Fault Tree Analysis
description
Transcript of Fault Tree Analysis
Fault Tree Analysis
Part 2: Problem Definition and Heuristic Guidelines for Fault Tree
Synthesis
FTA Procedure
• Problem Definition
• Fault Tree Synthesis
• Solution - Minimal Cut Sets
• Probability Calculation
Step 1: PROBLEM DEFINITION
• TOP Event
• Boundary Conditions
- unallowed events (impossible events)
- existing events (certain events)
- system physical bounds
- level of resolution
- other assumptions , e. g. Initial conditions.
E M
COOLING WATER EMERGENCYHEAD TANK
Step 2: FAULT TREE SYNTHESIS
REACTANT YREACTANT X
COOLING WATER
OUT
COOLING WATER
IN
COOLING WATER
SUPPLY PUMPPUMP X
LOSS OFREACTION CONTROL (A+B+C)+(B+D+E)+(B+F).G
OR
LOSS OFAGITATION
SUPPLY OF REACTANTX STOPS
LOSS OF COOLINGON JACKET
OR OR AND(A+B+C) (B+D+E) (B+F).G
PUMP XFAILS
OPERATORERROR
FAILURE OFPOWER SUPPLY
AGITATORMECHANICAL
FAILURE
FAILURE OFWAWER SUPPLYFAILS
EMERGENCYSUPPLYFROM
HEAD TANKFAILS
OR
PUMP XMACHANICAL
FAILURE
FAILURE OFPOWER SUPPLY
OPERATORERROR
FAILURE OFPOWER SUPPLY
WATER PUMPMECHANICAL
FAILURE
B FDBA
C B EGOR
(A+B) (B+F)
HEURISTIC GUIDELINES
1) Replace an abstract event by a less abstract event.
Loss of Cooling water
No Water from Pump
2) Classify an event into more elementary events.
Tank Explosion
OR
Explosion Explosion by by Overfilling Runaway Reaction
HEURISTIC GUIDELINES
3) Identify distinct causes for an event.
Runaway Reaction
OR
Excessive Loss of Feed Cooling
4) Couple trigger event with “no protective action”.
Overheating
AND
Loss of No System Cooling shutdown Water
HEURISTIC GUIDELINES
5) Find cooperative causes for an event.
Fire
AND
Leak of Source of Flammable Fluid Sparks
6) Pinpoint a component failure event.
No Cooling Water
AND
Main Valve Bypass Valve is Closed isn’t Opened
Note, 1) - 6) are state-of-system events.
Component failure(state-of-component event)
CommandfaultPrimary
failure Secondaryfailure
7) Develop a component failure using Fig. 2.22
State-of-system event
Figure 2.22. Development of a component failure (state-of-component event).
Example - The Process
This example shows how the heuristic guidelines can be used to construct fault trees.
In the pumping system shown in the next page, the tank is filled in 10 min and empties in the next 50 minutes; thus, the cycle time is 1 hr. After the switch is closed, the timer is set to open the contacts in 10 min. If the mechanisms fail, then the alarm horn sounds and the operator opens the switch to prevent a tank rupture due to overfilling.
Timer
PumpTank
Horn
Switch
Powersupply
Contacts
Operator
Schematic diagram for a pumping system.
Example - The Fault Tree
A fault tree with the top event of “tank rupture (at time t)” is shown in the next page.
This tree shows which guidelines are used to develop events in the tree.
Operator Failures
The operator in this example can be regarded as a system component, and the gate E is developed by using the guidelines of Fig. 2.22.
A primary operator failure means that the operator functioning within the design envelope fails to push the panic button when the alarm sounds.
The secondary operator failure is, for example, “operator has been killed by a fire when the alarm sounded.” The command fault for the operator is “no alarm sounds.”
Lambert, H. E. , “System Safety Analysis and Fault Tree Analysis,” UCID-16238, 31, May 9, 1973
Expect no miracles; if the “normal” functioning of a component helps to propagate a fault sequence, it must be assumed that the component functions “normally.”
Write complete, detailed fault statements.
Avoid direct gate-to-gate relationships.
Think locally. Always complete the inputs to the gate.
Include notes on the side of the fault tree to explain assumptions not explicit in the fault statements.
Repeat fault statements on both sides of the transfer symbols.
Example
The following figure shows a reaction system in which the temperature increases with the feed rate of flow-controlled stream D.
Heat is removed by water circulation through an exchanger.
Normal reactor temperature is 200 F, but a catastrophic runaway will start if the reactor temperature reaches 300 F.
Example
In view of this situation, 1. The reactor temperature is monitored;2. Rising temperature is alarmed at 225 F (see
horn);3. An interlock shuts off stream D at 250 F,
stopping the reaction (see solenoid and valve A);
4. The operator can initiate the interlock by pushing the panic button.
Assumptions
• Secondary failures are neglected.
• The alarm signal always reaches the operator whenever the horn sounds