FCCURa tor V s ructural R air Utilizing tomat˘ W d Metal Ovlay · 1 Pedro ador VP hie Technologˇ...

22
www.azz.com 1 Pedro Amador VP & Chief Technology Officer – AZZIncorporated FCCURegenerator Vessel Structural Repair Utilizing Automated Weld Metal Overlay 29 Sept – 3 Oct 2014 RIO DE JANEIRO

Transcript of FCCURa tor V s ructural R air Utilizing tomat˘ W d Metal Ovlay · 1 Pedro ador VP hie Technologˇ...

www.azz.com 1

Pedro Amador

VP & Chief Technology Officer – AZZ Incorporated

FCCU Regenerator Vessel Structural Repair

Utilizing Automated Weld Metal Overlay

29 Sept – 3 Oct 2014

RIO DE JANEIRO

www.azz.com 2

Topics

Background of Structural Weld Overlay Repairs with Automated Welding

• Engineered Repair History

• Automated Welding Enablers

• The Temperbead Process

• Early Use examples in Refinery Applications

FCCU Regenerator Vessel Repair

• Problem Introduction and Refinery Decision Points

• Description of Vessel Condition

• Analytical Support for Structural Overlay Repair Option

• Field Implementation of Repair

Summary of Results

www.azz.com 3

Industry experience

Initial uses of “Engineered Structural Overlay” weld repairs were in the nuclear industry

in the 1990’s.

• Primary Piping to Vessel Connections

• Highly stressed weld joints

• Corrosive environment created SCC conditions

• Common in BWR and PWR designs

www.azz.com 4

Industry experience

• Structural WOL process patented

• Residual stresses from welding were used to generate compressive stresses at the

joint area

• Added strength of deposit provided a redundant repair

• Over 1,000 nuclear applications performed throughout the world

Welded Structural Overlay Being Applied Cross Section – Stress Analysis Model of Nozzle

Nozzle

Piping

Affected Weld

Simulated Crack

Structural

Overlay

www.azz.com 5

Industry experience

Early Application in Refinery

Pressure Vessel Example

• FCCU stripper/reactor

• High temperature creep failure

• 5 Year life extension required

Anticipated Design Repair

• Model existing failure condition

• Develop “Engineered Design Repair”

to manage stress levels below creep

failure limits

• Perform level 3 FFS analysis

Engineered Design Repair

• Reduced scope of work

• Reduced cost for repair

• Provided Validation of repair lifetime FCCU Stripper/Reactor failure area

www.azz.com 6

Industry experience

Engineered Repair Design

Areas Exceeding Creep Stress Limit

Engineered Structural Overlay

Post Overlay Stress Gradients

Estimated Life of Repair

Well in Excess of 5 Years

Regions below

temperature

threshold for

creep

www.azz.com 7

Industry experience

Automated Welding Enablers

Automated Control of Welding Parameters

• All welding parameters are controlled through automation

• Resulting heat input is predictable and

homogeneous throughout the deposit

• Resulting mechanical properties and residual

stresses are predictable

Capabilities Enabled by Predictable Properties

• Accurate and homogeneous mechanical

properties available for analysis

• Predictable quality of deposited weld metal

• Parameter control allows the use of

the temperbead process

• Minimization of distortion caused by welding

• Minimization of dilution of deposited metal

Automated Welding System

Applying Inconel 625 in Pressure Vessel

www.azz.com 8

Industry experience

The Temperbead Process

Can be used as an alternative to post weld heat treating

Ideal for large overlays on pressure vessels

HAZ created by 1st weld layer

HAZ is tempered by

deposition of successive

layers

www.azz.com 9

Structural Overlay Repair of FCCU

Regenerator Vessel

www.azz.com 10

Structural Overlay Repair of FCCU Regenerator Vessel

• Refinery Located in Barrancabermeja, Colombia

• Two small leaks detected in April 2013

• Leak Areas repaired using external window patches

• May of 2013 UT mapping indicated significant loss of wall thickness in the cone to

cylinder transition of the vessel

• Several repair options were evaluated:

Option Implementation

Schedule

Repair

Complexity

Repair Integrity

Window Replacement Long High (internals) High

Window Patches Medium Low Medium-Low

Structural Overlay Short Low High

www.azz.com 11

Structural Overlay Repair of FCCU Regenerator Vessel

• The FCCU is critical to the overall refinery capacity

• This refinery provides the majority of fuels for Colombia

• Structural overlay was selected because of short implementation schedule and same

or better repair life when compared to other options

Technical Concerns

• Given the thin remaining wall, can overlay be applied without causing excessive

vessel distortion?

• Will the applied overlay meet the structural stability requirements per API 579-1 FFS

Assessment?

www.azz.com 12

Structural Overlay Repair of FCCU Regenerator Vessel

www.azz.com 13

As Found Wall Thickness

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 # 55 56 57 58 59 60 61 62 63 64 65 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81

A

B

C

D

E

F

West North East South West

Radial Location

Above Required Acceptable

MarginalBelow Min Wall

Nozzle

Reinforcement

Areas

Lowest thickness

location

.192” (4.9mm)

Original Thickness

Cone = Approx 1.1” (28mm)

Shell = Approx 0.8” (21mm)

Marginal Thickness

Less than 0.7” (17.8mm)

C

o

n

e

www.azz.com 14

Structural Overlay Repair of FCCU Regenerator Vessel

Failed weld allowed

an opening to form

Significant wall

thickness loss

experienced

Significant ID wall

thickness loss

experienced

www.azz.com 15

Structural Overlay Repair of FCCU Regenerator Vessel

Thermal Image and

Photo of leak

location

Thermal Image and

Photo of leak

location

www.azz.com 16

Overlay Design

Two engineering efforts were performed to design and qualify the structural overlay:

1. Predictive Numerical Distortion Analysis

• Large areas of the as-found vessel are critically thin

• Since all weld overlays cause some distortion an analysis was performed to

ensure that distortion experienced would not affect the vessel internals and

that the vessel would meet the code required Out-of-Roundness UG-80

criteria.

2. Assessment of Structural Stability

• This analysis determined that structural integrity of the vessel would be

achieved by the application of a structural overlay to restore the loss of

thickness.

• A FFS evaluation was performed in accordance with API579-1 / ASME FSS-1

• All dead weight, product weight, environmental loadings and seismic loads

were taken into account.

• Vessel was analyzed including the predicted distortions caused by the overlay

developed in the No. 1 analysis above.

www.azz.com 17

Overlay Design

Weld Overlay Design

Platform was removed

for overlay installation

www.azz.com 18

Overlay Design

Predicted Layer 1 Distortion Predicted Layer 3 Distortion

www.azz.com 19

Overlay Design

Shaded Plot of Vessel Predicted Plastic

Collapse Load - Operation after Repair

No Plastic

FFS Criteria

No Plastic

collapse of the

vessel occurs

from the

identified load

case.

Meets API 579

FFS Criteria

www.azz.com 20

Three Layer Structural Overlay

Finished Structural Overlay

(three layers)

www.azz.com 21

Summary

Results

• Structural Overlay was utilized to repair significant pressure vessel wall thinning.

• A proprietary predictive numerical distortion analysis was used to determine

viability of repair prior to implementation.

• A Fitness for Service analysis was performed per API 579 to qualify the repair.

• Project was performed ahead of estimated schedule with zero safety incidents.

• Project was completed below initial estimated cost.

www.azz.com 22

Contact

Contact Information

Pedro Amador

VP & Chief Technology Officer

[email protected]

+ 1 (678) 728-9100

Norcross, GA, USA