FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA...

35
FCPS Liberty Elementary School Feasibility Study Meeting #6 – Notes PAA Project #18‐35 Meeting Date: February 14, 2019 – FCPS Central Office Board Room Meeting started at 2:00 pm Meeting ended at 3:20 pm Attendees: FCPS Educational Planning Team Holly Nelson – FCPS Facilities Planner Adnan Mamoon – FCPS Director of Capital Programs Kim Day – FCPS Curriculum & Instruction Steve Raff – FCPS Elementary Director Dawn Worrell – FCPS Construction Accountant Patrick Little – FCPS Maintenance Design Team Kori Purdum Matheis – Proffitt & Associates – Principal Architect Madalyn Burns – Proffitt & Associates – Senior Architectural Designer Meeting Discussion: 6.1 Project Overview A. Schedule – Kori provide an update on the schedule, we are on track for completion of the draft study booklet by March 14. B. ALTA Survey Status – Survey should be complete by late February, weather permitting. 6.2 Review updated conceptual design options and proposed phasing of construction A. Option 1 ‐ Renovations and Additions with partial demolition 1. In this option: a. Construction phasing was proposed as follows: Phase 1 ‐ Existing building and driveways would remain in use. Construction of new bus loop from Daysville Road. Phase 2 ‐ New bus loop from Daysville Road completed and in use. Existing building and Route 26 driveway would remain in use. Demolish

Transcript of FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA...

Page 1: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

 

 

FCPS Liberty Elementary School  Feasibility Study Meeting #6 – Notes PAA Project #18‐35   Meeting Date: February 14, 2019 – FCPS Central Office Board Room Meeting started at 2:00 pm  Meeting ended at 3:20 pm  Attendees: FCPS Educational Planning Team Holly Nelson – FCPS Facilities Planner  Adnan Mamoon – FCPS Director of Capital Programs Kim Day – FCPS Curriculum & Instruction  Steve Raff – FCPS Elementary Director Dawn Worrell – FCPS Construction Accountant Patrick Little – FCPS Maintenance  Design Team Kori Purdum Matheis – Proffitt & Associates – Principal Architect Madalyn Burns – Proffitt & Associates – Senior Architectural Designer   

Meeting Discussion:  6.1 Project Overview 

A. Schedule – Kori provide an update on the schedule, we are on track for completion of the draft study booklet by March 14.  

B. ALTA Survey Status – Survey should be complete by late February, weather permitting.  

6.2 Review updated conceptual design options and proposed phasing of construction A. Option 1 ‐ Renovations and Additions with partial demolition 

1. In this option: a. Construction phasing was proposed as follows: 

Phase 1 ‐  Existing building and driveways would remain in use. Construction of new bus loop from Daysville Road. 

Phase 2 ‐  New  bus  loop  from Daysville  Road  completed  and  in  use.  Existing building  and  Route  26  driveway  would  remain  in  use.  Demolish 

Page 2: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

Feasibility Study Meeting #6 – Notes Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 2 of 6  

portion of existing Daysville driveway and existing bus loop/parking. Construction  of  north  addition,  soft  and  paved  play  areas,  and building services driveway.  

Phase 3 ‐  North  addition,  play  areas,  and  building  services  driveway  are completed  and  ready  to  use.  The  north  addition  includes  a  public entrance,  Gymnasium,  Cafeteria,  food  services,  building  services, music classrooms and a classroom cluster. Existing Route 26 driveway would remain in use. All of existing 1960s building and north portion of  existing  1980s  building  retained  and  in  use.  Demolish  south portion of 1980s building  (Media Center plus  two classrooms) and entirety of 1950s building.  

Phase 4 ‐  Demolish Route 26 driveway. Construction of south addition, pre‐k play area, and car/parking loop from Route 26.  

Final ‐   South addition, pre‐k play and car/parking loop from Route 26 are all complete and ready for use. South addition includes the new entry, media center, kindergarten classrooms, art classrooms and support spaces. 

2. Changes from previous meeting: a. Added secondary entrance/exit from car loop to Daysville Road.  b. Removed softball field and replaced with open green space. 

3. Pros for this layout include: a. Classroom layouts cluster well for grade level grouping. b. Simplified floor elevations compared to Option 2 – only one level at first floor, 

two levels for second floor. c. Additions  envelop  the  existing  building  –  will  allow  for  a  new  unified  façade 

design, visible from both roads. d. Good separation of buses, cars, and building services/loading. e. Lots of car queuing space. 

4. Cons/action items for this layout include a. Keeping existing 1960s two‐story addition and tying the new two‐story structures 

into it may create a hardship in terms of ceiling height. Ramping will be required along the second‐floor corridor in order to provide greater floor‐to‐floor height at the addition than in the existing building. 

b. Green space is far from the school and is awkward to have to access via narrow space between bus loop and drop‐off loop. 

c. The Media Center and many support spaces do not have access to views to the exterior. Daylight could still be incorporated via clerestory windows however. 

d. Car queuing will block parking.  

B. Option 2 ‐ Renovations and Additions with limited demolition 1. In this option: 

a. Construction phasing would be as follows: Phase 1  ‐ Existing 1950s and 1980s portion of building and driveways would 

remain  in  use.  Construction of  new bus  loop  from Daysville  Road. 

Page 3: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

Feasibility Study Meeting #6 – Notes Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 3 of 6  

Demolish existing 1960s portion in its entirety. Minor modification to the existing Daysville driveway/bus loop will be required in order to complete this phase. 

Phase 2 ‐  New bus loop from Daysville Road complete and ready to use. Portion of  existing  building  and  Route  26  driveway  would  remain  in  use. Demolish Daysville driveway/bus loop. Construction of east addition, soft and paved play areas, and building services driveway.  

Phase 3 ‐  East addition, play areas and building services driveway complete and ready to use. East addition includes a public entrance, Gymnasium, Cafeteria,  food  services,  building  services,  music,  and  a  two‐story addition with  kindergarten  classrooms  and  support  spaces  on  the lower  level  and  new  classrooms  and  support  spaces  on  the main level. Renovation of existing gymnasium and cafeteria. Existing Route 26 driveway would be demolished. Construction of drop‐off/parking loop from Route 26. 

Phase 4 ‐  Drop‐off/parking loop from Route 26 is complete and ready to use.  Existing gymnasium has been renovated and is ready to occupy as a new media  center.  The existing  cafeteria has  been  converted  to  a new  administration  suite  and  is  ready  to  occupy.  Renovation  of existing administration and media center spaces occurs once these functions can move into their newly renovated areas. 

Final ‐  Renovations  of  the  existing  administration  suite  to  serve  as  new classrooms and support spaces and existing media center to be new art classrooms are completed and ready to occupy. 

2. Changes from previous meeting: a. Added secondary entrance/exit from car loop to Daysville Road.  b. Relocated bus loop, paved and soft play areas.  c. Removed softball field and replaced with open green space. 

3. Pros for this layout include: a. Good separation of buses and cars. b. Lots of car queuing space. c. More open green space/play area compared to Option 1. d. Retains more of existing recently replaced roof. 

4. Cons/action items for this layout include a. Administration  suite  and  new main  entrance  on  lower  level  are  not  desirable 

because of separation from other spaces and low ceiling heights. b. Possible  conflicts  for  construction  of  east  classroom  addition  if  the  existing 

foundations  from  the  1920s  building  were  not  fully  demolished.  Possibly additional costs for hazardous material abatement. 

c. Lots of changes in elevation on main level, three ramps in both of the corridors.  d. More of the existing building façade to remain and require upgrades.  e. Kindergarten and Pre‐K are on a different floor level than gymnasium, cafeteria, 

and specials.  f. Car queuing will block parking. 

Page 4: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

Feasibility Study Meeting #6 – Notes Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6  

 C. Option 3A ‐ New construction 

1. In this option: a. The proposed school is similar to the footprint of the future elementary school 

prototype (East County Elementary).  b. The new facility is sited so that it can be constructed while the existing building 

remains  operational,  then  once  it  is  occupied,  the  existing  building  can  be demolished. 

c. The main  entry wing with  administration  and  art  classrooms  is  located  to  the north east and faces Route 26. The two‐story classroom wings are located to the south. The public spaces including, music, cafeteria and gymnasium are located to the north west. 

d. Car rider drop off loop and main parking would be accessed from Route 26. The driveway entrance is relocated to the crest of the hill along Route 26 for better visibility.  

e. Bus  loop,  additional  parking  and  building  services  would  be  accessed  from Daysville Road.  

f. Paved and soft play areas are located near the gymnasium and cafeteria.  2. Changes from previous meeting: 

a. Flip administration wing with classroom wing.  b. Relocated bus and car loop. c. Reconfigured paved and soft play areas.  d. Removed softball field and replaced with open green space. 

3. Pros of this layout include: a. New  school  can  be  constructed  without  demolition  of  the  existing  building. 

Seems  like  a  cheaper  option  compared  to  occupied  construction.  All  students remain on site. 

b. Daylight provided to all classrooms.  c. Good separation of buses, cars, and building services/loading. d. Lots of car queuing space.  e. Parking and bus drop off are both close to the main entry. 

4. Cons/action items for this layout include: a. Least amount of open green space b. Not possible to bring second entrance/exit from Daysville Road due to position of 

building. c. Car traffic onto Route 26. d. Car queuing will block parking. 

 D. Option 3B ‐ New construction 

1. In this option: a. The proposed school is similar to the footprint of the future elementary school 

prototype (East County Elementary).  b. The new facility is sited so that the existing building will be demolished and then 

the new school is constructed. 

Page 5: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

Feasibility Study Meeting #6 – Notes Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 5 of 6  

c. The main  entry wing with  administration  and  art  classrooms  is  located  to  the south west and faces Route 26. The two‐story classroom wings are located to the east. The public spaces including, music, cafeteria and gymnasium are located to the north west. 

d. Car rider drop off loop and main parking would be accessed from Daysville.  e. Bus loop, additional parking and building services would be accessed from Route 

26.  f. Paved and soft play areas and softball fields are located near the gymnasium and 

cafeteria.  2. Changes from previous meeting: 

e. Flip administration wing with classroom wing.  f. Removed softball field and replaced with open green space. 

3. Pros of this layout include: a. Demolition of existing building prior to starting construction of the new building 

allows building to be pulled closer to Rt 26 and preserves more open green space along Daysville. 

b. Daylight provided to all classrooms.  c. Good separation of buses, cars, and building services/loading. d. Lots of car queuing space. 

4. Cons/action items for this layout include: a. Students will either have to be relocated to another facility off‐site or portables 

will need to be brought on‐site to house students during the demolition and new construction process.  

b. Bus traffic in and out on 26 may not be feasible. Look at an option showing cars and buses enter from Daysville then split on site. 

c. Car queuing will block parking. d. Visitor parking is on the opposite side of the building from the main entry – this 

doesn’t  work  from  a  security  standpoint,  buses  and  visitor  parking  should  be switched. 

 E. General discussion during review of options: 

1. Reviewed  schools  with  similar  occupied  renovations  and  phasing  where  students remained  on  site.  Similar  FCPS  schools  include  West  Frederick  Middle,  Brunswick Middle, Thurmont Middle, and Waverley Elementary. Will need to consider risks, costs and challenges.  

2. Holly will get feedback from the Director of Transportation about bringing bus traffic in and out on Route 26.  

3. For  option  3B,  price  for  having  portables  on  site.  Gymnasium  could  be  in  a  tent structure. Cafeterias could be compromised of multiple portables, or students could eat lunch in their classrooms.  

4. For final presentation, give detailed scheduling information ‐ i.e. construct parking loop during the summer, hold for six months than commence demolition/construction the next summer. 

Page 6: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

Feasibility Study Meeting #6 – Notes Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 6 of 6  

5. The existing building will require significant upgrades include all new door hardware, plumbing fixtures and accessible restrooms, etc.  

6. Signage and building elevation/features can be used to distinguish main entry. 7. Steve is adamantly against moving kids off site (because this elementary school has the 

largest  feeder  area)  or  using  temporary  facilities  because  they  will  be  tough  sells. Prefers all elementary grades under one roof rather than the idea of having a separate primary facility.  

6.3 Recap feedback from Community Meeting #2 A. There were mixed responses from the Community. Generally liked the idea of salvaging the 

existing building but not the final results or retaining the existing spaces. Concerned of length of  construction  time/phasing  and  impact  for  students. Want  to  pay homage  to  history  of Liberty similar to the Linganore High School vestibule.  

B. There was  concern  about  relocating  the  students  because  of  transportation  distance  and possibly students being separated.  

C. Holly would like to ask teachers and students for additional input.   

6.4 Discuss materials and systems for proposed construction A. To begin preparing cost estimates we will move forward with additions/new construction 

will be steel frame with masonry exterior and a mix of masonry and gypsum board interiors.   

6.5 Two week look‐ahead A. The design team will continue working on the ALTA survey, modification of sketch options of 

the replacement, additions/renovations options, and prepare cost estimates to share at the 

next meeting. 

The next regular design team meeting has been rescheduled for Friday, March 8, 2019 from 10:00 AM – 12:00 PM at Liberty Elementary School.  This  summarizes  the  topics  discussed  at  the meeting.  Please  review  and  address  any  comments  and corrections to the Architect within 5 days of receipt of these minutes.  

Kori Purdum Matheis, AIA, LEED AP BD+C  Distribution via email – all attendees & design committee members  Attachments:   

Meeting #6 Presentation Slides 

Page 7: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

L I B E R T Y E L E M E N TA RY S C H O O LF E A S I B I L I T Y S T U D YF R E D E R I C K C O U N T Y P U B L I C S C H O O L S

F E A S I B I L I T Y S T U D Y M E E T I N G # 6F e b r u a r y 1 4 , 2 0 1 9

Page 8: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

AGENDA

MEETING TOPICS:1. Project Overview

a. Scheduleb. ALTA Survey Status

2. Review updated conceptual design options and proposed phasing of construction

a. Renovations and Additions with partial demolitionb. Renovations and Additions with limited demolitionc. New Constructiond. Discuss pros/cons of each – which goals are addressed and which are not?

3. Recap feedback from Community Meeting #24. Discuss materials and systems for proposed construction

Page 9: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

P R O J E C T S C H E D U L E

Page 10: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

EXISTING FLOOR PLAN

M A I N L E V E L I S A P P R O X . 2 8 , 5 0 0 G S F

3

3

K

K

2 2

1

1

55

4

4

YM

CA

MU

SIC

SP

EC

.E

D.

AR

T

E X I S T I N G C O N D I T I O N S

Page 11: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

SITE AERIAL PHOTO

E X I S T I N G C O N D I T I O N S

Page 12: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

FEASIBILITY STUDY OPTIONS

P R O J E C T A P P R O A C H

Option 1 Option 2 Option 3A

New Construction –Replacement

Construction of an entirely new facility on

the existing site to meet the Ed. Spec.

requirements and then demolition of the entire

existing building.

Option 3B

New Construction –Replacement

Demolition of the entire existing building prior to

construction of an entirely new facility on

the existing site to meet the Ed. Spec. requirements.

Renovation and additions with partial

demolition

Complete renovation of the existing facility to remain, demolition of

over half of the existing building, and

construction of additional space to meet the Ed. Spec. requirements.

Renovation and additions with limited

demolition

Complete renovation of the existing facility to

remain, demolition of a limited portion of the existing building, and

construction of additional space to meet the Ed. Spec. requirements.

Page 13: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #1PHASE 1

C O N C E P T S I T E P L A N

Page 14: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #1PHASE 2

C O N C E P T S I T E P L A N

Page 15: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #1PHASE 3

C O N C E P T S I T E P L A N

Page 16: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #1PHASE 4

C O N C E P T S I T E P L A N

Page 17: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #1PHASE 5

C O N C E P T S I T E P L A N

Page 18: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #1FLOOR PLANS

C O N C E P T F L O O R P L A N

BASE BID

L O W E R L E V E L

U P P E R L E V E L

Page 19: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #1FLOOR PLANS

C O N C E P T F L O O R P L A N

L O W E R L E V E L

U P P E R L E V E L

FUTURE EXPANSION

Page 20: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #2PHASE 1

C O N C E P T S I T E P L A N

Page 21: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #2PHASE 2

C O N C E P T S I T E P L A N

Page 22: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #2PHASE 3

C O N C E P T S I T E P L A N

Page 23: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #2PHASE 4

C O N C E P T S I T E P L A N

Page 24: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #2PHASE 5

C O N C E P T S I T E P L A N

Page 25: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

ADDITION / RENOVATION OPTION #2FLOOR PLANS

C O N C E P T F L O O R P L A N

L O W E R L E V E L

U P P E R L E V E L

BASE BID

Page 26: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

FUTURE EXPANSION

ADDITION / RENOVATION OPTION #2FLOOR PLANS

C O N C E P T F L O O R P L A N

L O W E R L E V E L

U P P E R L E V E L

Page 27: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

REPLACEMENT OPTION #3APHASE 1

C O N C E P T S I T E P L A N

Page 28: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

REPLACEMENT OPTION #3APHASE 2

C O N C E P T S I T E P L A N

Page 29: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

REPLACEMENT OPTION #3BPHASE 1

C O N C E P T S I T E P L A N

Page 30: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

REPLACEMENT OPTION #3BPHASE 2

C O N C E P T S I T E P L A N

Page 31: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

REPLACEMENT OPTION #3A & 3BFLOOR PLANS

C O N C E P T F L O O R P L A N

L O W E R L E V E L

U P P E R L E V E L

Page 32: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

C O M M U N I T Y M E E T I N G # 2Q U E S T I O N S & C O M M E N T S

• Which options are cheapest/quickest/easiest for construction and students?• Will have more cost information at the meeting next month. Options 1 & 2 will require

large amount of upgrades, phasing and longer construction. • Plans for where students would go during construction (3A & 3B)? Will students be split up

similar to Linganore?• Temporary modular classrooms and/or busing elsewhere. Students stay together.

• Are 3D renderings available?• No – more detailed drawings in the design phase

• Any reason why strange shapes/angles/not compact?• We try to match existing circulation/provide daylight/site constraints and

setbacks/classroom clusters• Will the memorials (i.e. trees, historic photographs, and gravestones) be preserved?

• Yes – memorials can be relocated and design can include displays for history.• Will the new school include elevators and be accessible?

• Yes – all options will require modernizing for accessibility.• Can options 3A and 3B include two access points like Options 1 and 2? Can cars and

buses enter in the same way then separate to loops?• We most likely can not fit a cut thru but can possibly connect the bus and car loops.

Page 33: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

Option 1 & 2 Pros• Saving some existing portions• Kids less interrupted• Two access routes for parents

Option 1 & 2 Cons• Two access routes could be used as a

pass thru for non-school vehicles –gates?

C O M M U N I T Y M E E T I N G # 2F E E D B A C K

Page 34: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

Option 3A Pros• Quicker construction• Students stay on site and together• Drawn to newer building – seems

easier and quicker than renovations and phasing

Option 3A Cons• Less green space• Would a traffic director be needed for

the bus entrance/exit on 26?

C O M M U N I T Y M E E T I N G # 2F E E D B A C K

Page 35: FCPS Liberty Elementary School Feasibility Study …...2019/02/14  · Liberty Elementary School PAA Project #18‐35 February 14, 2019 Page 4 of 6 C. Option 3A ‐ New construction

Option 3B Pros• Quicker construction• Drawn to newer building – seems

easier and quicker than renovations and phasing

Option 3B Cons• Less green space• Inconvenient for kids and parents to

relocate temporarily• All kids must be kept together if this

option is chosen • Would a traffic director be needed for

the bus entrance/exit on 26?

C O M M U N I T Y M E E T I N G # 2F E E D B A C K