FARDOG 04JAN01
description
Transcript of FARDOG 04JAN01
D. Finley / Fermilab FARDOG / January 4, 2001 1
fFARDOG 04JAN01
• Discussion of FY01 Budget and Goals for RF Structures
D. Finley / Fermilab FARDOG / January 4, 2001 2
fFY01 LC R&D Goals / Technical Division
• RF Structure Factory• Make first Fermilab Xband structure
• By about mid-March01 or so (we hope)• (See below also)
• Occupy IB4 SW Corner• Finish RF QC Lab
• Need expertise from BD and TD• Using expertise from INR Collaboration (see
later slide)• Now have BD Network Analyzer from BD
(Thanks, John)• Need a second NA bySEP01 (Peter?)
• Get first furnace operating• Full Size Furnace by SEP01 (we hope)• Baby Furnace (~120K$) by APR01
• Magnets• Finish four prototypes• Measure with mostly existing equipment• Take over some motion control
development• Understand beam alignment
requirements
• Collaboration High Gradient Tests• Have made, now send, 20 disks to
SLAC• First, we do RF QA on them• SLAC provides couplers etc and
assembles into a complete structure• “Same as” SLAC / Robertson model
• Make two entire “20 cell” structures• aka “1st Fermilab Xband structures”• To get on SLAC “High Power Testing”
List, need to “Show me the structure!”
• IB5 CDR w/ FESS• $25K from RAT, $25K from TD• Assembly Line for beam line units• Not necessarily “NLC Project” building
… could instead be for additional space needed for ongoing TD activities
D. Finley / Fermilab FARDOG / January 4, 2001 3
fIndustrial Building 4 (IB4)
Notes:
1. Southwest Corner is lower right of picture
2. RF structure work
- Uses all of SW corner (2 clean rooms, rf lab, work area, furnace area)
- Shares QC Laboratory for mechanical QC
- Shares Machine Shop
3. This is not an optimum arrangement for the work flow for making structures
4. “Beam Line Unit” Assembly area would occupy most (if not all) of IB4
D. Finley / Fermilab FARDOG / January 4, 2001 4
fIB4 SW Corner
Note: Furnace area is large enough for baby furnace … full size furnace is mounted over Clean Room B (the one on the left)
Copper parts go in … structures come out
D. Finley / Fermilab FARDOG / January 4, 2001 5
fINR Collaboration (Troitsk, Russia)
• Reference: Finley to Yarba 12/20/00 email “INR and TD”
• Item 1: In support of the RF QC Lab
• Gennady Romanov (TD Guest) coordinating the setting up of the RF QC Lab
• with Ding Sun (BD), Tug Arkan, Brian Smith, Evgueni Borissov(TD)
• What is to be done in IB4?• Short stack and full length structure
measurements• plunger and bead pull techniques
• FY01 New Guests• Gonin: rf calculations to help
understand measurements• Khabibulin: improve throughput (aka
automation)• 3rd person: Brazing
• Small piece of hardware from INR
• Item 2: In support of understanding structure vacuum
• To be done at INR• Develop realistic and useful
computer codes• Start with 1.8 meter RDDS as
specific example at appropriate level of detail
• Example: Model the time development of the vacuum after a discharge and outgassing
• How fast does the gas move?• Which direction?• How long does it take to pump
down so that processing can continue?
D. Finley / Fermilab FARDOG / January 4, 2001 6
fFY01 LC R&D Goals for TD / Background
• Budget $1.3M• Top Down (see slide from LaDaune T.)
• Magnets (MAT)• $195K Salaries, $70K M&S
• RF Structures (RAT)• $540K Salaries, $495K M&S
• Sum• $735K Salaries, $565K M&S
• Caution: November 2000 obligations already close to linear budget for FY01 …
• Develop funding “understandings”
• ~100K$ TD Equipment for Baby Furnace• “Small%” FTEs not charged to LC R&D?
• Have made no changes in TD reporting yet, small changes might be needed.
• ~$75K TD Equipment for 2nd Network Analyzer
• ~$600K Full Size Furnace - NIU funds
• Update multi-year plan• Integrate into SLAC tests
• Make Structures so that SLAC can do High Gradient tests on them
• Integrate into ETF• Will force 1 structure / month issue• Will force “beam line unit” issues into
the open
• Integrate into Industry• Need to determine appropriate strategy
for scaling up industrialization issues• Need to determine sensible role for
SBIRs
Note on throughput:
R&D needs about 1 structure / month
Project production rate is ~ 6 structures / day
D. Finley / Fermilab FARDOG / January 4, 2001 7
fTD NLC R&D Budget Report November 2000
Code Cost Cat BudgetYTD
Actual Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Open Comm Prior Year
Open Comm Curr Mo
Open Comm Prev Mo
Cost + Chg in Comm
(% Spent)
TD-E&F NLC Magnet R&D4MAT 1YA PERSONNEL COSTS195.0 30.0 15.8 14.2 15%
1YB MATERIALS & SERVICES70.0 20.9 15.6 5.3 0.0 4.6 2.2 36%Total: 265.0 50.9 31.4 19.5 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 4.6 2.2 21%
TD-E&F NLC Structures R&D4RAT 1YA PERSONNEL COSTS540.0 76.7 34.2 42.5 14%
1YB MATERIALS & SERVICES495.0 50.5 17.1 33.4 59.2 70.4 58.8 12%Total: 1,035.0 127.2 51.3 75.9 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 59.2 70.4 58.8 13%
17% of Year Passed
Cost Cat BudgetYTD
Actual Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Open Comm Prior Year
Open Comm
Curr Mo
Open Comm
Prev Mo
Cost + Chg in Comm
(% Spent)1YA PERSONNEL COSTS 735.0 106.7 50.0 56.7 0.0 0.0 15%1YB MATERIALS & SERVICES565.0 71.4 32.7 38.7 59.2 74.9 61.0 15%Total: 1,300.0 178.1 82.7 95.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 59.2 74.9 61.0 15%
D. Finley / Fermilab FARDOG / January 4, 2001 8
fFY01 TD LC R&D FTEs and Salaries
Plan on FY01 Salaries = $735K
FY01 TD LC R&D Salaries
0100200300400500600700800
Oct-0
0
Dec-0
0
Feb-0
1
Apr-0
1
Jun-
01
Aug-0
1
Month
YT
D K
$
Projected K$
Actual K$
Plan to add ~ 0.3 FTE / month through August 2001
Have 8.72 FTE at FY01 End
Start with 5.42 FTE at FY00 End
FY01 TD LC R&D FTEs
0
2
4
6
8
10
Month
FTE
s b
y m
on
th
FTE Projection
Actual FTE
D. Finley / Fermilab FARDOG / January 4, 2001 9
fPreliminary FY01 TD LC R&D Projection
• Note: Oct Nov are history
FY01 TD LC R&D Projection beyond Nov00
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
160.0
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Month
M&
S b
y m
on
th
4.0 Assumed MAT Monthly Average without items below
15.0 Assumed RAT Monthly Average without items below
120.0 RAT Feb Baby Furnace75.0 RAT Jun Network Analyzer25.0 RAT Apr FESS CDR 5 is done (put all costs here)
45.0 RAT Sep Contingency including travel30.0 MAT Sep Contingency including travel
D. Finley / Fermilab FARDOG / January 4, 2001 10
fFY01 LC R&D … Waiting in the Wings
• Windowtron R&D• $100K M&S estimate• “Windowtron” = single cell (or less) rf
breakdown studies led by SLAC• Grew out of breakdown workshop• Miss opportunity for more global
involvement (CERN, Cornell, Fermilab)
• Moderately Damped Design• … at least not under TD leadership• ~ 0.5 FTE
• Beam Line Unit Design• Unit = “rf structures and a magnet”
on a support girder• Unit is “repeated” throughout linac• Need final structure design (Q: “Are
there three or four per unit?)• “Generic design” for support girder is
not appropriate• ~1 FTE
• Parametric Study on Bonding• $75K to $150K M&S estimate• initiated in FY00 when RDDS structure
design was thought to be final ...but is actually premature at this time
• “Parametric Study” = systematically map out costs of producing disks vs required performance of bond joints
• but will need to be done to determine a defensible cost estimate of the full linac … once a structure design has been determined
• settle the issue of brazing vs. bonding
• Equipment, equipment, equipment ...
• optical measurements (>~ $200K)• laser interferometer for magnet
measurements (~$150K)