREASING PULVERIZING UNIT CAPACITY FROM 0.1 TO 0.3 MTPA.
Creative Engineers & Consultants, Chennai – 600 059 F-67